Uploaded by Mr A. Anbezhil

Hot-Tapping-TDW Presentation

advertisement
Pipeline Integrity, Hot Tapping &
Plugging Seminar
Sol Elite Marbella, Anyer
10 May 2007
Hot Tapping & Plugging
Gunavel Rathinam
Regional Sales Manager
AGENDA
•
•
•
•
•
•
•
Objective
Basic Concept
Associated equipment
Fitting Specification
Large Diameter stopple
MTM Hitemp stopple
Strength / Q & A
What is HOT TAPPING?
Hot Tapping Is an Operation to an opening
into a pressurised pipe, tanks conveying a
product without having to shut down the
process.
PURPOSE OF HOT TAPPING
z
TO GAIN SAFE ACCESS TO THE PIPELINE CONTENTS :
¾
FOR DELIVERY TO ANOTHER SOURCES
z
TO ACCEPT ADDITIONAL PRODUCT FROM A NEW OR UNTAPPED SOURCE
z
TO OBTAIN INFORMATION ON INTERNAL PIPELINE CONDITION
z
TO INSTALL :
¾ PIG SIGNAL
¾ CORROSION PROBE OR COUPON
¾ CHEMICAL INJECTION POINT
¾ SAMPLING POINT
z
TO CREATE A BYPASS
z
TO ALLOW INSERTION OF LINE PLUGGING EQUIPMENT (STOPPLE)
The Hot Tapping Process
Tapping-Maintaining the Coupon:
Hot Tapping Applications
What are the Typical Setups?
Hottap Operation
HOT TAPPING DATA SHEETS
Why is a Tapping data Sheet
required?
Ensure Correct Equipment is used.
The Pipeline conditions are
considered for Hot Tapping &
STOPPLE Applications
®
Flow conditions are considered for
Pilot drill Selection.
The correct Cutters & Pilot drills are
used for Pipe O.D & Valve I.D.
Hot Tap Data Sheet
Valve Size (Inches)
Flange Series ( # )
Line Size
Pipe Material
Wall Thickness (inches)
Product
Pressure ( Psig )
Temperature (Deg C)
Velocity (m/s)
Wall Thickness-Branch
Orientation of line :
A & B Dimension
-
Size of hottap
Pressure rating of equipment
Type of cutter & Pilot Drill
Type of cutter
Type of cutter and model of machine
Packing of machine
Pressure rating of machine
Temp rating of machine
Coupon retention
Size of cutter
Horizontal / Vertical
Travel of machine
What is STOPPLE?
Temporary plugging to isolate section of
a pipeline without interruption of flow or
without pipeline shutdown
PURPOSE OF STOPPLING
z
TO REMOVE A SECTION OF THE PIPELINE
TO INTRODUCE AN EQUIPMENT OR VALVE INTO AN
EXISTING PIPELINE
z
z
TO RE-LOCATE / REROUTE AN EXISTING PIPELINE SECTION
z
TO CREATE A BYPASS
Hottap & Stopple Plugging
STOPPLE® Plugging is the process of
inserting a plugging head into a pipeline to
temporarily isolating a section of pipe while
diverting the product flow using a bypass
installed around an isolated section. So that
repairs, modifications, installation or
relocation of essential piping systems can be
accomplished, on stream WITHOUT
SHUTDOWN.
STOPPLE OPERATION
Stopple Plugging
How Does the Plug Work?
Folding Plugging Head
Plugging Head
Bypass/Stay On-stream
Why Tap and Plug?
•
•
•
Pipeline Repair
Valve Installation/Replacements
Tie-ins
Pipeline Plugging
How is the Completion Plug Set?
LOCK-O-RING Plug
COMPLETION OPERATION
HT&P Equipment
Quality Service Requires Quality Equipment:
Stopple Equipment & accessories
Consist 5 major Components :
• Hottap Machine
• Sandwich Valves
• Hydraulic Cylinder & Housing
• Plugging Head & Sealing element
• Stopple Fitting
Hottap Machine & Sandwich Valve
• Tapping machine
• Sandwich Valves
Tapping Machine
Specifications
ƒ
ƒ
ƒ
ƒ
ƒ
Maximum Operating Pressure
1480 psi @ 100° F
Maximum Operating
Temperature 700º F at 700 psi
Boring Bar Travel
9 T101
= 18” ( ¾” ~ 4”)
9 660
= 42” ( 3” ~ 12”)
9 760
= 66” ( 3” ~ 16”)
9 1200
= 72” ( 12” ~ 30”)
9 1200XL=102”( 12” ~ 48”)
Rate of automatic feed
9 T101 – Manual Feed
9 660/760
– Standard .005"/rev.
