10481-BCL-AKSX-PR-REP-0001-A0 NNPC Nigerian National Petroleum Corporation Ajaokuta Kaduna Kano Gas Pipeline Project PROCESS DESIGN BASIS 06-01-2021 Project Management Consultant EPC Contractor BRENTEXCPP Limited Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS REVISION A0 06-01-2021 5 01-11-2020 4 13-08-2020 3 18-07-2020 2 10-06-2020 1 AFC – Approved for Construction Prateek Sheikh Luo Yexin Prateek Sheikh Luo Yexin Prateek Sheikh Luo Yexin Nadeem Sheikh Luo Yexin IFA - Issued for Approval Shakeel Sheikh Luo Yexin 06-05-2020 IFR - Issued for Review Shadab Sheikh Luo Yexin 0 22-03-2020 IFR - Issued for Review Shakeel Sheikh Luo Yexin Rev. Date Status Description Originator Checked Approved IFC - Issued for Construction IFC - Issued for Construction IFA - Issued for Approval 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 2 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS TABLE OF CONTENTS 1 GENERAL 7 2 PURPOSE 7 3 DEFINITIONS AND ABBREVIATIONS 8 3.1 Definitions 8 3.2 Abbreviations 8 3.3 Referenced Documents 10 3.4 Metric System Used 12 3.5 Codes and Standards 14 4 5.0 6.0 OVERVIEW OF THE AKK PIPELINE SYSTEM 16 4.1 Key System Requirements 16 4.1.1 Early Gas Phase 16 4.1.2 Phase 1 16 4.1.3 Phase 2 16 4.2 Pipelines 17 4.3 Block Valve Station 17 4.4 Pigging Stations 18 4.5 Terminal Gas Stations 18 4.6 Design Life 18 4.7 Project Battery Limits 18 4.8 Environmental Conditions 19 4.7.1 20 Reference Conditions PROCESS DESIGN DATA 22 5.1 AKK pipeline sections design conditions 22 5.2 Gas Composition 23 5.3 Gas Properties 27 5.4 Gas Flow Rates 28 5.5 Battery Limit Conditions 29 PROCESS DESCRIPTION FOR SOW 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis 30 Page 3 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 7.0 INSTALLATIONS AT OFF-TAKE GAS METERING STATION 31 8.0 PROCESS AND MECHANICAL EQUIPMENT 32 8.1 Pig Launcher and Receiver 32 8.2 Filter Separator 32 8.3 Line Heaters 34 8.4 Gas Metering and Control Package (PCV) 34 9.0 PROCESS UTILITY SYSTEMS 37 9.1 Vent System 37 9.1.1 Piping System 37 9.1.2 Knock Out Drum 38 9.1.3 KO Drum Level Control System 38 9.1.4 Cold Vent Stack 38 9.1.5 Vent Gas Metering System 39 9.2 Fuel Gas System 39 9.3 Compressed Air System 40 9.4 Nitrogen System 41 9.5 Gas Engine Generator 41 9.6 Diesel Fuel System 42 9.7 Diesel Generator 42 9.8 Utility Water System 43 9.8.1 Pipes 43 9.8.2 Water wells 43 9.8.3 Submersible pumps 43 9.8.4 Raw water tank 43 9.8.5 Potable water treatment unit 43 9.8.6 Disinfection units 44 9.8.7 Potable water tanks 44 9.8.8 Pump units (booster unit) 44 9.9 Closed Drain System 9.10 Open Drain System 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis 46 46 Page 4 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 10.0 11.0 9.10.1 Pipes 47 9.10.2 Oil water separators 47 9.11 Simulations 47 KADUNA & KANO FACILITIES DESIGN BASIS 48 10.1 Criteria for sizing of station piping 48 10.2 Criteria for orifice meter sizing 48 10.3 Criteria for Relief System Sizing 49 10.3.1 Relief causes 49 10.3.2 General Design Criteria 49 10.3.3 Emergency isolation and blowdown system 51 10.3.4 Manual depressurization 51 HOLD LIST 52 FIGURES Figure 1 AKK (Segment 2) Overall Pipeline Route Figure 2 AKK Section Overview Map Figure 3 Project Overview Map Figure 4 Block Flow Diagram for AKK Pipeline (Segment 2) TABLES Table 1 Units of Measurement Table 2 List of applicable Codes and Standards Table 3 Pipelines of the AKK Section within the AKK pipeline system [Ref 2] Table 4 Block Valves of Pipeline Section within the TNGP System [Ref 27] Table 5 Location of Pigging Stations [Ref 27] Table 6 Location of Terminal Gas Stations [Ref 27] Table 7 Environmental Conditions for the AKK Project area [Ref 2, 28] Table 8 Pipelines operating and design conditions Table 9 Specification for Eastern Gas Supply System [Ref 2] 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 5 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Table 10 West African Gas pipeline (WAGP) Specification [Ref 2] Table 11 OB3 Pipeline Gas Composition [Ref 2] Table 12 Gas composition at Ikot Abasi Metering station [Ref 2] Table 13 Gas Composition at Ikot Abasi Metering Station (Thermochemistry) [Ref 2] Table 14 Gas specification and composition used for simulations. [Ref 2] Table 15 Trans Nigeria Gas Pipeline Project gas properties [Ref 2] Table 16 Summary of Gas volumes supplied withdrawn Table 17 Trans Nigeria Gas Pipeline Project pressure requirements at battery limit [Ref 4] Table 18 Design conditions for Pig Launcher and Receiver Table 19 Filter Separator Separation Efficiency - Kaduna & Kano TGS [Ref 14, 15] Table 20 Filter Separator Design Conditions- Kaduna & Kano TGS [Ref 14, 15] Table 21 Line Heater Design Conditions – Kaduna & Kano TGS Table 22 Gas Metering and Control Skid Design conditions- Kaduna & Kano TGS Table 23 Vent System Design Conditions Table 24 Fuel Gas System Design Conditions Table 25 Compressed Air System Design Conditions Table 26 Inlet Oil water parameters Table 26 Design Requirements for Station piping 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 6 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 1 GENERAL The Nigerian National Petroleum Corporation (NNPC), hereby referred to as the OWNER has awarded the contract to Brentex CPP Limited for the Engineering, Procurement and Construction of Ajaokuta Kaduna Kano (AKK) Gas Pipeline and Stations Project (Segment 2) from Block Valve Station 12 (outer line of the fence) to Kano Terminal Gas Station with a distance of about 318.66 km of the Trans Nigeria Gas Pipeline and stations. The pipeline runs from BVS12 roughly northern towards Kano TGS as illustrated in Figure 1 below: Figure 1 AKK (Segment 2) Overall Pipeline Route This document covers the technical requirements for engineering works and services, including all items such as pipelines, crossings, stations, BVS, ancillary installations, temporary installations, etc. 2 PURPOSE The purpose of the document is to provide the basis for developing the process deliverables for the AKK (Kaduna to Kano Section) scope of work. The scope of work is limited to KADUNA and KANO TGS stations along with the pipeline section from Block Valve Station 12 (outer line of the fence) to Kano Terminal Gas Station with a distance about 318.66km of the Trans Nigeria Gas Pipeline and stations. Therefore, this document will contain the design basis for KADUNA and KANO stations TGS facilities and pipeline. In addition to the requirement specified in this document, the relevant statutory authority requirements must be observed wherever applicable. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 7 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 3 DEFINITIONS AND ABBREVIATIONS 3.1 Definitions 3.2 PROJECT Ajaokuta Kaduna Kano Gas Pipeline Project. OWNER Nigerian National Petroleum Corporation (NNPC). PMC NETCO-ILF Consortium. CONTRACTOR Brentex CPP Limited. SUBCONTRACTOR The party(s) which carries out all or part of the engineering, design, survey and geotechnical investigation as specified by the CONTRACTOR. SUPPLIER The company or factory that designs and manufactures the Equipment and provides it to the OWNER of this Project. SUB-SUPPLIER The company or factory that subcontracts the design and manufacture of the equipment and provides to SUPPLIER for this Project. Shall Indicates a mandatory requirement. Should Indicates a strong recommendation. Abbreviations AG Above Ground AKK Ajaokuta – Kaduna – Kano API American Petroleum Institute bara Absolute pressure in bar barg Gauge pressure in bar BDV Blowdown Valve BL Battery Limit BVS Block Valve Station CCR Central Control Room CS Compressor Station DP Design Pressure DPR Department of Petroleum Resources EIA Environment Impact Assessment EGP Early Gas Phase 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 8 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS ELPS Escravos-Lagos Pipeline System EPC Engineering, Procurement and Construction ESD Emergency Shutdown F&G Fire and Gas FCV Flow Control Valve FOC Fiber Optic Cable FEED Front End Engineering and Design GA General Arrangement GC Gas Chromatograph GCV Gross Calorific Value GGS Gas Generator Set GP Gas Plant HC Hydrocarbons HHV High Heating Value IA Instrument Air ICAO International Civil Aviation organization ILF ILF Consulting Engineers KP Kilometer Point LHV Lower Heating Value LMLS Load Management and Load Shredding system MCC Motor Control Centre MMscfd Million Standard Cubic Feet per Day MS Metering Station NGC Nigerian Gas Company NNPC Nigerian National Petroleum Corporation OB3 Obiafu/Obrikom to Oben Pipeline Ob/Ob Obiafu/Obrikom OUA Obigbo-Umuahia-Ajaokuta PCV Pressure Control Valve PP Power Plant PPM Parts Per Million PS Pigging Station PSD Process Shutdown QIT Qua Iboe Terminal ROW Right of Way 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 9 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 3.3 RTU Remote Terminal Unit SA Service Air SCADA Supervisory Control and Data Acquisition SCR Station Control Room SOW Scope of work SDV Shutdown Valve TGS Terminal Gas Station TNGP Trans Nigeria Gas Pipeline TUCO Turbo compressor VTC Vendor to confirm WAGP West Africa Gas Pipeline WT Wall Thickness Referenced Documents Ref. 1 Document No. Document Title 10481-BCL-AKSX-PR-DWG-0001 Trans Nigeria Gas Pipeline System Flow Diagram for Segment 2 2 Deleted 3 10481-BCL-AKS4-PR-REP-0001 Heat and Material balance for Kano Terminal Gas Station 4 10481-MOM-NETCO-ILF-OSL0008 MOM-Steady State Hydraulic Simulation Alignment Meeting 5 10481-BCL-AKSX-PR-PHL-0005 Relief & Venting Philosophy 6 10481-BCL-AKSX-ME-SPC-0004 Specification for Fuel Gas Skid 7 10481-BCL-AKS4-PR-DAT-0001 Process Equipment Data Sheet- Fuel Gas Package Kaduna TGS 8 10481-BCL-AKSX-ME-SPC-0012 Specification for Air Compressor Package & Air Dryer Package 9 10481-BCL-AKS2-PR-CAL-0005 Process Calculation for utility system for Kaduna TGS. 10 10481-BCL-AKS4-PR-CAL-0005 Process Calculation for utility system for Kano TGS. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 10 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Ref. Document No. Document Title 11 10481-BCL-AKSX-PP-SPC-0002 Piping Material Class Specification 12 10481-BCL-AKS2-PR-CAL-0002 Process Calculation for Relief Load for KADUNA TGS 13 10481-BCL-AKS4-PR-CAL-0001 Process Calculation for Relief Load for KANO TGS 14 10481-BCL-AKS2-PR-DAT-0001 Process Equipment Data Sheet-Inlet Filter Separator Kaduna TGS 15 10481-BCL-AKS4-PR-DAT-0002 Process Equipment Data Sheet-Inlet Filter Separator Kano TGS 16 10481-BCL-AKSX-EL-SPC-0007 Low Voltage Diesel Generator Set Specification 17 10481-BCL-AKSX-EL-SPC-0006 Low Voltage Gas Generator Set Specification 18 10481-BCL-AKSX-ME-SPC-0003 Specification for Filter Separator 19 10481-BCL-AKPL-PR-PFD-0001 Process Flow Diagram For The Pipeline System for Segment 2 20 Deleted 21 Deleted 22 10481-BCL-AKS2-PR-REP-0002 Depressurization study Report for Kaduna TGS 23 10481-BCL-AKS4-PR-REP-0002 Depressurization study report for Kano TGS 24 10481-BCL-AKS2-PR-CAL-0001 Line sizing calculation notes Kaduna TGS 25 10481-BCL-AKS4-PR-CAL-0004 Line sizing calculation notes Kano TGS 26 O027-TQ-BCL-ILF-0051-TQ TQ Reply for Technical Clarification on Scope Of Work 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 11 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Ref. 3.4 Document No. Document Title 27 10481-BCL-AKPL-PE-REP-0004 Pipeline Station Location Selection Report 28 10481-BCL-AKGE-PR-REP-0005 Nigerian Meteorological Data Report Metric System Used The units used for all calculations and referenced on all drawings and documentation are given in SI units except piping diameter which will be given in inches, pressure given in bar, flow rate given in million standard cubic feet per day (MMscfd) and water content given in pounds per million standard cubic feet(lb/MMscfd). Any gas specifications and data provided by the Owner will be used in original units to maintain easy reference to the source [Ref 2]. Table 1 Units of Measurement Designation Length Time Pressure Differential Pressure Area 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Unit Abbreviation Kilometer km Meter m Centimeter cm Millimeter mm Year y Day d Hour h Second s bar absolute bara bar gauge barg bar, bar, Millibar mbar Square meter m2 Page 12 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Designation Unit Abbreviation Volume Cubic meter m3 Temperature Degree Celsius o Viscosity (Dynamic) Centipoises cP Viscosity (Kinematic) Centistokes cSt Flow rate (Mass) Kilogram per hour kg/h Flow rate (Volume for Gas) Million Standard Cubic MMscfd feet per day Flow rate (Volume for Gas) Standard Cubic Feet per SCFH hour Flow rate (Volume for Gas) Standard Cubic Feet per SCFM minute Flow rate (Volume for liquid) Cubic meter per hour m3/h Flow Velocity Meter per second m/s Force Kilonewton kN Energy Joule J Kilojoule kJ Megajoule MJ Revolution per minute rev/min Rotation Speed C rpm Electrical Voltage Electrical Current Electrical Frequency 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Volt V Kilovolt kV Millivolt mV Ampere A Kilo ampere kA Milliampere mA Hertz Hz Page 13 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Designation Unit Electrical Power Stress Abbreviation Kilowatt kW Kilovolt-ampere kVA Pounds per Square inch psi Newton per square Milli- N/mm2 meter MPa Mega Pascal kPa Kilo Pascal Weight 3.5 Kilograms kg Pounds lb Angles Degree O Velocities Meter per second m/s Acceleration Meter per square second m/s2 Codes and Standards Table 2 Sr. No. List of applicable Codes and Standards Standard Description 1 API 5L Specification for Line Pipe 2 API 6D Specification for Pipeline valves. 3 API STD 520 Sizing, Selection, and Installation of Pressure-Relieving Devices in Refineries, Part I. 4 API RP 520 Sizing, Selection, and Installation of Pressure-Relieving Devices in Refineries, Part II. 5 API STD 521 Pressure Relieving and Depressuring Systems. 6 API STD 530 Calculation of Heater-Tube Thickness in Petroleum Refineries 7 API RP 535 Burners for Fired Heaters in General Refinery Services 8 API STD 560 Fired Heaters for General Refinery Services 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 14 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Sr. No. Standard 9 API STD 619 Rotary – Type Positive Displacement Compressors 10 API STD 661 Air-Cooled Heat Exchangers for General Refinery Service 11 API STD 680 Packaged Reciprocating Plant and Instrument Air Compressors for General Refinery Services 12 ASME B16.47 Large Diameter Steel Flanges 13 ASME B16.5 Pipe Flanges and Flanged Fittings 14 ASME B31.3 Process Piping 15 ASME B31.8 Gas Transmission and Distribution Piping Systems 16 ASTM D1785 Standard Specification for Poly (Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40, 80, and 120 17 ASTM D3350 Standard Specification for Polyethylene Plastics Pipe and Fittings Materials 18 ASTM F714 Standard Specification for Polyethylene (PE) Plastic Pipe (DR-PR) Based on Outside Diameter 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Description Page 15 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 4 OVERVIEW OF THE AKK PIPELINE SYSTEM 4.1 Key System Requirements The AKK Gas Pipeline Project (as part of the planned Trans Nigerian Gas Pipeline network) needs to be constructed to accommodate future gas demands and supplies. The design pressure of the future gas pipeline supplying the gas to future consumers and connected downstream TGS will be at the same value as a design pressure of the TGS. The project development phases are identified and captured in the time frame of three expansion phases: 4.1.1 Early Gas Phase Early Gas Phase is driven by availability of two main gas sources Oso Platform (gas delivered via Qua Iboe Terminal) and existing Cawthorne Channel, Alakiri and Obigbo satellite gas plants and the need of gas supply to the Escravos Lagos Pipeline (Western Gas Transmission System). Gas from QIT will be transferred through new QIT-Obigbo-Ob/Ob pipeline to Ob/Ob metering station upstream of the inlet to the OB3. Gas from Cawthorne Channel and Alakiri will be transferred through new Cawthorne Channel-Obigbo pipeline. 4.1.2 Phase 1 Phase 1 is driven by availability of additional gas supplies from Assa Gas Plant and the need of gas supply to the Northern / Eastern States through new Obigbo-UmuahiaAjaokuta pipeline and new Ajaokuta-Kaduna-Kano pipeline. 4.1.3 Phase 2 Phase 2 accounts mainly for additional gas supplies from a further increased capacity of Oso Platform via QIT. Gas from QIT in addition to the QIT-Obigbo-Ob/Ob pipeline will be evacuated through new QIT-Uyo-Umuahia pipeline. Phase 2 is not within the scope of work of this project. However, the system has to be designed in such a way that allows for expansion to phase 2 when additional gas volumes will be available and will need to be transported. Therefore, the station inlet and outlet headers as well as the linear pipeline section shall be designed for phase 2 flow rates. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 16 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 4.2 Pipelines The pipeline project scope is summarised in the following table: Table 3 Pipelines of the AKK Section within the AKK pipeline system [Ref 2] Development Phase Pipeline Phase1 Station Name Section Size Ajaokuta – Kaduna - Block Valve Station Kano Gas Pipeline 12-Kaduna TGS 40” Kaduna TGS – Zaria PS and future tie-in for TGS 40” Zaria PS- Kano TGS 40” In general, the operation of pipeline will be one direction. 