Uploaded by forpus

Preston-PPT-ch09

advertisement
Project Management from Simple to Complex
9-1
This work is licensed under the
Creative Commons Attribution-Noncommercial-Share Alike 3.0 Unported License.
To view a copy of this license,
visit http://creativecommons.org/licenses/by-nc-sa/3.0/or send a letter to
Creative Commons, 171 Second Street, Suite 300, San Francisco, California, 94105, USA
9-2
Chapter 9
Estimating and Managing Costs
9-3
Learning Objectives
•
Describe methods of estimating costs
•
Identify the effects of project phase and complexity on the choice of
estimating method
•
Describe the method of combining cost estimates with a schedule to
create a budget
•
Describe methods to manage cash flow
•
Describe the terms and relationships of budget factors used in earned
value analysis
9-4
Learning Objectives
•
Calculate and interpret budget and schedule variances
•
Calculate and interpret the schedule performance index and the cost
performance index
•
Calculate and interpret estimates to complete the project
•
Calculate the revised final budget
9-5
Estimating Costs to Compare and Select
Projects
•
Economic factors are an important consideration when choosing between
competing projects
•
To compare the simple paybacks/internal rates of return between
projects, an estimate of the cost of each project is made
•
The estimates must be accurate enough so that the comparisons are
meaningful
9-6
Estimating Costs to Compare and Select
Projects
•
Compared to later phases, the methods of estimating project costs during
the selection phase:
– Are faster
– Consume fewer resources
– Rely on expert judgment of experienced managers
•
Expert judgment: Decisions based on incomplete information made by
people who have extensive personal experience
9-7
Estimating Costs to Compare and Select
Projects
•
Analogous estimate: Budget estimate based on a similar project
•
Parametric estimate: Estimates that are calculated by multiplying
measured parameters by cost-per-unit values
9-8
Estimating Costs to Initiate Projects
•
Vendor bid analysis
– An RFP is issued and sent to a list of qualified vendors
– Vendors respond with a proposal and an estimate of the cost
– The project management team reviews the vendor responses
– The project selection decision might have to be reconsidered if:
• Vendors’ estimates are much higher than expected
• The project cannot be completed for the cost that was used to select the project
9-9
Estimating Costs to Initiate Projects
•
Bottom-up estimating: Sum of estimates of each detail of the activity and
project
– Very accurate
– Time-consuming
– On projects with low complexity, the cost estimates can be done on
spreadsheet software
– On larger projects, software that manages schedules can manage and display
costs by activity and category
9-10
Figure 9.2 - Detailed Cost Estimate
Click below to
view full-size
9-11
Figure 9.3 - Sum of Detailed Costs by Type
Click below to
view full-size
9-12
Estimating Costs to Initiate Projects
•
Activity-based estimates
– An activity can have costs from more than one vendor plus costs for labor and
materials from internal sources
– Detailed estimates from all sources are reorganized
– Costs associated with a particular activity are grouped by adding the activity
code to the detailed estimate
9-13
Figure 9.4 - Detailed Costs Associated with
Activities
Click below to
view full-size
9-14
Estimating Costs to Initiate Projects
•
Establishing a Budget
– Determine how much money is needed for:
• Each group of tasks
• The whole project
– Cost aggregation: Sum of component costs
– Transfer of money to the project account must be appropriately timed
– Reconciliation: Matching funds provided with funds spent
9-15
Figure 9.5 - Fund Transfers and Expenditures
Click below to
view full-size
9-16
Managing the Budget
•
Funding for the project should be available when it is needed
•
Financial people prefer to keep the company’s money working in other
investments before transferring it to the project account
•
The project manager prefers to have as much cash available as possible to
use if activities exceed budget expectations
9-17
Managing the Budget
•
Contingency reserve: Money held to pay for predictable but unspecified
extra costs
– Likely to be spent
– Part of the total budget for the project
•
Management reserve: Money available for changing project scope
– Not likely to be spent
– Not part of the project’s budget baseline
– Can be included in the total project budget
9-18
Evaluating the Budget
•
Earned value management (EVM): Method of comparing the budgeted
and actual costs of a project during the project
– Budgeted cost of work scheduled (BCWS): All the items in the cost estimate
– Planned value (PV): Sum of the items in the BCWS that should have been spent
by a particular day
– Budgeted cost of work performed (BCWP): The budgeted cost of work
scheduled that has been done
– Earned value (EV): Sum of budgeted expenses up to a particular point in the
schedule
– Actual cost (AC): Sum of money spent so far
9-19
http://www.youtube.com/watch?v=7WsfuvHegxE&feature=related
9-20
9-21
9-22
9-23
9-24
Figure 9.7 - Planned Value, Earned Value,
and Actual Cost
Click below to
view full-size
9-25
Evaluating the Budget
•
Schedule variance (SV): Difference between earned value and planned
value
– SV = EV − PV
– A negative schedule variance means the project is behind schedule
•
Cost variance: Difference between earned value and actual cost
– CV = EV − AC
– A positive CV indicates the project is under budget
9-26
Evaluating the Budget
•
Schedule performance index (SPI): Ratio of earned value to planned
value
– SPI = EV/PV
– A SPI value less than one indicates the project is behind schedule
•
Cost performance index (CPI): Ratio of earned value to actual cost
– CPI = EV/AC
Evaluating the Budget
•
Estimate to complete (ETC): Estimate of the amount of money needed to
complete the unfinished part of the project
•
Atypical cost variance
– ETC = Budget at completion (BAC) − Earned value (EV)
• Budget at completion: Budget for the entire project
•
Typical cost variance
– ETC = (BAC – EV)/CPI
• CPI: Cost performance index
9-28
Evaluating the Budget
•
Estimate at completion (EAC): Revised project budget based on actual
cost to date plus the estimate to complete (ETC)
– EAC = AC + ETC
9-29
Figure 9.9 - Summary of Terms and Formulas
for Earned Value Analysis
Click below to
view full-size
9-30
Download