Uploaded by Tomas Casillas-Gerena

- ANSI ASSE A10.1 – 2011 Pre-Project & Pre-Task Safety and Health Planning American National Standard for Construction and Demolition Operations (2011, AMERICAN SOCIETY OF SAFETY ENGINEERS) - libgen.l

AMERICAN NATIONAL STANDARD
ANSI/ASSE A10.1 – 2011
ANSI/ASSE A10.1 – 2011
Pre-Project & Pre-Task
Safety and Health Planning
American National Standard
for Construction and
Demolition Operations
AMERICAN SOCIETY OF
SAFETY ENGINEERS
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
ANSI/ASSE A10.1 – 2011
The information and materials contained in this publication have been developed from sources believed
to be reliable. However, the American Society of Safety Engineers (ASSE) as secretariat of the ANSI
accredited A10 Committee or individual committee members accept no legal responsibility for the
correctness or completeness of this material or its application to specific factual situations. By publication
of this standard, ASSE or the A10 Committee does not ensure that adherence to these recommendations
will protect the safety or health of any persons, or preserve property.
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
ANSI®
ANSI/ASSE A10.1 – 2011
American National Standard
Construction and Demolition Operations
Pre-Project & Pre-Task Safety and Health Planning
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Secretariat
American Society of Safety Engineers
1800 East Oakton Street
Des Plaines, Illinois 60018-2187
Approved December 16, 2011
Effective June 4, 2012
American National Standards Institute, Inc.
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
American
National
Standard
Approval of an American National Standard requires verification by ANSI that the
requirements for due process, consensus, and other criteria for approval have
been met by the standards developer. Consensus is established when, in the
judgment of the ANSI Board of Standards Review, substantial agreement has
been reached by directly and materially affected interests. Substantial
agreement means much more than a simple majority, but not necessarily
unanimity. Consensus requires that all views and objections be considered, and
that a concerted effort be made toward their resolution. The use of American
National Standards is completely voluntary; their existence does not in any
respect preclude anyone, whether he/she has approved the standards or not,
from manufacturing, marketing, purchasing, or using products, processes, or
procedures not conforming to the standards. The American National Standards
Institute does not develop standards and will in no circumstance give an
interpretation of any American National Standard. Moreover, no person shall
have the right or authority to issue an interpretation of an American National
Standard in the name of the American National Standards Institute. Requests for
interpretation should be addressed to the secretariat or sponsor whose name
appears on the title page of this standard.
Caution Notice: This American National Standard may be revised or withdrawn
at any time. The procedures of the American National Standards Institute require
that action be taken periodically to reaffirm, revise, or withdraw this standard.
Purchasers of American National Standards may receive current information on
all standards by calling or writing the American National Standards Institute.
Published February, 2012 by:
American Society of Safety Engineers
1800 East Oakton Street
Des Plaines, Illinois 60018-2187
(847) 699-2929 • www.asse.org
Copyright ©2012 by the American Society of Safety Engineers
All Rights Reserved.
No part of this publication may be reproduced
in any form, in an electronic retrieval system or
otherwise, without the prior written permission
of the publisher.
Printed in the United States of America
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
Foreword
(This Foreword is not a part of American National Standard A10.1-2011.)
A10.1
A10.2
A10.3
A10.4
A10.5
A10.6
A10.7
A10.8
A10.9
A10.10
A10.11
A10.12
A10.13
A10.15
A10.16
A10.17
A10.18
A10.19
A10.20
A10.21
A10.22
A10.23
A10.24
A10.25
A10.26
A10.27
A10.28
A10.29
A10.31
A10.32
A10.33
A10.34
A10.37
A10.38
A10.39
A10.40
A10.41
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Pre-Project & Pre-Task Safety & Health Planning
Safety, Health, and Environmental Training (under development)
Powder-Actuated Fastening Systems
Personnel Hoists and Employee Elevators
Material Hoists
Demolition Operations
Transportation, Storage, Handling, and Use of Commercial Explosives and
Blasting Agents
Scaffolding
Concrete and Masonry Construction
Temporary and Portable Space Heating Devices
Personnel and Debris Nets
Excavation
Steel Erection
Dredging
Tunnels, Shafts, and Caissons
Safe Operating Practices for Hot Mix Asphalt (HMA) Construction
Temporary Roof and Floor Holes, Wall Openings, Stairways, and Other
Unprotected Edges
Pile Installation and Extraction Operations
Ceramic Tile, Terrazzo, and Marble Work
Safe Construction and Demolition of Wind Generation/Turbine Facilities (under
development)
Rope-Guided and Non-Guided Workers’ Hoists
Safety Requirements for the Installation of Drilled Shafts (under development)
Roofing – Safety Requirements for Low-Sloped Roofs
Sanitation in Construction
Emergency Procedures for Construction Sites
Hot Mix Asphalt Facilities
Work Platforms Suspended from Cranes or Derricks
Aerial Platforms in Construction (under development)
Digger-Derricks
Personal Fall Protection Used in Construction and Demolition Operations
Safety and Health Program Requirements for Multi-Employer Projects
Public Protection
Debris Nets
Basic Elements of a Program to Provide a Safe and Healthful Work Environment
Construction Safety and Health Audit Program
Reduction of Musculoskeletal Problems in Construction
Equipment Operator and Supervisor Qualifications and Responsibilities (under
development)
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
This standard is one of a series of safety standards that have been formulated by the
Accredited Standards Committee on Safety in Construction and Demolition Operations,
A10. It is expected that the standards in the A10 series will find a major application in
industry, serving as a guide to contractors, labor, and equipment manufacturers. For the
convenience of users, a list of existing and proposed standards in the A10 series for
Safety Requirements in Construction and Demolition Operations follows.
A10.42
A10.43
A10.44
A10.46
A10.47
A10.48
A10.49
Rigging Qualifications and Responsibilities in the Construction Industry
Confined Spaces in Construction (under development)
Lockout/Tagout in Construction
Hearing Loss Prevention
Highway Construction Safety
Communication Tower Erection (under development)
Control of Health Hazards (under development)
One purpose of these standards is to serve as guides to governmental authorities having
jurisdiction over subjects within the scope of the A10 Committee standards. If these
standards are adopted for governmental use, the reference of other national codes or
standards in individual volumes may be changed to refer to the corresponding
regulations.
Revisions: The A10 Committee welcomes proposals for revisions to this standard.
Revisions are made to the standard periodically (usually five years from the date of the
standard) to incorporate changes that appear necessary or desirable, as demonstrated
by experience gained from the application of the standard. Proposals should be as
specific as possible, citing the relevant paragraph number(s), the proposed wording, and
the reason for the proposal. Pertinent documentation would enable the A10 Committee to
process the changes in a more timely manner.
No one but the A10 Committee (through the A10 Secretariat) is authorized to provide any
interpretation of this standard.
Approval: Neither the A10 Committee nor American National Standards Institute (ANSI)
"approves," "certifies," "rates," or "endorses" any item, construction, proprietary device, or
activity.
Appendices: Appendices are included in most standards to provide the user with
additional information related to the subject of the standard. Appendices are not part of
the approved standard.
Committee Meetings: The A10 Committee meets twice a year. Persons wishing to attend
a meeting should contact the Secretariat for information.
Standard Approval: This standard was processed and approved for submittal to ANSI by
the American National Standards Committee on Safety in Construction and Demolition
Operations, A10. Approval of the standard does not necessarily imply (nor is it required)
that all Committee members voted for its approval. At the time this standard was
published, the A10 Committee had the following members:
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Interpretations: Upon a request in writing to the Secretariat, the A10 Committee will
render an interpretation of any requirement of the standard. The request for interpretation
should be clear, citing the relevant paragraph number(s) and phrased as a request for a
clarification of a specific requirement. Oral interpretations are not provided.
