Target USA export order process(Lingerie items) Detailed step by step work description performed by BD merchant team. 1.Inquiry for business award( new program):BD merchant receives business award notification/OCN,CMS from PPO merchant before the start of a new season in response to query from BD team. BD team ask for below infos to PPO for next step preparation. a.total program qty b.first delivery date c.gmt SMV d.Any reference sample/red seal sample sending date e. bulk/sample material sending date(initial) f. styling details like gmts construction/any 2nd process applicable or not 2.Placement meeting (formerly known as toll gate meeting):Placement meeting is the first event after order confirmation which need to be performed between vendor & buyer as the launch of the new program. Purpose of placement meeting:a.Any disputable issues can be presented with modified proposal specially on gmts construction process/operation for further analysis from factory/vendor end towards buyer & vice versa as well considering mass bulk production stage. b. Further discussion on production start/finish schedule is possible in the meeting for smooth delivery/shipment of the program. C. any action called out from any party at placement meeting that needs to be addressed before TPR meeting is closed out beforehand. Attendees of placement meeting:a. Vendor’s Management Team(PPO/HK merchant, PPO sample room concern) b. Factory Representative (BD merchant/sample room technical concern/QA team c. Target Sourcing team (HK) d. Target PSQA(BD office) Standard lead time for placement meeting schedule based on first delivery date: The meeting can be arranged any time before TPR if really required but 60-65 days before first delivery date is optimal period to call this meeting. Sequence of placement meeting arrangement: Query for docs by PPO team to BD required for placement meeting booking place BD team sends the required docs to PPO(factory initial prod plan,RA,MCP,factory machine capacity) PPO team ask for placement meeting schedule to buyer through mail(manual booking submission with required docs like: placement meeting pilot grid, factory initial prod plan,RA,MCP,factory machine capacity) Buyer confirm placement meeting schedule/timing BD merchant need to send below docs to PSQA for his review through mail 2-3 days before actual placement meeting date. 1.BOM/Specification if available 2.Fit comments if available 3. Reference/Design sample pic/Red seal sample Pic if available 4.CMS Placement meeting conducted by all concerned parties on scheduled date with VC facility. Buyer sends back placement meeting pilot grid updates to vendor/factory after successful finish of the meeting. 3.Target Production readiness(TPR): Target production readiness is a type of inspection conducted by Target PSQA compulsorily in pre production stage of a new program/style. Successful TPR meeting is the precondition for starting bulk production of any new style. Production factory itself needs to arrange TPR inviting the PSQA. Purpose of TPR:a. successful TPR is a must to start bulk production of a new program in a new factory. b.It also refers to PP meeting with Target where PSQA approves the style for production sealing the PP sample(base sample size gmt) with yellow tag(standard to follow in bulk). Attendees of TPR meeting:a. Target PSQA b.production factory representatives from all concerned dept. like merchandising, QA, Quality, production, IPE,maintenance, warehouse,technical . Standard lead time for placement meeting schedule based on first delivery date:45-50 days (considering orders with 2nd process available) before the first delivery date of a new program. Sequence wise preparational activities required before TPR Once placement meeting done, BD merchant start chasing PPO for all required docs as per TPR check list After getting receiving confirmation of all required docs including PP sample material factory ETA date from PPO & PP sample completion date from BD sample room BD merchant fix a possible date for TPR ensuring standard lead time as mentioned above for TPR so that delivery & factory may not get impacted. BD merchant need to place TPR booking in Buyers online site (Inspectiro) 14 days before the probable TPR date & inform Target PSQA through mail for his confirmation of the proposed meeting date. BD merchant needs to maintain Strong follow up with PPO for all docs receiving/modification & with BD sample room for PP sample readiness (3 days before TPR meeting). BD merchant has to prepare PVP file with all correct docs as per TPR check list & hand over to Target factory QA 3 days before TPR meeting & take his confirmation: PVP file ok or not. BD merchant need to arrange internal TPR meeting with factory all concerned dept/concern 3-5 days before actual TPR meeting with PSQA. BD merchant need to send below docs to PSQA for his review through mail 2-3 days before actual TPR meeting date & call out if any further query from him/her. 1.Internal TPR meeting notes. 