VGB-Standard Recommendations for the Inspection and Overhaul of Steam Turbines VGB-S-115-00-2016-01-EN (formerly VGB-R 115) Publisher: VGB PowerTech e.V. Publishing house: VGB PowerTech Service GmbH Verlag technisch-wissenschaftlicher Schriften Deilbachtal 173, 45257 Essen, Germany Phone: +49 201 8128-200 Fax: +49 201 8128-302 E-mail: mark@vgb.org ISBN 978-3-86875-908-2 (Print) ISBN 978-3-86875-909-9 (eBook) All rights reserved, VGB PowerTech. www.vgb.org VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 Single User License/Einzelplatzlizenz General terms and conditions of VGB PowerTech Service GmbH to be applied. Es gelten die AGB der VGB PowerTech Service GmbH. www.vgb.org/shop. Single user license Einzelplatzlizenz One printout allowed Ein Ausdruck erlaubt No digital copy allowed Keine digitale Kopie erlaubt No network access allowed Kein Einstellen in Netzwerke erlaubt 1 1 All other rights reserved | Alle weiteren Rechte vorbehalten. ---------VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Copyright VGB-Standards, hereafter referred to as “work”, including all articles and images, are protected by international copyright. VGB PowerTech owns and controls the copyright. The term “work“ covers the publication at hand as printed hard copy and as digitalised version. The copyright covers the entire work and parts of it. Any kind of use beyond the limits of copyright is prohibited without the prior written consent of VGB PowerTech. Any unauthorised reproduction, translation, digitalisation and modification will constitute an infringement of copyright. Disclaimer VGB-Standards are recommendations, the application of which is optional. VGBStandards represent the state of the art at the time of publication. No claim regarding its completeness and correctness is made as a matter of principle. Application of VGB-Standards is carried out at the user's own responsibility and risk. VGB PowerTech accepts no legal liability in the event of any claim relating to or resulting from the application of VGB-Standards. Treatment of proposing amendments Amendments can be sent to the e-mail address vgb.standard@vgb.org. The subject line should contain the exact specification of the relevant document in order to clearly assign the e-mail content to the appropriate VGB-Standard. 2 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Preface to the third edition After many years of favourable experience in the use of VGB Guideline VGB-R 115, a revision became necessary on the occasion of the transposition of the Guideline into a VGB-Standard, especially due to the changed framework conditions on the energy market. The necessity and usefulness of inspections and overhauls of steam turbine plants is undisputed. Based on long-term experience, the most diverse strategies have been developed and criteria used during recent years for optimal scheduling of turbine inspections and to minimize the time required for the implementation of inspections and overhauls. The efforts of turbine owners therefore focus on achieving optimum performance with the objective of lengthening the intervals between required inspections and overhauls. The recommendations for the inspection and overhaul of steam turbines provided in this standard cover a variety of different aspects. Essen, January 2016 VGB PowerTech e.V. 3 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Authors The following contributors were involved in the transposition of the former VGBGuideline into a VGB-Standard: Dipl.-Ing. Klaus Blomeier, VGB PowerTech e.V. Dipl.-Ing. Dipl.-Wirtsch.-Ing. Hans-Günter Busch, HDI Global SE Wolfgang Daum, VGB PowerTech e.V. Dipl.-Ing. Albert Harrer, Harrer Turbine Consult Dipl.-Ing. Heiko Höhne, Uniper Kraftwerke GmbH Dipl.-Ing. Peter Richter, VGB PowerTech e.V. Dipl.-Ing. Thomas-Michael Scholbrock, BASF SE Dipl.-Ing. Hartmut Strangfeld, RWE Power AG 4 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Contents 1 1.1 1.2 Introduction ............................................................................................... 6 Object ......................................................................................................... 6 Scope ......................................................................................................... 6 2 2.1 2.2 Basic considerations for the inspection and overhaul of steam ............ turbines ..................................................................................................... 7 Theoretical considerations in scheduling inspections and overhauls .......... 7 Practical considerations in scheduling inspections and overhauls .............. 9 3 3.1 3.2 3.3 Types of inspections and overhauls ..................................................... 10 Minor overhaul or inspection ..................................................................... 10 Intermediate overhaul ............................................................................... 10 Major overhaul .......................................................................................... 11 4 Inspection and overhaul considerations .............................................. 12 5 5.1 5.4 5.5 5.6 Scheduling inspections and overhauls ................................................ 14 Initial service period (< 25,000 EOH), until minor overhaul/inspection .......... (see 3.1) ................................................................................................... 16 Second service period (between 25,000 and 50,000 EOH), ......................... until intermediate overhaul (see 3.2)......................................................... 16 Third service period, until major overhaul (between 50,000 and .................. 100,000 EOH) (see 3.3)............................................................................ 16 Unplanned inspections and overhauls due to irregularities ....................... 16 Unplanned inspections and overhauls due to damage ............................. 17 Summary .................................................................................................. 18 6 6.1 6.2 6.3 Planning for inspections and overhauls ............................................... 19 Spare parts planning................................................................................. 19 Planning for intermediate and major overhauls ........................................ 19 Marginal conditions for implementing inspections and overhauls ............. 21 7 Tests and inspections during overhauls .............................................. 23 8 8.1 8.2 8.2.1 8.2.2 Results of overhaul, conclusions.......................................................... 27 Documentation.......................................................................................... 27 Conclusions drawn from overhauling results ............................................ 29 Conclusions for further operation .............................................................. 29 Conclusions for next inspection/overhaul ................................................. 29 9 Literature ................................................................................................. 30 10 Appendix ................................................................................................. 