See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/272091797 Railway Bridges – Safety in design for train derailments Conference Paper · October 2011 CITATIONS READS 3 5,163 2 authors: Frank Rapattoni Raphael Grzebieta WSP UNSW Sydney 8 PUBLICATIONS 4 CITATIONS 241 PUBLICATIONS 4,289 CITATIONS SEE PROFILE Some of the authors of this publication are also working on these related projects: Safety Management for Heavy Vehicle Transport Operations View project Special Issue "Ergonomics and Sustainability" View project All content following this page was uploaded by Frank Rapattoni on 10 February 2015. The user has requested enhancement of the downloaded file. SEE PROFILE Railway Bridges – Safety in design for train derailments Frank Rapattoni1, Prof. Raphael Grzebieta2 1 Parsons Brinckerhoff 2 Transport And Road Safety Research, UNSW Abstract Derailment of rail cars remains one of the most dangerous hazards for bridges over and under railway lines with the potential of harm to railway users, road users and people in nearby buildings. Although their occurrence is rare the consequences are always severe if not catastrophic. The disasters at Granville (Australia) and Eschede (Germany) are two examples which demonstrate the possible consequences of such events with high loss of lives, disruption of services and costly damages. Prescriptive requirements to safeguard against the impact by de-railed cars are contained in the Australian bridge design standard AS5100. The intent of the provisions is to avoid catastrophic failures of bridges due to loading or collision impact by derailed trains or road vehicles and to provide a “forgiving” environment to minimise the probability of injury to the occupants of derailed trains. The provisions are considered to be world’s best practice but implementation is often difficult and inconsistent. Practice varies considerably among rail authorities around the world. The UIC Code provides comprehensive recommendations about risk avoidance and control. Assessments to provide design solutions to limit risk as low as reasonably practicable (ALARP) can be used to justify a structural arrangement which does not comply with AS5100. The Australian Transport Council’s (ATC) “Safe System” approach came into effect as of 20th May 2011 and requires zero harm at all stages in the life of a structure. This approach complements the current provisions in AS5100. Design solutions should comply with the intent of the “Safe System” and the AS5100 provisions and consider the possibility of train derailments with realistic, if not worst case, accident models to prevent human trauma. Crash simulation software can assist in identifying the hazards, likely consequences and test proposed solutions at the early stages of design. V. Ponnampalam, H. Madrio and E. Ancich Sustainable Bridges: The Thread of Society AP-G90/11_034© ABC 2011 81 82 Rapattoni, Grzebieta Introduction Derailment of rail cars remains one of the most dangerous hazards for bridges over and under railway lines and for rail passengers. Although their occurrence is rare the consequences are always severe if not catastrophic. The disasters at Granville (Australia) (Fig.1) and Eschede (Germany) (Fig. 2) are two examples which demonstrate the possible consequences of such events with high loss of lives, disruption of services and costly damages. This is a follow up paper to [2]and [3] which outlined the provisions in AS5100 [4] in regards to collision loads and design requirements. In brief, • The intent of AS5100 is to avoid catastrophic failures of bridges due to loading or impact by derailed trains or road vehicles and provide a “forgiving” environment by preventing hard impacts to minimise the probability of injury to the occupants of derailed trains. • There is a need for better practical design guidance to ensure best practice in maximising safety. The current limited prescriptive provisions do not provide adequate information for designers or rail authorities to make important decisions in regards to acceptable risks. A “Safe System” approach in design of road infrastructure is now required under the new Australian Transport Council’s (ATC’s) safety paradigm shift. This requires zero harm at all stages in the life of a structure. The new provisions set down by the Australian Transport Council (ATC), consisting of federal, state and territory ministers, are firmly based on the “Safe System” approach principles and are framed by the guiding vision that no person should be killed or seriously injured on Australia's roads [1]. This came into effect as of 20th May 2011 and requires zero harm at all stages in the life of a structure. This includes any deaths resulting from an errant vehicle causing a train derailment because of inadequate roadside barrier provision. This paper discusses the current provisions in AS5100 and international codes, past and current practice and future directions in design using the “Safe System” approach, which complements the intent of AS5100, towards the achievement of Zero Harm. The use of risk assessment models and the latest advances in crash simulation software to assist in identifying the hazards, likely consequences and test proposed solutions are also discussed. Railway Bridges – Safety in design for train derailments 83 AS 5100 – 2004 Provisions Bridges over railways For bridges over railway lines, AS5100.1 provisions are as follows: 11.3.1 General For collision from railway traffic, to minimize the likelihood of damage