1 / 45
Who has content authority to make decisions at the User Story level during Program Increment (PI)
Planning?
Agile Team
Scrum Masters
Release Train Engineer
Product Owner
Correct answer:
Product Owner
Question
2 / 45
Which two statements are true about uncommitted objectives? (Choose two.)
Uncommitted objectives are not included in the team's commitment
Uncommitted objectives help improve predictability
The work to deliver the uncommitted objectives is not planned into the iterations during PI Planning
Uncommitted objectives do not get assigned a planned business value score
Uncommitted objectives are extra things the team can do in case they have time
Correct answer:
Uncommitted objectives are not included in the team's commitment
Uncommitted objectives help improve predictability
Question
3 / 45
What is the basic building block when organizing around value?
Individuals
Agile Teams
Agile Release Trains
Hierarchies
Correct answer:
Agile Teams
Question
4 / 45
Which statement is true about DevOps?
Measurements are not a top priority for DevOps
DevOps automation of testing reduces the holding cost
DevOps is an approach to bridge the gap between development and operations
Lean-Agile principles are not necessary for a successful DevOps implementation
Correct answer:
DevOps is an approach to bridge the gap between development and operations
Question
5 / 45
The House of Lean is a classic metaphor describing the mindset essential for Lean thinking. Which one of
the four pillars advocates a 'Go See' mindset?
Flow
Respect for people and culture
Relentless improvement
Innovation
Correct answer:
Innovation
Question
6 / 45
What is considered an anti-pattern when assigning business values to team PI Objectives?
Assigning business values to uncommitted objectives
Business Owners assigning the business value
Business Owners assign high values to important Enabler work
All PI Objectives are given a value of 10
Correct answer:
All PI Objectives are given a value of 10
Question
7 / 45
Which statement is true about the Innovation and Planning (IP) Iteration?
The Scrum Master can decide if the IP Iteration is necessary
It is used as a weekly sync point between the Scrum Masters
Without the IP Iteration, there is a risk that the 'tyranny of the urgent' outweighs all innovation activities
It is used annually when the team needs to refocus on work processes
Correct answer:
Without the IP Iteration, there is a risk that the 'tyranny of the urgent' outweighs all innovation activities
Question
8 / 45
Which of the core competencies of the Lean Enterprise helps align strategy and execution?
Business Solutions and Lean Systems Engineering
Team and Technical Agility
DevOps and Release on Demand
Lean Portfolio Management
Correct answer:
Lean Portfolio Management
Question
9 / 45
What must management do for a successful Agile transformation?
Change Scrum Masters in the team every two weeks
Send someone to represent management, and then delegate tasks to these individuals
Strive to think of adoption as an area they can control
Commit to quality and be the change agent in the system
Correct answer:
Commit to quality and be the change agent in the system
Question
10 / 45
What can be used to script the change to SAFe?
The Lean-Agile Center of Excellence (LACE) charter
The Program Kanban
The Implementation Roadmap
The portfolio canvas
Correct answer:
The Implementation Roadmap
Question
11 / 45
What is the foundation of the SAFe House of Lean?
Flow
Value
Leadership
Relentless improvement
Correct answer:
Leadership
Question
12 / 45
What is the best measure of progress for complex system development?
Prioritized backlog
System Demo
Inspect and Adapt
Iteration Review
Correct answer:
System Demo
Question
13 / 45
What can be used as a template for putting SAFe into practice within an organization?
SAFe Principles
SAFe Core Values
SAFe Implementation Roadmap
SAFe House of Lean
Correct answer:
SAFe Implementation Roadmap
Question
14 / 45
What is one component of the Continuous Delivery Pipeline?
Continuous Cadence
Continuous Planning
Continuous Exploration
Continuous Improvement
Correct answer:
Continuous Exploration
Question
15 / 45
What are the last three steps of the SAFe Implementation Roadmap?
Train Lean-Agile change agents, extend to the portfolio, accelerate
Train Lean-Agile change agents, identify Value Streams and Agile Release Trains, extend to the portfolio
Launch more Agile Release Trains and Value Streams, extend to the portfolio, accelerate
Launch trains, coach Agile Release Train execution, train executives and managers
Correct answer:
Launch more Agile Release Trains and Value Streams, extend to the portfolio, accelerate
Question
16 / 45
What is Business Agility?
