See discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/327786356 Short Circuit Analysis & Over current Relaying Coordination of IEEE 9-Bus System Conference Paper · April 2018 DOI: 10.1109/IMTIC.2018.8467260 CITATIONS READS 6 2,791 5 authors, including: Shoaib Ahmed Shaikh Kundan Kumar Sukkur Institute of Business Administration University of Delhi 28 PUBLICATIONS 86 CITATIONS 8 PUBLICATIONS 26 CITATIONS SEE PROFILE SEE PROFILE Asif Raza Solangi Shubash Kumar Mehran University of Engineering and Technology Yan Shan University 6 PUBLICATIONS 19 CITATIONS 10 PUBLICATIONS 36 CITATIONS SEE PROFILE Some of the authors of this publication are also working on these related projects: Analysis of different lights used in a shopping mall-A comparative study View project Control, System Dynamics, Modelling, Matlab, Simulink, Vehicle Dyanmics View project All content following this page was uploaded by Shoaib Ahmed Shaikh on 09 April 2019. The user has requested enhancement of the downloaded file. SEE PROFILE Short Circuit Analysis & Over current Relaying Coordination of IEEE 9-Bus System Shoaib A. Shaikh, Kundan Kumar Asif R. Solangi, Shubash Kumar Aizaz Ali Soomro, Hamdard University Karachi shoaib.ahmed@hamdard.edu.pk FEST Indus University, Karachi solangiasif66@gmail.com NED UET, Karachi Abstract—It is an essential and compulsory to design an empty interrupted electrical power system network having security, stability and reliability in this electricity dependent era. In this paper Short circuit analysis and Protection relying coordination of IEEE 9-Bus system is analyzed and designing of overcurrent relaying scheme to operate the relay quickly and disconnect the faulty section from healthy section. Electrical Power system built in the industry needs appropriate protection strategy for reliable operation. Undetected and sudden faults can become hazardous and disturb the entire system, power devices and causes the overheating, unbalanced system conditions, up and down of the system voltage and blackouts etc. Proposed designing consists of nine buses (two generator buses, one slack bus and six load buses), three transformers of 100MVA at three buses Bus- 1, 2 &3, placement of transmission lines are used. The load flow and fault analysis study are carried out before the protection design of the system. The power flow analysis keeps vital role due to identification of network capability to run with maximum load having no any effect on the system stability. The load flow and fault analysis study are carried out before the protection design of the system. Keywords— IEEE 9- Bus system, Load flow analysis, Short circuit (SC) analysis, Protection relaying coordination, OC protection. I. INTRODUCTION Electrical Power system covers three principal parts as Generation, transmission and distribution systems. The main objective of the power system is to fulfill all the segments of the system electrical energy with high possible efficiency to deliver to users at satisfactory frequency, voltages and reliability. An important segment is the distribution system which connects the generators and equipment used on the consumer side by carrying the electricity from transmission system comprises of feeders, distributors and service mains with suitable protective and controlling devices [1]. A report has been created which showed that 80% interruptions are observed to the consumer side in due to failure of distribution system. To make it an efficient system, distribution automation is made applicable to the 978-1-5386-6594-7/18/$31.00 ©2018 IEEE distribution feeders for the achievement of substantial and quick enhancement in security, reliability and quality to the customers. Several techniques as var planning, optimization of network, stat estimation, feeder reconfiguration, analysis of fault etc. has mandated to construct distribution automation (DA) effectively [2-6]. Old-style objects engaged to secure acceptable protection whereas controlling the system have been insufficient [7]. The essential requirement of Power Company and utility is classified as efficient arrangement and exact forecast of equipment age having strictness to avoid the under-usage and over-usage of existing resources. Requirements to model power system of main three categories electrical power generation, transmission and distribution has become necessary for making some actual-value verdicts for capital investment and management. The factors for modeling and designing the efficient systems with the usage of analytical tools comprise: augmented productivity, reduction of capital disbursement, decrease in inventory outdated segments, decrease in repair cost, investment reduction after first year execution and enhanced amenities etc. [8]. Analysis of faults had become sophisticated and difficult in old era but in this scientifically and technological era it has become complex and convenient as numerous