EC
er
ty
of
D
Overview of the FIDIC
FORMS OF CONTRACT
Pr
op
Michel francis
Chief Architect, LEED AP, PQP
Lecturer
History
Founded in 1984
In Abu Dhabi since 1995
of
D
•
•
EC
DEC Introduction
Our Services
Building & Infrastructure Design and Engineering
•
Project Management
•
LEED & Estidama Consultancy
•
Oil & Gas Fields Services
•
Specialized Engineering Services
Pr
op
er
ty
•
EC
FIDIC TRAINING
of
D
3FOLD DUCATION
http://3foldtraining.com/
3 DAYS TRAINING
•
DETAILED ANALYSIS OF THE FIDIC FORM OF CONTRACTS
•
PROJECT MANAGEMENT UNDER FIDIC CONTRACTS
•
CLAIMS MANAGEMENT AND AVOIDANCE
•
CASE STUDIES
•
AVAILABLE IN ABU DHABI AND DUBAI
Pr
op
er
ty
•
EC
About FIDIC
Pr
op
er
ty
of
D
FIDIC - International Federation of Consulting
Engineers
Founded in 1913
Charged with promoting strategic
Membership covers 98 countries
Publishes international standard forms of contracts
Publishes business practice documents
Organizes annual conference and seminars
FIDIC OBJECTIVES
Pr
op
er
ty
of
D
1. Be recognized
2. Promote ethics and integrity
3. Maintain representation
4. Enhance image
5. Promote development
6. Promote FIDIC Forms of Contract
7. Improve and develop training
8. Encourage Young Professionals
EC
About FIDIC
EC
The 1999 Suite of Standard Conditions of Contract
of
D
• Conditions of Contract for Construction - design by
Employer: The Construction Contract (Red Book)
er
ty
• Conditions of Contract for Plant and Design-Build - design
by Contractor: The Plant and Design/Build Contract
(Yellow Book)
op
• Conditions of Contract for EPC Turnkey Projects: The
EPC/Turnkey Contract (The Silver Book)
Pr
• Short Form of Contract: The Short Form (The Green
Book)
EC
Why the FIDIC Forms
Risk allocation
Compensation and time extension
Engineer
Pr
op
er
ty
of
D
EC
Principles behind the 1999 Books
Consistancy
Clarity
Balance
Law compatibility
Prepared by Engineers
Role of Engineer
Employer Representative
Priority to WORK
Financial Management
Suits Local and International Law
Adjudication
er
op
Pr
ty
of
D
Principles
of
D
EC
Distinction between the Books
Pr
er
op
• Risk?
ty
• Design?
op
er
ty
Who does the DESIGN
Competitive TENDERING
RISK balance
CLAIMS follow procedure
ENGINEER no longer ‘impartial’
Pr
of
D
EC
The 1999 Red and Yellow Books
ty
Pr
er
EC
Design by the Employer
Need modern multi-discipline
contracts
Partial Contractor design possible
Payment based on remeasurement
DAB instead of Engineer Decision
op
of
D
The 1999 Red Book
EC
of
D
The 1999 Yellow Book
payment based on lump sum
er
op
DAB instead of Engineer Decision
Pr
ty
For E&M plant, & Designed by the
Contractor
Multi-discipline contracts recognised
Partial Employer design
EC
The Silver Book (EPCT Contract)
E & M and Plant
All Types of Employers
Civil law jurisdictions
Fixed price and two-party approach
Pr
op
er
ty
of
D
More certain price and time
Contractor covers most risks
Employer pays more
Completely new Book - ‘unbalanced’ risk
Suitable for:
op
er
ty
of
D
Design by Contractor
Employer’s Requirements functional basis
Contractor carries out all EPCT
No Engineer
Lump Sum Price
Thorough Testing
Contractor carries risks, so Employer pays more
Final price and time more certain
Small number of tenderers
Contractor uses own methods
Has to prove reliability and performance
Pr
EC
Special Features of the Silver Book
EC
Silver Book Not Suitable when…
Pr
op
er
ty
of
D
insufficient time or information
underground work
Employer supervision
Intermediary party
Partly designed by Employer
public bidding
GO FOR P&DB (yellow book) instead
op
er
ty
of
D
US$ 500,000 and 6 months
Simple works
15 clauses
Simple Language
Balanced risk
No Engineer
Design by either party
All types of construction
Payment method varies
Pr
EC
The Green Book (Short Form of Contract)
EC
Dredging and Reclamation
Pr
op
er
ty
of
D
Design by Employer or Contractor
Valuation – all main methods
available
Engineer to act “fairly”
No defects liability on dredging
Special insurance provisions
Adjudication by DAB first
of
D
EC
Red Book MDB Harmonised Version
Pr
op
er
ty
Based on 1999 Red Book
Changes required by MDBs
Use subject to special licence
op
er
ty
DBO (Gold Book), First Edition 2008
Assumes ~20y operation period
Modern approach to risk and insurance
Employer’s Representative
Adjudication by DAB first
Pr
of
D
EC
Design, Build and Operate Projects
of
D
EC
Subcontracts
Pr
op
er
ty
Conditions of Subcontract for
Construction, 1st Edition 2011
Intended for use with 1999 Red
Book
General Conditions – Particular
Conditions
Annexes require provision of
relevant information
EC
of
D
Consultant Agreement
Pr
op
er
ty
Client-Consultant Agreement
(White Book), 4th Ed 2006
Intended for use for Feasibility,
design, administration and PM
Intended for international use but
adaptable for domestic use.
