Uploaded by appletk

45312505

advertisement
Request for Qualifications-Based Proposals for Construction Contract
Farmington Civic Center Renovations & Expansion
PROJECT NO. CCEXP, RFP NO. 18-122315
IMMEDIATE ATTENTION
ADDENDUM TWO
September 1, 2017
Receipt of this addendum shall be noted on Page 3 in the Request for Qualifications-based
Proposal documents for the above referenced RFQP.
The addendum is hereby made part of the Contract Documents to the same extent as though it
were originally included therein. Refer to "Bid Form" for acknowledgment of addenda.
All Contractors, Subcontractors and suppliers are reminded that they shall be familiar with all
addenda items (as well as all parts of the construction documents) so as to understand the extent
of their work and its interrelation with other trades.
To all bidders for furnishing all labor and materials necessary for the following contract:
BIDDING FORMS AND PROJECT MANUAL ITEMS
ITEM AD2-A1
General Clarifications:
1. The COF owned lot on the Northwest corner of the intersection of W La Plata St and N
Behrend Ave can be used as a contractor staging and parking.
2. The project construction phasing schedule can be found on sheet AS101.
3. The plan holders list and pre-proposal conference sign-in sheet can be obtained by
going to the COF website using the following link:
http://www.fmtn.org/bids.aspx?bidID=339.
4. The A/V equipment manufacturer and parts number is included in section 07 41 00
attached to this addendum.
5. Subcontractor bonding requirements for this project will be governed by section 13-4-37
and 13-1-148.1 NMSA 1978.
6. Please see City of Farmington, Form AF-4 Estimate of Taxes, for tax information
regarding this project.
ITEM AD2-A2
Tab IV – Proposal Process/Proposal Format Requirements
The last day for submitting questions directly related to specification sections 27 41 00 & 27 41
01 will be September 7th, 2017.
ITEM AD2-A3
Tab IV – Proposal Process/Proposal Format Requirements
The last day for submitting questions other than for specification sections 27 41 00 & 27 41 01
was August 31st, 2017.
AD2-1
ITEM AD2-A4
Table of Contents
Add section 07 21 19 Foamed-In-Place Insulation into Division 07.
ITEM AD2-A5
Section 01 22 00 – Unit Prices
Page 01 22 00, page 1, section 1.07, add paragraph “B” below to section 1.07 (Revised Cost
Proposal Form attached):
B.
Item: Per square foot to remove and replace existing 5/8” gypsum board attached directly to the existing
structure or on a suspension system with new 5/8” gypsum board finished to level 3 and painted.; Section
09 21 16 for gypsum board requirements.
ITEM AD2-A6
Section 01 63 00 – Product Substitution Procedures
Page 01 63 00, page 1, section 1.03 replace paragraph “A” with paragraph “A” below:
1.03
SUBSTITUTIONS
A. During bidding, Owner will consider written requests from qualified bidders, subcontractors, and
manufacturers for substitutions.
1. Submit separate request for each substitution directly to the City of Farmington’s Procurement
Department by email at jlrowland@fmtn.org.
2. Submit substitution request in accordance with Instructions to Bidders.
3. Substitutions approved during bidding will be listed in Addenda.
ITEM AD2-A7
Section 01 63 00 – Product Substitution Procedures
The last day for submitting prior approval request will be September 7th, 2017.
ITEM AD1-A8
Section 07 21 19 – Foamed In-Place Insulation
Add section 07 21 19, dated 8/31/2017, attached to this addendum into project manual.
ITEM AD2-A9
Section 09 68 00 – Carpeting
Replace section 09 68 00 with section 09 68 00, dated 8/31/2017 attached to this addendum.
ITEM AD2-A10
Section 27 41 00 – Audio-Visual Systems
Add specification section 27 41 00, dated 8/30/2017, attached to this addendum into project
manual.
ITEM AD2-A11
Section 27 41 01 – Audio-Visual Systems Demolition
1. Add specification section 27 41 01, dated 8/30/2017, attached to this addendum into
project manual.
2. All A/V equipment that is to be removed, is to be turned over to the Owner for storage.
No equipment that is demoed is to be reinstalled.
ITEM AD2-A12
Division 27 Specifications and Theatrical A/V Sheets
Clarification: The A/V scope of work included in the drawing sheets and specifications must be
included in the General Contractor’s bid for the project.
AD2-2
CIVIL ITEMS
CIVIL SHEETS
ITEM AD2-C1
Sheet C102 – Demolition Plan
Clarification: in the storage shed north of the exhibit hall, remove the “(BY OTHERS)”
designation from the work description for the work.
STRUCTURAL ITEMS
STRUCTURAL SHEETS
ITEM AD2-S1
Sheet S102-Foundation Plan
Clarification: Revised detail bubbles on plans to reflect detail renumbering per the attached
sheets to this addendum.
ITEM AD2-S2
Sheet S302-Foundation Details
Clarification: C1 and C3/S304- Revised detail call out to correspond with plan per the attached
sheets to this addendum.
ITEM AD2-S3
Sheet S302-Foundation Details
C4/S302 – Revised Detail # and concrete dimension above grade per the attached sheets to
this Addendum.
ITEM AD2-S4
Sheet S302-Foundation Details
C5/S302- added concrete foundation for flag pole per the attached sheets to this addendum.
ITEM AD2-S5
Sheet S402-Enlarged Plan and Section & Details
1. A2/S402 - Added grade beams to pick up studs on North and South sides of landing per
the attached sheets to this addendum.
2. E1/S402 – Changed line work to reflect existing ramp and added grade beam on each
side of the landing per the attached sheets to this addendum.
ITEM AD2-S6
Sheet S405-Enlarged Plan and Section & Details
A4/S405 – revised opening height per the attached sheets to this addendum.
ARCHITECTURAL SHEETS
ITEM AD2-A13
Sheet ADS101 – Demolition Site Plan
Revise demolition keynote #133 to read as “133. DEMOLISH EXISTING BUILDING
(HATCHED AREA), WALL FOOTING, ELECTRICAL AND MECHANICAL ITEMS IN THEIR
ENTIRETY. THE EXTERIOR WALLS ARE ASSUMED TO BE 6” METAL STUDS WITH
STUCCO FINISH. REFER TO SPECIFICATION SECTION 02 41 00 FOR BUILDING
DEMOLITION REQUIREMENTS”.
AD2-3
ITEM AD2-A14
Sheet AD101 – Demolition Floor Plan – Exhibit Hall
Clarification: in the existing area to become new room E136, the CMU infill area is 2’-8” x 10’-0”.
ITEM AD2-A15
Sheet AD102 – Demolition Floor Plan - Theater
Replace legend on sheet with legend on sheet AD2-01 attached to this addendum.
ITEM AD2-A16
Sheet A101 – Floor Plan – Exhibit Hall
In rooms E138 & E139 (office) revise the finish floor designation to read as “C1”.
ITEM AD2-A17
Sheet A101 – Floor Plan – Exhibit Hall
For window type E2, the existing glass for the bottom panel must be re-cut and reused. The sill
no longer slopes with the ramp, but is flat per E1/S402.
ITEM AD2-A18
Sheet A101 – Floor Plan – Exhibit Hall
In room E137, replace the room tag with room tag below:
ITEM AD2-A19
Sheet A102 – Floor & Dimension Plan – Exhibit Hall Addition
Revise keyed note 05 40 00.S8 to read as “8”, 18GA STEEL STUDS, 16" OC MINIMUM”.
ITEM AD2-A20
Sheet A104 – Floor Plan – Theater Mezzanine
In room T201 (Corridor) revise the wall finish designation to read as “M”. New finish to be
installed over existing T&G wood for this room only, not over CMU as noted in the room finish
legend. The new finish shall be installed on the south and west walls from 8’-0” AFF to 10’-0”
AFF.
ITEM AD2-A21
Sheet A121 – RCP Exhibit Hall
Clarification: The ceiling area between corridor #1 and Corridor #2 is divided by an existing to
remain bulkhead. The same is true for the area dividing the ceilings between corridor # 2 and
the entry, as well as for the area dividing the ceilings between corridor #2 and corridor #3.
ITEM AD2-A22
Sheet A121 – RCP Exhibit Hall
In room E101, on the existing to remain coffered ceiling, there is a 4’-0” x 4’-0” area that has
sustained water damage to the existing gypsum board. Remove existing gypsum board,
provide new 5/8” gypsum board, finish to level 5 and provide new paint.
ITEM AD2-A23
Sheet A121 – RCP Exhibit Hall
On the exterior soffit, east of room E101, there are two (2) 12” x 12” access panels to be
removed and replaced. Provide two (2) 12” x 12” new access panels per section 08 31 00.
Paint panels to match adjacent new finish color.
AD2-4
ITEM AD2-A24
Sheet A201 – Exterior Elevations
D1/A201, in the areas where the existing aluminum storefront is recessed along the south
elevation of the building, there are existing screw in hooks that must be removed and existing
stucco patched to match existing to remain stucco finish, hooks are ¼” in diameter x 3” in
length. Hooks are located around the entire perimeter of the recess at 2’-0” O.C. Hooks will not
be re-installed.
ITEM AD2-A25
Sheet A203 – Exterior Elevations
A1/A201, in the areas where the existing aluminum storefront is recessed along the south
elevation of the building, there are existing screw in hooks that must be removed and existing
stucco patched to match existing to remain stucco finish, hooks are ¼” in diameter x 3” in
length. Hooks are located around the entire perimeter of the recess at 2’-0” O.C. Hooks will not
be re-installed.
ITEM AD2-A26
Sheet A401 – Enlarged Floor Plan
1. Clarification: on drawing D4, the wall separating the two larger desks is metal studs and
5/8” gypsum board on both sides, provide paint to both sides. Wall is 5’-0” high.
2. Clarification: on drawing D4, the wall at the end of the desk running north-south is metal
studs and 5/8” gypsum board on both sides, provide paint to both sides. Wall is 5’-0”
high.
ITEM AD2-A27
Sheet A510 – Details - Roofing
Clarification: detail E4 is used to show how the medium density foam insulation is to be
installed, as such, this detail can be used for 6” or 10” steel stud walls. The wall batt insulation
to be provided should be governed by the wall sections, not this detail.
ITEM AD2-A28
Sheet A601 – Door and Window Schedule
Insert hardware set #38 into the HDW SET column in the door schedule for door E137A.
THEATRICAL ITEMS
THEATRICAL A/V SHEETS
ITEM AD2-A/V-1
Sheet AV104 – AV Floor Plan – Theater Mezzanine
In room T205, change the “PS” designation to “PC”. See “PC” description on sheet AV001.
ITEM AD2-A/V-2
Sheet AV401 – AV – Rack & Plate Details - Elevations
Clarifications: The plate referred to as (FB-2) in the documents is to be installed in room T205
(Mixing Booth) located at (IP).
END OF ADDENDUM NO. 2
AD2-5
CITY OF FARMINGTON, NEW MEXICO
COST PROPOSAL, FORM AF-3
ADDENDUM TWO
FARMINGTON CIVIC CENTER RENOVATIONS & EXPANSION
PROJECT #CCEXP, RFP #18-122315
RFP OPENING: SEPTEMBER 19, 2017 AT 2:00 PM
ITEM #
QTY
UOM
DESCRIPTION
UNIT
PRICE
EXTENDED
PRICE
A.
1
LS
FURNISH ALL MATERIALS,
EQUIPMENT, AND PERFORM ALL
LABOR FOR THE CIVIC CENTER
RENOVATIONS PER SPECIFICATIONS
AND DRAWINGS
B.
1
LS
PURCHASE, DELIVERY AND
INSTALLATION OF TWO (2) KALCO
LIGHTING CUSTOM MADE TRIBECCA,
ITEM #4299, FROST CHANDELIER
FINISH: SATIN BRONZE, 16 LAMP
CAPACITY PER CHANDELIER,
MEDIUM LAMP BASE. CHANDELIER
DIMENSIONS 48” IN DIAMETER AND
72” IN HEIGHT. ALLOWANCE
INCLUDES 35 HALOGEN BULBS FOR
CHANDELIERS.
$11,200.00
$11,200.00
C.
1
LS
INSPECTING AND TESTING
ALLOWANCE. PAYMENT OF
INSPECTING AND TESTING SERVICES
SPECIFIED IN SECTION 01 40 00 –
QUALITY REQUIREMENTS
$35,000.00
$35,000.00
TOTAL BASE BID ITEMS A THROUGH C:
Having examined the Place of The Work and all matters referred to in the Instructions to Bidders and
the Contract Documents prepared by the City of Farmington and Greer Stafford/SJCF Architecture,
Inc. for the above mentioned project, we, the undersigned, hereby propose to Furnish All Materials
and Equipment and to Perform All Labor for and incidental to the Work, offer to enter into a Contract
to perform the Work for the Sum of:
TOTAL BASE BID ITEMS A THROUGH C INCLUSIVE IN WORDS: THE SUM OF
DOLLARS AND
CITY OF FARMINGTON FORM AF-3
CENTS.
CITY OF FARMINGTON, NEW MEXICO
COST PROPOSAL, FORM AF-3
The following are Alternates for specific portions of the Work as listed. The undersigned proposes to
perform the Work called for in the following Alternates for the described additions to the above Base
Bid. Refer to Section 01 23 00 for complete description of Alternate Work.
Alternate prices are not part of evaluation, but will be reviewed.
ITEM #
QTY
UOM
DESCRIPTION
Additive
Alternate #1
1
LS
Outdoor Trellis and Steel Pergola
Additive
Alternate #2
1
LS
Pop Jet Fountain
Additive
Alternate #3
1
LS
Digital Marque
Additive
Alternate #4
1
LS
Admin Office Remodel
PRICE
The following are Unit Prices for specific portions of the Work as listed. The Undersigned hereby
agrees that the following Unit Prices will prevail for such additions; it being understood, however, that
the Owner may reject any such Unit Prices at the time of acceptance of the proposal (Bid). The
following is the list of Unit Prices:
ITEM #
UOM
DESCRIPTION
1
SQ FT
Stucco Replacement
2
SQ FT
Remove and replace existing 5/8”
gypsum board with new 5/8”
gypsum board
CITY OF FARMINGTON FORM AF-3
UNIT PRICE
ADDENDUM #2
8/2017
ADDENDUM #2
ADDENDUM #2
ADDENDUM #2
ADDENDUM #2
8/2017
ADDENDUM #2
ADDENDUM #2
8/31/2017 3:41:13 PM
LEGEND:
AREA OF EXISTING ASBESTOS VINYL TILE
TO REMAIN AND BE COVERED WITH FLOOR
TYPE V2
AREA OF EXISTING CARPET REMOVAL
AREA OF 3'-0" WIDE SLAB SAWCUT & REPLACEMENT,
REFER TO PLUMBING
EXISTING WALL TO REMAIN
C:\Users\smeza.MAIN\Documents\FCC Expansion_R17_smeza.rvt
ENTIRE OR PORTION OF EXISTING WALL
TO BE DEMOLISHED
FARMINGTON CIVIC CENTER RENOVATIONS &
EXPANSION
CITY OF FARMINGTON
JOB NO.
5264.00
DATE
08/31/17
PAGE
ADD-02
-01
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
SECTION 07 21 19
FOAMED-IN-PLACE INSULATION
PART 1 GENERAL
1.01 SECTION INCLUDES
A.
Foamed-in-place insulation.
1.
In locations idendentified in the drawings and details.
1.02 REFERENCE STANDARDS
A.
ASTM C518 - Standard Test Method for Steady-State Thermal Transmission Properties by Means of the Heat
Flow Meter Apparatus; 2010.
B.
ASTM D2842 - Standard Test Method for Water Absorption of Rigid Cellular Plastics; 2012.
C.
ASTM E84 - Standard Test Method for Surface Burning Characteristics of Building Materials; 2015a.
D.
ASTM E96/E96M - Standard Test Methods for Water Vapor Transmission of Materials; 2014.
E.