and collapse of bridges and other structures over or adjacent to railway tracks as a result of collision from railway vehicles, the following shall apply: (a) Unless approved otherwise by the relevant authority, bridges over railways shall have a clear span between abutments. (b) Where the relevant authority agrees that the requirement of Item (a) is not achievable, supports adjacent to railway tracks may be permitted subject to the following conditions being met, and in the following order of preference: (i) Alternative load paths are available through the structure to ensure that the superstructure does not collapse in the event of removal of the supporting piers or columns as a result of collision. In this case, the supporting piers shall not be of heavy construction. They may have independent deflection walls. However, they shall not have integral deflection walls. (ii) The support piers are of heavy construction designed to resist the loads specified in AS 5100.2. Such supports shall be protected from head-on collision by deflection walls or the like. Any supports that cannot be protected from head-on collision shall be designed to be removable in accordance with Item (b)(i). AS 5100.2 Clause 10.4.3 specifies design collision loads of a) 3000 kN parallel to rails and b) 1500 kN normal to rails It is important to note that the loads specified in this Clause allow for “….moderate derailments and minor collisions but not major derailments of a 300LA train… This may also represent a self-propelled passenger train derailing at moderate speed” (Ref. Clause C.10.4.3). In effect these loads represent “… only a glancing blow, not a head-on collision” (Ref. Clause C11.3.2). A head-on collision of a train at operational speed with a pier will produce much higher loads than specified by AS5100 and the hard impact would impact severely 84 Rapattoni, Grzebieta on train occupants due to the high sudden deceleration. The Eschede accident (Fig.2) shows the possible consequences of this type of collision. The AS5100 provisions are considered to be world’s best practice to ensure maximum safety but implementation is often difficult and inconsistent. Strict compliance has proved impractical in some situations [3], especially when attempting to modify existing bridges to comply with the provisions. Underbridges AS 5100.2 Clause 10.5.1 specifies that “Railway bridges designed to carry 300LA loads shall be designed for two separate train derailment load cases as set out in Clauses 10.5.2 and 10.5.3”. For underbridges the specified train loads will be applied at the most critical location, at the edge of the bridge deck. It is noted that there are no provisions intended to retain a de-railed train on the bridge. This is left to the discretion of the rail authority. Provision of “guard rails” (double rails) is usually specified by the rail authorities [5] although there is a growing trend towards adopting more robust containment systems [2]. International Codes The UIC Code [6] sets out recommendations for managing risk from derailed trains near structures for different train types and speed. It discusses preventative and protective measures and recommends suitable measures to reduce as far as is reasonably practicable the effects of an accidental impact from a derailed vehicle against the supports of structures located above tracks and supports carrying superstructures of different classes: • Class A – superstructures supporting elevated structures that are permanently occupied such as offices, lodgings or offices and • Class B - superstructures not supporting elevated structures such as bridges The UIC Code differentiates between new and existing structures in view of the difficulty and cost in relocating the supports to improve safety for the latter. The recommendation in this case is to consider and compare the risk of impacting the Railway Bridges – Safety in design for train derailments 85 supports with the level of other risks to the safety of train operations to assess priorities for ameliorative works. The UIC Code recommendations provide comprehensive design guidelines to minimise risks however it does not require prevention of a head-on collision with heavy piers as prescribed by AS5100. In regards to deflecting devices it states that guide walls are suitable only if they can absorb high horizontal loads and have a high degree of ductility. Energy absorbing devices are not considered practical due to the great deformation distance needed to guarantee sufficient energy absorption for a typical train travelling at the operational speed. The American Railways Engineering Maintenance-of-way Association (AREMA) [9][provides detailed recommendations on design of “crash walls” for piers but has no explicit provision prohibiting head-on impact of a derailed train with piers. Past and Current Australian Practice Bridges over railways The preferred bridge type is a single clear span over railways as this prevents any possibility of a collision. However, this is not always possible due to the increased span length and/or cost of alternative bridge types which may be required. Long spans may not be practical at some locations as girders may be too deep and a through-truss, through-girder or cable stayed bridge may prove too costly or unsuitable for the location. The currently most common bridge type specified is multi-span with simply supported precast beams on heavy reinforced concrete piers designed for the above collision loads. This choice is