Quantitative Analysis for Management, 11e (Render) Chapter 1 Introduction to Quantitative Analysis 1) Interviews, statistical sampling, and company reports provide input data for quantitative analysis models. Answer: TRUE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 2) In the early 1900s, Henry Ford pioneered the principles of the scientific approach to management. Answer: FALSE Diff: 2 Topic: WHAT IS QUANTITATIVE ANALYSIS? 3) Managers do not need to be familiar with the limitations, assumptions, and/or specific applicability of the quantitative analysis technique to use it for accurate decision making. Answer: FALSE Diff: 2 Topic: INTRODUCTION 4) During World War II, many new scientific and quantitative techniques were developed to assist the military, and these developments were so successful that many companies started using similar techniques in managerial decision making and planning after the war. Answer: TRUE Diff: 2 Topic: WHAT IS QUANTITATIVE ANALYSIS? 5) When a problem is difficult to quantify, it may be necessary to develop unspecific objectives. Answer: FALSE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 6) The Quantitative Analysis Approach consists of six steps. Answer: FALSE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 7) A mathematical model shows the relationship between quantifiable and non-quantifiable information. Answer: FALSE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 1 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 8) Decision variables may also be called parameters. Answer: FALSE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 9) Model variables can be controllable or uncontrollable. Answer: TRUE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 10) A series of steps or procedures that are repeated is known as an algorithm. Answer: TRUE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 11) A model is a representation of a situation. Answer: TRUE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 12) A parameter is a measurable quantity that may vary or is subject to change. Answer: FALSE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 13) Trying various approaches and picking the one resulting in the best decision is called incomplete enumeration. Answer: FALSE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 14) All problems can be solved by considering only the quantitative issues. Answer: FALSE Diff: 1 Topic: WHAT IS QUANTITATIVE ANALYSIS? 15) A profit equation is an example of a schematic model. Answer: FALSE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 16) Testing the data and model should be done before the results have been analyzed. Answer: TRUE Diff: 1 Topic: THE QUANTITATIVE ANALYSIS APPROACH 2 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 17) Sensitivity analysis helps us estimate the effect of known and unknown errors in our model. Answer: TRUE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 18) Models can help us analyze a problem and sell a decision to those who must implement it. Answer: TRUE Diff: 1 Topic: HOW TO DEVELOP A QUANTITATIVE ANALYSIS MODEL AACSB: Communication 19) A sensitivity analysis allows a manager to answer the "what if" questions. Answer: TRUE Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 20) One problem in using a quantitative model is that the necessary data may be unavailable. Answer: TRUE Diff: 1 Topic: POSSIBLE PROBLEMS IN THE QUANTITATIVE ANALYSIS APPROACH 21) Which of the following terms is interchangeable with quantitative analysis? A) management science B) economics C) financial analysis D) statistics E) None of the above Answer: A Diff: 1 Topic: WHAT IS QUANTITATIVE ANALYSIS? 22) Operations Research is known as A) the science of numerical analysis. B) the science of sensitivity analysis. C) the science of better. D) the science of modeling. E) None of the above Answer: C Diff: 2 Topic: INTRODUCTION 3 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 23) Who is credited with pioneering the principles of the scientific approach to management? A) Adam Smith B) Henri Fayol C) John R. Locke D) Frederick W. Taylor E) Charles Babbage Answer: D Diff: 2 Topic: WHAT IS QUANTITATIVE ANALYSIS? 24) A(n) ________ is a representation of reality or a real-life situation. A) objective B) model C) analysis D) algorithm E) None of the above Answer: B Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 25) A measurable quantity that may vary, or is subject to change, and can be controlled is known as a(n) A) decision variable. B) algorithm. C) parameter. D) solution. E) None of the above Answer: A Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 26) A set of logical and mathematical operations performed in a specific sequence is called a(n) A) complete enumeration. B) diagnostic analysis. C) algorithm. D) objective. E) None of the above Answer: C Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 4 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 27) The ability to examine the variability of a solution due to changes in the formulation of a problem is an important part of the analysis of the results. This type of analysis is called ________ analysis. A) sensitivity B) implicit C) normal D) scale E) objective Answer: A Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 28) Which of the following is not one of the steps in the quantitative analysis approach? A) Defining the Problem B) Developing a Solution C) Observing a hypothesis D) Testing a Solution E) Implementing the Results Answer: C Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 29) The condition of improper data yielding misleading results is referred to as A) garbage in, garbage out. B) break-even point. C) uncontrollable variable. D) postoptimality. E) None of the above Answer: A Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 30) Expressing profits through the relationship among unit price, fixed costs, and variable costs is an example of A) a sensitivity analysis model. B) a quantitative analysis model. C) a postoptimality relationship. D) a parameter specification model. E) None of the above Answer: B Diff: 1 Topic: HOW TO DEVELOP A QUANTITATIVE ANALYSIS MODEL 5 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 31) The widespread applicability of operations research methods to business followed which war? A) The U.S. Civil War B) World War I C) World War II D) The Korean War E) The Vietnam War Answer: C Diff: 2 Topic: WHAT IS QUANTITATIVE ANALYSIS? 32) Which of the following statement(s) are true regarding the advantages of mathematical modeling? A) Models accurately represent reality. B) Models can help decision makers formulate problems. C) Models can save time. D) Models may be the only way to solve some large and complex problems in a timely manner. E) All of the above Answer: E Diff: 1 Topic: HOW TO DEVELOP A QUANTITATIVE ANALYSIS MODEL 33) A measurable quantity that is inherent in the problem is called a(n) A) decision variable. B) uncontrollable variable. C) algorithm. D) parameter. E) enumeration variable. Answer: D Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 34) Trying various approaches and picking the one that results in the best decision is called A) the trial-and-error method. B) incomplete enumeration. C) complete enumeration. D) algorithmic approximation. E) sensitivity analysis. Answer: A Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 6 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 35) Models that do not involve risk or chance are A) probabilistic models. B) postoptimality models. C) deterministic models. D) MIS models. E) None of the above Answer: C Diff: 2 Topic: HOW TO DEVELOP A QUANTITATIVE ANALYSIS MODEL 36) If input data are accurate to three significant digits, then the solution results can be accurate to how many significant digits? A) one B) two C) three D) four E) six Answer: C Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 37) Postoptimality analysis is most closely associated with A) collecting input data. B) developing a model. C) sensitivity analysis. D) writing a computer program. E) None of the above Answer: C Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 38) The break-even point is an example of a A) postoptimality model. B) quantitative analysis model. C) schematic model. D) sensitivity analysis model. E) None of the above Answer: B Diff: 1 Topic: HOW TO DEVELOP A QUANTITATIVE ANALYSIS MODEL 7 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 39) Stochastic models are synonymous with A) deterministic models B) schematic models. C) qualitative models. D) conceptual models. E) None of the above Answer: E Diff: 2 Topic: GLOSSARY 40) A controllable variable is also called a A) parameter. B) decision variable. C) mathematical model. D) measurable quantity. E) None of the above Answer: B Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 41) Evaluating all possible values of a variable in a model is called A) trial and error. B) complete enumeration. C) an algorithm. D) variablization. E) None of the above Answer: B Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 42) What is the formula for the break-even point of a simple profit model? A) Fixed Cost / Variable Cost Per Unit B) (Selling Price Per Unit —Variable Cost Per Unit) / Fixed Cost C) Fixed Cost / (Selling Price Per Unit —Variable Cost Per Unit) D) Fixed Cost / (Variable Cost Per Unit — Selling Price Per Unit) E) Selling Price Per Unit — (Fixed Cost / Variable Cost Per Unit) Answer: C Diff: 2 Topic: HOW TO DEVELOP A QUANTITATIVE ANALYSIS MODEL AACSB: Quantitative Skills 8 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 43) The break-even point of a simple profit model represents a(n) A) decision variable. B) uncontrollable variable. C) parameter. D) constant. E) None of the above Answer: A Diff: 3 Topic: HOW TO DEVELOP A QUANTITATIVE ANALYSIS MODEL 44) A(n) ________ model is one that is accurate and correctly represents the problem or system under investigation. A) robust B) valid C) sensitive D) optimal E) feasible Answer: B Diff: 2 Topic: HOW TO DEVELOP A QUANTITATIVE ANALYSIS MODEL 45) Which Excel feature is an optimization technique that can maximize or minimize a quantity given a set of limitations or constraints? A) Optimizer B) Goal Seek C) Analysis Tool-Pak D) Algorithm Builder E) Solver Answer: E Diff: 3 Topic: THE ROLE OF COMPUTERS AND SPREADSHEET MODELS IN THE QUANTITATIVE ANALYSIS APPROACH AACSB: Use of IT 46) Which Excel feature allows the user to specify a target or goal and the variable that is desired to change in order to achieve that goal? A) Solver B) Goal Search C) Target Search D) Goal Seek E) Target Seek Answer: D Diff: 3 Topic: THE ROLE OF COMPUTERS AND SPREADSHEET MODELS IN THE QUANTITATIVE ANALYSIS APPROACH 9 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Use of IT 47) All of the following are real computer applications that perform quantitative analysis except A) Solver in Excel. B) Goal Seek in Excel. C) Excel QM. D) POM-QM for Windows. E) QA for Windows. Answer: E Diff: 2 Topic: THE ROLE OF COMPUTERS AND SPREADSHEET MODELS IN THE QUANTITATIVE ANALYSIS APPROACH AACSB: Use of IT 48) As one attempts to develop a model, which of the following problems might she encounter? A) The problem may not fit a textbook approach. B) There will be no data available to test the model. C) Not everyone will understand the problem in the same way. D) All of the above E) None of the above Answer: D Diff: 1 Topic: POSSIBLE PROBLEMS IN THE QUANTITATIVE ANALYSIS APPROACH 49) Which of the following is a picture, drawing, or chart of reality? A) scale model B) physical model C) mathematical model D) schematic model E) abstract model Answer: D Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 50) Which of the following is not considered a possible problem in the quantitative analysis approach? A) validity of the data B) lack of commitment C) resistance to change D) subjective solutions E) hard-to-understand mathematics Answer: D Diff: 2 Topic: POSSIBLE PROBLEMS IN THE QUANTITATIVE ANALYSIS APPROACH 10 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 51) Quantitative analysis is ________. Answer: the scientific approach to managerial decision making Diff: 2 Topic: WHAT IS QUANTITATIVE ANALYSIS? 52) Identify the steps of the quantitative analysis approach. Answer: (1) Defining the Problem, (2) Developing a Model, (3) Acquiring Input Data, (4) Developing a Solution, (5) Testing the Solution, (6) Analyzing the Results, and (7) Implementing the Results Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH AACSB: Analytic Skills 53) A controllable variable is also called a ________ variable. Answer: decision Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 54) A picture, drawing, or chart of reality is a ________ model Answer: schematic Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 55) Identify some possible problems in the quantitative analysis approach. Answer: Answers will vary but may include: conflicting viewpoints, ignoring the impact on other departments, poor assumptions, outdated solutions, difficulty matching the textbook approach, trading off model complexity with ease of understanding, poor input data, hard-to-understand mathematics, and having only one answer is limiting. Diff: 2 Topic: POSSIBLE PROBLEMS IN THE QUANTITATIVE ANALYSIS APPROACH 56) Identify three potential problems with people (two with management and one with the quantitative analysts themselves) that may hinder successful implementation of a quantitative model. Answer: Answers will vary but may include: (1) lack of commitment by management, (2) resistance to change by management, and (3) lack of commitment by quantitative analysts. Diff: 2 Topic: IMPLEMENTATION–NOT JUST THE FINAL STEP 11 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 57) In making a decision, both ________ and quantitative factors must be considered. Answer: qualitative Diff: 2 Topic: WHAT IS QUANTITATIVE ANALYSIS? 58) Inaccurate model input data leads to inaccurate model solutions. This phenomenon is commonly referred to as ________. Answer: garbage in, garbage out Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 59) The solution process of ________ implies that we look at all possible solutions. Answer: complete enumeration Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 60) Once we have a solution, we should then perform ________ analysis. Answer: sensitivity or postoptimality Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 61) ________ models do not involve risk or chance. Answer: Deterministic Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 62) ________ models are synonymous with stochastic models. Answer: Probabilistic Diff: 2 Topic: THE QUANTITATIVE ANALYSIS APPROACH 63) How can an analyst overcome the threats to successful implementation of a quantitative model? Answer: Answers will vary; one solution is for analysts to work with users and take their feelings into account instead of telling them what to do. Diff: 2 Topic: IMPLEMENTATION–NOT JUST THE FINAL STEP Quantitative Analysis for Management, 11e (Render) Chapter 3 Decision Analysis 1) Expected monetary value (EMV) is the average or expected monetary outcome of a decision if it can be repeated a large number of times. Answer: TRUE Diff: 2 12 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: DECISION MAKING UNDER RISK 2) Expected monetary value (EMV) is the payoff you should expect to occur when you choose a particular alternative. Answer: FALSE Diff: 2 Topic: DECISION MAKING UNDER RISK 3) The decision maker can control states of nature. Answer: FALSE Diff: 1 Topic: THE SIX STEPS IN DECISION MAKING 4) All decisions that result in a favorable outcome are considered to be good decisions. Answer: FALSE Diff: 2 Topic: INTRODUCTION 5) The difference in decision making under risk and decision making under uncertainty is that under risk, we think we know the probabilities of the states of nature, while under uncertainty we do not know the probabilities of the states of nature. Answer: TRUE Diff: 2 Topic: TYPES OF DECISION-MAKING ENVIRONMENTS 6) EVPI (expected value of perfect information) is a measure of the maximum EMV as a result of additional information. Answer: TRUE Diff: 2 Topic: DECISION MAKING UNDER RISK 7) When using the EOL as a decision criterion, the best decision is the alternative with the largest EOL value. Answer: FALSE Diff: 2 Topic: DECISION MAKING UNDER RISK 8) To determine the effect of input changes on decision results, we should perform a sensitivity analysis. Answer: TRUE Diff: 2 Topic: DECISION MAKING UNDER RISK 9) The maximax decision criterion is used by pessimistic decision makers and maximizes the maximum outcome for every alternative. Answer: FALSE Diff: 1 13 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: DECISION MAKING UNDER UNCERTAINTY 10) The maximin decision criterion is used by pessimistic decision makers and minimizes the maximum outcome for every alternative. Answer: FALSE Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY 11) Optimistic decision makers tend to discount favorable outcomes. Answer: FALSE Diff: 2 Topic: THE SIX STEPS IN DECISION MAKING 12) The decision theory processes of maximizing expected monetary value (EMV) and minimizing expected opportunity loss (EOL) should lead us to choose the same alternatives. Answer: TRUE Diff: 2 Topic: DECISION MAKING UNDER RISK 13) The several criteria (maximax, maximin, equally likely, criterion of realism, minimax regret) used for decision making under uncertainty may lead to the choice of different alternatives. Answer: TRUE Diff: 1 Topic: DECISION MAKING UNDER UNCERTAINTY 14) A decision table is sometimes called a payout table. Answer: TRUE Diff: 2 Topic: THE SIX STEPS IN DECISION MAKING 15) The nodes on decision trees represent either decisions or states of nature. Answer: TRUE Diff: 2 Topic: DECISION TREES 16) Any problem that can be presented in a decision table can also be graphically portrayed in a decision tree. Answer: TRUE Diff: 2 Topic: DECISION TREES 17) Any problem that can be represented in a decision tree can be easily portrayed in a decision table. Answer: FALSE Diff: 2 Topic: DECISION TREES 14 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 18) In a decision table, all of the alternatives are listed down the left side of the table, while all of the possible outcomes or states of nature are listed across the top. Answer: TRUE Diff: 2 Topic: THE SIX STEPS IN DECISION MAKING 19) The EMV approach and Utility theory always result in the same choice of alternatives. Answer: FALSE Diff: 1 Topic: UTILITY THEORY 20) Utility theory may help the decision maker include the impact of qualitative factors that are difficult to include in the EMV model. Answer: TRUE Diff: 1 Topic: UTILITY THEORY 21) In a decision problem where we wish to use Bayes' theorem to calculate posterior probabilities, we should always begin our analysis with the assumption that all states of nature are equally likely, and use the sample information to revise these probabilities to more realistic values. Answer: FALSE Diff: 2 Topic: HOW PROBABILITY VALUES ARE ESTIMATED BY BAYESIAN ANALYSIS 22) A utility curve that shows utility increasing at an increasing rate as the monetary value increases represents the utility curve of a risk seeker. Answer: TRUE Diff: 2 Topic: UTILITY THEORY 23) A utility curve that shows utility increasing at a decreasing rate as the monetary value increases represents the utility curve of a risk seeker. Answer: FALSE Diff: 2 Topic: UTILITY THEORY 24) The criterion of realism is also called the Laplace criterion. Answer: FALSE Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY 25) Utility values typically range from -1 to +1. Answer: FALSE Diff: 2 Topic: UTILITY THEORY 15 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 16 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 26) By studying a person's Utility Curve, one can determine whether the individual is a risk seeker, risk avoider, or is indifferent to risk. Answer: TRUE Diff: 2 Topic: UTILITY THEORY 27) The equally likely decision criterion is also called the Laplace criterion. Answer: TRUE Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY 28) Utility theory provides a decision criterion that is superior to the EMV or EOL in that it may allow the decision maker to incorporate her own attitudes toward risk. Answer: TRUE Diff: 2 Topic: UTILITY THEORY 29) The assignment of a utility value of 1 to an alternative implies that alternative is preferred to all others. Answer: TRUE Diff: 2 Topic: UTILITY THEORY 30) A second table (an opportunity loss table) must be computed when applying the maximin decision criterion. Answer: FALSE Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY 31) The following figure illustrates a utility curve for someone who is a risk seeker. Answer: TRUE Diff: 2 17 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: UTILITY THEORY 18 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 32) An analytic and systematic approach to the study of decision making is referred to as A) decision making under risk. B) decision making under uncertainty. C) decision theory. D) decision analysis. E) decision making under certainty. Answer: C Diff: 2 Topic: INTRODUCTION 33) What makes the difference between good decisions and bad decisions? A) A good decision is based on logic. B) A good decision considers all available data. C) A good decision considers all alternatives. D) A good decision applies quantitative approaches. E) All the above Answer: C Diff: 1 Topic: INTRODUCTION 34) Expected monetary value (EMV) is A) the average or expected monetary outcome of a decision if it can be repeated a large number of times. B) the average or expected value of the decision, if you know what would happen ahead of time. C) the average or expected value of information if it were completely accurate. D) the amount you would lose by not picking the best alternative. E) a decision criterion that places an equal weight on all states of nature. Answer: A Diff: 2 Topic: DECISION MAKING UNDER RISK 35) Which of the following is not considered a criteria for decision making under uncertainty? A) optimistic B) pessimistic C) equally likely D) random selection E) minimax regret Answer: D Diff: 1 Topic: DECISION MAKING UNDER UNCERTAINTY 36) A pessimistic decision making criterion is A) maximax. B) equally likely. C) maximin. D) decision making under certainty. 19 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall E) minimax regret. Answer: C Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY 37) Which of the following is true about the expected value of perfect information? A) It is the amount you would pay for any sample study. B) It is calculated as EMV minus EOL. C) It is calculated as expected value with perfect information minus maximum EMV. D) It is the amount charged for marketing research. E) None of the above Answer: C Diff: 2 Topic: DECISION MAKING UNDER RISK 38) Which of the following is not a characteristic of a good decision? A) based on logic B) considers all available data C) considers all possible alternatives D) employs appropriate quantitative techniques E) always results in a favorable outcome Answer: E Diff: 2 Topic: INTRODUCTION 39) The following is a payoff table giving profits for various situations. What decision would an optimist make? A) Alternative 1 B) Alternative 2 C) Alternative 3 D) Do Nothing E) State of Nature A Answer: B Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 20 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 40) The following is a payoff table giving profits for various situations. What decision would a pessimist make? A) Alternative 1 B) Alternative 2 C) Alternative 3 D) Do Nothing E) State of Nature A Answer: A Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 41) The following is an opportunity loss table. What decision should be made based on the minimax regret criterion? A) Alternative 1 B) Alternative 2 C) Alternative 3 D) State of Nature A E) Does not matter Answer: C Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 21 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 42) The following is an opportunity loss table. What decision should be made based on the minimax regret criterion? A) Alternative 1 B) Alternative 2 C) Alternative 3 D) State of Nature C E) Does not matter Answer: B Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 43) The following is a payoff table. What decision should be made based on the minimax regret criterion? A) Alternative 1 B) Alternative 2 C) Alternative 3 D) State of Nature C E) Does not matter Answer: A Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 22 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 44) The following is a payoff table. What decision should be made based on the minimax regret criterion? A) Alternative 1 B) Alternative 2 C) Alternative 3 D) State of Nature C E) Does not matter Answer: A Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 45) The following is an opportunity-loss table. The probabilities for the states of nature A, B, and C are 0.3, 0.5, and 0.2, respectively. If a person were to use the expected opportunity loss criterion, what decision would be made? A) Alternative 1 B) Alternative 2 C) Alternative 3 D) State of Nature C E) State of Nature B Answer: C Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 23 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 46) The following is a payoff table giving profits for various situations. The probabilities for states of nature A, B, and C are 0.3, 0.5, and 0.2, respectively. If a person selected Alternative 1, what would the expected profit be? A) 120 B) 133.33 C) 126 D) 180 E) None of the above Answer: C Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 47) Dr. Mac, a surgeon, must decide what mode of treatment to use on Mr. Samuels. There are three modes of treatment: Mode A, B, and C; and three possible states of nature: 1.Treatment succeeds and patient leads a normal life, 2. Patient survives treatment but is permanently disabled, and 3. Patient fails to survive treatment. Dr. Mac has prepared the decision table below. What mode of treatment maximizes the expected value? A) Mode A B) Mode B C) Mode C D) All three treatments are equally desirable. E) Normal Life Answer: C Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 24 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 48) Consider the following payoff table. Based upon these probabilities, a person would select Alternative 2. Suppose there is concern about the accuracy of these probabilities. It can be stated that Alternative 2 will remain the best alternative as long as the probability of A is at least A) 0.33. B) 0.50. C) 0.40. D) 0.60. E) None of the above Answer: A Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 49) Consider the following payoff table. How much should be paid for a perfect forecast of the state of nature? A) 170 B) 30 C) 10 D) 100 E) 40 Answer: B Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 25 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 50) The following is a payoff table giving profits for various situations. The probabilities for states of nature A, B, and C are 0.3, 0.5, and 0.2, respectively. If a perfect forecast of the future were available, what is the expected value with this perfect information? A) 130 B) 160 C) 166 D) 36 E) None of the above Answer: C Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 51) The following is a payoff table giving profits for various situations. The probabilities for states of nature A, B, and C are 0.3, 0.5, and 0.2, respectively. If a perfect forecast of the future were available, what is the expected value of perfect information (EVPI)? A) 166 B) 0 C) 36 D) 40 E) None of the above Answer: C Diff: 3 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 26 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 52) Nick has plans to open some pizza restaurants, but he is not sure how many to open. He has prepared a payoff table to help analyze the situation. As Nick does not know how his product will be received, he assumes that all three states of nature are equally likely to occur. If he uses the equally likely criterion, what decision would he make? A) Open 1 B) Open 2 C) Good market D) Fair market E) Do nothing Answer: B Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 53) Nick has plans to open some pizza restaurants, but he is not sure how many to open. He has prepared a payoff table to help analyze the situation. Nick believes there is a 40 percent chance that the market will be good, a 30 percent chance that it will be fair, and a 30 percent chance that it will be poor. A market research firm will analyze market conditions and will provide a perfect forecast (they provide a money back guarantee). What is the most that should be paid for this forecast? A) $ 44,000 B) $ 53,000 C) $123,000 D) $176,000 E) $132,000 Answer: C Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 27 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 54) Which of the following is the fourth step of the "Six Steps in Decision Making"? A) Select one of the mathematical decision theory models. B) List the possible alternatives. C) Apply the model and make your decision. D) List the payoff or profit of each combination of alternatives and outcomes. E) Identify the possible outcomes or states of nature. Answer: D Diff: 2 Topic: THE SIX STEPS IN DECISION MAKING 55) Which of the following is not one of the steps considered in the "Six Steps in Decision Making"? A) Clearly define the problem at hand B) List the possible alternatives. C) Apply the model and make your decision. D) List the payoff or profit of each combination of alternatives and outcomes. E) Evaluate the success of the decision. Answer: E Diff: 2 Topic: THE SIX STEPS IN DECISION MAKING 56) Optimistic decision makers tend to ________. A) magnify favorable outcomes B) ignore bad outcomes C) discount favorable outcomes D) A and B E) B and C Answer: D Diff: 2 Topic: THE SIX STEPS IN DECISION MAKING AACSB: Reflective Thinking 57) Pessimistic decision makers tend to ________. A) magnify favorable outcomes B) ignore bad outcomes C) discount favorable outcomes D) A and B E) B and C Answer: C Diff: 2 Topic: THE SIX STEPS IN DECISION MAKING 28 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 58) In decision theory, we call the payoffs resulting from each possible combination of alternatives and outcomes ________. A) marginal values B) conditional values C) conditional probabilities D) Bayesian values E) joint values Answer: B Diff: 2 Topic: THE SIX STEPS IN DECISION MAKING 59) Another name for a decision table is a ________. A) payment table B) payout table C) payoff table D) pay-up table E) decision tree Answer: C Diff: 1 Topic: THE SIX STEPS IN DECISION MAKING 60) How are decision tables organized? A) alternatives down the left, states of nature on top, payoffs inside B) states of nature down the left, alternatives on top, payoffs inside C) alternatives down the left, payoffs on top, states of nature inside D) payoffs down the left, alternatives on top, states of nature inside E) states of nature down the left, payoffs on top, alternatives inside Answer: A Diff: 1 Topic: THE SIX STEPS IN DECISION MAKING 61) The three decision-making environments are decision making under ________. A) utility, risk, and certainty B) utility, risk, and uncertainty C) utility, certainty, and uncertainty D) utility, equity, and certainty E) risk, certainty, and uncertainty Answer: E Diff: 1 Topic: TYPES OF DECISION-MAKING ENVIRONMENTS 29 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 62) In decision making under ________, there are several possible outcomes for each alternative, and the decision maker does not know the probabilities of the various outcomes. A) risk B) utility C) certainty D) probability E) uncertainty Answer: E Diff: 2 Topic: TYPES OF DECISION-MAKING ENVIRONMENTS 63) In decision making under ________, there are several possible outcomes for each alternative, and the decision maker knows the probability of occurrence of each outcome. A) risk B) utility C) certainty D) probability E) uncertainty Answer: A Diff: 2 Topic: TYPES OF DECISION-MAKING ENVIRONMENTS 64) The optimistic decision criterion is the criterion of ________. A) maximax B) maximin C) realism D) equally likely E) minimax regret Answer: A Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY 65) The Hurwicz criterion is also called the criterion of ________. A) regret B) equality C) optimism D) realism E) pessimism Answer: D Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY 30 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 66) The equally likely criterion is also called the ________ criterion. A) Hurwicz B) uncertainty C) Laplace D) LaFlore E) Huchenmeizer Answer: C Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY 67) Decision trees are particularly useful when A) perfect information is available. B) formulating a conditional values table. C) the opportunity loss table is available. D) a sequence of decisions must be made. E) all possible outcomes and alternatives are not known. Answer: D Diff: 2 Topic: DECISION TREES 68) The expected value of sample information (EVSI) can be used to A) establish a maximum amount to spend on additional information. B) calculate conditional probabilities. C) establish risk avoidance. D) provide points on a utility curve. E) None of the above Answer: A Diff: 2 Topic: DECISION MAKING UNDER RISK 69) A market research survey is available for $10,000. Using a decision tree analysis, it is found that the expected monetary value with no survey is $62,000. If the expected value of sample information is -$7,000, what is the expected monetary value with the survey? A) $45,000 B) $62,000 C) -$17,000 D) $55,000 E) None of the above Answer: A Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 31 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 70) A market research survey is available for $10,000. Using a decision tree analysis, it is found that the expected monetary value with the survey is $75,000. The expected monetary value with no survey is $62,000. What is the expected value of sample information? A) -$7,000 B) $3,000 C) $7,000 D) $13,000 E) None of the above Answer: E Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 71) In the construction of decision trees, which of the following shapes represents a state of nature node? A) square B) circle C) diamond D) triangle E) None of the above Answer: B Diff: 1 Topic: DECISION MAKING UNDER RISK 72) In the construction of decision trees, which of the following shapes represents a decision