ID Task Mode 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Task Name S 1 Design and Build 18 Luxury Decks 1.1 Project Management 1.1.1 Conceptual Design 1.1.1.1 Survey the homes and location 1.1.2 Create Proposal For Decks 1.1.2.1 General layouts with CAD or Lowes deck builder 1.2 Project Planning 1.2.1 Get Building Permits 1.2.1.1 Apply for deck permit with the county office 1.2.2 Pre-Build Meeting 1.2.2.1 Create meeting with all company labourers 1.3 Construction of 18 Decks 1.3.1 Layout 18 Decks 1.3.1.1 Locate utility lines before digging 1.3.1.2 Layout the outside the deck and ramp posts with string and batter board 1.3.1.3 Remove sod inside the deck perimeter and ramp area 1.3.1.4 Layout deck and ramp post holes with plumb bob 1.3.1.5 Mark deck joist height on the wall of each house 1.3.2 Set Posts, Footings and Beam 1.3.2.1 Dig all Post Holes 1.3.2.2 Check layout and holes with inspector 1.3.2.3 Pour footings with Post Base 1.3.2.4 Layout fabric and gravel Project: M2 - WBS - Deck Assig Date: Fri 9/27/19 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 1 Sep 8, '19 S M T ID Task Mode 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 Task Name 1.3.2.5 Build Support Beams 1.3.2.6 Install support beams and level 1.3.2.7 Building inspector to inspect work if required 1.3.3 Framing the Deck and Ramp 1.3.3.1 Install floor joists and stringers with screws, brackets and hangers 1.3.3.2 Install ramp joists and stringer with screws, brackets and hangers. Add gravel as required for ramp ledger at lawn level. 1.3.3.3 Layout copper gas lines before decking is installed 1.3.3.4 Install electrical conduit and wiring as required for the perimeter lights 1.3.3.5 Have building inspector check gas and electrical lines 1.3.3.6 Install decking using spacers for drainage 1.3.3.7 Drill Holes for Utilities 1.3.4 Installing Hand Rail and Cedar Privacy Screen 1.3.4.1 Install Handrail Posts 1.3.4.2 Frame and build cedar privacy screens 1.3.4.3 Install Handrail and Glass 1.3.5 Final Aesthetics 1.3.5.1 Install natural gas heaters and fire table 1.3.5.2 Install perimeter lights 1.3.5.3 Build and install two cedar bench seats per deck 1.3.5.4 Install deck skirting 1.3.5.5 Call building inspector to sign off the project 1.3.5.6 Clean up work site, tools and garbage material 1.4 Project Closeout Project: M2 - WBS - Deck Assig Date: Fri 9/27/19 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 2 S Sep 8, '19 S M T ID Task Mode 47 48 49 50 51 Task Name 1.4.1 Review construction with stakeholders 1.4.1.1 Walkthrough the decks with the stakeholders to make sure everything complies with their needs 1.4.1.2 Provide a cost report 1.4.1.3 Note any areas for improvement for future projects 1.4.1.4 Project complete Project: M2 - WBS - Deck Assig Date: Fri 9/27/19 Task Inactive Summary External Tasks Split Manual Task External Milestone Milestone Duration-only Deadline Summary Manual Summary Rollup Progress Project Summary Manual Summary Manual Progress Inactive Task Start-only Inactive Milestone Finish-only Page 3 S Sep 8, '19 S M T