of
D
(FIDIC GREEN BOOK)
EC
Which Format
ty
(FIDIC GREEN BOOK)
er
(FIDIC RED BOOK)
Pr
op
(FIDIC YELLOW BOOK)
(FIDIC SIVER BOOK)
EC
Structure of the 1999 FIDIC contracts
The main clauses:
• General
Cl 2 – 4
• The Parties & the Engineer
4Cl 5 – 7
of
D
Cl 1
• Sub, staff, labour, materials, workmanship, quality (testing)
• Time
Cl 9 - 11
• Testing, taking-over, defects liability
Cl 12 – 14
• Measurements, variations and payment
Cl 15 and 16
• Termination
Cl 20
er
op
Pr
Cl 17
ty
Cl 8
• Risks, Insurance and Force Majeure
• Claims and disputes
EC
of
D
Pr
op
er
ty
Main Parties to the Contract and
Responsibilities
Pr
op
er
ty
of
D
The basic (typical) contract layout
EC
Structure of the 1999 FIDIC contracts
of
D
EC
Main Parties to the Contract and Responsibilities
Pr
op
er
ty
The Employer
of
D
EC
Main Parties to the Contract and Responsibilities
Pr
op
er
ty
The Contractor
of
D
EC
Main Parties to the Contract and Responsibilities
Pr
op
er
ty
The Engineer
EC
of
D
Pr
op
er
ty
FIDIC PROJECT SETTING
EC
Programming of the project – set your aim
of
D
What are the answers to Project Considerations
And thus, what Project Strategy does this generate?
Pr
op
er
ty
Project Strategy
The answers to this should form a solid base for
which delivery methods and contract forms to use.
EC
Choice of Delivery method – type of contract
• Construction and Sub-Contractor
• Construction (MDB)
• Plant, Design & Build
• Turn Key (EPC)
• Dredging
Pr
• Client/Consultant
• Joint Venture
• Sub-Consultant
• Representative
Form of contract for works:
op
Model agreements for
professional services:
er
ty
of
D
Use the appropriate Delivery Methods:
Form of contract for works
and operations:
• Design, Build & Operate (DBO)
EC
Choice of Delivery method – type of contract
YES
of
D
Contract Preparation: Choice of appropriate form
GREEN BOOK
STRAIGHTFORWARD?
RED BOOK
ty
YES
EMPLOYER DESIGN?
op
CONTRACTOR
DESIGN
NO
PLANT AND/OR HIGH
RISK?
Pr
NO
er
YES
NO
YELLOW BOOK
Fixed price,
YES
Little employer
involvement,
No major
unforeseen
risks?
NO
SILVER BOOK
DISCUSS IN DETAIL
EC
Choice of Delivery method – type of contract
Pr
op
er
ty
of
D
Construction contract vs. Design-build contract
The Contractor’s role regarding the designs
EC
of
D
Pr
op
er
ty
Contract documents as per FIDIC
op
er
ty
of
D
Contract Agreement (Contract Form)
Letter of Tender (Tender Form)
Appendix to Tender
Conditions of Contract
Specifications (Red Book) / Employer’s Requirements (Yellow Book)
Drawings
Bill of Quantities (Red Book) / Schedule of Payments (Yellow Book)
Any other document forming part of the Contract (Addenda, Q/A)
Pr
EC
Contract documents as per FIDIC
EC
of
D
ty
Pr
op
er
Payment Under FIDIC
of
D
EC
Payment Contract Documents as per FIDIC
er
ty
Bill of Quantities (Red Book)
Pr
op
Schedule of Payments (Yellow Book)
EC
of
D
ty
Pr
op
er
Claims Under FIDIC
op
of
D
ty
er
Scope in FIDIC
Recognition
Provisions
Requirements
Pr
EC
Claims under FIDIC
op
er
ty
of
D
Identify actions that caused it
Identify entitlement in cost or time
Establish link to contract
Create support by documentation
Base on project schedules
Create Cause and Effect links
Pr
EC
Contractor Claim
EC
Employer Claim
to
er
ty
of
D
Employers are entitled
claim. Example: Rejection
Pr
op
Procedure for Employer claim
EC
of
D
Pr
op
er
ty
Claim Settlement Procedure
EC
CLAIM SETTLEMENT PROCEDURE
ty
of
D
FIDIC Specifies multi-tier
op
er
Cost goes up with tier level
Pr
Early resolution is best
EC
CLAIM SETTLEMENT PROCEDURE
of
D
Tier 1: Engineer Determination
er
ty
Tier 2: Dispute Adjudication Board
op
Tier 3: Amicable Settlement
Pr
Tier 4: Arbitration
EC
of
D
Pr
op
er
ty
The Dispute Adjudication Board
EC
THE DISPUTE ADJUDICATION BOARD
of
D
DAB in Practice
What is a Dispute Board (“DB”)?
