SAUDI ARABIAN OIL COMPANY
Contract No. 6600031345
CONSTRUCTION OF LOADING RACK
FACILITIES AT THE RT DISTRIBUTION
BI - 10 - 00914
DISCIPLINE
ENGINEER
PAINTING PROCEDURE
DATE:
PROJECT
ENGINEER
DATE:
CERTIFIED
DATE:
CONSTRUCTION
AGENCY
DATE:
OPERATIONS
PREPARED BY:
DATE:
DWG.TYPE PLANT NO. INDEX
Coating Procedure
Construction of Loading Rack Facilities at the RT
Ras Tanura
DOC
Saudi Arabia
GEN
RJO / EWO:
A
6600031345
DRAWING NO.
SHT.NO.
REV.NO.
1.1. A
HE-000060
1
of
7
A
EDSD/2616-0399.doc
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
DATE:
BY:
CONTROL NUMBER
EDSD
VERIFICATION
Saudi Aramco 2616-ENG (03/99)
REVISION
REVISIONCERTIFICATION
CERTIFICATE
(DCC) NO. _____________________
BY DRAWING COMPLETION CERTIFICATE
APPROVAL/CERTIFICATION REQUIREMENTS,
OF THIS DRAWING IS COVERED, FOR ALL
THIS INDICATES THAT REV. NO.__________
A
REV
NO.
JAN 22 2014
DATE
660003134
5
JO/EWO
ISSUED FOR REVIEW AND APPROVAL
DESCRIPTION
OM
PO
MP
ARM
ENGG CERT
PMT OPRNS
SAUDI ARABIAN OIL COMPANY
Ras Tanura
TABLE OF CONTENTS
A.
SCOPE & PURPOSE
B.
APPLICABILITY
C.
RESPONSIBILITY
D.
GENERAL
E.
DEFINITIONS
F.
PROCEDURE
G.
RECORDS
H.
REFERENCES
I.
ATTACHMENTS
DISCIPLINE
ENGINEER
DATE:
PROJECT
ENGINEER
DATE:
CERTIFIED
DATE:
CONSTRUCTION
AGENCY
DATE:
OPERATIONS
DATE:
DWG.TYPE PLANT NO. INDEX
Coating Procedure
Construction of Loading Rack Facilities at the RT
DOC
Saudi Arabia
GEN
RJO / EWO:
A
6600031345
DRAWING NO.
SHT.NO.
REV.NO.
1.1. A
HE-000060
2
of
7
A
EDSD/2616-0399.doc
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
DATE:
BY:
CONTROL NUMBER
EDSD
VERIFICATION
Saudi Aramco 2616-ENG (03/99)
A. SCOPE & PURPOSE
JO/EWO
660003134
5
JAN 22 2014
B. APPLICABILITY
All Piping, Structural Steel and Concrete Painting Works.
C.
Project Manager / Construction Manager
Discipline Engineer
QA/QA Manager
QC Personnel
 Material Controller
D.
DATE:
CERTIFIED
DATE:
CONSTRUCTION
AGENCY
DATE:
OPERATIONS
BY:
DATE:
(DCC) NO. _____________________
BY DRAWING COMPLETION CERTIFICATE
APPROVAL/CERTIFICATION REQUIREMENTS,
OF THIS DRAWING IS COVERED, FOR ALL
REVISION
REVISIONCERTIFICATION
CERTIFICATE
THIS INDICATES THAT REV. NO.__________
EDSD
VERIFICATION
CONTROL NUMBER
DATE:
RESPONSIBILITY




