Uploaded by mohammedamerk1

JSA BUT Lifting and installation skid

advertisement
Job Safety Analysis Worksheet
Short Descriptive Title of Task:
JSA No.: CMIT-F.W.-JSA-BUT-008
LIFTING AND
INSTALLATION OF THE BIG
PARTS OF SKIDS
■ New
Revised
Reviewed
Existing procedures, guidelines or other procedures that apply:
PTW required and
No.:
Special Training Certificates
required:
Work Location: BUT
Area Authority:
Oilfield manager Approval:
1. Sequence of Basic
Task Steps
1.Lifting preparation
2. Potential Hazards
1.
2.
3.
Analysis Review
(New/Change): NEW
Subject Matter Expert Review:
PPE (example: respirator, gloves, special footwear, harness, etc.) and
special ER facilities, equipment and supplies needed.
Gloves、helmets、safety goggles, safety shoes
Simultaneous work underway:
3. Recommended Action or Procedure
Crane and sling have defects, 1.
Communication gap
2.
Personal injury
3.
4.
5.
6.
7.
8.
9.
Get the PTW.
Hold the tool-box meeting before starting the job.
Keep all tools and other equipment out of walkways and working surfaces, Clear
work area from any obstruction.
Isolate the working site using the warning tape and keep the non-related people out
of the working site.
Check the crane should be inspected and certified.
Riggers should be qualified.
The used lifting gears shall be inspected and related certificates shall be reviewed by
lifting commander.
lifting gears and shackles shall be inspected and Crane inspection 3rd party
certificate and lifting gears 3rd party certificate shall be available on site (photo copy
shall be not accepted)
Before starting lifting, the crane Operator and lifting commander(rigger) should have
brief meeting at lifting site (know the lifting signals and work scope)
1
4. person in charge
. Haleem
Abd AL-kaeem
Mohammed K
TEL:
07800019820
1.
2.
2. Lifting
1.Crane damage.
2.Cargo damage.
3.Finger crushed.
4.Load falling.
5.Caught between load and
crane/structure.
6. Outrigger losing stability.
7.Structural damage.
8.Buildings, equipment
damage by carne boom.
9.Hoisting equipment
breakdown.
10. Poor or lack of
communication.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
3. Skid Installation
Sand Removal / Fiber Ball
1.Hand injury / Finger crushed
2.Falling from heights.
3.Caught between skid and
structure/ground.
4.Slip and trip.
5.Falling from same level.
6. Bruising.
7.Equipment damaged by
contact with skid.
8.Skid damaged during
installation.
Prepare PTW for this activities and have them sign by relevant departments.
TBT+JAS to all involves workers. Lifting operation to be explained in advance to all
workers.
Lifting Plan available and approved by all PMC,Contractor and FCD.
Training and qualifications of operator valid/update and appropriate for this job.
Check by PMC, contractor and WTP HSE crane technical conditions, outriggers
extensions and hoisting equipment – before actual lifting start.
Check slings, taglines and shackles for internal and/or external damages. Should be under
validation time.
Perform lift test for heavy equipment, in a safe area.
Barricade lifting area and check wind speed (10.8 m/s), before lifting. Create exclusion
zone for pedestrians. Post warning signs.
Prohibit lifting during foggy and/or rainy weather.
Designate lifting coordinator and rigger in charge of this lifting. Have them dress in
distinctive colors.
Only one person is communicating with crane operator. Apply communication methods.
Prohibit to stand and/or walk under the load during lifting. Provide tag lines for direction
of the load.
Ground area used by the crane should be level, compacted and no underground
pipes/cables located under the crane surface.
During lifting is prohibit that load and/or boom pass over live CPD facilities (pipes,
vessels, reactors etc.). Avoid SIMOPS activities at all time.
Emergency Units (fire truck, ambulance) stand by for intervention in case that lifting is
failing.
Supervision at site all time from HSE and Civil Department.
1.
2.
3.
4.
5.
6.
7.
Prepare PTW for this activity and have them sign by relevant departments.
TBT+JAS to all involves workers.
Provide full PPE for all workers involved in this operation.
Barricade work area and place warning signs during this installation.
Supervision at site all time from HSE and relevant department.
Skid should be proper secured on his position before installation work start.
Follow design from drawing in order to prevent any malfunctions, that could jeopardize
worker’s life.
8. Provide safety harness is necessary to perform working at height.
9. Avoid SIMOPS activities, during skid installations.
10. First Aid Kit on site – and Emergency units (ambulance, fire truck) if is necessary.
2
. Haleem
Abd AL-kaeem
Mohammed K
TEL:
07800019820
. Haleem
Abd AL-kaeem
Mohammed K
TEL:
07800019820
4. Housekeeping
1.Back pain.
2.Slip and Trip.
3.Falling from same level.
4.Hand injury.
5. Bitten by venomous
animal/insects.
1.
2.
3.
4.
Move all materials, tools, equipment and waste out of CPD area, when work is
completed.
Make sure that no materials, tools and/or equipment was left behind.
Maintain fix barricade in area, if situation is required. Post warning signs.
Garbage bags resulting from housekeeping to be loaded in trucks and removed from CPD
area.
All the staffs working on the site ensure to be familiar with the details above, and follow the instruction.
SIGNATURE:
3
. Haleem
Abd AL-kaeem
Mohammed K
TEL:
07800019820
4
Download