node? A) square B) circle C) diamond D) triangle E) None of the above Answer: A Diff: 1 Topic: DECISION MAKING UNDER RISK 73) Bayes' theorem enables decision makers to revise probabilities based on A) perfect information. B) knowing, ahead of time, the actual outcome of the decision. C) additional information. D) measurements of utility. E) None of the above Answer: C Diff: 2 Topic: HOW PROBABILITY VALUES ARE ESTIMATED BY BAYESIAN ANALYSIS 32 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 74) In Bayesian analysis, conditional probabilities are also known as which of the following? A) anterior probabilities B) posterior probabilities C) prior probabilities D) marginal probabilities E) joint probabilities Answer: B Diff: 2 Topic: HOW PROBABILITY VALUES ARE ESTIMATED BY BAYESIAN ANALYSIS 75) A company is considering producing a new children's bar soap. A market research firm has told the company that if they perform a survey, a positive survey of a favorable market occurs 65 percent of the time. That is, P(positive survey ∣ favorable market) = 0.65. Similarly, 40 percent of the time the survey falsely predicts a favorable market; thus, P(positive survey ∣ unfavorable market) = 0.40. These statistics indicate the accuracy of the survey. Prior to contacting the market research firm, the company's best estimate of a favorable market was 50 percent. So, P(favorable market) = 0.50 and P(unfavorable market) = 0.50. Using Bayes' theorem, determine the probability of a favorable market given a favorable survey. A) 0.62 B) 0.38 C) 0.53 D) 0.65 E) None of the above Answer: A Diff: 2 Topic: HOW PROBABILITY VALUES ARE ESTIMATED BY BAYESIAN ANALYSIS AACSB: Analytic Skills 76) The Hurwicz criterion coefficient of realism measures the decision maker's degree of ________. A) utility B) pessimism C) certainty D) optimism E) regret Answer: D Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY 77) What is the range of the Hurwicz criterion coefficient of realism α? A) 1 to 100 B) 1 to 10 C) 0 to 10 D) 0 to 1 E) −1 to 1 Answer: D Diff: 2 33 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: DECISION MAKING UNDER UNCERTAINTY 78) Utilization of Bayes' theorem requires the use of all but A) prior probabilities. B) marginal probabilities. C) conditional probabilities. D) posterior probabilities. E) expected monetary values (EMV). Answer: E Diff: 2 Topic: HOW PROBABILITY VALUES ARE ESTIMATED BY BAYESIAN ANALYSIS 79) A risk avoider is a person for whom the utility of an outcome A) decreases as the monetary value increases. B) stays the same as monetary value increases. C) increases at an increasing rate as the monetary value increases. D) increases at a decreasing rate as monetary value increases. E) None of the above Answer: D Diff: 2 Topic: UTILITY THEORY 80) A utility curve showing utility increasing at an increasing rate as the monetary value increases represents A) a risk avoider. B) utility assessment. C) a risk seeker. D) conditional values. E) expected utilities. Answer: C Diff: 2 Topic: UTILITY THEORY 81) In constructing a utility curve, A) a comparison is made of the different amounts of money at different times. B) the certainty of a certain amount is compared with the willingness to gamble that amount on a larger amount. C) one takes the risk out of gambling. D) inflation plays a critical part in the evaluation. E) None of the above Answer: B Diff: 2 Topic: UTILITY THEORY 82) Utility values typically range from A) -1 to 1 B) 1 to 10 34 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall C) 0 to 1 D) 1 to 100 E) None of the above Answer: C Diff: 2 Topic: UTILITY THEORY 83) A rational decision maker must choose between two alternatives. Alternative 1 has a higher EMV than Alternative 2, but the decision maker chooses Alternative 2. What might explain why this occurs? A) Alternative 2 may have a higher expected utility. B) Alternative 1 may have a lower expected opportunity loss. C) The probabilities are not known. D) A rational decision maker could not possibly choose alternative 2. E) None of the above Answer: A Diff: 2 Topic: UTILITY THEORY AACSB: Reflective Thinking 84) Robert Weed is considering purchasing life insurance. He must pay a $180 premium for a $100,000 life insurance policy. If he dies this year, his beneficiary will receive $100,000. If he does not die this year, the insurance company pays nothing and Robert must consider paying another premium next year. Based on actuarial tables, there is a 0.001 probability that Robert will die this year. If Robert wishes to maximize his EMV, he would not buy the policy if the EMV were negative for him. He has determined that the EMV is, negative for him, but decides to purchase the insurance anyway. Why? A) He believes that the actual likelihood of his death occurring in the next twelve months is really much greater than the actuarial estimate. B) While the EMV is negative, the utility gained from purchasing the insurance is positive, and high. C) Mr. Weed is not rational. D) A or C E) None of the above Answer: B Diff: 2 Topic: UTILITY THEORY AACSB: Reflective Thinking 85) If one's utility curve is not a straight line (i.e., risk indifferent), then one's utility can, over a particular range of EMV, A) increase at an increasing rate as the monetary value increases. B) increase at an increasing rate as the monetary value decreases. C) increase at a decreasing rate as the monetary value increases. D) increase at a decreasing rate as the monetary value decreases. E) Any of the above Answer: E Diff: 2 35 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: UTILITY THEORY 86) It is sometimes said that "Those who gamble the most are the ones who can least afford to lose." These people gamble because A) the EMV is positive. B) the EMV is negative. C) the gambler has no family to consider if he/she dies. D) there is utility other than monetary to consider. E) None of the above Answer: D Diff: 2 Topic: UTILITY THEORY 87) A manager is deciding whether or not to build a small facility. Demand is uncertain and can be either at a high or low level. If the manager chooses a small facility and demand is low, the payoff is $300. If the manager chooses a small facility and demand is high, the payoff is $100. On the other hand, if the manager chooses a large facility and demand is low, the payoff is -$200, but if demand is high, the payoff is $800. (a) What would be the best decision based on the maximax criterion? (b) What would be the best decision based on the maximin criterion? (c) What would be the best decision based on the minimax regret? Answer: (a) large facility highest overall payoff = $800 (b) small facility highest minimum potential payoff = $100 (c) large facility lowest maximum regret = $500 Diff: 1 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 88) A manager is deciding whether or not to build a small facility. Demand is uncertain and can be either at a high or low level. If the manager chooses a small facility and demand is low, the payoff is $100. If the manager chooses a small facility and demand is high, the payoff is $300. On the other hand, if the manager chooses a large facility and demand is low, the payoff is -$200, but if demand is high, the payoff is $800. (a) What would be the best decision based on the Laplace criterion? (b) What would be the best decision based on Hurwicz's criterion of realism using α = 0.6? Answer: (a) large facility equally weighted payoff = $300 (b) large facility weighted average = $400 Diff: 1 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 89) A concessionaire for the local ballpark has developed a table of conditional values for the various alternatives (stocking decision) and states of nature (size of crowd). 36 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall If the probabilities associated with the states of nature are 0.30 for a large crowd, 0.50 for an average crowd, and 0.20 for a small crowd, determine: (a) the alternative that provides the greatest expected monetary value (EMV) (b) the expected value of perfect information (EVPI) Answer: (a) For large inventory alternative maximum EMV = $12,200 (b) EVPI = 13800 -12200 = 1,600 Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 90) A concessionaire for the local ballpark has developed a table of conditional values for the various alternatives (stocking decision) and states of nature (size of crowd). If the probabilities associated with the states of nature are 0.30 for a large crowd, 0.50 for an average crowd, and 0.20 for a small crowd, determine: (a) the opportunity loss table. (b) minimum expected opportunity loss (EOL). Answer: (a) Opportunity loss table (b) minimum EOL = $1,600 Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 37 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 91) The ABC Co. is considering a new consumer product. They believe there is a probability of 0.4 that the XYZ Co. will come out with a competitive product. If ABC adds an assembly line for the product and XYZ does not follow with a competitive product, their expected profit is $40,000; if they add an assembly line and XYZ does follow, they still expect a $10,000 profit. If ABC adds a new plant addition and XYZ does not produce a competitive product, they expect a profit of $600,000; if XYZ does compete for this market, ABC expects a loss of $100,000. (a) Determine the EMV of each decision. (b) Determine the EOL of each decision. (c) Compare the results of (a) and (b). (d) Calculate the EVPI. Answer: (a) (b) (c) The plant addition is best for both models. The maximum EMV alternative is always the same as the minimum EOL alternative. (d) EVPI = 44,000 Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 92) The ABC Co. is considering a new consumer product. They have no idea whether or not the XYZ Co. will come out with a competitive product. If ABC adds an assembly line for the product and XYZ does not follow with a competitive product, their expected profit is $40,000; if they add an assembly line and XYZ does follow, they still expect a $10,000 profit. If ABC adds a new plant addition and XYZ does not produce a competitive product, they expect a profit of $600,000; if XYZ does compete for this market, ABC expects a loss of $100,000. Calculate Hurwicz's criterion of realism using α's of a. 0.7, b. 0.3, and c. 0.1. Answer: Diff: 2 38 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skill 93) Barbour Electric is considering the introduction of a new product. This product can be produced in one of several ways: (a) using the present assembly line at a cost of $25 per unit, (b) using the current assembly line after it has been overhauled (at a cost of $10,000) with a cost of $22 per unit; and (c) on an entirely new assembly line (costing $30,000) designed especially for the new product with a per unit cost of $20. Barbour is worried, however, about the impact of competition. If no competition occurs, they expect to sell 15,000 units the first year. With competition, the number of units sold is expected to drop to 9,000. At the moment, their best estimate is that there is a 40% chance of competition. They have decided to make their decision based on the first year sales. (a) Develop the decision table (EMV). (b) Develop a decision table (EOL). (c) What should they do? Answer: (a) (b) (c) They should build the new line. Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 39 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 94) The following payoff table provides profits based on various possible decision alternatives and various levels of demand. The probability of a low demand is 0.4, while the probability of a medium and high demand is each 0.3. (a) What decision would an optimist make? (b) What decision would a pessimist make? (c) What is the highest possible expected monetary value? (d) Calculate the expected value of perfect information for this situation. Answer: (a) Alternative 3 (b) Alternative 2 (c) Alternative 1 maximum EMV = 110 (d) EVPI = 117- 110 = 7 Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY and DECISION MAKING UNDER RISK AACSB: Analytic Skills 95) The ABC Co. is considering a new consumer product. They believe that the XYZ Co. may come out with a competing product. If ABC adds an assembly line for the product and XYZ does not follow with a competitive product, their expected profit is $40,000; if they add an assembly line and XYZ does follow, they still expect a $10,000 profit. If ABC adds a new plant addition and XYZ does not produce a competitive product, they expect a profit of $600,000; if XYZ does compete for this market, ABC expects a loss of $100,000. For what value of probability that XYZ will offer a competing product will ABC be indifferent between the alternatives? Answer: Let X = probability XYZ offers a competing product. Then: EMV(assembly line) = $10,000∗X + $40,000∗(1-X) EMV(addition) = -$100,000∗X + $600,000∗(1-X) or: $10,000∗X + $40,000∗(1-X) = -$100,000*X + $600,000∗(1-X) or: $10,000∗X - $40,000∗X + $40,000 = -$100,000∗X -$600,000∗X + $600,000 -$30,000∗X + $700,000∗X = $600,000 - $40,000 $670,000∗X = $560,000 X = $560,000/$670,000 = 0.836 If the probability that XYZ will offer a competing product is estimated to be 0.836, then ABC will be indifferent 40 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall between the two alternatives. If the probability that XYZ will offer a competing product is estimated to be less than 0.836, then ABC should invest in the addition. 41 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 96) A company is considering expansion of its current facility to meet increasing demand. A major expansion would cost $500,000, while a minor expansion would cost $200,000. If demand is high in the future, the major expansion would result in an additional profit of $800,000, but if demand is low, then there would be a loss of $500,000. If demand is high, the minor expansion will result in an increase in profits of $200,000, but if demand is low, then there is a loss of $100,000. The company has the option of not expanding. For what probability of a high demand will the company be indifferent between the two expansion alternatives? Answer: If we define X = probability of high demand, then: $300,000∗X - $1,000,000∗(1-X) = $0∗X - $300,000∗(1-X) X = 0.7 For a probability of high demand equal to 0.7, the decision maker would be indifferent between the two expansion alternatives. Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 42 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 97) Orders for clothing from a particular manufacturer for this year's Christmas shopping season must be placed in February. The cost per unit for a particular dress is $20 while the anticipated selling price is $50. Demand is projected to be 50, 60, or 70 units. There is a 40 percent chance that demand will be 50 units, a 50 percent chance that demand will be 60 units, and a 10 percent chance that demand will be 70 units. The company believes that any leftover goods will have to be scrapped. How many units should be ordered in February? Answer: Payoff Table: EMV(50) = .4(1500) + .5(1500) + .1(1500) = 1500 EMV(60) = .4(1300) + .5(1800) + .1(1800) = 1600 EMV(70) = .4(1100) + .5(1600) + .1(2100) = 1450 Thus, 60 units should be ordered. Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 98) Suppose that the payoff from an investment depends upon market conditions. A great market has payoff of $200,000, a normal market has a payoff of $100,000, and a poor market has a payoff of $20,000. Using an α-value of 0.3, what is the criterion of realism value? Answer: 0.3($200,000) + 0.7($20,000) = $74,000 Diff: 1 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 99) A market research survey is available for $5,000. Using a decision tree analysis, it is found that the expected monetary value with no survey is $49,000. If the expected value of sample information is -$4,000, what is the expected monetary value with the survey? Answer: EV with SI = 49,000 - $4,000 + 5,000 = $50,000 Diff: 1 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 100) David N. Goliath is planning to open a sporting goods store. However, the initial investment is $120,000. He currently has this money in a certificate of deposit earning 10 percent. He may leave it there if he decides not to open the store. If he opens the store and it is successful he will generate a profit of $50,000. If it is not successful, he will lose $90,000. What would the probability of a successful store have to be for David to prefer this to investing in a CD? Answer: p(50,000) - (1-p)(90,000) > 0.10(120,000), therefore p > 0.7286 43 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 101) You are considering adding a new food product to your store for resale. You are certain that, in a month, minimum demand for the product will be 6 units, while maximum demand will be 8 units. (Unfortunately, the new product has a one-month shelf life and is considered to be waste at the end of the month.) You will pay $60/unit for this new product while you plan to sell the product at a $40/unit profit. The estimated demand for this new product in any given month is 6 units(p=0.1), 7 units(p=0.4), and 8 units(p=0.5). Using EMV analysis, how many units of the new product should be purchased for resale? Answer: EMV(purchase 6 for resale) = 6(40)(0.1) + 6(40)(0.4) + 6(40)(0.5) = 240 EMV(purchase 7 for resale) = [6(40)-60](0.1) + 7(40)(0.4) + 7(40)(0.5) = 270 EMV(purchase 8 for resale) = [6(40)-2(60)](0.1) + [7(40)-60](0.4) + 8(40)(0.5) = 260 Choose to purchase 7 units for resale (largest EMV) Diff: 2 Topic: DECISION MAKING UNDER RISK AACSB: Analytic Skills 102) Mark M. Upp has just been fired as the university bookstore manager for setting prices too low (only 20 percent above suggested retail). He is considering opening a competing bookstore near the campus, and he has begun an analysis of the situation. There are two possible sites under consideration. One is relatively small, while the other is large. If he opens at Site 1 and demand is good, he will generate a profit of $50,000. If demand is low, he will lose $10,000. If he opens at Site 2 and demand is high, he will generate a profit of $80,000, but he will lose $30,000 if demand is low. He also has the option of not opening at either site. He believes that there is a 50 percent chance that demand will be high. A market research study will cost $5,000. The probability of a good demand given a favorable study is 0.8. The probability of a good demand given an unfavorable study is 0.1. There is a 60 percent chance that the study will be favorable. (a) Should Mark use the study? Why? (b) If the study is done and the results are favorable, what would Mark's expected profit be? Answer: (a) Yes, he should use the study. His EMV with the study is $29,800 while the highest EMV without the study is $25,000. (b) Given a favorable survey result, Mark would select Site 2 and have an EMV of $53,000. Diff: 2 Topic: DECISION TREES AACSB: Analytic Skills 44 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 103) Mark M. Upp has just been fired as the university bookstore manager for setting prices too low (only 20 percent above suggested retail). He is considering opening a competing bookstore near the campus, and he has begun an analysis of the situation. There are two possible sites under consideration. One is relatively small, while the other is large. If he opens at Site 1 and demand is good, he will generate a profit of $50,000. If demand is low, he will lose $10,000. If he opens at Site 2 and demand is high, he will generate a profit of $80,000, but he will lose $30,000 if demand is low. He also has the option of not opening either. He believes that there is a 50 percent chance that demand will be high. Mark can purchase a market research study. The probability of a good demand given a favorable study is 0.8. The probability of a good demand given an unfavorable study is 0.1. There is a 60 percent chance that the study will be favorable. Should Mark use the study? Why? What is the maximum amount Mark should be willing to pay for this study? What is the maximum amount he should pay for any study? Answer: Yes, he should use the study. His EMV with the study is $34,800 while the highest EMV without the study is $25,000. He should pay no more than $9,800 for this study. He should pay no more than $10,000 for a "perfect" study. Diff: 2 Topic: DECISION TREES AACSB: Analytic Skills 104) Before a marketing research study was done, John Colorado believed there was a 50/50 chance that his music store would be a success. The research team determined that there is a 0.9 probability that the marketing research will be favorable given a successful music store. There is also a 0.8 probability that the marketing research will be unfavorable given an unsuccessful music store. (a) If the marketing research is favorable, what is the revised probability of a successful music store? (b) If the marketing research is unfavorable, what is the revised probability of a successful music store? Answer: (a) 0.82 (b) 0.11 Diff: 2 Topic: HOW PROBABILITY VALUES ARE ESTIMATED BY BAYESIAN ANALYSIS AACSB: Analytic Skills 105) Before a market survey is done, there is a 50/50 chance that a new soccer supply store would be a success. The people doing the survey have determined that there is a 0.9 probability that the survey will be favorable given a successful store. There is also a 0.75 probability that the survey will be unfavorable given an unsuccessful store. What is the probability that the survey will be unfavorable? Answer: (1−.9)(.5) + (.75)(.5) = 0.425 Diff: 2 Topic: HOW PROBABILITY VALUES ARE ESTIMATED BY BAYESIAN ANALYSIS AACSB: Analytic Skills 45 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 106) Before a marketing research study was done, John Colorado believed there was a 50/50 chance that his music store would be a success. The research team determined that there is a 0.9 probability that the marketing research will be favorable given a successful music store. There is also a 0.8 probability that the marketing research will be unfavorable given an unsuccessful music store. (a) If the marketing research is favorable, what is the revised probability of an unsuccessful music store? (b) If the marketing research is unfavorable, what is the revised probability of an unsuccessful music store? Answer: (a) 0.18 (b) 0.89 Diff: 2 Topic: HOW PROBABILITY VALUES ARE ESTIMATED BY BAYESIAN ANALYSIS AACSB: Analytic Skills 107) Mark M. Upp has just been fired as the university bookstore manager for setting prices too low (only 20 percent above suggested retail). He is considering opening a competing bookstore near the campus, and he has begun an analysis of the situation. There are two possible sites under consideration. One is relatively small while the other is large. If he opens at Site 1 and demand is good, he will generate a profit of $50,000. If demand is low, he will lose $10,000. If he opens at Site 2 and demand is high he will generate a profit of $80,000, but he will lose $30,000 if demand is low. He also has decided that he will open at one of these sites. He believes that there is a 60 percent chance that demand will be high. He assigns the following utilities to the different profits: Using expected utility theory, what should Mark do? Answer: Expected utility (Site 1) = 0.6(0.72) + 0.4(0.22) = 0.52 Expected utility (Site 2) = 0.6(1.00) + 0.4(0.00) = 0.60 Therefore he should open at Site 2. Diff: 2 Topic: UTILITY THEORY AACSB: Analytic Skills 46 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 108) Mark M. Upp has just been fired as the university book store manager for setting prices too low (only 20 percent above suggested retail). He is considering opening a competing bookstore near the campus, and he has begun an analysis of the situation. There are two possible sites under consideration. One is relatively small, while the other is large. If he opens at Site 1 and demand is good, he will generate a profit of $50,000. If demand is low, he will lose $10,000. If he opens at Site 2 and demand is high he will generate a profit of $80,000, but he will lose $30,000 if demand is low. He also has decided that he will open at one of these sites. He believes that there is a 50 percent chance that demand will be high. He assigns the following utilities to the different profits: For what value of utility for $50,000, U(50000), will Mark be indifferent between the two alternatives? Answer: Expected utility (Site 1) = 0.5X + 0.5(0.22) Expected utility (Site 2) = 0.5(1) + 0.5(0) = 0.50 Therefore: 0.5X + 0.5(0.22) = 0.50 or: 0.5X = 0.50 - 0.11 = 0.39 and: X = 0.39/0.5 = 0.78 Therefore, if Mark has U(50,000) = 0.78 he will be indifferent between the two alternatives. Diff: 2 Topic: UTILITY THEORY AACSB: Analytic Skills 109) Suppose that the payoff from an investment depends upon market conditions. A great market has payoff of $200,000, a normal market has a payoff of $100,000, and a poor market has a payoff of $20,000. What is the Laplace criterion value? Answer: ($200,000 + $100,000 + $20,000) / 3 = $320,000/3 = $106,667 Diff: 1 Topic: DECISION MAKING UNDER UNCERTAINTY AACSB: Analytic Skills 110) Briefly describe decision making under certainty. Answer: Decision makers know with certainty of the consequence of every alternative or decision choice. Diff: 2 Topic: TYPES OF DECISION-MAKING ENVIRONMENTS 111) Briefly describe decision making under risk. Answer: There are several possible outcomes for each alternative, and the decision maker knows the probability of occurrence of each outcome. Diff: 2 Topic: TYPES OF DECISION-MAKING ENVIRONMENTS 112) Briefly describe decision making under uncertainty. Answer: There are several possible outcomes for each alternative, and the decision maker does not know the probabilities of the various outcomes. Diff: 2 47 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: TYPES OF DECISION-MAKING ENVIRONMENTS 48 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 113) List the six steps in decision making. Answer: 1. Clearly define the problem at hand. 2. List the possible alternatives. 3. Identify the possible outcomes or states of nature. 4. List the payoff or profit of each combination of alternatives and outcomes. 5. Select one of the mathematical decision theory models. 6. Apply the model and make your decision. Diff: 2 Topic: THE SIX STEPS IN DECISION MAKING 114) Describe the structure of a payoff table. Answer: All of the alternatives are listed down the left side of the table, and all of the possible outcomes or states of nature are listed across the top. The body of the table contains the actual payoffs. Diff: 2 Topic: THE SIX STEPS IN DECISION MAKING 115) Briefly describe decision tree analysis. Answer: define the problem, draw the tree, assign the probabilities to the states of nature, estimate payoffs for each alternative, compute EMV Diff: 2 Topic: DECISION TREES 116) Briefly describe EVSI. Answer: EVSI = EMV (best decision with sample information) - EMV (of best decision without sample information) Diff: 2 Topic: DECISION TREES 117) Describe the utility curve of a risk seeker. Answer: utility increasing at an increasing rate as the monetary value increases Diff: 2 Topic: UTILITY THEORY 118) Describe the utility curve of a risk avoider. Answer: utility increasing at a decreasing rate as the monetary value increases Diff: 2 Topic: UTILITY THEORY 119) List the five major decision criteria used when making decisions under uncertainty. Answer: (1) maximax (optimistic), (2) maximin (pessimistic), (3) criterion of realism (Hurwicz), (4) equally likely (Laplace), and (5) minimax regret Diff: 2 Topic: DECISION MAKING UNDER UNCERTAINTY 49 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Quantitative Analysis for Management, 11e (Render) Chapter 7 Linear Programming Models: Graphical and Computer Methods 1) Management resources that need control include machinery usage, labor volume, money spent, time used, warehouse space used, and material usage. Answer: TRUE Diff: 1 Topic: INTRODUCTION 2) In the term linear programming, the word programming comes from the phrase "computer programming." Answer: FALSE Diff: 2 Topic: INTRODUCTION 3) One of the assumptions of LP is "simultaneity." Answer: FALSE Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 4) Any linear programming problem can be solved using the graphical solution procedure. Answer: FALSE Diff: 1 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 5) An LP formulation typically requires finding the maximum value of an objective while simultaneously maximizing usage of the resource constraints. Answer: FALSE Diff: 2 Topic: FORMULATING LP PROBLEMS 6) There are no limitations on the number of constraints or variables that can be graphed to solve an LP problem. Answer: FALSE Diff: 1 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 7) Resource restrictions are called constraints. Answer: TRUE Diff: 1 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 8) One of the assumptions of LP is "proportionality." Answer: TRUE Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 50 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 9) The set of solution points that satisfies all of a linear programming problem's constraints simultaneously is defined as the feasible region in graphical linear programming. Answer: TRUE Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 10) An objective function is necessary in a maximization problem but is not required in a minimization problem. Answer: FALSE Diff: 1 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 11) In some instances, an infeasible solution may be the optimum found by the corner point method. Answer: FALSE Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 12) The rationality assumption implies that solutions need not be in whole numbers (integers). Answer: FALSE Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 13) The solution to a linear programming problem must always lie on a constraint. Answer: TRUE Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 14) In a linear program, the constraints must be linear, but the objective function may be nonlinear. Answer: FALSE Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 15) Resource mix problems use LP to decide how much of each product to make, given a series of resource restrictions. Answer: FALSE Diff: 2 Topic: FORMULATING LP PROBLEMS 16) The existence of non-negativity constraints in a two-variable linear program implies that we are always working in the northwest quadrant of a graph. Answer: FALSE Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 17) In linear programming terminology, "dual price" and "sensitivity price" are synonyms. Answer: FALSE 51 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Diff: 2 Topic: SENSITIVITY ANALYSIS 52 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 18) Any time that we have an isoprofit line that is parallel to a constraint, we have the possibility of multiple solutions. Answer: TRUE Diff: 2 Topic: FOUR SPECIAL CASES IN LP 19) If the isoprofit line is not parallel to a constraint, then the solution must be unique. Answer: TRUE Diff: 2 Topic: FOUR SPECIAL CASES IN LP AACSB: Reflective Thinking 20) When two or more constraints conflict with one another, we have a condition called unboundedness. Answer: FALSE Diff: 2 Topic: FOUR SPECIAL CASES IN LP 21) The addition of a redundant constraint lowers the isoprofit line. Answer: FALSE Diff: 2 Topic: FOUR SPECIAL CASES IN LP 22) Sensitivity analysis enables us to look at the effects of changing the coefficients in the objective function, one at a time. Answer: TRUE Diff: 2 Topic: SENSITIVITY ANALYSIS 23) A widely used mathematical programming technique designed to help managers and decision making relative to resource allocation is called ________. A) linear programming B) computer programming C) constraint programming D) goal programming E) None of the above Answer: A Diff: 1 Topic: INTRODUCTION 24) Typical resources of an organization include ________. A) machinery usage B) labor volume C) warehouse space utilization D) raw material usage E) All of the above 53 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: E Diff: 1 Topic: INTRODUCTION 54 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 25) Which of the following is not a property of all linear programming problems? A) the presence of restrictions B) optimization of some objective C) a computer program D) alternate courses of action to choose from E) usage of only linear equations and inequalities Answer: C Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 26) A feasible solution to a linear programming problem A) must be a corner point of the feasible region. B) must satisfy all of the problem's constraints simultaneously. C) need not satisfy all of the constraints, only the non-negativity constraints. D) must give the maximum possible profit. E) must give the minimum possible cost. Answer: B Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 27) Infeasibility in a linear programming problem occurs when A) there is an infinite solution. B) a constraint is redundant. C) more than one solution is optimal. D) the feasible region is unbounded. E) there is no solution that satisfies all the constraints given. Answer: E Diff: 2 Topic: FOUR SPECIAL CASES IN LP 28) In a maximization problem, when one or more of the solution variables and the profit can be made infinitely large without violating any constraints, the linear program has A) an infeasible solution. B) an unbounded solution. C) a redundant constraint. D) alternate optimal solutions. E) None of the above Answer: B Diff: 2 Topic: FOUR SPECIAL CASES IN LP 29) Which of the following is not a part of every linear programming problem formulation? A) an objective function B) a set of constraints C) non-negativity constraints 55 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall D) a redundant constraint E) maximization or minimization of a linear function Answer: D Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 30) When appropriate, the optimal solution to a maximization linear programming problem can be found by graphing the feasible region and A) finding the profit at every corner point of the feasible region to see which one gives the highest value. B) moving the isoprofit lines towards the origin in a parallel fashion until the last point in the feasible region is encountered. C) locating the point that is highest on the graph. D) None of the above E) All of the above Answer: A Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 31) The mathematical theory behind linear programming states that an optimal solution to any problem will lie at a(n) ________ of the feasible region. A) interior point or center B) maximum point or minimum point C) corner point or extreme point D) interior point or extreme point E) None of the above Answer: C Diff: 1 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 32) Which of the following is not a property of linear programs? A) one objective function B) at least two separate feasible regions C) alternative courses of action D) one or more constraints E) objective function and constraints are linear Answer: B Diff: 1 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 33) The corner point solution method A) will always provide one, and only one, optimum. B) will yield different results from the isoprofit line solution method. C) requires that the profit from all corners of the feasible region be compared. D) requires that all corners created by all constraints be compared. E) will not provide a solution at an intersection or corner where a non-negativity constraint is involved. 