ASTM E283 - Standard Test Method for Determining the Rate of Air Leakage Through Exterior Windows,
Curtain Walls, and Doors Under Specified Pressure Differences Across the Specimen; 2004 (Reapproved 2012).
F.
ASTM E2178 - Standard Test Method for Air Permeance of Building Materials; 2013.
1.03 ADMINISTRATIVE REQUIREMENTS
A.
Preinstallation Meeting: Convene one week prior to commencing work of this section.
1.04 SUBMITTALS
A.
See Section 01 30 00 - Administrative Requirements, for submittal procedures.
B.
Product Data: Provide product description, insulation properties, and preparation requirements.
C.
Certificates: Certify that products of this section meet or exceed specified requirements.
D.
Manufacturer's Installation Instructions: Indicate special procedures, and perimeter conditions requiring special
attention.
1.05 QUALITY ASSURANCE
A.
Manufacturer Qualifications: Company specializing in manufacturing products of the type specified in this
section, with not less than three years of documented experience.
B.
Applicator Qualifications: Company specializing in performing work of the type specified, with minimum three
years documented experience.
1.06 FIELD CONDITIONS
A.
Do not apply foam when temperature is below that specified by the manufacturer for ambient air and substrate.
B.
Do not apply foam when temperature is within 5 degrees F of dew point.
PART 2 PRODUCTS
2.01 MATERIALS
A.
Foamed-In-Place Insulation: Medium-density, rigid or semi-rigid, open or closed cell polyurethane foam;
foamed on-site, using blowing agent of water or non-ozone-depleting gas.
1.
Regulatory Requirements: Conform to applicable code for flame and smoke limitations.
2.
Aged Thermal Resistance: R-value of 5 (deg F hr sq ft)/Btu, minimum, when tested at 1 inch thickness in
accordance with ASTM C518 after aging for 180 days at 75 degrees F.
3.
Water Vapor Permeance: Vapor retarder; 4 perm, maximum, when tested at intended thickness in
accordance with ASTM E96/E96M, desiccant method.
4.
Water Absorption: Less than 3.5 percent by volume, maximum, when tested in accordance with ASTM
D2842.
5.
Air Permeance: 0.004 cfm/sq ft, maximum, when tested at intended thickness in accordance with ASTM
E2178 or ASTM E283 at 1.5 psf.
6.
Closed Cell Content: At least 90 percent.
FOAMED-IN-PLACE INSULATION
07 21 19 - 1
8/31/2017
FCC Renovation & Expansion
7.
8.
9.
G/S SJCF Arch 5164.00
Surface Burning Characteristics: Flame spread/Smoke developed index of 25/450, maximum, when tested
in accordance with ASTM E84.
Nominal Density: 1.75 lbs / cuft, when tested in accordance with ASTM D 1622.
Products:
a. Dow Chemical Company; Froth-Pak Foam Insulation: www.dow.com.
b. Commercial Thermal Solutions, Inc; Tiger Foam Insulation: www.tigerfoam.com.
c. Fomo Products, Inc.; Handi Foam Insulation: www.fomo.com.
d. Substitutions: See Section 01 60 00 - Product Requirements.
PART 3 EXECUTION
3.01 EXAMINATION
A.
Verify work within construction spaces or crevices is complete prior to insulation application.
B.
Verify that surfaces are clean, dry, and free of matter that may inhibit insulation adhesion.
3.02 PREPARATION
A.
Mask and protect adjacent surfaces from over spray or dusting.
B.
Apply primer in accordance with manufacturer's instructions.
3.03 APPLICATION
A.
Apply insulation in accordance with manufacturer's instructions.
B.
Apply insulation by spray method, to a uniform monolithic density without voids.
C.
Patch damaged areas.
D.
Where applied to voids and gaps assure space for expansion to avoid pressure on adjacent materials that may
bind operable parts.
E.
Trim excess away for applied trim or remove as required for continuous sealant bead.
3.04 PROTECTION
A.
Do not permit subsequent construction work to disturb applied insulation.
END OF SECTION
FOAMED-IN-PLACE INSULATION
07 21 19 - 2
8/31/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
SECTION 09 68 00
CARPETING
PART 1 GENERAL
1.01 SECTION INCLUDES
A.
Carpet tile, loose laid with edges and control grid adhered.
B.
Carpet tile.
C.
Accessories
D.
Floor preparation by General Contractor.
1.02 RELATED REQUIREMENTS
A.
Section 03 30 00 - Cast-in-Place Concrete: Restrictions on curing compounds for concrete slabs and floors.
B.
Section 09 6500 - Resilient Flooring: Base and flooring transition accessories.
1.03 REFERENCE STANDARDS
A.
ASTM D2859 - Standard Test Method for Ignition Characteristics of Finished Textile Floor Covering Materials;
2006 (Reapproved 2011).
B.
ASTM E648 - Standard Test Method for Critical Radiant Flux of Floor-Covering Systems Using a Radiant Heat
Energy Source; 2014c.
C.
ASTM F710 - Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring; 2011.
D.
CRI (CIS) - Carpet Installation Standard; Carpet and Rug Institute; 2011.
E.
NFPA 253 - Standard Method of Test for Critical Radiant Flux of Floor Covering Systems Using a Radiant Heat
Energy Source; 2015.
1.04 SUBMITTALS
A.
See Section 01 30 00 - Administrative Requirements, for submittal procedures.
B.
Product Data: Provide data on specified products, describing physical and performance characteristics; sizes,
patterns, colors available, and method of installation.
C.
Samples: Submit two carpet tiles illustrating color and pattern design for each carpet color selected.
D.
Manufacturer's Installation Instructions: Indicate special procedures and perimeter conditions requiring special
attention.
E.
Maintenance Data: Include maintenance procedures, recommended maintenance materials, and suggested
schedule for cleaning.
F.
Maintenance Materials: Furnish the following for Owner's use in maintenance of project.
1.
See Section 01 60 00 - Product Requirements, for additional provisions.
2.
Extra Carpet Tiles: Quantity equal to 5 percent of total installed of each color and pattern installed.
1.05 QUALITY ASSURANCE
A.
Manufacturer Qualifications: Company specializing in manufacturing specified carpet tile with minimum three
years documented experience.
B.
Installer Qualifications: Company specializing in installing carpet tile with minimum three years documented
experience and approved by carpet tile manufacturer.
C.
Preinstallation Meeting: Convene one week prior to commencing work related to products of this section;
require attendance of all affected installers.
1.06 FIELD CONDITIONS
A.
Do not install carpet until spaces are enclosed and weathertight, wet work in spaces is complete and dry, and
ambient temperature and humidity conditions are maintained at occupancy levels during the remainder of the
construction period.
B.
Store materials in area of installation for minimum period of 24 hours prior to installation.
CARPETING
09 68 00 - 1
8/31/2017
FCC Renovation & Expansion
C.
G/S SJCF Arch 5164.00
Maintain 65 to 90 deg F ambient temperature with a maximum relative humidity of 65%, 48 hours prior to,
during and 72 hours after installation.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A.
Basis of Design:
1.
InterfaceFLOR, Inc.: www.interfaceflor.com.
B.
Prior Approvals:
1.
Other manufacturers wishing to submit for prior approval must submit 1 full sample of each color and
pattern that they believe matches the specified carpet tiles. Requests to use equivalent products of other
manufacturers shall be submitted in accordance with Section 01 60 00 - Product Requirements. Architect
reserves right to reject proposed substitutions on basis of color and pattern compatibility even though
fabrication and materials are equivalent.
2.02 MATERIALS
The following carpet products/lines are approved:
A.
Modular Carpet Tiles:
1.
Product: As schedueled below manufactured by InterfaceFLOR, Inc..
a. Construction: Tufted pattern loop.
b. Yarn System: 100 percent universal type 6,6 nylon with post-consumer content.
c. Dye Method: 100 percent solution dyed.
d. Dye Lots: Non-mergeable.
e. Tufted Yarn Weight: 16 oz/sy.
f.
Gauge: 1/10 inch.
g. Pile Height: 0.11 inch.
h. Pile Thicknes: 0.062 inch.
i.
Pile Density: 9,290 oz/cy.
j.
Green Label Plus.
k. Backing: GlasBac or GlasBac RE by InterfaceFlor.
l.
Traffic Classification: Heavy.
m. Size: 25 cm x 1 m (8.845 x 39.38 inch)
n. Color: As selected from manufacturer's full range.
o. Pattern: Ashlar.
p. Contractor shall allow for a mixture of 33 percent of the above specified carpet tile
products/styles/colors for field and accent tiles.
2.
Carpet Tile Schedule:
a. Scheduled "C1"
1) Collection: Aerial
2) Style: 163110AK00
3) Color: 104883 Greige/Honey
4) Installation Pattern: Ashlar
b. Scheduled "C2"
1) Collection: Surreal Pattern Library
2) Style: 1237202500
3) Color: 101049
4) Pattern: Labyrinth M0560
5) Fiber Verification – Certification from the fiber producer verifying use of premium branded,
type 6,6 or 6 fiber in the submitted carpet product. Premium branded fibers are identified as
Invista, Aquafil, Solutia or Universal. Fibers extruded by carpet mills will be considered
“unbranded” for purposes of this specification. All fibers must have a modification ratio of 2.5
or less.
6) Tufted Yarn Weight: 23 oz/yd squared.
7) Machine Gauge: 5/64 in.
CARPETING
09 68 00 - 2
8/31/2017
FCC Renovation & Expansion
c.
d.
G/S SJCF Arch 5164.00
8) Pile Height: .21 in
9) Pile Thickness: .156 in
10) Stitches: 10.66/in
11) Pile Density: 5308
12) Size: 19.69 in x 19.69.
13) No substitutions allowed for this carpet type
Scheduled "C3"
1) Field Color and Stair Threads
(a) Collection: Harmonize
(b) Style: 138720ak00
(c) Color: 104046 Mesquite
(d) Installation Pattern: Ashlar
2) Accent Color and Stair Risers
(a) Collection: Ground Waves
(b) Style: 138730AK00
(c) Color: 104058 Mesquite/Colors
(d) Installation Pattern: Ashlar
(e) Provide 20% of the accent color
Scheduled "C4"
1) Field Color and Satir Threads
(a) Collection: Ground Waves Verse
(b) Style: 163130AK00
(c) Color: 104906 Mesquite/Colors
(d) Installation Method: Ashlar
(e) Carpet Tile Adhesive to be used to adhere carpet tiles in sloped floor areas and stair
threads and risers:
2) Stair Risers:
(a) Collection: Ground Waves
(b) Style: 138730AK00
(c) Color: 104058 Mesquite/Colors
(d) Carpet Tile Adhesive to be used to adhere carpet tiles in sloped floor areas and stair
threads and risers.
B.
Modular Entry Carpet Tiles:
1.
Product: Flor & Super Flor as manufactured by InterfaceFLOR, Inc..
a. Color: As selected from manufacturer's full range.
b. Construction: Hair tile, needle punch.
c. Yarn System: 83 percent nylon, 17 percent polyester
d. Dye Lots: Non-mergeable.
e. Pile Height: 0.16 inch.
f.
Pile Thickness: 0.165 inch.
g. Pile Density: 8,945 oz/c7
h. Total Thickness: 0.32 inch.
i.
Backing: Graphlar by InterfaceFlor.
j.
Traffic Classification: Severe.
k. Size: 50 cm x 50 cm.
l.
Color: As selected from manufacturer's full range.
m. Pattern: Quarter-turn.
C.
Prior Approvals:
1.
Manufacturers wishing to submit for prior approval must submit 1 full sample of each color and pattern
that they believe matches the specified carpet tiles. Requests to use equivalent products of other
manufacturers shall be submitted in accordance with Section 01 60 00 - Product Requirements. Architect
CARPETING
09 68 00 - 3
8/31/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
reserves right to reject proposed substitutions on basis of color and pattern compatibility even though
fabrication and materials are equivalent.
2.03 ACCESSORIES
A.
Sub-Floor Filler: White premix latex; type recommended by flooring material manufacturer.
B.
Stair nosings for seating area stairs in theater to be specified under the electrical lighting specifications.
C.
Stair Nosing: As specified in Section 09 65 00.
D.
Adhesives for stair nosings:
1.
Compatible with materials being adhered; maximum VOC content of 50 g/L; CRI (GLP) certified; in lieu
of labeled product, independent test report showing compliance is acceptable.
a. Water-resistant, mildew-resistant, nonstaining type to suit products and subfloor conditions indicated,
that complies with flammability requirements for installed carpet and is recommended or provided by
carpet manufacturer
E.
Carpet Tile Adhesive to be used to adhere carpet tiles in sloped floor areas and stair threads and risers:
1.
Products:
a. Stauf USA, LLC; D737 High-Tack: www.staufusa.com/#sle.
b. Substitutions: Section 01 60 00 - Product Requirements.
F.
Glue: Installation shall be free of glue (sprayed or spread).
G.
Installation connectors: Compounded acrylic adhesive, applied to PET polyester backing with PET polyester
release liner (clear 3” x 3” polyester squares with small quantity of a pressure sensitive adhesive applied on one
side of the polyester film). The squares connect the carpet modules together to form a stable surface over hard
surface. The connectors shall contain no liquid components, have “zero” calculated VOC’s and help to minimize
floor prep in all future installations.
H.
Ancillary Materials: To be selected by installation provider to meet specifications and project requirements.
PART 3 EXECUTION
3.01 EXAMINATION
A.
Verify that sub-floor surfaces are smooth and flat within tolerances specified for that type of work and are ready
to receive carpet tile.
B.
Verify that sub-floor surfaces are dust-free and free of substances that could impair bonding of adhesive
materials to sub-floor surfaces.
C.
Cementitious Sub-floor Surfaces: Verify that substrates are dry enough and ready for flooring installation by
testing for moisture and pH.
1.
Test in accordance with ASTM F710.
2.
Remove coatings, including curing compounds, and other substances that are incompatible with adhesives
and that contain soap, wax, oil, or silicone, without using solvents. Use mechanical methods recommended
in writing by carpet manufacturer.
D.
Verify that required floor-mounted utilities are in correct location.
3.02 PREPARATION
A.
Prepare floor substrates as recommended by flooring and adhesive manufacturers.
B.
General Contractor to prepare the sub-floor as follows:
1.
Remove sub-floor ridges and bumps. Fill minor or local low spots, cracks, joints, holes, and other defects
with sub-floor filler.
2.
Fill or level cracks, holes and depressions 1/8 inch wide or wider, and protrusions more than 1/32 inch,
unless more stringent requirements are required by manufacturer's written instructions.
3.
Apply, trowel, and float filler to achieve smooth, flat, hard surface. Prohibit traffic until filler is cured.
C.
Vacuum clean substrate.
CARPETING
09 68 00 - 4
8/31/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
3.03 INSTALLATION (GENERAL)
A.
Modules should be designed such that they create a “floating floor” with no adhesion to the slab, eliminating any
future floor preparation charges on subsequent installations.
B.
Comply with manufacturer’s instructions and recommendations. A “no-glue” waterless method of installation is
preferred using materials described in Part 2 above. In the event a releaseable glue method of installation is
required for any part of the installation, consult with Architect and Manufacturer.
3.04 INSTALLATION
A.
Starting installation constitutes acceptance of sub-floor conditions.
B.
Install carpet tile in accordance with manufacturer's instructions and CRI (CIS).
C.
Blend carpet from different cartons to ensure minimal variation in color match.
D.
Maintain dye lot integrity. Do not mix dye lots in same room or space.
E.
Cut carpet tile clean. Fit carpet tight to intersection with vertical surfaces without gaps.
F.
Locate change of color or pattern between rooms under door centerline.
G.
Installation Method: Free lay. Install carpet tiles without adhesvies, with pressure-sensitive installation
connectors. .
H.
Trim carpet tile neatly at walls and around interruptions.
I.
Complete installation of edge strips, concealing exposed edges.
3.05 INSTALLATION ON STAIRS
A.
Use one piece of carpet for each tread and the riser below. Apply seam adhesive to all cut edges.
B.
Lay carpet with pile direction in the length of the stair.
C.
Adhere carpet tight to stair treads and risers.
