APS Training Preparation

advertisement
APS Training Preparation
28/10/2021
Planner Codes and Settings Criteria
1) Planner Codes

Follow APS proposal.
Classification
Critical
Purchased Items
Supply
High
Low
/
Regular
S
/
/
A
/
/
/
/
/
B
C

Usage
/
Lead Time
Restricted
Long
/
/
Mid
Short
/
/
/
/
Classifications description.
Classification
Description
S
Highly critical with long lead time and restricted supply
A
High usage with regular supply and medium-term lead time
B
Moderate usage with short lead times and good supply
C
Low usage with regular supply and short lead time
/
Planner Codes and Settings Criteria
1) Planner Codes

Example : Planner Codes for CHARGER, DEVICE & OMB Model.
Classification
Planner Codes
CHARGER
DEVICE
OMB
S
CS
DS
OS
A
CA
DA
OA
B
CB
DB
OB
C
CC
DC
OC
Note :
Planner Codes has only 3 characters limitation.
Product to be update to the new BOM structure
Model: CERBO GX
Product to be update to the new BOM structure
Model: CERBO GX – Engineering BOM Structure
Product to be update to the new BOM structure

Model: CERBO GX – Highly critical with long lead time and restricted supply


Model: CERBO GX – High usage with regular supply and medium-term lead time
Product to be update to the new BOM structure

Model: CERBO GX – Moderate usage with short lead times and good supply


Model: CERBO GX – Low usage with regular supply and short lead time
Item Lead Time for items that were originally > 365 days
➢
Lead time followed the supplier updated.
➢
999 code is part under allocation, separated it with this code for our understanding.
➢
Allocation mean the parts supplied according to the availability and share %, and not follow
the lead time given.