Assessment Task 3 Manage project cost BSBPMG533 Student Declaration To be filled out and submitted with assessment responses ◻ I declare that this task and any attached document related to the task is all my own work and I have not cheated or plagiarised the work or colluded with any other student(s) ◻ I understand that if I am found to have plagiarised, cheated or colluded, action will be taken against me according to the process explained to me ◻ I have correctly referenced all resources and reference texts throughout these assessment tasks. ◻ I have read and understood the assessment requirements for this unit ◻ I understand the rights to re-assessment ◻ I understand the right to appeal the decisions made in the assessment Unit Title Unit Code Student name Student ID number Student signature Date Task Number BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 2 greenwichcollege.edu.au ------OFFICE USE ONLY----For Trainer and Assessor to complete: ◻ Student requested reasonable adjustment for the assessment Marking Sheet Comments N DNS Did the student satisfactorily: The student has satisfactorily completed and submitted the following: Y Completed successfully ☐ ☐ ☐ ☐ ☐ ☐ Determination of cost monitoring and control procedures for each scenario in Task 3.1 Determination of project budget variations due to scenarios scenario in Task 3.1 Action plan to address each scenario scenario in Task 3.1 Change Request Form scenario in Task 3.1 2 x Status Report scenario in Task 3.1 Email to Project Team to monitor the implementation of the action plan scenario in Task 3.1 Email to Project Team to communicate the financial completion process in Task 3.2 Outline of actions to address invoicing issue in Task 3.2 Lessons learned report in Task 3.2 Lessons learned report– Case Study in Task 3.3 Demonstrated ability to: Implement agreed financialmanagement processes and procedures for monitoring actual expenditure against budget Identify cost variations and evaluate alternative actions BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 3 greenwichcollege.edu.au Marking Sheet Comments DNS This is evidenced by: Determination of cost monitoring and control procedures for each scenario Determination of project budget variations due to scenarios Action plan to address each scenario Change Request Form 2 x Status Report Email to Project Team to monitor the implementation of the action plan Email to Project Team to communicate the financial completion process Outline of actions to address invoicing issue Demonstrated ability to: Review project outcomes using available records Review cost-management issues and document improvements N Did the student satisfactorily: Implement and monitor agreed actions for maintaining financial objectives Provide accurate and timely financial reports Conduct activities to signify financial completion according to task and organisational requirements Y Completed successfully ☐ ☐ ☐ This is evidenced by: Lessons learned report Lessons learned report– Case Study Task Outcome: Satisfactory ☐ Not Yet Satisfactory ☐ Student Name: Assessor Name: Assessor Signature: Date: BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 4 greenwichcollege.edu.au Table of Content Student Declaration ............................................................................................................................................... 2 Task 3 – Manage project costs and complete cost-management processes ................. 6 Task 3.3 Monitor and control project costs ................................................................................................... 8 Task 3.2 Complete cost-management processes ...................................................................................... 14 Task 3.3 Review cost-management – Case Study .................................................................................... 16 BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 5 greenwichcollege.edu.au Task 3 – Manage project costs and complete costmanagement processes Task summary and instructions What is this assessment task about? Task 3.1 and 3.2 build on Task 2.1 Task 3.3 builds on Task 2.2 Please note that the performance evidence for this unit of competency requires you to demonstrate the ability to manage project cost on at least two occasions. This assessment has been designed to meet that requirement. This task comprises of the following assessment methods: o Product-based ☒ o Direct observation of Role-Play ☐ o Case Study ☒ o Other (specify) ☐ It has been designed to evaluate your ability to/competency in: Implement agreed financial-management processes and procedures for monitoring actual expenditure against budget Identify cost variations and evaluate alternative actions Implement and monitor agreed actions for maintaining financial objectives Provide accurate and timely financial reports Conduct activities to signify financial completion according to task and organisational requirements Review project outcomes using available records Review cost-management issues and document improvements You are required to address the following: Task 3.1 Monitor and control project costs o Address a Case Study with scenarios and manage project costs Task 3.2 Complete cost-management processes o Finalise cost-management processes at project closure o Develop a lessons learned report Task 3.3 Case Study o Develop a lessons learned report for the Case Study BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 6 greenwichcollege.edu.au Task summary and instructions What do I need to do to complete this task satisfactorily? Specifications Although the assessment requires group collaboration to simulate a work environment, the assessment submission is individual, and it will be marked as such. submit the completed assessment tasks, according to