PROJECT MANAGEMENT MANUAL ISSUE II: APRIL, 2019 |Page LIST OF ACRONYMS BOQ Bill of Quantities CMT Contract Management Team CT Current Transformer ERA Electricity Regulatory Authority ESMP Environmental and Social Management Plan FAT Factory Acceptance Tests GPS Global Positioning System HSP Health and Safety Plan LC Local Council LV Low Voltage MV Medium Voltage NEMA National Environmental Management Authority NSSF National Social Security Fund PPE Personal Protective Equipment PPDA Public Procurement Disposal of Public Assets Authority REA Rural Electrification Agency UNRA Uganda National Roads Authority UWA Uganda Wildlife Authority VAT Value Added Tax VT Voltage Transformer SCC Special Conditions of the Contract STDO Service Territory Development and Operations i|Page TABLE OF CONTENTS LIST OF ACRONYMS .......................................................................................................................... i FOREWORD ..................................................................................................................................... vii REVISION RECORD ....................................................................................................................... viii 1 Introduction ...............................................................................................................................1 2 About the Project Management Unit .................................................................................3 Operations of Project Development and Management Department .........................3 Brief on Contract Management Team ....................................................................................4 3 Contract Effectiveness ............................................................................................................5 4 Contract Execution Start Documentation ........................................................................6 Project Work Schedules ..............................................................................................................6 Approval of Project Personnel..................................................................................................6 Approval of Manufacturers and Technical Specifications .............................................7 Procurement Plan ..........................................................................................................................7 Approval of Subcontractors for Installation Works .........................................................8 5 Engineering Designs and Surveys ................................................................................... 10 Engineering Design and Survey Report by the contractor ......................................... 10 Engineer’s Review Report ....................................................................................................... 12 Environmental and Social Management Tools (ESMTs) ............................................. 12 Implementation Plan ................................................................................................................. 13 6 Tests and Inspections .......................................................................................................... 15 Factory Acceptance Tests and Inspections of materials ............................................. 15 Factory Acceptance Tests ........................................................................................................ 15 6.2.1 Poles ........................................................................................................................................ 15 6.2.2 Transformers ....................................................................................................................... 16 6.2.3 Conductors ........................................................................................................................... 17 6.2.4 Insulators .............................................................................................................................. 17 6.2.5 Bulk Meters .......................................................................................................................... 19 6.2.6 Metering Unit....................................................................................................................... 19 6.2.7 Circuit breaker (Auto-Recloser)................................................................................... 19 ii | P a g e 6.2.8 Air Break Switch ................................................................................................................. 20 6.2.9 Load Break Switch ............................................................................................................. 20 6.2.10 Accessories (LV and MV) ................................................................................................ 21 FAT Report .................................................................................................................................... 21 Inspection upon delivery to site ........................................................................................... 21 7 Considerations for Effective Contract Management ................................................. 23 General Considerations ............................................................................................................ 23 7.1.1 Managing Additional Scope............................................................................................ 23 7.1.2 Managing Payment Certificates .................................................................................... 23 7.1.3 Managing Time Extension .............................................................................................. 26 7.1.4 Managing Performance.................................................................................................... 26 7.1.5 Change Management ........................................................................................................ 27 8 Site Office, Store and Yard Inspection ............................................................................ 28 9 Construction Site Supervision .......................................................................................... 30 Project Supervision by REA Engineer................................................................................. 30 Supervision by Safeguards Team ......................................................................................... 33 9.2.1 Safeguards Monitoring and Implementation Report ........................................... 34 Supervising the consultant ..................................................................................................... 37 Supervision by Wayleaves Officer ........................................................................................ 37 9.4.1 Definitions ............................................................................................................................ 37 9.4.2 Supervision Checkpoints ................................................................................................ 37 Supervision by Outreach Unit ................................................................................................ 39 9.5.1 Definitions ............................................................................................................................ 39 9.5.2 Supervision Checkpoints ................................................................................................ 39 9.5.3 Issues Addressed ............................................................................................................... 40 10 Progress Reporting............................................................................................................... 43 Clerk of Works ............................................................................................................................. 43 Project Engineers Progress Reports ................................................................................... 43 Contractor’s Monthly Progress Reports ............................................................................ 44 Consultant’s Progress Reports .............................................................................................. 45 11 Pre-Commissioning, Commissioning and Project Completion ............................. 47 iii | P a g e Introduction ................................................................................................................................ 47 Pre-commissioning exercise ................................................................................................. 47 11.2.1 Participants and Deliverables ....................................................................................... 47 11.2.2 Final Inspections ................................................................................................................ 48 11.2.3 Network Testing ................................................................................................................. 48 Commissioning and Handover Exercise ........................................................................... 49 Certificate of Practical Completion ..................................................................................... 49 Project Completion Report .................................................................................................... 50 Structure by Structure Audit ................................................................................................ 50 12 Connections ............................................................................................................................. 53 General Guidelines .................................................................................................................... 53 Earthing Kit.................................................................................................................................. 54 13 Defects Liability Period (DLP) .......................................................................................... 55 14 Contract Closure .................................................................................................................... 57 ANNEXES ........................................................................................................................................... 58 ANNEX 1: PROJECT IMPLEMENTATION CYCLE .................................................................... 59 ANNEX 2: STAKEHOLDER ANALYSIS AND PARTICIPATION MATRIX .......................... 60 ANNEX 3: RISK ANALYSIS MATRIX .......................................................................................... 61 ANNEX 4: CONTRACT MANAGEMENT PLAN ......................................................................... 89 ANNEX 5: CHECKLIST FOR ENVIRONMENTAL ASPECTS OF REA PROJECTS .............. 91 ANNEX 6: SURVEY METHODOLOGY AND PRESENTATION ........................................... 107 ANNEX 7A: POLES’ PRE-DISPATCH CHECKLIST (CREOSOTE) ..................................... 111 ANNEX 7B: POLES’ PRE-DISPATCH CHECKLIST (CHROMATED COPPER ARSENATE) ................................................................................................................................... 113 ANNEX 8: FAT CHECKLIST FOR TRANSFORMERS ............................................................ 115 ANNEX 9.0 REA INSPECTION CHECKLIST FOR MANUFACTURING PLANTS FOR CONDUCTORS............................................................................................................................... 121 ANNEX 9A: FAT CHECKLIST FOR LV ABC CONDUCTOR, THREE PHASE ................... 128 iv | P a g e ANNEX 9B: FAT CHECKLIST FOR LV ABC CONDUCTOR, SINGLE PHASE ................... 129 ANNEX 10: FAT CHECKLIST FOR TRANSFORMER WIRING AL / PVC CABLE .......... 130 ANNEX 11: FAT CHECKLIST FOR HV BARE CONDUCTOR 50SQMM ........................... 131 ANNEX 12: FAT CHECKLIST FOR HV BARE CONDUCTOR 100 SQMM ........................ 132 ANNEX 13: FAT CHECKLIST FOR GSW 3/2.64 ................................................................... 133 ANNEX 14: FAT CHECKLIST FOR GSW 7/2.64 ................................................................... 134 ANNEX 15: FAT CHECKLIST FOR GSW 7/4.00 ................................................................... 135 ANNEX 16: ROUTINE TEST - COMPOSITE LINE POST INSULATORS .......................... 136 ANNEX 17: ROUTINE TEST - PIN INSULATORS ................................................................. 137 ANNEX 18: ROUTINE TEST - DEAD END STRAIN INSULATORS ................................... 138 ANNEX 19: ASSESSMENT OF MANUFACTURER’S LEGAL AND REGULATORY COMPLIANCE, CERTIFICATION AND EXPERIENCE .......................................................... 139 ANNEX 20 A: IPC CMT CLEARANCE FORM .......................................................................... 140 ANNEX 20 B: INTERIM PAYMENT CERTIFICATE TEMPLATE ....................................... 141 ANNEX 21: CONTRACT CHANGE ORDER FORM ................................................................ 143 ANNEX 22: SITE INSPECTION CHECKLIST .......................................................................... 144 ANNEX 23: DAILY REPORT TEMPLATE FOR CLERK OF WORKS ................................. 146 ANNEX 24: WEEKLY PROGRESS REPORT ........................................................................... 147 ANNEX 25: SHUT DOWN AND COMMISSIONING LETTER TEMPLATE (GENERAL) 149 ANNEX 26: SHUT DOWN AND COMMISSIONING LETTER TEMPLATE (UMEME) ... 150 ANNEX 27: INVITATION LETTER FOR COMMISSIONING OF BULK METERING UNITS AND AUTO RECLOSERS (UETCL) ........................................................................................... 151 ANNEX 28: INVITATION LETTER FOR COMMISSIONING (UEDCL) ............................. 153 ANNEX 29: COMMISSIONING REPORT TEMPLATE .......................................................... 154 ANNEX 30: CERTIFICATE OF PRACTICAL COMPLETION ............................................... 159 ANNEX 31: SUB-CONTRACTING CRITERIA ......................................................................... 160 v|Page ANNEX 32: APPROVAL OF MANUFACTURER AND TECHNICAL SPECIFICATIONS . 170 ANNEX 33: LETTER OF INTRODUCTION TO THE DISTRICT ......................................... 179 ANNEX 34: STRUCTURE BY STRUCTURE AUDIT TOOL .................................................. 180 ANNEX 35: CONTRACT CLOSURE CHECKLIST ................................................................... 181 ANNEX 36: NO CLAIM CERTIFICATE ..................................................................................... 183 ANNEX 37: CIRCUIT BREAKER COMMISSIONING FORM ................................................ 184 ANNEX 38: CONTRACT ASSESSMENT TOOL (CONTRACTOR) ...................................... 186 ANNEX 39: CONTRACT ASSESSMENT TOOL (CONSULTANT) ...................................... 199 ANNEX 40: CONTRACT MANAGEMENT PLAN ................................................................... 205 ANNEX 41: PROJECT CHARTER .............................................................................................. 230 ANNEX 42: DESIGN AND CONSTRUCTION TEMPLATE ................................................... 238 vi | P a g e FOREWORD The Rural Electrification Agency (REA) Project Management Manual is a guideline that contains procedures, processes, policies, checklist, and parameters needed to enable the day to day management and supervision of REA projects from the design stage through to the construction and commissioning stages; including connections in line with environmental and social safeguards. Anchored in the dictates of the Rural Electrification Strategy and Plan (RESP 2013-2022) for REA to adopt technical standards for all construction design, this manual is part of the Agency efforts towards ensuring a 26% rural electrification access in an effective and efficient manner by 2022. In this regard, therefore, the manual offers guidance on a range of key project management aspects including; project documentation and progress reporting; engineering design and survey; tests and inspections; quality management, change management, commissioning, performance assessment, risk analysis and stakeholder engagement. Templates are provided in the manual to offer practical guidance on how to handle documentation for the various supervision aspects throughout the project cycle including; Factory Acceptance Test (FAT) checklists for power line components and equipment; checklist for legal and regulatory compliance; payment certificates, contract change order form, site inspection checklist, report templates; shut down and commissioning documentation templates and sub-contracting criteria. The Agency acknowledges the efforts that have been put into this process to produce working documents for better service delivery. This manual has been developed through a collective effort of a team of Engineers, environmental and Social Safeguards personnel with vast experience in power line construction and project management. The REA Project Development and Management team, led by the Department Manager, has particularly been instrumental in developing this manual. It is my hope, therefore, that all projects and managed as guided by this manual and all project management teams at the Agency will adhere to the guidelines here to ensure effectiveness and efficiency as REA dedicates its work to the socio-economic transformation, in an equitable and sustainable manner for rural development. For God and My Country. GODFREY R. TURYAHIKAYO EXECUTIVE DIRECTOR vii | P a g e REVISION RECORD VERSION 1.0 DATE 30/06/2016 ORIGINATORS Twongirwe Caleb Bisikwa Sarah Mbekeka Molly REVIEWED BY 2.0 30/03/2019 Twongirwe Caleb Kenneth Kahuma Adella Kyohairwe Godfrey Werikhe Eng. Eng. John A. Turyagyenda Eng. Henry I. Aine Lutwama Charles Wegulo Byakatonda Samuel Bishop Anthony Wamabuya Fred Asiimwe Adella Kyohairwe Onzia Joseph Kimera Raymond Kenneth Kahuma APPROVED BY Turyahikayo Godfrey Eng. John Turyagyenda Benon Bena Eng. Henry I. Aine Grace Birikadde Richard Muhangi Wegulo S. Byakatonda Samuel Bishop Anthony Wamabuya Christopher Katende Fred Asiimwe A Onzia Joseph Kimera Raymond Sarah Bisikwa Dr.Patricia Litho Molly Mbekeka James G. Litta viii | P a g e ISSUE For issue to all REA and Accredited Contractors’ or Consultants’ staff involved with the design, construction and supervision of overhead distribution lines, and is for reference by field, technical and engineering staff. Where this Manual is issued as a controlled document replacing an earlier edition, remove and destroy the superseded document. DISCLAIMER REA Manuals are subject to on-going review, the information contained in this document may be amended by REA at any time. Inconsistencies may exist between standard documents. In such instances, the most recent Manual shall prevail. This document has been developed using information available from field and other sources and is suitable for most situations encountered in Rural Electrification. Particular conditions, projects or localities may require special or different practices. It is the responsibility of the Project manager, Engineering supervisor, Contractor, assured quality controller and the individuals involved to make sure that a safe system of work is employed and that statutory requirements are met. REA disclaims any and all liability to any person or persons for any procedure, process or any other thing done or not done, as a result of this Manual. INTERPRETATION In the event that any user of this manual considers that any of its provisions is uncertain, ambiguous or otherwise in need of interpretation, the user should request REA to clarify the provision. REA’s interpretation shall then apply as though it was included in the Manual. ix | P a g e 1 Introduction Rural Electrification Agency (REA) is a semi-autonomous body created by an Act of parliament under Ministry of Energy and Mineral Development. REA is mandated to implement rural electrification programs in Uganda and has a vision of achieving universal access to electricity by 2035. Since its formation in 1999, Government of Uganda through Rural Electrification Board and REA has implemented several rural electrification projects. To effectively carry out this function on behalf of the Government of Uganda, REA established the Projects Development and Management Department with a core mandate of effective Project Management and Supervision. This manual is designed to guide the project management teams in the day-to-day management of Rural Electrification projects with a key emphasis placed on ensuring quality in delivery of the projects as a whole. This manual issues guidelines, content checks and quality checks on activities, procedures, practices and documentation used to manage factors affecting project implementation including Cost Management, Time Management, Quality Management, Scope Management, Stakeholder Management and Risk Managements. This manual discusses key areas of project implementation including contract effectiveness, initial project documentation, Engineering Design and Survey, Construction Environmental and Social Management Framework and Plan, and associated work procedures and guidelines, Tests and Inspections of materials and equipment, considerations for effectively managing the contract, construction supervision, report formats, pre-commissioning and commissioning guidelines, connections and project closure. Engineers, environmentalists and social safeguards staff are however encouraged to read the following documents in order to effectively use this manual: i. EPC Contract’s ii. Construction Manual iii. Manufacturing manuals, Standards and Specifications of Materials iv. Environmental and Social Management Framework and Plan, and associated work procedures and guidelines 1|Page The scope of work consists of supervising all works including designing, surveying and line route profiling; pegging and bush clearing; procurement and delivery to site of MV and LV overhead line construction materials including distribution transformers, bulk metering equipment and switchgears, overhead bare conductors, treated wooden poles, line insulators and related hardware accessories and protection device; medium voltage and low voltage network construction; installation of distribution transformers and protection equipment and network testing; pre-commissioning and commissioning; development and submission of as built drawings. The manual also contains the Project Implementation Cycle (Annex 1) that clearly highlights the documentation, approvals and stakeholders involved at each stage of project; Stakeholder Analysis and participation matrix (Annex 2) and Risk Analysis Matrix (Annex 3). 2|Page 2 About the Project Management Unit The Project Development and Management department (PDM) is the project implementation unit of REA. The department is staffed with a mix of professionals ranging from Engineers, Sociologists and Environmental practitioners. This section therefore briefly discusses the operations of the PDM department and the Contract Management Team. Operations of Project Development and Management Department To date, the operations of the Department are categorized into aspects highlighted below, i). Project Development: Design Review, including updating technical specification, preparation of bidding documents and procurement assistance. This activity is core and is currently handled by the manager with assistance from the Principle and senior engineers, in addition to overseeing the operations of the whole department. ii). Construction Supervision. The core activity undertaken is the supervision of construction works to ensure quality compliance and good workmanship. This activity is currently undertaken by the Project Engineers, under the supervision of the respective project coordinators. As a key role, they manage the day-to-day activities of the projects. iii). Project Monitoring. Project monitoring and control is a key function conducted at a senior level and is executed through project monitoring CMTs. Their main role is project and contract management. The CMT includes a senior engineer, senior environmentalist and social development officers and the principle community outreach officer. The main task is to interface with the supervision engineers and the communities outreach CMTs and interpret information generated for monitoring and control purposes. The CMT focuses on ensuring compliance to quality, scope, budget, time and social and environmental requirements of the project, offering technical support to the operations CMT (assistant project engineers and assistant community outreach officers) iv). Overall Project Management. The project management function is overseen at the principal level. The principal project engineer, senior environmental officers and the principal community outreach officers oversee the project management function for projects under implementation and the post construction phase. 3|Page v). Stakeholder Engagement. Project success is fully dependent on the level of engagement of the targeted beneficiaries. As such, the operations of the department have been structured in a way that community engagement, mobilization and involvement is conducted in parallel with construction supervision. This is the primary role of the community outreach unit, who are the “face of REA” out there. Brief on Contract Management Team Upon contract signing, the REA accounting officer nominates a contract manager in accordance with the PPDA guidelines to oversee the management of the contract. Thereafter, a Contract Management Team (CMT) is established, through a dully signed Contract Management Plan (CMP) (Attached in Annex 40) which spells out the roles and responsibilities of the team members. The CMT consists of professional to manage the engineering, GIS and operations, communication and community outreach, social and environmental components of the project. On project kick-off, a Project Management Charter Annex 41 is signed-off to guide the relationship between the CMT, EPC contractor and the supervision consultant. 4|Page 3 Contract Effectiveness The Contract manager should ensure the following documents have been filed. Table 1: Contract Management Documentation and Timelines NO. DOCUMENT TIMELINE 1 PP Form 49 (attached in Annex 4) Upon appointment of Contract manager 2 Performance Security Within specified days as per the contract 3 Advance Payment Guarantee Within specified days as per the contract Notes: a) Advance payment will be made to the Contractor upon presentation of an unconditional Bank Guarantee of an equivalent amount from a reputable licensed commercial bank acceptable to the employer. The Advance Payment will be recovered at an amortisation rate specified in the Contract. b) Insurance Cover All Insurance agreements for Construction projects shall be made under the professional assistance of an Insurance Broker who shall be in possession of a valid operational license issued by Insurance Regulatory Authority (IRA). The Contractor shall submit credentials of the Insurance Broker to REA for Approval. To this end, the Insurance Covers shall be accompanied with notes from the Approved Insurance Broker. The Contractor shall also submit a receipt from an Insurance Service Provider as proof of payment for the Insurance Covers. All insurance covers shall be prepared in accordance with the works Contract. As a minimum, the Engineer shall ensure that: The minimum cover for insurance of the Works, Plant and Materials is: Full replaceable cost/value. The third party shall cover the employer’s personnel. The minimum cover for insurance of Equipment shall be: Full Replacement Value The minimum cover for insurance of property is: Full Replacement Value Workman’s compensation shall include the Contractor’s employees. It shall also include subcontractors for works where applicable. c) The standard form of Performance Security acceptable to the Employer shall be an Unconditional Bank Guarantee in the format presented in the Bidding Documents for works. 5|Page 4 Contract Execution Start Documentation Project Work Schedules Upon Contract Signature, a Project Kick-off meeting shall be held within 10 days. This meeting shall be guided by the Project Management Cycle (attached in Annex 1). After this meeting, the Contractor shall be required to furnish REA with a Month Zero implementation plan within 10 days. The Plan shall clearly show activities the Contractor intends to accomplish in the period after contract signature and prior to effectiveness or activities to be executed within the first the first 28days from signature. As a minimum, the plan shall clearly detail the dates of submission of the following key contract deliverables: Performance Security, Advance Payment Guarantee, Insurance Covers, Contractor’s Organogram, Subcontractor’s Profiles, Detailed Technical Specifications and Manufacturer Details, Project Procurement Plan, Project Completion Schedule and Schedule of Personnel. This plan shall be discussed and signed off by the Contractor, Client and Supervision Consultant. Onwards, the Contractor shall provide an updated work schedule, monthly, as indicated in the Contractor’s progress report (Section 9.3). Approval of Project Personnel The Contractor shall submit the project execution organogram, committing to the availability of the key personnel. To this, detailed and updated CV’s shall be submitted for review and prior to acceptance, interviews chaired by the REA shall be conducted to confirm specific experience of the team. Upon acceptable performance, the REA shall issue approvals of the organogram and the key personnel, clearing the team for deployment. In case the contractor wishes to avail personnel different from those stipulated in the contract, the contractor shall submit a request for change of project personnel; stating the justification for this change, their positions and proposed personnel. The contractor shall attach CVs of the proposed personnel whose qualifications should be equal to or greater than those of the stipulated personnel as per the contract. 6|Page Approval of Manufacturers and Technical Specifications The Contractor shall provide details of the manufacturer and their guaranteed technical specifications supported by technical drawings. The CMT shall review them to ensure compliance to REA’s requirements for those materials and shall issue an Approval of the Manufacturer and Technical Specifications (Annex 4 and 32) when compliance is met. Submissions and or drawings shall either be approved or rejected with comments. The Engineer’s approval does not in any way relive the Contractor of his full responsibility for the correctness of his documentation and the proper functioning, quality and compliance with the Specifications of all plant and equipment supplied by him. Procurement Plan The procurement plan shall be issued by the contractor and should include the following items: a) List of Items to be procured b) Name and contacts of supplier c) Location of supplier d) Approvals of Supplier and Product Specifications issued by REA should be attached. e) Expected Date of Placement and Confirmation of Orders f) Quantities to be supplied g) Manufacturing period (Start and end dates) h) Planned dates for Factory Acceptance Tests and/or pre-dispatch inspection i) Expected date of Delivery to the country/ site j) Packaging Methodology k) Methodology of handling, transportation, delivery and storage of materials l) Company profiles of the Transporter and the Clearing Agents m) Risk assessment clearly indicating risk mitigation Plan n) Representative of the contractor The procurement plan shall be submitted to the Project Manager for review and approval prior to placement of orders. 7|Page Action by REA The Engineer shall ensure that the Procurement plan is submitted within 28 days after contract start date. The Engineer in consultation with Procurement and Disposal Unit shall review the plan, prepare an assessment report recommending approval of Clearing Agents, Method of Packaging, Transporter and Risk management plan. The Engineer shall also confirm placement of orders. Approval of Subcontractors for Installation Works The main contractor shall submit a detailed company profile of the subcontractors for installation works including the following: i). Certificate of Incorporation ii). Valid trading license iii). Income tax clearance iv). Valid VAT registration certificate v). Valid PPDA registration certificate vi). Articles and Memorandum of Association vii). Particulars of the Directors (Company form 7) with copy of identification (driving permit, national ID or passport) and detailed CVs with passport photos attached viii). Office premises ix). Valid NSSF registration certificate x). Audited books of accounts for the previous 1 years xi). Should not be suspended by PPDA or development partners xii). Recommendation from registered Engineer xiii). Acceptable code of conduct Minimum Technical Experience and Capability of the Firm shall be: Proof of existence of the company for 2 years and proof of two (02) similar works done in the last 2 years similar in scope, amount and complexity. 8|Page Table 2: Key personnel with the minimum level of qualification and experience No. Personnel Minimum Specific Qualification/Expertise Experience 1 Project Manager/ BSc. Electrical Engineering 2 years Electrical Engineer 2 Foremen Ordinary Diploma in Electrical 5 years Engineering or equivalent Note: Either the Electrical Engineer and/or the General Foreman shall be a holder of a valid Class B ERA Certificate. Action by REA The Engineer shall review the company profiles (Refer to Annex 31 for the full subcontracting criteria), prepare and submit an assessment report prior to recommendation for approval, rejection or modification where applicable. 9|Page 5 Engineering Designs and Surveys The Contractor shall embark on Engineering designs and surveys as agreed in the Project Completion Schedules after Contract Effectiveness. The surveys and designs shall be done in conformity with environmental and social standards, requirements and best practices. The major expected outcomes of this activity shall include the Engineering Design and Survey report; and Environmental and Social Management Tools. The Contractor shall also furnish the Project Manager with a Project Implementation Plan prior to commencement of works. Engineering Design and Survey Report by the contractor This report shall be prepared and submitted by the contractor. Survey drawings and report shall fully be signed by the Contractor’s Project Engineer. Submission shall not be accepted if not signed by the contractor’s Project Engineer. The report shall include the following: Chapter one: Brief description of the general geographical, social and physical environmental characteristics of the site including soil types, general topography, vegetation and plantations in the area, swamps, farm lands, rivers, water bodies, social economic set up of the area, social services, Protected areas etc. Chapter two: Economic Analysis – economic activities carried out in the area. Chapter three: Development projects and plans within the project area – such as resorts, tourist attractions, cultural sites, local council and district development plans especially concerning water and roads which can be obtained from UNRA and District physical planners. Chapter four: General Technical Considerations: This chapter should briefly discuss the existing power network from which the Tee-off will be; taking into consideration the following: i). ii). Substation Installed capacity, protection settings (grading) Any future expansion plans such as construction of spare bays General condition of the existing power line The construction type The length of the line 10 | P a g e Details of the primary substation from which the existing line originates Current voltage profile and load profile of the primary substations (Should be within the 10% voltage drop tolerance) Nature of load that the feeder serves - Industrial loads or domestic loads Voltage at the point of connection (Measured from the nearest Transformer) Chapter five: Survey methodology – the methodology shall detail the line route survey, structure spotting, and profiling. The line route survey shall be conducted using high precision survey equipment that shall be compatible with PLS CAD. The profiling and network modelling shall be done using PLS CAD. Should describe considerations taken during the survey activity, Personnel experience and qualification of team executing the survey activity, Tools used (RTK, GPS). (Refer to Annex 6 for the detailed Survey Methodology). Chapter six: Design criteria – describe type of structures used, power line components sizing, type of construction and their justification (simulations, load flow studies and calculations done). Chapter seven: Construction Methodology – should include the construction type, transition from one construction stage to another, how to ensure quality of works and how to ensure timely completion among others. Methodology on how to deal with swamps; managing environmental and social aspects of the project including safety shall be included as well. Attachments: The following shall be attached to the report. a) Survey report, Design and Structural drawings, Pole schedules (structures and accessories, structure number, pole height, and span length), material list, updated BoQs; Coordinates of Project Affected Persons (PAPs) and Beneficiaries b) List of required approvals arising from the power line design for example approvals from statutory authorities (e.g. NEMA, NFA, UWA etc.), use of Pin / Light/Flying Angle structures, use of three member structures with a span greater than 300m, use of guy poles, the format and the notation of the drawings, the initial sag and tension tables c) Latest Physical Plan for the District d) Design and Construction Tool (Template is attached in Annex 42) 11 | P a g e Note: The survey of the low voltage network shall be conducted in a manner that will record in detail the last mile consumer. The details shall include the full names, contact details of owner, GPS coordinates of their location (Arc 1960 UTM coordinate system), nature of structure and status of wiring. This list shall be submitted alongside the low voltage structure schedules for each distribution transformer and shall be verified by the project manager prior to approval of the design drawings. Engineer’s Review Report The Engineer shall go with the report to the field to verify the information given and write a report which shall include the following: Chapter one: Introduction – Contract details Chapter two: Findings from site inspection and review of Engineering Design and Survey Report by the contractor Chapter three: Scope Analysis (Contractual vs As-pegged) Chapter four: Financial Analysis (Contractual vs As-pegged) Chapter five: Risks and mitigation Plan Chapter six: Recommendations and Conclusion Environmental and Social Management Tools (ESMTs) The Contractor shall prepare all the necessary ESMTs and these shall include: a) Construction Environmental and Social Management Plan b) Community and Communication Engagement Plan c) Occupational Health and Safety Plan (OHSP) d) Alcohol Substance Abuse Policy e) HIV management Program f) Occupational Health and Safety work procedures g) Health, safety & Environment (HSE) Policy h) HIV management Program i) Alcohol Substance Abuse Policy j) Occupational Health and Safety (OHS) inspection, testing and monitoring procedures k) Incident investigation, management and reporting procedure l) Waste Management Plan m) Procedure for Decommissioning Equipment Storage Yard 12 | P a g e n) Wetland work and restoration procedures o) Transport Management Plan/Procedure p) Community Engagement Plan q) Procedures for materials stores and restoration r) Labor Management Plan s) Risk Assessment – Indicate possible risks to the project and mitigation actions Implementation Plan Prior to commencement of Construction Works, the Contractor shall provide a detailed Project Implementation plan. This Plan shall include the following items as a minimum; Chapter one: Introduction Brief Project description Purpose of the Implementation Plan Assumptions and Constraints made during the development of the plan Chapter two: Management Overview Major Tasks – Brief description of major tasks involved in the project implementation Updated Project Completion Work Schedule – Use MS Project or equivalent and present using a Gantt Chart Risk Management Plan Quality Control Plan; include considerations to ensure that the method presented is followed Chapter three: Implementation Support Project Organogram showing Role, Name, Contact (Include personnel responsible for connections) Deployment Plan – Indicate the number of required personnel, their skill levels, their respective roles, responsibilities and key deliverables. Tools and equipment to be used – specify models, versions, ownership status, licensing and manufacture support (Indicate tools and equipment relevant at each stage) Facilities – Site Stores and Offices including location (Refer to Annex 22 for the Site Inspection Checklist). 