DOC. NO.: 0304-GP-112 JOB NO. : 2011065 PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN PROJECT : BIR EL MSANA FIELD DEVELOPMENT PROJECT CONTRACT NO. : BMS-001 LOCATION : BIR EL MSANA, ALGERIA CONTRACTING AUTHORITY : SONATRACH SPA / HESS (RHOURDE EL ROUNI) LIMITED / PETRONAS CARIGALI OVERSEAS SDN BHD 0 Mar. 14, 2012 Approved for Design Y. M. Kim D.S.Bae J.W. Lee REV. DATE DESCRIPTION PREPARED CHECKED APPROVED APPROVED BY CA PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 1 OF 45 REVISION LOG REV. NO. REV. DATE REVISED PAGE MAJOR CHANGE DESCRIPTION A1 Nov. 25, 2011 - Issued for Approval A2 Jan. 27, 2012 ALL CA’s Comment Incorporated 0 Mar.14.2012 Approved for Design PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 2 OF 45 TABLE OF CONTENTS 1. PURPOSE................................................................................................................ 4 2. SCOPE .................................................................................................................... 4 3. ABBREVIATION AND ACRONYMS ........................................................................ 4 4. HSE LEADERSHIP AND ACCOUNTABILITY ......................................................... 4 5. HSE POLICY ........................................................................................................... 5 6. HSE ORGANIZATION AND RESPONSIBILITIES................................................... 8 7. SUBCONTRACTOR .............................................................................................. 12 8. MANAGEMENT OF CHANGE ............................................................................... 14 9. COMPETENCY ASSURANCE .............................................................................. 14 10. INTEGRITY ASSURANCE..................................................................................... 15 11. RISK EVALUATION AND MANAGEMENT ........................................................... 15 12. CONSTRUCTION SAFETY PLANNING................................................................ 22 13. COMMISSIONING SAFETY PLANNING............................................................... 24 14. START-UP PRECAUTIONS SAFETY PLANNING ................................................ 25 15. HSE DOCUMENTATION ....................................................................................... 24 16. HSE TRAINING ..................................................................................................... 27 17. PERMIT TO WORK SYSTEM................................................................................ 31 18. PERSONAL PROTECTIVE EQUIPMENT (PPE) ................................................... 33 19. COMMUNICATION NETWORK............................................................................. 33 PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 3 OF 45 20. HSE MEETINGS .................................................................................................... 35 21. EMERGENCY EVACUATION PROCEDURE ........................................................ 37 22. FIRE PREVENTION AND PROTECTION .............................................................. 37 23. HSE AWARENESS ................................................................................................ 38 24. MANAGEMENT OF WASTE MATERIALS ............................................................ 38 25. WELFARE.............................................................................................................. 41 26. IMPLEMENTATION AND MONITORING ............................................................... 42 27. AUDIT AND REVIEW ............................................................................................ 42 PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 1. Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 4 OF 45 PURPOSE The purpose of this Health, Safety and Environmental Plan is to outline the scope of services and activities that shall be undertaken in the Project HSE scope of the Bir El Msana (BMS) Project, hereinafter referred to as the ‘Project’. This document describes Contracting Authority (herein after referred to as ‘CA’) EHS Plan, CA EHS Management Plan, HYUNDAI Engineering Co., Ltd. (Contractor) HSE Management System, and ensures that all major hazards that could cause harm to people, environment or assets have been identified, and suitable controls and risk reduction measures are implemented so that the risk associated to the work is as low as reasonably practicable (ALARP). 2. SCOPE This Project HSE Plan is developed, based on the CA’s requirements, and is designed to describe how Contractor will manage and coordinate their HSE operations during the Engineering, Construction, Commissioning and Start-up Phase for BMS Project of the Contracting Authority. 3. 4. ABBREVIATIONS AND ACRONYMS CA Contracting Authority (Bir El Msana – BMS). CONTRACTOR Hyundai Engineering Co,. Ltd. COSHH Control of Substances Hazards to Health. EPC Engineering, Procurement and Construction. HSE Health, Safety and Engineering. HAZOP Hazard and Operations. SIL Safety Integrity Level. QRA Quantitative Risk Assessment. SIMOPs Simultaneous Operations. HEMP Hazard Effects Management Process. JSA Job Safety Analysis. PPE Personnel Protective Equipments. PTW Permit to Work HSE LEADERSHIP AND ACCOUNTABILITY Contractor will ensure that all Contractor’s personnel are briefed, understand and strictly adhere to CA’s policies and directives on the health, safety and the environment. Contractor will demonstrate leadership and commitment through actively participating in all aspects of HSE management, supporting open dialogue and by allocating sufficient resources to ensure that the HSE requirements are met. Contractor will ensure that HSE responsibilities, authorities, accountabilities and competencies are clearly defined, documented, communicated and exercised at all levels. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 5 OF 45 Contractor will ensure that individuals and team contributions to HSE performance are recognized and considered during performance appraisals. Contractor will set clear HSE goals, objectives and targets and ensure that performance is evaluated against them. 5. HSE POLICY 5.1 HSE Policy Statement Contractor is committed to achieving the highest level of Health, Safety and Environment (HSE) Management in all activities and services it undertakes. To comply with these commitments, Contractor will: Establish and implement the HSE Management System. Employ proactive measures on risk assessment and environmental impact assessment, and establish controls across all of its operations. Comply with current applicable HSE legislation and welcome the recommendations from interested parties that will positively contribute to the safety of the Project, the Environment and the Workplace. Establish the HSE objectives and periodically monitor HSE performance for continual improvement. Educate employees and relevant Subcontractors’ personnel in their roles and responsibilities and train them to be competent for the duty in order to achieve conformance to this policy. Review on an annual basis and revise this policy as necessary to ensure it remains relevant and appropriate to all requirements. The HSE policy statement of Contractor is shown below. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 5.2 Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 6 OF 45 Project HSE Policy Statement Contractor will prepare, implement and maintain a Project HSE Policy which shall contain a written statement of policy describing Contractor's HSE Philosophy and Project HSE Objective. It shall be communicated to all personnel and posted at prominent area. These will be displayed at all contractor and sub-contractor sites. 5.3 Drug and Alcohol Policy Statement Contractor shall have the right to prevent entry to the work site of any persons suspected of being under the influence of drugs and/or alcohol. The introduction of alcohol or illegal PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 7 OF 45 drugs on to the work site shall be strictly prohibited. Anyone found under the influence of alcohol or drugs shall be removed from site. All personnel will be advised on this Policy at their induction briefing and that Contractor may carry out random testing on the personnel on the project. 5.4 HSE Objectives Contractor will incorporate the following objectives: Identify all potential hazards associated with the execution of the Project, and to develop prevention, control and mitigation measures to eliminate or minimize harm to people, damage to plant or equipment, or adverse impact on the environment. Encourage the adoption of a positive, proactive, committed HSE culture throughout all phases of the Project. Achieve a target of zero fatalities and zero lost time injuries. Minimize any impact on the natural environment. Implement a management system with clear health, safety and environmental objectives. Review the management of HSE throughout the Project duration in order to continuously improve performance. Communicate all the above objectives to all personnel in the Project. To engineer a safe, reliable, operable and maintainable facility. To create a work environment that fosters prevention of incidents and delivers a goal of zero harm to people and property. To ensure all parties carry out sufficient risk assessments to cover all activities. Minimize emissions and waste. Maximize resources and energy. Demonstrate no harm to the environment. To meet host Government Legislation. Management to conduct weekly site walk around to increase visible commitment. Effective HSE training. Identification of all hazards. Openness between CA, Contractor, Sub-contractor and workforce. Effective and frequent HSE meetings. Effective Reporting of Near Miss and Unsafe Acts. Incentives for good HSE performance. Tools equipment and PPE always fit for purpose. Emergency Response Plans ensuring all incidents are controlled and have limited impact. Develop an Environmentally and Socially aware culture. Effective communication at all levels to promote the ethos of zero harm to people PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 8 OF 45 property and the environment. Measure HSE Performance relative to continual improvement. Perform scheduled audits : Internal; External; Corporate; Technical. The aim of Contractor is to complete the Project achieving the HSE target of zero fire and zero fatal accidents. 6. HSE ORGANIZATION AND RESPONSIBILITIES 6.1 HSE Organization Responsibility for HSE permeates to all levels within the organizational structure of the Project, and the Contractor down to each subcontractor and supplier. Coordination and cooperation between and across these levels is aided through the use of a site HSE committee comprised of Contractor and subcontractor site management, field supervision and employees. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 6.1.1 Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 9 OF 45 Project Manager Has the project responsibility and authority for ensuring that the specific HSE requirements are identified, defined and fulfilled. These are defined in the project specific HSE plan/process maps/work methods and procedures. Also he’s responsible for ensuring all of his management team which includes the Construction Manager, Pre-commissioning Manager and Engineering Manager, Procurement Manager, is meeting their HSE objectives and for attending on a regular basis project HSE Committee meetings and recording the findings. Responsibilities also include: 6.1.2 Ensuring adequate HSE resources are available to implement HSE on the Project Chairs HSE meetings Supporting the application of the HSE Management System Project HSE Manager The HSE Manager establishes the safety control procedure based on CA’s safety manuals, Governmental and CA’s requirements to prevent possible accidents arising at site. Safety Officers will be assigned for safety assurance and control. The HSE Manager and his staffs will take necessary actions to maintain the facilities in a safe condition and instruct all site personnel to realize the importance of safety and to observe the safety rules. The HSE Manager always keeps close working association with the respective Construction Superintendents and draws their full attention towards accident prevention and safe working practices. The followings are the few of the specific responsibilities of the HSE Manager. Establishing field safety program. Adopting and applying standard safety practices, procedures, techniques and method. Establishing field security programs and making every possible arrangement for good implementation according to the program. Conducting initial orientation and regular safety meetings to ensure familiarization of all concerned party with safety requirements and to maintain safety consciousness and accident prevention measures. Determining the legal requirements for protecting worker and the public from accidents and health hazards. Providing a comprehensive program which will ensure the protection of life and property and fostering construction efficiency through selective use of safe work practices and PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 10 OF 45 through the establishment and maintenance of safe working conditions. 