fast and reliable computing methods have been introduced as MATLAB, ETAP etc. The fast and reliable techniques for different faults also require an effective and efficient faultanalysis technique. The exact information of fault is not only acceptable for fault recognition algorithms or prototypes but proper protective relays operation and correct resolve of different fault types [9]– [12]. The software tools for the analysis of power system are not partial to their main technical characteristics though it also contains separate competences for modeling, design and analysis of the system. Key features comprise; power flow analysis, Load flow analysis, short circuit (SC) analysis, power system stability, power system protection, coordination of the system, optimal power flow and reliability etc. In this paper we have worked on the short circuit analysis of IEEE 9-bus system with overcurrent (OC) relaying scheme on ETAP software by examining the normal load-flow along with fault analysis. A procedure to obtain the electrical power systems steady-stat voltages at fundamental frequency is named as load flow [13]. Out of nine buses, we have considered here two voltage-controlled buses i.e. 1 and 2, one as swing bus i.e. 3 and six buses as load buses i.e. 49, three transformers with a transmission line in between them. For the protection circuit breakers have also been placed with an addition of overcurrent relays. Several three phase faults as L-G, L-L and L-L-G have been placed individually on Bus-7 and results have been recorded also. Furthermore, short circuit analysis of system is also included in this paper to determine the positive (+ve), negative (-ve) and zero -sequence impedance of faults. Last and the main task of our work is on the sequence of operation of relays connected on bus-7 and controlling on the relay having minimal effect should run first and so on. II. OVERVIEW OF FAULTS AND FORMULAE In this era the electrical power system is almost interconnected in which faults may occur and currents flowing with a high rate must be disrupted before the establishment of normal conditions. Several types of fault occur as symmetrical and unsymmetrical faults. The classification is also depicted in fig.1. From the faults, the dangerous fault due to which maximum interruption arises in network accessories is three phase fault or symmetrical fault [14]. and protective relays keep vital role in designing of the protection system to separate and disconnect the faulty section from the normal or Steady State section. CBs rated in MVA are designed and selected based on the interrupting capacity of current by taking momentary SC current until relay cross the threshold limit. It will be better for the system that circuit ought to be separated on interruption at the initial stage otherwise CB could not be able to break it because of internal CB’s arc conduction [14]. The equation 1 relevant to CB is given as: SSC=√3*VPRE*ISC (1) Where; SSC= Short circuit power, VPRE=System pre-fault voltage ISC= short circuit current In this paper the fault is placed on the bus-7. For the estimation of fault, the methodologies as base MVA and per unit are applied here, the formulae in equation form are given in equation 2-5. !"#$ = Zold Z Base = ( 3 :;<, * :;<, Z p. u = Z ∗ ( I sc = *+,*./0 ) + 3./0 3+,- ² … (2) ………………………………. (3) B CDEF G CDEF² ) …………………………. (4) B EJ KLM∗NO⁶ R G QDEF∗NOᵌ …………….…………… (5) The protective relay is used for sensing the fault current which then send the trip signal to the circuit breaker. The proper setting of the relay is necessary for the efficient power system. Different types of protective relays exist are selected based on several applications as distance relays, differential relays, overcurrent relays etc. The relay has two setting; plug setting and time setting. The time setting is for deciding the time of relay operation whereas plug setting decision is done based on current required to pick up for the relay. The relay for time setting and pick up setting is shown in fig.2 Fig. 1 Types of Fault Fault is an undesired and sudden condition that not only make the network stressed but also effect on the cost due to equipment failure. Before damaging any equipment, it is mandatory to block the high flow of current. Fault in a distribution network is undesired situation that puts the network into more stressed condition. The result of fault is a very high current flow and it is necessary to block it before it damages any section of network. Circuit breakers Fig. 2 Overcurrent relay Several mathematical models exist for the OC relays as Inverse definite time over current relay, very inverse definite time overcurrent relay and extremely inverse time overcurrent relay are shown in equation 6-8 respectively. top = top = top = O.NU(VWB) X YBW Z.Z[ \N N].