13 | P a g e The Project Implementation Plan should be approved and signed by the Contractor’s Project Manager. The amount to be withheld for late submission of an updated Program is: 0.2% of the contract sum. Action by REA CMT shall review the Implementation plan, prepare an assessment report and make recommendation for approval, rejection or modification where applicable. The report shall entail the following: Chapter one: Introduction including Brief Project description Chapter two: Observations from review of the Implementation plan Chapter three: Recommendations and Conclusion 14 | P a g e 6 Tests and Inspections All materials shall be tested to ensure compliance to REA standards and specifications. Prior to placement of an order, all manufacturers’ material specifications should have been reviewed and approved by REA. Factory Acceptance Tests and Inspections of materials Factory Acceptance Tests (FAT) will be carried out for major equipment and materials. Upon substantial completion of manufacturing and production of the equipment or materials, the manufacturer shall submit specific production line test reports for the completed products together with the manufacturer’s test procedures and protocols for review before inviting the client for FATs. For other materials and accessories, the manufacturer shall submit for review and approval material specifications and production line/ routine test reports (should include serial numbers) for REA materials prior to dispatch. For poles, Material Safety Data Sheets for chemicals used shall also be submitted. For all imported materials except meters, after FATs and materials are ready for shipment, a Pre-export Verification for Conformity (PVOC) shall be carried as required by UNBS and a Certificate of Conformity (CoC) issued prior to shipment. Action by REA The Engineer shall review production line test reports and the manufacturer’s test procedures and protocols in line with respective REA manuals and/or IEC Standards, and recommend approval for FATs or dispatch. Factory Acceptance Tests Below is a list of major equipment and the minimum required tests which shall be carried out. The tests may vary depending on the Contract. 6.2.1 Poles The following tests and checks will be carried out in accordance with REA Wooden Pole Treatment, Transportation, Handling and Erection Manual: i) Visual inspection ii) Measure of Pole Lengths iii) Measure of Pole Top Diameters 15 | P a g e iv) Cantilever test to assess mechanical strength v) Midpoint test to assess mechanical strength vi) Retention tests to measure how much treatment chemical has been retained in the pole vii) Penetration tests to ascertain how far the chemical has penetrated into the sap wood viii) Check manufacturer’s documents relating the chemicals quality and efficiency. Refer to Annex 7 for the Pole’s Pre-dispatch Checklist. 6.2.2 Transformers The following tests should be carried out in accordance with REA Transformer Manufacturing Manual: i) Insulation resistance test to assess the condition of insulation of all insulated parts of a transformer ii) Vector group test to confirm that the vector group is provided iii) Voltage ratio test to ensure that the turns ratio of the windings is correct and that the tapping on any of the windings have been made at correct position iv) DC winding resistance test to measure the DC resistance between lines of all windings and to detect faulty or poorly made connections. Test results are important in full load loss measurement v) Oil dielectric test to confirm the electrical strength of the transformer oil vi) Separate source voltage withstand test to determine the integrity of the insulation between windings and earth vii) Induced over voltage test at high frequency to verify voltage withstand strength between the windings and Earth, the withstand strength between the phases, and between turns of a phase under test viii) No load test (core loss- hysteresis loss and eddy current loss) to determine the No Load losses of a transformer. It also checks whether any damages have been caused to windings and insulation from prior tests ix) Full load loss test (copper losses) to assess the Full Load Loss (copper loss) and the impedance voltage of a transformer x) Zero sequence impedance test to determine the zero sequence impedance of the transformer 16 | P a g e xi) Sound level test to determine the sound level of the transformer xii) Temperature rise test to determine the temperature rise of the transformer xiii) Measurement of electrical break through voltage of copper wire to assess the insulation of copper wire xiv) Dry power frequency voltage withstand test to identify any flashover or punch of the bushings xv) Pressure testing to ensure that the finished transformers withstand high pressure and to detect any leak points xvi) Capacity or Rating Test Refer to Annex 8 for the FAT Checklist for Transformers. 6.2.3 Conductors The following tests should be carried out in accordance with IEC 61089 and IEC 889; i) Tensile tests to confirm tensile strength of conductors ii) Wrapping tests to determine ductility of conductors (how easily it can be wound and twisted) iii) Electrical resistance measurements to determine the DC resistance iv) Conductor grease test to determine the resistance to corrosion and rust v) Verification of dimensions of cable including measurements for strand diameter of strand, overall cable diameter, cross sectional area and number of strands. vi) Visual examination including Surface Condition inspection vii) Zinc coating thickness test viii) Lay ratio and Direction of Lay ix) Breaking Load Test x) Elongation Test xi) Tests on XLPE Insulation including measurement of nominal insulation wall thickness. Refer to the FAT checklists in Annexes 9-18. 6.2.4 Insulators Tests are carried out for the different insulators a) Composite line post insulators tested in accordance with IEC 61952 and IEC 62217 i) Tensile load test ii) Visual examination 17 | P a g e iii) Verification of dimensions iv) Tests on interfaces and connections of metal fittings Thermal-mechanical pre-stressing Water immersion pre-stressing Verification tests / visual examination Steep-front impulse voltage test Dry power frequency voltage test v) Test of housing Accelerated weathering test Tracking and erosion test Flammability test vi) Test for the core material Dye penetration test Water diffusion test vii) Assembled core load tests Verification of the maximum design cantilever load Tensile load test viii) Dry lightning impulse withstand voltage test ix) Wet power frequency test x) Cantilever failing load test Attached is the checklist for Composite Line Post Insulators in Annex 16. b) Pin insulators tested in accordance with IEC 60383 i) Power frequency puncture voltage ii) Mechanical failing load test iii) Porosity test iv) Verification of dimensions v) Visual inspection Attached is the checklist for Pin Insulators in Annex 17. c) Dead end strain insulators tested in accordance with IEC 61109 i) Steep front impulse voltage withstand test ii)Lightning impulse flashover voltage test iii) Radio interference voltage test 18 | P a g e Attached is the checklist for Dead End Strain Insulators in Annex 18. 6.2.5 Bulk Meters The following tests shall be carried out during the FAT: i) Environment Tests ii) Accuracy Class Test iii) Voltage and Frequency Variation Test iv) Burden test and load test under minimum, maximum and average load v) Mechanical strength test (Degree of protection) vi) Voltage Withstand vii) Registers and Energy Flow Direction viii) Time and Synchronization ix) Meter Markings 6.2.6 Metering Unit The following tests shall be carried out during the FAT: i) Voltage withstand tests ii) Secondary impedance and voltage withstand. Tests for Secondary VT and CT winding. iii) Insulation resistance test iv) Ration tests for both VT and CT v) Accuracy class for both VT and CT vi) Magnetization characteristic and the Burden for the CT and VT vii) Terminal Markups viii) Degree of Protection for the Unit 6.2.7 Circuit breaker (Auto-Recloser) i) Voltage withstand ii) Contact resistance measurement iii) Continuity test for voltage and current (Secondary) Circuit iv) Tripping and closing time v) Arch resistance test and arc discharge vi) Auto-Reclosing time/cycle vii) VT Secondary winding voltage withstand viii) CT Secondary winding voltage withstand 19 | P a g e ix) Short circuit current withstand x) Insulation resistance xi) Winding resistance for VT and CT Secondary xii) Protection Schemes and characteristics xiii) Minimum fault pick up levels for each scheme xiv) External analogue input testing facility for both VT and CT (Shorting facility for CT and opening facility for the VT) xv) Communication to Remote operation xvi) Signaling: Local signaling; Remote Signaling xvii) Current Loggers; fault invents storage and retrieval xviii) Communication protocols active xix) Operation Counters tests xx) Terminal Marking xxi) Ingress protection for Control panel xxii) Controls: Mechanical and Electrical operation; Remote and local operation 6.2.8 Air Break Switch i) Voltage Withstand ii) Contact resistance iii) Insulation Resistance test iv) Arch resistance measurement v) Electrical Discharge vi) Closing and opening time at Nominal load vii) Rating/Current Rating 6.2.9 Load Break Switch i) Voltage Withstand ii) Contact resistance iii) Insulation Resistance test iv) Arch resistance measurement v) Electrical Discharge vi) Closing and opening time at Nominal load vii) Rating/Current Rating viii) Electrical operation and mechanical operation controls ix) Remote Control and local Control 20 | P a g e x) Tripping and closing xi) Signaling to Remote 6.2.10 Accessories (LV and MV) i) Dimension measurements and quality of workmanship ii) Tests for thickness of Galvanization (where applicable) iii) Mechanical Strength tests such as Tensile Strength Test iv) Visual inspection for conformity with specification v) Inspection for markings vi) Confirmation of material composition vii) Suitability for application for which it is intended The manufacturer shall avail steel or aluminum quality test reports where applicable. FAT Report The Engineer shall submit an FAT report including the following: Chapter one: Introduction – details of contract, brief of procurement process and relevant approvals issued, FAT Team composition Chapter two: Assessment of manufacturer’s Legal and Regulatory Compliance certification and experience (Checklist is attached in ANNEX 19) Chapter Three: Factory and Manufacturing Process Assessment Chapter Four: Methodology (Testing procedures used, sampling methodology) Chapter Five: Product Tests Chapter Six: Recommendations and Conclusion Attachments: Material Test Reports and Checklists Inspection upon delivery to site This shall be done for all equipment to assess damage (if any) caused during transportation and delivery. It will be carried out as part of the monthly site inspections. Where applicable, the Engineer shall move with the list of materials’ serial numbers issued by the manufacturer during the FAT and carry out a visual Inspection to confirm delivered quantities and serial numbers at the site store or yard. The Engineer shall prepare a report after this exercise which shall at the minimum include: Chapter One: Introduction – contract particulars, materials being inspected 21 | P a g e Chapter Two: Confirmation of manufacturer of materials as per the approval of manufacturer and material specifications. Chapter three: Confirmation of quantities as per the FAT report and packaging lists. Chapter Four: Observations from physical inspections of materials Chapter Five: Observations from dimension measurements Chapter Six: Observations from confirmation of engravings and labels Chapter Seven: Results from penetration tests for poles. For CCA treated poles, sample retention tests shall be done using a handheld spectrometer Chapter Eight: Recommendations and Conclusions Attachments: Pictorial evidence of activity, copies of delivery notes 22 | P a g e 7 Considerations for Effective Contract Management General Considerations This section discusses some key considerations to effectively manage contracts. This includes managing additional scope; managing project cost: payment certificates; project time management; performance appraisals; and change management. The Engineer shall be careful to read the Contract under supervision. The Contract shall either be an Ad-measurement or Lump Sum Contract. 7.1.1 Managing Additional Scope The Contract manager shall identify the need for additional works, and communicate this need to the contractor to furnish the agency with the detailed survey drawings and bills of quantities at the at the same price rates of the original contract. The Consultant shall write a financial and technical evaluation report to back up the viability of the schemes. The PMU shall then review the above mentioned documents and submit to Procurement and Disposal Unit for onward action. 7.1.2 Managing Payment Certificates The Contractor shall submit to the Project Manager monthly statements of the estimated value of the work executed less the cumulative amount certified previously. Such statements shall be submitted monthly prior to the monthly site inspection. Based on the facts collected from the site, payment assessment and certification shall be made by Engineer. The certificate shall then be forwarded for payment. The detailed process through which the Certificate goes is illustrated in Figure 1 below. The minimum time required for: a). Donor funded projects is: 66 Days b). Government of Uganda projects is: 31 Days The CMT Evaluation shall be done jointly and the Environmental Officer, Wayleaves Officer, Outreach officer shall sign on IPC CMT Clearance Form (attached in Annex 20A) after stating clearance or objection to payment of the items claimed for in that Certificate. 23 | P a g e Figure 1: IPC Processing Stages, Responsible Parties and Timelines Transporter Project Funder Preparatio n and Submission Contractor ED REA (Registry) Manager Finance Ministry of Finance registry Donor Funded Projects Payment (e.g. by DHL) Transportation to Funder Processing Approval Processing Processing Processing 15 Days 10 Days 1 Days 3 Day 3 Days 5 Days 1 Days Consultant Project Engineer Assessmen Assessmen t 4 Days 4 Days Project Coordinato Review Review Review Approval Processing Processing Accounts Departmen t Processing 1 Days 1 Day 1 Day 3 Day 3 Days 2 Days 2 Days MPDM DED-TO ED Manager Finance Principal Accountant ED DED-TO MPDM Review Review 2 Day 2 Day Audit Review 7 Days GoU Funded Projects Payment 3 Days Note: All days are working days CMT assessment shall be done by the Project Engineer, Environmental Officer, Wayleaves Officer, Outreach officer 24 | P a g e Some of the key points the Engineer and the CMT should note include: a). The certificate shall be developed cumulatively. Refer to Annex 20B for the format of an Interim Payment Certificate. b). The proportion of payments retained in percentage is: 10%. c). The amount to be withheld for late submission of an updated Program is: 0.2% of the contract sum. d). Liquidated Damages: If so stated in the Special Conditions of the Contract (SCC), the Contractor shall pay liquidated damages to the Employer at the rate per day stated in the SCC for each day that the Completion Date is later than the Intended Completion Date. The total amount of liquidated damages shall not exceed the amount defined in the SCC. The Employer may deduct liquidated damages from payments due to the Contractor. Payment of liquidated damages shall not affect the Contractor’s liabilities. If the Intended Completion Date is extended after liquidated damages have been paid, the Project Manager shall correct any overpayment of liquidated damages by the Contractor by adjusting the next payment certificate. The Contractor shall be paid interest on the overpayment, calculated from the date of payment to the date of repayment, at the rates specified in the Contract. The Certificate should entail the following: Contract Name and Procurement Reference Contract Details: Funder, Contractor, Status on insurance covers and securities (Include expiry dates of Advance Payment Guarantees; Performance Securities; Insurance Covers) e.t.c Progress of works Certification (in table form) Recommendations Attachments: Engineer’s Assessment in form of BoQs (where applicable), Engineer’s Progress Report, Contractor’s claim, Copies of all Delivery Notes, Bill of Lading, Commercial Invoice, Packaging Lists, Manufacturer’s Warrantee Certificate, Insurance Certificate, Certificate of Origin, valid Copies of Advance Payment Guarantees, Performance Securities and Insurance Covers. The Contractor can employ methods to manage project cost such as Earned Value Analysis. 25 | P a g e 7.1.3 Managing Time Extension The Engineer shall monitor the project time using the Project Schedules presented in the Project Implementation Plan. One recommendable tool that can be used to monitor time is MS Project using Gantt charts, critical path method. In case more time is required to complete Project activities, a Change Order shall be issued. The contractor shall formally request for time extension with justification. The Engineer shall review and recommend for time extension if the grounds are acceptable. This shall be issued through a Change Order. (Attached as Annex 21) Unjustifiable extension shall be granted subject to enforcement of liquidated damages Note: In-case there is a cost implication involved, a contract variation shall be initiated by the Engineer. 7.1.4 Managing Performance a) Contractor’s Performance Appraisal The Contract Manager shall appraise the Contractor quarterly in line with the Contract Assessment Tool (Annex 38). The assessment reports shall form part of the project closure report. The overall performance from these assessments shall inform the completion certificate b) Consultant’s Performance Appraisal The Consultant shall be appraised quarterly using the Contract Assessment Tool (Annex 39). The assessment reports shall form part of the project closure report. The overall performance from these assessments shall inform the completion certificate 26 | P a g e 7.1.5 Change Management Table 3: The table showing the Change Management process RESPONSIBLE PERSON STAGE a) Submission of Change Request DETAILS/ PROCESS Background to the issue Proposal No Contract Contract Amendment Amendment Stakeholder Stakeholder Justification/ Benefits b) Review and Assessment Justification Engineer Engineer Project Manager -Contracts Committee -PDU -Accounting Officer Accounting Officer Implementation of Change Project Manager Contractor Supervision and Monitoring Engineer Engineer Post implementation Review Engineer Engineer Cost/ Benefit Analysis Impact on Cost Impact on time Impact on Quality Impact on stakeholders Qualification Assessment of liquidated damages Recommendation c) Approval Review Approval d) Implementing Change Order Approval subject to liquidated damages Communication of Change Contractor 27 | P a g e 8 Site Office, Store and Yard Inspection The contractor shall have a site office located within the project area. It shall have the following: a) The Site Office shall have the following documents: i). Copy of the Contract ii). Updated Monthly Implementation Plan and copies of the previous ones iii). Copies of Approved Technical specifications for all materials including accessories iv). Copies of Approved Design and Survey Report (Survey Drawings, Structural drawings, e.t.c.) v). Organogram clearly indicating names and roles of employees vi). ESMP – Environmental and Social Management Plan and associated work procedures including waste management and restoration plans vii). Instruction Books – these shall be in Triplicate (self-carbonating) specific to the project with the project name and contractor’s address printed on every page. It shall include sections for Instructions, Date and Signature. viii). Daily Logbook (Should include: Section worked on, Date, Number of Workers who have worked that day, Actual work done, Weather conditions, Incidents on site) ix). Complaints register x). Visitors’ book xi).HSE Policies and work procedures b) The Site Store should have the following: i). Dedicated Store Manager ii). Fencing iii). Security iv). Fire extinguisher v). Material receiving forms vi). Appropriate and adequate sanitation facilities vii). Material Dispatch book viii). Delivery Notes from suppliers ix). Updated Quantities of materials in store (Inventory) 28 | P a g e x). Visitors book xi). HSE policies and work procedures xii). CESMP c) Yard i). Vegetation growth shall be well maintained ii). The yard shall be spacious enough to accommodate materials iii). There is security iv). The yard shall be accessible to the site in accordance with environmental management plan d) Health and Safety Considerations: the following should be existent on site to ensure the health and safety of the contractor i). Contractor’s Health and Safety Manual ii). Personal Protective Equipment – Helmets, gloves, uniform, overalls, safety boots, sound protectors e.t.c iii). First Aid Kit iv). Sign Posts such as “Men at Work” v). Condoms vi). Appropriate and adequate sanitation facilities vii). CESMP viii). HSE polices and work procedures Refer to Annex 22 for the Site Store, Office and Yard Inspection checklist Action by REA The Engineer shall use the above mentioned checklist to ensure compliance and the findings shall be included in the monthly progress report. 29 | P a g e 9 Construction Site Supervision Site supervision exercises shall be conducted at least once a month with all relevant project stakeholders. This shall include REA’s representatives (Project Engineer, Community Outreach Officer, Environmental Specialist, Way leaves Officer), Consultant’s personnel, Contractor’s personnel, Service provider and Community Focal persons. Project Supervision by REA Engineer The Engineer shall use the Construction Manual as reference on how construction activities can best be carried out to ensure quality power lines are constructed. The Engineer shall do a walk-patrol while inspecting works carried out on the power line and the following minimum checks shall be done at each stage of construction: a) Pit Excavation The foreman should fill out the quality control form for all completed pole and stay pits. This form shall be filled by the contractor’s, signed by the contractor’s engineer, Consultant and REA’s supervision engineer. Prior to signing of the quality control form, REA’s engineer, shall take a sample of the pits indicated in the quality control form and confirm the depth of pits, take note of changes in the line route and structure type as well as span lengths. Any changes to the approved design shall be captured in the quality control form. Check that pole pits have been excavated to the right depths (1/6 of the pole height) and widths. Ensure that poles are positioned prior to pit excavation. Take note of the type of soil where each pit has been dug. After the inspection and verification of all pits, the Engineer or his representative shall issue an approval prior to pole erection. b) Pole Erection Ensure that all poles erected are in a good physical condition as per the REA Pole Treatment, Handling, Transportation and Erection Manual. Ensure that in swampy areas, murram is adequately filled. Erected poles must be fitted to be firm, plumb and are properly aligned with other structures in the line route. Poles should not be interfered with by cutting to make up for shallow pits. Verify that the poles erected have the manufacturer’s pole tags. 30 | P a g e Confirm that the wood poles are not tempered with by cutting at the top or butt to makeup for short pole pits or create clearance especially for LV poles. Ensure that the pole color coding for different pole sizes and ground line distance is marked on the pole. For construction of lines with overhead continuous earth-wire, ensure that the earthwire is installed on every other pole for both MV and LV. No pole shall be erected without earth-wire. After the inspection and verification of erected poles, the Engineer or his representative shall sign pole erection quality control form and issue an approval prior to dressing. c) Dressing Check to ensure that all the required pole hardware and accessories as per the approved structure drawings have been installed on the respective structure type. After the inspection and verification of all dressed pole structures, the Engineer or his representative shall issue an approval prior to conductor stringing. d) Installation of Stays Ensure that the required number of stays per structure, as per the approved structural drawings have been installed. Ensure that stay pits are to the standard depths (1/6 pole height). Ensure that the required materials for a stay assembly as per the REA structural drawings are there. Ensure that the stay blocks are concrete or galvanized steel plates. Wooden stay stabs shall not be used. After the inspection and verification of all stay assemblies, the Engineer or his representative shall issue an approval prior to tensioning and sagging. e) Conductor Stringing Ensure that stringing is conducted using conductor drums installed on standard drum jerks. Ensure that conductor is not be rolled on the ground to avoid damage of conductor surface. Care should be taken while stringing/ running out conductor to avoid kinking, twisting or abrading the conductor in any manner. Stringing shall be planned in such a way that terminations are done at section structures. After the inspection and verification of all stringing works, the Engineer or his representative shall issue an approval prior to installation of stays. 31 | P a g e f) Conductor tensioning and Sagging Check that the conductors have been strung with precision to ensure that the correct ground clearance and tension is attained. After the inspection and verification of all tensioning and sagging works, the Engineer or his representative shall issue an approval prior to Installation of Jumpers. g) Jumpers for section structures Check to ensure that jumpers are of proportionate length shall be used to avoid compromising clearance during windy conditions. Jumpers joining adjacent conductors having angle of separation greater than 120% shall be supported by a pilot spindles. Ensure that a pair of adequately sized PG clamps are used in jumper terminations. The jumper contact resistance shall be tested by the contractor and consultant. After the inspection and verification of all jumpers, the Engineer or his representative shall issue an approval prior to earthing of transformers. h) Earthing of transformers Ensure that the earthing of transformers is as per the Construction Manual. Ensure that the earth values do not exceed 5 ohms for both LV and HV. The HV side and LV side of the transformer shall be earthed separately and the respective earth pits shall be located a distance not less than 5m apart. The earth wires used/running from the transformer to the ground shall be neatly stapled on the wooden structure. The earth pits shall be dug up and earth pits filled with components required for earthing such as charcoal, salt, water, copper rod among others. After the inspection and verification of all earthing works, the Engineer or his representative shall issue an approval prior to installation of surge arresters. i) Installation of Surge Arrestors Ensure that surge arrestors have been installed on all transformers, underground cables, and terminal poles. Ensure that surge arresters have installed every 10 km for lines without continuous overhead earth-wire. After the inspection and verification of all surge arresters installation works, the Engineer or his representative shall issue an approval. 32 | P a g e j) Installation of equipment and switchgear This includes Transformers, Meters and Metering units, ABS or LBS, Auto-reclosure, Circuit Breakers, etc. Ensure the equipment have been installed as per the approved structural drawings. Inspection of equipment installations shall be carried out along with the Operator….. Supervision by Safeguards Team With the commencement of works, day-to-day environmental monitoring will be carried out by the CSC Site Supervisors, and REA safeguard team shall carry out periodic monitoring. To aid this process, the contractors will have to put in place an Environmental Management System (EMS) in line with the National Environment (Audit) Regulations, 2006 and ensure that this system is signed off by REA. Under this system, the contractor will use their Environmental Specialist for coordination and internal selfmonitoring. The work of the Site Supervisors/Clerks of works will also comprise systematic observation of all site activities, as a check that the contract requirements relating to environmental matters are being complied with, and that no unforeseen impacts are occurring. Note that this monitoring will also include cross cutting issues such as HIV/AIDS awareness and mitigation, and occupational health and safety. Monitoring will take the form of visual observations, documents checks, and interviews carried out concurrently with the engineering monitoring activities and will be guided by periodic advice from the CSC Environmental Specialist as well as REA Safeguards team. Site inspections will take place with the emphasis on early identification of any environmental problems and the initiation of suitable remedial action through instructions to the contractors issued according to standard procedures. Where remedial actions have been required on the part of the contractors, further checks will need to be made to ensure that these are actually being implemented to the agreed schedule and in the required form. As experience of the principal problem areas is gained, attention will be concentrated on locations and activities which are known to be the most troublesome, with a lower frequency of inspections at problem-free locations. The Contractor will make daily environmental reports using conventional report. Assistance to the developing of these forms will be provided by the CSC Environmental Specialist. This form should be approved by the REA Environmental team. 33 | P a g e The CSC will decide on the appropriate course of action to be taken in cases where unsatisfactory reports are received from contractors regarding environmental matters. In the case of relatively minor matters, verbal advice to the contractor on the need for remedial action may suffice but, in all serious cases, the CSC should recommend an appropriate course of action to the Contractor. The CSC may withhold certificates of works approval or full payment of fees on the basis of non-compliance with the conditions of the project EIA certificate. Monthly reports shall be compiled by the Contractor which document environmental and social performance against the CEMP. This shall be verified and approved by the CSC with a copy forwarded to REA for review and action. Approval of this report will facilitate payment of the supporting item in the project BoQ to the Contractor. Monthly reports prepared by the CSC for the REA will contain a brief section referring to environmental and social matters, which summarizes the results of CSC daily site monitoring, remedial actions which have been initiated, and whether or not the resultant action is having the desired result. The reports will also identify any unforeseen environmental problems and will recommend suitable additional actions. 9.2.1 Safeguards Monitoring and Implementation Report The Project Manager shall monitor the implementation of the ESMP and prepare a safeguards monitoring and implementation report. The report shall be of the following format; Logo (optional) Project Title Name of project Report No The progress and Monitoring Report number should specify the month quarter and the year it belongs to. Reporting Period DD-Month-YYYY to DD-Month-YYYY Prepared By Individual or entity that prepared the document Contact Physical address, telephone, email, website 34 | P a g e As a basic minimum, the report shall cover the following key areas Chapter One: General Summary Description of the Project: Provide a summary description of the project. Project Location: Indicate the project location and geographic boundaries. Project Contractor: Provide contact information and roles/responsibilities for the Contractor and Sub-contractor in regard to environmental and social management aspects. Other Entities Involved in the Project: Provide contact information and roles/responsibilities for any other entities involved in support of the project. Describe key technical skills that have been deployed to implement the project successfully and demonstrate that the implementing team’s human and financial resources have been adequate to implement the project. Project Reporting period: Indicate the project reporting period, specifying the month and year for the start and end dates of the reporting period. Project Status/ Progress: Use MS Project or a management software to indicate progress of the Project Chapter Two: Implementation of Construction Environmental and Social Management Plan (CESMP) Using a table format of the CESMP, describe and demonstrate with evidence its implementation status. Compliance to component specific management plans/work procedures: Describe and demonstrate with evidence how the contractors are implementing /complying with their respective component specific environmental and social management plans/work procedures Description of the Project Safeguards strategy: Describe the project activity or activities (including the technologies or measures employed) and how it/they have achieved environmental and social management objectives of the project. Describe how project activities have helped in achieving projects environmental and social safeguards goals 35 | P a g e Management of Risks to Project Benefits: Describe the implementation of measures in mitigating environmental and social safeguards risks during the reporting period. Describe the implementation of measures that maintained and enhanced environmental and social benefits. Current Problems & Risks: What environmental and social problems and risks occurred during this monitoring period? Is there any remedial action taken? Do you have any proposals to remedy them? Any kind of bottleneck or obstacle (contractual, administrative, legal, practical and any other problems) preventing the activities to be realized and progress towards achieving the project goal should be explained. Anticipated Problems & Risks: Is there any anticipated problem or risk that may hinder project progress in the next reporting period? Do you have any proposals to remedy them? Anticipated problems in terms of environmental and social issues which have a possibility to endanger the project progress during next reporting period should be stated. The measures taken, or to be taken or any assistance required should be listed. HIV/AIDS management: Demonstrate with evidence how the HIV/AIDs management for the project has been done during the reporting period Gender aspects of the project: Demonstrate with evidence and figures how gender aspects of the projects are being implemented Employment Opportunities and Workers Safety: Describe training provided for the project’s employees and relevant people from the communities. Describe how people from the communities have been given equal employment opportunities. Describe the implementation of measures to inform workers of risks to their safety and to minimize such risks Stakeholders: Describe how communities and other stakeholders potentially affected by the project activities have been involved in project implementation process. List and describe how conflicts and grievances that may have arisen were handled. Chapter Three: Legal Status Compliance to the environmental and social safeguards requirements: Identify and demonstrate compliance of the project with all and any relevant local, national laws, statutes and regulatory frameworks as well as funder’s safeguards requirements. 