6.1.3 Supervising whether the work is performing in accordance with recognized safety standards, codes, statutory and/or local regulations, which may already exists or may come into force at later stage. Conducting Accident/Incident investigations using Root Cause Analysis. Coordinate with CA and Contractor Medical Teams to ensure compliance with expectation. Site HSE Manager Coordinates with the Project HSE Manager and reports to the Construction Manager. He is responsible for reviewing, monitoring, auditing and reporting on the performance of the HSE activities and performs audits directly or through specialists assigned from the corporate organization at his request. The Site HSE Manager will coordinate with the Construction Manager, Construction Supervisors, Quality Assurance and Quality Control to ensure that the work is being performed as required by the project HSE documents and procedures. Specifically, he will review and approve method statements and Permit to Work requests. In addition he is responsible for: Ensuring all HSE activities on site are in accordance with this Construction Safety Plan and the Construction HSE Reference Manual. Ensuring all subcontractors/suppliers and visitors on site comply with project HSE requirements. Coordinating with the CA Site HSE Representatives to establish meetings, training, assessments, etc Ensuring construction activities comply with all Algerian Legislation. HSE training/inductions and awareness training and hazard Identification. Ensuring Risk Assessments are carried out for all potentially hazardous activities. Notifying directly to the Project HSE Manager any HSE concerns with reporting responsibility to the Construction Manager. Preparing or amending the necessary work methods and procedures for working safely at site. Implementation of the Transportation Policy and Standards Ensuring all medical resources is in accordance with project requirements Ensuring all Emergency Response planning is in accordance with project requirements and that ER training is carried out. Develop, maintain and implement site Emergency Response Plan. Also make planning for emergencies with the Site Manager Responsible for accident investigation and reporting Reporting site HSE Inputs and statistics to CONTRACTOR Corporate HSE Department on a monthly basis Responsible for site safety, security and labors health Application of HSE on site on behalf of the Construction Manager Line management of the HSE Department PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 6.1.4 Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 11 OF 45 Improvement of HSE awareness and culture Advice to Construction Manager on HSE issues Administration and application of the safety incentive scheme Cooperation and coordination with the CA’s Safety Audit Review and implement the approved Safety Audit recommendation performed by the CA. Conduct scheduled inspections and HSE audits of all work areas and advising managers / area supervisors on unsatisfactory conditions or practices being observed. Develop, maintain and implement site Traffic Plan in coordination with Construction Manager. Shall report administratively to CONTRACTOR HSE Manager and functionally to Construction Manager Construction Manager Responsible for ensuring all construction activities are completed in accordance with the project HSE objectives and that all of his line management is suitably competent and trained in the same. He is responsible for ensuring that all managers, supervisors and designated subcontractor personnel reporting to him attend all required HSE meetings and training and comply with/support all HSE activities including: The Construction Manager will also have the overall responsibility for constructability and plot plan and layout reviews for construction safety aspects. Under his authority, the construction supervisors will implement the CONTRACTOR HSE policy in the daily activities. 6.1.5 Promoting the implementation of the HSE Plan by personal example Ensuring that safe construction equipment, tools and personal protection equipment and sufficient facilities for welfare, first aid and sanitation are available and used. Applying for Permits to Work Instructing the personnel working under their supervision to establish work methods, to plan the sequence of operations, to outline potential hazards at each stage, and to indicate precautions to be adopted. Checking work methods for newly started and major activities before work starts. Creating safety awareness by holding safety meetings and talks Field Engineers and Supervisors Field Engineers and Supervisors shall generally assist the Construction Manager/Section Manager in the execution of their duties. Field engineers and supervisors' general responsibilities include, but are not limited to: Being familiar with the requirements and recommendations for Safe Working Practices and Method Statements etc. applicable to their work place and ensure that they are enforced. Incorporating HSE instructions into the routine day to day orders and make sure they are understood and obeyed. Preventing site persons from taking unnecessary risks. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 6.1.6 Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 12 OF 45 Ensuring that all employees and sub-contractor’s personnel are suitably trained for the work in which they will be engaged. Ensuring that all employees and sub-contractor’s personnel adopt correct HSE precautions. Checking that all plant and equipment, including power and hand tools are maintained in a good condition and remove from use any defective items. Maintaining organized tidy and safe working areas. Maintaining all welfare facilities in a clean and safe condition. Ensuring that all operators/labor are provided with and use approved personal protective equipment. Ensuring that instructions are given in the use of any potentially hazardous materials. Discouraging horseplay and take actions against those who consistently fail to take care of their own Health and Safety and of other persons working with them or in the vicinity. Stopping any activity on site if there is an immediate risk of injury to any site personnel, or the possibility of a dangerous occurrence happening. Participate in any accident/incident investigation. Worker's Responsibility Workers shall report to work in a fit and proper condition to perform their job in a safe and competent manner. Workers shall observe and follow all established site HSE rules and safe work practices. They shall adhere to all work directives and procedures for the tasks assigned (whether provided orally or in writing). The use of personal electronic equipment such as hand phone, radio/tape sets shall be strictly prohibited at the site. Workers can have ‘STOP Work authority’ for each worker if the person observes unsafe situation. Workers shall report immediately any unsafe act or condition observed to a supervisor. 7. SUBCONTRACTOR 7.1 Subcontractor Selection and Interface Management Each subcontractor has the primary responsibility for the safety of the activities of its own employees in conformance with CONTRACTOR HSE requirements. The subcontractors will be required to Have in place/adopt HSE, plans and procedures matching project requirements Implement the CONTRACTOR HSE Plan for Construction, Comply with CA/ CONTRACTOR HSE procedures, and Prepare method statements and Pre-task Planning and Risk Analysis as required by CA and CONTRACTOR. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 13 OF 45 Identify the PPE requirement from CONTRACTOR HSE team and comply with it. CONTRACTOR will interface and manage subcontractors through pre-bid/award and kickoff meetings, weekly progress and performance reviews (including a review and trending of HSE matrix). This will also be facilitated by establishing a close working relationship between all Subcontractor HSE personnel and CONTRACTOR HSE personnel (Site HSE Committees, weekly meetings, assistance with HSE Toolbox Talk materials, etc) and through involvement of Subcontractor's in all sites HSE programs, inspections, meetings, and celebrations of success initiated on site. CONTRACTOR will when preparing all contracts and purchase orders attach HSE requirements to ensure HSE requirements are complied with. 7.2 Managing Subcontractors All subcontractors involved in the work will submit their own HSE program before contract with CONTRACTOR. CONTRACTOR will ensure that each subcontractor understands and follows the HSE Management System for this Project prior to mobilizing to site. CONTRACTOR will ensure that the applicable HSE procedures are communicated to the CA, subcontractors. 7.3 Working with Subcontractors CONTRACTOR will assess the capability of those who work on Contractor’s behalf to operate approved standards and monitor their performances. CONTRACTOR will work with subcontractors to encourage a responsible and effective approach to HSE and security management. They are to align with Contractor’s system wherever practical and possible. 7.4 Discipline to subcontractors All employees in the Project will comply with the HSE and security management rules and regulation of the Project. Any employees who violate HSE and security work practices and procedure repeatedly or seriously will be removed from the project/worksite. 7.5 Subcontractor Construction Manager Subcontractor construction managers will provide their workers with a safe and healthy working environment. They will be responsible for promoting safety and health consciousness among their workers at all times. They will be held accountable for enforcing: Subcontract requirements for HSE Provision of adequate and safe construction equipment and tools, and personal protection equipment for their workers That construction work is executed in the safest manner and follows a planned work sequence and procedures. Inspections of the work area to ensure that the entire work area is maintained in a safe and healthy condition PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 7.6 Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 14 OF 45 Supervisors take immediate corrective actions for any infractions. The holding of subcontractor safety meetings Actions required as a HSE Committee member. Subcontractor Safety Officers The subcontractor safety officers will: Implement and coordinate with CONTRACTOR HSE requirements within their respective work groups under CONTRACTOR overall supervision and direction. Become familiar with and comply with all Algerian Laws and regulations, Company, and CONTRACTOR HSE requirements, plans and procedures, including reporting and work permit procedures. Inspect construction areas and prepare reports and corrective action lists. Organize CONTRACTOR, Company, and subcontractor safety meetings, training and tool-box meetings. Subcontractor shall provide a sufficient number of qualified, full-time and dedicated field safety officers to support the Site HSE Plan. 7.7 Subcontractor Supervisory Personnel It is the responsibility of the subcontractor supervisors and foremen to ensure that their workers strictly adhere to the HSE procedures in their specific work and work areas. They shall promptly correct any unsafe conditions. They shall attend and actively participate in all required orientation, training sessions and meetings. They shall be cognizant of their positions as safety role models for their workforce and act accordingly. 