3.06 CLEANING
A.
Remove excess adhesive without damage, from floor, base, and wall surfaces.
B.
Remove and dispose of debris and unusable scraps.
C.
Replace carpet where damaged, flawed and can't be cleaned satisfactorily.
D.
Remove yarns that protrude from carpet surface.
E.
Clean and vacuum carpet surfaces.
F.
Protect carpet against damage from construction operations and placement of equipment and fixtures during the
remainder of construction period.
END OF SECTION
CARPETING
09 68 00 - 5
8/31/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
SECTION 27 41 00
AUDIO-VIDEO SYSTEMS
P1 GENERAL
1.01
REFERENCE TO OWNER’S GENERAL CONDITIONS
A.
1.02
1.03
1.04
The Owner’s General Conditions shall be considered part of this Specification. Unless this Section
contains statements, which are more definitive or more restrictive than those contained in the Owner’s
General Conditions, this Specification shall not be interpreted as waiving or overruling any
requirements expressed in the General Conditions.
RELATED DOCUMENTS
A.
Drawings and general provisions of the Contract, including General and Supplementary Conditions
and other Division 01 Specification Sections, apply to this Section.
B.
Electrical infrastructure (electrical j-boxes, conduit) for AV systems is shown on AV drawings and is
the responsibility of the Div. 26 Electrical Contractor.
C.
Section 274101 “DEMOLITION FOR AUDIO-VISUAL SYSTEMS”
RELATED WORK
A.
AV Contractor shall coordinate with Electrical Contractor on raceway/junction box locations for
audio-video equipment and routing of audio, video, control, and power cables/raceway from
equipment, terminal and pull boxes to system equipment racks.
B.
AV Contractor shall be responsible for the coordination of equipment and materials provided and
installed by others where they relate to AV systems, unless otherwise shown in this Section or the
Drawings, shall include but are not limited to:
1.
Electrical Outlets
2.
Floor boxes
3.
Furniture
4.
Conduit, Raceway and Cable Tray
5.
Junction Boxes
6.
Telecommunications Outlets
7.
Lighting Control Devices
8.
Building Management Systems
DEFINITIONS
A.
The following shall serve as general identifiers as specified herein.
1.
Owner – City of Farmington, New Mexico
2.
Consultant – The Consultant is D.L. Adams Associates.
3.
Architect – Greer Stafford/SJCF Architecture, Inc.
4.
Contractor – The Contractor is the firm submitting a proposal to furnish and install the Work
as defined within this Specification.
5.
Project – The Project is the Audio-Visual Systems installation in the facilities of the
Farmington Civic Center Renovations & Expansion.
6.
Work – The term “Work” means all construction and services specified within this document.
The Work includes all related labor, materials, equipment, and services provided, or to be
provided, by the Contractor to fulfill the proposal’s obligations.
7.
Drawings – The term “Drawings” means all Theatre Systems Drawings and associated
sketches, details, riser diagrams, etc.
AUDIO-VISUAL SYSTEMS
27 41 00 - 1
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
B.
As used in the Drawings and Specifications for the Work, certain non-technical words and phrases
shall be understood to have specific meanings as follows, regardless of indications to the contrary in
the General Conditions or other documents governing the Work.
1.
“Furnish” – Purchase and deliver to the project site complete with every necessary
appurtenance and support, all as part of the Audio-Video Systems Work. Purchasing shall
include payment of all sales taxes and other surcharges as may be required to assure that
purchased items are free of all liens, claims, or encumbrances.
2.
“Install” – Unload at the delivery point at the site and perform every operation necessary to
establish secure mounting and correct operation at the proper location in the project, all as
part of the Work.
3.
“New” – Manufactured within the past year and never used.
4.
“Provide” – Furnish and Install.
C.
Regardless of their usage in codes or other industry standards, certain words or phrases as used in the
Drawings or Specifications for the Work, shall be understood to have the specific meanings as
described to them in the following list:
1.
“Audio-Video Closet” – The enclosed area or room specifically designated for the routing,
termination, and/or cross connecting of Audio-Video Systems cable (i.e. riser cable) to other
Audio-Video Systems cable and/or equipment.
2.
“AV” – Audio-Video
3.
“AVC” – Audio-Video Systems Contractor.
4.
“AV System(s)” – Audio-Video System(s), includes all components contained herein that
work in conjunction to create and completely integrated and fully functioning system as
described within the Drawings and Specifications
5.
“AV Systems Control Room” and/or “AV Systems Headend” – The enclosed area or room
specifically designated for the routing, termination, and/or cross connecting of audio and
video system cable (i.e. riser cable) to other audio or video system cable, and/or equipment
and racks.
6.
“Circuit” – Any specific run of circuitry.
7.
“Circuitry” – Any Work which consists of wires, cables, raceways, and/or specialty wiring
method assemblies complete with associated junction boxes, pull boxes, outlet boxes, joints,
couplings, splices, and connections except where limited to a lesser meaning by specific
description.
8.
“Concealed” (as applied to circuitry) – Covered completely by building materials, except for
penetrations (by boxes and fittings) to a level flush with the surface as necessitated by
functional or specified accessibility requirements.
9.
“Exposed” (as applied to circuitry) – Not covered in any way by building materials.
10.
“NIC” – Not in Contract
11.
“Normal Work Conditions” – Locations within building confines that are not damp, wet, or
hazardous and that are not used for air handling.
12.
“OFE” – Owner Furnished Equipment
13.
“Patch Panel” – A System of terminal blocks, patch cords, and backboards that facilitate
administration of cross-connecting cables.
14.
“Raceway” – Any pipe, duct, extended enclosure, or conduit (as specified for a particular
System) which is used to contain wires and which is of such nature as to require that the
wires be installed by a “pulling in” procedure.
15.
“Riser” – Shall refer to the portion of the installation that transmits between building floors
(or between Audio-Video Systems rooms), also referred to as “Backbone Cabling”.
16.
“Standard” (as applied to wiring devices) – Not of a separately designated individual type.
17.
“System” – See “AV Systems”
18.
“Wiring” – see “Circuitry”
D.
Additional Terms:
AUDIO-VISUAL SYSTEMS
27 41 00 - 2
7/26/2017
8/30/2017
FCC Renovation & Expansion
1.
2.
3.
4.
5.
6.
1.05
G/S SJCF Arch 5164.00
The term “shall” is mandatory; the term “will” is informative; the term “should” is advisory;
and the term “provide” means furnish and install.
Where the word “conduit” is used without specific reference to type, it shall be understood to
mean “raceway”.
The term “custom” indicates systems or components that shall be designed and fabricated by
the Contractor based on the drawings and specifications.
The term “future” indicates systems or components that will be added to the system later but
shall be provisioned for now.
The term “equal” indicates systems or equipment that is of the same size, color, design,
function, efficiency, etc. as of that specified.
Reference to “U.L. (Materials Construction) Standards” shall mean the “Standards for
Safety” published by Underwriters Laboratories, Inc
SCOPE OF WORK
A.
General:
1.
The work as described herein shall be furnished and installed by one firm alone, hereafter
referred to as the AV Contractor. The AV Contractor shall furnish and install all equipment,
and audio/video signal and control wiring for the AV Systems described herein. The
Contractor further agrees that they shall provide all Work as may be required to make a
complete and fully functioning system of that which may not be fully defined in the Contract
Documents.
2.
The specifications and drawings shall be read and used together, system features which are
mentioned in one are not necessarily shown in the others. In case of conflict between the
drawings and specifications, request clarification. It shall be understood that the Equipment
Lists, Specifications and Drawings are complementary. Where there are conflicts within the
documents, the overall design intent shall govern.
3.
The work provided shall be complete and the systems shall be fully operational as shown on
audio visual system "AV" drawings and described in Paragraph 1.7 herein.
4.
Equipment not mentioned herein nor shown on drawings but necessary to meet the
requirements of this section shall be provided without claim for additional payment.
5.
The project documentation is, in general, diagrammatic and/or developed to communicate
design intent. The Contractor shall coordinate the installation of all devices and/or equipment
with the Owner prior to installation based on the existing field conditions.
6.
The AV Contractor shall coordinate all installed items with associated trades (electrical,
mechanical, Telecom, etc.) including all necessary cable pass-thrus and structural
needs/requirements.
7.
The AV Contractor shall provide all software programming required to provide fully
operational systems.
8.
AV Contractor shall conduct a frequency audit of the site prior to selection of wireless
operating frequencies. Select frequencies such that systems are free of interference. Include
an intermodulation interference analysis. Coordinate frequencies and specific
transmitter/receiver selection using professional wireless audio systems software.
9.
The AV Contractor shall coordinate the specific programming requirements of the AV
Control System with a designated Owner representative, including touch screen layouts and
page navigation. All programming written for this project shall be the property of the Owner
and shall be provided to the Owner upon completion.
10.
Digital video systems in this design shall employ an EDID management strategy and shall be
HDCP compliant.
B.
Work Included Elsewhere
AUDIO-VISUAL SYSTEMS
27 41 00 - 3
7/26/2017
8/30/2017
FCC Renovation & Expansion
1.
2.
3.
C.
1.06
G/S SJCF Arch 5164.00
Installation of raceway, pull-boxes, plywood backboards and floor-boxes (provided under
electrical Work). Coordination is required within the design to verify the appropriate
raceways are in place.
Installation and termination of network systems except dedicated AV network systems.
Cutting, patching and painting of walls, unless damaged performing the work described
herein.
Coordinated Work
1.
Coordinate with related trades to schedule the Work and ensure a complete installation in
accordance with the schedule outlined by the Owner.
2.
Coordinate all IP device requirements with the Telecom Contractor, Owner, and General
Contractor.
3.
Coordinate all building network connectivity requirements with the Telecom Contractor and
Owner.
4.
Coordinate furniture and custom millwork with furniture and millwork providers.
5.
Coordinate structural backing and support requirements with General Contractor.
6.
AV Contractor shall participate in pre-construction conferences with General Contractor,
Electrical Contractor, Theatre Contractor and Design Team to coordinate new electrical
conduit and equipment routing and locations prior to installation.
GENERAL CONDITIONS
A.
The Contractor represents that they are familiar with, and have expertise in the Work of this nature
and scope.
B.
The Contractor shall comply with all of the regulations, including safety regulations of national, city,
local and other government agencies having jurisdiction concerning the work of the Contractor. The
Contractor shall give all notices and comply with all laws, ordinances, codes, rules, and regulations
bearing on the conduct of the Work. If the Contractor performs any work, which is contrary to such
laws, ordinances, codes, rules and regulations, they shall make all changes for compliance and bear all
associated costs.
C.
The Contractor shall be responsible to provide and maintain a storage facility as required. If this
storage facility is required to be on-site it shall be the Contractor's responsibility to coordinate the size
and spatial requirements with the General Contractor. The Contractor shall assume full responsibility
for the storage facility and all contents, unless otherwise indicated by the Owner.
D.
The Contractor shall provide all protection necessary to safeguard their work from damage by their
operations and the operations of others. Unless the Contractor proves to the Owner’s satisfaction that
the Work has been damaged by others, the Contractor shall promptly repair, adjust, and clean all
defective installations and bear all associated costs.
E.
All of the Contractor's work shall be tested and inspected by all authorities having jurisdiction and in
accordance with all specifications. The Contractor shall coordinate and cooperate fully and shall
provide at no additional cost to the Owner, manpower, drawings, facilities, scaffolds, etc. to
reasonably assist the inspectors.
F.
The Owner reserves the right to furnish any materials necessary for the Project.
G.
All permits required for any part of the Contractor's work shall be procured and paid for by the
Contractor. The Contractor shall determine all permits required and transmit this information to the
Owner. If it is determined that the Contractor’s work falls reasonably within another party’s permit
(General Contractor, Electrician, etc.) the Contractor shall not be required to procure additional
permits provided written authorization is provided to the Contractor by the party holding the permit.
H.
The Contractor must state if they intend to utilize a subcontractor, and provide said subcontractor's
name and address. The subcontractor shall comply with all the same rules, regulations, laws and
AUDIO-VISUAL SYSTEMS
27 41 00 - 4
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
codes, licenses, etc. as required by the Contractor and as specified herein. The Owner and/or
Consultant reserves the right to approve or disapprove any subcontractor proposed by Contractor.
I.
The Contractor, upon receiving notice from Owner and/or Consultant that the Contractor has
furnished inferior, improper or unsound work or materials (including equipment), or work or materials
at variance with that which is specified, will, within 24 hours, proceed to remove such work or
materials and make good all other work or materials damaged thereby, and, at the option of the
Owner, the Contractor shall immediately replace such work or materials with work or materials as
specified. The removal, replacement, and repair shall be performed at such times and with manpower
sufficient, in the judgment of the Owner, so as to avoid disturbance to occupants, or other ongoing
work for the Project.
1.
If the Contractor does not remove such unsound Work within a reasonable time, the Owner
may remove it and may store the material at the expense of the Contractor. If the Contractor
does not pay the expenses of such removal within ten (10) days’ time thereafter, the Owner
may, upon written notice, sell such materials at auction or at private sale and shall account for
the net proceeds thereof, after deducting all the costs and expenses that should have been
borne by the Contractor and all expenses of the sale.
2.
The Owner shall have the authority at all times, until final completion and acceptance of the
Work, to inspect and reject work and materials which in its judgment are not in conformity
with the Drawings and Details, Room Data Sheets and Specifications, and its decision in
regard to character and value of Work shall be final and conclusive on both contracting
parties. If the Owner permits said Work or materials to remain, the Owner shall be allowed
the difference in value or shall at its election have the right to have said Work or materials
repaired or replaced, as well as the damage caused thereby, at the expense of the Contractor,
at any time within one (1) year after the completion of the entire project, or within such
longer period as may be covered by any guaranty; and neither payments made to the
Contractor, nor any other acts of the Owner, shall be construed as evidence of acceptance,
waiver, or estoppels.
3.
Any expense incurred by the Owner in connection with the foregoing, shall be borne by the
Contractor, and the Owner may withhold money due to the Contractor or recover money
already paid to the Contractor, to the extent of such expense.
J.
The Drawings for the Work utilize symbols and schematic diagrams that have no dimensional
significance. The Work shall be installed to fulfill the diagrammatic intent expressed on the
Drawings, field layouts, and shop drawings of all trades.
K.
Certain details appear on the Drawings for the Work that are specified with regard to the
dimensioning and positioning of the Work. These are intended only for general information purposes.
They do not obviate field coordination for individual items of the indicated Work.
L.
Information as to general construction and architectural general construction and architectural features
and finishes shall be derived from the structural and architectural drawings and specifications, and
may require ongoing coordination with the Architect and/or Construction Team.
M.
The Work called for under this Contract shall be carried on simultaneously with the Work of other
trades and Owner functions in such a manner as to not delay the overall progress of the construction
project. The Contractor is responsible for all coordination of the Work with other trades and Owner.
N.
Include in the Work all necessary supervision and issuing of all coordination information to any other
trades who are supplying work to accommodate the Audio-Video Systems installation. For items of
equipment which are to be installed but not purchased as part of the Work, the Work shall include:
1.
Coordination of delivery
2.
Unloading from delivery trucks
3.
Safe handling and field storage up to the time of permanent placement in the project
4.
Correction of any damage to the item(s) caused by the Contractor
AUDIO-VISUAL SYSTEMS
27 41 00 - 5
7/26/2017
8/30/2017
FCC Renovation & Expansion
5.
O.
1.07
G/S SJCF Arch 5164.00
Mounting in place and connection(s) as specified
Items which are to be installed, but not purchased as part of the Work shall be carefully examined
upon delivery to the project. Claims that any of these items have been received in such condition that
their installation will require procedures beyond the reasonable scope of the Work will be considered
only if presented in writing within one (1) week of the date of delivery to the project of the items in
question. The Work includes all procedures necessary to put in satisfactory operation all items for
which no claims have been submitted as outlined above.
SUMMARY
A.
Applicable Locations:
1.
Theatre
2.
Convention Center
B.
Theater Descriptions and Functions
1.
