Uploaded by lehaphuong03

Englisch (PDF-Datei 0,7 MB) - Von Roll

advertisement
9th INSUCON International Electrical Insulation Conference, Berlin 2002
NEW MATERIALS AND TECHNIQUES
FOR THE PRODUCTION OF COILS AND ROEBEL BARS
Rudolf Bruetsch, Roger Schwander, Franz Wolf and Marco Naegelin
Von Roll Isola, CH-4226 Breitenbach, Switzerland
INTRODUCTION
The driving force of material and process development
in the insulation technology of rotating high voltage
machines has changed in the last ten to fifteen years.
Being mainly technology driven in the past, cost has
become the determining factor in the industry. Cost
reduction programmes are very popular in the machine
industry and any improvements in products or
processing are only accepted if they reduce overall
cost. On the other hand, high voltage motors and
generators are long-life capital goods and a reduction in
reliability cannot be tolerated. To be successful in the
market any development of new insulating materials
has to reflect these facts.
In the manufacturing process of rotating high voltage
machines a substantial part of the total insulating cost
is related to labour. We estimate that for large
machines the contribution of labour to the total
insulating cost is between 30 and 60 %, the higher
percentages being related to machines where press cure
or single bar VPI technology is applied [1].
In the manufacturing process of large machines the
production and insulation of Roebel transposed bars is
an essential part. Roebel bars are manufactured
according to the following steps:
1 Conductors - usually enamelled and/or single or
double Daglas covered – are cut to the appropriate
length and crimping of the wire is done to form the
crossovers on top and at the bottom of the stack. After
stripping off the insulation at the ends the conductors
are laid together to constitute a half–bar.
this purpose. Figure 1 shows where the materials are
being placed in the Roebel bar.
Insulating or
conductive
mastic
Insulated
conductor
Stack
separator
Conductor
crossover
Figure 1 Placement of insulating or conductive mastic
and stack separator in the Roebel bar
5 Finally both ends of the Roebel bar have to be bent
carefully to form the end winding (Figure 2). This step
is critical for two reasons: Bending has to be done
precisely so that the bars fit perfectly in the stator and it
also has to be done carefully to avoid any damage of
the conductor insulation.
2 A separator is used to bond two half–bars together.
The separator material is a fleece or a fabric
impregnated with a thermosetting epoxy resin. Curing
time needed to ensure mechanical stability of the bar
for further handling is typically ½ hour at 160 °C.
3 At the crossovers of the Daglas-insulated conductors
damage of the conductor insulation may occur during
the mechanical bending of the wire. Therefore mica
chips have to be placed between adjacent conductors at
the position of the crossovers to ensure a reliable
insulation. This is usually done by hand.
4 The gaps on top and at the bottom of the Roebel
bars have to be filled to avoid partial discharge. Mostly
a mastic – non conductive or conductive is applied for
Figure 2 Roebel bar end windings of a hydro generator
All these process steps are labour-intensive and
therefore a significant cost factor in the production of
Roebel bars. In order to respond to the demand of cost
reduction a new range of fast curing products for the
consolidation of Roebel bars and double layer coils
was developed. The main feature of the new products
is a short curing cycle at relatively low temperatures,
which is sufficient to provide mechanical and
dimensional stability of the bar or coil for further
handling. After application and curing of the main wall
insulation the fast curing materials meet class F
requirements.
The application of the fast curing materials can be
automated using new types of equipment for the
production and consolidation of Roebel bars. This
equipment eliminates the application of insulating
chips at the Roebel crossovers. The application of the
mastic is also automated and optimal edge radii are
generated eliminating all finishing work.
FAST CURING MATERIALS FOR
CONSOLIDATION OF ROEBEL BARS
THE
Specifications of the new range of fast curing electrical
insulating materials were chosen to meet the demand
for cost reduction and the technical requirements
related to handling and reliability. Requirements are:
-
All materials based on epoxy binder resin
chemistry to be compatible with all insulating
materials used in practice.
-
Shelf life of ≥ 4 months at room temperature.
-
Fast curing conditions 15 min. at 120 – 130°C
to achieve sufficient mechanical stability.
-
Mechanical stability after fast curing defined
by a glass transition temperature of the
material of ≥ 120°C to allow the next steps of
manufacturing to take place.
-
Thermal class F after full curing together with
the main wall insulation.
The range of the newly developed fast curing products
covers Glasoflex® stack separator materials for the slot
part and a more flexible version for the end parts and
two versions of mastic to fill the gaps in Roebel bars at
crossovers. An overview on the product range is given
in table 1.
TABLE 1 Properties of fast curing electrical insulating
materials for Roebel bar consolidation
Separator
Materials
Glasoflex®
Nominal
Thickness
Total
Weight
Glass Fabric
Glass
Fleece
Resin
Thickness
after Consolidation
Thermal
Class
Mastics
Density
Resistivity
Thermal
class
Unit
For Slot Part
For End
Part
mm
0.35
0.70
1.00
0.40
g/m2
500
480
855
290
g/m2
g/m2
230
-
80
270
2 x 50
50
g/m2
mm
270
0.23
400
0.22
485
0.4
240
0.14
F
F
F
F
Unit
g/m3
Ωm
Non Conductive
1.55
∞
F
Conductive
1.55
< 50’000
F
pation curve. The glass transition temperature of the
separator materials was determined as a function of
curing time and temperature applied. Results are shown
in figure 3.