2.BOM/Specification 3.Fit comments 4. Red seal sample Pic. 5.Production plan 6.RA 7. MCP As a last checking for safety BD merchant take confirmation from factory QA if both PVP file & PP samples (size set) ready or not. BD merchant need to book meeting room in prior & inform factory all concerned dept. representatives to attend the TPR meeting on time. TPR meeting takes place in production factory premises in the presence of PSQA (physical/visual) & all concerned dept. representatives from factory end as per already confirmed time schedule. PSQA finalizes his comment for the TPR inspection based on PVP filing presentation & PP sample quality, if found everything ok, he proceeds for yellow sealing in PP sample. For any objection/challenge he finishes the inspection report with required comment(need to be complete by factory before dupro) BD merchant downloads the TPR inspection report & keeps for record. 3.PP sample requirement/development process: In order to launch a new program of Target USA buyer in a factory PP sample must be made in the factory, normally the samples developed by sample room which need to keep ready before TPR. Eventually core/base sized PP sample (one pc) is sealed as yellow seal by PSQA of which standard must be followed for bulk production. a. Required gmts qty as PP sample: For a single color program PP sample need to be arranged minimum 1 pc in each size as per Sizes mentioned in buyer spec sheet. However for multi colors PP sample can be arranged in jumping sizes to make one complete size set out of all colors. b. PP sample material source & required lead time: PPO merchants arrange sample material (bulk material standard) & sends to BD via courier in response to continuous chasing by BD merchant.BD merchant fixes the TNA securing 60 days lead time for PP sample of a new program that means PP sample material must be inhouse in BD factory 60 days before first delivery date. c. Documents required prior to PP sampling: Below docs are highly essential to be available in BD factory before starting PP sampling. Lists given below. 1.approved/updated operation chart (rcvd by BD sample room) 2.approved/updated pattern (rcvd by BD sample room) 3.Red seal sample (rcvd by BD merchant & DG sample (rcvd by BD sample room 4.Fit comment approved by buyer (soft copy rcvd by BD merchant from PPO) 5. Sample MO (PPO merchant BD merchant BD sample room) 6.PPO swatch/Trim card 7.All types label lay out. Sequence wise activities done by BD merchant for new style PP sample purpose: BD merchant chases PPO team for PP sample materials sending/ETA date including above mentioned docs. Once get the courier packing list from PPO merchant,checks if any material missing/short & get back to PPO with missing/short items. Release sample MO/order to BD sample room & ask for sample ready date once all materials issue ok to sample room. Notify factory QA for his technical follow up Strongly follow up with BD sample room concern till the sample get ready & finally checked by factory QA (2-3 days before TPR date) DUPRO (During Production Inspection): Dupro is one of the types of inspections at Target which needs to be performed at During Production stage by local PSQA or buyer approved 3rd party inspector.A factory manufacturing a new program/style(Target owned brand) require to arrange dupro inspection against this program & of course attain pass result to proceed for FRI stage. Dupro booking process:BD factory concern/merchant need to place booking for dupro inspection against first set order through Inspectorio sight minimum of 3 business days prior to requested inspection date. DUPRO Inspection is a vendor paid activity Prework before Dupro inspections factory need to do: Factory must ensure being prepared for the Target inspection on the date and time scheduled including the following minimum requirements. If any below are not prepared, the inspector is instructed by Target to Abort the inspection and the vendor/factory will have to reschedule. Allow inspector access to the factory Finished production units ready for inspection according to Target DUPRO quantity/percentage requirements: 10%(minimum)-40%(maximum) qtys of assigned PO qty must be Produced . A completed Target Production Readiness (TPR) report with acceptable status for inspection to be conducted or documentation for a waived TPR Detailed specifications for the product being inspected Approval Samples (i.e. Red/White, Yellow Label/Seal samples) factory is responsible for having all documentation as required in the Target Production Validation Packet (PVP) & they must be made available to the inspector for review upon request. The Factory must have performed their own internal inspections (Pre final) with a satisfactory result and records made available for the third party inspector to review.) Retail packaging must be available . TPR follow-up actions must be complete if any applicable. DUPRO inspection timing: Process Inspection DUPRO Timing Production complete (set order): Min ≥ 10% Max ≤ 40% Certain tasks ensured by BD merchant for Dupro Inspection purpose:1.Once rcvd CMS from PPO ,select the PO no./lot/qty(normally first set PO) for dupro inspection & check with factory planners for safe plan of dupro qty. 2.To inform during TPR probable dupro inspection date & qty to all concerned dept from factory for their proactive support. 3.follow up dupro qty prod status with production/quality/QA concern daily bas 4. checks with QA whether Product Validation Packet (PVP) is up to date & ready for Dupro. 5. checks with BV concen if any query found on dupro inspection booking. 