Uploaded by xandergr02

7.2 Damages

advertisement
PRINCIPLES OF BUSINESS LAW
TOPIC 7: REMEDIES FOR BREACH
DAMAGES
DAMAGES:
OVERVIEW
• Damages consist of an award of money to be
paid by the defendant to the plaintiff.
• Damages for breach of contract are not
intended to be punitive; they are
compensatory. They compensate for a loss
suffered by the plaintiff because of the breach
of contract.
• Damages aim to put the non-breaching party in
the position she would have been in if the
contract had been properly performed.
COMMON LAW
REMEDIES:
DAMAGES:
OVERVIEW
When determining whether a person is entitled to
damages, it is not necessary to consider the nature
of the term nor the nature of the breach.
• This is only relevant to ‘termination’
DAMAGES AIM TO
PUT THE PLAINTIFF
IN THE POSITION
SHE WOULD HAVE
BEEN IN IF THE
CONTRACT HAD
BEEN PROPERLY
PERFORMED:
RADFORD V DE
FROBERVILLE
• Facts
• R owned two blocks of land
• He sold one to F on the condition that she build
an expensive brick wall on the boundary
• F failed to build the wall
• R sued for breach of contract, claiming the full
costs of building the wall
• F argued that damages should be limited to the
reduction in the value of R’s property caused by
the absence of a wall
• Issue:
• What was the appropriate measure of damages?
• Decision
• R could recover damages measured by reference
to the cost of building the wall
RADFORD V DE
FROBERVILLE
• Reason
• Contractual damages aim to put the nonbreaching party in the position they would have
been in had the breach not occurred
• Had the breach not occurred, the wall would have
been built on the property
• R was entitled to damages equal to the cost of
building the wall
• Facts
• B leased a building to T for ten years
DAMAGES AIM TO
PUT THE PLAINTIFF IN
THE SAME POSITION
AS IF THE CONTRACT
HAD BEEN PROPERLY
PERFORMED:
TABCORP HOLDINGS V
BOWEN INVESTMENTS
• It was a term of the lease that T would not make
substantial alterations to the building without B’s
consent
• T, in breach of this term, demolished and then
rebuilt the building foyer
• Issue:
• Was B entitled to recover the full cost of restoring
the foyer to its previous state?
• Or, was B only entitled to damages if the building
was worth less as a result of the T’s changes?
• Decision
• B was entitled to recover the full costs of restoring
the foyer to its previous state
TABCORP
HOLDINGS V
BOWEN
INVESTMENTS
• Reason
• The aim is to put the non-breaching party in the
position she would have been in had there been
no breach – this does not simply mean financial
position but rather the same actual position
• Damages should thus cover the cost of restoring
the foyer
COMMON LAW
REMEDIES:
DAMAGES:
COMPENSABLE
LOSS
• Damages can be claimed to compensate for two
types of loss:
1. Direct loss
• Koufos v C Czarnikow Ltd
2. Consequential loss
• Hadley v Baxendale
DAMAGES:
DIRECT LOSS
• A party who suffers direct loss because of the
breach is entitled to recover that loss from the
party in breach.
• A direct loss arises naturally from the breach.
• The Koufos case provides examples of direct
loss.
• Facts
• C chartered K’s ship to carry cargo
DIRECT LOSS:
KOUFOS V
CZARNIKOW
LTD
• The ship ran late and, when it arrived, the market
price of the cargo was lower than the market
price on the day that the cargo should have
arrived
• C sued for compensation for loss it suffered
because it received a lower price
• Issue
• Was C entitled to damages to compensate for the
loss flowing from the lower price?
• Decision
DIRECT LOSS:
KOUFOS V
CZARNIKOW
LTD
• Damages were payable to compensate for the
losses caused by the drop in market price
• Reason
• A direct loss is a loss that naturally arises from the
breach according to the usual course of things.
• Given the fluctuation in market prices, the loss is
a natural consequence of the breach
• The loss was a direct loss and thus recoverable
• A party who suffers consequential loss because
of the breach is entitled to recover that loss from
the party in breach.
DAMAGES:
CONSEQUENTIAL
LOSS
• Consequential loss is more remote than direct
loss.
• A consequential loss is a loss that may
reasonably be supposed to have been in the
contemplation of both parties (at the time of
formation) as a probable result of a breach.
• Hadley v Baxendale
• Facts
• H engaged B to deliver a broken mill shaft to the
mill manufacturer (so that the manufacturer could
make a replacement)
CONSEQUENTIAL
LOSS:
HADLEY V
BAXENDALE
• B said he would make the delivery the following
day but in fact took several days
• During the periods of delay H’s mill stood idle
• Issue
• Was H entitled to compensation for lost profits?
