Uploaded by Suraj Shambharkar

Scope of Work AOPMT

advertisement
ONSHORE
ENGINEERING
SERVICES
NEW DELHI
SCOPE OF WORK
(MOBILE BASED ONLINE PROJECT
MONITORING TOOL)
SCOPE OF WORK
FOR
MOBILE APPLICATION BASED ONLINE PROJECT
MONITORING TOOL
(A.O.P.M.T)
Version 1.4
ONSHORE
ENGINEERING
SERVICES
NEW DELHI
SCOPE OF WORK
(MOBILE BASED ONLINE PROJECT
MONITORING TOOL)
Table of Contents
1. Project Planning & Monitoring Process
2. Requirement of Licenses
3. Requirement of Primavera Expert
4. Visits
5. Experience
6. Road Map for Implementation
7. Terms & Conditions : Mobile Application Based Online Project Monitoring
Tool (AOPMT)
ONSHORE
ENGINEERING
SERVICES
NEW DELHI
SCOPE OF WORK
(MOBILE BASED ONLINE PROJECT
MONITORING TOOL)
1. Project Planning &Monitoring Process (As applicable, but not limited to)
i.
The A.O.P.M.T proposes to provide real time visibility during execution at task level
for both parties (ONGC & LSTK Contractor) to see what is happening on the ground.
ii.
Review mechanism is enabled on the mobile phone and most project deadline
impacted information is available on the phone in real time without any intervention.
iii.
The Successful bidder will procure product/tool licenses for ONGC and should
include latest working version of Primavera EPPM Version 8.1 with web service
access (on the cloud) with compatible mobile based application licenses as a bundle
viz. Hawk-Eye etc.
iv.
A.O.P.M.T should have:
a. A Simple User Input Interface so that LSTK authorized person can update
the project progress on a daily basis without much effort and any extra
expertise.
b. An in built mechanism so that any stakeholder/authorized can get
prioritization on their task list including those task which are slipping and
will impact the project deadline.
c. Be able to provide a prioritized view only for those tasks that are allocated
to a certain user.
d. Ability to depict/demonstrate the current duration of project’s task level
date slippages/delays & current project bottlenecks at any point in time.
e. Ability for any line manager to see all tasks of their subordinates.
f. Application should have been running in India on any large EPC project
(project budget Rs 100 Crs. or higher) with at least 50 licenses issued.
v.
The procured licenses will be shared among ONGC Project Team, E.P.M.C/T.P.I &
LSTK Contractor in order to have a real time visibility during execution at task and
update and monitoring accordingly. However, the distribution of licenses will be at
the sole discretion of ONGC.
vi.
As a part of planning package, LSTK contractor will build and shares a task level
schedule in consultation with Primavera Expert of A.O.P.M.T Vendor.
vii.
The finalized and duly approved planning package needs to be mapped in A.O.P.M.T.
The application should be compatible with smart phones having Android version 5
(Lollipop) & above and iOS version 7.0 and above.
viii.
Task Owner will update every task in progress every day like no of days remaining
to complete the required task. In addition, task owners will also timely update ‘start
ONSHORE
ENGINEERING
SERVICES
NEW DELHI
SCOPE OF WORK
(MOBILE BASED ONLINE PROJECT
MONITORING TOOL)
task’ and ‘finish task’ in real time or at the earliest. This data will flow directly into
the application.
ix.
The application will run a “Reschedule” process every midnight taking in all the task
progress reported for the day. The next day all users will receive updated task
priorities.
x.
Task progress data flowing daily from LSTK Contractor authorized representative the
source data from the contractor is the only data that would be used. If TPI feels data
is incorrect even then the contractor is the one who corrects the data and not the
TPI. This ensures contractor is always in control of what is being reported and
recorded in Primavera.
xi.
Information should be available at macro level (impact on project deadline) as well
as micro level if needed (which task and who needs what help to help expedite), by
tapping the screen. Therefore, what owner sees is identical to what contractor sees.
xii.
Re-Scheduling &re-planning (if needed) of the complete project plan which will be
mapped to A.O.P.M.T.
xiii.
A.O.P.M.T tool should have Virtual Support Helpdesk (access by email / phone /
Skype). Support in English & Hindi.
The above methodology should ensure:
 Development of a Comprehensive & Reasonable Project Plan.
 Continuous & Activity Based Monitoring of Entire Project Plan. (D&E
to Commissioning).
 Ready Repository of deviations in Project Plan (Planned vs Actuals
Start / End Date in Project Plan).