34 5.2 5.3 5 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 1 Introduction 1.1 Object Steam turbine plants are used in industry and in utility power plants in various ways to generate electrical energy, to drive compressors and pumps, and to provide costeffective heating or process steam at various pressure levels. The turbine design data are determined by the specific requirements and needs of the different user groups. This means that the steam turbines have to be adapted to the process conditions of each specific application and that a differentiated approach to maintenance has to be adopted accordingly. The prevailing economic boundary conditions of steam and electricity generation make great demands on the thermal efficiency and on the availability and reliability of steam turbine plants. In the past, an inspection and overhaul strategy tailored to the specific plant has proved to be an important tool for ensuring optimal and reliable operation. To permit an overall assessment of the condition of steam turbines and their auxiliaries, a factfinding inspection after opening of plant components is required in addition to the usual monitoring routines, inspections and additional measurements. These recommendations provide guidelines for scheduling inspections and overhauls, taking into account the type of turbine, the design, the monitoring and diagnostic equipment, the operation regime, the duty and the age of the unit. 1.2 Scope These recommendations apply to: utility superheated steam turbines, utility saturated steam turbines, industrial steam turbines, steam turbines in refuse / RDF incineration plants and biomass fired plants, steam turbines for mechanical drives and their ancillary and auxiliary systems, such as gear units, condensers and oil supply systems. Generators are covered by VGB Guideline VGB-R 167. The present standard does not cover instrumentation and control systems, for which other considerations apply. 6 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 2 Basic considerations for the inspection and overhaul of steam turbines Inspections and overhauls are necessary in order to maintain steam turbines. Their purpose is to maintain/improve safety, availability and economic efficiency during the forthcoming service period, determine the present condition of the unit, detect and avert impending failures, eliminate defects, refurbish worn parts, obtain information for assessing the remaining life and thus indications of future inspection and overhaul requirements, and enable improvements and upgrading measures. 2.1 Theoretical considerations in scheduling inspections and overhauls A turbine is a system consisting of numerous parts. Even if the reliability of the individual components is relatively high, the probability of a failure of the complete system increases with the number of component parts, a significant factor being the number of operating hours. An increased number of starts and shutdowns, and lowload operation, can cause component stresses that are different from those faced in the past, which likewise have an impact on the inspection/overhaul date. The service time of a steam turbine unit can be divided into three phases: Phase 1: Initial service period: at its end, minor inspections/overhauls will typically be carried out. Phase 2: Second service period: at its end, an intermediate inspection/overhaul will be carried out, with mainly foreseeable maintenance requirements, for instance due to wear and tear of highly stressed components such as valves, and control and safety equipment. Phase 3: Main service period The main service period is the period from commencement of initial commissioning until the first major inspection/overhaul, or the period between two major inspections/overhauls, as the case may be. These service periods can be graphically represented in a kind of bathtub curve, as shown in Figure 1. 7 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Time-independent influences are predominant in the left-hand part of Figure 1 while time-dependent influences prevail in the right-hand part. Time-independent influences can recur after each overhaul. Fig. 1. Failure probability of a unit as a function of its operating hours. 8 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 2.2 Practical considerations in scheduling inspections and overhauls For the scheduling of inspections and overhauls a time-based approach or a condition-based approach can be adopted. For the latter, it must be possible to assess the condition of the turbine generator. In scheduling inspections and overhauls, two factors are significant: a) Time-independent influences, such as: deficiencies related to planning, design, calculation and/or construction, faults during manufacturing, installation and/or repair, material defects or confusion of materials (quality assurance), damage, faulty operation and faulty maintenance. Time-independent influences are frequently due to human failures. They depend on the knowledge, skill, experience and diligence of the manufacturers and owners. It is known from experience that these influences mainly have effects during the initial service period after first installation and must in some cases also be anticipated after inspections and overhauls. b) Time-dependent influences, such as: wear and tear, corrosion and erosion damage, deformation, changes in the blading, life expenditure, relaxation, starting and load spectra, deposits of any kind, including consequential damage, poor maintenance, experience with comparable units. Time-dependent influences are due to stresses experienced by individual components in relation to the design levels during the service life of the unit, especially as a result of start-up and shutdown procedures, load changes and special modes of operation or operation at off-nominal conditions. Frequent starts and shutdowns and more frequent low-load operation need to be considered in particular. 9 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 3 Types of inspections and overhauls DIN 31051 and DIN EN 13306 define and distinguish between maintenance measures as follows: Servicing: Measures for maintaining the function and for delaying the consumption of the existing wear reserve. Inspection: Measures for determining and assessing the actual condition, including determination of the cause of wear and derivation of necessary measures. Repair: Measures performed to restore the function. On the basis of the DIN standard, the present standard defines the types of inspections and overhauls as follows: Minor overhaul or inspection Intermediate overhaul Major overhaul Note: Servicing measures are carried out continuously. The safety equipment covered by VGB-R 103, “Guideline for monitoring, limiting and protection devices on steam turbine plants” is to be given special consideration. 3.1 Minor overhaul or inspection A “minor overhaul” should be performed as necessary during an outage caused by other plant components or during a failure-induced or planned outage of the unit. In the case of new plants, it is useful to also carry out a minor overhaul prior to expiry of the warranty period. The primary objective is to prevent forced outages by systematic inspection. No casing parts are opened. Information can be obtained for an “intermediate overhaul” or a “major overhaul” (for scope of work, see Sheets 1 and 2 of Appendix 1). 3.2 Intermediate overhaul An “intermediate overhaul” is performed during a planned outage of the unit. If required, a turbine section and/or major turbine components, such as valves, bearings or couplings, are opened and overhauled; in addition, other parts of the unit can be subjected to boroscopic inspection. The measures taken also focus on smallscale repair work in the surroundings of the steam turbine installation. Intermediate overhauls also serve to obtain detailed information for the next “major overhaul” (for scope of work, see Sheets 1 and 2 of Appendix 1). 10 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 3.3 Major overhaul A “major overhaul” is performed during a planned outage of the turbine generator and allows thorough checking and a fact-finding inspection and repair of all components. Within the scope of a major overhaul, the casings are opened. The duration of the outage depends on the rating and design of the turbine generator, the scope of restoration work and the number of staff assigned (for scope of work, see Sheets 1 and 2 of Appendix 1). An event of failure or damage can be used to bring forward an upcoming overhaul, see section 5.5. 