Richard King, CSP, Chairman
James Tomaseski, Vice Chairman
Timothy R. Fisher, CSP, CHMM, ARM, CPEA, Secretary
Jennie Dalesandro, Administrative Technical Support
Organization Represented
Name of Representative
Accident Prevention Corporation
Frank Burg, CSP, P.E.
Michael Serpe, CSP
Matthew J. Burkart, P.E.
Judith Burkart
Robert Renney
Ted P. Sharp
Thad Nosal
James G. Borchardt, CSP, CPE
Aegis Corporation
Alstom Power
American Insurance Services Group
ASCE - Construction Institute Committee
American Society of Safety Engineers
American Wind Energy Association
American Work Platform Training, Inc.
Asbestos Workers International Union
Associated Builders and Contractors, Inc.
Associated General Contractors of America, The
Association of Union Constructors, The
A-Z Safety Resources, Inc.
Barton-Malow Company
Black & Veatch
Building & Construction Trades Department
CPWR - Center for Construction Research & Training
Capital Safety Group
Clark Construction Group
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Cole-Preferred Safety Consulting, Inc.
Philip L. Colleran
Construction & Realty Safety Group, Inc.
ECI Safety Services Co.
Edison Electric Institute
E. I. Dupont de Nemours & Company
Elevator Industry Preservation Fund
Ellis Fall Safety Solutions
Gilbane Building Co.
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
William R. Nash, P.E.
Ken Shorter, CSP, ARM
A. David Brayton, CSP, CPC
Michele Myers Mihelic
Dennis W. Eckstine
Terry Lynch
Jim E. Lapping, MS, P.E., CSP
Chris Williams
Charlie Bird
Kevin Cannon
Wayne Creasap, II
Jane F. Williams, CPEA, CCA
Mark Klimbal, CSP, ARM
Clayton Shafer
Richard F. King, CSP
John H. Johnson
Pete Stafford
Jim Platner, Ph.D., CIH
Mike McCann, Ph.D., CIH
Pete Stafford
Scott C. Casebolt
J. Thomas Wolner, P.E.
Tim Sirofchuck, CSP
Kurt Dunmire
Barry Cole
Philip L. Colleran, CSP
Ron Lattanzio
Frank Marino
Anthony Merisola
Patrick Brennan, CSHM, CSSM
R. Lee Reed, Jr.
Charles Kelly
Gary Birchall
Ronald Probasco, CSP
Garry Kosinski
Rod Gilles
J. Nigel Ellis, Ph.D., P.E., CSP, CPE
John Whitty, P.E.
Anthony O’Dea, CSP, CHST
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
Richard D. Hislop
Independent Electrical Contractors, Inc.
Institute of Makers of Explosives
Charles Praul, Jr., ASP
Richard Hislop
John P. Masarick
Bob Baird
Lon D. Santis
Susan JP Flanagan
International Association of Bridge, Structural,
Ornamental and Reinforcing Iron Workers
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Steve Rank
Robert Migliaccio, Sr.
International Brotherhood of Boilermakers
Brian Loftus
Bridget Connors
International Brotherhood of Electrical Workers
James Tomaseski
International Brotherhood of Teamsters
LaMont Byrd, CIH
Julie Plavka
International Safety Equipment Association
Cristine Fargo
International Union of Bricklayers & Allied Craftworkers Michael Kassman, CHST
Eileen Betit
International Union of Operating Engineers
Emmett Russell
Steve Brown
Jack L. Mickle & Associates
Jack Mickle, Ph.D., P.E.
Steve Stock, P.E., PLS
Laborers’ International Union of North America
Scott Schneider, MS, CIH
Walter A. Jones, MS
Marsh USA, Inc.
Timothy Bergeron, CSP
Maryland Occupational Safety & Health
Mischelle Vanreusel
Eric Uttenreither
Mechanical Contractors Association of America
Peter Chaney, MS, CSP
Dennis Langley
MYR Group, Inc.
National Association of Home Builders
Robert Matuga
Marcus Odorizzi
National Association of Railroad Safety
Consultants & Investigators
Lewis Barbe, P.E., CSP, CRSP
National Electrical Contractors Association
Michael J. Johnston
Jerry Rivera
National Institute for Occupational Safety & Health
Thomas G. Bobick, Ph.D., P.E., CSP, CPE
Matt Gillen, CIH
National Railroad Contractors &
Maintenance Association
Jeffrey D. Meddin, CSP, CHCM, CHEP
National Roofing Contractors Association
Harry Dietz
Tom Shanahan
National Society of Professional Engineers
E. Ross Curtis, P.E., DFE
Paul Swanson, P.E.
Operative Plasterers and Cement Masons
International Association
Gerald Ryan
Daniel M. Paine
Daniel M. Paine
Barbara Paine
Phoenix Fabricators and Erectors, Inc.
Robert E. Clouse, CSP, CHST
Frank Massey
Powder Actuated Tool Manufacturer’s Institute
James A. Borchers
David Jablonski
Power Consultants, Incorporated
David Goldsmith
Camille Villanova
Professional Safety Consultants, Inc.
Jim E. Lapping, MS, P.E., CSP
Anthony Brown
Property Casualty Insurers Association of America
John Rabovsky, MS, CSP, ARM
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
Ryland Group, Inc., The
Scaffolding, Shoring & Forming Institute
Shafer Safety Solutions, LLC
Sheet Metal & Air Conditioning Contractors’
National Association
Sheet Metal Workers International Association
SPA, Incorporated
Turner Construction Company
United Association of Plumbers and Pipefitters
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
United Brotherhood of Carpenters and
Joiners of America
United Union of Roofers, Waterproofers and
Allied Workers
U.S. Department of the Army – Corps of Engineers
U.S. Department of Energy
West Virginia University Extension Service
Winchester Homes Inc.
ZBD Constructors (Zurn Industries)
Daniel Lavoie, CSP
Bob Masterson, CSP
Chris Johnson
Carmen Shafer, CSP, CHST, CRIS
Mike McCullion, CSP, ARM
Joe Visgaitis
Gary Batykefer
Charles Austin, MS
Stanley Pulz, CSP, P.E.
Richard B. Loucks, Ph.D., P.E.
Cindy L. DePrater, ALCM
Paul Huntley
Laurie Shadrick
Eric Packard
William Irwin
Thomas L. Kavicky
John Barnhard
Brian Becker, MS
Ellen B. Stewart, CSP
Leslie Bermudez
Brandon Takacs
Mark Fullen, Ed.D., CSP
Thomas Trauger
Larry Freiert
Greg Thompson, CSP
Jeffrey D. Meddin, CSP, CHCM, CHEP
Independent Expert(s) on the A10 Committee:
Francis A. Dougherty with the U.S. Department of Labor – OSHA
Subgroup A10.1 had the following members:
Peter G. Chaney, MS, CSP (Chair)
Timothy Bergeron, CSP
Gary Birchall
Thomas G. Bobick, Ph.D., P.E., CSP, CPE
James G. Borchardt, CSP, CPE
Matthew J. Burkart, P.E.
Jack Duley
Dona L. File
Mark Fullen
Carl Heinlein, CSP, ARM, CPEA, CSHM, OHST
Richard Hislop
Richard King, CSP
Mark Klimbal, CSP, ARM
Robert Matuga
Mike McCullion, CSP, ARM
James. D. McIntosh, CIH, CSP
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Ronald McKenzie
Michele Myers Mihelic
John Neil
Jim Platner, Ph.D., CIH
Stanley Pulz, CSP, P.E.
