CORPORATE SAFETY INSTRUCTION JOB SAFETY ANALYSIS: PR/LPD/P- 007 (02.002) Rev. 02 JOB SAFETY ANALYSIS (JSA) WORKSHEET Job Safety Analysis Worksheet Insulation , cladding & Silicone JSA No: PR/DEP/SEC/JSA/001 Date: DEC. 08, 2016 Revision No: 00 Section: Insulation and cladding Supervisor (Name & Sign): MOHINDER PAL SINGH for piping & Equipment Location: (P360) Reviewed and Approved By(Name & Sign): Sequence of Job Steps to be Performed 1. 2. 1. Work Permit PR/CSF/CSS/P-24 (06.001) Risk/Hazard (Refer Hazard Checklist) 1.1 Work permits No management control and the execution as per PRC and Contractor safety management system will not be followed. Risk Rating (Low, Moderate, High, Critical) Low Mitigation Hazard Control Measures (existing and additional) to reduce the risk to moderate or low. 1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6 1.1.7 Permit shall comply with PRC work permit system. Obtain work permit from PRC permit issuer. Tool box meeting shall be done to discuss the potential hazards and safe system of work. Safe work permit, JSA, WERA and MS shall be at work site and secured before any works commence. At least one work permit receiver shall be present at site at all time during work activities. Supervisor to prepare required safe work plan, permit shall be one day in advance. Supervisor, foreman and HSE officer to monitor the activity respectively. Action By GS/ GLOBAL SUHAIMI - WPR - Safety Officer 2.1.1 Ensure proper PPE’S 2. Hauling of materials to be use. 2.1 Slip trip & injuries Moderate 2.2 Improper body position 2.1.2 Daily housekeeping & 2.1.3 Materials arrangement to be maintained at site. 2.1.4 Ensure proper ergonomics 3. Lifting of materials 3.1Unauthorized person 3.2 Fall objects and personnel injury. Low Low 3.3 Personnel injury. Low 3.4 Slip, trip. Low 3.1.1 safety precautions like Gloves, coverall, dust mask.etc. 3.1.2 Training to employee for safe lifting of loads. In cramped or enclosed spaces where fiber glasses insulation is generally installed 3.1.3Daily housekeeping & materials arrangement to be maintained at site. GS/ Global suhaimiSupervisor - Foreman - All concerned people GS/ Global suhaimi Supervisor - Foreman - Equipment Operator/ Driver - All concerned people 3.1.4 Qualified rigger shall choose adequate slings for the intended lift. The load shall be directly attended by the rigger / where there is potential for the load toe equipment, material shall be handled by trained & qualified operators3.1.5 3.1.5 Hauling of materials to be used.3.1.6 3.1.6 Lifting of materials. 4.1.1 Underground cable detector shall be used prior to GS/ excavation and periodically during excavation Raymond works. - Area Trial pit shall be provided in all excavated areas Supervisor 4 Excavation works Width: 1.5 ~ 2.8 Depth: 1.5 ~ 3.0 4.1 Damage to the existing underground utility services. Moderate 4.1.2 4.1.3 4.1.4 4.1.5 4.1.6 4.1.7 4.2 Fall down of personnel 4.2.1 Low 4.2.2 4.3 Collision of Excavator, Dump Truck and Loader Moderate prior to usage of machine. Manual excavation shall be done on identified affected utilities. If unknown cable shall be discovered, report immediately to the PRC concerned department/GSCA HSE department for their action. When underground facilities are exposed (electric, gas, water, telephone, etc.) they shall be protected by support installation as necessary to avoid damage. All working crew shall familiarize different warning signage at site. Existing underground piping, electrical cables, etc., that could be undermined by an excavation shall be properly braced or shored. Hard barricade and safety signage shall be installed around the excavation area. All excavated soil shall be stockpiled 0.60m away from the excavation pit and shall be transferred immediately to the designated area. 4.2.3 Sufficient ladders or stairs shall be installed for the access point to excavation pit. 4.3.1 Swing area of Excavator shall be provided with barricade to prevent unnecessary entry of personnel. Trained flagman shall be placed and shall serve as a spotter visible to the operator. Workers shall be instructed not to work under and within the swing radius of the equipment. Warning signs shall be provided while the 4.3.2 4.3.3 4.3.4 - Foreman - Equipment Operator/ Driver - All concerned people equipment’s are working. 