6. Before placing dupro booking request checks & confirms whether black seal required during dupro or to arrange separate sample pull based on the lead time available ok to receive top test report before the delivery date. 7. Completes TPR follow-up actions if any applicable. Target product testing: The Multi-Stage Testing (MST) procedure is designed to test Target products throughout the product lifecycle. This helps identify potential issues prior to initial shipment and continually monitor quality for ongoing shipments. Vendors/factory must ensure that Target Multi-Stage testing is built into their production plan. Normally we find below types testing required for Target products. Target Brand products are tested to approved 3RD party laboratory protocols, which evaluate aspects including, but not limited to, safety and regulatory requirements, labeling, warnings, claims, performance etc. Testing must be completed for all sellable DPCIs. 1.PPT – PPT refers to Pre-Production Testing which is performed Prior to mass production & must be complete prior to TPR.. As per our working procedure PPO merchant team do all PPTs.BD merchant may require to arrange a PPT if rcvd any special query from PPO/HK team.However for PPT we need to follow local TRF using Target protocols, not using Target TRF. 2. TOP /Top of Production Testing: Top tests need to be performed During Production.It is compulsory for factory/vendor to complete top test stage with pass result for Target product, any new impression/color before shipment through test submission with all required docs,materials to approved closest 3rd party lab. Factory/Vendors are responsible for testing costs. ORT:ORT refers to on going random test which need to be performed once the time validity of existing test report of any style/color expires. For apparel(adult) products ORT need to occurs in 12 calendar months after the most recent acceptable testing so often it is termed as ORT12.factory/vendors need to arrange ORT stage with an approved 3rd party lab. Factory/Vendors are responsible for testing costs. Certain tasks need to be complete/maintained by BD merchant for TOP/ORT purpose:To ensure TOP/ORT stage completion smoothly BD merchant need to do/monitor below essential jobs: 1. fixes TOP/ORT submission date in TNA in advance for proper preparation 2. Prepares TRF correctly 3.arranges all other necessary docs, black seal samples, additional gmts & materials before test submission scheduled date. 4.need to check if any light colors fabric/elastic included for test submission,if so arranges treatment for PH test fail issue. 5. have strong follow up with BV concern over any failing issue & ontime test report receiving for urgent case. Final Random Inspection:FRI- final random inspection conducted by approved 3rd party inspection agency is a must for vendor/factory to arrange shipment/delivery. Based on passed report in FRI factory gets shipment release order. Prework to complete by factory before FRI arrangement: The Factory must have performed their own internal inspections (Pre final) with a satisfactory result and records made available for the third party inspector to review. Allow inspector access to the factory Finished production units ready for inspection according to Target FRI quantity/percentage requirements: 100% product(booked PO qty must be produced and a minimum of 80% product packed Detailed specifications for the product being inspected Approval Samples (i.e. Red/White, Yellow Label/Seal samples) factory is responsible for having all documentation as required in the Target Production Validation Packet (PVP) & they must be made available to the inspector for review upon request. The Factory must have performed their own internal inspections (Pre final) with a satisfactory result and records made available for the third party inspector to review.) DUPRO follow-up actions must be complete if any applicable. Target Vendor Inspection (TVI) – Vendor Self Inspection (VSI-FRI) Execution: Business partners whose factories have proven quality performance with Factory Risk Prediction (FRP) or FQI “Low” ratings are empowered to execute their final inspections internally replacing FRI performed by Third Party. . Partners with qualifying factories are required to maintain an Inspectorio Pro-subscription plan to access the necessary capabilities needed to execute vendor inspection activities, which provides greater visibility, transparency and enhanced reporting capabilities. TVI FRIs are requested by the vendor/factory through Inspectorio SIGHT, and Vendor/Factory/Independent Inspection Agency executes the inspection. If there is a Fail Vendor/factory reviews a CAPA as needed, and works with the factory concerned dept./area to complete the process. Certain jobs done by BD merchant for VSI FRI purpose: o When the Factory is ready for FRI, BD merchant completes VSI-FRI booking using Inspectorio, of course 3 business/working days prior to the product inspection date. Analyses all the POs/qtys for FRI weekly basis & divides the POs among all working days in a balanced way based on available time/man power of QA/production status. Updates the final FRI schedule(PO wise) to all concerned dept. especially QA & packing. Follow up production daily basis & have close monitoring on the POs which under tight production plan.