Iraq Kurd Substation Management Program Performance Substation Management 3-Substation Equipment Specification (Equipment Specification, Associated System Design and Tests) April , 2015 Sang Jin Chung 1 / 72 Contents Ⅰ. Specifications for Substation Equipments Ⅱ. Associated System in Substation Ⅲ. Tests– Type test, FAT, Site test, etc. 2 / 72 Ⅰ. Specifications for Substation Equipments Functions of Substation Equipment Equipment Function 1. Bus-Bar Incoming & outgoing ckts. Connected to bus-bar 2. Circuit Breaker Automatic switching during normal or abnormal conditions 3. Isolators Disconnection under no-load condition for safety, isolation and maintenance. 4. Earthing switch To discharge the voltage on dead lines to earth 5. Current Transformer To step-down currents for measurement, control & protection 6. Voltage Transformer To step-down voltages for measurement, control & protection 7. Lightning Arrester To discharge lightning over voltages and switching over voltages to earth 3 / 72 Ⅰ. Specifications for Substation Equipments (2) Functions of Substation Equipment (cont’d) 8. Shunt reactor To control over voltages by providing reactive power compensation 9. Neutral-Grounding resistor To limit earth fault current 10. Coupling capacitor To provide connection between high voltage line & PLCC equipment 11. Line –Trap To prevent high frequency signals from entering other zones. 12. Shunt capacitors To provide compensations to reactive loads of lagging power factors 13. Power Transformer To step-up or step-down the voltage and transfer power from one a.c. voltage another a.c. voltage at the same frequency. 14. Series Capacitor Compensation of long lines. 4 / 72 Substation Equipment - Circuit Breaker Circuit Breakers (400kV, 132kV and 66kV) Ⅰ. Specifications for 5 / 72 Main Parameters • Rated Voltage (kV) • Rate Continuous Current (A) • Rated short circuit Breaking Current (kA, rms) • Rated short circuit Making Current (kA, peak) = 2.5ⅹ Rated Breaking current, rms (Asymmetrical) • TRV : Transient Recovery Voltage (kV) - The recovery voltage is the voltage which appears across the terminals of a pole of a circuit breaker(The voltage difference between the supply voltage and the load voltage). This voltage may be considered in two successive time intervals: one during which a transient voltage exists, followed by a second one during which a power frequency voltage alone exists. 6 / 72 Main Parameters (2) • First–pole–to-clear factor (kpp) - kpp is a function of the grounding arrangements of the system. It is the ratio of the power frequency voltage across the interrupting pole before current interruption in the other poles, to the power frequency voltage occurring across the pole or poles after interruption in all three poles. - For the three-phase short-circuit condition of the neutral ungrounded system, 1.5 p.u. is required in A phase. Figure ; Ungrounded system after interruption of the first phase 7 / 72 TRV Figure 1. - Recovery voltage in case of a capacitive load Figure 2 - Voltages on terminals of the first pole that clears threephase capacitive currents in a system with isolated neutral 8 / 72 TRV (2) Figure 3. Evolution of voltages with restrike occurring a half cycle after current interruption, in case of single- Figure 4. TRV in inductive circuit, 90 degree lagging current phase capacitive current switching 9 / 72 POW - Capacitor Switching • Point On Wave Switching (POW) - Controlled closing of shunt capacitor banks (POW) is used to minimize the power system transients by operating each CB pole at the most favorable time instant. - For wye-connected grounded-neutral, shunt capacitor banks are energized when the voltage is equal to zero on each phase. - All phases are closed within 120 electrical degrees. 10 / 72 POW - Capacitor Switching (2) 11 / 72 POW ( Example – Alstom RPH3 ) 12 / 72 Circuit Breaker – Test Routine Test Type Test - 1. Mechanical test 1. Operational test 2. Thermal test 2. Measurement of resistance of the main circuits 3. Dielectric test 3. One minute p.f. voltage withstand test (dry ) 4. Short circuit test Making capacity test Breaking capacity test Duty cycle tests Short time current tests ※ Detailed Testing for Type test and Routine test will be explained later in in Ⅲ. Tests– Type test, FAT, Site test. 13 / 72 Substation Equipment - Isolator 400kV Isolator Ⅰ. Specifications for 14 / 72 Substation Equipment – Isolator (2) Mechanical Interlock with Earthing switch Front View DS Control Box Top View Ⅰ. Specifications for ※Two rotating axises can not operate at the same time and DS can be operated only at a certain position(ES is open). 