8. MANAGEMENT OF CHANGE The Contractor continuously manages, monitor and assess changes in designs or procedures that could potentially affect EHS performance. Of primary concern to the CA is the possibility of changes being undertaken that impact on hazards and/or their potential effects. The Contractor’s change procedure shall ensure that any change proposal is reviewed by the Contractor’s EHS specialists prior to its implementation and the Contractor shall provide the Contracting Authority with a report of each such change insofar as it is associated with the Contractor’s performance of the Contract. Any change that involves safety critical equipment shall be referred to the Contracting Authority Representative for review prior to implementation. The Contractor shall implement procedures to cover changes to conditions or processes on each Worksite. Any change that may affect the health, safety, environment or security at a Worksite shall be covered by a procedure that ensures that all Personnel at that Worksite are made aware of the implications for their conduct at the Worksite. 9. COMPETENCY ASSURANCE The Contractor make provision for ensuring that all Contractor’s Personnel are suitably qualified, appropriately trained, experienced and familiar with the work they are to perform. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 15 OF 45 Prior to commencing Work at any Worksite, the Contractor shall demonstrate to the satisfaction of the Contracting Authority that all of its Personnel have successfully completed essential training to ensure competence and safe performance of duties appropriate to the parts of the Work being performed. Prior to awarding any sub-contract, the Contractor shall have a process to assess subcontractor’s ability to comply with these EHS requirements and can demonstrate that all sub-contractors are suitably qualified, appropriately trained, experienced and familiar with the Work they are to perform. Upon request by the Contracting Authority, the Contractor shall provide evidence of such assessment prior to the bid award. The Contractor is ultimately responsible for the performance of any sub-contractor and must ensure all subcontractors agree in writing to abide by the Contracting Authority’s EHS requirements. Contractor identifies inexperienced personnel so that others take precautions in their presence. Any Contractor personnel with less than six months of service in the same job/position with his/her present employer will be considered a Short Service Employee (SSE). The SSE(s) shall have a mentor assigned to the work site to provide consistent coaching, feedback, and oversight while employees develop skill sets to conduct their job tasks safely. 10. INTEGRITY ASSURANCE The Contractor has responsible for assuring the underlying integrity of any equipment or systems developed and/or used in the Contractor’s performance of the Contract. The Contracting Authority expects that integrity will be primarily assured by the Contractor’s effective application of internationally recognized codes and standards and an appropriate quality management system. 11. RISK EVALUATION AND MANAGEMENT Risk Management shall be performed before any work commences by all relevant project personnel, all subcontractor organizations and on all worksites where hazards have been identified or potential hazards are thought to exist. 11.1 Safety Planning and Coordination The safety planning will start with the mobilization of the Project HSE manager and the preparation of the Subcontracts packages. As members are assigned to the HSE Group, they will familiarize themselves with the site conditions and analyze the construction planning and construction equipment and resources, under the responsibility of the Project HSE Manager. The Project HSE Manager will identify and list: The work areas close to the existing facilities and, therefore, requiring work permits. Activities requiring a Job Safety Analysis (JSA) and recommendations on how to carry out the work. These lists will be issued for review to CA. The results of the safety planning will be published and discussed at the safety meetings, pre-construction meetings and kick-off meetings with the sub-contractors. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 11.2 Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 16 OF 45 Hazard Recognition and Control HEC structured processes to be utilized during the planning and execution phases of the work to identify, assess, and eliminate / control potential work site hazards includes the following: Project HSE Plan Site HSE Plan Construction Hazard Analysis Methods Statements Job Safety Analysis The identification and evaluation of hazards and environmental issues at the various stages of the Project and the development of control measures is part of the HSE management system. The Project will use the Site HSE Plan as the basis for site HSE Planning for identified risks/hazards. The project policy commits all personnel to ensure that prior to starting any task a risk assessment is completed. The risk assessment has the prime purpose of identifying the hazards associated with the task, who can be hurt and both that the appropriate controls are in place and the risks are reduced to as low as reasonably practicable. As an outcome of the hazard analysis, subcontractors shall be required to prepare JSA that address the tasks to be performed. Then as part of the two week look ahead, the tasks shall be planned and, equipment and personnel resources shall be identified and JSA developed. Thereafter ongoing risk assessment, minimize residual risk, hazard identification and elimination are achieved at the task level during the construction phase through inspections and audits. 11.3 Engineering The Safety Design Philosophy has been established as a separate document (0304-LB100) to ensure compliance with CA’s HSE Management Systems, Contract requirement and relevant legislation in Algeria from engineering stage and it provides controls for the managements of the Project HSE Risk to a level that is As Low As Reasonably Practicable (ALARP). 11.3.1 Risk Assessment The identification, assessment and management process shall be regulated by specific procedures, developed based on the plant characteristics, location, applicable legislation, and CA’s requirements. Risk identification, assessment and management of Engineering shall be an integral part of the safety engineering activities. Tools to be used include: Review and update of studies conducted during the FEED phase of the project, such as HAZID and P&ID safety review study HAZOP, SIL/LOPA Study PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 17 OF 45 Design reviews, such as 3D Model Reviews Safety reviews, such as QRA, Emergency Events and Consequence Assessment, Safety Case etc. Constructability reviews Check lists Management of Changes 11.3.2 Contractor HSE Management Contractor is committed to design the plant to meet industry standards of which HSE is a key element. The relevant Contractor engineering standards along with the project design criteria (Specifications, Drawings and documents) will be applied as the minimum HSE engineering standard for this Project HSE Manager will be responsible for ensuring that HSE is applied as per the relevant project specifications, procedures, international codes and standards. It is the individual Lead Engineers and Engineers responsibility to apply the HSE standards and design the plant to meet modern standards. 11.3.3 Identification of Hazards and Effect Early identification, analysis and evaluation of risks are important to enable Contractor to take preventive measures. The target is to reduce the exposure to an acceptable level and to execute tasks according to the applicable norms and regulations. In the Process Safety Management structure, which provides a framework of organizational structure, procedures and practices used to manage and reduce risks in order to prevent the consequences of catastrophic releases of toxic or explosive materials, Hazard Identification Reviews are essential tools to conduct organized, systematic and documented assessments to identify and analyze the potential hazards associated with the production process. The following methodologies will be applied in the Project development phase: HAZOP (Hazards & Operability) Review SIL (Safety Integrity Level) Study QRA (Quantitative Risk Assessment) including Fire and Explosion Hazard Analysis Emergency Events and Consequence Assessment RAM study Safety Case Safety Critical Elements and Performance Standards Escape and Evacuation Study Alarm Rationalization Review All procedures used to execute the above methodologies will comply with CA’ Standards. 11.4 Construction 11.4.1 Risk Assessment As for Engineering, the identification, assessment and management process shall be PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 18 OF 45 regulated by specific procedures, developed based on the plant characteristics, location, applicable legislation, and CA’s requirements, shall apply. Risk identification, assessment and management in Construction shall be an integral part of the construction activities, starting from the planning at the Home Office. The following tools shall be used Review of the studies conducted during the engineering phase of the project Participation in the 3D Model Reviews and Building Reviews Constructability reviews Check lists Job Risk Analysis Pre-start check list Workshops for specific areas of risks or hazards including SIMOPS Based on the results of this process at the Home Office, the methods of construction and type of equipment to be used are selected and the documentation to be prepared, identified. During construction, risk identification, assessment and control shall be regularly carried out as part of the pre-job risk analysis, and the preparation of method statements. Specific construction risk assessments shall be conducted by HEC with the participation of CA and Subcontractors for such items as heavy lift, concurrent construction of different disciplines (e.g., as civil works and piping) in the same area at different elevations, confined space work, radiographic examination at the Site, hydrostatic testing and SIMOPS. 11.4.2 HSE Management HSE management and safe working practices to be considered for transition phase since activities will be occurring without operating facility. That is Construction /Commissioning/ Startup activities will be going on at the same time. The Site Manager has responsibility for HSE during the construction phase. He is assisted in the implementation of HSE by the Site HSE Manager. HSE is everybody’s responsibility and the Site Manager will ensure that all members of the Project understand their duties. 11.4.3 Identification of Hazards and Effect The Contractor shall adopt various HEMP techniques to identify hazards in construction and completion phases to assess their likelihood and consequences. The analysis shall be used in implementing control measures to manage the risk effectively. Construction site risk will be identified and mitigated in a planned manner that will be established before commencement of construction work. Job Safety Assessment and other industry standard methods will be implemented to assess the hazards and identify the relevant controls required to control the risks. Job Safety Analysis (JSA) Control of Hazardous Material PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 19 OF 45 Preparation and implementation of relevant site HSE procedure Implementation and monitoring of effective general workplace practices Implementation of Permit to Work (PTW) system given by the CA Effective site supervision Preparation of hazardous chemicals and dangerous goods/materials inventory 11.4.4 Job Safety Analysis (JSA) Contractor will perform JSA to analyze the individual steps of a particular job and identify the hazards and risks involved in each step so as to develop ways to minimize or eliminate them as below sequence. Select the job to be analyzed with consideration of “Frequency of Accident", “Severity Potential”, “New Work Operation”, “New Job” and “High-rated Job” Break the job down into a sequence of steps, each describing what to do. Identify Hazards and Potential Accidents which are associated with job step Decide what control measures or job procedures are necessary to eliminate or minimize the hazards. Perform education for involved employees and ensuring the implementation of control measures. HEC supervisors or Subcontractors will develop and perform a pre-task job safety analysis in order to set out clear procedures and safety requirements for new activities and those hazardous activities listed by the Site HSE Manager. The JSA is a step-by-step analysis of the work to ensure that all the hazards are identified and the necessary precautions are taken into account to eliminate or isolate the hazards of the work to be performed. A standard form will be used for recording the results of the analysis. Depending on the complexity of the activity analyzed, more than one sheet, additional information and diagrams or Material Safety Data Sheets (MSDS) may be attached. The supervisor will present the JSA to the work crew who will carry out the work to ensure that they understand the risks involved and the work methods to be applied. 