Uploaded by john ford

OP content

advertisement
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents : Module 1: Overview
of the Construction Process : Fact Sheet 1.1: Stage 1—The concept of a
project : Stage 1–The concept of a project
1m
Stage 1–The concept of a project
A project is... an individual or collaborative enterprise that is carefully planned to
achieve a particular aim. (Oxford University Press, 2021).
Footnote 1.
Oxford University Press. (2021). Oxford
languages. https://languages.oup.com/google-dictionary-en/
What's your project?
Most of us will have set out to complete a project at some stage in our lives. A
project is a series of tasks that, when carefully planned and carried out, will lead to
a particular outcome.
In construction terms, a project can be as small as renovating a bathroom
or repairing a leaking garage roof to a huge and complex enterprise to build
specialised construction projects such as the Marsden Oil Refinery, Forsyth Barr
Stadium in Dunedin, or architecturally unique buildings such as Te Papa and the
Beehive.
To complete a project, the right resources (both financial and skills) must be in
place and an appropriate process planned.
A construction project life cycle
Typically, there are three overarching stages of a construction project:



design
procurement
construction.
© The Open Polytechnic of New Zealand Ltd
You'll take a brief look at each stage next.
Thoughts on this page?
RETURN
PREVIOUS: TOPICS IN THIS MODULE
NEXT: CONSTRUCTION PROCESS–THE DESIGN STAGE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.1: Stage 1—The concept of a
project : Construction process–The design stage
1m
Construction process–The design stage
Stage 1: The design stage
In this first stage, the owner of a building needing modification or the client
wanting a new build will engage the services of a designer or architect to turn their
proposal into a design for the building.
Depending on the size and complexity of the project, the architect may create a
design team. For the more complex projects, this will include one or more
specialist engineers, such as structural engineers or fire engineers, and specialist
consultants such as quantity surveyors and project managers.
Design brief
The design team works with the client to identify the client's requirements and
form a brief. From this brief, the team produces documentation including
construction drawings, technical specifications and estimated costs that can be used
to procure the services of a contractor to construct the building.
Building consent
Once the final design has been agreed and the project has reached the construction
drawing stage–known as the working drawing stage–applications are made to the
local authority for building consent.
© Getty Images
Thoughts on this page?
RETURN
PREVIOUS: STAGE 1–THE CONCEPT OF A PROJECT
NEXT: CONSTRUCTION PROCESS–THE PROCUREMENT STAGE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.1: Stage 1—The concept of a
project : Construction process–The procurement stage
5m
Construction process–The
procurement stage
What is procurement?
Procurement is the process of acquiring and delivering goods, services, and works.
It starts with identifying the need and finishes with either the end of a service (or
project) contract or the disposal of an asset (New Zealand Government
Procurement, n.d.).
Footnote 1.
New Zealand Government Procurement. (n.d.). Definitions – A list of words and
what they mean. Retrieved September 30,
2021. https://www.procurement.govt.nz/procurement/principles-charter-andrules/government-procurement-rules/definitions/
Procurement
When the design has got to a certain stage–and this stage varies between different
projects and the approach taken–the services of a contractor have to be obtained.
The process of securing the services of a contractor is known as procurement.
There are different approaches to procurement depending on the method chosen to
deliver the project. You'll learn about these different procurement and delivery
methods in Module 1 Fact sheet 1.3.
Procurement and tendering
Whatever procurement method is chosen, at some stage the project work will need
to be put out to tender. This means that sufficient documentation is 'put out to
market' so that potential contractors (tenderers) can 'tender' (or bid) for the work to
construct (and sometimes design) the project.
The amount and type of documentation provided for tender vary depending on the
procurement and delivery method chosen (see Fact sheet 1.3). Next, you'll take a
brief look at the process of tendering.
The next course, CON102 Tendering Administration Processes for Construction
Projects, explores tendering in more detail.
What is a tender?
A tender is a written or formal offer to do a job or supply goods, for an agreed
price (Cambridge Dictionary, n.d.).
Footnote 2.
Cambridge Dictionary. (n.d.). Tender. In Cambridge Dictionary.org. Retrieved
September 30 2021. https://dictionary.cambridge.org/dictionary/english/tender
Invitation to tender
Once the design documentation is agreed upon and completed, contractors are
invited to tender for the work.
Invitations to tender are sent out in one of four ways:
Open tender—The invitation to tender is advertised publically via a publication.
The platform that government organisations use for publishing a tender is the New
Zealand Government Electronic Tenders Service (or GETS for short).
Selective tendering—A known contractor is asked to submit a tender for the
project.
Seeking a negotiated contract—A contractor is asked to carry out work for an
agreed amount.
Advertising for an expression of interest—Contractors who want to apply for the
construction project work submit a proposal that outlines their expertise,
experience with similar projects, capability as a construction company, and their
professional qualifications and memberships. From these applicants, strong
candidates are invited for an interview with a panel comprising the client and the
design team.
Tender documentation
When a design is put out to tender, the main contractors (known as tenderers) are
supplied with the same information and tender documents.
This documentation may include:




Drawings—site plans, floor plans, layout plans, sections, elevations and
detail drawings.
Specifications—details of the type of work and the materials to be used.
Schedule of quantities—a list of all the materials to be used and their
quantities. This documentation would usually only be provided for larger
projects.
Related information—where relevant.
Using these documents, the tenderers prepare a tender outlining how much they
would charge the client to do the work specified.
All tenders must be submitted by a set date and time. Late submissions are not
accepted to avoid disadvantaging those who submitted on time.
What if...
...there are questions raised?
Sometimes, contractors (the tenderers) may have questions about the
documentation. If this is the case, they may raise these questions with the design
team. The design team responds by issuing Notices to Tenderers (NTT). These
contain the required clarifications or corrections to the tender documents and are
provided to all tenderers so that everyone receives the same information.
...some of the work is outside the scope of the contractor?
If some of the work includes specialist areas outside the contractor's normal work
areas, these contractors can, in turn, place tenders out to specialist contractors or
subcontractors for this work. Examples of these may include structural steelwork
contractors, electrical contractors, HVAC (Heating, Ventilation, and Air
conditioning) engineers.
Choosing a tender
Once all tenders are received, the design team reviews them. The team may ask the
tenderer to clarify some details. They may also check that the contractors
(tenderers) have the requisite experience, expertise and financial security to
complete the project.
When the team is satisfied that all criteria have been met, they rank the bids in
order of suitability and discuss or present them to the client. It's usual practice that
the client accepts the lowest price but the client is not obliged to do so.
If none of the tender submissions meet the client's requirements, the client can retender the project with additional material or select different contractors.
Becoming legally binding
Once the client and design team have decided which contractor they want to work
with and have informed them, the tender document submitted by that contractor
becomes legally binding.
From the accepted tender, the contract documents for the construction phase of
the project are drawn up.
You'll look at the construction stage next.
Thoughts on this page?
RETURN
PREVIOUS: CONSTRUCTION PROCESS–THE DESIGN STAGE
NEXT: CONSTRUCTION PROCESS–THE CONSTRUCTION STAGE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.1: Stage 1—The concept of a
project : Construction process–The construction stage
1m
Construction process–The construction
stage
Once the contracts are in place and the necessary building consents have been
obtained by the client, the construction phase can begin.
Variations
As construction progresses, there may be changes to the original design and
documentation. These changes are called variations. Usually, they are initiated by
the client, the contractor, or a member of the design team.
When a variation occurs, the drawings must be revised and written confirmation of
what has changed from the original documentation must be issued. All changes
must be re-costed by the quantity surveyor. Variations often result in additional
costs to the contract, which is why they must be in writing–occasionally they may
result in savings.
As-built drawings
At the end of the contract, the designer gives the client a set of 'as-built' drawings
and documentation. These are a record of the design of the building plus all the
changes that took place during the actual construction. In other words, they're a
detailed blueprint of the building as it was actually built.
This is a vital record to enable the efficient ongoing maintenance of the building.
Before exploring these stages of the construction process in more detail, take the
opportunity to look at different types of construction projects.
Thoughts on this page?
RETURN
PREVIOUS: CONSTRUCTION PROCESS–THE PROCUREMENT STAGE
NEXT: TYPES OF CONSTRUCTION PROJECTS–RESIDENTIAL
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.1: Stage 1—The concept of a project : Types
of construction projects–Residential
2m
Types of construction projects–
Residential
What projects will you work on?
In the construction industry, you have the opportunity to gain experience in a range
of construction projects. Broadly speaking, these could be residential, commercial,
institutional, specialised or civil construction projects.
Take a brief look at each of these.
Construction is big business
In February 2019, there were 65,230 enterprises in the construction industry with
177,000 employees (Stats NZ, 2019).
Footnote 1.
Stats NZ. (2019, October 25). Construction industry at the top of the ladder for
business counts growth. https://www.stats.govt.nz/news/construction-industry-atthe-top-of-the-ladder-for-business-counts-growth
Overall, it employs over 250,000 people in the different construction areas.
Construction is the fifth largest sector in the Aotearoa New Zealand economy
(MBIE, 2020).
Footnote 2.
MBIE. (2020, July 23). Construction fact sheet — July 2020 — impacts of COVID19 and future outlook. https://www.mbie.govt.nz/dmsdocument/11600construction-factsheet-july-2020
An infographic from Ministry of Business, Innovation and Employment's 2021 Annual
Report on trends in the building and construction sector.
© Crown Copyright
Residential construction projects
In the construction industry, a residence is a building that people live in. It's a term
that refers to detached, semi-detached, and terraced houses, flats, apartment blocks,
townhouses, and also nursing homes, elderly persons' homes and dormitories.
Small-scale building companies
Many of our detached homes in Aotearoa New Zealand are built by small-scale
building companies consisting of fewer than five employees. These companies rely
on using labour-only contractors (for carpentry, concrete, roofing, wallboard,
bricklaying) and subcontractors (such as electricians, plumbers and gas fitters).
Franchised residential building companies
Group housing companies offer packages for new houses based on standard plans.
Others specialise in mass-produced prefabricated homes.
© Getty Images
Next
Strong growth in residential building
construction
In February 2019, over 30,000 people were employed in the residential
construction industry.
That's an increase of over 50% in the past five years (Stats NZ, 2019).
Footnote 3.
Stats NZ. (2019, October 25). Construction industry at the top of the ladder for
business counts growth. https://www.stats.govt.nz/news/construction-industry-atthe-top-of-the-ladder-for-business-counts-growth
Will this be maintained?
It's hard to predict the future, but it's always possible to look at what the experts
say.
If you're interested in analysing the future outlook in the construction sector, read this fourpage PDF, Construction fact sheet–July 2020–impacts of COVID-19 and future outlook.
Next, take a look at other types of construction projects.
Thoughts on this page?
RETURN
PREVIOUS: CONSTRUCTION PROCESS–THE CONSTRUCTION STAGE
NEXT: TYPES OF CONSTRUCTION PROJECTS–COMMERCIAL AND INSTITUTIONAL
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.1: Stage 1—The concept of a project : Types
of construction projects–Commercial and institutional
20m
Types of construction projects–
Commercial and institutional
Commercial construction projects
Select the white arrows < > at the side of each image to see examples of
commercial construction projects such as retail malls, warehouses, multi-purpose
office blocks. Other examples of these projects include factories and workshops.
From this, you'll ascertain that:
Commercial construction is the building of a structure to be used for commercial or
industrial use.
Types of commercial construction projects–retail malls
© Getty Images
Next
Compared with the small-scale residential builder, commercial construction
involves medium- to large-scale companies. These companies have a larger
workforce, access to greater capital, and larger and more extensive equipment.
In Aotearoa New Zealand, main commercial contractors cover all aspects of the
construction process from design to construction to cost analysis. In addition to
permanent staff, main contractors employ subcontractors with specialist fields of
expertise, such as pile driving and steel fabrication. Both of these are common in
Aotearoa New Zealand due to the need for earthquake strengthening in our larger,
commercial buildings.
Institutional construction projects
Institutional construction projects involve the building of schools, colleges,
hospitals, clinics, museums, art galleries, sports stadiums, and cultural centres.
Large-scale construction companies undertake these projects. As with large-scale
commercial construction projects, the main contractors will employ many
specialist subcontractors for their specialist services.
In these projects, it's usually the client who will employ the main project manager
as the risks are high, and financial penalties may be imposed if the project is not
delivered within time and budget.
Select the white arrows < > at the side of each image to see examples of different
institutional construction projects.
Types of institutional construction projects–sports stadium
© Getty Images
Next
ACTIVITY 1.1: COMMERCIAL CONSTRUCTION COMPANIES
How many large construction companies can you think of that operate in Aotearoa
New Zealand?
Write a list then Submit your answer. Check the feedback and compare it with the
list you collated.
BOLDITALICUNDERLINE
BULLET LISTNUMBERED LISTALIGN LEFTALIGN CENTERALIGN RIGHT
SUPERSCRIPTSUBSCRIPT
TABLE
0Word(s)0 words written
SAVE DRAFT SUBMIT
You might like to explore the websites of some of these companies listed in the
feedback to the commercial construction companies task.
If you do, you'll notice that different companies specialise in different types of
construction projects. Some will specialise in large commercial or institutional
projects like those mentioned previously; whereas others will specialise in
infrastructure projects such as roading, or drain laying, or water system
management; or specialised construction projects such as oil refineries.
Take a look at specialised construction projects next.
Thoughts on this page?
RETURN
PREVIOUS: TYPES OF CONSTRUCTION PROJECTS–RESIDENTIAL
NEXT: TYPES OF CONSTRUCTION PROJECTS–CIVIL CONSTRUCTION AND SPECIALISED CONSTRUCTION
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents : Module 1: Overview
of the Construction Process : Fact Sheet 1.1: Stage 1—The concept of a
project : Types of construction projects–Civil construction and specialised
construction
1m
Types of construction projects–Civil
construction and specialised
construction
Civil construction projects
Civil construction projects do not involve habitable buildings. Instead, they include
mega-structures such as roads, dams, bridges or tunnels. These may be referred to
as 'horizontal' construction projects (as opposed to the 'vertical' construction
projects of buildings).
Like institutional or large commercial construction contractors, contractors who
undertake civil construction projects are large, corporate organisations with
significant assets and access to specialised expertise.
Select the white arrows < > at the side of each image to see examples of Aotearoa
New Zealand civil construction projects.
Types of civil construction projects—bridges such as Arthur's Pass in the South Island
© Getty Images
Next
Specialised construction projects
Specialised construction projects tend to be one-off projects involving a
combination of government and private financial backing, and several large
contractors–many of whom may be brought in from overseas.
Marsden Point oil refinery is an example of a specialised construction project in
Aotearoa New Zealand. It took two years to build back in the 1960s with the
American company, Bechtel, as the main engineering and construction contractor.
Specialised construction projects–Marsden oil refinery
© Getty Images
Now that you've explored the concept of a project and looked at examples of types
of construction projects, next you'll look at the start of the construction process–
beginning with the design stages.
Thoughts on this page?
RETURN
PREVIOUS: TYPES OF CONSTRUCTION PROJECTS–COMMERCIAL AND INSTITUTIONAL
NEXT: STAGE 2–DESIGN
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.2: Stage 2—Design : Stage 2–Design
1m
Stage 2–Design
In this fact sheet, you'll explore what happens in the design stage of a construction
project, who's involved, and what documents they produce.
Who's involved during the design stage?
Depending on the scale and complexity of the project, the design team could be as
small as a single designer or it could involve many designers, engineers, quantity
surveyors and landscape designers.
What happens during the design stage?



The client's needs are identified.
The client's needs are translated into a design.
The design is checked to make sure it's feasible within the project
constraints of time, budget, space and other resources.
The design stage can be considered in four stages:




The design brief.
Preliminary design.
Developed design.
Detailed design.
These stages may be given different names in different contexts, and one stage
may overlap with another, but this classification is helpful to enable a high-level
understanding of the design processes involved in a construction project.
Let's look at each in turn.
Thoughts on this page?
RETURN
PREVIOUS: TYPES OF CONSTRUCTION PROJECTS–CIVIL CONSTRUCTION AND SPECIALISED CONSTRUCTION
NEXT: THE DESIGN BRIEF
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.2: Stage 2—Design : The design brief
1m
The design brief
The client's requirements
Clients may be one individual, a group of individuals, an organisation or a
company who has identified a need for a building or modification of a building,
and who have the means to finance the building project.
Clients may know the type of building required or they may only know what
outcomes they desire from the project, or what problems or deficiencies they wish
the building project to solve.
The designer's focus
The design team listens to the client and establishes their requirements through
discussion, research and consultation.
Their aim is to prepare a brief that both satisfies the client's needs and meets the
requirements for good design, buildability and sustainability.
What's the outcome?
The completed design brief must present a solution that meets the client's
requirements in terms of:




the function of the building and its interior spaces
the structure of the building within the constraints of the site and regulations
cost–taking into account the client's budget, size of the building and quality
aesthetics–how the building looks with respect to its function, its
surroundings and local culture.
Thoughts on this page?
RETURN
PREVIOUS: STAGE 2–DESIGN
NEXT: PRELIMINARY DESIGN
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.2: Stage 2—Design : Preliminary design
10m
Preliminary design
What happens in the preliminary design
stage?
In the preliminary design stage, concept designs are created as initial design
proposals based on the client's brief. This stage may also be known as the
schematic design stage.
Think of this stage as a type of brainstorming–multiple concept designs are put
forward, each meeting the design brief in slightly different ways. The designers
will test ideas such as:


circulation–how people will move around the building
spatial flow–what activities will occur in the building and how they need to
relate to each other.
Not all the concept designs will be suitable when the constraints of the site, time,
budget and so on are considered. But, by testing these ideas first, the final design is
more likely to meet the client's requirements effectively.
As well as ideas, the preliminary design stage is also a time for
gathering information from specialists.
Who's involved in the preliminary design
stage?




Specialist consultants–such as engineers (structural engineers, services
engineers and so on) provide input and feedback based on their areas of
expertise and investigations they may conduct on the site so that the services
and mechanical processes can be integrated into the designs.
Quantity surveyors (QS)–it's a quantity surveyor's job to outline the
preliminary cost of the proposed design, assess the impact of changes on the
original budget, and consider likely future costs in terms of running costs
and maintenance.
Client or client's representative (often a designer)–will investigate viable
options with contractors who have the right expertise for particular designs
or services. They will also use the cost estimates from the QS to estimate
how long the construction process is likely to take and to start drawing up a
planned outline of the construction programme.
Designer–The designer will draw designs based on the preferred and most
feasible concepts. They may use 3D modelling software to provide virtual
walkthroughs and show the client how the building will work. The designer
will adapt the designs as needed based on feedback from the stakeholders
listed above.
What's the outcome of the preliminary design
stage?
Based on all this input, the preliminary design stage results in design drawings
(such as plan, sections, elevations, views) that communicate the design concept to
the client and other stakeholders. The number of design drawings required will
vary depending on the size and complexity of the project.
There may also be a preliminary design report to accompany the drawings to
outline features such as structural components, material and equipment
specifications and cost schedules.
Go / No-go
At the end of the preliminary design stage, sufficient ideas, information and input
are gathered to decide if the project is viable for the client or not.
In a simple project, it's possible that the process will go straight from the
preliminary design stage to the detailed design stage. In more complex projects, a
developed design stage is also required–you'll explore this next.
If you are new to the construction sector, you may like to watch the following videos which
demonstrate what is meant by the design drawing terms:
Floor plan (How to Architect, 2009) (3:11).
Footnote 1.
How to Architect. (2009, December 30). How to draw like an architect, pt1 – The floor
plan [Video]. YouTube. https://www.youtube.com/watch?v=b_bEps3hJLI
Elevation (How to Architect, 2010) (2:16).
Footnote 2.
How to Architect. (2010, January 7). How to draw like an architect, pt 2 – The
elevation [Video]. YouTube. https://www.youtube.com/watch?v=5zIZBZRea8w
Section (How to Architect, 2010) (2:32).
Footnote 3.
How to Architect. (2010, January 12). How to draw like an architect, pt 3 – The wall
section [Video]. YouTube. https://www.youtube.com/watch?v=MKc7yYurPis
Thoughts on this page?
RETURN
PREVIOUS: THE DESIGN BRIEF
NEXT: DEVELOPED DESIGN
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents : Module 1: Overview
of the Construction Process : Fact Sheet 1.2: Stage 2—Design : Developed design
2m
Developed design
What happens in the developed design stage?
Once the design team has agreed on the preliminary design, the concept is further
developed to define the functionality and spatial flow required, to ensure the
required structural strength and integrity can be provided and all the services
included within the project budget.
In other words, a developed design is adding the necessary details to the
preliminary design.
Who's involved in the developed design stage?