36 | P a g e Include a list of all relevant laws and regulations where relevant, demonstrate with evidence how compliance was achieved. Chapter Four: Past Recommendations & Follow up from the previous reporting Period If any, the recommendations from the previous monitoring period, and the actions taken in accordance with these recommendations should be reported here. Supervising the consultant The Engineer shall ensure that the Consultant submits a quality control plan. The Engineer shall ensure that the consultant has deployed the required human resource as per the contract. The Engineer shall submit a daily report in the format provided by REA. The consultant shall also submit monthly and quarterly reports in the format provided below. The consultant shall certify works and recommend payment by submitting a payment certificate based on the contractor’s claim. The format shall be in the form of BoQs of works. The Consultant shall review and approve all technical specifications, attend FATs, issue approvals after every stage of installation works through the clerk of works. Supervision by Wayleaves Officer 9.4.1 Definitions A wayleave is an easement or right-of-way (RoW) granted by one person to another to facilitate access or passage of a Utility. Right of way: The most feasible route that leads to minimal damages. This shall be checked against the drawings. 9.4.2 Supervision Checkpoints The Wayleaves Officer shall undertake a patrol while inspecting works carried out on the power line and the following minimum checks shall be done: a) Check that the power lines are not routed over people’s buildings or in a way that affects their land without their consent. 37 | P a g e b) Ensure and emphasize that the cuttings/destructions made are within the wayleave corridor/trace which is 5 -10metres in trading centers and 10-20metres in forested areas. While clearing this trace, the contractor must avoid wanton destruction of project affected persons property. The measurements given in table 4 constitute the total width of the wayleaves corridor/trace and depend on the voltage being transmitted as indicated. Table 4: Widths of Wayleaves Corridor S/N TYPE OF NETWORK WIDTH (METERS) 1 LV network 5 2 11/33kV single circuit line 10 3 33kV double circuit line 20 c) Land Entry: Emphasis shall be made concerning negotiation before the contractor and subcontractor access one’s land d) Consent: Ensure consent is obtained starting from the local leadership to the communities. Further consent shall be obtained from land owners where the transformer structures are installed. Building a power line without wayleaves consent is tantamount to building an illegal line, which is bound to be challenged for removal one time or another. Hence the contractor can only proceed with works after obtaining consent. In this regard, the Contractor shall be provided with free wayleaves consent forms. The contractor’s social/wayleaves officer shall move with the LC chairperson to obtain consent from the locals prior to construction and the forms kept in a file that the REA wayleaves officer shall review. The contractor should notify the Wayleaves Unit of any line alterations that may be needed and can only proceed with construction works after the firm has duly served notice and obtained consent from would be affected land owners. 38 | P a g e Supervision by Outreach Unit 9.5.1 Definitions Community outreach is an act or practice of visiting and providing services to people who might not otherwise have access to those services. Community outreach unit is under the project development and management department. It is responsible for engaging communities in REA’s project areas so as to influence their attitudes and perception to accept and support the project in a given area or district. Several problems come up as a result of the project in an area and as such sensitization is one of the key elements. The community outreach unit’s main objective is to make the people appreciate the projects in their communities so as to create easy way leaves for the contractors and also sensitize the rural people on the advantages and benefits of electricity in rural areas. 9.5.2 Supervision Checkpoints The Community Outreach Officer shall undertake a patrol while inspecting works carried out on the power line and the following minimum checks shall be done: Plan and implement community outreach strategies that advance REA’s mission and goals Plan and direct rural electrification awareness campaigns in relation with other relevant government entities by the use of media, workshops and meetings. Mobilize communities in established service territories to initiate cooperatives to manage the supply of electricity to themselves. Assist community groups in identification of productive income generating activities and educate them on how to benefit from these activities. In collaboration with the corporate unit and engineering teams, organize and manage project launching and commissioning events. Contribute towards the preparation and implementation of project work plans together with the planning and project development and monitoring teams as well as the way leaves office. Prepare quarterly and annual progress reports in the area of community outreach. The measurements and details given below in the table are tools we use when in the field 39 | P a g e Impact Capture Result the of Identifying the problem stimulate Analyzing the context interest Defining the purpose of raising awareness Improve public knowledge and Gathering and exchanging information understanding Improving self-understanding of the situation Building trust in decision making Empowering stakeholders to break barriers Developing new ideas Developing new relationships Mobilize willingness to act Gather adequate resources Foster partnerships Change social attitudes and behavior Monitor progress Evaluate results communities attention and Enhance social skills Increase capacity Implement change 9.5.3 Issues Addressed a) Entry into Communities prior to construction works Project acceptance and soliciting community support is done when we are entering communities whereby we sensitize the rural people on the advantages or benefits of electricity and how it will have a positive impact in their communities. Way leaves acquisition is also done when entering a given community whereby we educate the local people on the procedure of way leaves and give them consent forms to sign allowing the contractors to start doing their jobs. Environmental aspects is another key factor we talk about while addressing communities since they also benefit from the environment and have to protect it from bad practices like bush burning which ends up polluting water bodies and the air hence air pollution. Healthy and safety is also important when addressing a community you have just entered since people need to take proper precaution when using electricity to prevent accidents that may be harmful to their health. 40 | P a g e Orientation of contractors and project areas is also done before and after entering communities to ensure that the contractors use the proper code of conduct when they are in the field so as to be on their best behaviors when carrying out their duties to avoid complaints and conflicts that may slow down the project. Establishing important networks in the community like local leadership, opinion leaders and respected elders is also a very important tool when entering communities because these are the same people who will be helping us in community mobilization and other related activities. Information on concession of the network is another important tool which can be useful in the field when you want to know the rates and tariffs of a given service provider in determining which electricity rates work in a given service territory. b) Preparing Communities to consume electricity Dealing with the attitudes and perception towards the use of electricity whereby the rural people have to be sensitized about the advantages or benefits of electricity for instance how it will help them get employment opportunities and improve on their standards of living. Readiness to consume: house wiring, procedures for connection, tariffs etc. This is done when bringing electricity to a given area or district whereby the local people are educated on the productive use of energy and energy efficiency so as to identify potential candidates. Health and safety in relation to electricity use; Electricity can severely injure people and cause damage to property however simple precautions can be taken when working with or near electricity to reduce the risk of injury to the people around it. The main hazards of working with electricity are: Electric shock and burns from contact with live parts Injury from exposure, fire from faulty electrical equipment Explosion caused by unsuitable electrical apparatus Productive use of energy i.e. investment opportunities in the energy sector; Productive use of energy is the basis for long term sustainable development intended by rural electrification programs to help the rural people improve on their standards of living by accepting electricity which will help them develop in many aspects of life. 41 | P a g e Use of electricity to add value in the agro process; This is done by sensitizing the people about how they will benefit from electricity through building small scale industries that will help them is processing their crops like maize, beans etc and also create employment opportunities for others. Energy efficiency; this refers to using energy well with a goal to reduce on the amount of energy required to provide goods and services. It also refers to using less energy to accomplish the same amount of work per unit of the energy which is often described as a measure of energy intensity. Promoting community policing against extortion, energy theft and vandalism is also something that we do when entering communities by creating awareness through sensitization whereby people are advised to keep their property safe and not engage in bad acts like bribes so as to get electricity through the right channels. c) General awareness creation and accountability to the public on RE in Uganda Policies governing rural electrification Status update and planned workshops for MPs Promoting the electricity cooperative model Investment opportunities in the energy sector Key partners in the energy sector and the roles the different players play d) Social responsibility within the communities that REA is operating Tree planting in conjunction with environmental unit Support to sports teams in schools and community Sponsor events Incorporating gender mainstreaming into all REA projects processes including feasibility studies Carrying out formative and evaluative monitoring and evaluation during and after project implementation to establish impact. 42 | P a g e 10 Progress Reporting These will be written by all focal stakeholders as indicated below; Clerk of Works This daily report should include specific details of work done in all project areas. It shall be in the format shown in Annex 23 and be submitted daily through appropriate communication media before close of business. Hard copies should be filed and kept in a file at site. Project Engineers Progress Reports Upon review of the clerk of works report, the Engineer shall generate a report which shall be submitted every two weeks. The format is attached as Annex 24. Also, after every site inspection, the Engineer shall submit a monthly report including: Chapter one; Introduction, Background, Project Objectives, Contract particulars Chapter two; Approvals issued (Include expiry dates of Advance Payment Guarantees; Performance Securities; Insurance Covers) Chapter three; Stakeholders engagement – district meetings, site meetings, interactions with the community, service providers Chapter four; Findings from the site inspection – stores, yard, office, quality of workmanship, level of deployment, observations and instructions from the works inspection including aspects of; engineering, environment (consideration for forest reserves, wetlands, trees, crops, human settlements, tourist/cultural sites), social (engagement and participation), health and safety (accident, use of PPE, safety of people around) Chapter five; Progress of Works (Actual vs Planned). An S-Curve shall be developed to compare actual work against the planned work. The S-Curve shall be developed based on design works, procurement both local and overseas and installation works and all this shall be based on the revised project schedule submitted by the contractor and approved by the consultant and REA. Chapter Six: Plan for the proceeding works. 43 | P a g e Chapter Seven: Update on payments, date certificate was submitted, amount paid and date payment was made Chapter Eight; Assessment of the consultant’s performance Chapter Nine; Status of risks identified from previous reporting periods, Risks identified and recommended mitigations measures Chapter Ten; Recommendations and Conclusions Contractor’s Monthly Progress Reports This report should include in detail, but not be limited to; Chapter one; Introduction, Background of the project, Project objectives, Contract particulars Chapter two; Update on payments; Status of payments, Date certificate was submitted, amount requested for, amount received and date payment was received, Planned value of works vs actual value of works claimed. Include statement of value of works thus far. Chapter three; List of materials at the site stores to support claims made in certificate Chapter four; Resource deployment for the next month, Personnel (details on sub-contractors if any), Tools and equipment, Materials Chapter five: Summary of approved construction methodology Chapter six; Progress of works and actions taken to address instructions given at previous site inspection including aspects of; engineering, environment. This should cover planned against actual and reasons for deviation from plan should be given. Chapter seven: Implementation of the contractor’s ESMP Chapter eight; Update on works completed within the previous month Chapter nine; An updated work schedule for the next month Chapter ten; An updated procurement schedule Chapter eleven; Risks identified and recommended mitigations measures Chapter twelve; Pictorial evidence of major milestones and issues Appendix; MS Project – tracking of project 44 | P a g e Consultant’s Progress Reports The consultant will submit both monthly and quarterly progress reports which should include in detail, but not be limited to; Monthly report: Chapter one; Introduction, Background, Project Objectives, Consultant’s contract details, summary of works contract. Chapter two; Deployment of Personnel, work done and actual input man hours and resources (logistics) deployed to facilitate smooth running of the activities Chapter three: Assessment of level of compliance to Approved Engineering Design and Survey Report Chapter four: Monthly ESMP Chapter five: Consultant’s Updated Monthly Quality control plan Chapter six; Update on progress of works (Actual vs Planned monthly works) This section shall be presented through the updated Project Completion Work Schedule and shall clearly indicate the following: i). Percentage completion, completed schemes, Milestones due, Bar graphs showing both percentage completion and completed schemes. ii). Late tasks In addition to this, the Consultant shall also prepare progress using an S-Curve. Chapter seven: Updated works’ monthly implementation plan Chapter eight; Update on contractor’s payments; update on consultant’s payments Chapter nine; Risks identified and recommended mitigations measures; Status of risks identified Chapter ten: Statement of performance of contractor Chapter eleven; Conclusions Attachments: Pictorial evidence of major mile milestones and issues Quarterly reporting: In addition to the content of the monthly report, chapters on the following should be included in the quarterly report 45 | P a g e Quarterly supervision work plan Overall project performance Analysis of trends and recommendations for improvement Consultant shall prepare a quarterly presentation to the client. The presentation shall focus on work progress, financial appraisal, risks identified and their mitigation measures, quality control measures, challenges met, environmental & social impact. 46 | P a g e 11 Pre-Commissioning, Commissioning and Project Completion Introduction The contractor shall schedule and communicate his need for shutdown schedules in time, 2 months prior to the proposed date. The Engineer shall always communicate the Monthly Shutdown Schedules to the Contractor as and when provided by the Service Providers. Upon completion of works, the contractor shall formally communicate to the Consultant and REA which shall then schedule a Pre-Commissioning date. On successful completion of this exercise, the commissioning and handover of the power network shall then be carried out. Procedures for both activities are explained below. Upon successful commissioning of the power line, the contractor shall request the Project Manager to issue a Certificate of Practical Completion of works, and the Project Manager will do so upon deciding that all the works are complete. The employer shall take over the site and works within seven days of issuing the Certificate of Practical Completion. However, the Contractor is liable for any defects that may arise during the Structure by Structure Audit and Defects Liability Period. Pre-commissioning exercise 11.2.1 Participants and Deliverables Success of this exercise requires full participation of the Client, Consultant, Contractor, Poles’ suppliers, Sub-contractors and designated Network Operator (Letters of invitation for commissioning are Attached in Annexes 25[General], 26 [UMEME], 27 [UETCL], 28 [UEDCL]). The Contractor shall furnish the Consultant and Client with the following documentation: i). As-built drawings (all LV beneficiaries shall be indicated) ii). Pole schedules complete with, but not limited to, Structure Types, Pole Heights, Span lengths, Chainage, Number of Stays, Angles and GPS coordinates for both MV and LV structures. iii). Warranties for materials iv). Operation and maintenance manuals for materials. v). Test Certificates/ Reports for materials 47 | P a g e The date by which operating and maintenance manuals are required is: ten (10) days before commissioning, except otherwise stated in the Contract of Works. The amount to be withheld for failing to produce “as built” drawings and/or operating and maintenance manuals by the date required is two percent (2%) of the final contract price. 11.2.2 Final Inspections The team shall patrol through the line to ascertain that the works done are to the required standards of quality. It is at this stage that a snag list, if necessary, shall be generated and remedies to rectify them shall be agreed upon. Also, the REA GIS Unit, along with the Consultant and the Contractor, shall review the As-built drawings for correctness. The approved As-built drawings shall inform the Project Manager during the preparation of the Contractor’s final (Penultimate) payment Certificate. 11.2.3 Network Testing The team shall also carry out No-load tests and On-load tests on the network as listed below: a) No-load testing of the network The tests carried out include; i) Pole sounding ii) Visual inspection of the network for adherence to the Engineering Design and Survey Report. iii) Measuring of earth resistances using an Earth Resistance Tester. b) On-load tests of the network The tests carried out shall include; i) Testing of transformers (refer to Annex 29) ii) Configuring of bulk energy meters, configuring switch gears iii) Network protection grading The expected outcome of this activity is a detailed Pre-Commissioning report from the Project Engineer/Manager highlighting the following; 48 | P a g e Chapter one: Contract particulars Chapter two: Stakeholders present at pre-commissioning exercise Chapter four: A detailed snag list, corrective remedies and timelines Chapter three: Summary of the off-load and on-load testing Chapter five: Recommendations and Conclusions Chapter six: Pictorial evidence of activity Attachments: Transformer Commissioning Report (See Annex 29), Metering Unit Commissioning Report, Auto-reclosure Commissioning Report, Signed attendance list of all participants Commissioning and Handover Exercise The power line shall be commissioned only after all snags have been rectified. Upon submission of all contractual deliverables and correction of snags identified at the pre-commissioning, the contractor formally communicates to REA to set a commissioning date. Success of this exercise requires full participation of the client, consultant, contractor, designated network operator and the community members. The activities carried out include; Confirmation that snags identified at the pre-commissioning have been rectified Engagement of the local community members by the community outreach team Handover of power network to operator The expected outcome of this activity is a detailed commissioning report from the Project Engineer/Manager highlighting the following; Chapter one; Contract particulars Chapter two; Stakeholders present at commissioning exercise Chapter three: Brief on Commissioning Function Attachments: Pictorial evidence of activity, Original Copy of the Asset Handover Instrument Certificate of Practical Completion The contractor shall request the project manager to issue a certificate of practical completion of works, and the project manager will do so upon deciding that the work is complete. The employer shall take over the site and works within seven days of issuing 49 | P a g e the certificate of completion. However, the Contractor is liable for any defects that may arise during the Defects Liability Period. Refer to Annex 30 for a template of the Certificate of Practical Completion Project Completion Report After commissioning, the Engineer shall write a project completion report and it shall include the following: Chapter one: Background information including Contract particulars, Objective of the project, output, Number of Connections Chapter two: Project performance assessment – Final account of cost, scope, duration of the project (Contractual vs As-Built). This will be guided by the structure by structure audit. Chapter three; Administrative reviews. This will be guided by the overall performance assessment of the contractor, as guided by the contractor’s performance assessment tool Chapter four: Administrative reviews. This will be guided by the overall performance assessment of the contractor, as guided by the consultant’s performance assessment tool Chapter five: Lessons learned Chapter six: Recommendations and Conclusion Attachments: Certificate of practical completion, commissioning test reports, Structure by Structure Audit report Attachments: Pictorial memory lane Structure by Structure Audit Upon completion of the project and production of the as-built drawings of the network, all major stakeholders including the client (planning, GIS, audit, PDM and STDO representatives), contractor, consultant, service provider, pole suppliers and suppliers of key network equipment. The main objectives of this exercise shall be: i). To confirm the status of the entire network at the time of completion. ii). To ascertain the soundness and/or the integrity of wood poles used on the project iii). To confirm Suppliers or manufacturers of poles iv). Receive and sign-off warranties for poles and other key network equipment v). To inspect and certify the quality of workmanship 50 | P a g e vi). To facilitate the preparation of the project final account. Data from this exercise shall be collected through three (3) major techniques: a) Visual Inspection This technique shall be used to obtain data regarding span length (a tape measure may be used if the need arises), mechanical damage, detect missing items or accessories, level of workmanship, corrosion of hardware, termite attack, insect attack, fungi attack, presence of a number and danger plates and any other snags that may not be covered by the audit tool. b) Pole Sounding This shall be used to test for hollowness of the poles. An individual shall hit the pole at least twice and listen for sounding to determine whether the pole is hollow or solid. c) Ground-line inspection The team shall take measurements for residual retention for CCA treated poles using a handheld spectrometer analyzer. Sampling shall be done at a rate agreed upon by the inspection team. d) Use of tree caliper This shall be used to measure the theoretical ground-line for all the poles to determine whether the pole sizes are adequate. An individual shall hold the tree caliper as close to the ground as possible on the pole or at the theoretical ground line marking/ painting placed by the manufacturer and take the reading on the tree caliper. This test shall be done if requested by the Project Manager or Client. The expected outcome of this activity is a detailed Structure by Structure Audit report from the Project Engineer/Manager highlighting the following; Chapter one; Introduction including Background of the Project, Contract particulars, Stakeholders present at the inspection. Chapter Two: Methodology Chapter Three: Discussion of findings; Quantified results showing locations; include any other snags and/or issues identified Chapter Four: Statement on certification of the As Built Infrastructure Chapter Five: Recommendations and Conclusion 51 | P a g e Attachments: Pictorial evidence of activity, Structure by Structure Audit reports (Refer to checklist attached in Annex 34), Drawings used during the audit (drawings shall have GPS Coordinates) The report shall be signoff by all the members. This activity shall be carried out prior to the close of DLP and the report shall form part of the project completion report. Note that the success of this exercise requires full participation of the Client, Consultant, Contractor, Pole suppliers, Sub-contractors and designated Network Operator. 52 | P a g e 12 Connections General Guidelines The contractor shall work with the client (REA), the community and the service provider to bridge the gap between the service provider and the targeted consumer. This shall include community mobilization to facilitate mass application for electricity service, facilitate the service provider to enable mass application and connection, provide technical assistance to the service provider including training on meter calibration and general end user installation practices. The Engineer shall ensure that every single phase no-pole service connection entails the following materials as stipulated by ERA. SN. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Table 5: Materials for single phase no-pole service connection QTY. (NO. OF ITEM DESCRIPTION UNIT UNITS) Single phase meter Piece 1 Meter box Piece 1 Circuit breaker (63A) Piece 1 Key pad (CIU) Piece 1 Key pad cable Piece 1 Communication cable Meter 50 Wall plugs/ Screws (3/2’) for fixing meter Piece 4 box Screws (1’) for fixing meter Piece 4 Seals for meter and meter box Piece 4 Single core cables (10mm)/meter tail Meter 0.3 Tower clips Piece 1 Preformed dead end Piece 1 Landing/wall bracket Piece 1 Cable, Solidal 16mmsq Meter 35 PG Clamp/line tap Piece 2 Hoop iron/ meter tie/bandit strapping Piece 2 Connectors Piece 2 Coach Screw Galv 75X12 Piece 1 Clamp Strain OH-Conc-10-16mmsq Piece 1 For customers who have been connected using Ready boards, the Engineer shall ensure that it is installed at least 150cm from the ground level and shall incorporate: Double pole MCB 20AMPS 2x square pin sockets (BS 1363) 53 | P a g e Passive base to receive prepaid meter or customer interface unit (CIU) All mounted on rails Bulkhead light with bayonet fitting Light switch 5AMP Earth bar and neutral bar The Engineer shall monitor the number of connections made by the contractor, especially during the DLP period, to ensure the target number of connections is achieved. Earthing Kit The earthing shall constitute of the following: a) A copper bonded earth rod. Accessories to be supplied together with the rod shall include: Standard Ground Rod Clamps High Strength Ground Rod Couplings Driving Studs Rod to Tape Clamp B Bond U Bolt Rod Clamp Brass Earth Clip Domestic Rod Earth Clip Suitable for cables in the range 4-25mm2 b) A complete installation shall also constitute a single core 10 mm2 earth wire measuring 10 meters 54 | P a g e 13 Defects Liability Period (DLP) Defects Liability period, 12 Calendar months, shall start on the final day of commissioning. During this period, site inspections and meetings shall be scheduled on a quarterly basis or when the need arises. The purpose of which is to find out the condition of the line, confirm that all snags identified after commissioning have been corrected by the contractor, get feedback from the stakeholders, namely but not limited to local leaders, beneficiaries, service providers among others. If there are any defects reported by the operator, the contractor shall immediately tasked to rectify them. The Contractor shall correct the notified Defect within the length of time specified by the Project Manager's notice and subsequently submit a defects correction report. If the Contractor has not corrected a defect within the time specified in the Project Manager's notice, the Project Manager will assess the cost of having the defect corrected, and the Contractor will pay this amount. A DLP Inspection Report shall be issued by the Engineer after every DLP site inspection and it shall include in detail, but not be limited to. Chapter one: Contract particulars Chapter two: Stakeholders present at DLP inspection Chapter three: Observations, instructions and timelines from the works inspection including aspects of; engineering, environment (consideration for forest reserves, wetlands, trees, crops, human settlements, tourist/cultural sites), social (engagement and participation), health and safety (accident, safety of people around) Chapter four: Consider assessment of the performance of the existing line and the new network as follows; Under the Existing network, consider the following where applicable; i). State of the wood poles, conductor, insulators and bush clearance. ii). Protection schemes iii). Faults and their respective fault drivers over an agreeable period of time (e.g. 3 months). 55 | P a g e iv). Voltages and frequency to measure quality of service v). Outages record over an agreeable period of time e.g. 3 months (SAIDI/ SAIFI) vi). Performance of equipment such as transformers, autorecloser, metering unit and switches. vii). Safety issues on the networks viii). Check MV and LV Voltages to measure quality of service ix). Updates on the number of connections made, connections applications that are pending where applicable. x). Cumulative units of energy imported where applicable. xi). Energy losses where applicable. xii). Snags identified during DLP inspection, Corrective actions and timelines allocated. Chapter four: Recommendations and Conclusions After the final DLP inspection, the Project Manager shall notify the Contractor of the identified snags. After the Contractor has corrected them, a verification exercise shall be carried out along with the Service Provider to confirm correction of snags. The Contractor shall the be issued an Operational Acceptance Certificate. This shall be issued only after the contractor has achieved the required connections as per the contract. Following this issuance, the Contractor shall then be at liberty to claim for the 5% Retention. 56 | P a g e 14 Contract Closure For completeness of contract closure, the certificates indicated in the Annex 35 – Checklist for Contract Closure) shall be issued by the responsible persons. The Contractor shall also issue to the Project Manager a No Claim Certificate in the format indicated in Annex 36. The Contract Manager/ Project Manager shall prepare a Project Closure report and shall include details of the following; Chapter one: Background information including Contract particulars, Objective of the project, output, Number of Connections and energy imported Chapter two: Project performance assessment – Final account of cost, scope, duration of the project (Contractual vs Final), O&M risks identified and mitigation measures. Chapter three: Administrative reviews – Contractor’s performance (Level of compliance to approved design and survey report, compliance to instructions, conduct) Chapter four: Administrative reviews - Consultant’s performance (measure against the expected deliverables) Chapter five: Lessons learned (include lessons learnt) Chapter six: Recommendations and Conclusion Attachments: Certificate for operational acceptance, Quarterly Contract Assessment Tools Attachments: Pictorial memory lane Note: For the Consultant, the report shall entail a cumulative account of their monthly reports. The Environment and Social safeguards shall also write a report in line with compliance to the project Environment and Social Safeguards requirements. 57 | P a g e ANNEXES 58 | P a g e ANNEX 1: PROJECT IMPLEMENTATION CYCLE 59 | P a g e ANNEX 2: STAKEHOLDER ANALYSIS AND PARTICIPATION MATRIX 60 | P a g e ANNEX 3: RISK ANALYSIS MATRIX Low Moderate High Key Likelihood to Occur 1 2 3 Impact Risk Rating 1 2 3 1-2 3-4 6-9 A. RAP ASSOCIATED RISKS NO. ACTIVITY HAZARD ASSOCIATED RISK LIKELIHOOD OF OCCURRENCE IMPACT RISK RATING MITIGATION MEASURES1 3 i) Involvement of district and civic leadership to mobilize and organize community meetings, use of alternative media and engagement channels like schools, radio, churches/mosques and market days among others to engage communities. Low or no Low or no participation of participation of the the community community 1 RAP Preparation 1 1 3 Delays caused as a result of negligence of the responsible officers shall be brought to the attention of the Accounting Officer to take appropriate punitive action. 61 | P a g e Locals refusing to Non Consent from Locals sign consent forms. Absenteeism of PAPs from project area Inability to access PAPs 1 3 3 1 1 1 i) Conduct an assessment of reasons for non-consent by PAPs ii) Ensure prior community education and sensitization on project benefits and compensation procedures including rights of PAPs. iii) Provision of compensation alternatives to PAPs including forms of additional support iv) Negotiations with the PAP v) Diverting the power line route i) Adopt commonly used channels to trace absentee PAPs eg through LCs, local radio announcements, publication of names in relevant newspapers and in public spaces like sub county headquarters, churches/mosques, markets etc. ii) Document efforts made with evidence. iii) Using the media to find the Absentee PAPs iv)Use of an ESCROW account to ensure compensation monies 62 | P a g e are available for absentee landlords as the search continues. Difficulty in assessment of property to be damaged Delayed Assessment of property to be damaged 1 3 3 i) Close supervision of the RAP consultant and ensuring prompt payment of the consultant's fees ii) Ensuring proper mobilization of the PAPs through local leaders, community gatherings and publicity on local radios. iii) Display at the sub county level clear assessment schedules with PAPs much ahead of time specifying dates and segments to be visited. iv) Involvement of district and civic leadership to mobilize and organize community meetings, use of alternative media and engagement channels like schools, radio, churches/mosques and market days among others to engage communities 63 | P a g e Poor quality consultancy reports Poor quality consultancy reporting on Project issues 2 3 6 i) Ensure high quality skilled and experienced team is in place ii) An outline of the contents of the report should be provided in the TORs. iii) Closely supervise the consultant's team to ensure compliance with the set TORs and time schedules within the contract. iv)Reviewing consultant’s reports within a week of submission and consultant responding to comments within 7 days. Delay in REA Clearance of RAP report Increased time allocated to preparation and approval of RAP report 1 3 3 i) A team should be constituted to review the RAP report timely 9 i) REA should facilitate the CGV's team for the field visits during assessment to reduce on the approval process and the CGV’s office. ii) An officer from the CGV's office should be assigned to handle REA RAPs Delay in CGV Clearance of RAP report Increased time allocated to preparation and approval of RAP report 3 3 64 | P a g e 2 RAP Implementation i) Timelines for addressing comments should be provided for in the TORs and REA should closely supervise the consultant to ensure compliance. ii) Direct discussions with the consultant on their reports to reduce back and forth formal communications to address comments which cause delays in report delivery. i) REA to reserve funds for the field exercise Delays in addressing comments by the RAP consultant Increased time allocated to preparation and approval of RAP report 3 3 9 Unavailability of timely of resources for REA teams to undertake Disclosure of the RAPs and obtain payment details of the PAPs Delayed Disclosure of the RAPs and obtainment of payment details of the PAPs 2 4 8 Unavailability of Delayed compensation of adequate funds for 3 PAPs compensation 3 6 i) REA should reserve sufficient funds for compensation of PAPs in every financial year 3 9 i) Timely processing of the funds by requisitioning immediately Delays in internal processing of Delayed compensation of PAPs 3 ii) Requisitions for funding will be made a month prior to the scheduled field activity to ensure timely processing and release to the team going to the field 65 | P a g e compensation monies within REA after receiving World Bank approvals of the RAP report ii) Timely review of the requisition by the Audit Unit. iii) Timely input of PAPs data into the E- payment system PAPs not being familiar with payments through eplatform Difficulty in payment of PAPs through e-platform Efficiency of epayment platform Increased processing time for compensation funds 2 2 2 2 4 4 i) REA will continuously take the lead in sensitization about the mobile money platform during its monthly field activities. ii) Messages educating PAPs about MM services will be broadcast on Radios, places of worship and local council notice boards. iii) Local mobile money (MTN & Airtel money) service providers will be identified to continuous educate and provide support to PAPs. i) Collaboration with officers involved within the payment chain, including MOFPED, BOU and Stanbic Bank. This shall be done by obtaining weekly 66 | P a g e Confirmation of Delayed receipt of receipt of payment to confirmation of receipt of 2 the PAPs payments to the PAPs Delayed Compensation of PAPs Change in Consent Position by the PAP 2 3 2 6 4 updates from these officials on the status of payments. ii) Meetings shall also be held with senior official to further emphasize the urgency of these payments towards the project’s success. iii) Institution of a joint tracking system to assess turnaround time at each stage at the end of every month. i) Obtaining weekly E – Payment status reports from Stanbic Bank on status of PAPs' payments i) Continuous sensitization of the PAPs ii) Timely payments iii) Working closely with the LCs and community members to provide accurate details of the household head or family member authorized to receive compensation of behalf of the family. iv)Negotiations and emphasis on project benefits 67 | P a g e v) Ensuring timely deployment of the contractor to effect construction works before changes in planting seasons and other new activities on the land. Negative Political Influence Increased difficulty in coordination of PAPs and process of compensation 2 1 2 i) Prior sensitization of political leaders to solicit their support for the project may help avert this to some extent. ii) Identify project champions for continuous engagement with PAPs and other stakeholders including local leaders iii) Involving the top district leadership throughout the activity ASSOCIATED RISK LIKELIHOOD OF OCCURRENCE IMPACT RISK RATING MITIGATION MEASURES2 B. PROCUREMENT RISKS NO. ACTIVITY 2 HAZARD Delays caused as a result of negligence of the responsible officers shall be brought to the attention of the Accounting Officer to take appropriate punitive action. 