15 / 72 Substation Equipment - Current Transformer 400kV Current transformer Ⅰ. Specifications for 16 / 72 Substation Equipment - Current Transformer (2) Equvalent Circuit CT Excitation curve(Knee Voltage) Ⅰ. Specifications for ※ The ‘knee-point’ of the excitation curve is defined as ‘that point at which a further increase of 10% of secondary emf would require an increment of exciting current of 50%’. 17 / 72 Substation Equipment - Current Transformer (3) LOCATION of Current Transformer Case 1. When CT can be accommodated within the CB, both sides of the circuit breaker should give the desired overlapping of protective zones Case 2. Due to substation space limitation, in case only on one side of the CB required, it is generally located on the circuit side of the CB. 18 / 72 Substation Equipment - CVT 400kV CVT Ⅰ. Specifications for 19 / 72 Equivalent Circuit – CVT Equvalent Circuit (Incl. EMU) Ⅰ. Specifications for 20 / 72 Type of VT Ⅰ. Specifications for ※ Lower cost at voltages 110kV and above, but do not usually have the very high accuracy required for some special metering functions. 21 / 72 Substation Equipment – Surge Arrestor 400kV Surge Arrestor Selection of Surge Arrestor Ⅰ. Specifications for 22 / 72 Substation Equipment – GIS 420kV Gas Insulated Switchgear Ⅰ. Specifications for 23 / 72 Substation Equipment – Surge Arrestor 400kV Surge Arrestor Selection of Surge Arrestor Ⅰ. Specifications for 24 / 72 Substation Equipment – Shunt Reactor 400kV Reactor and NGR Ⅰ. Specifications for 25 / 72 Substation Equipment – Series Capacitor 500kV Series Capacitor for 1,000 km line Ⅰ. Specifications for -2326 / 72 Substation Equipment – Power Transformer 400kV Auto Transformer Ⅰ. Specifications for 27 / 72 Power Transformer - Main Parameters • Rated Voltage, kV (Primary/Secondary), Frequency, Hz • Rate Power (ONAN/ONAF), MVA • Winding Connection; Primary-Secondary, D-Y • Type of Cooling, OA/FA/FAOA • Temp rise (top oil, winding) • OLTC, Tap voltage range(%), Number of Taps • % Impedance • Insulation level (lightning, power frequency) • No-load loss(kW), Load-loss(kW), guaranteed values. 28 / 72 Power Transformer – No Load Current The no load current If is needed to supply the no load losses and to magnetize the transformer core. Ic IF E1 Qc E1 Im f If IF ※ 1) Magnetizing current which is merely utilized for magnetizing the core, Im, 2) And other component of the source current, Ic, is consumed for compensating the core losses in transformer 29 / 72 IcI m Power Transformer – Load Current Loaded Transformer Ⅰ. Specifications for • As I2 is flowing through the secondary, a self mmf in secondary winding will be produced. Here it is N2I2, where, N2 is the number of turns of the secondary winding of Tr. ※ mmf is magneto motive force. 30 / 72 Power Transformer - Equivalent Circuit Ⅰ. Specifications for V1: Primary voltage (supply) I1 : Primary current. V2: Secondary voltage (load) I2: : Secondary current The turn ration, voltage ration, is E1/E2 = N1/N2 . At the primary winding, On Load Tap Changer (OLTC or ULTC) is installed where the current is small and its operating range is ±10%. 31 / 72 Power Transformer - Efficiency The efficiency of the transformer is the ratio of output (secondary) power to the input (primary) power. Formally the efficiency is η: P 2 P 1 Where, P1 : The input power (Primary) = V1I1 cosf1 P2 : The output power (Secondary) = V2I2 cosf2 Ⅰ. Specifications for P1 P2 PL PL is the power loss in the transformer = Pcopper + Piron V2' I 2' cos f2 V2' I 2' cos f2 I 2'2 Req Piron 32 / 72 Power Transformer – Voltage Regulation The voltage regulation is dependant on the transformer impedance. Also the load current, I is important. When it is capacitive the voltage regulation becomes positive, so the transformer reactance increase the output voltage. Ⅰ. Specifications for VR V1 V2' I 2' Req cosf I 2' X eq sin f 33 / 72 Power Transformer - Efficiency The efficiency of the transformer is the ratio of output (secondary) power to the input (primary) power. Formally the efficiency is η: P2 P 1 Where, P1 : The input power (Primary) = V1I1 cosf1 P2 : The