Overall Description
a.
The Farmington Civic Center Theater sound reinforcement system will be provided
with several key upgrades to bring the Theatre AV system up to current ADA standards
as well as into compliance with current FCC requirements. The theatre will also receive
a new high-performance sound reinforcement system for use with local and regional
touring acts.
b.
Upgrades shall include:
1)
Audiovisual network.
2)
Wireless microphone upgrades.
3)
Assistive listening system.
4)
Audio Distribution.
5)
Sound Reinforcement System.
6)
Support Equipment
2.
Audiovisual Network:
a.
An audiovisual network shall be provided in the Theater, connected to the Audiovisual
network in the Convention Center. It shall be the responsibility of the AV contractor to
configure the AV network for the optimal transmission of digital audio, optimal digital
video transmission, and optimal transmission of control system protocols.
b.
The AV network shall consist of a one POE+ network switch located in the basement
amplifier rack. The AV contractor shall coordinate with switch manufacturer for
support as required to properly configure the AV network, including remote or on-site
manufacturer switch configuration.
c.
All network cabling provided by the AV contractor shall adhere to the applicable
Category 6A standards. Provide test reports prior to system checkout documenting
compliance with applicable standards for all installed network cables.
3.
Wireless microphone upgrades:
a.
Provide ten (10) channels of wireless microphone receivers to replace existing wireless
microphones in prohibited bands. Provide ten (10) new handheld transmitters with
condenser microphone heads and ten (10) new bodypack transmitters. Provide two (2)
new directional antennas mounted to the front of the technical booths with antenna
distribution for all new wireless microphone receivers. Connect new wireless
microphones to existing analog console with the existing interconnection cabling.
4.
Assistive listening system:
a.
Provide a new ADA-compliant RF assisted listening system, consisting of a transmitter
located in the basement amplifier rack, an antenna mounted on the side wall of the
theatre house, and an ADA-compliant compliment of receivers and telecoil neck loops.
Provide and install compliance signage. Coordinate location and mounting of signage
with Owner and Architect.
AUDIO-VISUAL SYSTEMS
27 41 00 - 6
7/26/2017
8/30/2017
FCC Renovation & Expansion
5.
6.
7.
C.
G/S SJCF Arch 5164.00
Audio distribution:
a.
Provide new aux/split outputs and an auxiliary main left and right inputs on the stage
right I/O plate.
b.
Provide new audio main left, main right, monitor 1-4 and dressing room inputs in the
Audio control booth.
Sound reinforcement system:
a.
Provide and install a new Digital Signal Processor (DSP) in the basement amplifier rack
to control and manage the new loudspeaker system.
b.
The DSP shall accept a contact closure signal from the fire alarm system (provided by
others) to mute the audio system.
c.
Provide and install a new exploded cluster and delay ring of loudspeakers below the
existing ceiling. Loudspeakers shall provide even and uniform coverage through the
house seating area. AV contractor to coordinate all penetrations required in ceiling with
GC.
d.
Loudspeakers to be custom color. AV contractor to submit requested color chips to
Architect and Owner for color selection and approval before ordering loudspeakers.
e.
Subwoofers shall be provided and located behind the existing speaker grille cloth.
Subwoofers shall be installed such that they provide high energy uniform low
frequency to the entire house seating area.
f.
Portable front fill loudspeakers and associated front fill connection plates shall be
provided near the stage lip.
g.
New amplifiers for the new main loudspeakers, delay loudspeakers, subwoofers, floor
monitor shall be provided in the basement amplifier rack.
h.
Provide and install new monitor output plates stage left and stage right.
Support Equipment:
a.
A 44RU floor-standing amplifier equipment rack shall be provided in the basement
storage room, complete with cable management, blank panels, and accessories as
required.
b.
Power sequencing shall be provided in the equipment rack and a remote trigger shall be
located in the audio control booth to turn on/off or place in standby key AV equipment
in the basement amplifier rack.
Convention Center Descriptions and Functions:
1.
Overall Description:
a.
The Farmington Convention Center upgrade and expansion shall include upgrades to
the AV systems in the existing exhibit hall. Additional spaces requiring AV shall
include two (2) new meeting rooms, an Outdoor Patio, and expansion of the Exhibit
Hall.
b.
Upgrades shall include:
1)
Audiovisual Network.
2)
Control system.
3)
Video system.
4)
Audio systems.
2.
Audiovisual Network:
a.
Audio, video, and control shall be converted to digital signals and be transported over
the network. It shall be the responsibility of the AV contractor to configure the AV
network for the optimal transmission of digital audio, digital video, and control
transmission.
b.
The AV network shall consist of a two POE+ network switches located in the AV
control room rack. The AV contractor shall coordinate with switch manufacturer for
support as required to properly configure the AV network, including remote or on-site
manufacturer switch configuration.
AUDIO-VISUAL SYSTEMS
27 41 00 - 7
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
c.
3.
All network cabling provided by the AV contractor shall adhere to the applicable
Category 6A standards. Provide test reports prior to system checkout documenting
compliance with applicable standards for all installed network cables.
Control System:
a.
A control system with a hardware central controller shall be provided to integrate and
simplify equipment controls and user functions.
b.
The control system shall monitor all equipment that provides bidirectional feedback and
report any failures or errors to an Owner designated representative. Coordinate
communication method (e-mail, etc.) with Owner.
c.
The control system shall accept a contact closure signal from the fire alarm system
(provided by others) to mute the audio system. A contact closure signal from any other
emergency systems (provided by others) shall be connected to the central controller and
shall mute audio when the emergency system is triggered.
d.
Touchscreen controllers shall be provided throughout the exhibit halls, meeting rooms,
Control Room, and Outdoor Patio. Each touch panel shall have password protection.
1)
The existing Exhibit Hall shall have a touch panel dedicated to each of the five
(5) zones and be mounted in the existing touch panel location and back boxes
where possible. touch panels shall provide local control to the exhibit hall in
which it is mounted. AV contractor to provide new back boxes or retrofit back
boxes as required to properly mount touch screens on wall.
2)
The Exhibit Hall Expansion shall have two (2) touch panel zones with new
touch panels located at the same height as the touch panels in existing Exhibit
Hall.
3)
Each meeting room shall have one (1) wall mounted touch panel at 42” AFF.
The touch panel shall provide local control to the meeting room.
4)
The Outdoor Patio shall have one (1) touch panel mounted with a weather proof
cover mounted at 42” AFF. The touch panel shall provide local control to the
Outdoor Patio.
5)
The Control Room shall have one (1) rack mounted touch panel. The Contorl
Room touch panel shall provide global control to the convention center as well
as be able to provide control of each individual space.
e.
Each touch screen mounted in the Exhibit Hall shall provide control over local inputs
including audio level control, mic/line preamp state, phantom power, Projector source
selection, projector control, screen control, projector lifts, and camera control. Each
touch screen shall also be able to control video and audio source routing and select
from the common sources such as CATV, Pandora, and Blu-ray. In addition, each touch
panel will have a secondary password level that allows access to control over the
common sources including CATV channel selection and Blu-Ray transport controls.
f.
Each touch screen mounted in the meeting rooms shall provide control over local inputs
including audio level control, mic/line preamp state, phantom power, display power,
and display source selection. Each touch screen shall also be able to control video and
audio source routing and select from the common sources such as CATV, Pandora, and
Blu-ray. In addition, each touch panel will have a secondary password level that allows
access to control over the common sources including CATV channel selection and BluRay transport controls.
g.
Each touch screen mounted in the Outdoor Patio shall provide control over local inputs
including audio level control, mic/line preamp state, phantom power, Each touch screen
shall also be able to control video and audio source routing and select from the common
sources such as CATV, Pandora, and Blu-ray. In addition, each touch panel will have a
secondary password level that allows access to control over the common sources
including CATV channel selection and Blu-Ray transport controls.
AUDIO-VISUAL SYSTEMS
27 41 00 - 8
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
h.
4.
The touch screen controller in the Control Room shall provide control over each
individual space, control over shared sources including the Blu-ray player, Pandora,
CATV and PTZ camera controls as well as provide the global control for room
combining set-ups including source routing of an input to any individual or
combination of displays within all rooms. These set-ups and configurations to be
coordinated with the Owner and Consultant.
i.
In general, the AV Contractor shall provide control and page layouts that provide the
operators easy intuitive control without limiting flexibility. All controls must include
but not be limited to the following:
1)
Fully develop touchscreen options and layouts through the process described in
Paragraph 1.08.C.
2)
General
a)
Power the system on/off, including provide shutdown conformation.)
b)
Provide camera control over both the exhibit hall camera as well as the
theatre camera with controls on selected touch panels as determined by
the Owner.
c)
PIN or password lock for base operation and a second level for advanced
controls, as requested by Owner.
3)
Typical video Control
a)
Video source select.
b)
Video source device controls where applicable.
c)
Power the video projector or display on/off.
d)
Lower/raise motorized projection screen as required. Provide a separate
control to raise/lower/stop screen.)
e)
Control projector lifts where applicable.
f)
Video mute.
4)
Audio control
a)
Provide audio level controls for both microphone and program audio
with mutes.
b)
Include a master audio level control.
c)
Input gain and phantom power settings.
d)
Route all audio sources to appropriate zone and/or space as required
(Control Room only.)
5)
Camera control
a)
Provide camera routing
b)
Provide pan, tilt, and zoom control
6)
Room/device status (Control Room only)
a)
Indicate projector lamp hours
b)
Provide service contact information
c)
Display monitored device errors, if any
Video System:
a.
Projectors, Screens and Displays
1)
Existing Exhibit Hall shall reuse the existing WXGA projectors and projection
screens.
2)
Two (2) new ceiling mounted wide screen (WXGA) video projectors with a
zoom lens shall be provided and installed in Exhibit Hall expansion. The
projector shall be similar to existing projectors in Exhibit Hall 1. AV Contractor
to confirm size, type and control method before purchase.
3)
Two (2) new motorized screens shall be provided in the Exhibit Hall Expansion.
these scenes shall be similar to the existing screens in Exhibit Hall 1 and shall be
16:10 format and approximately 198”diagonal. AV Contractor to confirm size,
type and control method to match existing screens before purchase.
AUDIO-VISUAL SYSTEMS
27 41 00 - 9
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
4)
5)
6)
5.
An 80” wall mounted display shall be provided and installed in Meeting Room 1
A 90” wall mounted display shall be provided and installed in Meeting Room 2.
A rack mounted display shall be provided and located in the Control Room as a
confidence monitor for all rooms.
7)
The Lobby displays are existing and shall be separate from the rest of the
system. they shall be connected through the building network to an Owner
furnished computer for content. The AV Contractor is to provide media payers
and software for each display. The Media players shall be mounted to the rear of
the existing displays
b.
Video Sources
1)
Common sources shall be located in the Control Room and be shared for all
spaces. The sources include:
a)
A Blu-ray player provided and installed by the AV Contractor.
b)
CATV receiver provided by Owner and installed by AV Contractor.
c)
Auxiliary VGA and HDMI input provided and installed in the equipment
rack by the AV contractor.
2)
Provided local video inputs in each exhibit hall and meeting room for
connection of portable video sources such as laptop computers. Inputs shall
include both VGA and HDMI video inputs.
3)
A PTZ camera shall be located in Exhibit Hall to provide the ability to view the
stage from different areas throughout the convention center.
4)
A PTZ camera shall be mounted in the Theatre to provide a video feed to the
convention center to support overflow. In addition to the convention center
having the capability to view and control the camera, the camera shall have the
capability to be controlled and viewed locally through the USB connection and
an Owner furnished laptop.
c.
Video transmission
1)
Each video input plate shall convert the video to digital for transmission to the
video projector and other displays via a digital video transmission system.
2)
The digital video shall be transported over CAT6A cabling through a POE+
network switch in the Control Room to each destination where it will be
converted back to HDMI.
3)
The video transmission system shall be capable of providing any input to any
output or multiple outputs simultaneously.
4)
All video transmission shall be HDCP compatible and provide correct EDID
information.
Audio System:
a.
The audio system shall provide consistent coverage throughout the Exhibit Hall as well
as the Outdoor Patio.
b.
Audio program from the Video system shall be provided from the AV network and
Audio embedded on the video shall be de-embedded within the DSP.
c.
Portable Assistive listening systems will be provided. Two (2) transmitters with
connection cables and ten 10 receivers with associated ear speakers and neck loops will
be provided.
d.
Exhibit Halls
1)
Each individual Exhibit hall shall have a dedicated zone. The system shall have
the capability to easily combine any or all zones as required.
2)
70V ceiling mounted full range loudspeakers shall be provided for sound
reinforcement and audio program playback. The AV Contractor shall provide
new wiring for all speakers.
AUDIO-VISUAL SYSTEMS
27 41 00 - 10
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
3)
e.
f.
8ohm ceiling mounted subwoofers shall be provided to extend the frequency
range and provide more low frequency content to the exhibit hall. The AV
Contractor shall provide new wiring for all speakers.
4)
Each zone shall have one (1) network audio interface plate that supports two (2)
XLR balanced inputs, A stereo unbalanced RCA input, and one (1) 3.5mm
stereo jack. The interface plate shall also have one (1) 3.5mm output. The XLR
inputs shall be switchable through the network for mic/line and phantom power.
5)
The AV system shall provide the capability to route audio from any input plate
to any destination including either meeting room, the exhibit halls, Outdoor
Patio, and the Control Room.
6)
Control Room aux inputs shall be capable of being routed to any destination.
7)
The AV network will provide main left and right audio from the theatre to the
convention center as a source. The theatre source shall be routable to any
destination and provide the ability to use any space within the convention center
as overflow with audio program from the Theatre when required.
Meeting Rooms
1)
70V ceiling mounted full range loudspeakers shall be provided for sound
reinforcement and audio program playback. The AV Contractor shall provide
new wiring for all speakers.
2)
Each meeting room shall have one (1) network audio interface plate that
supports two (2) XLR balanced inputs, A stereo unbalanced RCA input, and one
(1) 3.5mm stereo jack. The interface plate shall also have one (1) 3.5mm output.
The XLR inputs shall be switchable through the network for mic/line and
phantom power.
3)
The AV system shall provide the capability to route audio from any input plate
to any destination including either meeting room, the exhibit halls, Outdoor
Patio, and the Control Room.
4)
The AV system shall provide the capability to route audio from any input plate
to any destination including either meeting room, the exhibit halls, Outdoor
Patio, and the Control Room.
5)
Control Room aux inputs shall be capable of being routed to any destination.
6)
The AV network will provide main left and right audio from the theatre to the
convention center as a source. The theatre source shall be routable to any
destination and provide the ability to use any space within the convention center
as overflow with audio program from the Theatre when required.
7)
Outdoor Patio
1)
The Outdoor Patio shall be divided into seven (7) zones. Typically, the space
shall be treated as a single zone however the system shall have the capability to
easily turn off or lower volume levels in any defined area (zone).
2)
Speakers shall be 70v pole mounted speakers.
3)
The Outdoor Patio shall have one (1) network audio interface plate that supports
two (2) XLR balanced inputs, A stereo unbalanced RCA input, and one (1)
3.5mm stereo jack. The interface plate shall also have one (1) 3.5mm output.
The XLR inputs shall be switchable through the network for mic/line and
phantom power.
4)
The AV system shall provide the capability to route audio from any input plate
to any destination including either meeting room, the exhibit halls, Outdoor
Patio, and the Control Room.
5)
Control Room inputs shall be capable of being routed to the Outdoor Patio
speakers.
AUDIO-VISUAL SYSTEMS
27 41 00 - 11
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
D.
AV Contractor’s Qualifications:
1.
The work of this section will be contracted to a single firm, referred to as the AV Contractor,
for undivided responsibility.
2.
The AV Contractor shall be experienced in the installation of professional AV systems and
have completed within the past five years at least three AV system projects of a size and
scope comparable to the project described herein.
3.
The AV Contractor shall have factory-certified programmers for the programming of any
processing and control equipment used in this project. The AV Contractor shall have a
manufacturer certified programmer on staff for any specialized equipment requiring
programming for the duration of this project.
