RBHraCaNacRkkm<úCa RksYgsaFarNkar nig dWkCBa¢Ún bTdæan sikSaKMerag pøÚvfñl; ROAD DESIGN STANDARD PART 2. PAVEMENT CAM PW.03.102.99 2003 This document has been produced for the Kingdom of Cambodia as a joint Australia – Cambodia project sponsored by the Australian Agency for International Development (AusAID). Valuable assistance and operational advice was provided by the staff of the Cambodian Ministry of Public Works and Transport (MPWT) as follow: I. Steering Committee (Appendix H) 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Mr. Tan Hay Sien, Director of Infrastructure Department ............................................ Chairman Dr. Yit Bunna, Director of Public Works Research Centre ........................Deputy Chairman Mr. Tauch Chan Kosal, Director of Heavy Equipment Centre ............................................... Member Mr. Lim Sidenine, Deputy Director of Bridge Construction Unit.................................... Member Dr. Phung Katry, Director of Waterway Department ................................................... Member Mr. Prum Sakun, Deputy Director of Cambodian Royal Railway ................................ Member Representative from Sihanouk Ville Port (Mr. Ma Sun Huot)................................................... Member Representative from Public Works Laboratory (Mr. Keo Leap)................................................ Member Representative from Phnom Penh Institute of Technology (Mr. Chhouk Chhay Horng) ......... Member Representative from Phnom Penh Public Works Department (Mr. Heng Nguon) ................... Member Representative from Ministry of Water Resources and Meteorology....................................... Member II. Assistance Preparation Staff from Public Works Research Centre: 1. 2. 3. 4. Mr. Nou Vaddhanak Mr. Kong Sophal Mr. Chan Somardy Mr. Tep Virith Technical research and specialist input was provided by the Australian consulting firms of McMillan Britton & Kell Pty Limited and Willing & Partners Pty Ltd. Reproduction of extracts from this publication may be made subject to due acknowledgment of the source. Although this publication is believed to be correct at the time of printing, neither the MPWT nor AusAID accept responsibility for any consequences arising from the use of the information contained in it. People using the information should apply, and rely upon, their own skill and judgement to the particular issue which they are considering. SECOND PRINTING FINANCED BY THE ASIAN DEVELOPMENT BANK LOAN NO. 1659 CAM (SF) ROAD DESIGN STANDARD FOREWORD The Cambodia Road Design Standard is intended to be used for the design of all new roads in the Kingdom of Cambodia. The Cambodian Road Design Standard consists of the following complementary documents which shall be considered together: - CAM PW 03-101-99 Road Design Standard – Part 1 - Geometry; - CAM PW 03-102-99 Road Design Standard – Part 2 - Pavement; - CAM PW 03-103-99 Road Design Standard – Part 3 - Drainage; For the purpose of regulating and interpreting the provisions of this Standard, the AUTHORITY shall be the Cambodian Ministry of Public Works and Transport. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 FOREWORD ROAD DESIGN STANDARD TABLE OF CONTENTS 2.1 INTRODUCTION .................................................................................. 5 2.2 PAVEMENT DESIGN SYSTEM ........................................................... 6 2.2.1 General ................................................................................................ 6 2.2.2 Pavement Design System For New Pavements .............................. 6 2.2.2.1 Input Variables...................................................................................... 7 2.2.2.2 Selecting a Trial Pavement Cross -Section .......................................... 8 2.2.3 Design System For Pavement Overlays........................................... 8 2.2.3.1 General ................................................................................................. 8 2.2.3.2 Evaluating the Existing Pavement ........................................................ 9 2.2.3.3 Recognition of the Existing Pavement's Needs.................................. 10 2.2.3.4 Selection of Overlay Thickness .......................................................... 10 2.3 ENVIRONMENT ................................................................................. 12 2.3.1 General .............................................................................................. 12 2.3.2 Moisture Environment...................................................................... 12 2.3.3 Temperature Environment ............................................................... 14 2.4 SUBGRADE EVALUATION............................................................... 16 2.4.1 General .............................................................................................. 16 2.4.2 Measures Of Subgrade Support...................................................... 16 2.4.3 Factors To Be Considered In Estimating Subgrade Support....... 16 2.4.4 Methods Of Estimating Subgrade Support Values ....................... 18 2.4.5 Field Determination Of Subgrade CBR........................................... 18 2.4.5.1 In-situ CBR Test ................................................................................. 18 2.4.5.2 Cone Penetrometers........................................................................... 18 2.4.6 Laboratory Determination Of Subgrade CBR And Elastic Parameters............................................................................ 19 2.4.6.1 Determination of Density for Laboratory Test..................................... 20 2.4.6.2 Determination of Design Moisture Content (DMC)............................. 20 2.4.7 Adoption Of Presumptive CBR Values........................................... 20 2.5 TRAFFIC INVESTIGATION ............................................................... 21 2.5.1 Estimating Flows .............................................................................. 21 2.5.1.1 Baseline traffic flows ........................................................................... 21 2.5.1.2 Traffic Forecasting .............................................................................. 22 2.5.2 Axle Loading ..................................................................................... 24 2.5.2.1 Axle load surveys................................................................................ 24 2.5.2.2 Axle Configurations and Equivalences ............................................... 24 2.5.2.3 Design Lanes...................................................................................... 25 1-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 TABLE OF CONTENTS ROAD DESIGN STANDARD 2.5.3 Design Period.................................................................................... 25 2.5.4 Traffic Growth ................................................................................... 26 2.5.5 Design Traffic For Flexible Pavement ............................................ 26 2.5.6 Design Traffic For Rigid Pavements............................................... 26 2.6 PAVEMENT MATERIALS.................................................................. 28 2.6.1 Granular Materials ............................................................................ 28 2.6.1.1 Introduction ......................................................................................... 28 2.6.2 Modified Materials ............................................................................ 28 2.6.3 Bitumen ............................................................................................. 29 2.6.3.1 Prime Coat.......................................................................................... 29 2.6.3.2 Tack Coat ........................................................................................... 29 2.6.3.3 Bituminous Surface treatment ............................................................ 29 2.6.3.3.1 Bituminous materials .......................................................................... 29 2.6.3.3.2 Aggregates ......................................................................................... 30 2.6.3.4 Asphaltic Concrete.............................................................................. 31 2.6.4 Concrete ............................................................................................ 32 2.6.4.1 Introduction ......................................................................................... 32 2.6.4.2 Sub-base Concrete............................................................................. 32 2.6.4.3 Base Concrete .................................................................................... 32 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS..................................... 34 2.8 DESIGN OF RIGID PAVEMENTS ..................................................... 43 2.8.1 General .............................................................................................. 43 2.8.2 Pavement Types ............................................................................... 43 2.8.2.1 Cement Concrete Pavements ............................................................ 43 2.8.2.2 Asphalt Surfaced Rigid Pavements .................................................... 44 2.8.3 Factors Used In Thickness Determination..................................... 44 2.8.3.1 Strength of Subgrade.......................................................................... 44 2.8.3.2 Concrete Strength............................................................................... 44 2.8.3.3 Design Traffic...................................................................................... 44 2.8.3.4 Provision of Sub-base......................................................................... 44 2.8.3.4.1 General ............................................................................................... 44 2.8.3.4.2 Bound Sub-base ................................................................................. 46 2.8.3.4.3 Lean Rolled Concrete Sub-base ........................................................ 46 2.8.3.4.4 Lean-Mix Concrete Sub-base............................................................. 46 2.8.3.4.5 Debonding of the Sub-base and Base................................................ 46 2.8.3.5 Concrete Shoulders ............................................................................ 47 2.8.3.6 Load Safety Factors............................................................................ 47 2.8.4 Base Thickness Design Procedure................................................. 47 2.8.4.1 General ............................................................................................... 47 2.8.4.2 Base Thickness Design Procedure .................................................... 47 2.8.4.3 Minimum Base Thickness................................................................... 61 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 TABLE OF CONTENTS 2-97 ROAD DESIGN STANDARD 2.8.4.4 2.8.5 Provision of Dowels and Tie Bars....................................................... 61 Reinforcement Design Procedures................................................. 62 2.8.5.1 Special Requirements for Reinforcement In Jointed ............................. Unreinforced Pavements .................................................................... 62 2.8.5.2 Reinforcement In Jointed Reinforced Pavements .............................. 62 2.8.5.3 Reinforcement In Continuously Reinforced Pavements..................... 63 2.9 OVERLAY DESIGN............................................................................ 68 2.9.1 General .............................................................................................. 68 2.9.2 Basic Principles ................................................................................ 68 2.9.3 Pavement Testing ............................................................................. 68 2.9.3.1 Method of Deflection Testing.............................................................. 68 2.9.3.2 Selection of Test Sites ........................................................................ 68 2.9.3.3 Test Modes ......................................................................................... 69 2.9.3.4 Other Tests ......................................................................................... 70 2.9.3.5 Measurement of Pavement Temperature........................................... 70 2.9.4 Pavement Evaluation........................................................................ 70 2.9.4.1 Selection of Homogeneous Sections.................................................. 70 2.9.4.2 Characteristic Site Temperature......................................................... 71 2.9.4.3 Adjustment of the Characteristic Deflection and Characteristic ............ Curvature to Account for the Testing Temperature ............................ 71 2.9.4.4 Adjustment of Deflection Data to Account for Seasonal Moisture Variations ............................................................................. 72 2.9.4.5 Design Traffic...................................................................................... 72 2.9.4.6 Performance Criteria (Design Deflection and Curvature)................... 73 2.9.4.7 Determination of Pavement Needs..................................................... 73 2.9.5 Selection Of Thickness .................................................................... 75 2.9.5.1 Granular Overlays............................................................................... 75 2.9.5.2 Asphalt Overlays................................................................................. 75 2.9.5.3 Characteristic Deflection (adjusted for temperature) Exceeds the Design Deflection.......................................................................... 75 2.9.5.4 Characteristic Deflection (adjusted for temperature) Less Than Design Deflection................................................................................ 78 2.9.5.5 Adjustment of Overlay Thickness to Allow for Locality Temperature . 78 2.9.5.6 Example of Asphalt Overlay Design ................................................... 79 3-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 TABLE OF CONTENTS ROAD DESIGN STANDARD APPENDIX A ............................................................................................................ 81 APPENDIX B ............................................................................................................ 83 APPENDIX C ............................................................................................................ 84 APPENDIX D ............................................................................................................ 85 APPENDIX E ............................................................................................................ 89 APPENDIX F ............................................................................................................ 90 APPENDIX F ............................................................................................................ 91 APPENDIX F ............................................................................................................ 92 APPENDIX F ............................................................................................................ 93 APPENDIX G ............................................................................................................ 94 APPENDIX H ............................................................................................................ 96 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 TABLE OF CONTENTS 4-97 ROAD DESIGN STANDARD 2.1 INTRODUCTION This Standard contains procedures for the design of the following forms of road pavement construction, • Flexible pavements consisting of unbound granular material. • Rigid pavements ( ie cement concrete pavements) • Overlays for flexible pavements. The procedures in this Standard are intended for the design of pavements whose primary distress mode is load associated. Where other modes of distress, such as environmental distress, have a significant effect on environmental performance, their effect will have to be separately assessed. It is assumed that pavements are constructed in compliance with modern quality control standards. Consideration of unsurfaced pavements has not been included in this Standard because the performance of these pavements is heavily dependent on the performance of local materials, local environmental conditions and maintenance policies. Consideration of overlays for rigid pavements has also been omitted because experience in this area has not been sufficiently extensive to allow formulation of a design procedure. This Standard contains detailed discussion of subgrade evaluation, pavement materials evaluation, analysis of traffic loading and structural design in addition to other factors relevant to pavement design. It is emphasised that this document should be used as a guide and not approached or referred to as a limiting design specification. Some judgement will have to be exercised by the designer in arriving at decisions as the parameters which are incorporated in particular designs. 5-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.1 INTRODUCTION ROAD DESIGN STANDARD 2.2 PAVEMENT DESIGN SYSTEM 2.2.1 GENERAL The aim of pavement design is to select the most economic pavement thickness and composition that will provide a satisfactory level of service for the anticipated traffic. To achieve this goal, the designer must have sufficient knowledge of the materials, the traffic, the local environment and their interactions to be able to predict the performance of any pavement composition. In addition he must know what level of performance, and what pavement condition will be considered satisfactory in the circumstances for which he is designing the pavement structure. Figure 2.2.1 System for the Design of Pavements Because of the many variables and interactions which influence the result, it is appropriate to adopt a systematic approach to pavement design. Depending on the amount of data which has to be provided, or conversely on the number of assumptions that have to be made, a pavement design procedure may be complex at one extreme or very simple at the other. Design procedures contained in this Standard are based on two similar design systems which are described in this Section. One system is for the design of new pavements and the other is more specifically for the design of overlays to rehabilitate existing flexible pavements. However, both are based on the same underlying principles that are typical of those used to solve any engineering design problem. 2.2.2 PAVEMENT DESIGN SYSTEM FOR NEW PAVEMENTS The system for the design of pavements is shown in flow chart form in Figure 2.2.1. Although in a practical design procedure some of the parts of the system may be omitted or combined with others, it is convenient to use Figure 2.2.1 to demonstrate the relationships between input variables, analytical methods and the decision processes which comprise pavement design. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.2 PAVEMENT DESIGN SYSTEM 6-97 ROAD DESIGN STANDARD 2.2.2.1 Input Variables (a) Design Traffic Axle numbers, load distribution, loading rate and tyre pressures can be significant in determining pavement performance. Not only must the current traffic be taken into account, but the change in volume and composition during the design period must also be estimated. Detailed consideration of traffic is contained in Section 2.5. (b) Subgrade and Pavement Materials Ideally the designer's knowledge of the pavement and subgrade materials should include the strength/stiffness parameters which can be used to quantify their load bearing properties the variations in these parameters which result from changes in moisture and temperature, increases in age, or cumulative distress during the design period the manner in which they deteriorate and the significant reaction to load (stress or strain) which can be used to quantify the rate of distress (refer to Table 2.2.1) the limiting value(s) of stresses or strains at which a given degree of distress will occur, commonly known as the performance criteria. Table 2.2.1 Distress modes for flexible pavements Distress Mode Rutting Likely Causes Densification Materials Affected All but sound cemented material Cracking Single high load, many repetitions of normal loads, thermal cycling, shrinkage Asphalt, cemented material Roughness Variability of density, material properties All Some of the above apply to the analysis phase of the design system. For example, parameters such as elastic stiffness are used in analytical models to determine load induced stresses and strains. The performance criteria on the other hand are used only to predict when distress will occur. Some analytical models have been developed in recent times that predict the development of roughness from a knowledge of the variability of material properties and layer thickness, among other things. Some materials such as asphalt and cemented gravels are complex to the extent that their performance criteria are a function of their stiffness. These relationships enable materials design to be incorporated into the overall pavement design system, as for example the design of a concrete mix is incorporated into the design of a concrete bridge beam. A detailed consideration of subgrades and pavement materials is contained in Sections 2.4 and 2.6 respectively. (c) Environment Variations in material properties due to changes in moisture and temperature may be measured by testing. The values to be used in analysis will depend on the actual moisture and temperature existing in service. Because of the complexity associated with this 7-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.2 PAVEMENT DESIGN SYSTEM ROAD DESIGN STANDARD requirement it is usually necessary to characterise a particular site environment to some extent. The significance of environmental effects depends on the materials that are selected for the pavement, but it can also depend on the temporal distribution of traffic loading. A detailed consideration of environmental effects is contained in Section 2.3. (d) Construction and Maintenance Considerations Construction and, to a lesser extent, maintenance policies can influence the type of pavement structure which is adopted. In addition, the properties of many materials are dependent on construction influences, including the level of compaction, the method of curing concrete or cemented materials, the type of equipment used for placing crushed rock, and the extent of sub-surface drainage incorporated in the design. 