FLOATING HEAD Heat Exchanger
General Assembly view
Gaskets
Tube side Inlet
Shell side Inlet
Shell
Gasket
Bundle
Floating Head
Back Cover
Distributor
Saddle
Tube side Outlet
Tube Sheet
2
Shell side Outlet
Floating Head Heat Exchanger
Cross Sectional View
Floating Head
Shell
Tube Bundle
Distributor
3
Baffle
Back cover
FLOATING HEAD Heat Exchanger
Split View of Parts
Gasket
Split ring
Gasket
Tube sheet
Distributor
Floating
Head
Shell
Floating
Head Detail
4
Gasket
Gasket
Tube Bundle
Tube sheet
Spacer
Back Cover
Do Not Start The Job Without A Safety Plan
5
FLOATING HEAD Heat Exchanger
Maintenance Activity Description
Blind Inlets-Outlets at
Disconnect and remove
plant area
Floating Head with gasket
Disconnect and remove
Install the bundle puller
Distributor with gasket
Disconnect and remove
Pull the bundle out
Back cover with gasket
Bundle Puller
Ground level
6
FLOATING HEAD Heat Exchanger
Maintenance Activity Description…..Continuation
Lower the bundle and
Lift the bundle puller with
take to hydro-jetting area
Clean Shell and covers
clean bundle and new gasket,
ready for reinstallation
Bundle Puller
7
Ground level
FLOATING HEAD Heat Exchanger
Maintenance Activity Description…..Continuation
Reinsert the bundle by
Lower the bundle puller to
bundle puller
the ground and take it away
Bundle Puller
8
Ground level
FLOATING HEAD Heat Exchanger
Maintenance Activity Description…..Continuation
 Shell Side Hydro-test
Install front Test Ring with
gasket
Install back Test Ring
with gasket
Install Pressure Gauge
Raise the pressure up to
value given by Inspection
Connect water pump
Fill the shell by water
Check leakages from
tubes
Install Blinds in shell
PG
Ground
level
9
Water Pump
FLOATING HEAD Heat Exchanger
 Shell Side Hydro-test …Check leakages from tubes continuation
PG
“B”
“A”
Water
View “A”
Water
View “B”
10
FLOATING HEAD Heat Exchanger
 Shell Side Hydro-test ….Continuation Details
PG
Tube leak elimination Details
“A”
Shell under pressure
“B”
Detail “A”
[By Expansion both sides]
Detail “B”
[By Plug both sides]
Leak
Leak
11
Tube Expander Tool
FLOATING HEAD Heat Exchanger
Maintenance Activity Description…..Continuation
Discharge water from
shell drain
Remove Test Ring &
gasket [distributor side]
Reinstall distributor
with new gasket &
tight bolts
Blind Distributor in &
out
PG
Drain
12
Remove Test Ring &
gasket [floating head
side]
Reinstall Floating Head
with split flange, new
gasket & tight bolts
FLOATING HEAD Heat Exchanger
 Tube Side Hydro-test ….Continuation Details
Check floating head
gasket sealing
Check distributor gasket
sealing
Install PG in distributor
top nozzle
Connect water pump
Fill tube side by water
Raise the pressure up to
value given by Inspection
PG
PG
Drain
Water Pump
13
Discharge the water,
remove PG and water
pump
Remove blinds form
distributor nozzle and
tight bolts
FLOATING HEAD Heat Exchanger
 Shell Side Final Hydro-test ….Continuation Details
Check Back cover
gasket sealing
Install Back cover with
Gasket
Connect water pump
Check bundle to shell
gasket sealing
Fill Shell side by water
Raise the pressure up to
value given by Inspection
Discharge the water,
remove PG and water
pump
Remove blinds form
shell nozzles and tight
bolts
PG
Drain
Water Pump
14
FLOATING HEAD Heat Exchanger
Handover & Final House Keeping
By Maintenance
 Remove tools and equipment
 Close Work permit
 Clean and wash the area
 Remove scaffold after unit start-up
15