68 | P a g e Gaps in Technical Specifications Use of unclear Technical Specifications in bidding documents 1 3 3 Failure to adhere to Delays in obtaining the the time lines in the required procurement procurement plan approvals 3 3 9 1 3 3 Procurement Aspects Low Bidder Turn-up Reduced competition Dedicated REA technical team shall timely review and confirm completeness of all technical specifications. i) Institute a tracking tool to assess turnaround time at each stage and flag delays. ii) Delays shall be brought to the attention of the Accounting Officer to take appropriate punitive action. iii) The responsible officers shall ensure completeness of submissions to reduce the number of reviews and comments i) The size and scope of works is sufficient to attract a good number of bidders. ii) Running the advert in various media houses both local and international as well as REA’s website. iii) Timely payments on running contracts to attract bidders for future jobs 69 | P a g e i) Delayed evaluation process Increase in delays in procurement 2 3 6 Low Quality Evaluation report Selection of poor quality Best Evaluated Bidders 1 3 3 Evaluators’ general ethical conduct Lack of ethics in evaluations 1 3 3 The Evaluation team should be constituted early and timelines have been set for the evaluation process ii) Pre-engagement training should be done to equip evaluation team members with basics and standard formats iii) Delays in the evaluation process should be brought to the attention of the Accounting Officer to take appropriate punitive action. i) Training sessions for Evaluation teams has been carried out ii) Team selected based on experience, seniority and commitment. i) Ethical conduct should be one of the criteria for selection of the members of the evaluation team. ii) Punitive action and penalties such as warning 70 | P a g e Delayed clearance internally Delayed internal approvals 1 Delayed clearance by Bank Increase in delays in procurement 1 Lack of ethics and fairness in evaluation. 2 2 3 3 Complaints on the bidding process /Administrative review 1 3 3 Delayed clearance by Delayed clearance by SG SG 1 3 3 letters, suspension and ultimately expulsion spelt out in the REA HR Manual are stringent enough to discourage unethical behaviour i) Weekly meetings by the contracts Committee ii) Timely submissions to the Contracts Committee. Engagement with the Bank’s Operational persons with REA’s technical persons to reduce the back and forth during review and approval process of documents. i) Adherence to the ethical code of conduct ii) The process shall be in a fair and complete at each stage to mitigate occurrence of complaints. iii) Speedy resolution of complaints and lessons drawn to improve future bidding processes Working closely with SG through weekly follow-up interactions and 71 | P a g e ensuring complete submissions to avoid unnecessary clarifications. Failure to secure Delayed approval of performance security performance security 1 with 28 days 3 3 IMPACT RISK RATING i) Adequate assessment of Bidders’ financial capacity. ii) Due Diligence on best evaluated bidders C. CONTRACT IMPLEMENTATION NO. ACTIVITY Contract Implementation HAZARD Contractors / Consultants not delivering on time LIKELIHOOD TO OCCUR ASSOCIATED RISK Delayed completion of project 2 3 6 MITIGATION MEASURES The consultant’s / contractors’ implementation plans shall be reviewed monthly. The contractor’s performance on the contract shall be assessed every 3 months using the performance assessment tools developed by the CMT. These quarterly and monthly reviews shall be used to find solutions to the causes of delays to project implementation on either the contractor or the client’s side. 72 | P a g e i) Ineffective personnel on the project shall be replaced. ii) The contractor and consultant shall timely submit claims for payment. iii) Verification of claims from the consultant shall be done jointly by the consultant and client to reduce time lags in payment. iv) The impact of delays due to bad weather and other unscheduled delays shall be minimized by providing for contingency allowance time in the contractor’s project implementation time schedule. Contractors / Consultants not delivering good quality work Poor quality deliveries by Contractors/ Consultants 1 3 3 The consultants / contractors will be required to submit a contract specific Quality Assurance Plan. The plan will be audited quarterly during implementation to ensure compliance. 73 | P a g e i) The CMT will deploy clerksof-work on ground to enhance supervision and ensure compliance with technical specifications and approved work procedures on ground. ii) Any delays due to poor designs shall be quantified and contractor penalized. The performance guarantee shall cover the designs as well and contractor shall be made aware that they stand to lose if designs are not done acceptably well. iii) Consultant and REA shall ensure the design documentation are reviewed quickly and comments submitted to ensure that contractor completes the designs on time Internal Delays in Processing Payments to Risk of claim for interests by Consultants and 1 Contractors 3 3 i) Timely processing and follow-up on payment claims within REA departments. ii) Timely feed back to the Contractor or Consultant on 74 | P a g e Consultants and Contractors quality and status of their payment claims. Theft and Vandalism of the network Increase in number of network outages 2 3 6 Change order risk Delays in project implementation 2 2 4 Contractor not complying with ESMP on site Implementing a project which is environmentally 2 and socially uncompliant. 3 6 i) Community policing ii) Monthly Community sensitization drives prior and during project implementation iii) Insuring all project materials during project implementation The consultants / contractors shall undertake design review at contract commencement. Any cause of changes will be identified, reviewed and approved by the CMT where such change orders are deemed necessary. The consultants/ contractors shall prepare a contract specific ESMP. Special Attention shall be paid to environmental and social safeguard aspects during implementation. The environmental and social aspects shall be addressed in a proactive manner. There shall be persons 75 | P a g e specifically for ESMP compliance on the CMT. Failure for identified beneficiaries to wire their houses for the connections Delay in achieving targeted connections 2 3 6 Failure to achieve project Failure to achieve the objectives and hence targeted number of 3 increased redundancy of Connections network assets. 3 9 i) During the preparation of the contractor’s engineering design, a data base of the targeted consumers shall be developed. The team shall profile the targeted beneficiaries and promote initiatives for readiness to use the power. ii) Ready Boards shall also be offered basing on i) above. i) Building the capacity of Service providers through trainings, increasing the number of their staff, technical support in their operations and maintenance programs. ii) Connection mobilization drives spearheaded by REA shall be carried in beneficiary communities at the project commissioning stage. iii) Subsidizing the connections cost through the connection policy D. CONSTRUCTION RISKS 76 | P a g e NO. 1 ACTIVITY Material handling and transportation HAZARD ASSOCIATED RISK LIKELIHOOD TO OCCUR IMPACT RISK RATING MITIGATION MEASURES • Self-loader/crane should be in good mechanical condition • The self- loader/crane should be operated by licensed operator • Ensure workers keep a safe distance from the loading area • Double check to ensure materials are firmly fastened • Passengers should not be carried in the same cabin as equipment • Employ enough manpower to handle such loads • Use of mechanised handlers if possible • Transportation of materials and equipment during the dry season when most roads are passable • Reasonable loading of vehicles when delivering to hard to reach places Snapping of selfloader hoisting rope/ equipment falling from crane grip Accidents resulting in bodily injuries or loss of lives. Equipment damage 1 3 3 Loosely fastened materials Road accident resulting in bodily injuries or loss of lives Equipment damage 2 3 6 Heavy manually handled loads Bodily injuries 2 2 4 Impassable or bad roads Road accidents and vehicles getting stuck 3 3 9 Poor handling and transportation of transformers Damage of transformer bushings 2 3 6 • Well-functioning self-loaders should be used 9 • Fragile materials should be transported separately. • Large vehicles with sufficient space should be used Loading fragile materials with nonfragile ones Damage of materials 3 3 77 | P a g e Over speeding Improper management of residual wires Seepage (Leaching) of chemicals from poles (stored at site) during treatment - Health effects associated with chemicals used for pole treatment Using short vehicles to transport poles 2 Line clearance Thorny plants, trees stumps etc Damage of materials Accidents leading to body injuries and/or deaths Wires can be used as snares. Injury to children and animals Pollution of soil and water, danger to plants and amphibians Long-term exposure, especially thorough direct contact with skin during wood treatment to low levels of creosote has resulted in skin cancer and cancer of the scrotum Development of sweeps on poles Mechanical damage on poles Body scratches 3 3 9 1 2 2 1 3 3 1 3 3 2 2 4 3 1 3 • Drivers should not exceed a speed limit of 60 Km/hr Put in place and implement residual wire management plan in protected areas Transporting poles that are completely dry (Sufficient chemical fixation time which is 72 hours) …..Poles storage above the ground covered with saw dust or sand Use of appropriate and adequate PPEs and/or use of mechanised equipment • Tracks with a minimum length equivalent to the height of the pole should be used • Workers wear Full Personal Protection Equipment 78 | P a g e Attacking Wild animals Injuries due to attacks 1 3 3 Falling branches and trees Bodily injuries and death 1 3 3 Cutting down people's vegetation without prior authorisation Using unskilled personnel to cut down and ferry trees Leaving chopped trees in the area Using inappropriate tools Having a live network within the falling distance of the tree Community members halting works Physical Attacks 3 3 Accidents and bodily injuries 1 3 Accidents Spoils esthetics of the area Delay of works Bodily injuries Live shocks/ Electrocutiion 2 1 2 2 2 3 9 3 2 4 6 • Workers to move in groups • Workers wear Full Personal Protection Equipment • First aid should be on site at all times • Vehicle should be present on site for emergency evacuation Workers wear Full Personal Protection Equipment Ensure workers keep a safe distance from the area being cleared Authorisation using concent forms should be obtained Use skilled personnel to cut and ferry trees Chopped trees should be disposed off after as soon as possible Contractor should use only approved tools for clearance • Trees should be cut gradually and carefully to avoid contact with the power line • Shutdowns should be requested for in cases where it is impossible to avoid contact with the live network 79 | P a g e 3 Pit and cable trench excavations Delays in project implementation as a result of community related issues Delays in project completion. Damaged Client reputation Client Law suits 3 3 9 Failing to obtained the required ground clearance Live shocks/ Electrocution 3 2 6 Energised underground cables and pressurised water pipes Loss of supply Damaged pipes and cables Body injuries and death from damaged pressurised pipes and exposed energised cable Sharp rough surfaced Injuries to hands and feet excavation tools •Carry out intense community sensitization prior to implementation. •Engage communities during project implementation •Proper Grievance Redress Means •Use community leaders as the face of the project •Use RTK survey technology for surveying •Avoid reckless cutting of trees. Only cut trees that are above 2.5m where you must •Do not cut any endangered trees species The contractor should be careful adhere to the minimum clearances provided for in the construction guidelines 3 3 9 • Seek Utilities layouts and plans from District Physical Planners • Take caution when excavating • Report any damage to the concerned asset manager 3 3 9 Workers wear Full Personal Protection Equipment 80 | P a g e Moving traffic Open pits and trenches Digging shallow pits especially on rocky ground Leaving pits open after excavation Poorly excavated pits on soft ground such as swamps Using inappropriate tools especially for holes for concrete poles 4 Pole positioning Poor handling or offloading of poles by throwing them off the track Injury due to vehicles swerving off the road into working area Bodily injury to both humans and animals The poles will not be fitted into the pit up to the theoretical ground line Support strength of the pole reduces 2 3 6 3 3 9 3 3 9 Accidents e.g children or livestock falling into the pits 2 3 6 Leaning poles 2 3 6 Wide pits that make backfilling difficult 2 2 Mechanical damage and splitting 4 3 3 9 Use of reflective road signs to alert road users of on-going works Open pits and trenches are barricaded with warning tape All pits should be inspected and approved prior to pole erection Pit excavation should be done after pole positioning All unused pits should be covered as soon as possible Pits should be inspected and approved by the Engineer prior to pole erection Use pole hole diggers with appropriate drill bit less than 400mm • Poles should be offloaded using cranes • Poles should be offloaded in the presence of the pole treatment plant representative and the contractor while ensuring no poles are dropped 81 | P a g e Dragging and rolling poles on ground Phyiscal damage to the pole and hence reducing the pole's sap wood 3 3 Positioning unsuitable pole sizes Undersized or oversized poles shall be used on pole structures 2 2 9 4 5 Pole erection Poles erected in shallow pits Reduced support strength of poles Increased posibility of poles rotting 3 3 9 Insufficient back filling Water logging around the theoretical ground line of the pole 3 2 6 Leaning poles Reduced firmness of the foundation of poles 3 3 9 Placing insufficient marrum especially on soft ground Placing few or no wounds of earthwire at the pole butt for poles with earth wire Using short poles e.g when crossing the road Poor plumbing of poles High resistance Reduced firmness of the earthwire 2 Reduced clearance 2 2 Leaning of poles 1 1 2 4 4 1 • Poles should be moved on rollers or carried using tracks or cranes • Poles should be guided using Crawbars • The contractor should avail Aspegged drawings to the foremen • The Clerk of works should inspect and approve all positioned poles prior to pole erection Erected poles should be inspected to ensure the marking on the theoretical ground line is covered All poles should be inspected to ensure proper backfilling by the Clerk of works, consultant or Engineer Marrum should be placed in the presence of the Engineer All poles with wounds of earthwire should be inspected by the clerk of works prior to backfilling 12m poles should be used while crossing roads The contractor should use proper plumb bobs 82 | P a g e Poor ramming Using inappropriate tools Fatigue due to working long hours at height Worn-out climbing irons and Belt 6 Pole Dressing Reduced firmness of the pole's foundation 2 2 Poor quality of works 1 2 4 2 Body injuries and death due to falling 1 2 Body injuries and death due to falling 2 3 6 Existing near live line Body injuries and death due to electrocution 2 3 6 Falling objects Head injuries due to falling objects 2 3 6 Lightning Lightening shocks 2 3 6 Reduced quality of works 1 3 Reduced quality of works 2 3 Using unskilled personnel Poor quality of works 1 3 Using inappropriate tools Poor quality of works Using unsuitable and unapproved materials Incomplete dressing on each pole structure 2 3 6 3 1 3 3 Proper rammers should be used Approved tools should be used All linesmen must anchor themselves with tied belts all the time while working height Climbing irons should be replaced if worn out Minimum clearance must be observed or live lines deenergised and earthed • Workers should wear hard hat helmets at all times • Linesmen should use tool bags and avoid throwing tools down Linesmen to work in equipotential zones created by earthed heavy shots All materials should be inspected after installation All pole structures should be inspected after installation Personnel should be approved by the Engineer prior to commencement of works Tools should be inspected and approved by the Engineer and Clerk of works 83 | P a g e 7 Installation of stays Failing to use the required PPE Body scratches and injuries 2 3 6 Using unsuitable materials e.g wood stay stubs Poor quality of works 2 3 6 Digging shallow stay pits Installing the wrong stay type Poor tensioning of stays 8 Conductor drawing and stringing Uneven walking surfaces Sharpnells on the conductor surface Snapping conductor Failing to use drum jakes Reduced firmness of the stay's foundation and hence reduced mechanical strength of the stay assembly Reduced support strength of the stay assembly Poor quality of works Reduced support strength of the stay assembly 1 3 3 2 1 2 Contractor should ensure that all workers have the required PPE before moving to site All stay assemblies should be inspected and approved by the Clerk of Works during installation to ensure appropriate materials such as concrete stay stubs are used All stay pits should be inspected before burying the stay stub and stay rod Engineer should inspect all stays to ensure they are appropriate for that structure 3 3 9 Engineer should inspect all stay assemblies to ensure they properly tensioned Bodily injuries 3 2 6 To watch walking surfaces Bruises on fingers 2 1 Bodily injuries Appearance of kinks during stringing Breaking of conductor 2 2 2 4 To wear gloves when laying conductors Tensioning conductors cautiously 2 2 4 Drum jakes should be used during stringing 84 | P a g e 9 Conductor tensioning and sagging 11 12 Cable Joining Transformer earthing Transformer installation 3 3 Use of tension and sagging charts 3 3 9 1 3 2 3 6 2 3 6 Loose jumpers 2 3 6 Obtaining poor earthing resistance values 3 3 9 Earthing should be done under supervision by the clerk of works Increased risk of faults damaging the network 3 3 9 Dig up more pits and connect them Intertwining of conductor 1 Poor tensioning of conductor Reduced clearance Increased possibility of line to line faults 1 Using inappropriate tools Poor quality of works Using unskilled personnel Poor quality of works Installing short jumpers 10 3 Drums of conductor should be off-loaded using cranes or under the inspection of the site supervisor Dropping drums of conductor from tracks Installing loose jumpers Failing to use two appropriate PG Clumps Failing to put all required components for earthing Failing to achieve the required earth resistance values Poor positioning of the transformer on the platform Reduced clearance between the jumper and the support structure Reduced clearance between the jumper and the support structure Imbalance to the transformer structure which could lead to leaning 1 3 3 2 2 Only approved tools should be used Personnel should be approved by the Engineer or Clerk of works prior to commencement of works All jumpers should be inspected by the Engineer and Clerk of Works All jumpers should be inspected by the Engineer and Clerk of Works All jumpers should be inspected by the Engineer and Clerk of Works Transformer installation should be done under the supervision of the clerk of works 85 | P a g e 13 Connection of new lines to existing live Grid 14 Working in Swampy areas 15 16 Working in dirty areas Use of unskilled personnel and tools Poor quality of works 2 3 6 Only authorised personnel should be allowed to install the transformer Using oversized protection equipment especially circuit breakers and fuse-links Reduced protection on the line 2 3 6 All protection equipment should be inspected prior to and after installation Live lines Electrocution 2 3 6 Deep water Drowning 2 3 6 Contaminated swampy water Infection with water borne diseases Infection with associated diseases 2 3 6 2 2 Dirty environment 4 Driving long distances Road accidents resulting in bodily injuries or loss of lives 3 3 9 Bad driving Road accidents resulting in bodily injuries or loss of lives 2 3 6 Driving to site • The live lines are isolated, earthed and a work permit issued before commencement of works • All personnel working at the Toff should wear protective gear such as gloves, overalls, eye protectors etc Measure depth of water depths before commencement of works Workers wear Gumboots and rubber gloves Workers wear Gumboots and rubber gloves Drivers are encouraged to limit journeys to manageable distances based on their judgement and capabilities • Installation of speed governors to control speed limits • Ensuring drivers are held accountable for incidents resulting from their actions 86 | P a g e Fire risks due to extreme weather 17 Environmental Risks Lines falling due to give away of soils Collapse of network resulting from pole failure. Loss of power supply to consumers Collapse of network. Loss of power supply to consumers Risks associated with Compliance with national environmental requirements Risks resulting from non-payment of subcontractors 18 Other management risks Contractor's breach of contractual obligations Defects in workmanship 2 2 2 Delayed implementation due to striking workers. Poor workmanship due to lack of motivation Implementing the contract with no reference to contract agreement Poor quality work 3 3 3 6 Ensure that fire retardants are used during pole treatment 6 •Ensure that pole positioning is not at the edge of any sharp end of a hill. •If it is at the edge of a hill with a potential of giving away, ensure that the edges are stabalised. •Proper compacting should be done. 6 •Ensure that workers in any protected areas have permits •Ensure that protected species are not interfered with 3 3 9 3 3 9 3 3 9 Contractors given timeframes within which to pay subcontractors and service providers. •REA to undertake assessment of contractors. •Contractor to possess contract agreement at site. •Check for personnel qualifications •Employ experienced personnel 87 | P a g e Failure to complete the project in the timeframe stipulated in the contract Extend contract on the basis of contract nonperformance. Possible contract termination 3 3 9 •Ensure that the contractor adheres to the timeframe and implementation plans • Monthly review of project progress Financial and reputational risks associated with scope variations Exceeding the contract price 3 3 9 •Scope variations should be backed by financial availability 9 •Ensure that works adhere to the Company's code of ethical conduct •Sensitize workers during toolbox talks •A social worker should be fully deployed at site •Ensure that workers have uniforms with numbers and their names for easy identification •Engage communities on the project scope and modalities of implementation •Projects maps showing beneficiary names should be distributed to all load centres Extortions from workers on ground Breached client reputation. Termination of worker’s contracts 3 3 88 | P a g e ANNEX 4: CONTRACT MANAGEMENT PLAN (FORM 49) Regulation 51(3) THE PUBLIC PROCUREMENT AND DISPOSAL OF PUBLIC ASSETS ACT, 2003 CONTRACT MANAGEMENT PLAN WORKS Procurement Reference Number Code of Procuring and Disposing Entity Works Financial year Sequence number Subject of Procurement Provider Contract Value Contract start date Contract end date (Start Date + Time for completion) Site possession date to contractor Supervisor or the engineer Guarantees (Where applicable) Performance guarantee Amount : Latest date for receipt: (28 DAYS AFTER NOTIFICATION OF CONTRACT AWARD) Advance payment guarantee Amount : Latest date for receipt: (48 DAYS FROM CONTRACT SIGNING) 89 | P a g e Date of release of bid security Date of release of advance payment guarantee Contract Progress Interim or Stage payments See attached sheet Contract Completion Date of taking over certificate (Release of % of Retention where applicable) Extension of time, if any Delay, if any Liquidated damages due, if any Date of performance certificate (date of taking over certificate + defects notification period and release of remaining % of retention) Return of performance security Final Payment Amount Date Retentions (Where applicable) The proportion of payments to be retained …………………………………… [Insert percent] percent. Defects Liability Period (Where applicable) Defects liability period Contractual Date of Performance Certificate (contract completion date + defects notification period) Contract Management Plan prepared by: Name: …………………………………… Position……………………………… Signature ………………………………… Date ………………………………… 90 | P a g e ANNEX 5: CHECKLIST FOR ENVIRONMENTAL ASPECTS OF REA PROJECTS ANNEX 5A: CHECKLIST FOR PREPARATION OF CESMP AND ATTENDANT PROTOCOLS This checklist complements the CESMP by helping the user to cross-check and guarantee that all the environmental aspects of the project have been considered/ addressed. CATEGORY Permits, certificates and explanations ENVIRONMENTAL ITEM 1. EIA and other permits MAIN CHECKS CONFIRMATION OF ENVIRONMENTAL CONSIDERATIONS 1. Has EIA been completed? 2. Have EIA reports been approved by NEMA? 3. Have EIA reports been unconditionally approved? If conditions are imposed on the approval, then an adjusted EMP must be developed. 2. Explanation to the public 4. In addition to the above approvals, have other required environmental permits been obtained from relevant authorities? 1. Are contents of the project and the potential impacts adequately explained to the public based on appropriate procedures, including information disclosure? 2. Are proper responses made to comments from the public and regulatory authorities? 91 | P a g e 1. Water quality Mitigation Measures 1. Is there a possibility that soil runoff from the bare lands resulting from earthmoving activities, such as cutting and filling will cause water quality degradation in downstream water areas? If water quality degradation is anticipated, are adequate measures considered? 2. Are measures adequately considered to mitigate potential pollution of cresol from the poles yard 3. Are measures adequately considered to mitigate potential hydrocarbon pollution from any spillages 2. Protected Areas 4. If the magnitude of potential pollution is big, has DWRM been fully engaged? 1. Is there a possibility that the project will affect protected areas? 2. Has UWA been fully engaged in case of Wildlife areas? 3. Has NFA been fully engaged in case of forest reserves? 3. Ecosystem 1. Are adequate measures taken to prevent disruption of migration routes and habitat fragmentation of wildlife, and livestock? 2. Is there a possibility that the project may cause impacts, such as reduction in wetland areas, and disturbance of ecosystem due to introduction of foreign materials? 92 | P a g e 4.Topography and geology If significant ecological impacts are anticipated, are adequate protection measures taken to reduce such impacts on the ecosystem? 1. Is there a soft ground on the route of power transmission lines that may cause slope failures or landslides? Are adequate measures considered to prevent slope failures or landslides, where needed? 2. Is there a possibility that civil works, such as cutting and filling will cause slope failures or landslides? Are adequate measures considered to prevent slope failures or landslides? 3. Is there a possibility that soil runoff will result from cut and fill areas, and borrow sites? Are adequate measures taken to prevent soil runoff 5. Resettlement /compensation 1. Is involuntary resettlement caused by project implementation? If involuntary resettlement is caused, are efforts made to minimize the impacts caused by the resettlement? 2. Is the resettlement plan, including proper compensation, restoration of livelihoods and living standards developed based on socioeconomic studies on resettlement/compensation? 3. Are agreements with the affected persons obtained prior to resettlement/compensation? 93 | P a g e 4. Is a plan developed to monitor the impacts of resettlement/compensation? 6. Living and livelihood 7. Heritage 8. Ethnic Minorities and Indigenous People 1. Is there a possibility that the project will adversely affect the living conditions of inhabitants? Are adequate measures considered to reduce the impacts, if necessary? 2. Is there a possibility that diseases, including communicable diseases, such as HIV will be introduced due to immigration of workers associated with the project? Are adequate considerations given to public health, if necessary? 1. Is there a possibility that the project will damage the local archaeological, historical, cultural, and religious heritage sites? Are adequate measures considered to protect these sites? 1. Where ethnic minorities and indigenous peoples are living in the rights-of-way, are considerations given to reduce impacts on the culture and lifestyle of ethnic minorities and indigenous peoples? 94 | P a g e 9. Impacts during construction 1. Are adequate measures considered to reduce impacts during construction (e.g. noise, vibrations, turbid water, dust, exhaust gases, and wastes)? 2. If construction activities adversely affect the natural environment (ecosystem), are adequate measures considered to reduce impacts? 3. If construction activities adversely affect the social environment, are adequate measures considered to reduce impacts? 10. Monitoring 4. Are health and safety measures in place? is health and safety education (e.g., traffic safety, public health) provided for project personnel, including workers? 1. Project specific EMP developed by REA and given to the Contractor for implementation and supervising firm for monitoring purposes. 2. Has the contractor developed CEMP? 3. The Contractor and the supervising firm must therefore have an environmentalist for guiding and monitoring environmental aspects 95 | P a g e ANNEX 5B: SAFEGUARDS MONITORING TOOL A. No 1 SOCIAL ASPECTS Area of intervention Occupation Safety Policy and Legal Framework The Occupational Safety and Health Act (2006). . Areas of observation Indicators 1. Policy displayed EHS Policy 2. Legality of work place 3. Training and awareness 4. PPEs 4. First Aid Kid 5. Fire safety Contractor Supervising Consultant Comment Safety related Work procedures Work place registration Certificate from DOSH displayed Training/awareness plan Training/awareness reports/attendance lists Availability of PPEs Records of issuance with acknowledgement by workers Appropriateness PPEs in use Accessibility Fully equipped Designated First Aiders Documented procedure for 1st aid administration Serviced Fire extinguishers appropriately located at the storage sites Designated Fire assembly point 96 | P a g e No Area of intervention Policy and Legal Framework Areas of observation Indicators 6. Drug and alcohol abuse Drug and alcohol abuse Policy Contractor Supervising Consultant Comment No of incidents recorded 2 Gender The National Gender Policy 1997. Equal employment opportunities Gender sensitive employment Policy Job Adverts encouraging women to apply Violence Complaints Register Gender sensitivities Well labelled Separate sanitary facilities Gender sensitive PPEs Training plans Attendance lists Training 3 COMMUNITY HEALTH OSH Policy, 2006, Public Health Act 1967, National HIV/AIDS Management Plan and other STDs Proof HIV/AIDS outreach activities (IEC material, T-shirts, Radio talk shows, etc.) 97 | P a g e No Area of intervention 4 Policy and Legal Framework HIV/AIDS Policy and World of Work 2017 Areas of observation Indicators Contractor Supervising Consultant Comment Condoms distribution accessibility and availability to workers HIV/AIDS management Champion on each crew Community safety Awareness and Sensitization records Caution signage No open pits left overnight 5 6 Community Engagement Labour The Local Governments Act, 1997 National Environment Act 1995 Gender Policy Disability Act The Electricity Act Employment Act (2006), the Workers Compensation Act (2000), Labor Disputes (Arbitration and Settlement) Act, (2006) and Labor Unions Act, 2006. Community Engagement plan Records of stakeholder consultation Radio talk shows Overall project acceptance Functional GRM PAPs signed consent forms Age restrictions employees on local people should be recruited Copies should provide copies of Identity Cards Work permit for foreign nationals Contracts/letters of engagement signed 98 | P a g e No Area of intervention Policy and Legal Framework Areas of observation Employment of women to ensure positive discrimination Indicators Contractor Supervising Consultant Comment Contractor Supervising Consultant Comment Code of conduct signed by all employees Enforce recruitment of persons of legal working age in accordance with the Labour Act and the Employment Act. Prioritize recruitment of local people especially for casual labour to reduce on influx of new workers B. PHYSICAL ASPECTS No Area of intervention Policy and Legal Framework Areas of observation 7 wetland wetland coverage in the The national project scope wetland conservation and management policy, wetland restoration 1995 , plan ESMP compliancy National Environmental Act level 1995 Indicators Approved ESMP High resolution project Satellite images submitted Marram backfilling of pole pits SOP/protocols in place & approval from NEMA for RoW Monthly ESMP progress report 99 | P a g e No Area of intervention Policy and Legal Framework The National Environment (Wetland, Riverbanks and Lakeshores Management) regulations 2000 Areas of observation Line Design survey Community Engagement plan (awareness and sensitization activities 8 Forest The national Status of Forests in the forestry and tree project scope planting act , 2003 National Environmental Act 1995 SOP /protocols in place pertaining to works in forested ecosystems Line design survey Indicators Contractor Supervising Consultant Comment Number of complaints registered Use of horizontal line configuration Line diversion Use of 2/3 member pole Use of insulated (ABC) conductors Stakeholder meeting minutes Awareness and sensitization attendance sheet High resolution project Satellite image submitted ESMP monthly progress report NFA clearance permit Powerline aligned in the Road Reserve Use of insulated (ABC) overhead conductors for low voltage Use of underground cables for medium voltages (11/33Kv) 100 | P a g e No Area of intervention Policy and Legal Framework Areas of observation 9 Status of Protected Game parks and Wildlife policy of areas in the scope Game reserves 1999 (Protected Areas) The wild life Act Cap Staff training 200 of 2000 Line design survey ESMP Compliance monitoring SOP/Protocols pertaining to works in protected area Indicators Contractor Supervising Consultant Comment High resolution project satellite image submitted Progress ESMP report Training certificate, report or attendance Powerline aligned in the road reserve Insulated conductors (ABC ) used for Low voltage lines Powerline aligned in the road reserve Insulated conductors (ABC ) used for Low voltage lines Underground cables used for medium voltages (11/33Kv) ESMP monthly progressive report Monitoring report Staff safety /sensitization and awareness on work hazard report UWA approval work permit 101 | P a g e No Area of intervention 10 Hydrology constituents of the community Policy and Legal Framework National Water Policy 1999 Areas of observation Indicators Status of Water sources in the project scope High resolution satellite image submitted The Water act, cap 152 ,1997 Contractor Supervising Consultant Comment Approved ESMP ESMP Compliancy level SOP/protocols in place Monthly ESMP progressive report 11 Endangered species (Flora & Fauna) RED Listed endangered species under IUCN Status of Endangered species ESMP compliance level Clearance certificate for RoW from directorate of water Community awareness and sensitization attendance sheet Approved ESMP report Stakeholder engagement plan SOP in place pertaining to endangered species Minutes and meeting attendance extracts Staff Training Training reports 102 | P a g e No Area of intervention 12 Archaeological objects/environ ment 13 Dust emissions & particulate matters Policy and Legal Framework National cultural policy 2006 Areas of observation Indicators Status of Archeological objects /environment Project Satellite image submitted & approval from district for the RoW SOP/protocol pertaining to managemnt and handling of Archaeological objects Staff training on handling of such sensitive environment Community engagement plan Monitoring report ESMP monthly progress report SOP in place pertaining to work related emissions Dust monitoring kit ESMP monthly progress report Pollution complaints on file Staff training reports Contractor Supervising Consultant Comment The Historical and monument Act, 1967 National Environmental Act 1995 The public Health Act, 281, 1964 Training report/ certificate Meeting Minutes and sensitization attendance sheet Emission Regulation 103 | P a g e No Area of intervention Policy and Legal Framework Areas of observation Indicators 14 Noise pollution National Environmental Act (Noise standards and control regulation 2013) SOP in place pertaining to work related noise Flight management plan in place and functioning Community engagement Monitoring report Monthly progressive report Contractor Supervising Consultant Comment The public Health Act, 281, 1964 15 Land use and Land clearance for the RoW The constitution of Republic of Uganda, 1995 Project satellite image submitted Land use in the Row Land act cap 227 , 1998 National land policy 2013 Voluntary offer for the RoW Community /stakeholder Engagement Consent forms signed by land owners Sensitization and awareness reports Community meeting minutes 104 | P a g e No Area of intervention Policy and Legal Framework 16 Storage yard Land act cap 227 , SOP/protocols pertaining to 1998 National Environmental Act 1995 17 Camp site The public Health Act, 281, 1964 Occupational health and safety act 2003 Employment act 2003 Areas of observation Waste management National Environment (Waste Management) regulation of 1999 The public Health Act, 281, 1964 Contractor Supervising Consultant Comment Permit/approval from relevant authorities management and set up of storage yard Health and safety Training on handling storage site Waste storage and discharge Health and safety Waste management Basic requirement security 18 Indicators SOP in place pertaining to handling and discharge of wastes Waste handling Safety kits in place Training report Waste management plan in place Health and safety training reports, incident reports , ESMP monthly progressive reports Waste management plan in place and functioning Clean water , shelter, Incident reports , fence , SOP in place Discharge/disposal license Monitoring report and monthly progressive report Waste management plan in place and functioning 105 | P a g e No Area of intervention Policy and Legal Framework Constitution of Uganda 1995 19 Chemical Areas of observation Indicators Qualified staff to handle wastes Training report or certification ,licenses Waste disposal /recycling environment Discharge permit/ approval from relevant authorities SOP/protocols Water Regulation ( waste discharge pertaining to regulation of 1997) management and control of chemicals staff capacity National Environment (protection & Handling and management of discharge/disposal solid & hazardous waste s.1 .15 of 1991) 10 Oil spills SOP /protocols in place pertaining management of and control of oil spills Contractor Supervising Consultant Comment ESMP monthly progressive reports and monitoring reports Training and certifications, reports and permits Discharge permit/licenses from relevant authorities Discharge permit/licenses, staff 106 | P a g e ANNEX 6: SURVEY METHODOLOGY AND PRESENTATION The line routes of the proposed power distribution project(s) shall be inspected before commencing the survey(s) with the project manager or their representative(s). The service provider shall obtain paper and digital maps, as well as geo-referenced Satellite imagery/aerial ortho photos which shall be not more than one year old, and of multispectral spatial resolution of 0.6m or better, covering a band of at least 1km wide (at least 500m on either side of the Indicative line route) based on Uganda’s National coordinate system, which is currently UTM Arc 1960 Zone 36N with Clarke 1880 as the ellipsoid of reference. The identified critical locations of proposed medium voltage line route will thereafter be finalized with the project manager or their representative(s). The next step will be establishment of survey control points and the final detailed survey, which shall include line profiling and pegging of the pole structure locations. Control Establishment Survey Prior to the final detailed field survey, inter-visible pairs of control points shall be established along the proposed line route at appropriate intervals to provide ease of reference for all subsequent surveys. They shall be made of concrete, with a bar or nail in the center, marking the precise point of co-ordinate measurement. These points shall be clearly labeled, described and documented by the service provider. Horizontal Control: Horizontal control survey will be executed using High accuracy and high precision dual frequency GNSS/GPS receivers. All GPS points shall be established with an accuracy of at least 5mm+/- 1ppm. Vertical (Elevation) Control: Vertical control survey will be done using automatic levels or intelligent total stations, and the heights shall be in reference to known benchmarks where possible. Assumed heights shall be used in situations where there are no known height benchmarks in the vicinity of the project area. Final Detailed Survey A final detailed survey shall be executed using high accuracy and high precision dual frequency GNSS/GPS receivers as well as intelligent total stations. Final survey drawings (as-pegged) and other details will be provided to the project manager or their representative(s) by the service provider for approval of the construction scope. 