11.4.5 Hazards Effects Management Process (HEMP) (Explain HEMP briefly) Activities of all personnel having access to the workplace (including Subcontractor, workers, visitors and CA). Facilities of the workplace to be provided by Contractor or others. Contractor will ensure that the results of these full and systematic assessments and the effects of the control measures are considered when setting / reviewing/ revise / updating HSE objectives. 11.4.6 Control of Substances Hazardous to Health (COSHH) The control of substances hazardous to health is recognized as a critical element of the safety program and will be achieved through a combination of hazard communication, PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 20 OF 45 establishment of HSE systems of work and controlled handling and disposal of such substances. All activities within the site will be carefully and systematically evaluated for potential health hazards to provide comfortable working circumstance and the preservation of good Health and Hygiene Practices. Methods such as systematic inspections, interviews and questionnaires, and follow up by technical sampling of the employees on location will assist in identifying and assessing hazards. A Health Risk Assessment shall be conducted to identify and evaluate the following health hazards: Chemical Hazards Noise Hazards Radiation Hazards Illumination Hazards Vibration Hazards Temperature Extremes Ergonomic Hazards Other surveys will be conducted as necessary. The health hazard control measures will be established during planning of Plant / facilities and improved according to necessity during the construction phase. The principal health hazard controls are: Elimination of hazards Substitution of safer substances and/or devices Engineering control, such as improvement of operation, providing safeguards, ventilation, etc. Administrative control, such as providing proper work procedures, observation of HSE requirements and rules, etc. Ensuring all exposed personnel wear and use proper Personal Protective Equipment The control system commences at the procurement stage, at which all vendors and Subcontractor will be required to submit Material Safety Data Sheets for all hazardous substances that they will be supplying. Copies of these data sheets (including methods of treatment of injuries sustained by hazardous substances) will be forwarded to the Site HSE Manager who will retain a master file. Subcontractor will be required to carry out assessments in co-ordination with the Site HSE Manager and Field Supervisors (Commissioning Engineers) and in compliance with recognized standards. Only when all parties are satisfied there are no suitable alternative safer materials, and, that the control measures are adequate, will the materials be permitted on the worksite and used. Such control measures will address transport, storage, labeling, packaging, handling, disposal, personnel protective equipment and emergency procedures and training therein. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 21 OF 45 Persons using such substances will be trained/ informed on acquainted with the associated hazards and the necessary control measures through pre-task instruction and ready availability of method statements and data sheets. The hazardous substances covered will also include products from construction processes (such as welding fumes and solvent vapors). The disposal of waste material will also be considered, e.g. spent lubricating oil. Storage of hazardous substances on site will be kept to a minimum, as agreed by the Contractor. The requirements of Control Procedure of Substances Hazardous to Health (to be developed later) will apply. 11.5 Environmental The most effective way to manage the environment is to avoid spillages. Where this is not entirely possible mitigation measures will be put in place. The Project HSE Plan contains further details on environmental management needs and will be read in conjunction with this Construction HSE Procedure. The Contractor and its Subcontractor will follow Project soil erosion control plans that are in place to identify and address appropriate erosion control measures. The Contractor and Subcontractors will comply with CA’s ESIA and will adopt the specific procedures. 11.5.1 Environmental Requirements and Protection These reports identified the environmental sensitivities and impacts relevant to this Project and to protect the environment by a hierarchy of measures based on firstly prevention, followed by mitigation or compensation. These measures define the environmental requirements. 11.5.2 Impacts and Environmental Assessments These assessments will be used in the preparation of permit applications for the disposal of construction wastes, both solids and liquids, and permits related to the disposal of excess soil, to ensure full control of any environmental impacts, during the construction phase. 11.5.3 Air Emissions Emissions during construction and commissioning will arise from the vehicles used for transportation and from the diesel generators. Dust and noise surveys will be carried out in the vicinity of the construction site. The Contractor will carry out surveys. Countermeasures for construction emissions are as follows: All internal combustion engines will be suitably serviced and maintained to reduce polluting emissions. Dust control will be accomplished by properly wetting the work area by water truck, etc., prior to commencing the work and/or other approved measures. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 11.6 Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 22 OF 45 Pre-commissioning and Commissioning 11.6.1 Risk Assessment The identification, assessment and management process for Engineering and Construction shall be regulated by specifically developed procedures based on the plant characteristics, location, applicable legislation, and CA’s requirements shall apply. Risk identification, assessment and management shall be an integral part of the precommissioning and commissioning activities. Based on the results of this process at the Home Office, the Pre-commissioning group may propose changes in design (precommissioning and commissioning in, or close to, general construction areas or punch listing in pre-commissioning and commissioning areas), for example addition of isolation valves. The following tools shall be used Review of the studies conducted during the engineering phase of the project, such as QRA Participation in the 3D Model Reviews Constructability reviews Check lists Job Risk Analysis Pre-start check list Job Task Analysis Health Risk Assessment Workshops for specific areas of risks or hazards At the Site, risk identification, assessment and control shall be regularly carried out, in particular for the coordination between the pre-commissioning and commissioning crews and the construction crews working in, or closed to, areas that have been energized. Specific risk assessment workshops shall be conducted by HEC with the participation of CA and Subcontractors for such items as energization of the facilities and introduction of hydrocarbons. The results of the workshops carried out before the start of construction, i.e., recommendations and action items, shall be regularly reviewed by the Pre-commissioning Manager to ensure that the assumptions made at the workshops on the working areas and the construction schedule are still valid. 12. CONSTRUCTION SAFETY PLANNING 12.1 Crane/Lifting Equipment/Lifting Gear Risks associated with lifting are significant and, coupled with the considerable scope of such activity, represent a substantial area of potential loss exposure. Consequently, the Contractor will utilize stringent control on both the lifts themselves and the hardware involved. Therefore, all cranes, Hiabs, piling rigs, etc., will be inspected, load tested and all certification checked by the Contractor prior to entry onto the worksite. The Heavy Lift Supervisor will maintain records of such inspections. All proposed Subcontractor prior to mobilization would assess crane/lift operators for competency and ensure that all certification is valid for the equipment being used. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 23 OF 45 This will comprise the submission of a valid national operators license and also the successful completion of a local competency test. All lifting equipment to be added to the Contractor’s lifting register and Colour Coded based on 6 month inspections/re-certifications by a competent person. If successful, operators will only be permitted to operate the equipment for which they have been assessed. 12.2 Temporary Electrics Contractor will prepare site specific procedures defining electrical safety requirements and precautions for those employees working near electrically operated equipment to ols, or with cause to work on or near electrically operated equipment tools, or with c ause to work on the construction power supply system. 12.2.1 Electrical Hazards: The construction site will present a number of potential hazards from the use of electrical tools and equipment and the electrical power supply which extends throughout the work site and each of the working areas. The hazards from electrical fault or mishap on the construction site are severe and ever present. They include: Electrocution or electrical shock which may kill or cause serious injury. Overhead electrical conductors may cause burn injury and ignite flammable materials. Switching or sparking of ordinary electrical equipment in flammable atmospheres may cause fires and explosions, even a small spark from a battery operated appliance may have sufficient energy as a source of ignition. Electrical arcing and flashover from improperly operated switches, etc. may cause burn injuries. Accordingly, proper care will be exercised when installing, operating and working around such electrical equipment and systems on the site. 12.2.2 Electrical Safety Measures: The electrical safety procedures to be applied on site and will include training/orienta tion of both Safety Supervisors and the work force in the hazards that can be enco untered and the safe working measures needed to protect against injury or damage 12.3 All Vehicles And Traffic Control Traffic on the worksite will be minimised so as to avoid unnecessary hazards and congestion at the workplace, with entry onto worksite being controlled via the issue of vehicle passes. Speed limits will be enforced by the Contractor Security Department. Specific accesses and egresses for pedestrians will be maintained at all times, as will routings for emergency vehicles. Any vehicle wishing to block roads for any period of time will first obtain a road closure permit from the Contractor. Subcontractor will be made aware of all such closures and heavy equipment routings at PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 24 OF 45 Subcontractor daily HSE meeting. The Contractor and Subcontractor will develop Road Safety Policies to minimize possibilities of traffic accidents on the public highway, e.g.: 12.4 Driving times Age Driving hours Route and resting plan Welding and Heat Operation The purpose of this welding and heating operations instruction is to outline the Safety requirements for managing and controlling operations involving the use of welding equipment on this Project. The main hazards likely to be encountered during welding and burning processes can be identified as follow: High Temperature causing risk of fire and burns. Fumes emitted from the process likely to cause injury to health. Radiation causing 'arc eye' and burns. Oxygen deficiency or enrichment, particularly within an enclosed space. Electric shock Explosions during the welding and cutting of drums, tanks or vessels which have contained flammable materials. These instructions provide general considerations for the control and use of welding and burning plant and equipment used on site which is based upon Permit to Work Camps, Offices. Fire watchers shall be placed whenever welding or cutting is performed in locations where a risk assessment shows an increased likelihood. 