2.2.2.2 Selecting a Trial Pavement Cross -Section The design process consists of selection of a trial pavement cross-section and analysing its performance when subjected to the input design parameters that are described in Section 2.2.1. A trial pavement cross-section may often be selected by judgement or by using a simple published design procedure. Many such procedures are empirical. Therefore, if one is used, it is desirable that it has been derived from experience and observations that are compatible with the design task at hand. If such a simple design procedure is assumed to be sufficiently reliable for the designer's needs, the design process is complete, since the following phases (analysis, distress prediction and design modification) are all considered to be taken care of. The example design charts in Section 2.7 of this Standard have been derived from the design system, but in each case for a specific set of input parameters. These parameters are listed on or adjacent to each chart. 2.2.3 DESIGN SYSTEM FOR PAVEMENT OVERLAYS 2.2.3.1 General The System for the design of pavement overlays is shown in flow chart form in Figure 2.2.2. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.2 PAVEMENT DESIGN SYSTEM 8-97 ROAD DESIGN STANDARD Figure 2.2.2 System for the Design of Pavement Overlays In principle there is little difference between the design of overlays and the design of new pavements, since each involves consideration of traffic, material and environment, an analysis, distress prediction and comparison of alternative designs. In practical terms the major difference is that for overlay design to be successful the needs of the existing pavement must be correctly diagnosed and then satisfied. In broad terms the overlay design system comprises: 2.2.3.2 • Evaluating the existing pavement condition. • Considering the traffic and environment to which it will be subjected in the design period. • Determining if the pavement needs additional strength to provide satisfactory service during the design period, and if possible the causes(s) of deficiencies. • Considering the materials which are available to overcome the pavement’s deficiencies, their potential modes of failure , their load resisting capabilities and the parameters which can be used to predict the rate at which distress will occur in the overlaid pavement. • Determining the thickness of material that must be placed on the existing pavement to provide satisfactory service in the design period. Evaluating the Existing Pavement This may be done by sampling and testing the existing pavement materials and the subgrade, and assigning strength parameters so that the structure can be analysed to determine its reaction to load. Alternatively, a non-destructive method such as deflection testing can be used to obtain the reaction to load directly. The method of analysing deflection testing can vary depending on the amount and type of data that is collected during the deflection survey. As more comprehensive data can be collected with recently developed equipment, such as the Deflectograph, Falling Weight Deflectometer and Benkelman Beams adapted to measure complete deflection bowls, better predictions can be made of the performance of the existing pavement. 9-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.2 PAVEMENT DESIGN SYSTEM ROAD DESIGN STANDARD The deflection testing and analysis method, which has been adopted in this Standard, is described in detail in Section 2.9. Its aim is to predict the future traffic loading which the pavement can support before permanent deformation reaches a tolerable limit, and also, for pavements which have uncracked asphalt surfacing, the traffic loading which can be supported before fatigue cracking occurs. These predictions take into account the pavement's temperature and subgrade moisture at the time of testing, and the environmental conditions which will apply during the pavement's service life. 2.2.3.3 Recognition of the Existing Pavement's Needs With experience, the needs of an existing pavement can often be recognised by inspection alone. Further information can be obtained by testing, the more detailed and comprehensive the tests then the more reliable will be the identification of pavement deficiencies and needs. Tests that directly measure a pavement's reaction to load, such as deflection tests, should be used where possible. This is preferable to a mere comparison of the pavement composition with that prescribed by empirical pavement design procedures since the latter tend to apply only to pavements of "average" quality. The measurements obtained by deflection testing, whether they be the maximum deflection at each test site or additional parameters which describe the shape of the deflected pavement surface, can be related to performance criteria. These performance criteria are usually empirically based but may also be based on the theoretical data obtained from, for example, a mathematical solution of elastic layered models. In practice there will be some variability in deflection test results throughout a given length of pavement, reflecting the variability in the many factors which contribute to pavement performance. By adopting a statistical approach, characteristic deflection values can be assigned to the section of pavement. This implies the acceptance of a probability that the performance of the ultimate overlay design will be acceptable. The most common performance criteria relate deflection under a standard load to the number of repetitions, which can be tolerated before a critical pavement condition, is reached. This is a very simplistic relationship, which assumes that the compound effect of all forms of distress in a particular type of pavement can be predicted by the measurement of only one reaction to load. More recently developed deflection testing and analysis methods tend to isolate different distress modes, with the rate of distress in each case being predicted by a different property of the deflected pavement shape with its own limiting criterion. If the deflection measurements (or derived measures in the case of the more sophisticated methods) exceed the limiting values given by the performance criteria, then the existing pavement is assumed to be inadequate for the design traffic and some treatment is required. This may include strengthening by the addition of a granular or asphalt overlay or by reconstruction, but other measures such as additional drainage works or resealing may also be effective. 2.2.3.4 Selection of Overlay Thickness The thickness of overlay which is needed to strengthen the pavement depends on : • the material to be used • the increase in strength which is required to reduce the pavement's response to load to tolerable limits as defined by the performance criteria • the amount of auxiliary work such as drainage improvement which is proposed in conjunction with the overlay ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.2 PAVEMENT DESIGN SYSTEM 10-97 ROAD DESIGN STANDARD The required thickness can be determined from empirical relationships based on observations of the effect of previous overlays. Mathematical predictions have also been made using typical material stiffnesses. Even so the effect of any proposed drainage improvements must be estimated, either by judgement based on experience or by analysis assuming certain changes will be achieved in the pavement and the subgrade because of the drainage works. When more than one performance criterion has been used to evaluate the existing pavement's needs and/or to select an overlay thickness, the controlling value will be the minimum thickness which satisfies all of the criteria. If it is considered impractical to apply the specified thickness (for example due to adjacent level controls), then a lesser amount may have to be adopted. By comparing the estimated effect of the thinner overlay with the limiting criteria, a prediction of the pavement's performance can be made. The value of the overlay can then be compared with the anticipated benefits and a decision made regarding its acceptability. For example, if the practical overlay may only last for one or two years it may be more cost effective to reconstruct the pavement. The pavement evaluation and overlay design methods which have been adopted in this Standard are described in detail in Section 2.9. 11-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.2 PAVEMENT DESIGN SYSTEM ROAD DESIGN STANDARD 2.3 ENVIRONMENT 2.3.1 GENERAL This Standard mainly describes procedures to enable pavements to be designed to withstand load-associated distress. While environmentally induced distress is mentioned in a number of passages, pavements where this is the major distress mode are not specifically discussed. The environmental factors, which significantly affect pavement performance, are: 2.3.2 • Moisture • Temperature MOISTURE ENVIRONMENT The moisture regime associated with a pavement has a major influence on the performance of the pavement. The stiffness/strength of unbound materials and subgrades is heavily dependent on the moisture content of the materials. Further guidance may be obtained in NAASRA (1983). The factors that must be assessed at the design stage include: • Rainfall/evaporation pattern • Permeability of wearing surface • Depth of water table • Relative permeability of pavement layers • Whether shoulders are sealed or not • Pavement type (boxed or full width) Moisture changes in pavements usually result from one or more of the following sources: (a) Seepage from higher ground to the road pavement (b) Fluctuations in the water table. (c) Infiltration of water through the surface of the road pavement and shoulders. (d) Transfer of moisture as a result of moisture content or temperature differences in either the liquid or vapour states, including transfer due to the moisture content at construction differing from the equilibrium moisture content. (e) The relative permeabilities of the pavement layers and subgrade. A significant decrease in permeability with depth (permeability reversal) can lead to saturation of the materials in the vicinity of the permeability reversal. Of the above sources only (a), (b) and (c) can be controlled by the installation of properly designed subgrade and pavement drains. Drains are only effective when subgrade moisture is subject to hydrostatic head (ie positive pore pressures). It is common for fine grained subgrade materials to have an equilibrium moisture content above optimum moisture content yet, because they are unsaturated, they cannot be drained. The above sources of moisture infiltration are illustrated in Figure 2.3.1. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.3 ENVIRONMENT 12-97 ROAD DESIGN STANDARD An alteration of the moisture content of the subgrade can result in two types of changes to its condition; a change in the volume and/or a change in strength. The significance of these changes will depend on their magnitude and the nature of the material in which the change takes place. Particular problems associated with expansive clays are given in references at the end of this Section. The effect of changes in moisture content on the strength / stiffness of the subgrade is taken into consideration by evaluating the strength parameters (eg CBR, modulus) at the highest moisture content likely to occur during the design period. It is important that as accurate an estimate as practicable be made for the design moisture content. Figure 2.3.1 Movement of Moisture in Road Pavements The sensitivity of the subgrade strength/stiffness to changes in moisture content should in all cases be assessed. In general the following comments apply: • For sandy soils, small fluctuations in moisture content produce little change in volume or strength/ stiffness. • For silty soils, small fluctuations in moisture content produce little change in volume but may produce large changes in strength and/or stiffness. • For clay, small fluctuations in moisture may produce large variations in volume and if the moisture content is near optimum moisture content large changes in strength/stiffness may also occur. Volume changes are minimised if the required density of the subgrade is obtained by compaction at a moisture content representing the value, which occurs most frequently. The moisture content that is used to compact the soil initially may also influence the extent of volume change. Estimation of both the design moisture content and the moisture content of minimum volume change is usually based on the use of the Equilibrium Moisture Content (EMC) concept where this is considered applicable. 13-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.3 ENVIRONMENT ROAD DESIGN STANDARD Equilibrium Moisture Content (EMC) The term Equilibrium Moisture Content refers to the concept that, in some situations, the moisture conditions under a sealed pavement reach a state of equilibrium with the moisture regime of the local environment at sometime after construction. The principal variables which control its state are: • Climate • Soil type • Depth to water table • Composition of the soil water In treating soil water as a variable in the behaviour of unsaturated soil there are basically only two ways of quantitatively expressing the soil water variable. These are: • In terms of the ratio of the soil water to another volumetric or gravimetric property of the soil (eg gravimetric moisture content) • In terms of the energy state of the soil water, such as soil moisture suction. Soil moisture suction is used here in the common context of negative pore pressures (matrix potential). However, "suction" is sometimes used in the context of total potential, when the osmotic (solute) potential of the soil is added to the matrix potential. For practical purposes, the condition at which soil strength is to be determined must finally be expressed in terms of (gravimetric) moisture content. If soil moisture content has been expressed in terms of soil suction, a conversion to moisture content is necessary to use EMC. However, since the measurement and monitoring of soil suction in the field and the determination of the relationship between soil suction and moisture content is difficult and not in general use, such methods are not described here. Some references are NAASRA (1974, 1983), OECD (1973). Richards (1969), Wallace (1974) and Waters and Kapitzke (1974). The conditions which leads to EMC are generally more stable towards the central portion of the pavement. Up to about 1.5 metres from each edge, fluctuations in moisture conditions can result from the relatively rapid changes in moisture content that can occur in the shoulder. These changes can cause the critical moisture content (ie Design Moisture Content) for the outer wheel path to be above the EMC estimated for the central portion of the pavement. In situations where changes in moisture content of the shoulders can be large, treatment of these areas should be undertaken to minimise this difference. Where such treatment is not applied or is not likely to be adequate, it will be necessary to adopt a design moisture content (DMC) more than the EMC for the centre portion of the pavement. Procedures for determining DMC are given in Section 2.4. 2.3.3 TEMPERATURE ENVIRONMENT The temperature environment has a major influence on the performance of pavements surfaced with asphalt wearing surfaces. Asphalt becomes stiff and brittle at low temperatures while it is soft and visco-elastic at higher temperatures. Permanent deformation in asphalt at high temperatures is not considered as a failure mode in this Standard. The only failure mode considered for asphalt ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.3 ENVIRONMENT 14-97 ROAD DESIGN STANDARD is flexural (fatigue) cracking. It is assumed that asphalt mixes are designed with sufficient stability so that permanent deformation does not need to be considered at the design stage. The distribution of temperature both on a daily and seasonal basis has an important bearing on pavement performance. If traffic loading occurs at night when temperatures are low, a considerable reduction in the life of thin asphalt surfacing may occur. The interaction of the traffic and temperature ranges must therefore be taken into account at the design stage. A procedure for doing this is presented in Section 2.6. Temperature may also affect the properties and performance of cemented layers and concrete. Temperatures can have a significant effect on the rate of strength gain of these materials and if high temperatures occur during construction, drying out will result, impairing both the ultimate strength and fatigue characteristics of the materials. 15-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.3 ENVIRONMENT ROAD DESIGN STANDARD 2.4 SUBGRADE EVALUATION 2.4.1 GENERAL The support provided by the subgrade is the most important factor in determining pavement design thickness, composition and performance. The subgrade strength is dependent on the conditions at construction and during service. Soil type, density and moisture content largely determine subgrade strength. The aim of subgrade evaluation is to estimate a value of subgrade support to use in design. 2.4.2 MEASURES OF SUBGRADE SUPPORT The measures of subgrade support used in this Standard are: • California Bearing Ratio (CBR) • Modulus of Subgrade Reaction (k) The use of these measures for designing various pavement types is given in Table 2.4.1. 2.4.3 FACTORS TO BE CONSIDERED IN ESTIMATING SUBGRADE SUPPORT The following factors must be considered in determining the design strength/stiffness of the subgrade: • sequence of earthworks construction; • the compaction moisture content used and field density achieved; • moisture changes during service life; • subgrade variability. The total pavement thickness may be governed by the presence of weak layers below the design subgrade level. Table 2.4.1 Use Of Subgrade Support Measures Measure of Subgrade Support Pavement Type Use CBR Flexible OK Rigid OK (a) Use k OK Sequence of Earthworks Construction In some cases it may be possible to select materials that will ultimately be located at the subgrade level by involvement in pre-construction planning. Where there is uncertainty as to which material will be available for use as a subgrade, a preliminary evaluation of material may be necessary with confirmation at the time of construction ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.4 SUBGRADE EVALUATION 16-97 ROAD DESIGN STANDARD (b) Compaction Moisture Content Used and Field Density Achieved A guide to the effects of variations in relative density and compaction moisture contents on subgrade is illustrated in Table 2.4.2 , Table 2.4.3 , and Table 2.4.4. Table 2.4.2 Relative Values Of Subgrade Support For Clay (PI>30) Density 1.05 MDD 1.00 MDD 0.95 MDD UNSOAKED Compaction Moisture Content (relative to OMC) 0.9 1.0 1.05 4.0 3.5 3.0 3.5 3.0 2.5 2.5 2.0 2.0 Density prior to 4 day soak 1.05 MDD 1.00 MDD 0.95 MDD 4 DAY SOAK Compaction Moisture Content (relative to OMC) 0.9 1.0 1.05 0.9 0.6 1.0 1.5 0.4 0.6 1.0 Table 2.4.3 Relative Values Of Subgrade Support For Clay (PI<30) Density 1.05 MDD 1.00 MDD 0.95 MDD UNSOAKED Compaction Moisture Content (relative to OMC) 0.9 1.0 1.05 2.0 1.8 1.2 1.0 1.2 1.0 1.0 Density prior to 4 day soak 1.05 MDD 1.00 MDD 0.95 MDD 4 DAY SOAK Compaction Moisture Content (relative to OMC) 0.9 1.0 1.05 1.2 2.0 2.2 0.8 1.0 1.1 0.5 0.5 0.6 Table 2.4.4 Relative Values Of Subgrade Support For Silty Sand Density 1.05 MDD 1.00 MDD 0.95 MDD (c) UNSOAKED Compaction Moisture Content (relative to OMC) 0.9 1.0 1.05 2.0 1.8 1.2 1.0 1.2 1.0 1.0 Density prior to 4 day soak 1.05 MDD 1.00 MDD 0.95 MDD 4 DAY SOAK Compaction Moisture Content (relative to OMC) 0.9 1.0 1.05 1.2 2.0 2.2 0.8 1.0 1.1 0.5 0.5 0.6 Moisture Changes during Service Life After construction, moisture conditions in subgrades will change subject to the influences outlined in Section 2.3. Table 2.4.2 , Table 2.4.3 , and Table 2.4.4 contain a guide to the magnitude of change in subgrade support, which can occur due to in-service moisture variations. Moisture changes may occur on a seasonal, and perhaps also on a sporadic, basis if the subgrade is subject to flooding. These variations, where possible, should be taken into account. (d) Subgrade Variability Subgrades are inherently variable in nature and the design value for subgrade support should be selected to reflect the degree of variability. 17-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.4 SUBGRADE EVALUATION ROAD DESIGN STANDARD 2.4.4 METHODS OF ESTIMATING SUBGRADE SUPPORT VALUES There are basically two modes of testing available for estimation of subgrade support values; laboratory testing and field testing. Field testing is only applicable where it is proposed that subgrade support values are to be extrapolated from an existing pavement and the subgrade soil conditions are similar to those of the proposed pavement. Laboratory testing is applicable both where a suitable existing pavement for extrapolation exists, or from first principles. 