Preliminaries: The Contractor has been contracted to supply and lay 30km of HDPE pipeline (“the Works)”. HDPE Pipeline will fall under the definition of “Materials” pursuant to SubClause 1.1.5.3. Liability: Under the Red Book 1999, the Contractor has an obligation to remedy any defects in the work (Sub-Clause 4.1). Furthermore, Sub-Clause 4.9 puts an obligation on the Contractor to institute quality assurance (QA) systems to demonstrate compliance with the requirements of the Contract and further provides that compliance with the QA system does not relieve the Contractor of any of his duties, obligations or responsibilities under the Contract. Therefore, despite the third-party inspection agency approving the pipes, the Contractor is still under a duty to carry out his own testing in order to comply with SubClause 4.9 as well as Sub-Clause 7.1 (the Contractor shall carry out the production and manufacture of Materials in a proper workmanlike and careful manner). The aforementioned scenario does not specifically state that the Contractor implemented any such system. Therefore he will be liable for failure to comply with Sub-Clause 4.9 and liable to remedy the defects as a result thereof. Furthermore, under Sub-Clauses 7.3 and 7.4, the Employer is entitled to conduct various activities including inspections and testing and Sub-Clause 7.3, in particular, states that no such activities relieves the Contractor from any obligation or responsibility. Therefore, the Employer should be advised that despite the Employer’s Personnel approving the pipes, the Contractor is still under an obligation to carry out the Works in accordance with the Contract (Sub-Clause 7.1). Therefore, the Contractor is still under a duty to suitably supply and lay the pipes in order to execute the Works. Actions available to the Employer: Pursuant to Sub-Clause 7.5 if, as a result of any inspection or testing etc., any Materials etc. is found to be defective etc., the Engineer may reject Materials by giving notice to the Contractor. Following same, the Engineer may instruct the Contract to remedy any defects within a certain time period (7.6). The Employer should further be advised that if the on-site tests are classified as re-tests (Sub-Clause 7.5), the Employer is entitled to recover the costs of same from the Contractor ad should therefore issue a 2.5 notice as soon as practicable (i.e. between months 16-18). The Employer should also bear in mind that if the Contractor fails to remedy the defect after a notice is issued under Sub-Clause 7.5 [Rejection ] or Sub-Clause 7.6 [Remedial Work ], within 28 days after receiving it, the Employer is entitled to terminate under sub clause 15.2. However, practically speaking, from the scenario it seems that if the Contractor places a new order, it will take approximately 8 months to reach country A and 2 months to lay same. Therefore, if the Contractor is to be given a reasonable opportunity to remedy the defects and a notice (Sub-Clause 7.5 [Rejection ] or SubClause 7.6 [Remedial Work ]) is given in month 16 then in or about months 26-28, the Contractor will be able to remedy the defects. Therefore, the Employer should also be advised that if the remedial works done by the Contractor results in delay to the Completion Date, he should also issue a 2.5 notice in respect of delay damages (SubClaus 8.7) , as the Contractor will not be entitle to an EOT in the circumstances. Lastly, since the Contractor has disputed its liability and has not taken any steps since the issue of the notice within 28 days, the Employer is entitled to terminate pursuant to SubClause 15.2. Furthermore, the said dispute will be considered a dispute for which the Employer should issue a 2.5 notice as soon as practicable and invoke the procedure to the DAB.