LONG-TERM CONSTRUCTION CONTRACTS (2) Test I – Multiple Choice (Theory) 01. In accounting for a long term construction contract using the percentage of completion method, the progress billings on contract account is a: a. Contra current asset account b. Contra noncurrent asset account c. Noncurrent liability account d. Revenue account 02. How should balances of progress billings and construction in progress be shown at reporting dates prior 03. prior to the completion of a long-term contract? a. Progress billings as deferred revenue, construction in progress as a deferred expense b. Progress billings as revenue, construction in progress as inventory c. Net, as current assets if debit balance and current liability if credit balance. d. Net, as income from construction if credit balance, and loss from construction if debit balance 03. Which of the following would be used in the calculation of the net profit recognized in the third and final year of a construction contract which is accounted for using the percentage of completion method? Contract price Actual total costs Income previously recognized a. Yes Yes No b. Yes Yes Yes a. Yes No Yes a. No No Yes 04. When should an indicated loss on a long term contract be recognized under the hybrid contract method and the percentage of completion method, respectively? Zero profit Percentage of Completion a. Immediately Immediately b. Immediately Over the life of the project c. Completion of contract Over the life of the project d. Completion of contract Immediately 05. A company uses the percentage of completion method to account for a four-year construction contract. Which of the following would be used in the calculation of the income recognized in the first year? Progress billing Percentage of Completion a. No No b. No Yes c. Yes No d. Yes Yes 06. In computing the percentage of completion ratio, under the cost to cost method, actual costs incurred should exclude: a. Costs of materials used in construction b. Costs of hiring equipment c. Costs of design and technical assistance d. Costs of materials purchased in advance 07. The excess of Construction in Progress account over the Contract billings is treated as: a. Current liability b. Current asset c. Other asset d. Noncurrent liability 08. Under PAS 11, Contraction Contracts, when it is probable that the total contract costs on a fixed price contract will exceed total contract revenue, the expected loss should be a. Se off against on other contract when available. b. Recognized as an expense immediately, unless revenue to-date exceed costs to-date. c. Apportioned to the years of the contract according to the percentage of completion method. d. Recognized as an expense immediately. 09. Before the year of completion, under the percentage of completion method, the year-end balance of the Construction in Progress account is equal to: a. Cost incurred to date b. Cost incurred this year c. Cost incurred to date plus gross profit earned to date d. Gross profit earned to date 10. The calculation of the income recognized in the third year of the five-year construction contract accounted for using the percentage of completion method includes the ratio of a. Total costs incurred to-date to total estimated costs. b. Total costs incurred to-date to total billings to-date. c. Cost incurred in year 3 to total estimated costs. d. Cost incurred in year 3 to total billings to-date. Test II - Problems 01. The Matibay Construction Corporation uses the percentage-of-completion method of recognizing income from long-term construction contracts. In 2018, Matibay entered into a fixed-price contract to construct a bridge for P30,000,000. Estimated costs to complete the construction and contract costs incurred up to 2020 were as follows: Cumulative Estimated costs Costs incurred to complete As of December 31, 2018………..P 2,000,000 P16,000,000 As of December 31, 2019……….. 11,000,000 11,000,000 As of December 31, 2020……….. 