output power (Secondary) = V2I2 cosf2 Ⅰ. Specifications for P1 P2 PL PL is the power loss in the transformer = Pcopper + Piron V2' I 2' cos f2 V2' I 2' cos f2 I 2'2 Req Piron 34 / 72 Power Transformer - % Impedance • The percentage impedance of a transformer is the volt drop on full load due to the winding resistance and leakage reactance expressed as a percentage of the rated voltage. • It influences the voltage regulation, system stability, short circuit current magnitude, etc. • Standard %Impedance (ANSI C57.12.10; 230kV and below) Ⅰ. Specifications for 35 / 72 Substation Equipment – Post Insulator 400kV Bus Post Insulator Ⅰ. Specifications for 36 / 72 Substation Equipment – Wave Trap Wave Trap Ⅰ. Specifications for 37 / 72 PLC & Wave Trap PLCC component - Coupling Capacitor • Wave Traps form part of a PLC(Power Line Carrier) communication scheme. Their function is to present a high impedance at the carrier frequency band while introducing negligible impedance at the power frequency itself. 38 / 72 Substation Equipment – Lightning Mast Ⅰ. Specifications for 39 / 72 Ⅱ. Associated System - Functions System Function 1. Substation Earthing system -- Earthmat -- Earthing spikes -- Earthing risers To provide an earthmat for connecting neural points, equipment body, support structures to earth. For safety of personnel and for enabling earth fault protection. To provide the path for discharging the earth currents from neutrals, faults, Surge Arresters, overheads shielding wires etc. with safe step-potential and touch potential. 2. Overhead earth wire shielding or Lightning masts. To protect the outdoor substation equipment from lightning strokes. 3. Illumination system (lighting) -- for switchyard lighting -- buildings -- roads etc. 40 / 72 Ⅱ. Associated System – Functions (Cont’d) 4. Protection system -- protection relay panels -- control cables -- circuit breakers -- CTs, VTs etc. To provide alarm or automatic tripping of faulty part from healthy part and also to minimize damage to faulty equipment and associated system. 5. Control cable For Protective circuits, control circuits, metering circuits, communication circuits 6. Power cable To provide supply path to various auxiliary equipment and machines. 7. PLCC system power line carries communication system -- line trap -- coupling capacitor -- PLCC panels For communication, telemetry, telecontrol, power line carrier protection etc. 41 / 72 Ⅱ. Associated System – Functions (Cont’d) 8. Fire Fighting system -- Sensors, detection system -- water spray system -- fire prot. panels, alarm system -- water tank and spray system To sense the occurrence of fire by sensors and to initiate water spray, to disconnect power supply to affected region to pin-point location of fire by indication in control room. 9. Auxiliary standby power system -- diesel generator sets -- switchgear -- distribution system For supplying starting power, standby power for auxiliaries 10. Telephone, telex, microwave, OPF For internal and external communication 42 / 72 Ⅱ. Associated System – Minimum Clearance 400kV 220kV 1. Phase to Earth 3500 mm 2100 mm 2. Phase to phase 4200 mm (Rod-conductor configuration) 4000 mm (Conductor-conductor configuration) 2100 mm 3. Sectional Clearance 6400 mm 4300 mm 43 / 72 Ⅱ. Asso’n System – Min. Clearance Live Line for Man 44 / 72 Clearance for Apparatus Maintenance 45 / 72 Clearance Diagram of Equipment 46 / 72 Ⅱ. Associated System (Cont’d) Busbar Design • Continuous current rating - Ampacity calculation as per IEEE:738 • Short time current rating (IEC-865) • Stresses in Tubular Busbar • Natural frequency of Tubular Busbar • Deflection of Tube • Cantilever strength of Post Insulator • Aeolian Vibrations 47 / 72 Ⅱ. Associated System (Cont’d) Gantry Structure Sag / Tension calculation : as per IS: 802 1995 Sr. Temp Wind Pressure 1. Min. No wind 2. Min. 36% 3. Every Day No wind T <= 22% of UTS 4. Every Day 100% T <= 70% of UTS 5. Max. (ACSR No wind 750C/ AAAC 850C) 48 / 72 Limits Clearances Ⅱ. Associated System (Cont’d) • Short Circuit Forces calculation - As per IEC : 865 - Short circuit forces during short circuit - Short circuit forces after short circuit - Short circuit forces due to “Pinch” effect for Bundled conductor - Spacer span calculation • Factor of safety of 2.0 under normal condition and 1.5 under short circuit condition 49 / 72 Ⅱ. Associated System (Cont’d) Lighting Design - Adequate lighting is necessary for safety of working personnel and O&M activities - Recommended value of Illumination level – Control & Relay panel area - 350 Lux (at floor level) – Test laboratory - 300 Lux – Battery room - 100 Lux – Other indoor area - 150 Lux – Switchyard - 50 Lux (main equipment) - 20 Lux (balance Area / road @ ground level) 50 / 72 Ⅱ. Associated System - Spacer span/Short Circuit forces GRAPH OF SPACER SPAN Vs CONDUCTOR TENSION FOR 400 KV TWIN MOOSE ACSR CONDUCTOR CONDUCTOR TENSION PER PHASE IN KG. 12000.00 10000.00 8000.00 6000.00 4000.00 2000.00 0.00 0 2 4 6 8 SPACER SPAN IN MTRS. 51 / 72 10 12 14 Ⅲ. Test – Type Test, FAT and Site test Power Transformer • Measurements of ;- Dissipation Factor & Capacitance - No-load Loss and Current - Noise Level - Load Loss & Impedance - Efficiency, Regulation, • Temperature Rise Test – Type test • Lightning Impulse Test, Full/Chopped Wave – Type test • Switching Impulse Test (Over 230 kV) – Type test • Applied Voltage Test and LTAC • Induced Voltage Test with PD Measurement • Leak Test with Tank Pressure (24hrs) • Short Circuit Test – Type test 52 / 72 Ⅲ. Type Test, FAT, Site Tests Circuit Breakers- Type Test -Type tests are the test of one CB or a first few CBs of each type made to the same specifications (designs). -Type tests can be classified in following groups 1) Mechanical test 2) Thermal test 3) Dielectric test 4) Short circuit test a. Making capacity test b. Breaking capacity test c. Duty cycle tests d. Short time current tests 53 / 72 Ⅲ. Type Tests– Circuit Breakers (Cont’d) 1) Mechanical test (Endurance test): - The breaker should be opened and closed satisfactory. - In this test the CB is opened and closed several times (500). - Some operations (50) are by energizing the relay, remaining are by closing the trip circuit by other means. - Mechanical test on a.c CB are conducted without current and voltage in the main circuit. - No adjustment or replacement of parts is permitted during the mechanical test, however lubrication is permitted as per manufacturer instructions. - After the test there should be no distortion or wear of parts. 54 / 72 Ⅲ. Type Tests– Circuit Breakers (Cont’d) 2) Thermal tests: - AC current of rated value is passed through a closed CB, continuously, until steady temp is attained. - Readings of temperature of various conducting, insulating and structural parts are taken at an interval of 1 or ½ hour. - When the steady temp is reached, the maxim temp rise of each part should be less than the permissible limit. • The temp. rise should not exceed 40º C for In ‹ 800 A, 50º C for In ≥ 800 A. - An additional requirement is the measurement of contact resistances between the moving and fixed contacts, with DC current of 100 A. • For Alstom 420kV SF6 circuit breaker, it is about 70 µΩ (Limit 83 µΩ) 55 / 72 Ⅲ. Type Tests – Circuit Breakers (Cont’d) 3) Dielectric test: • 1. a. b. 2. These are conducted to confirm the rated insulation level of the circuit breaker. These can be classified as ; Power frequency tests. - Between poles and earth with circuit breaker open, a. Across terminals with circuit breaker open b. Between poles with circuit breaker closed, - The voltage gradually increased and maintained at test value for 1 minute. Impulse tests. - In this test impulse voltage of specified shape and magnitude is applied to the breaker. - For outdoor circuit dry and wet tests are conducted. 56 / 72 Ⅲ. Type Tests– Circuit Breakers (Cont’d) 4) Short circuit testing : - There are two types of short circuit testing stations to prove the MVA ratings of the circuit breaker, a)The field type testing station and b) L aboratory type testing station. a. The field type testing station -The power is supplied directly by the power system. • - It is most convincing method, but it has following drawbacks: i) That flexibility of the system available is limited. ii) It is difficult to set the system for the specified RRRV for HV CB. iii) It is not possible to repeat the test again and again without disturbing networks, hence not suitable for research/development. iv) The power available in the field testing station vary according to load connected on the network and layout of the network. 