R. Lee Reed, Jr.
Robert Renney
Brett Richardson
Jerry Rivera
Stanley Rosen
Scott Schneider, MS, CIH
Laurie Shadrick
Carmen Shafer, CSP, CHST, CRIS
Mischelle Vanreusel
Chris Williams
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
Contents
SECTION ............................................................................................................ PAGE
1. General ............................................................................................................ 10
1.1 Scope..................................................................................................... 10
1.2 Purpose ................................................................................................. 10
1.3 Exceptions ............................................................................................. 10
2. References ...................................................................................................... 10
3. Definitions ........................................................................................................ 10
4. Construction Owners – Pre-Project Safety and Health Planning .................... 12
4.1 General Responsibilities in Safety and Health Planning ....................... 12
4.2 Construction Safety and Health in Project Design ................................ 12
4.3 Project Constructor Candidate Evaluations .......................................... 13
5. Project Constructors – Pre-Project Safety and Health Planning ..................... 13
5.1 General Responsibilities in Project Safety and Health Planning ........... 13
5.2 Project Hazard Identification ................................................................. 13
5.3 Project Specific Safety and Health Plan ................................................ 13
5.4 Planning for Safety and Health with Contractor Candidates ................. 14
5.5 Contractor Candidate Evaluations ......................................................... 15
6. Project Constructors – Pre-Task Safety and Health Planning ........................ 15
6.1 Coordination of Pre-Task Planning with Contractors ............................ 15
7. Contractors – Pre-Project Safety and Health Planning ................................... 16
7.1 General Responsibilities in Project Safety and Health Planning ........... 16
7.2 Project Hazard Identification ................................................................. 16
7.3 Project Specific Safety and Health Plan ................................................ 16
7.4 Planning for Safety and Health with Sub-Tier Contractor Candidates .. 16
7.5 Sub-Tier Contractor Candidate Evaluations .......................................... 17
7.6 Safety and Health Training .................................................................... 18
7.7 Construction Equipment ........................................................................ 18
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
8. Contractors – Pre-Task Safety and Health Planning ...................................... 18
8.1 Task Hazard Analysis ............................................................................ 18
8.2 Task Specific Safety and Health Training ............................................. 19
8.3 Safety Equipment .................................................................................. 19
Appendixes:
A
A10.1 Outline ......................................................................................... 20
B
Safety and Health Performance Measurement Criteria Guidelines ...... 21
C
Project Hazard Identification Guidelines for Project
Constructors and Contractors ............................................................... 23
D
Task Hazard Analysis Guidelines .......................................................... 24
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
AMERICAN NATIONAL STANDARD A10.1
PRE-PROJECT & PRE-TASK SAFETY AND HEALTH PLANNING
GENERAL
ANSI/ASSE A10.34, Protection of the Public
on or Adjacent to Construction Sites
1.1
Scope. This standard establishes
the elements and activities for pre-project
and pre-task safety and health planning in
construction.
ANSI/ASSE A10.38, Basic Elements of an
Employer’s Program to Provide a Safe and
Healthful Work Environment
1.2
Purpose. The primary purpose of
this standard is to assist construction
owners,
project
constructors
and
contractors in making pre-project and pretask safety and health planning a standard
part of their planning processes. This
standard is also intended to assist owners in
establishing a process for evaluating project
constructor candidate safety and health
performance and planning practices.
1.3
3.
3.1
Company Safety and Health
Program. A written company program
describing how the company will address
safety and health as it pertains to workers,
other affected personnel and the general
public. (Refer to ANSI/ASSE A10.33, Safety
and Health Program Requirements for MultiEmployer Projects, ANSI/ASSE A10.38,
Basic Elements of an Employer’s Program
to Provide a Safe and Healthful Work
Environment, and ANSI/ASSE A10.34,
Protection of the Public on or Adjacent to
Construction Sites for guidance on program
development.)
Exceptions.
1.3.1
In cases of practical difficulties,
unnecessary hardships or new developments, the construction owner or project
constructor may grant exceptions to literal
requirements of this standard. These
exceptions may permit use of other
methods, but only when it is clearly
indicated and documented that the chosen
alternative method(s) provides adequate
workplace safety and health protection.
3.2
Competent Person. One who is
capable of identifying existing and
predictable hazards in surroundings which
are unsanitary, hazardous or dangerous to
employees, and who has the authority to
take prompt corrective measures to
eliminate them.
1.3.2
This standard is not intended for
owners of residential property contracting
for work to build or work on their personal
residence.
2.
DEFINITIONS
3.3
Construction Owner. The entity
or entities who contract with a project
constructor to perform construction or
demolition work.
REFERENCES
3.4
Complex Task. Any potentially
hazardous task that requires specific
competencies e.g. structural engineering
expertise, complex crane hoist/lift expertise,
industrial hygiene expertise, etc., for safe
and successful completion. Examples of
complex tasks may include, but are not
necessarily
limited
to
excavations,
demolition, confined space entry, hazardous
The following existing industry standards
are referenced in this standard.
ANSI/ASSE A10.33, Safety and Health
Program Requirements for Multi-Employer
Projects
10
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
1.
AMERICAN NATIONAL STANDARD A10.1-2011
substance abatement and
(cranes and helicopters), etc.
critical
lifts
measures. These tasks include, but are not
necessarily limited to the following:
3.5
Construction
Project.
All
construction
and/or
demolition
work
performed by or for the construction owner
as stated in the project documents.
1)
Tasks that could result in a
worker falling 6 feet or more to a
lower level.
2)
Tasks that could result in a
worker being struck by an object.
3.6
Contract Documents. Documents
that are part of the contract between the
owner and project constructor, which
include, but are not necessarily limited to
the project manual, bid packages, drawings,
plans, specifications, addenda, general and
special conditions, schedules, scope
reviews, site utilization plans, safety and
quality plans and project procedures.
3)
Tasks that could result in a
worker being caught in an
excavation cave-in.
4)
Tasks that could result in a
worker being exposed to energized electrical parts.
3.7
Contractor. A subcontractor (subtier contractor), specialty contractor or other
entity as designated in the project
documents, responsible for part of the
construction process on a construction
project.
5)
Tasks that could result in
overexposure to health hazards.
6)
Routine tasks that become
non-routine due to unexpected
occurrences such as equipment
breakdowns, weather conditions,
changes in the project specific
safety plan, etc.
3.8
Contractor
Candidate.
Any
potential contractor who is either bidding on
or otherwise being considered to perform
part of the construction process on a
construction project.
3.13
Pre-Project Safety and Health
Planning. The process of incorporating
worker safety and health into the planning of
a construction project.
3.9
Craft Labor. Any person(s)
employed by a contractor to perform
construction work.
3.14
Pre-Task Safety and Health
Planning. The process of incorporating
worker safety and health into the planning of
each complex task and potentially
hazardous task in each phase of the project.
3.10
Critical Topics. Topics to be
considered during the development of a
project specific safety and health plan.
3.11
Operational Plan (Construction
Sequence Plan). The documents that
address the milestones, activity dates and
updated schedules during each phase of
construction, and the methods to be used to
achieve them.
3.15
Project Constructor. The person,
firm or corporation, i.e. construction
manager, general contractor, project
constructor or other entity, as designated in
the project documents, responsible for
supervising and controlling all construction
work performed on the project.
3.12
Potentially Hazardous Task. Any
task that presents a substantial probability
of death, serious physical harm or
significant impairment to health without
appropriate safety or health protective
3.16
Project Constructor Candidate.
Any potential project constructor who is
either bidding on or otherwise being
considered to supervise and control all
11
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
construction work to be performed on the
project.
goals and policies for safety and health are
established for the project.
3.17
Project Hazard Identification.
The process of identifying complex tasks
and other potentially hazardous tasks
throughout project construction.
4.1.2
The construction owner shall
ensure that the project specific safety and
health policies are implemented by the
project constructor and evaluated for
necessary changes throughout project
construction.
3.18
Project Specific Safety and
Health Plan. A written plan describing how
project specific safety and health issues
such as complex tasks and potentially
hazardous tasks will be addressed. The
plan is based on the most current
operational plans, company safety and
health programs, hazard identification
reports and all applicable topics listed in
5.3.1.