Glass Transition
Temperature (°C)
180
170
160
150
140
130
120
Test results
The mechanical stability of the separator material can
be expressed by the mechanical dissipation factor and
the glass transition temperature. Dynamic mechanical
analysis (DMA) was used to measure the mechanical
dissipation factor at a frequency of 1 Hz. According to
IEC 61006 the glass transition temperature is defined
as the temperature of the peak of the mechanical dissi-
0
1
2
3
4
Curing Time (hours)
Curing at 120°C
5
6
Curing at 160°C
Figure 3 Glass transition temperature of fast curing
stack separator materials in function of curing time and
temperature according to IEC 61006
The results show that after an initial curing of 15 min.
at 120°C a glass transition temperature of 153°C is
obtained which is sufficient to ensure mechanical
stability for further handling of the Roebel bars. During
the curing cycle of the main wall insulation – which is
usually done at 160°C – the separator material will
fully cure; the corresponding values of the glass
transition temperatures are 168°C after ½ hour and
169°C after 1 hour at 160°C.
To ensure reliable longterm thermal ageing properties
the temperature index of the separator materials was
determined according to IEC 60216. Measurements of
weight loss and flexural strength were made at
temperatures of 180, 200, 220 and 240°C. The
temperature index was determined for 10 % weight
loss of organic matter and 50 % of loss of flexural
strength. Results are given in figure 4.
The manufacturing centre consists of the following five
main units:
Time (h)
100’000
Flex.Strength
Temp. Index
= 159 °C
Figure 5 Manufacturing centre for automated
production of Roebel bars
Weight Loss
Temp. Index
= 168 °C
Straightening-, stripping- and cutting- machine
The machine is capable to process single solid or
hollow conductors. Conductors are automatically cut
and straightened and the insulation is stripped off at the
conductor ends.
10’000
1’000
Crimping unit
100
0.24
0.23
0.22
0.21
0.20
Temperature (10-2/K)
0.19
Figure 4 Determination of the temperature index of
fast curing separator materials according to IEC 60216
In the crimping unit the individual conductors are
shaped at one or both sides. Crimping is done 3dimensionally so that the conductor insulation remains
intact and no mica chips have to be placed between
conductors at the position of crossovers. This unit is
also supporting the trend from 360°- towards 540°- and
720°-Roebel bars to minimize electromagnetic losses
in the stator.
Buffer unit and assembling table
NEW PROCESS EQUIPMENT FOR
CONSOLIDATION OF ROEBEL BARS
THE
To meet the demand for cost saving and to use the
potential of fast curing materials in the production of
Roebel bars a manufacturing line was developed which
enables automated production of Roebel bars (Figure
5).
After the forming process the conductors are laid in a
magazine with a tilting system to constitute a half-bar.
According to the chosen option, the half-bars are either
manually unloaded on an assembling table or
automatically unloaded on a storage conveyor. The
manual braiding of the conductors to half-bars is a very
easy operation due to the 3-dimensional crimping. Two
half-bars are then joined and a fast curing stack
separator is inserted to form the complete Roebel bar
(Figure 6).
bars are ready for the application of the mainwall
insulation.
Forming the end windings with the bar forming
machine
The last step in Roebel bar production before applying
the main wall insulation is the forming of the end
windings at both ends of the bar. End windings are
automatically bent by the new bar forming machine
(Figure 8). It is equipped with 21 numerical axes
resulting in a tolerance of the bending of ± 0.2 mm.
Time needed for forming both ends of one Roebel bar
is approx. 2½ minutes.
Figure 6 To half-bars on the assembling table before
joining to a Roebel bar
Protection taping and insertion of fast curing mastic
The fast curing mastic is applied in tape form. The
dimensions of the cross-section of the mastic tape have
to be selected to give an optimal filling of the gaps at
the Roebel crossovers. The mastic tape is covered by a
release film on the outer side and after application on
top and bottom of the Roebel bar it is fixed by a shrink
film taped around the bar. All these process steps are
done automatically by this unit (Figure 7).
Figure 8 Bar forming machine, version for hydro bars
CONCLUSIONS
Significant cost reduction can be achieved in the
production of coils and Roebel bars for rotating high
voltage machines by applying new insulating materials
and new techniques. The combination of a new range
of fast curing insulating materials for the consolidation
of bars together with a new highly automated
production line which eliminates all labour–intensive
manufacturing steps results in a considerable saving of
time and cost. Large original equipment manufacturers
have installed this equipment and time reduction
realized in the production of Roebel bars is up to 80 %.
Figure 7 Unit for applying insulating or conductive
mastic and protection taping
After that the Roebel bar is ready for curing the
consolidating materials. Since the stack separator and
the mastic are both fast curing, the curing cycle needs
only a holding time of 15 minutes at 120°C. Then the
taped shrink film and the release film can easily be
removed. The faces and edges of the cured mastic need
no finishing, after forming the evolvents the Roebel
References
[1] Allison, J., Bruetsch, R. and Thaler, T. ”Factors
Determining Cost and Quality of the Electrical
Insulation in the VPI Process”, IEEE International
Symposium on Electrical Insulation, Montreal,
Canada, June 1996, pp. 259-262.
Download