56 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: C Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 57 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 34) When a constraint line bounding a feasible region has the same slope as an isoprofit line, A) there may be more than one optimum solution. B) the problem involves redundancy. C) an error has been made in the problem formulation. D) a condition of infeasibility exists. E) None of the above Answer: A Diff: 2 Topic: FOUR SPECIAL CASES IN LP 35) The simultaneous equation method is A) an alternative to the corner point method. B) useful only in minimization methods. C) an algebraic means for solving the intersection of two or more constraint equations. D) useful only when more than two product variables exist in a product mix problem. E) None of the above Answer: C Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 36) Consider the following linear programming problem: The maximum possible value for the objective function is A) 360. B) 480. C) 1520. D) 1560. E) None of the above Answer: C Diff: 3 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 58 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 37) Consider the following linear programming problem: The feasible corner points are (48,84), (0,120), (0,0), (90,0). What is the maximum possible value for the objective function? A) 1032 B) 1200 C) 360 D) 1600 E) None of the above Answer: B Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 38) Consider the following linear programming problem: Which of the following points (X,Y) is not a feasible corner point? A) (0,60) B) (105,0) C) (120,0) D) (100,10) E) None of the above Answer: C Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 59 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 39) Consider the following linear programming problem: Which of the following points (X,Y) is not feasible? A) (50,40) B) (20,50) C) (60,30) D) (90,10) E) None of the above Answer: A Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 40) Two models of a product — Regular (X) and Deluxe (Y) — are produced by a company. A linear programming model is used to determine the production schedule. The formulation is as follows: The optimal solution is X = 100, Y = 0. How many units of the regular model would be produced based on this solution? A) 0 B) 100 C) 50 D) 120 E) None of the above Answer: B Diff: 1 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 60 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 41) Two models of a product — Regular (X) and Deluxe (Y) — are produced by a company. A linear programming model is used to determine the production schedule. The formulation is as follows: The optimal solution is X=100, Y=0. Which of these constraints is redundant? A) the first constraint B) the second constraint C) the third constraint D) All of the above E) None of the above Answer: B Diff: 3 Topic: FOUR SPECIAL CASES IN LP AACSB: Analytic Skills 42) Consider the following linear programming problem: What is the optimum solution to this problem (X,Y)? A) (0,0) B) (50,0) C) (0,100) D) (400,0) E) None of the above Answer: B Diff: 3 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 61 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 43) Consider the following linear programming problem: This is a special case of a linear programming problem in which A) there is no feasible solution. B) there is a redundant constraint. C) there are multiple optimal solutions. D) this cannot be solved graphically. E) None of the above Answer: E Diff: 3 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 44) Consider the following linear programming problem: This is a special case of a linear programming problem in which A) there is no feasible solution. B) there is a redundant constraint. C) there are multiple optimal solutions. D) this cannot be solved graphically. E) None of the above Answer: A Diff: 3 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 62 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 45) Which of the following is not acceptable as a constraint in a linear programming problem (maximization)? A) Constraint 1 B) Constraint 2 C) Constraint 3 D) Constraint 4 E) None of the above Answer: A Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 46) If one changes the contribution rates in the objective function of an LP, A) the feasible region will change. B) the slope of the isoprofit or isocost line will change. C) the optimal solution to the LP is sure to no longer be optimal. D) All of the above E) None of the above Answer: B Diff: 2 Topic: SENSITIVITY ANALYSIS 47) Sensitivity analysis may also be called A) postoptimality analysis. B) parametric programming. C) optimality analysis. D) All of the above E) None of the above Answer: D Diff: 2 Topic: SENSITIVITY ANALYSIS 48) Sensitivity analyses are used to examine the effects of changes in A) contribution rates for each variable. B) technological coefficients. C) available resources. D) All of the above E) None of the above Answer: D Diff: 2 Topic: SENSITIVITY ANALYSIS 63 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 49) Which of the following is a basic assumption of linear programming? A) The condition of uncertainty exists. B) Independence exists for the activities. C) Proportionality exists in the objective function and constraints. D) Divisibility does not exist, allowing only integer solutions. E) Solutions or variables may take values from -∞ to +∞. Answer: C Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 50) The condition when there is no solution that satisfies all the constraints simultaneously is called A) boundedness. B) redundancy. C) optimality. D) dependency. E) None of the above Answer: E Diff: 2 Topic: FOUR SPECIAL CASES IN LP 51) If the addition of a constraint to a linear programming problem does not change the solution, the constraint is said to be A) unbounded. B) non-negative. C) infeasible. D) redundant. E) bounded. Answer: D Diff: 2 Topic: FOUR SPECIAL CASES IN LP 52) Which of the following is not an assumption of LP? A) simultaneity B) certainty C) proportionality D) divisibility E) additivity Answer: A Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 64 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 53) The difference between the left-hand side and right-hand side of a less-than-or-equal-to constraint is referred to as A) surplus. B) constraint. C) slack. D) shadow price. E) None of the above Answer: C Diff: 2 Topic: LINEAR PROGRAMMING MODELS: GRAPHICAL AND COMPUTER METHODS 54) The difference between the left-hand side and right-hand side of a greater-than-or-equal-to constraint is referred to as A) surplus. B) constraint. C) slack. D) shadow price. E) None of the above Answer: A Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 55) A constraint with zero slack or surplus is called a A) nonbinding constraint. B) resource constraint. C) binding constraint. D) nonlinear constraint. E) linear constraint. Answer: C Diff: 1 Topic: SOLVING FLAIR FURNITURE’S LP PROBLEM USING QM FOR WINDOWS AND EXCEL 56) A constraint with positive slack or surplus is called a A) nonbinding constraint. B) resource constraint. C) binding constraint. D) nonlinear constraint. E) linear constraint. Answer: A Diff: 1 Topic: SOLVING FLAIR FURNITURE’S LP PROBLEM USING QM FOR WINDOWS AND EXCEL 65 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 57) The increase in the objective function value that results from a one-unit increase in the right-hand side of that constraint is called A) surplus. B) shadow price. C) slack. D) dual price. E) None of the above Answer: B Diff: 2 Topic: SENSITIVITY ANALYSIS 58) A straight line representing all non-negative combinations of X1 and X2 for a particular profit level is called a(n) A) constraint line. B) objective line. C) sensitivity line. D) profit line. E) isoprofit line. Answer: E Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 59) In order for a linear programming problem to have a unique solution, the solution must exist A) at the intersection of the non-negativity constraints. B) at the intersection of a non-negativity constraint and a resource constraint. C) at the intersection of the objective function and a constraint. D) at the intersection of two or more constraints. E) None of the above Answer: D Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM 60) In order for a linear programming problem to have multiple solutions, the solution must exist A) at the intersection of the non-negativity constraints. B) on a non-redundant constraint parallel to the objective function. C) at the intersection of the objective function and a constraint. D) at the intersection of three or more constraints. E) None of the above Answer: B Diff: 2 Topic: FOUR SPECIAL CASES IN LP 66 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 61) Consider the following linear programming problem: The maximum possible value for the objective function is A) 360. B) 480. C) 1520. D) 1560. E) None of the above Answer: E Diff: 3 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 62) Consider the following linear programming problem: Which of the following points (X,Y) is feasible? A) (10,120) B) (120,10) C) (30,100) D) (60,90) E) None of the above Answer: C Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 67 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 63) Consider the following linear programming problem: Which of the following points (X,Y) is in the feasible region? A) (30,60) B) (105,5) C) (0,210) D) (100,10) E) None of the above Answer: D Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 64) Consider the following linear programming problem: Which of the following points (X,Y) is feasible? A) (50,40) B) (30,50) C) (60,30) D) (90,20) E) None of the above Answer: C Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 65) Which of the following is not an assumption of LP? A) certainty B) proportionality C) divisibility D) multiplicativity E) additivity Answer: D Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 68 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 66) Consider the following linear programming problem: This is a special case of a linear programming problem in which A) there is no feasible solution. B) there is a redundant constraint. C) there are multiple optimal solutions. D) this cannot be solved graphically. E) None of the above Answer: B Diff: 3 Topic: FOUR SPECIAL CASES IN LP AACSB: Analytic Skills 67) Which of the following functions is not linear? A) 5X + 3Z B) 3X + 4Y + Z - 3 C) 2X + 5YZ D) Z E) 2X - 5Y + 2Z Answer: C Diff: 1 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 68) Which of the following is not one of the steps in formulating a linear program? A) Graph the constraints to determine the feasible region. B) Define the decision variables. C) Use the decision variables to write mathematical expressions for the objective function and the constraints. D) Identify the objective and the constraints. E) Completely understand the managerial problem being faced. Answer: A Diff: 2 Topic: FORMULATING LP PROBLEMS 69 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 69) Which of the following is not acceptable as a constraint in a linear programming problem (minimization)? A) Constraint 1 B) Constraint 2 C) Constraint 3 D) Constraint 4 E) Constraint 5 Answer: E Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 70) What type of problems use LP to decide how much of each product to make, given a series of resource restrictions? A) resource mix B) resource restriction C) product restriction D) resource allocation E) product mix Answer: E Diff: 2 Topic: FORMULATING LP PROBLEMS 71) Consider the following linear programming problem: This is a special case of a linear programming problem in which A) there is no feasible solution. B) there is a redundant constraint. C) there are multiple optimal solutions. D) this cannot be solved graphically. E) None of the above Answer: B Diff: 3 Topic: FOUR SPECIAL CASES IN LP AACSB: Analytic Skills 70 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 72) Consider the following constraints from a linear programming problem: 2X + Y ≤ 200 X + 2Y ≤ 200 X, Y ≥ 0 If these are the only constraints, which of the following points (X,Y) cannot be the optimal solution? A) (0, 0) B) (0, 200) C) (0,100) D) (100, 0) E) (66.67, 66.67) Answer: B Diff: 3 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 73) Consider the following constraints from a linear programming problem: 2X + Y ≤ 200 X + 2Y ≤ 200 X, Y ≥ 0 If these are the only constraints, which of the following points (X,Y) cannot be the optimal solution? A) (0, 0) B) (0, 100) C) (65, 65) D) (100, 0) E) (66.67, 66.67) Answer: C Diff: 3 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 74) A furniture company is producing two types of furniture. Product A requires 8 board feet of wood and 2 lbs of wicker. Product B requires 6 board feet of wood and 6 lbs of wicker. There are 2000 board feet of wood available for product and 1000 lbs of wicker. Product A earns a profit margin of $30 a unit and Product B earns a profit margin of $40 a unit. Formulate the problem as a linear program. Answer: 71 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Diff: 2 Topic: FORMULATING LP PROBLEMS AACSB: Analytic Skills 75) As a supervisor of a production department, you must decide the daily production totals of a certain product that has two models, the Deluxe and the Special. The profit on the Deluxe model is $12 per unit and the Special's profit is $10. Each model goes through two phases in the production process, and there are only 100 hours available daily at the construction stage and only 80 hours available at the finishing and inspection stage. Each Deluxe model requires 20 minutes of construction time and 10 minutes of finishing and inspection time. Each Special model requires 15 minutes of construction time and 15 minutes of finishing and inspection time. The company has also decided that the Special model must comprise at least 40 percent of the production total. (a) Formulate this as a linear programming problem. (b) Find the solution that gives the maximum profit. Answer: (b) Optimal solution: X1 = 120, X2 = 240 Profit = $3,840 Diff: 3 Topic: FORMULATING LP PROBLEMS and GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 72 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 76) The Fido Dog Food Company wishes to introduce a new brand of dog biscuits (composed of chicken and liver-flavored biscuits) that meets certain nutritional requirements. The liver-flavored biscuits contain 1 unit of nutrient A and 2 units of nutrient B, while the chicken-flavored ones contain 1 unit of nutrient A and 4 units of nutrient B. According to federal requirements, there must be at least 40 units of nutrient A and 60 units of nutrient B in a package of the new biscuit mix. In addition, the company has decided that there can be no more than 15 liver-flavored biscuits in a package. If it costs 1 cent to make a liver-flavored biscuit and 2 cents to make a chicken-flavored one, what is the optimal product mix for a package of the biscuits in order to minimize the firm's cost? (a) Formulate this as a linear programming problem. (b) Find the optimal solution for this problem graphically. (c) Are any constraints redundant? If so, which one or ones? (d) What is the total cost of a package of dog biscuits using the optimal mix? Answer: (b) Corner points (0,40) and (15,25) Optimal solution is (15,25) with cost of 65. (c) 2X1 + 4X2 ≥ 60 is redundant. (d) minimum cost = 65 cents Diff: 3 Topic: FORMULATING LP PROBLEMS and GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 73 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 77) Consider the following linear program: (a) Solve the problem graphically. Is there more than one optimal solution? Explain. (b) Are there any redundant constraints? Answer: (a) Corner points (0,50), (0,200), (50,50), (75,75), (50,150) Optimum solutions: (75,75) and (50,150). Both yield a profit of $3,000. (b) The constraint X1 ≤ 100 is redundant since 3X1 + X2 ≤ 300 also means that X1 cannot exceed 100. Diff: 3 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 78) Solve the following linear programming problem using the corner point method: Answer: Feasible corner points (X,Y): (0,3) (0,10) (2.4,8.8) (6.75,3) Maximum profit 70.5 at (6.75,3). Diff: 3 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 79) Solve the following linear programming problem using the corner point method: Answer: Feasible corner points (X,Y): (0,2) (0,10) (4,8) (10,2) Maximum profit is 52 at (4,8). Diff: 3 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 74 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 80) Billy Penny is trying to determine how many units of two types of lawn mowers to produce each day. One of these is the Standard model, while the other is the Deluxe model. The profit per unit on the Standard model is $60, while the profit per unit on the Deluxe model is $40. The Standard model requires 20 minutes of assembly time, while the Deluxe model requires 35 minutes of assembly time. The Standard model requires 10 minutes of inspection time, while the Deluxe model requires 15 minutes of inspection time. The company must fill an order for 6 Deluxe models. There are 450 minutes of assembly time and 180 minutes of inspection time available each day. How many units of each product should be manufactured to maximize profits? Answer: Maximum profit is $780 by producing 9 Standard and 6 Deluxe models. Diff: 3 Topic: FORMULATING LP PROBLEMS and GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 81) Two advertising media are being considered for promotion of a product. Radio ads cost $400 each, while newspaper ads cost $600 each. The total budget is $7,200 per week. The total number of ads should be at least 15, with at least 2 of each type. Each newspaper ad reaches 6,000 people, while each radio ad reaches 2,000 people. The company wishes to reach as many people as possible while meeting all the constraints stated. How many ads of each type should be placed? Answer: Feasible corner points (R,N): (9,6) (13,2) (15,2) Maximum exposure 54,000 with 9 radio and 6 newspaper ads. Diff: 3 Topic: FORMULATING LP PROBLEMS and GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 75 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 82) Suppose a linear programming (minimization) problem has been solved and the optimal value of the objective function is $300. Suppose an additional constraint is added to this problem. Explain how this might affect each of the following: (a) the feasible region, (b) the optimal value of the objective function. Answer: (a) Adding a new constraint will reduce the size of the feasible region unless it is a redundant constraint. It can never make the feasible region any larger. However, it could make the problem infeasible. (b) A new constraint can only reduce the size of the feasible region; therefore, the value of the objective function will either increase or remain the same. If the original solution is still feasible, it will remain the optimal solution. Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM and FOUR SPECIAL CASES IN LP AACSB: Analytic Skills 83) Upon retirement, Mr. Klaws started to make two types of children's wooden toys in his shop Wuns and Toos. Wuns yield a variable profit of $9 each and Toos have a contribution margin of $8 each. Even though his electric saw overheats, he can make 7 Wuns or 14 Toos each day. Since he doesn't have equipment for drying the lacquer finish he puts on the toys, the drying operation limits him to 16 Wuns or 8 Toos per day. (a) Solve this problem using the corner point method. (b) For what profit ratios would the optimum solution remain the optimum solution? Answer: Corner points (0,0), (7,0), (0,8), (4,6) Optimum profit $84 at (4,6). Diff: 3 Topic: FORMULATING LP PROBLEMS and GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 76 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 84) Susanna Nanna is the production manager for a furniture manufacturing company. The company produces tables (X) and chairs (Y). Each table generates a profit of $80 and requires 3 hours of assembly time and 4 hours of finishing time. Each chair generates $50 of profit and requires 3 hours of assembly time and 2 hours of finishing time. There are 360 hours of assembly time and 240 hours of finishing time available each month. The following linear programming problem represents this situation. Maximize Subject to: 80X + 50Y 3X + 3Y ≤ 360 4X + 2Y ≤ 240 X, Y ≥ 0 The optimal solution is X = 0, and Y = 120. (a) What would the maximum possible profit be? (b) How many hours of assembly time would be used to maximize profit? (c) If a new constraint, 2X + 2Y ≤ 400, were added, what would happen to the maximum possible profit? Answer: (a) 6000, (b) 360, (c) It would not change. Diff: 3 Topic: FORMULATING LP PROBLEMS and GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 85) As a supervisor of a production department, you must decide the daily production totals of a certain product that has two models, the Deluxe and the Special. The profit on the Deluxe model is $12 per unit, and the Special's profit is $10. Each model goes through two phases in the production process, and there are only 100 hours available daily at the construction stage and only 80 hours available at the finishing and inspection stage. Each Deluxe model requires 20 minutes of construction time and 10 minutes of finishing and inspection time. Each Special model requires 15 minutes of construction time and 15 minutes of finishing and inspection time. The company has also decided that the Special model must comprise at most 60 percent of the production total. Formulate this as a linear programming problem. Answer: Diff: 2 Topic: FORMULATING LP PROBLEMS AACSB: Analytic Skills 77 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 86) Determine where the following two constraints intersect. 5X + 23Y ≤ 1000 10X + 26Y ≤ 1600 Answer: (108, 20) Diff: 1 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 87) Determine where the following two constraints intersect. 2X - 4Y = 800 −X + 6Y ≥ -200 Answer: (500, 50) Diff: 1 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 88) Two advertising media are being considered for promotion of a product. Radio ads cost $400 each, while newspaper ads cost $600 each. The total budget is $7,200 per week. The total number of ads should be at least 15, with at least 2 of each type, and there should be no more than 19 ads in total. The company does not want the number of newspaper ads to exceed the number of radio ads by more than 25 percent. Each newspaper ad reaches 6,000 people, 50 percent of whom will respond; while each radio ad reaches 2,000 people, 20 percent of whom will respond. The company wishes to reach as many respondents as possible while meeting all the constraints stated. Develop the appropriate LP model for determining the number of ads of each type that should be placed. Answer: Diff: 2 Topic: FORMULATING LP PROBLEMS AACSB: Analytic Skills 78 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 89) Suppose a linear programming (maximization) problem has been solved and the optimal value of the objective function is $300. Suppose a constraint is removed from this problem. Explain how this might affect each of the following: (a) the feasible region. (b) the optimal value of the objective function. Answer: (a) Removing a constraint may, if the constraint is not redundant, increase the size of the feasible region. It can never make the feasible region any smaller. If the constraint was active in the solution, removing it will also result in a new optimal solution. However, removing an essential constraint could cause the problem to become unbounded. (b) Removal of a constraint can only increase or leave the same the size of the feasible region; therefore, the value of the objective function will either increase or remain the same, assuming the problem has not become unbounded. Diff: 2 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM and FOUR SPECIAL CASES IN LP AACSB: Analytic Skills 90) Consider the following constraints from a two-variable linear program. (1) X ≥ 0 (2) Y ≥ 0 (3) X + Y ≤ 50 If the optimal corner point lies at the intersection of constraints (2) and (3), what is the optimal solution (X, Y)? Answer: Y = 0, so X + 0 = 50, or X = 50. Thus the solution is (50, 0). Diff: 1 Topic: GRAPHICAL SOLUTION TO AN LP PROBLEM AACSB: Analytic Skills 79 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 91) Consider a product mix problem, where the decision involves determining the optimal production levels for products X and Y. A unit of X requires 4 hours of labor in department 1 and 6 hours a labor in department 2. A unit of Y requires 3 hours of labor in department 1 and 8 hours of labor in department 2. Currently, 1000 hours of labor time are available in department 1, and 1200 hours of labor time are available in department 2. Furthermore, 400 additional hours of cross-trained workers are available to assign to either department (or split between both). Each unit of X sold returns a $50 profit, while each unit of Y sold returns a $60 profit. All units produced can be sold. Formulate this problem as a linear program. (Hint: Consider introducing other decision variables in addition to the production amounts for X and Y.) Answer: Maximize: 50X + 60Y Diff: 3 Topic: FORMULATING LP PROBLEMS AACSB: Analytic Skills 92) A plastic parts supplier produces two types of plastic parts used for electronics. Type 1 requires 30 minutes of labor and 45 minutes of machine time. Type 2 requires 60 minutes of machine hours and 75 minutes of labor. There are 600 hours available per week of labor and 800 machine hours available. The demand for custom molds and plastic parts are identical. Type 1 has a profit margin of $25 a unit and Type 2 have a profit margin of $45 a unit. The plastic parts supplier must choose the quantity of Product A and Product B to produce which maximizes profit. (a) Formulate this as a linear programming problem. (b) Find the solution that gives the maximum profit using either QM for Windows or Excel. Answer: (b) X1 = 914.28, X2 = 114.28 Diff: 2 Topic: FORMULATING LP PROBLEMS and SOLVING FLAIR FURNITURE’S PROBLEM USING QM FOR WINDOWS and EXCEL 80 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytic Skills 93) A company can decide how many additional labor hours to acquire for a given week. Subcontractor workers will only work a maximum of 20 hours a week. The company must produce at least 200 units of product A, 300 units of product B, and 400 units of product C. In 1 hour of work, worker 1 can produce 15 units of product A, 10 units of product B, and 30 units of product C. Worker 2 can produce 5 units of product A, 20 units of product B, and 35 units of product C. Worker 3 can produce 20 units of product A, 15 units of product B, and 25 units of product C. Worker 1 demands a salary of $50/hr, worker 2 demands a salary of $40/hr, and worker 3 demands a salary of $45/hr. The company must choose how many hours they should contract with each worker to meet their production requirements and minimize labor cost. (a) Formulate this as a linear programming problem. (b) Find the optimal solution. Answer: (b) X1 = 0, X2 = 9.23, X3 = 7.69 Diff: 3 Topic: FORMULATING LP PROBLEMS and SOLVING FLAIR FURNITURE’S PROBLEM USING QM FOR WINDOWS and EXCEL AACSB: Analytic Skills 94) Define dual price. Answer: The dual price for a constraint is the improvement in the objective function value that results from a one-unit increase in the right-hand side of the constraint. Diff: 2 Topic: SENSITIVITY ANALYSIS 95) One basic assumption of linear programming is proportionality. Explain its need. Answer: Rates of consumption exist and are constant. For example, if the production of 1 unit requires 4 units of a resource, then if 10 units are produced, 40 units of the resource are required. A change in the variable value results in a proportional change in the objective function value. Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM 96) One basic assumption of linear programming is divisibility. Explain its need. 81 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: Solutions can have fractional values and need not be whole numbers. If fractional values would not make sense, then integer programming would be required. Diff: 2 Topic: REQUIREMENTS OF A LINEAR PROGRAMMING PROBLEM Quantitative Analysis for Management, 11e (Render) Chapter 9 Transportation and Assignment Models 1) Transportation and assignment problems are really linear programming techniques called network flow problems. Answer: TRUE Diff: 2 Topic: INTRODUCTION 2) Transportation models may be used when a firm is trying to decide where to locate a new facility. Answer: TRUE Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 3) A typical transportation problem may ask the question, "How many of X should be shipped to point E from source A?" Answer: TRUE Diff: 1 Topic: THE TRANSPORTATION ALGORITHM 4) The objective of a transportation problem solution is to schedule shipments from sources to destinations while minimizing total transportation and production costs. Answer: TRUE Diff: 1 Topic: THE TRANSPORTATION ALGORITHM 5) In a transportation problem, each destination must be supplied by one and only one source. Answer: FALSE Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 6) In a transportation problem, a single source may supply something to all destinations. Answer: TRUE Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 7) In finding the maximum quantity that can be shipped on the least costly route using the stepping-stone method, one examines the closed path of plus and minus signs drawn and selects the smallest number found in those squares containing minus signs. Answer: TRUE 82 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 8) In using the stepping-stone method, the path can turn at any box or cell that is unoccupied. Answer: FALSE Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 9) Using the stepping-stone method to solve a maximization problem, we would choose the route with the largest positive improvement index. Answer: TRUE Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 10) One of the advantages of the stepping-stone method is that if, at a particular iteration, we accidentally choose a route that is not the best, the only penalty is to perform additional iterations. Answer: TRUE Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 11) A "balanced problem" exists in a transportation model when the optimal solution has the same amount being shipped over all paths that have any positive shipment. Answer: FALSE Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 12) It is possible to find an optimal solution to a transportation problem that is degenerate. Answer: TRUE Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM 13) A solution to the transportation problem can become degenerate at any iteration. Answer: TRUE Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM 14) The transportation algorithm can be used to solve both minimization problems and maximization problems. Answer: TRUE Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 15) Assignment problems involve determining the most efficient assignment of people to projects, salesmen to territories, contracts to bidders, and so on. Answer: TRUE Diff: 1 83 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: THE ASSIGNMENT ALGORITHM 16) The objective of an assignment problem solution most often is to minimize the total costs or time of performing the assigned tasks. Answer: TRUE Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 17) In the assignment problem, the costs for a dummy row will be equal to the lowest cost of the column for each respective cell in that row. Answer: FALSE Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 18) The Hungarian method is designed to solve transportation problems efficiently. Answer: FALSE Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 19) Maximization assignment problems can easily be converted to minimization problems by subtracting each rating from the largest rating in the table. Answer: TRUE Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 20) In a transportation problem, a dummy source is given a zero cost, while in an assignment problem, a dummy source is given a very high cost. Answer: FALSE Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM Table 9-1 21) What is the total cost represented by the solution shown in Table 9-1? A) 60 B) 2500 84 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall C) 2600 D) 500 E) None of the above Answer: D Diff: 2 Topic: THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 22) What is the value of the improvement index for cell B1 shown in Table 9-1? A) -50 B) +3 C) +2 D) +1 E) None of the above Answer: C Diff: 2 Topic: THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills Table 9-2 23) In Table 9-2, cell A3 should be selected to be filled in the next solution. If this was selected as the cell to be filled, and the next solution was found using the appropriate stepping-stone path, how many units would be assigned to this cell? A) 10 B) 15 C) 20 D) 30 E) None of the above Answer: B Diff: 2 Topic: THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 85 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 9-3 The following improvements are proved for Table 9-3: Cell A1 A3 B2 B-Dummy C1 C2 Improvement Index +2 +6 +1 +2 +2 +1 24) The cell improvement indices for Table 9-3 suggest that the optimal solution has been found. Based on this solution, how many units would actually be sent from source C? A) 10 B) 170 C) 180 D) 250 E) None of the above Answer: B Diff: 2 Topic: THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 25) In Table 9-3, suppose shipping cost from source C to point 2 was 8, which below would be true? A) There would be multiple optimal solutions. B) The minimum possible total cost would decrease. C) The minimum possible total cost would increase. D) Another dummy column would be needed. E) None of the above Answer: A Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM 86 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytic Skills 87 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 26) Both transportation and assignment problems are members of a category of LP techniques called ________. A) transshipment problems B) Hungarian problems C) source-destination problems D) supply and demand problems E) network flow problems Answer: E Diff: 2 Topic: INTRODUCTION 27) Transportation models can be used for which of the following decisions? A) facility location B) production mix C) media selection D) portfolio selection E) employee shift scheduling Answer: A Diff: 1 Topic: THE TRANSPORTATION ALGORITHM 28) When using a general LP model for transportation problems, if there are 4 sources and 3 destinations, which of the following statements is true? A) There are typically 4 decision variables and 3 constraints. B) There are typically 12 decision variables and 7 constraints. C) There are typically 7 decision variables and 7 constraints. D) There are typically 12 decision variables and 12 constraints. E) There are typically 12 decision variables and 3 constraints. Answer: B Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 29) The two most common objectives for the assignment problem are the minimization of ________. A) uncertainty or inexperience B) total costs or inexperience C) total costs or total time D) total time or inexperience E) total costs or uncertainty Answer: C Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 88 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 30) Assuming that Table 9-4 represents the results of an iteration of a transportation model, Table 9-4 The next tableau will be: A) B) 89 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall C) D) E) None of the above Answer: B Diff: 3 Topic: THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 90 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 9-5 31) Table 9-5 represents a solution that is A) clearly optimal for a minimization objective. B) degenerate. C) infeasible. D) All of the above E) None of the above Answer: B Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills Table 9-6 32) In Table 9-6, if cell A3 is filled on the next iteration, what is the improvement in the objective function? A) 60 B) 30 C) 530 D) 590 E) None of the above Answer: B Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 91 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 92 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 33) A transportation problem A) is a special case of the linear programming problem. B) can be solved by linear programming, but is solved more efficiently by a special-purpose algorithm. C) may give an initial feasible solution rather than the optimal solution. D) requires the same assumptions that are required for linear programming problems. E) All of the above Answer: E Diff: 2 Topic: VARIOUS Table 9-7 34) Table 9-7 illustrates a(n) A) optimal solution. B) degenerate solution. C) unbounded solution. D) infeasible solution. E) None of the above Answer: D Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 35) The only restriction we place on the initial solution of a transportation problem is that A) we must have nonzero quantities in a majority of the boxes. B) all constraints must be satisfied. C) demand must be less than supply. D) we must have a number (equal to the number of rows plus the number of columns minus one) of boxes that contain nonzero quantities. E) None of the above Answer: B Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 93 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 36) Which of the following is used to summarize conveniently and concisely all relevant data and to keep track of algorithm computations? A) source-destination matrix B) Hungarian table C) stepping-stone grid D) transportation table E) tabulation report Answer: D Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 37) In Table 9-8, which cell should be filled on the next iteration? Table 9-8 A) A1 B) ADummy C) B2 D) C1 E) C2 Answer: B Diff: 3 Topic: THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 94 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 9-9 38) The solution presented in Table 9-9 is A) infeasible. B) degenerate. C) unbounded. D) optimal. E) None of the above Answer: D Diff: 3 Topic: THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills Table 9-10 39) What is wrong with Table 9-10? A) The solution is infeasible. B) The solution is degenerate. C) The solution is unbounded. D) Nothing is wrong. E) There are too many filled cells. 