made mainly due to the lower cost of this system, using economical prestressed concrete (PSC) beams. For this type of construction, AS5100.1 Clause 11.3.1 (b) (ii) requires the use of deflection walls to avoid the possibility of head-on impact with the heavy pier. If this is not possible, AS5100 requires that a pier-redundant bridge with frangible piers be adopted to prevent a hard impact with the train (Cl. 11.3.1 b (i)). In order to justify the use of a bridge with heavy piers not complying with Clause 11.3.1 (b) (ii), a risk analysis is required to demonstrate that the risk to life from an impact by a derailed train is “as low as reasonably practicable” (ALARP) and can be accepted. The test for ALARP is often very difficult as tradeoffs are 86 Rapattoni, Grzebieta usually required between safety and cost and involves subjective judgments about what is a “socially acceptable risk” and what cost is justifiable to reduce the risk. It is considered that risk analysis should be used as a last resort when it is not possible to contain risks in a design within a reasonable budget as this approach requires numerous assumptions in regards to • Probability of train derailments over the design life of the structure • Consequences due to derailment – likely fatalities and property damage • Subjective judgments of what is an acceptable risk Whilst designers are responsible to design to the required safety standard, rail and road authorities are responsible for making the decision about acceptable risk using guidelines which reflect the community’s acceptance or aversion to risk. A typical matrix delineating boundaries of acceptable risk is shown below. Acceptable Risk for Bridges over Railways 1.E-01 INTOLERABLE 1.E-03 1.E-04 TOLERABLE IF ALARP year (F) Frequency of N or more fatalities per 1.E-02 1.E-05 1.E-06 NEGLIGIBLE ALARP - As Low As Reasonably 1.E-07 N umber of fatalities (N ) (S Source: Main Roads WA) An alternative strategy proposed when it is not possible to contain risks in a design within a reasonable budget is to use the “Safe System” approach [1], using a holistic Crashworthy System and a Vision Zero philosophy ([10],[11],[12]) which now governs road design and indeed present day Occupational Health and Safety. That is, to reduce the kinetic energy of the system such that incidents can be contained to a tolerable, survivable level. Hence, for example, the speed of the train along the line should be reduced to a speed at which, if a derailment does occur, the impacted pier or support could withstand the impact load and cause no injury to people. This speed limit could be maintained until such time that the structural system can be designed to tolerate a higher speed derailment incident. Railway Bridges – Safety in design for train derailments 87 Pier-redundant bridges The authors are not aware of any bridges in Australia over railways designed in accordance with Cl. 11.3.1(b)(i). The reluctance to use this bridge system is mainly due to the preference of using robust piers which can withstand a moderate or glancing impact from a derailed train without failure as well as unfamiliarity with this type of bridge and the higher construction cost of the superstructure. A pier-redundant bridge requires a continuous superstructure, typically using composite steel girders, which can be designed to span the resulting extended span after a pier collapse, without a total collapse. The bridge would be designed for all dead loads and limited live loads as deemed appropriate (20% minimum in AS5100). The overhead design clearance should be increased to allow for the resulting high deflections to avoid impact by the train with the superstructure. Repairs following an extreme incident would be extensive, consisting of temporary propping, jacking the superstructure to its original level, rebuilding the piers and repairing the deck but considered acceptable given the rarity of this event and saved lives. From a structural point of view, this bridge system is viable, as demonstrated by two bridges over the Murray River at Berri and Hindmarsh Island [2] and may prove to be more economical in some instances due to the lower cost of the substructure which would not be required to be designed to withstand the collision loads. Future Directions - Towards a “Safe System” A “Safe System” approach in design of road infrastructure is now required under the new Australian Transport Council’s (ATC’s) safety paradigm shift [1]. The (ATC) “Safe System” approach came into effect as of 20th May 2011 and requires zero harm at all stages in the life of a structure. If that is not possible for the funds available then, either the project is abandoned or speeds are reduced to ensure that incidents can be contained to survivable levels. Prescriptive code provisions should be considered as minimum requirements and used as guidelines. Design solutions should comply with the intent of the “Safe System” and the AS5100 provisions and consider the possibility of train derailments with realistic, if not worst case, accident models to prevent human trauma. The following is a discussion of the recommended design approach and considerations towards the achievement of this objective. 