2.4.5 FIELD DETERMINATION OF SUBGRADE CBR This procedure may be used to determine the design CBR where soils similar to those of the subgrade of the road being designed, have existed under a sealed pavement for at least two years and are at density and moisture conditions similar to those likely to occur in service. Care must be taken to carry out tests when the subgrade is in a critical moisture condition or, alternatively, seasonal adjustments may be made. A number of field tests may be used to estimate subgrade CBR, eg. In-situ CBR test and Cone Penetrometer. The results of such tests should be analysed statistically and a design CBR chosen at a percentile level appropriate to the particular case. The ten percentile level value (Mean minus 1.3 times Standard Deviation) has been used commonly for design of highway pavements. 2.4.5.1 In-situ CBR Test The in-situ CBR test is given in AS 1289. This test is time consuming and expensive. The number of tests required to establish the variability of the CBR for each type of material may be so large as to make the use of the in-situ CBR test impracticable. 2.4.5.2 Cone Penetrometers Cone penetrometer tests are described in AS 1289 and may be used for fine grained subgrades. CBR results can be determined from Figure 2.4.1 for the dynamic cone penetrometer and from Figure 2.4.2 for the static cone penetrometer. The relationship given in Figure 2.4.2 is a general relationship that suits most soil types. For further information relating to specific soil types the following references may provide assistance: Schofield (1986), Mullholland (1984) and Smith & Pratt(1983). ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.4 SUBGRADE EVALUATION 18-97 ROAD DESIGN STANDARD Figure 2.4.1 Correlation of Dynamic Cone Penetration and CBR. Figure 2.4.2 Correlation of Static Cone Penetration and CBR When using the cone penetrometers extensively for subgrade investigation, a limited number of in-situ CBR measurements should be carried out on the particular material being tested to confirm that the adopted relationship is valid. 2.4.6 LABORATORY DETERMINATION OF SUBGRADE CBR AND ELASTIC PARAMETERS This procedure may be used to determine design CBR where sufficient samples of the subgrade material for the new pavement can be obtained for detailed laboratory investigations and where a reasonable estimate can be made of likely subgrade density and moisture conditions in service. The method is particularly useful when a close similarity in density, moisture content and materials is not available between the proposed pavement and any existing road. 19-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.4 SUBGRADE EVALUATION ROAD DESIGN STANDARD Laboratory tests may be undertaken on specimens compacted at the design moisture content (DMC) and density, which correspond to those likely to occur in service or at a particular compaction standard and moisture as a characterising test. Alternatively, undisturbed samples can be obtained from the field by coring. Methods for determining the design moisture content are given in Appendix D. It may not always be practicable to prepare laboratory specimens at the selected density. In such cases, at least four specimens should be prepared at the DMC and at densities as close as possible to the characteristic value. The design value may be interpreted from interpolation of the results for these specimens. 2.4.6.1 Determination of Density for Laboratory Test The density selected for testing should correspond to that which will occur in service and may be one of the following: 2.4.6.2 • In-situ density of undisturbed or reworked subgrade as appropriate • Minimum standard of compaction achieved in construction (embankments) • Density after swelling has occurred (expansive soils) Determination of Design Moisture Content (DMC) There are several procedures for estimating the DMC. For practical application however, a compromise must be reached between the level of precision to be obtained and the cost of obtaining the necessary input data to determine the DMC. In all cases, however, the designer should ensure, either on the basis of knowledge of moisture conditions likely to occur in his locality, or by means of detailed field investigations that test moisture conditions realistically represent service conditions. Two methods for estimating the DMC are given in Appendix D. 2.4.7 ADOPTION OF PRESUMPTIVE CBR VALUES This approach may be used when no other relevant information is available. It is particularly useful for lightly trafficked roads where extensive investigations are not warranted, and also at preliminary design stages for all roads. Typical presumptive values of CBR are given in Table 2.4.5. However, such values should be determined on the basis of local experience, Table 2.4.5 Typical Presumptive Design CBR Values Description of Subgrade Material USC Classification Highly Plastic Clay CH Silt ML Silty Clay Sandy Clay Sand Typical CBR Values % Well drained Poorly drained 5 2.3 CL SC 6.7 4.5 SW, SP 15 – 20 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.4 SUBGRADE EVALUATION 20-97 ROAD DESIGN STANDARD 2.5 TRAFFIC INVESTIGATION 2.5.1 ESTIMATING FLOWS 2.5.1.1 Baseline traffic flows In order to determine the total traffic over the design life of the road the first step, is to estimate baseline traffic flows. The estimate should be the (Annual) Average Daily Traffic (ADT) currently using the route, classified into the vehicle categories of cars, light goods vehicles, trucks (heavy goods vehicles) and buses. The ADT is defined as the total annual traffic summed for both directions and divided by 365. It is usually obtained by recording actual traffic flows over a shorter, period from which, the ADT is then estimated. For long projects, large differences in traffic along the road may make it necessary to estimate the flow at several locations. It should be noted that for structural design purposes the traffic loading in one direction is required and for this reason care is always required when interpreting ADT figures. Traffic counts carried out over a short period as a basis for estimating the traffic flow can produce estimates that are subject, to large errors because traffic flows can have large daily, weekly, monthly and seasonal variations. The daily variability in traffic flow depends on the volume of traffic. It increases as traffic levels fall, with high variability on roads carrying less than 1000 vehicles per day. Traffic flows vary more from day-to-day than from week-to-week over the year. Thus there are large errors associated with estimating average daily traffic flows (and subsequently annual traffic flows) from traffic counts of only a few days duration, or excluding the weekend. For the same reason there is a rapid decrease in the likely error as the duration of the counting period increases up to one week. For counts of longer duration improvements in accuracy are less pronounced. Traffic flows also vary from month-month so that a weekly traffic count repeated at intervals during the, year provides a better base for estimating the annual volume of traffic than a continuous traffic count of the same duration. Traffic also varies considerably through a 24-hour period and this needs to be taken into account. In order to reduce error, it is recommended that traffic counts to establish ADT at a specific site conform to the following practice: (i) The counts are for seven consecutive days. (ii) The count on some of the days is for a full 24 hours, with preferably at least one 24 hour count on a weekday and one during a weekend. On the other days 16-hour counts should be sufficient. These should be grossed up to 24 hour values in the same proportion as the 16 hour/24 hour split on those days when full 24 hour counts have been undertaken. (iii) Counts are avoided at times when travel activity is abnormal for a short period due to the payment of wages and salaries, public holidays etc. If abnormal traffic flows persist for extended periods, for example during harvest times, additional counts need to be made to ensure this traffic is properly included. (iv) If possible the seven-day counts should be repeated several times throughout the year. (v) Country-wide traffic data should be collected on a systematic basis to enable seasonal trends in traffic flows to be quantified. Unfortunately, many of the counts that are available are unreliable, especially if they have been carried out manually. Therefore, where seasonal adjustment factors are applied to traffic survey data in order to improve the accuracy of baseline traffic figures, the quality of the statistics on which they are based should be checked in the field. 21-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.5 TRAFFIC INVESTIGATION ROAD DESIGN STANDARD Classified traffic counts are normally obtained by counting manually. These counts can be supplemented by automatic counters which use either a pneumatic tube laid across the surface of the carriageway or a wire loop fixed to the carriageway surface or preferably, buried just beneath it. Pneumatic tubes require regular maintenance and can be subject to vandalism. Buried loops are preferred, but installing a loop beneath the road surface is more difficult and more expensive than using a pneumatic tube. In their basic form automatic counters do not distinguish between different types of vehicle and so cannot provide a classified count. Modern detector systems are now available which can perform classified vehicle counting, but such systems are expensive and not yet considered to be sufficiently, robust for most developing country applications. 2.5.1.2 Traffic Forecasting Even with a developed economy and stable economic conditions traffic forecasting is an uncertain process. In a developing economy the problem becomes more difficult because such economies are often very sensitive to the world prices of just one or two commodities. In order to forecast traffic growth it is necessary to separate traffic into the following three categories. (a) Normal traffic. Traffic, which would pass along the existing road or track even if no new pavement was provided. (b) Diverted traffic. Traffic that changes from another route (or mode of transport) to the project road because of the improved pavement but still travels between the same origin and destination. (c) Generated traffic. Additional traffic that occurs in response to the provision of new or improved roads. Normal traffic. The commonest method of forecasting normal traffic is to extrapolate time series data on traffic levels and assume that growth will either remain constant in absolute terms ie. a fixed number of vehicles per year (a linear extrapolation) or constant in relative terms ie. a fixed percentage increase. Data on fuel sales can often be used as a guide to country-wide growth in traffic levels, although improvements in fuel economy over time should be taken into account. As a general rule it is only safe to extrapolate forward for as many years as reliable traffic data exists from the past and for as many years as the same general economic conditions are expected to continue. As an alternative to time, growth can be related linearly to anticipated Gross Domestic Product (GDP). This is normally preferable since it explicitly takes into account changes in overall economic activity, but it has the disadvantage that a forecast of GDP is needed. The use of additional variables, such as population or fuel price, brings with it the same problem. If GDP forecasts are not available, then future traffic growth should be based on time series data. If it is thought that a particular component of the traffic will grow at a different rate to the rest, it should be specifically identified and dealt with separately. For example a plan to expand a local town or open a local factory during the design life of the road could lead to different growth rates for different types of vehicles. Similarly there may be a plan to allow larger freight vehicles on the road, in which case the growth rate for trucks may be relatively low because each truck is heavier. Whatever the forecasting procedure used, it is essential to consider the realism of forecasting future levels. Even in the short term it is unlikely that developing countries will sustain the high rates of growth experienced in the past and factors such as higher fuel costs and vehicle import restrictions could also tend to depress future growth rates. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.5 TRAFFIC INVESTIGATION 22-97 ROAD DESIGN STANDARD Diverted traffic. Where there are parallel routes traffic will usually travel on the quickest or cheapest route although this may not necessarily be the shortest. Thus surfacing an existing road may divert traffic from a parallel and shorter route because higher speeds are possible on the surfaced road. Origin and destination surveys should be carried out to provide data on the traffic diversions likely to arise. Assignment of diverted traffic is normally done by an all-or-nothing method in which it is assumed that all vehicles that would save time or money by diverting would do so, and that vehicles that would lose time or increase costs would not transfer. With such a method it is important that all perceived costs are included. In some of the more developed countries there may be scope for modelling different scenarios using standard assignment computer programs. Diversion from other transport modes, such as rail or water, is not, easy to forecast. Transport of bulk commodities will normally be by the cheapest mode, though this may not be the quickest. However, quality of service, speed and convenience are valued by intending consignors and for general goods diversion from other modes should not be estimated solely on the basis of door to door transport charges. Similarly, the choice of mode for passenger transport should not be judged purely on the basis of travel charges. The importance attached to quality of service by users has been a major contributory factor to the world-wide decline in rail transport over recent years. Diverted traffic is normally forecast to grow at the same rate as "traffic' on the road from which it is diverted. Generated traffic. Generated traffic arises either because a journey becomes more attractive by virtue of a factor time reduction or because of the increased development that is brought about by the road investment. Generated traffic is difficult to forecast accurately and can be easily overestimated. It is only likely to be significant in those cases where the road investment brings about large reductions in transport costs. For example in the case of a small improvement within an already developed highway system, generated traffic will be small and can normally be ignored. However, in the case of a new road allowing access to a hitherto undeveloped area, there could be large reductions in transport cost as a result of changing mode. For example from animal based transport to motor vehicle transport. In such a case generated traffic could be the main component of future traffic now. The recommended approach to forecasting generated traffic is to use demand relationships. The price elasticity of demand for transport is the responsiveness of traffic to change in transport costs following a road investment. On inter urban roads a distinction is normally drawn between passenger and freight traffic. On roads providing access to rural areas a further distinction is usually made between agricultural and non-agricultural freight traffic. Evidence from several evaluation studies carried out in developing countries shows price elasticity of demand varies between 0.6 to 2.0, with an average of about 1.0. This means that a one percent decrease in transport costs leads to a one percent increase in traffic. Calculations should be based on door to door travel costs estimated as a result of origin and destination surveys and not just on that part of the trip incurred on the road under study. The available evidence suggests that the elasticity of demand for passenger travel is usually slightly greater than unity. In general the elasticity of demand for goods is much lower and depends on the proportion for transport costs in the commodity price. 23-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.5 TRAFFIC INVESTIGATION ROAD DESIGN STANDARD 2.5.2 AXLE LOADING 2.5.2.1 Axle load surveys If no recent axle load data is available it is recommended that axle load surveys of heavy vehicles are undertaken whenever a major road project is being designed. Ideally, several surveys at periods that will reflect seasonal changes in the magnitude of axle loads are recommended. Portable vehicle-wheel weighing devices are available which enable a small team to weigh up to 910 vehicles per hour. Detailed guidance on carrying out axle load surveys and analysing the results is given in TRRL Road Note 40 (Transport and Road Research Laboratory (1978)). It is recommended that an axle load survey be carried out by weighing a sample of vehicles at the roadside. The sample should be chosen such that a maximum of about 60 vehicles per hour is weighed. The weighing site should be level and, if possible, constructed in such a way that vehicles are pulled clear of the road when being weighed. The portable weighbridge should be mounted in a small pit with its surface level with the surrounding area. This ensures that all of the wheels of the vehicle being weighed are level and eliminates the errors which can be introduced by even a small twist of the vehicle. More importantly, it also eliminates the large errors that can occur if all the wheels on one side of multiple axle groups are not kept in the same horizontal plane. The load distribution between axles in multiple axle groups is often uneven and therefore each axle must be weighed separately. The duration of the survey should be based on the same considerations as for traffic counting outlined in Section 2.5.1.1. On certain roads it may be necessary to consider whether the axle load distribution of the traffic travelling in one direction is the same as that of the traffic travelling in the opposite direction. Significant differences between the two streams can occur on roads serving docks quarries, cement works etc., where the vehicles travelling one way are heavily loaded but are empty on the return journey. In such cases the results from the more heavily trafficked lane should be used when converting commercial vehicle flows, to the equivalent number of standard axles for pavement design. Similarly, special allowance must be made for unusual axle load on roads which mainly serve one specific economic activity, since this can result in a particular vehicle type being predominant in the traffic spectrum. This is often the case. For example in timber extraction areas, mining areas and oil fields. 2.5.2.2 Axle Configurations and Equivalences The damage due to different axle groups is dependent on the axle spacing, the number of types per axle, the load on the group and the suspension. For design purposes, it is generally appropriate to consider axle groups in terms of the following four types: • single axle with single wheels; • single wheels single axle with dual wheels; • tandem axles both with dual wheels; • tri-axles all with dual wheels. Table 2.5.1 Axle Loads Which Cause Equal Damage Axles Configuration Load (kN) Single Single Single Dual 53 80 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.5 TRAFFIC INVESTIGATION Tandem Dual 135 Tri-axle Dual 181 24-97 ROAD DESIGN STANDARD The standard axle is defined as a single axle with dual wheels that carries a load of 8.2 tonnes. Loads on the axle configurations given above that cause the same amount of damage as the standard axle are given in Table 2.5.1. For axle group loads other than those in Table 2.5.1, the damage caused is expressed as the number of standard axles which produce the same damage and is calculated as follows:   Load on axle group No. of standard axles for same damage =   ï£ Appropriate load from Table 2.5.1  EXP Where the exponent EXP may vary depending on the type of pavement. Commonly, a value of 4 is adopted for the exponent in which case the number of standard axles for the same damage is termed the number of equivalent standard axles (ESAs). 2.5.2.3 Design Lanes Construction of now pavements and overlaying of existing pavements usually affects two or more traffic lanes. It is usual practice to adopt the same pavement design for all lanes. The design traffic should be that in the lane which carries the most commercial vehicular traffic and it is designated the design lane. 2.5.3 DESIGN PERIOD The design period is the length of time expressed in years before it is anticipated that rehabilitation of the pavement will be necessary to restore shape, repair other forms of distress, or to provide additional pavement strength. Rehabilitation, which may consist of granular or asphalt overlay, major patching or improvements or removal of selected areas of pavement materials, initiates a new design period. In this regard, resurfacing a pavement with a sprayed seal or a very thin asphalt overlay does not in itself constitute rehabilitation in the pavement design sense. Some typical design periods are outlined below: • New granular pavements 20 - 25 years • New rigid pavements 20 - 40 years • Asphalt overlays 10 - 15 years • Granular overlays 10 - 20 years Various factors will influence the choice of design period. They include: • Maintenance strategies. Highly trafficked facilities will demand long periods of low maintenance. • Funding considerations. • Other factors, such as inadequate geometry or traffic capacity, may limit the life of the roadway and necessitate early reconstruction. 