107 | P a g e Power Line Route Profile(s) Power line route profile surveys shall be done using either intelligent total stations or Dual frequency GNSS/GPS in RTK mode or a combination of the two. It is however advisable to record the survey data using string system method as it is easier to use in generating drawings by an Automated mapping software like PLS CAD. Line profiling will be achieved by carrying out topographic surveys along the proposed line route at 20m intervals. However, any significant change of slope occurring in between the 20m spot heights should also be heighted. Where ground slope across the line route exceeds 1 in 25 the level of ground left and right of the center line will be recorded at an offset distance of 10m. Line Profile drawings will be provided together with the line route and pole schedule. Drawings Presentation of Information on the Survey Drawings The survey drawings should be as detailed as possible so as to enable REA staff carry out analysis on the built network. Colour Coding For clear presentation of information on the drawings, it is required that the drawings have a uniform colour coding as described below; a. For the MV lines 33kV or 11kVshall be represented as a Bold black line. b. LV lines shall be represented as a broken black line, with 1-phase or 3-phase indicated at the respective sections. c. Distribution transformers shall be a big black dot. d. Poles shall be small black dots and shall bear incremental numbers. These pole numbers shall begin at the connection point, at the start of the project line in conformity with the project name. e. The service connection cables shall be light blue. Legend / Key 108 | P a g e a. The project title shall include voltage level, name of the major load center(s) and the District e.g. Proposed 33kV Power supply to …………… TC or Village or sub-county and environs in …………… District. b. The legend shall give a description of the symbols in their respective color codes determined by the voltage levels as described in the section above. c. The distribution transformer size shall be indicated. Labeling of Sheets a. It shall be required that the “to” and “from” is indicated on each sheet. b. Each sheet shall be numbered clearly, for example Sheet 1 of 12 At the T-off point; a. Indicate existing line with the color coding as described in the previous section and at the connection point, the feeder name should be given. b. Indicate the road directions on each end of the existing line, this gives a more clear indication of the location of the area. REA shall review and approve the draft survey drawings before the final drawings are submitted in soft and hard. The drawings MUST include a page showing the entire power line route in form of a line diagram. 109 | P a g e Flow chart of the method statement - Technique Based on Satellite images and GPS Satellite Images Horizontal & Vertical Control Geo reference the Images & Plotting the line Route Finalize the critical locations Preliminary Survey Preparation of Image Drawings (Scale 1: 2000 & 1: 10000) Field Check & Finalize the Line Route Preparation of Final Image Drawings (Scale 1 : 2000 & 1: 10000) Profile Survey Preparation of Final Profile Drawings Final Report Preparation of 1: 10,000 Map Placement of Angle Points & Intermediate Points 110 | P a g e ANNEX 7A: POLES’ PRE-DISPATCH CHECKLIST (CREOSOTE) RURAL ELECTRIFICATION AGENCY Poles’ Pre-dispatch Testing Tool Supplier Name: Location: Date: Preservative Creosote The following documents have been provided and reviewed by the FAT Team: No. Documents 1 Documentation under pole receiving 2 Documentation under pole seasoning 3 Documentation under pole treatment 4 A copy of post treatment test report 5 Manufacturers documents relating the chemicals quality ✓/X Comments and efficiency 111 | P a g e Pole Testing No. Pole Length Pole Top Diameter Penetration >20mm Retention >115kg/m3 Mid-point Mid(Expected Results point according to SANS) Cantilever (Expected Results according to SANS) Cantilever Visual Inspection 1 2 3 4 5 6 7 8 9 10 11 12 13 Comments: Name Date Signature REA Representative Contractor Treatment Plant Manger 112 | P a g e ANNEX 7B: POLES’ PRE-DISPATCH CHECKLIST (CHROMATED COPPER ARSENATE) RURAL ELECTRIFICATION AGENCY Poles’ Pre-dispatch Testing Tool Supplier Name: Location: Date: Preservative CCA The following documents have been provided and reviewed by the FAT Team No. Documents 1 Documentation under pole receiving 2 Documentation under pole seasoning 3 Documentation under pole treatment 4 A copy of post treatment test report 5 Manufacturers documents relating the chemicals quality and efficiency ✓/X Comments 113 | P a g e Pole Testing No. Pole Length Pole Top Diameter Penetration >20mm Retention >115kg/m3 Mid-point Mid(Expected Results point according to SANS) Cantilever (Expected Results according to SANS) Cantilever Visual Inspection 1 2 3 4 5 6 7 8 9 10 11 12 Comments: Name Date Signature REA Representative Contractor Treatment Plant Manger 114 | P a g e ANNEX 8: FAT CHECKLIST FOR TRANSFORMERS A. TRANSFORMER PLANT INSPECTION TOOL DOCUMENT TYPE: DISTRIBUTION TRANSFORMER MANUFACTURING PLANT INSPECTION TOOL DOCUMENT NUMBER: REVISION NUMBER: 1 LAST REVISION DATE: Mar-19 REFERENCE DOCUMENTS: DISTRIBUTION TRANSFORMER SPECIFICATION & DISTRIBUTION TRANSFORMER MANUFACTURING PROCESS MANUAL PLANT NAME: INSPECTION DATE: LOCATION: YEARS IN OPERATION: NO. 1.0 1.1 1.2 1.3 1.4 1.4.1 1.4.2 1.4.3 1.5 1.6 1.7 1.8 1.9 2.0 2.1 ASPECT OF INSPECTION ACCEPTANCE CRITERIA FINDING (Yes/No) REMARKS Availability of Documentary Evidence for Legal, Statutory & Quality Valid ISO 9001:2008 or Quality Management Certification Equivalent Enviromental Management Valid ISO 14001:2004, Certification NEMA or Equivalent Occupation Health and Safety Valid OHSAS 18001:2007 Management System or Equivalent Availability of Health, Safety, Enviroment & Quality (HSEQ) Policies & Yes Manuals Presence of Procedure for Enviromental Aspect Enviromental Aspect Evaluation Register Presence of Hazard Procedures for Hazard Identification Register Procedure for Risk Assessment Presence of Risk Register Availability of Manufacturing Processes Yes Manual & Procedures Availability of Manufacturing Processes Yes Checklists Availability of Testing Protocals Yes Availability of Valid Type Test Yes Certificates Availability of Valid Equipment Yes Calibration Certificates Production Capacity Availability of Adequate Structure of Yes the Production Team 115 | P a g e 2.2 2.3 2.4 2.5 2.6 2.7 2.8 i ii iii iv v vi vii viii 3.0 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 3.12 i ii Adquate Mix of Qualification & Expereince of the Production Personel Capacity of Raw Material Storage Area Capacity of Production Area Number of Production Lines Capacity of Finished Transformer Storage Area Number of Transformer Per Day/Month Availability of Key Production Line Equipment Crane Fork Lifts Loading Bays Core Cutting Machines with Step Lap technology Drying Oven Testing Labaratory Vacuum Chamber/Equipment Winding Machines Yes No. of sqm? No. of sqm? No.? No. of sqm? No.? Yes Yes Yes Yes Yes Yes Yes Yes Distribution Transformer Construction Process Check Availability of Full Fledged Design Yes Office (Space, Tools & Personel) Availability of Procedure for Identification & Review of Customer Yes Requirements Yes Is there a Design Action Plan? Is there a Design Review Yes Checklist/Procedure? Availability of Design Reports Prior to Yes Manufacturing Presence of Job Card Ability to Trace a Transformer Back up System or Equivalent to Raw Materials Presence of Material List with Quality Certficatio, Compliant to Client Availability of Adquate Raw Materials Specification Sourcing System Check Whether the Core Is Securely Yes Clamped Check Availability of Winding Yes Instruction from the Design Report with Winding Technicians Check Availability of Drying Oven & Capacity of the Highest Rated Yes, 630KVA, No? Transformer and Number of Transformers it can Accommodate Oil filled in Vacuum Chamber Check Oil Filling Procedure Check Conformity to Minimum Dimensions for Tank Fabrication 3mm for < 400kVA & 6mm for > 400kVA Minimum Tank Thickness 3mm for < 400kVA & 6mm for > 400kVA Minimum Base Thickness 116 | P a g e iii iv v 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11 4.12 4.13 4.14 4.15 4.16 4.17 5.0 4mm for < 400kVA & 6mm for > 400kVA Minimum Cover Plate Thickness 6mm Minimum Flange Thickness 1.2mm Minimum Radiator Thickness Compliance Check to Minimum Technical Characteristics Armophous or CRGO Silicon Steel Sheets Core Material 0.23 +-3% Core Thickness (mm) Aluminum Winding Material Mineral Transformer Oil Type 70kV Transformer Oil BDV A Insulation Board Class Insulation Board Minimum Dielectric 60kV/mm Strength in oil 5 Off-Load Tap Changer Steps Off-Load Tap Changer Lockable in Tap Yes Position Selected Presence of Pressure Relief Value, Yes Minimum 0.35 bars Yes Tank Hermetically Sealed Mild Steel Tank materials Hot Dip Galvanised & Powder Coated Tank Coating >100um (50um + 50um) Tank Overall Coating Thickness Tank Comprises of Base, Tank, Flange, Yes Top Cover, Lifting Lugs, Earthing Points? Tank has Provision for Mounting Surge Yes Arrestors? Yes Bushing have Arcing Horns? Inspection & Testing 5.1 Check Availability of Full Fledged Testing Laboratory 5.2 Carry out Routine Tests on Sample Finished New Distribution Transformer 6.0 6.1 6.2 6.3 Product Handling & Packaging Presence of Proper Handling Equipment Transformer to be Securely Packaged in Palates Palates to be Labelled as per Client Specification Completed with all equipment necessary to carry out all Routine Test as required per IEC 60076 Attach Routine Test Report in line with IEC 60076 Yes Yes Yes Signed: ………………………………………………… REA Representative ………………………………………………… UMEME Representative ………………………………………….. UEDCL Representative ………………………………………………… PLANT Representative 117 | P a g e B. FAT CHECKLIST FOR TRANSFORMERS PHYSICAL INSPECTION: Physical Inspection No. Aspect of inspection Methods of inspection Sampling Acceptance criteria Equipment Hot dip zinc Galvanized, Use coating powder coated, ≥ 100µm thickness (BS 729) gauge. Remarks rate 1 External surface Visual and measurement 10% coating of tanks (Elcometer) 2 Internal surface of Visual 1 per type tank 3 4 Dimension Oil resistant paint & Size and Physical check and 1 per type construction measurement & Size (a) Outdoor bushing (a) Approved as per the 1 per type Creepage specification distance drawing and Approved drawing Approved drawing & Size (b) Phase to phase (b) 40mm/kV clearance (c) 800mm (c) Phase to Earth (d) To be provided with clearance hardware (d) Bi-metallic crimping connector for conductor. 5 Oil level inside tank Visual inspection of the oil 1 per type Should be above active to be checked level gauge. Note: Ambient & Size part when the Oil gauge is at minimum. 6 Packing Physical inspection Should be as per specification 118 | P a g e Routine Test No. 1 Aspect of Applicable inspection standard Insulation IEC- 60076 Sampling rate Acceptance criteria Equipmen t 10% ≥ 1000 MΩ when 5000V is applied Insulation resistance for 60 seconds for HV & E, HV & LV resistance measurement and 1000V applied for 60 seconds meter for LV&E. (Megger) – 5kV 2 Separate source IEC- 60076 100% Test set should not trip when 70kV AC voltage is applied for 60 seconds for 33kV Dielectric withstand. TX, 28kV for 11kV TX, and 3kV for Test set LV windings. 3 Vector relation IEC - 60076 10% Vector group displayed to be as per Transform specification – Dyn11 er ratio meter. 4 Transformer IEC - 60076 10% ratio 5 Winding resistance IEC - 60076 10% at Transformer ratio as per Transform specification with ±5% tolerance er ratio for the respective taps positions. meter. All phase resistance values should Transform be similar. er winding rated tap resistance meter 6 No load loss IEC - 60076 10% The deviation of no load loss value AC should be ≤15% of specified value analyzer No load current shall be less than 5% of rated. 119 | P a g e Remarks 7 Load Loss IEC - 60076 10% Deviation of full load losses corrected to 750 C shall be within 15% of the specified value. Total losses – deviation of the AC analyzer component losses should be within 15% while deviation of maintaining the total the losses within10% of the specified value 8 9 Induced Should withstand double the rated High voltage at High voltage at 120 HZ applied to LV frequency frequency windings for 50 seconds. test set. Measure the electrical strength of Oil TX oil when a layer of oil is placed Dielectric between two electrodes, which are test set Testing over the electrical strength of transformer oil IEC - 60076 IEC - 156 100% Oil sample placed at 2.5mm apart. Average breakdown voltage of the oil must be > 50kV. 120 | P a g e ANNEX 9.0 REA INSPECTION CHECKLIST FOR MANUFACTURING PLANTS FOR CONDUCTORS Documentation 1.1 1.2 1.3 The plant has the following Valid Certification: ✓/X Quality Management Certificate: ISO 9001:2008 Environmental Management Certificate: ISO 14001:2004 NEMA EIA Certificate or Equivalent OHSAS Certificate: OHSAS 18001:2007 UNBS Certification or Equivalent Occupational Health and Safety Certification from Ministry of gender, Labour and Social Development or Equivalent The plant has the following documentation: ✓/X HSEQ Policies and Manuals Process Manual Quality Plans Manufacturing Procedures Inspection Instructions Test Protocols Test reports Process Checklists Type test certificates Calibration Records The plant has the following HSEQ Procedures ✓/X Procedure for Environmental Aspect Evaluation (Environmental aspect register) Hazard Identification (hazard register) Risk Assessment (risk register) Auditor's Comment Auditor's Comment Auditor's Comment Design Process 2.1 Review of the Design Process for compliance to specifications & standards; the plant has the ✓/X following: Procedure for identification & review of customer requirements Design Action Plan Design review checklist Design report Design Software Auditor's Comment 121 | P a g e Material Inspection 3.1 3.2 3.3 Aluminum ingots Aluminum content is atleast 99.5% Documentation Test certficate clearly showing the composition of the tested sample of Al. ingots Alloying ingots Silicon content is atleast 99% Documentation Test certficate clearly showing the composition of the tested sample of Silicon Alloying element Mg. ingots Mg. content is taleast 99% Documentation Test certficate clearly showing the composition of the tested sample of Mg. ingots ✓/X Auditor's Comment ✓/X Auditor's Comment ✓/X Auditor's Comment ✓/X Auditor's Comment ✓/X Auditor's Comment Aluminuium Alloy Wire Rod 4.1 Chemical Analysis of molten metal Atleast 2 samples from different locations are taken The sample complies with ASTMB 398, table 1 Element Composition,% Copper max 0.1 Iron max 0.5 silicon 0.050-0.90 Manganese,max 0.0.3 magnesium 0.6-0.9 Zinc,max 0.1 Chromium,max 0.03 Boron ,max 0.06 Other elements, Total ,max 0,03 Other elements, Total ,max 0.1 aluminium Remainder Documentation Chemical analysis report of molten metal Tools/Apparatus Spectrometer 4.2 Casting of Alloy bar Plant has an internal standard for casting alloy bar and it is implemented 122 | P a g e 4.3 4.4 4.5 Treatment of alloy cast bar by induction furnace ✓/X Temperature is recorded on an hourly basis Temperature reanges between 5100c to 5300c (at entry of roll milling) Documentation Temparature records Rolling of aluminium Alloy Rods followed by ✓/X quenching and coiling The plant has an internal plant standard for rolling of aluminium Alloy Rods, quenching and coiling Temparature ranges from 400c to 800c (after quenching) Documentation Internal plant standard for rolling of aluminium Alloy Rods, quenching and coiling The plant carries out the following tests on the wire ✓/X rod using caliberated tools Tests to verify Diameter Tests to verify Tensile strength Tests for Elongation Tests to check for cleanliness and surface smoothness (visual check): The wire rod should be smooth and free from pipes laps, cracks ,kinks,twists,scams & other injurious defects within the limits of good commercial practice Documentation Caliberation Certfificates for tools used Test Reports for all the above tests Auditor's Comment Auditor's Comment Auditor's Comment Aluminium Alloy Drawn Wire (Before Aging) 5.1 The following tests are carried out on the Aluminium Alloy Drawn Wire Test for Diameter according to ASTM 398, clause no. 11.0 and customer specification Test for Tensile strength; minimum - 27kg/mm2 Test for Resisitivity - Max-34.50Ωmm2 /km at 20 degrees Documentation Tests reports/ certificates List of tools used in drawing the wire ✓/X Auditor's Comment 123 | P a g e Aluminuim Alloy Wire Ageing Process 6.1 Aluminum Alloy wire Ageing process time & temperature during process Temperature is maintained at 150 ± 5 degrees centigrade for 4 to 5 hours Documentation Aging process documentation/ process manuals List of tools used in Aging process ✓/X Auditor's Comment Aluminium Alloy after Aging Process 7.1 The following tests are carried out after Aging ✓/X process: Visual inspection for surface finishing and winding according to ASTMB 398,clause no.13. The wire should be smooth and free from all imperfections not consistent with good commercial practice Check for Diameter of drawn aluminum alloy wire according to ASTM 398,cause no.11.0 & customer specification Breaking load /tensile test according to ASTMB 398 table -2; Min -315N/mm2/(AVG) and Min 305N/mm2 (Ind) Test for Resistivity according to ASTMB 398,clause no 9.0; Max 32.841Ω mm2/km at 200c Test for elongation according to ASTMB 398,table -2; Min = 3.0% on 250 mm gauge length Wrapping test (bending properties) according to ASTMB 398, clause no,8.0. Eight turns should be wrapped round a mandrel of diameter equal to the wire diameter. The wire should not break Documentation Test Reports/ certificates Auditor's Comment Final Conductor Stringing 8.1 Lay ratio/Direction &compactness Lay ratio/Direction &compactness is done according to AST B399, Clause no 7.0: layer max min Dir 1+6 16 10 RH Documentation ✓/X Auditor's Comment 124 | P a g e 8.2 Quality control documents for lay ratio/ direction and compactness The following tests are carried out after final ✓/X conductor stringing Visual checks for joints according to ASTM B 399, clause no. 6.0 & Table-4. No joint are permitted in center wire. Joint are permitted in six wire layers but such joint shall be no closer than 15m. Check for Surface cleanliness. After reeling the conductor, the exposed surface of the outer layer of conductor is wrapped with water proof plastic sheet to preserve the conductor from dirt, grit and damaged during transportation and handling. Visual checks for Surface smoothness/ scratches according to ASTM B 399, clause no. 13. The conductor shall be clean and free of imperfections not consistent with good commercial practice Documentation Test Reports for the above tests Auditor's Comment Routine and Accetance Test on Final Conductor 9.1 All tests as per clause 7.0 are carried out on atleast ✓/X 10% of the drums The tests are according to ASTM B399, ASTM B 399 & IEC 61089 Documentation Test Reports Auditor's Comment Tests on Finished Conductor 10.1 10.2 Visual inspections for surface smoothness This is done according to ASTM B 399, clause no. 13. The conductor should be clean and free of imperfections not consistent with good commercial practice Documentation Test Report Measure for conductor diameter This is done according to Clause no.6.6.3 of IEC 61089 12.78mm +1% Documentation Test Report ✓/X Auditor's Comment Auditor's Comment 125 | P a g e 10.3 10.4 10.5 10.6 Check for lay ratio ✓/X One sample for every 10 drums is checked according to ASTM B 399, clause no. 7.0 LAYER MIN MAX Alloy (6+1) 10 16 Documentation Test Report Check for direction of layer ✓/X One sample for every 10 drums is tested according to ASTM B, 399, clause no 7.4. Direction of lay of the outermost layer should be right hand Documentation Test Report Check for Unit weight of conductor ✓/X This should be done according to Clause no.6.6.3 of IEC 1089 standard weight of the conductor without grease=273.8kg/km. Documentation Test Report Visual check for surface finish and winding; One sample for every 10 drums or part thereof. According to ASTM B 399, clause no.13: The wire should be smooth and free from all imperfections not consistent with good commercial practice. According to ASTM B 398, CLAUSE NO. 11 & customer specification; Tolerance: ± 1% According to ASTM B 399, clause no.14.2Min. 299..25N/mm2 (AV). Min.-289.75N/mm2 (Ind) According to ASTM B398, CLAUSE NO.9.0. Max.32.841Ωmm2/km at 200C According to ASTM B 398, Table-2. Min= 3.0% on 250mm gauge length According to ASTM B 398, clause no.8.0. Eight turns shall be wrapped round a mandrel of diameter equal to the diameter. The wire shall not break. Documentation Test Reports Auditor's Comment Auditor's Comment Auditor's Comment Auditor's Comment 126 | P a g e Personnel 11.1 The plant has adequate production team: Minimum Personnel Working Experience Qualification BSc. Electrical Production Engineering 3 years Manager / BSc. Mechanical Engineering BSc. Electrical Quality Engineering Control 3 years / BSc. Officer Mechanical Engineering Documentation Structure of the manufacturing facility ✓/X 127 | P a g e ANNEX 9A: FAT CHECKLIST FOR LV ABC CONDUCTOR, THREE PHASE Test standard: Production Name ABC cable Type and size ABC Test quantity 3x50+1x54.6mm2 NO. TEST ITEM Manufacturer: Date: EXPECTED RESULT UNIT 1 1.1 1.2 1.3 1.4 Drum No. Phase conductor Material Strands number Shape Approximate overall diameter 1.5 Max. DC resistance at 20°C Ω/km 0.6 2 2.1 2.2 3 3.1 Phase XLPE insulation Nominal thickness mm 1.7 3.2 3.3 Strands number Approximate overall diameter Nos mm Aluminum alloy 7 9.5 3.4 Max. DC resistance at 20°C Ω/km 0.596 3.5 Neutral wire breaking load kN 16.6 4 4.1 5 5.1 Neutral XLPE insulation Nominal thickness Complete conductor Overall diameter of cable mm 1.7 mm 29 5.2 AC voltage test Aluminum 7 Circular 30 Nos. mm Neutral conductor Material NAME EVALUATION kV/min 3.5/1 Non breakdown TITLE COMPANY SIGNATURE 128 | P a g e ANNEX 9B: FAT CHECKLIST FOR LV ABC CONDUCTOR, SINGLE PHASE Production name Type and size NO. 1 1.1 1.2 1.3 1.4 1.5 ABC cable Test standard: Manufacturer: ABC 1x50+1x54.6m m2 Test quantity Date: TEST ITEM Drum No. Phase conductor Material Strands number Shape Approximate overall diameter Max. DC resistance at 20°C UNIT Nos. mm EXPECTED RESULT Aluminum 7 Circular 8.1 Ω/km 0.6 mm 1.7 Aluminum alloy 7 9.5 2 2.1 2.2 3 3.1 Phase XLPE insulation Nominal thickness 3.2 3.3 No mm 3.4 Strands number Approximate overall diameter Max. DC resistance at 20°C Ω/km 0.596 3.5 Neutral wire breaking load kN 16.6 4 4.1 5 5.1 Neutral XLPE insulation Nominal thickness Complete conductor Overall diameter of cable mm 1.7 mm 29 5.2 AC voltage test NAME Neutral conductor Material kV/min EVALUATION 3.5/1 Non breakdown TITLE COMPANY SIGNATURE 129 | P a g e ANNEX 10: FAT CHECKLIST FOR TRANSFORMER WIRING AL / PVC CABLE Production name Transformer Wiring Al / PVC Cable Test standard Type and size 1X120mm2 Test quantity NO. TEST ITEM 1 Conductor 1.1 Material 1.2 Strands number 1.3 Shape 1.4 Approximate overall diameter mm 13.1 1.5 Max. DC resistance at 20°C Ω/km 0.248 2 PVC insulation 2.1 Nominal thickness mm 1.7 2.2 Approximate overall diameter mm 16.4 3 Complete conductor 3.1 AC voltage test NAME UNIT EXPECTED RESULT IEC 60502 EVALUATION Aluminum Nos. 7 Circular kV/mi n TITLE 3.5/1 Non breakdown COMPANY SIGNATURE DATE 130 | P a g e ANNEX 11: FAT CHECKLIST FOR HV BARE CONDUCTOR 50SQMM Production name All Aluminum Alloy Conductor Test standard Type and size AAAC- 50mm2 Test quantity NO. TEST ITEM UNIT EXPECTED RESULT EVALUATION Smooth in surface, uniform and tight in stranding, no corrosion on surface 1 Appearance 2 Construction 2.1 Number of conductor Nos. 7 2.2 Diameter of single wire mm 3.03 2.3 Overall diameter of conductor mm 9.07 2.4 Strands direction of aluminum outmost layer 3 Performance of conductor 3.1 Breaking load kN 3.2 Calculated DC resistance at 20°C Ω/km NAME IEC 61089 Right TITLE 16.205 0.65 COMPANY SIGNATURE DATE 131 | P a g e ANNEX 12: FAT CHECKLIST FOR HV BARE CONDUCTOR 100 SQMM Production name All Aluminum Alloy Conductor Test standard Type and size AAAC- 100mm2 Test quantity No. TEST ITEM 1 Appearance 2 Construction UNIT EXPECTED RESULT Nos. 7 2.2 Diameter of single wire mm 4.26 2.3 Overall diameter of conductor mm 12.8 2.4 Strands direction of aluminum outmost layer Right Performance of conductor 3.1 Breaking load kN 43.47 3.2 Calculated DC resistance at 20°C Ω/km 0.28 NAME EVALUATION Smooth in surface, uniform and tight in stranding, no corrosion on surface 2.1 Number of conductor 3 IEC 61089 TITLE COMPANY SIGNATURE DATE 132 | P a g e ANNEX 13: FAT CHECKLIST FOR GSW 3/2.64 NO. TEST ITEM UNIT 1 EXPECTED RESULT Smooth in surface, uniform and tight in stranding, no corrosion on surface Appearance 2 Construction 2.1 Number of conductor Nos. 3 2.2 Diameter of single wire mm 2.64 2.3 Strands direction of aluminum outmost layer Right 2.4 Weight of Zinc Coating 2.5 Coating type 3 Performance of conductor 3.1 Calculated Tensile Strength NAME EVALUATION Kg/m2 0.24 Hot dip galvanised kN TITLE 19.2 COMPANY SIGNATURE DATE 133 | P a g e ANNEX 14: FAT CHECKLIST FOR GSW 7/2.64 NO. TEST ITEM 1 UNIT Appearance EXPECTED RESULT Smooth in surface, uniform and tight in stranding, no corrosion on surface 2 Construction 2.1 Number of conductor Nos. 7 2.2 Diameter of single wire mm 2.64 2.3 Strands direction of aluminum outmost layer 2.4 Weight of Zinc Coating 2.5 Coating type 3 Performance of conductor 3.1 Calculated Tensile Strength NAME EVALUATION Right Kg/m2 0.24 Hot dip galvanised kN TITLE 44 COMPANY SIGNATURE DATE 134 | P a g e ANNEX 15: FAT CHECKLIST FOR GSW 7/4.00 NO. TEST ITEM 1 Appearance UNIT EXPECTED RESULT EVALUATION Smooth in surface, uniform and tight in stranding, no corrosion on surface 2 Construction 2.1 Number of conductor Nos. 7 2.2 Diameter of single wire mm 4 2.3 Strands direction of aluminum outmost layer 2.4 Weight of Zinc Coating Right Kg/m2 0.24 Coating type Hot dip galvanised 2.5 3 Performance of conductor 3.1 Calculated Tensile Strength NAME kN TITLE 44 COMPANY SIGNATURE DATE 135 | P a g e ANNEX 16: ROUTINE TEST - COMPOSITE LINE POST INSULATORS Production name Composite line post insulators Type and size NO. 1 2 3 4 5 6 7 8 9 10 Test standard IEC 62223/ 61952/62217 Test quantity ASPECT OF INSPECTION/TEST UNIT OF MEASURE EXPECTED RESULTS Nominal system Voltage Visual examination Verification of dimensions Nominal Height Minimum Nominal Creepage distance Tensile load test (applied 9.4kV for 10s) kV 33 mm mm kV 240 2400 No damage (deformation/cracking) seen kV ok ( same oC for CT and HT) kV kV No cracks/damage No cracks No puncture >180 >160 Tests on interfaces and connections of metal fittings: Thermal-mechanical pre-stressing (4.0kV for 48h) Water immersion pre-stressing Verification tests / visual examination Steep-front impulse voltage test Dry power frequency voltage test Min Power Frequency withstand Voltage (Dry) Test of housing Accelerated weathering test Tracking and erosion test No tracking and no erosion, no shed punctured Flammability test Test for the core material No drops Dye penetration test Water diffusion test No penetration No puncture or flash over (leakage current <1.0mA) Assembled core load tests kN No cracks or permanent deformation. No dye penetration Verification of the maximum design cantilever load Tensile load test (15kN) kN kV no pull out or breakage of end fitting No flashover kV kN No Flashover >20 Dry lightning impulse withstand voltage test (200kV) Wet power frequency test (95kV) Cantilever failing load test NAME TITLE TEST RESULTS COMPANY SIGNATURE DATE 136 | P a g e ANNEX 17: ROUTINE TEST - PIN INSULATORS Production name Pin insulators Test standard Type and size ABC 3x50+1x54.6mm2 Test quantity NO. ASPECT OF INSPECTION 1 Visual Inspection 2 System Voltage UNIT IEC 60502/ IEC 62223 EXPECTED RESULTS TEST RESULTS Out door kV 33 Verification of dimensions 3 Nominal Diameter mm 315 (205±5) 4 Nominal Height mm 240 (269±5) Min. Nominal creepage mm 825 (900±10) Distance 5 Power frequency puncture kN voltage ≥ 185 6 Mechanical failing load kN test(Cantilever Strength) Proposity test Freshly broken pieces of porcelain shall show no dye penetration after having been immersed for 24 hours in an alcoholic mixture of fushing at a pressure of 2000 p.s.i Lightning withstand kV voltage (1.2/50ms) Min. Power frequency kV Flashover Voltage Wet ≥10 7 8 NAME TITLE no dye penetration 170 110 COMPANY SIGNATURE DATE 137 | P a g e ANNEX 18: ROUTINE TEST - DEAD END STRAIN INSULATORS Production name Dead end strain insulators Type and size NO. 1 2 3 4 5 6 7 8 9 10 11 NAME Test standard IEC 62223/IEC 61109 Test quantity ASPECT OF INSPECTION/TEST Nominal Voltage Steep front impulse voltage withstand test (1000-1500kV) Lightning impulse flashover voltage test Radio interference voltage test Dry flashover voltage test Wet flashover voltage test Impulse withstand voltage test (+) Impulse withstand voltage test (-) Minimum tensile failing load Porosity test Thermal Test. Creepage distance TITLE UNIT kV kV EXPECTED RESULTS TEST RESULTS 33 No Puncture kV kV kV kV <200µV 12 70 200 kV 210 kN 40 no dye penetration mm 825 COMPANY SIGNATURE DATE 138 | P a g e ANNEX 19: ASSESSMENT OF MANUFACTURER’S LEGAL AND REGULATORY COMPLIANCE, CERTIFICATION AND EXPERIENCE NO. MANUFACTURER ASSESSMENT UNIT 1 Name Name of Supplier 2 Provide detail of legal status of the company Copy of Company Registration certificate 3 Provide details of the premises Copy of Business trading license 4 Years of existence Proof of existence for the past 10 years 5 Reference list of similar supply contracts Detailed list of clients with full contacts addresses 6 Quality Management System Copy of ISO 9001:2008 certificate or equivalent 7 Product type test reports by an internationally recognized electrical testing laboratory Copy of Reports. Those issued beyond 3 years should be certified by issuer. 8 Routine test reports for each product Copies of recent reports should 9 Manufacturer’s authorization letter. Original copy, dully signed and sealed 10 Manufacturer’s guaranteed technical specifications Original copy, dully signed and sealed and supported the respective authorization letter REQUIRED BIDDER’S MANUFACTURER SPECIFICATIONS COMPLIANCE 139 | P a g e ANNEX 20 A: IPC CMT CLEARANCE FORM No. Name and Signature Personnel Comment Name: Environmental Officer Signature: Name: Sociologist Signature: Name: Outreach Officer Signature: Name: Wayleaves Officer Signature: Name: GIS Officer Signature: 140 | P a g e ANNEX 20 B: INTERIM PAYMENT CERTIFICATE TEMPLATE (…insertcompany address…) To: Executive Director Thru: Deputy Executive Director-TO Thru: Manager Project Development and Management Thru: Senior Construction Engineer Date: (….insert Date…..) Subject: (….Insert Project Name as stated in the contract….) Interim Payment Certificate No (…insert Number…..) The Government of Uganda represented by the Rural Electrification Board contracted (…..insert name of contractor…..) for the construction of the aforementioned electrification project. The contract worth (….…insert total contract price, both in words and in figures, as stated in the contract, including taxes applicable and contingency……..) was signed on (….insert date of contract signature……….) and became effective on (………insert date of contract effectiveness as per the terms of the contract…….). This contract was varied by (………insert total amount as per the addendum …….) amending the total contract price to (……..insert total amount as per addendum and addendum no…….) and the contract duration from (…..original completion date……) to (……amended completion date….) to allow for implementation of extra scope. Upon achievement of contract effectiveness, the contractor submitted Advance Payment Guarantees, Performance Securities and Insurance Covers whose status of validation is tabulated in the table below. No. Particular 1 2 Advance Payment Guarantee Performance Security 3 Insurance Covers Date of Expiration The Contractor thereafter undertook engineering designs and the design report was approved on (…….insert date of approval of design report. Note that no interim payments should be made before approval of the engineering design report….). Upon approval of the design, the contractor commenced works and to-date, the overall physical progress is summarized below. (…… insert table summarizing progress as follows… 141 | P a g e No. Particular 1 Engineering Design 2 Procurement of Imported materials 3 Procurement of local materials 4 HV installation works 5 LV installation works 6 Equipment commissioning Progress (%) ………………) Following receipt of the contractor’s claim, a site meeting preceded by an inspection of works and material verification, was conducted and I certified progress as tabulated below; (…………….. No Particular Amount (…Insert currency…) . 1 Cumulative Value of Works Certified 1a Imported materials (Tax Exclusive) 1b Local Supplies (inclusive of VAT) 1c Design, Transport and Installation(Inclusive of VAT) 1d Total Value of works certified 2 Less (Deductables) 2a (… percentage as stated in contract…)Retention (…percentage as stated in contract…) Advance payment 2b recovery 2c Previous Payments certificate No.1 certificate No.2 ……etc,…. 2d Total Deductables Total Payable under this certificate (Cumulative value – total deductible) 1d-2d I hereby recommend payment totaling to (………state total payable both in words and in figures….) to (….name of the contractor as stated in the contract…..) in this interim payment certificate no. (….insert no….) 3 Signature: (…..insert Contract manager’s name….) 