4.
The AV Contractor shall have capabilities and in-house facilities for installation, shop
fabrication and repair service of professional AV systems.
5.
The AV Contractor shall have on their full-time payroll at least one staff engineer having a
minimum five years of experience as a professional AV designer. In place of a qualified staff
engineer, the AV Contractor may retain a consulting engineer to direct the project. Prior to
bid acceptance, the qualifications of the consulting engineer shall be submitted for the
approval of the Consultant. Said staff or consulting engineer shall:
a.
Provide all technical liaisons between the AV Contractor and the Consultant.
b.
Represent the AV Contractor at meetings and conferences, and be present at the job site
for all inspections.
c.
Be responsible for supervision of all technical and engineering work required executing
the contract, approving, and signing the shop drawings.
6.
All Contractors desiring to submit bids for the installation of the audio-video systems
specified herein, not listed in below must be qualified in writing by the Consultant by
addendum prior to the bid opening.
7.
Bids submitted by Contractors who have not been qualified will not be accepted.
8.
Contractors not listed below, desiring to bid on this installation, shall submit the required
qualification statement of Paragraph 1.08.A. Qualification shall be subject to Consultant’s
approval.
E.
Qualified AV Contractors, listed in alphabetical order, are as follows:
1.
There are no pre-approved contractors at this time. All Contractors shall be required to
submit the required qualification statement in Paragraph 1.08.A.
F.
Minimum Performance Requirements: To meet the minimum performance requirements, the AV
Contractor shall be responsible for:
1.
Each component's conformance with the manufacturer's published specifications and other
requirements as stated herein.
2.
Detailed checking of each item of equipment provided each portion of the installation, and of
the complete installation to find and remedy any defects therein.
3.
Setting the system gain structure, including initial adjustment of digital signal processing, and
amplifier gain controls and, under the direction of the Consultant, making the final
adjustment of these items.
4.
Alignment and focus of video displays adjusting for optimized settings. Under the direction
of the Consultant, if required, making final adjustments to the displays and associated video
processing equipment.
5.
Adjusting/applying EDID management strategy and adjusting color space for all displays in
order to display the most optimal image possible for each video source.
G.
Applicable Standards and Codes: In addition to all applicable local and state codes, the work shall be
in accordance with the latest revisions of all applicable standards and specifications of the following:
1.
NAB - National Association of Broadcasters
2.
UL - Underwriters Laboratories
AUDIO-VISUAL SYSTEMS
27 41 00 - 12
7/26/2017
8/30/2017
FCC Renovation & Expansion
3.
4.
1.08
G/S SJCF Arch 5164.00
EIA - Electrical Industries Association
NEC - National Electrical Code
H.
Final Acceptance: Final acceptance shall be contingent upon issuance by the Consultant of a letter of
acceptance stating that the work has been completed and is in accordance with the contract
documents.
I.
Manufacturers' Qualifications:
1.
All electronic products shall be designed and marketed by the manufacturer for application in
professional video projection, sound amplifying, reproduction and recording systems.
2.
All products proposed by the AV Contractor for use in the systems described herein are
subject to approval by the Consultant.
SUBMITTALS
A.
Prior to bidding, submit the following:
1.
AV Contractor Qualification Statement: Non-pre-qualified AV Contractors shall submit
electronic media in PDF format containing a statement of the AV Contractor's qualifications
for approval.
2.
As a minimum, this submittal shall include the following:
a.
A list of AV systems of comparable size and scope to that described herein, completed
by the AV Contractor in the last five (5) years. Show project name and address, year of
completion and the name, telephone number, and e-mail address of a person to contact
who is a representative of the Owner or User.
b.
A personal resume of formal education and experience of the qualified staff engineer
who would direct the work.
c.
A personal resume of the staff member(s) with the required manufacturer certification
and control system programming qualifications.
d.
A description of the AV Contractor's capabilities and facilities for rack assembly, shop
fabrication, software programming, repair and servicing of AV systems.
e.
A letter from the processor and control system manufacturer(s) certifying that the AV
Contractor’s software programmers have been factory trained and are qualified to
provide the proposed installation.
B.
After the contract has been awarded, but before product procurement or installation begins, submit the
following:
1.
Shop Drawings: The shop drawings shall be submitted after award of contract and be of a
scale suitable for fabrication. Contractor shall make the following shop drawing submittals:
a.
A schedule of equipment to be provided for the systems with quantities, including that
required for items which are to be fabricated by the AV Contractor. Include cable,
connectors, and items which are to be custom fabricated. Do not include extraneous
information or products which are not to be used in the project.
b.
A set of manufacturer’s equipment specifications with detailed technical information
describing and illustrating all components and materials to be used in the installation of
the AV systems. This includes those items listed by manufacturer and model number in
Paragraph 2.03 and any other components needed to provide complete functional
systems. Where a manufacturer provides a specification sheet with multiple products or
options, highlight the product and options to be provided.
c.
A set of drawings showing items which are to be fabricated by the AV Contractor
including, but not limited to, custom panels and receptacle plates. Drawings shall show
materials, finishes and panel/control markings when applicable. Custom panels and
receptacle plates shall be manufactured only by approved manufacturers. Typical
drawings are only acceptable for identical items. Similar items with different marking
shall be submitted separately.
AUDIO-VISUAL SYSTEMS
27 41 00 - 13
7/26/2017
8/30/2017
FCC Renovation & Expansion
d.
e.
f.
g.
h.
i.
C.
G/S SJCF Arch 5164.00
A set of drawings including, but not limited to, floor plans, reflected ceiling plans,
elevations, and sections detailing the layout and location of equipment. Show
equipment to scale and include manufacturer and model numbers on drawings. Include
required equipment clearances, projection beam paths, camera fields of view, device
aiming and orientation, details showing any AV equipment integrated into furniture,
and loudspeaker tap settings on reflected ceiling plans.
A set of one-line block diagrams showing exactly the manner in which the AV
Contractor proposes to install the systems. Show all switches, modifications to
equipment, relay and control circuits. Show all equipment/apparatus items which are
required for realization of the functions described herein. Label each item with
manufacturer and model number. Provide wire tags for all connections including wire
number, signal type, wire manufacturer and model, and connectors. Show wire numbers
as they will be displayed in the field.
Detailed diagrams showing equipment rack layouts. Show equipment manufacturer,
model number, electrical loads, electrical power circuit numbers, heat loads, and
electrical power sequencing for all equipment. Provide rear views of racks with rear
facing equipment. Provide text for custom lamacoid equipment labels.
Detailed drawings of custom millwork and technical furniture to be provided by the
Contractor, including but not limited to mix position desks and lecterns. Show all
conduit, boxes, and coordination with other trades.
Equipment mounting details showing all video displays, loudspeakers, projection
screens, and other equipment requiring mounting or suspension. Show all hardware
identified by manufacturer and model number. All rigging, overhead suspension, and
mounting shall be reviewed and stamped by a structural engineer licensed in the state
where the Work is to be performed.
Any items listed as “submit for review” in Paragraph 2.03 herein.
During installation but before system testing, submit the following:
1.
Digital Signal Processor configuration files:
a.
Complete digital signal processor files provided in the DSP manufacturer’s file format.
2.
Control System Submittal
a.
Prior to beginning any programming coordinate with the Owner and Consultant on
general expectations.
b.
Conduct a programming discovery meeting with the Owner to review the following:
1)
General overall layout
2)
Color palette
3)
Expected control functions by room
4)
Organization of basic and advanced functions
5)
Detailed expectations for advanced control of individual components or
subsystems
6)
Expectations for automated or grouped control functions
7)
Any other control related functionality as required by the Owner
c.
Provide three (3) programming submittals with four revisions to the Owner and
Consultant as follows:
1)
The first submittal shall be comprised of a list of functions to be provided by the
space. One revision shall be made after comment.
2)
The second submittal shall be comprised of working touch panel screen shots
provided by room. One revision shall be made after comment.
3)
The third submittal shall be comprised of working touch panels of each type and
loaded with each room’s specific programming. The Owner shall be able to
operate the panel and navigate to all pages but will not be able to control any
equipment. One revision shall be made after comment.
AUDIO-VISUAL SYSTEMS
27 41 00 - 14
7/26/2017
8/30/2017
FCC Renovation & Expansion
4)
5)
G/S SJCF Arch 5164.00
The system shall be reviewed again with the Owner when fully functioning
during the initial Consultant post-construction visit. One revision shall be made
after comment.
During each submittal, the Contractor shall be prepared to discuss and document
button-by-button expected functions or sequences as they relate to final system
operation.
D.
After the installation of infrastructure is complete but before the installation of AV equipment, submit
the following:
1.
RF Coordination & RF Remote Antenna Cable Report. Provide a report including the
following:
a.
Provide the operating frequencies of all AV wireless equipment. Provide the output of
intermodulation analysis software showing that the selected frequencies will be free
from intermodulation interference as well as external interference documented in the
FCC database.
b.
Use an RF scanner used on site to determine if interference sources not in the FCC
database are present in the selected frequency bands. Document the results in the report.
c.
Provide the measured length of RF cable runs to all remote antennas.
d.
Provide the wireless equipment manufacturer recommended cable RG type for each
run.
e.
Provide the proposed cable to be installed, including manufacturer and model number.
f.
Provide the attenuation in dB/100ft at the worst-case frequency used by the antenna.
Where required, interpolate cable manufacturer provided attenuation data.
g.
Calculate the signal attenuation of each remote antenna RF cable run and provide the
results. Attenuation should not exceed 3dB. If calculated attenuation is greater than 3
dB, select a lower loss cable and perform the calculations again. See Paragraph 2.05 for
acceptable cable. If the calculated attenuation is too high using the best specified cable,
provide an amplifier to make up for signal loss, but avoid over-amplifying the signal.
E.
After submittals in Paragraph 1.08.C and 1.08.D have been approved but before the initial postconstruction Consultant site visit, submit the following:
1.
Testing Report. Provide a report documenting the results of system tests described in
Paragraph 3.04. The Consultant will not schedule the initial post-construction site visit until
this report has been delivered.
F.
After the initial post-construction Consultant site visit, submit the following:
1.
A signed copy of the initial post-construction Consultant site visit punch list with each
completed item initialed. The Consultant will not schedule the final post-construction or visit
until this document has been delivered.
G.
After the final Consultant site visit and final punch list has been completed, submit the following:
1.
Operation Manual: Provide the following in a neatly bound binder with tabbed dividers
between sections. Also, provide a digital copy in PDF format on a CD-ROM or USB solid
state memory drive.
a.
Title Page
b.
Table of Contents
c.
Description of each system including key features and operational concepts
d.
Setup diagrams and instructions to use in typical situations as directed by the Owner
e.
Single-line block diagrams showing all major system components
f.
Manufacturer’s operation manuals and information sheets for equipment intended for
operation by system users
g.
A sheet of web links to relevant industry resources such as:
1)
The Shure publication Microphone Techniques for Live Sound Reinforcement
2)
The Soundcraft Guide to Mixing
AUDIO-VISUAL SYSTEMS
27 41 00 - 15
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
3)
2.
3.
4.
1.09
1.10
The Electro-Voice PA Bible including Introduction, PA Bible, and Additions
two, three, four, five, seven, eight, nine, fourteen, and twenty
h.
Key schedule cross-referencing all keys to their respective functions and extra copies of
all keys required to open or operate equipment specified in this section.
Maintenance Manual: Provide the following in a neatly bound binder with tabbed dividers
between sections. Also, provide a digital copy in PDF format on a CD-ROM or USB solid
state memory drive.
a.
Title Sheet
b.
Table of Contents
c.
Company name, address, telephone number, e-mail address, website, and contact name
for system service or maintenance
d.
Listing of all equipment and materials with names of manufacturers and model numbers
or part numbers
e.
Product manufacturer’s warranties and a typed one-year system warranty explicitly
covering all materials and labor
f.
Manufacturer’s service manuals for all major equipment items
g.
A recommended preventative maintenance schedule with reference to the applicable
pages in the manufacturer’s maintenance manuals. Where the manufacturer provides
inadequate information, provide the information necessary for proper maintenance.
h.
Provide a working copy of the latest version of all software required to operate or
configure the systems specified herein.
i.
All software shall be fully documented, and that documentation included.
j.
Software shall be furnished on a CD-ROM or USB solid state memory drive attached to
the binder.
k.
All user definable software configurations and/or programming shall become the sole
property of the Owner. This includes all source code, source code copyrights, and
related documentation.
Training Materials as described herein.
As-Built Drawings
a.
Maintain a full set of shop drawings at the project site marked up to indicate actual
locations of equipment, boxes, and other items called for in this section. After the final
Consultant site visit, compile the mark-ups into a set of as-built drawings and provide
to the General Contractor, Architect, and Consultant.
WARRANTY
A.
Provide a written one (1) year warranty, signed by the Contractor, due on the date of the final
acceptance.
B.
Include the following provisions:
1.
Warranty all equipment and the installation to be free of faulty workmanship.
2.
Warranty all components and materials to be free of defects for a period of one (1) year from
the date of final acceptance.
3.
Paint and exterior finishes, fuses and lamps are excluded from above warranty, except when
damage or failure results from defective materials or workmanship covered by the warranty.
SERVICE WARRANTY
A.
Replace defective materials and repair faulty workmanship within forty-eight (48) hours of discovery
at no cost to the Owner during the period of the warranty.
B.
The Contractor shall be available on call and on eight (8) hour notice during the first month following
acceptance of the system, to assist the Owner’s representatives in any problems which may arise
during the initial period of operation.
AUDIO-VISUAL SYSTEMS
27 41 00 - 16
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
C.
At no additional charge, provide maintenance service for a period of one (1) year after final
acceptance of installation. This service shall consist of at least one visit six months and one visit
eleven months after final acceptance for checking the equipment and making any necessary
adjustments.
D.
If, during the warranty period, any component is out of service for more than seven (7) days due to
unavailability of parts or service, supply and install an identical new component. If an identical
component is not available, substitute equivalent equipment, but only with the approval of the Owner.
P2 PRODUCTS
2.01
2.02
MATERIALS
A.
All materials, equipment and apparatus shall be new and of the latest design or model offered for sale
by the manufacturer.
B.
Principal items of equipment and apparatus are identified herein by part number and manufacturer.
Alternate part numbers and manufacturers are identified in instances in which equivalence has been
determined.
C.
For all items which are identified by part number and manufacturer, performance specifications which
are published in the most recent manufacturer's data sheets available at the time of bidding this
contract shall be applicable to the present work as though fully written out herein.
D.
For those items which are not identified by part number and manufacturer, the AV Contractor may
select items which conform to the functional and/or technical specifications. For all such items, the
AV Contractor shall submit exact make and model for approval including all technical data which is
available from the supplier or manufacturer.
EQUIVALENT EQUIPMENT
A.
2.03
All equipment listed by make/model in Paragraph 2.03 represents a minimum standard of
performance based on specifications supplied by the manufacturer. All equipment substitutions shall
be submitted to the Consultant for review and approval prior to bid. It is the responsibility of the AV
Contractor to prove that requested substitutions are equivalent to the specified product and compatible
with the overall system design, intent, and electrical infrastructure. If requested by the Consultant, the
AV contractor shall submit a sample of any proposed substitutions.
Equipment
A.
