Uploaded by Andrew Allenpina

Project Draft

advertisement
Project Resource Management
Plan Resource Management
In order to execute a complex project such as developing a COVID-19 tracking and vaccine finder application, it is necessary to leverage the
skills of many people. This project is relatively low in physical resources, but requires significant resources in software development and
administration. The resource management documentation will outline the basic structure of the organization and the responsibility of each
person working in the project. The organization structure will be layered to provide both adequate resource assignment to major tasks within
the project and to provide oversight on the accomplishment of tasks.
Organization Structure
The organizational chart is a breakdown of only the human resources of the project.
The emphasis is placed in the human resources because the project has little or no
materials or equipment. Human resources being the chief resource available, the
breakdown structure for these resources is necessary for the assignment of
responsibilities. The responsibility matrix below is a diagram of the different tasks
that need to be completed in the project as well as the various parties that may be
involved in that task. The legend shows the level of involvement by each party.
Some tasks require involvement from many parties while some require only one or
two resources to be involved in the task. The listed tasks are somewhat linear in
project progression, therefore requiring little or no involvement from roles such as
testing and customer support. The use of those resources are much greater later in
the project when their role begins work in supporting the project.
Resource Estimation
Given the local nature of the project, the resources to complete the project are
extremely limited. Almost all involved parties are SS community members that are
giving personal time and resources to the accomplishment of the project. This
limitation is also bound by the fact that support for such an application will likely be
limited in the community given the split support for COVID-19 mitigation measures.
Resource Acquisition
The acquisition of human resources for the project could be accomplished through
many methods including social media recruiting, flyers, and direct recruiting.
However, we believe that the most advantageous way of acquiring resources is by
gaining support of the local HOA board and administrators. They will need to be
project advocates in recruiting and also serve as resources themselves. Without the
consent and support of the HOA, the project would likely be unable to gain enough
resources to finish the project in a timely fashion.
Additionally, members of this project team and participating stakeholders will not be
working on this project on a full-time basis. This means that the project manager will
need to be explicit in delegation of duties and the responsibility matrix must be
referenced and updated immediately if there are any changes. Failure to update the
responsibility matrix and publish the changes to all project team members could
result in project delays.
Resource Management
This project presents significant barriers to successful resource management. The
project manager has significant interest in the management of the project team,
however because the project is being conducted with resources from the community
and with HOA resources, the existing hierarchies pose a challenge to conflict
management and performance reviews of any resources. Additionally, existing
relationships, negative or positive, will exist in the community and could have a
profound impact on team member behaviors and participation in the project.
Because of these challenges, the project manager will need to carefully determine
where it is appropriate to control the resource management and when the existing
hierarchies should take precedence in reviewing the performance of resources. The
relationships of resident of the community will likely play a small role in resource
management, but it would be high risk not to consider the community dynamics and
socio-political landscape of the community when conducting the project.
Responsibility Matrix
Tasks
Project Ideation
Bid \ proposal acceptance
Software requirement
specification
Finalize design doc
Staff hiring and allocation
UI and User Interface
Wireframe creation
coding \app development
demo 1.0 to stakeholder
Feedback Integration
Testing \ integration
Production Deployment
Live support
User feedback integration
* R = Responsible
*A = Accountable
*P = Participant
*I = Informed
Project
Sponsor
I
Product
Owner
R
R
Project
Manager
A
A
I
R
A
R
R
I
I
I
P
I
I
R
R
I
R
A
I
R
R
R
R
R
A
I
I
I
I
I
R
HOA
members
Development
Designer
Lead
Developer
Test
Engineer
Customer
Support
A
P
I
P
P
A
A
R
A
A
R
A
A
A
A
A
A
A
P
A
P
A
A
A
P
P
P
A
P
A
P
Plan Risk Management
The risk management plan for our project focuses our strategy toward reducing or mitigating risk that would prevent completion or
delay of project completion. There are additional risks to be concerned with that do not rise to the level of concern for immediate
intervention and generally lean toward acceptance. The reason for this stance of risk management is because many user,
stakeholders are split on wanting immediate implementation or are resistant to implementation of our app. Because of these forces,
the primary concern is timely completion rather than risk associated with budget and to some degree, scope.
Identify Risk and Analysis
The following table is a risk register that identifies the risks associated with the project, risk owners, and mitigation plans for said
risk. The risk on this register is prioritized by a factor of the probability and the Impact level.
Risk Register
ID
1
2
3
Activity
Risk
Not factoring out of
Planning and Analysis
scope
Increase Budget due to
any delays or
Planning and Analysis unexpected added steps
Development delay due
Development
to scope creep
Critical bug detection
4
Integration and Testing
Probability Impact WA
4
5
20
3
7
21
4
8
32
4
9
36
Team(s)
Mitigation Plan
Project
All stakeholders brainstorming
Manager and to add both inscope and out of
stakeholders scope plan ideation
Contract given on the basis of
Project
component instead of hours
Manager
wages
Timely reviews and
Development
communication plan done to
team
ensure smooth processing
QA and
Additional negative test cases
Development to be included in Quality
Teams
validation
5
Planning
6
Maintenance
Staff shortage due to
COVID
Change in Govt. Policies
3
8
24
2
5
10
Establishing Proxy for key
Project
members in Project
Manager
Management and development
roles
Development Notifying end users via
team
reminders/alerts
Plan Risk Response
The following diagram represents a visual depiction of the weighted average of risk level for
each risk factor identified on the risk register. The risk factors in the red category are higher
priority risk factors that need to be addressed with risk mitigation measures before address
other risk factors unless the risk management strategy expressly requires certain types of
risk to be addressed first.