DISCIPLINE
ENGINEER
DATE:
PROJECT
ENGINEER
The scope of this procedure is to define the criteria of workmanship for the proper execution of
the painting Works in accordance with client requirements, drawings, specifications,
manufacturer’s instructions for storage, mixing, handling & application and applicable codes
and standards.
The purpose of this procedure is to detail the techniques to be applied on the different
activities relevant to the proper execution of the painting activities.
A
REV
NO.
DATE
DESCRIPTION
ISSUED FOR REVIEW AND APPROVAL
OM
PO
MP
ENGG CERT
ARM
SAUDI ARABIAN OIL COMPANY
GENERAL
 The responsibility for the process control of the painting Works rests primarily with the QC
Inspectors, the discipline Engineer and the discipline Foreman with and audit by the QA &
QC Managers.
 The discipline Engineer and the discipline Foreman shall ensure the required work permits
are available and in place on a daily basis. Similarly they shall ensure that utilized drawings
are latest version.
 Surface preparation shall conform to the Project specifications.
 Client specifications and drawings, manufacturer instructions/recommendations shall
supersede the techniques detailed in this procedure when they differ.
 The following procedure is a basic outline of requirements and in all cases the relevant
SATIP (if available) shall be reviewed by QC Manager or QC Supervisor to ensure
Inspectors are fully aware of tests and documentation requirements prior to start of work.
DWG.TYPE PLANT NO. INDEX
Coating Procedure
Construction of Loading Rack Facilities at the RT
Ras Tanura
DOC
Saudi Arabia
GEN
RJO / EWO:
A
DRAWING NO.
SHT.NO.
REV.NO.
1.1. A
HE-000060
3
of
7
A
6600031345
EDSD/2616-0399.doc
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT OPRNS
Saudi Aramco 2616-ENG (03/99)
ISSUED FOR REVIEW AND APPROVAL
DESCRIPTION
JAN 22 2014
660003134
5
JO/EWO
DATE
A
REV
NO.
DISCIPLINE
ENGINEER
DATE:
PROJECT
ENGINEER
DATE:
CERTIFIED
DATE:
CONSTRUCTION
AGENCY
DATE:
OPERATIONS
BY:
DATE:
(DCC) NO. _____________________
BY DRAWING COMPLETION CERTIFICATE
APPROVAL/CERTIFICATION REQUIREMENTS,
OF THIS DRAWING IS COVERED, FOR ALL
THIS INDICATES THAT REV. NO.__________
EDSD
VERIFICATION
CONTROL NUMBER
DATE:
REVISION
REVISIONCERTIFICATION
CERTIFICATE
E.
OM
PO
MP
ENGG CERT
ARM
SAUDI ARABIAN OIL COMPANY
F.
DEFINITIONS
SATIP: Saudi Aramco Typical Inspection Plan
SAIC: Saudi Aramco Inspection Checklists
SATR: Saudi Aramco Test Record
PROCEDURE
1. Material
 Material shall be in accordance with client requirements and specifications as per
SAMSS, material receiving inspection shall be in accordance with relevant SATIP and
SAIC.
2. Personnel and Equipment
 All Abrasive Blasters, Painting/Coating Applications and Crew Supervisors shall be
qualified, approved and possess valid certification in accordance with SAEP 312.
 All compressed air used for abrasive blasting or coating operations shall be free of oil
moisture and contamination. The QC Inspector shall as a minimum check air quality at
the start and mid points of each 8 hour period.
 All Blasting equipment shall have an operational dead-man control fitted.
 Minimum nozzle pressure for blasting of steel shall be 90 psig.
 Quality Control Equipment shall be available as required by project scope and SAES-H100 Attachments.
3. Process Control for Painting Works
 All painting must conform to the applicable approved project painting specifications. A
thorough review of these specifications at the beginning of the project will help to
assure quality workmanship and avoid rework.
 Many items should be painted before erection in order to achieve required quality at
lowest cost.
 When painting structural steel prior to erection, care must be taken to ensure that mark
numbers needed for erection are not painted over.
 The following items should be painted before subsequent operations take place that
would make them inaccessible:
 The topside of pipe supports and pipe sleeper bearing angles should be painted
before the piping is installed.
 Miscellaneous pipe supports, clamps, guides, etc., should be painted before
attachment to the pipe and especially before the pipe is insulated.
 When grating requires paint, the gratings and their supports should be painted before
installation.
 Pipe flanges and other exposed surfaces on insulated pipe lines should be cleaned
and painted, in accordance with the specifications, before insulating the line.
DWG.TYPE PLANT NO. INDEX
Coating Procedure
Construction of Loading Rack Facilities at the RT
Ras Tanura
DOC
Saudi Arabia
GEN
RJO / EWO:
A
DRAWING NO.
SHT.NO.
REV.NO.
1.1. A
HE-000060
4
of
7
A
6600031345
EDSD/2616-0399.doc
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT OPRNS
Saudi Aramco 2616-ENG (03/99)
SAUDI ARABIAN OIL COMPANY
JO/EWO
660003134
5
JAN 22 2014





