PROJECT PROCUREMENT PROCUREMENT OF COMMERICAL KITCHEN EQUIPMENT AND MACHINERY FOR A RESTAURANT BUSINESS PROJECT PROCUREMENT PLAN GROUP 6 RAMEEN SHAKEEL JAVERIA RIAZ UMER SHAFIQ OMAR ASHFAQ Page 1 of 11 PROJECT PROCUREMENT PLAN Table of Contents Project Charter ........................................................................................................................................ 3 Project Description: ............................................................................................................................ 3 Project Objective................................................................................................................................. 3 Make or Buy Analysis .............................................................................................................................. 5 Potential Suppliers: ................................................................................................................................. 9 TERMS AND CONDITIONS ..................................................................................................................... 10 TABLE OF CONTENT 1. Project description……………………………………………………………………………………………….. 3 2. Project objectives…………………………………………………………………………………………………. 3 3. Definition……………………………………………………………………………………………………………… 3 4. Project scope statement………………………………………………………………………………………. 4 4.1. In scope………………………………………………………………………………………………………… 4 4.2. Out of scope…………………………………………………………………………………………………. 4 4.3. Project pre-requisite…………………………………………………………………………………….. 4 4.4. Enterprise environmental factors…………………………………………………………………. 4 4.5. Organizational process asset………………………………………………………………………….4 5. Make or buy decision………………………………………………………………………………………….. 5 6. Work break down structure………………………………………………………………………………… 5 7. Risk categorization……………………………………………………………………………………………… 6 8. Risk register………………………………………………………………………………………………………… 6 9. Risk matrix……………………………………………………………………………………………………………7 10. Project schedule…………………………………………………………………………………………………. 7 11. Supplier selection criteria…………………………………………………………………………………… 8 12. Bids participant………………………………………………………………………………………………….. 9 13. Success criteria…………………………………………………………………………………………………... 9 14. Terms and condition………………………………………………………………………………………….. 10 15. Conclusion…………………………………………………………………………………………………………. 11 Page 2 of 11 PROJECT PROCUREMENT PLAN Project Charter Project Description: This project is forA Restaurant is to be setup Food’s inn is a major restaurant chain established in 2018 having several branches in different cities of Pakistan presently. Currently, they intend to open a new branch in Karachi city’s food street area. Project Objective The purpose of this project is to procure commercial kitchen equipment and machinery and make them operational for Food’s inn restaurant who is recently going to open its branch in Karachi. Definitions Commercial kitchen equipment: is defined as commercial-only equipment that is suitable to be installed in a commercial kitchen environment to include, but not limited to: Mixer, Grinder, Blender, Chopper, Non-stick cookware, Coffee/tea maker, Cooking range, Stove, BBQ pit, Deep fat fryer, Grill, Toaster, Microwave, Refrigerator, Utensils and kitchen tools. Supplier/Vendor: An individual or entity whose work is to sell the goods to the final consumer. To make the goods available to the people who need it. Buyer/ Contractor: An individual or entity employed to select and purchase stock or materials for a large retail or manufacturing or service business. Page 3 of 11 PROJECT PROCUREMENT PLAN Project scope statement In scope The scope of this project includes: To procure commercial-only kitchen equipment and machinery. The machinery list includes: Mixer, Grinder, Blender, Chopper, Non-stick cookware, Coffee/tea maker, Cooking range, Stove, BBQ pit, Deep fat fryer, Grill, Toaster, Microwave, Refrigerator, Utensils and kitchen tools. Any unexpected equipment failure that requires an emergency repair call and cost way more than simple maintenance shall be taken into account by the Supplier. Out of scope The shipping and delivery charges shall not be paid by the supplier. Setup and installation work shall not be carried out by the supplier. Remanufactured or refurbished products are not acceptable. Project Pre-Requisite Availability of land/ storage Requirement estimation has already been done. The restaurant menu is finalized. Enterprise Environmental Factors Market demand of the type of cuisine that will be served in the restaurant and equipment required in its preparation. The resources available to acquire machinery and equipment The HR expertise related to operating commercial machinery. Organizational Process Assets Processes, guidelines and procedures provided by the fo;od’s inn team which was practiced in the past project Lesson learned register from the other branches projects. Food’s inn corporate knowledge base with their experience with similar past projects on other locations Page 4 of 11 PROJECT PROCUREMENT PLAN Make or Buy Analysis To decide whether to Make or Buy the required products, a thorough Make or Buy analysis has been conducted in which it is concluded that all the required goods for this project are over the counter available and the complexity of buying them is significantly less than producing them in-house. Figure 1: Make or Buy Analysis Work Breakdown Structure Work Breakdown Structure defines the deliverables at the result of each activity performed. Figure 2: Work Breakdown Structure Page 5 of 11 PROJECT PROCUREMENT PLAN RISK CATAGORIZATION Risk is any unexpected event or result deviated from the desired outcome that can affect the project. Procurement risk are possible failure to procure goods or services. It is obtained through different identification processes which give risk register once combined in a tabular form. It includes risk probability, its impact and contingency plan to avoid possible failure of the procurement hence the project. Risk Register Risk register is a central depository of all the identified risk to track and plan best course of action against each. Here each risk is tabulated with regards to procurement that will ease to meet the objective and goal, that is in-time and accurate procurement. RISK ID RISK CATAGORY PROBABILIT Y IMPAC T RESPONS E 1 Economical 1.1 E1 Taxation 1 3 Accept 1.2 E2 Price Hikes 3 5 Accept 2 Political Strikes Strikes can disrupt timely delivery of items 2 2 Accept Natural disaster Natural disaster can cause delayed delivery 3 4 Accept 4 3 Mitigate 3 3 Mitigate 3 5 Mitigate 3 4 Mitigate RISK TYPE 2.1 P1 3 Environmen t 3.1 En1 4 Technical 4.1 T1 Warranty 4.2 T2 Estimation 4.3 T3 Availability 4.4 T4 Malfunctioning DESCRIPTION New taxes introduced by government Prices increased due to inflation Machines delivered without warranty imporper requirement estimation Required models not available in market Defective product delivered Page 6 of 11 PROJECT PROCUREMENT PLAN 4.5 T5 Logistics 4.5. 