25-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.5 TRAFFIC INVESTIGATION ROAD DESIGN STANDARD 2.5.4 TRAFFIC GROWTH Based on road traffic survey information, it is reasonable, in most circumstances, to assume that traffic volumes will increase geometrically either for the entire design period or up to a stage where "road capacity" is reached. If “road capacity” is achieved traffic volumes are assumed to remain constant for the remainder of the design period. If there is an indication that "road capacity" is likely to be reached within the design period, it is recommended that the designer establish that there is no planned upgrading of the road geometry within the design period before he adopts "no growth" traffic volume for the period of "full capacity". Adoption of "no-growth" traffic volumes for a period of "saturation" will entail modification of the approach used below to aggregate daily traffic volumes for total design traffic. For geometric traffic growth throughout the design period, total traffic over the design period is determined by multiplying the total traffic in the first year by the appropriate Cumulative Growth Factor from Table 2.5.2. Table 2.5.2 Cumulative Growth Factor Design Period (Years) 5 10 15 20 25 30 35 40 2.5.5 Growth rate (% pa) 0 5 10 15 20 25 30 35 40 2 5.2 10.9 17.3 24.3 32 40.6 50.0 60.4 4 5.4 12.0 20.0 29.8 41.6 56.1 73.7 95.0 6 5.6 13.2 23.3 36.8 54.9 79.1 111.4 154.8 8 5.9 14.5 27.2 45.8 73.1 113.3 172.3 259.1 10 6.1 15.9 31.8 57.3 98.3 164.5 271 442.6 DESIGN TRAFFIC FOR FLEXIBLE PAVEMENT The design parameter required is the number of ESAs. Annual average daily number of ESAs, NE is calculated from Method 4 of Appendix C. The design number of ESAs is then calculated as: NE x 365 x GF Where GF is the cumulative growth factor from Table 2.5.2. This value is used as input to the design procedure outlined in Section 2.7 for flexible pavements and Section 2.9 for overlays. 2.5.6 DESIGN TRAFFIC FOR RIGID PAVEMENTS The design traffic is characterised by the cumulative number of commercial vehicle axle groups expected in the design lane during the design period , together with the proportions of each type of axle group and the distribution of load on each type of axle group. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.5 TRAFFIC INVESTIGATION 26-97 ROAD DESIGN STANDARD Loads on an axle group type are typically grouped into 10 kN intervals. Appendix F contain examples of load distributions. The design number of commercial vehicle axle groups over the design life of the pavement is given by: Cag = Cd x 365 x GF Where: Cag = Cd = GF = design number of commercial vehicle axle groups. initial number of commercial vehicle axle groups per day the cumulative growth factor from Table 2.5.2. The design procedure in Section 2.8 caters for each of the following axle types: • Single axles with single wheels; • Single axles with dual wheels; • Tandem axles with dual wheels; and • Tri-axles with dual wheels. Other axle types are to be converted to one of the above as follows: (i) convert spread tandem axle loads to dual typed single axle loads on the basis that a spread tandem axle is equivalent to two dual typed single axles, each of which has half of the spread tandem axle load. (ii) Convert twin steer axles to single axles with single wheels on the basis that a twin steer axle is equivalent to two single axles with single wheels each with half the load. 27-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.5 TRAFFIC INVESTIGATION ROAD DESIGN STANDARD 2.6 PAVEMENT MATERIALS 2.6.1 GRANULAR MATERIALS 2.6.1.1 Introduction Granular material consists of gravel or crushed rock which have a grading that makes them mechanically stable, workable and able to be compacted. Modified granular materials consist of gravel or crushed rock to which small amounts of stabilising agent have been added to improve their performance (eg by reducing plasticity) without causing a significant increase in structure stiffness. Modified granular materials are considered to behave as unbound granular materials. Table 2.6.1 Physical Properties of Granular Pavement Material Material Sub base Grading Envelope Liquid limit fraction passing 0.425 mm Plasticity Index Ratio fraction passing 0.075 mm sieve and 0.425 mm sieve Abrasion CBR 4 day soaked No of cracked faces Sodium sulphate soundness loss Sub base Test Method Base course Shoulder A-E AASHTO T27 A-C A-D < 35 % < 10 T 89 T 90 < 25 % <6% < 35 % >4 , <15 2/3 2/3 < 50 % > 30 % T 96 T 193 < 40 % > 80 % 2 < 12 % T 104 < 12 % > 30 % Table 2.6.2 Grading Requirements for Granular Pavement Material Sieve Designatio n 50 mm 25 mm 10 mm 4.75 mm 2.00 mm 0.425 mm 0.075 mm 2.6.2 Grading A 100 30 – 65 20 – 50 15 – 40 8 – 20 2–8 Grading Grading Grading Grading Grading B C D E E Percentage by weight passing square mesh sieves 100 100 100 75 – 95 100 100 100 100 40 – 75 50 – 85 49 – 77 30 – 60 35 – 70 50 – 90 20 – 45 25 – 50 40 – 70 40 – 100 55 – 100 15 – 30 15 – 35 20 – 50 30 – 70 40 – 100 5 - 15 5 - 15 5 – 20 6 - 20 8 - 25 MODIFIED MATERIALS Bound pavement materials are those produced by additions of cement, lime or other hydraulically binding agent to granular materials in sufficient quantities to produce a bound layer with significant tensile strength. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.6 PAVEMENT MATERIALS 28-97 ROAD DESIGN STANDARD Table 2.6.3 Physical Properties of Bound Pavement Materials Grades Soil Cement Base Desirable Absolute Well Well graded graded % retained on 4.75 mm sieve % Passing 0.075 sieve Fraction Passing 0.425 mm PI LL 2.6.3 BITUMEN 2.6.3.1 Prime Coat Soil Cement Sub - base Desirable Absolute Well Well graded graded Lime Soil > 30 % <6% < 25 % <15 % < 40 % < 10 % < 30 % < 40 % < 40 % < 20 % < 40 % 6 % - 20 % < 40 % The prime coat shall be a medium or slow curing cutback liquid asphalt conforming to the requirements of AASHTO M82 or slow setting emulsified asphalt conforming to the requirements of AASHTO M82. Application temperatures shall be as follows: Type and Grade MC – 30 MC – 70 SC – 70 CSS – 1 2.6.3.2 Application Temperature 30 – 90 ºC 50 – 100 ºC 50 – 100 ºC 25 – 50 ºC Tack Coat The tack coat shall be one of the following bituminous materials: Designation Type of material Application temperature Residual bitumen application rates RC – 70 Rapid curing liquid asphalt Rapid curing liquid asphalt Rapid setting 50 ºC – 100 ºC 0.1 – 0.3 l/m2 80 ºC – 100 ºC 0.1 – 0.3 l/m2 20 ºC – 70 ºC 0.1 – 0.3 l/m2 RC – 250 CRS – 2 2.6.3.3 Bituminous Surface treatment 2.6.3.3.1 Bituminous materials Bituminous materials used in surface treatments shall be one of the types and grades listed in the following table and approved by the Engineer. Designation 60 – 70 80 – 100 RC – 250 RC – 800 RC – 3000 29-97 Type of Material Bitumen Bitumen Cutback Bitumen, Rapid Curing Cutback Bitumen, Rapid Curing Cutback Bitumen, Rapid Curing ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.6 PAVEMENT MATERIALS ROAD DESIGN STANDARD RC – 2 CRS – 2 CRS – 3 Emulsified Bitumen Cationic Emulsified Bitumen Cationic Emulsified Bitumen The materials shown above shall be in compliance with AASHTO designations M20 – 70, M41 – 75, M140 – 82 and M208 – 81, as applicable. Bitumen shall only be cut back on site if so instructed and approved by the Engineer. 2.6.3.3.2 Aggregates Aggregates for bituminous surface treatments shall consist of clean, dry, hard durable crushed stone or crushed gravel free from dust, clay, dirt and other deleterious matter. Aggregates shall meet the quality requirements of AASHTO M80 except as altered herein. All aggregates shall be mechanically screened to remove dust and small particles. Where bitumen or cutback bitumen is used, aggregates shall be pre-coated. Where emulsified asphalt is used, only washed aggregates will be allowed. When subjected to the coating and stripping test, AASHTO test method T182, the aggregates shall have a coated area of not less than 95 %. Aggregates which do not meet this requirement may be used for bituminous surface treatments provided an approved chemical additive or wetting agent is used to create a water resistant film. When crushed gravel is used to produce sealing aggregate , not to less than 75 % by weight of the particles shall have at least two fractured faces. The minimum size of stone to be crushed to produce sealing aggregate shall be least four times the maximum size of the sealing aggregate. The aggregate shall have a percentage wear not exceeding 35 when tested for abrasion resistance by AASHTO Method T96 and, when subjected to five cycles of the sodium sulphate test for soundness ( AASHTO test Method T104 ) shall have a weight loss not greater than 12 %. The flakiness index by British Standard 812, shall not exceed 33 %. Aggregate sizes and gradings to be used in various applications of surface treatment shall be determined using Table 2.6.4 , Table 2.6.5, and Table 2.6.7. Table 2.6.4 Categories of Road Surface Hardness Surface Category Very Hard Penetration at 30 ºC (mm) 0–2 Hard 2–5 Normal 5–8 Soft 8 – 12 Definition Surface such as concrete or chemically stabilised roadbases into which negligible penetration of chippings will occur under heavy traffic. Granular roadbases into which chippings will penetrate only slightly under heavy traffic. Bituminous roadbase or basecourses into which chipping will penetrate moderately under medium and heavy traffic. Bitumen rich asphalts into which chipping will penetrate considerably under medium and heavy traffic. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.6 PAVEMENT MATERIALS 30-97 ROAD DESIGN STANDARD Table 2.6.5 Traffic Category For Surface Dressing Category Approximate Number of Vehicles with Unladen Weight Greater Than 1.5 tonnes (per day) Over 2000 1000 – 2000 200 – 100 20 – 200 Less than 20 1 2 3 4 5 Table 2.6.6 Recommended Maximum Chipping Size (mm) Surface Category Very Hard Hard Normal Soft 1 10 14 20 2 10 14 14 20 Traffic Category 3 6 10 14 14 4 6 6 10 14 5 6 6 6 10 Table 2.6.7 Grading Requirements For Surface Chip Nominal Size of Material 25.0 mm 19.0 mm 12.5 mm 9.5 mm 2.6.3.4 25.0 mm 90-100 100 Percent by weight passing AASHTO sieve Size 19.0 12.5 9.5 mm 4.75m 2.36m mm mm 0.45 0-10 0-5 0-2 90.100 0.30 0-8 0-2 100 90.100 0-40 0-8 0-2 100 90-100 0-30 0-8 1.18 mm 0-0.05 0-0.05 0-0.05 0-2 Asphaltic Concrete (a) Coarse Mineral Aggregate Coarse aggregate ( retained on the 4.75 mm sieve ) shall be crushed stone, or crushed gravel, and unless otherwise stipulated, shall conform to the quality requirements of AASHTO M 80. When crushed gravel is used, it shall also meet the pertinent requirement of Section 2.2.1 of AASHTO M147-6S and not less than 75 % by weight of the particles retained on the 4.75 mm sieve shall have at least two fractured faces and 90 % one or more fractured faces. The abrasion loss (AASHTO T96) shall not exceed 40 %. Any aggregates liable to polish shall not be used for the coarse aggregate fraction. The coarse aggregate shall be of such gradation that when combined with other required aggregate fractions in proper proportion the resultant mixture will meet the gradation required for the composition of the mixture. (b) Fine Mineral Aggregate Fine aggregate (passing the 4.75 mm sieve) shall consist of natural sand, stone screenings, or a combination thereof, and shall conform to the quality requirements of AASHTO M299 ASTM D10730. Fine aggregate shall be of such gradation that when combined with other required aggregate fractions in proper proportions, the resultant mixture will meet the gradation required for composition of the mixture. The sand equivalence, tested in accordance with AASHTO T176, shall be greater than 50. 31-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.6 PAVEMENT MATERIALS ROAD DESIGN STANDARD (c) Mineral Filler Filler material for asphaltic concrete shall conform to the requirements in AASHTO M17. When the Strength Index as determined according to the Ontario Vacuum Immersion Marshall Test or the US Army Corps of Engineers – Asphalt Institute Immersion Marshall Test is than 75 % either 1 to 2 % of hydrated lime or 2 to 4 % of Portland cement by weight may be added to the mix. (d) Asphalt Materials Asphalt cement shall conform to the requirements given in AASHTO M20-70. Asphalt cement shall be designated by its penetration value ( eg AC 60-70). Cut back asphalts shall be of the rapid curing type or the medium curing type and shall conform to AASHTO designations M81-75 and M82-75 respectively. Cut back asphalt shall be described by its kinematic velocity value at 60 ºC.( eg RC 250, MC 70) 2.6.4 CONCRETE 2.6.4.1 Introduction Concrete (cement concrete) refers to a homogeneous mixture of hydraulic cement, fine and coarse aggregate, water and chemical admixtures. The cementitious portion of concrete may be of Portland cement or blended cement. Blended cements consist of Portland cement mixed with additives such as ground granulated blast furnace slag (slag) and/or pulverised fuel-ash (fly-ash). Chemical admixtures may be used for set retardation, water reduction and air entrainment. Concrete can be used as a sub-base in either flexible or rigid pavements and as a base in rigid pavements. 2.6.4.2 Sub-base Concrete Lean-mix concrete which is used for sub-base construction may contain a fly-ash blended cement and is required to attain a characteristic 28 day compressive strength of 5 MPa (with fly-ash) and 7 MPa (without fly-ash). The strength of concrete made using fly-ash blended cement increases at a slower rate up to 28 days. The construction of both rigid and flexible bases over poor subgrades is facilitated by the adoption of a concrete sub-base. For example, weak subgrades may preclude the use of rollers. Where sub-base concrete is used in the design of a flexible pavement, for structural design purposes the characteristics which must be known and evaluated are modulus, Poisson’s ratio and performance under repeated loading. 2.6.4.3 Base Concrete A rigid pavement is defined as a pavement having a base of cement concrete. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.6 PAVEMENT MATERIALS 32-97 ROAD DESIGN STANDARD The 28 day concrete flexural strength is a key design parameter in predicting pavement performance. The 28 day design flexural strength of concrete suitable for road pavement construction is typically 3.0 to 5.0 MPa. Steel-fibre reinforced concrete should have a 28 day flexural strength in the range 5.0 to 5.5 MPa. Since at the time of undertaking the thickness design the concrete will only have a nominal target strength, the design strength should be expressed in terms of the characteristic flexural strength to the nearest 0.25 MPa. A 28 day design characteristic flexural strength of 4.25 MPa is considered to correspond to a 28 day characteristic compressive strength of 32 MPa. The durability of the concrete wearing surface requires a 28 day characteristic compressive strength of not less than 32 MPa (Refer to AS 3600 “Concrete Structures” for concrete wearing courses subject to highway traffic). A typical relationship for converting 28 day compressive strength to 28 day flexural strength for concrete with crushed aggregate is: f cf = 0.75 ( f c ) 0.50 (2 - 1.) Where: fc fcf = = 28 day concrete compressive strength (MPa). 28 day concrete flexural strength (MPa). The indirect tensile or splitting (Brazilian) test, has also been used for the control of concrete strength in pavement work. A typical relationship for converting splitting strength into flexural strength is: f cf = 1.37 f cs (2 - 2.) Where: fcs = 28 day concrete splitting or indirect tensile strength. The actual strength relationships for a given concrete mix will be dependent on the properties of its constituents, particularly the micro-texture and particle shape of the coarse aggregate. For pavement thickness design purposes the above relationships are sufficiently accurate for concretes made with crushed aggregates possessing smooth micro-texture. 33-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.6 PAVEMENT MATERIALS ROAD DESIGN STANDARD 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS New flexible pavements shall be designed in accordance with the following charts. Chart 1 Granular Roadbase / Surface Dressing Chart 2 Composite roadbase (Unbound & Cement) / Surface Dressing Chart 3 Granular Roadbase / Semi-Structural Surface Chart 4 Composite Road base / Semi-Structural Surface Chart 5 Granular Roadbase / Structural Surface Chart 6 Composite Roadbase / Structural Surface Chart 7 Bituminous Roadbase / Semi-Structural Surface Chart 8 Cement Roadbase / Surface Dressing ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS 34-97 ROAD DESIGN STANDARD CHART 1 G RANULAR RO ADBASE / SURFACE DRESSING T1 S1 SD 150 175 300 S2 SD T2 T3 SD SD 150 200 225* 200 300 300 SD SD 150 200 150 200 175 200 200 200 SD SD 150 200 250 225 SD SD 150 200 175 150 SD SD SD 150 100 150 100 SD 150 150 S3 SD 150 200 S4 SD 150 125 S5 T4 SD T5 SD T6 225 250* 300* 325* 300 300 300 SD 200 SD 200 SD 225 225* 275* 300* 200 200 200 SD 200 275* SD 200 200 SD SD 200 325* SD SD 225 350* SD 200 225 250 275 SD SD 175 200 225 250 100 125 150 175 SD SD SD SD SD 150 175 200 225 250 S6 T8 SD 200 200 T7 Note: 1 * U p to 100mm of sub-base may be substituted with selected fill prov ided the sub-base is not reduced to less than the roadbase thickness or 200mm whichev er is the greater. The substitution ratio of sub-base to selected fill is 25mm : 32mm 2 * A cement or lime-stabilised sub-base may also be used. 35-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS ROAD DESIGN STANDARD ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS 36-97 ROAD DESIGN STANDARD 37-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS ROAD DESIGN STANDARD ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS 38-97 ROAD DESIGN STANDARD 39-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS ROAD DESIGN STANDARD ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS 40-97 ROAD DESIGN STANDARD 41-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS ROAD DESIGN STANDARD ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.7 DESIGN OF NEW FLEXIBLE PAVEMENTS 42-97 ROAD DESIGN STANDARD 2.8 DESIGN OF RIGID PAVEMENTS 2.8.1 GENERAL This section provides guidance on the thickness design of rigid pavements proposed for roads carrying commercial traffic with a design traffic loading exceeding one million commercial vehicle axle groups. The information herein may not be appropriate for residential or industrial pavements. The design method is based on assessments of: (i) the predicted traffic volume and composition over the design period; (ii) the strength of the subgrade in terms of its California Bearing Ratio (CBR %); and (iii) the strength of the concrete to be used in the pavement. With these assessments remaining constant the concrete base thickness will vary according to the type of shoulder and joint/reinforcement details adopted. The selection of the overall pavement configuration is a matter for decision by the designer based on its suitability for a particular project and economics. 2.8.2 PAVEMENT TYPES 2.8.2.1 Cement Concrete Pavements A cement concrete pavement is defined as a pavement having a base of Portland cement concrete. The principal types are: • jointed plain (unreinforced) concrete pavements (PCP); • jointed reinforced concrete pavements (JRCP); • continuously reinforced concrete pavements (CRCP). The amount, if any, of reinforcement required in a concrete pavement is governed by the spacing of contraction joints. The three main pavement configurations are: (a) Unreinforced concrete pavements that have undowelled or dowelled contraction joints at 4 to 5 m spacings. (b) Reinforced concrete pavements which have dowelled contraction joints at approximately 8 to 15 m spacings. (c) Continuously reinforced concrete pavements where sufficient steel reinforcement has been added to control crack widths and no contraction joints are required. Additional types of concrete pavements are: • steel-fibre reinforced and • prestressed concrete pavements. Design procedures for prestressed concrete pavements are not included in this Standard. 43-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD 2.8.2.2 Asphalt Surfaced Rigid Pavements Each type of concrete pavement described above may be provided with an asphalt surface, typically up to 50 mm thick. The design procedure does not allow any contribution by the asphalt surface to the structural performance of the pavement. 2.8.3 FACTORS USED IN THICKNESS DETERMINATION 2.8.3.1 Strength of Subgrade For rigid pavement thickness design, the strength of the subgrade may be assessed in terms of CBR. Methods of assessing the design CBR of the subgrade are discussed in Section 2.4. 2.8.3.2 Concrete Strength The determination of concrete strength is discussed in Section 2.6.4. The 28 day flexural strength (modulus of rupture) of the concrete is used as the design strength. 2.8.3.3 Design Traffic The methods of determining the design traffic loading for rigid pavement thickness design are included in Section 2.5.6. 2.8.3.4 Provision of Sub-base 2.8.3.4.1 General Recommended minimum sub-base requirements are given in Figure 2.8.1. For traffic loadings covered by this Standard the following recommendations are made: (i) the minimum sub-base thickness should be 100 mm. (ii) sub-base materials should be at least of the quality of bound material as described in Clause 2.8.3.4.2; except that (iii) where jointed undowelled bases are being designed lean-mix concrete is recommended. Note: It is not the intention of this Standard to preclude sub-base materials and thicknesses different to those described in Items (i) to (iii) above or as given in Figure 2.8.1 (in combination with an appropriate base thickness) where these have been found to give good long-term performance under particular conditions or whose performance is supported by relevant research. If the use of unbound sub-base materials is considered, for thickness design purposes the subgrade CBR is adopted as the effective CBR. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 44-97 ROAD DESIGN STANDARD Figure 2.8.1 Minimum Sub base requirements for Rigid pavements The effective subgrade CBR for bound and lean-mix concrete sub-bases is obtained from Figure 2.8.2. For subgrades with a design subgrade CBR of less than 2%, it may not be possible to achieve compaction with rollers and the following design parameters are recommended: • the provision of a 150 mm thick sub-base of lean mix concrete; and • the use of a maximum value of 5 % for the effective subgrade CBR. Note: Other sub-base types which can be adequately constructed may be used providing special investigations into the assessment of the effective design subgrade CBR are carried out. Figure 2.8.2 Effective Increase in Subgrade Strength due to Provision of Bound (Or Mass Concrete) Sub-Base Course 45-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD A bound or lean mix concrete sub-base is provided under a concrete pavement for one or more of the following reasons: (a) to provide a stable working platform on which to operate construction equipment; (b) to provide uniform support under the pavement; (c) to reduce deflection at joints thus maintaining effective load transfer across contraction joints by aggregate interlock (especially if no other load transfer devices are provided); (d) to assist in the control of shrinkage and swelling of high volume change subgrade soils; and (e) to resist erosion of the sub-base and limit "pumping" at joints and slab edges. Note: Pumping is defined as the ejection of fine particles in suspension (usually in wet weather) along or through transverse or longitudinal joints or cracks. It is caused by downward slab movement as heavy axle loads traverse joints, Pumping leads to the removal of sufficient sub-base or subgrade material so that slab ends are left unsupported resulting in cracking or faulting of the slab. 2.8.3.4.2 Bound Sub-base For the purpose of rigid pavement design, a bound sub-base is defined as being composed of either: (i) cement-stabilised granular material with not less than 5 % by mass cementitious content to ensure satisfactory erosion resistance (verifiable by laboratory erodability testing). The cementitious content may include lime/fly ash and/or ground granulated blast furnace slag; or (ii) dense-graded asphalt; or (iii) lean rolled concrete having a characteristic 28 day strength of not less than 5 MPa. 2.8.3.4.3 Lean Rolled Concrete Sub-base Lean rolled concrete as defined in Clause 2.8.3.4.2 (iii) should be considered for design purposes to be a bound sub-base. 2.8.3.4.4 Lean-Mix Concrete Sub-base Lean-mix concrete (LMC) is to have a characteristic 28 day compressive strength of not less than 5 MPa (with fly-ash) or 7 MPa (without fly-ash), and be designed to have low shrinkage, typically less than 450 microstrain. Note: Lean-mix concrete sub-bases are constructed as mass concrete without transverse joints and will therefore develop cracks. It is intended to achieve a pattern of relatively closely spaced and narrow cracks which in conjunction with a debonding layer will not reflect into the base. This is controlled by limiting both the upper strength and shrinkage of the sub-base concrete. These limitations are inherent in Figure 2.8.2. 2.8.3.4.5 Debonding of the Sub-base and Base It is assumed that the sub-base and base are designed to be unbonded. This is accomplished by application of a bond-breaking layer to the surface of the sub-base. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 46-97 ROAD DESIGN STANDARD 2.8.3.5 Concrete Shoulders Provision is made in the design procedure for the incorporation of concrete shoulders. Concrete shoulders enhance the pavement performance and enable a lesser base thickness to be adopted. For the purposes of this Standard, a concrete shoulder is defined as: (a) a keyed and tied (in accordance with Clause 2.8.4.6.2) shoulder with a minimum width of 1.5 m from the edge of the trafficked lane; or (b) a 600 mm integrally cast widening of the trafficked lane, this may include integral channel or kerb/ channel. 2.8.3.6 Load Safety Factors In the design procedure, the axle loads are multiplied by a load safety factor (LSF). These load safety factors are used to incorporate varying levels of design reliability. The following values are recommended: • For major freeways and other multi-lane projects carrying LSF = 1.2 uninterrupted flows of high volumes of commercial vehicles, and where high levels of serviceability are sought throughout the design period with minimum maintenance. • This value of 1.2 maybe reduced to 1.15 taking into account factors such as the use of appropriate weigh-in-motion data and the availability of alternative traffic routes. An example would be the case of a very busy urban freeway with no alternative routes and where weigh-in-motion data is available for a period of at least two months for a nearby site consistent with that being designed. • For freeways, highways and arterial road projects with moderate LSF = 1.1 volumes of commercial vehicles. • LSF = 1.0 For roads carrying low volumes of commercial vehicles. 2.8.4 BASE THICKNESS DESIGN PROCEDURE 2.8.4.1 General The procedure for the determination of the thickness of rigid pavements is based on "Thickness Design for Concrete Highway and Street Pavements," Portland Cement Association USA (EB209.01P). 1984. The two distress modes considered in this procedure are: (i) flexural fatigue cracking of the pavement base; (ii) subgrade/sub-base erosion arising from repeated deflections at joints and planned cracks. Account is taken of the presence or absence of dowelled joints or concrete shoulders. For design purposes continuously reinforced pavements are treated as dowelled jointed pavements. Information is required on both axle types and load distributions and the number of repetitions of each axis type/load combination expected to use the pavement during its design life. 2.8.4.2 Base Thickness Design Procedure A trial base thickness is selected and the total fatigue and erosion damage are calculated for the entire traffic volume and composition during the design period. If either fatigue or 47-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD erosion damage exceeds 100 percent, the trial thickness is increased and the design process is repeated. The design thickness is the least trial thickness which has a total fatigue less than or equal to 100 percent and a total erosion damage less than or equal to 100 per cent. The steps in the thickness design are illustrated in Figure 2.8.3 and are detailed in Table 2.8.1. A pro–forma to assist with design calculations is provided in Appendix F. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 48-97 ROAD DESIGN STANDARD Figure 2.8.3 Rigid Pavement Design System 49-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD Table 2.8.1 Design Procedure for Base Thickness Step 1 2 3 Activity Select a rigid pavement type, either jointed undowelled, jointed dowelled or continuously reinforced concrete base. Decide whether concrete shoulders are to be provided. 5 Using the design subgrade CBR and the predicted number of commercial vehicle axle groups over the design period determine the Figure 2.8.1. sub-base thickness and type from Using the design subgrade CBR and the selected sub base determine the Effective Subgrade CBR from Figure 2.8.2. Select the 28-day flexural strength of the concrete base (f’cf). 6 Select the appropriate load safety factor. 7 Select a trial base thickness (appropriate trial base thicknesses may be governed by such factors as formwork depth or estimated from experience or by using the example design charts provided herein). For the Single Steer (SS) axle group, determine the equivalent stress and the erosion factor from Table 2.8.2 or Table2.8.3 as appropriate. Determine the stress ratio factor by dividing the equivalent stress by the flexural strength. For each load range for this axle group type, determine the load per tyre on the axle group and multiply by the safety factor to Determine the design load per tyre. If the design load per tyre exceeds 65 kN, assume a value of 65 kN (the upper limit in Figure 2.8.4 to Figure 2.8.6) Using the stress ratio factor and the design load, determine from Figure 8.4 the allowable number of repetitions to fatigue starting with the highest load per tyre of this axle group type. Calculate the ratio of the expected fatigue repetitions to the allowable repetitions. Multiply by 100 to determine the percentage Fatigue. Using the erosion factor, determine from Figure 2.8.5 or Figure 2.8.6 (as appropriate) the allowable number of repetitions for erosion. Calculate the ratio of the expected erosion repetitions to the allowable repetitions. Multiply by 100 to determine the percentage erosion damage. Repeat steps 11 to 14 each load per tyre on this axle group until the allowable load repetitions as read from Figure 2.8.4 and Figure 2.8.5 or Figure 2.8.6 exceed 107 and 108 respectively, at which point further load repetitions are not deemed to contribute to pavement distress. Sum the percentage fatigue for all relevant loads of this axle group type; similarly , sum the percentage erosion for all relevant loads of this axle group type. Repeat steps 8 to 16 for each axle group type. Sum the total fatigue and total erosion damage for all axle group types. Steps 7 to 18 inclusive are repeated until the least thickness which has a total fatigue less than of equal to 100 percent and also a total erosion damage less than or equal to 100 percent is determined. This is the base concrete pavement design thickness. 4 8 9 10 11 12 13 14 15 16 17 18 19 Reference Section 2.8.2.1 Section 2.8.3.5 Section 2.8.3.4 Section 2.8.3.4 Section 2.8.3.2 Section 2.8.3.6 Appendix F Note: Selection of the final base thickness may be governed by construction factors such as survey levels, etc. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 50-97 ROAD DESIGN STANDARD Figure 2.8.4 Fatigue Analysis with and without Concrete Shoulder – Allowable load repetitions based on stress ratio. 51-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD Figure 2.8.5 Erosion Analysis without Concrete Shoulder – Allowable Load repetitions based on Erosion factor. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 52-97 ROAD DESIGN STANDARD Figure 2.8.6 Erosion Analysis with Concrete Shoulder – Allowable Load Repetitions based on Erosion Factor 53-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD Figure 2.8.7 Recommended maximum tiebar spacing for concrete pavements assuming 12 mm diameter tie bars, grade 400Y steel and subgrade friction factor of 1.5. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 54-97 ROAD DESIGN STANDARD Table 2.8.2 Equivalent Stresses And Erosion Factors For Pavements With No Concrete Shoulders Slab Effective Thickness CBR of (mm) Subgrade Equivalent Stresses SS SD TAD TRD SS Erosion Factors Undowelled Dowelled or CRC SD TAD TRD SS SD TAD TRD 150 150 150 150 150 150 150 150 5 10 15 20 25 35 50 75 1.70 1.62 1.59 1.56 1.54 1.49 1.43 1.38 2.72 2.56 2.48 2.43 2.37 2.26 2.15 2.02 2.25 2.09 2.01 1.97 1.92 1.82 1.73 1.64 1.68 1.58 1.53 1.51 1.48 1.43 1.40 1.36 2.80 2.79 2.78 2.77 2.77 2.76 2.74 2.72 3.40 3.39 3.38 3.37 3.37 3.36 3.34 3.32 3.50 3.46 3.44 3.43 3.42 3.39 3.36 3.33 3.55 3.50 3.47 3.46 3.44 3.40 3.37 3.32 2.60 2.59 2.59 2.59 2.59 2.58 2.57 2.56 3.21 3.20 3.20 3.19 3.19 3.18 3.17 3.16 3.30 3.28 3.27 3.26 3.25 3.23 3.21 3.19 3.37 3.32 3.30 3.29 3.28 3.25 3.22 3.19 160 160 160 160 160 160 160 160 5 10 15 20 25 35 50 75 1.54 1.47 1.44 1.41 1.39 1.34 1.30 1.24 2.49 2.34 2.26 2.22 2.17 2.07 1.96 1.85 2.08 1.92 1.84 1.80 1.76 1.67 1.58 1.49 1.55 1.44 1.39 1.37 1.34 1.29 1.25 1.23 2.72 2.71 2.70 2.69 2.69 2.68 2.66 2.64 3.32 3.31 3.30 3.29 3.29 3.28 3.26 3.24 3.43 3.39 3.37 3.36 3.35 3.32 3.28 3.26 3.47 3.43 3.41 3.40 3.38 3.34 3.30 3.25 2.52 2.51 2.51 2.50 2.50 2.49 2.49 2.48 3.12 3.11 3.11 3.10 3.10 3.09 3.09 3.08 3.22 3.20 3.19 3.18 3.17 3.15 3.13 3.12 3.30 3.26 3.24 3.23 3.21 3.18 3.15 3.12 170 170 170 170 170 170 170 170 180 180 180 18 0 180 180 180 180 5 10 15 20 25 35 50 75 5 10 15 20 25 35 50 75 1.41 1.34 1.31 1.29 1.27 1.23 1.19 1.14 1.29 1.23 1.20 1.18 1.16 1.12 1.09 1.03 2.27 2.14 2.07 2.03 1.99 1.90 1.81 1.70 2.10 1.98 1.92 1.88 1.84 1.76 1.67 1.57 1.93 1.78 1.71 1.67 1.63 1.54 1.46 1.37 1.81 1.66 1.59 1.55 1.51 1.43 1.35 1.26 1.44 1.33 1.28 1.26 1.23 1.18 1.14 1.10 1.35 1.24 1.19 1.17 1.14 1.09 1.05 1.01 2.64 2.62 2.62 2.61 2.61 2.60 2.58 2.57 2.57 2.55 2.55 2.54 2.54 2.53 2.51 2.49 3.24 3.22 3.22 3.21 3.21 3.20 3.18 3.17 3.17 3.15 3.15 3.14 3.14 3.13 3.11 3.10 3.37 3.33 3.31 3.30 3.28 3.25 3.22 3.19 3.33 3.28 3.25 3.24 3.23 3.20 3.17 3.13 3.43 3.38 3.35 3.34 3.32 3.28 3.24 3.19 3.37 3.32 3.29 3.28 3.26 3.22 3.19 3.14 2.44 2.43 2.43 2.42 2.42 2.41 2.40 2.40 2.36 2.35 2.35 2.35 2.35 2.34 2.33 2.32 3.04 3.03 3.03 3.02 3.02 3.01 3.01 3.00 2.97 2.96 2.96 2.95 2.95 2.94 2.93 2.92 3.15 3.13 3.12 3.11 3.10 3.08 3.06 3.04 3.09 3.07 3.05 3.04 3.03 3.01 2.99 2.97 3.24 3.20 3.18 3.17 3.15 3.12 3.08 3.05 3.20 3.15 3.12 3.11 3.09 3.06 3.02 2.99 190 190 190 190 190 190 190 190 5 10 15 20 25 35 50 75 1.19 1.13 1.10 1.09 1.07 1.03 1.00 0.96 1.95 1.84 1.78 1.75 1.71 1.63 1.55 1.46 1.69 1.55 1.49 1.45 1.41 1.33 1.26 1.17 1.27 1.16 1.11 1.09 1.06 1.01 0.97 0.91 2.50 2.48 2.48 2.47 2.47 2.46 2.44 2.43 3.11 3.09 3.08 3.07 3.07 3.06 3.04 3.03 3.28 3.23 3.20 3.19 3.17 3.14 3.10 3.07 3.32 3.27 3.24 3.23 3.21 3.17 3.14 3.09 2.29 2.28 2.28 2.27 2.27 2.26 2.26 2.25 2.90 2.89 2.88 2.88 2.88 2.87 2.86 2.85 3.03 3.00 2.98 2.98 2.97 2.95 2.93 2.91 3.15 3.10 3.07 3.06 3.04 3.00 2.97 2.93 200 200 200 200 200 200 200 200 210 210 210 210 210 210 210 210 5 10 15 20 25 35 50 75 5 10 15 20 25 35 50 75 1.10 1.05 1.02 1.01 0.99 0.96 0.92 0.89 1.02 0.97 0.94 0.93 0.92 0.89 0.86 0.82 1.81 1.70 1.65 1.62 1.59 1.52 1.44 1.36 1.69 1.59 1.54 1.51 1.48 1.41 1.35 1.27 1.60 1.46 1.40 1.36 1.33 1.25 1.18 1.10 1.50 1.38 1.32 1.28 1.25 1.18 1.11 1.03 1.20 1.10 1.05 1.02 0.99 0.94 0.89 0.84 1.14 1.04 0.99 0.96 0.93 0.88 0.83 0.78 2.44 2.42 2.42 2.41 2.40 2.39 2.38 2.36 2.38 2.36 2.36 2.35 2.34 2.33 2.32 2.30 3.04 3.02 3.02 3.01 3.01 3.00 2.98 2.96 2.99 2.97 2.96 2.95 2.95 2.94 2.92 2.90 3.23 3.18 3.15 3.14 3.12 3.09 3.06 3.00 3.18 3.13 3.10 3.09 3.07 3.04 3.01 2.95 3.27 3.22 3.19 3.18 3.16 3.12 3.09 3.04 3.23 3.18 3.15 3.13 3.11 3.07 3.04 2.98 2.23 2.22 2.22 2.21 2.21 2.20 2.19 2.18 2.17 2.16 2.15 2.14 2.14 2.13 2.13 2.12 2.83 2.82 2.82 2.81 2.81 2.80 2.79 2.78 2.77 2.76 2.75 2.75 2.75 2.74 2.73 2.72 2.97 2.95 2.93 2.92 2.91 2.89 2.87 2.85 2.92 2.89 2.87 2.87 2.86 2.84 2.81 2.79 3.10 3.05 3.02 3.01 2.99 2.95 2.92 2.88 3.06 3.01 2.98 2.96 2:94 2.90 2.88 2.83 Note: SS - single axle, single -tyres; SD - single axle, dual tyres; TAD - tandem axle, dual tyres; TRD - triple axle, dual tyres 55-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD Table 2.8.2 (Cont.) Equivalent Stresses And Erosion Factors For Pavements With No Concrete Shoulders Slab Effective Thickness CBR of (mm) Subgrade Equivalent Stresses SS SD TAD TRD SS Erosion Factors Undowelled Dowelled or CRC SD TAD TRD SS SD TAD TRD 220 220 220 220 220 220 220 220 5 10 15 20 25 35 50 75 0.94 0.90 0.88 0.87 0.85 0.82 0.79 0.76 1.58 1.49 1.44 1A2 1.39 1.33 1.27 1.19 1.42 1.30 1.25 1.22 1.18 1.11 1.04 0.97 1.08 0.98 0.93 0.91 0.88 0.83 0.79 0.73 2.33 2.31 2.30 2.29 2.29 2.28 2.26 2.24 2.93 2.91 2.90 2.89 2.89 2.88 2.86 2.85 3.14 3.09 3.06 3.05 3.03 2.99 2.96 2.92 3.19 3.13 3.10 3.09 3.07 3.03 3.00 2.95 2.11 2.10 2.09 2.08 2.08 2.07 2.07 2.06 2.71 2.70 2.69 2.69 2.69 2.68 2.67 2.66 2.87 2.84 2.82 2.81 2.80 2.78 2.76 2.72 3.02 2.96 2.93 2.92 2.90 2.86 2.83 2.78 230 230 230 230 230 230 230 230 240 240 240 240 240 240 240 240 5 10 15 20 25 35 50 75 5 10 15 20 25 35 50 75 0.88 0.84 0.82 0.81 0.80 0.77 0.74 0.71 0.82 0.79 0.77 0.76 0.75 0.72 0.69 0.67 1A9 1.24 1.36 1.34 1.31 1.25 1.19 1.12 1.40 1.32 1.28 1.26 1.23 1.17 1.12 1.05 1.35 1.24 1.19 1.16 1.12 1.05 0.99 0.91 1.29 1.18 1.13 1.10 1.06 0.99 0.94 0.86 1.03 0.94 0.89 0.87 0.84 0.78 0.74 0.70 0.98 0.89 0.85 0.83 0.80 0.74 0.70 0.66 2.28 2.26 2.25 2.24 2.23 2.21 2.20 2.19 2.23 2.21 2.20 2.19 2.18 2.17 2.15 2.13 2.88 2.86 2.85 2.84 2.83 2.81 2.80 2.79 2.83 2.81 2.80 2.79 2.78 2.76 2.75 2.74 3.10 3.05 3.02 3.00 2.98 2.94 2.91 2.86 3.08 3.01 2.98 2.96 2.94 2.90 2.86 2.83 3.14 3.09 3.06 3.05 3.03 2.99 2.95 2.91 3.11 3.05 3.02 3.01 2.99 2.95 2.91 2.86 2.05 2.04 2.03 2.03 2.03 2.02 2.01 2.00 1.99 1.98 1.98 1.97 1.97 1.96 1.95 1.94 2.65 2.64 2.64 2.63 2.63 2.62 2.61 2.60 2.60 2.59 2.58 2.57 2.57 2.56 2.55 2.54 2.82 2.79 2.77 2.76 2.75 2.73 2.70 2.68 2.78 2.74 2.72 2.72 2.71 2.69 2.66 2.63 2.98 2.92 2.89 2.88 2.86 2.82 2.78 2.74 2.94 2.88 2.85 2.84 2.82 2.78 2.74 2.69 250 250 250 250 250 250 250 250 5 10 15 20 25 35 50 75 0.77 0.74 0.72 0.71 0.70 0.68 0.65 0.63 1.33 1.25 1.21 1.18 1.16 1.11 1.06 0.99 1.23 1.12 1.07 1.04 1.01 0.95 0.89 0.82 0.94 0.86 0.81 0.79 0.76 0.71 0.67 0.61 2.18 2.16 2.15 2.14 2.13 2.12 2.10 2.08 2.78 2.76 2.75 2.74 2.73 2.71 2.70 2.69 3.02 2.97 2.94 2.93 2.91 2.87 2.83 2.79 3.07 3.01 2.98 2.97 2.95 2.91 2.88 2.83 1.94 1.93 1.93 1.92 1.92 1.91 1.90 1.89 2.54 2.53 2.53 2.52 2.52 2.51 2.50 2.49 2.73 2.70 2.68 2.67 2.66 2.64 2.61 2.59 2.90 2.65 2.82 2.80 2.78 2.74 2.70 2.65 260 260 280 260 260 260 260 260 5 10 15 20 25 35 50 75 0.73 0.70 0.68 0.67 0.66 0.64 0.61 0.59 1.26 1.18 1.15 1.12 1.10 1.05 1.00 0.95 1.18 1.08 1.03 1.00 0.97 0.91 0.85 0.78 0.90 0.82 0.78 0.75 0.73 0.68 0.64 0.58 2.13 2.11 2.10 2.09 2.08 2.07 2.05 2.03 2.73 2.71 2.70 2.69 2.69 2.68 2.65 2.64 2.99 2.93 2.90 2.89 2.87 2.83 2.80 2.75 3.03 2.98 2.95 2.93 2.91 2.87 2.84 2.78 1.89 1.88 1.88 1.87 1.87 1.86 1.85 1.84 2.49 2.48 2.48 2.47 2.47 2.46 2.45 2.44 2.69 2.66 2.64 2.63 2.62 2.59 2.56 2.54 2.87 2.81 2.78 2.76 2.74 2.70 2.67 2.61 270 270 270 270 270 270 270 270 5 10 15 20 25 35 50 75 0.66 0.66 0.64 0.63 0.62 0.60 0.58 0.56 1.19 1.12 1.09 1.06 1.04 0.99 0.95 0.89 1.13 1.03 0.98 0.96 0.93 0.87 0.81 0.74 0.87 0.79 0.75 0.72 0.70 0.65 0.61 0.57 2.09 2.07 2.06 2.05 2.04 2.02 2.00 1.99 2.69 2.67 2.66 2.65 2.64 2.63 2.61 2.59 2.95 2.90 2.87 2.85 2.83 2.79 2.76 2.70 3.00 2.94 2.91 2.90 2.88 2.84 2.80 2.75 1.84 1.83 1.83 1.82 1.82 1.81 1.80 1.79 2.44 2.43 2.43 2.42 2.42 2.41 2.40 2.39 2.65 2.62 2.60 2.59 2.58 2.55 2.52 2.50 2.83 2.78 2.75 2.73 2.71 2.67 2.63 2.58 280 280 280 280 280 280 280 280 5 10 15 20 25 35 50 75 0.65 0.62 0.60 0.60 0.59 0.57 0.55 0.53 1.13 1.06 1.03 1.01 0.99 0.94 0.90 0.86 1.08 0.99 0.94 0.92 0.89 0.83 0.78 0.71 0.83 0.75 0.72 0.69 0.67 0.62 0.59 0.53 2.05 2.03 2.01 2.00 1.99 1.97 1.96 1.94 2.65 2.63 2.62 2.61 2.60 2.58 2.56 2.55 2.92 2.86 2.83 2.82 2.80 2.76 2.72 2.68 2.97 2.91 2.88 2.87 2.85 2.81 2.77 2.72 1.60 1.79 1.78 1.77 1.77 1.76 1.75 1.74 2.40 2.39 2.38 2.37 2.37 2.36 2.35 2.34 2.62 2.58 2.58 2.55 2.54 2.51 2.48 2.46 2.80 2.74 2.71 2.70 2.68 2.64 2.60 2.55 Note: SS - single axle, single tyres; SD - single axle, dual tyres; TAD - tandem axle, dual tyres; TRD - triple axle, dual tyres ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 56-97 ROAD DESIGN STANDARD Table 2.8.2 (Cont) Equivalent Stresses And Erosion Factors For Pavements With No Concrete Shoulders Slab Effective Thickness CBR of (mm) Subgrade Equivalent Stresses SS SD TAD TRD SS Erosion Factors Undowelled Dowelled or CRC SD TAD TRD SS SD TAD TRD 290 290 290 290 290 290 290 290 5 10 15 20 25 35 50 75 0.61 0.59 0.58 0.57 0.56 0.54 0.52 0.50 1.08 1.01 0.98 0.96 0.94 0.90 0.86 0.81 1.04 0.95 0.90 0.88 0.85 0.80 0.75 0.68 0.80 0.73 0.70 0.67 0.65 0.60 0.56 0.52 2.01 1.99 1.97 1.96 1.95 1.93 1.92 1.90 2.61 2.59 2.58 2.57 2.56 2.54 2.52 2.50 2.89 2.83 2.80 2.79 2.77 2.73 2.69 2.64 2.93 2.88 2.85 2.83 2.81 2.77 2.74 2.68 1.75 1.74 1.74 1.73 1.73 1.72 1.71 1.70 2.35 2.34 2.34 2.33 2.33 2.32 2.31 2.30 2.58 2.54 2.52 2.51 2.50 2.47 2.44 2.42 2.77 2.71 2.68 2.67 2.65 2.61 2.56 2.51 300 300 300 300 300 300 300 300 5 10 15 20 25 35 50 75 0.58 0.56 0.55 0.54 0.53 0.51 0.49 0.47 1.03 0.97 0.94 0.92 0.90 0.86 0.82 0.78 1.00 0.91 0.87 0.85 0.82 0.77 0.72 0.65 0.77 0.70 0.67 0.65 0.63 0.58 0.54 0.50 1.97 1.95 1.93 1.92 1.91 1.89 1.88 1.86 2.57 2.55 2.54 2.53 2.52 2.50 2.48 2.46 2.86 2.80 2.77 2.76 2.74 2.70 2.66 2.61 2.90 2.85 2.82 2.80 2.78 2.74 2.70 2.65 1.71 1.70 1.69 1.68 1.68 1.67 1.66 1.65 2.31 2.30 2.30 2.29 2.29 2.28 2.26 2.26 2.55 2.51 2.49 2.48 2.46 2.43 2.41 2.37 2.74 2.68 2.65 2.64 2.62 2.58 2.53 2.48 310 310 310 310 310 310 310 310 5 10 15 20 25 35 50 75 0.55 0.53 0.52 0.51 0.50 0.49 0.47 0.45 0.98 0.92 0.89 0.88 0.86 0.82 0.78 0.74 0.97 0.89 0.84 0.82 0.79 0.74 0.69 0.63 0.74 0.68 0.65 0.63 0.60 0.55 0.51 0.48 1.94 1.91 1.89 1.89 1.88 1.86 1.84 1.82 2.54 2.51 2.49 2.49 2.48 2.46 2.44 2.42 2.83 2.77 2.74 2.73 2.71 2.67 2.63 2.58 2.88 2.82 2.79 2.77 2.75 2.71 2.67 2.62 1.67 1.66 1.65 1.64 1.64 1.63 1.62 1.61 2.27 2.26 2.25 2.24 2.24 2.23 2.22 2.21 2.51 2.47 2.45 2.44 2.43 2.40 2.37 2.34 2.71 2.65 2.62 2.61 2.59 2.55 2.50 2.45 320 320 320 320 320 320 320 320 5 10 15 20 25 35 50 75 0.53 0.51 0.50 0.49 0.48 0.46 0.44 0.43 0.94 0.88 0.85 0.84 0.82 0.78 0.75 0.71 0.93 0.85 0.81 0.79 0.76 0.71 0.67 0.61 0.71 0.65 0.62 0.60 0.58 0.54 0.51 0.45 1.90 1.87 1.85 1.85 1.84 1.82 1.80 1.78 2.50 2.48 2.46 2.45 2.44 2.42 2.40 2.38 2.80 2.74 2.71 2.70 2.68 2.64 2.60 2.55 2.85 2.79 2.76 2.74 2.72 2.68 2.64 2.59 1.63 1.62 1.61 1.60 1.60 1.59 1.58 1.57 2.23 2.22 2.21 2.20 2.20 2.19 2.18 2.17 2.48 2.44 2.42 2.41 2.40 2.37 2.33 2.31 2.89 2.63 2.60 2.58 2.56 2.52 2.47 2.42 330 330 330 330 330 330 330 330 5 10 15 20 25 35 50 75 0.50 0.48 0.47 0.46 0.46 0.45 0.42 0.41 0.90 0.85 0.82 0.80 0.78 0.74 0.71 0.68 0.90 0.82 0.79 0.76 0.74 0.69 0.64 0.59 0.69 0.63 0.60 0.58 0.56 0.52 0.48 0.45 1.87 1.84 1.82 1.81 1.80 1.78 1.76 1.74 2.47 2.44 2.42 2.42 2.41 2.39 2.36 2.35 2.78 2.72 2.69 2.67 2.65 2.61 2.57 2.52 2.82 2.76 2.73 2.72 2.70 2.66 2.62 2.57 1.59 1.58 1.57 1.56 1.56 1.55 1.54 1.53 2.19 2.18 2.17 2.16 2.16 2.15 2.14 2.13 2.45 2.41 2.39 2.38 2.36 2.33 2.30 2.28 2.66 2.60 2.57 2.55 2.53 2.49 2.45 2.40 340 340 340 340 340 340 340 340 5 10 15 20 25 35 50 75 0.48 0.46 0.45 0.44 0.44 0.43 0.40 0.39 0.86 0.80 0.78 0.77 0.75 0.72 0.68 0.65 0.87 0.79 0.76 0.73 0.71 0.66 0.62 0.56 0.65 0.61 0.58 0.57 0.55 0.51 0.47 0.43 1.84 1.81 1.79 1.78 1.77 1.75 1.73 1.71 2.44 2.41 2.39 2.38 2.37 2.35 2.33 2.31 2.75 2.69 2.66 2.64 2.62 2.58 2.54 2.49 2.79 2.74 2.71 2.69 2.67 2.63 2.59 2.54 1.55 1.54 1.53 1.52 1.52 1.51 1.50 1.49 2.15 2.14 2.14 2.13 2.12 2.11 2.10 2.09 2.42 2.38 2.36 2.35 2.33 2.30 2.27 2.24 2.63 2.57 2.54 2.52 2.50 2.46 2.42 2.37 350 350 350 350 350 350 350 350 5 10 15 20 25 35 50 75 0.46 