Equipment nameplates
Nameplates on valves, instruments etc.
Valve stems.
Load scales on spring hangers and supports.
Pump shafts and other machined surfaces.
 Gauge glasses, thermometers, pressure gauges, etc.
3.1. Surface Preparation
 The Painting Foreman shall ensure that personnel are qualified as required by
SAEP-316 and in accordance with Client requirements, specifications and
applicable standards carry out the surface preparation.
 Visual inspection shall be carried out in order to decide if substrate requires solvent
or detergent cleaning prior to abrasive blasting. Cleaning shall be done in
accordance with specifications.
 Sandblasting should be performed outside the work areas, whenever possible. And
only with sand prior approved by Client Project Inspection Unit.
A
REV
NO.
DATE
DESCRIPTION
ISSUED FOR REVIEW AND APPROVAL
OM
PO
MP
ENGG CERT
ARM
 Electrical and Instrument supports should be painted before the electrical devices or
instruments are mounted.
 All other items which will be inaccessible after erection should be painted prior to
erection.
The following items should be masked or otherwise protected when painting:
DISCIPLINE
ENGINEER
DATE:
PROJECT
ENGINEER
3.2. Primer Coat
 Before commencing with the application of the primer coat of paint a thorough
review of the painting specifications and APCS must be made.
DATE:
CERTIFIED
 Complete kits shall be mixed in accordance to the manufacturer instructions. They
shall be thoroughly mixed until they are smooth and free from lumps and then
strained. Inorganic zinc coating shall be mechanically agitated at all times.
DATE:
CONSTRUCTION
AGENCY
 Coating shall commence with noting pot life. Over coats/topcoats shall be applied
within the manufacturers minimum and maximum re-coat times.
DATE:
OPERATIONS
 Dry film thickness of each coating shall be in accordance with specification or
manufacturers recommendations, whichever is greater. The primer coat must be
inspected and approved before application of the second or finish coat.
DATE:
BY:
 Refer to the specifications for special requirements when painting the following
items:

(DCC) NO. _____________________
BY DRAWING COMPLETION CERTIFICATE
APPROVAL/CERTIFICATION REQUIREMENTS,
OF THIS DRAWING IS COVERED, FOR ALL
REVISION
REVISIONCERTIFICATION
CERTIFICATE
THIS INDICATES THAT REV. NO.__________
EDSD
VERIFICATION
CONTROL NUMBER
DATE:
Equipment and piping requiring cold insulation.
DWG.TYPE PLANT NO. INDEX
Coating Procedure
Construction of Loading Rack Facilities at the RT
Ras Tanura
DOC
Saudi Arabia
GEN
RJO / EWO:
A
DRAWING NO.
SHT.NO.
REV.NO.
1.1. A
HE-000060
5
of
7
A
6600031345
EDSD/2616-0399.doc
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT OPRNS
Saudi Aramco 2616-ENG (03/99)

Equipment and piping that require high temperature paint. Keep in mind
that some high temperature paints must be cured before applying the
second coat and that some uncured paints will not provide corrosion
protection.

Items to be painted with temperature indicating paint.

Galvanized items when painting is specified.