^(VWB) X YBW X \N _O.O(VWB) X YBW [ \N …………………… (6) relays and in the last the results taken in the form of curves in the graph. …………………………..... (7) ……………………………. (8) Where; PSM= I relay / PS and Plug setting= rated CT secondary x some percentage The primary current of CT is decided by considering the maximum load current which CT primary must carry. Next category is the setting of relay which involves the selection of pick up value of the relay and operating time of the relay. The arrangement of pick-up setting should be done such that coordination time in between relays must guarantee fault interruption safely and securely [15]. Pick up value of the relay can be set by keeping in mind that relay should operate in both conditions in normal load conditions and certain extension of overload to be supplied. Hence the pickup value should be greater than maximum allowable load. At the same interval, the response of the relay should also be sensitive on the lowest fault as well. Thus, pick up value should always be kept lesser than the smallest value of fault current If. To set the pickup value, a rule is depicted as below: `a, cde < `g. h < `i, cjk A study of protection coordination is used for governing the trip setting of each device used in the system network so as to get minimum interruption but maximum protection for the faults occur in the system [16]. A relay must gain an adequate fortuitous for protecting the system from abnormal conditions under the primary protection. If failure occurs in primary protection to sense and clear the fault, then the backup protection for clearing the fault should start their work to initiate the trip. Therefore, as soon as initiation of the fault occur, it must be detected by the both protection primary as well as back up. Overshoot of the relay which is due to moment of inertia is should be allowable. It is also important that if fault occurs on any location of feeder then OC relays must coordinate for transformer and feeder for assuring safer as well as efficient operation of protection scheme design otherwise it may fail. The stand coordination time interval is 0.2 to 0.4sec [17]. III. METHODOLOGY AND SIMULTAION RESULTS It is an essential for any work to make a pictorial view or flow chart which in short show the whole work in conclusion. In this research work we have designed the IEEE 9-Bus system in ETAP software. The input data which was used in designing the system is given in the table.1-6. The formulae also represented in the second part. The flow chart in fig. 3 depicts several parts which have been done in designing the system include: simulation of the IEEE 9-Bus system, Load flow analysis, Short circuit analysis, selection of protective OC relays, relay coordination of CT and PT and circuit breakers, calculation of currents after the setting of Fig 3: Flow chart of the system A. Load flow analysis of IEEE 9 Bus system Load flow analysis is an essential for the designing of protective equipment as CBs, CTs, and Relays etc. The designing through computational methods has become advantageous and beneficial for the power utility companies and protection engineers. In the old era the system used was very complicated, cost-effective and time consuming. In this paper the first IEEE 9-Bus system is designed with different types of buses (Generating, Swing and Load Bus), Transformers, placement of T/L between the buses, Circuit breakers adjacent to buses with OC relays and Capacitor as shown in fig.4 and Fig.5. After designing the IEEE 9-Bus system, the load flow analysis is completed which shows that system is normal and their parameters (active, reactive powers etc.) are within permissible limits and no any fault exist. The input data of Generators, Buses, Transformers, Conductor length etc. are represented in the diagrams. B. Placement of fault on Bus-7 After inserting the data in normal load conditions, the unsymmetrical faults (i.e., Line-t-ground, Line-Line and Line-Line-Ground faults) were placed on bus 7 one by one as shown in fig.6. The results are recorded, and it is being observed that the three-phase fault current is most severe and greater than other faults. Fig. 4 IEEE 9-Bus system Fig. 5 Proposed system C. SC Analysis Furthermore, the S.C analysis of IEEE 9-Bus system is included for determining the fault of positive, negative and zero-sequence impedance. The figure .8 also represent the IEEE 9-Bus system with placement of fault. Fig.6 Faults IV. RELAY OPERATION The Load flow analysis, SC analysis has been completed with the results in the form of tables. Now the main task of our research work is the placement of protective relays on bus-7, CBS and their proper operation. For this, the sequence of relay operation is mandatory which is given in table. 