– Slow Feed .003"/Rev
9 1200 – 0.4” / Rev
Power Sources = Air motor or
Hydraulic Power
Accessories
Cutter
ƒ Type of cutter
9 Standard cutter
9 Stopple cutter
9 Tank cutter
9 Special angled cutter
Pilot Drill
ƒ Centering pin for cutter
ƒ Coupon retention devices
ƒ Multi U-wire Pilot drill
Stopple Plugging Equipment
• Hydraulic Cylinder &
Housing
• Plugging Head &
Sealing element
• Stopple Fitting
Stopple Fitting
HIGH PRESSURE FITTINGS
Well designed, engineered and
manufactured
Wide variety of fittings available
Designed, tested and manufactured to be
used on pipelines operating under various
codes – ASME B31.8, ASME B31.4,
ASME B31.3, DOT Part 192 and 195 and
comparable international codes
Material certificates available
Weldability assured
Installation instructions with each fitting
HOT TAP FITTING
VARIATIONS
Stopple Fitting
Lock-O-Ring
Flange & Plug
T-O-R
Fitting
Assembly
Subsea Mechanical fitting
& Spherical fitting
3- Way fitting
Type of fitting
DESIGN CODES
ANSI B 31.3 – Chemical plant & Petroleum Refinery piping
ANSI B 31.8 – Gas Transmission and Distribution piping System
ANSI B 31.4 – Liquid Petroleum Transportation piping System
ANSI B 31.1 – Power Piping
CONSTRUCTION CODE
INFORMATION
ASME B31.1 ( POWER PLANT )
1) Power Piping
2) Allowable SMYS based on temperature
3) Temperature Range minus 20 degrees F to the plus
limits of listed materials
4) PWHT is required when the Governing Thickness
exceeds 3/4 inch, or 1 inch if a 200 oF preheat is used.
(Table 132)
CONSTRUCTION CODE
INFORMATION
ASME B31.3 ( REFINERY, TOPSIDE, HPI )
1) Process Piping
2) Allowable SYMS based on temperature
3) Temperature Range plus and minus limits of listed
materials
4) PWHT is required when the Governing Thickness
exceeds 3/4 of an inch. (Paragraph 331.1.3)
CONSTRUCTION CODE
INFORMATION
ASME B31.4
1) Pipeline Transmission Systems for liquid Hydrocarbons and
other Liquids
2) Design factor .72
3) Temperature Range -20 to +250 degrees F.
4) PWHT is required when the Governing Thickness exceeds 11/4 inches, or 1-1/2 inches if a 200 oF preheat is used. Joints
qualified at as-welded thickness may be exempt.
(Paragraph 434.8.9(a))
CONSTRUCTION CODE
INFORMATION
ASME B31.8
1) Gas Transmission and Distribution Piping Systems
2) Design factors based on locations classes, .72, .6, .5 and .4
3) Temperature Range -20 to +450 degrees F with temperature
derrating factors above 250 degrees F.
4) PWHT required when the Governing Thickness exceeds 11/4 inches. (Paragraph 825.2)
DESIGN FACTOR
Design Factor is a way of discounting material strength for Safety
Consideration.
The smaller the Design Factor value the more conservative the
design.
Thickness = Pressure x Diameter / 2 X Mat. Strength X DF
DF - CHART
DESIGN FACTOR
0.72
0.60
0.50
0.40
MAWP (PSI)
1480
1230
1025
820
Method of Pipeline Expansion and modification
Conventional Method = Shutdown
Best Way = Hot Tap
1) High cost of throughput loss
2) Contractual requirements to pipeline
customer
3) Loss of expensive product
4) Environmental issues
5) Wait till next shutdown period
1) Solve maintenance problems at
minimal cost with no shutdown or
spillage
2) Reduce Environmental impact/
hazardous with very little drain
down or refill
3) No loss of expensive product
4) Well proven, safe and common
technique
Benefits of Hot Tapping & Plugging
;No Shut down to plants or
Piping Systems
;Time Saving
;Minimum Personnel
Required
;Money Saving
EXAMPLE : 10” Natural Gas Tie-in into
existing system in Gas Separation Plant
Location : Gas Separation plant
Plant Capacity : 230 mmscfd
Duration of work : 7-10 days
Production : US$ 100,000.00/day
Conventional Method
1) Loss of production = $100,000/day *
10days = $1,000,000
2) Loss of Product ( NG)
3) Contractual penalty from customer
4) Environment & Safety issue
5) Increase in Operation cost
EXAMPLE : 10” Natural Gas Tie-in into
existing system in Gas Separation Plant
Location : Gas Separation plant
Plant Capacity : 230 mmscfd
Duration of work : 7-10 days
Production : US$ 100,000.00/day
TDW Way(on stream w/o shutdown)
1) No loss of production / product
= Save $1,000,000
2) No contractual penalty from customer =
$$$
3) No Environment & Safety issue
Well proven technology
4) Overall project cost at less than
anticipated
Mitigate Your Risk – Stay Online
The greatest percentage of accidents in plant and refineries
happen when bringing the system back online.
This risk associated with igniting the burners after shutdown is
costly in three ways :
- Cost of being offline
- The cost to human life
- Cost of rebuilding, both the facility
and reputation for safety.
Thank You
Your Source for…
Global Pipeline Solutions
Download