Uploaded by Jay Mar isorena

MS for AIR BLOWER AND FIRE PUMP ROOM-5-5-22

advertisement
A
May 13, 2022
Rev
Date
For Review
JTI
PBS
ZSD
DESCRIPTION
MADE
CHECKED
APPR’D
Client
Katipunan Road, Balara, Quezon City, Philippines
Project
DESIGN AND BUILD OF HINULUGANG TAKTAK
SEWAGE TREATMENT PLANT (STP)
Taktak Road, Antipolo City, Rizal
Contractor
FREY-FIL and Toshiba Water Solutions (In Consortium)
Engineer
Method Statement:
Key Plan
CONSTRUCTION OF AIR
BLOWER BLDG. AND FIRE
FIGHTING BLDG.
Project
Document
Code
Type
HTSTP
MS
Discipline Code
Document Nº
Rev
PM
00017
A
Contents
1.
PURPOSE ...................................................................................... 2
2.
SCOPE ........................................................................................... 2
3.
GENERAL REQUIREMENT............................................................... 3
3.1.
MATERIALS ................................................................................... 3
3.2.
EQUIPMENTS AND TOOLS ............................................................. 3
3.3.
MANPOWER .................................................................................. 4
4.
INSPECTION AND TESTING ........................................................... 4
5.
METHOD OF CONSTRUCTION ........................................................ 4
5.1.
INITIAL SURVEY ........................................................................... 4
5.2.
SETTING OUT ................................................................................ 4
5.3.
CONSTRUCTION OF COLUMN, BEAM, AND SLAB ............................ 4
5.3.1
COLUMN CONSTRUCTION.............................................................. 5
5.3.2
CONSTRUCTION OF BEAMS AND SLAB .......................................... 6
5.4.
CONSTRUCTION OF WALLS USING POLYWALL SYSTEM ................ 7
6.0
SAFETY REQUIREMENT ................................................................. 8
6.1
SAFE WORK PRACTICES ................................................................ 8
6.2
COVID-19 GUIDANCE, PRECAUTION AND MITIGATION ................ 9
6.3
HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL
(HIRAC) 10
6.4
PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENT ........ 11
7.0
INSPECTION AND TEST PLAN ..................................................... 12
8.0
APPLICABLE INSPECTION CHECKLIST ........................................ 13
9.0
APPROVED PLANS ....................................................................... 14
10.0
POLYWALL EPS PANEL ................................................................ 15
Page | 1
1.
PURPOSE
The purpose of this Method Statement is to provide information about construction
method to be employ on the Construction of Air Blower Building and Fire Fighting
Building. The foregoing procedures and methods are formulated to attain the
scheduled program of the project within the prescribed contract time.
2.
SCOPE
This Method Statement applies to all works such as excavation including ground
preparation, setting out, backfilling and compaction, concreting works, and other
related to the construction of Air Blower Building and Fire Fighting Building as per
project requirements and referring with the approved Specification and Drawing.
AIR
AND
BLOWER BUILDING
FIRE
FIGHTING
BUILDING
Fig. 1.0 SITE DEVELOPMENT
Page | 2
3.
GENERAL REQUIREMENT
The following lists are the manpower, materials, and equipment requirements for the
construction of Air Blower Building and Fire Fighting Building. However, the quantities
per item were not indicated, so it would not limit the Contractor against providing less
than or more than the quantity would have been stipulated for such a thing.
3.1. MATERIALS
Approval shall be obtained for all the materials with reference to the Engineer
approved materials prior to commencement of activities, Materials Inspection
Request will be submitted to the Engineer upon material arrival to the Warehouse.
All materials must be stored properly as per Manufacturer’s recommendation. The
material shelf life will be monitored as per Manufacturer’s datasheet.
1. Reinforcing Steel Bars, Gr. 60
2. Forms, props and shuttering
3. Scaffolding
4. Ready Mix Concrete
5. Burlap Mats
6. Polywall – EPS Panel (Exterior and Interior Wall)
7. Polywall Adhesives
8. PU Foam
9. Mesh Tapes
10. Cement mortar
11. PPE
12. Consumables
3.2. EQUIPMENTS AND TOOLS
The following equipment and tools shall be used for the various activities.
