Task Name
S
1 Design and Build 18 Luxury Decks
1.1 Project Management
1.1.1 Conceptual Design
1.1.1.1 Survey the homes and location
1.1.2 Create Proposal For Decks
1.1.2.1 General layouts with CAD or Lowes deck builder
1.2 Project Planning
1.2.1 Get Building Permits
1.2.1.1 Apply for deck permit with the county office
1.2.2 Pre-Build Meeting
1.2.2.1 Create meeting with all company labourers
1.3 Construction of 18 Decks
1.3.1 Layout 18 Decks
1.3.1.1 Locate utility lines before digging
1.3.1.2 Layout the outside the deck and ramp posts with string and batter board
1.3.1.3 Remove sod inside the deck perimeter and ramp area
1.3.1.4 Layout deck and ramp post holes with plumb bob
1.3.1.5 Mark deck joist height on the wall of each house
1.3.2 Set Posts, Footings and Beam
1.3.2.1 Dig all Post Holes
1.3.2.2 Check layout and holes with inspector
1.3.2.3 Pour footings with Post Base
1.3.2.4 Layout fabric and gravel
Project: M2 - WBS - Deck Assig
Date: Fri 9/27/19
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 1
Sep 8, '19
S
M
T
ID
Task
Mode
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
Task Name
1.3.2.5 Build Support Beams
1.3.2.6 Install support beams and level
1.3.2.7 Building inspector to inspect work if required
1.3.3 Framing the Deck and Ramp
1.3.3.1 Install floor joists and stringers with screws, brackets and hangers
1.3.3.2 Install ramp joists and stringer with screws, brackets and hangers. Add gravel as required for
ramp ledger at lawn level.
1.3.3.3 Layout copper gas lines before decking is installed
1.3.3.4 Install electrical conduit and wiring as required for the perimeter lights
1.3.3.5 Have building inspector check gas and electrical lines
1.3.3.6 Install decking using spacers for drainage
1.3.3.7 Drill Holes for Utilities
1.3.4 Installing Hand Rail and Cedar Privacy Screen
1.3.4.1 Install Handrail Posts
1.3.4.2 Frame and build cedar privacy screens
1.3.4.3 Install Handrail and Glass
1.3.5 Final Aesthetics
1.3.5.1 Install natural gas heaters and fire table
1.3.5.2 Install perimeter lights
1.3.5.3 Build and install two cedar bench seats per deck
1.3.5.4 Install deck skirting
1.3.5.5 Call building inspector to sign off the project
1.3.5.6 Clean up work site, tools and garbage material
1.4 Project Closeout
Project: M2 - WBS - Deck Assig
Date: Fri 9/27/19
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 2
S
Sep 8, '19
S
M
T
ID
Task
Mode
47
48
49
50
51
Task Name
1.4.1 Review construction with stakeholders
1.4.1.1 Walkthrough the decks with the stakeholders to make sure everything complies with their needs
1.4.1.2 Provide a cost report
1.4.1.3 Note any areas for improvement for future projects
1.4.1.4 Project complete
Project: M2 - WBS - Deck Assig
Date: Fri 9/27/19
Task
Inactive Summary
External Tasks
Split
Manual Task
External Milestone
Milestone
Duration-only
Deadline
Summary
Manual Summary Rollup
Progress
Project Summary
Manual Summary
Manual Progress
Inactive Task
Start-only
Inactive Milestone
Finish-only
Page 3
S
Sep 8, '19
S
M
T
Download