4.4.1 5 Manual Excavation 4.4 Removal of big stone by Mechanical equipment. Low 5.1 Weather Hot and humid weather resulting to heat stress and dehydration. Low 4.4.2 5.1.1 5.1.2 5.1.3 Low 5.1.4 5.2 Damage to the existing underground utilities Low 5.1.1 5.1.2 5.1.3 5.1.4 5.1.5 5.1.6 Installation of shoring shall be provided on class B soil to prevent the occurrence of sidewall cave-in. Only trained flagman shall control the movements of the equipment. Provision for cool drinking water and shaded rest place. Supervisor shall monitor its workforce by looking for signs of dehydration. Impose staggered working hours. Include substitution of workforce to allow sufficient rest between workers. Management & workers shall follow heat stress work/ rest period (min.) ratio on the job: Work = Rest periods (min.) 50 = 10 30 = 10 20 = 10 Maintain daily excavation checklist Excavation should not commence until all available service location drawings have been examined. Mark clearly the areas to be excavated and the underground utilities thru as-built drawing or using radar detector. Ensure all workers undergone confined space training if the trench is more than 1.2m. Do not use heavy equipment within the vicinity of the underground utilities. Conduct gas test if the trench is deeper than 1.2m prior to start of work. GS/ Raymond - Area Supervisor - Foreman - All concerned people 5.3 Fall down to excavation 5.1.7 Whenever necessary, test pit shall be made to determine the exact location of existing utilities. 5.3.1 Excavated materials must be stored at least 60cm from the edge of the embankment. Ensure that no one should stand on the edge of excavation. Provide hard barricade along the open side of trench and entry/escape ladder. Post signs indicating the hazards near the barricade. If the required slope in not possible, provide shoring on both side of the trench. Only hand excavation is allowed within the utilities. All existing underground utilities shall be protected by approved temporary supports using fabricated frames, steel columns or concrete blocks depending on the site requirements and their loads. 5.3.2 5.3.3 5.3.4 5.3.5 5.3.6 5.3.7 6 Lifting of pipes and other materials by use of Crane, Boom truck, Forklift. (PS/CSF/CSS/M001) Petro Rabigh Construction Safety Manual 6.1 Unauthorized Personnel Entry to the working area. Low 6.1.1 6.1.2 6.1.3 6.1.4 6.1.5 6.1.6 Ensure to obtain lifting permit approval prior to start of lifting activities. Crane working area and other material stock to be isolated by installing barricade with proper signage. HSE officer shall be in the working area at all times. Access point and other working area shall be isolated with barricade with proper signage. GS trained flagman shall be assigned for the equipment’s in the working area and to control the traffic flow. Equipment shall be certified by PRC or by approved third party. GS/ Raymond - Area Supervisor - Foreman - Equipment Operator/ Driver - All concerned people 6.1.7 Driver or Operator shall have a valid Saudi driver’s license and had undergo PRC driver’s improvement program (DIP). 6.1.8 Driver/Operator shall check first the possible route and familiarize the road and identify the difficulties in driving. 6.1.9 Operator shall be familiar of the equipment he operates. 6.1.10 All personnel that are not directly involve for the job shall be instructed to keep away from the offloading area. 7 Cutting of Existing Pipe (14” FW line) 6.2 Fault in lifting gear 6.2.1 All lifting tools/gears(hook, shackles, slings, wire) shall be inspected and approved by GS assigned inspector and PRC inspector. 6.3 Unsafe operation of Crane and other equipment (ie, boom truck, trailer, etc.) 6.3.1 Outriggers have to be extended, fixed on the ground with proper supporting plates and shall be installed at least more than 3m from the crane. Crane operators and riggers must have a valid certificate issued by third party approved by PRC or PRC certificate. 7.1 Pressurized line 6.3.2 6.3.3 6.3.4 Use of softener around sharp objects. Operator/Driver of the equipment shall check and inspect the equipment or vehicle using the equipment or vehicle daily checklist. Any found problems shall report to Company’s maintenance department. Equipment will not be used until the problems are fixed. 7.1.1 Cutting of existing pipe shall commence after obtaining clearance and approval from PRC. Isolation and depressurization of existing line shall be performed by PRC. 7.1.2 GS/ Raymond - Area Supervisor - Foreman 7.1.3 7.1.4 7.1.5 7.1.6 7.1.7 7.1.8 8 Welding works (Flange installation to existing line) 8.1 8.1.1 8.1.2 8.1.3 8.1.4 9 9.1 Shortage of oxygen Installation and inside the excavation grinding of pipes in pit. confined space Low After line depressurization, remaining draining works will be executed by GS. Water from existing line will be discharge to the evaporation pond situated along Road 28. Pipe shall be cut using electric grinder utilizing cutting disc. Above electrical cutting works shall be followed after checking trench condition using gas detector and it shall be confirmed by PRC. Personnel doing the cutting shall be provided with appropriate protection. Fire extinguisher shall be kept during work for cutting of existing pipe. Welding works shall commence after ensuring that pipeline is totally dried out. If some leakage or drippings noted, PRC shall find ways and means to isolate the line. Welding area shall be isolated and barricaded. Trained fire watch man shall be provided to the welding area. 8.1.5 Fire extinguisher shall be kept during welding works. 