Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer Rights, Obligations & Remedial Rights of the Employer, of the Contractor, and of the Role of the Engineer Under the Public Procurement Agency (PPA) Conditions of Contract For Works (Based on National Competitive Bidding) (January, 2006) Clauses 2 2.1 3 3.1 4 4.1 5 5,1 Description of Subject Matter Interpretation Providing instruction to clarify queries about the General Conditions of Contract (GCC) Language & Law Law governing the Contract Engineer’s Decision Deciding on contractual matters between the the Employer & the Contractor Representing the Employer Delegation Delegating duties & responsibilities Employer Engineer Contractor Remarks Obligation It gives the legal framework of the Contract Obligation Obligation Obligation Obligation Right Right 1 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 6. 6.1 7 7.1 8. 8.1 9 9.1 9.2 10 10.1 Communications Communicating in writing Subcontracting Subcontracting Works by securing prior approval from the Engineer Approving subcontracting Other Contractors Cooperating & sharing the Site with other Contractors, public authorities, utilities, and the Employer Providing with facilities for other Contractors… Modifying Schedules of other Contractors Notifying such modifications to the Engineer Personnel Employing key personnel named in the Schedule of Key Personnel Employing other personnel with the approval of the Engineer Approving the replacement of Key Personnel Asking the removal of the Contractor’s personnel, on the ground of misconduct of the Personnel Ensuring the removal of such Personnel Employer’s & Contractor’s Risk Carrying the risks designated as Employer’s risks Carrying the risks designated as Obligation Obligation Obligation Right Obligation Obligation Right Obligation Right Obligation Right Right Obligation Obligation Obligation 2 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 11 11.1 11.2 12 12.1 13 13.1 Contractor’s risks Employer’s Risks Lists of Employer’s risks Time framework for the obligation: from the Completion Date until the Defects Correction Certificate been issued Contractor’s Risks Risks excluding risks of the Employer Responsible from the Start Date until the Defects Correction Certificate been issued by the Engineer Insurance Providing insurance cover for risks responsible for it Ensuring the insurance cover from the Start Date until the end of Defects Liability Period Obligation The risks are related to injury to persons, damage to property & to the Works excluding the Contractor’s responsibility Obligation Obligation Responsible for injury to person, damage to property, to Works, Materials & Plant & Equipment Obligation Obligation Obligation 3 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 13.2 13.3 13.4 13.5 14 14.1 15 15.1 16 16.1 17 17.1 18 18.1 18.2 Delivery of insurance policies for the approval of the Engineer Approving policies & certificates Assuring compensation to be payable in the types & proportion of currencies Arranging the insurance by the Employer at the cost of the Contractor Deducting from any monies due to the Contractor No alteration of the terms of the insurance without the approval of the Engineer Complying with any conditions of the insurance Site Investigation Reports Relying on any Site Investigation Reports Queries about the Special Conditions of Contract (SCC) Clarifying queries on the SCC Contractor to Construct the Works Constructing & installing the Works, as per the Specification & Drawings The Works to be Completed by the Intended Completion Date(ICD) Completion of the Works by the ICD Approval by the Engineer Submitting the design for Temporary Works for the approval for the Engineer Approving the Temporary Works Taking design responsibility for Obligation Before Start Date Right Obligation Right If the Contractor fails to provide same Remedial Right Right Obligation Obligation Obligation Obligation Obligation Obligation Obligation Obligation Right Obligation 4 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 18.3 18.4 18.5 19 19.1 20 20.1 21 21.1 22 22.1 Temporary Works Approval of the Temporary Works by the Engineer No alteration of responsibility by approval of the Engineer Obtaining approval of third parties for the design of Temporary Works Submitting drawings for the approval of the Engineer Safety Assuring the safety of all activities on the Site Discoveries Notifying the discovery of historical & other significant value to the Engineer Instructing the Contractor how to manage the discoveries Complying the instruction of the Engineer Possession of the Site Giving possession of the Site to the Contractor Presumption of delay against the Employer Access to the Site Allowing access to the Engineer & any other persons authorized by the Engineer Authorizing the Contractor for such purpose Right Obligation Obligation If required Obligation Both for Permanent Works & Temporary Works Obligation Obligation Right Obligation Obligation Obligation Obligation Right 5 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 23 23.1 24 24.1 25 25.2 25.3 26 26.1 27 27.1 27.3 Instructions Carrying out of all instructions of the Engineer Disputes Referring the disputes to the Adjudicator, within 14 days of the Engineer’s decision Procedure for Disputes Sharing the fee & reimbursable of the Adjudicator equally & jointly Referring the decision of the Adjudicator within 28 days from the Adjudicator’s decision To be bound by the decision of the Adjudicator, if the decision of same were not referred to arbitration Conduction the arbitration Replacement of Adjudicator Replacing the Adjudicator Jointly appointing a new Adjudicator Designating a new Adjudicator by an Appointing Authority, in case of disagreement Program Submitting a program for approval by the Engineer Submitting an updated program for the approval of the Engineer Withholding a payment, if an updated program not submitted by the Contractor Continuation of withholding payment Obligation Right Right Obligation Obligation Right