95 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: E Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 40) Which of the following statements concerning the transshipment problem are false? A) The number of units shipped into a transshipment point should be equal to the number of units shipped out. B) There can be constraints on the number of units shipped out of an origin point. C) There can be constraints on the number of units shipped into a destination point. D) The transshipment problem can be solved with linear programming. E) Any units shipped from one origin point must all go to the same destination point. Answer: E Diff: 2 Topic: THE TRANSSHIPMENT PROBLEM 41) What is said to exist when total demand equals total supply in a transportation problem? A) an equalized problem B) an equilibrialized problem C) a harmonized problem D) a balanced problem E) This situation can never occur. Answer: D Diff: 1 Topic: THE TRANSPORTATION ALGORITHM Table 9-11 42) A company must assign mechanics to each of four jobs. The time involved varies according to individual abilities. Table 9-11 shows how many minutes it takes each mechanic to perform each job. If the optimal assignments are made, how many total minutes would be required for completing the jobs? A) 0 B) 4 C) 17 D) 16 E) None of the above Answer: D Diff: 3 Topic: THE ASSIGNMENT ALGORITHM AACSB: Analytic Skills 96 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 97 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 9-12 43) Given Table 9-12, the final table for an assignment problem, who should be assigned to job 2? A) worker A B) worker C C) either worker A or worker C D) neither worker A nor worker C E) worker D Answer: B Diff: 2 Topic: THE ASSIGNMENT ALGORITHM AACSB: Analytic Skills Table 9-13 44) Table 9-13 provides information about a transportation problem. This problem is A) unbounded. B) unbalanced. C) infeasible. D) All of the above E) None of the above Answer: B Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 98 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 45) Which of the following statements concerning transportation and assignment models is false? A) The transportation, transshipment, and assignment problems can all be solved using linear programming. B) A common objective is cost minimization. C) Both transportation and assignment models involve the distribution of goods from sources to destinations. D) The assignment problem can have a maximization objective. E) The transshipment problem is a special class of transportation problems. Answer: C Diff: 2 Topic: VARIOUS 46) Which of the following is not part of the transportation algorithm? A) northwest corner rule B) stepping-stone method C) balanced transportation table D) portfolio selection E) Hungarian method Answer: D Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 47) Which technique requires that we start in the upper-left-hand cell of the table and allocate units to shipping routes in a "stair step" fashion? A) upper-left rule B) stair step method C) northwest corner rule D) Vogel's approximation method E) MODI Answer: C Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 48) If items being transported must go through an intermediate point before reaching a final destination, then this situation is known as a(n) ________. A) transshipment problem B) assignment problem C) transportation problem D) intermediate point problem E) None of the above Answer: A Diff: 2 Topic: THE TRANSSHIPMENT PROBLEM 99 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 49) Which of the following accurately describes steps of the northwest corner rule, after making the initial allocation of units in the northwest cell? A) Move down first, and then move right. B) Move right first, and then move down. C) Move right or down first, depending on whether the demand requirement or the supply capacity, respectively, is exhausted first. D) Move right or down first, depending on whether the supply capacity or the demand requirement, respectively, is exhausted first. E) Move diagonally first. Answer: C Diff: 3 Topic: THE TRANSPORTATION ALGORITHM 50) When using the stepping-stone method, what is the maximum amount that can be shipped on the new route? A) the smallest number found in the squares with minus signs B) the smallest number found in the squares with plus signs C) the smallest number along the closed path D) the minimum of the demand requirement for that column and the supply capacity for that row E) the largest number found on the squares with minus signs Answer: A Diff: 2 Topic: THE TRANSPORTATION ALGORITHM Table 9-14 51) The solution presented in Table 9-14 is A) infeasible. B) degenerate. C) unbounded. D) optimal. E) Both B and D Answer: E Diff: 3 100 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: VARIOUS AACSB: Analytic Skills 101 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 9-15 52) The solution shown in Table 9-15 is A) infeasible. B) degenerate. C) unbounded. D) optimal. E) None of the above Answer: E Diff: 3 Topic: VARIOUS AACSB: Analytic Skills 53) In a transshipment problem involving 3 origins, 2 intermediate points, and 4 final destinations, what is the maximum number of decision variables? A) 24 B) 9 C) 14 D) 7 E) 20 Answer: A Diff: 2 Topic: THE TRANSSHIPMENT PROBLEM 102 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 9-16 54) The solution shown in Table 9-16 is A) infeasible. B) one of a number of alternate solutions. C) unbounded. D) optimal. E) None of the above Answer: D Diff: 3 Topic: THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 55) A certain firm has four different operations that must be assigned to four locations. The profit (in thousands of dollars) associated with each operation at each location is presented below. The firm's vice president would like to assign the various operations so that the total profit is maximized. Find the appropriate assignments. Answer: Assign W to 2, X to 4, Y to 3, and Z to 1. Total profit = $48 (thousand) Diff: 3 Topic: THE ASSIGNMENT ALGORITHM AACSB: Analytic Skills 103 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 56) What is the overall objective in applying the transportation method to the facility location problem? A) minimize the distance traveled B) minimize the number of items shipped C) maximize the value of items shipped D) minimize the cost of the distribution system E) None of the above Answer: D Diff: 2 Topic: FACILITY LOCATION ANALYSIS 57) An artificial source added to a transportation table when total demand is greater than total supply is called ________. A) excess source B) filler source C) dummy source D) demand source E) supply source Answer: C Diff: 1 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM 58) Which of the following techniques can be used for moving from an initial feasible solution to an optimal solution in a transportation problem? A) Hungarian method B) stepping-stone method C) northwest corner rule D) Vogel's approximation method E) All of the above Answer: B Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 59) Which of the following is an applicable characteristic in using the stepping-stone method? A) Only an unoccupied square may be used as a "stepping-stone." B) Only an occupied square may be used as a "stepping-stone." C) Only the column and row with the highest factory capacity may be used as a "stepping-stone." D) All of the above E) None of the above Answer: B Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 104 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 60) After testing each unused cell by the stepping-stone method in the transportation problem and finding only one cell with a negative improvement index, A) once you make that improvement, you would definitely have an optimal solution. B) you would make that improvement and then check all unused cells again. C) you could stop because you already had the optimal solution. D) you should check to be sure that you don't have to add a dummy source or dummy destination. E) None of the above Answer: B Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 61) In the transportation problem, using the stepping-stone method, A) you may not skip over an empty cell. B) you may not skip over a used cell. C) your path may not cross over itself. D) if you have an optimal solution and get an improvement index of zero, there is another optimal solution. E) None of the above Answer: D Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM 62) If we want to quickly arrive at a "feasible," but not necessarily "optimal" solution to the transportation problem, we will use the A) stepping-stone method. B) northwest corner rule. C) Vogel's approximation method. D) MODI method. E) Any of the above Answer: B Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 63) If the total supply from the sources does not equal the total demand from the destinations in the transportation problem, A) and if supply is greater than demand, add a dummy source or factory. B) the amount put in a dummy source or destination should make supply and demand equal. C) and if demand is greater than supply, add a dummy destination or warehouse. D) All of the above E) None of the above Answer: B Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM 105 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 64) In a transportation problem, degeneracy occurs when A) the number of used (or full) cells does not equal the number of rows plus columns minus one. B) in an initial solution, both a row total and a column total are satisfied simultaneously. C) during an improvement, two negative cells contain the same smallest amount. D) All of the above E) None of the above Answer: D Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM 65) Practically speaking, multiple optimal solutions ________. A) are infeasible B) are unbounded C) are degenerate D) are unbalanced E) provide management with greater flexibility in selecting and using resources Answer: E Diff: 1 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM 66) Which of the following is not considered a special situation with the transportation algorithm? A) unbalanced transportation problems B) degeneracy C) unconstrained transportation problems D) more than one optimal solution E) maximization transportation problems Answer: C Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM 67) Which of the following is not a step in the Hungarian method of assignment? A) find the opportunity-cost table B) test for an optimal assignment C) enumerate all possible solutions D) revise the opportunity-cost table E) None of the above Answer: C Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 68) Why don't we want to use the transportation algorithm to solve the assignment problem? A) It would likely lead to an unbounded solution. B) It would likely lead to a degenerate solution. C) It would likely lead to an infeasible solution. D) It would likely lead to multiple optima. 106 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall E) It would likely lead to an unbalanced solution. Answer: B Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 69) In an assignment problem A) the number of rows and columns must be equal. B) the number of rows must exceed the number of columns. C) the number of rows must equal or exceed the number of columns. D) the number of columns must equal or exceed the number of rows. E) None of the above Answer: A Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 70) In revising the opportunity cost table of the assignment problem, after drawing lines through all of the zeros, A) the smallest uncovered number is added to all zeros. B) the smallest uncovered number is added to all uncovered numbers. C) the largest uncovered number is added to all uncovered numbers. D) the smallest uncovered number is added to all numbers at the intersection of lines. E) the largest uncovered number is added to all numbers at the intersection of lines. Answer: D Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 71) Which of the following methods is used only with the assignment problem? A) the Hungarian method B) stepping-stone method C) MODI method D) Vogel's approximation method E) the simplex method Answer: A Diff: 1 Topic: THE ASSIGNMENT ALGORITHM 72) Objectives of the assignment problem can include A) minimize total costs. B) minimize total time to perform the tasks at hand. C) minimize opportunity costs. D) maximize profit. E) All of the above Answer: E Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 107 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 73) In solving maximization assignment problems, A) just reverse all the decision rules used in the minimizing algorithm (if it says subtract, now add, and so on). B) convert the problem to an equivalent minimization problem. C) use the Australian transformation process and convert the data. D) All of the above E) None of the above Answer: B Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 74) Which tableau is the solution to the transportation problem depicted below? Table 9-17 A) B) 108 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 109 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall C) D) E) None of the above Answer: A Diff: 3 Topic: VARIOUS AACSB: Analytic Skills 110 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 75) Which tableau is the solution to the following transportation table? Table 9-18 A) B) 111 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall C) D) E) None of the above Answer: E Diff: 3 Topic: VARIOUS AACSB: Analytic Skills 112 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 76) Table 9-19 describes a transportation problem: Table 9-19 (a) Use the northwest corner method to get an initial solution. (b) What is the cost of the initial solution? (c) Use the stepping-stone method to find the optimal solution. (d) What is the cost of the optimal solution? (e) Is there an alternate optimal solution? Answer: (a) (b) Cost = 280 (c) Optimal solution: (d) (e) Cost = 210 no Diff: 3 113 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: VARIOUS AACSB: Analytic Skills 114 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 77) Four projects must be completed, and each of four employees will be assigned to work on exactly one of the four projects. The table below presents an estimate of the cost that each employee would incur if working on the respective projects. What is the minimum-cost assignment of workers to projects? Answer: MaryProject 2, ElizabethProject 4, StevenProject 1, JoshuaProject 3 Diff: 2 Topic: THE ASSIGNMENT ALGORITHM AACSB: Analytic Skills 78) SE Appliances manufacturers refrigerators in Richmond, Charlotte, and Atlanta. Refrigerators then must be shipped to meet demand in Washington, New York, and Miami. The table below lists the shipping costs, supply, and demand information. How many units should be shipped from each plant to each retail store in order to minimize shipping costs? Answer: Ship 1000 units from Richmond to New York, 1000 units from Charlotte to Washington, 800 units from Atlanta to New York, and 1200 units from Atlanta to Miami, with the 500 from Charlotte to the Dummy unshipped. Diff: 2 Topic: THE TRANSPORTATION ALGORITHM AACSB: Analytic Skills 115 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 79) Neki Sports Company manufacturers treadmills in factories located in Pittsburgh and Kansas City. These are shipped to regional distribution centers in Chicago, Phoenix, and Philadelphia. Ultimately they are delivered to supply houses in New York and Los Angeles. The available supplies at the factories, demands at the final destinations, and shipping costs are illustrated in the table below. Formulate this problem as a linear program. Answer: Let (1) = Pittsburgh, (2) = Kansas City, (3) = Chicago, (4) = Phoenix, (5) = Philadelphia, (6) = New York, and (7) = Los Angeles Let xij = the number of units shipped from location i to location j. The LP is as follows: Minimize total cost = 4x13 + 3x23 + 8x14+ 6x24 + 2x15+ 5x25 + 5x36 + 8x46 + 2x56 + 7x37 + 3x47 + 9x57 Subject to: x13 + x14 + x15 ≤ 1500 x23 + x24 + x25 ≤ 1000 x13 + x23 = x36 + x37 x14 + x24 = x46 + x47 x15 + x25 = x56 + x57 x36 + x46 + x56 = 1200 x37 + x47 + x57 = 800 All xij ≥ 0 Diff: 2 Topic: THE TRANSSHIPMENT PROBLEM AACSB: Analytic Skills 116 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 80) Neki Sports Company manufacturers treadmills in factories located in Pittsburgh and Kansas City. These are shipped to regional distribution centers in Chicago, Phoenix, and Philadelphia. Ultimately they are delivered to supply houses in New York and Los Angeles. The available supplies at the factories, demands at the final destinations, and shipping costs are illustrated in the table below. Determine how many units should be shipped for all possible origin and destination points (final or intermediate) in the distribution network in order to minimize shipping costs. Answer: The best solution is to ship 1200 units from Pittsburgh to Philadelphia, ship 800 units from Kansas City to Phoenix, then 1200 units from Philadelphia to New York, and 800 units from Phoenix to Los Angeles. Diff: 2 Topic: THE TRANSSHIPMENT PROBLEM AACSB: Analytic Skills 81) Describe a general transportation problem. Answer: a specific case of linear programming concerned with scheduling shipments from sources to destinations while minimizing transportation costs Diff: 2 Topic: INTRODUCTION 82) What is meant by a balanced transportation problem? Answer: a situation in which total demand equals total supply exactly Diff: 2 Topic: THE TRANSPORTATION ALGORITHM 83) The assignment problem is a special case of the transportation problem. So, then, why is it not recommended to use the transportation algorithm to solve the assignment problem? Answer: It would result in a severe degeneracy problem. Diff: 2 Topic: THE ASSIGNMENT ALGORITHM 84) When is a dummy destination added to a transportation problem? Answer: when total supply exceeds total demand Diff: 2 Topic: SPECIAL SITUATIONS WITH THE TRANSPORTATION ALGORITHM 117 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Quantitative Analysis for Management, 11e (Render) Chapter 11 Network Models 1) The minimal-spanning tree technique finds the shortest route to a series of destinations. Answer: FALSE Diff: 2 Topic: INTRODUCTION 2) In the minimal-spanning tree technique, it is necessary to start at the last node in the network. Answer: FALSE Diff: 2 Topic: MINIMAL-SPANNING TREE PROBLEM 3) The maximal-flow technique would be helpful to city planners in determining how freeways should be expanded. Answer: TRUE Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 4) The minimal-spanning tree technique determines the path through the network that connects all the points while minimizing total distance. Answer: TRUE Diff: 2 Topic: INTRODUCTION 5) The shortest-route technique is the same as the minimal-spanning tree technique. Answer: FALSE Diff: 1 Topic: INTRODUCTION 6) Busy highways are often analyzed with the maximal-flow technique. Answer: TRUE Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 7) Transportation companies would definitely be interested in the shortest-route technique to optimize travel. Answer: TRUE Diff: 2 Topic: SHORTEST-ROUTE PROBLEM 8) Cable television companies would employ the shortest-route technique to lay out the cables connecting individual houses. 118 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: FALSE Diff: 2 Topic: MINIMAL-SPANNING TREE PROBLEM 119 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 9) We may begin the maximal-flow technique by picking an arbitrary path through the network. Answer: TRUE Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 10) The maximal-flow technique finds the maximum flow of any quantity or substance through a network. Answer: TRUE Diff: 1 Topic: INTRODUCTION 11) The maximal-flow technique might be used by the U.S. Army Corps of Engineers to study water run-off in an attempt to minimize the danger from floods. Answer: TRUE Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 12) The shortest-route technique might be used by someone planning a vacation in order to minimize the required amount of driving. Answer: TRUE Diff: 2 Topic: SHORTEST-ROUTE PROBLEM 13) The points on the network are referred to as nodes. Answer: TRUE Diff: 2 Topic: INTRODUCTION 14) Lines connecting nodes on a network are called links. Answer: FALSE Diff: 2 Topic: INTRODUCTION 15) A traveling salesperson might use the shortest route technique to minimize the distance traveled to reach one of his/her customers. Answer: TRUE Diff: 2 Topic: SHORTEST-ROUTE PROBLEM 16) In the minimal-spanning tree technique, if there is a tie for the nearest node, that suggests that there may be more than one optimal solution. Answer: TRUE Diff: 2 Topic: MINIMAL-SPANNING TREE PROBLEM 17) The maximal-flow model might be of use to an engineer looking for spare capacity in an oil pipeline system. 120 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: TRUE Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 121 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 18) The shortest-route model assumes that one is trying to connect two end points in the shortest manner possible, rather than attempting to connect all the nodes in the model. Answer: TRUE Diff: 2 Topic: SHORTEST-ROUTE PROBLEM 19) In the maximal-flow technique, a zero (0) means no flow or a one-way arc. Answer: TRUE Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 20) The maximal-flow model assumes that there is a net flow from "source" to "sink." Answer: TRUE Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 21) If your goal was to construct a network in which all points were connected and the distance between them was as short as possible, the technique that you would use is A) shortest-route. B) maximal-flow. C) shortest-spanning tree. D) minimal-flow. E) minimal-spanning tree. Answer: E Diff: 2 Topic: INTRODUCTION 22) The minimal-spanning technique would best be used A) to assign workers to jobs in the cheapest manner. B) to determine LAN network wiring within a building. C) to minimize traffic flow on a busy highway. D) by a trucking company making frequent but repeatable drops. E) to determine the number of units to ship from each source to each destination. Answer: B Diff: 2 Topic: MINIMAL-SPANNING TREE PROBLEM 23) The maximal-flow technique would best be used A) to assign workers to jobs in the cheapest manner. B) to determine the number of units to ship from each source to each destination. C) to determine LAN network wiring within a building. D) to maximize traffic flow on a busy highway. E) by a trucking company making frequent but repeatable drops. Answer: D Diff: 2 122 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: MAXIMAL-FLOW PROBLEM 123 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 24) A line in a network that may represent a path or a route is called a(n) ________. A) arc B) branch C) line D) fork E) sink Answer: A Diff: 1 Topic: INTRODUCTION 25) A point in the network, that is at the beginning or end of a route is called a(n) ________. A) arc B) branch C) line D) node E) source Answer: D Diff: 1 Topic: INTRODUCTION 26) The final node or destination in a network is called a(n) ________. A) arc B) branch C) source D) mouth E) sink Answer: E Diff: 1 Topic: MAXIMAL-FLOW PROBLEM 27) The origin or beginning node in a network is called ________. A) home B) delta C) source D) mouth E) sink Answer: C Diff: 1 Topic: MAXIMAL-FLOW PROBLEM 28) A technique that allows a researcher to determine the greatest amount of material that can move through a network is called A) maximal-flow. B) maximal-spanning. C) shortest-route. 124 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall D) maximal-tree. Answer: B Diff: 2 Topic: INTRODUCTION 29) The first step in the maximal-flow technique is to A) pick the node with the maximum flow. B) pick any path with some flow. C) eliminate any node that has a zero flow. D) add a dummy flow from the start to the finish. E) None of the above Answer: B Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 30) The shortest-route technique would best be used to ________ A) assign workers to jobs in the cheapest manner. B) determine the number of units to ship from each source to each destination. C) determine the amount of LAN network wiring within a building. D) minimize the amount of traffic flow on a busy highway. E) determine the path for a truck making frequent but repeatable drops. Answer: E Diff: 2 Topic: SHORTEST-ROUTE PROBLEM 31) When using the shortest-route technique, the first step is to A) connect the nearest node that minimizes the total distance to the origin. B) trace the path from the warehouse to the plant. C) determine the average distance traveled from source to end. D) find the nearest node to the origin and put a distance box by the node. E) None of the above Answer: D Diff: 2 Topic: SHORTEST-ROUTE PROBLEM 32) The shortest-route technique might be logically used for A) finding the longest time to travel between two points. B) finding the shortest travel distance between two points. C) finding the most scenic route to allow travel to several places during a trip on spring break. D) connecting all the points of a network together while minimizing the distance between them. E) None of the above Answer: B Diff: 2 Topic: INTRODUCTION 125 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 33) All the nodes must be connected in which of the following techniques? A) minimal-flow B) maximal-spanning tree C) shortest-route D) maximal-flow E) minimal-spanning tree Answer: E Diff: 1 Topic: MINIMAL-SPANNING TREE PROBLEM 34) The minimal-spanning tree technique would best be used A) by a forest ranger seeking to minimize the risk of forest fires. B) by a telephone company attempting to lay out wires in a new housing development. C) by an airline laying out flight routes. D) None of the above E) All of the above Answer: B Diff: 2 Topic: MINIMAL-SPANNING TREE PROBLEM 35) Which of the following techniques is not discussed in Chapter 11? A) shortest-route B) maximal-flow C) linear programming D) minimal-flow E) minimal-spanning tree Answer: D Diff: 1 Topic: VARIOUS 36) The maximal-flow technique might be used A) to help design the moving sidewalks transporting passengers from one terminal to another in a busy airport. B) by someone designing the traffic approaches to an airport. C) by someone attempting to design roads that would limit the flow of traffic through an area. D) All of the above E) None of the above Answer: D Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 37) Which of the following problems can be solved using linear programming? A) maximal-flow problem B) shortest-route problem C) minimal-spanning tree problem D) A and B 126 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall E) A, B, and C Answer: D Diff: 2 Topic: VARIOUS 38) Which of the following problems can be solved as a linear program using binary decision variables? A) maximal-flow problem B) shortest-route problem C) minimal-spanning tree problem D) A and B E) A, B, and C Answer: B Diff: 2 Topic: SHORTEST-ROUTE PROBLEM 39) Which of the following problems can be solved as a linear program using integer decision variables? A) maximal-flow problem B) shortest-route problem C) minimal-spanning tree problem D) A and B E) A, B, and C Answer: A Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 40) The second step in the maximal-flow technique is to A) pick the node with the maximum flow. B) pick any path with some flow. C) decrease the flow as much as possible. D) add capacity to the path with minimum flow. E) find the arc on the previously chosen path with the smallest flow capacity available. Answer: E Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 41) The shortest-route technique would best be used to A) plan the routes for a vacation driving tour. B) plan the route for a school bus. C) determine the path for a truck making frequent runs from a factory to a warehouse. D) All of the above E) None of the above Answer: D Diff: 2 Topic: SHORTEST-ROUTE PROBLEM 127 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 42) When using the shortest-route technique, the second step is to A) find the next-nearest node to the origin and put the distance in a box by the node. B) trace the path from the warehouse to the plant. C) determine the average distance traveled from source to end. D) find the nearest node to the origin and put a distance box by the node. E) None of the above Answer: A Diff: 2 Topic: SHORTEST-ROUTE PROBLEM 43) In network models, the lines connecting the nodes are called ________. A) bridges B) arrows C) spans D) arcs E) links Answer: D Diff: 2 Topic: INTRODUCTION 44) Given the following distances between destination nodes, what is the minimum distance that connects all the nodes? From 1 2 1 To 2 3 3 Distance 300 150 200 A) 450 B) 150 C) 350 D) 650 E) None of the above Answer: C Diff: 2 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 45) Given the following distances between destination nodes, what is the minimum distance that connects all the nodes? From 1 1 2 To 2 3 3 Distance 200 300 350 128 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 2 3 4 4 350 250 A) 100 B) 750 C) 850 D) 900 E) None of the above Answer: B Diff: 2 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 129 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 46) Given the following distances between destination nodes, what