11 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 4 Inspection and overhaul considerations Once the steam turbine unit has been carefully designed, engineered and installed, and upon successful commissioning and handover to the owner, the owner is responsible for the proper operation, monitoring and maintenance of the plant. Constant monitoring of all operating parameters reduces the risk of malfunctions and can in many cases prevent damage. As a matter of principle, malfunctions and failures cannot be completely ruled out in machines of any kind. With this in mind, inspections and preventive measures are carried out during scheduled outages in order to reduce the amount of damage and number of malfunctions. Monitoring of the long-term service performance of the steam turbine likewise contributes to knowledge of the plant condition and thus permits longer intervals between inspections/overhauls and shorter duration of inspections and overhauls. Inspections and overhauls are planned according to safety and economic requirements. In addition to the cost of the overhaul proper, the non-availability of the unit is an important factor. It is determined by the outage duration due to malfunctions or damage. Hence, lengthening the inspection intervals is expedient only if this does not result in increased non-availability. A forced outage due to damage will normally result in a longer downtime than a planned outage for inspection and overhaul. An outage due to a breakdown always occurs unexpectedly, i.e. normally at an unsuitable time. It the plant is operated in accordance with the principles set out in VGB Guideline VGB-R 105 and with the manufacturer’s operation manual, service life issues should not be a determinant during the first main service period. Inspections and overhauls on steam turbines may become necessary earlier than scheduled, due to more frequent starts and shutdowns, extreme low-load service or poor quality of oil or feedwater. Experience has shown that issues of material fatigue and remaining service life become more important once 100,000 equivalent operating hours have been accrued. From this time on, it is absolutely necessary to consider these influencing factors in the scheduling of inspections and overhauls, because certain components, e.g. components in the superheated steam section, can only be dismantled with significant effort once a high number of operating hours has been accrued; 12 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN signs of fatigue and creep, such as the formation of cracks in casings and/or the deflection of diaphragms, must be specifically monitored and measured over an extended period in order to draw conclusions about the remaining service life; turbine-internal superheated steam carrying pipes that are operated in the creep range must be subjected to periodic inspections; once 200,000 equivalent operating hours have been accrued, statements regarding the remaining life are possible only on the basis of findings from inspections and overhauls. A computational assessment is not always possible, because sometimes no complete documentation of the operation mode over the entire service life of the turbine is available. For turbine plants of an older design, further aspects have to be considered (drawings no longer available, casting patterns already destroyed, etc.). The above instructions are applicable only to steam turbine plants that are operated and serviced in accordance with the technical rules and codes of practice. Further aspects and the considerations in scheduling of inspections and overhauls specified in section 2 hereinabove are: the inspection needs of associated major components (steam boiler, generator), owner‘s operating experience, manufacturer’s recommendations for inspection and overhaul, exchange of experience with other owners, expected operation regime, conditions agreed with the insurer, literature. 13 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 5 Scheduling inspections and overhauls Planned inspections and overhauls, both preventive and condition-based, are scheduled on the basis of the inspection and overhaul strategy. Unplanned inspections and overhauls result from irregularities in the unit or from malfunctions requiring a shutdown of the unit. There is a smooth transition between planned preventive maintenance strategy and condition-based maintenance strategy. Even in the case of the planned preventive or condition-based maintenance strategy, checks and inspections should be carried out at certain intervals, which can help to use forthcoming outages and overhaul shutdowns more effectively. There is a general interest in extending the time between overhauls, which are sometimes performed at fixed and comparatively short intervals. Efforts should be made to attain greater flexibility in establishing inspection intervals and to lengthen the service periods between overhauls in relation to the condition of the unit (condition-based maintenance). Besides the design, the available monitoring and protection equipment and the operation regime, the in-service behaviour of the unit and any changes as compared to its normal condition are of crucial importance. The aspects resulting therefrom for the scheduling of the overhaul/inspection are proper operation of the steam turbine unit, and equivalent operating hours, also accounting for the number of starts. These are impacted by the design type, operation and maintenance, ambient conditions, steam parameters, and fleet experience. Equivalent operation hours (EOH) are defined by the following relationship: TEOH Tact ns T s where: TEOH = equivalent number of operating hours, Tact = actual number of operating hours, ns = number of starts, without differentiating between hot and cold starts, Ts = number of additional operating hours to be considered for one start. According to the present state of knowledge, each start incurs a penalty in terms of an equivalent number of 20 to 30 operating hours. 14 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Further findings and insights must be considered: Turbine design e.g. split casing turbines or barrel type turbines, condensing turbines with great exhaust steam wetness, high-temperature turbine sections of austenitic materials, geared turbines Mode of operation e.g. continuous duty, off-nominal conditions, starting and loading modes, temperature transients and resulting material stresses, variable-pressure/ constant-pressure operation In-service observations e.g. running smoothness, bearing and casing temperatures, alignment conditions, stage pressures and temperatures, expansion and thrust data, leakage steam flow rates, terminal temperature difference of condenser, signs of wear and tear, leakages, changes in service fluids such as turbine oil, lubricants, feedwater, cooling water Special measurements e.g. internal efficiency, vibration analysis, heat consumption Boroscopic inspection of plant parts Deformation of foundations Evaluations/changes in the steam pipework system and the resulting forces and torques acting on the turbine inlet connections Oil analyses (see VGB-S-416), Feedwater analyses (see VGB-S-010) Functional checks e.g. protection and control equipment (see VGB-R 103) Life assessment calculations Turbine life expenditure Coast-down times, shape of the coast-down curve Valve closing times Casing temperature measurements for determination of insulation condition Inspection intervals of other power plant components, e.g. steam boiler and generator Manufacturer’s and/or insurer’s recommendations 15 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Exchange of experience with other turbine owners, e.g. information on known weaknesses or damages Influence of downtime (see VGB-S-016). 5.1 Initial service period (< 25,000 EOH), until minor overhaul/inspection (see 3.1) It is advisable to check the unit for defects and deficiencies prior to expiry of the warranty period (warranty inspection). A specific inspection, supported by videoboroscopic inspection without time-consuming disassembly of components is suitable for this purpose. Casings are normally not opened after such a short service period. In the case of turbines of new design, suitable arrangements in this regard should be agreed between the manufacturer and the owner. 5.2 Second service period (between 25,000 and 50,000 EOH), until intermediate overhaul (see 3.2) If no irregularities are detected by process monitoring or other in-service measurements and if no negative experience with comparable units has become known, it is recommended to carry out an intermediate overhaul after the end of the second service period. 