88 Rapattoni, Grzebieta “Safe System” approach Considering a risk avoidance strategy or “Safe System” approach, the design should be carried by: • Considering design options to prevent or limit derailments within the sphere of influence of possible impact in the vicinity of a structure, such as rail geometry, clearances, location of switching points and crossings as well as track/train type if possible. Design Codes [6] recognise that the probability of derailment is much higher at curves, crossings and switching points in particular, based on studies of past crashes. Generally, the bridge design engineer’s scope does not include rail track design or setting operating train speed. However, this is considered to be important in minimising risk and should be considered in a holistic approach to design through close interaction with the rail track designers and operations managers at the early stages of design. Design standards should highlight this requirement as design changes at advanced stages of design are often prohibitive. 1. Considering bridging options which avoid potential collisions with a derailed train or that are less vulnerable to impact (including speed reduction). The following Table 1 identifies the risk level for typical types of bridges over railways and possible ameliorative measures: Table 1 – Type of Bridge over Railways and Risk level BRIDGE TYPE RISK LEVEL AMELIORATIVE MEASURES COMMENT Single Clear Span NIL Not required Preferred Multi-span with simply supported or non pierredundant spans with frangible piers VERY HIGH Essential use of deflection walls to avoid impact with the frangible piers This type must be avoided due to the high risk of failure Multi-span with frangible pier and PierRedundant Superstructure LOW Impact with frangible piers will most likely lead to bridge collapse and fatalities (Fig. 1). Impact with frangible piers should not lead to train passenger fatalities. Reduce rail speed to ensure that a derailed train will not crash into the pier. Desirable use of deflection walls to avoid impact with the frangible piers and their failure due to a minor derailment impact. Frangible piers with enough robustness to avoid failure due to Requires continuous superstructur e designed for DL and limited LL (20% Railway Bridges – Safety in design for train derailments Multi-span with Heavy Pier 89 Frangible piers may fail due to collision loads from a minor derailment. minor impact loads minimum) for extended span. HIGH Essential use deflection walls or other impact absorbing system to avoid head-on impact with the piers. Design of deflection walls between tracks to redirect derailed train is difficult and costly. Hard impact with heavy pier can lead to passenger fatalities (Fig. 2) Desirable use of continuous pierredundant superstructures. Speed reduction for impact at tolerable levels. Fig. 1. Collapse of Bold St Bridge at Granville (NSW, Australia), 1977, after demolition of pier by a derailed train Fig. 2. Collapse of Bridge at Eschede (Germany), 1998, after initial impact with pier by a derailed fast train The following Table 2 identifies the risk level for typical under-bridge types and possible ameliorative measures: 90 Rapattoni, Grzebieta Table 2 – Type of Underbridge and Risk Level BRIDGE TYPE RISK LEVEL AMELIORATIVE MEASURES COMMENT Beam & slab or box girder bridges VERY LOW Impact with supporting beams not possible Nil. Very low risk of bridge collapse. “Guard-rails” to contain train on bridge after minor, lowspeed derailment Will not retain train on the bridge in a fast derailment unless ballast walls high enough and designed for collision loads. Throughtruss bridge HIGH Impact with truss either within bridge or approaches can cause bridge failure (Fig. 3) Use deflection walls within the bridge to avoid impact with the supporting truss and deflection walls on approaches to avoid head-on impact with end of truss. Reduce speed to minimise risk of derailment Most vulnerable unless ameliorative measures implemented. Safe bridge system with ameliorative measures and/or speed reduction. MEDIUM Design for AS5100 collision loads within the bridge and use of approach deflection walls to avoid head-on impact with the girder’s end. Reduce speed to reduce derailment risk and kinetic energy. Vulnerable unless ameliorative measures implemented Safe bridge system with ameliorative measures as it will contain a derailed train on the structure Concrete Throughgirder bridge Impact with girder upstand on approach constitutes a hard impact with possible bridge collapse. Impact within bridge can dislodge bridge off bearings Fig. 3. Derailed train causing collapse of truss bridge 1. Designing for collision loads by considering realistic, possible derailment scenarios, not just applying prescribed design nominal loads to parts of the structure, as prescribed by AS5100. Railway Bridges – Safety in design for train derailments 91 This may be done by: • Considering a derailed, out of control train hurtling towards the bridge and predicting the likely impact scenario. • Reference to technical papers, available literature and data dealing with past incidents to understand crash dynamics. • Collision simulation with the latest software to assist in identifying the hazards, likely consequences and test proposed solutions. This would offer a very desirable alternative if models could be calibrated to reflect real collisions. This is discussed below. • Designing to ensure that the intent of the “Safe System” approach and AS5100 provisions are implemented if a collision is possible. The prime prerequisites are avoidance of bridge collapse and avoidance of hard impact by a derailed train by providing a “forgiving” environment to minimise the probability of fatalities either within the train or within the sphere of