Uploaded by chengmaninang25

NPCP CHAPTER 1

advertisement
ADMINISTRATION
SECTION 100
PERMIT
- Required
RMP - Registered and Licensed Master Plumber
R.A. 1378 - Plumbing Code
Jurisdiction
DPWH
DILG
DENR
DOH
City Mayors
Officers of the Building Official
SECTION 101
TO WHOM PERMITS MAY BE ISSUED
- RMP
holding a valid, unexpired and unrevoked cetificate
SECTION 102
- Application
APPLICATION OF PERMIT
RMP
Building Owner
a. Plumbing Work
b.Land - Land registration and street address
c. Use or Occupancy
d.Datas
Plans
Computation
Drawings
Technical Specs
e. Others
f. Signed of Owner or Permittee
g. Signed and sealed by RMP - Plan and specs
Diagrams
6 sets
SECTION 103
PERMIT ISSUANCE
- Approved by Administrative authority
- Retention of Plans
1 sets
Admin
2
Applicant or owner
1
Jobsite
- Validity of permit
- Expiration
1 year or 365 days - if plumbing work has not yet started
from the day it was issued
4 months or 120 days - if it is not started
from the day it was suspended
- Fees for Renewal
50% of the original fees
SECTION 104
APPLICATION FOR EXISTING PLUMBING SYSTEM
- Addition, Alteration or Repairs
- Changes ing Building occupancy
- Maintenance
All Plumbing system
Materials
Appurtenances
Existing of New
- Moved Buildings
SECTION 105
- General
INSPECTIONS
Admistrative Plumbing personel
Plumbing Inspector
- Operation of Plumbing Equipment
request of inspection shoud be atleast
72 hours or 3 days before
- Re inspection
Fee is required
No payment, no reinspection
Download