instructions, complete the tasks with sufficient detail and present them in a professional manner, use your own words and reference sources appropriately, meet the word count where required, use the scenario provided, use the templates provided where required, for your performance to be deemed satisfactory in this assessment task you must satisfactorily address all of the assessment criteria, if part of this task is not satisfactorily completed you will be asked to complete further assessment to demonstrate satisfactory performance. You must deliver/participate in: NA You must submit to GOALS Resources and equipment • • • • • • • Determination of cost monitoring and control procedures for each scenario Determination of project budget variations due to scenarios Action plan to address each scenario Change Request Form 3 x Status Report Email to Project Team to monitor the implementation of the action plan Email to Project Team to communicate the financial completion process Outline of actions to address invoicing issue Lessons learned report Lessons learned – Case Study Computer with Internet access Access to Microsoft Office suites or similar software Learning material Scenario for assessment as provided Appendices as provided Relevant policies and procedures as provided Templates as provided BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 7 greenwichcollege.edu.au Task summary and instructions Re-submission opportunities You will be provided feedback on your performance by the Assessor. The feedback will indicate if you have satisfactorily addressed the requirements of each part of this task. If any parts of the task are not satisfactorily completed, the assessor will explain why, and provide you written feedback along with guidance on what you must undertake to demonstrate satisfactory performance. Re-assessment attempt(s) will be arranged at a later time and date. You have the right to appeal the outcome of assessment decisions if you feel that you have been dealt with unfairly or have other appropriate grounds for an appeal. You are encouraged to consult with the assessor prior to attempting this task if you do not understand any part of this task or if you have any learning issues or needs that may hinder you when attempting any part of the assessment. Complete the following activities: Task 3.1 Monitor and control project costs Assume that the following has happened when executing the project; please contextualise the scenario to reflect your project cost management plan. A B C D Scenarios 25% timeline The project sponsor communicated the decision to use a different supplier for one of the costs items listed in the project budget. This will increase the cost of that item by 5%. Specify what cost item is affected based on your budget: <Add> 25% timeline New software was purchased for the project by a project team member with access to the project corporate credit card; the software was purchased for $ 464.00. Therefore, the item was not an approved expense and was not recorded in the project budget or approved through the change management process. 50% timeline Due to the consequences of Covid19 on the company, the project budget is cut by 10%. 75% timeline The project team is working additional hours due to issues with the project schedule. This will increase the costs of human resources by 8%. BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 8 greenwichcollege.edu.au Scenarios The project sponsor has agreed to add $2,000.00 to the budget. 1. For each scenario: Detail what cost monitoring and control procedures were applied to monitor actual expenditure against budget. Identify and list the variations in the project budget. Scenario Monitoring and control (30-50 words/scenario) A B C D List of variations in the budget, including % of the variation 2. For each scenario: Determine what actions are needed to ensure cost objectives remain achievable throughout the project life cycle. Develop an action plan for each scenario. Explain what cost-analysis methods were used to identify the cost variations and evaluate alternative actions to support project progress. (40-80 words) Scenario Key actions 2-3/scenario Responsibility Timeline Resources A B C Costanalysis methods Explain what cost-analysis methods were used to identify the cost variations and evaluate alternative actions to support project progress. (40-80 words) 3. Change Request BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 9 greenwichcollege.edu.au Complete a Change Request Form (Template 1) to implement one or more actions needed to address one of the scenarios. Template 1 -Change Request Form Change Request – Project Issued by Change/s Requested Reason for change/s Impact on the project Change authorised: Yes/No Signed: Signed Signed Project Manager Sponsor Client Date Date Date Record Complete the filing record below to save the project documentation in the project management record system. Project Title: Project Sponsor: Project Client: Project Manager: Date: Version: File Name: 4. Status Report BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 10 greenwichcollege.edu.au Complete a Status Report (Template 2) for the 50% and the 75% scenarios. Determine the impact of the budget variations on the project deliverables in the status report. Add additional rows if needed. Template 2 -Status Report Status Report – 50% timeline <Add Project Name> Prepared by: Date: Attention to: Executive summary report Use this section for summary information about the status of the project. Deliverable Deliverable Work to date status Planned Status realisation date Use this section for summary information about the status of the deliverables of the project. Budget status Budget Item Estimated Cost Actual Cost Variation % Use this section for a summary of the status of the project’s budget BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 11 greenwichcollege.edu.au Status Report – 50% timeline Record Complete the filing record below so that the project documentation can be saved in the project management record system. Project Title: Project Client: Project Sponsor: Project Manager: Date: Version: File Name: Status Report – 75% timeline <Add Project Name> Prepared by: Date: Attention to: Executive summary report Use this section for summary information about the status of the project. Deliverable Deliverable status Work to date Planned Status realisation date Use this section for summary information about the status of the deliverables of the project. BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 12 greenwichcollege.edu.au Status Report – 75% timeline Budget status Budget Item Estimated Cost Actual Cost Variation % Use this section for a summary of the status of the project’s budget Record Complete the filing record below so that the project documentation can be saved in the project management record system. Project Title: Project Sponsor: Project Client: Project Manager: Date: Version: File Name: 5. Monitoring implementation Write an email (Template 3) to the Project Team asking them to monitor the implementation of the agreed actions to address one of the scenarios. The text of the email should be in grammatically correct English, written in an appropriate (polite, business-like) style. (50-100 words) Template 3 -Email Email to Project Team To: BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 13 greenwichcollege.edu.au Cc: Bcc: Subject: Date email is sent: Attachments: Task 3.2 Complete cost-management processes 1. Financial completion process Write an email (Template 3) to the Project Team to explain how to ensure that all tasks related to cost-finalisation are completed (list the key tasks and outline the associated processes). Additionally, explain how the project financial records will be documented and transferred to the finance department. The text of the email should be in grammatically correct English, written in an appropriate (polite, business-like) style. (50-100 words) Template 3 -Email Email to Project Team To: Cc: Bcc: Subject: Date email is sent: Attachments: 2. Invoicing issue During the project reconciliation process, you have found that an invoice for a cost item is not reflective of the quote agreed on with the supplier. You had a quote for $ 800.00 from an electrician for a security audit and electrical inspection of the new campus. The service supplier charged $1,000. BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 14 greenwichcollege.edu.au Outline how the situation is addressed according to your project cost management and finalisation processes. (50-100 words) 3. Lessons Learned Consider the scenarios addressed in Task 3.1, your planning work in Task 2.1, and the following feedback: Estimates were not produced in a timely manner. Some miscommunications with the project team limited the visibility to project field activities, causing inaccurate paper processes and inefficiencies. A unified project cost management platform is recommended for future projects. Review the project outcomes to determine the effectiveness of cost management in the project. Complete a lessons learned report (Template 4). Template 4 -Lessons Learned Lessons Learned Report Name of project: Overview A brief summary of how cost was managed, to include issues and how they were addressed. Was the project delivered within budget? Worked well Could have gone better List 2-3 items List 2-3 items Lessons learned and suggested improvements (40-80 words): Record Complete the filing record below to save the project documentation in the project management record system. BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 15 greenwichcollege.edu.au Lessons Learned Report Project Title: Project Sponsor: Project Client: Project Manager: Date: Version: File Name: Task 3.3 Review cost-management – Case Study Consider the Case Study you worked on in Task 2.2. Assume that you have executed the project and collected the following feedback about project cost management. Changes to the budget were reactive instead of proactive, causing an increase in budget by 10% The marketing team underestimated some project cost items when providing feedback to the project team The use of a shared spreadsheet for the project budget caused several errors in data entry One of the suppliers recommended by the Marketing Manager was not on the list of the organisation’s preferred suppliers One invoice was not paid by the due date Unclear responsibilities relevant to project finances between the Project Manager and the Marketing Manager Good monitoring procedures implemented by the Project Manager prevented more severe issues Clear organisational policies and procedures about finance processes Lack of project cost management knowledge in the marketing team Review the feedback above to determine the effectiveness of cost management in the project. Complete a lessons learned report (Template 4). Template 4 -Lessons Learned Case Study Lessons Learned Report Name of project: Overview A brief summary of how cost was managed, to include issues and how they were addressed. Was the project delivered within budget? BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Page 16 greenwichcollege.edu.au Lessons Learned Report Worked well Could have gone better List 2-3 items List 2-3 items Lessons learned and suggested improvements (40-80 words): Record Complete the filing record below to save the project documentation in the project management record system. Project Title: Project Sponsor: Project Client: Project Manager: BSBPMG533 - Manage project cost V3 2021 RTO Provider: 91153 - CRICOS Code: 02672K Date: Version: File Name: Page 17 greenwichcollege.edu.au