1. Backhoe
2. Mobile Crane
3. Stake Truck
4. Boom Truck
5. Transit Mixer
6. Concrete Pump Truck
7. One Bagger Mixer
8. Service Vehicle
9. Survey Instruments
10. Concrete Vibrators
11. Shovels
12. Electric Grinder
13. PU foam gun
14. Electric Hammer/ Drill
15. Minor Tools
Page | 3
3.3. MANPOWER
1. Project Engineer
2. QAQC Engineer
3. Safety Officer
4. Safety Aide
5. Project Nurse
6. Surveyor
7. Instrument Man
8. Heavy Equipment Operator
9. Service Driver
10. Foreman
11. Skilled Labor
12. Unskilled Labor
4.
INSPECTION AND TESTING
Site inspection and or approval shall be in accordance with the approved Inspection
and Test Plan for all activities in addition to the Project Quality Plan of the Project.
5.
METHOD OF CONSTRUCTION
This section covers the work method to be apply in the construction of Air Blower
Building and Fire Fighting Building.
5.1. INITIAL SURVEY
Upon receipt of approved drawings and with the approval of the Engineer, an initial
survey together with the Engineer shall be conducted to confirm the site and
established construction limits.
Proper fencing using board-ups/ bollards, caution tapes and site sign boards shall
be installed prior to the construction activities.
5.2. SETTING OUT
The surveyor shall set out the location of the columns according to the grids shown
in the approved Plan and marked the elevations using pins and paint markings.
5.3. CONSTRUCTION OF COLUMN, BEAM, AND SLAB
This covers the method to be implemented in the construction of columns, beams,
and slabs. The construction will consist of three stages starting from the ground
level up to the third floor level. The sequence of construction for each stages will
not vary, which start by the construction of columns followed by beams and slab
construction. The beams and slabs will be casted simultaneously to achieved
monolithic connection.
Page | 4
Fig. 2.0
5.3.1
Cross Section
COLUMN CONSTRUCTION
Upon determining the column location, reinforcing steel bars shall proceed
in accordance to the steel reinforcement requirements as shown in the
approved Plans.
At the ground level along GL G, the column starter bars will be fix to the
prolonging vertical bars of MBBR substructure as shown in Fig 3.1. On the
other side along GL E, where the column will be sitting at the MBBR walls,
the column starter will be fix as shown in Fig 3.2.
Fig. 3.1
Typical Column Starter Bar at
Ground Level
Fig. 3.2
Typical Column Starter Bar at
the Top of MBBR Wall
All Steel reinforcement shall be adequately placed in the position shown on
the approved Plan and firmly held there during placing and setting of the
Page | 5
concrete. Ties shall be space in accordance to the Plan and shall be tied at
all intersections. Ties shall be fastened on the inside.
After completion of reinforcing steel requirements for each stages, it shall
be offered to the Engineer for inspection. Upon Engineer approval, the
formworks shall be placed and fixed in conformance to the approved Plan.
Care shall be carried out to ensure that any formwork system is installed
and supported correctly when applied on site conditions may vary.
Prior to concreting works, confirm and establish all reference points and
mark the limit of concrete elevation.
Subsequently, the area is prepared for concrete pouring upon completion of
formworks installation. The concrete shall be place by means concrete pump
truck and deposited as nearly as possible in its final position using elephant
trunk and discharge hose without causing segregation and displacement of
the reinforcement. The concrete shall be compacted using vibrators during
placement, and shall be worked around reinforcement and into corners of
forms.
The forms shall remain in place undisturbed for not less than 24 hours after
concrete pouring.
The removal of formwork shall be carried out only after the time when
concrete has gained sufficient strength, at least twice the stress to which
the concrete may be subjected to when the formworks are removed.
The removal of column forms and shuttering shall be carried after 24 hours
or as recommended by the Engineer. Care shall be taken in the removal of
forms not to damage the concrete surface and avoid early removal of forms
as this may incur premature cracks in to the concrete.