Theatre
DESCRIPTION
MANUFACTURER
MODEL NUMBER
AUDIO DEVICES
Wireless Microphone Receiver (4-Ch)
w/ Wireless Bodypack Transmitter
w/ Wireless Handheld Transmitter
Shure
Shure
Shure
ULXD4Q
ULXD1
ULXD2/B87A
2
8
8
Wireless Microphone Receiver (2-Ch)
w/ Wireless Bodypack Transmitter
w/ Wireless Handheld Transmitter
Shure
Shure
Shure
ULXD4D
ULXD1
ULXD2/B87A
2
2
2
AUDIO-VISUAL SYSTEMS
27 41 00 - 17
QTY
7/26/2017
8/30/2017
FCC Renovation & Expansion
Wireless Microphone Antenna Distribution
Wireless Antennas
w/ Antenna Bracket
G/S SJCF Arch 5164.00
1
2
2
Shure
Shure
PWS
UA844+SWB
UA864US
S9826
Main Loudspeakers w/ Custom Color
w/ Set up cost RAL standard color
w/ Rigging
D&B
D&B
D&B
Vi7P
Submit color samples to
Architect for color choice
O0001
VP Flying Adapter
Portable Front Fill Loudspeakers
D&B
E6
4
Subwoofers
w/ Rigging
D&B
D&B
Vi-SUB
Vi Mounting frame top
3
3
DSP
w/ Analog Input Cards
w/ Data Port Output
w/ Analog Output Cards
w/ AES Output Cards
QSC
QSC
QSC
QSC
QSC
Core 510i
CIML4
CODP4
COL4
CAES4
1
3
1
2
2
Amplifier A
Amplifier B
Amplifier C
D&B
D&B
QSC
1
1
1
Amplifier D
QSC
30D
30D
CXDQ 4.3
70 V CX Series - Field
Verify
ALS Transmitter
w/ ALS Receivers
w/ Compliance Signage
w/ ALS Neck Loops
w/ Rack Mount Kit
w/ Universal Antenna Kit
Listen Tech
Listen Tech
Listen Tech
Listen Tech
Listen Tech
Listen Tech
LT-800-072
LR-4200-072
LA304
LA-166
LA-326
LA-122
1
39
1
10
1
1
VIDEO DEVICES
Theater Camera
Panasonic
AW-HE40
1
Video Encoder
AMX
NMX-ENC-N1115-WP
1
Camera Control interface plate
Custom
Custom
1
AUDIO-VISUAL SYSTEMS
27 41 00 - 18
7
1
7
1
7/26/2017
8/30/2017
FCC Renovation & Expansion
ACCESSORIES
44RU Floor-Standing Rack
w/ Locking Vent Door
G/S SJCF Arch 5164.00
1
1
Middle Atlantic
Middle Atlantic
ERK-4428
LVFD-44
Middle Atlantic
Middle Atlantic
Middle Atlantic
As Required
BR-1
USC-6R
Middle Atlantic
MPR-9A
Middle Atlantic
Middle Atlantic
Middle Atlantic
Middle Atlantic
MPR Series, As Required
M2X20IGA
RLM-20IGA
MPR-SS
Remote Power Sequencing Control Switch
Middle Atlantic
USC-SWL
1
Uninterruptible Power Supply
Middle Atlantic
UPS-1000R
1
Complete with all necessary accessories
including Locking Vent Door, Fans, Cable
Management, Blank Panels, Etc.
w/ Brush Panels
w/ Power Sequencing Controller
Equipment Rack Vertical Power Distribution
Raceway
w/ Tails, Jumpers, Mounting Hardware, Blank
Plates, and Accessories
w/ 20A 2x Constant Modules
w/ 20A Remote Modules
w/ Surge Suppression Device
1
Complete with all necessary accessories
Included in Convention
Center Master Quote
Included in Convention
Center Master Quote
12 Port Patch Panel
w/ Modular Jacks
w/ Patch Cables
Belden
Belden
Belden
POE+ Network Switch
Cables, Plates, Rigging Hardware, and
Connectors
AUDIO-VISUAL SYSTEMS
1
AR
AR
AR
AR
1
AX104564
RVAMJKUXX-B24
CA2110XXXX Series
As Required
27 41 00 - 19
1
1
1
1
AR
AR
7/26/2017
8/30/2017
FCC Renovation & Expansion
B.
G/S SJCF Arch 5164.00
Convention Center
DESCRIPTION
MANUFACTURER
MODEL NUMBER
QTY
DISPLAY DEVICES
LCD Projector, WGXA, 5,000 Lumen
w/ Mount
Panasonic
Chief
PT-EW550U
2
2
16:10 198" Screen (Field Verify Screen Size)
Draper
Access E Matt White
2
90" Meeting Room Display
w/ Mount
W/ Back Box
Sharp
Chief
Middle Atlantic
LC-90LE657U
XSM1U
PRX-WB-9X14
1
1
1
80" Meeting Room Display
w/ Mount
W/ Back Box
Sharp
Chief
Middle Atlantic
LC-80LE661U
XSM1U
PRX-WB-9X14
1
1
1
Control Room Screen
Tote Vision
LED-1562HDR
1
AUDIO DEVICES
Ceiling Loudspeakers
Ceiling Subwoofers
Outdoor Loudspeakers
w/ Pole Mount
QSC
QSC
Bose
Bose
AD-C6T
AD-C81T
DS100SE
48
10
33
33
DSP Core
QSC
Core 110f
2
Power Amplifier
QSC
CXD8.4QN
1
Power Amplifier
QSC
CXD8.8QN
1
Portable ALS transmitter
w/ Portable ALS connection cable
Portable ALS Receivers
Listen
Custom
Listen
LT-700-072
Custom
LR-500-072
2
2
10
Network Wall Interface Plates
AtteroTech
unD6IO
10
VIDEO DEVICES
Video Encoders
Video Encoder
AMX
AMX
NMX-ENC-N1115-WP
NMX-ENC-N1115-WP
9
1
AUDIO-VISUAL SYSTEMS
27 41 00 - 20
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
Video Decoders
AMX
NMX-DEC-N1222
9
Rack Mount Video Decoder
w/ Rack Mount Kit
AMX
AMX
NMX-DEC-N1222
NMX-ACC-N9102
1
1
Rack Mount Video Encoders
w/ Rack Mount Kit
AMX
AMX
NMX-ENC-N1222
NMX-ACC-N9102
2
1
Convention Camera
Panasonic
AW-HE40
1
Blu-Ray Player
w/ Rack Mount Kit
Oppo
Oppo
UDP-203
1
1
Digital Signage Player
Software (Coordinate w/Owner)
Cenique
Ping HD
C610
O.F.E.
3
AR
CONTROL DEVICES
Control Processor
w/ Relay Module
w/ Rack Mount Kit
AMX
AMX
AMX
NX1200
EXB Rel 8
AVB-VSTYLE-RMK-1U
1
2
1
Control Touchscreens
w/ Rough-In Box
w/ Rack Mount Kit
w/ Weather Proof Back Box and Cover
AMX
AMX
AMX
MSD-701
CB-MXSA-07
MSA-RMK-07
Provided By Electrical
11
10
1
1
Network Switches
Extreme Networks
Complete with all necessary accessories
48 Port Patch Panel
24 Port Patch Panel
w/ Modular Jacks
w/ Patch Cables
Extreme Networks
Belden
Belden
Belden
Belden
Quote# DLAA FCC 16208
Quote# DLAA FCC 16208
AX104563
AX104564
RVAMJKUXX-B24
CA2110XXXX Series
Middle Atlantic
SR-46-28
Middle Atlantic
Middle Atlantic
AR
PDT-1620C-NS
ACCESSORIES
46RU Floorstanding Swing Rack
Complete with all necessary accessories
including Vent Door, Fans, Cable
Management, Blank Panels, Etc.
w/ Vertical Power Strip
AUDIO-VISUAL SYSTEMS
1
1
1
3
AR
1
AR
27 41 00 - 21
1
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
w/ Brush Panels
w/ Pull Out Rack shelf
w/ Open Clamp Rack shelf
w/ Drawer
w/ Custom AUX Panel
w/ Video Encoder
w/ Headphone Amp
w/ Rack Speaker
W/ Unbalanced Line Input
w/ XLR Inputs
Middle Atlantic
Middle Atlantic
Middle Atlantic
Middle Atlantic
Custom
AMX
RDL
RDL
RDL
Neutrik
BR-1
VSA-1626
OCAP-2
UD2
Custom
NMX-ENC-N1115-WP
DB-HPA3
DB-SP1A
DS-CIJ3
NC3FD-L-B-1
1
1
1
1
1
1
1
1
1
2
Wall Mounted Rack
Middle Atlantic
SPM-4
1
Uninterruptible Power Supply
Middle Atlantic
UPS-2200R
1
Cable, Connectors, Plates, Hardware, Misc.
Custom
Custom
AR
2.04
EQUIPMENT PERFORMANCE SPECIFICATIONS
A.
2.05
The performance specifications for all components shall be as published in the most recent
manufacturer's data sheets available at the time of bidding this contract and shall be applicable to the
present work as though fully given herein.
WIRING AND CONDUCTORS
A.
Installed microphone and line level cable:
1.
Cable shall be 22 AWG stranded tinned copper, UL Listed, NEC Type CM CMR or CMP,
PVC jacketed, twisted pair, with 100% coverage overall foil shield. Where required by code
installed microphone and line level cables shall be plenum rated.
2.
Approved non-plenum cables:
a.
Belden 8451, 9451
b.
West Penn 77291
c.
Liberty 22-1P-EX
d.
Clark SPA22GS
e.
Submit proposed alternative for approval
3.
Approved plenum cables:
a.
Belden 9451P
b.
West Penn D25291
c.
Liberty 22-1P-CMP-EZ
d.
Clark SPA22GSP
e.
Submit proposed alternative for approval
B.
Portable microphone, line level, and single channel analog party line intercom cable:
1.
Cable shall be 20 AWG stranded tinned copper, EPDM Jacket, with minimum 85% coverage
tinned copper braid shield.
2.
Approved portable microphone cable:
a.
Belden 8412
AUDIO-VISUAL SYSTEMS
27 41 00 - 22
7/26/2017
8/30/2017
FCC Renovation & Expansion
b.
c.
G/S SJCF Arch 5164.00
Clark FF220
Submit proposed alternative for approval
C.
Analog party line intercom systems cable:
1.
Cable shall be 18 AWG stranded tinned copper, UL listed, NEC Type CM, CMR, or CMP,
PVC jacketed, twisted pair, with 100% coverage overall foil shield. Where required by code,
analog party line intercom system cables shall be plenum rated.
2.
Approved non-plenum cables:
a.
Belden 8760
b.
West Penn 77293
c.
Clark SPA18GS
d.
Submit proposed alternative for approval
3.
Approved plenum cables:
a.
Belden 88760
b.
West Penn D25293
c.
Clark SPA18GSP
d.
Submit proposed alternative for approval
D.
Loudspeaker cable for high impedance (70V) systems:
1.
Cable shall be copper 14 AWG, UL Listed, NEC Type CL3 or CL3P, PVC jacketed, stranded
conductor.
2.
Approved non-plenum cables:
a.
Belden 8473
b.
West Penn 226
c.
Liberty 14-2C
d.
Clark CW1402
e.
Submit proposed alternative for approval
3.
Approved plenum cables:
a.
Belden 6100UE
b.
West Penn 25226B
c.
Liberty 14-2C-P
d.
Clark CW1402P
e.
Submit proposed alternative for approval
E.
Loudspeaker cable for low impedance systems, runs less than 150’, except 4-ohm dedicated low
frequency loudspeakers (subwoofers):
1.
Cable shall be copper 12 AWG, UL Listed, NEC Type CL3, PVC jacketed, stranded
conductor.
2.
Approved non-plenum cables:
a.
Belden 8477, 5000UE
b.
West Penn 227
c.
Liberty 12-2C
d.
Clark CW1202
e.
Submit proposed alternative for approval
3.
Approved plenum cables:
a.
Belden 6000UE
b.
West Penn 25227B
c.
Liberty 12-2C-P
d.
Clark CW1202P
e.
Submit proposed alternative for approval
F.
Loudspeaker cable for low impedance systems, runs greater than 150’, and for all 4 ohm dedicated
low frequency loudspeakers (subwoofers):
AUDIO-VISUAL SYSTEMS
27 41 00 - 23
7/26/2017
8/30/2017
FCC Renovation & Expansion
1.
2.
3.
G/S SJCF Arch 5164.00
Cable shall be copper 10 AWG, UL Listed, NEC Type CL2, PVC jacketed, stranded
conductor. Where required by code, loudspeaker cables shall be plenum rated.
Approved non-plenum loudspeaker cables:
a.
Belden 5T00UP
b.
West Penn HA210
c.
Clark CW1002
d.
Submit proposed alternative for approval
Approved plenum loudspeaker cables:
a.
Belden 6T00UP
b.
West Penn 25210
c.
Clark CW1002P
d.
Submit proposed alternative for approval
G.
Portable loudspeaker cable:
1.
Cable shall be 12 AWG, UL listed, NEC Type SJ, EPDM insulation, rubber jacket. Portable
loudspeaker cables shall be two conductor except where used to service biamplified
loudspeakers, in which case cables shall be four conductor.
2.
Approved manufacturers:
a.
General Cable/Carol
b.
Rapco/Horizon SJ12/2
c.
Clark PWC-12/2-SJOOW
d.
Submit proposed alternative for approval
H.
RF cable for wireless microphone antennas and assisted listening antennas:
1.
Note: Before installing or ordering RF cable, submit wireless microphone cable report.
2.
Cable type (RG designation) shall be as specified by equipment manufacturer and dependent
on cable length.
3.
Approved non-plenum RF cables:
a.
Approved non-plenum RG58/U
1)
Belden 8262
2)
West Penn 812, 813
3)
Liberty RG58-CMR
4)
Clark RG58/U
5)
Submit proposed alternative for approval
b.
Approved non-plenum RG8/X:
1)
Belden 9258
2)
West Penn 807
3)
Clark RG8X
4)
Submit proposed alternative for approval
c.
Approved non-plenum RG213/U:
1)
Belden 8267
2)
Clark RG213/U
3)
Submit proposed alternative for approval
d.
Approved non-plenum RG8/U:
1)
Belden 9913
2)
West Penn 808F
3)
Liberty RG8-CMR
4)
Clark RF50LL
5)
Submit proposed alternative for approval
4.
Approved plenum RF cables:
a.
Approved plenum RG58/U:
1)
Belden 88240
2)
West Penn 25810
AUDIO-VISUAL SYSTEMS
27 41 00 - 24
7/26/2017
8/30/2017
FCC Renovation & Expansion
b.
G/S SJCF Arch 5164.00
3)
Liberty RG58-CMP
4)
Clark RG58-PLEN
5)
Submit proposed alternative for approval
Acceptable RG8/U:
1)
Belden 89913
2)
Liberty RG8-CMP
3)
Clark RG8PL
4)
Submit proposed alternative for approval
I.
Crestron DM Cable:
1.
Cable shall be UL listed shielded twisted pair, four pair, 24 AWG solid copper conductor as
specified by manufacturer.
2.
Acceptable Crestron non-plenum DM 8G Cable:
a.
Crestron DM-CBL-8G-NP
b.
Belden 1212F
c.
Submit proposed alternative for review
3.
Acceptable Crestron non-plenum DM 8G Cable:
a.
Crestron DM-CBL-8G-P
b.
Belden 1213F
c.
Submit proposed alternative for review
J.
AMX DXLink Cable:
1.
Cable shall be UL listed Cat 6A, F/UTP-foil shielded, four pair, 23AWG solid bare copper
conductors as recommended by AMX.
2.
Acceptable non-plenum AMX DXLink Cable:
a.
Belden 10GX62F
b.
Submit proposed alternative for review
3.
Acceptable plenum AMX DXLink Cable:
a.
Belden 10GX63F
b.
Submit proposed alternative for review
K.
Extron XTP and DTP Cable:
1.
Cable shall be UL listed, SF/UTP, overall tinned copper braid shield, four pair, 24 AWG
insulated solid copper conductors as recommended by Extron.
2.
Acceptable non-plenum Extron XTP and DTP cable:
a.
Extron XTP DTP 24
b.
No known equal
3.
Acceptable plenum Extron XTP and DTP cable:
a.
Extron XTP DTP 24P
b.
No known equal
L.
Network Audio/Video Cable:
1.
Cable shall be UL listed Cat 6A, F/UTP-foil shielded, four pair, 23AWG solid bare copper
conductors as recommended by AMX.
2.
Approved non-plenum network audio/video cable:
a.
Belden 10GX62F
b.
Liberty 24-4P-L6ASH
c.
