APS Training Preparation 28/10/2021 Planner Codes and Settings Criteria 1) Planner Codes Follow APS proposal. Classification Critical Purchased Items Supply High Low / Regular S / / A / / / / / B C Usage / Lead Time Restricted Long / / Mid Short / / / / Classifications description. Classification Description S Highly critical with long lead time and restricted supply A High usage with regular supply and medium-term lead time B Moderate usage with short lead times and good supply C Low usage with regular supply and short lead time / Planner Codes and Settings Criteria 1) Planner Codes Example : Planner Codes for CHARGER, DEVICE & OMB Model. Classification Planner Codes CHARGER DEVICE OMB S CS DS OS A CA DA OA B CB DB OB C CC DC OC Note : Planner Codes has only 3 characters limitation. Product to be update to the new BOM structure Model: CERBO GX Product to be update to the new BOM structure Model: CERBO GX – Engineering BOM Structure Product to be update to the new BOM structure Model: CERBO GX – Highly critical with long lead time and restricted supply Model: CERBO GX – High usage with regular supply and medium-term lead time Product to be update to the new BOM structure Model: CERBO GX – Moderate usage with short lead times and good supply Model: CERBO GX – Low usage with regular supply and short lead time Item Lead Time for items that were originally > 365 days ➢ Lead time followed the supplier updated. ➢ 999 code is part under allocation, separated it with this code for our understanding. ➢ Allocation mean the parts supplied according to the availability and share %, and not follow the lead time given. Thank You