Designer–will focus on finalising the details of the 'spatial
coordination'; that is, how the spaces in and around the building
will work to enable it to function as needed for the number of
people and types of activities involved.
Specialist consultants–the structural engineers and building
services consultants will finalise their project strategies so the
designer can check and incorporate them into the final design.
Quantity surveyor (QS)–QS completes their cost estimates and
life cycle costs and checks they're within the client's budget. They
will also identify specific costs associated with construction (for
example, pumps and cranes) and post-construction (for example,
fitting out the building). The QS monitors the design process
throughout to ensure changes are within budget.
What's the outcome of the developed design
stage?
At the end of the developed design stage, more detailed drawings will be drawn up
or completed. These may be highly technical and outside the normal scope of the
client, so careful explanation may be needed to ensure the client has a sufficient
understanding of the project.
Developed drawing–site plan of a garage
© Design Factum Ltd
Thoughts on this page?
RETURN
PREVIOUS: PRELIMINARY DESIGN
NEXT: DETAILED DESIGN STAGE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.2: Stage 2—Design : Detailed design stage
2m
Detailed design stage
What happens in the detailed design stage?
In the detailed design stage, the design team refines the design to provide technical
definitions for the project. Any specialist work needed is agreed on and the details
finalised as part of the design.
Drawings produced at this stage will show the working details of how the building
is to be constructed. They'll be drawn at such a scale and accuracy that it's possible
to show details of; for example, junctions–not just at one angle but at different
angles–so what's required to construct them is clear to the contractors.
Who's involved in the detailed design stage?
The same team members as before. Often they may work independently to bring
all the details together, so it's important that the lead designer, or project lead, or
client's representative coordinates and collates all the information to ensure the
whole design works.
What's the outcome of the detailed design
stage?
At the end of this stage, all design aspects are complete. Any changes after this
stage could be expensive to accommodate.
The detailed design drawings and accompanying documentation are collated and
will be the documents that are put out to tender.
Detailed drawing–section of planned garage
© Design Factum Ltd
When the detailed design documents are ready, the next stage in the construction
process is procuring the services of a contractor or contractors who will build the
project.
There are different ways of procuring a contractor which depends on the approach
to building you wish to take–this is known as the procurement or delivery method.
You'll look at these next.
Thoughts on this page?
RETURN
PREVIOUS: DEVELOPED DESIGN
NEXT: STAGE 3–PROCUREMENT STAGE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.3: Stage 3—Procurement stage : Stage 3–
Procurement stage
45m
Stage 3–Procurement stage
What is procurement?
Procurement is the process of acquiring and delivering goods, services, and works.
It starts with identifying the need and finishes with either the end of a service (or
project) contract or the disposal of an asset (New Zealand Government
Procurement, n.d.).
Footnote 1.
New Zealand Government Procurement. (n.d.). Definitions – A list of words and
what they mean. https://www.procurement.govt.nz/procurement/principles-charterand-rules/government-procurement-rules/definitions/
Procurement strategy
In the construction sector, procurement refers to the process (usually after the
design phase) where the client, client representative and design team decide:



how they're going to seek potential contractors to build the project (known
as the approach to market)
how they'll evaluate each contractor who puts forward a tender, then select
their best option
what delivery method they'll use for the project.
This is known as the procurement strategy.
How to develop an effective procurement strategy
MBIE has developed guidelines that it considers good practice when developing a
procurement strategy for a construction project. While these guidelines are
intended for government agencies undertaking construction projects, they also
apply to non-government construction projects (MBIE, 2019).
Footnote 2.
MBIE. (2019, October). Developing your construction procurement strategy—
Construction procurement
guidelines. https://www.procurement.govt.nz/assets/procurementproperty/documents/developing-your-procurement-strategy-constructionprocurement.pdf
In these guidelines, they identify factors that help you develop an effective
procurement strategy. These are to:





make sure you fully understand your project's characteristics, such as the
key drivers, constraints and risks
work out the best delivery models for your project
involve key stakeholders and specialists early in your planning and
development process
challenge any assumptions
use practical techniques to analyse issues to help you make the right
decisions.
Next are the three crucial steps in a procurement strategy.
Steps to developing your procurement strategy
© MBIE
Gather and analyse project information
The first step in procurement as you gather information is to make sure you fully
understand the project brief. Table 1.1 shows some key areas to consider.
If you're new to the construction sector, the information in this table may look overwhelming.
How can you remember it all? You don't have to! These are the sort of factors you'll naturally
think about–as a team–when beginning a project. Not convinced? Read the table then test
your own thinking with the scenario that follows.
Table 1.1 Gathering information for your procurement strategy
Project requirements
Project constraints
Project risks
Client capability
What are your...
What are your...
Could there be issues
with...
Do you know about
your...
priorities
site constraints such as size,
geotechnical, cultural, and
outcomes
environmental considerations.
site
permits
design
client knowledge,
experience and
resources
materials
desired milestones
design criteria and
Could there be issues with...
client concern
planning and consent
different delivery
methods
reasons behind
them.
finances
their experience with
design complexity.
Is there...
stakeholder
management
neighbouring sites
during and after
building.
their desired level of
oversight in the
project.
flexibility for change.
ACTIVITY 1.2: ANALYSING PROJECT INFORMATION
Read the following scenario, then list at least six important features of this project
that need to be considered in the project brief.
Scenario
The new board of trustees for a local high school wants to construct a new,
innovative and complex gymnasium. As a member of the board and as an
architectural designer, you're the most experienced member in construction
procurement and they're looking to you for early stage guidance.
Because they're a public institution, they require a high degree of transparency in
costs, and have a low tolerance to risk or cost fluctuations. A competitive cost is
required by the government. The project is expected to cost around $7.2 million.
Funding is currently secured for $5.9 million. The board has several options to
fund the balance and is not concerned about the shortfall.
Developed design is not yet complete. The project has a tight timeframe as the
board wishes to minimise disruption to the school. All the board members are busy
professionals and are unable to actively monitor or invest time into the building
process.
Their intention is to potentially lease or share ownership of the building with a
private organisation to reduce costs and to make better use of the space, but this is
not yet confirmed. This project will be a focal point for the community, community
stakeholder management is a priority.
They are interested in involving a specialist contractor at an early stage to ensure
the technical aspects of the gym are state-of-the-art. The contractor's involvement
will influence the final set of drawings.
BOLDITALICUNDERLINE
BULLET LISTNUMBERED LISTALIGN LEFTALIGN CENTERALIGN RIGHT
SUPERSCRIPTSUBSCRIPT
TABLE
0 / 500 Word Limit
SAVE DRAFT SUBMIT
ACTIVITY 1.3: CATEGORISING PROJECT INFORMATION
Now you've elicited the key features of this college gymnasium project, familiarise
yourself with the terminology involved in construction by classifying each feature
to its appropriate category.
Drag each term to the appropriate column, then Submit your answer. Note, not
every column will have the same number of terms.
Project requirements
Project constraints
Early engagement with specialist
Cost transparency
Stakeholder management
Low client capability
New, innovative gymnasium
Low risk
Design complexity
Cost fluctuations
Possible shared ownership
Tight timeframe
SUBMIT
Project risks
Client capability
The next step in your procurement strategy is to determine your preferred delivery
model.
So, on the following pages, you'll look at the different types of delivery models,
their advantages and disadvantages, and what to consider when choosing the
delivery model.
Thoughts on this page?
RETURN
PREVIOUS: DETAILED DESIGN STAGE
NEXT: TYPES OF DELIVERY MODELS
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.3: Stage 3—Procurement stage : Types of
delivery models
20m
Types of delivery models
Choosing the right delivery model is one of the most important decisions in the
construction procurement process–choosing the wrong model can affect the cost,
quality and timing of your project.
The delivery model you select will also determine how you organise your project
team.
Each model has its advantages and disadvantages, so a model should be chosen
based on what is most appropriate for your project (MBIE, 2019).
Footnote 1.
MBIE. (2019, October 19). Developing your construction procurement strategy —
Construction procurement
guidelines. https://www.procurement.govt.nz/assets/procurementproperty/documents/developing-your-procurement-strategy-constructionprocurement.pdf
You'll look at some common delivery models next.
How to make the most of the next few pages
In the next few pages, you'll explore six different types of procurement and
delivery methods commonly used in Aotearoa New Zealand. It's a lot of
information to take in, so you may wish to collate some useful ideas and notes as a
table or spreadsheet, such as this table shown here.
Table 1.2 Collating notes on construction procurement methods
Method
What it is
When it's used
Its advantages
Alternatively, or in addition, you may wish to compile a document of flow charts
for each method that show the contractual relationships between the different
stakeholders at the different stages of the project. Examples, such as this one in
Fig. 1.1, are shown in the course.
Fig. 1.1 Contractual relationships in a traditional–design, bid, build model
© MBIE
Thoughts on this page?
RETURN
PREVIOUS: STAGE 3–PROCUREMENT STAGE
NEXT: TRADITIONAL–DESIGN, BID, BUILD METHOD
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.3: Stage 3—Procurement stage : Traditional–
design, bid, build method
20m
Traditional–design, bid, build method
Traditional–design, bid, build delivery method
In a traditional delivery method, the client chooses an architect or design team and
asks them to prepare specifications for a given budget.
When the plans and design drawings are complete, the client releases them for
bidding to general contractors. The contractors bid against each other for the work.
The client evaluates the contractors' bids, selects a contractor, and establishes a
contract with the chosen contractor to build the project.
When does the traditional method work best?
When:

the client wants to retain overall control of the design throughout the project






the client has project management and/or construction development
experience
requirements are straightforward and the scope is well-defined
there is sufficient time to allow for separate design, tender and construction
phases
there's likely to be a large pool of tenderers and strong competition to win
the contract for the project
site conditions are known
cost certainty is required.
What are the advantages and disadvantages of the traditional
method?
Table 1.3 Advantages and disadvantages of the traditional method
Advantages
Disadvantages
Client has full control over design and specifications at all
stages.
It's time-consuming–particularly to get full design a
tender stage.
Design team is directly employed by the client, so work in
the client's best interests.
The client doesn't get the benefit of the contractor
optimise the design from a construction perspectiv
The tendering process is straightforward which lowers the
cost and effort for the client.
Design risk rests with the client and construction ris
be hard to decide who's responsible for defects late
The tendering process introduces competition which
results in lower prices.
The tender process puts pressure on contractors to
the risk of poorer quality work.
Cost is established at the beginning.
The client is responsible for cost and time overruns
The traditional delivery method is well-known and
understood.
Contract variations, including design changes, are easy to
deal with.
(MBIE, 2019)
Footnote 1.
MBIE. (2019, October). Traditional delivery model – Construction procurement
guidelines. https://www.procurement.govt.nz/assets/procurementproperty/documents/traditional-delivery-model-construction-procurement.pdf
Figure 1.1 shows the contractual relationships of the key stakeholders in a
traditional delivery method (MBIE, 2019).
Footnote 2.
MBIE. (2019, October). Traditional delivery model –Construction procurement
guidelines. https://www.procurement.govt.nz/assets/procurementproperty/documents/traditional-delivery-model-construction-procurement.pdf
Fig. 1.1 Contractual relationships of the key stakeholders in a traditional delivery method
© MBIE
Dig deeper
If you would like to read more about the traditional, design, bid, build procurement method,
then you can read this four-page information sheet by MBIE on the Traditional delivery
model–construction procurement.
Next, explore the design and build method.
Thoughts on this page?
RETURN
PREVIOUS: TYPES OF DELIVERY MODELS
NEXT: DESIGN AND BUILD (TURNKEY) METHOD
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.3: Stage 3—Procurement stage : Design and
build (turnkey) method
20m
Design and build (turnkey) method
Design and build delivery method
In the design and build delivery method, the client contracts with the main
contractor who takes responsibility for both the design and construction phases for
an agreed lump sum price.
The client outlines, in detail, their requirements for the building–this information is
then used in the tender process to seek contractors who will bid for both the design
and construction phases of the project.
In this way, the design and build method is sometimes called a turnkey approach
because the client doesn't have to do anything except choose a contractor to do the
design and build, choose a design, sign the contract, pay for the project, then pick
up the key at the end of the construction stage. However, the requirements the
client draws up initially must be detailed and comprehensive to ensure the final
building meets the client's objectives.
When does the design and build method work best?
When:




the client has clear specifications to provide to the design and build
contractor at the time of tender
the client is comfortable giving up design control to the main contractor and
their designers
speed of construction is important
cost certainty at the outset is important.
What are the advantages and disadvantages of the design and
build method?
Table 1.4 Advantages and disadvantages of the design and build (turnkey) method
Advantages
Disadvantages
Speed to completion–construction on site can begin before all detailed design
is complete.
The client must be clear about thei
they get the best outcomes.
Advantages
Disadvantages
There's potential for innovation as the design stage benefits from the
contractor's inputs around the best materials and construction
methodologies.
Sufficient time is needed in the ten
both design proposals and construc
Cost certainty–provided clear functional requirements are provided by the
client at tender.
Cost of tendering is usually higher f
delivery method.
Potentially fewer disputes as the main contractor has responsibility for both
design and construction.
There may also be a smaller pool o
method.
The client is not responsible for cost and time overruns.
The designer is accountable to the
their own design consultants to mo
(MBIE, 2019)
Footnote 1.
MBIE. (2019, October). Design and build delivery model – Construction
procurement guidelines. https://www.procurement.govt.nz/assets/procurementproperty/documents/design-and-build-delivery-model-constructionprocurement.pdf
Figure 1.2 shows the contractual relationships of the key stakeholders in a design
and build delivery model (MBIE, 2019).
Footnote 2.
MBIE. (2019, October). Design and build delivery model — Construction
procurement guidelines. https://www.procurement.govt.nz/assets/procurementproperty/documents/design-and-build-delivery-model-constructionprocurement.pdf
Fig. 1.2 The contractual relationships of key stakeholders in a design and build delivery
model
© MBIE
Variations of design and build
There are variations to the design and build model as outlined here:
Competitive–This is the process described above. Contractors prepare tenders for
both the design and construction proposals based on the client's output
specifications (that is, their detailed requirements for the project).
Develop and construct–The client appoints design consultants to design the
building to a partial stage known as 'scope design'. This is then taken to tender. The
chosen contractor uses their own in-house design consultants to complete the
design and construction work.
Novation–The client appoints design consultants to develop the design to a stage
at which it can be taken to tender. This team of design consultants then transfers
(novates) to the contractor who has won the bid. This variation is seen as a way to
encourage contractors to bid and avoid high design development costs.
Dig deeper
If you would like to read more about the design and build (turnkey) method of delivery, then
read this six-page information sheet Design and build delivery model–construction
procurement guidelines.
Next, you'll explore different types of managed delivery models.
Thoughts on this page?
RETURN
PREVIOUS: TRADITIONAL–DESIGN, BID, BUILD METHOD
NEXT: DIRECT MANAGED MODEL
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.3: Stage 3—Procurement stage : Direct
managed model
20m
Direct managed model
There are different managed delivery models available to a client. For example:


Packaged-based delivery model–with its two alternatives of construction
management and management contracting.
Direct managed delivery model.
You'll look at the direct managed delivery model now and the package-based
delivery model next.
Direct managed delivery model
In the direct managed delivery model, the client directly manages all aspects of the
work, such as coordinating the design development, setting up the site, hiring
equipment, undertaking the project management, being responsible for quality
control.
When does the direct managed delivery model work best?
When:




The client has their own team of designers, quantity surveyors, engineers,
contract administrators and so on, or at least people they can easily contract
to do this work.
The client wants or needs to control all aspects of the project.
The project is small.
Flexibility on scheduling and delivery is required.
What are the advantages and disadvantages of the direct
managed delivery model?
Table 1.5 Advantages and disadvantages of the direct managed delivery method
Advantages
Disadvantages
Can be an efficient process for small projects.
Client retains a lot of risk.
Useful if there are limited numbers of suitable
contractors.
There's no tender price competition, so the client may be
Useful if there are different areas of work that do not
overlap.
A lot of oversight is required and the client may struggle t
sufficient expertise.
Easier to change the design during the construction
phase.
Helps to develop the in-house expertise of the client's
employees.
Footnote 1.
MBIE. (2019, October). Direct managed delivery model – Construction
procurement guidelines. https://www.procurement.govt.nz/assets/procurementproperty/documents/direct-managed-delivery-model-construction-procurement.pdf
(MBIE, 2019)
Figure 1.3 shows the contractual relationships in a direct managed delivery model.
Fig. 1.3 Contractual relationships of key stakeholders in a direct managed model
© MBIE
Dig deeper
If you would like to read more about the direct managed model, then read this two-page PDF
from MBIE on the Direct Managed Delivery Model
Next, find about the package-based delivery model–another type of direct managed
model.
Thoughts on this page?
RETURN
PREVIOUS: DESIGN AND BUILD (TURNKEY) METHOD
NEXT: PACKAGE-BASED DELIVERY MODEL
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.3: Stage 3—Procurement stage : Packagebased delivery model
20m
Package-based delivery model
Package-based delivery method
A package-based delivery model can be one of two approaches, both of which
break down the project into smaller management methods (packages), with the
client employing either a construction manager or a management contractor. These
manage the breakdown of the contract into smaller packages, supervise the
tendering process and manage the contracts.
Construction management approach–In this approach, the client contracts the
trade contractors and suppliers, then the construction manager manages these
resources and each stage of the project.
Management contracting approach–Here, the client employs a management
contractor to contract the trade contractors and suppliers, then manages the
resources and each stage of the project.
Select the white arrows < > at the side of each image to see flow charts
representing the contractual relationships of both these types of packaged-based
delivery methods. Note the different relationships around the construction manager
and management contractor roles.
Fig. 1.4 Relationship of key stakeholders in a construction management, package-based
delivery method
© MBIE
Next
When does a package-based delivery method
work best?
When:


faster project delivery times are required
the project requires specialist services that a single main contractor could
not easily provide