Monitor Risk
Risk will need to be monitored continuously throughout the life of the project. Risk audits will
reveal if there is a change in the risk impact or probability for any of the identified risks,
which could potentially change their position on the Impact/Probability chart. Additionally, the
project team should report and evaluate new risks and add them to the risk register. Newly
identified risks that could delay the project will be prioritized and mitigated as early as
possible in the project
Identify Stakeholders
There are many groups that have interest in a COVID-19 tracking app and vaccination finder. We identified the potential
stakeholders for such an application and determined the role they would play in the development and fielding of our application. In
the stakeholder register, we evaluated the level of interest and influence that each stakeholder had in the project and how much
they could be impacted by the project outcome. Then we identified at what point in the project we would need the stakeholder to
be involved.
Stakeholder Matrix
Name
Role
Ben
Community
Manager
Product
Owner
HOA admin
\ Resident
HOA
members \
Resident
HOA
members \
Resident
Project
Staff
Society
Residents
Megha
Amy
Don
Cindy
Employees
Local
community
members
How much does
this impact
them?
Significant
Project Rank
Interest
Influence 1-5
Enabler
What would we like them to do?
When are they needed?
Throughout the project
Enabler
Invest in resource and manage
project
Manage the project and requirement
Minimal
Significant
Enabler \
Influencer
Enabler \
Influencer
Support, involve and influence
residents to participate
Support, involve and influence
residents to participate
After the app is created and motivate people to
participate
After the app is created and motivate people to
participate
Significant
Enabler \
Influencer
Support, involve and influence
residents to participate
After the app is created and motivate people to
participate
Minor
Enabler
Create and execute the project
Significant
Enabler
Provide info and use application
Participate in collection
Throughout the project as per their respective
roles and responsibilities
After the app is created, to participate and
provide data
Significant
Throughout the project
Plan Stakeholder Engagement
After identifying stakeholders and the expected level of involvement, then we needed
to plan how we would engage the stakeholder and to what degree they are aware of
our project and its potential impacts on them. First we created a stakeholder
engagement assessment matrix to depict stakeholder knowledge and drive our
engagement plan. Then we created an engagement plan that would address
stakeholders in a way that respected their level of knowledge.
ID
Stakeholder
Role
Unaware
1
Ben
2
Megha
3
Amy
HOA admin \
Resident
4
Don
HOA
members \
Resident
5
Cindy
HOA
members \
Resident
6
Employees
Project Staff
7
Local
community
members
Society
Residents
C
8
Local Public
Health
Department
Government
Agency
C
Resistant
Neutral Supportive
Community
Manager
Leading
CD
Product
Owner
CD
C
D
C
D
CD
C
C
D
D
D
D
The stakeholder engagement plan outlines conventional approaches and methods
for engaging each stakeholder. These engagements should be used to increase
stakeholder participation and improve awareness from the current level (annotated
as a C in the stakeholder engagement matrix above) to the desired level (annotated
as a D in the stakeholder engagement matrix above). In specific cases, such as the
community members, there are multiple current and desired levels of engagement.
The different classifications are indicative of the populace being mixed in its support
of the COVID-19 vaccine and the realization of the threat it poses to the community.
Stakeholder Engagement Plan
Name
Ben
Megha
Amy
Don
Cindy
Employees
Local community members
R
Comm
Comm
Comm
Regular com
Communication in Hom
Manage Stakeholder Engagement
Despite the goal to gain positive interest and involvement of all stakeholders, many
stakeholders will either not have interest in the project outcome or they may actively
resist the project. In order to determine which stakeholders are a high priority, we
used a power/interest grid. This will help us in determining which stakeholders
require attention earlier and throughout the project and which stakeholders may not
need engagement beyond initial attempts to build interest in the project outcome.
Monitor Stakeholder Engagement
Using the Power/Interest grid, the project manager and project team need to
prioritize engagements with project stakeholders. Stakeholders that fall in the 2nd
quadrants are the highest priority and must be monitored closely throughout the life
of the project. The stakeholders in the 3rd quadrant have low power but a high level
of interest, therefore they require regular engagement to keep them informed on the
project. The stakeholders in the first quadrant have power or influence in the project
but little interest in the project or its outcomes. These stakeholders must be kept
happy to avoid increasing interest and using their power to derail a project. The
stakeholders in the 4th quadrant have little power and little interest in the project
outcomes, therefore they must be monitored to ensure that they do not gain
additional power or interest in the project. All must be continuously monitored for
changes that could cause their position in the power/interest grid to change.
Download