is the minimum distance that connects all the nodes? From 1 2 1 2 3 4 3 To 2 4 3 3 4 5 5 Distance 100 150 200 50 175 250 300 A) 100 B) 150 C) 550 D) 1225 E) None of the above Answer: C Diff: 2 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 47) Given the following distances between destination nodes, what is the minimum distance that connects all the nodes? From 1 1 2 2 1 3 3 4 To 2 3 3 5 4 4 5 5 Distance 100 50 200 325 50 350 400 450 A) 300 B) 525 C) 675 D) 1925 E) None of the above Answer: B Diff: 2 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 130 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 48) Pipeline fluid flows are indicated below. Determine the maximum flow from Node 1 to Node 3. From Node 1 3 1 2 2 3 To Node 3 1 2 1 3 2 Fluid Flow 400 100 300 0 100 100 A) 100 B) 400 C) 500 D) 700 E) None of the above Answer: C Diff: 2 Topic: MAXIMAL-FLOW PROBLEM AACSB: Analytic Skills 49) Pipeline fluid flows are indicated below. Determine the maximum flow from Node 1 to Node 4. From Node 1 2 1 4 1 3 2 4 3 4 To Node 2 1 4 1 3 1 4 2 4 3 Fluid Flow 400 0 200 200 200 0 200 200 300 300 A) 200 B) 300 C) 600 D) 700 E) None of the above Answer: C Diff: 2 Topic: MAXIMAL-FLOW PROBLEM 131 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytic Skills 132 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 50) Find the shortest route from Node 1 to Node 4 using the shortest-route technique. From Node 1 1 2 2 3 To Node 2 3 3 4 4 Distance 300 200 50 250 450 A) 650 B) 450 C) 550 D) 500 E) 800 Answer: D Diff: 2 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 51) Find the shortest route from Node 1 to Node 4. From Node 1 1 1 2 2 3 To Node 2 3 4 3 4 4 Distance 250 400 600 50 300 200 A) 750 B) 500 C) 550 D) 600 E) 50 Answer: B Diff: 2 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 133 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 52) Find the shortest route from Node 1 to Node 6. From Node 1 1 2 2 4 3 3 5 To Node 2 3 4 3 6 4 5 6 Distance 150 200 200 50 100 300 350 100 A) 300 B) 450 C) 550 D) 650 E) None of the above Answer: B Diff: 2 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 53) Given the following distances between destination nodes, what is the minimum distance that connects all the nodes? From 1 2 1 2 3 4 To 2 3 3 4 5 5 Distance 120 100 200 150 90 170 A) 290 B) 310 C) 620 D) 460 E) None of the above Answer: D Diff: 2 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 134 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 54) Given the following distances between destination nodes, what is the minimum distance that connects all the nodes? From 1 1 1 2 2 3 3 4 4 5 To 2 3 5 3 4 4 5 5 6 6 Distance 200 300 400 300 400 200 200 100 300 400 A) 1000 B) 800 C) 700 D) 1100 E) None of the above Answer: D Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 55) Given the following distances between destination nodes, what is the minimum distance that connects all the nodes? From 1 1 2 2 2 3 3 4 4 5 To 2 3 3 4 5 4 5 5 6 6 Distance 100 200 100 150 200 150 300 250 200 100 A) 900 B) 650 C) 400 D) 1200 135 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall E) None of the above Answer: B Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 56) Given the following distances between destination nodes, what is the minimum distance that connects all the nodes? From 1 1 2 2 1 3 3 3 4 4 5 To 2 3 3 5 4 4 5 6 5 6 6 Distance 100 50 200 300 50 350 400 400 450 350 200 A) 900 B) 1200 C) 1100 D) 700 E) None of the above Answer: D Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 57) Pipeline fluid flows are indicated below. Determine the maximum flow from Node 1 to Node 4. From Node 1 3 1 2 2 3 3 4 To Node 3 1 2 1 3 2 4 3 Fluid Flow 200 0 150 50 100 100 150 50 136 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall A) 100 B) 150 C) 200 D) 50 E) None of the above Answer: B Diff: 3 Topic: MAXIMAL-FLOW PROBLEM AACSB: Analytic Skills 58) Pipeline fluid flows are indicated below. Determine the maximum flow from Node 1 to Node 5. From Node 1 2 1 3 1 4 1 5 2 4 3 4 3 5 4 5 To Node 2 1 3 1 4 1 5 1 4 2 4 3 5 3 5 4 Fluid Flow 300 0 0 150 200 200 100 100 200 200 250 300 300 250 100 0 A) 300 B) 400 C) 600 D) 500 E) None of the above Answer: D Diff: 3 Topic: MAXIMAL-FLOW PROBLEM AACSB: Analytic Skills 137 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 59) Find the shortest route from Node 1 to Node 5 using the shortest-route technique. From Node 1 1 2 2 3 3 4 To Node 2 3 3 4 4 5 5 Distance 200 150 50 300 250 200 150 A) 350 B) 400 C) 450 D) 600 E) None of the above Answer: A Diff: 3 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 60) Find the shortest route from Node 1 to Node 5. From Node 1 1 1 2 2 3 3 2 To Node 2 3 4 3 4 4 5 5 Distance 250 150 200 50 150 150 100 150 A) 200 B) 350 C) 250 D) 450 E) None of the above Answer: C Diff: 3 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 138 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 61) Find the shortest route from Node 1 to Node 6. From Node 1 1 2 2 2 3 3 4 5 To Node 2 3 3 4 5 4 5 6 6 Distance 150 200 100 200 50 350 300 100 100 A) 300 B) 450 C) 550 D) 650 E) None of the above Answer: A Diff: 3 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 139 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 62) Given the following traffic flows, in hundreds of cars per hour, what is the maximum traffic flow from City 1 to City 7? 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 From City 1 1 1 2 2 2 3 3 3 4 4 4 5 5 5 5 5 5 6 6 6 7 7 7 To City 2 3 5 1 4 5 1 5 6 2 5 7 1 2 3 4 6 7 3 5 7 4 5 6 Flow 4 8 5 0 3 3 0 3 1 3 3 4 1 0 2 0 1 5 1 4 1 2 1 0 A) 1200 B) 1400 C) 900 D) 800 E) None of the above Answer: C Diff: 3 Topic: MAXIMAL-FLOW PROBLEM AACSB: Analytic Skills 140 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 63) Solve the minimal-spanning tree problem defined below: Branch 1 2 3 4 5 6 Start Node 1 1 2 2 3 4 End Node 3 2 4 5 4 6 Cost 5 1 3 4 6 2 A) total cost = 13 B) total cost = 15 C) total cost = 17 D) total cost = 11 E) None of the above Answer: B Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 64) Find the shortest route from Node 1 to Node 6. 1 2 3 4 5 6 7 8 9 From Node 1 1 2 2 2 3 4 4 5 To Node 2 4 3 4 5 4 5 6 6 Distance 100 215 70 200 110 320 200 200 200 A) total distance = 350 B) total distance = 410 C) total distance = 270 D) total distance = 520 E) None of the above Answer: B Diff: 3 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 141 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 65) Given the following traffic flows, in hundreds of cars per hour, what is the maximum traffic flow from Town 1 to Town 7? 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 From Town 1 1 1 2 2 2 3 3 3 4 4 4 5 5 5 5 5 5 6 6 6 7 7 7 To Town 2 3 5 1 4 5 1 5 6 2 5 7 1 2 3 4 6 7 3 5 7 4 5 6 Flow 4 7 9 0 3 5 1 3 4 3 1 0 1 0 3 0 5 1 1 6 3 5 2 0 A) max flow = 4 units B) max flow = 6 units C) max flow = 3 units D) max flow = 9 units E) None of the above Answer: A Diff: 3 Topic: MAXIMAL-FLOW PROBLEM AACSB: Analytic Skills 142 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 66) Find the shortest route from Node 6 to Node 1. Branch 1 2 3 4 5 6 7 8 9 From Node 1 1 2 2 2 3 3 4 5 To Node 2 3 3 4 5 4 5 6 6 Distance 150 200 100 200 50 350 300 100 100 A) branches 9, 7, and 2 B) branches 8, 6, and 2 C) branches 8, 6, 7, and 1 D) branches 9, 5, and 1 E) None of the above Answer: D Diff: 3 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 143 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 67) Given the pipeline fluid flows indicated below, determine the maximum flow from Node 1 to Node 5. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 From Node 1 2 1 3 1 4 1 5 2 4 3 4 3 5 4 5 To Node 2 1 3 1 4 1 5 1 4 2 4 3 5 3 5 4 Fluid Flow 300 0 0 150 200 200 100 100 200 200 250 300 300 250 100 0 A) 250 B) 300 C) 350 D) 450 E) None of the above Answer: E Diff: 3 Topic: MAXIMAL-FLOW PROBLEM AACSB: Analytic Skills 144 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 68) Find the least amount of cable that will allow Jack's Cable Company to connect the following nodes (houses). From Node 1 1 1 2 2 3 To Node 2 3 4 3 4 4 Distance 250 150 400 50 100 200 A) 250 B) 400 C) 350 D) 300 E) None of the above Answer: D Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 69) Given the following nodes and distances, determine the minimum length of cable necessary to connect all six nodes. 1 2 3 4 5 6 7 8 9 From Node 1 1 2 2 2 3 3 4 5 To Node 2 3 3 4 5 4 5 6 6 Distance 150 200 100 200 50 350 300 100 100 A) 200 B) 300 C) 400 D) 500 E) None of the above Answer: D Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM 145 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytic Skills 146 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 70) Given the following nodes and distances, determine the minimal length of cable necessary to connect all nodes, using Node 2 as the starting point. 1 2 3 4 5 6 7 8 9 10 From 1 1 1 2 2 3 3 4 4 5 To 2 3 5 3 4 4 5 5 6 6 Distance 200 300 400 300 400 200 200 100 300 400 A) 1200 B) 1100 C) 900 D) 700 E) None of the above Answer: B Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 147 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 71) Find the shortest route from Node 1 to each of the other nodes in the transportation network represented below. Route from Node 1 to 2 1 to 3 2 to 3 2 to 4 3 to 4 3 to 5 4 to 5 4 to 6 5 to 6 Distance 50 100 75 65 80 70 65 200 130 Answer: Node 2 3 4 5 6 Shortest Route 1-2 1-3 1-2-4 1-3-5 1-2-4-5-6 Distance 50 100 115 170 310 Diff: 3 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 148 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 72) As part of the planning for a major office development project, it is necessary to install telephone line to the buildings. Information about the project is given below. The distances are provided in hundreds of feet. Which offices should be connected so that total wiring costs (i.e., total distance) are minimized? What is the total length of this? Building 1 to 2 1 to 4 2 to 3 2 to 4 3 to 5 3 to 6 4 to 5 4 to 7 5 to 7 6 to 7 Distances (100s ft) 4 3 2 4 1 5 3 3 2 6 Answer: One solution is to connect 1-4, 2-3, 3-6, 3-5, 4-5, 5-7. Total length = 16. Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 73) A cable company must is to provide service for 7 houses in a particular neighborhood. They would like to wire the neighborhood in a way to minimize the wiring costs (or distance). How should the cable company wire the neighborhood and what would be the minimal length of the network? House 1 to 2 1 to 3 1 to 4 2 to 3 2 to 4 2 to 5 3 to 5 3 to 6 4 to 5 4 to 7 5 to 7 6 to 7 Distances (yards) 100 400 300 300 250 400 350 450 300 250 100 150 Answer: One solution is to connect 1-2, 2-3, 2-4, 4-7, 5-7, 6-7. Total length = 1150. Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 149 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 150 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 74) Given a network with the following distances: From Node 1 1 2 2 3 3 3 4 5 To Node 2 3 3 4 4 5 6 5 6 Distance 4 1 2 3 6 3 9 7 5 (a) Determine which nodes should be connected to get the minimum distance from Nodes 1 through 6. (b) Determine the minimum distance. Answer: (a) Connect 1-3-5-6. (b) Minimum distance = 9 Diff: 3 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 75) The west-to-east air traffic system passing through the United States can handle aircraft flows with capacities in hundreds of planes per hour as shown. What is the peak air traffic load (From City 1 to City 5) in aircraft per hour that this system can handle? Answer: Route 1235 can handle 200 per hour, and Route 145 can handle 300 per hour for a total of 500 aircraft per hour. Diff: 3 Topic: MAXIMAL-FLOW PROBLEM AACSB: Analytic Skills 151 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 76) Find the shortest route from Node 1 to each of the other nodes in the transportation network represented below. Route From Node 1 to 2 1 to 3 2 to 3 2 to 5 3 to 4 3 to 5 3 to 6 4 to 6 5 to 6 Distance 50 100 75 60 80 70 65 200 150 Answer: Node 2 3 4 5 6 Shortest Route 1-2 1-3 1-3-4 1-2-5 1-3-6 Distance 50 100 180 110 165 Diff: 3 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 152 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 77) A logistics company is determining the shortest route to get to a selected final destination. The information on possible paths and distances is given below: Route From Node 1 to 2 1 to 3 1 to 4 2 to 4 2 to 5 3 to 4 3 to 5 4 to 5 4 to 6 5 to 6 5 to 7 6 to 7 Distance 50 100 125 75 180 100 125 170 200 125 100 75 Answer: 1-3-5-7 = 325 Diff: 3 Topic: SHORTEST-ROUTE PROBLEM AACSB: Analytic Skills 78) As part of the planning for a major office development project, it is necessary to install telephone lines to the buildings. Information about the project is given below. The distances are provided in hundreds of feet. Which offices should be connected so that total wiring costs (i.e., total distance) are minimized? What is the total length of this? Buildings 1 to 2 1 to 3 1 to 4 2 to 4 3 to 5 3 to 6 4 to 5 4 to 7 5 to 7 6 to 7 Distances (100s ft) 4 3 2 4 1 5 3 3 2 6 Answer: Connect: 1-4, 4-5, 5-7, 3-6, 5-3, and either 4-2 or 1-2. Total length is 1700 feet. Alternate solutions exist. Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 153 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 79) Brantley College has decided to "wire" its campus. The first stage in this effort is to install the "backbone," i.e., to connect all the buildings. The table below gives the distances between the various buildings on campus in hundreds of feet. How should the buildings be connected to minimize the total length of cable? What length of cable is required? Answer: Connect: 1-2, 2-4, 4-6, 3-5, 5-6. Total length is 1600 feet. Diff: 3 Topic: MINIMAL-SPANNING TREE PROBLEM AACSB: Analytic Skills 80) Given a network with the following distances: From Node 1 1 2 2 3 3 3 4 4 5 5 6 To Node 2 4 3 4 4 5 6 5 7 6 7 7 Distance 4 1 2 3 6 4 2 7 5 5 8 4 (a) Determine which nodes should be connected to get the minimum distance flowing from Node 1 through Node 7. (b) Determine the minimum distance. Answer: (a) Connect: 1-4, 4-7. (a) Minimum distance = 6 Diff: 3 Topic: SHORTEST-ROUTE PROBLEM 154 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytic Skills 155 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 81) The east-to-west (City 5 to City 1) air traffic system passing through the U.S. can handle aircraft flows with capacities in hundreds of planes per hour as shown. What is the peak air traffic load in aircraft per hour from City 5 to City 1 that this system can handle? Answer: 500 aircraft per hour. Diff: 3 Topic: MAXIMAL-FLOW PROBLEM AACSB: Analytic Skills 82) A water company is analyzing the flow of water through pipes in an office building. The flow capacities are given in the table below. Flow is measured in 100 gallons/hour. What is the maximal flow of water from node 1 to node 5? Answer: 700 gallons per hour. Diff: 3 Topic: MAXIMAL-FLOW PROBLEM AACSB: Analytic Skills 83) Describe the steps of the shortest-route technique. Answer: (1) Find the nearest node to the origin (plant). Put the distance in a box by the node. (2) Find the nextnearest node to the origin (plant), and put the distance in a box by the node. In some cases, several paths will have to be checked to find the nearest node. (3) Repeat this process until you have gone through the entire network. The last distance at the ending node will be the distance of the shortest route. You should note that the distance placed in the box by each node is the shortest route to this node. These distances are used as intermediate results in finding the next-nearest node. Diff: 3 Topic: SHORTEST-ROUTE PROBLEM 84) Briefly describe the minimal-spanning technique. Answer: determines the path through a network that connects all the points while minimizing the total distance 156 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Diff: 2 Topic: INTRODUCTION 157 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 85) Briefly describe the maximal-flow technique. Answer: determines the maximal flow of any quantity or substance through a network Diff: 2 Topic: INTRODUCTION 86) Briefly describe the minimal shortest-route technique. Answer: determines the shortest route through a network Diff: 2 Topic: INTRODUCTION Quantitative Analysis for Management, 11e (Render) Chapter 12 Project Management 1) PERT and CPM are quantitative analysis tools designed to schedule and control large projects. Answer: TRUE Diff: 1 Topic: INTRODUCTION 2) PERT is a deterministic analysis tool allowing for precise times of activities within a project. Answer: FALSE Diff: 2 Topic: INTRODUCTION 3) PERT had its beginnings in a military department of the United States. Answer: TRUE Diff: 2 Topic: PERT/CPM 4) CPM is a probabilistic analysis of managing a project. Answer: FALSE Diff: 2 Topic: INTRODUCTION 5) The first step in planning and scheduling a project is to develop the work breakdown structure. Answer: TRUE Diff: 2 Topic: INTRODUCTION 6) A PERT/CPM network is a graphical display of a project that connects activities. Answer: TRUE Diff: 1 Topic: PERT/CPM 7) The optimistic time is the greatest amount of time that could be required to complete an activity. 158 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: FALSE Diff: 2 Topic: PERT/CPM 8) PERT is a network technique similar to CPM, but PERT allows for project crashing, whereas CPM does not. Answer: FALSE Diff: 2 Topic: PERT/CPM and PROJECT CRASHING 9) In PERT, the most likely completion time of an activity is used to represent that activity's time within a project. Answer: FALSE Diff: 2 Topic: PERT/CPM 10) The expected completion time and variance of an activity is approximated by the normal distribution in a PERT analysis. Answer: FALSE Diff: 2 Topic: PERT/CPM 11) PERT was developed for a project for which activity or task times were uncertain. Answer: TRUE Diff: 2 Topic: PERT/CPM 12) CPM was developed for use in managing projects about which we have good information about activity or task completion times. Answer: TRUE Diff: 2 Topic: PERT/CPM 13) With PERT, we are able to calculate the probability of finishing the project within a specified time. Answer: TRUE Diff: 2 Topic: PERT/CPM 14) With CPM, we are able to calculate the probability of finishing the project within a specified time. Answer: FALSE Diff: 2 Topic: PERT/CPM 15) Both PERT and CPM networks show activities and activity sequences. Answer: TRUE Diff: 2 Topic: PERT/CPM 159 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 16) The identification of the project activities and their time, cost, resource requirements, predecessors, and person(s) responsible is called PERT planning. Answer: FALSE Diff: 2 Topic: INTRODUCTION 17) Before drawing a PERT or CPM network, we must identify all activities and their predecessors. Answer: TRUE Diff: 2 Topic: PERT/CPM 18) The three time estimates employed in PERT are optimistic time, average time, and pessimistic time. Answer: FALSE Diff: 2 Topic: PERT/CPM 160 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 19) Given the variability of the activity completion times, the original critical path we identify in our PERT analysis may not always be the actual critical path as the project takes place. Answer: TRUE Diff: 2 Topic: PERT/CPM 20) In PERT, the earliest start time for an activity is equal to the latest of the earliest finish times of all of its immediate predecessors. Answer: TRUE Diff: 2 Topic: PERT/CPM 21) PERT stands for Probabilistic Evaluation and Review Technique. Answer: FALSE Diff: 3 Topic: INTRODUCTION 22) One of the most significant benefits of PERT is that it forces the project manager to sit down and plan the project in great detail—and thus come to an understanding of relationships between the activities. Answer: TRUE Diff: 2 Topic: PERT/CPM 23) Slack is the time an activity can be delayed without impacting the completion time of the project. Answer: TRUE Diff: 2 Topic: PERT/CPM 24) The variance of the project completion time is equal to the sum of the variances of all the activities. Answer: FALSE Diff: 2 Topic: PERT/CPM 25) In PERT, we assume that the project completion time can be modeled by the normal distribution. Answer: TRUE Diff: 2 Topic: PERT/CPM 26) One PERT/COST assumption is that money is spent at a constant rate over the time taken to complete an activity. Answer: TRUE Diff: 2 Topic: PERT/COST 27) CPM stands for Comprehensive Project Method. 161 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: FALSE Diff: 3 Topic: INTRODUCTION 162 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 28) The longest time path through a PERT/CPM network is called the critical path. Answer: TRUE Diff: 2 Topic: INTRODUCTION 29) In CPM, crashing an activity that is not on the critical path increases the cost of the project. Answer: TRUE Diff: 2 Topic: PROJECT CRASHING 30) Through the use of PERT/CPM, astute managers can derive flexibility by identifying noncritical activities and replanning, rescheduling, and reallocating resources such as personnel and finances. Answer: TRUE Diff: 2 Topic: INTRODUCTION 31) In PERT, the variance in completion time is equal to the variance of the most time consuming activity on the critical path. Answer: FALSE Diff: 2 Topic: PERT/CPM 32) Given the assumptions in PERT, the probability that a project will be completed in less time than required by the activities on the critical path is approximately 50%. Answer: TRUE Diff: 2 Topic: PERT/CPM 33) Gantt charts and PERT diagrams provide the same information, just in different formats. Answer: FALSE Diff: 2 Topic: PERT/CPM 34) Gantt charts contain information about the time taken by each activity, but not about the sequential dependencies of the activities. Answer: TRUE Diff: 2 Topic: PERT/CPM 35) The critical path of a network is the A) shortest time path through the network. B) path with the fewest activities. C) path with the most activities. D) longest time path through the network. E) None of the above 163 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: D Diff: 2 Topic: INTRODUCTION 164 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 36) In a PERT network, the earliest (activity) start time is the A) earliest time that an activity can be finished without delaying the entire project. B) latest time that an activity can be started without delaying the entire project. C) earliest time that an activity can start without violation of precedence requirements. D) latest time that an activity can be finished without delaying the entire project. E) None of the above Answer: C Diff: 1 Topic: PERT/CPM 37) Slack time in a network is the A) amount of time that an activity would take assuming very unfavorable conditions. B) shortest amount of time that could be required to complete the activity. C) amount of time that you would expect it would take to complete the activity. D) difference between the expected completion time of the project using pessimistic times and the expected completion time of the project using optimistic times. E) amount of time that an activity can be delayed without delaying the entire project. Answer: E Diff: 2 Topic: PERT/CPM 38) The first step in planning and scheduling a project is to develop the ________. A) employee scheduling plan B) PERT/CPM network diagram C) critical path D) work breakdown structure E) variance calculations for each activity Answer: D Diff: 2 Topic: INTRODUCTION 39) Which of the following is not a concept associated with CPM? A) normal time B) probability C) normal cost D) crash cost E) deterministic network Answer: B Diff: 2 Topic: INTRODUCTION 40) PERT A) assumes that we do not know ahead of time what activities must be completed. B) assumes that activity time estimates follow the normal probability distribution. C) is a network technique that uses three time estimates for each activity in a project. 165 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall D) is a deterministic network technique that allows for project crashing. E) None of the above Answer: C Diff: 2 Topic: PERT/CPM 41) CPM A) assumes we do not know ahead of time what activities must be completed. B) assumes that activity time estimates follow the normal probability distribution. C) is a deterministic network technique that allows for project crashing. D) is a network technique that allows three time estimates for each activity in a project. E) None of the above Answer: C Diff: 2 Topic: PERT/CPM 42) Managers use the network analysis of PERT and CPM to help them A) derive flexibility by identifying noncritical activities. B) replan, reschedule, and reallocate resources such as manpower and finances. C) plan, schedule, monitor, and control large and complex projects. D) All of the above E) None of the above Answer: D Diff: 2 Topic: INTRODUCTION 43) The expected time in PERT is A) a weighted average of the most optimistic time, most pessimistic time, and four times the most likely time. B) the modal time of a beta distribution. C) a simple average of the most optimistic, most likely, and most pessimistic times. D) the square root of the sum of the variances of the activities on the critical path. E) None of the above Answer: A Diff: 2 Topic: PERT/CPM 44) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 6, and 14 days respectively, compute the PERT expected activity time for this activity. A) 8 B) 6 C) 7 D) 9 E) None of the above Answer: C Diff: 2 166 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: PERT/CPM AACSB: Analytic Skills 167 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 45) Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 5, and 14 days respectively, compute the PERT expected activity time for this activity. A) 6 B) 7 C) 9 D) 5 E) None of the above Answer: A Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 46) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18 days respectively, compute the PERT expected activity time for this activity. A) 14 B) 12 C) 11 D) 13 E) None of the above Answer: D Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 47) Given an activity's optimistic, most likely, and pessimistic time estimates of 2, 10, and 20 days respectively, compute the PERT variance for this activity. A) 3 B) 6 C) 9 D) 18 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 48) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, compute the PERT variance for this activity. A) 2.33 B) 5.44 C) 8.00 D) 64.00 E) None of the above Answer: B Diff: 2 168 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: PERT/CPM AACSB: Analytic Skills 169 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 49) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 15 days, respectively, compute the PERT standard deviation for this activity. A) 2 B) 4 C) 5 D) 15 E) None of the above Answer: A Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 50) Given the following small project, the critical path is ________ days. Activity A B C Immediate Predecessor A, B Time (days) 10 4 6 A) 10 B) 14 C) 16 D) 20 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 51) Given the following small project, the critical path is ________ days. Activity A B C Immediate Predecessor A - Time (days) 8 4 10 A) 4 B) 10 C) 12 D) 22 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM 170 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytic Skills 171 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 12-1 The following represents a project with know activity times. All times are in weeks. Activity A B C D E F Immediate Predecessor A B C, D B Time 4 3 2 7 4 5 52) Using the data in Table 12-1, what is the minimum possible time required for completing the project? A) 8 B) 14 C) 25 D) 10 E) None of the above Answer: B Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 53) Using the data in Table 12-1, what is the latest possible time that C may be started without delaying completion of the project? A) 0 B) 4 C) 8 D) 10 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 54) According to Table 12-1, compute the slack time for activity D. A) 0 B) 5 C) 3 D) 6 E) None of the above Answer: A Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 172 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 55) Using the data in Table 12-1, compute the latest finish time for activity E. A) 4 B) 10 C) 14 D) 25 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills Table 12-2 The following represents a project with four activities. All times are in weeks. Activity A B C D Immediate Predecessor A B Optimistic Time 2 8 6 5 Most Likely Time 8 8 9 11 Pessimistic Time 14 8 18 17 56) According to the data in Table 12-2, what is the critical path? A) A-B B) A-C C) B-D D) A-B-C-D E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 57) According to the data in Table 12-2, what is the minimum expected completion time for the project? A) 18 B) 19 C) 37 D) 11 E) None of the above Answer: B Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 173 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 58) According to Table 12-2, there are four activities in the project. Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. If you wished to find the probability of finishing the project in 20 weeks or fewer, it would be necessary to find the variance and then the standard deviation to be used with the normal distribution. What variance would be used? A) 2 B) 4 C) 8 D) 12 E) None of the above Answer: B Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 59) According to Table 12-2, there are four activities in the project. Assume the normal distribution is appropriate to use to determine the probability of finishing by a particular time. What is the probability that the project is finished in 16 weeks or fewer? (Round to two decimals.) A) 0.07 B) 0.93 C) 0.43 D) 0.77 E) None of the above Answer: A Diff: 3 Topic: PERT/CPM AACSB: Analytic Skills 60) Consider a project that has an expected completion time of 60 weeks and a standard deviation of five weeks. What is the probability that the project is finished in 70 weeks or fewer? (Round to two decimals.) A) 0.98 B) 0.48 C) 0.50 D) 0.02 E) 0.63 Answer: A Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 174 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 61) Your company is considering submitting a bid on a major project. You determine that the expected completion time is 100 weeks and the standard deviation is 10 weeks. It is assumed that the normal distribution applies. You wish to set the due date for the project such that there is an 85 percent chance that the project will be finished by this time. What due date should be set? A) 108.0 B) 110.4 C) 89.6 D) 85.0 E) 100 Answer: B Diff: 3 Topic: PERT/CPM AACSB: Analytic Skills Table 12-3 Activity A B C D E Immediate Predecessor --A A B, C Optimistic 4 12 2 5 6 Most Likely 5 16 8 5 7 Pessimistic 6 18 14 5 8 Standard Deviation 0.333 1.000 2.000 0.000 0.333 Variance 0.111 1.000 4.000 0.000 0.111 62) According to Table 12-3, there are five activities in a PERT project. Which activities are on the critical path? A) A-B-C-D-E B) A-C-E C) B-D D) A-B-C-D E) B-E Answer: E Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 63) According to Table 12-3, there are five activities in a PERT project. What is the variance of the critical path? A) 5.222 B) 4.222 C) 1.222 D) 0 E) 1.111 Answer: E Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 175 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 64) According to Table 12-3, there are five activities in a PERT project. If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer, what mean and variance would be used? A) 20 and 4.222 B) 30 and 5.222 C) 20 and 5.222 D) 30 and 4.222 E) 22.667 and 1.111 Answer: E Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 65) The critical path of a network is the A) path with the least variance. B) path with zero slack. C) path with the most activities. D) path with the largest variance. E) None of the above Answer: B Diff: 2 Topic: PERT/CPM 66) In a PERT network, the latest (activity) start time is the A) earliest time that an activity can be finished without delaying the entire project. B) latest time that an activity can be started without delaying the entire project. C) earliest time that an activity can start without violation of precedence requirements. D) latest time that an activity can be finished without delaying the entire project. E) None of the above Answer: B Diff: 1 Topic: PERT/CPM 67) The work breakdown structure involves identifying the ________ for each activity. A) time B) cost C) resource requirements D) predecessors E) All of the above Answer: E Diff: 2 Topic: INTRODUCTION 176 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 68) PERT stands for ________. A) probabilistic evaluation and review technique B) program evaluation and review technique C) probability of expected run times D) program of expected run times E) project evaluation and review technique Answer: B Diff: 2 Topic: INTRODUCTION 69) CPM stands for ________. A) critical path management B) critical project management C) critical project method D) critical path method E) centralized project management Answer: D Diff: 2 Topic: INTRODUCTION 70) Which of the following questions can be answered by PERT? A) When will the entire project be completed? B) What is the probability that the project will be completed by a specific date? C) What are the critical activities? D) What are the noncritical activities? E) All of the above Answer: E Diff: 1 Topic: PERT/CPM 71) In PERT, we assume that A) the times to complete individual activities are known with certainty. B) all activities are carried out by staff from our own organization. C) the total cost of a project is independent of the time to complete the project. D) the total time to complete all activities on the critical path is described by a normal distribution. E) None of the above Answer: D Diff: 2 Topic: PERT/CPM 72) The two common techniques for drawing PERT networks are ________. A) NOA and NRA B) AON and AOA C) GANTT and NOA D) ONA and OAO 177 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall E) CAN and CAA Answer: B Diff: 3 Topic: PERT/CPM 73) In PERT analysis, the probability of the optimistic time occurring should be on the order of ________. A) 1/2 B) 1/3 C) 1/6 D) 1/10 E) 1/100 Answer: E Diff: 2 Topic: PERT/CPM 74) The expected time in PERT is A) greater than the most likely time. B) equal to the most likely time. C) less than the most likely time. D) any of the above E) None of the above Answer: D Diff: 2 Topic: PERT/CPM 75) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 7, and 11 days respectively, compute the expected time for this