Right Obligation Obligation Obligation Obligation Right Right Right Right Right Right Obligation Obligation Right Right 6 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 27.4 28 28.1 28.2 29 29.1 30 30.1 31 until the next program Approval of program by the Engineer, no effect on the obligation of the Engineer Observing the contents of the revised Program Extension of the Intended Completion Date Extending the Intended Completion Date(ICD), If the Compensation Events(CE) occurred or Variation issued Deciding on the extension of ICD within 21 days from request by the Contractor Submitting full supporting information to the Engineer(upon the effect of CE or Variation instruction) Acceleration Wishing the finishing of the Works before the ICD Obtaining priced proposal from the Contractor Adjusting & confirming the new ICD Acceptance or rejection of the proposal Delays Ordered by the Engineer Instructing to delay the start or progress of the activities Management Meetings Obligation Obligation Right It shall show the effects of Variations & Compensation Events Right Obligation Obligation Right Right Right /Obligation Right For acceleration measure Right/Obligation Right 7 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 31.1 31.2 32. 32.1 32.2 33 33.1 34 34.1 Requiring to attend a management meeting by the Contractor or the Engineer Recording & providing copies of the meeting(also to the Employer) Deciding on the actions to be taken by the Employer or by the Contractor Early Warning Warning the Engineer of specific likely future events or circumstance that may adversely affect the quality, increase the Contract Price or delay Requiring the Contractor to provide an estimate of the expected effect of the events on the Contract Price & Completion Date Providing the estimate as soon as reasonably possible Cooperating with the Engineer to avoid or reduce the effects of events… Identifying Defects Checking the Works & notifying any defects to the Contractor Instructing the Contractor to search for a defect Instructing the Contractor to uncover & test any work that the Engineer considers may have a defect Tests Instructing the Contractor to carry out Right Right Obligation Right Obligation Obligation Right Obligation Obligation Right Right Right Right 8 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 35 35.1 36 36.1 37 37.4 37.5 tests not specified in the Specification Carrying out the instruction Effects of carrying out the tests Defects observed: Covering the costs by the Contractor No defects observed No defects: Considering the test as Compensation Event Correction of Defects Giving notice to the Contractor of any defects before the end of Defects Liability Period(DLP) Correcting the notified Defect within the time specified in the notice Uncorrected Defects Assessing the cost of having the defects corrected, if the defect uncorrected by the Contractor Paying the cost of the correction Bill of Quantities or Activity Schedule (Quantity based v. Lump Sum) Providing updated Activity Schedules within 14 days of being instructed to by the Engineer Showing delivery of Materials to the Site separately on the Activity Schedule Obligation Obligation Remedial Right Right Obligation Right Obligation Alternative types of contract under the conditions of contract Obligation Obligation If payment on Materials on Site 9 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer shall be made separately 39 39.1 40 40.1 40.2 Variations Inclusion of Variations in the updated Program Payment for Variations Providing with quotation for carrying out the Variation Assessing the quotation before the variation ordered Using the rate in the BOQ to calculate the value of Variation Obligation Consider the type of contract Obligation Obligation Right Quoting in the form of new rates for the relevant item of work, Obligation 40.3 Ordering the variation & making a change to the Contract Price, if the Contractor’s quotation is unreasonable Right 40.4 Deciding that the urgency of varying the work would prevent a quotation being given & considered without delaying the work Effect of the decision: Right Remedial Right For admeasurements contracts If the cost per unit of quantity changes, or if the nature or timing of the work in the variation does not correspond with items in the BOQs Both for admeasurements & Lump Sum Contract Both for admeasurements & Lump Sum Contract Both for 10 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 40.5 41 41.1 42 42.1 42.2 42.3 42.5 42.6 43 43.1 44 44.1 44.2 No quotation by the Contractor & treating the Variation as Compensation Event Entitlement to no additional payment for costs, if the Contractor fails to give early warning Cash Flow Forecasts Providing an updated Cash flow forecast Payment Certificates Submitting monthly statements of the estimated value of the Works executed Checking the Statement & certifying the Payment Determination of the value of the Works Valuation of the value of the work executed including Variations & Compensation Event Excluding any items certified by the Engineer, due to latter information Payments Paying the Contractor the amounts certified by the Engineer within 30 days of each certificate Getting payment of interest for late payment, in the next payment Compensation Events-CE Declaration of CE Deciding by the Engineer on the additional Contract Price & on the No Remedial Right admeasurements & Lump Sum Contract Both for admeasurements & Lump Sum Contract Obligation Obligation Obligation Right Obligation Right Obligation Remedial Right Obligation 11 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 44.3 44.4 45 45.1 47 47.1 47.2 48 48.1 48.2 48.3 extension of time to the ICD Providing information demonstrating the effect of CE up on the Contractor’s forecast cost Assessing the situation & adjusting the Contract Price No entitlement to compensation, in not giving early warning Tax Not adjusting the Contract Price , if taxes, duties & other levies are changed that affect the Contract Price Price Adjustment