12.5 Excavation Procedures Excavation procedures(0304-ZB-136) will be developed to address soil classification, benching, shoring, air sampling, and entry and exit routes, spoils location, and traffic and equipment management. 13. COMMISSIONING SAFETY PLANNING Commissioning Group will pay particular attention to identify any additional flanging, spading or valve isolation requirements to ensure the integrity of live systems in an area where construction work is still being carried out. Development of diesel and water management plans, and waste disposal procedures will be carried out. The safety and welfare of the work force and the need to protect equipment must be considered paramount and highlighted in any work permit that is issued. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 13.1 Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 25 OF 45 Work Permit Control a) Once a system has been handed over from Construction to Commissioning and comes under the care and custody of Commissioning, the Commissioning Manager will be responsible for issuing work permits that will govern all activities to be carried out in the areas being commissioned. b) A Permit Office will be provided to manage the issue regarding the Work Permits. 13.2 Prevention of Contact Ingestion Skin Contact Burns Eye Contact 13.3 Eating and drinking will be only allowed in designated areas. Measures must be taken to prevent hazardous materials from contacting the skin and provide first aid or medical treatment in the case of accidental contact. Non-porous gloves and goggles are minimum requirements. All process equipment in accessible areas operating at temperatures above about 70oC is normally insulated to ensure personnel protection. Lines and equipment in cryogenic service are also insulated for heat retention and for protection against cold burns. General-purpose gloves will be worn. Eye irritants can cause permanent damage to the eye very rapidly. All eye injuries will receive immediate medical attention. Eye wash bottles and water coolers will be located on plant against recognized approved standards where materials such as acids, alkalis, amines can be encountered. Safety glasses must be worn and goggles must be worn on the helmet in all commissioning areas. Maintenance of Safety Equipment All safety equipment will be checked on a monthly basis and must be maintained in a condition ready for use. Fire extinguishers must be checked at monthly intervals and recharged or replaced immediately after use. All air and water hose equipment must be returned to their original place after use. Access to such equipment must not be obstructed. When a fire extinguisher is used the occurrence of a fire will be reported in an incident report. No work on any live equipment will be done without a properly authorized permit to work issued by the Commissioning Manager or his designees. 13.4 Housekeeping Loose materials etc., will never are left in a manner causing a tripping hazard on platforms, access ways, etc. Access to ladders and fire escapes must be kept accessible at all times. Waste and refuse must be put in proper designated areas or containers. 14. START-UP PRECAUTIONS SAFETY PLANNING 14.1 Work Permit Control All work will have a Work Permit issued by the CA operations. All conditions on the work PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 26 OF 45 permit will be strictly adhered to such as fire extinguishers to be in place and drainage systems covered. 14.2 Emission to Atmosphere Hot liquids or vapours must never be discharged directly to the atmosphere. All measures must be taken to prevent or control emissions. Where temporary noise pollution exceeds 85 dBA, temporary silencers will be used. 14.3 Toxic Gases Vessels may contain highly toxic gases. Inert gases such as nitrogen pose a particular hazard of asphyxiation. Extreme care must be taken in the venting purging, cooling and opening of such equipment. 14.4 Working Practices 1) No burning, welding, cutting, grinding, or other hot work will be allowed in live areas unless properly authorized by a permit to work issued by the CA Operation representatives. 2) No person will be permitted to work within a flammable atmosphere. Where appropriate proof tested flammable gas detector of calibrated will be employed to minimize the risks from any leakage by providing adequate warning. 3) Authorized personnel in compliance with a permit to work will only work electrical equipment on. 4) Do not use hydrocarbons to clean machinery or for any other cleaning purposes. Use a permitted cleaning agent instead. 5) When pressurized systems are to be worked on a procedure with a method statement must accompany the work permit. 6) Environmental requirements for collection of cleaning agents to be determined 7) Guards around moving shafts or couplings, which have been removed must be replaced when repair work is completed and before equipment is energized. 8) During flushing or air blowing, areas where liquids or gases are exiting must be barricaded off and warning signs, written in English and local languages displayed. 15. HSE DOCUMENTATION 15.1 General The HSE documentation consists of the following: Project HSE Plan, this document Confined Space Entry Procedure (0304-ZB-118) Site Health, Safety and Environment Plan (0304-ZB-124) Emergency Response Plan (0304-ZB-128) Environmental Management Plan (0304-ZB-132) Work at Height Procedure (0304-ZB-134) Incident Reporting and Investigation (0304-ZB-135) PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 15.2 Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 27 OF 45 Occupational Health Policy and Procedure (0304-ZB-137) Health Risk Assessment (0304-ZB-138) HSE Schedule and Indices (0304-ZB-139) Safety Management Plan (0304-ZB-142) Project HSE Audit Procedure and Plan (0304-ZB-143) CA Procedures and Requirements. These procedures shall be followed by HEC as per contract agreement with CA Documentation Hierarchy The hierarchy of the HSE Documentation is as follows: Laws and Regulations of Algeria Contract between CA and Contractor CA Project Specifications and Mandatory Procedures Contractor HSE documentation, plans and procedure Project Management Directives Internationally recognized standards for items that are not adequately covered by regulations or project requirements 16. HSE TRAINING 16.1 General Information Contractor will establish and provide the essential resources (human, technical and economic) to ensure the implementation, control and improvement of the HSE system. The CA is the main reference for Contractor and subcontractor HSE training requirement. Therefore, Contractor will establish the necessary means are taken to ensure that any person working for the Project has, but are not limited to: 16.2 Their HSE functions and responsibilities clearly defined. The necessary experience and information to carry out his functions. The necessary means and resources to carry out the work. Awareness of the policy and the requirements of the system, the preventive aspects of his work and consequences of non compliance with procedures. HEC, Subcontractor and Supplier Personnel All HSE training for construction personnel will be conducted through the following: Work-site admission orientation sessions Pre-construction meetings for critical activities Training and awareness sessions Safety meetings 16.3 HSE Induction Training for New Entrants It is mandatory for all managers and employees of the Contractor and Subcontractor to PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 28 OF 45 attend HSE Induction Training prior to starting their fieldwork. Without taking this training course, they cannot receive an Identification (ID) card for entry to work on the construction site. Prior to the HSE Induction Training, all managerial personnel and employees will submit their “Personal Information” using the designated form (name, age, gender, profession, physical status, experience, license or certification, etc.). For the training of safe work practices, “Safe Work Practices and Equipment Standards”, which will be developed including the requirements of CA legislations and standards, is available for trainer’s use. Any Contractor personnel with less than six months of service in the same job/position with his/her present employer will be considered a Short Service Employee (SSE). The SSE(s) shall have a mentor assigned to the work site to provide consistent coaching, feedback, and oversight while employees develop skill sets to conduct their job tasks safely. The Induction Training includes individual instruction given to new entrants workers and their supervisors according to their work categories, as described below, but not be limited to: 16.4 General Orientation All personnel assigned to or visiting the construction site will be given a site induction course and badge/sticker the first day of work by HEC. This course is mandatory and no entry to the Construction Site or work will be allowed prior to participation in the Safety Induction. Outline of the work and the work procedures. Working Rules: Duty hours Overtime work Transportation Prohibition of smoking Drugs and alcohol Possession of firearms, etc. Participation in the Tool Box Meetings, Security rules, including Gate Control, Confirmation and registration of worker’s craft certificates or other form of qualification, Traffic rules and regulations, Outline of Emergency Procedure, Work Permit System Fire Prevention Personal Protective Equipment Requirements and abuse /ineffective use Personal Health and Hygiene Anticipated environmental problems and their countermeasures, Housekeeping requirements PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 16.5 Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 29 OF 45 Avoidance of spillage/contamination, use of drip trays, oil pans, HSE Training for Managers and Supervisors In addition to the Induction Training for new entrants, specific HSE training is given to Contractor and Subcontractor Managers (Two times per year) and Supervisors (Three times per year) by the Site HSE Manager or competent persons assigned by Site HSE Manager, the training will cover, but not be limited to: 16.6 Individual’s roles and responsibilities for HSE management Enhancement of HSE awareness (emphasize Line Responsibilities) Regular safety activities HSE Committee Meeting and other HSE meetings Incident Reporting and Investigation Environmental Awareness & issues Hazard Awareness and Communication Light and Heavy Vehicle Daily Check Method Statement, Risk Analysis Job Safety Analysis, for permanent and temporary works HSE Management System HSE Training for Specific Hazardous Work Special training will be given by competent persons designated/approved by the Site HSE Manager, to supervisors, foremen and workers involved in specific hazardous or harmful work, the training will cover, but not be limited to: 16.7 Handling organic solvents, and toxic and hazardous chemicals Handling and storage of radioactive materials Work under, over on or near water Deep excavation and trenching Work in confined areas or narrow spaces Rigging, lifting and crane operation Erection and dismantling of scaffolds Work in or near an existing plant (regardless of whether operating or not) Removal of Grating Working at Heights Hot works Stored Energy Fire, Evacuation and First-Aid Training Fire and First Aid Training, and Evacuation Training will be given to all employees. The competent personnel designated by the Site HSE Manager conduct this training. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 16.8 : 0304-GP-112 : 2011065 :0 : 30 OF 45 HSE Training Matrix Item General HSE induction Training Initial HSE induction Training Specific HSE Training Change of Work TBM Doc. No. Job No. Rev. No. Page Contents Attendee - Risk Assessment Matrix / Results of HSE inspections / Identification of Risks and Hazards from the work - Risks and Hazards from the work - Safety Work Method - Usage of PPE and Safety equipment - Accident Cases and its safety measures - HSE notices and news - Emergency preparedness and Response (Natural Disasters, Fire and environment Spill) All - HEC & Project site’s HSE Policy and Target - Implementation of HSE Management system - Identification of HSE Requirement and applicable law. - Job Safety Analysis and Results from HSE Meetings and Inspections - Each Job description on HSE area - Emergency preparedness and Response (Natural Disasters, Fire and environment Spill) - Korean Occupational Safety and Health Law (Only for Korean Project) - Legal Obligation for overseas project. - Legal Obligation for each country. - Project General Information, Plot Plan, Process information, Risk Area Classification and Safety Signage on site. - The usage and distribution of PPE - Specific Site Safety Rules (Using safety passages and housekeeping) - Safety matters for heave equipment. - Fire protection/fighting Safety - Emergency response awareness - Heat stress - Working at height safety - Excavations safety - Confined space entry - Incident reporting and investigation - Lifting safety - Rigging/Slinging safety - Heavy equipment for the work - Accident cases from similar types of work - The usage of PPE - Emergency preparedness and Response (Natural Disasters, Fire and environment Spill) - The specific information on its area. - Implement of TBM activities. - A brief on the HSE Matters Instructor Site Manger Supervisor HSE Manager Site Manger from Sub-con. External instructor Supervisors And Site Managers from Sub-Con. All Site Manger HSE Manger Site Manger from Sub-con All Site Manager Qualified Person Third Party All Site Manager HSE Manager Site Manager from Sub-com All Site Manager HSE Manager Site Manager from Sub-com Foremen PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 17. Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 31 OF 45 PERMIT TO WORK SYSTEM A permit to work system will be implemented on the Project, to ensure that those tasks attracting elements of risk will be subjected to thorough and systematic planning and preparation prior to their authorization to proceed. The Contractor will continually update the precise scope of the application reflecting the differing needs of the various construction phases and also the need to interface with the permit to work systems to be implemented during commissioning and start up. Notwithstanding this, certain activities mentioned below are required to obtain a Work Permit issued by Contractor issuers. Confined Space Entry, Radiography, pneumatic testing, Removal of grating and handrails on structures, etc., Electrical work require to de-energize or isolate electrical equipment/components, Explosive Device, use of cartridge-operated tools, Pressurized Testing The underlying philosophy of the Contractor permit to work system is that Subcontractor task supervisor receives a permit only after it has been reviewed by The Contractor Discipline Supervisor and approved by the relevant Area Construction Manager (Commissioning Manager). Further, the permit program provides a form of method statement, job safety analysis that clearly identifies measures to be adopted by Subcontractor and his employees. Only persons who have successfully completed the Contractor permit to work training module will be permitted to initiate, receive, review or authorise permits. The system that allows central control and ongoing monitoring of higher risk activities to ensure that activities are; 1) Authorized by the appropriate site supervisory personnel responsible for the particular area or for control of hazardous activities, 1) Carried out by qualified personnel using appropriate safety precautions 2) Ensures that those activities with potentially hazardous interactions do not take place at the same time. 17.1 Cold & Hot Work Permit Cold Work Permit 2) General construction/commissioning work and maintenance not involving the breaking of containment of hydrocarbon system 3) Working with radioactive sources: Radiography Certificate also required 4) Working with nitrogen gas 5) Excavations: Excavation Certificate also required 6) Working with mineral fiber PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 32 OF 45 7) Handling or use of hazardous substances 8) Spray painting/coating 9) Work affecting the availability of fire and gas detection system, e.g. flammable gas detection, fire detection and Uninterruptible Power Supplies (UPS) 10) Work affecting the availability of fire protection gaseous system (CO2) 11) Work affecting the availability of process safety and protection arrangement, e.g., Emergency Shutdown Valve (ESDV) systems, blow down and drains systems 12) Work affecting the internal or external communications systems of the installation/site 13) Working on computer controlled systems 14) Removal of handrails, gratings, hatches and fixed ladders 15) Work at height greater than 1.8 meters 16) Pressure testing of plant and equipment 17) Bleeding down vessels to drains or to atmosphere 18) Use of equipment or work in Non-Hazardous Zones involving: a) Dry grit/shot blasting b) Cartridge operated tools c) Use of torque wrenches in Hazardous Zones 19) Electric work Hot Work Permit 1) Work involving naked flame 2) Welding 3) Use of portable grinder (electrically and air power) 4) Use of heat shrink blowers and electric power tools in Hazardous Zones 5) Nitrogen/ Gas leak testing of plant and equipment 17.2 Confined Spaces Permit A space that is large enough and so configured that an employee can bodily enter and perform assigned work. 1) Confined Space permits are required for any confined space entry operations 2) A confined space is a place, which if substantially (though not always entirely) enclosed, and where there is a reasonably foreseeable risk of serious injury form hazardous substances or conditions within the space or nearby. Examples of confined spaces are closed tanks, vessels, sewers, open-topped tanks, vats, pits, and closed and unventilated or inadequately ventilated rooms 3) Some places fall within the definition of a confined space only occasionally, perhaps due to the type of work to be undertaken e.g. spray painting in a room. Spaces may become confined due to a change in the condition inside or change in the degree of enclosure or confinement that may occur intermittently. 4) An initial gas test must be recorded on the Confined Space permit and must be continuous unless special dispensation is granted. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 18. Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 33 OF 45 PERSONAL PROTECTIVE EQUIPMENT (PPE) An effective PPE program is an essential protection against those hazards, which cannot be engineered out of the construction environment. Further, the conformance to the PPE program also provides a valuable indicator of safety attitudes and behaviour of the workforce. The Contractor and Subcontractor will ensure that all PPE is "fitted" correctly to meet individual requirements. All PPE will conform to either AS, BS, ANSI or DIN standards when applicable, be suitable for the purpose, and will be maintained by individuals to ensure that the integrity of such equipment is not compromised. In addition, such equipment will be provided free issue to all Subcontractors, and replaced as required. Certain items of PPE will be mandatory and worn at all times whilst on the worksite, these will be: Safety helmets Safety footwear with steel toecaps Safety glasses with side protection Coveralls (minimum 60% cotton or 100% cotton) Welders Coverall, Fire retardant During the Commissioning phase in addition to the mandatory wearing of P.P.E specified in above other items of appropriate type of equipment required by/for the work will be in use. Also, any persons working at an elevation of 1.8 meters or above will wear a full-body safety harness with dual lanyards that will be attached to an adequate load bearing anchor point or lifeline appropriate fall arrest or on an incomplete structure when working outside handrails. However, the Contractor stresses that this is a residual form of protection, the need for which will be avoided wherever practicable by the use of safe working platforms. 19. COMMUNICATION NETWORK Effective communications are vital to the successful implementation of the health, safety and environmental plan. Communications take many forms but their common objective is to improve understanding of health, safety and environmental matters, thus obtaining the support, co-operation and commitment of all interested parties. Contractor will ensure that all of its personnel are able to communicate in a safe, clear and effective manner. It is imperative that all personnel are given and understand written, visual and oral instruction from management and supervisors. Contractor will provide all resources necessary to ensure that communications are understood among all personnel on any Worksite. Contractor will carefully consider and specify the requirements for communication between multi-national workforces and ensure that each work crew shall use a common language or have an in-crew interpreter. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 34 OF 45 [Contractor HSE Site Communication Chain] Construction Director Monthly Site HSE Committee CA & Contractor HSE Strategy Meeting CONSTRUCTION Construction Manager Fortnightly Contractor/Subcontractor HSE Meetings Weekly Discipline Contractor/party/Subcontractor Co-ordination Meeting HSE representation Weekly Progress Meeting Party/Subcontractor HSE Officer/Management Toolbox Talks/Daily HSE Contractor/party/Subcontractor HSE weekly coordination Meeting Contractor/party/Subcontractor HSE Officers/Supervisor Daily Meeting CA, Contractor & Subcontractor: Senior Line Management Construction Manager Discipline Supervisors HSE Officers Weekly HSE Scoring The above communication chain will be developed to incorporate Commissioning team members as Project progresses. 