5.3 Third service period, until major overhaul (between 50,000 and 100,000 EOH) (see 3.3) Planning for the major overhaul is determined by the inspection findings and test results obtained during the intermediate overhaul and the minor inspection. The first major overhaul is performed between 50,000 and 100,000 EOH. If the major overhaul reveals no serious findings, the same interval time between major overhauls can be kept for future overhauls. Findings, a changed operation regime, life expenditure, and operating experience from comparable turbines may indicate the need for shorter intervals. 5.4 Unplanned inspections and overhauls due to irregularities The intervals indicated in sections 5.1 to 5.3 hereinabove are applicable to the condition that process monitoring and other specific measurements (e.g. efficiency, heat consumption or stage pressure measurements) and the inspection findings reveal no irregularities. However, if process monitoring of the turbine generator reveals irregularities (deviations from nominal conditions) which are substantiated by additional checks (e.g. measurements), it may be necessary to advance the date of the next overhaul (see Appendices 3.1 and 3.2). 16 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Moreover, information provided by the manufacturer, by other turbine owners or by the insurer on incidents experienced with similar units can lead to an unplanned inspection or overhaul. If findings and results of inspections indicate the need for extended plant downtime, advancing the date of a planned major overhaul may be contemplated for economic reasons. 5.5 Unplanned inspections and overhauls due to damage Bringing forward the date of a planned overhaul may be expedient for economic reasons, not only in the case of damage to the turbine generator, but also in the case of a failure experienced by a non-redundant plant component (steam boiler, pressure vessel, generator transformer etc.). In contrast to an unplanned inspection/overhaul due to irregularities, which in most cases does not necessitate an immediate shutdown of the turbine generator, damage may require an immediate shutdown. If the time necessary for repair of the damage results in extended downtime of the turbine generator, the date of a planned (major) overhaul may be advanced. 17 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 5.6 Summary A basic inspection schedule for the entire service life of the turbine taking into account the above considerations is shown in Figure 2. Typical basic inspection schedule for the entire service life of a turbine Service life Initial service period Minor overhaul/inspection Minor overhaul/ inspection Minor overhaul/ inspection Second service period Minor overhaul/inspection Inspection Intermediate overhaul Major overhault Fig. 2. ~ 2 to 3 days ~ 1 to 4 weeks ~ 6 to 8 weeks Main service period Major overhaul Typical basic inspection schedule for the entire service life of a turbine. 18 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 6 Planning for inspections and overhauls It is the goal of inspection and overhaul planning to find a favourable time/cost ratio for a defined scope of overhauling activities. This includes spare parts planning, implementation planning and consideration of the necessary marginal conditions. 6.1 Spare parts planning The spare parts considered necessary by agreement between the owner and the contractor should be available in the number required prior to commencement of the inspection/overhaul. The decision on the purchase of spare parts mainly depends on the following criteria: significance of the turbine generator/the plant for the company, cost of outage due to unexpected/extended downtime, probability of failure, delivery time of spare parts, operation of several identical units by the company, and consolidated spare parts inventory shared by several companies. Certain spares should be purchased in due time so as to be prepared for life expenditure of the original parts. Delivery time / availability of spare parts The spare parts must be stocked in such a way as to be protected against corrosion and damage and to be easily found. Any parts withdrawn from stock should be replaced in due time either by ordering new parts or by reconditioning parts removed from the unit. In the event of the design of the turbine generator being changed, the spare parts have to be examined for their fitness for use. 6.2 Planning for intermediate and major overhauls Approximately one to two years before the start of the overhaul, the owner should send a detailed specification of supplies and services to the manufacturer and/or to potential service companies. If the turbine unit is covered by insurance, the insurer should be informed in time about the date and scope of the planned overhaul. 19 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN In addition to the definition of the scope of the overhaul by means of the specification of supplies and services, other aspects also need to be clarified, such as: estimated spare parts requirements, delivery times of spare parts, time needed for oil flushing to VGB-S-030, completeness and condition of spare parts kept on stock by the owner. Orders for replacement of missing or unserviceable spare parts must be placed immediately, taking into account any design modifications to date, availability of tools and fixtures (items kept available by the owner, items to be provided by the contractor). The following requirements depend on the kind, duration and scope of the overhaul: Owner and contractor should jointly compile a preliminary manpower and overhaul time schedule. A work schedule is to be compiled showing the work to be performed in workshops (owner, manufacturer and outside contractors). A clear division of responsibility must be agreed upon for any ancillary work required, such as disassembling and reassembling of instrumentation and motors, including their re-commissioning. Both the contractor and the owner must consider in their plans the availability of the necessary workshop and machine tool capacity. Special attention should be devoted to balancing facilities that may be necessary. Blocking of the spring packs of the turbine foundation is to be considered, where applicable. The mode of transport, transport permit, transport insurance and the provision of transport facilities must be agreed upon between the owner and the manufacturer. In good time prior to the start of the overhaul, the actual condition of the turbine generator is to be determined by measurements (e.g. pressures, efficiency, vibration levels, foundation displacements) and compared with the nominal condition. No later than four months before the start of the overhaul, a further pre-overhaul meeting should be held, focussing on the following additional requirements: Project managers are to be designated. The results of the measurements should be evaluated to determine the need for additional inspection/overhauling activities. The manpower and work schedules must be updated. 20 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN The required manpower qualification levels as well as the composition of the overhaul crews should be finalized. Working hours should be agreed upon. The time schedule for the entire overhaul period requires updating. Note that disassembling without delay enables a fact-finding inspection to be performed by the owner and the contractor at an early date and thus facilitates attending to unexpected damage. The areas of activities under control of the contractor and owner during the overhaul at the power plant are to be agreed upon. All documents required for the overhaul should be on hand before the start of the overhaul (as-built documentation, drawings, installation records etc.). It is recommended that all parties involved in the overhaul should meet for an exchange of experience as soon as the turbine has been restarted. 