Masonry when specified.
JO/EWO
660003134
5
JAN 22 2014
3.3. Finish Coats
 Identification of various components by painting with special colors varies from job
to job. The Painting Foreman shall refer to the project paint specifications for
specific requirements. The following items may require color identification:

Firewater piping and fire hydrants.

Piping in hazardous service.

Guard posts and rails.
When applicable, the requirements for safety color schemes and plant color
scheme shall be adhered to, as indicated in the specifications.
When applying a color code, the following should be controlled:
A
REV
NO.
DATE
DESCRIPTION
ISSUED FOR REVIEW AND APPROVAL
OM
PO
MP
ENGG CERT
ARM
SAUDI ARABIAN OIL COMPANY
DISCIPLINE
ENGINEER
DATE:
PROJECT
ENGINEER

Positions of lettering, marking at the stage of draft.

Size, space between letters, style, arrow direction at the stage of draft.

Color of the lettering after painting.
 The Painting Foreman / QC Inspector shall ensure that the total dry film thickness
is as called for in the painting specifications.
DATE:
CERTIFIED
DATE:
CONSTRUCTION
AGENCY
G.
RECORDS
All records relevant to above procedure shall be kept by the QC Manager in the site office
for the duration of the project and transferred to the Area Head Office, at the achievement of
the project, to be filed, archived and kept for a period of three years.
DATE:
OPERATIONS
DATE:
(DCC) NO. _____________________
BY DRAWING COMPLETION CERTIFICATE
BY:
H.
APPROVAL/CERTIFICATION REQUIREMENTS,
OF THIS DRAWING IS COVERED, FOR ALL
REVISION
REVISIONCERTIFICATION
CERTIFICATE
THIS INDICATES THAT REV. NO.__________
EDSD
VERIFICATION
CONTROL NUMBER
DATE:
REFERENCES
SAES-H-100
SAES-H-101
SAES-H-101V
SAEP 316
DWG.TYPE PLANT NO. INDEX
Coating Procedure
Construction of Loading Rack Facilities at the RT
Ras Tanura
DOC
Saudi Arabia
GEN
RJO / EWO:
A
DRAWING NO.
SHT.NO.
REV.NO.
1.1. A
HE-000060
6
of
7
A
6600031345
EDSD/2616-0399.doc
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
PMT OPRNS
Saudi Aramco 2616-ENG (03/99)
REVISION
REVISIONCERTIFICATION
CERTIFICATE
(DCC) NO. _____________________
BY DRAWING COMPLETION CERTIFICATE
APPROVAL/CERTIFICATION REQUIREMENTS,
OF THIS DRAWING IS COVERED, FOR ALL
THIS INDICATES THAT REV. NO.__________
A
REV
NO.
JAN 22 2014
DATE
660003134
5
JO/EWO
ISSUED FOR REVIEW AND APPROVAL
DESCRIPTION
OM
PO
MP
ARM
ENGG CERT
PMT OPRNS
SAUDI ARABIAN OIL COMPANY
I.
ATTACHMENTS
SATIP-H-100-01
SAIC-H-2027
SAIC-H-2028
SAIC-H-2029
SAIC-H-2030
SAIC-H-2031
SAIC-H-2032
SAIC-H-2033
DISCIPLINE
ENGINEER
DATE:
PROJECT
ENGINEER
DATE:
CERTIFIED
DATE:
CONSTRUCTION
AGENCY
DATE:
OPERATIONS
DATE:
DWG.TYPE PLANT NO. INDEX
Coating Procedure
Construction of Loading Rack Facilities at the RT
Ras Tanura
DOC
Saudi Arabia
GEN
RJO / EWO:
A
6600031345
DRAWING NO.
SHT.NO.
REV.NO.
1.1. A
HE-000060
7
of
7
A
EDSD/2616-0399.doc
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
DATE:
BY:
CONTROL NUMBER
EDSD
VERIFICATION
Saudi Aramco 2616-ENG (03/99)
Download