142 | P a g e ANNEX 21: CONTRACT CHANGE ORDER FORM CONTRACT CHANGE ORDER Contract Name Contract Reference No : (…insert contract name…) : (…insert Contract reference number…) Employer : THE GOVERNMENT OF THE REPUBLIC OF UGANDA REPRESENTED BY THE RURAL ELECTRIFICATION BOARD OF THE MINISTRY OF ENERGY AND MINERAL DEVELOPMENT Contractor : (…insert name of the contractor…) Date : (…insert current date…) Pursuant to Regulation 54 of the Public Procurement and disposal of Public Assets (Contracts) Regulations 2014, titled “Change orders to Contracts, we hereby issue a change order to the Contract as follows: 1. Subject of Change : (insert performance/duration of the Contract) 2. Change Request No contract e.g. two) subject of change e.g. Time of : (insert number of times a change is being made to the 3. Other changes to the Contract : (state any other previous changes made to the contract e.g. Time Extensions) In accordance with GCC 28.1, the Contract is hereby amended to extend the Intended Completion Date stipulated under GCC 17.1 of the Special Conditions of Contract from (…insert current project time scope e.g. twelve (12) calendar months) to (…insert proposed project time scope e.g. fifteen (15) calendar months) from the Start date. Authorized on behalf of the Employer: ____________________________ Godfrey Turyahikayo EXECUTIVE DIRECTOR Signed for and on behalf of the Contractor: _________________________ Name: ________________________________ 143 | P a g e ANNEX 22: SITE INSPECTION CHECKLIST The site office has the following documents; a) Copy of the contract Updated Monthly Implementation Plan (Previous Plans b) should also be availed) Copies of Approved Technical specifications for all c) materials including accessories e) Copies of Approved Design and Survey Report Organogram clearly indicating names and roles of f) employees g) Environmental and Social Management Tools i). CESMP – Construction Environmental and Social Management Plan and associated work procedures: ii). HSE Policy iii). Occupational Health and Safety Management Plan iv). HIV management Program v). Alcohol Substance Abuse Policy vi). Incident investigation, management and reporting procedure vii). Waste Management Plan viii). Procedure for Decommissioning Equipment Storage Yard ix). Wetland work and restoration procedures x). Transport Management Plan/Procedure xi). Community Engagement Plan Procedures for materials storage i) Instruction Books in Triplicate j) Daily Logbook k) Visitors book l) Complaints Register The site store should have the following: a) Dedicated Store Manager b) Fencing c) Security d) Fire extinguisher e) Material receiving forms f) Material Dispatch Book g) Updated Quantities of materials in store h) Delivery Notes from suppliers i) Visitors' Book The following are in existence on site to ensure the health and safety of the contractor: a) Contractor's Health and Safety Manual PPE such as gloves, safety shoes, overalls, helmets, b) climbers ✓/X Comments ✓/X Comments Comments 144 | P a g e c) First Aid Tool d) Sign Posts such as “Men at Work” e) Condoms f) Clean Toilets g) Clean and suitable rooms for accommodation The following considerations for the Yard have been made: a) Vegetation growth shall be well maintained b) The yard spacious enough to accommodate materials c) There is security The yard is accessible in accordance with environmental d) management plan The yard is distant enough from homesteads and other e) people-congested areas Comments 145 | P a g e ANNEX 23: DAILY REPORT TEMPLATE FOR CLERK OF WORKS RURAL ELECTRIFICATION AGENCY Date Project Details Day's Work Work Duration Weather Conditions Personnel Present DAY WORK LOG Officers Names Name Scope Section Scope Start Signature End Remarks Good Bad Remarks (No. of hours lost) Name No. No. Project Engineer Supervisor Foreman Linesmen Mates Casual laborers Materials received Material Quantity Materials Rejected Materials Used Material Quantity Ground No. of Pits Excavated Total Work Done Sandy Swampy Rocky HV LV PPE for Workers Incidents Normal Remarks No. of Poles Erected No. of Structures Dressed No. of Structures Strung No. of Equipment Installed Others Instructions Issued Changes Proposed Safety Issues Accidents 146 | P a g e Challenges Faced ANNEX 24: WEEKLY PROGRESS REPORT RURAL ELECTRIFICATION AGENCY WEEKLY PROGRESS REPORT DATE WEEK Project Details of Name Scope Work Section Section Scope Overall % Deployment status Planned Actual % Var Remarks/Action Project Engineer Supervisor Foreman Linesmen Casual Laborers Cumulative Materials received vs Planned Deliveries Planned Actual % Var Remarks/Action Poles Conductors Accessories Transformers Switchgear Others Cumulative Work Done vs Planned Schedule Planned HV Actual LV HV % Variance LV HV Remark LV Survey Pits Excavated Poles Erected 147 | P a g e Structures Dressed Structures Strung Equipment Installed Others Instructions Issued Proposed Changes Qualification Statement Safety Environmental and Social Safeguards Community Involvement Project Administration Risks and Mitigation Measures Risks Mitigation Measures Project Engineer’s Signature Name Signature 148 | P a g e ANNEX 25: SHUT DOWN AND COMMISSIONING LETTER TEMPLATE (GENERAL) …insert full address of the service provider, Usually the CTO or MD…) Request for shut down, Commissioning and Handover of (….insert actual name of the scheme, indicating the district…..) The Government of Uganda represented by the Rural Electrification Agency contracted (….insert name of contractor…) (here in called the contractor) for the implementation of the (…..insert name of the scheme..) located in (…..insert District..) The works have been completed and off-load testing of the network successfully conducted and commissioning and final takeover scheduled from (….insert date…..) This network falls under (….insert the name of the service territory..) and shall be operated by (….name of the service provider…) as per the lease agreement signed with the Rural Electrification Agency. The scope of works include:- (….insert No. Scheme Name District Feeder HV LV (1Phase) As Built Scope LV Transformer (3Phase) Capacity ……) This is to request you to; 1. Grant a shut down on the above feeder to enable interconnection 2. Nominate a team that will facilitate the final inspection and commissioning of the network 3. Thereafter, take over the operation of the network. Please liaise with (……insert name of the Contract manager …) on behalf of the Agency and (…..insert name of the project engineer….) on behalf of the contractor, who will coordinate the above exercise. Your corporation shall be highly appreciated For your reference, attached hereto is the as-built drawings and the pre-commissioning test results Signature (….Insert name of MPDM…) For: Executive Director C.C. C.C C.C Service Provider Regional Offices Supervision Consultant Contractor 149 | P a g e ANNEX 26: SHUT DOWN AND COMMISSIONING LETTER TEMPLATE (UMEME) (…insert full address of the service provider, Usually the CTO) Request for shut down, Commissioning and Handover of (….insert actual name of the scheme, indicating the district…..) The Government of Uganda represented by the Rural Electrification Agency contracted (….insert name of contractor…) (here in called the contractor) for the implementation of the (…..insert name of the scheme..) located in (…..insert District..) The works have been completed and off-load testing of the network successfully conducted and commissioning and final takeover scheduled from (….insert date…..) This network falls under the UMEME Service Territory and shall be operated as per the new Electricity Distribution Network Agreement signed with the Rural Electrification Agency. The scope of works include:- (….insert No. Scheme Name District Feeder HV LV (1Phase) As Built Scope LV (3Phase) Transformer Capacity ……) This is to request you to; 1. Grant a shut down on the above feeder to enable interconnection 2. Nominate a team that will facilitate the final inspection and commissioning of the network 3. Thereafter, take over the operation of the network. Please liaise with (……insert name of project engineer…) on behalf of the Agency and (…..insert name of the project engineer….) on behalf of the contractor, who will coordinate the above exercise. Your corporation shall be highly appreciated. For your reference, attached hereto is the as-built drawings and the pre-commissioning test results Signature (….Insert name of MPDM…) For: Executive Director C.C. Service Provider Regional Offices C.C Supervision Consultant C.C Contractor 150 | P a g e ANNEX 27: INVITATION LETTER FOR COMMISSIONING OF BULK METERING UNITS AND AUTO RECLOSERS (UETCL) (…insert date…) The Chief Executive Officer, Uganda Electricity Transmission Company Limited Plot 10, Hannington Road P.O. Box 23841, Kampala (…insert address of the operator of feeder network…) RE: COMMISSIONING OF BULK METERING UNITS AND AUTO RECLOSERS IN (…insert district name…) The Government of Uganda represented by the Rural Electrification Agency contracted (…insert name of the Contractor…) (herein called the contractor) for the implementation of construction works from (…insert project details…). The works have been completed with a metering unit and auto recloser installed at the start of each tee-off listed in the table below. Off-load testing of the network was successfully conducted and commissioning and final takeover scheduled for (…insert date…). This network falls under the (…insert name of the Service Territory…) and shall be operated by (…insert name of the Service Provider…) as per the new Electricity Distribution Network Agreement (this is for UMEME) or lease agreement (other Service Providers) signed with the Rural Electrification Agency. The scope of works include:Scheme No. Description Feeder Name Distri ct TX Capacity MV Route LV Route (kVA) Length Length This is to request you nominate a team that will commission the bulk meters and system protection switch gears. The key stake holders include; REA (the client), UETCL (systems operator), (…insert name of operator of feeder network…) (operator of feeder network) and (…insert name of operator of the newly constructed network…) (operator of newly constructed network). Activities will involve energizing the networks, taking initial readings on the meters, checking protection settings and verification of the functional operation of the interfacing switch gears. 151 | P a g e Please liaise with (…insert name and contact of REA representative…) on behalf of the Agency and (…insert name and contact of the Contractor’s representative…) on behalf of the contractor, who will coordinate the above exercise. Your corporation shall be highly appreciated. (….Insert name of MPDM…) For: Executive Director C.C Operator of the Feeder Network C.C. Service Provider Regional Offices C.C Supervision Consultant C.C Contractor 152 | P a g e ANNEX 28: INVITATION LETTER FOR COMMISSIONING (UEDCL) (…insert date…) The Managing Director, Uganda Electricity Distribution Company Limited (UEDCL) P.O. Box 7390, KAMPALA – UGANDA. COMMISSIONING OF (…insert name of the project…) The Government of Uganda represented by the Rural Electrification Board signed a contract with (…insert name of the contractor…) to execute (…insert name of the project…). The works have been completed and off-load testing of the network successfully conducted. Commissioning and final takeover have been scheduled from (…insert date…). The line is therefore ready for commissioning and/or eventual takeover. These networks fall under the (…insert name of service territory…) and will be managed by UEDCL under the Management and Operations Agreement. As Built Scope Scheme No. District Feeder HV LV LV Transformer Name (1Phase) (3Phase) Capacity The purpose of this communication is therefore to request you to nominate a team of this is to request you to; i. Nominate a team that will facilitate the final inspection and commissioning of the network. ii. Thereafter, take over the operation of the network. Please liaise with (…insert name, phone contact and e-mail of REA representative(s)…) on behalf of the Agency and (…insert name, phone contact and e-mail of Contractor’s representative(s)…) on behalf of the Contractor, who will coordinate the above exercise. Your corporation shall be highly appreciated. For your reference, attached hereto is the as-built drawings and the pre-commissioning test results. Signature (….Insert name of Project Manager…) For: Executive Director Cc: UEDCL Service Territory Manager Cc: Contractor’s Project Manager 153 | P a g e ANNEX 29: COMMISSIONING REPORT TEMPLATE RURAL ELECTRIFICATION AGENCY TRANSFORMER COMMISSIONING REPORT TRANSFORMER PARTICULARS LOCATION MAKE TYPE RATING (kVA) SERIAL NUMBER YEAR OF MANUFACTURE % IMPEDANCE NUMBER OF PHASES RATED VOLTAGE PRIMARY (kV) OIL LEVEL TEST RESULTS EARTH RESISTANCE TEST NO LOAD OUTPUT VOLTAGE COMMENTS SECONDARY (V) COMMENTS HV (Ω) LV (Ω) PHASE-PHASE (V) RY RB YB PHASE-NEUTRAL (V) R-N Y-N B-N FINAL TAP POSITION FUSE RATING (A) PRIMARY SECONDARY (CCT SECONDARY (CCT 1) 2) PHASE SEQUENCE GENERAL PASS ASSESSMENT WITNESSED BY CONTRACTOR Name Designation Signature Date FAIL REA CONSULTANT OPERATOR 154 | P a g e OVERHEAD STRUCTURE INSPECTION CHECKLIST FOR REA SCHEMES. SCHEME NAME………………………………………………………………………………………………………. LOCATION OF THE T-OFF…………………………………………………………………………………… FEEDER NAME………………………………………………………………………………………………………. SERVICE PROVIDER DISTRICT…………………………………………………………………………………………………… Observations/Measurements to be made Outcome for TX No 1 Outcome for Outcome for TX No 2 TX No3 Check for T-off protection(DOFI installed) Check for alignment of DOFI Are conductors jointed with ferrules No of PG clamps on each HV jumper No of missing pole caps No of loose stays Incomplete stay works In adequate clearance btn LV pole and HV conductors Inadequate clearance between HV conductors(11&33) No of sections with missing insulator supports Tree(s) under, close or touching HV line. Long HV spans(Above 100m) Clearance of HV conductor from ground. Backfilling of HV poles not to required standard. 155 | P a g e Leaning Structures (T-off, Transformer, 3 or 2-members) No of loose spindles. Inadequate clearance btn stay and conductor(LV orHV) No of broken HV insulators No of vandalized HV stays No of substandard poles(9m,10m,12m,14m) No of rotten poles(9m,10m,12m,14m Check HV and LV bushings if lugged Check Transformer earth tank if lugged. Check jumpers to arrestors if connected using Pg clamps No of blown arrestors Check LV breakers, lucy cut-outs if lugged Check for clearance between phases of the breaker(s) No of faulty breakers No of LV circuits LV radius(X- Y- No of long LV spans Missing pole caps on LV poles No of fallen LV poles. Conductor firmly bound on insulators Danger Plates mounted on HV poles Pole tags available on MV poles 156 | P a g e Surge arrestors on terminal structure(s) No of leaning intermediate poles Serial number of the transformer Rating of the transformer Impedance Year of manufucture Make of the transformer Tap Position TX GPS X-coordinate TX GPS Y- coordinate HV-earth impedance value in Ohoms LV-earth impedance value in Ohoms Earth value for surge arrestors Red and yellow voltage Red and Blue voltage Yellow and Blue voltage Red and Neutral voltage Yellow and Neutral voltage Blue and Neutral voltage 157 | P a g e INITIAL SCHEME HANDOVER (FOR OPERATION) MINUTE FORMAT CONTRACTOR: ……………………………. SCHEME NO: …………………………….. PROJECT NAME: ……………………………. We the undersigned confirm the services described in the Acceptance Certificate and other attachments herewith have been completed in accordance with the contract requirements. We agree the asset can be handed over to [INSERT SERVICE PROVIDER] Engineer of ……………………….………….. [INSERT SERVICE PROVIDER] District who will be responsible for the operating of the asset from the date given on the Acceptance Certificate while the Contractor meets the maintenance obligation till the end of Defects Liability Period. Scope of works:………………………………………………………………………………….. Name: Signature: Date: 1. Contractor Person. ………………………………. ………………… ……………… 2. District Official. (Operations Engineer). ………………………………. ………………… ……………… 3. Quality Compliance Officer. ………………………………. ………………… …………… 4. System Control /Protection Engineer. ………………………………. …………………… ………………... 5. REA Engineer ……………………………….. …………………… …………………. 6. Quality Assurance Manager ……………………………………… …………………….. 158 | P a g e ANNEX 30: CERTIFICATE OF PRACTICAL COMPLETION CERTIFICATE OF PRACTICAL COMPLETION EMPLOYER: RURAL ELECTRIFICATION AGENCY MINISTRY OF ENERGY AND MINERAL DEVELOPMENT P.O.BOX 7317, KAMPALA CONTRACTOR: (……….name of contractor as stated in contract…..) (………address of contractor, including country…..) CONTRACT: (…..state the name of the contract…………) CONTRACT NO: (…….insert procurement reference number as stated in contract…) PROJECT SCOPE: ENGINEERING, PROCUREMENT AND CONSTRUCTION OF (insert as-built MV and LV length...) and the INSTALLATION OF (…insert no..) DISTRIBUTION TRANSORMERS plus the connection of (…..insert no….) last mile consumers Contract Signing Date :…………… Contract Effectiveness Date : ……………. Date of Commissioning and Handover :…………….. End of Defects Liability Period :……………… We hereby certify that subject to the contractor’s liability to remedy all defects which may become apparent during the Defects Liability Period, the works under the signed contract were practically completed on ………… and that in relation to the said works, the said Defects Liability Period of One calendar Year will end on ……………….. (…insert Name…) EXECUTIVE DIRECTOR 159 | P a g e ANNEX 31: SUB-CONTRACTING CRITERIA Introduction This criterion only covers subcontracting of construction and installation works of the projects being implemented by Rural Electrification Agency (REA). Other sub-contractors for example supplier of materials, manufacturers, transporters, etc. shall be addressed in the respective REA equipment and process manuals Main Contractor a) Definition A main contractor is a company contracted by REA to carry out design, supply or construction of 33kV or 11kV lines and associated low voltage networks in rural electrification projects areas b) Responsibility of the main contractor The major responsibility of the main contractor shall include but not limited to i). Performance of the contract ii). Project management iii). Engineering design iv). Pre-financing the project implementation v). Coordination, supervision and monitoring of all sub-contractors vi). Development and implementation of ESMP vii). Sub-contractor payment for works completed and certified by the main contractor shall not be subject to client payment to the main contractor viii). From submission of the sub-contractor’s claim, verification and payment shall be within a period of one month. c) Scope of the main contractor The scope of the main contractor shall include but not limited to surveying and line route profiling, pegging and bush clearing, procurement and delivery to site of MV and LV overhead line construction materials including distribution transformers, bulk metering equipment and switchgears, overhead bare conductors, aerial bundled conductors, treated wooden poles, line insulators and related hardware accessories and protection 160 | P a g e devices, medium voltage and low voltage network construction, installation of distribution transformers and protection equipment and network testing, commissioning and development and submission of as built drawings. Sub-Contractor a) Definition A sub-contractor is a company contracted by the main contractor to undertake specifics part of the contract. b) Roles and responsibility of the sub-contractor The sub-contractor shall be responsible for the following i). Construction of works and installation of equipment as per sub-contract ii). Ensuring safety of all workers iii). Ensure proper handling of equipment and materials iv). Ensure security of materials and equipment under his/her custody v). Ensure execution of works as per the approved methodology vi). Handling sub-contractor staff welfare and payments promptly vii). Use of personnel with the required technical qualifications and experience viii). Providing the required minimum tools and equipment needed to implement the works ix). Implementation of the works in line with the acceptable code of conduct c) Scope of the sub-contractor The scope of the sub-contractor shall be limited to any or all of the following Surveying, pegging and route clearance Transportation of materials and equipment from the contractor store to site at the specified rate Installation works (i.e pit excavation, erection, dressing, stringing, equipment installation) Preparation of as-built drawings for the section of the works implemented Qualification Requirements a) Eligibility 161 | P a g e i). Certificate of Incorporation ii). Valid trading license iii). Income tax clearance iv). Valid VAT registration certificate v). Valid PPDA registration certificate vi). Articles and Memorandum of Association vii). Particulars of the Directors (Company form 7) with copy of identification(driving permit, national ID or passport) and detailed CVs with passport photos attached viii). Office premises ix). Valid NSSF registration certificate x). Audited books of accounts for the previous 1 years i). Should not be suspended by PPDA or development partners ii). Recommendation from registered engineer iii). Acceptable code of conduct b) Organizational Structure of the Sub-Contractor The staffing of the sub-contractor shall be organized in a way to include the following key positions with minimum level of qualification and experience. i). Engineering ii). Finance iii). HR c) Minimum Technical Experience and Capability of the Firm i). Proposed construction methodology ii). Proof of existence of for 2 year iii). Proof of two (02) similar works done in the last 2 years similar in scope, amount and complexity iv). Indicate details of works currently under implementation by the subcontractor indicating scope and amount 162 | P a g e No. Table 6: Key personnel with the minimum level of qualification and experience Personnel Minimum Qualification/Expertise Experience Project Manager/ Electrical Bsc. Electrical Engineering with Class B ERA 2 years Engineer certificate Foremen Ordinary diploma in electrical or equivalent 5 years d) Minimum Financial Requirement i). Proof of availability of cash or line of credit to fund works to a total of Fifty Million Shillings (UGX 50,000,000) ii). The sub-contractor shall pre-finance works to a total of Fifty Million shilling (UGX 50,000,000) iii). Letter authorizing the main contractor to seek information relating to the financial capability of the sub-contractor from their bankers e) Minimum Equipment Owned by the Sub-Contractor The following are the minimal tools and equipment needed to execute the minimum amount of work. The quantities for the following tools & equipment shall increase commensurate to the amount of work to be sub-contracted i). Drums jerks – (02) ii). Climbing irons – (10) iii). Self-loader (boom) truck – (01) iv). Service van for workers movements(transportation of workers on the same vehicles with materials is not encouraged) – (01) v). Truck/Lorry for transporting materials – (01) vi). Pulley lifts – (03) vii). Camlongs – (05) viii). Compression tools – (02) ix). Turfors – (02) x). Pit excavation irons – (30) xi). Power saw – (01) xii). Earth resistance meter Guidelines to Sub-Contracting 163 | P a g e a) Supervision The main contractor shall be responsible for supervising the sub-contractor. The main contractor shall assign at all a resident engineer with a minimum of bachelor’s degree in electrical engineering who will be responsible for supervising the sub-contractor. b) Approvals i). The Main contractor shall seek written approval from the employer prior to engagement of the sub-contractor. ii). A profile of the sub-contractor with all the required information shall be submitted to the client with a draft sub-contract agreement in line this criteria. The client’s respective Contract manager shall be a witness on behalf of the main contractor in the sub-contract agreement. iii). The main contract shall retain 10% of the contract sum as security for performance. iv). The sub-contractor shall not be allowed to sub-contractor further. v). Joint ventures are allowed and shall be assessed cumulatively. vi). In seeking for the above approval, the main contractor shall clearly indicate the section of the work they intend to subcontract and the level of engagement in line with line construction i.e surveying, pit excavations, erection, dressing and stringing. c) Scope of work to be contracted The minimum amount of work to be subcontracted shall be 25km of HV and associated low voltage networks. The following tasks shall not be sub-contracted and shall remain the responsibility of the main contractor; i). Overall engineering design ii). Project reporting and communications iii). Materials sourcing and procurement iv). Material and equipment safety on site before project closure v). Pre-commissioning and commissioning. The main contractor shall first ascertain that the works have been done satisfactorily by the sub-contractor 164 | P a g e before communicating to the client for inspection, pre-commissioning and commissioning. vi). Stakeholder engagement d) REA Image At all times, REA’s values shall be upheld by the main contractor and the sub-contractor in the field. e) Un-condition termination clauses The under-listed conditions shall form part of the conditions for termination by of the contract and shall be part of the sub-contract agreement i). Extortion of money from project beneficiaries in disguise of extend service ii). Breach of the approved methodology iii). Breach of the approved code of conductor iv). Implementation of works outside the provided scope by the main contractor v). Theft and vandalism of project materials and equipment by sub-contractor f) Sub-contractor Payments The contractor shall be paid for works completed either per stage or activity as shown in section (Minimum rates per activity). Issuance of advance payment shall be at per the terms and conditions of the main contractor. Sub-contractor payments for works completed shall not be subject to client’s payment to main contractor. 165 | P a g e Minimum Installation rate for Sub-contracting (Wooden Poles) Unit of Measure Quantity Unit Rate 1 Systems Interface Switchgear (The Unit Cost shall include the safe storage, appropriate installation, termination and commissioning. The unit measure shall also include the installation of accessories and /or auxiliary equipment required for proper functioning) 33kV Load Break Switches No. 1 500,000 2 11kV Load Break Switches No. 1 500,000 3 33kV Bulk Metering Unit complete with a main and check bulk energy meters No. 1 550,000 4 11kV Bulk Metering Unit complete with a main and check bulk energy meters No. 1 550,000 5 33kV Air Break Switches No. 1 500,000 6 11kV Air Break switches No. 1 500,000 7 33kV Auto-Reclosure No. 1 500,000 8 11kV Auto-Reclosure No. 1 500,000 9 3 Phase, 33kV, Drop-out Fuse Isolators No. 1 100,000 10 3 Phase, 11kV, Drop-out Fuse Isolators No. 1 100,000 B High Voltage Overhead line Works Route Survey, Profiling, Line designs and Templating and Pegging Structure Positions, Bushing clearance at this stage is not allowed. Bush Clearance during construction As-Built Drawings Treated Wooden pole structures km 1 300,000 km km 1 1 150,000 200,000 Per Pole 1 10,000 Normal Per Pit 1 15,000 Rocky Per Pit 1 20,000 Swampy Per Pit 1 20,000 Sandy Per Pit 1 15,000 Per Structure No. No. 1 1 50,000 70,000 120,000 Item Description A 11 12 (Overall unit measure shall consist of pole offloading, positioning, pole pit excavation, pole erection, dressing and complete assembly of a structure. Surge arresters at appropriate structures, structure number and danger plates, circuit labels and pole hardware accessories to be included in the overall unit measure.) Pole Positioning Excavation Single Member Structures 13 Intermediate Erection Dressing Total 14 Light Angle Per Structure 166 | P a g e Erection Dressing NO. NO. 1 1 Total 15 Straight Section Erection Dressing Total 16 Angle Section Erection Dressing Total 17 Line Tee-off Erection Dressing Total 18 Terminal Erection Dressing Total 50,000 70,000 120,000 Per Structure No. No. 1 1 50,000 70,000 120,000 Per Structure No. No. 1 1 50,000 70,000 120,000 Per Structure No. No. 1 1 50,000 70,000 120,000 Per Structure No. No. 1 1 50,000 70,000 120,000 Per Structure N0. N0. 1 1 100,000 140,000 240,000 Per Structure No. No. 1 1 100,000 140,000 240,000 Per Structure No. No. 1 1 100,000 140,000 240,000 Per Structure No. No. 1 1 100,000 140,000 Two Member structures 19 Support/Intermediate Erection Dressing Total 20 Straight Section Erection Dressing Total 21 Angle Section Erection Dressing Total 22 Equipment Structure Erection Dressing 167 | P a g e Total 23 Tee-off Erection Dressing Total 24 Terminal Erection Dressing Total 240,000 Per Structure No. No. 1 1 100,000 140,000 240,000 Per Structure No. No. 1 1 100,000 140,000 240,000 Per Structure No. No. 1 1 150,000 210,000 360,000 Per Structure No. No. 1 1 150,000 210,000 360,000 Per Structure No. No. 1 1 150,000 210,000 360,000 Three Member Structures 25 Support/Intermediate Erection Dressing Total 26 Straight Section Erection Dressing Total 27 Angle Section Erection Dressing Total Stays and Galvanised steel wires Per Complete Stay The unit cost shall include the complete installation 7/4 stay wire, stay rods, buckles, stay insulators and all the necessary accessories for a complete stay assembly. 28 Conventional Stay Assembly No. 1 125,000 29 Flying Stay Assembly No. 1 150,000 30 Short Stay Assembly No. 1 135,000 31 Prop (Guy) pole Stay No. 1 150,000 Conductors Stringing Per KM The unit cost shall include the proper handling and storage and installation on assembled structures. Including stringing, sagging, connecting jumper and installing all necessary termination hardware accessories. 32 AAAC100 km 1 900,000 33 AAAC50 km 1 800,000 34 Distribution Substations/Transformer Installation Per Transformer 168 | P a g e 35 (The Unit Cost shall include the safe storage, installation and commissioning, including the proper termination of 70mm 2 copper or 120mm2 cables for LV outgoing circuits, LV cut-out fuses, surge arresters, and earthing requirements. The cost of the structure is excluded) C Low Voltage Overhead line Works 36 Survey, Bush Clearance, Profiling, Line designs and Pegging (LV) 37 Conductor Stringing ABC 50mm2 38 No 1 1,000,000 km 1 200,000 Per Km (The unit cost shall include the proper handling and storage and installation on assembled structures. Including all necessary termination hardware accessories required for the low voltage network. Exclude the cost of assembly of structures which is measured else were.) km 1 1,000,000 As-Built Drawing km 1 150,000 LV distribution network Structures Per Structure (Unit measure to include pole offloading, positioning, pit excavation, erection, dressing and complete assembly of LV structures, including installation of appropriate insulators, termination and pole hardware accessories. A minimum span length of 50m shall be maintained.) 39 ABC T from Strain No. 1 100,000 40 ABC T from Intermediate No. 1 100,000 41 ABC Terminal Assembly No. 1 100,000 42 ABC Intermediate Assembly (0-30) No. 1 100,000 43 ABC Strain Assembly (30-60) No. 1 100,000 44 ABC Strain Assembly (60-90) No. 1 100,000 45 ABC X Intermediate- Intermediate No. 1 100,000 46 ABC X Intermediate- Strain No. 1 100,000 47 LV Stays No. 1 120,000 48 Transport Cost Per KM km 1 15,000 169 | P a g e ANNEX 32: APPROVAL OF MANUFACTURER AND TECHNICAL SPECIFICATIONS Annex 32 A: Transformers Our Ref: …….. (Insert date) …. (Insert Address for the Contractor Attn: Authorized Signatory as per contract) Dear Sir/Madam, (Insert Contract Name) Approval of Manufacturer and Technical Specifications Reference is made to yours date (….insert date…), in which you proposed supply of transformers from (…insert full address of the proposed manufacturer…). The details of the factory and the transformer specification have been assessed and found ( …complaint or not….) with conditions detailed below. This is to therefore; Approve (….full details of the manufacturer…) as the manufacturer of distribution transformers for the above mentioned Approve distribution transformer specifications as detailed in the technical assessment attached subject to the following under listed conditions; 1. A second brass/stainless steel plate similar to the rating plate shall be attached to one side of the transformers with words of “REA, Voltage/Rating (e.g. REA 33/50) “stenciled in black ink. 2. No load and Load losses and Noise levels Size (KVA) Voltage (V) 25 50 100 200 315 500 No Load Loss (W) 11 33 150 150 175 250 325 430 400 630 510 800 710 1000 Load Loss (W) 11 33 605 480 1305 680 2135 1250 2850 2500 3850 3500 4850 4250 Noise dB (A) 45 48 50 51 55 56 3. The winding should be either copper wire or foil 170 | P a g e 4. The core type should be three limbs stacked made of CRGOSS cut using step-lap technology 5. The tank should be hermetically sealed, hot dip galvanized & powder coated to total minimum coating thickness of 100um 6. The tank should be fabricated with the following minimum thickness for transformers rated less than 400KVA; tank – 3mm, base – 3mm, cover plate – 4mm, flange – 6mm, radiator – 1.2mm while for 400KVA and above tank – 6mm, base – 6mm, cover plate – 6mm, flange – 6mm, radiator – 1.2mm. The respective transformers shall be accepted upon passing the Routine Tests that shall be conducted at the manufacturers premise in accordance to IEC 60076 standard. The manufacturer’s testing protocols shall be submitted for review and approval by the client prior to scheduling of factory acceptance tests. The above withstanding, all the products shall have to conform to Pre-Export Verification of Conformity (PVoC) as required by Uganda National Bureau of Standards. The contractor shall facilitate post shipment inspection and testing to confirm performance characteristics of the respective transformers, which will be conducted at a testing laboratory designated by REA. This approval does not rescind you of your contractual obligation. FOR EXECUTIVE DIRECTOR Cc: (…..Supervision consultant…) 171 | P a g e Annex 32 B: Conductor Ref: ……….. …(Insert date)….. The Project Manager …(Insert Contractor’s Name)… ….(Insert Address of Contractor)…… (INSERT CONTRACT NAME) Approval of Manufacturer and Technical Specifications Reference is made to yours dated …(Insert date)…, in which you proposed change of supplier for AAAC conductors from ….(Insert full name and address of the factory of the proposed manufacturer)….... The details of the factory and the conductor specification have been assessed and found complaint with conditions detailed below. This is to therefore; Approve …..….(Insert full name and address of the factory of the proposed manufacturer)…, as the manufacturer of AAAC Conductors for the above-mentioned project Approve AAAC Conductors specifications as detailed in the technical assessment attached with emphasis on the following under listed conditions; 1. All drums of AAAC Conductors shall be labeled with words indicating “Client, DC resistance at 200C, Tensile Strength in kN, Number of stands and Stand diameter” marked in black ink on the palate. 2. The AAAC Conductors shall meet the following minimum specifications. Parameter Unit Required Specifications AAAC 100sqmm Conductor Number of Strand Diameter of Strand Calculated D.C Resistance at 200C Calculated Tensile Strength AAAC 50sqmm Conductor Pcs mm Ohms/km kN 7 4.26 0.3357 30.17 172 | P a g e Number of Strand Diameter of Strand Calculated D.C Resistance at 200C Calculated Tensile Strength Pcs mm Ohms/km kN 7 3.02 0.668 15.8 The respective AAAC Conductors shall be accepted upon passing the Routine Tests that shall be conducted at the manufacturers premise in accordance to IEC 61089 and ASTM B399 standards. The manufacturer’s testing protocols shall be submitted for review and approval by the client prior to scheduling of factory acceptance tests. The above withstanding, all the products shall have to conform to Pre-Export Verification of Conformity (PVoC) as required by Uganda National Bureau of Standards. The contractor shall facilitate Post- Shipment Inspection and Testing to confirm performance characteristics of the respective AAAC Conductors, which will be conducted at a testing laboratory designated by REA. This approval does not rescind you of your contractual obligation. …..(Insert Name of MPDM or DED-TO)…. For: EXECUTIVE DIRECTOR c.c: Project Manager, ….(Insert name of supervision consultant)… 173 | P a g e Annex 32 C: ABC Cable Ref: ……….. …(Insert date)….. The Project Manager …(Insert Contractor’s Name)… ….(Insert Address of Contractor)…… (INSERT CONTRACT NAME) Approval of Manufacturer and Technical Specifications Reference is made to yours dated …(Insert date)…, in which you proposed change of supplier for LV Aerial Bundled Cables from ….(Insert full name and address of the factory of the proposed manufacturer)….... The details of the factory and the LV Aerial Bundled Cables specification have been assessed and found complaint with conditions detailed below. This is to therefore; Approve …..….(Insert full name and address of the factory of the proposed manufacturer)…, as the manufacturer of LV Aerial Bundled Cables for the above-mentioned project. Approve LV Aerial Bundled Cables specifications as detailed in the technical assessment attached with emphasis on the following under listed conditions; 7. All drums of LV Aerial Bundled Cables shall be labeled with words indicating “Client, DC Resistance at 200C, Tensile Strength in kN, Number of stands and Stand diameter” marked in black ink on the palate. 8. The LV Aerial Bundled Cables shall meet the following minimum specifications Parameter Unit Required Specifications LV Aerial Bundled Cables Diameter of Conductor per Phase mm 8.2 0 Calculated D.C Resistance at 20 C Ohms/km 0.641 Insulation Level kV 0.65/1.2 Insulating Material Black weather resistant cross linked thermosetting polyethylene (XLPE) Neutral Messenger Nominal cross-sectional area mm2 54.6 Diameter of Core mm 9.2 174 | P a g e The respective LV Aerial Bundled Cables shall be accepted upon passing the Routine Tests that shall be conducted at the manufacturers premise in accordance to IEC 61089 and SANS 1418 standards. The manufacturer’s testing protocols shall be submitted for review and approval by the client prior to scheduling of factory acceptance tests. The above withstanding, all the products shall have to conform to Pre-Export Verification of Conformity (PVoC) as required by Uganda National Bureau of Standards. The contractor shall facilitate Post- Shipment Inspection and Testing to confirm performance characteristics of the respective LV Aerial Bundled Cables, which will be conducted at a testing laboratory designated by REA. This approval does not rescind you of your contractual obligation. …..(Insert Name of MPDM or DED-TO)…. For: EXECUTIVE DIRECTOR c.c: Project Manager, ….