6.3 Marginal conditions for implementing inspections and overhauls Planning should include wash rooms and locker rooms for outside contractors’ personnel, and an adequate number of toilets and parking spaces. The availability of accommodation and catering facilities near the power plant outside working hours and of rooms for having meals at the power plant should be clarified. Good lighting and electric power at the required supply voltages for the connection of the necessary electrical appliances must be available. The supply of compressed air to the jobsite must be ensured. Heating and welding equipment with an adequate supply of oxygen and gas cylinders must be provided. Inductive preheating is to be considered, if necessary. Necessary special tools and fixtures are to be kept available, e.g. bolt heaters, special hoisting equipment, alignment shaft with inductive transmitters etc. A cleaning/abrasive blasting contractor and a thermal insulation contractor should be informed about and contracted for the scope of work to be performed. A layout plan of the turbine house indicating the permissible loads must be available. Crane availability and use must be clarified. Work benches, racks, supporting trestles, transportation skids, hoisting equipment etc. are to be provided. 21 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Racks, cases or containers for small items should be provided at the job site for dismantled small items, such as, for instance, shaft glands, valve stems, casing and bearing seal rings, bolts, etc., in order to ensure an orderly laying down of the parts and to avoid confusion of parts manufactured from different materials. An adequate number of wooden planks, beams and trestles for the laying down of components should be made available and inspected for their fitness for service before being used. Covers and means for blocking off are to be provided for the protection of working areas. Provision of a lockable container for storage of special parts may be advisable in some cases. It is recommended to set up a tool and material crib in the vicinity of the steam turbine generator in order to eliminate long distances. An office room/container with communication facilities for the overhaul personnel should be provided. Before the start of the overhaul, the working time regulations and the rules of conduct at job site must be handed out to all persons involved. The accident prevention rules must be laid out for perusal, and the staff must be instructed in these rules and practices. Lists of all ropes and slings required and of all loads to be lifted must be available. It is advisable to store all ropes and slings in a proper manner in a single location. It is It is recommended to provide tags with details of safe load capacity, description and length. Ropes and spreaders allowing for adjustment of length must be made available. After use, the ropes and slings must be inspected for their condition and, if necessary, replaced. Collecting pans and containers for oil to be drained and oil-absorbing substances must be kept available in adequate numbers. The Water Resources Act and the Ordinance on Hazardous Substances must be observed. Consumables and auxiliary materials, such as non-linting cleaning rags, solvents, lubricants, sealing materials, shims etc. are to be made available. After completion of the overhaul, all tools and appliances used must be checked for fitness for reuse and for completeness. It should be ensured that an efficient nearby workshop will be available for use at any time. 22 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 7 Tests and inspections during overhauls The following principal techniques, identified by code numbers, are available for inspecting steam turbine generator components. Details on their application are given in Appendix 2. Code number (see Appendix 2, Sheets 1 to 3) Functional tests 1 Visual inspection (outside/inside) 2 naked eye, good lighting and optical aids boroscope (rigid and flexible; accessories: TV camera, monitor, video recorder) magnifying glass inspection of surface microstructure (e.g. roughness) blueing check Surface crack examination 3 liquid penetrant testing (note: thorough precleaning of surface may be required, e.g. for component surfaces affected by scaling) magnetic particle testing note: not applicable to austenitic materials) eddy-current testing Ultrasonic testing Phased array 4 Radiographic testing 5 X-ray gamma-ray (isotope) Determining crack depth 6 as far as practicable by means of potential probe or ultrasonic method; possibly drilling and/or grinding of cracks 23 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Code number (see Appendix 2, Sheets 1 to 3) Ring test 7 mainly for assessing tightness of blade seating Determining natural frequencies of components 8 primarily to detect changes in natural frequencies for moving and stationary blades holographic inspection and test methods Detecting permanent deformations 9 length measurements, e.g. to determine clearances, ovality, deformations, gaps runout tests, e.g. to determine distortions geodetic measurements, e.g. foundation, machine base, bearing pedestals Wall thickness measurements 10 by means of calipers or ultrasonic testing Non-destructive tests 11 on-site examination of surface microstructure by means of optical microscope or replica methods after etching of the surface, film or lacquer replica, VGB-S-517-00-2014-11DE-EN hardness test, e.g. Brinell, Rockwell, Vickers material identification test, e.g. by means of hand spectroscope Material tests using test specimens 12 tensile test for determination of yield strength, tensile strength, elongation after fracture and reduction of area notched-bar impact test chemical analysis 24 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Code number (see Appendix 2, Sheets 1 to 3) Determining residual stress 13 strain gauges ring core method X-ray goniometer Leakage test by 14 filling pressurizing evacuating (e.g. by means of a test gas) Electrochemical examination of protective coatings 15 e.g. on condenser tubes of copper alloy materials, by potential/resistance measurement Resistance measurement to check shaft earthing system (shaft currents) 16 Quality control of service fluids e.g. lubricating and control fluids, anti-seize agents, grease 25 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN The scope of tests and inspections should be agreed between the manufacturer and the owner in due consideration of experience available from comparable units and new findings derived from failures. The manufacturer should indicate highly stressed areas of the components requiring inspection. The scope of tests and inspections should be specified in checklists, taking into account the type of turbine, the operation regime and the age of the machine. In many cases it is advisable to subject a particular component to several different test procedures, since the results partly complement each other. Appendix 2 lists a number of recommended test procedures classified according to steam turbine components, to be applied during overhauls. They relate to tests on the turbine, condenser, heat exchangers, internal piping system of the turbine and auxiliary systems of the steam turbine unit. The test results should be recorded and kept for the entire lifetime of the turbine (e.g. reports, sketches, drawings, photographs, radiographs and recalculation records). Planning of overhauls should take into account the extra time and additional expense for the tests and inspections. Moreover, the long intervals between overhauls make it necessary to include in the test programme a considerably larger number of items than previously. 