ATT01 17043.000162-NA.014

advertisement
Inspection Test Record
CITR501-C COATING
Reference
SBM Purchase Order:
001.17043.000162
Date:
17/11/2021
Package description:
PME‐SHELL&TUBE EXCHANGERS
Project:
PROSPERITY FPSO
Supplier:
HEATEC JIETONG PTE LTD
Parent tag:
771-HEST-0062
Supplier Group:
HEATEC JIETONG PTE LTD
Main Component
tag:
771-HEST-0062
Item
Y
Description
1. Specification (Note 1)
Verify approval of documents
1.1
Ref:
1.2
Photos N/A
SO17033- PESDMCPF006001-A2-Ch. 4.5 /
10.6
Notes:
Photos N/A
Verify working procedure(s) is / are approved by SBM before starting coating
activities
Ref:
1.4
Notes:
CONTRACTOR’s personnel shall be qualified in accordance to the provisions
specified in Section 10.6 of this Specification.
Ref:
1.3
SO17033- PESDMCPF006001-A2-Ch. 11
SO17033- PESDMCPF006001-A2-Ch. 4.5 /
10.6.5
Notes:
Photos N/A
Ensure requirements for the application of Pre-Fabrication Primers are followed up by
the Supplier.
Ref:
SO17033- PESDMCPF006001-A2-Ch. 7
Notes:
All inspection equipment shall have valid and up to date calibration certificates,
details of which shall be issued for review along with the CONTRACTOR’s coating
records, see Section 10.8 - Inspection Equipment Calibration Records.
1.5
Dry Film Thickness gauges shall be zeroed and calibrated in accordance with the
manufactures instructions at the start of each shift and thereafter every three hours.
Ref:
SO17033- PESDMCPF006001-A2-Ch. 10.5.3
 SBM Offshore
Notes:
Photos N/A
Page 1 of 8
P/L
N/A
Inspection Test Record
CITR501-C COATING
2. Preparation
2.1
As far as possible the direct contact of different metals shall be avoided. In cases
where this is unavoidable due to specific design requirements, suitable isolation shall
be installed between the differing metals to mitigate bi-metallic corrosion, such as
Pikotek, Teflon or similar approved isolation systems.
Ref:
2.2
SO17033- PESDMCPF006001-A2-Ch. 4.6
Notes:
All coating materials shall be supplied to the work site in their original unopened and
clearly identified containers, bearing readable labels. Storage requirements according
to specification Ch. 4.9.2
Ref:
SO17033- PESDMCPF006001-A2-Ch. 4.9.2
Notes:
Photos N/A
Ensure test panels are available, cleaned and painted during coating activities
2.3
Ref:
2.4
SO17033- PESDMCPF006001-A2-Ch. 10.7
Notes:
See photos
Where possible, fixed scaffolding or staging shall be used for surface preparation and
coating and will be subject to COMPANY approval.
Ref:
SO17033- PESDMCPF006001-A2-Ch. 4.9.3
Notes:
See photos
Make sure that adequate ventilation is installed during blasting and coating activities.
2.5
Ref:
SO17033- PESDMCPF006001-A2-Ch. 4.9.4
Notes:
Photos N/A
In order to prevent condensation, the steel temperature should always be at least 3°C
above the dew point. All surfaces shall be visibly dry and clean at time of application
and this condition shall be maintained until the coating is cured.
2.6
Verify that de-humidification is installed where required.
Ref:
SO17033- PESDMCPF006001-A2-Ch. 4.9.5
Notes:
Ensure proper lighting is installed
2.7
Ref:
SO17033- PESDMCPF006001-A2-Ch. 4.9.6
Notes:
Photos N/A
Notes:
Photos N/A
Ensure that safety precautions are implemented
2.8
Ref:
2.9
SO17033- PESDMCPF006001-A2-Ch. 4.10.2
Prior to blasting, all sharp edges shall be rounded with a minimum radius of 2 mm in
accordance with ISO 8501-3 P3 (Table 1, item 2.1).
Ref:
SO17043- PESDMCPF006001-A2-Ch. 3.1
 SBM Offshore
Notes:
Photos N/A
Page 2 of 8
Inspection Test Record
CITR501-C COATING
Surface preparation before blasting:
Removal of steel / weld imperfections, pre-cleaning and degreasing.
See also Chapter 5.7 for SS & CRA’s if applicable.
2.10
See also Chapter 5.8 for hot dip galvanized steel if applicable
See also Chapter 5.9 for prefabrication primers
Ref:
SO17033- PESDMCPF006001-A2-Ch. 5.1 /
5.2 / 5.3 / 5.7 / 5.8 / 5.9 / 10.5.3 (table 10.1)
Notes:
Photos N/A
3. Abrasive blast cleaning
Ensure that equipment for abrasive blast cleaning complies with the specification
3.1
Ref:
SO17033- PESDMCPF006001-A2-Ch. 5.4.2
Notes:
Photos N/A
Abrasive materials used for blast cleaning must be in compliance with specification.
See also Chapter 5.7 for SS & CRA’s if applicable.
3.2
See also Chapter 5.8 for hot dip galvanized steel if applicable
See also Chapter 5.9 for prefabrication primers
Ref:
3.3
SO17033- PESDMCPF006001-A2-Ch. 5.4.3 /
5.7 / 5.8 / 5.9 /10.5.3 (table 10.1)
Notes:
Photos N/A
Blast cleaning shall not be conducted when the surfaces are less than 3°C above
dew point or when the relative humidity of the air is above 85% (or as per
Manufacturer recommendations).
