DATA RESULT A (1-2) B (2-3) DURATION (Days) 2 4 C (3-4) 2 D (4-5) E (5-6) F (5-7) G (7-8) H (8-9) I (9-12) J (8-10) K (10-13) L (13-16) M (16-19) N (12-15) O (9-11) P (11-14) Q (15-18) R (14-17) S (17-20) T (19-21) U (21-22) 1 1 6 1 5 1 8 1 3 2 6 2 2 1 3 3 2 3 ACTIVITY JOB DESCRIPTION A. Clearing, Lay Outing, and Staking B. Foundation, Wall footing and Septic Tank Excavation C. Fabrication and Installation of Forms and Rebars for Foundation and Wall footing D. Pouring of Concrete for Foundation and Wall footing E. Laying of CHB and pouring of concrete for Septic tank F. Fabrication and Installation of Forms and Rebars for Column G. Pouring of Concrete for Column H. Laying of CHB for Walls I. Backfilling J. Fabrication and Installation of Forms and Rebars for Roof Beams K. Pouring of Concrete for Roof Beam L. Fabrication and Installation of Trusses and Purlins M. Laying of G.I sheet and accessories N. Plastering of Walls, Columns, and Beams O. Fabrication and Installation of Forms and Rebars for Floor Slab P. Pouring of Concrete for Floor Slab Q. Installation of Doors and Windows R. Installation of Ceiling S. Installation of Electrical and Plumbing Fixtures T. Tile Works U. Paint Works and Finishes PATH TOTAL DURATION A-B-C-D-E-U A-B-C-D-F-G-H-0-P-R-S-U A-B-C-D-F-G-H-I-N-Q-U A-B-C-D-F-G-J-K-L-M-T-U 13 33 34 35 DATA SHEET ACTIVITY DURATION ES EF LS LF TF FF A (1-2) B (2-3) C (3-4) D (4-5) E (5-6) 2 4 2 1 1 0 6 1 5 1 8 1 3 2 6 2 2 1 0 3 3 0 2 3 0 2 6 8 9 10 9 15 16 21 16 24 25 28 22 21 23 28 29 25 28 31 30 32 2 6 8 9 10 10 15 16 21 22 24 25 28 30 28 23 25 29 29 28 31 31 32 35 0 2 6 8 31 32 9 15 16 24 16 24 25 28 25 22 24 31 32 26 29 32 30 32 2 6 8 9 32 32 15 16 21 25 24 25 28 30 31 24 26 32 32 29 32 32 32 35 0 0 0 0 22 22 0 0 0 3 0 0 0 0 3 1 1 3 3 1 1 1 0 0 0 0 0 0 0 22 0 0 0 0 0 0 0 0 0 0 0 0 3 0 0 1 0 0 Dummy (6-21) F (5-7) G (7-8) H (8-9) I (9-12) J (8-10) K (10-13) L (13-16) M (16-19) N (12-15) O (9-11) P (11-14) Q (15-18) Dummy (18-21) R (14-17) S (17-20) Dummy (20-21) T (19-21) U (21-22) CRITICAL ACTIVITY ҉ ҉ ҉ ҉ ҉ ҉ ҉ ҉ ҉ ҉ ҉ ҉ ҉ MILESTONE CHART ACTIVITY JOB DESCRIPTION STARTING TIME COMPLETION TIME A Clearing, Lay Outing, and Staking Foundation, Wall footing and Septic Tank Excavation Fabrication and Installation of Forms and Rebars for Foundation and Wall footing Pouring of Concrete for Foundation and Wall footing Laying of CHB and pouring of concrete for Septic tank Fabrication and Installation of Forms and Rebars for Column Pouring of Concrete for Column 08-Aug-17 09-Aug-17 10-Aug-17 13-Aug-17 14-Aug-17 15-Aug-17 16-Aug-17 17-Aug-17 18-Aug-17 18-Aug-17 18-Aug-17 23-Aug-17 24-Aug-17 24-Aug-17 Laying of CHB for Walls 25-Aug-17 29-Sep-17 Backfilling Fabrication and Installation of Forms and Rebars for Roof Beams Pouring of Concrete for Roof Beam Fabrication and Installation of Trusses and Purlins Laying of G.I sheet and accessories 30-Aug-17 30-Aug-17 25-Aug-17 01-Sep-17 01-Sep-17 02-Sep-17 03-Sep-17 05-Sep-17 04-Sep-17 04-Sep-17 Plastering of Walls, Columns, and Beams Fabrication and Installation of Forms and Rebars for Floor Slab Pouring of Concrete for Floor Slab 03-Sep-17 08-Sep-17 03-Sep-17 04-Sep-17 05-Sep-17 06-Sep-17 Installation of Doors and Windows 06-Sep-17 06-Sep-17 Installation of Ceiling Installation of Electrical and Plumbing Fixtures Tile Works 06-Sep-17 08-Sep-17 09-Sep-17 11-Sep-17 05-Sep-17 06-Sep-17 Paint Works and Finishes 11-Sep-17 13-Sep-17 B C D E F G H I J K L M N O P Q R S T U