(Insert name of supervision consultant)… 175 | P a g e Annex 32 D: Galvanized Steel Earth Wires & Galvanized Steel Stay Wire Ref: ……….. …(Insert date)….. The Project Manager …(Insert Contractor’s Name)… ….(Insert Address of Contractor)…… (INSERT CONTRACT NAME) Approval of Manufacturer and Technical Specifications Reference is made to yours dated …(Insert date)…, in which you proposed change of supplier for Galvanized Steel Earth Wires & Galvanized Steel Stay Wire from ….(Insert full name and address of the factory of the proposed manufacturer)…..... The details of the factory and the Galvanized Steel Earth Wires & Galvanized Steel Stay Wire specification have been assessed and found complaint with conditions detailed below. This is to therefore; Approve …..….(Insert full name and address of the factory of the proposed manufacturer)…, as the manufacturer of Galvanized Steel Earth Wires & Galvanized Steel Stay Wire for the above-mentioned project. Approve Galvanized Steel Earth Wires & Galvanized Steel Stay Wire specifications as detailed in the technical assessment attached with emphasis on the following under listed conditions; 1. All drums of Galvanized Steel Earth Wires & Galvanized Steel Stay Wire shall be labeled with words indicating “Client, Tensile Strength in kN, Number of stands and Stand diameter” marked in black ink on the palate. 2. The Galvanized Steel Earth Wires and Galvanized Steel Stay Wires shall meet the following minimum specifications Parameter Galvanised Steel Earth Wire (3/2.64) Diameter of Strand Calculated Tensile Strength Weight of Zinc Coating Coating Type Galvanised Steel Stay Wire (7/4.0) Calculated Tensile Strength Unit Required Specifications mm kN Kg/m2 2.64 18 0.24 Hot dip galvanized kN 101 176 | P a g e Weight of Zinc Coating Coating Type Galvanised Steel Stay Wire (7/2.64) Calculated Tensile Strength Strand Diameter Weight of Zinc Coating Coating Type Kg/m2 0.24 Hot dip galvanized kN mm Kg/m2 44 2.64 0.24 Hot dip galvanized The respective Galvanized Steel Earth Wires and Galvanized Steel Stay Wires shall be accepted upon passing the Routine Tests that shall be conducted at the manufacturers premise in accordance to IEC 888 and ASTM A475 standards. The manufacturer’s testing protocols shall be submitted for review and approval by the client prior to scheduling of factory acceptance tests. The above withstanding, all the products shall have to conform to Pre-Export Verification of Conformity (PVoC) as required by Uganda National Bureau of Standards. The contractor shall facilitate Post- Shipment Inspection and Testing to confirm performance characteristics of the respective Galvanized Steel Earth Wires and Galvanized Steel Stay Wires, which will be conducted at a testing laboratory designated by REA. This approval does not rescind you of your contractual obligation. …..(Insert Name of MPDM or DED-TO)…. For: EXECUTIVE DIRECTOR c.c: Project Manager, ….(Insert name of supervision consultant)… 177 | P a g e Annex 32E: Wooden or Concrete Poles Ref: ……….. …(Insert date)….. The Project Manager …(Insert Contractor’s Name)… ….(Insert Address of Contractor)…… (INSERT CONTRACT NAME) Approval of Manufacturer and Technical Specifications Reference is made to yours dated …(Insert date)…, in which you proposed change of supplier for Treated Wooden Poles from ….(Insert full name and address of the factory of the proposed manufacturer)….... The details of the factory and the Treated Wooden Poles specification have been assessed and found complaint with conditions detailed below. This is to therefore; Approve …..….(Insert full name and address of the factory of the proposed manufacturer)…, as the manufacturer of Treated Wooden Poles for the above-mentioned project Approve Treated Wooden Pole specifications as detailed in the technical assessment attached, on condition that all “conditions for approval” be effected. The poles shall be accepted upon passing the Pre-dispatch Tests that shall be conducted at the manufacturers premise in accordance to REA’s pole treatment manual and reference standards. The manufacturer’s testing protocols shall be submitted for review and approval by the client prior to scheduling of factory acceptance tests. The above withstanding, samples of the concentrate and the mixture of the preservative shall routinely be subjected to chemical composition analysis tests at the contractor’s cost, which will be conducted at a testing laboratory designated by REA. This approval does not rescind you of your contractual obligation. …..(Insert Name of MPDM or DED-TO)…. For: EXECUTIVE DIRECTOR 178 | P a g e ANNEX 33: LETTER OF INTRODUCTION TO THE DISTRICT (Insert Date) Chief Administrative Officer (Insert District Name) Dear Sir/Madam LETTER OF INTRODUCTION The Government of Uganda represented by the Rural Electrification Board has signed a contract with (...insert name of Contractor…) for the construction of power networks in (…mention names of Districts…). Here in attached are the load centers that will be electrified in (…insert name of District to which this letter is going…) under this project. The Contractor is mobilizing and soon will commence the execution of the above construction works starting with powerline route survey. The purpose of this communication therefore is to introduce to you (...insert name of Contractor…) the contractor of the project on behalf of the Agency. In order to implement the project smoothly, the Agency requests you to nominate a focal person that will work closely with the Project management team. The contact person for the contractor shall be (…insert Contractors contact personnel…), and (…REA’s contact personnel…) shall represent the Rural Electrification Agency Your kind cooperation will be highly appreciated (Insert name of MPDM) FOR: EXECUTIVE DIRECTOR. cc: cc: cc: cc: cc: cc: cc: All District MPs Woman MP LC V Chairman District Security Officer District Environmental Officer Project Manager, (Contractor’s Name) Project Manager, (Consultant’s Name) 179 | P a g e ANNEX 34: STRUCTURE BY STRUCTURE AUDIT TOOL Name of Project: Name of Scheme: Date: M - Mechanical Damage W - Poor Workmanship O - Any Other H - Hollow Heart S - Structure Number Plate MI - Missing Item(s) C - Corrosion of hardware T - Termite Attack F - Fungi attack I - Insect Attack NO POLE POLE SPAN TYPE HEIGHT LENGTH NO OF STAYS MEASUREMENT TEST VISUAL OBSERVATION DIAMETER AT SOUNDING POLES ACCESSORIES EQUIPMENT GROUNDLINE OF POLES H F T CA W TA S I O M MI W C O M MI W C O TA - Presence of Manufacturer's Tag CA - Cracks REMARKS 180 | P a g e ANNEX 35: CONTRACT CLOSURE CHECKLIST Project Name: ……………………………… Start Date: …………………………. End Date: …………………. NO. DESCRIPTION CC-01 Certificate of Final Amendment of the Contract CC-02 Certificate of “ As Built” Drawing Receipt CC-03 Certificate on all Miscellaneous Technical records CC-04 Certificate of Scope Completion CC-05 Certificate on Liquidated Damages for Delay CC-07 Certificate on Payment Reconciliation CC-08 Certificate on Labor Payment CONTENT OF CERTIFICATION Certification that all amendments have been issued: Last Amendment # and date……….. Certification that contractor has furnished all as built drawing in soft copy and in requisite numbers in hard copies on ……… Certification that all relevant technical records (e.g. Operation and Maintenance Manuals, Wayleaves forms) (refer paragraph 3.24 of Procurement Manual for Works) are available and kept at …………. Certification that contract has been completed as required by the scope of work Certification that LD for Delay as per contract provision is resolved Certification that all payments released to the contractor have been reconciled and no recoveries are pending A certification that all labor payment including any Provident Fund liabilities have been complied as per statutory requirement CC-09 Certificate on A certification that all scaffoldings, Removal of all surplus material, rubbish and malba Surplus Material and has been removed. This shall be issued Site Cleared after a final site inspection by REA with the contractor CC-10 Certification on A certificate that contractor has fulfilled Defect Liability all its defect liability obligations Obligation REFERENCE DOCUMENT AND RESPONSIBLE PERSON Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Environment and Social Personnel Project Manager Service Territory Department 181 | P a g e CC-11 Certificate on Return of all BGs? Performance Security and other Financial Documents CC-12 No Claim Certificate A certificate that all security deposits, BG, hypothecation deed, insurance policies have been returned Procurement A no claim certificate to be obtained as per attached format and exchanged for CC-11 Project Manager 182 | P a g e ANNEX 36: NO CLAIM CERTIFICATE (On Company Letterhead) To, (Contract Executing Officer) Procuring Entity_______________________ NO CLAIM CERTIFICATE Contract Name: …………………………….. Procurement Reference Number: …………………………………………….. Date: ………………………………………. We have received the sum of ( ______________________________________only) in full and final settlement of all the payments due to us for the completion of work of under the abovementioned contract agreement, between us and the Government of Uganda through the Rural Electrification Agency. We hereby unconditionally, and without any reservation whatsoever, certify that with this payment, we shall have no claim, whatsoever of any description, on any account, against the government, against aforesaid contract agreement executed by us. We further declare unequivocally, that with this payment, we have received all the amounts payable to us, and have no dispute of any description whatsoever, regarding the amounts worked out as payable to us and received by us, and that we shall continue to be bound by the terms and conditions of the contract agreement, as regards performance of the contract. Yours faithfully, Signatures of Contractor or Officer authorized to sign the Contract Documents On behalf of the Contractor (Company Stamp) Date: Place: 183 | P a g e ANNEX 37: CIRCUIT BREAKER COMMISSIONING FORM RURAL ELECTRIFICATION AGENCY Commissioning Form/Report for Circuit Breaker (Auto Recloser) 1.General Information Substation Name Feeder Name Scheme/ Project Name Voltage Level Commissioning Date 2. Functional Tests Circuit Breaker Tests Local operation CB Open/Close Local operation CB Open/Close Remote operation CB Open/Close Remote operation CB Open/Close Breaker status Open/Close Selector switch Local Remote Local Remote Expected Results Pass Fail Fail Pass 3. Relay Trip Test No. 1 Settings Overcurrent Load current Test current Reclose time Set Remarks Remarks 4. Relay Auto-recloser Test Number of trips Set to lock out Actual Actual 184 | P a g e Rem 5. Protection Settings CT – Ratio CT - Tap(In) BB Voltage No. 1 2 3 6 Settings Overcurrent Earth fault S E/F Ph. Unbalance I> t> I>> t>> %In t> I>> t>> %In 6. Protection Settings for (Nearest substation) CT – Ratio CT - Tap(In) BB Voltage No. 1 2 3 6 Settings Overcurrent Earth fault S E/F Ph. Unbalance I> 7.Earth Resistance results 8.General remarks Commissioned by: ………………………………………………………. Date : ……………………………………………………… 185 | P a g e ANNEX 38: CONTRACT ASSESSMENT TOOL (CONTRACTOR) CONTRACT ASSESSMENT GUIDELINE Stage 1: Assess Detailed Items based on: Quality Submission (Adequacy, Completeness, Usefulness) Timely Submission (Agreed upon timelines) Non-responsiveness Stage 2: Obtain Section Marks in Percentage Sum up all fraction marks from detailed scores and multiply by (1/total no. of items scored) Multiply the total mark by 100% Stage 3: Multiply each percentage mark by it's percentage weight Stage 4: Grade final score as below Satisfactory: Average: Unsatisfactory: 2 1 0 80 to 100 60 to 80 <60 Contractor Performance Evaluation CONTRACTOR: PROJECT NAME: DESCRIPTION: CONTRACT No.: CONTRACT No.: CONTRACT VALUE: DATE: Ranking: START DATE: For definitions refer to Backup sheets: COMPLETION DATE: A CONTRACT EFFECTIVENESS 2% Stage Mark 0% B CONTRACTOR DEPLOYMENT MANAGEMENT 8% 0% 0.00% C TIME MANAGEMENT 5% 0% 0.00% D PHYSICAL PROGRESS OF WORKS 20% 0% 0.00% E COST MANAGEMENT 8% 0% 0.00% EVALUATION SECTION WEIGHT Weighted Score 0.00% 186 | P a g e F QUALITY CONTROL 10% 0% 0.00% G ENGINEERNG DESIGNS 18% 0% 0.00% H COMMUNICATION STRATEGY 5% 0% 0.00% I COMMUNITY OUTREACH AND STAKEHOLDER ENGAGEMENT 8% 0% 0.00% J ENVIRONMENT, SOCIAL, SAFETY COMPLIANCE 8% 0% 0.00% K PERFORMANCE OF KEY PROJECT PERSONNEL 8% 0% 0.00% TOTAL 0.00% GRADING: Name: Signature: Date: Contractor: Consultant: Project Manager: Manager: Director: (required for Final only) NOTE: If the contractor disagrees with this evaluation, it is to submit its objections in writing with supporting evidence within five (5) business days 187 | P a g e Contractor Performance Evaluation DELIVERABLES COMMENTS/ CORRECTIVE MEASURES Marks Q A CONTRACT EFFECTIVENESS 1 Performance Security witihin 28 days after notification of contract award 0 2 Advance Payment Guarantee and Claim witihin 48 days from contract signature 0 3 Comprehensive Insurance Covers witihin 28 days from Commencement Date? 0 B CONTRACTOR DEPLOYMENT MANAGEMENT 1 Contractor's Organogram 0 2 Availability of Key Personnel during project execution 0 3 Facilitation of Key Project Personnel and Field Teams 0 4 Adequate updated CVs upon change of Contractor's personnel and Updated Schedule of Personnel 0 5 Submission for approval of Sub-contractor's profiles 0 Q T Stages T Stage 1 Stage 1 Stage 2 0% Stage 2 0% 188 | P a g e 6 Witnessed Sub-contracts by REA representative 0 7 Management of Sub-contractors 0 C TIME MANAGEMENT 1 Month Zero Implementation Plan 0 2 Submission of Project Completion Schedule 0 3 Project Procurement Plan, sub-sequent updates and Impementation 0 4 FAT schedules and sub-sequent updates 0 5 Shutdown shedules and Impementation 0 D PHYSICAL PROGRESS OF WORKS 1 Q Q T T Stage 1 Stage 2 0% Stage 1 Stage 2 Performance against the month zero implementation timelines 0 0% 2 Performance against the monthly timelines 0 3 Compliancy to Contractual Project Completion Schedules 0 189 | P a g e 4 Performance against the weekly timelines 0 E COST MANAGEMENT 1 Submission of updated BoQs? 0 2 Submission of Financial report (Statement of value of works) accompanied by the notes of progress from the Engineer? 0 3 Submission of copies of invoices or equivalent documents proving payment for Equipment/ Materials/ Mobilisation? 0 F QUALITY CONTROL 1 Submission of Quality Control Plans and Impementation 0 2 Submission and Approval of Detailed Technical Specifications and Manufacturer Details 0 3 Manufaturer's FAT Test Methodology/ Test Protocols 0 4 FAT Outcomes (Reports, Rejection of materials, etc) 0 5 Risk Management Plan and Impementation 0 Q Q T T Stage 1 Stage 1 Stage 2 0% Stage 2 0% 190 | P a g e 6 Updated Risk Management and Mitigation Plan IN Progress Report 0 7 Application for change of supplier with a clear justification 0 G ENGINEERING DESIGNS 1 Approved Engineering Design Report 0 2 Approved As-pegged drawings 0 3 Is the Contrator adhering to engineering designs? Evidenced through Progress reports 0 H COMMUNICATION STRATEGY 1 Community Engagement Plan and Implementation 0 2 HIV/AIDS sensitisation plan and implemnttaion 0 3 IEC (Information, Education and Communication) materials for the project 0 4 Gender awareness plan and implemntation 0 5 Daily Progress Report 0 6 Monthly progress reports 0 7 Conflict resolution strategies 0 8 Responses to communications and instructions from Project Manager 0 Q Q T T Stage 1 Stage 1 Stage 2 0% Stage 2 0% 191 | P a g e 9 Incident reporting mechanism 0 10 Defects Correction Reporting 0 11 Requred cost, time and scope variation documents 0 I 1 2 COMMUNITY OUTREACH AND STAKEHOLDER ENGAGEMENT Q T Stakeholder Engagement Plan/ Strategy and Implementation Stakeholder Matrix indicating each Stakeholder's impact on project Community mobilization/ Sensitization plan Stage 1 0 0 3 Community Sensitization Report 0 4 Inclusion of District leaders in project implementation - Should appear in Record Books at CAO's office 0 5 Attendance list attached to the Contractor's Monthly progress report 0 J ENVIRONMENT, SOCIAL, SAFETY COMPLIANCE 1 Prepared and submitted an acceptable CESMP in line with EIA certificate and ESMP in the PB 0 2 Prepared and submitted an acceptable Community Engagement Plan 0 3 Prepared and submitted Management Plan 0 4 Prepared and submitted an acceptable Health and Safety Management Plan an acceptable Stage 2 HIV Q T Stage 1 0% Stage 2 0 192 | P a g e 5 Prepared and submitted an acceptable Management Plan 6 Prepared and submitted an acceptable wetlands work procedures 0 7 Prepared and submitted an acceptable storage yard management and restoration plan 0 8 Prepared and submitted an acceptable Abuse Policy 0 9 10 11 Waste Substance Prepared and submitted an acceptable Incident Management Plan Prepared and submitted an acceptable hazardous materials management plan Prepared and submitted an acceptable project specific Emergency preparedness and Response Plan 0 0 0 0 12 Prepared and submitted an acceptable a Grievance Management Plan 0 13 Maintains environmental and social management records 0 14 Availability of a designated personnel in the field for environmental and social aspects of the project 0 15 Choice of materials storage area appropriate(Not in sensitive ecosystems) 0 16 First aid / emergency facilities / procedures are in place. 0 17 Records of HIV Sensitisation and condoms distribution to workers available 0 0% 193 | P a g e 18 Records of PPE issuance and enforcement in place 0 19 Records of tool box meetings 0 20 Complaints tracking register in place 0 21 Records of compliance with labour laws and policies in place(Welfare of workers, gender) 0 22 Records of regular environmental monitoring in place 0 23 Submission of monthly Environmental and Social Monitoring reports detailing compliance with CESMP and work procedures and plans 0 24 Level of compliance with CESMP 0 25 Level of compliance with work procedures and plans 0 26 27 28 Level of compliance with OHS (Occuation, Health and Safety) requirements Level of compliance with Contract obligations on safeguards Level of compliance with safeguards requirements in REA construction guidelines Name: 0 0 0 Signature: Date: Contractor: Consultant: Project Manager: MPDM: NOTE: If the contractor disagrees with this evaluation, it is to submit its objections in writing with supporting evidence within five (5) business days Division 194 | P a g e PERFORMANCE OF KEY PROJECT PERSONNEL NO. 1 PERSONNEL Project Manager (Name) KEY DELIVERABLES (should be Specific, CONTRACTUAL Measurable RESPONSIBILITIES Achievable, Realistic and Timebased) A completion certificate upon successful implemention of Ensure perfromance project (completed of the contract in time, within budget, scope and with acceptable quality) Ensuring timely submission of required documentation Manage the day to Timely response to day administration formal communications regarding the project Progress reporting Progress reports Schedule and facilitate top Signed minutes Marks COMMENTS/ CORRECTIVE MEASURES Q T Stages Stage 1 Stage 2 0 0 0 0% 0 0 195 | P a g e management meetings Facilitate stakeholder involvement Monthly inspection reports 0 Q 2 Power System Engineer (Name) Development of the contractors Engineering design engineering design report report Development and enforcement of the Contractor's Quality contractors quality Management Plan management plan Oversee construction supervision Ensure adherence to the approved construction methodoloy Progress Reports Schedule and facilitate monthly site meetings T 0 0 0 0% Ensure stakeholder participation during implementation Facilitate FATs, network precommisioning, FAT Reports 0 196 | P a g e commisioning and handover Certify progress of works DLP monitoring and reporting Statement of value of works done DLP monitoring reporting 0 0 Q 3 Surveyor (Name) Conduct engineering Geo-referenced Assurveys inline with pegged survey the REA survey drawings methodology Facilitate the development of the Engineering design contractors report engineering design report Facilitate the development of the Geo-referenced Asas-built report and Built survey report the commisioning report Facilitate monthly Network inspection activities, network Commisioning final inspection and Report precommisioning activities 0 0 Foreman (Name) Oversee day to day site activities Duly signed Daily Work Log 0% 0 0 Q 4 T T 0 0% 197 | P a g e Report daily progress Day-to-day construction supervision to ensure compliance with the approved engineering design report. Q Implementation of the approved ESMP Monthly Progress reporting 5 Monthly Progress Report 0 Q 6 Social/ communications officer (Name) T Preparation of the contractors Social management plan Contractors Environmental and Social management plan Implementation of the approved ESMP Monthly Progress reporting Monthly Progress Report Average Mark 0% T 0 0% 0 0% 198 | P a g e ANNEX 39: CONTRACT ASSESSMENT TOOL (CONSULTANT) CONSULTANT ASSESSMENT GUIDLINE Stage 1: Stage 2: Stage 3: Stage 4: Assess Detailed Items based on: Quality Submission (Adequcy, Completeness, Usefulness) Timely Submission (Agreed upon timelines) Non-responsiveness 2 1 0 Obtain Section Marks in Percentage Sum up all fraction marks from detailed scores and multiply by (1/total no. of items scored) Multiply the total mark by 100% Multiply each percentage mark by it's percentage weight Grade final score as below GRADE EXCELLENT VERY GOOD GOOD SATISFACTORY FAIR POOR SCORES 80-100% 70-79% 60-69% 50-59% 40-49% 0-39% 199 | P a g e Consultant Performance Evaluation CONSULTANT PROJECT NAME: CONTRACT No.: CONTRACT VALUE: DATE: START DATE: COMPLETION DATE: A Engineering Design and Survey 20% Stage Mark 0% B Procurement 10% 0% 0% C Pit excavation, Pole erection, pole dressing, conductor stringing, tensioning and sagging 20% 0% 0% D Project progress inspection 5% 0% 0% E Preparing Variations 10% 0% 0% F Pre-commissioning and commissioning 10% 0% 0% G DLP inspection 5% 0% 0% H Project Closure 5% 0% 0% I Environmental and Social activities 15% 0% 0% EVALUATION SECTION TOTAL WEIGHT Weighted Score 0% 0% GRADING: Name: Signature: Date: Consultant: Project Manager: Manager: Director: (required for Final only) NOTE: If the contractor disagrees with this evaluation, it is to submit its objections in writing with supporting evidence within five (5) business days 200 | P a g e CONSULTANT ASSESSMENT TOOL Consultant: Project Name Assessment period ACTIVITY CONTRACTUAL DELIVERABLES Presence of project manager in Uganda (project Area) Approved updated contractor's work plan Presence of surveyor DESIGN AND SURVEY PROCUREMENT Timely evaluation and submission approved contractor's engineering design and survey report Timely Submission and review of Communication and community mobilization management plan Timely submission of Quality control plan Timely submission of Risk management plan Postshipment inspection report for transformers, CONSULTANT's ASSESSMENT ACTUAL TIMELINE COMMENTS MARK Q T Stage 1 All the time 0 Monthly 0 during the Engineering Design 0 4 months from effectiveness 0 Quartely 0 2 months from effectiveness 2 months from effectiveness Upon delivery of materials Stage 2 0% 0 0 0 201 | P a g e AAAC bare conductor , ABC conductor, Insulators, Line accessories Approved postshipment Reports by the Distribution Engineer prior to delivery and distribution to project sites Verification of pole delivery notes by Clerk of Works & distribution Engineer Review of approved Technical Specifications Aapproved FAT reports As and when material are delivered to site stores 0 Upon delivery of poles 0 1 month from effectiveness As and when after FATs 0% 0 0 IMPLEMENTATION Deployment and presence of Distribution Engineer on site Deployment and presence Pit excavation, of clerk of works Pole erection, pole Project progress report dressing, (including 3 sets of progress conductor photographs, updated stringing, approved contractor's tensioning and implementation plan, daily sagging work logs, updated risk management report, and updated progress status report per scheme, Noice of All the time 0 All the time 0 Monthly 0 0% 202 | P a g e early warning, Envionmental monitoring report, Up-dated deployment schedule) Project pogress inspection Preparing Variations Timely submission of Shutdown requests As when a scheme is complete 0 Signed Minutes of monthly site inspections and technical meetings before 15th of the the subsequent Month 0 Variation assessment report (including change order instructions) Project financial appraisal report with in 7 days of the upon receipt of request 0 Quarterly 0 Pre-commissioning report Approved As-built drawings and pole schedules Precommissioning and commissioning Final Inspection report as when a scheme completed Prior to commissioning Before commissioning Equipment commissioning reports and project appraisal At commissioning report 3 months after Project completion report commissioning Certificate of pactical After Successful completion commissioning 0% 0% 0 0 0 0 0% 0 0 203 | P a g e DLP inspection DLP report with proof of stakeholder participation Project closure report Project Closure Environmental and Social activities Final financial appraisal report Deployment and presence of sociologist on site Presence of environmentalist on site Monitoring and ensuring the contractor implementats an approved ESMP Checklist on environmental and social requirements Awareness strategy HIV/AIDs sensitization plan Labor management plan NAME Quarterly after commissioning 1 year from commissioning 3 months after commissioning 0 0% 0 0% 0 1 Week per month 0 2 Week per month 0 Part of Monthly reports 0 1 Month after effectiveness Quarterly Report Quarterly Report Quarterly Report 0% 0 0 0 0 Signature Date Consultant Project Manager MPDM 204 | P a g e ANNEX 40: CONTRACT MANAGEMENT PLAN CONTRACT MANAGEMENT PLAN FOR IMPLEMEMNTATION OF (…insert Project Name…) (insert date of submission: Month, Year) 205 | P a g e EXECUTIVE SUMMARY The Contract Management Plan (CMP) outlines the Agency’s commitment to successful implementation of the project. It details the structure and approach to be adopted during planning and execution of the (…insert Project Name...). The CMP appreciates that in order for the project to be successfully implemented, other project management aspects should be considered and appreciated during the entire cycle. Emphasis has been put on identification and management of resources needed, stakeholders involved, associated risks, mode of communication, reporting, information handling and a commitment of compliance to social and environmental safeguards, in addition to quality and timely delivery of the project. As part of the resource identification and management, the CMP identifies appropriate expertise required, respective skills, techniques and tools needed and has established a CMT structure that will be dedicated to the successful delivery of the project. The (…insert Project Name...) CMT shall be responsible for successful implementation of the project with special emphasis on stakeholder management, risk management, communication and information management and social and environmental safe guard’s compliance during contract execution. The team shall support the (…insert activities under this Project; for example: packaging, design, procurement, contracting, implementation and defects liability monitoring of the infrastructure projects). 206 | P a g e TABLE OF CONTENTS Acronyms List of Figures List of Tables 207 | P a g e 1.0 PROJECT BRIEF 1.1 Project Objectives (…insert project objectives, for example: i). The Project Development Objective is to increase access to electricity in rural areas of Uganda. ii). The Global Environmental Objective is to increase access to electricity in rural areas of Uganda and reduce greenhouse gas emissions. …) 1.2 Project Scope (…insert Project Scope. Present the scope in a tabular form; the extent to which it is possible…) 1.3 Project Schedule (…Insert Project Timelines. Clearly indicate, in tabular form, the status of all completed, on-going and pending project activities…) 2.0 RESOURCE PLANNING AND MANAGEMENT Resource planning has been undertaken benchmarking the objectives of the project and the adequate technical input to implement the project, establishing a CMT structure. The respective stages in the project cycle have been analyzed to determine adequate professional mix and tools required as enablers. 2.1 CMT Mix and Composition In order to successfully manage the (…insert Project Name…) to ensure compliance with quality, timelines and social and environmental requirements, the following expertise shall be required: (…insert table indicating all required team members and their general responsibilities. The Table showed below is for illustration purposes…) Table xxx: CMT Mix and Composition No. Team Member General Responsibility 1. Project Will play a coordination role of all the key stakeholders of the Coordinator project through the management of adequate and timely information. 208 | P a g e 2 Contract Manager Shall be responsible for ensuring implementation of all Contractual requirements 3 Project Engineer Shall assume the role of the client’s engineer, responsible for quality management during design and implementation of the project. 4 Clerk of works/ Will deputize the project engineer at site majorly tasked with Resident Engineers construction supervision and adherence to approved construction standards. 5 Social Will be responsible for monitoring compliance to social development safeguards during project development and implementation. officer 6 Wayleaves officers Will be responsible for supporting the RAP development and implementation. 7 8 Environmental Will be responsible for ensuring environmental compliance officer during project development and implementation. Community and Will coordinate all marketing and mobilization for Outreach officer connections and will work closely with the Electricity Service Providers to create demand for connections and efficient and productive use of energy. (…insert any other points to note regarding team composition for example: The project shall be managed within REA’s established departments from which, a dedicated Contract Management Team (CMT) has been structured to oversee the implementation of Project. The Service Territory Development and Operation Department shall house the execution of the last mile connections. …) 209 | P a g e 2.2 Organizational Structure of the CMT (…Insert CMT Organizational Structure. A structure is given below for illustration purposes….) Figure 1: Contract Management Team Structure Exective Director Manager Project Development & Management Project Cordinator Project Engineer/ Contract Manager Environmental Officer Community and Communications Officer Wayleaves Officer Social Development Officer Others.... Clerks of Works/ Resident Engineers Supervision Consultant Works Contractor 210 | P a g e 2.3 CMT Staffing Requirements 2.3.1 Proposed Staffing Requirements The availability of the proposed expert mix and adequate numbers of personnel is illustrated in the table below. The proposed staffing has taken into consideration the current REA portfolio (…insert Table indicating CMT Composition. The Table given below is for illustration purposes…) Table 7: (…insert Project Name…) Contract Management Team Composition Lot Scope (km) SP/ST Lot 1 Lot 2 Lot 3 250 130 160 KIL UMEME UMEME Key: Project Coordinator 1 Contract Manager 1 Project Engineer 1 Social Development Officer 1 Environmental Expert 1 Wayleaves Officers 1 Community and Outreach Officer 2 Clerks of Works 1 1 1 Already available Recruitment Process On-Going Additional Staff Required 211 | P a g e 2.4 Roles of Each Member of the Contract Management Team (…insert table clearly spelling out the roles of the CMT as illustrated below…) Member Project Coordinator Roles 1. Undertake preparation and monitoring implementation of the annual work plan 2. Liaise with the technical Departments within REA to ensure that Project activities are implemented as per the approved work plan 3. Undertake preparation of monthly project implementation progress reports to REA’s Management, (…Project Funder...) and other stakeholders as required. 4. Ensure that project implementation is supervised as required. 5. Ensure that progress and quality of construction works are properly monitored 6. Ensure that Links with the project beneficiaries are maintained and their issues are attended to in a timely manner, working with the officers responsible for public outreach and wayleaves. 7. Participate in contract negotiations when nominated 8. Oversees communication with the funder, including preparing quarterly progress reports and facilitating the mission visits 9. Prepares the loan disbursement schedule 10. Monitor the loan duration 11. Shall be the contract manager for the consultant where the loan has more than one lot and common consultant Contract Manager Project Engineer Shall effectively manage the contract in compliance with PPDA (Contracts) Regulation, 2014, Part V – Contract Management, and specifically; 1. Review and approve i. Participate in the review technical specifications for process for technical Contract all networks specification for all Manager/ materials/components prior networks to commencement of materials/components Project Engineer manufacturing. ii. Ensure that the 2. Confirm placement of orders materials/network and delivery schedules with components delivered to suppliers site and installed conform to the approved technical specifications for all networks materials/components 212 | P a g e 3. Review for completeness and recommended for approval detailed engineering design prior to commencement of works iii. iv. v. 4. Review and recommend iv. approval of subcontractor in line with contractual requirements, REA subcontracting guidelines and PPDA regulations, including due-diligence 5. Facilitate monthly site visits vi. 6. Schedule and facilitate monthly top-level progress review meeting with the project managers at REA vii. offices 7. Prepare test protocols, viii. schedule and facilitate material inspections at manufacturer’s premises and upon delivery including poles 8. Review and recommend ix. change orders, contract amendments and or instructions to avoid compensation events 9. Ensure timely execution of x. time change orders, contract amendments and issue of instructions 10. Review and certify progress xi. of works and subsequent payments timely 11. Review and approves test xii. protocols, schedule and facilitate shutdowns, Participate in the review of detailed engineering designs prior to commencement of works Ensure that approved engineering designs are compiled to during implementation Ensure adherence to good engineering practices with reference to the contract, manuals, standards and engineering memorandum Supervise subcontractors in line with contractual requirements and REA subcontracting guidelines and PPDA regulations, including due-diligence Coordinate stakeholders’ meeting during implementation of the project Ensure community participation during implementation of the project Participate in the preparation test protocols and material inspections at manufacturer’s premises and upon delivery including poles Ensure timely recommendation of change orders and contract amendments to mitigate compensation events Ensure timely execution of instructions Certify progress of works and recommend for payment Schedule power shutdowns, pre-commissioning and commissioning activities 213 | P a g e network pre-commissioning xiii. and commissioning 12. Facilitate handover of completed networks 13. Schedule and conduct periodic defects liability xiv. inspections/audits, generate snags list and follow-up correction of snags xv. 14. Schedule and facilitate final defects liability inspection with all major stakeholders xvi. 15. Ensure project cost, quality xvii. and time control 16. Assess the overall xviii. performance of the contractor & or Consultant Assess the performance of the project engineer 17. Monitor environmental and xix. social safeguards compliance Prepare for review test protocols, facilitate shutdowns and network pre-commissioning and commissioning Facilitate handover of completed networks in line with the set procedures Participate in periodic defects liability inspections/audits, generate snags list and follow-up correction of snags Participate in final defects liability inspection with all major stakeholders Develop for approval and ensure implementation of the approved quality control plan with a focus on the key implementation stages of the project Jointly participate in the assessment of the performance of the contractor and consultant Report environment, social and safety concerns to environmental and social safeguards team for action xx. Enforce recommendations from the environmental audits xxi. Prepare weekly and monthly project progress reports Prepare technical project closure report 18. Ensure timely submission and filling of progress reports, programs and key contractual deliverables 19. Prepare comprehensive project closure report 1. Review the contractor’s Social Management Plans for compliance with the project’s objectives and ensures its implementation. 2. Supervising and coordinating all social related activities of the project, including the supervision of the contractor and the consultant’s social activities 3. Coordinating social impact assessment and management during the preparation, implementation and monitoring of participatory Resettlement Action Plans (RAPs) and carry out post RAP 214 | P a g e 4. Social 5. Development Officer 6. 7. 8. 9. 1. 