4.2
Construction Safety and Health
in Project Design.
4.2.1
Throughout the design phase of
the project, the construction owner shall
provide leadership and maintain a decisionmaking policy to enhance worker safety and
health on the project.
3.19
Safety and Health Design
Specifications. Construction specifications
established during the design process to
minimize safety and health hazards for
workers, such as permanent fall arrest
anchors on flat unprotected roofs.
4.2.2
The construction owner shall
ensure safety and health design specifications are established and incorporated into
the appropriate contract documents. Where
an owner retains a design professional, the
design
professional
shall
propose
occupational safety and health design
specifications that will help to prevent or
minimize work related hazards.
3.20
Task. Any activity or process with
multiple steps with an established beginning
and end.
4.2.3
The construction owner shall
ensure all safety and health design
specifications and information on any
remaining identified risks are provided to the
project constructor in a pre-project meeting.
3.21
Task Hazard Analysis. The
process of analyzing work tasks to identify
potential hazards and determine how to
address them so that the task can be
completed safely. The process includes the
evaluation of the task, affected workers,
tools, materials, equipment and identification of appropriate hazard controls. The
process is also commonly referred to as an
Activity Hazard Analysis or Job Hazard
Analysis.
4.2.4
The construction owner shall
require the project constructor to become
familiar with the project’s safety and health
design specifications, and convey the
specifications requirements to all contractors and other affected project
personnel.
4.
CONSTRUCTION OWNERS –
PRE-PROJECT SAFETY AND HEALTH
PLANNING
4.1
General
Responsibilities
Safety and Health Planning.
4.2.5
During the bidding phase of a
project, the owner shall ensure that
sufficient time and information are available
for the project constructor candidates to
adequately evaluate design requirements
and investigate site conditions.
in
4.1.1
The construction owner shall
ensure that project specific expectations,
12
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
AMERICAN NATIONAL STANDARD A10.1-2011
AMERICAN NATIONAL STANDARD A10.1-2011
4.2.6
The owner shall ensure that
sufficient time and resources are made
available for pre-project safety and health
planning.
minimum, a list of the complex tasks and
site conditions anticipated for the project,
and a description of each of them.
5.3
Project
Health Plan.
4.3
Project Constructor Candidate
Evaluations.
1)
Materials
storage.
4.3.2
Performance measurement criteria
shall be used to help determine whether
project constructor candidates qualify to
work on a project.
2)
and
delivery
and
Traffic control.
3)
Construction equipment
shared work areas.
4.3.3
The construction owner shall
require project constructor candidates to
submit an operational plan and their
company safety and health program.
in
4)
Safety equipment in shared
work areas.
4.3.3.1 The plans and programs shall be
evaluated as part of the project constructor
selection process.
5)
Onsite first aid and medical
treatment facilities.
6)
Emergency eye wash and
emergency shower facilities.
5.
PROJECT CONSTRUCTORS –
PRE-PROJECT SAFETY AND HEALTH
PLANNING
in
5.1.1
The project constructor shall plan
for overall safety and health on the project.
5.2
Safety
5.3.1
As part of the planning process,
the project constructor shall develop a
project specific safety and health plan which
includes the impact of safety and health on
the following critical topics where applicable:
4.3.1
The construction owner shall
establish and implement an evaluation
process that measures the safety and
health performance of project constructor
candidates (see Appendix B for examples).
5.1
General
Responsibilities
Project Safety and Health Planning.
Specific
7)
Change facilities.
8)
Sanitary facilities.
9)
Washrooms.
10) Clean rooms and storage
areas.
Project Hazard Identification.
11) Break rooms/areas.
5.2.1
The project constructor shall
perform project hazard identification using
contract documents, project schedules, site
assessments, drawings, plans, building
information models, project specifications,
etc. to identify the complex tasks that will be
performed on the project.
12) Shower facilities.
13) Decontamination facilities.
14) Inclement weather protection
plan.
5.2.1.1 The project constructor shall
develop a project hazard identification
report. The report shall include, at a
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
15) Access and egress routes.
16) Vehicular access control.
13
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
5.3.3
The project constructor shall
evaluate the plan throughout project
construction and revise it as necessary. The
project constructor shall immediately advise
all contractors about changes made to the
plan.
17) Parking facilities.
18) Walkways and pedestrian
sheds for pedestrians.
19) Housekeeping.
5.4
Planning for Safety and Health
with Contractor Candidates.
20) Material handling.
21) Scheduling.
5.4.1
The project constructor shall
address project specific safety and health
procedures and requirements in a pre-bid
meeting with all contractor candidates.
22) Overtime work.
23) Shift work.
5.4.2
Prior to the meeting, the project
constructor shall provide each contractor
candidate with the following documents:
24) Incident reporting.
25) Incident
dures.
response
proce-
1)
The project constructor’s
project specific safety and health
plan.
26) Unsafe conditions reporting.
27) Communication.
2)
The project constructor’s
project hazard identification report.
28) Emergency action plan.
5.4.3
The following topics, at a
minimum, shall be addressed in the
meeting.
29) Chemical use and storage.
30) Controls
hazards.
for
chemical
5.4.3.1 Complex tasks and how they are
to be addressed by each contractor.
31) Site security.
5.4.3.2 Contents of the project constructor’s project specific safety and health
plan with emphasis on the following:
32) Special hazards.
33) Illumination.
34) Public exposure protection.
1)
Minimum safety and health
staffing requirements and qualifications.
35) Potentially hazardous adjacent operations.
2)
Project specific safety and
health orientation for workers and
supervisors.
36) Potential for earthquakes and
other environmental issues.
5.3.2
The project constructor shall
establish a system to confirm that its project
specific safety and health plan is
implemented by all contractors on the
project.
3)
Requirements for drug and
alcohol testing on the project.
4)
Critical topics identified in
5.3.1.
14
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
5)
Use of construction equipment with specific regard to worker
safety and health.
5.4.4
The discussion on the project
specific safety and health plan shall include
the specific responsibilities of each
contractor.
Candidate
Evalu-
7)
Resources the supervisors
will use to communicate with nonEnglish speaking workers.
5.5.1
The project constructor shall
establish and implement an evaluation
process that measures the safety and
health performance of contractor candidates
(see Appendix A for examples).
8)
Methods of safety and health
mentoring for new workers.
6.
PROJECT CONSTRUCTORS –
PRE-TASK SAFETY AND HEALTH
PLANNING
5.5.2
The established safety and health
performance measurement criteria shall be
used to help determine whether a contractor
candidate qualifies to work on a project.
6.1
Coordination
of
Planning with Contractors.
5.5.3
The project constructor shall
evaluate each contractor candidate’s
company safety and health program. The
results of the evaluation shall be included as
part of the contractor selection process.
Pre-Task
6.1.1
The project constructor shall
establish regular safety and health planning
meetings with all contractors for the purpose
of coordinating project activities.
5.5.4
The project constructor shall
require each contractor candidate to provide
a report covering safety and health
equipment, resources and activities anticipated for the project. At a minimum, the
report
shall
include
the
following
information:
6.1.2
The meetings shall be timed to
allow adequate planning for each approaching construction phase and complex task.
6.1.3
The project constructor shall
require all contractors to participate in the
planning meetings.
1)
Safety staff based on the
scope of work.
6.1.4
The project constructor shall
establish the agenda for each planning
meeting addressing the following topics
where applicable:
2)
Pre-project and onsite safety
and health training including time
allocated for craft labor safety and
health training.
1)
Upcoming complex tasks.
3)
A substance abuse program,
which includes a company policy,
and drug and alcohol testing.
2)
Project design factors applicable to worker safety and health
in upcoming tasks.
4)
Personal
ment.
3)
Identification of overhead
and underground utilities.
protective
equip-
4)
Introduction
tractors.
15
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
of
new
con-
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
5.5
Contractor
ations.