2. Requirement of Licenses:Number: 50 tokens
Time Duration: 36 months
ONSHORE
ENGINEERING
SERVICES
NEW DELHI
SCOPE OF WORK
(MOBILE BASED ONLINE PROJECT
MONITORING TOOL)
Category of Users located at multiple locations:
Client
OES-Delhi
Work Centre
EPMC/TPI
LSTK Contractor
3. Requirement of Consulting Services:
In order to ensure that a reliable and comprehensive project plan/schedule, detailing
all major activities is in place in the planning package which will ensure that project
monitoring on real time basis is achieved.
Services of Primavera Expert will be utilized at various stages of finalization of planning
package in consultation of key stakeholders.
4. Visits:
One Primavera Expert will be required to visit OES Delhi & respective ONGC Work
Center (as and when required) during various stages of finalization & implementation of
Planning Package.
Stage
Activity
Remarks
Stage 1 Preparation up Planning Package
During the stage Primavera Expert
(to be completed within 15 Days from NOA)
along with LSTK Contractor’s Planner
needs to Visit OES Delhi as and when
required. Concluding meeting to be
held @OES Delhi.
Stage 2 Firming up Planning Package with
During the stage Primavera Expert
WorkCentre’s Inputs (to be completed along with LSTK Contractor’s Planner
within 30 days from NOA )
needs to Visit ONGC Mehsana as an
when required. Concluding meeting
to be held @ONGC Mehsana.
Stage 3 Finalization & Submission of PlanningDuring the stage Primavera Expert
Package(to be completed within
along with LSTK Contractor’s Planner
45 days from NOA
needs to Visit OES Delhi as an when
required. Concluding meeting to be
held @OES Delhi.
5. Experience:
S.No Category
1
Primavera
Expert
Qualification & Experience
Aiding &Advising during planning, scheduling & re-planning (if
needed)of the complete project plan using Primavera.
The expert must have successfully implemented two (2) Primavera
based project planning in Hydrocarbon/ Petrochemical sector.
ONSHORE
ENGINEERING
SERVICES
NEW DELHI
SCOPE OF WORK
(MOBILE BASED ONLINE PROJECT
MONITORING TOOL)
6. Road Map for Implementation
Stages for Finalization of Project Plan (PP)
 Stage 1: Preparation of PP by LSTK Contractor as per details above.
 Stage 2: Firming up of PP at concerned Asset
(Participants: Pr. Gr., EPMC I/c Project , Surface Team,
Asset-Co-ordinator, ROU/LAQ In-charge, Planning Engg. Of LSTK,
A.O.P.M.T Vendor Primavera Expert etc.
 Stage 3: Finalization of PP & Closure Meeting to be chaired by CESOnshore.
7. Terms & Conditions : Mobile Application Based Online Project Monitoring Tool
(AOPMT)
i.
Please refer detailed scope of work as brought out above.
ii.
Bidder shall quote all inclusive licence and associated services cost
(excluding taxes & duties) separately, for implementation of complete
scope of work/ services for Mobile Application Based Online Project
Monitoring Tool (AOPMT), at A3-i and A3-ii of Price Schedule i.e Appendix
A-3. Taxes and Duties shall be quoted separately by the bidder.S
iii.
Bidder shall provide all licences, as defined in scope of work, prior to or
along with first submission of planning package. Licences shall be
distributed by ONGC. Bidder shall have no rights against distribution of
licenses.
iv.
Licenses provided by the Bidder should be valid for 36 months from the
date of purchase of licenses. Licenses shall be transferable from one user
to another, as directed by Company, without any cost implications.
v.
Bidder shall ensure the availability of software capabilities, as per defined
scope, (Annexure-1) for 36 months from the date of purchase of licenses.
vi.
Bidder shall ensure the availability of planning engineer/ Primavera
expert of AOPMT vendor, as per requirement during the currency of the
contract including finalization of planning package, restructuring of
tasks, change of baseline schedules.
vii.
Bidder shall submit responsibility matrix clearly identifying the
responsible person for each task and the same identified person shall be
responsible for updation of progress data on continuous basis in the
mobile application.
viii. Bidder shall also provide an undertaking from AOPMT vendor stating the
following:
ONSHORE
ENGINEERING
SERVICES
NEW DELHI
SCOPE OF WORK
(MOBILE BASED ONLINE PROJECT
MONITORING TOOL)
“The approved planning package prepared under Primavera (V8.1 or
above plus web service access) mapped into the AOPMT (name may be
changed as per software name) software is compatible and workable and
shall not affect the capabilities of the software, as defined in AOPMT scope
of work in any manner, whatsoever”.
ix.
Invoicing and Payments against the software licenses and associated
services shall be made as per Milestone Payment Formula.