activity. A) 5 B) 6 C) 7 D) 12 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 76) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 13 days respectively, compute the expected time for this activity. A) 3 B) 4 C) 5 D) 6 E) None of the above Answer: D 178 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 179 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 77) Given an activity's optimistic, most likely, and pessimistic time estimates of 1, 9, and 23 days respectively, compute the PERT expected activity time for this activity. A) 10 B) 12 C) 9 D) 11 E) None of the above Answer: A Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 78) Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 6, and 9 days respectively, compute the PERT variance for this activity. A) 3 B) 1 C) 9 D) 6 E) None of the above Answer: B Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 180 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 79) The project described by: Activity A B C D E Immediate Predecessor -A A B C Time (days) 10 4 6 7 5 is best represented by which of the following networks? A) B) C) D) E) None of the above Answer: A Diff: 1 Topic: PERT/CPM 181 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytic Skills 182 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 80) The project described by: Activity A B C D E Immediate Predecessor -A A B, C C Time (days) 10 4 6 7 5 has a critical path of length of ________. A) 21 days B) 14 days C) 23 days D) 32 days E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 81) The project described by: Activity A B C D E Immediate Predecessor -A -B, C D Time (days) 6 2 8 5 7 has a critical path of length of ________. A) 15 days B) 20 days C) 17 days D) 18 days E) None of the above Answer: B Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 183 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 12-4 The following represents a project with known activity times. All times are in weeks. Activity A B C D E F G Immediate Predecessor --A B C, D B E, F Time 4 3 2 7 4 5 4 82) Using the data in Table 12-4, what is the minimum possible time required for completing the project? A) 8 B) 12 C) 18 D) 10 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 83) Using the data in Table 12-4, what is the latest possible time that C may be started without delaying completion of the project? A) 0 B) 4 C) 8 D) 10 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 84) Using the data in Table 12-4, compute the slack time for activity D. A) 0 B) 5 C) 3 D) 6 E) None of the above Answer: A Diff: 2 Topic: PERT/CPM 184 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytic Skills 185 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 85) Using the data in Table 12-4, compute the latest finish time for activity E. A) 4 B) 10 C) 14 D) 25 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 86) Using the data in Table 12-4, determine the latest time activity A can be started without delaying the project completion. A) 4 B) 3 C) 8 D) 6 E) None of the above Answer: A Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 87) Using the data in Table 12-4, determine the latest time activity A can be finished and not delay any activity? A) 4 B) 0 C) 8 D) 5 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 88) Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks. What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.) A) 0.68 B) 0.78 C) 0.22 D) 0.32 E) None of the above Answer: B Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 186 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 187 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 89) Your company is considering submitting a bid on a major project. You determine that the expected completion time is 150 weeks and the standard deviation is 10 weeks. It is assumed that the normal distribution applies. You wish to set the due date for the project such that there is a 95 percent chance that the project will be finished by this time. What due date should be set? A) 108.0 B) 160.4 C) 166.5 D) 135.0 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills Table 12-5 Activity A B C D E F G H Immediate Predecessor --A B B C, D C, D E, F Time 4 5 3 8 2 3 7 2 ES 0 0 4 5 5 13 13 16 EF 4 5 7 13 7 16 20 18 LS 6 0 10 5 16 15 13 18 LF 10 5 13 13 18 18 20 20 90) How long could Table 12-5's activity E be delayed without delaying the completion of the project? A) 7 B) 16 C) 11 D) 18 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 91) How long could Table 12-5's activity F be delayed without delaying the project? A) 2 B) 3 C) 14 D) 16 E) None of the above Answer: A 188 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 92) What is the minimum possible time required for completing the Table 12-5 project? A) 14 B) 18 C) 17 D) 20 E) None of the above Answer: D Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills Table 12-6 Activity A B C D E F G H Immediate Predecessor --A A B, C B D, E G, F Optimistic 2 2 1 5 6 14 1 1 Most Likely 3 5 2 5 7 14 5 4 Pessimistic 4 8 9 5 8 14 9 8 σ 0.333 1.000 1.330 0.000 0.333 0.000 1.333 1.167 σ2 0.111 1.000 1.780 0.000 0.111 0.000 1.780 1.362 93) Which activities are part of Table 12-6's critical path? A) A-B-E-G-H B) A-C-E-G-H C) A-D-G-H D) B-F-H E) None of the above Answer: D Diff: 3 Topic: PERT/CPM AACSB: Analytic Skills 94) What is the variance of Table 12-6's critical path? A) 5.222 B) 4.364 C) 1.362 D) 5.144 E) 2.362 189 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: E Diff: 3 Topic: PERT/CPM AACSB: Analytic Skills 190 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Figure 12-1 95) Given the network in Figure 12-1, the critical path is A) A-C-F-H. B) B-D-E-F-H. C) A-C-E-G-H. D) B-D-G-E-F-H. E) None of the above Answer: B Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 96) Given the network in Figure 12-1, the time to complete those activities on the critical path is expected to be ________. A) 20 B) 22 C) 25 D) 26 E) None of the above Answer: C Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 97) Given the network shown in Figure 12-1, assume that completion of A is delayed by two days. What other activities are impacted? A) B B) D C) E D) C E) None of the above Answer: D Diff: 2 Topic: PERT/CPM 191 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytic Skills 192 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 98) Given the network shown in Figure 12-1, assume that completion of B is delayed by two days. What happens to the project? A) The critical path is extended by two days. B) The start of activity F is delayed by two days. C) The start of activity E is delayed by two days. D) All of the above E) None of the above Answer: D Diff: 2 Topic: PERT/CPM 99) Given the network shown in Figure 12-1, assume that the completion of activity C is delayed by four days. What changes will take place? A) The critical path will change to: A-C-B-D-E-F-H. B) Activity F will be delayed by four days. C) Activity E will be delayed by four days. D) Activity G will be delayed by four days. E) None of the above Answer: E Diff: 3 Topic: PERT/CPM AACSB: Analytic Skills 100) Given the network shown in Figure 12-1 and the following information, what is the variance of the critical path? Activity A B C D E F G H Expected time 3 5 6 4 5 4 6 7 Variance 2 3 3 1 1 2 2 2 A) 16 B) 7 C) 9 D) 8 E) None of the above Answer: C Diff: 3 Topic: PERT/CPM AACSB: Analytic Skills 193 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 101) PERT often assumes that time estimates follow which of the following probability distributions? A) normal B) exponential C) binomial D) Poisson E) None of the above Answer: E Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 102) PERT assumes that the total completion time of a projects follows which of the following probability distributions? A) normal B) exponential C) binomial D) Poisson E) None of the above Answer: A Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 103) The crash time of an activity represents A) the normal time to complete an activity. B) the most pessimistic time to complete an activity. C) the incremental decrease in the time to complete an activity. D) the shortened activity time. E) None of the above Answer: D Diff: 2 Topic: PROJECT CRASHING 104) Reducing the overall activity time is based on which of the following steps? A) crashing activities with the lowest overall crash cost B) crashing activities with the lowest overall normal cost C) crashing activities on the critical path based on lowest overall cost D) crashing activities on the critical path based on lowest cost/week E) crashing activities with the lowest cost/week. Answer: D Diff: 2 Topic: PROJECT CRASHING 194 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 105) An alternative approach to project crashing is to use which of the following techniques? A) linear programming B) nonlinear programming C) Markov analysis D) queuing theory E) None of the above Answer: A Diff: 2 Topic: PROJECT CRASHING 106) Which of the following is not a decision variable when formulating the project crashing problem as a linear program? A) the early finish times of critical activities B) the early finish times of non critical activities C) the start time of the project D) the finish time of the project E) the early start times of all activities Answer: E Diff: 2 Topic: PROJECT CRASHING 107) Which of the following statement about project crashing is false? A) The crash cost is greater than or equal to the normal cost of an activity. B) The crash time is less than or equal to the normal time to complete an activity. C) Reducing the time of an activity on the critical path automatically reduces total project duration. D) It may not be possible to crash a particular activity. E) Crashing may not lead to an overall reduction in costs for the project. Answer: C Diff: 3 Topic: PROJECT CRASHING 108) The process of smoothing out the utilization of resources in a project is called A) CPM. B) PERT. C) project crashing. D) work breakdown structure. E) resource leveling. Answer: E Diff: 1 Topic: OTHER TOPICS IN PROJECT MANAGEMENT 195 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 109) Consider the following project schedule: Activity A B C D E F G H Immediate Predecessor --A B B C, D C, D E, F Time 4 5 3 8 2 3 7 2 ES 0 0 4 5 5 13 13 16 EF 4 5 7 13 7 16 20 18 LS 6 0 10 5 16 15 13 18 LF 10 5 13 13 18 18 20 20 (a) Which activities are critical? (b) Which activity has the most slack? Answer: (a) B, D, G (b) E Diff: 1 Topic: PERT/CPM AACSB: Analytic Skills 110) Consider the project with the following estimates for activity times and precedence relationships: Activity A B C D E F G H Optimistic Time 3 5 2 2 1 3 7 2 Most Likely Time 4 7 3 5 7 5 8 6 Pessimistic Time 5 9 10 8 7 7 9 10 Immediate Predecessor(s) ----A B B C, D D, E F (a) What is the expected duration of the project? (b) What is the project variance? (c) If the deadline of the project is 25 days, what is the probability of finishing the project on time? Answer: (a) 23 (b) 3.67 (c) 0.8508 Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 196 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 111) Consider the tasks, durations, and predecessor relationships in the following network. Draw the network and answer the questions that follow. Activity A B C D E F G H I J Immediate Predecessors) --A A B D, C C F F E, G, H I Optimistic (Weeks) 4 2 8 1 6 2 2 6 4 1 Most Likely (Weeks) 7 8 12 2 8 3 2 8 8 2 Pessimistic (Weeks) 10 20 16 3 22 4 2 10 12 3 (a) What is the expected duration of the project? (b) What is the probability of completion of the project before week 42? Answer: (a) 40 (b) 8079 Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 197 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 112) Given: Activity A B C D E F G Optimistic 3 6 6 0.5 2 4 1 Most Likely 4 7 9 1 3 5 3 Pessimistic 5 14 12 1.5 10 12 11 Determine: (a) the critical path. (b) the probability that the project will be completed in 22 weeks. Answer: (a) Critical path is A-C-F. Expected time is 19. (b) Variance for critical path is 2.889, so standard deviation is 1.70. P(X ≤ 22) = 0.9608 Diff: 3 Topic: PERT/CPM AACSB: Analytic Skills 198 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 113) A small software development project has five major activities. The times are estimated and provided in the table below. Activity A B C D E Immediate Predecessor --A B C a 2 10 4 2 3 m 5 10 7 5 3 b 8 10 10 14 3 (a) What is the expected completion time for this project? (b) What variance would be used in finding probabilities of finishing by a certain time? Answer: (a) expected completion time = 16 (Activities B-D) (b) variance = 0 + 4 = 4 Diff: 3 Topic: PERT/CPM AACSB: Analytic Skills 199 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 114) Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks). Activity A B C D E F G Normal Time 4 2 3 8 6 3 4 Crash Time 3 1 3 4 3 2 2 Normal Cost 2200 2200 500 2300 900 3000 1400 Crash Cost 2600 2800 500 2600 1200 4200 2000 Immediate Predecessor ---A B C D, E (a) What is the project completion date? (b) What is the total cost required for completing this project on normal time? (c) If you wish to reduce the time required to complete this project by one week, which activity should be crashed, and how much will this increase the total cost? Answer: (a) Project completion time = 16 weeks (Activities A-D-G) (b) Total cost = $12,300 (c) Crash D, one week at an additional cost of $75 Diff: 3 Topic: PERT/CPM and PROJECT CRASHING AACSB: Analytic Skills 200 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 115) Draw the PERT network associated with the following activities. Activity A B C D E F G H I J Immediate Predecessor -A A B B C, E A, D F F G, H, I Answer: Diff: 2 Topic: PERT/CPM AACSB: Analytic Skills 201 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 116) Given (Time in weeks): Activity A B C D E F G H I Optimistic 3 6 2 6 4 1 1 2 1 Most Likely 4 7 3 9 5 3 2 5 4 Pessimistic 5 14 10 12 12 11 9 8 7 Determine: (a) the critical path. (b) the probability that the project will be completed in 22 weeks. Answer: (a) Critical path is B-E-G-I. (b) Variance for critical path is 6.33; standard deviation is 2.51. The probability that the project will be completed in 22 weeks = 0.65. Diff: 3 Topic: PERT/CPM AACSB: Analytic Skills 202 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 117) A small software development project has four major activities. The times are estimated and provided in the table below. Immediate Activity Predecessor A -B A C A D B E D F C G E, F H C I G, H a 2 3 4 2 3 6 1 6 3 m 5 6 7 5 3 8 1 10 4 b 8 9 10 14 3 10 1 14 5 (a) What is the expected completion time for this project? (b) What variance would be used in finding probabilities of finishing by a certain time? Answer: (a) expected completion time = 26 (Activities A-C-H-I) (b) variance = 3.88 Diff: 3 Topic: PERT/CPM AACSB: Analytic Skills 203 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 118) Development of a new deluxe version of a particular software product is being considered. The activities necessary for the completion of this are listed in the table below (Time in weeks). Activity A B C D E F G H I Immediate Predecessor -A A B D C E, F C G, H a m b 2 3 4 2 3 6 1 6 3 5 6 7 5 3 8 1 10 4 8 9 10 14 3 10 1 14 5 (a) If you wish to reduce the time required to complete this project by two weeks, which activity(ies) should be crashed, and how much will this increase the total cost? (b) What would be the added cost if you wanted to complete the project in the minimum time possible? Answer: (a) Crash D, two weeks at an additional cost of $100 (b) Crash D 4 weeks, G 2 weeks, E 3 weeks, A 1 week, and B 1 week, for a total additional cost of $1,700 Diff: 3 Topic: PERT/CPM and PROJECT CRASHING AACSB: Analytic Skills 119) PERT is the acronym for what? Answer: Program Evaluation and Review Technique. Diff: 2 Topic: INTRODUCTION 120) In a PERT analysis, how is the optimistic time defined? Answer: the estimated time for an activity, should circumstances go as well as possible (should have a low probability of actual occurrence) Diff: 2 204 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Topic: PERT/CPM 205 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 121) CPM is the acronym for what? Answer: Critical Path Method Diff: 2 Topic: INTRODUCTION 122) In PERT analysis, how is the pessimistic activity time defined? Answer: the estimated time for an activity, based on unfavorable conditions (should have a low probability of actual occurrence) Diff: 2 Topic: PERT/CPM 123) In PERT/CPM, what is meant by the critical path? Answer: the series of activities in a network that has zero slack or the longest time path through a network Diff: 2 Topic: PERT/CPM 206 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 97) Define infeasibility with respect to an LP solution. Answer: This occurs when there is no solution that can satisfy all constraints simultaneously. Diff: 2 Topic: FOUR SPECIAL CASES IN LP 98) Define unboundedness with respect to an LP solution. Answer: This occurs when a linear program has no finite solution. The result implies that the formulation is missing one or more crucial constraints. Diff: 2 Topic: FOUR SPECIAL CASES IN LP 99) Define alternate optimal solutions with respect to an LP solution. Answer: More than one optimal solution point exist because the objective function is parallel to a binding constraint. Diff: 2 Topic: FOUR SPECIAL CASES IN LP 100) How does the case of alternate optimal solutions, as a special case in linear programming, compare to the two other special cases of infeasibility and unboundedness? Answer: With multiple alternate solutions, any of those answers is correct. In the other two cases, no single answer can be generated. Alternate solutions can occur when a problem is correctly formulated whereas the other two cases most likely have an incorrect formulation. Diff: 2 Topic: FOUR SPECIAL CASES IN LP AACSB: Reflective Thinking Quantitative Analysis for Management, 13e (Render et al.) Chapter 13 Waiting Lines and Queuing Theory Models 33) Assume that we are using a waiting line model to analyze the number of service technicians required to maintain machines in a factory. Our goal should be to A) minimize the number of machines needing repair. B) minimize the downtime for individual machines. C) minimize the percent of idle time of the technicians. D) minimize the total cost (cost of maintenance plus cost of downtime). Answer: D Diff: Moderate Topic: WAITING LINE COSTS LO: 12.1: Describe the trade-off curves for cost of waiting time and cost of service. AACSB: Analytical thinking Classification: Concept 34) In queuing analysis, total expected cost is the sum of expected ________ plus expected ________. 207 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall A) service costs, arrival costs B) facility costs, calling costs C) calling costs, waiting costs D) service costs, waiting costs Answer: D Diff: Easy Topic: WAITING LINE COSTS LO: 12.1: Describe the trade-off curves for cost of waiting time and cost of service. AACSB: Analytical thinking Classification: Concept 208 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 35) In queuing theory, the calling population is another name for A) the queue size. B) the servers. C) the arrivals. D) the service rate. Answer: C Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 36) An arrival in a queue that reneges is one who A) after joining the queue, becomes impatient and leaves. B) refuses to join the queue because it is too long. C) goes through the queue, but never returns. D) jumps from one queue to another, trying to get through as quickly as possible. Answer: A Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 37) The customer who arrives at a bank, sees a long line, and leaves to return another time is A) balking. B) cropping. C) reneging. D) blithering. Answer: A Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 209 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 38) The customer who arrives at a bank, enters a line, and decides to leave is A) balking. B) cropping. C) reneging. D) blithering. Answer: C Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 39) The three major characteristics of the input source that generates arrivals or customers for the service system are A) size, demographics, and behavior. B) size, pattern, and behavior. C) demographics, pattern, and behavior. D) size, demographics, and pattern. Answer: B Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 40) The term queue "discipline" describes the A) degree to which members of the queue renege. B) sequence in which members of the queue arrived. C) degree to which members of the queue are orderly and quiet. D) sequence in which members of the queue are serviced. Answer: D Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 210 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 41) A vendor selling newspapers on a street corner is an example of a A) single-channel, multiphase system. B) single-channel, single-phase system. C) multichannel, multiphase system. D) multichannel, single-phase system. Answer: B Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 42) Lines at banks where customers wait for a teller window are usually representative of a A) single-channel, multiphase system. B) single-channel, single-phase system. C) multichannel, multiphase system. D) multichannel, single-phase system. Answer: D Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 43) Which of the following distributions is most often used to estimate the arrival pattern? A) negative exponential B) normal C) Poisson D) Erlang Answer: C Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 211 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 44) A single automatic car wash with one bay and a cycle time of 2.5 minutes is what type of model? A) M/M/1 B) M/M/2 C) M/D/2 D) M/D/1 Answer: D Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 45) A single automatic car wash with one bay and a service time that is normally distributed is what type of model? A) M/M/1 B) M/D/2 C) M/D/1 D) M/G/1 Answer: D Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 46) A suburban specialty restaurant has developed a single drive-thru window. Customers order, pay, and pick up their food at the same window. Arrivals follow a Poisson distribution, while service times follow an exponential distribution. What type of queuing model is exhibited in this problem? A) M/M/1 B) M/M/2 C) M/D/2 D) M/D/1 Answer: D Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Concept 212 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 47) A professor holds office hours during final exam week and discovers much to his dismay that his sudden popularity affords him little time to engage in his favorite activity, watching cat videos. Fifteen students per hour arrive at his office and he patiently answers questions, averaging three minutes per student. If the average cat video is 60 seconds, how many videos can the professor watch in an hour? A) 15 B) 18 C) 20 D) 24 Answer: A Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 48) A professor holds office hours during final exam week and discovers much to his dismay that his sudden popularity affords him little time to engage in his favorite activity, watching cat videos. Fifteen students per hour arrive at his office and he patiently answers questions, averaging three minutes per student. On average, how many students are waiting to ask questions? A) 2.00 B) 2.25 C) 2.50 D) 2.75 Answer: B Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 213 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 49) A professor holds office hours during final exam week and discovers much to his dismay that his sudden popularity affords him little time to engage in his favorite activity, watching cat videos. Fifteen students per hour arrive at his office and he patiently answers questions, averaging three minutes per student. On average, how long must a student wait in line to get their last-minute questions answered? A) 3 minutes B) 6 minutes C) 9 minutes D) 12 minutes Answer: C Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 50) A professor holds office hours during final exam week and discovers much to his dismay that his sudden popularity affords him little time to engage in his favorite activity, watching cat videos. Fifteen students per hour arrive at his office and he patiently answers questions, averaging three minutes per student. A student joins the line at 9:45 am and the test is at 10:00 am the same morning. How much time does the student have after getting his question answered to get to the exam room? A) 12 minutes B) 9 minutes C) 6 minutes D) 3 minutes Answer: D Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 214 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 51) Customers enter the waiting line at a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is four per minute and the average service rate of a single server is seven per minute, what is the average number of customers in the system? A) 0.43 B) 1.67 C) 0.57 D) 1.33 Answer: D Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 52) Customers enter the waiting line at a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is four per minute and the average service rate of a single server is seven per minute, what is the average number of customers waiting in line behind the person being served? A) 0.76 B) 0.19 C) 1.33 D) 1.67 Answer: A Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 215 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 53) Customers enter the waiting line to pay for food as they leave a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is four per minute and the average service rate of a single server is seven per minute, what proportion of the time is the server busy? A) 0.43 B) 0.57 C) 0.75 D) 0.25 Answer: B Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 54) Customers enter the waiting line to pay for food as they leave a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is four per minute and the average service rate of a single server is seven per minute, on average, how much time will elapse from the time a customer enters the line until he/she leaves the cafeteria? A) 0.67 minute B) 0.50 minute C) 0.75 minute D) 0.33 minute Answer: D Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 216 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 55) At a local fast-food joint, cars arrive randomly at a rate of 12 every 30 minutes. The fast food joint takes an average of 2 minutes to serve each arrival. The utilization factor for this system is A) 0.467. B) 0.547. C) 0.800. D) 0.133. Answer: C Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 56) At a local fast food joint, cars arrive randomly at a rate of 12 every 30 minutes. Service times are random (exponential) and average 2 minutes per arrival. The average time in the queue for each arrival is A) 2 minutes. B) 4 minutes. C) 6 minutes. D) 8 minutes. Answer: D Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 57) Which of the following distributions is most often used to estimate service times? A) negative exponential B) normal C) Poisson D) Erlang Answer: A Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 217 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 58) Most systems use a queue discipline known as A) shortest processing time. B) longest processing time. C) FIFO. D) earliest due date. Answer: C Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 59) A queuing system with a normally distributed arrival pattern, exponential service times, and three servers would be described as A) G/G/3. B) M/M/3. C) G/M/3. D) M/G/3. Answer: C Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 60) The initial state of a queuing system (for example, when a restaurant first opens), is referred to as the ________ state. A) steady B) primary C) introductory D) transient Answer: D Diff: Moderate Topic: SOME GENERAL OPERATING CHARACTERISTIC RELATIONSHIPS LO: 12.7: Understand Little's Flow Equations. AACSB: Analytical thinking Classification: Concept 218 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 61) A post office has a single line for customers waiting for the next available postal clerk. There are two postal clerks who work at the same rate. The arrival rate of customers follows a Poisson distribution, while the service time follows an exponential distribution. What type of queuing model applies here? A) M/M/1 B) M/M/2 C) M/D/2 D) M/D/1 Answer: B Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 62) A post office has a single line for customers waiting for the next available postal clerk. There are two postal clerks who work at the same rate. The arrival rate of customers follows a Poisson distribution, while the service time follows a normal distribution. What type of queuing model applies here? A) M/M/2 B) M/D/2 C) M/D/1 D) M/G/2 Answer: D Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 219 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 63) A post office has a single line for customers waiting for the next available postal clerk. There are two postal clerks who work at the same rate. The arrival rate of customers follows a Poisson distribution, while the service time follows an exponential distribution. The average arrival rate is three per minute and the average service rate is two per minute for each of the two clerks. What is the average length of the line? A) 3.429 B) 1.929 C) 1.143 D) 0.643 Answer: B Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 64) A post office has a single line for customers waiting for the next available postal clerk. There are two postal clerks who work at the same rate. The arrival rate of customers follows a Poisson distribution, while the service time follows an exponential distribution. The average arrival rate is three per minute and the average service rate is two per minute for each of the two clerks. How long does the average person spend waiting for a clerk? A) 3.429 minutes B) 1.929 minutes C) 1.143 minutes D) 0.643 minute Answer: D Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 220 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 65) A post office has a single line for customers waiting for the next available postal clerk. There are two postal clerks who work at the same rate. The arrival rate of customers follows a Poisson distribution, while the service time follows an exponential distribution. The average arrival rate is three per minute and the average service rate is two per minute for each of the two clerks. What proportion of time are both clerks idle? A) 0.643 B) 0.250 C) 0.750 D) 0.143 Answer: B Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application Table 12-1 M/M/2 Mean Arrival Rate: Mean Service Rate: Number of Servers: Server wage Customer waiting cost Probability of zero customers in system: 20 customers/hour 12 customers/hour 2 $10/hour $20/hour 0.280 66) According to the information provided in Table 12-1, on average, how many customers are in the line? A) 3.79 B) 3.33 C) 4.25 D) 4.33 Answer: A Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 221 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 67) According to the information provided in Table 12-1, how long does a customer wait on average? A) 11 minutes B) 11 minutes 30 seconds C) 12 minutes 15 seconds D) 12 minutes 45 seconds Answer: B Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 68) Using the information provided in Table 12-1, counting each person being served and the people in line, on average, how many customers would be in this system? A) 4.85 B) 5.05 C) 5.45 D) 6.15 Answer: C Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 69) According to the information provided in Table 12-1, what is the hourly total cost of the system for customers and servers? Assume that servers are paid only when they are helping customers. A) $117.67 B) $121.47 C) $129.09 D) $125.76 Answer: D Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 222 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 70) According to the information provided in Table 12-1, what percentage of the total available service time is being used? A) 83.0% B) 87.0% C) 78.3% D) 60.0% Answer: A Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 71) According to the information provided in Table 12-1, what is the average amount of time a customer waits and is served? A) 15 minutes 40 seconds B) 16 minutes 20 seconds C) 17 minutes D) 17 minutes 40 seconds Answer: B Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 223 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 12-2 M/M/2 Mean Arrival Rate: Mean Service Rate: Number of Servers: 5 occurrences per minute 3 occurrences per minute 2 Queue Statistics: Mean Number of Units in the System: Mean Number of Units in the Queue: Mean Time in the System: Mean Time in the Queue: Service Facility Utilization Factor: Probability in No Units in System: 5.455 3.788 1.091 minutes 0.758 minutes 0.833 0.091 72) According to the information provided in Table 12-2, which presents a queuing problem solution, on average, how many units are in the line? A) 5.455 B) 3.788 C) 1.091 D) 0.758 E) 0.833 Answer: B Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 73) According to the information provided in Table 12-2, which presents a queuing problem solution, what proportion of time is at least one server busy? A) 0.833 B) 0.758 C) 0.091 D) 0.909 Answer: D Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking 224 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Classification: Application 225 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 74) According to the information provided in Table 12-2, which presents a queuing problem solution, there are two servers in this system. Counting each person being served and the people in line, on average, how many people would be in this system? A) 5.455 B) 3.788 C) 9.243 D) 10.900 Answer: A Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application Table 12-3 M/M/3 Mean Arrival Rate: Mean Service Rate: Number of Servers: 4 occurrences per minute 2 occurrences per minute 3 Queue Statistics: Mean Number of Units in the System: Mean Number of Units in the Queue: Mean Time in the System: Mean Time in the Queue: Service Facility Utilization Factor: Probability in No Units in System: 2.889 0.889 0.722 minutes 0.222 minutes 0.667 0.111 75) According to the information provided in Table 12-3, which presents a queuing problem solution, what proportion of time is the system totally empty? A) 0.111 B) 0.333 C) 0.889 D) 0.667 Answer: A Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking 226 