0.44 0.43 0.42 0.42 0.41 0.39 0.37 0.83 0.78 0.75 0.74 0.72 0.69 0.65 0.62 0.85 0.77 0.74 0.71 0.69 0.64 0.60 0.54 0.63 0.59 0.56 0.55 0.53 0.49 0.46 0.42 1.80 1.77 1.75 1.75 1.74 1.72 1.69 1.67 2.41 2.38 2.36 2.35 2.34 2.32 2.29 2.28 2.72 2.67 2.64 2.62 2.60 2.56 2.52 2.47 2.77 2.71 2.68 2.66 2.64 2.60 2.56 2.51 1.51 1.50 1.50 1.49 1.49 1.48 1.46 1.46 2.11 2.10 2.10 2.09 2.09 2.08 2.07 2.06 2.39 2.35 2.33 2.32 2.30 2.27 2.24 2.21 2.61 2.55 2.52 2.50 2.48 2.44 2.39 2.34 Note: SS - single axle, single tyres; SD - single axle, dual tyres; TAD - tandem axle, dual tyres; TRO - triple axle, dual tyres 57-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD Table2.8.3 Equivalent Stresses And Erosion Factors For Pavements With Concrete Shoulders Slab Effective Thickness CBR of (mm) Subgrade Equivalent Stresses SS SD TAD TRD SS Erosion Factors Undowelled Dowelled or CRC SD TAD TRD SS SD TAD TRD 150 150 150 150 150 150 150 150 5 10 15 20 25 35 50 75 1.42 1.36 1.33 1.32 1.30 1.27 1.23 1.20 2.16 2.04 1.98 1.94 1.90 1.82 1.74 1.65 1.81 1.70 1.65 1.62 1.59 1.53 1.49 1.43 1.45 1.39 1.36 1.35 1.33 1.30 1.27 1.26 2.34 2.32 2.32 2.31 2.30 2.29 2.27 2.25 2.94 2.92 2.92 2.91 2.90 2.89 2.87 2.85 2.99 2.94 2.91 2.90 2.88 2.85 2.82 2.79 3.00 2.94 2.91 2.90 2.88 2.84 2.81 2.77 2.14 2.13 2.12 2.11 2.10 2.08 2.06 2.04 2.74 2.72 2.72 2.71 2.70 2.69 2.67 2.65 2.78 2.73 2.70 2.69 2.67 2.64 2.60 2.57 2.81 2.75 2.72 2.70 2.67 2.63 2.59 2.56 160 160 160 160 160 160 160 160 5 10 15 20 25 35 50 75 1.29 1.24 1.21 1.20 1.18 1.15 1.12 1.10 1.98 1.87 1.82 1.79 1.75 1.67 1.60 1.52 1.67 1.56 1.51 1.49 1.46 1.41 1.36 1.30 1.33 1.26 1.23 1.21 1.20 1.17 1.15 1.13 2.26 2.24 2.24 2.23 2.23 2.22 2.20 2.18 2.87 2.85 2.84 2.83 2.83 2.82 2.80 2.78 2.93 2.88 2.85 2.84 2.82 2.79 2.75 2.72 2.95 2.89 2.86 2.84 2.82 2.78 2.75 2.69 2.06 2.04 2.04 2.03 2.02 2.00 1.98 1.97 2.66 2.64 2.64 2.63 2.62 2.61 2.59 2.57 2.72 2.67 2.64 2.62 2.60 2.56 2.53 2.50 2.77 2.69 2.66 2.64 2.62 2.57 2.53 2.49 170 170 170 170 170 170 170 170 5 10 15 20 25 35 50 75 1.17 1.13 1.11 1.10 1.08 1.05 1.03 1.02 1.83 1.73 1.68 1.65 1.62 1.55 1.49 1.41 1.55 1.45 1.40 1.38 1.35 1.30 1.25 1.19 1.22 1.16 1.13 1.12 1.10 1.07 1.04 1.03 2.19 2.17 2.17 2.16 2.16 2.15 2.13 2.11 2.80 2.78 2.77 2.76 2.76 2.75 2.73 2.71 2.88 2.83 2.80 2.79 2.77 2.73 2.70 2.66 2.90 2.84 2.81 2.79 2.77 2.73 2.70 2.64 1.99 1.97 1.96 1.95 1.95 1.94 1.91 1.89 2.59 2.57 2.57 2.56 2.55 2.53 2.51 2.49 2.66 2.61 2.58 2.57 2.55 2.51 2.47 2.43 2.72 2.64 2.61 2.59 2.57 2.53 2.48 2.43 180 180 180 180 180 180 180 180 5 10 15 20 25 35 50 75 1.07 1.03 1.01 1.01 1.00 0.98 0.95 0.94 1.70 1.60 1.55 1.53 1.50 1.44 1.38 1.31 1.44 1.35 1.30 1.28 1.25 1.20 1.16 1.10 1.13 1.07 1.04 1.03 1.01 0.98 0.96 0.94 2.13 2.11 2.10 2.09 2.09 2.08 2.06 2.04 2.73 2.71 2.71 2.70 2.69 2.68 2.66 2.64 2.83 2.78 2.75 2.73 2.71 2.67 2.64 2.61 2.86 2.79 2.76 2.74 2.72 2.68 2.64 2.60 1.92 1.90 1.89 1.88 1.88 1.87 1.84 1.82 2.52 2.50 2.50 2.49 2.48 2.46 2.44 2.42 2.61 2.56 2.53 2.51 2.49 2.45 2.42 2.36 2.68 2.60 2.57 2.54 2.52 2.47 2.42 2.37 190 190 190 190 190 190 190 190 5 10 15 20 25 35 50 75 0.99 0.96 0.94 0.93 0.92 0.90 0.88 0.87 1.58 1.49 1.44 1.42 1.40 1.35 1.29 1.22 1.35 1.26 1.21 1.19 1.17 1.12 1.08 1.02 1.05 0.99 0.97 0.96 0.94 0.91 0.88 0.86 2.07 2.05 2.04 2.03 2.03 2.02 2.00 1.98 2.67 2.65 2.64 2.63 2.63 2.62 2.60 2.58 2.78 2.72 2.70 2.69 2.67 2.63 2.60 2.55 2.82 2.75 2.72 2.70 2.68 2.64 2.60 2.55 1.86 1.84 1.83 1.82 1.81 1.79 1.77 1.76 2.46 2.44 2.43 2.42 2.41 2.40 2.38 2.36 2.57 2.51 2.48 2.46 2.44 2.40 2.36 2.32 2.64 2.56 2.53 2.50 2.48 2.43 2.38 2.31 200 200 200 200 200 200 200 200 5 10 15 20 25 35 50 75 0.91 0.89 0.87 0.86 0.85 0.83 0.82 0.81 1.47 1.39 1.35 1.33 1.30 1.25 1.20 1.14 1.27 1.18 1.15 1.12 1.10 1.05 1.01 0.95 0.99 0.93 0.90 0.89 0.87 0.84 0.82 0.80 2.01 1.99 1.98 1.97 1.97 1.96 1.94 1.92 2.61 2.59 2.59 2.58 2.57 2.56 2.54 2.52 2.74 2.69 2.66 2.64 2.62 2.58 2.54 2.51 2.78 2.71 2.68 2.66 2.64 2.60 2.55 2.50 1.80 1.78 1.77 1.76 1.75 1.73 1.71 1.69 2.40 2.38 2.37 2.36 2.35 2.33 2.31 2.30 2.52 2.46 2.43 2.42 2.40 2.36 2.32 2.27 2.60 2.52 2.49 2.46 2.44 2.39 2.33 2.28 210 210 210 210 210 210 210 210 5 10 15 20 25 35 50 75 0.85 0.82 0.80 0.80 0.79 0.77 0.76 0.75 1.38 1.30 1.27 1.24 1.22 1.17 1.13 1.07 1.20 1.11 1.08 1.05 1.03 0.98 0.94 0.90 0.93 0.87 0.84 0.83 0.81 0.78 0.76 0.74 1.96 1.94 1.93 1.92 1.91 1.90 1.88 1.86 2.56 2.54 2.53 2.52 2.51 2.49 2.48 2.47 2.70 2.65 2.62 2.60 2.58 2.54 2.51 2.45 2.75 2.67 2.64 2.62 2.60 2.56 2.51 2.46 1.74 1.72 1.71 1.70 1.69 1.67 1.65 1.64 2.34 2.32 2.31 2.30 2.29 2.28 2.26 2.24 2.48 2.42 2.39 2.37 2.35 2.31 2.27 2.22 2.57 2.49 2.45 2.43 2.40 2.34 2.29 2.22 Note: SS - single axle, single tyres; SD - single axle, dual tyres; TAD - tandem axle, dual tyres; TRO - triple axle, dual tyres ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 58-97 ROAD DESIGN STANDARD Table2.8.3 (Cont.) Equivalent Stresses And Erosion Factors For Pavements With Concrete Shoulders Slab Effective Thickness CBR of (mm) Subgrade Equivalent Stresses SS SD TAD TRD SS Erosion Factors Undowelled Dowelled or CRC SD TAD TRD SS SD TAD TRD 220 220 220 220 220 220 220 220 5 10 15 20 25 35 50 75 0.79 0.77 0.76 0.75 0.74 0.72 0.71 0.70 1.30 1.22 1.19 1.17 1.15 1.11 1.06 1.01 1.13 1.05 1.02 0.99 0.97 0.92 0.88 0.85 0.87 0.81 0.79 0.78 0.76 0.73 0.71 0.69 1.91 1.89 1.88 1.87 1.86 1.85 1.83 1.81 2.51 2.49 2.48 2.47 2.46 2.45 2.43 2.41 2.67 2.61 2.58 2.56 2.54 2.50 2.47 2.41 2.72 2.64 2.61 2.58 2.56 2.52 2.48 2.41 1.68 1.66 1.66 1.65 1.64 1.62 1.60 1.58 2.29 2.27 2.26 2.25 2.24 2.22 2.20 2.18 2.44 2.38 2.35 2.33 2.31 2.27 2.23 2.18 2.54 2.46 2.42 2.39 2.37 2.32 2.26 2.19 230 230 230 230 230 230 230 230 5 10 15 20 25 35 50 75 0.74 0.72 0.71 0.70 0.69 0.68 0.67 0.66 1.22 1.15 1.12 1.10 1.08 1.04 1.00 0.96 1.08 1.00 0.97 0.94 0.92 0.87 0.83 0.80 0.82 0.77 0.75 0.74 0.72 0.69 0.67 0.65 1.86 1.84 1.83 1.82 1.81 1.80 1.78 1.76 2.46 2.44 2.43 2.42 2.41 2.40 2.38 2.36 2.63 2.57 2.54 2.52 2.50 2.46 2.43 2.37 2.69 2.61 2.58 2.55 2.53 2.48 2.44 2.37 1.63 1.61 1.60 1.59 1.58 1.56 1.54 1.53 2.23 2.21 2.21 2.20 2.19 2.17 2.15 2.13 2.40 2.34 2.31 2.29 2.27 2.23 2.19 2.12 2.50 2.42 2.39 2.36 2.34 2.28 2.22 2.16 240 240 240 240 240 240 240 240 5 10 15 20 25 35 50 75 0.69 0.67 0.66 0.65 0.65 0.64 0.63 0.62 1.16 1.09 1.06 1.04 1.02 0.98 0.95 0.89 1.02 0.95 0.92 0.89 0.87 0.83 0.79 0.76 0.78 0.72 0.70 0.69 0.68 0.66 0.63 0.61 1.81 1.79 1.78 1.77 1.76 1.75 1.73 1.71 2.41 2.39 2.38 2.37 2.36 2.35 2.33 2.31 2.60 2.54 2.51 2.49 2.47 2.43 2.39 2.34 2.66 2.58 2.55 2.52 2.50 2.45 2.41 2.34 1.58 1.56 1.55 1.54 1.53 1.51 1.49 1.48 2.18 2.17 2.15 2.14 2.13 2.11 2.10 2.08 2.36 2.30 2.27 2.25 2.23 2.19 2.15 2.10 2.47 2.39 2.36 2.33 2.31 2.25 2.19 2.13 250 250 250 250 250 250 250 250 5 10 15 20 25 35 50 75 0.65 0.63 0.62 0.61 0.61 0.60 0.59 0.58 1.09 1.03 1.00 0.99 0.97 0.93 0.90 0.86 0.98 0.90 0.87 0.85 0.83 0.79 0.75 0.72 0.73 0.69 0.67 0.66 0.64 0.61 0.59 0.57 1.77 1.74 1.73 1.72 1.72 1.71 1.68 1.66 2.37 2.35 2.34 2.33 2.32 2.30 2.28 2.27 2.56 2.50 2.47 2.45 2.43 2.39 2.36 2.30 2.63 2.55 2.52 2.49 2.47 2.42 2.38 2.31 1.54 1.52 1.50 1.49 1.48 1.46 1.44 1.43 2.14 2.12 2.11 2.10 2.09 2.07 2.05 2.03 2.32 2.26 2.23 2.22 2.20 2.16 2.11 2.06 2.45 2.37 2.33 2.30 2.28 2.22 2.16 2.10 260 260 260 260 260 260 260 260 5 10 15 20 25 35 50 75 0.61 0.60 0.59 0.58 0.57 0.56 0.56 0.55 1.04 0.98 0.95 0.94 0.92 0.88 0.85 0.81 0.93 0.86 0.83 0.81 0.79 0.75 0.71 0.68 0.71 0.66 0.63 0.62 0.61 0.59 0.56 0.54 1.72 1.70 1.69 1.68 1.67 1.66 1.64 1.62 2.33 2.30 2.28 2.28 2.27 2.26 2.24 2.22 2.53 2.47 2.44 2.42 2.40 2.36 2.32 2.27 2.61 2.53 2.49 2.46 2.44 2.39 2.35 2.28 1.49 1.47 1.46 1.45 1.44 1.42 1.40 1.38 2.09 2.07 2.06 2.05 2.04 2.02 2.00 1.98 2.29 2.23 2.20 2.18 2.16 2.12 2.08 2.01 2.42 2.34 2.30 2.28 2.25 2.19 2.13 2.06 270 270 270 270 270 270 270 270 5 10 15 20 25 35 50 75 0.57 0.55 0.55 0.54 0.54 0.53 0.53 0.52 0.99 0.93 0.90 0.89 0.87 0.84 0.80 0.77 0.89 0.83 0.80 0.78 0.76 0.72 0.68 0.65 0.66 0.62 0.60 0.59 0.58 0.56 0.53 0.52 1.68 1.66 1.65 1.64 1.63 1.61 1.59 1.58 2.28 2.26 2.25 2.24 2.23 2.22 2.20 2.18 2.50 2.44 2.41 2.39 2.37 2.33 2.29 2.24 2.58 2.50 2.47 2.44 2.42 2.37 2.32 2.25 1.45 1.43 1.41 1.40 1.39 1.37 1.35 1.34 2.05 2.03 2.02 2.01 2.00 1.98 1.96 1.94 2.25 2.20 2.17 2.15 2.13 2.09 2.04 1.99 2.39 2.31 2.27 2.25 2.22 2.16 2.11 2.03 280 280 280 280 280 280 280 280 5 10 15 20 25 35 50 75 0.54 0.52 0.52 0.51 0.51 0.50 0.50 0.49 0.94 0.89 0.86 0.85 0.83 0.80 0.76 0.74 0.86 0.79 0.76 0.74 0.73 0.69 0.66 0.62 0.63 0.60 0.58 0.57 0.56 0.54 0.51 0.49 1.64 1.62 1.61 1.60 1.59 1.57 1.55 1.54 2.25 2.22 2.20 2.20 2.19 2.18 2.16 2.14 2.48 2.41 2.38 2.36 2.34 2.30 2.26 2.21 2.56 2.48 2.44 2.42 2.39 2.34 2.29 2.22 1.40 1.38 1.37 1.36 1.35 1.33 1.31 1.29 2.01 1.99 1.97 1.96 1.95 1.93 1.91 1.89 2.22 2.16 2.13 2.12 2.10 2.06 2.01 1.96 2.37 2.29 2.25 2.22 2.20 2.14 2.08 2.00 Note: SS - single axle, single tyres; SD - single axle, dual tyres; TAD - tandem axle, dual tyres; TRD - triple axle. dual tyre 59-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD Table2.8.3 (Cont) Equivalent Stresses And Erosion Factors For Pavements With Concrete Shoulders Slab Effective Thickness CBR of (mm) Subgrade Equivalent Stresses SS SD TAD TRD SS Erosion Factors Undowelled Dowelled or CRC SD TAD TRD SS SD TAD TRD 290 290 290 290 290 290 290 290 5 10 15 20 25 35 50 75 0.51 0.50 0.50 0.49 0.49 0.48 0.47 0.47 0.90 0.85 0.82 0.81 0.79 0.76 0.73 0.70 0.82 0.76 0.73 0.72 0.70 0.66 0.63 0.60 0.60 0.57 0.55 0.54 0.53 0.51 0.49 0.47 1.61 1.58 1.56 1.56 1.55 1.53 1.51 1.50 2.21 2.18 2.16 2.16 2.15 2.14 2.12 2.10 2.45 2.39 2.36 2.34 2.32 2.28 2.23 2.18 2.54 2.46 2.42 2.39 2.37 2.32 2.27 2.19 1.36 1.34 1.33 1.32 1.31 1.29 1.27 1.25 1.97 1.94 1.92 1.92 1.91 1.89 1.87 1.85 2.19 2.13 2.10 2.08 2.06 2.02 1.98 1.93 2.34 2.26 2.22 2.20 2.17 2.11 2.05 1.98 300 300 300 300 300 300 300 300 5 10 15 20 25 35 50 75 0.49 0.48 0.47 0.46 0.46 0.46 0.45 0.45 0.86 0.81 0.78 0.77 0.76 0.73 0.70 0.67 0.79 0.73 0.70 0.69 0.67 0.64 0.60 0.57 0.58 0.55 0.53 0.52 0.51 0.49 0.46 0.45 1.57 1.55 1.53 1.52 1.51 1.49 1.48 1.46 2.17 2.15 2.14 2.13 2.12 2.10 2.08 2.06 2.42 2.36 2.33 2.31 2.29 2.25 2.20 2.15 2.52 2.44 2.40 2.37 2.35 2.30 2.24 2.17 1.32 1.30 1.29 1.28 1.27 1.25 1.23 1.21 1.93 1.91 1.89 1.88 1.87 1.85 1.83 1.81 2.16 2.10 2.07 2.05 2.03 1.99 1.95 1.90 2.32 2.24 2.20 2.18 2.15 2.09 2.03 1.95 310 310 310 310 310 310 310 310 5 10 15 20 25 35 50 75 0.46 0.45 0.45 0.44 0.44 0.43 0.43 0.42 0.81 0.77 0.75 0.74 0.72 0.69 0.67 0.63 0.76 0.70 0.68 0.66 0.64 0.61 0.58 0.54 0.55 0.52 0.50 0.50 0.49 0.47 0.44 0.43 1.54 1.51 1.49 1.49 1.48 1.46 1.44 1.42 2.14 2.11 2.09 2.09 2.08 2.06 2.04 2.02 2.40 2.33 2.30 2.28 2.26 2.22 2.18 2.13 2.50 2.42 2.38 2.35 2.33 2.28 2.22 2.15 1.29 1.27 1.25 1.24 1.23 1.21 1.19 1.17 1.89 1.87 1.86 1.85 1.84 1.82 1.79 1.77 2.13 2.07 2.04 2.03 2.01 1.97 1.92 1.87 2.30 2.22 2.18 2.15 2.13 2.07 2.01 1.93 320 320 320 320 320 320 320 320 5 10 15 20 25 35 50 75 0.44 0.43 0.43 0.42 0.42 0.41 0.41 0.41 0.78 0.74 0.72 0.71 0.69 0.66 0.64 0.62 0.74 0.68 0.65 0.64 0.62 0.59 0.55 0.53 0.53 0.50 0.48 0.48 0.47 0.45 0.43 0.41 1.50 1.48 1.46 1.45 1.44 1.42 1.41 1.39 2.11 2.08 2.06 2.06 2.05 2.03 2.01 1.99 2.37 2.31 2.28 2.26 2.24 2.20 2.15 2.10 2.48 2.40 2.36 2.33 2.31 2.26 2.20 2.12 1.25 1.23 1.22 1.21 1.20 1.18 1.15 1.13 1.85 1.83 1.82 1.81 1.80 1.78 1.76 1.74 2.10 2.05 2.02 2.00 1.98 1.94 1.89 1.84 2.27 2.19 2.15 2.13 2.10 2.04 1.98 1.91 330 330 330 330 330 330 330 330 5 10 15 20 25 35 50 75 0.42 0.41 0.41 0.40 0.40 0.39 0.39 0.39 0.74 0.71 0.69 0.68 0.67 0.64 0.61 0.59 0.71 0.65 0.63 0.62 0.60 0.57 0.53 0.51 0.51 0.48 0.46 0.46 0.45 0.43 0.41 0.39 1.47 1.44 1.42 1.42 1.41 1.39 1.37 1.35 2.07 2.05 2.03 2.02 2.01 1.99 1.97 1.95 2.35 2.29 2.26 2.24 2.21 2.17 2.13 2.06 2.46 2.38 2.34 2.31 2.29 2.24 2.18 2.10 1.22 1.19 1.17 1.17 1.16 1.14 1.12 1.10 1.82 1.79 1.77 1.77 1.76 1.74 1.72 1.70 2.07 2.02 1.99 1.97 1.95 1.91 1.87 1.80 2.25 2.17 2.13 2.11 2.08 2.02 1.96 1.88 340 340 340 340 340 340 340 340 5 10 15 20 25 35 50 75 0.40 0.39 0.39 0.38 0.38 0.37 0.37 0.37 0.71 0.68 0.66 0.65 0.64 0.62 0.59 0.57 0.69 0.64 0.61 0.60 0.58 0.55 0.52 0.49 0.49 0.47 0.45 0.44 0.43 0.41 0.39 0.38 1.44 1.41 1.39 1.39 1.38 1.36 1.34 1.32 2.04 2.02 2.00 1.99 1.98 1.96 1.94 1.92 2.33 2.26 2.23 2.21 2.19 2.15 2.10 2.05 2.44 2.36 2.32 2.29 2.27 2.22 2.16 2.08 1.18 1.16 1.15 1.14 1.13 1.11 1.08 1.06 1.78 1.76 1.75 1.74 1.73 1.71 1.69 1.67 2.05 1.99 1.96 1.94 1.92 1.88 1.84 1.79 2.23 2.15 2.11 2.09 2.06 2.00 1.94 1.86 350 350 350 350 350 350 350 350 5 10 15 20 25 35 50 75 0.38 0.37 0.37 0.36 0.36 0.36 0.36 0.35 0.69 0.65 0.63 0.62 0.61 0.59 0.57 0.55 0.67 0.62 0.59 0.58 0.56 0.53 0.50 0.47 0.47 0.45 0.44 0.43 0.42 0.40 0.38 0.36 1.41 1.38 1.36 1.36 1.35 1.33 1.31 1.29 2.01 1.98 1.96 1.96 1.95 1.93 1.91 1.89 2.31 2.24 2.21 2.19 2.17 2.13 2.08 2.03 2.43 2.35 2.30 2.28 2.25 2.19 2.14 2.06 1.15 1.13 1.11 1.10 1.09 1.07 1.05 1.03 1.75 1.73 1.71 1.70 1.69 1.67 1.65 1.63 2.02 1.97 1.94 1.92 1.90 1.86 1.81 1.76 2.21 2.13 2.09 2.07 2.04 1.98 1.92 1.84 Note: SS - single axle, single tyres; SD - single axle, dual tyres; TAD - tandem axle, dual tyres; TRD - triple axle. dual tyres ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 60-97 ROAD DESIGN STANDARD 2.8.4.3 Minimum Base Thickness Irrespective of the base thickness determined in accordance with procedure, the minimum allowable thickness of concrete base to be trafficked by commercial vehicles shoulder be: (i) 150 mm; except for (ii) steel – fibre reinforced concrete where the minimum thickness of base should be not less than 125 mm. These minimum thickness of concrete base also apply to asphalt surfaced rigid pavements. 2.8.4.4 Provision of Dowels and Tie Bars The thickness design procedure provides for the option of dowelled or undowelled contraction joints, as well as the option of adopting concrete shoulders (defined in Section 2.8.3.5 ). 2.8.4.4.1 Dowels Dowel bars are to be plain steel bars of Grade 250R and 450 mm long. Dowels should be straight with one and free from burrs. Appropriate dowel diameters are given in Table 2.8.4. Dowels at a spacing 300 mm should be installed at transverse contraction joints where applicable. Dowels must be securely held parallel to each other, to the road centreline and to the centreline of surface of the finished pavement. More than half of the smooth end of the dowels should be coated with a debonding agent to ensure lack of bond to the concrete on that side of the joint. Table 2.8.4 Appropriate Dowel Diameters Slab Thickness mm *Dowel Diameter mm 20 125 < h ≤ 140 24 140 < h ≤ 160 28 160 < h ≤ 190 33 190 < h ≤ 220 36 220 < h ≤ 250 * AS 2338 preferred dimensions of wrought metal products 2.8.4.4.2 Tie Bars Tie bars prevent separation of the pavement at longitudinal joints, allowing warping or curling to occur without excessive restraint. Tie bars are to be 12 mm diameter Grade 400 Y deformed steel bars, one metre long, placed centrally in the joint at spacing determined from Figure 2.8.7. A coefficient of friction of 1.5 ( between base and sub-base ) is assumed in Figure 2.8.7. Table 2.8.5 gives indicative values of the coefficient of friction for different bond-breaking systems. For the coefficient of friction of 1.0 an increase of 30 % in the spacing given in Figure 2.8.7 is required and a coefficient of 2.0 requires a 30 % reduction in the spacing derived from Figure 2.8.7. 61-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD Table 2.8.5 Values of Coefficient of Friction Coefficient of Friction 1.0 1.5 2.0 2.8.5 Bond-breaking system A bituminous sprayed seal applied to the sub base surface A thin coat of wax debonding agent applied to the sub base surface A chlorinated rubber curing compound applied to the sub base surface or use of an asphalt sub base REINFORCEMENT DESIGN PROCEDURES The purpose of reinforcing steel in rigid pavements is not to prevent cracking of the concrete, but to hold tightly closed any cracks that do occur in such manner that the load carrying capacity of the slab is preserved. In jointed pavements the amount of steel is governed by the spacing of contraction joints. In the case of continuously reinforced pavements, sufficient steel is provided to eliminate the need for contraction joints. 2.8.5.1 Special Requirements for Reinforcement In Jointed Unreinforced Pavements In jointed unreinforced pavements, reinforcement (usually in the form of welded wire fabric) is sometimes necessary to control cracking. Concrete slabs which are reinforced are those in which it is anticipated that cracks could occur due to stress concentrations which cannot be avoided by re-arrangement of the slab pattern. Typical applications are: (i) odd-shaped slabs (ii) mismatched joints; and (iii) slabs containing pits or structures. 2.8.5.2 Reinforcement In Jointed Reinforced Pavements The required area of reinforcing steel in jointed reinforced pavements is given by the equation: As = Where AS = fs = g h L M µ = = = = = µLM gh 2 fs (2 - 3.) the required area of steel (mm2/m width of slab). the allowable tensile stress of the reinforcing steel (MPa). Usually 0.6 times the yield strength. the acceleration due to gravity (m/s2 ) thickness of the slab (m). the distance between untied joints and/or free edges of the slab (m). the mass per unit volume of the slab (kg/m3) the coefficient of friction between the concrete base slab and the sub-base; this varies from 1.0 to 2.0 depending on the type of debonding layer applied to the sub-base (see Clause 2.8.4.4.2). ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 62-97 ROAD DESIGN STANDARD The areas of longitudinal steel provided by rectangular and square mashes are detailed in Table 2.8.6. Experience has shown that the use of slab lengths of over 15 metres could reduce joint performance, costs and riding quality. Slabs in excess of 15 metres in length are not recommended. Table 2.8.6 Dimensions and Mass of Plant Hard – Drawn Steel Wire Fabric Cross wires Longitudinal wires Ref No. Size mm Pitch mm Rectangular meshes F1218 12.5 100 F1118 11.2 100 F1018 10 100 F918 9 100 F818 8 100 F718 7.1 100 F928 9 200 F828 8 200 Square meshes F81 8 F102 10 F92 9 F82 8 F72 7.1 F62 6.3 F52 5 F42 4 100 200 200 200 200 200 200 200 Size mm Pitch mm Area of crosssection Long. Cross mm2/mmm2/m Mass per unit area kg/ m2 8 8 8 8 8 8 8 8 200 200 200 200 200 200 250 250 1 227 985 785 636 503 396 318 251 251 251 251 251 251 251 201 201 11.606 9.707 8.138 6.967 5.919 5.081 4.076 3.552 8 10 9 8 7.1 6.3 5 4 100 200 200 200 200 200 200 200 503 393 318 251 198 156 98 63 503 393 318 251 198 156 98 63 7.892 6.165 4.994 3.946 3.108 2.447 1.542 0.987 The use of steel fibre reinforced concrete is appropriate where increased flexural strength is required to control cracking in odd-shaped slabs and where increased abrasion resistance is required for durability. This type of pavement is often used for toll plazas, roundabouts and bus-stops. Steel fibres are between 15 mm and 50 mm in length with either enlarged ends which act as anchorages and/or crimping to improve bond. Typically, 15 mm to 50 mm fibres are added to the concrete at a rate of approximately 75 to 45 kg/m 3 respectively (referred to as the fibre "loading"). Steel fibre reinforced concrete may be used for thin bonded overlays for which fibre "loadings" would be about 33 % higher. Steel fibre reinforced concrete should have a 28 day flexural strength of not less than 5.5 MPa. 2.8.5.3 Reinforcement In Continuously Reinforced Pavements 2.8.5.3.1 Longitudinal Reinforcement The action of the steel reinforcement is initially to provide restraint to shrinkage of the concrete and finally to tie the planned cracks together. With the pavement ends anchored, the steel initially remains unstressed while tension builds up in the concrete. When cracking occurs, local tension results in the steel and limits the opening of the crack. 63-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD This tension is balanced by compression elsewhere in the steel, until further cracking develops. The final distribution of stresses are tensile in the concrete and compressive in the steel between cracks, and tensile in the steel at the cracks. Due to the stresses in the steel changing so rapidly, adequate bond strength between steel and concrete is essential. The proportion of the cross sectional area of the pavement which is to be longitudinal reinforcing steel in continuously reinforced concrete pavements is given by the equation:  ft'   f  d b (eS + eT ) b p= ï£ 2W where: p = f’t/fb = db es = = eT = W = (2 - 4.) the required proportion of the area which is to be longitudinal reinforcing steel. This is the ratio of the cross sectional area of the reinforcing steel to the gross area of the cross section of the slab. the ratio of the direct tensile strength of the immature concrete to the average bond strength between the concrete and steel. The value of this ratio may be assumed to be 1.0 for plain bars or 0.5 for deformed bars complying with AS 1302. diameter of longitudinal reinforcing bar (mm). the estimated shrinkage strain. The shrinkage strain may be considered to be in the range 200 to 300 microstrain for a concrete with a laboratory shrinkage not exceeding 450 microstrain at 28 days when tested in accordance with AS 1012 Part 13 (after three weeks air drying). the estimated maximum thermal strain from the peak hydration temperature to the lowest likely seasonal temperature. A value of 300 microstrain may be assumed, except when the average diurnal temperature at the time of placing concrete is 10 ºC or less, when a value of 200 microstrain may be assumed. the maximum allowable crack width (mm). A value of 0.3 mm should be used in normal conditions, with 0.2 mm for severe exposure situations. Equation (2 - 4.) indicates that the proportion of steel is inversely proportional to the bond strength. In order to provide adequate bond capacity, the longitudinal reinforcing steel should be detailed as follows: (i) Deformed bars should be used. (ii) The diameter of the bars should not exceed 20 mm. (iii) The centre-to-centre spacing of the bars should not be greater than 225 mm. For deformed bars, Equation (2 - 4.) may be simplified as: p= 0.25 d b (eS + eT ) W (2 - 5.) To ensure against yielding of the steel, the actual steel reinforcement ratio should exceed the critical value given by the following equation: p crit = where: Pcrit = f ct (1.3 − 0.2 µ ) f sy − m f ct (2 - 6.) the minimum proportion of longitudinal reinforcement to match the design concrete strength. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 64-97 ROAD DESIGN STANDARD fct = µ = fsy = M = The concrete tensile strength (MPa). A value not exceeding 60 % of the 28 day concrete flexural strength (fet) may be assumed. the coefficient of friction between the concrete base slab and the sub-base; this varies from 1.0 to 2.0 depending on the type of debonding layer applied to the sub-base (Clause 8.4.4.2). the characteristic (95 %) yield strength (0.2 % proof stress) of the longitudinal reinforcing steel. A value of 430 MPa may be assumed for deformed bars conforming to AS 1302. the ratio of the elastic moduli of steel to concrete, Es / Ec. A value of 7.5 may be assumed. Equation (2 - 6.) indicates that the critical proportion of longitudinal reinforcing steel increases more rapidly than the tensile strength of the concrete. The minimum percentage of longitudinal steel to be provided is 0.6 per cent. In the design of continuously reinforced pavements, it is important that an optimum amount of longitudinal steel of suitable type is provided so that crack spacing and crack width can be controlled. If the spacing of the cracks is too wide, the cracks themselves will become wide with a consequent loss in aggregate interlock load-transfer and accelerated corrosion of the steel. If the spacing between cracks is too small, disintegration of the slab may commence. The function of the longitudinal steel is to keep the cracks in the concrete tightly closed, thereby ensuring load transfer across the cracks and also preventing the ingress of water and grit into the cracks. The theoretical spacing of cracks in continuously reinforced pavements may be estimated by the following equation: f ct2 Lcr = m p 2 u f b [(eS + eT ) Ec − f ct ] where: Lcr = fct = m p u = = = fb = eS = eT = Ec = (2 - 7.) the theoretical spacing between cracks the tensile strength of the concrete (MPa). the ratio of the elastic moduli of steel to concrete Es / Ec. A value of 7.5 may be assumed. the area of longitudinal steel per unit area of concrete (ie., steel ratio) the area of longitudinal steel per unit area of concrete (ie steel ratio) the perimeter of bar per unit area of steel which may be simplified to 2/radius of the bar (m-u) the bond stress (MPa); for mature concrete, and when deformed bars are used this maybe assumed as 2fct the estimated shrinkage strain. The shrinkage strain may be considered to be in the range 200 to 300 microstrain for a concrete with a laboratory shrinkage not exceeding 450 microstrain at 28 days when tested in accordance with AS 1012 Part 13 (after three weeks air drying). the estimated maximum thermal strain from the peak hydration temperature to the lowest likely seasonal temperature. A value of 300 microstrain may be assumed, except when the average diurnal temperature at the time of placing concrete is 100 ºC or less, when a value of 200 microstrain may be assumed. the modulus of elasticity of concrete (MPa). This equation indicates that the spacing of cracks is inversely proportional to p, u and fb; consequently to ensure fine cracks and optimum crack spacings, the percentage reinforcement and perimeter to area relationship of the bars should be high. A closer 65-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD spacing of cracks is also obtained when the bond stresses are high, therefore the use of deformed bars is preferred. Experience with continuously reinforced pavements indicates that the optimum crack spacing is between 1.0 and 2.0 metres. Size and spacing of reinforcement may be determined by reference to Figure 2.8.8. 2.8.5.3.2 Transverse Reinforcement The required area of transverse reinforcing steel (As) in continuously reinforced pavements is calculated using Equation (2 - 3.). Note: The following detailing is recommended: (i) Deformed bars not less than 12 mm in diameter. (ii) A maximum centre-to-centre bar spacing of 750 mm. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS 66-97 ROAD DESIGN STANDARD Figure 2.8.8 Reinforced Design Chart for Continuously reinforced concrete pavements using Grade 400 Y steel in accordance with AS 1302-1991 67-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.8 DESIGN OF RIGID PAVEMENTS ROAD DESIGN STANDARD 2.9 OVERLAY DESIGN 2.9.1 GENERAL The purpose of overlay design is to determine the appropriate thickness of either an asphalt or granular layer which, when placed on an existing pavement, will overcome the strength deficiencies of the pavement and retain its own structural integrity throughout the design period. The adopted system for overlay design is described in Section 2.2.3. One of the most important aspects of the overlay design system is the identification of the pavement's deficiencies and needs. The procedures which follow depend on deflection testing to do this although other tests may be used to supplement the deflection data. 2.9.2 BASIC PRINCIPLES Experience has shown that the pavement deflection caused by a standard axle load is an indication of the rate at which permanent pavement deformation will occur under traffic. As the functional adequacy of the pavement is dependent, in part, on this permanent deformation, a relationship between the cumulative number of standard axle loads and measured surface deflection can be developed. Using this relationship a design deflection can be determined for any particular traffic loading. If actual deflections are kept below this design deflection, permanent deformation should be kept to an acceptable level. Where asphalt surfacing exists or is proposed, the level of deflection alone does not give a reliable indication of the likelihood of fatigue cracking. It has been found that a better prediction of fatigue performance is obtained from the curvature of the deflected pavement surface. The curvature of the deflection bowl is defined by a curvature function which is described in Section 2.9.3.3. For any particular design traffic loading there is a tolerable level of curvature function. If the actual curvatures are kept below this value then an acceptable fatigue life for asphalt will result. Maximum deflection is used to control fatigue cracking in cemented materials as no appropriate curvature function has yet been developed for this purpose. 2.9.3 PAVEMENT TESTING 2.9.3.1 Method of Deflection Testing Two methods of deflection measurement are commonly used. Two common methods used to measure deflection include the Benkelman Beam and the Lacroix Deflectograph. Although the principles applied to obtain deflection readings are the same for each device, the ancillary equipment, such as the vehicles used to apply the test load in each case, may differ slightly. The relative effect of each device theoretically varies to some extent depending on the composition of the pavement being tested. The following analysis and design procedures are applicable to either Benkelman Beam or Deflectograph data. 2.9.3.2 Selection of Test Sites When deflection testing is being undertaken by the Deflectograph, it is necessary to select only the transverse location of wheel path positions, because the longitudinal spacing of test sites is automatically controlled. Wheel path positions should be selected keeping in mind any proposed changes to the road alignment. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN 68-97 ROAD DESIGN STANDARD For Benkelman Beam testing, the spacing of individual test sites in a given section of road is arranged so that the pavement designer can review the general pattern of the deflections of the whole section of road and define subsections of consistent deflection pattern. An adequate number of results for each sub-section, at least 10 and preferably upwards of 30, must be obtained for the purposes of statistical analysis. Normally the spacing used lies between 5 m and 200 m with 50 m being a common value. Similar comments; apply to the selection of test sites in wheel path positions. 2.9.3.3 Test Modes The Deflectograph and Benkelman Beam are capable of obtaining measurements for several forms of pavement reaction to load. Different procedures or test modes are used depending on the information required. The two pavement reactions used for analysis in this Standard are: (a) Maximum Deflection For the Deflectograph this is the maximum reading recorded for each test site. For the Benkelman Beam the "maximum deflection" may be taken as the total deflection minus the residual deflection. (b) Deflection Bowl The deflection bowl is the shape of the pavement surface caused by a load applied to it. It is not usually measured directly but is estimated using the principle of superposition from a series of deflection readings taken at a specific point on the pavement as the load approaches or recedes from that point. For example the deflection in a deflection bowl at a point 200 mm from the point of maximum deflection, is assumed to be equal to the deflection of a specific test site when the moving test load is 200 mm away. The shape of the deflection bowl is therefore obtained by plotting recorded deflection against the distance to load for a series of positions of the load. While this is more easily obtained with the Deflectograph it can also be measured without much difficulty by making relatively inexpensive modifications to a Benkelman Beam. The Curvature Function CF of a deflection bowl is given by: CF where Do = D200 = = Do - D200 maximum deflection for a test site the deflection measured at the site when the test load is 200 mm from the point at which the maximum deflection was produced (in the direction of travel) Figure 2.9.1 shows in schematic form the dimension represented by the curvature function. Figure 2.9.1 Curvature Function 69-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN ROAD DESIGN STANDARD 2.9.3.4 Other Tests Sometimes it is desirable to supplement deflection tests with other data to identify the pavement's needs with more confidence, especially for large jobs. Section 2.9.4 contains some guidance regarding the interpretation of deflection test data. This information can also be used to select an appropriate supplementary testing program where necessary. 2.9.3.5 Measurement of Pavement Temperature Variations in temperature result in significant changes in the stiffness of asphalt and therefore in the strength of pavements containing asphalt layers. The temperature of asphalt surfacing must, therefore, be recorded at a depth of 30 mm during deflection testing so that appropriate adjustments can be made during the analysis and design phases. If weather conditions vary during the deflection survey, then several measurements of temperature must be taken and different adjustments made for corresponding sections of the test length. 2.9.4 PAVEMENT EVALUATION 2.9.4.1 Selection of Homogeneous Sections In practice the strength of a pavement varies from site to site and it may be necessary to divide the test section into subsections having relatively uniform deflection and/or curvature patterns. In selecting homogeneous subsections consideration should be given to the following: • Subgrade type and likely variations • Drainage • Seepage • Topography • Construction and maintenance history • Pavement composition (particularly overall depth and the thickness of any asphalt or cemented layer) The preferred method of obtaining some of this information is by site inspection during which surface defects should also be recorded to assist in the interpretation of deflection test results. Single "characteristic" values of deflection and curvature are then assigned to these subsections for evaluation purposes. Homogeneous subsections may be considered to be those whose deflection and curvature values have a coefficient of variation (ie standard deviation divided by mean) of 0.25 or less. The characteristic deflection, CD, of a section or subsection of pavement is a value calculated from the test deflections and equal to the average deflection µ plus a factor f times the standard deviation, S. Thus CD = µ + f S ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN 70-97 ROAD DESIGN STANDARD where f is selected by the designer to provide a suitable characteristic design deflection. This should correspond to the degree of reliability required in the rehabilitation treatment. Recommended values of f, given in Table 2.9.1 will generally be appropriate. However, it must be appreciated that because of the widely different conditions which can apply to particular roads in the one category, adoption of another value may be necessary. The Characteristic Curvature of a length of pavement is equal to the mean of the test curvature functions. Table 2.9.1 Recommended Values For “ f “ Road Functional Class F 1 and 6 2.00 2, 7, 8 and 9 1.65 3, 4 and 5 1.30 For definition of classes see Appendix A. 2.9.4.2 % of all deflection which will be covered by the characteristic deflection 97.5 95 90 Characteristic Site Temperature Because the strength of asphalt varies with temperature, the performance of a pavement which contains asphalt will reflect the temperature regime at the locality in question. A site may be characterised by a weighted mean annual pavement temperature (WMAPT) for the purpose of analysing deflections and designing asphalt overlays. Usually deflection testing will be carried out when the pavement is at a temperature other than the WMAPT. In these cases an adjustment must be applied to convert the measured deflections to values representative of the pavement response at the WMAPT. 2.9.4.3 Adjustment of the Characteristic Deflection and Characteristic Curvature to Account for the Testing Temperature The method for adjusting measured deflections to allow for temperature is as follows. Step 1 fT = Determine the temperature factor fT where Measured temperature at time of testing Assumed WMAPT for the site Step 2 From Figure 2.9.2 determine the Deflection Adjustment Factor considering the existing asphalt thickness. No temperature adjustment is required if the pavement does not contain asphalt. Step 3 Divide the characteristic deflection by the Deflection Adjustment Factor. The Characteristic Curvature function is adjusted for temperature using a similar method to that described for deflection adjustment. The temperature adjusted curvature function is calculated by dividing the measured value by the Curvature Adjustment Factor from Figure 2.9.2. 71-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN ROAD DESIGN STANDARD Figure 2.9.2 Temperature Correction for deflection and curvatures. 2.9.4.4 Adjustment of Deflection Data to Account for Seasonal Moisture Variations In some localities a slight increase in deflection during or soon after wet seasons is common due to higher moisture contents under the pavement at these times. However the seasonal effect of moisture is not a straightforward rainfall / deflection relationship. Account must be taken of changes in moisture regime which includes surface infiltration, permeability of the pavement layers and subgrade, evaporation and drainage conditions at the site. The evaporation and drainage factors limit the quantity of water available to infiltrate the subgrade while the permeability controls the rate of infiltration and consequently the time lag between the incidence of rain and Its effect on deflection. There are insufficient data available to enable a general relationship to be developed for the effect of seasonal moisture variations on deflections. It is suggested that site specific data be obtained where possible and used to account for this phenomenon. 2.9.4.5 Design Traffic The design traffic to be used for the evaluation of existing pavements and for overlay design should be based on a design period which may be defined as the time from when rehabilitation and/or testing occurs until further treatment is necessary. The method to be used for calculating the design traffic is the same as that described in Section 2.5. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN 72-97 ROAD DESIGN STANDARD 2.9.4.6 Performance Criteria (Design Deflection and Curvature) The adopted relationship between design deflection and traffic loading is contained in Figure 2.9.3. Curve 1 controls the rate of permanent deformation in the pavement and subgrade and may be used for all pavements regardless of surfacing type, as the fatigue performance of asphalt surfacing is controlled by means of the curvature criteria. Curve 2 is intended to be used to inhibit cracking in pavements with cemented bases in lieu of a separate curvature function as none has been developed to date. The design deflection criteria may be applied to any locality regardless of the temperature regime. Curves 1 and 2 are considered to define deflection levels associated with satisfactory pavement performance for the relevant traffic loading. Figure 2.9.3 Design Deflection Levels by Design Traffic (ESA) The adopted relationship between curvature and traffic loading is contained in Figure 2.9.4. It should be noted that it is applicable to dense graded asphalt mixes. There is insufficient field data available to provide fatigue performance criteria for other mix types such as open graded asphalt. 2.9.4.7 Determination of Pavement Needs In many instances the needs of an existing pavement can be readily identified by an experienced observer. Deflection testing and the analyses described previously supplement these observations. Experience gained in the assessment of pavement conditions by means of deflection testing, particularly when test sites are closely spaced, has enabled certain general guidelines to be established. Some of these are listed below to assist the designer. 73-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN ROAD DESIGN STANDARD Figure 2.9.4 Design Curvature Function Design Traffic (ESA) (a) very high deflections (more than 1.5 mm) indicate weak subgrade conditions, and low deflections a strong subgrade. (b) high values of curvature function indicate a weak or very thin pavement, or a pavement with cracked surfacing, and low curvature functions a strong pavement. (c) substantially different deflections and curvature functions between left and right test wheel paths may indicate the presence of a former pavement widening or verge water ingress. (d) a high deflection peak near a pavement edge may be caused by poor local drainage such as a blocked subsurface drain. (e) a series of high deflection peaks across all test wheel paths sometimes indicates a poorly back filled culvert or service trench or a poorly drained junction between two pavement types. (f) a generally low but extremely variable deflection pattern may indicate an old failing pavement which may be cracked or poorly patched. (g) a relatively widely spread peak of high deflections across all test wheel paths may indicate a poorly drained cut-fill area. (h) residual deflections - generally the Benkelman Beam records a positive residual deflection of up to 0.15 mm. This is thought to be of little concern. A substantial positive residual implies a weak pavement, probably poor compaction. A negative residual deflection may indicate that shoving is taking place in the pavement and the situation requires further investigation, but is also common in pavements with cemented layers where the beam supports are within the deflection bowl. A well defined area of low deflections measured by the Deflectograph in a section containing otherwise moderate to high deflections may indicate unstable pavement material. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN 74-97 ROAD DESIGN STANDARD 2.9.5 SELECTION OF THICKNESS 2.9.5.1 Granular Overlays Granular overlays are usually placed on existing granular pavements. If the existing pavement has a bituminous surfacing then it is usually desirable to break the seal to ensure that water is not trapped in the overlay. The selection of overlay thickness is based on the characteristic deflection of the existing pavement and the reduction required to reach the design deflection. Based on available field data it may be assumed that a 6 percent reduction in deflection will result for each 25 mm of granular overlay thickness. The required overlay thickness may be obtained directly by using Figure 2.9.5. Figure 2.9.5 Effect of Granular overlay on Deflection These relationships apply to cases where no other major improvements are made at the time of placing the overlay such as if extensive drainage works were carried out. 2.9.5.2 Asphalt Overlays If it is proposed to provide additional pavement strength or improved riding quality by means of an asphalt overlay, the following procedure should be used to select the appropriate overlay thickness. In the case of overlaying to improve riding quality, the thickness of asphalt required may need to be thicker than determined by this procedure to satisfy shape requirements. The procedure is summarised in Figure 2.9.6 in flow chart form. 2.9.5.3 Characteristic Deflection (adjusted for temperature) Exceeds the Design Deflection The overlay thickness required is the maximum of those needed to satisfy the deflection criteria and also the fatigue criteria. Figure 2.9.7 is used to select the overlay thickness TD 75-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN ROAD DESIGN STANDARD needed to reduce the Characteristic Deflection to the Design Value. Note that Characteristic Deflection must first be adjusted for temperature as described in Section 2.9.4.3 if the existing pavement has an asphalt surface. Figure 2.9.6 Effect of Asphalt Overlay on deflection Similarly F is used to select the overlay thickness TC needed to reduce the curvature to the tolerable value. The appropriate overlay is then the maximum of TD and TC. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN 76-97 ROAD DESIGN STANDARD Figure 2.9.7 Pavement Analysis and Asphalt Overlay Design 77-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN ROAD DESIGN STANDARD 2.9.5.4 Characteristic Deflection (adjusted for temperature) Less Than Design Deflection If the existing pavement does not have an asphalt surface then no asphalt is required for strengthening purposes. If it is proposed to place an asphalt overlay for other reasons, such as for regulation of surface levels, or if the existing pavement has an asphalt surface, then a check must be made to ensure that the design curvature function is not exceeded. The minimum overlay thickness required to reduce the characteristic curvature to the tolerable value may be obtained from Figure 2.9.8. Figure 2.9.8 Reduction in D0 - D200 due to Asphalt Overlay 2.9.5.5 Adjustment of Overlay Thickness to Allow for Locality Temperature The overlay thicknesses given in Figure 2.9.7 and F apply to a locality where the WMAPT is 25 ºC. Where higher WMAPT's apply, a given thickness of asphalt will be less effective in reducing deflections because of its reduced stiffness, and for temperatures below 25 ºC the reverse will hold. Therefore the overlay thickness TD, appropriate to a particular site should be calculated by multiplying the value obtained from Figure 2.9.7 by a factor obtained from Figure 2.9.9. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN 78-97 ROAD DESIGN STANDARD Figure 2.9.2 Overlay Adjustment Factors The required overlay thickness TC, obtained from Figure 2.9.8 need not be adjusted to allow for temperature because although curvature reduction will be less at high temperatures, the asphalt will have a greater fatigue life which provides a compensating effect. The greater curvature reduction at low temperatures will also be compensated by a relatively lower fatigue life. 2.9.5.6 Example of Asphalt Overlay Design A section of pavement which contains 50 mm of asphalt situated in a locality where the WMAPT is 30 ºC produced the following reaction to load when deflection testing was carried out using the Deflectograph. The pavement temperature at the time of testing was 20 ºC. Given that • Calculated Characteristic Deflection = 1.20 mm • Characteristic Curvature = 0.26 mm • Design Traffic loading = 5 x 101 ESA Then • Design Deflection (from Figure 2.9.3) = 0.95 mm • Design Curvature (from Figure 2.9.4) = 0.13 mm • Temperature factor = Tmeasured / Tstandard = 20 / 30 = 0.67 • From Figure 2.9.2 the deflection adjustment factor =0.96 • Temperature adjusted characteristic deflection = 1.20 / 0.96 = 1.25 mm 79-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN ROAD DESIGN STANDARD • Overlay thickness TD required to reduce the characteristic deflection to the design deflection (when WMAPT is 25º C) from Figure 2.9.3 = 70 mm. • Overlay Adjustment factor for WMAPT 30 ºC from Figure 2.9.9 = 1.13 • Overlay thickness To required to reduce the characteristic deflection to the design deflection for WMAPT 30 ºC = 70 X 1.13 = 80 mm CHECK FOR FATIGUE CRACKING • From Figure 2.9.2 the curvature adjustment factor = 0.96 • Temperature adjusted characteristic curvature = 0.26 / 0.96 = 0.27 m • Overlay thickness TC required to reduce the characteristic curvature to the design curvature from F = 100 mm • No adjustment is made to TC to account for temperature. • Required overlay thickness is the larger of TD and TC = 100 mm ie. the overlay thickness required to satisfy both permanent deformation and asphalt fatigue criteria. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 2.9 OVERLAY DESIGN 80-97 ROAD DESIGN STANDARD APPENDIX A DEFINITIONS OF TERMS Annual Average Daily Traffic (AADT) The total yearly traffic volume divided by 365. California Bearing Ration (CBR) The ration expressed as a percentage between a test load and an arbitrarily defined standard load. This test load is that required to cause a plunger of standard dimensions to penetrate at a specified rate into a specifically prepared soil specimen. Commercial Vehicle A vehicle having at least one axle with dual wheels and/or having more than two axles. Course One or more layers of the same material within a pavement structure. Curvature Function Of a deflection bowl is the difference in maximum deflection at a test site and the deflection at a point 200 mm from the point at which the maximum deflection was produced (in the direction of travel). Cemented Materials Those produced by addition of cement, lime or other hydraulically binding agent to granular materials in sufficient quantities to produce a bound layer with significant tensile strength. Deflection The vertical elastic (recoverable) deformation of a pavement surface between the tyres of a standard axle. A period considered appropriate to the function of the road. It is used to determine the total traffic for which the pavement is designed. Design Period Design Subgrade Level (DSL) The level of the prepared formation after completion of stripping and excavation or filling and upon which the pavement is to be constructed. (Design Subgrade Level = Finished Surface Level-Nominated Pavement Thickness). Layer The portion of a pavement course placed and compacted as an entity. Modified Materials Granular materials to which small amounts of stabilising agent have been added to improve their performance (e.g. by reducing plasticity) without causing a significant increase in structural stiffness. Modified materials are considered to behave as unbound materials. Modulus of Subgrade Reaction The slope of the straight line drawn from the origin to a given point on the stress deflection curve obtained from a plate bearing test. 81-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX A ROAD DESIGN STANDARD Pavement (Structure) The portion of the road, excluding shoulders, placed above the design subgrade level for the support of, and to form a running surface for, vehicular traffic. Permeability Reversal Occurs at a pavement layer interface when the coefficient of saturated permeability of the upper layer is at least 100 times greater than that of the layer below it. Roughness The roughness of the pavement surface in counts/km as measured by a Roughness Meter. Shoulder The portion of the road contiguous and flush with the pavement. Stabilisation The treatment of a road pavement material to improve it or to correct a known deficiency and thus enhance its ability to perform its function in the pavement. Standard Axle Single Axle with dual wheels loaded to a total mass of 8.2 t. Traffic Lane The portion of a carriageway allotted for use of a single lane of vehicles. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX A 82-97 ROAD DESIGN STANDARD APPENDIX B PAVEMENT LIFE MULTIPLIERS To utilise Pavement Life Multipliers in a design procedure, it is necessary to know the day/night traffic spectrum. If PD = % of ESAs during day (7 am to 9 pm) then (100- PD) = % of ESAs at night (9 pm to 7 am) PLM = 100 PD + 100 - PD PLM D PLM N where PLM = Pavement Life Multiplier total traffic To input the Pavement Life Multiplier into a design procedure, the normal traffic loading N (in ESAs) is divided by the Pavement Life Multiplier to give a modified traffic loading NA. This modified loading is then used for any part of the design procedure relating to the asphalt layers. (eg to check tolerable deflections for pavements surfaced with asphalt). NA = N/PLM NA = Design Traffic Loading for asphalt (ESAs) N = Standard Design Traffic Loading (ESAs) The method of calculation of Pavement Life Multipliers is given in detail in Youdale (1984). 83-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX B ROAD DESIGN STANDARD APPENDIX C METHODS FOR CHARACTERISING INITIAL DAILY TRAFFIC Calculate initial daily ESAs as follows: Ne = NA1J F E1J + j NA2J F E2J + j NA3J F E3J + j NA4J F E4J j Where NAij is the average daily number of axles (in the first year) of type I, carrying a load of magnitude j and FEij is the number of ESAs for each pass of the axle group I carrying load j with the summations being taken over the appropriate load ranges. Values for FEij are contained in Table C1. Table C1 – Number of ESA’s per Axle Group Load on axle group kN 20 3040 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 Single Axle Single Tyre 0.02 0.10 0.32 0.79 1.6 3.0 5.2 Number of ESA’s Single Axle Dual Axle Dual tyres Dual Tyres 0 0 0.02 0 0.06 0.01 0.15 0.02 0.32 0.04 0.59 0.07 1.0 0.12 1.6 0.20 2.4 0.30 3.6 0.44 5.1 0.62 0.86 1.2 1.5 2.0 2.5 3.2 3.9 4.8 5.9 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX C Tri Axle Dual Tyres 0 0 0 0.01 0.01 0.02 0.04 0.06 0.09 0.14 0.19 0.27 0.36 0.47 0.61 0.78 0.98 1.2 1.5 1.8 2.2 2.6 3.1 3.6 4.3 5.0 5.7 6.6 84-97 ROAD DESIGN STANDARD APPENDIX D DETERMINATION OF DESIGN MOISTURE CONTENT D.1 Introduction These procedures may be used to estimate design surged moisture conditions. Two procedures are given and these are based on field studies which indicate that a reasonable prediction of moisture conditions in a surged may be made by assessing the conditions of existing similar subgrades in the vicinity and/or the moisture conditions in natural ground below the zone of seasonal influence. A flow chart for the two methods is given in Figure D1. In many cases a detailed investigation to determine design moisture content is not warranted and this applies for example where local policies, reflecting local experience, define test conditions. As a particular example there are several circumstances where saturated conditions may be anticipated (eg below ground water tables, areas of inundation) and tests may be carried out under soaked conditions without further evaluation. D.2 Prediction Of DMC From Existing Roads D.2.1 Considerations in Use of Method This procedure may be used to predict DMC provided the following features are similar for the road being designed and the existing roads. a) Soil Density The effect of subgrade density on moisture content is difficult to establish and for this reason, efforts should be made to measure the existing moisture content at sites where the in-situ density corresponds closely with that proposed for the new pavement. Where differences occur, particularly when the existing density is greater that the proposed density, care should be exercised and an adjustment made on the following bases: • Existing density less than proposed density: no adjustment. • Existing density greater than proposed density: FMC = FMCe + 12.5 (FD-PD) where PD = Proposed subgrade density (t/m3) FD = Existing subgrade density (t/m3) FMCe = Existing subgrade gravimetric moisture content(%) applies for PD and FD > 1.1 t/m3. (b) Drainage Conditions The following drainage conditions for the existing and proposed pavements should correspond: • Position of catch drains, table drains and subgrade pavement drains • Shoulder crossfall and condition (eg vegetated, sealed) 85-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX D ROAD DESIGN STANDARD • Longitudinal grade • Formation profile (boxed, full width) • Cut or fill When selecting sites for measuring moisture conditions, care should be taken to ensure measurements are taken well away from any trees as they can greatly influence subgrade moisture conditions. This is particularly true during the spring and summer growth seasons. (c) Position of the Water Table, Climate and Land The depth of permanent ground water, climatic conditions and topography of the existing and proposed pavements should be similar. (d) Pavement Composition Where the pavement is composed of a number of courses above the subgrade and the coefficient of saturated permeability of the subgrade is estimated to be at least 100 times less than that of the course above it (permeability reversal), consideration should be given to assessing the subgrade on the basis of soaked conditions if rainfall conditions warrant. For accurate prediction of DMC from tests on existing roads, consideration should be given to the following: i) Time Since Completion of Seal If the period of sealing is not less than two years, the effect of time on the subgrade moisture content can usually be neglected. If the age of the seal is less than two years, this method may not be reliable. ii) Soil Type The field Moisture Content (FMC) of the subgrade in the proposed pavement may be estimated from the existing subgrade using the following equations: Proposed Existing Subgrade Subgrade Where: OMC = Optimum Moisture Content for standard compactive effort, PL = the Plastic Limit. The equation expressed in Plastic limit is only applicable to fine grained soils, ie more than 80 % passing a 425 µm sieve. The values of the FMC obtained from the above two equations should be averaged. D.2.2 Details of Procedure The procedure consists of the following steps. (a) Select sections of the existing road with conditions which correspond to those which will exist in the road being designed. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX D 86-97 ROAD DESIGN STANDARD (b) Within the sections chosen for investigation, select a number of sites for sampling. The longitudinal location of the sites should be in a random pattern and appropriate to the accuracy of the prediction required. The lateral location of sites will normally be in the outer wheel paths. A check on the moisture condition of the inner wheel path should be made to ensure that the design moisture content is based on the correct value. If the cross section of the road differs markedly from that proposed to be used, judgement will be required in the selection of the lateral position of sampling to ensure correspondence of conditions. (c) For each section, sample the subgrade at the sites selected and also the corresponding proposed subgrade. Sampling of the existing road should be at a depth of approximately 300 mm below subgrade. Measure the field moisture contents and carry out classification tests. (d) At each site on the existing road, determine the field moisture content (FMC). (e) Derive the ratio FMC / OMC or, for a fine grained soil, FMC / PL. (f) Analyse these ratios statistically for all sites in the section and adopt the 90 th percentile (mean + 1.3 standard deviations). Other percentile values may be adopted if considered more appropriate. (g) Multiply the 90 th percentile values of the above ratios respectively by the OMC (or PL) of the proposed subgrade. (h) The DMC may be obtained by adopting the values derived in (g) with corrections applied for seasonal variations and edge effects. If data on seasonal variations is not available, but a regular rainfall pattern exists, the indications are that the worst moisture conditions in subgrades occur at, or shortly after, times when rainfall is high and evaporation is low. D.3 Prediction Of DMC By Site D.3.1 Investigation In cases where a satisfactory degree of correspondence between the pavement characteristics of existing and proposed pavements cannot be established, the following procedure can be adopted to estimate the DMC of the proposed subgrade: (a) Delineate the terrain through which the road will pass into units of similar physiographic features. This can be done from either aerial photographs, maps or field inspection. If is assumed that terrain units of the same type will have the same subgrade moisture conditions. (b) Take samples at selected positions in units representative of each terrain type at a level below the zone of seasonal variation (not less than two metres) where the water table is below this zone and at a depth of 300mm above the water table if this occurs at a depth of less than two metres. The number of units taken as representative of each terrain type and the number of samples taken, will depend on the precision of the estimate required. Representative samples of the subgrade material proposed should also be obtained if the above samples are not appropriate. (c) Determine the FMCs and carry out classification testing on all samples. (d) Derive the ratio FMC/OMC and for a fine grained soil FMC/PL. (This is not necessary if the subgrade will consist of the same material being sampled at depth). (a) Analyse these ratios statistically (on FMC only if material identical to subgrade) for each sample in the terrain unit and adopt the 90th percentile value (mean +1.3 standard deviation). Other percentiles may be used if considered more appropriate. 87-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX D ROAD DESIGN STANDARD (f) Multiply the 90th percentile values of the above ratios respectively by the OMC and PL of the proposed subgrade. (g) The DMC may be obtained by adopting the values derived in (f) (and (e) when the subgrade is similar to moisture content samples) with corrections applied for edge effects. ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX D 88-97 ROAD DESIGN STANDARD APPENDIX E THE EFFECT OF ASPHALT THICKNESS ON THE FATIGUE LIFE OF ASPHALT SURFACED PAVEMENTS Some of the example design charts which are contained in this Standard indicate that for a given design traffic, asphalt stiffness, thickness of granular or cemented base or subbase, and subgrade stiffness, two asphalt thicknesses provide the same theoretical fatigue performance. The reason for this can be explained by examining the relationship between asphalt thickness and horizontal strain at the bottom of the asphalt induced by a standard load for a given composition of underlying material. A typical relationship is illustrated in Figure E.1. As asphalt thickness is increased horizontal strain increases from a negative value (ie compression) at zero asphalt thickness to low positive values (tension). Asphalt layers which are relatively thin and represent only a small proportion of the overall pavement stiffness offer little resistance to the flexure of the underlying structure. In this range of thickness the greater the depth of asphalt the greater the magnitude of tensile strain induced at its underside. With further increases in thickness the asphalt layer begins to exert an influence on the total pavement structure. A peak strain level is reached usually in the range of 40-80 mm for highway traffic loading. Further increases in asphalt thickness reduce the flexure of the structure and the resulting strain in the asphalt. Figure E1 Asphalt Strain vs Thickness Therefore there are generally two asphalt thicknesses that give the same magnitude of strain, one to the left of the maximum point on the curve and one to the right. The discontinuity that occurs at the broken line shown on some of the charts represents the pavement composition where the overall life of the pavement is determined equally by asphalt fatigue and subgrade strain criteria. 89-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX E ROAD DESIGN STANDARD APPENDIX F EXAMPLES OF USE OF DESIGN PROCEDURES FOR RIGID PAVEMENTS – SHEET 1 CALCULATION OF CONCRETE PAVEMENT THICKNESS Project: _____________________________________________ Date: ____________ Source of Load Data ......................... ________________ Characteristic (28 day) CRC/Dowelled joints ........................ yes _____ no _____ Flexural Strength f’ of ________ MPa Concrete Shoulder............................. yes _____ no _____ Subgrade CBR ________ % Design Period ............................................. _________ years Sub-base Thickness & Type_______ mm Design Traffic ................................... _________ CV axle groups Effective CBR ________ % Load Safety Factor LSF .................... _________ TRIAL BASE THICKNESS ________ mm Fatigue Analysis Axle Load (kN) Design Load/Tyre (kN) Expected Repetitions Allowable Repetitions Fatigue (%) Erosion Analysis Allowable Repetitions Damage (%) SINGLE AXLES / SINGLE WHEELS (SS) Equivalent Stress ______ Stress Ratio Factor ______ Erosion Factor ______ Single-steer axles Twin-steer axles SINGLE AXLES / DUAL WHEELS (SD) Equivalent Stress ______ Stress Ratio Factor ______ Erosion Factor ______ Non-steer single axles ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX F 90-97 ROAD DESIGN STANDARD APPENDIX F EXAMPLES OF USE OF DESIGN PROCEDURES FOR RIGID PAVEMENTS – SHEET 2 Fatigue Analysis Axle Load (kN) Design Load/Tyre (kN) Expected Repetitions Allowable Repetitions Fatigue (%) TANDEM AXLES / DUAL WHEELS (TAD) Equivalent Stress ______ Stress Ratio Factor ______ Non-steer double axles Erosion Analysis Allowable Repetitions Damage (%) Erosion Factor ______ TRI - AXLES / DUAL WHEELS (TRD) Equivalent Stress ______ Stress Ratio Factor ______ Erosion Factor ______ Non-steer triple axles TOTAL Fatigue % 91-97 TOTAL Erosion % ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX F ROAD DESIGN STANDARD APPENDIX F EXAMPLES OF USE OF DESIGN PROCEDURES FOR RIGID PAVEMENTS – SHEET 3 CALCULATION OF EXPECTED REPETITIONS Project ____________________________________________ Date: _______ Load (Axle kN) Proportion Of Loads X (%/100) Proportion Of Axle Group (%/100)* X Design Traffic CV Axle Groups = Expected Repetitions SINGLE AXLES / SINGLE WHEELS Single-steer axles Twin-steer axles SINGLE AXLES / DUAL WHEELS Non-steer single axles * ** A constant for each axle type. A constant for the design (CV = commercial vehicles). ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX F 92-97 ROAD DESIGN STANDARD APPENDIX F EXAMPLES OF USE OF DESIGN PROCEDURES FOR RIGID PAVEMENTS – SHEET 4 Load (Axle kN) Proportion Of Loads X (%/100) Proportion Of Axle Group (%/100)* X Design Traffic CV Axle Groups = Expected Repetitions TANDEM AXLES / DUAL WHEELS Non-steer double axles SINGLE AXLES / DUAL WHEELS (TRD) Non-steer triple axles 93-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX F ROAD DESIGN STANDARD APPENDIX G Prakas No. 377, Dated 11th October, 2001 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX G 94-97 ROAD DESIGN STANDARD Prakas No. 377, Dated 11th October, 2001 (Cont.) 95-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX G ROAD DESIGN STANDARD APPENDIX H Decision No. 328, Dated 13th November, 1998 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX H 96-97 ROAD DESIGN STANDARD Decision No. 328, Dated 13th November, 1998 (Cont.) End of Document 97-97 ROAD DESIGN PART 2 - PAVEMENT, CAM PW 03-102-99 APPENDIX H