Uploaded by Owais Sayed

new doc

advertisement
Date:
Approval needed by:
SUBMITTAL
TRANSMISSION OF MATERIAL/SAMPLE DOCUMENTS
CONTRACTOR:
SUBMITTED FOR
PACKAGE NO. PS-08/B
Fire Fighting
CODE
APPROVAL
INFORMATION
RECORD
REFERENCE
1
2
3
ACTION
TO:
Cc.
Cc.
Cc.
Cc.
WE ARE SENDING HERE WITH THE DOCUMENT LISTED BELOW.
S/N
1
No.
Copies
Dwgs., Specs. or
BOQ Ref. No
3
Specification No.
FF section 2-2.3
section 3-3.2
DOCUMENT
NO.
FF-MS0001
DESCRIPTION
CODE
A
APPROVED
APPROVED AS
NOTED
APPROVED
SUBJECTED
TO ADDITIONAL
INFO
REVISE AND
RESUBMIT
D
FOR INFORMATION
R
Soft Copy
B
C
TYPE
REV.
06
CODE
SUBMITTED BY
(1)
Tower-B Method Statement for
Fire Hydrant, Sprinkler pipes &
fittings installation & Hydro test
√
MS
ACTION
(2)
1
HIGHLIGHT DEVIATIONS:
I certify that above submitted items have been reviewed in detail and correct and in strict conformance
with specification except as otherwise stated
COPIES: 3 HARD COPIES
Design Consultant to enter Action Codes and Remarks, and return to Contractor
REMARKS:
COPIES:
DATE:
(1) Code to be entered by contractor
• TYPE: SD· Shop Drawings GT- Guarantee / Warrantee MD - Manufacturer's Data SM-Sample TI- Test/Inspection CD- Coordination Dwg
(2) Code to be entered by Designer / Consultant
CA- Calculation
CT- Certificates
MS- Method Statement
SC- Schedule
RP- Report
OT- Others
WORLI MIXED USE DEVELOPMENT PROJECT – PHE/FF
Response to Samsung comments
Comments received for:
1
2
Submittal No:
Contractor Submittal No:
Revision:
Submitted Date:
BSL Reply Date:
Comments received Date:
Action Code:
Sr No.
A
Method Statement for Fire Hydrant,
Sprinkler pipes & fittings installation &
Hydro test
Comments from Samsung
SMT-BS-0034
BSL Reply to Samsung
General Comments:
Flushing of FF system shall be in accordance with
NFPA guidelines
Confirm compliance
Submit separately hold tite joint compound material with
technical details for Engineers
The same submitted through submittal no – SMT-BS-0166,
dated 8th March 2014 & same approved as noted
Handling/shifting of pipe inside shaft riser to be briefed
Logistic plan for vertical material movement shall be
submitted separately for approval
Attached risk assessment not specify to the activity
involved
Revised RA attached
3
4
5
Mention the testing pressure for hydro-testing separately
for risers as well as branch pipes
Testing pressure shall be 2 times the working pressure or 1.5
times the working pressure plus 3.5 bar whichever is the
lowest but in any case not less than 7 bars as per
specification is referred for construction. This will retain @
lowest point of the riser of that particular zone. (Page
Attached)
The same is mentioned in MOS under the head of “material
standard” 6.1. G.I. Pipe 25mm dia to 150mm dia shall be as
per IS: 1239 – “C” Class.
G.I. Pipe of size 200mm and above shall be as per IS: IS: 3589
min wall thickness 6.35 mm.
6
Type of material & jointing procedure to be mentioned
Fittings – 25mm dia to 50mm dia shall be “G.I. Threaded
forged” fitting. Jointing procedure for these fitting with
piping shall be “thread” joint.
Fittings – 65mm dia & above shall be “D.I. grooved type”
fitting. Jointing procedure for these fitting with piping shall
be “grooved” joint
Date:
Approval needed by:
SUBMITTAL
TRANSMISSION OF MATERIAL/SAMPLE DOCUMENTS
CONTRACTOR:
SUBMITTED FOR
PACKAGE NO. PS-08/B
Fire Fighting
CODE
APPROVAL
INFORMATION
RECORD
REFERENCE
1
2
3
ACTION
TO:
Cc.
Cc.
Cc.
Cc.
WE ARE SENDING HERE WITH THE DOCUMENT LISTED BELOW.
S/N
1
No.
Copies
Dwgs., Specs. or
BOQ Ref. No
3
Specification No.
FF section 2-2.3
section 3-3.2
DOCUMENT
NO.
FF-MS0001
DESCRIPTION
CODE
A
APPROVED
APPROVED AS
NOTED
APPROVED
SUBJECTED
TO ADDITIONAL
INFO
REVISE AND
RESUBMIT