4.3 Block Valve Station The block valve stations in the project scope are tabulated as follows (spacing is according to ASME 31.8 and local regulations if more stringent requirements are applicable): Table 4 Development Phase Phase1 Block Valves of Pipeline Section within the TNGP System [Ref 27] Pipeline Station Name KP Block Valve Station 13 333.955 Block Valve Station 14 361.328 Block Valve Station 15 380.334 Block Valve Station 16 411.548 Ajaokuta –Kaduna – Block Valve Station 17 445.362 Kano Gas Pipeline Block Valve Station 18 473.491 Block Valve Station 19 525.633 Block Valve Station 20 554.654 Block Valve Station 21 577.159 Block Valve Station 22 598.061 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 17 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 4.4 Pigging Stations Following pigging stations are foreseen in the Segment 2 pipeline system (in accordance with Pigging philosophy Doc. No 10481-BCL-AKGE-PM-PHL-0002) Table 5 Development Phase Phase1 4.5 Location of Pigging Stations [Ref 27] Pipeline Station name KP Kaduna Pigging Station KP 402.443 Ajaokuta –Kaduna – Zaria Pigging Station KP 496.408 Kano Gas Pipeline Kano Pigging Station KP 623.27 Terminal Gas Stations The terminal gas station will be designed to measure gas flow rate, to reduce gas pressure accounting for the full range of expected downstream gas volumes and pressures. The station shall be self-supporting with full process and utilities systems within the plant battery limit. The Segment 2 pipeline system configuration accounts for terminal gas stations as detailed in the following table: Location of Terminal Gas Stations [Ref 27] Table 6 Development Phase Phase1 4.6 Pipeline Station name and location Ajaokuta –Kaduna Kaduna Terminal Gas Sta– Kano Gas Pipe- tion line Kano Terminal Gas Station KP KP 402.443 KP 623.27 Design Life The entire Pipeline System including equipment, such as block valve stations, pigging stations and metering stations, shall be designed for a life time of twenty-five years. 4.7 Project Battery Limits The battery limits of the Ajaokuta-Kaduna-Kano Gas Pipeline system are: 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 18 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS According to the project scope of work, AKK Project (Segment 2) concerns only with Early Gas Phase (EGP) and Phase 1. However, analysed system has to be designed in a way that allows for expansion to Phase 2, when additional gas volumes will be available and will need to be transported. Ajaokuta Kaduna Kano (AKK) Gas Pipeline and Stations Project (Segment 2) start from Block Valve Station 12 (outer line of the fence) to Kano Terminal Gas Station. At BVS 21, an offtake towards Kano IPP (17.6 km 24” spur line) is to be provided for future provision. A flow rate of 270 MMscfd shall be foreseen for the Phase 1 / 2 offtake. While this additional spur line is out of scope for the project, the additional 270 MMscfd will have to be considered in the hydraulic simulations. 4.8 Environmental Conditions Topography: Rather flat /hilly, raising to the north after Izom city Climate: Tropical savannah (wet and dry) climate (Aw acc. to Köppen-Geiger classification) Temperatures: High Rainfall: High during wet season (April to November) Humidity: Low. Soil pH: from 5.6-6.0 (moderately acid) to 6.1-6.5 (slightly acid) from Kaduna to Kano. The environmental conditions for the AKK Project area are presented in Table 7. Table 7 Environmental Conditions for the AKK Project area [Ref 2, 28] Location Northern Part (AKK) Design wind velocity (Kaduna) 50 km/hr (14 m/s/27Knots) Design wind velocity (Zaria) 55.6 km/hr (15.4 m/s/30 Knots) Design wind velocity (Kano) 50 km/hr (14 m/s/27Knots) Design Wind Speed for Structural Design 144 km/hr (40 m/s) Mean maximum ambient temperature (Kaduna) 41.7 °C Mean Minimum ambient temperature (Kaduna) 14.2 oC Mean maximum ambient temperature (Zaria) 38.5 °C 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 19 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Location Northern Part (AKK) Mean Minimum ambient temperature (Zaria) 13.1 oC Mean maximum ambient temperature (Kano) 41.0 °C Mean Minimum ambient temperature (Kano) 8.4 oC Black Bulb Temperature 60°C Minimum average relative humidity 60% Ground Temperature 25°C Maximum relative humidity 98% Mean annual total rainfall (period of the year) 700 mm Design average annual rainfall (period of the year) 700 mm Design mean maximum hourly rainfall 70 mm Prevailing wind direction south-west Seismic zone according to Modified Mercalli scale (MM) Zone 0: MM V and below 4.7.1 Reference Conditions The reference pressure and temperature for “standard cubic feet” are defined as 1.013 Bara and 15.56°C respectively [Ref 2]. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 20 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Figure 2 Figure 3 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis AKK Section Overview Map Project Overview Map Page 21 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 5.0 5.1 Process Design Data AKK pipeline sections design conditions Figure 4 Block Flow Diagram for AKK Pipeline (Segment 2) 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 22 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Table 8 Pipelines operating and design conditions Pipeline Maximum Operating Pressure Ajaokuta– Kaduna– Kano Gas Pipeline 94 barg 5.2 Design Pressure Maximum design temperature Minimum underground design temperature Minimum above ground design temperature Supply Temperature From Segment 1 98 barg 60˚C 0˚C -29˚C 25˚C Gas Composition Gas supplied to Trans Nigeria Gas Pipeline System is considered as dry, sweet gas that meets NGC’s gas quality specification. The gas specification for Eastern Gas Supply Systems (for Obigo Node, Alscom, Ibom Power etc.) is presented in Table 9 below. Table 9 Specification for Eastern Gas Supply System [Ref 2] Composition Minimum Maximum Hydrocarbon Dew Point 0 10°C Water Content 0 7lbs/MMscf Methane 82% 96% Vol Ethane 0.1% 10% Vol Propane 0.1% 8% Vol Butanes 0 5% Vol Pentanes 0 1.10% Vol Hexane- Plus 0 1.0% Vol Total inert gases 0 15% CO2 0 10% N2 0 3% Vol H2S 0ppm 10ppm Total Sulphur 0ppm 28ppm 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 23 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Composition Minimum Maximum O2 0ppm 10ppm Higher heating Value (GCV) 950btu/scf 1150btu/scf Wobbe Index(HHV basis) 47 MJ/m3 52 MJ/m3 Delivery Temperature 20°C 50°C The gas specification for West African Gas Pipeline Specification (for ELPS, Oben Node, Ajaokuta etc.) is presented in Table 10 below: Table 10 West African Gas pipeline (WAGP) Specification [Ref 2] Composition Minimum Maximum C1 84% Vol 95% Vol C2 - 10% C3 - 8% C4+paraffin - 5% CO2 - 4% N2 - 3% H2S - 4ppm by volume Total Sulphur - 28ppm O2 - 10ppm H2O - 7lb/MMscf HC Dew Point - 10°C Higher Heating Value 1000 btu/scf 1150btu/scf Wobbe Index 47 MJ/m3 52 MJ/m3 1281 (based on btu/scf) 1396 (based on btu/scf) 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 24 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS OB3 Pipeline Gas Composition (for the fields around Obite Gas Plant) is presented in Table 11 Table 11 Obite GP OB3 Pipeline Gas Composition [Ref 2] AgipEbocha AgipIdu AgipAgb ainbiri AgipAkri Assa North Central CPF Ready beyond 2015 Volume (MMscfd) 165 50 150 100 20 1000 (>2016) 6000 Component Mole % Mole % Mole % Mole % Mole % Mole % Mole % C1 83.874 85.370 94.6 88.960 80.280 89.77 98.8 C2 6.887 6.701 3.26 5.260 8.680 3.95 0.92 C3 3.423 4.091 0.250 2.700 4.900 2.64 0.1 C4 1.596 2.206 0.150 1.140 2.230 1.20 0 C5 0.518 0.994 0.050 0.310 0.680 0.35 0 C6+ 0.423 0.000 0.130 0.280 0.250 0.36 0 CO2 3.220 0.506 1.439 1.218 2.852 1.65 0 N2 0.058 0.130 0.120 0.130 0.130 0.08 0.2 Total 100 100 100 100 100 100 100 Gas composition of the sample taken from the Ikot Abasi Metering Station is presented in Table 12 and 13 below Table 12 Gas composition at Ikot Abasi Metering station [Ref 2] Sr. No Compound Symbol Mole % 1 Methane C1 86.85 2 Ethane C2 5.33 3 Propane C3 3.54 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 25 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Sr. No Compound Symbol Mole % 4 Normal butane n-C4 1.05 5 Iso Butane i-C4 0.62 6 Normal Pentane n-C5 0.28 7 Iso Pentane i-C5 0.30 8 Hexane C6+ 0.14 9 Carbon Dioxide CO2 1.85 10 Oxygen O2 0.00 11 Nitrogen N2 0.04 Table 13 Gas Composition at Ikot Abasi Metering Station (Thermochemistry) [Ref 2] Thermochemistry Parameters Value Unit Avg. Molecular Wt 19.43 g/mole Specific gravity 0.673 SG Hydrocarbon Dew Point Temperature N/A °C Water Dew Point temperature N/A °C Moisture Content 4.50 lb/MMScf Higher Heating value 1150.45 btu/Scf Lower Heating Value 1040.84 btu/Scf Wobbe Index 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis 1402.37 Page 26 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS For the purpose of the simulations, gas compositions as per FEED Stage Heat and Mass Balance – Kano TGS (Document No: G791-ILF-AKS4-PR-CAL-0002 REV. 1) shall be taken, since the available gas specification provided by NNPC (Eastern Gas Supply Systems and WAGP Gas Specification) are adjusted in a way to cover the range of C6+ at a higher possible level, keeping the gas specification requirements i.e. water dew point, hydrocarbon dew point and heating value to account for any liquid components that may be seen during pipeline and stations operation. The gas specifications are given in Table 14. Table 14 5.3 Gas specification and composition used for simulations. [Ref 2] Component Unit Gas Composition used for simulations C1 % mol 84.04 C2 % mol 6.79 C3 % mol 3.42 i-C4 % mol 0.82 n-C4 % mol 0.74 i-C5 % mol 0.31 n-C5 % mol 0.25 C6+ % mol 0.27 N2 % mol 0.15 CO2 % mol 3.21 H2O lb/MMscf 7 HC Dew Point °C 9.9 MW kg/kmol 20.03 Gas Properties The gas properties as defined in Table 15 shall be used in equipment specifications for the Project. Values are extracted from the Eastern Gas Supply System gas specifications provided. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 27 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Table 15 Trans Nigeria Gas Pipeline Project gas properties [Ref 2] Component Unit Gas Source Eastern Gas Supply System C1 % vol 82-96 C2 % vol 0.1-10 C3 % vol 0.1-8 C4 % vol 0-5 C5 % vol 0-1.1 C6+ % vol 0-1 CO2 % vol 0-10 N2 % vol 0-3 H2O % vol - H2S ppm 0-10 Water Content lb/MMscfd 0-7 Water Content mg/m3 0-112 HC Dew Point °C Maximum 10 HHV Btu/scf 950-1150 Wobbe Index MJ/m3 47-52 Btu/scf 1261-1396 5.4 Gas Flow Rates The Table 16 summarizes the gas volumes supplied to and withdrawn from the AKK pipeline system at the battery limit of each pipeline section. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 28 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Table 16 Facility Summary of Gas volumes supplied withdrawn In-take Cumulative gas in-take/gas withdraw (MMscfd) Off-take Early Gas Phase Phase 1 Phase 2 Ajaokuta – Kaduna – Kano Gas Pipeline (AKK) Kaduna TGS - 175 280 Zaria TGS - 0 140 Kano IPP - 270 270 Kano TGS - 50 50 Total Intake from Segment 1 - 495 740 5.5 Battery Limit Conditions Battery Limit conditions at the TGS are provided below in the table. Table 17 Trans Nigeria Gas Pipeline Project pressure requirements at battery limit [Ref 4] Selection Criteria AKK Gas Pipeline Min. gas arrival pressure at Kaduna TGS: 43 barg Min. gas arrival pressure at Zaria TGS: 43 barg Min. gas arrival pressure at Kano TGS: 43 barg Min. gas outlet pressure at Kaduna TGS : 39 barg Min. gas outlet pressure at Zaria TGS : 39 barg Min. gas outlet pressure at Kano TGS : 39 barg Erosional velocity / Design velocity: 18 m/s / 9 m/s 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 29 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 6.0 Process Description for SOW Gas from AKK Gas Pipeline will be partially transferred to the Kaduna Terminal Gas Station, while the surplus gas will be further transported to Kano Terminal Gas Station through the AKK pipeline which is a termination point for the AKK pipeline. Gas will arrive at the respective TGS and will flow to the process trains for treatment before sending the gas to the off-takers. Inlet Filter Separators will be the first stage of the gas conditioning to remove any solid and liquid particles from the gas stream. Next the gas will be transferred to the Line Heaters for heating. The heater outlet temperature shall compensate for the following gas cooling at the metering and control skid caused by the Joule Thomson effect”. After passing through the line heaters, the heated gas will flow to the Gas Metering and Control Skid. The PCV which is part of the metering and control package will maintain a constant gas pressure at the TGS outlet header and at the same time will restrict the flow to limit the gas drawn (pressure control with flow-rate override). The export gas drawn from the TGS system will be measured and recorded by the metering system, which will be installed upstream of the pressure control valve. The metering and control package will provide custody transfer rates between AKK Gas Pipeline and gas off-takers downstream the TGS will reduce gas pressure and control gas flow to the gas off-takers and will transmit the AKK system boundary conditions data (actual pressure and flow) to the SCADA and Pipeline Leak Detection System. The Kaduna-Kano pipeline section will be equipped with intermediate Pigging stations. Kaduna and Zaria Pigging station will be each equipped with Pig Launcher and Receiver, whereas Kano TGS will be equipped with only a Receiver. The design of the launcher will be capable to perform intelligent pig launching operation. The SDV valve will be provided at the station inlet and outlet. In case of an emergency event the SDV valves will cut off the gas supply from the AKK and to the off-takers. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 30 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 7.0 Installations at Off-Take Gas Metering Station There are several gas in-takes and off-takes of the analysed pipeline system. The gas volumes supplied to the network and off-taken from the system are based on “The System Selection Report [Ref.20] and based on the new future offtake towards Kano IPP (17.6 km 24” spur line) with a flow rate of 270 MMscfd.[Ref 26] According to the project scope of work, AKK Project concerns only Early Gas Phase (EGP) and Phase 1. However, analysed system has to be designed in such a way that allows for expansion to Phase 2, when additional gas volumes will be available and will need to be transported. Ajaokuta Kaduna Kano (AKK) Gas Pipeline and Stations Project (Segment 2) starts from Block Valve Station 12 (outer line of the fence) to Kano Terminal Gas Station. This section covers the process facilities required at Kaduna and Kano Off-Take Gas Metering Stations. The process facilities at Off-Take MS will include: • Pig Launcher(to be provided at Kaduna TGS); • Pig Receiver (to be provided at Kaduna & Kano TGS); • Filter Separator Skids; • Gas Line heaters • Gas Metering and Control Packages; Utility Systems including: • Vent System • Instrument Air System • Fuel Gas Conditioning System • Nitrogen system • Fire Fighting System ( includes Fire Water Pump Package) • Utility Water System • Diesel Fuel System • Diesel Generator Set • Gas Engine Generator Set • Utility Air System • Closed Drain System 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 31 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 8.0 Process and Mechanical Equipment 8.1 Pig Launcher and Receiver Pig Launcher shall be designed for use of intelligent pigs (6 m maximum length). Design code for Pig Launcher will be ASME B31.8 or ASME Section VIII Div 2 and shall be confirmed later. In case of ASME B31.8 use, a design factor depending on the location but not less than Location Class 2 shall be taken. The same corrosion allowance for the launcher/receiver as for the pipeline shall be considered. The quick opening closure shall be equipped with a mechanical interlocking system to prevent opening of a pressurized vessel. Pig signallers will be installed on both sides of the pig launcher/receiver outlet valve to provide confirmation that the pig was successfully launched/ received and passed through the pig trap valve. Provision shall be made in layout for pig trays with handling and lifting facilities for pig inserting/removal operations. The hazardous fluids drained from the pig launchers and receivers containing flammable or hazardous substances will be drained to the closed drain system. Table 18 8.2 Design conditions for Pig Launcher and Receiver Design Pressure (barg) Design Temperature (°C) 98 -29 to 60 Filter Separator Inlet gas arriving at stations is specified as a dry gas with a maximum hydrocarbon dew point of 10°C and a minimum inlet temperature of 20°C. It is therefore assumed that condensation of gases at station inlet does not occur and under normal operating conditions only minor amounts of solids may be expected. In case of off-spec gas and/or during commissioning, gas might condensate, leading to liquids in the lines. Thus, for protection of the downstream equipment, 2-stages, horizontal Filter Separators shall be installed. The horizontal filter separator vessels shall contain two separation sections and separate condensate collection sumps located below. It is envisaged that the filters shall be cartridge type at 1st stage and vane type at 2nd stage. The filters will be installed in parallel with a filtration capacity sufficient to