Sand Gravel Cement CONCRETE MIX 4:2:1 4.5M³ CONCRETE MIX RATIO: 4:2:1 Cement: 1/7 x 4.5m³/0.023=0.643/0.023=27.95 bags=28 bags Sand: 0.0643x2=1.29m³ round up 1.5m³ Gravel: 0.0643x4=2.57m³ round up to 3m³ Mix gravel: 1.5m³+2.57m³=4.5m³ STEEL ROD LAP Example: D12 bars in ring beam Formula given Note: steel rods are 6 meters in length, there they need to join by overlapping 2x24.8 =49.6m (Without lap) 49.6÷6=8.2 i.e. 8 laps Full length of steel rod 40dx12=480mm or 0.48m 8x0.48m=3.84m 24.9-(0.05+0.05) =24.8 Standard lap Length 49.6+3.84=53.44 =54meters (with lap lengths added) Prepared by Andrew Araha 50mm cover SLUMP TEST (CONCRETE) Process; 1. 2. 3. 4. 5. Ramp 25 times, refill and compact 25 times, refill cone 25 times Pour it and place bucket beside it Measure the distance between that the concrete fall and height of bucket, If the distance is 80mm, the concrete is 20mpa Bucket that is used to mix the concrete 80mmm Measure the distance between highest point of concrete and the height of bucket, if your measurement is 80mm, then your concrete mix is right at 20 MPa (required) Concrete poured out of mixing bucket or cone Prepared by Andrew Araha 17 MPA MORTAR TO BLOCK WORK Mortar Mix Ration: 3:1 (4 parts) 10mm thick mortar bed 150mm 200mm 400mm 200mm E.g.: Number of concrete blocks: 1500 blocks (150mm or 6” Blocks) 0.6x0.2x0.01=1.2x10-03 1500x1.2x10-03=1.8m3 =2m3 Mortar Mix Ratio: 3:1 Cement: 1/4x2/0.023=0.5/0.023=21.74=22 bags (40kg bag cement) Sand: 0.5x3=1.5m3 of sand Prepared by Andrew Araha BLOCK WORK CORE FILL CONCRETE ESTIMATE Prepared by Andrew Araha