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Classification: Application 227 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 76) According to the information provided in Table 12-3, which presents a queuing problem solution, on average, how long does each customer spend waiting in line? A) 0.333 minute B) 0.889 minute C) 0.222 minute D) 0.722 minute Answer: C Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 77) According to the information provided in Table 12-3, which presents a queuing problem solution, what is the utilization rate of the service facility? A) 0.889 B) 0.222 C) 0.722 D) 0.667 Answer: D Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 78) If everything else remains constant, including the mean arrival rate and service rate, except that the service time becomes constant instead of exponential A) the average queue length will be halved. B) the average waiting time will be doubled. C) the average queue length will be doubled. D) There is not enough information to know what will happen to the queue length and waiting time. Answer: A Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 228 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 79) At an automatic car wash, cars arrive randomly at a rate of 7 cars every 30 minutes. The car wash takes exactly 4 minutes (this is constant). On average, what would be the length of the line? A) 8.171 B) 7.467 C) 6.53 D) 0.467 Answer: C Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 80) At an automatic car wash, cars arrive randomly at a rate of 7 every 30 minutes. The car wash takes exactly 4 minutes (this is constant). On average, how long would each car spend at the car wash? A) 28 minutes B) 32 minutes C) 17 minutes D) 24 minutes Answer: B Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 81) At an automatic car wash, cars arrive randomly at a rate of 7 every 30 minutes. The car wash takes exactly 4 minutes (this is constant). On average, how long would each driver have to wait before receiving service? A) 28 minutes B) 32 minutes C) 17 minutes D) 24 minutes Answer: A Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 229 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 82) At an automatic car wash, cars arrive randomly at a rate of 7 every 30 minutes. The car wash takes exactly 4 minutes (this is constant). On average, how many customers would be at the car wash (waiting in line or being serviced)? A) 8.17 B) 7.46 C) 6.53 D) 0.46 Answer: B Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 83) At a local fast food joint, cars arrive randomly at a rate of 12 every 30 minutes. The fast food joint takes exactly 2 minutes (this is constant). The average total time in the system is A) 5.4 minutes. B) 6.0 minutes. C) 8.0 minutes. D) 2.5 minutes. Answer: B Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 230 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 12-4 The sentient car wash in Luther knows she is in for a busy day when dawn breaks on a gorgeous spring morning. She is capable of washing a car every four minutes, and by the looks of things, it is reasonable to expect a steady stream of twelve cars per hour arriving. Because she is fully automatic, she knows that the four-minute estimate is accurate and invariant. She values her time at $10 per hour. Yes, it seems low, but as a single bay car wash, there are few other jobs in town she is qualified for. (We won't get into her unsuccessful turn at the beauty salon.) She estimates that customer time can be valued at $15 per hour. 84) According to the information provided in Table 12-4, how much time will the average customer spend waiting in line? A) 8 minutes B) 9 minutes C) 10 minute D) 11 minute Answer: A Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 85) According to the information provided in Table 12-4, on average, how many customers are in line? A) 1.2 cars B) 1.6 cars C) 1.75 cars D) 2.1 cars Answer: B Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 231 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 86) According to the information provided in Table 12-4, how many minutes per hour will the car wash be idle and able to ponder the meaning of life? A) 9 minutes B) 10 minutes C) 12 minutes D) 15 minutes Answer: C Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 87) According to Table 12-4, what is the total hourly cost of the system for customers and the car wash herself? Assume the car wash is paid only when she is washing cars. A) $38 B) $40 C) $42 D) $44 Answer: D Diff: Difficult Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 88) According to Table 12-4, what is the total number of cars in the system? A) 2.40 B) 2.75 C) 3.10 D) 3.45 Answer: A Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 232 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 12-5 M/D/1 Mean Arrival Rate: Constant Service Rate: 5 occurrences per minute 7 occurrences per minute Queue Statistics: Mean Number of Units in the System: Mean Number of Units in the Queue: Mean Time in the System: Mean Time in the Queue: Service Facility Utilization Factor: 1.607 0.893 0.321 minutes 0.179 minutes 0.714 89) According to the information provided in Table 12-5, which presents the solution for a queuing problem with a constant service rate, on average, how much time is spent waiting in line? A) 1.607 minutes B) 0.714 minute C) 0.179 minute D) 0.893 minute Answer: C Diff: Easy Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 90) According to the information provided in Table 12-5, which presents the solution for a queuing problem with a constant service rate, on average, how many customers are in the system? A) 0.893 B) 0.714 C) 1.607 D) 0.375 Answer: C Diff: Easy Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 233 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 91) According to the information provided in Table 12-5, which presents a queuing problem solution for a queuing problem with a constant service rate, on average, how many customers arrive per time period? A) 5 B) 7 C) 1.607 D) 0.893 Answer: A Diff: Easy Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 92) According to the information provided in Table 12-5, which presents the solution for a queuing problem with a constant service rate, on average, how many minutes does a customer spend in the system? A) 0.893 minute B) 0.321 minute C) 0.714 minute D) 1.607 minutes Answer: B Diff: Easy Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 93) According to the information provided in Table 12-5, which presents the solution for a queuing problem with a constant service rate, the probability that the server is idle is A) 0.217. B) 0.643. C) 0.286. D) 0.714. Answer: C Diff: Easy Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 234 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 94) Thanks to a generous and eccentric donor, the school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the probability that none of the fax machines need toner? A) 1.1500 B) 1.1658 C) .8578 D) .7696 Answer: C Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 95) Thanks to a generous and eccentric donor, the school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the average number of fax machines in the queue? A) 0.5658 fax machines B) 0.3304 fax machines C) .0563 fax machine D) .0142 fax machine Answer: D Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 96) Thanks to a generous and eccentric donor, the school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the average number of fax machines in the system? A) .0142 fax machine B) .1563 fax machine C) .0249 fax machine D) .2749 fax machine Answer: B Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with 235 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 97) Thanks to a generous and eccentric donor, the school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the average waiting time in the queue? A) .0142 hour B) .1563 hour C) .0249 hour D) .2749 hour Answer: C Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 98) Thanks to a generous and eccentric donor, the school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the probability that one of the fax machines needs toner? A) 0.22 B) 0.19 C) 0.16 D) 0.13 Answer: D Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 236 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 12-6 Customers arrive at coffee shop at a rate of 40 per hour. There are 2 servers available and it takes an average of 1 minute to serve each customer. 99) Using Table 12-6, what proportion of time are the servers busy? A) 0 B) 0.333 C) 0.5 D) 0.6667 Answer: B Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 100) Using Table 12-6, what is the probability of no customers in the system? A) 0 B) 0.333 C) 0.5 D) 0.667 Answer: C Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 101) Using Table 12-6, what is the average number of customers in the coffee shop? A) 0.0833 B) 0.5 C) 0.75 D) 1.33 Answer: C Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. 237 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytical thinking Classification: Application 102) Using Table 12-6, what is the average number of customers waiting in line? A) 0.0833 B) 0.5 C) 0.75 D) 1.33 Answer: A Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 103) The school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the average time spent in the system? A) .0142 hour B) .1563 hour C) .0249 hour D) .2749 hour Answer: D Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 104) The school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the probability that 2 fax machines need toner at the same time? A) .8576 B) .1286 C) .0129 D) .1415 Answer: C Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with 238 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 239 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 105) A new shopping mall is considering setting up an information desk manned by one employee. Based upon information obtained from similar information desks, it is believed that people will arrive at the desk at the rate of 15 per hour. It takes an average of two minutes to answer a question. It is assumed that arrivals are Poisson and answer times are exponentially distributed. (a) Find the probability that the employee is idle. (b) Find the proportion of time that the employee is busy. (c) Find the average number of people receiving and waiting to receive information. (d) Find the average number of people waiting in line to get information. (e) Find the average time a person seeking information spends at the desk. (f) Find the expected time a person spends waiting in line to have his question answered. Answer: (a) Po = 0.50 (b) ρ = 0.50 (c) L = 1 (d) Lq = 0.50 (e) W = 0.0667 hour (f) Wq = 0.0333 hour Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 240 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 106) A new shopping mall is considering setting up an information desk manned by one employee. Based upon information obtained from similar information desks, it is believed that people will arrive at the desk at the rate of 15 per hour. It takes exactly two minutes to answer each question. It is assumed that arrivals are Poisson. (a) Find the probability that the employee is idle. (b) Find the proportion of time that the employee is busy. (c) Find the average number of people receiving and waiting to receive information. (d) Find the average number of people waiting in line to get information. (e) Find the average time a person seeking information spends at the desk. (f) Find the expected time a person spends waiting in line to have his question answered. Answer: (a) Po = 0.50 (b) ρ = 0.50 (c) L = 0.75 (d) Lq = 0.25 (e) W = 0.05 hour (f) Wq = 0.03 hour Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 241 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 107) Sam the Vet is running a rabies vaccination clinic for dogs at the local grade school. Sam can vaccinate a dog every 3 minutes. It is estimated that the dogs will arrive independently and randomly throughout the day at a rate of 1 dog every 6 minutes, according to a Poisson distribution. Also assume that Sam's vaccinating times are exponentially distributed. (a) Find the probability that Sam is idle. (b) Find the proportion of time that Sam is busy. (c) Find the average number of dogs receiving or waiting to be vaccinated. (d) Find the average number of dogs waiting to be vaccinated. (e) Find the average time a dog waits before getting vaccinated. (f) Find the average amount (mean) of time a dog spends between waiting in line and getting vaccinated. Answer: (a) Po = 0.5 (b) ρ = 0.5 (c) L = 1 (d) Lq = 0.5 (e) Wq = 0.05 hour (f) W = 0.1 hour Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 242 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 108) Sam the Vet is running a rabies vaccination clinic for dogs at the local grade school. Sam can vaccinate a dog every 3 minutes. It is estimated that the dogs will arrive independently and randomly throughout the day at a rate of 1 dog every 4 minutes, according to a Poisson distribution. Also assume that Sam's vaccinating times are exponentially distributed. (a) Find the probability that Sam is idle. (b) Find the proportion of time that Sam is busy. (c) Find the average number of dogs receiving or waiting to be vaccinated. (d) Find the average number of dogs waiting to be vaccinated. (e) Find the average time a dog waits before getting vaccinated. (f) Find the average amount (mean) of time a dog spends between waiting in line and getting vaccinated. Answer: a. Po = 0.25 b. ρ = 0.75 c. L = 3 d. Lq = 2.25 e. Wq = 0.15 hour f. W = 0.2 hour Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 109) A dry cleaner has a single drive-thru window for customers. The arrival rate of cars follows a Poisson distribution, while the service time follows an exponential distribution. The average arrival rate is 16 per hour and the average service time is three minutes. (a) What is the average number of cars in the line? (b) What is the average time spent waiting to get to the service window? (c) What percentage of time is the dry cleaner's drive-thru window idle? (d) What is the probability there are more than 2 cars at the drive-thru window? Answer: (a) Lq = 3.2 (b) Wq = 0.2 hour (12 minutes) (c) Po = 0.20 (d) Pn > k = 0.512 Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 243 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 110) A dry cleaner has a single drive-thru window for customers. The arrival rate of cars follows a Poisson distribution, while the service time follows an exponential distribution. The average arrival rate is 16 per hour and the average service time is three minutes. If the dry cleaner wants to accommodate (have enough room for) all of the waiting cars at least 96 percent of the time, how many car-lengths should they make the driveway leading to the window? Answer: The probability of having more than 14 cars in the system is (16/20)14 + 1 = 0.035, so they should make the driveway approximately 13 car-lengths long (because one car will be at the service window). (The probability of having more than 13 cars in the system is 0.044 (which is too high), and the percentage only gets worse as the queue length is shortened.) Diff: Difficult Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 111) Sam the Vet is running a rabies vaccination clinic for dogs at the local grade school. Sam can vaccinate a dog every 3 minutes. It is estimated that the dogs will arrive independently and randomly throughout the day at a rate of 1 dog every 6 minutes, according to a Poisson distribution. Also assume that Sam's vaccinating times are exponentially distributed. Sam would like to have each waiting dog placed in a holding pen. If Sam wants to be certain he has enough cages to accommodate all dogs at least 90 percent of the time, how many cages should he prepare? Answer: He needs to prepare 2 cages. The probability of having more than 3 dogs in the system is 0.0625 while the probability of having more than 2 dogs in the system is 0.125. Diff: Difficult Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 244 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 112) A new shopping mall is considering setting up an information desk operated by two employees. Based on information obtained from similar information desks, it is believed that people will arrive at the desk at the rate of 20 per hour. It takes an average of 4 minutes to answer a question. It is assumed that arrivals are Poisson and answer times are exponentially distributed. (a) Find the proportion of the time that the employees are busy. (b) Find the average number of people waiting in line to get some information. (c) Find the expected time a person spends just waiting in line to have his question answered. Answer: (a) ρ = 0.667 (b) Lq = 1.0667 (c) Wq = 0.0533 hour Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 113) Cars arrive at a parking lot entrance at the rate of 20 per hour. The average time to get a ticket and proceed to a parking space is two minutes. There are two lot attendants at the current time. The Poisson and exponential distribution appear to be relevant in this situation. (a) What is the probability that an approaching auto must wait? (b) What is the average waiting time? (c) What is the average number of autos waiting to enter the garage? Answer: (a) Po = 0.50 (b) Wq = 0.25 minute (c) Lq = 0.0833 auto Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 245 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 114) Bank Boston has a branch at Bryant College. The branch is busiest at the beginning of the college year when freshmen and transfer students open accounts. This year, freshmen arrived at the office at a rate of 40 per day (8-hour day). On average, it takes the Bank Boston staff person about ten minutes to process each account application. The bank is considering having one or two tellers. Each teller is paid $12 per hour and the cost of waiting in line is assumed to be $8 per hour. (a) What is the total daily waiting cost for the single teller model? (b) What is the total daily waiting cost for the two-teller model? (c) What is the total daily service cost for the single teller model? (d) What is the total daily service cost for the two-teller model? (e) Which model is preferred? Answer: (a) Total wait cost = [(5 * .833 hours) (8)] * 8 hours/day = $266.56 (b) Total wait cost = [(5 * .035 hours) (8)] * 8 hours/day = $11.20 (c) Total service cost = (1 * $12) * 8 hours/day = $96 (d) Total service cost = (2 * $12) * 8 hours/day = $192 (e) Two channel model Diff: Difficult Topic: VARIOUS LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 246 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 115) At the start of football season, the ticket office gets busy the day before the first game. Customers arrive at the rate of four every ten minutes. A ticket seller can service a customer in four minutes. Traditionally, there are two ticket sellers working. The university is considering an automated ticket machine similar to the airlines' e-ticket system. The automated ticket machine can service a customer in 2 minutes. (a) What is the average length of the queue for the in-person model? (b) What is the average length of the queue for the automated system model? (c) What is the average time in the system for the in-person model? (d) What is the average time in the system for the automated system model? (e) Assume the ticket sellers earn $8 per hour and the machine costs $20 per hour (amortized over 5 years). The wait time is only $4 per hour because students are patient. What is the total cost of each model? Answer: (a) Lq = 2.844 (b) Lq = 1.6 (c) W = 0.1852 hour or 11.11 minutes (d) W = 0.1 hour or 6 minutes (e) Total cost (in-person) = (2 ∗ $8/hour) + (24/hour ∗ .1852 hours) ($4/hour) = $33.78 Total cost (automated) = (1 ∗ $20/hour) + (24/hour ∗ .1 hour) ($4/hour) = $29.60 Diff: Difficult Topic: VARIOUS LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 116) Consider a single-server queuing system with Poisson arrivals of 10 units per hour and a constant service time of 2 minutes per unit. How long will the customer waiting time be in seconds, on average? Answer: 10 / [(2)(30)(30 − 10)] = .00833333 hours = 0.5 minute = 30 seconds Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 247 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 117) There is a tutoring lab at a university that holds 20 students. Due to the popularity of the 3 tutors, the lab is always at capacity. Each student approaches a tutor an average of 2 times per hour, and a tutor spends on average 5 minutes per question from a student. The service time follows an exponential distribution. (a) What proportion of the time are the tutors busy? (b) What is the average waiting time for students in queue? Answer: (a) ρ = 0.86 (b) Wq = 0.06 hour Diff: Moderate Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 118) A professor decides to hold a three-hour window open for student advising. The professor has 15 advisees. He's unsure if each advisee will show up, and it's possible that a single advisee could show up multiple times during the 3-hour window. On average, the professor will spend 12 minutes with each student. He usually expects each student to arrive once during the 3-hour window. (a) What proportion of the time can the professor expect to be busy during the window? (b) What is the expected number of students in queue during the window? (c) What is the expected wait time in queue during the window? Answer: (a) ρ = 0.82 (b) Lq = 1.88 (c) Wq = 0.46 hour Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 248 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 119) Customers arrive at a bank at a rate of one every minute. The bank has 3 tellers and on average, it takes two minutes to service a customer. (a) What proportion of time are the tellers busy? (b) What is the average number of customers in the bank? (c) What is the average weight time? Answer: (a) ρ = 0.67 (b) L = 2.89 (c) Wq = 0.01 hour = 0.89 minutes = 53.33 seconds Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 120) Customers arrive at their friendly DMV at a rate of 45 people per hour. There are four servers that can process customers at an average of 3 minutes. (a) What is the average wait time? (b) What is the average number of customers waiting? (c) What is the average number of customers in the DMV? Answer: (a) Wq = 0.01 hours = .41 minutes = 24.81 seconds (b) Lq = 0.31 customers (c) L = 2.56 Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 121) What is meant by a single-channel queuing system? Answer: one service facility system fed by one queue Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 249 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 122) What is meant by a multichannel queuing system? Answer: more than one service facility all fed by the same queue Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 123) What is meant by a single-phase system? Answer: Arrivals leave the system after receiving service at only one station. Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 124) What is meant by a multiphase system? Answer: Service is provided at more than one station, one after the other. Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 125) What is the difference between customers balking and customers reneging? If you managed a retail store how would you track and differentiate between customers that balked and reneged? Answer: Balking occurs when customers decline to join the queue, typically because they see the line is too long and they don't have enough time. Reneging occurs when customers join the queue and change their mind later and depart the queue. Answers will vary as to how they can be tracked. It may be easier to track those that renege if some part of the service process has already begun and customer information is recorded. Alternatively, security camera footage could be checked at the end of each day to see the number that joined a line and then left. Balking would probably be tougher to capture in most situations. Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 250 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 126) What is the difference between a transient state and a steady state? How could you as a manager distinguish between the two? Answer: A steady state is the normal operating condition of the queuing system. A queuing system is in a transient state before the steady state is reached. A manager would expect to be in a transient state at opening time each day or after a holiday and be in steady state during most operating hours if most queuing analysis assumptions are reasonable. For pure customer service situations, there may be additional transient periods of the day, for example, a lunch or dinner rush at a restaurant. Diff: Moderate Topic: SOME GENERAL OPERATING CHARACTERISTIC RELATIONSHIPS LO: 12.7: Understand Little's Flow Equations. AACSB: Analytical thinking Classification: Concept 127) Four thousand students are admitted each year at a large regional university. The average time to complete a degree is six years and the university's retention rate initiative achieves 100% (no students drop out or transfer). What is the student population? Answer: 24,000 students; L = λW = 4000 students/year × 6 years Diff: Easy Topic: SOME GENERAL OPERATING CHARACTERISTIC RELATIONSHIPS LO: 12.7: Understand Little's Flow Equations. AACSB: Analytical thinking Quantitative Analysis for Management, 13e (Render et al.) Chapter 13 Waiting Lines and Queuing Theory Models 33) Assume that we are using a waiting line model to analyze the number of service technicians required to maintain machines in a factory. Our goal should be to A) minimize the number of machines needing repair. B) minimize the downtime for individual machines. C) minimize the percent of idle time of the technicians. D) minimize the total cost (cost of maintenance plus cost of downtime). Answer: D Diff: Moderate Topic: WAITING LINE COSTS LO: 12.1: Describe the trade-off curves for cost of waiting time and cost of service. AACSB: Analytical thinking Classification: Concept 34) In queuing analysis, total expected cost is the sum of expected ________ plus expected ________. A) service costs, arrival costs B) facility costs, calling costs C) calling costs, waiting costs D) service costs, waiting costs 251 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Answer: D Diff: Easy Topic: WAITING LINE COSTS LO: 12.1: Describe the trade-off curves for cost of waiting time and cost of service. AACSB: Analytical thinking Classification: Concept 252 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 35) In queuing theory, the calling population is another name for A) the queue size. B) the servers. C) the arrivals. D) the service rate. Answer: C Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 36) An arrival in a queue that reneges is one who A) after joining the queue, becomes impatient and leaves. B) refuses to join the queue because it is too long. C) goes through the queue, but never returns. D) jumps from one queue to another, trying to get through as quickly as possible. Answer: A Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 37) The customer who arrives at a bank, sees a long line, and leaves to return another time is A) balking. B) cropping. C) reneging. D) blithering. Answer: A Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 253 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 38) The customer who arrives at a bank, enters a line, and decides to leave is A) balking. B) cropping. C) reneging. D) blithering. Answer: C Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 39) The three major characteristics of the input source that generates arrivals or customers for the service system are A) size, demographics, and behavior. B) size, pattern, and behavior. C) demographics, pattern, and behavior. D) size, demographics, and pattern. Answer: B Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 40) The term queue "discipline" describes the A) degree to which members of the queue renege. B) sequence in which members of the queue arrived. C) degree to which members of the queue are orderly and quiet. D) sequence in which members of the queue are serviced. Answer: D Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 254 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 41) A vendor selling newspapers on a street corner is an example of a A) single-channel, multiphase system. B) single-channel, single-phase system. C) multichannel, multiphase system. D) multichannel, single-phase system. Answer: B Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 42) Lines at banks where customers wait for a teller window are usually representative of a A) single-channel, multiphase system. B) single-channel, single-phase system. C) multichannel, multiphase system. D) multichannel, single-phase system. Answer: D Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 43) Which of the following distributions is most often used to estimate the arrival pattern? A) negative exponential B) normal C) Poisson D) Erlang Answer: C Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 255 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 44) A single automatic car wash with one bay and a cycle time of 2.5 minutes is what type of model? A) M/M/1 B) M/M/2 C) M/D/2 D) M/D/1 Answer: D Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 45) A single automatic car wash with one bay and a service time that is normally distributed is what type of model? A) M/M/1 B) M/D/2 C) M/D/1 D) M/G/1 Answer: D Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 46) A suburban specialty restaurant has developed a single drive-thru window. Customers order, pay, and pick up their food at the same window. Arrivals follow a Poisson distribution, while service times follow an exponential distribution. What type of queuing model is exhibited in this problem? A) M/M/1 B) M/M/2 C) M/D/2 D) M/D/1 Answer: D Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Concept 256 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 47) A professor holds office hours during final exam week and discovers much to his dismay that his sudden popularity affords him little time to engage in his favorite activity, watching cat videos. Fifteen students per hour arrive at his office and he patiently answers questions, averaging three minutes per student. If the average cat video is 60 seconds, how many videos can the professor watch in an hour? A) 15 B) 18 C) 20 D) 24 Answer: A Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 48) A professor holds office hours during final exam week and discovers much to his dismay that his sudden popularity affords him little time to engage in his favorite activity, watching cat videos. Fifteen students per hour arrive at his office and he patiently answers questions, averaging three minutes per student. On average, how many students are waiting to ask questions? A) 2.00 B) 2.25 C) 2.50 D) 2.75 Answer: B Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 257 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 49) A professor holds office hours during final exam week and discovers much to his dismay that his sudden popularity affords him little time to engage in his favorite activity, watching cat videos. Fifteen students per hour arrive at his office and he patiently answers questions, averaging three minutes per student. On average, how long must a student wait in line to get their last-minute questions answered? A) 3 minutes B) 6 minutes C) 9 minutes D) 12 minutes Answer: C Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 50) A professor holds office hours during final exam week and discovers much to his dismay that his sudden popularity affords him little time to engage in his favorite activity, watching cat videos. Fifteen students per hour arrive at his office and he patiently answers questions, averaging three minutes per student. A student joins the line at 9:45 am and the test is at 10:00 am the same morning. How much time does the student have after getting his question answered to get to the exam room? A) 12 minutes B) 9 minutes C) 6 minutes D) 3 minutes Answer: D Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 258 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 51) Customers enter the waiting line at a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is four per minute and the average service rate of a single server is seven per minute, what is the average number of customers in the system? A) 0.43 B) 1.67 C) 0.57 D) 1.33 Answer: D Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 52) Customers enter the waiting line at a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is four per minute and the average service rate of a single server is seven per minute, what is the average number of customers waiting in line behind the person being served? A) 0.76 B) 0.19 C) 1.33 D) 1.67 Answer: A Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 259 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 53) Customers enter the waiting line to pay for food as they leave a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is four per minute and the average service rate of a single server is seven per minute, what proportion of the time is the server busy? A) 0.43 B) 0.57 C) 0.75 D) 0.25 Answer: B Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 54) Customers enter the waiting line to pay for food as they leave a cafeteria on a first-come, first-served basis. The arrival rate follows a Poisson distribution, while service times follow an exponential distribution. If the average number of arrivals is four per minute and the average service rate of a single server is seven per minute, on average, how much time will elapse from the time a customer enters the line until he/she leaves the cafeteria? A) 0.67 minute B) 0.50 minute C) 0.75 minute D) 0.33 minute Answer: D Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 260 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 55) At a local fast-food joint, cars arrive randomly at a rate of 12 every 30 minutes. The fast food joint takes an average of 2 minutes to serve each arrival. The utilization factor for this system is A) 0.467. B) 0.547. C) 0.800. D) 0.133. Answer: C Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 56) At a local fast food joint, cars arrive randomly at a rate of 12 every 30 minutes. Service times are random (exponential) and average 2 minutes per arrival. The average time in the queue for each arrival is A) 2 minutes. B) 4 minutes. C) 6 minutes. D) 