57 / 72 Ⅲ. Type Tests– Circuit Breakers (Cont’d) • • • • • • b. Laboratory type testing station - It has special generators to supply power for the testing. - In this it is possible to vary the test condition as required. - Such station is suitable for design engineer and supply engineer, and the designer can study the behavior of arc rupture and make necessary improvements. - The test can be performed again and again in order to show the reproducibility of the results. - The supply engineer can get satisfaction whether his breaker satisfies the requirements enunciated by specifications. - The magnitude of the test voltage and the short circuit can be selected by adjusting generators excitation and connection of the transformers. 58 / 72 Ⅲ. Tests– Circuit Breakers (Cont’d) b. Laboratory type testing station (Cont’d) - Further variation of current can be effected by means of tapped res istors and reactors. This also serves control on power factor. - The circuit is closed by specially designed make switch, designed for closing on very heavy currents, but never break currents. - Synchronized closing is controlled by means of a small pilot gener ator coupled to the generator shaft and can be very accurately set t o occur at any instant within the voltage wave. - With this the phase opposition at the commencement of short circu it can be selected. - And short circuit current either fully symmetrical or with any degre e of symmetry can be produced. 59 / 72 Ⅲ. Type Tests– Circuit Breakers (Cont’d) b. Laboratory type testing station (Cont’d) - Master CB is provided as a backup protection, in case of failure of CB under test to open the circuit. - By adding capacitor, any desired high frequency can be obtained. - The breaker under test is enclosed in a test cell made of reinforced concrete having a provision of observation while test is in progress. - The recording equipment is located in a control room, and the contr ol operations are carried out from the control room. - Direct testing involves subjecting a complete breaker or breaker pol e to full power or stress during the test. - The necessary preparation of C.B testing include connecting the equ ipment, adjusting the magnitude of reactors, connecting transforme rs to get desired test voltage etc. 60 / 72 Ⅲ. Tests– Circuit Breakers (Cont’d) b. Laboratory type testing station (Cont’d) - The contacts on sequence switch are adjusted to get desired timings. - The oscillographs are adjusted and calibrated. - While testing breaking capacity; Master circuit-breaker and C.B und er test are closed first, Short circuit is applied by closing the makin g switch. - The breaker under test is opened at desired moment - Making capacity test is necessary type test, all C.Bs are tested for th eir ability to make on to a Short-circuit. - The master C.B and the make switch are closed first, the breaker un der test is closed on a three phase short-circuit 61 / 72 Ⅲ. Tests– Circuit Breakers (Cont’d) Indirect testing - The short-circuit power available in testing stations (which is of the order of 4000 MVA in lab type testing station) is no longer sufficient to test a complete breaker ( which is of rated breaking capacity of the order of 10,000 MVA at 245 KV) - Even single pole of a EHV CB cannot be tested by direct means , as all EHV CB are with several arc interrupter units per pole, each unit can be separately tested. This is called unit testing. - From tests on one unit, the capacity of the complete pole and breaker is determined. - Synthetic testing is another popular method which permits testing of breaker of capacity 5, times that of the plant. 62 / 72 Ⅲ. Tests– Circuit Breakers (Cont’d) - The important Indirect Methods include the following: ◦ Unit testing: which means testing one or more units separately. ◦ Synthetic testing: In which the current source providing short circuit current and voltage source supplying re-striking and recovery voltage are different. ◦ Substitution test: These are conducted for oil CB, the characteristics of current versus time are obtained for different voltages, the performance beyond the tested value is determined by approximation ◦ Compensation tests: which are conducted on oil CB in critical range of low current by suitable compensation such as increased frequency, increase re-striking voltages etc. ◦ Capacitance tests: the capacitor which is charged by a voltage source is discharged through the breaker, an oscillatory circuit provides re-striking voltage. 