treat the maximum nominal gas flow rate at 0.5 bar maximum pressure drop (clean). The criterion for separation efficiency of the filter separator has been shown in table 19[Ref 14, 15]. The filters will be equipped with differential pressure monitoring and automatic liquid discharge to the closed drain system. Potential 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 32 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS overfill and gas break through shall be monitored and automatic PSD measures shall be in place to protect the subsequent systems [Ref 2]. Filter Separator Separation Efficiency - Kaduna & Kano TGS [Ref 14, 15] Table 19 Separation Efficiency Liquid Droplets Solid Droplets ≥1 μm 99% ≥3μm 100% ≥1 μm 99% ≥3μm 100% Filter separators and all other pressurized components shall be designed, fabricated, welded and tested in accordance with ASME VIII Division 1. The filter separators shall be designed and manufactured to ensure low-maintenance, long-lasting and reliable operation. [Ref 14, 15] The quick opening closure shall be equipped with a mechanical interlocking system to prevent opening of a pressurized vessel. Filters shall be equipped with manual venting facilities. The design and operating conditions of filter separator at Kaduna and Kano TGS are as follows [Ref 2, 14, 15]: Table 20 Filter Separator Design Conditions- Kaduna & Kano TGS [Ref 14, 15] Parameter Value for KADUNA TGS Value for KANO TGS Design Pressure 98 barg 98 barg Design Temperature -29/60°C -29/60°C 175MMscfd 50 MMscfd Number of Filter Separator 2x100%W 2x100%W Maximum pressure drop clean 0.5 bar 0.5 bar Maximum pressure drop dirty 1.0 bar 1.0 bar Operating Capacity Each Filter Separator 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis of Page 33 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 8.3 Line Heaters The Line Heaters shall be provided at stations where gas pressure reduction is required before gas is transferred to gas off-takers. The gas temperature shall be set at a level to compensate for the J-T effect (gas temperature reduction during gas pressure reduction) and to provide gas superheating about 15°C above HC dew point temperature at the TGS outlet. Thus, the gas shall be heated in indirect water bath line heaters. The Line Heater shall be provided with atmospheric expansion tank, manual drain; main burner; pilot burner; fuel gas and combustion air system. The gas heating coil will be immersed into the hot water contained in the boiler. The temperature of the gas delivered to the TGS outlet header will be controlled by a temperature control loop using the heater by pass. The design pressure in combination with the design temperature may require ASME Class 900 flanges [Ref 2]. The design and operating conditions of line heaters at Kaduna and Kano TGS are as follows: Line Heater Design Conditions – Kaduna & Kano TGS Table 21 Parameter Value for KADUNA TGS Value for KANO TGS 98 barg 98 barg -29°C - 100°C -29°C - 100°C 25oC 25oC Number of Line Heater 1W+1S 1W+1S Maximum pressure drop clean 0.5 bar 0.5 bar Design Pressure Coil Design Temperature Gas Temperature PCV Downstream 8.4 Gas Metering and Control Package (PCV) The Gas Metering and Control Package shall be provided, designed for gas pressure and volume flow control and custody transfer rates between the stations. The gas metering and control package shall be designed as package-unit, skid-mounted, with all necessary ladders and platforms provided. Gas Metering and Control Package shall consist of four main functions: • Gas metering – meters installed within the skid; 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 34 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS • Online proving - master meter (meter prover) installed on the separate prover run within the skid; • Downstream pressure control – PCV installed within the skid; • Gas analysis – separate Gas Chromatograph delivered with the skid. For metering, orifice meters (e.g., senior orifice & Ultrasonic) compliant to custody transfer certification by DPR are planned which allow for fast and simple exchange of orifice plates under pressure without flow interruption. These metering runs (custody transfer) will be provided with a separate, dedicated prover run and a gas chromatograph (GC) recording gas composition data. The GC shall meet requirements of the DPR “Guidelines for the Determination of Quantity and Quality of Gas at Custody Transfer Points”. The gas chromatograph shall be located close to the Gas Metering and Control Skid to allow for the shortest practical sampling route between the sampling point and analyser. Water dew point analysis shall be implemented in form of dedicated water dew point analyser. Single sampling point shall be provided for each fiscal metering skid. sampling probe / sensor shall be designed such that it is possible to be retracted under operating pressure. Analyser shall indicate water dew point and moisture content as a minimum. Water dew point measuring system shall be equipped with automatic compensation of pressure and temperature. The whole uncertainty of the water dew point calculation shall be ±0.5 °C or better. The Gas Metering and Control Package will be also used to transmit AKK system boundary conditions data (actual pressure and flow) to the SCADA and pipeline leak detection system. The pressure control valves shall be installed downstream each meter lines to cover control requirements of the station design conditions. The turn-down ratio of the control valves shall be the same or better than that of the metering equipment [Ref 2]. The gas metering and control skid design conditions at Kaduna and Kano TGS are as follows: Table 22 Gas Metering and Control Skid Design conditions- Kaduna & Kano TGS Parameter Value for KADUNA TGS Value for KANO TGS Design Pressure 98 barg 98 barg Design Temperature -29/60°C -29/60°C Required min. pressure downstream PCV 45 barg 45 barg 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 35 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Parameter Value for KADUNA TGS Value for KANO TGS 175 MMscfd 50 MMscfd 2 (1W+1S) 2 (1W+1S) Size of Meter Run (Inch) 16 (VTC) 8(VTC) Size of (Inch) 16(VTC) 8(VTC) Operating Capacity Number of Meter Run Meter Prover 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 36 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 9.0 Process Utility Systems The process utility systems described below shall be provided at each Metering Station. 9.1 Vent System Vent system shall provide safe and reliable method for disposal of flammable gases during the following scenarios: • Relief due to fire in the pipeline system; • Relief due to malfunction of process equipment, process upsets, utility failure, blocked outlet, etc.; • Emergency depressurization (either manual or activated by the ESD system); • Maintenance depressurization. The vent system shall comprise of the following main components shortly described in paragraphs below [Ref 22, 23]: • • • • 9.1.1 Piping system (tail pipes, sub-headers and main header); KO drum; KO drum level control system (Level control valve and drain pipes); Vent stack package including vent stack tip and vent stack riser. Piping System Cold vent collection headers are required to collect relief, blowdown and venting loads from the facility and route them to the knock out (KO) drum. Materials of cold vent system piping shall account for the most extreme release conditions and any temperature drop which may occur during depressurization process due to the Joule-Thomson effect. The design shall be done on a basis of maximum allowable mach number or maximum allowable back pressure (whichever is more stringent). The velocity in the cold vent piping shall not exceed Mach number of 0.6 in the main headers and 0.7 in the tail pipes. The velocity in the cold vent stack shall not exceed 0.5 Mach for peak flow. The maximum allowable back pressure shall not reduce relieving capacity of any of the pressure relieving device and shall be lower than pressure rating of piping materials [Ref 5]. Vent header shall be self-draining with no low points towards to the KO drum. The piping between cold vent stack and KO drum shall be sloped to the drum. The minimum slope in both cases shall be 1:500 [Ref 5]. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 37 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS The cross-sectional area of cold vent piping in each section shall not be lower than that in the preceding section. Lines from individual relief valves should be sized for the PSV rated flow. The main header, sub-headers, KO drums, cold vent stack and cold vent tips shall be sized to handle the maximum coincidental emergency loads. Since the simultaneous occurrence of two or more unrelated contingencies is unlikely, unrelated contingencies should not be used as a basis for determining the maximum system load. 9.1.2 Knock Out Drum From main header gas will flow through the knock-out drum to collect liquid droplets (if any) and further to the cold vent stack. Knock out drum is required to separate condensed liquids from gas in inlet stream and to hold the maximum amount of liquid that can be relieved during an emergency depressurization. Collected liquids shall be routed to the closed drain system [Ref 5]. KO drum shall be installed as close as possible to the cold vent stack. Possibility of personnel access for maintenance on KO drum shall be taken into consideration in case of cold vent systems with automatic depressurization [Ref 5]. KO drum shall be sized for maximum gas relief case and case at which maximum liquids (if any) may appear. KO drum shall be sized so that maximum size of exiting droplets will not be larger than 600 microns as per API 521. 9.1.3 KO Drum Level Control System KO drum shall be equipped with Level control system used for removing accumulated liquid from the drum. The capacity of KO control valve shall be sufficient to drain out the liquid between high level to low level within 10 minutes. The level control valve shall open at high level on KO drum and close on low level. This will avoid the ESD level 2 tripping in TGS which will be activated on high-high liquid level in KOD [Ref 5, 12]. 9.1.4 Cold Vent Stack Cold vent stack shall be sized so that dispersion of gas into the atmosphere will not be harmful to the personnel. Location of the cold vent stack shall be downwind or crosswind of personnel accommodation and/or work areas based on the prevailing wind conditions. The location of the vent stack(s) shall be in a safe distance from process facilities, fence line and occupied buildings at the station [Ref 5]. The height and location of the vent stack shall be selected so that the concentration of vapour at a point of interest is below the lower flammable limit of the vapour. The height 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 38 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS and location shall also be selected taking possible unintended ignition of the vented gas into account [Ref 5]. Aircraft warning lights shall be installed at the cold vent stack structure (45m or above) as per ICAO requirement. Lightening arrestors shall be foreseen in the cold vent system design. This is applicable to Kaduna, Kano, Zaria Stations and Block Valve Stations. 9.1.5 Vent Gas Metering System Vent gas metering device shall be provided on vent lines upstream of cold vent stack (downstream of KO drum, if any). The metering devices shall be suitable for high turndown ratios. The volume of vent gas shall be recorded in station control system and transferred to SCADA [Ref 5]. Any gas releases due to the operational upsets, gas venting or ESD operation shall be measured as per DPR requirements. Thus, metering will be provided as a part of cold vent stack system. Table 23 Description Vent System Design Conditions Vent KO Drum Design Pressure (barg) FV/10 Design Temperature (°C) -46/80 Vent Stack FV/10 -45/210 9.2 Fuel Gas System Fuel gas conditioning sequence is described as follows: • Removal of liquids and solids by filtering; • Temperature controlled pre-heating upstream the pressure reduction valve; • Pressure reduction to required pressure level; Fuel gas system mainly consists of filtering system, gas metering system, gas pre-heating, pressure reducing, protection with safety shut-off valves and relief valves, isolation valves and piping components with fittings, flanges and bolting materials. Fuel gas system shall be configured as 100% redundant. One train in operation and one train stand by. Each fuel gas unit skid shall be designed according to the fuel gas system specification [Ref 6] 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 39 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS The filters shall be able to remove 99% of solid particles down to 10 microns and larger [Ref 7]. The fuel gas system take off shall be downstream of the station filter separators for normal station operation, however, alternative supply from the pipeline for the station start-up and/or upset shall be considered in the design. The fuel gas system shall supply high pressure consumers (turbines) and low-pressure gas consumers including gas generators. Table 24 Fuel Gas System Design Conditions Equipment Design Pressure (barg) Design Temperature (°C) Coalescer 98 (-)29 - 60 Electric Heater 98 (-)29 - 100 9.3 Compressed Air System A station instrument air (IA) and utility air (UA) facility including a distribution system shall be provided. The compressed air system mainly serves for the reliable and cost-effective supply of compressed air for the compressor stations. Mainly block and control valves with pneumatic actuators are supplied with compressed air. The compressed air system shall consist of air compressors, buffer tanks, dryer pack-ages with relevant filters, air receivers (storage tank) and relevant piping system. Instrument air unit shall be skid mounted [Ref 8]. The IA and UA facilities will be located under a common sun shed. To prevent condensation in the supply piping and instruments, the dew point of the compressed air at operating pressure shall be at the level required by the nitrogen generation package and instrument gas consumers’ Vendor but at least 10 °C below the lowest expected ambient temperature [Ref 2]. Table 25 Compressed Air System Design Conditions Design Pressure (barg) 10 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Design Temperature (°C) 80 Page 40 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 9.4 Nitrogen System Nitrogen bottles shall be provided to purge the vent system and for maintenance purging of process equipments. For the purpose of vent header purging, nitrogen bottled package is provided with permanent connect to vent header. An adequately sized restriction orifice alongwith isolation valve shall be provided at the vent header for operator to sweep-through purge the vent header to reduce oxygen concentration upto allowable limit (6% as per API-521), to remove air ingresses in to vent system for prevent formation of flammable mixture in and to minimise nitrogen loss during purging. In scenario of accidental fire at the vent stack, nitrogen package can also utilize for extinguishing the fire. This shall be done using fire snuffing connection at the vent header (in the downstream of KOD). An adequately sized restriction orifice alongwith isolation valve shall be provided at the vent header for operator to extinguish the fire. For maintenance of process equipment, the purging of process equipment shall be performed to reduce oxygen concentration upto allowable limit (6% as per API-521) for maintenance and prevent any chance of accidental fire during ventilation of process equipment. The vessel purging shall be done using mobile bottles by connecting directly to the vessel. 9.5 Gas Engine Generator Each GGS shall consist of the following main parts: • Gas engine; • Generator; • Starter equipment; • Fuel system; • Lubrication system; • Air intake and exhaust system; • Acoustic enclosure; • Auxiliary power distribution system; • Protection, control and monitoring system. Gas generators sets (GGS’s) will operate as a local power plant (PP) providing primary power supply for the Kaduna & Kano TGS. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 41 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Each PP will operate in 1+1 philosophy with 1 GGS’s operating as primary unit and 1 GGS operating as a stand-by unit at one time. Each GGS will be utilized as a primary and standby unit rotationally. Changeover sequence will be automatically performed by the Power Plant Control System (PPCS) through load management and load shredding system (LMLS)in order to ensure equal, annual operation time of each unit. PP shall operate in such way that there will always be at least 15% of single GGS nominal power available in a system as a spinning reserve. If there is not enough spinning reserve in the system, then additional GGS will be started immediately. In case of any abnormal condition in the running gas generator viz. overheating, failure of auxiliaries, overload scenarios etc, the standby gas generator is capable to take full load automatically of TGS (within a span of 1-2 min approx.) to provide uninterrupted power supply & prevent TGS shutdown due to power supply failure. Generators shall operate with their star points directly grounded. Gas engine and generator shall be placed on a common base frame and connected with a dry flexible coupling. The GGS’s shall be installed in the acoustic enclosures [Ref 17]. 