8 minutes. Answer: D Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 57) Which of the following distributions is most often used to estimate service times? A) negative exponential B) normal C) Poisson D) Erlang Answer: A Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 261 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 58) Most systems use a queue discipline known as A) shortest processing time. B) longest processing time. C) FIFO. D) earliest due date. Answer: C Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 59) A queuing system with a normally distributed arrival pattern, exponential service times, and three servers would be described as A) G/G/3. B) M/M/3. C) G/M/3. D) M/G/3. Answer: C Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 60) The initial state of a queuing system (for example, when a restaurant first opens), is referred to as the ________ state. A) steady B) primary C) introductory D) transient Answer: D Diff: Moderate Topic: SOME GENERAL OPERATING CHARACTERISTIC RELATIONSHIPS LO: 12.7: Understand Little's Flow Equations. AACSB: Analytical thinking Classification: Concept 262 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 61) A post office has a single line for customers waiting for the next available postal clerk. There are two postal clerks who work at the same rate. The arrival rate of customers follows a Poisson distribution, while the service time follows an exponential distribution. What type of queuing model applies here? A) M/M/1 B) M/M/2 C) M/D/2 D) M/D/1 Answer: B Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 62) A post office has a single line for customers waiting for the next available postal clerk. There are two postal clerks who work at the same rate. The arrival rate of customers follows a Poisson distribution, while the service time follows a normal distribution. What type of queuing model applies here? A) M/M/2 B) M/D/2 C) M/D/1 D) M/G/2 Answer: D Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 263 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 63) A post office has a single line for customers waiting for the next available postal clerk. There are two postal clerks who work at the same rate. The arrival rate of customers follows a Poisson distribution, while the service time follows an exponential distribution. The average arrival rate is three per minute and the average service rate is two per minute for each of the two clerks. What is the average length of the line? A) 3.429 B) 1.929 C) 1.143 D) 0.643 Answer: B Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 64) A post office has a single line for customers waiting for the next available postal clerk. There are two postal clerks who work at the same rate. The arrival rate of customers follows a Poisson distribution, while the service time follows an exponential distribution. The average arrival rate is three per minute and the average service rate is two per minute for each of the two clerks. How long does the average person spend waiting for a clerk? A) 3.429 minutes B) 1.929 minutes C) 1.143 minutes D) 0.643 minute Answer: D Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 264 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 65) A post office has a single line for customers waiting for the next available postal clerk. There are two postal clerks who work at the same rate. The arrival rate of customers follows a Poisson distribution, while the service time follows an exponential distribution. The average arrival rate is three per minute and the average service rate is two per minute for each of the two clerks. What proportion of time are both clerks idle? A) 0.643 B) 0.250 C) 0.750 D) 0.143 Answer: B Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application Table 12-1 M/M/2 Mean Arrival Rate: Mean Service Rate: Number of Servers: Server wage Customer waiting cost Probability of zero customers in system: 20 customers/hour 12 customers/hour 2 $10/hour $20/hour 0.280 66) According to the information provided in Table 12-1, on average, how many customers are in the line? A) 3.79 B) 3.33 C) 4.25 D) 4.33 Answer: A Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 265 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 67) According to the information provided in Table 12-1, how long does a customer wait on average? A) 11 minutes B) 11 minutes 30 seconds C) 12 minutes 15 seconds D) 12 minutes 45 seconds Answer: B Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 68) Using the information provided in Table 12-1, counting each person being served and the people in line, on average, how many customers would be in this system? A) 4.85 B) 5.05 C) 5.45 D) 6.15 Answer: C Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 69) According to the information provided in Table 12-1, what is the hourly total cost of the system for customers and servers? Assume that servers are paid only when they are helping customers. A) $117.67 B) $121.47 C) $129.09 D) $125.76 Answer: D Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 266 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 70) According to the information provided in Table 12-1, what percentage of the total available service time is being used? A) 83.0% B) 87.0% C) 78.3% D) 60.0% Answer: A Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 71) According to the information provided in Table 12-1, what is the average amount of time a customer waits and is served? A) 15 minutes 40 seconds B) 16 minutes 20 seconds C) 17 minutes D) 17 minutes 40 seconds Answer: B Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 267 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 12-2 M/M/2 Mean Arrival Rate: Mean Service Rate: Number of Servers: 5 occurrences per minute 3 occurrences per minute 2 Queue Statistics: Mean Number of Units in the System: Mean Number of Units in the Queue: Mean Time in the System: Mean Time in the Queue: Service Facility Utilization Factor: Probability in No Units in System: 5.455 3.788 1.091 minutes 0.758 minutes 0.833 0.091 72) According to the information provided in Table 12-2, which presents a queuing problem solution, on average, how many units are in the line? A) 5.455 B) 3.788 C) 1.091 D) 0.758 E) 0.833 Answer: B Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 73) According to the information provided in Table 12-2, which presents a queuing problem solution, what proportion of time is at least one server busy? A) 0.833 B) 0.758 C) 0.091 D) 0.909 Answer: D Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking 268 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Classification: Application 269 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 74) According to the information provided in Table 12-2, which presents a queuing problem solution, there are two servers in this system. Counting each person being served and the people in line, on average, how many people would be in this system? A) 5.455 B) 3.788 C) 9.243 D) 10.900 Answer: A Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application Table 12-3 M/M/3 Mean Arrival Rate: Mean Service Rate: Number of Servers: 4 occurrences per minute 2 occurrences per minute 3 Queue Statistics: Mean Number of Units in the System: Mean Number of Units in the Queue: Mean Time in the System: Mean Time in the Queue: Service Facility Utilization Factor: Probability in No Units in System: 2.889 0.889 0.722 minutes 0.222 minutes 0.667 0.111 75) According to the information provided in Table 12-3, which presents a queuing problem solution, what proportion of time is the system totally empty? A) 0.111 B) 0.333 C) 0.889 D) 0.667 Answer: A Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking 270 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Classification: Application 271 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 76) According to the information provided in Table 12-3, which presents a queuing problem solution, on average, how long does each customer spend waiting in line? A) 0.333 minute B) 0.889 minute C) 0.222 minute D) 0.722 minute Answer: C Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 77) According to the information provided in Table 12-3, which presents a queuing problem solution, what is the utilization rate of the service facility? A) 0.889 B) 0.222 C) 0.722 D) 0.667 Answer: D Diff: Easy Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 78) If everything else remains constant, including the mean arrival rate and service rate, except that the service time becomes constant instead of exponential A) the average queue length will be halved. B) the average waiting time will be doubled. C) the average queue length will be doubled. D) There is not enough information to know what will happen to the queue length and waiting time. Answer: A Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 272 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 79) At an automatic car wash, cars arrive randomly at a rate of 7 cars every 30 minutes. The car wash takes exactly 4 minutes (this is constant). On average, what would be the length of the line? A) 8.171 B) 7.467 C) 6.53 D) 0.467 Answer: C Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 80) At an automatic car wash, cars arrive randomly at a rate of 7 every 30 minutes. The car wash takes exactly 4 minutes (this is constant). On average, how long would each car spend at the car wash? A) 28 minutes B) 32 minutes C) 17 minutes D) 24 minutes Answer: B Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 81) At an automatic car wash, cars arrive randomly at a rate of 7 every 30 minutes. The car wash takes exactly 4 minutes (this is constant). On average, how long would each driver have to wait before receiving service? A) 28 minutes B) 32 minutes C) 17 minutes D) 24 minutes Answer: A Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 273 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 82) At an automatic car wash, cars arrive randomly at a rate of 7 every 30 minutes. The car wash takes exactly 4 minutes (this is constant). On average, how many customers would be at the car wash (waiting in line or being serviced)? A) 8.17 B) 7.46 C) 6.53 D) 0.46 Answer: B Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 83) At a local fast food joint, cars arrive randomly at a rate of 12 every 30 minutes. The fast food joint takes exactly 2 minutes (this is constant). The average total time in the system is A) 5.4 minutes. B) 6.0 minutes. C) 8.0 minutes. D) 2.5 minutes. Answer: B Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 274 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 12-4 The sentient car wash in Luther knows she is in for a busy day when dawn breaks on a gorgeous spring morning. She is capable of washing a car every four minutes, and by the looks of things, it is reasonable to expect a steady stream of twelve cars per hour arriving. Because she is fully automatic, she knows that the four-minute estimate is accurate and invariant. She values her time at $10 per hour. Yes, it seems low, but as a single bay car wash, there are few other jobs in town she is qualified for. (We won't get into her unsuccessful turn at the beauty salon.) She estimates that customer time can be valued at $15 per hour. 84) According to the information provided in Table 12-4, how much time will the average customer spend waiting in line? A) 8 minutes B) 9 minutes C) 10 minute D) 11 minute Answer: A Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 85) According to the information provided in Table 12-4, on average, how many customers are in line? A) 1.2 cars B) 1.6 cars C) 1.75 cars D) 2.1 cars Answer: B Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 275 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 86) According to the information provided in Table 12-4, how many minutes per hour will the car wash be idle and able to ponder the meaning of life? A) 9 minutes B) 10 minutes C) 12 minutes D) 15 minutes Answer: C Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 87) According to Table 12-4, what is the total hourly cost of the system for customers and the car wash herself? Assume the car wash is paid only when she is washing cars. A) $38 B) $40 C) $42 D) $44 Answer: D Diff: Difficult Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 88) According to Table 12-4, what is the total number of cars in the system? A) 2.40 B) 2.75 C) 3.10 D) 3.45 Answer: A Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 276 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 12-5 M/D/1 Mean Arrival Rate: Constant Service Rate: 5 occurrences per minute 7 occurrences per minute Queue Statistics: Mean Number of Units in the System: Mean Number of Units in the Queue: Mean Time in the System: Mean Time in the Queue: Service Facility Utilization Factor: 1.607 0.893 0.321 minutes 0.179 minutes 0.714 89) According to the information provided in Table 12-5, which presents the solution for a queuing problem with a constant service rate, on average, how much time is spent waiting in line? A) 1.607 minutes B) 0.714 minute C) 0.179 minute D) 0.893 minute Answer: C Diff: Easy Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 90) According to the information provided in Table 12-5, which presents the solution for a queuing problem with a constant service rate, on average, how many customers are in the system? A) 0.893 B) 0.714 C) 1.607 D) 0.375 Answer: C Diff: Easy Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 277 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 91) According to the information provided in Table 12-5, which presents a queuing problem solution for a queuing problem with a constant service rate, on average, how many customers arrive per time period? A) 5 B) 7 C) 1.607 D) 0.893 Answer: A Diff: Easy Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 92) According to the information provided in Table 12-5, which presents the solution for a queuing problem with a constant service rate, on average, how many minutes does a customer spend in the system? A) 0.893 minute B) 0.321 minute C) 0.714 minute D) 1.607 minutes Answer: B Diff: Easy Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 93) According to the information provided in Table 12-5, which presents the solution for a queuing problem with a constant service rate, the probability that the server is idle is A) 0.217. B) 0.643. C) 0.286. D) 0.714. Answer: C Diff: Easy Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 278 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 94) Thanks to a generous and eccentric donor, the school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the probability that none of the fax machines need toner? A) 1.1500 B) 1.1658 C) .8578 D) .7696 Answer: C Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 95) Thanks to a generous and eccentric donor, the school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the average number of fax machines in the queue? A) 0.5658 fax machines B) 0.3304 fax machines C) .0563 fax machine D) .0142 fax machine Answer: D Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 96) Thanks to a generous and eccentric donor, the school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the average number of fax machines in the system? A) .0142 fax machine B) .1563 fax machine C) .0249 fax machine D) .2749 fax machine Answer: B Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with 279 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 97) Thanks to a generous and eccentric donor, the school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the average waiting time in the queue? A) .0142 hour B) .1563 hour C) .0249 hour D) .2749 hour Answer: C Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 98) Thanks to a generous and eccentric donor, the school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the probability that one of the fax machines needs toner? A) 0.22 B) 0.19 C) 0.16 D) 0.13 Answer: D Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 280 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall Table 12-6 Customers arrive at coffee shop at a rate of 40 per hour. There are 2 servers available and it takes an average of 1 minute to serve each customer. 99) Using Table 12-6, what proportion of time are the servers busy? A) 0 B) 0.333 C) 0.5 D) 0.6667 Answer: B Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 100) Using Table 12-6, what is the probability of no customers in the system? A) 0 B) 0.333 C) 0.5 D) 0.667 Answer: C Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 101) Using Table 12-6, what is the average number of customers in the coffee shop? A) 0.0833 B) 0.5 C) 0.75 D) 1.33 Answer: C Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. 281 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall AACSB: Analytical thinking Classification: Application 102) Using Table 12-6, what is the average number of customers waiting in line? A) 0.0833 B) 0.5 C) 0.75 D) 1.33 Answer: A Diff: Moderate Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 103) The school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the average time spent in the system? A) .0142 hour B) .1563 hour C) .0249 hour D) .2749 hour Answer: D Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 104) The school of business has 3 fax machines. The toner in each machine needs to be changed after about 5 hours of use. There is one unit secretary who is responsible for the fax machine maintenance. It takes him 15 minutes to replace the toner cartridge. What is the probability that 2 fax machines need toner at the same time? A) .8576 B) .1286 C) .0129 D) .1415 Answer: C Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with 282 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 283 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 105) A new shopping mall is considering setting up an information desk manned by one employee. Based upon information obtained from similar information desks, it is believed that people will arrive at the desk at the rate of 15 per hour. It takes an average of two minutes to answer a question. It is assumed that arrivals are Poisson and answer times are exponentially distributed. (a) Find the probability that the employee is idle. (b) Find the proportion of time that the employee is busy. (c) Find the average number of people receiving and waiting to receive information. (d) Find the average number of people waiting in line to get information. (e) Find the average time a person seeking information spends at the desk. (f) Find the expected time a person spends waiting in line to have his question answered. Answer: (a) Po = 0.50 (b) ρ = 0.50 (c) L = 1 (d) Lq = 0.50 (e) W = 0.0667 hour (f) Wq = 0.0333 hour Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 284 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 106) A new shopping mall is considering setting up an information desk manned by one employee. Based upon information obtained from similar information desks, it is believed that people will arrive at the desk at the rate of 15 per hour. It takes exactly two minutes to answer each question. It is assumed that arrivals are Poisson. (a) Find the probability that the employee is idle. (b) Find the proportion of time that the employee is busy. (c) Find the average number of people receiving and waiting to receive information. (d) Find the average number of people waiting in line to get information. (e) Find the average time a person seeking information spends at the desk. (f) Find the expected time a person spends waiting in line to have his question answered. Answer: (a) Po = 0.50 (b) ρ = 0.50 (c) L = 0.75 (d) Lq = 0.25 (e) W = 0.05 hour (f) Wq = 0.03 hour Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 285 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 107) Sam the Vet is running a rabies vaccination clinic for dogs at the local grade school. Sam can vaccinate a dog every 3 minutes. It is estimated that the dogs will arrive independently and randomly throughout the day at a rate of 1 dog every 6 minutes, according to a Poisson distribution. Also assume that Sam's vaccinating times are exponentially distributed. (a) Find the probability that Sam is idle. (b) Find the proportion of time that Sam is busy. (c) Find the average number of dogs receiving or waiting to be vaccinated. (d) Find the average number of dogs waiting to be vaccinated. (e) Find the average time a dog waits before getting vaccinated. (f) Find the average amount (mean) of time a dog spends between waiting in line and getting vaccinated. Answer: (a) Po = 0.5 (b) ρ = 0.5 (c) L = 1 (d) Lq = 0.5 (e) Wq = 0.05 hour (f) W = 0.1 hour Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 286 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 108) Sam the Vet is running a rabies vaccination clinic for dogs at the local grade school. Sam can vaccinate a dog every 3 minutes. It is estimated that the dogs will arrive independently and randomly throughout the day at a rate of 1 dog every 4 minutes, according to a Poisson distribution. Also assume that Sam's vaccinating times are exponentially distributed. (a) Find the probability that Sam is idle. (b) Find the proportion of time that Sam is busy. (c) Find the average number of dogs receiving or waiting to be vaccinated. (d) Find the average number of dogs waiting to be vaccinated. (e) Find the average time a dog waits before getting vaccinated. (f) Find the average amount (mean) of time a dog spends between waiting in line and getting vaccinated. Answer: a. Po = 0.25 b. ρ = 0.75 c. L = 3 d. Lq = 2.25 e. Wq = 0.15 hour f. W = 0.2 hour Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 109) A dry cleaner has a single drive-thru window for customers. The arrival rate of cars follows a Poisson distribution, while the service time follows an exponential distribution. The average arrival rate is 16 per hour and the average service time is three minutes. (a) What is the average number of cars in the line? (b) What is the average time spent waiting to get to the service window? (c) What percentage of time is the dry cleaner's drive-thru window idle? (d) What is the probability there are more than 2 cars at the drive-thru window? Answer: (a) Lq = 3.2 (b) Wq = 0.2 hour (12 minutes) (c) Po = 0.20 (d) Pn > k = 0.512 Diff: Moderate Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 287 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 110) A dry cleaner has a single drive-thru window for customers. The arrival rate of cars follows a Poisson distribution, while the service time follows an exponential distribution. The average arrival rate is 16 per hour and the average service time is three minutes. If the dry cleaner wants to accommodate (have enough room for) all of the waiting cars at least 96 percent of the time, how many car-lengths should they make the driveway leading to the window? Answer: The probability of having more than 14 cars in the system is (16/20)14 + 1 = 0.035, so they should make the driveway approximately 13 car-lengths long (because one car will be at the service window). (The probability of having more than 13 cars in the system is 0.044 (which is too high), and the percentage only gets worse as the queue length is shortened.) Diff: Difficult Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 111) Sam the Vet is running a rabies vaccination clinic for dogs at the local grade school. Sam can vaccinate a dog every 3 minutes. It is estimated that the dogs will arrive independently and randomly throughout the day at a rate of 1 dog every 6 minutes, according to a Poisson distribution. Also assume that Sam's vaccinating times are exponentially distributed. Sam would like to have each waiting dog placed in a holding pen. If Sam wants to be certain he has enough cages to accommodate all dogs at least 90 percent of the time, how many cages should he prepare? Answer: He needs to prepare 2 cages. The probability of having more than 3 dogs in the system is 0.0625 while the probability of having more than 2 dogs in the system is 0.125. Diff: Difficult Topic: SINGLE-CHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/1) LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 288 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 112) A new shopping mall is considering setting up an information desk operated by two employees. Based on information obtained from similar information desks, it is believed that people will arrive at the desk at the rate of 20 per hour. It takes an average of 4 minutes to answer a question. It is assumed that arrivals are Poisson and answer times are exponentially distributed. (a) Find the proportion of the time that the employees are busy. (b) Find the average number of people waiting in line to get some information. (c) Find the expected time a person spends just waiting in line to have his question answered. Answer: (a) ρ = 0.667 (b) Lq = 1.0667 (c) Wq = 0.0533 hour Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 113) Cars arrive at a parking lot entrance at the rate of 20 per hour. The average time to get a ticket and proceed to a parking space is two minutes. There are two lot attendants at the current time. The Poisson and exponential distribution appear to be relevant in this situation. (a) What is the probability that an approaching auto must wait? (b) What is the average waiting time? (c) What is the average number of autos waiting to enter the garage? Answer: (a) Po = 0.50 (b) Wq = 0.25 minute (c) Lq = 0.0833 auto Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 289 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 114) Bank Boston has a branch at Bryant College. The branch is busiest at the beginning of the college year when freshmen and transfer students open accounts. This year, freshmen arrived at the office at a rate of 40 per day (8-hour day). On average, it takes the Bank Boston staff person about ten minutes to process each account application. The bank is considering having one or two tellers. Each teller is paid $12 per hour and the cost of waiting in line is assumed to be $8 per hour. (a) What is the total daily waiting cost for the single teller model? (b) What is the total daily waiting cost for the two-teller model? (c) What is the total daily service cost for the single teller model? (d) What is the total daily service cost for the two-teller model? (e) Which model is preferred? Answer: (a) Total wait cost = [(5 * .833 hours) (8)] * 8 hours/day = $266.56 (b) Total wait cost = [(5 * .035 hours) (8)] * 8 hours/day = $11.20 (c) Total service cost = (1 * $12) * 8 hours/day = $96 (d) Total service cost = (2 * $12) * 8 hours/day = $192 (e) Two channel model Diff: Difficult Topic: VARIOUS LO: 12.3: Analyze a variety of operating characteristics of waiting lines for single channel models with exponential service times and infinite calling populations. 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 290 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 115) At the start of football season, the ticket office gets busy the day before the first game. Customers arrive at the rate of four every ten minutes. A ticket seller can service a customer in four minutes. Traditionally, there are two ticket sellers working. The university is considering an automated ticket machine similar to the airlines' e-ticket system. The automated ticket machine can service a customer in 2 minutes. (a) What is the average length of the queue for the in-person model? (b) What is the average length of the queue for the automated system model? (c) What is the average time in the system for the in-person model? (d) What is the average time in the system for the automated system model? (e) Assume the ticket sellers earn $8 per hour and the machine costs $20 per hour (amortized over 5 years). The wait time is only $4 per hour because students are patient. What is the total cost of each model? Answer: (a) Lq = 2.844 (b) Lq = 1.6 (c) W = 0.1852 hour or 11.11 minutes (d) W = 0.1 hour or 6 minutes (e) Total cost (in-person) = (2 ∗ $8/hour) + (24/hour ∗ .1852 hours) ($4/hour) = $33.78 Total cost (automated) = (1 ∗ $20/hour) + (24/hour ∗ .1 hour) ($4/hour) = $29.60 Diff: Difficult Topic: VARIOUS LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 116) Consider a single-server queuing system with Poisson arrivals of 10 units per hour and a constant service time of 2 minutes per unit. How long will the customer waiting time be in seconds, on average? Answer: 10 / [(2)(30)(30 − 10)] = .00833333 hours = 0.5 minute = 30 seconds Diff: Moderate Topic: CONSTANT SERVICE TIME MODEL (M/D/1) LO: 12.5 Analyze a variety of operating characteristics of waiting lines for single channel models with deterministic service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 291 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 117) There is a tutoring lab at a university that holds 20 students. Due to the popularity of the 3 tutors, the lab is always at capacity. Each student approaches a tutor an average of 2 times per hour, and a tutor spends on average 5 minutes per question from a student. The service time follows an exponential distribution. (a) What proportion of the time are the tutors busy? (b) What is the average waiting time for students in queue? Answer: (a) ρ = 0.86 (b) Wq = 0.06 hour Diff: Moderate Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 118) A professor decides to hold a three-hour window open for student advising. The professor has 15 advisees. He's unsure if each advisee will show up, and it's possible that a single advisee could show up multiple times during the 3-hour window. On average, the professor will spend 12 minutes with each student. He usually expects each student to arrive once during the 3-hour window. (a) What proportion of the time can the professor expect to be busy during the window? (b) What is the expected number of students in queue during the window? (c) What is the expected wait time in queue during the window? Answer: (a) ρ = 0.82 (b) Lq = 1.88 (c) Wq = 0.46 hour Diff: Difficult Topic: FINITE POPULATION MODEL (M/M/1 WITH FINITE SOURCE) LO: 12.6: Analyze a variety of operating characteristics of waiting lines for single channel model with exponential service times and finite calling populations. AACSB: Analytical thinking Classification: Application 292 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 119) Customers arrive at a bank at a rate of one every minute. The bank has 3 tellers and on average, it takes two minutes to service a customer. (a) What proportion of time are the tellers busy? (b) What is the average number of customers in the bank? (c) What is the average weight time? Answer: (a) ρ = 0.67 (b) L = 2.89 (c) Wq = 0.01 hour = 0.89 minutes = 53.33 seconds Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 120) Customers arrive at their friendly DMV at a rate of 45 people per hour. There are four servers that can process customers at an average of 3 minutes. (a) What is the average wait time? (b) What is the average number of customers waiting? (c) What is the average number of customers in the DMV? Answer: (a) Wq = 0.01 hours = .41 minutes = 24.81 seconds (b) Lq = 0.31 customers (c) L = 2.56 Diff: Difficult Topic: MULTICHANNEL QUEUING MODEL WITH POISSON ARRIVALS AND EXPONENTIAL SERVICE TIMES (M/M/m) LO: 12.4: Analyze a variety of operating characteristics of waiting lines for multi-channel models with exponential service times and infinite calling populations. AACSB: Analytical thinking Classification: Application 121) What is meant by a single-channel queuing system? Answer: one service facility system fed by one queue Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 293 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 122) What is meant by a multichannel queuing system? Answer: more than one service facility all fed by the same queue Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 123) What is meant by a single-phase system? Answer: Arrivals leave the system after receiving service at only one station. Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 124) What is meant by a multiphase system? Answer: Service is provided at more than one station, one after the other. Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 125) What is the difference between customers balking and customers reneging? If you managed a retail store how would you track and differentiate between customers that balked and reneged? Answer: Balking occurs when customers decline to join the queue, typically because they see the line is too long and they don't have enough time. Reneging occurs when customers join the queue and change their mind later and depart the queue. Answers will vary as to how they can be tracked. It may be easier to track those that renege if some part of the service process has already begun and customer information is recorded. Alternatively, security camera footage could be checked at the end of each day to see the number that joined a line and then left. Balking would probably be tougher to capture in most situations. Diff: Moderate Topic: CHARACTERISTICS OF A QUEUING SYSTEM LO: 12.2: Describe the basic queuing system configurations and the three parts of a queuing system: the calling population, the queue itself, and the service facility. AACSB: Analytical thinking Classification: Concept 294 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall 126) What is the difference between a transient state and a steady state? How could you as a manager distinguish between the two? Answer: A steady state is the normal operating condition of the queuing system. A queuing system is in a transient state before the steady state is reached. A manager would expect to be in a transient state at opening time each day or after a holiday and be in steady state during most operating hours if most queuing analysis assumptions are reasonable. For pure customer service situations, there may be additional transient periods of the day, for example, a lunch or dinner rush at a restaurant. Diff: Moderate Topic: SOME GENERAL OPERATING CHARACTERISTIC RELATIONSHIPS LO: 12.7: Understand Little's Flow Equations. AACSB: Analytical thinking Classification: Concept 127) Four thousand students are admitted each year at a large regional university. The average time to complete a degree is six years and the university's retention rate initiative achieves 100% (no students drop out or transfer). What is the student population? Answer: 24,000 students; L = λW = 4000 students/year × 6 years Diff: Easy Topic: SOME GENERAL OPERATING CHARACTERISTIC RELATIONSHIPS LO: 12.7: Understand Little's Flow Equations. AACSB: Analytical thinking 295 Copyright © 2012 Pearson Education, Inc. publishing as Prentice Hall