D
FOR INFORMATION
R
Soft Copy
B
C
TYPE
REV.
06
CODE
SUBMITTED BY
(1)
Tower-B Method Statement for
Fire Hydrant, Sprinkler pipes &
fittings installation & Hydro test
√
MS
ACTION
(2)
1
HIGHLIGHT DEVIATIONS:
I certify that above submitted items have been reviewed in detail and correct and in strict conformance
with specification except as otherwise stated
COPIES: 3 HARD COPIES
Design Consultant to enter Action Codes and Remarks, and return to Contractor
REMARKS:
COPIES:
DATE:
(1) Code to be entered by contractor
• TYPE: SD· Shop Drawings GT- Guarantee / Warrantee MD - Manufacturer's Data SM-Sample TI- Test/Inspection CD- Coordination Dwg
(2) Code to be entered by Designer / Consultant
CA- Calculation
CT- Certificates
MS- Method Statement
SC- Schedule
RP- Report
OT- Others
CONTRACTOR’S SUBMITTAL
PROJECT TITLE:
CONTRACTOR:
PROJECT DIRECTOR:
DISCIPLINE:
SCHEDULE ACTIVITY No.:
DATE REQUESTED
BY CONTRACTOR:
DATE SENT:
DRAWING REFERENCE
TYPE:
SUBMITTED FOR:
TO:
CC:
CONTRACTOR’S SUBMITTAL NO:
REFERENCE NO:
CHECK ONE:
 ORIGINAL SUBMITTAL
 2nd SUBMITTAL OF
 SUBMITTAL OF
 O and M SUBMITTAL
Initiator:
LEGEND
Submitted for:
Action:
Approved A
APPROVAL:
Approved as Noted B
Type:
Shop drawing SD
Calculation CA
Certificate CT
No
Copies
Doc No.
INFORMATION:
Approved subjected to Additional info C
Revise & Resubmit:-D
Guarantee/Warrantee GT
Manufacturer’s Data MD
Sample SM
Verified Statement VS
Schedule SC
Report RP
Rev
Description
Type
Tower-B Method Statement for Fire Hydrant,
Sprinkler pipes & fittings installation & Hydro test
RECORD:
For information R
Test/Inspection TI
Others OT
Soft copy
SmtP
(a) WE HAVE VERIFIED THAT THE MATERIAL, EQUIPMENT OR OTHER INFORMATION CONTAINED IN THIS SUBMITTAL MEETS ALL THE REQUIREMENTS SPECIFIED OR
SHOWN (NO EXCEPTIONS)
(b) WE HAVE VERIFIED THAT THE MATERIAL EQUIPMENT OR OTHER INFORMATION CONTAINED IN THIS SUBMITTAL MEETS ALL THE REQUIREMENTS SPECIFIED OR
SHOWN EXCEPT FOR THE FOLLOWING DEVIATIONS
Project Director
Date:
ORL COMMENT: Refer comments on attached sheets.
SECTION 17
FIRE PROTECTION INSTALLATION
GENERAL SPECIFICATION
TESTING COMMISSIONING AND HAND OVER
same throughout the jacking pressure range varied by
applying the hand pump
iii) Flow switches
 The testing equipment for the flow switches shall be as shown on the drawings or of an equivalent
approved by the Employer
 The calibration test equipment shall provide a flow of 60 dm3/min over the vane of the flow switch in
the direction shown, to be confirmed by the direct reading flow meter.
 The flow switch contacts shall make with energisation of the lamp and the buzzer, upon a flow
not greater than 60 dm3/min flowing over the vane in the correct direction.
iv) Hydrostatic Tests





All parts of the water circuit shall be filled with water before hydrostatic pressure testing, and pump
running tests for verification of pressure and flow rate, are conducted.
The hand jacking pump shall be applied to increase the system pressure to 2 times the working
pressure or 1.5 times the working pressure plus 3.5 bar whichever is the lower but in any case not less
than 7 bars. The pressure shall be maintained for a period not less than 24 hours.
Where any section of pipework or equipment unable to withstand the maximum pipework test
pressure, it shall be isolated during the pipework test then that section of pipework or equipment shall
be re-tested at the appropriate test pressure.
The working pressure for various systems shall be as NFPA rules or NBC/BIS guidelines.
Before performing the hydrostatic test, the following system component shall be fulfilled:
For WR/HR System
 All first aid hose reel isolating gate valves shall be closed.
Download