West Penn 4246AF
d.
Clark CN423C6AS
e.
Submit proposed alternative for review
3.
Approved plenum network audio/video cable:
a.
Belden 10GX63F
b.
Liberty 24-4P-P-L6ASH
c.
West Penn 254246AF
AUDIO-VISUAL SYSTEMS
27 41 00 - 25
7/26/2017
8/30/2017
FCC Renovation & Expansion
d.
e.
2.06
G/S SJCF Arch 5164.00
Clark CN423C6ASP-6
Submit proposed alternative for review
CONNECTORS
A.
3-Pin XLR connectors:
1.
3-pin XLR cable connectors shall be 3-pole XLR type connectors, with solder cups, with
black metal housing, and with gold contacts.
2.
Approved 3-Pin XLR cable connectors:
a.
Neutrik NC3FXX-B, NC3MXX-B
b.
Submit Proposed Alternative for Approval
3.
Approved 3-Pin XLR chassis connectors:
a.
Neutrik NC3FD-L-B-1, NC3MD-L-B-1
b.
Submit proposed alternative for approval
B.
4-Pin XLR connectors:
1.
4-pin XLR cable connectors shall be 4-pole XLR type connectors, with solder cups, with
black metal housing, and with gold contacts.
2.
Approved 4-Pin XLR cable connectors:
a.
Neutrik NC4FXX-B, NC4MXX-B
b.
Submit proposed alternative for approval
3.
Approved 4-Pin XLR chassis connectors:
a.
Neutrik NC4FD-L-B-1, NC4MD-L-B-1
b.
Submit proposed alternative for approval
C.
5-Pin XLR connectors:
1.
5-pin XLR cable connectors shall be 5-pole XLR type connectors, with solder cups, with
black metal housing, and with gold contacts.
2.
Approved 5-Pin XLR connectors:
a.
Neutrik NC5FXX-B, NC5MXX-B
b.
Submit proposed alternative for review
3.
Approved 5-Pin XLR chassis connectors:
a.
Neutrik NC5FD-B-1, NC5MD-B-1
b.
Submit proposed alternative for review
D.
6-Pin XLR connectors:
1.
6-pin XLR cable connectors shall be 6-pole XLR type connectors, with solder cups, with
black metal housing, and with gold contacts.
2.
Note: 6-Pin XLR connectors shall use the “Switchcraft Style” pinout to correctly interface
with Clear-Com equipment.
3.
Approved 6-Pin XLR connectors:
a.
Neutrik NC6FSXX, NC6MSXX
b.
Submit proposed alternative for review
4.
Approved 6-Pin XLR chassis connectors:
a.
Neutrik NC6FSD-L-1, NC6MSD-L-1
b.
Submit proposed alternative for review
E.
Speakon connectors:
1.
Speakon cable connectors shall be four pole, with chuck type strain relief, screw terminals,
rated for 30A.
2.
Speakon panel connectors shall be four pole, D-sized, with Faston crimp terminals, rated for
30A.
3.
Approved Speakon cable connectors:
a.
Neutrik NL4FC
b.
Submit proposed alternative for approval
AUDIO-VISUAL SYSTEMS
27 41 00 - 26
7/26/2017
8/30/2017
FCC Renovation & Expansion
4.
G/S SJCF Arch 5164.00
Approved Speakon chassis connectors:
a.
Neutrik NL4MP
b.
Submit proposed alternative for approval
F.
RCA connectors:
1.
RCA cable connectors shall be two pole RCA type, with nickel body, with nickel contacts,
with solder cups, with cable clamp.
2.
Approved RCA cable connectors:
a.
Neutrik NYS352
b.
Switchcraft 3502A
c.
Canare F09, F10
d.
Submit proposed alternative for approval
3.
Approved RCA chassis connectors (D sized connector):
a.
Neutrik NF2D-B
b.
Canare RJ-RUD
c.
Submit proposed alternative for review
4.
Approved RCA chassis connectors (panel mount):
a.
Neutrik NYS367
b.
Switchcraft 3501FPX
c.
Canare RJ-R
d.
Submit proposed alternative for review
G.
1/8” mini (3.5mm) TRS connectors:
1.
1/8” mini cable connectors shall be three pole, with black body, with gold contacts, with
solder cups, with cable clamp.
2.
Approved 1/8” mini straight connectors:
a.
Neutrik NYS231BG
b.
Switchcraft 35HDBAU
c.
Canare F-12
d.
Submit proposed alternative for review
3.
Approved 1/8” mini right angle connectors:
a.
Neutrik NTP3RC-B
b.
Switchcraft 35HDRABAU
c.
Submit proposed alternative for review
4.
Approved 1/8” mini chassis connectors (D sized panel connector):
a.
Switchcraft EH35MMSSCB
b.
Submit proposed alternative for review
5.
Approved 1/8” mini chassis connectors:
a.
BTX CA-C493
b.
RCI Custom RCICH-30-493A
c.
Submit proposed alternative for review
H.
Ruggedized Cat5 8P8C (RJ45) connectors:
1.
Cat5 RJ45 cable connectors shall be with black ruggedized locking shell, with chuck type
strain relief
2.
Cat5 RJ45 chassis connectors shall be ruggedized, latch locking RJ45 type connectors,
complying with Cat5e TIA/EIA568B and ISO/IEC 11801 standard
3.
Approved unsheilded Cat5 RJ45 cable connectors:
a.
Neutrik NE8MC-1 shell with Neutrik compliant RJ45 connector
4.
Approved Cat5 RJ45 punchdown chassis connectors:
a.
Neutrik NE8FDV-YK-B, Neutrik NE8FDV-Y110-B
b.
Submit proposed alternative for review
I.
Cat6 8P8C (RJ45) connectors:
AUDIO-VISUAL SYSTEMS
27 41 00 - 27
7/26/2017
8/30/2017
FCC Renovation & Expansion
1.
2.07
G/S SJCF Arch 5164.00
Cat6 RJ45 connectors shall be ruggedized
PLATES AND PANELS
A.
Custom plates and panels:
1.
Approved manufacturers:
a.
Panelcrafters
b.
RCI Custom
c.
Whirlwind
d.
Rapco/Horizon
e.
BTX
f.
Middle Atlantic Products
g.
Submit proposed alternative for approval
P3 EXECUTION
3.01
3.02
COORDINATION
A.
The AV Contractor shall coordinate this work with the other electrical work and the work of other
trades.
B.
Locations shown on AV Drawings are approximate. Refer to Architectural drawings for dimensions.
FABRICATION
A.
Design/Engraving:
1.
All equipment controls, receptacles and all indicators shall have, unless otherwise noted,
lamacoid, permanently engraved, or silk screened fully descriptive identification labels. The
resolution of silk screened labels shall not be less than 90,000 dots/sq. in.
2.
The word "engraved" shall mean that the identification shall be engraved into the indicated
panel, plate or control surface.
3.
All engraving shall be with 5/32" high characters, unless otherwise noted, and shall be filled
with engraver's enamel of a contrasting color.
B.
Custom Plates:
1.
Receptacles shall be screwed, bolted or flush-riveted to the plate.
2.
Plates shall be marked to indicate function and circuit of the receptacle, for example:
MICROPHONE.
C.
Terminals and Terminations:
1.
Microphone cables shall not be spliced or otherwise interrupted from termination to
termination. All cables shall have visible adhesive identifying markers on each end.
2.
Wiring in terminal cabinets shall be tied and clamped neatly to backboards or cableforms.
3.
Terminals shall, unless otherwise specified, be one of the following types:
a.
Wire-wrap type terminal block.
b.
Barrier strips with screw terminals.
4.
Each terminal strip shall have a legibly marked identification strip.
D.
Structural Assemblies:
1.
Provide holes required for securing other components or assemblies to structural steel
framing and for passage of other components through steel framing members as shown on
final shop drawings. Cut, drill or punch holes perpendicular to metal surfaces. Do not flame
cut holes or enlarge holes by burning.
2.
In fabricating mounting brackets and other steel components requiring bends, the radii of the
bends shall not be less than three times the thickness of the steel being bent.
3.
All bolts and nuts used in the fabrication of mounting hardware shall be Grade 5 or better.
AUDIO-VISUAL SYSTEMS
27 41 00 - 28
7/26/2017
8/30/2017
FCC Renovation & Expansion
3.03
G/S SJCF Arch 5164.00
INSTALLATION
A.
General:
1.
Keep the job adequately staffed at all times. Designate a field supervisor to be present on the
job site and in responsible charge during all phases of installation and check out. Maintain
same supervisor throughout the execution of the work unless circumstances beyond the
control of the AV Contractor intervene.
2.
Install the system in cooperation with other trades in order to achieve coordinated progress
and satisfactory final results. Watch for conflicts with work of other trades on the job.
3.
Execute without claim for extra payment, moderate moves or changes as are necessary to
accommodate other equipment or preserve symmetry and pleasing appearance.
4.
The AV Contractor shall do all cutting and patching necessary for proper installation of the
system and shall repair any damage done by himself or his workmen. Any required
penetration of slabs or CMU walls shall be made by a cutting method rather than by a
concussive method.
5.
On completion, remove all rubbish and unused materials from the premises and clean the
premises and all equipment where dirtied by removing all dirt, dust, stains and fingerprints.
B.
Equipment Racks:
1.
Supply completely assembled and fully shop-tested racks with all internal wiring completed
as required to provide a complete system, to the extent that such items are not provided by
others.
2.
Install rack mounted equipment with black 10-32 star post drive security screws head screws
with nylon washers, Middle Atlantic HTX or equivalent.
3.
Wiring internal to equipment racks shall be installed neatly and bundled according to
function. Separate power cables as far as possible from microphone level and line level signal
cables. Provide lacer bars, horizontal cable managers, and vertical cable managers where
required. Attach cable bundles every 6” to cable management.
4.
Provide security covers for non-user-operated equipment having front panel controls. Where
required by equipment manufacturer security covers shall be vented. Install covers at the
conclusion of system test, tuning, and equalization.
5.
All blank rack panels and connector panels shall be flanged to increase stiffness. Flat panels
will not be accepted.
6.
All equipment not available with an integral rack mounting kit shall be provided with a rack
shelf including custom faceplate that fully covers any open space around the device. Fasten
equipment to rack shelf where appropriate.
7.
Provide rack slides for all equipment requiring access to side or top panels for routine
adjustment or cleaning.
8.
All open areas on front faces shall be covered with blank panels. Where obstructions prevent
the installation of full rack space blanks, install ½ or 1/3 space blanks.
9.
Heavy equipment, such as power amplifiers, shall be supported from rear rack rails in
addition to front attachments. All equipment in portable equipment racks shall be supported
from rear rails in addition to front attachments.
10.
Locate all rack mounted equipment requiring adjustments, cleaning or similar attention so
that it will be accessible. Ensure that equipment with sliding shelves, portable device docks,
or user interaction functions operate smoothly without obstruction.
C.
Equipment, Boxes, Plates:
1.
Secure all equipment, except equipment designed to be portable, firmly in place, including
loudspeakers, racks, amplifiers, cables, and displays.
2.
Install work neatly, with boxes, equipment, etc. plumb and square.
3.
Locate all apparatus requiring adjustments, cleaning or similar attention so that it will be
accessible.
AUDIO-VISUAL SYSTEMS
27 41 00 - 29
7/26/2017
8/30/2017
FCC Renovation & Expansion
4.
5.
6.
7.
8.
9.
G/S SJCF Arch 5164.00
All supporting structures and enclosures supplied by the AV Contractor, not having a
standard factory paint finish, shall be painted. Paint specifications and color shall be supplied
by the Architect.
Color and finish of blank panels and custom assembly panels shall match adjacent equipment
panels to the extent possible. Paint all conduit and boxes to match adjacent surfaces. The
finish of wall mounted receptacle panels shall be coordinated with the Architect.
The equipment specified herein must be capable of operation in environments of normal
humidity, dust and temperature. AV Contractor should avoid installing equipment where
extreme environmental conditions can occur and shall be responsible for protection of
equipment and related wiring from such conditions.
The AV Contractor shall take precautions to prevent electromagnetic and electrostatic hum.
Install the equipment to provide safe operation. Provide ventilation as required to maintain
equipment within the manufacturers specified temperature limits.
Any obstructions or conflicts in the rated coverage pattern of loudspeakers not shown on
design drawings shall be reported to the Consultant. If unreported obstructions are found
during testing, the Contractor shall move loudspeakers without claim for extra payment.
D.
Installed Cabling & Conduit:
1.
Provide all cables necessary for interconnection of permanently mounted equipment. Use
terminations required to achieve full function of equipment as specified herein.
2.
All cables shall be continuous and only spliced where approved on shop drawings.
3.
Exercise care in wiring to avoid damage to the cables and to the equipment. Make all joints
and connections with rosin-core solder or with mechanical connectors approved for Class I
wiring.
4.
Run lines in separate metallic conduits for microphone level circuits (up to -20 MBm), line
level circuits (up to +30 dBm), loudspeaker circuits (above +30 dBm) and power circuits.
Non-metallic or PVC conduits for AV system wiring are not acceptable unless otherwise
noted. Use only cables which are insulated from the conduit and from each other for the
entire conduit length.
5.
Ground audio cable shields at both ends. Provide green heat shrink tubing for all exposed
cable shields or shield drain conductors at termination points.
6.
Provide the separation shown in the following chart between conduits carrying the following
signal types. Where conduits must cross and separation cannot be maintained, cross at a 90
degree angle.
E.
Wire Terminations:
1.
Make connections using rosin-core solder or approved mechanical connectors.
2.
Terminate three pin XLR connectors according to AES12-1992 (r2004) standard: Pin 1 =
Shield, Pin 2 = Audio High (+), Pin 3 = Audio Low (-). Do not connect shields to connector
shells.
3.
Field terminated Speakon connectors shall be terminated with screw terminals. Do not tin
wires or solder connectors. Strip 20mm from cable jacket and 8 mm from conductor
insulators as directed by manufacturer. Use only an appropriate Ponzidrive bit when
tightening screw terminals.
4.
Speakon chassis connectors shall be terminated with 4.8mm x 0.5mm Faston crimp
connectors.
5.
Provide only factory terminated HDMI, DVI, and DisplayPort digital video cables. Field
terminated cables shall not be acceptable.
F.
Portable Cabling: Provide portable cabling required to connect all portable equipment specified by
this section.
G.
Labeling:
AUDIO-VISUAL SYSTEMS
27 41 00 - 30
7/26/2017
8/30/2017
FCC Renovation & Expansion
1.
2.
3.04
G/S SJCF Arch 5164.00
Clearly, logically and permanently mark switches, connectors, jacks, relays, receptacles,
cables and cable terminations.
Etch, engrave, silk screen or apply in a similar permanent manner all legends and markings
on all custom panels and receptacle plates. Embossed tape, press type, etc., are not
acceptable.
TESTING
A.
Instrumentation: The AV Contractor shall provide the following test equipment for use during initial
tests and adjustments and during acceptance testing and final adjustment of the system:
1.
Sound Level Meter: Shall meet ANSI S1.4 specifications for Type I sound level meters.
SMAART with a Type I microphone and calibrator is acceptable.
2.
Sine Wave Generator: Continuously variable from 20 Hz to 20,000 Hz within +1 dB with
less than 0.5% THD.
3.
Pink Noise Generator: Generator shall produce at least 1 volt RMS of pink noise.
4.
AC Voltmeter: With frequency response of +1 dB from 20 to 20,000 Hz, 0.0001 volts to
minimum input impedance of 0.1 megohm.
5.
Data Communications Cable Verifier: Fluke MicroScanner2 or equivalent.
6.
Polarity checker: Studio Six Digital AudioTools speaker polarity module or equivalent.
7.
All other equipment required to conduct tests, equipment setup and checkouts outlined in this
specification.
B.
System compliance testing and documentation. The Contractor shall perform the following tests and
provide a compliance document confirming the results of all tests prior to the final Consultant site
visit.
1.
Audio System Tests:
a.