6)
Other safety and health
resources anticipated for the
project.
AMERICAN NATIONAL STANDARD A10.1-2011
5)
Substantive changes to the
project’s work environment.
7.
CONTRACTORS
–
PREPROJECT
SAFETY
AND
HEALTH
PLANNING
6)
Changes to the
communication plans.
7.1
General
Responsibilities
Project Safety and Health Planning.
7.1.1
Each contractor shall plan for
safety and health on the project.
Crane movements.
8)
Construction equipment and
vehicle traffic patterns designed to
reduce the risk to pedestrian
traffic.
7.2
7.2.2
Each contractor shall develop a
project hazard identification report. At a
minimum, the report shall include a list of
the potentially hazardous tasks with
accompanying descriptions of each of them.
and
11) Substantive changes concerning hazardous substances
(hazard communication).
7.3
Project
Health Plan.
12) Energized electrical conductors such as overhead power
lines.
13) Substantive
project plans.
changes
Specific
to
and
7.3.2
Each contractor shall develop a
project specific safety and health plan. The
plan shall include provisions for addressing
complex tasks and other project specific
safety and health issues such as potentially
hazardous tasks identified during the
contractor’s project hazard identification
process.
of
16) Lockout/tagout requirements.
17) Potentially hazardous materials at existing facilities.
7.4
Planning for Safety and Health
with Sub-Tier Contractor Candidates.
18) Contingency
plans
and
changes to contingency plans for
emergency rescues, evacuations
and other unanticipated events.
7.4.1
Each contractor shall address
project
specific
safety
and
health
procedures and requirements at a pre-bid
meeting with all sub-tier contractor
candidates.
19) Training.
20) Specific hazards.
16
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Safety
7.3.1
Each contractor shall review the
project
constructor’s
project
hazard
identification report. Potentially hazardous
tasks identified by a contractor that are not
addressed in the report shall be reported by
that contractor to the project constructor.
14) Chemical use, storage and
disposal.
15) Use and maintenance
engineering controls.
Project Hazard Identification.
7.2.1
Each contractor shall perform
project hazard identification within its scope
of work to identify the potentially hazardous
tasks that will be required to be performed.
9)
Construction equipment and
vehicle traffic pattern changes.
10) Special
equipment
material delivery.
in
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
7)
project’s
AMERICAN NATIONAL STANDARD A10.1-2011
7.4.2
The contractor shall provide each
sub-tier contractor candidate with the
following documents prior to the meeting:
the specific
contractor.
each
7.5.1
Each contractor shall evaluate the
safety and health performance of each subtier contractor candidate before contracting
with them to perform work on the project.
2)
The project constructor’s
project hazard identification report.
7.5.2
The
project
constructor’s
established safety and health performance
measurement criteria shall be used by the
contractor to help determine whether a subtier contractor candidate qualifies to work on
a project.
3)
Critical topics identified in
5.3.1.
4)
The
contractor’s
project
specific safety and health plan.
5)
The
contractor’s
project
hazard identification report.
7.5.3
The contractor shall require each
sub-tier contractor candidate to submit its
company safety and health program.
contract
7.5.4
The contractor shall evaluate each
sub-tier contractor candidate’s company
safety and health program. Each program
shall be evaluated as part of the sub-tier
contractor selection process.
7.4.3
The following topics, at a
minimum, shall be addressed in the
meeting.
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
7.4.3.1
work.
of
7.5
Sub-Tier Contractor Candidate
Evaluations.
1)
The project constructor’s
project specific safety and health
plan.
6)
All
applicable
documents.
responsibilities
Complex tasks within the scope of
7.5.5
The contractor shall require each
sub-tier contractor candidate to provide a
report
covering
safety
and
health
equipment, resources and activities anticipated for the project. At a minimum, the
report shall include the following:
7.4.3.2 Potentially hazardous tasks within
the scope of work.
7.4.3.3 Contents of the contractor’s project
specific safety and health plan with
emphasis on the following:
1)
Safety staff based on the
scope of work.
1)
Minimum safety and health
staffing requirements and qualifications.
2)
Onsite safety and health
training including the time allocated for craft labor safety and
health training.
2)
Project specific safety and
health training for workers and
supervisors.
3)
A substance abuse program,
which includes a company policy,
and drug and alcohol testing.
3)
Requirements for drug and
alcohol testing on the project.
4)
Personal protective equipment required within their scope of
work.
7.4.4
The discussion on the project
specific safety and health plan shall include
17
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
5)
Use of construction equipment with specific regard to worker
safety and health.
2)
Project specific safety and
health orientation.
3)
Identification of, and corresponding protective measures for,
the most common applicable trade
specific safety and health hazards.
6)
Other safety and health
resources anticipated for the
project.
7)
Methods the supervisor will
use to communicate with nonEnglish speaking workers.
4)
Site emergency
procedures.
5)
Instruction
on
how
to
effectively communicate critical
safety and health issues with nonEnglish speaking workers.
8)
Methods of safety mentoring
for new workers.
9)
Contact
information
for
individuals responsible for safety
including the names of competent
persons assigned to the project.
7.6
and
7.7
Construction Equipment.
7.7.1
As part of the planning process,
each contractor shall determine what
construction equipment will be needed for
the project within its scope of work.
health
Safety and Health Training.
7.7.1.1 Each
contractor
shall
plan
equipment selection based on available
safety features such as rear-view cameras
with cab monitors, back-up alarms, side
view visibility ports, noise levels, noise
controls, etc.
7.6.1
Each contractor shall establish a
safety and health training plan within the
scope of work for affected craft labor and
supervisors.
7.6.1.1 Craft labor safety and health
training shall include the following types of
training:
7.7.1.2 Each contractor shall plan for short
term and long term equipment maintenance,
regular
equipment
inspections
and
operators’ equipment-specific training.
1)
New hire orientation.
2)
Job specific training.
8.
CONTRACTORS – PRE-TASK
SAFETY AND HEALTH PLANNING
3)
Site-specific training.
8.1
4)
Regular
meetings.
onsite
Task Hazard Analysis.
8.1.1
As part of the planning process,
each contractor shall perform a task hazard
analysis before beginning work on any
complex task or potentially hazardous task.
All task hazard analyses shall occur as
close to the time the task will begin as is
feasible.
safety
7.6.2
Safety and health training for
supervisors shall include the following types
of training:
1)
Instruction
on
how
to
establish a safe project work
environment.
8.1.2
Each contractor shall identify the
individuals responsible for supervising and
18
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
10) Other safety
topics as needed.
response
AMERICAN NATIONAL STANDARD A10.1-2011
performing each complex
potentially hazardous task.
task
and
8.1.3
Each contractor shall assign
responsibility for implementation of safety
and health control measures that will be
established for each complex task or
potentially hazardous task.
8.1.4
Each affected supervisor and all
affected craft labor shall be informed about
the task hazard analysis and required to
participate in the process. Participation shall
include discussion on accomplishing the
task step by step with appropriate work
activities, communication and personal
protective equipment.
8.1.5
All affected craft labor shall be
informed how to contact the supervisor or
competent person overseeing the complex
task or potentially hazardous task.
8.2
Task Specific Safety and Health
Training.
8.2.1
Each affected supervisor shall
ensure that each individual responsible for
performing any part of a complex task or
potentially hazardous task has been
properly trained to perform the task safely.
8.3
Safety Equipment.
8.3.1
Each affected supervisor shall
ensure that craft labor receives the safety
and/or health equipment identified in the
task hazard analysis and the appropriate
training necessary to perform the task
safely.
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
19
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
Appendix A – The following Appendix is non-mandatory and is included for informational
purposes only.