26 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 8 Results of overhaul, conclusions 8.1 Documentation Detailed documentation of the results is an integral part of any overhaul or inspection (see also VGB-S-029). It is recommended that this documentation be compiled in cooperation between the contractor and the owner, in due consideration of the needs and requirements. The following headings are intended as a recommendation for the set-up and contents of the documentation. The order in which they are mentioned does not imply any ranking in priority. Implementation of overhaul Manpower and work schedules. Logging of each day’s activities, their sequence and the required number of working hours together with a statement of qualifications. Bar charts, critical-path diagrams, minutes of meetings, assessment of overall condition on the basis of the operating data recorded. Inspection findings should be described in detail and supported by photographs, video recordings, sketches, etc. Significant leads can already be found in the process of disassembling the turbine and its components. The inspection findings report is compiled by the contractor. In case of disagreements, the owner and/or the expert have the right to have their comments recorded in this report. Restoration and repair work Kind and scope of the restoration and repair work performed. Upgrading and modification work Kind and scope of the work. Spare parts List of spare parts used. Modifications to spare parts are to be specially recorded. Service fluids Information on quantities replenished and material designations. Test records for component parts Test records and factory assembly records for replacement parts and components reconditioned at the manufacturer’s workshops, material test certificates. 27 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Settings records and functional test records Settings and tests of control, monitoring, limiting and protective equipment, oil throttles, oil pressures, shaft lift oil pressures. Assembly records Records of all measurements taken. Plant records Drawings, piping diagrams, operating instructions, etc. should be checked for continued validity and revised as necessary. Operating records Operating data should be recorded under comparable steady-state conditions before and after the overhaul and checked for any departure from their nominal values. Data to be recorded include, but are not limited to: live steam conditions and valve positions, stage pressures and temperatures, casing temperatures, oil pressures and temperatures, cooling water inlet temperature and temperature rise in oil cooler, terminal temperature difference of oil cooler, bearing temperatures, expansions, vibrations, data of gland steam sealing system, data of vacuum test, terminal temperature difference of condenser. As a prerequisite for acceptance of the contractor’s inspection and overhaul services by the owner, the assembly and commissioning records (also preliminary and/or handwritten records) must have been submitted to the owner. Prior to the closing of the turbine casing, the clearances set should have been approved in writing by engineering department of the contractor. The commissioning procedure is to be discussed and agreed between the contractor and the owner. Special measurements Efficiency, heat consumption, foundation distortion, intercept valve test. Costs Recording of total cost of overhaul, broken down by personnel, material and outside contractor costs. Planned/actual comparison Comparison of planned data with the actual overhaul process. 28 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 8.2 Conclusions drawn from overhauling results 8.2.1 Conclusions for further operation Normally, no restrictions need to be observed for future operation if the components were left in the condition as found due to the absence of deficiencies, were replaced by spare parts (e.g. parts subject to wear and tear, such as valve stems; typically small items which are kept on stock), or were reconditioned at site, at manufacturer’s works or at an outside contractor’s facility. If damaged components (e.g. casings with cracks) have to be left in the condition as found, it should be decided whether operation can be continued, if necessary with a change in the operation mode. This decision may result from: re-analysis of component stress levels, envisaged remaining service life of the unit, duration of repair work, or non-availability of replacement parts. The condition of the damaged components must be monitored and documented. If necessary, additional monitoring facilities should be provided. Any required spare parts should be ordered. 8.2.2 Conclusions for next inspection/overhaul The findings, if possible supplemented by a life expectancy calculation and operating and overhauling experience available from other units of the same type, may prompt a change in the current periodic inspection intervals established for a particular turbine generator. Shortening of the time between overhauls is always recommended when there are indications of particular components approaching their expected end-of-life, while replacement does not yet appear absolutely necessary. An analysis of the procedure details of the preceding overhaul can provide important hints for planning the next overhaul. Problems frequently recurring during an overhaul include difficulties during disassembly, unexpected findings, unavailability of replacement parts, delay in repair of damaged components, and difficulties in procurement of material and special fixtures. 29 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 9 Literature DIN 1943 Thermal acceptance tests of steam turbines (VDI standard for steam turbines) DIN 31051 Grundlagen der Instandhaltung (Fundamentals of maintenance) DIN 31661 Gleitlager-Begriffe; Merkmale und Ursachen von Veränderungen und Schäden (Plain bearings; terms, characteristics and causes of changes and damages) DIN 51515, Part 1 Lubricants and governor fluids for turbines – Minimum requirements – Part 1: Turbine oils TD for normal service DIN 51515, Part 2 Lubricants and governor fluids for turbines – Minimum requirements – Part 2: Turbine oils TG for high temperature service DIN EN 13306 Maintenance – Maintenance terminology DIN ISO 7919 Mechanical vibration of non-reciprocating machines – Measurements on rotating shafts and evaluation DIN ISO 10816 Mechanical vibration – Evaluation of machine vibration by measurements on non-rotating parts VGB-M 101 Empfehlung zum Vermeiden von Schäden an Dampfturbosätzen (innere Verschmutzung) (Recommendations for the avoidance of damage to steam turbine generators (internal fouling)) VGB-M 108 Ausrichtkontrolle an Turbosätzen (Alignment checking of turbinegenerators) VGB-M 109 Recommendations for control and lubrication systems of steam and gas turbine installations VGB-M 110 Fast cooling-down of steam turbines VGB-M 111 Maßnahmen zur Lebensdauerverlängerung und Ertüchtigung von Dampfturbinenanlagen (Service life extending measures and upgrading measures for steam turbine units) VGB-M 114 Wirkungsgradänderungen an Dampfturbinen-Ursachen und Gegenmaßnahmen (Changes in steam turbine efficiency – causes and countermeasures) VGB-M 120 Vermeidung von Fremdkörpereintrag in geöffnete Systeme/ Komponenten von Kraftwerken (Avoidance of foreign body ingress into opened systems/components of power plants) 30 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN VGB-M 305 Umgang mit wassergefährdenden Stoffen im Kraftwerksbereich (Handling of substances hazardous to water in power plants) VGB-M 633 Aufgaben der Vermessung bei Planung, Bau und Betrieb von Kraftwerken und anderen Industrieanlagen (Surveying tasks in the planning, construction and operation of power plants and other industrial plants) VGB-M 634 Präzisionshöhenmessungen an Turbosatzanlagen (Highprecision levelling for turbine generator units) VGB-R 103 Guideline for monitoring, limiting and protection devices on steam turbine plants VGB-R 105 Thermal behaviour of steam turbines VGB-R 106 Tubes for condensers and other heat exchangers for the operation of steam turbine plants – Copper alloys VGB-R 108 Fire protection in power plants VGB-R 113 Tubes for condensers and other heat exchangers for the operation of steam turbine plants – Stainless steels VGB-R 114 Tubes for condensers and other heat exchangers for the operation of steam turbine plants – Titanium VGB-R 118 Anleitung zum Überwachen von Dampfturbinen durch Messen des inneren Wirkungsgrades (Guidelines for the monitoring of steam turbines by measurement of internal efficiency) VGB-R 121 Supverision-, Limiting- and Protection Devices on Gas Turbine Systems VGB-R 126 Recommendations for design and operation of vacuum pumps at steam turbine condensers VGB-R 167 Overhaul recommendations for turbo-generators VGB-R 503 Guideline for