7. The protective relays which were connected to the bus-7 are checked a on their operation and occurrence of tripping of CBs is also observed with some time delay. The relay-5 due to the least effect of power system, energize first and tripped the consistent circuit breaker and major part of power system protection is observed from the SC current followed by relay 6 and 7. The graph of the relay setting is given in the fig. 8&9 which clearly shows the operating time and the effect of overcurrent according the desired conditions. Also, the operational curve of the branches Cleary shows the pictorial view of the operation of the branches and the faulty bus. Fig 8. Operational Branches Curve Fig 7. sequence of operation of relay REFERENCES [1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] Fig 9. Combine curve of all operational relay V. CONCLUSION A power flow study, which has been considered as an important for the future planned expansion of Electrical power system and for the reliable and efficient determination of operating existed system. The basic and preliminary data is magnitude and the phase angle (ɸ) of the voltage (V) at each bus, active and reactive power (P & Q) flow in each line from the power flow study. The severe faults due to short circuit or other reasons can damage the whole power system which obviously disturbs the system, but also give a big financial loss of equipment, conductors, machines etc. This system design is very much important because sudden and undetected malfunctioning is hazardous for the whole network, which causes system unbalanced, overvoltage, overcurrent and blackouts, etc. In this research work the SC analysis of IEEE 9-Bus system containing two generator buses, one slack and six load buses has been analyzed by putting the unsymmetrical faults and the designing of OC relay operation with quick disconnect during the faults has also been analyzed in ETAP software. The faults were placed on the bus-7, relay operation is checked, and tripping of CBs is also observed with some delay of time. The relay-5 first started energizing due to low effect which tripped the consistent circuit breaker and after that main portion of protection is checked and observed from the short circuit current of the relay6&7. The proposed protective approaches improved the system benefits to both the utility companies and consumers. View publication stats [12] [13] [14] [15] [16] A. Sampath Kumar, V. Vasudaven, J. Antony, Madhu Sudhana Raju, L.Ramesh “Minimization of Power Losses in Distribution System through nd HVDS Concepts” Proc. Of 2 International Conference on Sustainable Energy and Intelligent System (SEISCON), pp.86-90, 20th - 2nd July 2011. Value of distribution automation applications, CEC 500-2007-028, Apr. 2004, Calif. Energy Commission, Sacramento, CA, Public Interest Energy Res. (PIER), Final Project Rep. Advanced distribution automation,” EPRI 2006 Portfolio, Elect. Power Res. Inst., Inc., Palo Alto, CA, 2006. N. S. Markushevich, A. P. Berman, C. J. Jensen, and J. C. Clemmer, “Implementation of advanced distribution automation in U.S.A. utilities,” in Proc. CIRED 16th Int. Conf. Exhib. Elect. Distrib., 2001, pp. 224–224, Part 1 G. W. Ault, C. E. T. Foote, and J. R. McDonald, “UK research activities on advanced distribution automation,” in Proc. IEEE Power Eng. Soc. General Meeting, Jun. 2005, vol. 1, pp. 2616–2619 C. L. Su and J. H. Teng, “Economic evaluation of a distribution automation project,” IEEE Trans. Ind. Appl., vol. 43, no. 6, pp. 1417– 1425, Nov. 2007. M. Begovic, D. Novosel, and M. Milisavljevic, “Trends in power system protection and control,” Decision Support Syst., vol. 30, no. 3, pp. 269– 278, Jan. 2001 Review: Power System Analysis Software Tools Lokendra Bam, Student Member, IEEE, and Ward Jewell, Fellow, IEEE R. Ramaswami and P. F. McGuire, “Integrated coordination and short circuit analysis for system protection,” IEEE Trans. Power Del., vol. 7, no. 3, pp. 1112–1120, Jul. 1992 R. E. Brown, “Impact of smart grid on distribution system design,” in Proc. IEEE Power Energy Soc. Gen. Meeting, Jul. 2008, pp. 1–4 M.-S. Choi, S.-J. Lee, D.-S. Lee, and B.-G. Jin, “A new fault location algorithm using direct circuit analysis for distribution systems,” IEEE Trans. Power Del., vol. 19, no. 1, pp. 35–41, Jan. 2004 B. Das, “Fuzzy logic-based fault-type identification in unbalanced radial power distribution system,” IEEE Trans. Power Del., vol. 21, no. 1, pp. 278–285, Jan. 2006 Sergio Herraiz, Luis Sainz, Jordi Clua; “Review of Harmo ic Load Flow Formulations”, IEEE Trans. On Power Del very, 2003, 18, (3), pp, 10791087 K. Tuitemwong and S. Premrudeepreechacharn, “Expert system for protective devices coordination in radial distribution network with small power producers,” IEEE Lausanne Power Tech, pp. 1159-1164, 2017 J. Sadeh, “Optimal coordination of overcurrent relay in an interconnected power system,” in Proc. Power System Computation Conference, August 2005 Patel, H.A., V.M. Sharma, and A. Deshpande, Relay Coordination using ETAP. [17] M. H. Hussan and S. R. A. Rahim, “Optimal overcurrent relay coordination, a review,” Procedia Engineering, vol. 53, pp. 332-336, 2015