A10.1 Outline
Owners Pre-Project Planning (Section 4)
 Ensure project safety policies are established and implemented 4.1
 Ensure safety is considered in the design process 4.2
 Establish project constructor candidate safety evaluation process criteria 4.3
Project Constructors Pre-Project Planning (Section 5)
 Plan for project’s overall safety and health 5.1
 Perform project hazard identification to identify Complex Tasks 5.2
 Develop a project hazard identification report 5.2
 Establish project specific safety and health plan 5.3
 Meet with contactor candidates to convey project safety issues/requirements 5.4
 Evaluate contractor candidates’ safety and health performance 5.5
Project Constructors Pre-Task Planning (Section 6)
 Establish regular safety coordination meetings with contractors hired for the project 6.1
Contractors Pre-Project Planning (Section 7)
 Plan for safety within scope of work 7.1
 Perform project hazard identification to identify Potentially Hazardous Tasks 7.2
 Develop a project hazard identification report 7.2
 Establish project specific safety and health plan 7.3
 Meet with sub-tier contractor candidates to convey project safety issues/requirements 7.4
 Evaluate sub-tier contractor candidates’ safety and health performance 7.5
 Establish safety and health training plan within the scope of work 7.6
 Select construction equipment based on available safety features 7.7
Contractors Pre-Task Planning (Section 8)
 Perform task hazard analysis for each Complex Task 8.1
 Perform task hazard analysis for each Potentially Hazardous Task 8.1
 Establish responsibility for supervision and actual work 8.1
 Ensure task specific safety training is completed before task begins 8.2
 Ensure all necessary safety equipment is readily available/accessible 8.3
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Non-Mandatory Appendices
 A10.1 Standard Outline - Appendix A
 Safety and Health Performance Measurement Criteria (Examples) - Appendix B
 Project Hazard Identification Guidelines-Project Constructors/Contractors - Appendix C
 Task Hazard Analysis Guidelines - Appendix D
20
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
Appendix B – The following Appendix is non-mandatory and is included for informational
purposes only.
Safety and Health Performance Measurement Criteria Guidelines
Examples of safety and health performance measurement criteria that can be used to evaluate
contractors’ safety and health performance are shown below. The ANSI A10 Committee
recommends the use of leading indicators. The committee believes that leading indicators
reflect a company’s safety performance more accurately than lagging indicators.
Leading Indicators
Leading indicators are metrics used to measure occupational safety and health activities. The
results can be used to identify shortcomings in safety and health programs and identify
corrective action necessary to prevent work related injuries and illnesses.
Examples of leading indicators:
•
•
•
•
•
•
•
•
•
•
•
•
•
Implementation of multi-employer site safety and health program
Implementation of contractor safety and health program
Frequency of project safety and health inspections
Tracking of safe/unsafe work practices
Percentage of inspection issues properly corrected
Frequency of safety and health communications i.e. safety meetings, formal safety
training sessions, short-duration training sessions, etc.
Frequency of investigations of incidents that resulted in work related injury or illness
Frequency of investigations of near miss incidents
Implementation of action plan for addressing results of investigations
Frequency of repeat incidence
Frequency of task hazard analyses performed for high hazard activities
Implementation of substance abuse program, which includes alcohol and drug
testing
Implementation of 100% hard hat and safety glasses policy
Lagging Indicators
Lagging indicators are metrics used to measure past occupational safety and health
performance. The results can be used to identify negative safety and health trends and identify
corrective action necessary to prevent future work related injuries and illnesses.
Occupational Injury and Illness Incidence Rates
Occupational injury and illness incidence rates are derived from a simple calculation. The rates
represent frequency and severity of work-related injuries and illnesses, and are calculated
based on 100 full time workers. Examples of occupational injury and illness incidence rates:
•
•
•
•
Fatality incidence rate
Recordable case injury incidence rate
Recordable case illness incidence rate
Recordable case injury and illness incidence rate
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
21
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
•
•
•
•
•
•
Lost workday cases injury incidence rate
Lost workday cases illness incidence rate
Lost workday cases injury and illness incidence rate
Lost workdays injury incidence rate
Lost workdays illness incidence rate
Lost workdays injury and illness incidence rate
Calculation:
200,000 = 100 full time workers x 40 hours per week x 50 weeks per year
N = the number from the type of incidence rate you are calculating
WH = Total work hours
N x 200,000
__________ = Incidence Rate (Per 100 Full Time Workers)
WH
For example, if N = 2 recordable cases and WH = 100,000
2 x 200,000 / 100,000 work hours = 4.0
Recordable Cases Incidence Rate = 4.0
Experience Modification Rates (EMR)
Experience modification rates are multipliers used in most states’ workers’ compensation
formulas. The rates are based on worker injury/illness loss history over a three year period (the
first three of the last four years) and can drive workers’ compensation insurance costs up or
down depending on the amount of loss that occurred over the three year period. An EMR of 1.0
is considered to be average. An EMR over 1.0 will increase the base premium. An EMR below
1.0 will result in a reduction to the base premium. Contractors should contact their workers’
compensation insurance carriers to obtain current and past EMRs.
Types of Experience Modification Rates:
•
•
•
•
Interstate
Intrastate
Monopolistic State Rate
Dual Rate
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
22
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
Appendix C – The following Appendix is non-mandatory and is included for informational
purposes only.
Project Hazard Identification Guidelines for
Project Constructors and Contractors
Purpose:
•
To identify complex tasks and potentially hazardous tasks, and inform all contractors
and other affected project personnel about them.
Procedure:
•
Evaluate project schedules, site assessments, building information models, project
specifications and/or any other documents that could help identify complex tasks and
potentially hazardous tasks.
•
Determine which tasks are likely to present a substantial probability of death, serious
physical harm or significant impairment to health without appropriate safety and
health protective measures such as tasks that could result in one or more of the
following:
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
-
•
(Project Constructors Only) Determine which of those tasks will require:
-
•
A worker falling 6 feet or more to a lower level.
A worker being struck by an object.
A worker being caught in an excavation cave-in.
A worker being exposed to energized electrical conductors or circuit parts.
A worker being overexposed to a significant health hazard.
Typical tasks becoming non-typical due to unexpected occurrences such as
equipment breakdowns, weather conditions, changes in the project specific
safety plan, etc.
Other significant ways a worker could be injured on a particular project.
Individuals with specialized competencies such as those provided by a registered
professional engineer, a specialized occupational safety and health professional
or an industrial hygienist.
A specialized contractor.
A specialized work crew.
Craft labor skills beyond the standard skills required for the specified craft.
Generate a project hazard identification report to share with all contractors and other
affected project personnel by listing the tasks that meet the criteria established in the
preceding two major bullets above. Provide a detailed, written description of each of
them including the anticipated hazards.
23
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
Appendix D – The following Appendix is non-mandatory and is included for informational
purposes only.
Task Hazard Analysis Guidelines
Purpose:
•
Identification of potential task specific safety and/or health hazards, and
establishment of safe and/or healthful task procedures.
General:
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
•
Perform the task hazard analysis as close to the task’s start-up time as possible.
•
Ensure each affected supervisor and all affected craft labor participate in the
analysis.
•
Identify the potential hazards.
•
Determine whether a permit, such as a confined space entry permit or hot work
permit, is necessary for craft labor protection.
•
Identify construction methods and/or control measures to eliminate or control the
risks.
•
Identify the safety and health equipment and materials needed to perform the task
safely.
•
Establish safe task procedures.
•
Provide task specific safety and health training for all affected craft labor.
•
Ensure the availability of safety and health equipment needed for the task.
•
Ensure a qualified safety professional or competent person participates when a
complex task is involved.
•
Determine whether emergency rescue planning is necessary.
•
Perform a pre-task briefing immediately prior to the start of the task to remind
affected craft labor about the hazards and established safe task procedures.
Task Hazard Analysis Procedures:
1.
Refer to list of complex tasks and/or potentially hazard tasks that will affect workers on
the project.
2.
Break each task down into specific steps and record them as follows:
24
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
3.
4.