the internal pipework of turbo-generator sets VGB-R 505 Guideline for the use of high-temperature bolting VGB-R 512 Guideline for the inspection and evaluation of in-service rotors and casings of steam and gas turbine generator sets VGB-S-010-T-00;2011-12.EN (formerly VGB-R 450) Feed water, boiler water and steam quality for power plants/industrial plants VGB-S-016-2014-08-EN Turbine internal drains VGB-S-029-S-00;2012-03-EN Maintenance-compatible documentation 31 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN VGB-S-030-00-2013-06-EN Oil system cleaning for gas and steam turbine plants VGB-S-416-00-2014-08-EN (formerly VGB-M 416) Part A: In-service monitoring of turbine oils in steam and gas turbines Part B: In-service monitoring of fire-resistant fluids for steam and gas turbines VGB-S-504-00-2013-12-EN (formerly VGB-R 504) Inspection and testing of large forgings and castings for steam and gas turbine generator sets VGB-S-517-00-2014-11-DE-EN Richtreihen zur Bewertung der Gefügeausbildung (formerly VGB-TW 507) und Zeitstandschädigung warmfester Stähle für Hochdruckrohrleitungen und Kesselbauteile und deren Schweißverbindungen Guidelines for rating the microstructural composition and creep rupture damage of creep-resistant steel for high pressure pipelines and boiler components and their weld connections VDMA 4315-ff Turbomaschinen und Generatoren – Anwendung der Prinzipien der Funktionalen Sicherheit (Turbomachinery and generators – Application of the principles of functional safety) VDEW-Empfehlungen zur Verbesserung der H2-Sicherheit wasserstoffgekühlter Generatoren. 1. Ausgabe 1989 (VDEW Recommendations for the improvement of H2 safety of hydrogen-cooled generators. 1st edition 1989) VGB Technisch-wissenschaftlicher Bericht VGB-TW 112: Auslegung und Betrieb von Dampfturbosätzen in Kraftwerken unter sicherheitstechnischen Gesichtspunkten. 1. Ausgabe Juni 1992 (VGB Technical Scientific Report 112: Safety aspects to be considered in the design and operation of steam turbine generator sets in power plants) Höxtermann, E.: Schaufelschäden an Dampfturbinen. VGB KRAFTWERKSTECHNIK 59 (1979), H. 12, S. 952 bis 964 (Blade damage in steam turbines. In: VGB KRAFTWERKSTECHNIK 59 (1979), issue 12, pp. 952-964) Höxtermann, E.: Erfahrungen mit Schäden in Form von Anrissen und Brüchen an Dampfturbinenwellen, Radscheiben und Generatorläufern. VGB-TW 107, 3. ergänzte Ausgabe, Mai 1992 (Experience with damage in the form of incipient cracks and fractures in steam turbine shafts, rotor discs and generator rotors. VGB Technical Scientific Report 107, 3rd edition May 1992) 32 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Schäden an Gleitlagern. Allianz-Druckstück Nr.: TI-DE-28/1990 (Damage to plain bearings. Allianz publication no. TI-DE-28/1990) Verordnung für gefährliche Stoffe (Gefahrstoffverordnung – GefStoffV) vom 26. August 1986, (BGBI. I, S. 1470), zuletzt geändert durch Verordnung vom 23. April 1990 (BGBI. I, S. 790) (German Ordinance on Hazardous Substances) Gesetz zur Ordnung des Wasserhaushaltes (Wasserhaushaltsgesetz – WHG). Bundesgesetzblatt (German Water Resources Act) Verordnungen der Länder über das Lagern wassergefährdender Stoffe (z. B. NRW: VO über Anlagen zum Lagern, Abfüllen und Umschlagen wassergefährdender Stoffe) (Ordinances on the German federal state level on the storage of substances hazardous to water) Verordnung über Gefährlichkeitsmerkmale von Stoffen und Zubereitungen nach dem Chemikaliengesetz (ChemG Gefährlichkeitsmerkmale – VO) (German Ordinance on hazard characteristics of substances and mixtures under the Chemicals Act) Unfallverhütungsvorschriften: Schutzmaßnahmen beim Umgang mit krebserzeugenden Arbeitsstoffen (VBG 113) (German Accident Prevention Regulations: protective measures in the handling of carcinogenic substances) Gesetz über die Vermeidung und Entsorgung von Abfällen (Abfallgesetz-ABfG) (German Waste Management Act) Gesetz zum Schutz vor gefährlichen Stoffen (ChemG) (German Act on protection against hazardous substances) Schönebeck, G.: Eine allgemeine holographische Methode zur Bestimmung räumlicher Verschiebungen. Dissertation, TU München (1979) (A general holographic method for the determination of 3D displacement. Doctoral thesis, TU Munich, 1979) 33 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN 10 Appendix Minor overhaul / inspection Intermediate overhaul Major overhaul Appendix 1/Sheet 1 Open couplings, measure preloads of coupling bolts, check axial and radial alignment, runout and displacement (external measurement of actual dimensions). O X X Check alignment of turbine casings and bearing housings. --- O X Disassemble bearings, check bearing metal, measure clearances, check bearing seats in bearing housings. O X X Examine, overhaul and, if required, replace seal rings of bearing housings. O X X Inspect bearing housing and casing guides for contamination (carbonized oil); if binding is detected, remove, clean and overhaul keys. O X X Examine sliding behaviour, remove and overhaul lubrite plates inserted below bearing housings. O X X Lift off bearing housings as far as practicable for overhaul of sliding surfaces and guides. Check condition of grout. --- O X Check spacer bolts at bearing housings and casing brackets and, if required, correct clearances. X X X Check anchor bolt preloads. --- X X Check emergency stop valves, control valves and bypass valves on their actuator and steam sides; if required, replace wearing parts. O X X Remove steam strainers; check for foreign objects and damage and, if required, repair or recondition strainers. --- X X Examine shutoff valves of exhaust steam pipes and of automatic and nonautomatic extractions on their actuator and steam sides. Replace gaskets and, if required, replace parts subject to wear and tear. X X X Inspect pipes and fittings of drainage system, open and clean silt traps. O X X Open turbine casings, measure casing distortion, check joints for erosion, perform crack testing. --- O X Inspect steam inlet elements in turbine casing for oxide scale, wear and free movement. --- O X Check inner casing guides for free movement and wear. --- O X Measure permanent elongation of high-temperature joint bolts and inspect bolts for embrittlement. Inspect all bolts for cracks. --- O X Scope of inspection and overhaul activities as dictated by condition assessment O = as necessary X = required --- = not required 34 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Minor overhaul / inspection Intermediate overhaul Major overhaul Appendix 1/Sheet 2 Check shaft glands and balance pistons for wear, oxide scale and deformation. Examine springs of spring-loaded segments. --- O X Check rotors for runout, rub marks, scoring of journal areas and cracks. Check couplings. --- O X Clean blades as necessary and inspect blades for damage. Perform crack testing and vibration testing on free-standing LP moving blades. --- O X Visually examine last stage of condensing turbine for erosion (crack testing as necessary). X X X Check seal strips for wear and oxide scale. --- O X Examine earthing brushes and contact faces on shaft, including proper functioning X X X Open main oil pump, check bearings, seal rings, shafts, impeller, etc. Open auxiliary oil pumps only if necessary. O O X Examine control and protective equipment, including automatic test facility, giving particular attention to parts subject to wear and tear and to parts susceptible to contamination. Replace parts as necessary. X X X Perform functional testing of monitoring equipment (mechanical, electrical, hydraulic and pneumatic). Recondition and recalibrate equipment as necessary. X X X Inspect condenser interior, tubes and water boxes for fouling and damage. Perform leakage tests on cooling water and steam sides. O X X Check evacuation system. O X X Inspect turbine-internal steam pipes and expansion joints for cracks, distortion and deformation. --- O X Inspect drain pipes for free passage and proper function (condensate traps and drain valves). --- O X Inspect main steam pipes (external). --- O X Inspect anchors, pipe hangers and supports. --- O X Inspect spray water system (HP, LP bypass station and gland steam and