63 / 72 Ⅲ. Type Tests– Circuit Breakers (Cont’d) Synthetic testing 64 / 72 Ⅲ. Tests– Circuit Breakers (Cont’d) Synthetic testing The synthetic test employs two sources namely, 1) 2) Current source (of relatively low voltage) Voltage source (of relatively low current) - The current source provides short-circuit current, the voltage source provides restriking voltage plus recovery voltage. - Other L,r,C etc are used to get desired test conditions, the switch S1 is closed to supply short-circuit current IG. - At near final current zero switch S2 ( which is usually a spark gap) is closed and V3 to applied to the breaker at an appropriate moment, the voltage will have transient because of L and C of the circuit 65 / 72 Ⅲ. Tests– Circuit Breakers (Cont’d) Advantages of this method; -The breaker can be tested for desired TRV and R.R.R.V -The short-circuit generator has to supply currents at a relatively less voltage ( as compared to direct testing) -Both test current and test voltage can be independently varied, so test become flexible -This is a simple method and can be applied to unit testing -With this method a breaker of capacity of five time that of the capacity of the test plan can be tested. 66 / 72 Ⅲ. Tests– Circuit Breakers (Cont’d) - In parallel current injection method, the voltage circuit (2) is effectively connected in parallel with current circuit (1) and the test breaker before the main current IG in test breaker current is properly simulated. 67 / 72 Ⅲ. FAT (Factory Acceptance Test) Circuit Breakers FAT - Routine test, Witness Test - These are performed for purpose of proving the correctness of assembly and material used. - These are performed on each individual circuit breaker. - Main routine test items include; 1) Operational test, 2) Measure ment of resistance of the main circuits, 3) One minute power frequency voltage dry withstand tests. - The customer can witness the testing process, and called as the witness test. 68 / 72 Ⅲ. Test – Site test Site Test–GIS (KEPCO, 170kV) Test Item Preparation Check Point Criteria □ Discussion with Operators/Field engineers; Work scope, Inspection procedure, Time required, Equipment outage, Neces sity to disconnect the trip circuit. ○ □ Check the equipment drawings/Cable list ○ ○ □ Operation voltage for DC/AC ; Closing 90-130V, voltage, 75~125% ;Trip voltage, 60~125% Vn=110V) □ Measuring instrument and special tools. □ Earthings for the compressor & hydraulic units. Insulation Resistance □ DC circuit of CB control circuit □ AC circuit (over 150V) Visual Check s 69 / 72 ○ ○ - Remarks Ⅲ. Site Test – Commissioning Test (GIS) Test for CB Unit □ Insulation resistance (Phase-to ground, P hase-to-phase) ≧ 1000MΩ □ Closing Time ≦ 150 msec □ Tripping Time (Coil 1, Coil 2) ≦ 33 msec □ On/Off time (phase discrepancy) □ Phase open relay operation (timer, trip operation) □ Check interlock for closing circuit ≦ 4 msec □ Check interlock for trip circuit yes ○ ○ ○ (for Loc□ Check Equipment status and Annunciatio al / Remote n with on/off operations. positions) CB, DS Trip/Alarm □ Check the contact status (Incl. Spare) ○ Signal Test ○ (with □ Confirm back to normal position after Relays alarm test (Air, Gas, Oil) energized) 70 / 72 Ⅲ. Site Test – Commissioning Test (GIS) Interlock Test BCT Insulation Resistance □ Interlock between CB, DS, and ES □ Between Bus ES and Bay #1, #2 Bus DS □ Between 1ry-2ndry windings, 1ry-Earth, 2ndry – Earth. □ Between phases of 2ndry windings □ Polarity test - Subtractive ? BCT Test □ CT ratio test- Ratio Correction Factor □ Saturation characteristics (at max. ratio)saturate over +110% of rated current. CT Connection □ Check correct ratio and connection (short CT neutral at protection side) □ CT terminal shall be shortened at the max. tap ratio Bus/Line PT Insulation Resistance □ Between 1ry-2ndry windings, 1ry-Earth □ 2ndry windings -Earth 71 / 72 ○ ○ 1ry windings : ≧ 1000MΩ, 2ndry winding s;≧ 2MΩ yes At each taps; RCF ≦ ± 10% yes ○ (refer relay tap setting tab le) ○ (use short bar and cable) ≧ 1000MΩ ≧ 2MΩ Ⅲ. Site Test – Commissioning Test (GIS) □ Polarity test - Subtractive ? Bus/Line PT Test PT Ground Connection PT Cable □ Ratio test-Ratio Correction Factor yes RCF ≦ ± 10% □ Local control box ○ □ PT Cable Shield ○ □ Bus/Line PT 2ndary Neutral ○ □ Corrosion protection of PT cable (Grease Injection) ○ □ Check whether correct ratio is used. 72 / 72