9.6 Diesel Fuel System Diesel fuel shall be used for the back-up diesel generator sets. Diesel will be delivered by road tanker to site and stored in a storage tank. The diesel storage tank capacity shall be determined based on the fuel consumption of the diesel generators. As a minimum diesel fuel for 7 days uninterrupted operation at emergency load of the generator will be provided [Ref 2]. 9.7 Diesel Generator The diesel generator sets shall consist of the following main parts: • Diesel engine, • Generator, • Starter equipment, • Fuel system, • Lubrication system, • Air intake and exhaust system, • Control and monitoring system, • Acoustic enclosure. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 42 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Diesel engine and generator shall be placed on a common base frame and connected with a dry flexible coupling. The DGS set shall be integrated in the DGS equipment container. The DGS sets shall be provided in a manner such that 15 sec after initiation of start the full load can be taken over [Ref 16]. 9.8 Utility Water System 9.8.1 Pipes Water distribution network shall be made of High-Density Polyethylene (HDPE), class A50 of Piping Classes Specification (G791-ILF-AKGE-PP-SPC-0001). 9.8.2 Water wells The minimum total capacity of all operating wells shall be the cumulative of the following consumption rates: • Raw water average daily consumption for the manufacture of potable water, plus, • Loss of water from the manufacture of potable water, plus, • Raw water average daily consumption for process, plus, • Raw water for filling Fire Fighting Tank; 9.8.3 Submersible pumps Submersible pump shall be suitable for operation under submerged condition in raw water; Submersible pump shall pump raw water to a raw water tank. The pump shall be controlled by a signal of the raw water tank filling level; 9.8.4 Raw water tank The minimum storage capacity of raw water shall be cumulative of the following consumption rates : • Daily consumption of 120 LPDPM, • Demand for process, • 5 days of reserve. 9.8.5 Potable water treatment unit Potable water treatment system shall produce potable water quality according to WHO standards. Potable water treatment unit shall be selected on the basis of the raw water characteristic and treatment needs. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 43 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Potable water treatment unit shall consist of following basic components : • Raw water line valve – valve that allows to cut off raw water supply line; • Pre-filter(s) - filter(s) used to remove sand silt, dirt and other sediment. The prefilter(s) shall be sediment type; • Reverse osmosis membrane – the membrane shall be spiral wound, made of the CTA (cellulose tri-acetate) which is chlorine tolerant; • Post filter – shall be made of carbon (either in granular or carbon block form). Post filtration process removes any remaining tastes and odors from water; • Automatic shut off valve – installed to conserve water. When the potable water tank is full this valve stops any further water from entering the reverse osmosis membrane, thereby stopping the water production. By shutting off the flow this valve also stops water from flowing to the drain; • Check valve – prevents the backward flow; • Flow restrictor – the device maintains the flow rate required to obtain the highest quality potable water; • Drain line – the line shall run from the outlet end of the reverse osmosis membrane housing to the drain. This line shall be used to dispose of the impurities and contaminants found in the water well. 9.8.6 Disinfection units Disinfection unit shall be designed to be added, at the relevant dosing point, the requested amount of disinfectant; Disinfection unit shall be designed for manual operation ; 9.8.7 Potable water tanks The potable tank shall be built from materials approved for potable water. The capacity of potable water tank shall be sufficient to meet potable water consumption requirements dimensioned according to below values: • Daily consumption of 120 LPDPM, • 2 days of reserve. Potable water tank shall be equipped with water level controlling device connected with automatic valve (valve equipped with electrical actuator); The water mirror will be adjusted through the emergency overflow drains directed into an open drain system ; 9.8.8 Pump units (booster unit) Pump unit shall be used to refilling potable water tank and firefighting water tank and to supply users. Pump unit shall be approved for potable water; 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 44 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Pump unit shall be controlled by a signal from pressure switch. Pump unit shall consist of minimum two operating pump (2x50%) and one standby pump and one standby pump (1 x 100%) 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 45 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 9.9 Closed Drain System The closed drain system shall be designed for collecting any liquids containing flammable or hazardous substances in Kaduna, Kano and Zaria TGS respectively. The main items system shall include: A closed drain vessel, to be installed in a concrete pit, equipped with truck loading connection; main header for collecting and draining condensate toward the closed drain vessel. All closed drain lines shall be routed to the header drain by gravity with a minimum slope of 1:100. The liquid content in the header shall be sloped to the closed drain vessel, from where it shall be pumped out using vacuum truck connection. The closed drain system shall account for reliable disposal of the drain fluids at the remote locations without possibility of arrival of vacuum trucks. Drainage flowrate shall not be bigger than the one resulting from draining largest item from the low-low liquid level to the bottom within one hour & drain drum shall be sized to accommodate this volume [Ref 5]. The drain operation shall be executed manually in controlled manner except for the filter separator skids and knock out drum in Kaduna and Kano Stations with automatic liquid discharge to the closed drain system. The minimum manual drain connection shall be 2” and minimum drain header size shall be 4”. 9.10 Open Drain System Non-hazardous water (storm water) shall be directed to open ditch with evacuation outside station. The surface water shall be collected in open channels and routed outside the station through concrete & stone run-off located around the station. Hazardous Open Drain System shall collect potentially contaminated water from process areas. Each process unit shall contain a sump which shall be sized to contain the rainfall lasting 15 minutes. Excess water shall be diverted into the non-hazardous open drain system. The Hazardous Open Drain collection header shall be routed to the hazardous open drain sump, where the collected oil will be separated and depending on location disposed locally or collected by vacuum trucks. the clear water from the sump will be discharged to non-hazardous open drain system [ref 5]. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 46 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 9.10.1 Pipes Non-hazardous (storm water) open drain system shall be made of uPVC per ASTM D1785; or RTR (fiberglass) ; Hazardous open drain system shall be made of High-Density Polyethylene (HDPE) per ASTM D3350and ASTM F714. 9.10.2 Oil water separators For inlet oil water parameters see below table: Table 26 Inlet Oil water parameters Oil content 600 ppm (expected) Oil specific gravity 0.885 kg/dm3 Hydrocarbon condensate content Hydrocarbon condensate specific gravity Total suspended Solids traces (accidental) Temperature (min/max) 5/60ºC 0.529 – 0.602 kg/dm3 100 ppm (expected) Oil water separators shall be sized to provide a hold up of 15mins. Oil separators shall be designed in accordance with API PUB 421 or the Design and Operation of Oil water separators or other acceptable references; A central oil-water separator shall be provided; Collected oil shall be evacuated by vacuum truck while clean water shall be diverted to the storm water system; Waste oil and oily sludge shall be disposed-off in a waste disposal facility as approved by the OWNER. 9.11 Simulations Steady State simulation shall be performed using Aspen HYSYS to verify the Heat & Material Balance and developing the input required for steady state hydraulic study. The design gas specification as stated in section 5.3 Table 14 shall be used. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 47 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 10.0 Kaduna & Kano Facilities Design Basis 10.1 Criteria for sizing of station piping Table 27 Design Requirements for Station piping Max △P [bar/100m] Service Max gas velocity [m/s] Single phase gas process line 0≤P≤35barg 0.11 20 35≤P≤140 barg 0.25 20 The line sizing to be performed for two different scenarios which covers the operating envelope of the station: Minimum Pressure Scenario developed to account for operating conditions of the station which are determined by minimum required gas pressure at the station inlet. The minimum inlet pressure is 43 barg. Maximum Pressure Scenario developed to account for operating conditions of the station which are determined by maximum gas pressure at the station inlet. The maximum inlet pressure of 94 Barg shall be considered for TGS sizing only. However, this pressure shall not be the normal operating Scenario. Diameter of piping shall be selected based on worst case scenario which is minimum pressure. Diameter of single HF train shall be selected with assumption that 30% of total gas flow rate will be transported via HF, 70 % of total gas flow rate will be transported via bypass [Ref 24, 25]. 10.2 Criteria for orifice meter sizing The metering runs shall be designed based on the requirements stated in DPR (Department of Petroleum Resources), “Procedure Guide for the Determination of Quantity and Quality of Gas and Gas Derivatives at Custody Transfer Points”, 2006. Requirements concerning orifice meter are as follows: • Design flow of metering runs and thereby orifice meters shall result from the criterion that maximum operating flow is 80% of design flow. • Beta ratio • Maximum allowable pressure drop across orifice meter shall be 1000 inch of H2O shall not be higher than 0.6 Sizing shall be carried out for worst case operating conditions (minimum operating pressure and maximum operating temperature) [Ref 9, 10]. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 48 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 10.3 Criteria for Relief System Sizing 10.3.1 Relief causes The relief causes considered in this report as per API STD 521 are as follows [Ref 12, 13]: • Gas expansion in the filter separators due to the fire; • Pressure rise in the closed drain vessel due to gas breakthrough through the filter separators’ condensate system; • Gas expansion in the line heaters with continued heat input while the process side is blocked; • Thermal expansion of trapped fluids in the pig receiver. The other sources of relief connected to the vent system are as follows: • Emergency depressurization of inventory trapped between shutdown valves; • Manual depressurization of facilities installed within the station; • Manual depressurization of pipeline. 10.3.2 General Design Criteria The following design criteria shall be followed in the design [Ref 12, 13]: • Pressure safety valves installed on each filter separator to be sized for fire case scenario; • Pressure safety valves installed on closed drain vessel to be sized for gas breakthrough through the filter separators condensate system; • Pressure safety valves installed on inlet line to line heaters to be sized for over pressurization due to outlet blockage with the continued heat input; • Pressure safety valves installed on pig launcher and pig receiver to be sized for thermal expansion of trapped fluids; • Maximum accumulated pressure in the vessel equipped with pressure safety valves for non-fire case: 110% of design pressure; • Maximum accumulated pressure in the vessel equipped with pressure safety valves for fire case: 121% of design pressure; • Incremental pressure loss in the PSV inlet line caused by the flow through the PSVs shall not exceed 3% of set pressure; 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 49 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS • The PSV outlet line design shall be done on a basis of maximum allowable Mach number or maximum allowable back pressure (whichever is more stringent). The velocity in the cold vent piping shall not exceed Mach number of 0.6 in the main headers and 0.7 in the tail pipes. The velocity in the cold vent stack shall not exceed 0.5 Mach for peak flow. The maximum allowable back pressure shall not reduce relieving capacity of any of the pressure relieving device and shall be lower than pressure rating of piping materials [Ref 5]. • Back pressure in the outlet piping downstream relief valve shall not exceed 10% of set pressure in case of conventional PSV and 50% of set pressure in case of balanced PSV. • Superimposed pressure in the vent system resulting from relief of other source shall not exceed 10% of set pressure in case of conventional PSV and 50% of set pressure in case of balanced PSV (only if simultaneous relief of these sources is credible) • The materials of discharge piping and vent stack shall be selected that are compatible with the expected minimum temperature during relief. • Exit velocity from vent stack for peak flow rate shall be 150m/s (recommended by API STD 521). • Emergency depressurisation shall allow for depressurisation of each ESD section from design pressure down to 50% of design pressure within 15 minutes [Ref 20]. 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 50 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS 10.3.3 Emergency isolation and blowdown system ESD System shall be provided as a primary overpressure protection. Process plant shall be segregated into different blowdown sections separated by ESD valves. ESD valves shall be provided as a minimum in the battery limits and HP/LP system boundaries. Each of the ESD section shall be equipped with blowdown valves (BDV). Blowdown valves shall be automatically actuated by signal from F&G system (fire and gas detection system) or manually by the operator. Facilities shall be provided to enable the operator to manually initiate blowdown. Blowdown system shall be sized for the fire scenario as it is more stringent scenario. Depressurization rate for the fire scenario shall results from reducing pressure at initial conditions to a level equivalent to 50% of the design pressure within approx. 15 minutes. Material of piping downstream of the BDV shall withstand cold temperatures occurring during depressurization due to Joule-Thompson effect. BDV and restriction orifices shall be installed at the highest point. [Ref 5]. 10.3.4 Manual depressurization Pipeline Each pipeline sections separated by block valve stations shall be manually depressurized in case of an emergency through the vent stack located at stations or vent stack located at block valve stations. A throttling valve (globe valve) and a properly sized restriction orifice shall be used as restriction element for depressurization to ensure re-leased gas flow and temperature are within desired limits (max 0.7 Mach flow and min temperature with LTCS limit of -46 deg C). The throttling element shall be sized such that depressurization will be carried out within a reasonable time. In order to limit the pipeline depressurisation time within 5 days, linear section depressurisation shall be conducted via upstream & downstream vent system simultaneously.. In order to minimise loss of gas & emissions during depressurisation, Each BVS & TGS is provided with mobile compressor connection across Station isolation valve (Gas operated Valve). After a section of pipeline is isolated by valves, and prior to blowdown, the pressure in the line can be reduced by using a mobile compressor(s) to transfer gas from that section to a downstream section of the pipeline. Further, The BVS vent system is provided with positive isolation to prevent any gas leakage & loss of gas during normal operation. Pig Launcher / Pig Receiver 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 51 of 52 ©2020 Ajaokuta Kaduna Kano Gas Pipeline Project 10481-BCL-AKSX-PR-REP-0001-A0 PROCESS DESIGN BASIS Pig launchers / receivers shall be depressurized manually only. Automatic blowdown valves are not necessary as pig launchers / receivers shall be depressurized during normal operation. A throttling valve (globe) and a properly sized restriction orifice shall be used as restriction element for depressurization to ensure released gas flow and temperature are within desired limits. Terminal Gas Station The process equipment shall be manually depressurized if any maintenance activities are required. All vents from each isolated section shall be collected into one sub-header connected to the main cold vent collecting header. A throttling valve (globe) and a properly sized restriction orifice shall be used as restriction element for depressurization to ensure released gas flow and temperature are within desired limits. 11.0 HOLD List 1. Deleted. 2. Deleted. 3. Deleted 10481-BCL-AKSX-PR-REP-0001_A0_AFC_Process Design Basis Page 52 of 52 ©2020