Emergency Systems Muting: Coordinate with others to test emergency system mute.
Document verification of system mute.
b.
Cabling:
1)
Check each microphone and line level cable for continuity of all conductors.
Verify connectors are terminated in accordance with AES12-1992 (r2004).
Document compliance on each line.
2)
Check each loudspeaker line for continuity. Positive polarity shall be marked
with red or white. Negative polarity shall be marked with black.
3)
Data communications cabling shall be tested with a cable verifier. Document
compliance.
c.
Loudspeaker Physical Alignment: Verify the height, vertical angle, and horizontal
angle of all loudspeakers with a laser inclinometer. Document the measured aiming
angles.
d.
Loudspeaker Line Impedance: Measure and document the impedance of each
loudspeaker and associated loudspeaker line. Using an audio impedance meter (not DC
resistance). Measure full range loudspeaker impedance at 200 Hz and 2000 Hz.
Measure subwoofer impedance at 50 Hz and 100 Hz. Measure high frequency driver
impedance at 4000 Hz and 8000 Hz. A full range impedance sweep using a software
impedance meter is also acceptable.
e.
Loudspeaker Polarity: Perform polarity checks on all independent loudspeakers.
Loudspeakers utilizing active crossovers shall have polarity checked on all individually
amplified components. Results from all polarity checks shall be included in compliance
documentation.
f.
Freedom from Buzzes, Rattles and Objectionable Distortion:
1)
Apply a slow continuous sine wave sweep at a level 3 dB below rated power
amplifier output voltage. Listen carefully for buzzes, rattles, and objectionable
distortion. Correct any causes of these defects, unless the cause is clearly outside
AUDIO-VISUAL SYSTEMS
27 41 00 - 31
7/26/2017
8/30/2017
FCC Renovation & Expansion
2.
G/S SJCF Arch 5164.00
the sound amplification system equipment and installation, in which case, the
cause shall be brought to the attention of the Consultant.
2)
Listen for audible buzzes or noise in the audio system. Coordinate the operation
of other building equipment, including but not limited to dimmers, motors, stage
lifts, and HVAC equipment to ensure that normal operation of such devices does
not cause audible noise in the sound system.
g.
Assistive Listening Systems: Verify that the system covers all portions of the audience
area with no audible signal dropouts.
h.
Gain Control Settings: Establish tentative normal settings for all gain controls. All
gain controls on rack-mounted equipment shall be adjusted for optimum signal-to-noise
ratio and signal balance. Settings may require further adjustment by the AV Contractor
as a result of testing by the Consultant. After final gain and attenuator settings have
been established, mark all control settings with an adhesive indicator dot or arrow.
i.
Freedom from Switching Transient Noise: Operate all control switches and relays,
while listening for clicks and pops in the system outputs. Eliminate any found.
j.
Listening Test: Listen to normal program material to be sure that there are no
remaining defects.
Video System Tests: The Contractor shall perform the following tests prior to the initial
Consultant site visit:
a.
Viewing Test: Apply SIMPTE split field color bars to an input of the video system and
adjust all displays and projectors. Adjust hue and saturation controls for optimum
picture quality and colorimetric uniformity. Route program material from each video
source to each display. Watch for ghosting and any effects of excessive VSWR.
Correct and defects found.
b.
Video Projector Alignment: Align all video projector for optimal focus and horizontal
and vertical linearity with a cross-hatch signal applied to the projector.
c.
Digital Video Distribution:The digital video distribution systems shall meet all the
requirements of the manufacturer as described in the manufacturer’s specifications.
Including available network bandwidth, EDID management, and video latency,
embedded audio passes and routes properly, and HDCP compliance.
d.
Resolution and Signal Types: Test all available inputs for standard resolutions and all
available signal types.
e.
Video Quality:
1)
Confirm the absence of processing errors throughout the entire video system
chain using calibrated test generators or applicable software. Confirmation must
specifically include but not limited to the following parameters:
a)
Frequency Response
b)
Compression Fidelity
c)
Subjective Image Fidelity
d)
Display Gamma
e)
Color Conversion Accuracy
f)
Color Matrix Mismatch
g)
White and Black Clipping
h)
Color Phase and Gain
i)
Lip-Sync
j)
Chroma Motion
k)
ErrorNoise
2)
The digital video distribution systems shall meet all the requirements of the
manufacturer as described in the manufacturer’s specifications. Including
available network bandwidth, EDID management, and video latency, and HDCP
Compliances.
AUDIO-VISUAL SYSTEMS
27 41 00 - 32
7/26/2017
8/30/2017
FCC Renovation & Expansion
3.
3.05
3.06
G/S SJCF Arch 5164.00
Reporting: Upon completion of above tests and any necessary adjustments, submit a written
report presenting test results for review by the Consultant prior to acceptance testing, final
tuning, and demonstration. With this report, submit written certification that the installation
conforms to the requirements stated herein, is complete in all respects, and is ready for
inspection, testing, and final tuning.
TEST, TUNING, AND EQUALIZATION PROCEDURE
A.
Test Phase:
1.
Upon approval of the preliminary test report by the Consultant, schedule the initial postconstruction Consultant site visit. During the visit, demonstrate the operation of each major
component of the system and the completed installation. After demonstration, assist as
required in the following acceptance tests:
a.
Listening Tests: These tests may include speech intelligibility survey and subjective
aural evaluations by observers at various positions under various operating conditions,
using live speech and/or recorded music material.
b.
Equipment Tests: Any measurements of frequency response, distortion, noise or other
characteristics and any operational tests deemed necessary may be performed on any
item or group of items to determine conformity with these requirements.
2.
If the need for adjustment or modification becomes evident during demonstration and testing,
continue working until the installation operates fully in accordance with the requirement of
this specification. The Consultant will prepare a punch list detailing any deficiencies found
during the test phase.
3.
The tuning and equalization procedure shall only take place once all work has been
completed and tested by the Consultant.
B.
Tuning and Equalization Phase:
1.
After punch list items identified in the test phase have been completed, assist the Consultant
in performing the tuning and equalization phase.
2.
During the tuning and equalization phase, AV system components shall be adjusted by the
contractor under the direction of the Consultant to optimize the performance of the AV
systems. The Contractor will document all changes and include them in the as built drawings.
The AV systems installation will not be considered complete until Consultant has completed
the system commissioning.
3.
The tuning and equalization phase requires that the location of the Work be absolutely quiet.
No other work may be performed during the procedure, except that which generates no noise.
If the room is not quiet upon the arrival of the Consultant and other work cannot be stopped
for the duration of the visit, the Consultant will reschedule the tuning and equalization
procedure at additional cost.
4.
The Contractor shall provide a technician familiar with the Work during the test, tuning, and
equalization procedure. It is estimated that this technician should be available for
approximately one eight hour day. This time shall be solely dedicated to the tuning and
equalization procedure and does not include time spent making the system functional or
completing items on the test phase punch list.
5.
The Test, Tuning, and Equalization procedure shall take place before the system is turned
over to the Owner or training occurs.
DOCUMENTATION
A.
Project Record:
1.
The AV Contractor shall supply clean As-Built prints of the system drawings which show all
changes which were made during fabrication and installation.
2.
The AV Contractor shall supply clean prints of all previously submitted and approved shop
drawings, revised to show all changes which were made during fabrication and installation.
AUDIO-VISUAL SYSTEMS
27 41 00 - 33
7/26/2017
8/30/2017
FCC Renovation & Expansion
3.
3.07
G/S SJCF Arch 5164.00
The AV contractor shall print a full sized copy of the system one line diagram on rigid
foamcore board and post it in a convenient location near the equipment rack.
B.
Maintenance Manual:
1.
The AV Contractor shall provide technical information for all electronic apparatus, including
but not limited to schematic diagrams and parts lists, manufacturer's installation instructions,
operating instructions and technical specifications.
2.
The AV Contractor submittal shall include all shop drawings prepared and used by the AV
Contractor, as well as those which were not required to be submitted for approval. This shall
include, but not be limited to, wiring diagrams, schedules for identification of building wiring
and installation details useful to a maintenance technician.
C.
Instruction Manuals:
1.
Provide two (2) copies of an Instruction Manual to the Owner containing the following:
a.
Title Page
b.
Table of Contents
c.
Description of each system including key features and operational concepts
d.
Setup diagrams and instructions to use in typical situations as directed by the Owner
e.
Single-line block diagrams showing all major system components
f.
Manufacturer’s operation manuals and information sheets for equipment intended for
operation by system users
g.
Key schedule cross-referencing all keys to their respective functions and extra copies of
all keys required to open or operate equipment specified in this section.
TRAINING AND INSTRUCTION
A.
Minimum of eight (8) hours of training shall be provided by the AV Contractor to Owner-designated
representatives for all installed systems at a time mutually agreed upon between Owner and AV
Contractor. The total training time may require that the training be broken into multiple sessions.
B.
All training shall be recorded by the AV Contractor. AV Contractor shall provide two (2) copies of
the training video on a format suitable to the Owner. AV Contractor will supply the equipment
necessary to record the training sessions.
C.
During the training, the participants shall be given opportunities for "hands-on" experience with
operating the controls. There shall be visual and audible demonstrations using the systems themselves
as aids. Personnel for instruction and training for the AV systems shall be designated by the Owner.
D.L. Adams Associates – 07/26/2017 – 100% Construction Documents
END OF SECTION
AUDIO-VISUAL SYSTEMS
27 41 00 - 34
7/26/2017
8/30/2017
FCC Renovation & Expansion
G/S SJCF Arch 5164.00
SECTION 274101
DEMOLITION FOR AUDIO-VISUAL SYSTEMS
P1 GENERAL
1.01
1.02
1.03
RELATED DOCUMENTS
A.
Drawings and general provisions of the Contract, including General and supplementary Conditions
and Division 1 Specification Sections, apply to this Section.
B.
Section 274100, “AUDIO-VISUAL SYSTEMS”
C.
“AVD” Series Audio-Visual Systems Demolition Drawings
D.
“AV” Series Audio-Visual Systems Drawings
SUMMARY
A.
This section includes requirements for audio and video systems demolition.
B.
Related Sections may include but are not limited to the following: Division 2 Section “Demolition.”
DEFINITIONS
A.
Remove: Detach items from existing construction and dispose of them off-site unless indicated to be
salvaged or reinstalled.
B.
Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and
deliver to Owner ready for reuse or storage as noted in construction documents or as directed by
owner.
C.
Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage,
prepare for reuse, and reinstall where indicated.
D.
Existing to Remain: Leave existing items that are not to be removed and that are not otherwise
indicated to be salvaged or reinstalled.
E.
Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods
and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be
salvaged or reinstalled.
P2 PRODUCTS
2.01
MATERIALS AND EQUIPMENT
A.
Materials and equipment for patching and extending work: As specified in Division 1 Specifications
and other Division 16 Specification Sections.
P3 EXECUTION
3.01
3.02
EXAMINATION
A.
Verify field measurements and circuiting arrangements are as shown on Drawings.
B.
Verify that abandoned caballing and equipment serve only abandoned facilities
C.
Demolition Drawings are based on field observation. Contractor to field verify all equipment location
and report discrepancies to Consultant before disturbing existing installations.
D.
Test and document all equipment that is to be reused. Notify GC and Consultant of any deficiencies
discovered during testing.
E.
By beginning of demolition, Contractor accepts existing conditions and has confirmed.
PREPARATION
A.
Coordinate disconnection of power circuits serving equipment to be removed.
DEMOLITION FOR THEATRE SYSTEMS
11 61 01 - 1
7/26/2017
FCC Renovation & Expansion
3.03
G/S SJCF Arch 5164.00
B.
Coordinate utility service outages with appropriate serving utility(s).
C.
Existing Audio Console: Owner to remove and store prior to construction. If console has not been
removed, contact Owner for removal and storage.
D.
Existing Portable Audio Equipment and Accessories: If any existing portable audio equipment,
portable cables, and accessories have not been removed from the area of work by Owner, contact
Owner for removal and storage.
E.
Protect all audiovisual systems equipment that cannot be removed from the area of work.
DEMOLITION AND EXTENSION OF EXISTING AUDIOVISUAL SYSTEMS
A.
General
1.
Protect existing audio-visual equipment and installations not scheduled for demolition. If
damaged or disturbed in the course of the work, notify GC and Consultant before removing
damaged portions and installing new materials and products of equal capacity, quality, and
functionality.
2.
Accessible Work: Remove exposed audio-visual equipment and installations scheduled for
demolished, in their entirety, including all associated rigging elements and wiring, unless
rigging elements or cabling will be reused.
3.
Abandoned Work: Cut and remove buried raceway and cabling indicated to be abandoned in
place, 2 inches below the surface of adjacent construction. AV contractor is responsible for
Capping raceways and patching all damaged surface to match existing adjacent finish.
4.
Remove, relocate, and extend existing installations to accommodate new construction where
required.
5.
Remove all abandoned cabling to source of supply.
6.
Remove exposed abandoned conduit including abandoned conduit above accessible ceiling
finishes. Cut conduit flush with wall and floors. AV contractor responsible for patching all
damaged surface to match existing adjacent finish.
7.
Disconnect abandoned connector plates and remove devices. Remove abandoned connector
plates if conduit servicing them is abandoned and removed. Provide blank covers for
abandoned junction boxes which are not removed.
8.
Disconnect and remove audiovisual systems electrical devices and equipment servicing
equipment that has been removed.
9.
Disconnect and remove all abandoned voice and data conductors/cables.
10.
Repair adjacent construction and finishes damaged during demolition and extension work.
11.
Extend existing installations using materials and products compatible with existing
installations and of equal capacity, quality and functionality.
12.
Remove demolished material from Project site.
13.
Remove, store, reinstall, reconnect, and make operational components indicated for relocation.
B.
Specific Removal Items
1.
Theater
a.
Remove and salvage existing theater amplifier rack, including all contents. Amplifier
rack located in Basement Level 0 room Ex Storage T003. Coordinate removal of
electrical circuits with Electrical Contractor.
b.
Remove and salvage existing output splitter connectors at the stage right I/O plate
including transformers.
c.
Remove and salvage existing wall mounted monitor/ back of house amplifier located
stage right in Level 1.5 room Stage T116.
d.
Remove existing monitor output plates, boxes, conduit, and wiring located stage right
and stage left in Level 1.5 room Stage T116. J-boxes and sections of conduit may
remain and be reused if sized and located appropriately.
e.
Remove and salvage existing theater loudspeakers, including all speaker components,
horns, enclosures, crossovers, and associated loudspeaker rigging.
f.
Remove and salvage wireless microphones receivers from Mixing Booth T205.
Wireless microphone transmitters associated with these receivers should also be
gathered and turned over to the owner at the same time as the receivers.
DEMOLITION FOR THEATRE SYSTEMS
11 61 01 - 2
7/26/2017
FCC Renovation & Expansion
2.
3.04
Convention Center
a.
Ballrooms
1)
Remove and salvage existing ceiling loudspeakers. Retain tile to reuse for new
speakers.
2)
Remove and salvage existing touchscreen and input panels. Retain back boxes
and conduit pathways. Retain existing category caballing only if it is appropriate
for reuse by new equipment.
3)
Remove existing AV rack, including all contents. Retain power and conduit
pathways.
4)
Remove and salvage existing camera and all associated cabling.
5)
Remove and salvage all video cabling associated with convention center
projectors
b.
Meeting Rooms
1)
Remove and salvage all AV equipment, connection plates, and cabling from
existing meeting rooms.
CLEANING AND REPAIR
A.
3.05
G/S SJCF Arch 5164.00
Clean and repair existing materials and equipment which remain or are to be reused.
OWNERSHIP
A.
All equipment, fixtures, devices, etc. which are removed shall be delivered to the Owner for
disposition and stored as directed by owner. All items which are removed but not wanted by the
Owner and which are not reused become the property of the Contractor and shall be removed from the
site.
D.L. Adams Associates – 07/26/2017 – 100% Construction Documents
END OF SECTION 274101
DEMOLITION FOR THEATRE SYSTEMS
11 61 01 - 3
7/26/2017
Download