• Decision
• H was not entitled to compensation for lost profits
• Reason
• The loss was not a direct loss
CONSEQUENTIAL
LOSS:
HADLEY V
BAXENDALE
• It does not flow naturally from the breach. Ordinarily
one would expect that a mill operator would have, or
could acquire, a spare mill shaft
• The loss was not a consequential loss
• Damages for consequential loss can only be claimed if
the losses may reasonably be supposed to have been
in the contemplation of both parties (at the time the
contract was made) as a probable result of such a
breach
• It was not within the common contemplation of the
parties that the mill would stand idle while the broken
shaft was being delivered to the mill manufacturer – H
had in no way indicated to B that this would be the
case
DAMAGES:
WASTED
EXPENSES
• Damages can be claimed for expenses
reasonably incurred in anticipation of the other
party performing his or her obligations.
• Damages will not be payable if the breaching
party can prove that the expenses would have
been wasted even if there had been no breach of
contract.
• McRae v Cth Disposals Commission
• Facts
WASTED
EXPENSES:
MCRAE V
COMMONWEALTH
DISPOSALS
COMMISSION
• CDC invited tenders for the purchase of an oil tanker said
to be lying on the Jourmaund Reef
• M won the tender and was given the precise latitude and
longitude of the tanker
• M embarked on a salvage operation
• There was no oil tanker lying anywhere near that location
• The court concluded that CDC had made a contractual
promise that the tanker was at that location and that this
promise had been breached
• Issue
• Could McRae recover damages to compensate for wasted
expenditure on the salvage operation?
• Decision
WASTED
EXPENSES:
MCRAE V
COMMONWEALTH
DISPOSALS
COMMISSION
• McRae was entitled to recover the costs of the
wasted salvage operation
• Reason
• The parties must have contemplated, when
contracting, that such expenses would be
incurred
• Generally speaking, damages cannot be sought
to compensate for disappointment or distress
caused by the breach.
DAMAGES:
STRESS AND
DISAPPOINTMENT
• One exception to this rule was recognised in
Baltic Shipping v Dillon
• Where a contract is for the provision of
enjoyment, entertainment or pleasure, damages
can be recovered where the breach causes
disappointment or distress
• Facts
• Mrs D was a passenger on a cruise ship who sought
damages for losses caused by the cruise ship
sinking on the tenth day of a fourteen day cruise
DAMAGES: STRESS
AND
DISAPPOINTMENT:
BALTIC SHIPPING V
DILLON
• The cruise ship sank as a result of the B’s negligence.
• B admitted liability for breach of contract, but
disputed D’s claim for damages based on distress
and disappointment said to be caused by the
breach.
• Issue
• Was D entitled to damages for distress and
disappointment?
• Decision
DAMAGES: STRESS
AND
DISAPPOINTMENT:
BALTIC SHIPPING V
DILLON
• D could recover damages for loss in the form of
distress or disappointment caused by the breach
• Held
• The general rule is that a plaintiff cannot claim
contractual damages for disappointment, distress
or injured feelings
• However damages of this kind were payable in
this instance as D had contracted for a trip meant
to provide pleasure, relaxation and entertainment
DAMAGES:
DUTY TO
MITIGATE
• A plaintiff cannot claim losses from a defendant
if those losses could have been avoided by the
plaintiff taking reasonable steps to avoid them.
• A plaintiff is under a duty to mitigate (minimise)
the losses that flow from a breach of contract.
• Facts
DUTY TO
MITIGATE:
BURNS V MAN
AUTOMOTIVE
(AUST) PTY LTD
• MAN supplied a defective commercial vehicle to
B (which amounted to a breach of contract)
• The defects could have been remedied if B had
the vehicle’s engine repaired or replaced
• B sued MAN to recover profits lost over a four
year period (the expected operating life of the
vehicle)
• Issue
• Had B taken reasonable steps to mitigate his loss?
• Decision
• B had taken adequate steps to mitigate the loss
DUTY TO
MITIGATE:
BURNS V MAN
AUTOMOTIVE
(AUST) PTY LTD
• Reason
• The faulty engine could have been repaired or
replaced
• However, B could not afford to do so
• Given B’s financial position, B had not acted
unreasonably in not getting the engine repaired
• B had not failed to mitigate his loss
• Parties are, within limits, free to define the scope
of the remedies that will be available in the
event of breach.
AGREED
PENALTY
CLAUSES
• Parties may agree in advance what losses are
likely to be suffered in the event of breach and
insert a ‘liquidated damages’ clause into the
contract which defines the level of damages that
will be paid in the event of breach
• Liquidated damages clauses must not penalise
(impose damages that bear no relationship to
any loss likely to be suffered)
Download