20,000,000 4,000,000 What is the percentage of completion during the year 2020? a. 25.00% b. 33.33% c. 50.00% d. 83.33% 02. In 2019, the Kenetics Construction Company started a construction job with a total contract price of P600,000. Any costs incurred are expected to be recoverable. The job was completed on December 31, 2020. Additional data are as follows: 2019 2020 Actual costs incurred P225,000 P255,000 Estimated remaining costs 225,000 Billed to client 240,000 360,000 Collected from client 225,000 375,000 Under the percentage of completion method, what amount of gross profit should be realized in 2019? a. P150,000 b. P120,000 c. P75,000 d. P60,000 03. Using the same information in no. 2 and under the percentage of completion method, what amount of gross profit should be realized in 2020? a. P120,000 b. P75,000 c. P45,000 d. P0 04. Lakeshore Construction Company has consistently used percentage of completion method of recognizing income. During 2019, the company entered into a fixed-price contract to construct an office building for P3,000,000. Information relating to the contract is as follows: 2019 2020 Percentage of completion 20% 60% Estimated total cost at completion P2,250,000 P2,400,000 Income recognized (cumulative) 150,000 360,000 How much costs were incurred in 2020? a. P600,000 b. P960,000 c. P990,000 d. P1,440,000 05. The Gamboa Construction Company started work on three job sites during the current year. Any costs incurred are expected to be recoverable. Data relating to the three jobs are given below: Contract Cost Site price incurred Batangas…….P500,000 P375,000 Laguna………. 700,000 100,000 San Fernando 250,000 100,000 Estimated costs to complete P400,000 100,000 Billings on contract P500,000 100,000 150,000 Collection on contract P500,000 100,000 100,000 What would be the amount of construction in progress to be reported on the year-end statement of financial position if the percentage- of-completion method is used? a. P765,000 b. P700,000 c. P265,000 d. P200,000 06. During 2020, Reach Construction started work on a P3,000,000 fixed-price construction contract. Any costs incurred are expected to be recoverable. The accounting records disclosed the following data for the year ended December 31, 2020: Costs incurred……………………………………………….P 930,000 Estimated cost to complete………………………………… 2,170,000 Progress billings…………………………………………….. 1,100,000 Collections…………………………………………………… 900,000 How much loss should Reach Construction have recognized in 2020 if the percentage- of-completion method is used? a. P100,000 b. P50,000 c. P30,000 d. P0 07. Daimler Construction Company uses the percentage –of-completion method of accounting. During 2020, Daimler contracted to build an apartment house for an individual for P10 million. The company estimated that total costs would amount to P8,000,000 over the period of construction costs during 2020. In connection with this contract, Daimler incurred P2,000,000 of construction cost during 2020. Daimler billed and collected P1.5 million from the client in 2020. How much gross profit should Daimler recognize in 2020? a. P300,000 b. P250,000 c. P187,500 d. P125,000 08. In 2020, AJD Construction Co. was contracted to build Village Company’s private road network for P100 million. The project was estimated to be completed in two years, and the contract provided for: (1) 5% mobilization fee (to be deducted from the last billing) payable within 15 days after signing of the contract, (2) 10% retention provision on all billings, and (3) Payment of progress billings within 10 days from acceptance. AJD, which uses the percentage-of-completion method of accounting, estimated a 25% gross margin on the project. By the end of 2020, AJD had presented progress billings corresponding to 50% completion. All of the progress billing presented in 2020 were accepted, except the last one for 10% which was accepted on January 7 2021. With the exception of one bill for 8% which was due on January 7, 2021, off of the billings accepted in 2020 were settled. Payments made by Village Company in 2020 amounted to: a. P33,800,000 b. P38,500,000 c. P 40,000,000 d. P45,000,000 09. 7ME Construction Corporation has the following date for large jobs in its Jobs in Progress account (000 omitted): Project No. 101 102 103 104 105 Actual Cost P 8,756 11,457 53,865 22,800 44,500 P141,378 ======= Estimated Total Costs P172,800 14,875 61,250 39,760 122,310 P410,995 ======= Contract Price P192,000 17,500 87,500 49,700 151,000 P497,700 ======= % of Completion 5 75 80 55 35 The company accounts for its large jobs by the percentage of completion method. Billings are done as follows: (a) 20% down payment upon contract signing; and (b) balance is billed according to percentage of completion, less an application of the down payment which is also according to percentage of completion. How much total billings were made by the company? a. P203,286 b. P99,540 c. P151,413 d. P189,266 10. Using the same information in no. 9, how much total revenue should be recognized by the company for the period under consideration? a. P120,060 b. 172,910 c. P146,485 d. P219,727