influence of a derailment. Perhaps the most challenging task in designing new bridges over railways is the prevention of head-on collision with a heavy pier. It is considered that research to develop an appropriate impact absorption system for a given design train and impact speed, should be undertaken by rail authorities. Mathematical collision simulation studies of derailments [7] done before the advent of fast computers attempted to simulate train derailment scenarios and provided the basis for the development of train containment barrier designs in Texas, USA. Collision simulation with the latest software can assist in identifying the hazards, likely consequences and test proposed solutions. For example, a recent investigation of collisions between trams and cars [8], [10], [11] using MADYMO and LSDYNA software shows the power of such programs in analysing collisions and consequences in terms of impact on humans and property damage. Conclusions Derailment of rail cars remains one of the most dangerous hazards for bridges over and under railway lines with the potential of harm to railway users, road users and occupiers of nearby buildings. Although their occurrence is rare the consequences are always severe if not catastrophic. The intent of the prescriptive requirements provisions in AS5100 is to avoid catastrophic failures of bridges due to loading or collision impact by derailed trains or road vehicles and to provide a “forgiving” environment to minimise the probability of injury to the occupants of derailed trains. The provisions are considered to be world’s best practice but implementation is often difficult and inconsistent. 92 Rapattoni, Grzebieta A “Safe System” approach in the design of road infrastructure is now required under the new Australian Transport Council’s (ATC’s) safety paradigm shift. This requires zero harm at all stages in the life of a structure and complements the provisions in AS5100. Zero Harm can be achieved by: • Considering design options to avoid or limit derailments. A risk avoidance and “Safe System” design approach is recommended at the early stages of rail track design with close interaction between rail track designers, operations managers and bridge designers to achieve maximum safety. This may include speed reductions if insufficient funds are available; • Considering bridging options which avoid potential collisions. The selection of an appropriate bridge type and speed reduction can often avoid most risks; • Designing for collision loads by considering realistic, possible derailment scenarios, not just applying design loads to parts of the structure, as prescribed by AS5100; • Designing to ensure that the intent of the “Safe System” approach and AS5100 provisions are implemented if a collision is possible. The prime prerequisites are avoidance of bridge collapse and avoidance of hard impact by a derailed train by providing a “forgiving” environment to minimise the probability of fatalities either within the train or within the sphere of influence of a derailment. • Collision simulation with the latest software to assist in identifying the hazards, likely consequences and test proposed solutions at the early stages of design; • Undertaking research to develop appropriate deflection walls or high energy absorbing systems to avoid head-on impacts with heavy piers; • Using risk analysis as a last resort after all possible engineering solutions have been exhausted. The UIC Code provides comprehensive guidelines and recommendations to minimise risk. Railway Bridges – Safety in design for train derailments 93 References [1] ATC, National Road Safety Strategy 2011-2020, http://www.atcouncil.gov.au/documents/atcnrss.aspx [2] Rapattoni, F, (2009) “AS 5100 Bridge Design Standard – Focus on Safety for Railway Bridges” Proceedings of AUSTROADS Sixth Conference, Auckland, May 2009. [3] Rapattoni, F, (2004) "Safety first for Bridges – by design", Proceedings of AUSTROADS Fifth Conference, Hobart, 2004. [4] AS 5100 – 2004 Bridge Design Standard. Standards Australia [5] Engineering Standard Structures ASC 310 V2.2 (2010) Rail Corporation [6] UIC Code (2002) “Structures built over railway lines – Construction requirements in the track zone [7] Hirsh, T,J, Harris,W,J, James, R,W, Lamkin, J, Heping Zang (1989) “Analysis and design of Metrorail-Railroad barrier system” RR 3780-2 on RP TTI 3780, Texan Transport Institute , Texas A&M University. [8] Grzebieta, R, H, Rechnitzer, G, (2000) “Tram Interface crashworthiness” Proceedings of International Crashworthiness Conference 2000, London (UK) Sept 2000 [9] American Railways Engineering Maintenance-of-way Association (AREMA) [10] Rechnitzer, G, and Grzebieta, R,H, (1999) “Crashworthy Systems – a paradigm shift in road safety design”, Transport Engineering in Australia, IEAust, Vol.5, No.2, Dec. 1999, (also presented and in proceedings of “Aus Top Tec” Topical Technical Symposia, Society of Automotive Engineers Australia, Melbourne, Aug 1999). [11] Grzebieta, R,H, and Rechnitzer, G, (2001) “Crashworthy Systems – a paradigm shift in road safety design (part II)”, Transport Engineering in Australia, IEAust, Vol. 7, Nos. 1&2, Dec 2001. [12] Grzebieta, R,H, and Rechnitzer, G, (2001) “Vision Zero - The need for crashworthy systems”, Proc. 24th Australasian Transport Research Forum, Zero road toll - A Dream or a Realistic Vision?, April, Hobart 2001, http://www.patrec.org/web_docs/atrf/papers/2001/1419_Grzebieta%20&%20Rechnitzer%2 0(2001).pdf View publication stats