The ability to compete and thrive in the digital age by quickly responding to market changes and emerging
opportunities with innovative business Solutions.
Applying Lean-Agile principles and practices to the specification, development, deployment, operation, and evolution
of the world's largest and most sophisticated systems.
A customer-centric approach to defining, building, and releasing a continuous flow of valuable products and services
to customers and users.
How Lean-thinking people and Agile Teams optimize their business processes, evolve strategy with clear and
decisive new commitments, and quickly adapt the organization as needed to capitalize on new opportunities.
Correct answer:
The ability to compete and thrive in the digital age by quickly responding to market changes and emerging
opportunities with innovative business Solutions.
Question
17 / 45
What is one of the Agile Release Train sync meetings?
Iteration Retrospective
Solution Demo
Scrum of scrums
Iteration Review
Correct answer:
Scrum of scrums
Question
18 / 45
How does SAFe provide a second operating system that enables Business Agility?
By focusing on customers, products, innovation, and growth
By achieving economies of scale
By creating stability and hierarchy
By building up large departments and matrixed organizations to support rapid growth
Correct answer:
By focusing on customers, products, innovation, and growth
Question
19 / 45
Design Thinking identifies at least four new ways to measure success. What are two of those ways? (Choose
two.)
Reliability
Desirability
Sustainability
Scalability
Marketability
Correct answer:
Desirability
Sustainability
Question
20 / 45
What is a minimum viable product?
A minimal product that can be built to achieve market dominance
A prototype that can be used to explore user needs
A minimal Story a team can deliver in an Iteration
A minimal version of a new product used to test a hypothesis
Correct answer:
A minimal version of a new product used to test a hypothesis
Question
21 / 45
If a program repeatedly shows separate Feature branches rather than a true System Demo, which practice
should be reviewed to address the issue?
Roadmap creation
Test first
Continuous Integration
Scrum of scrums
Correct answer:
Continuous Integration
Question
22 / 45
Which statement fits with the SAFe Core Value of Built-in Quality?
Quality is not part of the SAFe Core Values
Quality should only be worked on during the Innovation and Planning Iteration
You cannot scale crappy code
Quality depends on the scale of the project and should be implemented from the top down
Correct answer:
You cannot scale crappy code
Question
23 / 45
What is part of the role of Product Management?
To facilitate backlog refinement sessions
To prioritize the Program Backlog
To assign business value to Features
To prioritize Enablers
Correct answer:
To prioritize the Program Backlog
Question
24 / 45
On day two of PI Planning, management presents adjustments based on the previous day's management
review and problem solving meeting. What is one possible type of adjustment they could make?
Adjust business priorities
Change a team's plan
Create new User Stories
Adjust the length of the PI
Correct answer:
Adjust business priorities
Question
25 / 45
What is the biggest benefit of decentralized decision-making?
Removing accountability from leaders
Creating better visualization
Ensuring strategic decisions are not made in a vacuum
Delivering value in the shortest sustainable lead time
Correct answer:
Delivering value in the shortest sustainable lead time
Question
26 / 45
Product Management has content authority over the Program Backlog. What do Product Owners have
content authority over?
Value Streams
Team Backlog
Portfolio Backlog
Portfolio Vision
Correct answer:
Team Backlog
Question
27 / 45
How is the flow of Portfolio Epics managed?
In the Program Kanban
In the Portfolio Kanban
In the Portfolio Backlog
In the Program Backlog
Correct answer:
In the Portfolio Kanban
Question
28 / 45
What is an example of applying cadence-based synchronization in SAFe?
Teams decide their own Iteration length
Teams allow batch sizes across multiple intervals
Teams meet twice every Program Increment (PI) to plan and schedule capacity
Teams align their Iterations to the same schedule to support communication, coordination, and system integration
Correct answer:
Teams align their Iterations to the same schedule to support communication, coordination, and system integration
Question
29 / 45
The Agile Release Train uses which type of teams to get work done?
Solution teams
Management teams
Cross-functional teams
Phased-review-process teams
Correct answer:
Cross-functional teams
Question
30 / 45
Which statement is a value from the Agile Manifesto?