Subsequently, the entire surface of the newly placed concrete shall be
maintained fully wetted for 72 hours after the concrete has been placed
unless otherwise specified.
5.3.2
CONSTRUCTION OF BEAMS AND SLAB
For each stages of slab and beams construction, it shall be carried out by
erecting scaffolding for worker’s access and slab shuttering support. The
surveyor shall mark the elevation of soffit of slab and beams. Install the
required forms of slab and beams. Ensure that base jacks are provided for
level adjustment just in case there is discrepancies.
The columns shall be braced and provide shuttering for the remaining
column height up to the beam level. For safety, edge protection shall be
provided along the perimeter.
Thereafter, fix the beam reinforcement and anchored it into the column
bars. The installation of steel reinforcement shall be according to the
approved Plan. Ensure that bottom reinforcements shall be lapped within
1/3 beam span from supports while the top reinforcement can be lapped at
midspan.
Page | 6
After completion of beam reinforcement, start fixing the required slab
reinforcement. Ensure that all MEPF inserts are installed before fixing of top
reinforcement.
Upon completion of reinforcement installation, it shall be offered to the
Engineer for his approval. When approved, the area is prepared for concrete
pouring by removal of unwanted materials. Prior to placing of concrete,
ensure that top of concrete columns is roughened and provided with the
approved bonding agent.
Prior to concreting works, top elevation of the slab and beams shall be
established.
Subsequently, placing of concrete shall proceed upon approval of the
Engineer. Concrete shall be place by means concrete pump truck and
deposited as nearly as possible in its final position using elephant trunk and
discharge hose without causing segregation and displacement of the
reinforcement. Concrete shall be evenly spread in layers and thoroughly
consolidated against and along the faces of all forms by means of immersion
or needle vibrator. For safety purposes, workmen shall not be allowed to
walk in the freshly mixed concrete with boots or shoes coated with earth or
foreign substances. In no case shall the vibrator be operated longer than
fifteen (15) seconds in any one location.
The forms shall remain in place undisturbed for not less than 24 hours after
concrete pouring. After the newly placed concrete had been sufficiently set,
it shall be properly cured by covering the entirely with moistened burlap
mats. The concrete shall be maintained fully wetted and in position for 72
hours after the concrete has been placed unless otherwise directed by the
Engineer.
The removal of forms, shuttering and props for the slab and beams shall be
carried out after 14 days or when the concrete has gained at least 70% of
its minimum specified strength as verified on its compression testing.
5.4. CONSTRUCTION OF WALLS USING POLYWALL SYSTEM
The interior and exterior walls of the structure will be constructed using Polywall
Expanded PolyStyrene (EPS) Sandwich Panels in lieu with the use of traditional
concrete hollow blocks. These panels are fabricated used EPS, cement and sand
that is bonded together using technical additives. Then sandwich with 4.5 mm
calcium silicate board on both side. The panels can be installed up to 3 m high and
5 m long. Just the conventional method, it will require lintel beam beyond 3 m high
and a stiffener column beyond 5 m long.
a. The installation of panels shall be according to Manufacturer’s specifications
as follows:
b. Clean and Setup the area. Repair uneven or unleveled surfaces before
cleaning the area.
c. Wall positioning. Established reference line for wall panel installation.
d. Prepare and apply the Polywall Adhesive on floor slab and between panels.
e. Position and install the panel in upright position. Use levelling tool to check
its alignment and correct accordingly. Then, drill and secure with dowel.
f. Apply grout to panel joints and spray PU foam between panels and
structural joints.
Page | 7
g. Subsequently, smoothened the joints by grinding it. Apply waterproofing
sealant on each joint, then put mesh tape on it and finally reapply
waterproofing sealant to cover the mesh tape.
h. Installing MEPF inserts by cutting out affected areas and fill with cement
mortar.
Please refer to Sec.10 for the approved datasheets of Polywall EPS Panels.