exhaust steam desuperheaters). O X X Drain lubricating and control fluid tanks. Separate and, if necessary, change fluids, inspect tanks, clean strainers. --- O X Inspect filters. Remove and clean filter elements and examine for damage X X X Remove tube bundles of coolers, examine tubes for mechanical damage and chemical attack. Clean. --- O X Inspect fluid pipes for damage. Eliminate leaks. X X X Inspect and clean fluid vapour extraction and conditioning systems. X X X Carry out oil flushing to VGB-S-030, “Oil system cleaning for gas and steam turbine plants” X X X Scope of inspection and overhaul activities as dictated by condition assessment 35 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 Minor overhaul / inspection Intermediate overhaul Major overhaul VGB-S-115-00-2016-01-EN Inspect gear couplings (multi-tooth and multiple-disc couplings, jackshafts, etc.) O O X Inspect turning gear equipment for wear and for proper function O O X Inspect gear units (tooth contact pattern, seating of thrust collars, surface crack testing, ultrasonic testing of gearing etc. as necessary. Observe manufacturer’s instructions and recommendations. O O X Scope of inspection and overhaul activities as dictated by condition assessment O = as necessary X = required --- = not required 36 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Appendix 2/Sheet 1 Test procedures to be applied to steam turbine components during inspections and overhauls Component Inspection findings Test procedures* Remarks Rotors Radial/axial rub marks Deformation of blade grooves Surface cracks Mechanical damage Erosion, corrosion Internal defects Permanent deformation Damage to shaft journals 2, 3, (4), (11), (13) 2, 3, 9 2, 3, (4), 6, 11 2, 3, (9) 2, (3) 4, 5 9, 11, 13 2, 3, 9 Including central and radial bores as well as welds Radial/axial rub marks Deformation of blade grooves Loose shrink fit Surface cracks Mechanical damage Erosion, corrosion Internal defects 2, (11) 2, 3, 9 2, (4), 7, 9, 13 2, 3, (4), (6) 2, 3, (9) 2, (3) 4, 5 Radial/axial rub marks Mechanical damage Deposits Erosion, corrosion Surface cracks Change in blade attachment and preloading Permanent deformation 2, 3, 7, (11) 2, 3, (9) 2, 11, 12 2, 3, (8) 2, 3, 4 Rigid couplings Looseness Eccentricity Permanent deformation Cracks 2, (4), 7 9 9, 11 2, 3 Flexible couplings Looseness Eccentricity Tooth flank damage Cracks Flow of damaging currents Changes in clearances 2,7 9 2, 3, 9, 11 2, 3 2, 16 2, 9 Nozzles, stationary blades, diaphragms Radial/axial rub marks Mechanical damage Deposits Erosion, corrosion Surface cracks Change in blade attachment and preloading Permanent deformation 2, 3, 7, (11) 2, 3, (9) 2, 11, 12 2, 3, (8) 2, 3, 4 Discs Moving blades * 2, (4), 7, 8, (9) 2, 9 2, (4), 7, 8, (9) 2, 9, (11) Primarily in disc bore Blade roots, airfoils, damping elements, lacing wires, shrouds, tenons, pins of pinned fork blades Also check for possible damage to bolt holes Blade roots, airfoils, damping elements, lacing wires, shrouds, tenons, pins of pinned fork blades Code numbers according to Section 7 Test procedures in parentheses should only be applied if the preceding tests have revealed a defect or if recommended by the manufacturer. 37 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Appendix 2/Sheet 2 Test procedures to be applied to steam turbine components during inspections and overhauls Component Inspection findings Test procedures* Non-contacting seal elements Restriction of free movement Mechanical damage Fracture Erosion, corrosion Permanent deformation Embrittlement of labyrinth sheet metal Mechanical damage Deformation Surface cracks (inner/outer surface) Erosion, corrosion Internal defects Permanent deformation Mechanical damage Surface cracks Erosion, corrosion Mechanical damage Surface cracks Permanent deformation Erosion/corrosion Deposits Changes in clearances Functional impairment Mechanical damage Corrosion Deposits Changes in clearances 1 2, 3, (9) 2 2 2, 11 Mechanical damage Deformation Cracks, leakage Corrosion Internal defects Mechanical damage Surface cracks Corrosion Cavitation Flow of damaging currents Deposits Bond failures (white metal lining) Seat contact pattern Changes in clearances Functional impairment Surface cracks Abrasion marks Permanent deformation Erosion, corrosion Changes in cold pull Leakage 2, 3, 9, (11) 2, 9 2, (3), 9, 14 2 4, 5 2, 3 2, 3 2, 3 2, 3 2, 3, 16 2, 12 2, 4, 7 2, (9) 2, 9 1, 2 2, 3 2, 3, 10, (11) 2, 9, 10 2, 9, 10 2, 9 2, 14 Outer casings, inner casings, stationary blade carriers, steam chest, valve bodies Flange and joint bolts Valve internals Monitoring, limiting and protective equipment; control system components, automatic test facility Bearing housings Bearings Steam pipes (internal), connecting elements expansion joints; drainage system * Remarks Oxide scale, if applicable 2 2, 3, 9 (11) 2, 9 Sealing, fitting and sliding faces 2, 3, (6) 2, (3) 4, 5 2, 3, 9 2, 3 2, 3, 4 (12) 2, (3) 2, 3 2, 3, 6 2, 9 2, 3 2, 12 1, 2, 9 1 2, 3 2, 3 2, 12 1, 2, 9 Sealing, fitting and sliding faces Especially in elbow areas and at welded joints Code numbers according to Section 7 Test procedures in parentheses should only be applied if the preceding tests have revealed a defect or if recommended by the manufacturer 38 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Appendix 2/Sheet 3 Test procedures to be applied to steam turbine components during inspections and overhauls Component Inspection findings Test procedures* Steam pipes (external), e.g. HP and IP steam pipes Surface cracks in weld joints Permanent deformation Changes in support 2, 3, 10, 11, (12) Steam strainers, including housings Surface cracks Mechanical damage Permanent deformation 2, (3), 11 2, 3 2, 9 Including embrittlement of materials and solidparticle erosion Lubricating and control fluid pipes Leakage Abrasion marks Surface cracks Deposits Corrosion 2, 14 2, 3, 10, 11 2, 3 2, 12 2, 12 Primarily at welds Condenser, coolers, spray water system Disturbed flow path Surface condition Mechanical damage Cracks Erosion, corrosion Leakage 1, 2 2, (3), (10), (15) 2, 3 2, (3), (12) 2, 10 2, 14 Gear Tooth contact pattern Surface cracks Mechanical damage Deposits Flow of damaging currents Changes in clearances 2, 3, 11 2, 3 2, 3 2, 12 2, 16 2, 9 Evacuation system Malfunction Erosion Wear Leakage 1, 2, 14 2 2, 9 2, 14 * 2, 9, 11, (12) 2, 9 Remarks For assessing forces and torques acting on the turbine For instance, protective coating, deposits Code numbers according to Section 7 Test procedures in parentheses should only be applied if the preceding tests have revealed a defect or if recommended by the manufacturer 39 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Appendix 3 Recommended actions on detection of off-normal conditions Appendix 3.1 Recommended measurements and checks Off-normal conditions detected by in-service measurements and checks 40 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29 VGB-S-115-00-2016-01-EN Appendix 3.2 Examples of actions on detection of off-normal conditions Example 1 Casing temperature difference, top/bottom (possible causes, for instance: internal casing leaks, damaged thermal insulation) Item in Appendix 3.1 2.2 Measurements and checks required: Interstage temperature Shaft, bearing housing, bearing vibrations Absolute and differential expansions Efficiency l Noise/rubbing Drains Thermal insulation Rundown time 1.2 3 4 11 12.1, 12.2 13 14 15 Additional checks recommended: Gland sealing system Heat consumption 6 11 Example 2 Thrust bearing temperatures rise (possible causes, for instance: higher axial thrust due to change in extraction steam flow, deposits, damage to blading, binding of casing supports) 5.2 Measurements and checks required: Stage pressures Absolute and differential expansions Lubricating oil system 1.1 4 10 Additional checks recommended: Behaviour of casing temperatures Vibrations Casing supports Efficiency Noise/rubbing Rundown time of turbine Foundation 2 3 7 11 12.1, 12.2 15 17 41 VGB PowerTech Publishing Services (c) Single User License Document, Licensee: - Lynda - Casey - lcasey@nrggos.com.au - 353 Hanson Road - Gladstone - 749765256 - 10 Sep 2020 05:41:29