client wishes to maintain control over the design and quality
the client requires expert advice around design and buildability from an
experienced construction manager or management contractor
the client is comfortable not knowing the final price (as each package is bid
and paid for individually)
there is adequate contingency in the budget to accommodate inflationary
costs per package or to prevent a reduction in quality.
What are the advantages and disadvantages of a package-based
delivery method?
Table 1.6 Advantages and disadvantages of a package-based delivery method
Advantages
Disadvantages
The design can be varied with relative ease.
The construction management approach carries more risk fo
contracting approach–as the client appoints the individual co
Management and coordination risk is reduced.
It's a large time commitment for the client–the client needs t
Contract administration is done by the construction
manager or management contractor.
Administrative arrangements are complex as they're renegot
Client maintains a high degree of control.
Uncertainty around final construction costs.
The client owns the risk that the design team can meet the re
management contractor's programme.
Footnote 1.
MBIE. (2019, October). Package based delivery
model. https://www.youtube.com/watch?v=MKc7yYurPis
(MBIE, 2019)
Dig deeper
If you would like to read more about the two different package-based delivery methods, then
read this three-page information sheet on the Package Based Delivery Model.
Next, find out about the early contractor involvement model.
Thoughts on this page?
RETURN
PREVIOUS: DIRECT MANAGED MODEL
NEXT: EARLY CONTRACTOR INVOLVEMENT METHOD
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.3: Stage 3—Procurement stage : Early
contractor involvement method
30m
Early contractor involvement method
The early contractor involvement method (ECI) can be incorporated into either a
traditional model or a novated design and build model, particularly if the client
wants to gain early advice from a contractor about design and buildability.
Rather than complete the design stage to developed design drawings and then put
the project out to tender, in an ECI method there are two stages to tendering.
First stage tender
The first stage tender documents should provide early design information–such as
concept or preliminary drawings–an indication of budget limit and sufficient
project information that the contractor can submit a tender response that covers; for
example, analysis of how realistic the client's budget is, the construction
methodology they would use, how they would manage health and safety, how the
contractor's project team would work with the client's design team, schedule of
rates and so on.
The client's first stage tender documents should also include a pre-construction
services agreement (PSA) that outlines, for the contractor, the services the
contractor should provide during the second tender stage. The PSA will also
contain conditions that the contractor must meet–such as performance standards
and acceptable contract sum. The PSA provides the client with the opportunity to
go back out to tender if these conditions are not met. The PSA also ensures
the contractor is paid for their services so far–this has the added bonus of
preventing later disputes over the use of intellectual property if some of the
contractor's ideas are subsequently used.
Second stage tender
The second stage tender involves the contractor working with the client's design
team to provide input into the design and buildability.
For a traditional delivery method, the client and contractor will agree on how the
project is to be split into work packages and will put out to tender for each
package. Once the client is happy with each package, the contractor is awarded the
contract to proceed to build usually on a lump sum fixed price.
For a design and build delivery model (the novated version), the design will not be
complete at the time of awarding the contract, so the contract sum is arrived at via
negotiation with the client's cost consultant (quantity surveyor) reviewing the
contractor's cost estimates. If the client doesn't want to be involved too much and
accepts the risk that comes with that, the contract may be awarded on a lump sum
fixed price. If the client wishes to have more collaboration with the design team
and contractor, then they may opt for a guaranteed maximum price contract.
When is an ECI model best used?
When:





the project is large and complex
innovative approaches are needed
collaboration will provide value
cost certainty and transparency is needed
flexibility in scheduling and delivery is possible.
What are the advantages and disadvantages of the ECI method?
Table 1.7 Advantages and disadvantages of the early contractor involvement
method
Advantages
Disadvantages
Greater opportunity for optimising the design from a construction
perspective.
Requires strong leadership from the client a
and cost consultants.
Fewer disputes because relationship principles and collaborative
practices are incorporated into the contract.
Open book negotiations are required in the
contractor's rates and margins to be indepe
Greater opportunity for innovation arising from the collaboration.
Competitive tension is present–which can b
Improved cost and time savings.
Earlier procurement of items with long lead times to prepare (such as
steel).
Footnote 1.
MBIE. (2019, October). Early contractor involvement – Construction procurement
guidelines. https://www.procurement.govt.nz/procurement/specialisedprocurement/construction-procurement/construction-procurement-guidelines/
(MBIE, 2019)
Dig deeper
If you would like to read more about the Early contractor involvement method, then read this
three-page information sheet from MBIE on Early Contractor Involvement Construction
Procurement Guidelines.
Next, you'll briefly look at two further (and final) procurement and delivery models
that involve collaboration.
Thoughts on this page?
RETURN
PREVIOUS: PACKAGE-BASED DELIVERY MODEL
NEXT: ALLIANCE DELIVERY MODEL AND PUBLIC PRIVATE PARTNERSHIP MODELS
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.3: Stage 3—Procurement stage : Alliance
delivery model and Public private partnership models
20m
Alliance delivery model and Public
private partnership models
Alliance delivery model
This model is based on collaborative relationships and good faith and trust so that
the decisions made are best for the project, not necessarily based on what's best for
the individual companies involved. It's best for highly complex or large
infrastructure projects as collaborative relationships facilitate innovative solutions.
A good example of the Alliance delivery model is seen in the Stronger Christchurch
Infrastructure Rebuild Team (SCIRT).
Follow this link if you would like to read more about SCIRT's $2.2 billion, five-year
programme of 700 individual projects–the model used, the programme management, people
and culture and construction processes involved.
Public-private partnerships
In a public-private partnership model (PPP), the private sector finances the
project (along with the government), builds the project then transfers control to the
public sector once complete. The details of the partnership vary depending on the
project.
The benefit of a PPP is that it facilitates innovation from the private sector.
In our final page on procurement, you'll look at two common pricing models,
before testing your knowledge and understanding of procurement with some
activities.
Thoughts on this page?
RETURN
PREVIOUS: EARLY CONTRACTOR INVOLVEMENT METHOD
NEXT: COMMON PRICING MECHANISMS
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.3: Stage 3—Procurement stage : Common
pricing mechanisms
3m
Common pricing mechanisms
There are different pricing mechanisms used depending on the level of cost
certainty needed by the client, the level of financial risk the client or contractor is
willing to accept, and the delivery model used.
Common pricing mechanisms are:





lump sum
guaranteed maximum price
target costs
measurement contract
cost-reimbursable contract.
See Fig. 1.6 to compare the pricing mechanism with the degree of financial risk for
the client and contractor.
Then see Fig. 1.7 to see which pricing mechanisms are usually applied to the
delivery model.
Fig. 1.6 Pricing mechanism and risk for client and contractor
© MBIE
Fig. 1.7 Delivery models and commonly associated pricing mechanisms
© MBIE
Lump sum contract
A lump sum contract is the most commonly used pricing mechanism. The contract
price is based on a single lump sum price for all the works agreed between the
client and contractor.
When are lump sum contracts best used?
Lump sum contracts are best used where projects are well defined at the tender
stage so that the contractor can accurately price the project and post-contract
changes are unlikely.
What are the risks with lump sum contracts?
With lump sum contracts, the contractor carries more financial risk–particularly in
a design and build model where the contractor contributes to the design.
While lump sum contracts therefore provide some cost certainty to the client, if the
client wishes to make changes post-contract this will result in a variation entitling
the contractor to add costs.
Inflation may increase the cost of materials and labour over the time of the project.
So, lump sum contracts may include mechanisms to deal with this or the contractor
will include this in their pricing–known as fixed price lump sum (MBIE, 2019).
Footnote 1.
MBIE. (2019, October). Lump sum contract – Construction procurement
guidelines. https://www.procurement.govt.nz/assets/procurementproperty/documents/lump-sum-contract-construction-procurement.pdf
Guaranteed maximum price (GMP)
Guaranteed maximum price contracts arose from the design and build (turnkey)
delivery models where the contractor is involved early and has full control in the
design stage so they can ensure the design is cost-effective. The contractor tenders
their price (GMP) for developing and managing the design and build of the project.
To enable a guaranteed maximum price contract, the client has to be very clear on
their desired outcomes in the information they provide for tendering. The client
also has to know there are suitable contractors with the right expertise to complete
the whole project.
The contractor also has to be able to take on the financial risk.
Any savings made may be shared between the client and contractor.
When are GMP contracts best used?
When:



projects are straightforward or ones with repeatable design elements such as
offices
the client can clearly define their requirements
the contractor is willing and has the expertise to be involved in the design
stage.
What are the risks associated with GMP contracts?
If the client has not outlined all their requirements clearly, any extra information
provided post-contract could result in the GMP being increased (MBIE, 2019).
Footnote 2.
MBIE. (October, 2019). Guaranteed maximum price – Construction procurement
guidelines. https://www.procurement.govt.nz/assets/procurementproperty/documents/guaranteed-maximum-price-construction-procurement.pdf
Next, test your knowledge and understanding of the procurement and delivery
models you've covered in Module 1.
Thoughts on this page?
RETURN
PREVIOUS: ALLIANCE DELIVERY MODEL AND PUBLIC PRIVATE PARTNERSHIP MODELS
NEXT: TEST YOUR KNOWLEDGE ON FACT SHEET 1.3
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.3: Stage 3—Procurement stage : Test your
knowledge on Fact sheet 1.3
30m
Test your knowledge on Fact sheet 1.3
Test your knowledge and understanding about the different procurement and
delivery methods by completing these tasks.
These activities are not marked, but feedback is provided when you submit your
answer.
You may need to refer back to the relevant pages about different methods or
models or use the notes, spreadsheets or flow charts you created.
ACTIVITY 1.4: DELIVERY MODELS AND PROJECT SCALE, COMPLEXITY
AND RISK
Drag and drop the name of the delivery model, closest to the level of
risk/complexity/scale that the model is most suitable for, then Submit your answer.
Level of risk/complexity/scale is as follows:
1. = Low risk
2. = Medium risk
3. = High risk
Traditional-design, bid and build
Design and build (turnkey)
Direct managed
Packaged
Early contractor involvement
1
3
1
2
3
Level of risk, complexity and scale
SUBMIT
ACTIVITY 1.5: DELIVERY MODELS AND OPPORTUNITY FOR
COLLABORATION AND INNOVATION
Which delivery models offer the most opportunity for collaboration and
innovation? Drag and drop the name of the delivery model closest to its level of
opportunity for collaboration and innovation, then Submit your answer.
Level of opportunity for collaboration and innovation:
1. = Low level
2. = Medium level
3. = High level
Traditional-design, bid, build
Design and build
Early contractor involvement
Packaged based
Alliance
1
3
1
2
3
Delivery models and opportunity for collaboration and innovation
SUBMIT
ACTIVITY 1.6: CONTRACTOR INVOLVEMENT AT THE DESIGN STAGE
Which of the following delivery methods involve the main contractor at the design
stage? Select all that apply, then Submit your answer.