19.1 Radio Contact Adequate numbers of intrinsically safe portable radios (walkie talkies), and chargers will be made available to the Construction and Commissioning Group. These will all be correctly licensed according to Algerian regulations and under the Contractor ARPT Radio licensed. This requirement will extend to all Sub-contractors. The radios will have channels allocated according to a radio channel master plan to be developed by the CA and the Contractor. Commissioning channels will accommodate the following requirements: Commissioning, Contractor and CA Emergency services Subcontractor and vendors For overlap with construction PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 20. HSE MEETINGS 20.1 Monthly Site HSE Committee Meeting Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 35 OF 45 Contractor Construction Director chairs the HSE Committee Meeting with members comprising Contractor Construction Managers, each Area Construction Managers, Site HSE Manager, all the Subcontractor Site Managers, HSE Managers, and the CA’s Project Manager, HSE Representatives. The HSE Committee Meeting will be monthly held throughout the construction and commissioning. The agenda for the meeting will be structured around the following guidelines: Minutes of the last meeting. Matters arising timely. Incidents and near misses. Feedback on incidents. Publicity/promotion/initiatives. Monthly look ahead of construction activities. Anticipated concerns. Interface between Subcontractor. Feedback from site personnel. The minutes of meeting will be prepared by the Contractor HSE staff, and distributed to relevant personnel of the CA, Contractor and all Subcontractor, and by so doing, communicating HSE issues and requirements to the workforce will be achieved. The major objectives of the HSE Committee Meeting are to: 20.2 Ensure that the HSE training programs are implemented and properly carried out to promote employees’ HSE consciousness and knowledge, Enhance and maintain housekeeping and waste disposal to the highest standard. Distribute any information and instructions from CA and/or the authorities concerned. Debate and confirm Monthly HSE Objectives and Targets proposed by the Contractor Construction Director. Recommend groups and individuals for HSE incentive awards in accordance with the HSE incentive award scheme. Announce Forthcoming changes in the type of work as the Project progress. Weekly HSE Coordination Meeting Contractor and Subcontractor will hold weekly HSE Coordination Meeting. Participants in this meeting will be: HSE Officers and Supervisors Subcontractor’s HSE Manager The purpose of this meeting is to review and coordinate the site activities planned, with the Contractor and Subcontractor, to discuss general HSE matters, to review and assess HSE PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 36 OF 45 inspections outputs, to discuss the lessons learn from site incident reports and measures take or to be taken to prevent the recurrence. HSE requirements and information will be reinforced and reviewed with Subcontractor in this meeting. The major objectives of the meeting are to: 20.3 Use findings of HSE scoring. Discuss HSE topics and any problems observed or anticipated. Have each Subcontractor report on the status and performance of HSE activities including HSE training. Report on recent incidents and near misses, and on follow-up actions. Weekly Discipline Contractor/Subcontractor Meeting Each construction area will hold a weekly discipline HSE meeting (more often if required) attended by all relevant Subcontractor Management and the Contractor supervisor, and chaired by the Contractor Area Construction Managers responsible for the area. Its objectives will include review of recent HSE performance, review of forthcoming key work activities, recent initiatives, Contractor interfaces, etc. 20.4 Daily Toolbox Meeting Daily ‘Toolbox Meeting’ will be given at start of each shift, and again just prior to non-routine activities. Subcontractor supervision will conduct these in a language understood by all members of the workforce and will address the application of safety rules and procedures to the hazards of current work. Two-way discussion will be encouraged. Duration of the team talk will typically be 5 minutes, but particularly hazardous operations may require extended team talks, for example, confined space entry. Two-way communication will be encouraged (An interpreter must be present if needed.). All work crews including supervisors, foremen and workers, will actively participate. Managers will attend as frequently as possible. As a continuation of Subcontractor daily talks prior to starting work, Area Supervisor’s (Commissioning Engineer’s) must hold daily commissioning team talks in order to explain details of Commissioning work to be carried out in that area and ensure the workforce understands all safety related matters concerning the work. A record of the date, the ongoing work, the toolbox topic and attendance will be kept. The Contractor line management will monitor the meetings on a weekly basis to check their effectiveness. Mainly, the working plan and procedures for the day are explained and confirmed including the following: Briefing on topics of HSE meetings, CA’s information, etc. Current HSE issues and concerns. Anticipated potential hazards and suitable countermeasures. Safety instructions for equipment and tools to be used. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 37 OF 45 Confirmation whether any Work Permits required for the work have been obtained. 20.5 Use of proper personal protective equipment (PPE) and safety devices. Information on other work to be conducted in the vicinity of the working area. Visual check of the health condition and proper allocation of workers. Special Meetings Additional meetings may be called to address special circumstances, e.g.: 21. Work involving novel construction or commissioning techniques. Work requiring special instructions and precautions. Visits by HSE or local regulatory authorities. Poor performance by specific Subcontractor. Feed back of audit findings. Reporting the impact on health, safety and environment of any design work concurrent with the construction phase (i.e. Identifying potential hazards, which were unknown at the contract award stage.) CA interface co-ordination. Subcontractor interface co-ordination. EMERGENCY EVACUATION PROCEDURE All site personnel will be advised of the actions to be followed in the event of fire, gas/toxic release or any other emergency situation. Such advice will be given at site inductions and subsequent ongoing safety training sessions. The procedure will be included in the HSE booklet issued to all employees and will also be published on notice boards, strategically placed around the site. Emergency telephone numbers will be listed. A basic map will be provided which shows evacuation routes and assembly points. Exercises in each facility shall be conducted at least every quarterly basis (to be discussed with Company to increase frequency at site) and the observation shall be recorded. The report should be forwarded to the HSSE Department and any remedial actions required shall be identified. 22. FIRE PREVENTION AND PROTECTION Whilst the risk of major fire damage in construction, pre-commissioning and start-up areas is considered by the Contractor to be reasonably minor, (with key risks presented by compressed gas cylinders, painting and insulation materials and general debris and rubbish), the risk in the camp and office areas is considered to be high. In order to prevent such hazards materializing, the Contractor will implement a Project-wide fire prevention/protection strategy that is characterized by the following general principles: PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 38 OF 45 Minimal bulk storage on site of flammable substances in appropriate containers Isolation of flammables from sources of ignition Training in fire prevention and suppression techniques Integrity of electrical equipment Permit to work control Containment of sparks and flames from Hot Works Escape route planning Restricted smoking areas. The employment and maintenance of fire extinguishers at strategic locations throughout the worksite and also the deployment of a fire and emergency response truck, which will remain permanently manned at a strategic location, will support this approach. This truck will be mobilized in response to all fires on site and will be used during emergency response training exercises. Prior to start of Start up, all operational fire protection equipment must be in place. The fire prevention/protection strategy will include all worksite offices, warehouses, camp, etc., and will be developed to include commissioning activities. 23. HSE AWARENESS 23.1 HSE Incentive Sheme The purpose of HSE incentive scheme is one kind of motivation technique for workers at site to promote individual safety performance, increasing the production and reduce injuries which will be done by providing individuals with a certain type of awards for good performance. 23.2 HSE Awareness Program Safety and training materials such as booklets, posters, visual aids, etc. will be suggested by Contractor. Each subcontractor will be expected to arrange for appropriate materials and should utilize the materials suggested. Posters of all sizes must be displayed in the appropriate languages at locations throughout the site. Site HSE Manager shall maintain the HSE scoreboard and display it at the key location of the project site facilities. Information of the HSE scoreboard shall be updated on daily basis Also Site HSE Manager shall arrange to issue HSE flyer for providing details of the site accidents/injuries, summarizing details and comments to avoid re-occurrence on the project site. Warning signs will be displayed throughout the site, wherever any hazard warrant their use. Bulletin boards will be used to advantage in displaying safety posters. 24. MANAGEMENT OF WASTE MATERIALS The objectives of waste management activities are to: PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 39 OF 45 Ensure safe and proper segregation, handling, storage, transport and disposal of waste. Identify environmental aspects and impacts Reduce/minimise the volume of waste or utilize as much as possible for recycle or reuse. Reduce/minimize the impact of dust, noise, light, odours, working hours and general disruption on the local community Assess any relevant task to ensure adequate controls are in place to minimize the impact of hazardous substances on individuals and to protect the environment Reduce/minimize the environmental impact of chemicals through correct selection, transportation, storage, deployment and disposal Manage all waste according to the following hierarchy: eliminate where possible, reduce at source, re-use, recycle and dispose. Disposal shall be in accordance with ‘duty of care’ principles and disposal records shall be maintained by Contractor and available for audit by CA Reduce/minimize any air emission and discharges to water. All waste management activities will comply with the applicable laws and regulations and the CA’s requirements. 24.1 Non-hazardous Waste Subcontractor are responsible for collection, segregation, recording, transport and disposal of waste to the location, designated by the CA, where located out of the Contractor asset/boundaries. 24.2 Hazardous Waste Hazardous substances will be handled, transported and stored at the Contractor designated storage on site properly. 24.3 Sewage Disposal The Contractor and Subcontractor will ensure that all sewage from offices, site and camp is treated properly and follow the local laws and regulations strictly. The sewage system will consist of sewage underground piping, manholes, lift station pit with pumps, biological sewage treatment plant and treated effluent underground piping to facilitate sewage management a bioreactor will be installed for the construction period. 24.4 Worksite Waste All waste material will be identified and segregated. Each Subcontractor will be responsible for the provision of such facilities to segregate waste. An adequate number of skips and bins will be located at key positions on the worksite by Subcontractor based on their workload. These items to be disposed of will be clearly identified according to the classification of waste, which they will generate. Subcontractor will be directly responsible for proper storage of waste in these containers. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 40 OF 45 Domestic waste from the temporary facilities etc. on the worksite will be handled in exactly the same manner as at the Labor Camp. Hazardous waste will be stored in a closed secure container, clearly marked, with Material Safety Data sheet, as hazardous material and transported to the Contractor designated onsite storage. All concrete debris and/or unused concrete will be deposited to an area being located out of the site designated by the CA. 24.5 Housekeeping All areas must be kept free from debris and waste material on an ongoing basis. At the end of each working day a check will be carried out by Subcontractor Task Supervisors to make sure that all waste material has been gathered and deposed of in the allocated area. All empty containers of hazardous material must be removed from the work area as soon as is reasonably practicable. All empty gas bottles must be returned to their storage area and stored in the proper manner. All spillages must be cleaned immediately in accordance with the product manufacturers recommendations and reported to the Site HSE Manager. A spillage is an environmental incident and will be reported in the Project Incident Data Base. An incident report and investigation report will be generated. The Contractor will keep an overview of spillages on an O/A Plot Plan. All cleaning materials due to solvent content etc. will be treated as hazardous waste and disposed of as such. Food consumption will not be permitted on the construction site. 24.6 Waste Collection and Disposal The Waste Management Plan(0304-ZB-132) will be an integral part of each subcontract and will be the responsibility of Subcontractor. This will ensure that good housekeeping is practiced and also that collection, segregation, storage and disposal of waste is properly controlled to minimize the environmental impact of the Project. Regular waste collections will be undertaken by a specified Subcontractor, who will be approved by the relevant Authority to carry and dispose of the various types of waste generated. The waste management co-coordinator of each Subcontractor will prepare a monthly report detailing the types and quantities of waste removed from site and/or stored on-site during that period. The Contractor Waste Management Controller will monitor all collection points to ensure that there is no over-spill or backlog of waste removal. In addition, they will spot check the waste control against its description on the Manifest before it leaves the site by the appointed transporter. Disposal by burning will be prohibited without prior permission of the Contractor/CA. All copies of permits must be retained by the waste disposal co-ordinator and must be produced on demand by any authorized authority. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN 25. WELFARE 25.1 Sanitation Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 41 OF 45 The Contractor and Subcontractor will ensure the provision of adequate sanitation including sufficient WC’s, urinals and washing facilities for all personnel, anti bacterial soaps and will be clean and maintain them on a daily basis. 25.2 Medical Facilities The Contractor believes that the utilization of a single medical facility ensures both consistency of treatment and accuracy and openness of injury reporting. Therefore, construction Subcontractor will be prohibited from establishing their own medical facilities, (other than immediate First Aid) with the result that all injuries, irrespective of seriousness, will be reported to the Project medical facility on an immediate basis. Qualified personnel for all hours during which activity is taking place on the worksite will man this facility. Detailed records of all such injuries and treatment will be maintained and will be input into the Incident Statistical analysis database. The medical facility will include emergency response equipment such as Para guard stretchers, resuscitation sets, etc., and will be supported by a fully equipped ambulance which itself will be manned by a dedicated driver and paramedic. In addition, appropriate vaccines and anti-venoms will be available. 25.3 Occupational Health In acknowledging the debilitating and chronic effects of occupational health hazards, the Contractor will operate an occupational health program that addresses often-neglected areas of construction activity such as hernia caused by manual handling, and a white finger disease resulted from continuous excessive exposure to excessive vibration. Noise will be limited to as low levels as are reasonably practicable, with personal hearing protection being utilized only as a secondary option after enclosure, segregation, modification, rotational assignments, etc. The risk of inhalation of hazardous substances will be minimized by the adoption of safe systems of work that include ventilation systems, enclosure and isolation, respiratory equipment program and substitution. All Project personnel will be subject to random testing for such substances. Sanitation and hygiene will also be emphasized throughout the Project and to this end; Subcontractor will be required to maintain all of their facilities in a clean and hygienic condition. The dangers of dehydration, sand fly leishmaniasis, sunburn and frostbite are recognised as areas of risk for which employees will be exposed. Training programs will be put in place. In order to provide a healthy environment for employees who do not smoke, smoking will not be permitted in any Project office, or sleeping accommodation. Smoking will only take place in dedicated areas outside of building. The Contractor recognizes that good housekeeping is the best form of pest and vector PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 42 OF 45 control. The Contractor approved Doctor will develop a pest and vector program to address site conditions. (e.g. mosquitoes: Spraying, no stagnant well, scorpions, vipers, sandflys etc.). 25.3.1 Health Policies and Procedures The Contractor will provide first aid, primary medical care, secondary medical, medical evacuation and medical emergency response for the worksite. For all employees, the Contractor and Subcontractor will maintain medical insurance for hospitalization, in-and-out patient physician examinations, emergency medical coverage, routine examinations and short-and long-term disability. Health insurance will be arranged for expatriate employees assigned to the Project. The Contractor will develop and manage by the following Policies and procedures(0304-ZB137): Smoking policy Fitness to Work health surveillance 26. IMPLEMENTATION AND MONITORING 26.1 HSE Performance(General) The Project HSE-MS shall be assessed and evaluated through 26.2 Site Safety Team monthly meetings Site safety committee regular meetings Verification and review of Project level documentation by Project HSE Manager, or discipline and personnel nominated by him, prior to issuing the documents to CA for their review. CA audits Lessons Learned The HEC shall ensure that lessons learned through the HSE monthly reports, audits and inspections are incorporated in the HSE-MS and the related documentations are published and explained to the project personnel and the workforce. 26.3 Safety Performance and Reporting The Contractor will report to the CA Representative the HSE status of the Work via the monthly report. The detail level of monthly HSE reporting shall be agreed between the CA Representative and the Contractor Representative before commencement of any part of the Work. The Contractor will notify the CA Representative both orally and in writing immediately after discovering, or receiving a report relating to, any of the following events that may occur: The death of any Personnel whilst performing any part of the Work; PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN The injury of any Personnel whilst performing any part of the Work where a recordable incident has occurred; Any high potential near miss or accident which has the potential for serious injury or serious damage to equipment; Any release, spill or discharge of a hazardous material associated with the Contractor’s performance of the Work, which either results in or has potential for significant injury or environmental damage; Any proceedings being commenced or threatened, alleging any failure by the Contractor or any of its Sub-Contractors to comply with any EHS requirements, irrespective of whether or not it is associated with the Contractor’s performance of the Contract;. Documentation The following reports, information and documentation shall be maintained and timely submitted to CA for each requirement: 26.5 : 0304-GP-112 : 2011065 :0 : 43 OF 45 26.4 Doc. No. Job No. Rev. No. Page Daily/Weekly HSE Report. Safety Training Records including a List of Recipients. Safety Patrol Report. Reports of Corrective Actions taken as instructed by HEC. Equipment Inspection and Maintenance Records. Accident/Incident/Near-miss Report. Equipment/Property Damage Report. Material Safety Data Sheets (MSDS). Work Permit Record. Housekeeping and Waste Disposal Records Monthly Safety Report Driver performance reports Action tracking register (ART) summary Incident Investigation and Reporting Serious incidents and injuries will be immediately reported to the Site Manager and to CA HSE representative. All incidents in common areas will be reported to CA as per CA Incident Reporting and Incident Procedure. All incidents will be investigated by HEC and in the event of a serious accident; HEC and CA will establish a Committee of Inquiry. The cause or the chain of events that led to an incident will be determined. Investigations will be conducted without prejudice and will focus on finding the facts, not faults or placing blame. The Site HSE Manager will set up an incident reporting and investigation procedure(0304ZB-135) and ensure that corrective actions to prevent recurrence of accidents are implemented. 27. AUDIT AND REVIEW The Project HSE audit shall be subject to audits under the Project HSE Audit Procedures PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 44 OF 45 and Plan(0304-ZB-143). Audits at the Site shall be conducted to assess compliance with local laws and regulations, CA’s requirements, (Contractor Management and HEC HSE plans and procedures). These audits shall be carried out by the Site HSE Manager with the support of the Corporate HSE Department at key points during construction and pre-commissioning, e.g., start of foundations, and structure and equipment erection; working at heights, heavy lifts, and energizing. Action items/non-conformances generated by the audits shall be recorded. An Action Log shall be prepared and maintained in such a way as to ensure that it is possible to trail from the initial recommendation to its final implementation. Action items, non-conformances generated by the audits shall be recorded by Project HSE Manager Site HSE Manager 27.1 Planning the Audit Programme. 27.1.1 The entire HSE System of the company which includes all current projects as well as the organisation shall be audited at least once a year. 27.1.2 The Manager of the Safety & Environment Department, Head Office shall prepare the annual audit programme. 27.2 Formation of Audit Team. 27.2.1 The Manager of the Safety & Environment Department, Head Office shall form HSE Audit Teams. 27.2.2 The Audit Team Leader shall have a good knowledge on ISO 14001, Health and Safety requirements and also sound auditing skills and techniques. 27.2.3 Audit Team Members should be selected on the basis of 1) Technical Background. 2) Impartiality 3) Knowledge of Auditing skill and technique. 27.3 Conducting the Audit. 27.3.1 Pre-Audit Meeting. 1) The Auditee should be informed of the Audit schedule at least a week in advance through a Audit plan in order to eliminate the element of surprise. 2) The Audit Team member should have a formal opening meeting with the Auditee's Representative(s) prior to commencement of the Audit, stating the scope of audit tabulated in the Audit Plan and explain how the audit will operate. The audit plan shall be acknowledge by the Auditee. PROJECT HEALTH, SAFETY AND ENVIRONMENT PLAN Doc. No. Job No. Rev. No. Page : 0304-GP-112 : 2011065 :0 : 45 OF 45 27.3.2 Audit. 1) The Audit Interview shall be intended for fact-finding and not fault finding on the system. The Audit Team Members should be objective in questioning the Auditee. 2) The Audit Team Members shall ask the Auditee to briefly run down the procedure, stop for clarification if necessary. 3) The Audit Team Members should ask for evidence wherever necessary such as reports, records, minutes, instructions, etc. 4) The Audit Team Members shall selectively question the staff/workers at that moment, not to interfere with the routine activities. 27.3.3 Post-Audit Meeting. 1) The Audit Team shall hold a meeting with the Auditee's management to present Audit Findings. 2) At this meeting, the non-conformities found during the actual audit and response dates shall be agreed. 27.4 Issue of Report and Corrective Request. 27.4.1 Within 2 weeks after the audit, the Audit Team shall issue the 'Audit Finding Report' to the Auditee, as necessary. 27.4.2 The Auditee must take action on the reported non-conformances and complete by the stipulated dates. 27.4.3 All 'Audit Finding Reports' issued shall be recorded and updated in the 'Audit Finding Report Log' by the Audit Team. 27.4.4 The Audit Team Leader shall condense facts of the Non-conformances in the 'Audit Summary Report' and submitt them to the Management Representative for his review and approval. 27.5 Close-out of 'Audit Finding Report' 27.5.1 The Audit Team shall evaluate the corrective action responses. 27.5.2 If the response is acceptable, the Audit Team shall verify the Corrective Actions taken and close-out the 'Audit Finding Report'. 27.5.3 If the response is unacceptable, the 'Audit Finding Report' shall be returned with comments.