•
Record enough steps to accurately identify the potential hazards, but record the
fewest number of steps possible.
•
Number each step in the sequence in which it will occur.
•
Anticipate and record everything workers must do to successfully complete the task.
•
Record any anticipated deviations from standard operating procedures.
•
While recording the steps, describe the beginning of each individual step with an
action verb such as “climbs the ladder” or “enters the confined space”.
•
Include the workers who will be performing the task in the process so important steps
are not omitted.
Using the information recorded from breaking the task down into steps, identify and
record all procedure based and environmental hazards by considering several questions
about each individual step such as the following:
•
Could a worker fall 6 feet or more to a lower level?
•
Could a worker be struck by an object?
•
Could a worker get caught up in an excavation cave-in?
•
Could a worker become exposed to an energized electrical conductor?
•
Could a worker become overexposed to a harmful chemical, harmful noise level or
some other health related hazard?
•
Has a typical task become non-typical due to unexpected occurrences, such as an
equipment breakdown, weather conditions, changes in the project specific safety
plan, etc.?
Develop and record a safe work procedure for each task by:
•
Identifying the best way to perform the task safely and effectively.
•
Identifying a way to change the physical conditions of the task.
•
Identifying an effective way to change the work procedure.
•
Identifying a way to reduce the frequency of exposure.
5.
Include each affected worker in the safe work procedure development process.
6.
Where unusual or unfamiliar steps are required to complete a task, train each affected
worker how to perform the task safely and efficiently. Ensure workers have a thorough
understanding about the safe work procedures developed for the task.
--``,`,``,``,`,````,``,,`,,,`,`-`-`,
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
25
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
AMERICAN NATIONAL STANDARD A10.1-2011
7.
Just before the task begins, bring all affected workers and supervisors together for a pretask briefing to:
•
Review the hazards identified in the task hazard analysis.
•
Review the established safe work procedures.
•
Determine whether any changes to the procedures are needed due to changes in
scheduling, weather conditions or any other pertinent factors.
•
Account for all of the necessary tools and/or equipment established in the
procedures.
•
Account for all of the necessary personal protective equipment established in the
procedures.
•
Provide each affected worker with a sign-off sheet that indicates they know the
hazards associated with the task, and understand how they are to protect
themselves from the hazards.
•
Collect and file the signed sign-off sheets.
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
26
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Page Intentionally Left Blank
Page Intentionally Left Blank
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
Page Intentionally Left Blank
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
1. GRANT OF LICENSE: Subject to the provisions contained herein and to the payment of all applicable
fees, the American Society of Safety Engineers (ASSE) grants you a nonexclusive, non-transferable license
to the materials contained herewith (the "Product"). Your licensed rights to the Product are limited to the
following:
(a) This License Agreement does not convey to you an interest in or to the Product, but only a limited
right of use revocable in accordance with the terms of this License Agreement.
(b) You may install one copy of the Product on, and permit access to it by, a single computer owned,
leased or otherwise controlled by you. In the event that computer becomes dysfunctional, such
that you are unable to access the Product, you may transfer the Product to another computer,
provided that the Product is removed from the computer from which it is transferred and the use of
the Product on the replacement computer otherwise complies with the terms of this Agreement.
Neither concurrent use on two or more computers nor use in a local area network or other network
is permitted. You shall not merge, adapt, translate, modify, rent, lease, sell, sublicense, assign, loan or give
to or otherwise transfer any of the Product, or copies thereof, or remove any proprietary notice or label
appearing on any of the Product to any individual or entity for any reason or purpose. You may copy the
Product only for backup purposes.
(c) You acknowledge and agree that the Product is proprietary to the Copyright holder (the "Owner")
identified on the front page of the Product, and is protected under U.S. copyright law and international
copyright treaties. You further acknowledge and agree that all right, title and interest in and to the Product,
including all intellectual property rights, are and shall remain entirely with the Owner.
(d) You shall provide ASSE or any designee of ASSE with all information necessary to assure
compliance with the terms of this Agreement. In the event you are not in compliance with the
terms of this Agreement through the actions of unrelated third parties, you shall use your best
efforts to cooperate with ASSE and any of its designees to assure compliance.
2. LIMITED WARRANTY:
(a) ASSE warrants for your benefit alone that, unless disclosed in the Product to the contrary, ASSE and
the Owner can license the Product and all copyright and trademarks related thereto or therein.
(b) THE EXPRESS WARRANTIES SET FORTH IN THIS SECTION 2 CONSTITUTE THE ONLY
WARRANTIES WITH RESPECT TO THE PRODUCT AND ASSE AND THE OWNER MAKE NO
OTHER REPRESENTATION OR WARRANTY OR CONDITION OF ANY KIND, WHETHER
EXPRESS OR IMPLIED (EITHER IN FACT OR BY OPERATION OF LAW) WITH RESPECT TO
ANY OF THE PRODUCT, INCLUDING, WITHOUT LIMITATION, WITH RESPECT TO THE
SUFFICIENCY, ACCURACY OR UTILIZATION OF, OR ANY INFORMATION OR OPINION
CONTAINED OR REFLECTED IN, ANY OF THE PRODUCT. ASSE AND THE OWNER
EXPRESSLY DISCLAIMS ALL WARRANTIES OR CONDITIONS OF MERCHANTABILITY OR
FITNESS FOR A PARTICULAR PURPOSE. NO OFFICER, DIRECTOR, EMPLOYEE, MEMBER,
AGENT, CONSULTANT, CONTRACTOR, REPRESENTATIVE OR PUBLISHER OF THE
COPYRIGHT HOLDER IS AUTHORIZED TO MAKE ANY MODIFICATION, EXTENSION, OR
ADDITION TO THIS LIMITED WARRANTY.
3. INDEMNIFICATION:
The Owner, ASSE, any agent, representative, publisher or distributor of the Product, or any of
their respective directors, officers, employees, agents, representatives or members (the “ASSE and
Owner Indemnified Parties”) shall have no liability for, and you shall defend, indemnify and hold
each of the ASSE and Owner Indemnified Parties harmless from and against, any claim, loss,
demand, liability, obligation and expenses (including reasonable attorneys' fees) based upon or
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
END USER LICENSE AGREEMENT
IMPORTANT - READ CAREFULLY BEFORE DOWNLOADING OR COPYING TO YOUR
COMPUTER ANYFILE(S) CONTAINED HEREWITH. THE STANDARD(S) AND OTHER
INFORMATION PROVIDED HEREWITH ARE COPYRIGHTED. BY DOWNLOADING ANY FILE
PROVIDED HEREWITH TO YOUR COMPUTER, YOU ARE ACCEPTING AND AGREEING TO
THE TERMS OF THIS LICENSE AGREEMENT. IF YOU ARE NOT WILLING TO BE BOUND BY
THE TERMS OF THIS LICENSE AGREEMENT, PRIOR TO DOWNLOADING OR COPYING TO
YOUR COMPUTER ANY FILES(S), YOU MUST DECLINE ACCESS TO SUCH MATERIALS.
arising out of any injury or damage, or any product liability claim, including but not limited to,
any personal or bodily injury or property damage, arising out of, pertaining to, or resulting in any
way from, the use or possession of any of the Product by you and/or any of your directors,
officers, employees, representatives, agents or contractors.