op
Must be independent
er
Consists of 1 or 3 persons.
ty
For duration of Contract
Must have access to project
Pr
Decision Binding
Stats Source: DRBF
op
Pr
ty
er
Case Studies
EC
of
D
EC
Case Study 1
of
D
Joint Operation/Administration of multiple
FIDIC Forms – A Case Study
er
ty
Red Book: Construction of Works
design by the Employer or ‘build
only’ contract forms.
Pr
op
Yellow Book: Construction of Works
design by the Contractor or
‘Design-Build’ contract forms.
EC
Case Study 1
of
D
Joint Operation/Administration of multiple
FIDIC Forms – A Case Study
er
ty
Civil Works Contractor (“CIV”):
construction of the civil works
Pr
op
Electrical and Mechanical Works
Contractor (“E&M”): design and
construction of the electrical and
mechanical works
EC
Case Study 1
of
D
Joint Operation/Administration of multiple
FIDIC Forms – A Case Study
ty
E&M delay that had a bearing on CIV
er
Recovery plan included temporary civil works
E&M not required to do it under contract
op
Engineer instructed CIV to carry out works
Pr
E&M proceeded with his obligation afterwards
EC
Case Study 1
of
D
Joint Operation/Administration of multiple
FIDIC Forms – A Case Study
er
ty
CIV presented invoice that
Engineer forwarded to E&M
op
E&M refused to reimburse
Pr
Engineer acted within the
ambit of
EC
Case Study 1
of
D
Joint Operation/Administration of multiple FIDIC
Forms – A Case Study
Pr
op
ED was issued under
Cl 3.5 & Cl 2.5
er
Notice of Employer
Claim in Cl 2.5
ty
No direct deduction
in Cl 14.6 (IPC)
ED stated that E&M was liable &
direct deduction in next IPC
EC
Case Study 1
of
D
Joint Operation/Administration of multiple
FIDIC Forms – A Case Study
er
op
Engineers issues ED
pursuant to Cl 20.1
and Cl 3.5
ty
CIV claim under Cl 20.1
Pr
Employer Liable to
reimburse
EC
Case Study 2
of
D
Misunderstanding of FIDIC contract
A Case Study
Pr
op
er
ty
March 2013 J Murphy & Sons
contracted with Beckton Energy
Ltd to design and build a
Combined Heat and Intelligent
Power Plant at Beckton East
London. Contract worth £50m.
Source
EC
Case Study 2
of
D
Misunderstanding of FIDIC contract
A Case Study
ty
The completion date set for 31 January 2015
op
er
Contractor delay of 409 days, Engineer not
granting any EOT
Liquidated damages £8,274,000
Pr
EOT Application late in FIDIC context
Use of the Yellow Book
EC
Case Study 2
of
D
Misunderstanding of FIDIC contract
A Case Study
ty
In FIDIC notice should be given ASAP. Failure entails loss of right
er
Good management system ensures timely submission
op
Resolution with DAB could have been used to avoid problems
Pr
Awareness of the FIDIC forms is essential
EC
of
D
Pr
op
er
ty
Best Practice For Claim
Avoidance
EC
BEST PRACTICE FOR CLAIM AVOIDANCE
of
D
Claim Atmosphere
Claims should be handled by experts.
er
ty
Use tools to identify problems.
op
Contracts drafting.
Pr
Construction management practices
EC
Case Study 3
of
D
Gemasolar - a Case of Success
A Case Study
Pr
op
er
ty
Gemasolar first thermosolar plant to
produce electricity 24 hrs (Spain)
Owners: Sener & Masdar in DBO
Operator: Torresol
Contractor: UTE C.T. Solar Tres & others
Contract Type: DBO / EPCT
Won the FIDIC award for best engineering
project in 100 years
EC
of
D
ty
Pr
op
er
Legislations: The Case of UAE
EC
LEGISLATIONS: THE CASE OF UAE
of
D
Civil Law based on Islamic Sharia
Contracts: Federal Law 5 of 1985
ty
Notable Articles:
Article 106 Abuse of Rights
Article 246 Good Faith
Article 249 Power to adjust oppressive contractual obligations
Articles 872 to 896 Muqawala (Job) Contracts
Pr
op
er
EC
of
D
ty
Pr
op
er
Thank You
Michel francis