2. Environmental Officer 3. implementation and a social audit to ensure that all the social impacts are addressed in accordance with the social safeguard instruments in place Spearheading sensitization and information dissemination on the project’s objectives within the project areas and develop and implement appropriate strategies to enhance community participation during project design and implementation Coordinating closely with the REA Way Leaves Officer, the Environmental Specialist and Community Outreach Unit to ensure that the RAPs and EIA processes capture all the relevant social aspects Providing guidelines on relevant social mitigation measures, including measures pertaining to way leaves acquisition and resettlement, protection of cultural resources, community & worker health and safety, child labor, forced labor, HIV/AIDS, and other issues where relevant, which should be considered during preparation of bidding documents for rural electrification projects Identifying potential sources of grievances, design and implement appropriate grievance redress mechanisms for the project to ensure effective and timely resolution of any complaints or grievances raised by stakeholders Supporting stakeholders including district and community members in identification, prioritization and mitigation of social, equity and gender issues during the project design and implementation, as well as monitoring and evaluation of social impacts of the projects Ensuring relevant government agencies, including Ministry of Finance, the Chief Government Valuer and partner agencies are well informed on issues related to the implementation of RAPs and required support for timely implementation Ensuring and monitoring compliance of the project activities with ESMP, ESMF, safeguards requirements, and the national environmental policy and legal requirements during construction of subprojects Reviewing Environmental and Social Impact Assessments, Environmental and Social Management Plans and Resettlement Action Plans (RAPs) of Rural Electrification projects and ensure that social issues are comprehensively addressed. Ensuring that the findings of Environmental and Social Impact Assessments (ESIAs) and RAPs including public consultation input of affected communities and their disaggregation in terms of gender, different levels of social vulnerability to project risks and impacts, as well as equitable access to project opportunities and benefits, are incorporated into project design and implementation strategies by providing technical input to requisite Environmental and Social Management Plans (ESMPs) and RAPs of Rural Electrification projects 215 | P a g e Wayleaves Officers Community and Outreach Officer 1. Negotiate Wayleaves for overhead electricity power lines and underground cables with landowners/occupiers and their agents/legal representatives 2. Sensitise the public about need for Wayleaves 3. Serve power line construction notices and obtain consents for each project in a timely manner 4. Compile accurate records of landowners and occupiers for each project 5. Provide wayleaves support for RAP studies and selection of new electricity power line routes 6. Secure access arrangements from landowners and occupiers for overhead/underground line construction work 7. Investigate and assess wayleaves compensation claims by landowners/occupiers for any losses or damage caused and negotiate settlement. 8. Act as liaison point between the landowner/occupier, contractor and project manager with regard to wayleaves issues 9. Attend Grievance Committee meetings and resolve disputes over Wayleave rights during project implementation 1. To market and mobilise for connections. 2. To promote the productive use of energy 3. To promote energy efficiency 1. Participate and ensure that the proposed line routes are complied with during implementation 2. Ensure that only the approved line materials are used during installation 3. Ensure materials are installed according to the approved construction methodology Clerks of Works 4. Verification of quantifies of materials received on site and used on the project by signing on the site delivery notes 5. Ensure proper handling and storage materials on site by the contractor 6. Submit the daily log sheets reports indicating the day’s work, weather conditions, compliance to safety, social and environmental requirements 2.5 CMT Skills Enhancement and Tools The CMT shall require the following to effectively perform the task assigned 2.5.1 Skills and Knowledge Enhancement 216 | P a g e (…insert any skills requirement the CMT should have…) Table 8: Skills and Knowledge Enhancement for CMT Activity Technical Orientation Skills Refresher Training Facilitator Who to Attend REA/HR/PDM/STDO Entire CMT Experts in Procurement, Project Entire CMT Management, Social & Environmental Safeguards, Power Distribution Systems 2.5.2 Tools (…insert a list of tools the CMT shall require to successfully deliver the project…) Table 9: Tools for CMT No. 1 2 3 4 Item Minimum Total No. Requirement Required 3 Double 1 Double 4 Cabin Pick- cabin pick-up Ups &1 per Project Station Engineer Wagon 5 Single Cabin 1 per Clerks of 5 Pick-Ups Works Laptops 1 per new 10 member of the CMT (excluding Clerks of Works) PPE (Safety 1 set per new 15 shoes, helmet, member gloves, overcoat) Availability Action Required 3 (…Funder…) to facilitate acquisition 0 (…Funder…) to facilitate acquisition (…Funder…) to facilitate acquisition 0 0 (…Funder…) to facilitate acquisition 2.6 CMT Responsibilities The CMT shall be specifically responsible for the successful execution of the project. They will support the design of the project ensuring timely and quality submission of documents, reports, studies and consultations. The team will be charged with first trucking and management of procurement planning, contracting and control. In addition, the team will be responsible for ensuring quality and timely deliverance of the project. 217 | P a g e Specifically, the CMT shall be responsible for the following:a) Monitor compliance to the plans to ensure zero negative variance b) Review technical documents for quality, adequacy and acceptance c) Support contracting through development of adequate and quality TOR’s, Statement of requirements, EOI’s and RFP’s d) Facilitate and support internal procurement clearances e) Support procurement planning, contracting and control f) Ensure contract effectiveness, schedule site handovers g) Review and approval of the contractor’s engineering design h) Supervise and manage consultancy services i) Monitor project implementation to ensure compliance with quality, timelines, scope and budget j) Monitor compliance with social and environmental safeguards k) Ensure stakeholder participation l) Review and maintain a risk management plan m) Manage change during construction n) Manage project information, communication and reporting o) Support commissioning and handover of the project p) Support connections of targeted population q) Undertake DLP monitoring 2.7 Modulus Operandi 2.7.1 Project Design and Procurement Management The CMT shall be responsible for supporting the design of the project. Specifically, the team shall ensure that the project is designed in recognition and compliance to the minimum technical standards, social and environmental safeguard requirements and full participation of key stakeholders. The team shall ensure harmonization of the engineering design process with the RAP studies, ensuring that all project RAPs are updated as per the final engineering designs. They will work with the design consultants to review submissions for quality check, compliance and inclusivity of all project aspects. The responsibility of quality management of documentation and information management shall sit with advisor, coordinator and the technical team. The engineer shall ensure designs are updated and 218 | P a g e compliant to the internationally accepted standards while the social safeguard team shall ensure compliance to Bank safeguard requirements and national policies, laws and guidelines. Key deliverables shall be an acceptable engineering design report, updated RAP report. Upon the clearance of the RAP report, the CMT shall facilitate the implementation of the RAP report for each line. Together with the internal stakeholders including the Finance Department and REA management, the CMT shall facilitate the compensation of PAP’s in a timely manner. The wayleaves officers shall be responsible for the implementation of the RAP and shall at all times maintain an updated database of PAPs. Reports shall be prepared on the status of compensation or acquisition of wayleaves and this shall aid the effectiveness of the contracts. The social development officer together with the community affairs team shall develop a grievance redress mechanism specific to each project. A complaints register shall be maintained at all times and shall be cascaded to the grass root structures of the project. The Community affairs team will initiate information flow, community sensitization and publicity of the project at this stage in order to achieve community participation in reediness for connections. Procurement planning shall be emphasized and procurement control implemented. The risk management plan herein shall guide the management of the procurement process and REA management shall be responsible for delivering the project timelines. The CMT shall support the contracting process through the review and preparation of statements of requirements, terms of references for project related services, preparation of requests for proposals and facilitating the evaluation process. At all stages, the CTM shall ensure adherence to the procurement plan. Emphasis shall be put on informal and formal communication amongst the key stakeholders, creation and maintaining of strategies linkages with key stakeholders, timely and complete reporting. 219 | P a g e 2.7.2 Construction Management The management of the project shall be handled at two levels, supervision and monitoring. Project Supervision Day to day supervision of the construction works shall be managed by the Assistant Project Engineers and the Community Affairs Assistants who will be resident at the project sites. The Assistant Project Engineers and the Community Affairs Assistants shall manage the day to day activities at the site including the receipt of project materials, confirmation of compliance to contractual standards, designs. The Assistant Project Engineers shall report daily to the Project Coordinator on the day’s progress and the report shall include accountability of the key stakeholders’ involvement in the day’s works, progress achieved, accidents recorded, materials received, assessment of quality of materials and the workmanship standards. The Assistant Project Engineers and the Community Affairs Assistants shall inform the monthly monitoring activities by identifying and recording key challenges, requests from communities for additional coverage in terms of scope and other issues that require engineer’s approval. In a bid to ensure compliance to the approved construction methodology, they will recommend for approval by the Engineer all stages of the construction. Project Monitoring Monitoring of the project shall be executed at the senior management level of the CMT. The Project Coordinator, Social Development Officer and the Environmental Officer shall be responsible for execution of contract performance monitoring. The team basing on the daily information flow from the Assistant Project Engineers and the Community Affairs Assistants shall track the progress of the project against set timelines and deliverables and flag variance from the agreed position. They shall ensure that the contractor with guidance of the consultants prepare the engineering design report, a community engagement plan and the environmental and social management plans. Upon approval of the plans, the CMT shall monitor compliance to the set standards, practices and schedules as stipulated in the plans. 220 | P a g e This CMT shall conduct monthly monitoring activities that will involve visiting the sites and conducting site meetings. They will ensure key stakeholder participation during the meetings and handle project arising matters. The team shall also review quality of workmanship and assess the performance of the Assistant Project Engineers and the Community Affairs Assistants and the contractor and consultants’ site management team. This team shall prepare monthly comprehensive reports comprising technical progress and safeguards management and shall be accountable for the overall project management. This team shall also coordinate the pre-commissioning testing of the networks and eventual commissioning and handover. 221 | P a g e Consumer Connections As part of the design preparation, the contractor’s designs shall include details of the targeted last mile connections within a no-pole service range. The Connections Unit will access the information on last mile connections as per the contractor’s designs and liaise with the Electricity Service Providers to commence community mobilization, conduct aggressive marketing for the product to bridge the gap between the consumer and the service provider. Upon commissioning of the network, the Service Territory Department together with the Electricity Service Providers shall conduct aggressive connection drives targeting the identified potential consumers. The CMT shall work closely with the Service Territory Department and Electricity Service Providers to profile potential consumers during the construction phase and facilitate initiatives to accelerate the readiness for connection. Supply of the connection materials to the Electricity Service Providers shall be done in time to ensure timely implementation of connections upon completion of construction. The CMT shall periodically review and assess the performance of the contractor and the consultant. An assessment tool shall be developed jointly with the key stakeholders and the same shall be used to determine the level of performance and compliance to contractual requirements. Results from the performance assessment shall be communicated to all stakeholders. 2.8 CMT Reporting Structure Reports shall be prepared on a Daily, Monthly, Quarterly, Annually and at end of major milestones by responsible persons at different stages for the target stake holders Table 10: Reporting Requirements per CMT Member Responsible Type Person Reports Assistant Daily Project Logs Engineers Community and of Brief Description of Frequency of To Whom Content Submission Work Project area, day’s work, Daily, Adhoc, Project work duration, weather Monthly Coordinator conditions, deployment of field teams for contractor 222 | P a g e Affairs & consultant, instructions Assistants issued by the engineer, environmental & social aspects handled and challenges encountered. Approvals issued, stakeholder engagement activities, environmental & social safeguard compliance levels, finding from site inspection & meetings, payment status, update on implementation plan, assessment of contractor & consultant, risk identification, movement & mitigation measures, recommendations Social Progress, Aspects on project social Monthly, Ad- MPDM Development Monitoring safeguards Environmental Progress, Aspects Officer Monitoring environmental safeguards hoc Community Activity Activities on community As per activity, Principal Affairs Reports engagement hoc Officer Assistants on project Monthly, Ad- MPDM and Monthly, Ad- Connections sensitization in relation to hoc Officer productive use of energy, awareness, mobilization, connections HIV/AIDS, etc. 223 | P a g e Wayleaves Activity Wayleaves Officers Reports activities acquisition As per activity, Senior in respective Monthly, Ad- Wayleaves project areas hoc Procurement Procurement Progress on processing Monthly, Specialist Progress various Reports, constraints met and any hoc Financial other issues that require Monitoring Management attention Officer HPDU contracts, Quarterly, Ad- Reports Project Quarterly, Financial status of the Quarterly, bi- Manager Accountant bi-annual project which report., final include, accounts cash payment could annual report., Finance and balances, end of year Administration status of report (MF&A) suppliers , reconciliation of accounts AfDB Project Status Coordinator Reports Progress on project Quarterly, Ad- MPDM components hoc 3.0 STAKEHOLDER ENGAGEMENT AND COMMUNICATION PLAN 3.1 Internal Stakeholder Table 11: Internal Stakeholders Identification and Engagement Stakeholder REA Board REA Management REA Internal Audit Finance and Administration Project Development & Management Service Territory Development & Operations Mode of Communication Reports Reports Reports Frequency Quarterly Monthly Monthly Reports Reports Monthly Monthly Reports Monthly Responsible Persons ED MPDM, MSTDO Coordinator Coordinator Coordinator, SPEs Coordinator, SPEIntensification, Marketing and Mobilisation Specialists 224 | P a g e Off-grid & Development Renewable Procurement & Disposal Unit Legal & Board Services 3.2 Energy Reports Monthly SPEs Reports Monthly Reports Monthly Procurement Specialist Wayleave Officers External Stakeholder Table 12: External Stakeholders Identification and Engagement Mode of Responsible Category of Frequency of engagement and Persons Stakeholder Communication communication Meetings, PAD, CMT, Partnership (…Funder…) Financiers Quarterly/Annual Activities, Reports, ly/ad hoc Emails, Website Coordinator Daily, Weekly, Reports, Social SPEs Construction Monthly, Media, Meetings, Supervision Consultant Quarterly, Workshops Consultants Completion Reports, Meetings, Workshops (Joint Mother Quarterly, sector reviews), MEMD Ministry Annually Partnership activities (energy Coordinator efficiency weeks) Environmenta Reports, Meetings Environmental Quarterly, Yearly, NEMA l Compliance Experts Ad hoc Regulator Daily, Weekly, Reports, Social SPEs Monthly, Media, Meetings, Contractors Contractors Quarterly, Workshops Completion Reports, Meetings, Borrower, Quarterly, MoFPED Workshops (Joint Monitoring Annually sector reviews). Coordinator Meeting, Door-toPrimary Door Visits, Radio Marketing and Communities Project Monthly, Ad hoc Talk Shows, Road Mobilisation Beneficiaries Shows, Specialists Exhibitions. Meetings, Network Monthly, Ad hoc, Concessionaires Workshop, Media, MSTDO operators Completion Emails, Websites Stakeholder 225 | P a g e Mode of Category of Frequency of Stakeholder engagement and Stakeholder Communication communication Meetings, Beneficiary, Local Workshops, Email, Liaison Quarterly, Ad hoc Governments Media Contacts Engagement Ministry of Partnership Gender, Labor & Regulator of events, Quarterly, Ad Hoc Social Social Aspects workshops, email, Development Reports, meetings, workshops, email, Oversight, media Parliament Quarterly, Ad hoc Monitoring engagement, site handovers and commissioning Face to face, Security, law meetings, site Police Ad hoc Enforcement handovers and commissioning Workshops, press conferences, press releases, radio/TV announcements and talk shows, Media Publicity Ad hoc covering events, print media articles and supplements, adverts Reports, meetings, workshops, email, Opinion media Local Leaders Ad hoc leaders engagement, site handovers and commissioning Face to face Civil Society Social issues Ad hoc Organization Chief Government Valuer NFA UWA Way leaves/ Ad hoc right of way Way leaves/right of Ad hoc way Way leaves/right of Ad hoc way Responsible Persons Social Development Officer Social Development Officer ED Community Affairs Assistants Marketing and Mobilisation Specialists Social Development Officer Social Development Officer Face to face, Wayleaves Reports, meetings, Officer emails Face to face, Environmental Reports, meetings, Officer emails Face to face, Environmental Reports, meetings, Officer emails 226 | P a g e Stakeholder UNRA URA PPDA ERA Solicitor General UETCL 3.2 Mode of Category of Frequency of engagement and Stakeholder Communication communication Way Face to face, leaves/right of Ad hoc Reports, meetings, way emails Face to face, Tax clearance Ad hoc Reports, meetings, emails Face to face, Procurement Monthly, Ad hoc Reports, meetings, Compliance emails Face to face, Regulatory Ad hoc Reports, meetings, Compliance emails Face to face, Contracts Reports, meetings, Ad hoc approvals emails Transmission of power Monthly, Ad hoc Responsible Persons Wayleaves Officer SPEs Procurement Officer Coordinator Manager Legal and Board Services Face to face, Reports, meetings, SPEs emails Claims and Dispute Management Plan The CMT shall make every effort to address any claim or dispute that may arise and endeavor to mitigate and resolve the problem. In the event of a claim or dispute, subject to the Conditions of the Contract. 227 | P a g e 4.0 RISK MANAGEMENT PLAN The objective of risk analysis in the context of this CMP is to identify, quantify, and mitigate factors that have the potential for compromising quality, driving up project costs and/or delay the project or its milestones. The main benefits of risk assessment include confidence in scope control, cost control, schedule and improved quality. (…insert Risk Management Matrix in the format used in the table below…) Table 13: Project Management Risk Analysis Matrix KEY Low Moderat e High No. 1 3 Activity RAP Preparat ion Likelihood Occur 1 to 2 3 Associated Risk Low or no participation of the community 1 Risk Rating 1-2 2 3 3-5 6-9 Impact Likelihood of Impact occurrence Risk Rating 1 3 3 Responsible party ii) Involvement of district and civic leadership to Senior Social mobilize and organize community meetings, Development use of alternative media and engagement Officer channels like schools, radio, churches/mosques and market days among others to engage communities. Mitigation Measures3 Delays caused as a result of negligence of the responsible officers shall be brought to the attention of the Accounting Officer to take appropriate punitive action. 228 | P a g e I the undersigned affirms that I have fully understood my obligations and responsibilities under the Contract Management Plan and do hereby append my signature in confirmation of the same. Signature: Designation: Date: I the undersigned affirms that I have fully understood my obligations and responsibilities under the Contract Management Plan and do hereby append my signature in confirmation of the same. Signature: Designation: Date: I the undersigned affirms that I have fully understood my obligations and responsibilities under the Contract Management Plan and do hereby append my signature in confirmation of the same. Signature: Designation: Date: I the undersigned affirms that I have fully understood my obligations and responsibilities under the Contract Management Plan and do hereby append my signature in confirmation of the same. Signature: Designation: Date: 229 | P a g e ANNEX 41: PROJECT CHARTER PROJECT CHARTER (this document shall be a living document throughout the project cycle to cater for the Different mile-stones sign-off dates) 1. General Project Information Project Name: Procurement Ref. No.: Employer: Consultant: Contractor: Sub-Contractor: District/Scheme: Impact of project: 2. Project Team (fill-in the project contact persons; add more fields as per requirement) Name Department Telephone E-mail Employer Project Manager Field Supervisor 1 Field Supervisor 2 Consultant Project Manager: Field Supervisor 1 Field Supervisor 2 Contractor Project Manager: Field Supervisor 1 Field Supervisor 2 Sub-Contractor Project Coordinator: Foreman Field Supervisor 3. Stakeholders (e.g., those with a significant interest in or who will be significantly affected by this project) Funder Employer Consultant Contractor Distributor (eg Umeme, UEDCL) Sub-Contractor 230 | P a g e 4. Project Scope Statement Project Purpose / Business Justification Describe the business need this project addresses (Shall be filled by Employer) Objectives (in business terms) Describe the measurable outcomes of the project, Deliverables Scope List what the project will and will not address (e.g., this project addresses units that report into the Office of Executive Vice President. Units that report into the Provosts Office are not included) Responsibility Matrix List the different role and responsibilities Employer (REA): 1. Assist contractor to obtain its subcontractor 2. Ensure that all contracts (Contractor – Subcontractor) are in place before project kick-off. 3. Ensure project key personnel are approved in accordance with required qualifications and experience for both the Contractor and Consultant prior to project kick-off 4. Approve C-ESMP 5. Provide general guidance on implementation of ESMP 6. Provide support in acquisition of licenses and permits 7. Monitor Contractor’s compliance with safeguard measures and attendant protocols and procedures 8. Provide support in implementation of CSR 9. Provide guidance and support on grievance redress, project awareness and community engagement 10. Approve line design, routine profiling and survey drawings of the contractor. 11. Highlight main issues of safety and Environmental concern in the project. 12. Avail material supply schedule for the project from the contractor to sub-contractor. 13. REA should monitor the material supply schedule and take punitive measures 14. REA has to handle arbitration issues between contractor, consultant and sub-contractor 15. Overall supervision on project 16. REA shall seek payment plans of the contractor to the subcontractor on a particular project 17. REA has to ensure that quality of work conforms to regulations. 18. REA should ensure that works are completed within the scheduled time. 19. REA should supervise the testing and commissioning of the completed project and should provide certificate of completion in that respect. 231 | P a g e Consultant: 1. Prepare and submit to REA a detailed project implementation schedule for each Lot and ensure adherence to the same. 2. Supervise the implementation of contracts for the project and establish a Project Site Organisation and ensure compliance of all project deliverables. 3. Provide assistance for the administration of the project in consultation with REA (Contracts Administration) 4. Monitor and Supervise the implementation of the Occupational Health and Safety Management Plan (OHSMP) proposed by the contractors. 5. Ensure and monitor compliance of project activities with Environmental and Social Management Plans (ESMP), ESMF and other safeguard requirements, national environmental policy, legal and regulatory requirements 6. Review Contractor’s ESMP for compliance with the projects’s objectivies and ensure its implementation 7. Monitor Contractor’s social activities including gender, labour, health and safety aspects 8. Ensure implementation of community sensitization strategies geared towards accelarated consumer connections and productive useds of electricity. 9. Confirm availability of key personnel in line with required qualifications and exeperiencePrepare and submit to REA a detailed social and environmental project implementation schedule 10. Ensure contractor fully implements all relevant mitigation measures and procedures specified in the ESMP 11. Monitor compliance by contractors during construction and commissioning for applicable legal requirements of Uganda. 12. Prepare and submit the Project Completion Report that outlines, inter-alia, achievements in meeting the objectives and target set out for the Implementing/Executing Agency. 232 | P a g e Contractor: 1. Develop site drawing 2. Carry out mapping survey and route profiling 3. Develop and implement approved project specific ESMP and attendance work related protocols and procedures in line with statutory requirements in force in Uganda, regulatory conditions specified in the Environmental Impact Assessment approval certificate and the funder’s requirements. 4. Ensure total compliance with contractual obligations 5. Ensure all prerequisite approvals, permits, licenses and consent forms are obtained prior to commencement of works. 6. Sourcing of sub-contractors and negotiations 7. Develop and operationalize a project implementation schedule 8. A meeting between sub-contractors and contractors 9. A site re-surveying of selected sub-contractors 10. Contract signing between contractor and sub-contractors 11. Avail Approved design and drawings to the sub-contractor and scope of work 12. Develop a work schedule and also share it with the sub-contractor 13. Submission of notices to relevant authorities. 14. Develop and operationalize a project specific GRM 15. Issue quality material to sub-contractors in time 16. Contractor must ensure that sub-contractor workers comply with safety standards required. 17. Contractor should ensure that the line design being constructed conform to standard and regulations described in the drawing 18. Contractor should ensure that there is continuous flow of supply of materials on project under construction 19. Contractor should ensure that security/ yard provided by the sub-contractor is adequate i.e. safe enough. 20. Develop and operationalize a Community Engagement Plan 21. Develop and implement a Stakeholder Engagement Plan and Communication Plan 22. Contractor should fulfill payment plan schedule after receiving certificate of completion from the sub-contractor as per contract. 23. Contractor should monitor works progress on weekly basis to avoid material wastage and minimize errors. 24. Where works require specialized machinery and specialized man power contractor should provide it. 25. Should provide transportation of materials to sub-contractors yard/ office 26. Contractor should transport/ carter for transport of poles to sub-contractors’ yard 27. Contractor should clear/ sort out ambiguities on ground/ site amongst sub-contractor, community and drawing and advise on way forward. 28. Contractor should ensure that all snags are cleared before testing Commissioning of the line. 29. Material reconciliation should be carried out between sub-contractor and contractor before submission of the final certificate. 30. Contractor should be in charge in DLP 31. The contractor shall provide certificate of completion of works upon commissioning of the line. 32. Contractor shall Ensure the line for DLP period against vandalism 33. Ensure timely submission of monthly progress reports 233 | P a g e Sub-contractor: 1. Sub-contractor should carry out site inspection along with a contractor on drawings 2. Inspect site before signing the contract 3. Establish site office. 4. Sensitization of community in conjunction with employer and contractor. 5. Mobilization of worker’s and tools and their compensation to site 6. Provide welfare of workers 7. Food 8. Accommodation, PPE, Healthy facility 9. Refer/escalate way leaves issues to contractor 10. In agreed terms, transport materials from contractor main store to sub contractor store with exception of Poles and transformer. 11. Execution of works as per drawing/ contract terms. 12. Sub-contractor to do line clearance responsibly in accordance with the regulation, where issues arise, it is in contractors to address such issues ASAP 13. Sub-contractor has to be in charge of his workers and if contractor seeks assistance from workers of subcontractor, the contractor should communicate to the management of sub-contractor 14. When special equipment/tools are required, the contractor should be in position to provide it after discussion/ negotiation with sub-contractor. 15. Subcontractor shall manage disciplines of his workers with exception of criminality, robbery etc which are police management issues. 16. It is the responsibility of the subcontractor to pay his workers and negotiate with them their payment terms. Where strike erupts, as a result of non-payment/ delayed payment of workers, contractor, employer and sub-contractor management should join efforts to calm the situation at a particular project. 17. Daily working hours of workers should be 8(eight) hours not exceeding 8pm 18. Sub-contractor shall carry out daily safety/ tool box talks before work commences. 19. Sub- contractor shall advise on contractor on ground of changes required with in the line (project) at time of execution. 20. Sub- contractor shall advise on contractor on ground of changes required with in the line (project) at time of execution. 21. Sub-contractor shall produce weekly reports to contractor stipulating works effected 22. Sub-contractor shall clear snags before handling in the line to contractor 23. In cases of disagreement, arbitration shall be headed by a team of not less three (3) REA (employer) officials, and members of consultants 24. Sub-contractor shall carryout preliminary test and data capture before handing in the project (precommissioning) to contractor 25. Extortion of money from community for power connection from community on a project is a crime, forwarded to police for handling, 26. Sub-contractor shall request in writing a certificate of completion of works for the project assigned from the contractor. 234 | P a g e LC/Community Leaderhip 1. The leadership in communities shall mobilise the communities to: 2. Provide conducive environment for execution of the project 3. Community should be sensitized on the proceedings and benefits of the projects 4. Community should be willing to avail land for the project 5. Community should give history of the area/ norms and practices. 6. Community should direct you to the leaders and willing to listen to them 7. Community should share sanitation facilities with workers for the period. 8. Community should provide rentable accommodation to sub contractor 9. Community should understand the progress, and be involved in project implementation process. 10. Community should be willing to allow for line clearance 11. Community should be sensitized about extraction of money by sub contractor workers. 12. The Community leadership shall also ensure: 13. Shall give direction to community as to benefit of the project 14. Guide the survey and mapping teams in the area. 15. Notify security personnel on the presence of project implementation 16. Take part in this sensitization of the community 17. Shall be first arbitrators on issues where line clearance arises 18. Leaders should emphasize that project belongs to community so they should take security 19. Leaders shall identify chaotic individuals and front them to sub-contractor and even identify those who can work on this project Project Milestones Milestone Line Route Inspection (shall be a fact Finding mission eg Topology) Contract Hand shake (documents like Contract, approved pricing, approved design and drawing shall be availed to the Subcontractor by the contractor prior or at signing) Kick-off Stakeholder meeting Field office set-up (mobilisation) Pole Erection Stringing Responsible Contractor Sub-Contractor Consultant Sign Date Contractor Sub-Contractor Employer Consultant Contractor Sub-Contractor Regional Police Contractor Sub-Contractor Contractor Sub-Contractor Contractor Sub-Contractor 235 | P a g e Transfomer Installation Contractor Sub-Contractor Inspection, Testing and Snag Clearance Contractor Sub-Contractor Pre-Commissioning Employer Consultant Contractor Sub-Contractor Project Assessment Meeting Employer Consultant Contractor Sub-Contractor Distributor (eg Umeme, UEDCL) Hand-over (hand-over shall be done from Consultant Subcontractor to Contractor if all Contractor installation requirements are fully satisfied Sub-Contractor and a Completion certification shall be issued to the Subcontractor) Commissioning (shall be done be between Employer contractor, Employer, Consultant and the Consultant power distribution company) Contractor Distributor (eg Umeme, UEDCL) Major Known Risks (including significant Assumptions) Identified on project basis by Contractor and subcontractor Risk Risk Rating (Hi, Med, Lo) Constraints List any conditions that may limit the project team’s options with respect to resources, personnel, or schedule (e.g., predetermined budget or project end date, limit on number of staff that may be assigned to the project). External Dependencies Will project success depend on coordination of efforts between the project team and one or more other individuals or groups? Has everyone involved agreed to this interaction? Way leaves Financing options 5. Communication Strategy (specify how the project managers/members will communicate to the Project Team members and Stakeholders, e.g., frequency of status reports, frequency of Project Team meetings, etc.) 236 | P a g e Communication shall be done by use of: 1. weekly reports 2. Memos 3. Using email, phone calls, text messages or face to face Meetings shall be held between stake holders 6. Sign-off Employer Name Signature Date (MM/DD/ YYYY) Subcontractor Contractor Consultant Employer 7. Notes 237 | P a g e ANNEX 42: DESIGN AND CONSTRUCTION TEMPLATE A. Tool District Name Characteristics of Existing System of Scheme Primary Name of State of feeder Substation Feeder start to Location of S/S, Name of Feeder loading, end distance from Feeder, conductor size, S/S, Capacity of voltage network Power level configuration/ tranformer, construction protection type, status of grading, current support loading of S/S structures MV Scope Line route length (km) Tee-Off Characteristics Line Tee-off Local Descripti on. Vilage or town Proposed Voltage Proposed Bulk Interconection Protection Metering Type of calculated type of Justification interconnection, at takeprotection, and ratings rating off point justification, ratings Tool (cont’d) Economic activity principle economic activity of project area. E.g cattle corridor Load Classification Load Assessment Study Calculate Future % Load Present/ developments growth Actual Load forecast p.a Domestic Commercial SME/ Industrial number of existing loads load clasification multiplied by average consumption per category information sourced from community leaders Estimated Peak Demand (Demand factor) growth rate, calculated considerations plus and forecast assumptions Electrical Characteristics Optimal Calculated line Voltage current drop calculated, based on peak demand and voltage profile Load flow results at terminal 238 | P a g e Tool (cont’d) Transformer Assessment MV Conductor Proposed MV line characteristics Assessment Proposed Protection Calculated Proposed Terain configutration Protection Protection Future Transformer conductor Conductor Extension size size Type of Primary Secondary calculated Type, size Predominant Type of equipment line Assess the transformer, based on and nature e.g construction and line protection posibility of capacity loading justification Hilly, and termianl scheme. future line type and rating of type and swampy, etc justification structure Earthing or extension fuse links, surge rating of protection surgearestors for both arersters and the MCB backborne arching hornes and tee-off Tool (cont’d) LV Reticulation Network Tranformer Location Line Route Lengh (km) physical location of tranformer Single phase Three phase Environmental and social Wayleaves Risks Aspects Circuits Protection Key Key Social Consent from Major Environmental characteristics local anticipated Characteristics communities. Risks Number Type and Aim to of rating of achieve outgoing MCB documented e.g forests, e.g culture, circuits free right of water crosings gender way Unique features Any other significant feature observed e.g transmision line crosing, SGR crosing), Other generation sources 239 | P a g e B. Transformer Sizing Template S.no. 1 (…insert name of Loading Center…) Beneficiary Categories No. of Total beneficiaries power in TC (W) RATE (W) (After Demand Accounting Factor for Demand factor) Domestic 6 500 0.6 300 1800 Commercial 8 800 0.8 640 5120 School 0 1500 0.6 900 0 Church Milling Machine Coffee Factory 0 800 0.6 480 0 0 10000 0.8 8000 0 0 60000 0.8 48000 0 Health Center 0 1500 0.8 1200 0 Total load after applying Demand factor Without Diversity factor Growth Factor power factor Calculated kVA 1.2 0.9 9226.67 Total load after applying Demand factor 6920 Load in KW Rq. Xmer capacity is 25KVA 9.23 240 | P a g e