Limit work in process
Build incrementally with fast, integrated learning cycles
Respect for people and culture
Respond to change
Correct answer:
Respond to change
Question
31 / 45
When basing decisions on economics, how are lead time, product cost, value, and development expense
used?
To take into account sunk costs
To recover money already spent
To limit work in process (WIP) through the system
To identify different parameters of the economic framework
Correct answer:
To identify different parameters of the economic framework
Question
32 / 45
In the Program Kanban some steps have work in process (WIP) limits. Why is this necessary?
To help Continuous Deployment
To enable multitasking
To keep timebox goals
To ensure large queues are not being built
Correct answer:
To ensure large queues are not being built
Question
33 / 45
What is one issue when organizing around hierarchical functions?
It reduces political tensions
It moves the decision to where the information is
It is not how value flows
It creates Agile business teams
Correct answer:
It is not how value flows
Question
34 / 45
Which statement accurately characterizes Strategic Themes?
They are large initiatives managed in the Portfolio Kanban that require weighted shortest job first prioritization and a
lightweight business case
They are a high-level summary of each program's Vision and are updated after every PI
They are requirements that span Agile Release Trains but must fit within a single Program Increment
They are business objectives that connect the SAFe portfolio to the Enterprise business strategy
Correct answer:
They are business objectives that connect the SAFe portfolio to the Enterprise business strategy
Question
35 / 45
What is the last step in Kotter's approach to change management?
Consolidate gains and produce more wins
Sustain and improve
Generate short-term wins
Anchor new approaches in the culture
Correct answer:
Anchor new approaches in the culture
Question
36 / 45
Which statement is a principle of the Agile Manifesto?
Visualize and limit WIP, reduce batch sizes, and manage queue lengths
Respect for people and culture
Measure everything
Simplicity “the art of maximizing the amount of work not done“ is essential
Correct answer:
Simplicity “the art of maximizing the amount of work not done“ is essential
Question
37 / 45
What are the three primary keys to implementing flow? (Choose three.)
Manage queue lengths
Visualize and limit work in process (WIP)
Increase capacity
Address the systemic problems
Frequent context switching
Reduce the batch sizes of work
Correct answer:
Manage queue lengths
Visualize and limit work in process (WIP)
Reduce the batch sizes of work
Question
38 / 45
Which two quality practices apply to Agile teams? (Choose two.)
Using nonfunctional requirements
Decentralized decision-making
Providing architectural runway
Establishing flow
Peer review and pairing
Correct answer:
Establishing flow
Peer review and pairing
Question
39 / 45
What is one Guardrail on Lean Budget spend?
Continuous Business Owner engagement
Spending caps for each Agile Release Train
Learning Milestones as objective measurements
Participatory budgeting
Correct answer:
Continuous Business Owner engagement
Question
40 / 45
What is one benefit of unlocking the intrinsic motivation of knowledge workers?
To lower work in process (WIP) limits
To centralize decision-making
To provide autonomy with purpose, mission, and minimum constraints
To strive to achieve a state of continuous flow
Correct answer:
To provide autonomy with purpose, mission, and minimum constraints
Question
41 / 45
What is found on a program board?
Features
User Stories
Epics
Tasks
Correct answer:
Features
Question
42 / 45
Which statement correctly describes one aspect of the team's commitment at the end of PI Planning?
A team commits only to the PI Objectives with the highest business value
A team commits to all the Features they put on the program board
A team does not commit to uncommitted objectives
A team commits to all the Stories they put on their PI plan
Correct answer:
A team does not commit to uncommitted objectives
Question
43 / 45
What is the impact of Customer Centricity?
To understand the Customer's needs
To interpret market rhythms
To design custom-built Customer Solutions
To build small, partial systems just in time
Correct answer:
To understand the Customer's needs
Question
44 / 45
Which is an aspect of systems thinking?
The length of the queue impacts the wait time
Mastery drives intrinsic motivation
Optimizing a component does not optimize the system
Cadence makes routine everything that can be routine
Correct answer:
Optimizing a component does not optimize the system
Question
45 / 45
What is used to capture the current state of the Portfolio and a primer to the future state?
Portfolio Vision
Portfolio Kanban
Portfolio Canvas
Portfolio Backlog
Correct answer:
Portfolio Canvas