Traditional- design, bid, build
Traditional- design, bid, build

Early contractor involvement
Early contractor involvement

Package based delivery method
Package based delivery method

Design and build
Design and build
SUBMIT
ACTIVITY 1.7: DELIVERY METHODS AND LEVEL OF CLIENT CONTROL
Put the following methods in order of the amount of control the client has over the
project. Start with the method which has the highest level of client control first.
Traditional- design, bid, build
Design and build
Direct managed
Package-based
SUBMIT
ACTIVITY 1.8: DELIVERY METHODS AND COST CERTAINTY AT OUTSET
Put the following delivery methods in order of cost certainty for the client at the
outset of the project. Start with the model or method that has the highest level of
cost certainty at the outset, then Submit your answer.
Package-based
Design and build
Early contractor involvement
Traditional- design, bid, build
SUBMIT
ACTIVITY 1.9: CLIENT AND DESIGN
If you were a client and were uncertain what design you'd like for your project,
which procurement and delivery method would you choose? Explain your choice
and give your reasons in the space provided, then Submit your answer.
BOLDITALICUNDERLINE
BULLET LISTNUMBERED LISTALIGN LEFTALIGN CENTERALIGN RIGHT
SUPERSCRIPTSUBSCRIPT
TABLE
0 / 500 Word Limit
SAVE DRAFT SUBMIT
Thoughts on this page?
RETURN
PREVIOUS: COMMON PRICING MECHANISMS
NEXT: STAGE 4–PRE-CONSTRUCTION STAGE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.4: Stage 4—Pre-construction stage : Stage 4–
Pre-construction stage
15m
Stage 4–Pre-construction stage
What is the pre-construction stage?
Between the end of the tender process–when the main contractor signs the
construction contract—and the first day of work on site, there is a long 'to do' list
that needs to be completed by the main contractor and members of their team.
By the time the pre-construction stage is reached, contracts, finance, permits and
consent are sorted.
What happens during the pre-construction
stage?
The construction team is being assembled and every phase of the project is being
planned, scheduled and budgeted for during the pre-construction stage.
Communication processes and expectations are determined.
Materials need to be purchased and suppliers are organised. Some materials have a
long lead time (that is, the time taken to source, produce and supply them), so
some materials may need to be swapped for alternatives due to availability or cost.
The design drawings will be checked. Some design changes may be negotiated at
this stage to streamline the build. Some components may need specific detailed
drawings created and approved to facilitate their assembly.
The main contractor will be awarding contracts to the subcontractors needed for
the construction project.
Sometimes this stage can take just as long as the actual construction. See the
following activity for a more detailed list of pre-construction activities.
ACTIVITY 1.10: PRE-CONSTRUCTION ACTIVITIES
The preparation activities undertaken by the main contractor and their team
comprise a long list. List four types of activities the main contractor must do before
work on site can start. Type your suggestions, then Submit your answer.
If you're new to the construction sector and are not sure, don't worry–have a
go, then review the feedback for more detailed answers. These tasks are not
marked.
BOLDITALICUNDERLINE
BULLET LISTNUMBERED LISTALIGN LEFTALIGN CENTERALIGN RIGHT
SUPERSCRIPTSUBSCRIPT
TABLE
0 / 500 Word Limit
SAVE DRAFT SUBMIT
In case you missed the previous activity, here's a list of some of the many
preparatory activities undertaken by the main contractor, construction manager and
their team in the pre-construction stage.
Preparatory work














identification of hazards on the construction site
plans for mitigating the risks of these hazards and the risks related to the
design itself
development and approval of a health and safety plan
organising of bonds, licences and insurance
establishing a detailed programme of works
setting up a system to track costs
organising a site survey to agree schedules of conditions for adjacent
buildings, where existing services are located and so on
setting up of a site office
procurement of materials and machinery
sourcing and contracting subcontractors
establishing a contact register of subcontractors
devising method statements for how things will be done
establishing inspection and site quality assurance plans
arranging services such as power and waste management for the site.
Next, you'll look at the construction stage.
Thoughts on this page?
RETURN
PREVIOUS: TEST YOUR KNOWLEDGE ON FACT SHEET 1.3
NEXT: STAGE 5–CONSTRUCTION
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents : Module 1:
Overview of the Construction Process : Fact Sheet 1.5: Stage 5—Construction
stage : Stage 5–Construction
1m
Stage 5–Construction
The goal of this stage is to have the structure built to plans and specifications, on
time and within budget in an incident-free project with a satisfied client at the end
of it.
The construction stage starts when the main contractor takes possession of the site
and ends when the building is complete and the site is handed over to the client.
During the construction stage, the client takes a step backward compared with their
level of involvement in the design stage; although they're likely to visit the site to
inspect progress. The client may also appoint a project manager who will:





review the contractor's method statements to ensure they're being
followed
inspect the quality of workmanship
monitor the work carried out
ensure specifications are complied with
ensure health and safety requirements are implemented.
You'll look at six different steps in the construction stage of the process–from
mobilisation to building handover and final completion stage (in Fact sheet 1.6)–so
you have a high-level understanding of the types of activities that occur
throughout.
© Getty Images
Thoughts on this page?
RETURN
PREVIOUS: STAGE 4–PRE-CONSTRUCTION STAGE
NEXT: STAGE 5 STEP 1–MOBILISATION
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.5: Stage 5—Construction stage : Stage 5 Step
1–Mobilisation
1m
Stage 5 Step 1–Mobilisation
What is mobilisation?
Mobilisation is the point at which the construction team is brought together to
prepare for construction.
It cannot take place until the contract is signed. Once the contract is signed, the
contractor has legal access to the site.
Mobilisation meeting
The mobilisation meeting–or the pre-start meeting–is held a couple of weeks
before work on site begins. Its purpose is to establish good working relationships
between those involved in the project, review the requirements and parameters of
the project, establish communication protocols and procedures, and clarify the
roles and responsibilities of all team members.
All relevant parties attend the mobilisation meeting. At the very least, this will
include the client, designer, quantity surveyor, project manager and main
contractor.
Thoughts on this page?
RETURN
PREVIOUS: STAGE 5–CONSTRUCTION
NEXT: STAGE 5 STEP 2A–ON-SITE CONSTRUCTION PHASE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.5: Stage 5—Construction stage : Stage 5 Step
2a–On-site construction phase
10m
Stage 5 Step 2a–On-site construction
phase
In case you haven't yet seen the 'to do' list of preparatory jobs that need to be
carried out by the main contractor before work on site can begin, here they are.
Remember, these occur before the on-site construction phase begins.
Preparatory work














identification of hazards on the construction site
plans for mitigating the risks of these hazards and the risks related to the
design itself
development and approval of a health and safety plan
organising of bonds, licences and insurance
establishing a detailed programme of works
setting up a system to track costs
organising a site survey to agree schedules of conditions for adjacent
buildings, where existing services are located and so on
setting up of a site office
procurement of materials and machinery
sourcing and contracting subcontractors
establishing a contact register of subcontractors
devising method statements for how things will be done
establishing inspection and site quality assurance plans
arranging services such as power and waste management for the site.
Once the mobilisation, planning and preparation work has been complete, work on
site can begin.
Making adjustments
Even with the best-planned construction projects, adjustments–both small and
large–sometimes need to be made to accommodate issues such as:





adverse weather
disruptions in the supply chain
unforeseen design or construction issues
issues with traffic or surrounding buildings and their occupants
human error and miscommunication


client change of plans
accidents.
All construction projects have processes in place to ensure that adjustments can be
made as seamlessly as possible. These processes include regular on-site meetings
and inspections.
On-site meetings
On-site meetings are a must and a consistent feature of any construction project.
The decision about when site meetings will be held and who will attend is decided
during the mobilisation stage. Sometimes site meetings–their frequency and
format–are determined in the contract.
Site meetings
These are formal meetings with agendas and minutes and action points recorded.
These minutes become legal records.
You will look at how to run a meeting effectively in Module 3.
Usually, site meetings are organised on a weekly basis and attended by the main
contractor, design team, client's representative and relevant subcontractors.
However, this depends on the size of the project. On large commercial construction
projects, the main contractor may arrange the main site meeting fortnightly and
smaller subcontractor meetings weekly.
A typical weekly site meeting will include:




a progress report from the contractor
an update on issues related to the availability of materials, labour and
possible delays due to weather or supply issues
a report from the QS on variations and budget costs to date
feedback from the client.
Subcontractor meetings
These meetings are to coordinate the work being completed by the subcontractors
and address any issues. In smaller projects, they may be subsumed into the weekly
site meeting.
These meetings will cover:



requests for further information from other trades by the design team
notification of any changes or adjustments so plans can be made to
incorporate these efficiently
checks on quality control and health and safety.
Toolbox meetings
These are often more informal meetings arranged with workers to provide an
opportunity to talk about issues and plans, particularly around health and safety.
Take a look at this case study video of Wellington Pipelines (Wellington Pipelines
Case Study, 2016) (3:20)
Footnote 1.
WorkSafe New Zealand. (2016, October 17). Wellington pipelines case
study [Video].
YouTube. https://www.youtube.com/watch?v=2SmwDomtLQc&t=1s
to see how they engaged their workers and incorporated a positive health and
safety culture through whanaungtanga (a sense of relationship, like a family). This
approach, instigated through toolbox meetings brought the following benefits:





innovation and practical improvement was driven by worker ideas
excellent worker buy-in
better reporting and site management
productivity benefits
client recognition (WorkSafe, 2017).
Footnote 2.
WorkSafe. (2017, September 4). Tikanga approach to health and safety
builds a stronger business. https://www.worksafe.govt.nz/the-toolshed/casestudies/wepr-case-studies/wellington-pipelines-tikanga
Next, you'll look at another important feature of the construction stage–on-site
inspections.
Thoughts on this page?
RETURN
PREVIOUS: STAGE 5 STEP 1–MOBILISATION
NEXT: STAGE 5 STEP 2B–ON-SITE INSPECTIONS
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.5: Stage 5—Construction stage : Stage 5 Step
2b–On-site inspections
1m
Stage 5 Step 2b–On-site inspections
There are a number of inspections conducted during the construction stage of a
project. Some are routine and some are by specialists assessing specific aspects of
the project.
Table 1.8 On-site inspections
Daily inspections
Weekly inspections
Other inspections
Building control inspection
Who: Main contractor with
subcontractors if needed.
Who: Project team
(design team plus main
contractor and client or
client's representative).
Who: Health and Safety
representative.
What: Checks health and
safety processes are
being followed.
Who: Building Control
inspector.
What: Checks work in
progress, records
completions, checks against
programme of works to
ensure project running to
schedule, within scope and
budget.
What: Checks progress
and quality to ensure
project conforms to
plans, specifications and
consent requirements.
Who: Subcontractors.
What: Inspects materials
being delivered and used.
When: At stages laid down
in the building consent.
Client (or their delegate)
must inform building
consent authority when
stage of work is ready for
inspection.
What: Building Control
inspector confirms work
meets the Building Code an
the consented plans and
specifications.
Thoughts on this page?
RETURN
PREVIOUS: STAGE 5 STEP 2A–ON-SITE CONSTRUCTION PHASE
NEXT: STAGE 5 STEP 3–THE PRE-FINISH OR SNAGGING STAGE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.5: Stage 5—Construction stage : Stage 5 Step
3–The pre-finish or snagging stage
5m
Stage 5 Step 3–The pre-finish or
snagging stage
What is a snag?
A snag is a small defect or problem that remains in a property after the building
work has been completed (New Build Consultants Ltd, n.d.).
Footnote 1.
New Build Consultants Ltd. (n.d.). What is
snagging? https://www.newbuildinspections.com/about-us/what-is-snagging/
The snagging stage
When
The snagging stage, also known as the pre-finish stage, usually takes place about
two weeks before the end date of the contract.
Who
It includes an on-site meeting of the project team; that is, the client, contractor and
the design team. The purpose of the meeting is to identify outstanding work, work
that has not been signed off during regular inspections, or visible minor issues
(snags).
What
The project team looks for unfinished surfaces, work not completed to
specification or good practice (such as scratches, missing hinges and so on), untidy
verges, rubbish not cleared. A snagging list is created of all the 'snags' found by the
team.
The QS or designer, together with the main contractor, agree on the snagging list
and the timeframes by which all the snags or items on the list need to be
completed. The QS must be involved in this process if it's likely to have significant
financial implications.
Once the list is agreed and issued, the items on the snagging list are addressed and
signed off before further invoices from the contractor are processed.
The project can then move to Step 6–the post-construction stage.
Thoughts on this page?
Addressing a snagging list
Have you been involved in a new house build or had renovations
done? Do you work for a construction company and have experience
on-site in construction projects?
Have you been involved in the snagging phase of a project? If so,
describe some snags that were found and what was required to resolve
them.
Please remember not to name any companies or individuals involved
in your discussion.
Write your comment
ADD FILE POST CANCEL
Sort by:
Like
Aaron Cain
01 Apr 2022, 12:12 PM
Vanity drawer handles are often the wrong way around from delivery. It's a simple problem
to solve but takes time.
Adjustment to external doors that don't latch correctly. Again a simple problem that takes
time.
Kitchen benchtops not sealed to walls. A return trip for the joiner.
REPLYREPLY
LIKELIKE
Jennelyn Ould
31 Mar 2022, 6:26 PM
1. uneven painting finishes - touched up by painters
2. damage on floor finishes - rework
3. Cleanliness
REPLYREPLY
LIKELIKE
Matthew Timperley
31 Mar 2022, 1:15 PM
- paint touch ups to walls, door jambs and architraves
- missing door handles or hinges
- smoke alarms not installed
- kitchen cabinetry door or drawers not lining up properly when closed
- marks or imperfections to external fittings eg: spouting and downpipes
REPLYREPLY
LIKELIKE
Leah Warbrick
29 Mar 2022, 1:30 PM
draft behind the kitchen sink
REPLYREPLY
LIKELIKE
Leah Warbrick
29 Mar 2022, 1:30 PM
door not flushed and gets stuck when closed
REPLYREPLY
LIKELIKE
Aneurin Lock
29 Mar 2022, 9:57 AM
Leaking pipe. Plumber to tighten fittings.
Door jamb damage. patch and repaint
REPLYREPLY
LIKELIKE
Barrett Warren-Chapman
27 Mar 2022, 7:07 PM
One snag that we came across during the end of the build was trying to keep the floors,
windows and walls tidy and presentable to the potential buyers (apartment building), while
minor finishing works were still going on
REPLYREPLY
LIKELIKE
Jinzhao Xia
26 Mar 2022, 10:44 AM
hinger screw missing
painting touch up
sillicon is not cleaned on surface
door stops missing
screw or nail pop up
extrior cladding is loose or damaged
REPLYREPLY
LIKELIKE
Jinzhao Xia
26 Mar 2022, 10:43 AM
This item was deleted by Jinzhao Xia.
Replies are now closed.
Peter Borja
26 Mar 2022, 9:17 AM
Garage door not closing properly
REPLYREPLY
LIKELIKE
Toi Pham
24 Mar 2022, 8:42 PM
Concrete residue on exterior wall
Decking to close not draining water
Scratches on interior wall
Tap fittings insecure
Rain water container lid missing, replaced with temporary lid.
REPLYREPLY
LIKELIKE
Julia Croft
23 Mar 2022, 7:39 PM
Sliding door to scullery not working smoothly
Wood panel cladding outside damaged
Rubbish on site
Light fitting in kitchen needed redoing
Concrete path needed resurfacing as large crack in it
REPLYREPLY
LIKELIKE
Rosemarie Holmes
23 Mar 2022, 7:09 PM
Snag list:
Scuffs on the walls from final fit-out. Painter asked to do touch ups.
Door stops not installed, builder asked to install.
Different door locks on a house, joinery company asked to make them the same.
Toilet roll holder install upside down so fixing screws visible, builder asked to fix.
Missing kitchen cabinet doo, kitchen company asked to remedy.
REPLYREPLY
LIKELIKE
David Grant
23 Mar 2022, 8:24 AM
Scratches/dents to surfaces
Glass needed replacement after damage from grinding
Areas of plaster work sub-standard.
Floor tile or carpet damage
Masking tape left on too long leaving residue
REPLYREPLY
LIKELIKE
Ezrah Sanders
19 Mar 2022, 8:17 PM
scratches to finished walls surfaces.
Aircon unit leaking.
Rubbish not removed.
The plastic covering is still on door handles or locks.
The painting was below average.
scuff marks on ceiling tiles.
REPLYREPLY
LIKELIKE
Jeanil Kim
17 Mar 2022, 8:48 PM
a.
b.
c.
d.
leaking roof
missing handles
raised ground level issues
incomplete paintwork
REPLYREPLY
LIKELIKE
Haider Ali
17 Mar 2022, 8:08 PM
Loose-fittings
Poor paint job
Poor installation of tiles
Rubbish
REPLYREPLY
LIKELIKE
Michael Mead
17 Mar 2022, 6:00 PM
- Dented window joinery
- Damaged windows
- Poor paint quality
REPLYREPLY
LIKELIKE
Danial Bin Samsuri
17 Mar 2022, 4:18 PM
-Concrete Ribs were abused and not properly taken care of onsite
-wrong installation hence needed to do extra installation
REPLYREPLY
LIKELIKE
Georgia Ballentyne
17 Mar 2022, 8:19 AM
Unfinished paint jobs - painters would go around and ensure all were finished to a high
standard
door handles not on properly - ensure all door handles are screwed in securely
rubbish left lying around the building - a big clean up done and put into the skip bin
REPLYREPLY
LIKELIKE
Jerome Raagas
15 Mar 2022, 7:17 PM
A good number of scenarios I have seen mostly would be 1. paint finishes, 2. loose electric
switches, 3.poor installation of door hinges, door closer, knobs. 4.Poor install of tiles.
REPLYREPLY
LIKELIKE
Nicola Heighway
15 Mar 2022, 7:52 AM
- spouting leaking as euro tray roofing not installed correctly
- Door handles not installed into cavity sliders
- Cavity slider door being scratched by protruding nail
- Vanities hadn't been sealed with silicon
REPLYREPLY
LIKELIKE
Andrew Cowen
14 Mar 2022, 11:29 AM
Water damage in power sockets. Installation of power cabling and sockets had been
completed before the space was water tight. Water hadn't been noticed at the time, but as the
project was of significant duration rust was showing around the power sockets. Cabling and
power outlets were replaced.
Significant marking on paint work. On a large project with a lot of contractors completing
rework marked or damaged paint finished walls. It was not identified which contractors had
created the marks, so the main contractor had to have the spaces repainted to a finished
standard.
Missing fixtures. Lack of security on site may have lead to items being removed and taken
from site, or they just had not been installed in the first place. The items had to be replaced by
the main contractor.
REPLYREPLY
LIKELIKE
Yufei Wei
14 Mar 2022, 7:24 AM
-Scratches on the wall
-Missing hinges
-untidy verges
-rubbish not cleared
REPLYREPLY
LIKELIKE
Luke Badcock
13 Mar 2022, 10:46 AM
- Marks on walls, paint to be fixed in areas
- Toilet roll holder not installed
- Rubbish not cleared yet
- Missing screws on hinges
REPLYREPLY
LIKELIKE
Lydia Ohuka
11 Mar 2022, 11:20 AM
Missing grout and chipped tiles
Paint flacking over sealant
Scuffs and chipped wood surface on door.
REPLYREPLY
LIKELIKE
Chris Seo
10 Mar 2022, 2:15 PM
Cracked tile.
Gutter is not pitched proper
Shower leaking
REPLYREPLY
LIKELIKE
Jamie Rafferty
09 Mar 2022, 11:29 AM
Snags that have been previously raised:
- Marks on walls and paint to be touched up
- sealing of penetrations
- Resetting of fittings such as electrical outlets to be aligned to be visually more appealing
REPLYREPLY
LIKELIKE
Jennifer Rhodes
05 Mar 2022, 4:10 AM
Cracks in concrete floor
Bad paint and plaster work
Fittings not fixed properly
REPLYREPLY
LIKELIKE
Jessica Thomas
03 Mar 2022, 6:01 PM
paint touch ups
toilet roll holders missing
external taps leaking
hot and cold water around the wrong way
REPLYREPLY
LIKE1
RETURN
PREVIOUS: STAGE 5 STEP 2B–ON-SITE INSPECTIONS
NEXT: STAGE 5 STEP 4–PRACTICAL COMPLETION STAGE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.5: Stage 5—Construction stage : Stage 5 Step
4–Practical completion stage
1m
Stage 5 Step 4–Practical completion
stage
Practical completion stage
Once the contractor has completed all the outstanding work, a final site visit is
held. At this visit, all work is checked. Once everyone has agreed it has been
completed to a satisfactory standard, it's signed off and a practical completion
certificate is issued.
The practical completion stage means that the client is able to occupy and use the
building, perhaps within certain constraints while waiting for some work to be
completed or rectified.
Retention fee
The client holds back a retention fee–usually about 3–5% of the contract sum, or as
specified in the contract–for the duration of the defects liability period. This is an
amount of time–often a year–during which if any defects in the work or materials
are found, the contractor must put them right at their own cost.
You'll learn about this in Stage 6 Step 6 Final Completion Stage, but we recommend you read
Stage 5 Project handover stage first.Step 6—Final completion stage
.
Thoughts on this page?
RETURN
PREVIOUS: STAGE 5 STEP 3–THE PRE-FINISH OR SNAGGING STAGE
NEXT: STAGE 6–POST-CONSTRUCTION STAGE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.6: Stage 6—Post-construction stage : Stage 6–
Post-construction stage
1m
Stage 6–Post-construction stage
In terms of the overall construction process, the post-construction stage is part of
the whole construction process. However, to aid learning we're exploring it as a
separate stage. In this post-construction Stage 6, we've continued with the steps
from the previous construction stage so you'll cover:


Step 5–Building handover stage.
Step 6–Final completion stage.
Step 5–Building handover stage
At the building handover stage, the client is given the keys and takes possession of
the building. The insurance of the building is given from the contractor to the
client.
The contractor gives the client the following documentation:




as-built drawings
code of compliance certificates (CCC)–both for the building and specific
systems within the building, such as active fire protection systems like
sprinkler systems
producer statements from the specialists involved–such as engineers, fire
protection installers, lift manufacturers
operation and maintenance manuals–both for the building and specific
systems within it.
Certificate of public use (CPU)
If the contractor is unable to obtain a code of compliance certificate due to
outstanding work identified by the building inspectors and still to be completed,
then the client is given a certificate of public use (CPU) which allows the building
(if it's a commercial or institutional building) to be used within certain limitations.
Thoughts on this page?
RETURN
PREVIOUS: STAGE 5 STEP 4–PRACTICAL COMPLETION STAGE
NEXT: STEP 6–FINAL COMPLETION STAGE
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Fact Sheet 1.6: Stage 6—Post-construction stage : Step 6–
Final completion stage
1m
Step 6–Final completion stage
Final completion stage–or the defects liability
period
What is the defects liability period (DLP)?
The defects liability period is a fixed period of time during which the contractor
has the right to return to the site to rectify any defects (McIntosh, 2018).
Footnote 1.
McIntosh, M. (2018, August 24). What is the defects liability period
(DLP)? Turtons Blog. https://www.turtons.com/blog/what-is-the-defects-liabilityperiod
Why do defects liability periods exist?
DLPs benefit both contractor and client. Clients want to occupy a building as soon
as construction is finished (practical completion stage), and contractors want the
opportunity to rectify defects or finish incomplete items of work rather than pay
the costs of the client engaging another contractor to conduct the work.
So, the defects liability period provides a compromise–the client can occupy the
building and the contractor can enter to complete any outstanding work.
What happens during the DLP?


The contractor has the right to return to the site to rectify defects or
complete unfinished works.
The client holds the retention fee until defects have been rectified.
How long is the DLP?
It can be anything from three to twelve months. It's usually set at six months,
depending on the size of the project.
Officially, the defects liability period starts after Step 4–the practical completion
stage where the client signs off the work after checking it's completed to a
satisfactory standard and the practical completion certificate issued.
At the end of the defects liability period, the client conducts another inspection of
the site with the contractor, the final certificate is released, and the retention money
is given to the contractor.
What happens to defects outside the DLP?
This depends on the type of contract. Generally, the DLP refers to the time period a
client has to give notice of a defect, not the time required to repair the defect. So,
provided the client has notified the contractor of the defect within the defects
liability period, then the contractor is obliged to fix the defect.
It's vital to check each contract in case variations occur.
Thoughts on this page?
RETURN
PREVIOUS: STAGE 6–POST-CONSTRUCTION STAGE
NEXT: MODULE 1 JOB SHEET
Skip to main content
Notifications
My courses
Overview
Contents
Downloads
Search
Tasks
Notes
New activity
Talk
CON101 Communication in the Construction Industry : Contents
: Module 1: Overview of the
Construction Process : Module 1 Job sheet : Module 1 Job sheet
60m
Module 1 Job sheet
Ka pai! Module 1 has been a big undertaking to cover–even at a high level–the
end-to-end construction process.
To practise what you've learnt, we recommend completing the task in this Job
sheet. It's not marked but will help you prepare for your assessments.
Here, you'll revisit the earlier scenario of the college gymnasium. This is outlined
again below.
Scenario
The new board of trustees for a local high school wants to construct a new,
innovative and complex gymnasium. As a member of the board and as an
architectural designer, you're the most experienced member in construction
procurement and they're looking to you for early-stage guidance.
Because they're a public institution, they require a high degree of transparency in
costs and have a low tolerance to risk or cost fluctuations. A competitive cost is
required by the government. The project is expected to cost around $7.2 million.
Funding is currently secured for $5.9 million. The board has several options to
fund the balance and is not concerned about the shortfall.
Developed design is not yet complete. The project has a tight timeframe as the
board wishes to minimise disruption to the school. All the board members are busy
professionals and are unable to actively monitor or invest time in the building
process.
Their intention is to potentially lease or share ownership of the building with a
private organisation to reduce costs and to make better use of the space, but this is
not yet confirmed. This project will be a focal point for the community and
community stakeholder management is a priority.
They are interested in involving a specialist contractor at an early stage to ensure
the technical aspects of the gym are state-of-the-art. The contractor's involvement
will influence the final set of drawings.
Your brief
As a board member of this college and also an architectural designer who has
worked in the region for a long time, you have many contacts in the design and
contracting space. As a result, you are expected to lead the subcommittee arranging
and overseeing the design and build of the gymnasium.
Your task is to determine the best procurement method for this project.
See further instructions in the task below.
JOB SHEET 1: CHOOSING A DELIVERY METHOD FOR NEW COLLEGE GYM
Given the project brief, decide which procurement and delivery method would be
best for this college gym construction project.
You may find it helpful to use an evaluation spreadsheet. If so, download the
spreadsheet and follow the instructions outlined in the Helpful tool section that
follows this task. It's not compulsory to use this tool for this task.
When you've decided on a method, outline the following as if you were presenting
it to the board.




the delivery method chosen
reasons for choosing this method over others
explain why at least two other methods were considered, but then discarded
describe the next steps the board can expect to take once they've agreed to
this method.
You can choose how you'd present this information to the board. It could be as a:




Word document with paragraphs and bullet points to be read with the
minutes.
Formal report (if you are already familiar with formal report writing).
PowerPoint.
Other apps or software you're comfortable using.
When your information is complete, upload it via the Add file button, then Submit
your answer and compare it with the feedback provided.
ADD FILE
SAVE DRAFT SUBMIT
Helpful tool
You may find it useful to use this evaluation tool for delivery and procurement
method (MBIE. n.d.).
Footnote 1.
MBIE. (n.d.). Delivery model evaluation
tool. https://www.procurement.govt.nz/procurement/specialisedprocurement/construction-procurement/construction-procurement-guidelines/
It's a spreadsheet that allows you to decide weightings for different criteria in your
project's context, then you rank each delivery method in terms of how well it
fulfills each criteria. The spreadsheet automatically calculates the total weighted
score for each method.
The method with the highest weighted score is likely to be the most appropriate
delivery and procurement method for your project.
Step-by-step instructions for use of a spreadsheet
A. On a separate piece of paper, rank the criteria listed in column A in order of
importance for the college gymnasium project.
B. Allocate a percentage weighting for each of the criteria–based on your ranking
in Step A–and put this percentage in column B. The percentages must total 100%.
C. Next, score each delivery method against how well that method fulfills each
criterion. Use a 0–5 scale as follows:
0–Method does not fulfil that requirement.
1–Method might meet some of the requirement but there are significant features of the method that will und
2–Method might meet some of the requirement but there are some features of the method that may undermin
3–Method satisfies the requirement.
4–Method satisfies the requirement and other features of the method enhance this.
5–Fulfilling this requirement is a strong feature of this method.
D. Check the total weighted score shown in row 19 for each method.
E. Do you think the method with the highest weighted score is the most appropriate
delivery and procurement method for the college gymnasium project?
When you've completed this task and considered the feedback, you're ready to
move to Module 2: Construction team roles and responsibilities.
Thoughts on this page?
RETURN
PREVIOUS: STEP 6–FINAL COMPLETION STAGE
NEXT: MODULE 1: REFERENCES
Download