6.0 SAFETY REQUIREMENT
6.1 SAFE WORK PRACTICES













Safety of the personnel and properties is to be given prime importance and
all the works to be carried out causing any accidents of property damages.
Construction premises shall be provided with adequate fire, emergency or
danger sign and safety instructions of standard colors and sizes visible
always
Adequate access and egress shall be provided to the site for work. All
personnel shall wear proper PPE’s.
Worker’s welfare facilities shall be provided on site with proper shed for
resting worker adequate supply of drinking water, with proper sanitary and
washing facilities.
All the equipment, tools and tackles being used for the work shall be in
good condition and maintained.
Good housekeeping practice shall be always maintained through
cleanliness of building, yards, machine and equipment’s, regular waste
disposal and orderly process, operations, storage, and filling materials.
Regular toolbox meeting shall be conducted regularly on the procedures to
execute the work safely.
Safety monitoring frequency shall be performed on a daily basis.
Ambient Air Monitoring shall be conducted in a different site for a quarterly
basis in accordance with the Air Quality and Dust Management Monitoring
Plan of the project.
For prevention and control of air pollution, and to minimize emissions of
airborne contaminants, a major area of emphasis for this project has to
maintain combustion powered-equipment in proper condition. Also, open
burning of debris was not permitted to in order to avoid smoke or fumes.
For extremely high temperatures encountered during the summer months,
work clothing was mandated to completely cover arms and legs while
safety glasses with dark lenses were used to combat glare. Cotton gloves
were issued to permit steel surfaces to be touched without causing burns.
To avoid unsafe and unacceptable noise levels on-site and in the adjacent
residential housing, the noise levels in the work areas were to be kept
below 75 decibels. Equipment used shall be properly maintained to avoid
problems with noise control equipment. Equipment that was not quite by
design was kept a sufficient distance away from to avoid sound levels in
excess of the specified limit. Also, hearing protection will be required to all
personnel working around equipment producing high noise levels.
For the confined spaces entry, the following are the important points to
secure first prior to start of activity:
1. Obtain a copy of the entry permit and hazard assessment and
review
the hazards associated with the space;
Page | 8
2. Ensure that the appropriate PPE, Rescue Retrieval Equipment and
Communications Equipment are available and in good working
condition;
3. Lock-out / Tag-out any hazardous energy that the entrant could be
exposed to;
4. Conduct continuous air monitoring utilizing a multi-gas air monitor;
5. The space must be labeled with a confined space “DANGER” sign.

A lifting permit will be secured (accomplished & signed) first prior to any
lifting works execution.
6.2 COVID-19 GUIDANCE, PRECAUTION AND MITIGATION
All works are to be in conjunction and adhering to the guidance and risk
assessments put in place by FFT. these shall include but are not limited to following
requirements and will be updated to suit any further government guidelines;






Site Covid-19 risk assessment for FFT to be reviewed before commencing
works
Adherence to minimum social distancing protocol.
Staggered break times, where required.
Face shield to be used when required. Risk Assessment will be required for
working within the minimum distance required.
No sharing of tools; any tools and equipment that are shared must be
cleaned before and after use
Distancing from other site operations whilst executing task to be
maintained at all times if this is not possible, works must stop and be
reviewed
Page | 9
6.3 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL (HIRAC)
Hazard Identification, Risk Assessment
and Control
(HIRAC)
Page | 10
6.4 PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENT
Protective clothing
(a jacket or protective suit)
Safety shoes
Personal hearing protectors
Protective gloves (canvas or leather)
Glasses / Eyes protection
Respiratory Protection
Helmet
Safety Harness
Page | 11
7.0 INSPECTION AND TEST PLAN
Inspection and Test Plan
(Civil Works)
Page | 12
8.0 APPLICABLE INSPECTION CHECKLIST
Inspection Checklist
Page | 13
9.0 APPROVED PLANS
Approved Plan
Page | 14
10.0POLYWALL EPS PANEL
Polywall EPS Sandwich Panel
(Approved Wall System)
Page | 15
Related documents
Download