4. LIMITATION OF LIABILITY:
a) You acknowledge that each of ASSE and Owner's obligations and liabilities with respect to the
Product are exhaustively defined in this Agreement. You are responsible for the consequences of any
use of any of the Product (whether or not such use was consistent with the license granted hereunder)
created therefrom. Whether or not ASSE or Owner has been advised of their possibility, neither ASSE
nor Owner nor any of its representatives or agents, directors, officers, employees, agents, representatives or
members, shall be liable, whether under contract, tort (including negligence) or otherwise, for any indirect,
special, punitive, incidental or consequential loss, damage, cost or expense of any kind whatsoever and
howsoever caused, that may be suffered by you or any of your directors, officers, employees, agents,
representatives or contractors or any third party.
b) If at any time an allegation of infringement of any rights of any third party is made, or in ASSE or
Owner's opinion is likely to be made, with respect to any of the Product, ASSE may, at its option and
at its own expense (i) obtain for you the right to continue using the Product, (ii) modify or replace the
Product or any portion thereof so as to avoid any such claim of infringements, or (iii) refund to you the
License Fee. ASSE shall have no liability to you if any claim of infringement would have been
avoided except for your refusal to use any modified or replacement Product supplied or offered to be
supplied pursuant to this Section 4(b) or to otherwise cease using the Product. Notwithstanding
anything contained in this Agreement, and except as set forth in Section 4(b) hereof, ASSE and/or
Owner's liability to you for damages pursuant to this Section 4(b), if any, shall not exceed the amounts
of the License Fee paid by you for the Product subject to any such claim.
c) Section 4(b) state the entire liability of ASSE and Owner with respect to the infringement or alleged
infringement of any third party rights of any kind whatsoever by any of the Product.
5. TERMINATION: This Agreement may be terminated immediately by Owner or ASSE upon breach of
any provision of this Agreement by you. Upon any termination of this Agreement, you shall immediately
discontinue the use of the Product and shall within ten (10) days either return files(s) on diskette(s), if any,
to ASSE or certify in writing to ASSE that the Product has been deleted from your computer and is
eliminated from your premises.
6. GOVERNING LAW: This Agreement shall be governed by the laws of the State of Illinois without
reference to its conflict of laws provisions and you further consent to jurisdiction by the state and federal
courts sitting in the State of Illinois.
7. MISCELLANEOUS: This Agreement constitutes the complete and exclusive agreement between
ASSE and you with respect to the subject matter hereof, and supercedes all prior oral or written
understandings, communications or agreements not specifically incorporated herein. This Agreement
may not be modified except in writing duly signed by an authorized representative of ASSE and you.
If any provision of this Agreement is held to be unenforceable for any reason, such provision shall be
reformed only to the extent necessary to make it enforceable, and such decision shall not affect the
enforceability (i) of such provision under other circumstances, or (ii) of the remaining provisions
hereof under all circumstances. Headings shall not be considered in interpreting the Agreement.
8. EXPORT: You may not load or export or re-export any of the Product or any underlying information
or technology except in full compliance with all United States and other applicable laws and regulations.
BY ACCESSING THE PRODUCT, YOU ACKNOWLEDGE THAT YOU HAVE READ THE
TERMS OF THIS LICENSE AGREEMENT AND AGREE TO BE BOUND BY ITS TERMS.
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
ANSI/ASSE A10 Construction
& Demolition Standards
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
A10.1 Pre-Project & Pre-Task Safety & Health Planning for Construction &
Demolition Operations
A10.3 Powder-Actuated Fastening Systems
A10.4 Personnel Hoists & Employee Elevators on Construction & Demolition Sites
A10.5 Safety Requirements for Material Hoists
A10.6 Safety & Health Program Requirements for Demolition Operations
A10.7 Safety Requirements for Transportation, Storage, Handling & Use of Commercial
Explosives & Blasting Agents
A10.8 Safety Requirements for Scaffolding
A10.9 Safety Requirements for Concrete & Masonry Work
A10.10 Safety Requirements for Temporary & Portable Space-Heating Devices
A10.11 Safety Requirements for Personnel & Debris Nets
A10.12 Safety Requirements for Excavation
A10.13 Safety Requirements for Steel Erection
A10.15 Safety Requirements for Dredging
A10.16 Safety Requirements for Tunnels, Shafts, & Caissons
A10.17 Safe Operating Practices for Hot Mix Asphalt (HMA) Construction
A10.18 Safety Requirements for Temporary Floor Holes, Wall Openings, Stairways &
Other Unprotected Edges
A10.19 Safety Requirements for Pile Installation & Extraction Operations
A10.20 Safe Operating Practices for Tile, Terrazzo, & Marble Work
A10.22 Safety Requirements for Rope-Guided & Non-Guided Workers’ Hoists
A10.24 Roofing Safety Requirements for Low-Sloped Roofs
A10.25 Sanitation in Construction
A10.26 Emergency Procedures for Construction & Demolition Sites
A10.27 Safety Requirements for Hot Mix Asphalt Facilities
A10.28 Safety Requirements for Work Platforms Suspended from Cranes or Derricks
A10.31 Safety Requirements, Definitions, & Specifications for Digger Derricks
A10.32 Fall Protection Systems for Construction & Demolition Operations
A10.33 Safety & Health Program Requirements for Multi-Employer Projects
A10.34 Protection of the Public on or Adjacent to Construction Sites
A10.38 Basic Elements of an Employer’s Program to Provide a Safe & Healthful Work Environment
A10.39 Construction Safety & Health Audit Program
A10.40 Reduction of Musculoskeletal Problems in Construction
A10.42 Safety Requirements for Rigging Qualifications & Responsibilities
A10.44 Control of Energy Sources (Lockout/Tagout) for Construction & Demolition Operations
A10.46 Hearing Loss Prevention for Construction & Demolition Workers
A10.47 Work Zone Safety for Highway Construction
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
Additional ANSI/ASSE Standards
Z359 STANDARDS
• Z359 Fall Protection Code 2.0
• Z359.0 Definitions & Nomenclature Used for Fall Protection & Fall Arrest
• Z359.1 Safety Requirements for Personal Fall Arrest Systems, Subsystems & Components
• Z359.2 Minimum Requirements for a Comprehensive Managed Fall Protection Program
• Z359.3 Safety Requirements for Positioning & Travel Restraint Systems
• Z359.4 Safety Requirements for Assisted-Rescue and Self-Rescue Systems, Subsystems & Components
• Z359.6 Specifications & Design Requirements for Active Fall Protection Systems
• Z359.7 Qualification & Verification Testing of Fall Protection Products
• Z359.12 Connecting Components for Personal Fall Arrest Systems
• Z359.13 Personal Energy Absorbers & Energy-Absorbing Lanyards
A1264 STANDARDS
• A1264.1 Safety Requirements for Workplace Walking/Working Surfaces & Their Access; Workplace
Floor, Wall & Roof Openings; Stairs & Guardrails Systems
• A1264.2 Standard for the Provision of Slip Resistance on Walking/Working Surfaces
• A1264.3 Technical Report: Using Variable Angle Tribometers (VAT) for Measurement of the Slip
Resistance of Walkway Surfaces
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
ADDITIONAL STANDARDS
• Z15.1 Safe Practices for Motor Vehicle Operations
• Z117.1 Safety Requirements for Confined Spaces
• Z244.1 Control of Hazardous Energy—Lockout/Tagout & Alternative Methods
• Z390.1 Accepted Practices for Hydrogen Sulfide Safety Training Programs
• Z490.1 Criteria for Accepted Practices in Safety, Health, & Environmental Training
• Z590.2 Criteria for Establishing the Scope & Functions of the Professional Safety Position
• Z590.3 Prevention through Design: Guidelines for Addressing Occupational Hazards & Risks in Design
& Redesign Processes
• ANSI/ASSE/ISO Risk Management Standards Package
Standards are available in hard copy or electronic format.
For a full list of standards and historical standards that ASSE has to offer, please visit our website at
www.asse.org or contact customer service at 847.699.2929 or customerservice@asse.org.
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT
A S
S E
--``,`,``,``,`,````,``,,`,,,`,`-`-`,,`,,`,`,,`---
Copyright American Society of Safety Engineers
Provided by IHS under license with ASSE/SAFE
No reproduction or networking permitted without license from IHS
Printed in U.S.A.
Licensee=Fermilab Research Alliance LLC/5970717001
Not for Resale, 05/07/2014 02:34:07 MDT