Adjustment of price, if allowed under the Special Conditions of Contract(SCC) by applying the respective price adjustment factor Submission (with its Bid) tabulation of Weightings & sources of Indices, subject to the approval of the Engineer Retention Retaining from each payment due to the Contractor Releasing half of the retained money to the Contractor Releasing the remaining half of the retained money upon the expiry of the DLP, provided all the defects have been remedied Substituting the retention money with an Obligation Obligation No Remedial Right No Obligation No Remedial Right Remedial Right Obligation Right Obligation Right Obligation Right Right 12 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 49 49.1 49.2 50 50.1 51 51.1 51.2 “on demand” Bank Guarantee Liquidated Damages Paying Liquidated Damages(LD) at the rate per day stated in the SCC Deducting the LD from the payments due to the Contractor Correcting any overpayment of LD by adjusting the next payment certificate, if the ICD is extended after the LD have been paid Entitlement to interest for such overpayment Bonus Getting bonus at the rate per calendar day stated in the SCC for each day that the completion is earlier than the ICD Advance Payment Making advance payment Providing unconditional Bank Guarantee Keeping the Guarantee valid & effective until the advance payment fully repaid Reduction of the amount of the Guarantee by the amount repaid by the Contractor Paying no interest for the advance payment Using the advance money only to pay for Equipment, Plant & Materials & mobilization expenses Providing evidence that the advance Obligation Remedial Right Obligation Remedial Right Right Less any days for which the Contractor is paid for acceleration Obligation Obligation Obligation Right Right Obligation Obligation 13 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 51.3 52 52.1 53 53.1 53.2 54 54.1 money has been used for the purpose intended Repaying the advance money from payments due to the Contractor Deducting from monies due to the Contractor Securities Providing Contract Securities to the Employer no latter than 15 days after receipt of the Letter of Acceptance Providing Performance Bond by the Domestic Contractors Providing Performance Bank Guarantee by the international Contractors Making the security valid until a date of issue of the Certificate of Completion Making the security valid until one year from the date of issue of the Certificate of Completion Day works Using Day work for small additional work, if with the approval of the Engineer Recording all work to be paid for as Day works on forms approved by the Engineer Verifying & signing the completed form within 2 days of the Day work being done Cost of Repairs Remedying loss or damage to the Works or Materials provided the loss or damage arises from the Contractor’s acts or Obligation Right Obligation Right Obligation Obligation Obligation In case of a Bank Guarantee In the case of a Performance Bond Right /Obligation Obligation Obligation Obligation 14 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 55 55.1 56 56.1 57 57.1 58 58.1 omissions Completion Requesting the Engineer to issue a Certificate of Completion (CC)of the Works Issuing a CC upon deciding that the Works have been so completed Taking Over Taking Over of the Works & the Site within 7 days of the Engineer’s issuing a CC Final Account Supplying a detailed account of the total amount payable under the Contract before the end of the DLP Issuing a Defects Liability Certificate(DLC) & certifying any final payment due to the Contractor Issuing a Schedule that states the scope of the corrections or additions that are necessary(if DLC not issued) Deciding on the amount payable to the Contractor by issuing payment certificate Operating & Maintenance Manual Supplying “as-built” Drawings and/or Operating & Maintenance manuals Right Obligation Obligation Obligation Obligation Right Right If the Final Account resubmitted by the Contractor found unsatisfactory Obligation If required by the dates specified in the SCC 15 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 58.2 59 59.1 59.2 59.3 59.4 59.5 60 60.1 60.2 Withholding of payment for not submitting the said documents by the Contractor Termination Terminating the Contract for fundamental breach of Contract caused by the Contractor Terminating the Contract for fundamental breach of Contract caused by the Employer List of fundamental breach of the Contract by the Contractor or by the Employer Giving notice to the Engineer for the grounds of termination other than specified in the Contract Deciding whether or not the breach is fundamental Terminating the Contract for convenience Stopping the work making the Site safe & secure & leaving the Site Payment upon Termination Issuing a certificate for the value of work done & Materials ordered Applying no additional LD Issuing a certificate for the value of work done, Materials ordered, reasonable cost of removal of Personnel, Costs for protecting & securing the Works, less Right Right Right Right Right Obligation Obligation Obligation Right If the Contract is terminated Obligation Obligation Obligation In case of termination due to the Contractor Right 16 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 61 61.1 62 62.1 62.2 advance payment Property Taking presumption in favour of the Employer that all Materials on the Site, Plant, Equipment, Temporary Works, and Works shall be the property of the Employer Release from Performance Certifying that the Contract has been frustrated Making the Site safe and stopping the work quickly as possible after receiving from the certificate from the Engineer Getting payment for all work carried out before receiving the certificate & for any work carried out afterwards to which a commitment was made Right Obligation Grounds of Frustration: outbreak of war or any other event entirely outside the control of the parties Obligation Remedial Right 17 Organized by: Zewdu Tefera Worke, Engineering Contracts Lawyer 18