1 T5.1 4.6 T6 Miscommunicatio n Delayed delivery from the vendor wrong delivery of products Miscommunicatio n regarding product type 4 4 Mitigate 3 4 Mitigate 4 4 Mitigate or delivery RISK MATRIX By evaluating the risk from expert opinion in the risk register Probability and Impact matrix is prepared to analyze the impact of each risk on our project. With the help of this, we will be able to decide what action needs to be taken. Whether we have to mitigate, avoid or accept the risk. Probability and Impact scale Negligible 5 4 3 2 1 Minor Moderate Major Very likely T3 E2 Likely En1 T4 T5.1 T5 T6 T2 T1 3 4 Moderate E1 Unlikely Extreme P1 Rare 1 2 5 Project Schedule This Project is set to be completed within 60 days period from project initiation to project closing. The estimated activity breakdown with its duration is as follow: Activity Duration (Days) Requirement Estimate 5 Procurement Plan 5 Supplier Selection 10 Page 7 of 11 PROJECT PROCUREMENT PLAN Award of Contract 3 Conduct Procurement 30 Close Procurement 7 Total days: 60 SUPPLIER SELECTION CRITERIA Supplier selection criteria involves obtaining bids and offers from different vendors. Selection criteria would be based on 1. Financial 60% Pricing: Pricing and Terms that provide for increased discounts and lower overall cost Financial stability 2. Technical 40% Reliability After sale service Market demand The cost will be weighted more for the successful selection of any supplier. 60% preference will be on the financial basis while 40% will be on technical. Since we will be working on a Fixed-Price contract, the supplier with the least quoted price will be preferred. After cost, the supplier must have a good reputation in the market. For this very purpose, we will ask them for references or relevant past work they have done. 5 years will be the minimum time requirement that the supplier must be in business to pass the criteria (Reliability). Another critical factor will be the after-sale service. If any equipment or machine results in a problem will the supplier replace or repair it. Page 8 of 11 PROJECT PROCUREMENT PLAN Potential Suppliers: Z'Mario Italian Kitchens System. Prestige Kitchens Awesome Kitchens WestPoint Anex Financial Evaluation: Supplier Name Dawlence Electronics Haier Pakistan Prestige Kitchens FINANCIAL EVALUATION Pricing Financial Stability (80) (20) 70 15 68 18 72 10 Total (100) 85 86 82 Technical Evaluation: Supplier Name Dawlance Electronics Haier Pakistan Prestige Kitchens TECHNICAL EVALUATION After sale Reliability service (20) (20) 19 15 17 13 13 15 Market Demand (60) 50 55 40 Total (100) 84 85 68 Calculating on the basis of weightage: Supplier Name Dawlance Electronics Haier Pakistan Prestige Kitchens FINAL EVALUATION Technical Evaluation Financial Evaluation (40%) (60 %) 27.6 51 28.8 51.6 21.2 49.2 Total (100 %) 78.6 80.4 70.4 Success Criteria To successfully pass the criteria supplier should get 85+ out of 100 points in financial category. While in the technical aspect they should achieve 80+ points out of 100. Altogether 80% would be the bench mark for winning the contract. Page 9 of 11 PROJECT PROCUREMENT PLAN TERMS AND CONDITIONS Completion Time Warranty Payment Support Invoice Damage Control Conflict of Interest Supplier must deliver the items within 3 weeks after receipt of firm supply order Minimum 1 year warranty is necessary for each product supplied Full payment will be made after delivery and satisfactory inspections of goods to the desired location Supplier shall provide a single point of contact plus a backup to contact customer service representative during normal business hours of every business day. Invoices shall be directed to the appropriate location(s) specified by the buyer. Invoices and payment terms must comply with the requirements of the buyer and supplier. Proper sale tax invoice would need to be presented for the payment and completion of the contract Supplier will be responsible for proper handling and delivering it to the desired location If Supplier fails to deliver, or erroneously delivers products, Supplier is required to take immediate corrective action to make the correct delivery at no cost to buyer. In order to avoid even the appearance of any conflict of interest, neither Supplier nor Buyer shall employ any employee of the other party for a period of one year from the date of contract Conflict of Interest In order to avoid even the appearance of any conflict of interest, neither Supplier nor Buyer shall employ any employee of the other party for a period of one year from the date of contract Force Majeure: Neither party shall be held responsible for any losses resulting of the fulfillment of any terms of the contract delayed or prevented by any cause not within the control of the party, and which by the exercise of reasonable diligence, said party is unable to prevent. General conditions Buyer reserve the right to refuse the service for any reason at anytime Without limiting to any right purchaser can return the non-conforming products Supplier represent and warrant to that all supplied item will be brand new and without any fault Supplier must be bound to give after sales service for at least a year after their services Page 10 of 11 PROJECT PROCUREMENT PLAN CONCLUSION After evaluating bids and offers from different suppliers we awarded Haier Pakistan the procurement contract after they successfully passed all the above listed criteria. We expect that all the terms and condition will be kept in mind during this whole process. Page 11 of 11