9.1.1 Confined space entry permit shall be secured and a standby man shall be assigned prior to start of work. An entry/exit logsheet shall be maintained for the entire work duration. Gas testing shall be done by the authorized gas tester prior to start of work and shall be continuously monitored. Trained standby man shall be placed on the access and on the opening of the pipe with log- 9.1.2 9.1.3 - Standby Man - Gas Tester - All concerned people GS/ Raymond GS/ Raymond - Area Supervisor - Foreman - Standby Man - Gas Tester - All in/out. 9.2 Suffocation, throat irritation, gastrointestinal tract and respiratory damage from inhalation/ingestion of RTR dust. Low 9.3 Skin allergy, dermatitis, and other skin diseases from contact with RTR dust. Low 9.2.1 9.2.2 9.2.3 9.2.4 9.3.1 9.3.2 9.3.3 10 Bonding /Lamination of joints 10.1 Mixed chemicals come in contact with skin, eyes, or ingested dust being inhaled. Low concerned people Authorized entrants shall have training in confined space entry. An approved disposable dust respirator shall be used. (Respirator type P1). Blowers shall be provided to drive away the dust from the person doing the pipe grinding. In case of inhalation, bring the personnel to an open space away from the work area to regain normal breathing pattern. Washing facilities shall be provided in working area. If in contact with dust, personnel shall wash the affected area. Eye protection shall be worn by wearing goggles with side protection and face shield. Eyewash shall be provided in site. 10.1.1 An approved disposable dust respirator shall be used. 10.1.2 Rubber gloves shall be worn when handling such chemicals. 10.1.3 Only competent person will the do the substance mixing. 10.1.4 Mixing area should be well ventilated to remove air borne substance. 10.1.5 Provide appropriate information, instruction and training to the assigned crew. 10.1.6 Refer to MSDS for the first aid instruction. GS/ Raymond - Area Supervisor - Foreman - Standby Man - Laminator 11 Backfilling 11.1 Cave – engulfment or collapse of disposal soil. Low 11.1.1 Equipment used to backfill excavated trench will carry current certification and will be maintained is a safe condition. 11.1.2 Trained and authorized operator shall be certified by Company. 11.1.3 Trained flagman shall be used to control the backfilling operation in order to prevent or warn the machinery from working too close to the excavation edge. 11.1.4 Unauthorized personnel should be removed from the areas where the backfilling works is taking place. 11.1.5 Stripped topsoil intended for reuse as agreed with the Company shall be stockpiled and/or spread at approved locations. The remaining topsoil shall be disposed at the designated location. 11.1.6 Maintain safe distance of the equipment while dumping. GS/ Raymond - Area Supervisor - Foreman - Equipment Operator/ Driver - All concerned people 12 General 12.1 Unauthorized access Low 12.1.1 Good supervision 12.1.2 Use correct tools for the job. 12.1.3 Unauthorized person should not use plant or equipment. 12.2 Smoking anywhere Low 12.2.1 Do not smoke near the plant and equipment or in area where flammable materials are stored or are in use. GS/ Raymond - WPR - Safety Officer - Supervisor - Foreman 12.3 Not provided with welfare facilities Low 12.3.1 Do not horseplay at the site. 12.3.2 Do not shortcut for access or egress. 12.3.3 Severe disciplinary action should be taken against any safety violations. 12.3.4 Rest shelter and toilet to be provided at designated area, together with drinking water. 12.3.5 Emergency number to be posted on site. In case of Emergency Unplanned emergency Plan & implementation How to Report Emergencies Petro Rabigh Telephone – Call 911 Outside phone or mobile phone – Call 012-425-0911 Say, “This is an emergency!” Describe the incident location (grid location: D2-054) Describe the incident Report injuries, if any Give your name and badge number Repeat the above information Stay on the line until further instructed JSA Team Members: Name Department PRC FSSD (PRC HSE) U & OM, HCTF (PRC Issuer) CP3 & 4 PMT / HSE Yahya H. Farsi Sign GSCA HSE Hyang Gon Lee Subcontractor HSE IMPORTANT: This JSA must be available at the place where the activity is being performed and all personnel involved must be informed of the hazards associated with the activities and the control measures to eliminate or minimize the hazards. This JSA must be reviewed if the scope of work changes or if any other major contingency occur. In case the plant emergency alarm is sounded, all work must be stopped, all permits will become automatically cancelled and Emergency Response Plan to be followed. Ensure the availability of contractor Supervisor during the activity, continuously