Ref:
SO17033- PESDMCPF006001-A2-Ch. 5.4.4 /
10.5.3 (table 10.1)
Notes:
See photos
Check Compressed air is free of oil and contamination (2 times per shift)
3.4
Ref:
SO17033- PESDMCPF006001-A2-Ch.10.5.3
(table 10.1)
Notes:
Photos N/A
Surface cleanliness shall be checked and conform to Class 2 of standard [17]. The
maximum acceptable total water-soluble salts contamination on abrasive blasted
surfaces before application of any primer.
3.5
See also Chapter 5.8 for hot dip galvanized steel if applicable
Ref:
SO17033- PESDMCPF006001-A2-Ch. 5.4.1 /
5.8 / 10.5.3 (table 10.1)
Notes:
2. See photos
Surface profile/roughness shall be measured according to standard [18] Parts 4 and
5. On case per case base measurements can be done by using Standard [18] Part 2
– Comparator procedure alone.
3.6
See also Chapter 5.7 for SS & CRA’s if applicable
See also Chapter 5.9 for prefabrication primers
Ref:
SO17033- PESDMCPF006001-A2-Ch. 5.4.3 /
5.7 / 5.9 / 10.5.3 (table 10.1)
 SBM Offshore
Notes:
2. See photos
Page 3 of 8
Inspection Test Record
CITR501-C COATING
Verify dust test are performed.
3.7
Ref:
SO17033- PESDMCPF006001-A2-Ch.10.5.3
(table 10.1)
Notes:
See photos
4. Power tool cleaning
Ensure power tool cleaning is executed according specification
4.1
See also Chapter 5.8 for hot dip galvanized steel if applicable
Ref:
SO17033- PESDMCPF006001-A2-Ch. 5.5 /
5.8 / Ch.10.5.3 (table 10.1)
Notes:
5. Paint application
5.1
Ensure requirements regarding storage, mixing, thinning, pot life according
specification are followed
Ref:
SO17033- PESDMCPF006001-A2-Ch. 6.1 /
10.5.1
Notes:
Photos N/A
Ensure environmental conditions are according to specification
5.2
Ref:
SO17033- PESDMCPF006001-A2-Ch. 6.2
Notes:
See photos
Notes:
See photos
Ensure that requirements for application are followed:
Chapter 6.3 for spray application
Chapter 6.4 for brush application
5.3
Chapter 6.5 for roller application
Chapter 6.6 stripe coating
Ref:
SO17033- PESDMCPF006001-A2-Ch. 6.3 to
6.7
Check Compressed air is free of oil and contamination (2 times per shift)
5.4
Ref:
SO17033- PESDMCPF006001-A2-Ch.10.5.3
(table 10.1)
Notes:
Photos N/A
Perform wet and dry film thickness checks and visual inspections
5.5
Ref:
SO17033- PESDMCPF006001-A2-Ch. 6.8 /
10.5.2 / 10.5.3 (table 10.1)
Notes:
See photos
Ensure requirements for repair of defects and touch up are followed
5.6
See Chapter 8.7 for repair of hot dip galvanized areas
Ref:
SO17033- PESDMCPF006001-A2-Ch. 6.9 /
8.7
 SBM Offshore
Notes:
Page 4 of 8
Inspection Test Record
CITR501-C COATING
Inspection and testing on completion of coating
5.7
Ref:
SO17033- PESDMCPF006001-A2-Ch. 10.5.4
(& table10-2)
 SBM Offshore
Notes:
See photos
Page 5 of 8
Inspection Test Record
CITR501-C COATING
Component Tag
number
 SBM Offshore
Page 6 of 8
5.7
5.6
5.4
5.3
5.2
5.1
4.1
3.7
3.6
3.5
3.4
3.3
3.2
3.1
2.10
2.9
2.8
2.7
2.6
2.5
2.4
2.3
2.2
2.1
1.5
1.4
1.3
1.2
1.1
Punch List item
Inspection Test Record
CITR501-C COATING
Tag number
Photo reference
Please see the photos in additional pages
Item
Documents Attached
1
2
3
 SBM Offshore
Page 7 of 8
Inspection Test Record
CITR501-C COATING
Completed By
(Supplier)
Company
Completed By
(Sub-Supplier)
HEATEC JIETONG
Signature
Print name
Date
Gopal
03/11/2021
17/11/21
Notes
Notes
Description
[1] Applicable Specifications:
SO17043- PESDMCPF006001-A2- FPSO MATERIALS SURFACE PREPARATION
AND COATINGS SPECIFICATION
Reference to:
SO17033- PESDMCPF006001-A2- FPSO MATERIALS SURFACE PREPARATION AND
COATINGS SPECIFICATION
Inspections on water jetting, hot dip galvanizing, passive fire protection not listed.
[2] Referenced codes:
[17] ISO 8502 Parts 1-10 Preparation of steel substrates before application of paints and
related products - Test for the assessment of surface cleanliness
[18] ISO 8503 Parts 1-5 Preparation of steel substrates before application of paints and
related products – Surface roughness characteristics of blast cleaned steel substrates
 SBM Offshore
Page 8 of 8
CITR501-C COATING
Visual Inspection after Blasting on Channel
Salt testing checked on Channel
Visual Inspection after Blasting on Shell side
Measuring of profile
Salt Testing on Channel surface
Profile checked on Channel
Salt Testing checked on Shell surface
Checking of Dust & profile
CITR501-C COATING
First Coat Inspection of Channel
MEK TEST Carried out
Second coat DFT Verfiy of Channel
Checking DFT
First Coat Inspection of Shell
MEK Test result found Satisfactory
Second coat DFT Verfiy of Shell
Verifying the environmental conditions
CITR501-C COATING
Shell Final coat DFT Check
DFT Checking on Shell test panels