UMTS_RNS_I_02_20090530
Node B Equipment Survey Process and
Environmental Acceptance
ZTE University
Content
Overview
Project Survey Process
Project Environment Survey Guide
Node-B (NB09) Project Survey Guide
Quality Control of Project Survey
Overview




Project survey is the initial stage of the whole project.
“Well begun is half done.”
It has direct influence on every link of the project
afterwards.
Introduction


Purpose: To provide normalized instructions on the
process, item and method of the project survey; to
offer a uniform survey standard to ensure good
preparation; and to make sure the project survey
plays its due role
Contents: Process, steps, methods, and filling in
forms
Overview

Project survey:
 Ensures accurate production scheduling and timely delivery
according to contract.
 Is the original basis for data configuration and debugging of
production lines.
 Is the basis of project design.
 Is the original material for the completion report.
 Is part of normalized project management.

Conducting no project survey, or wrong project survey, will result in:
 Delay in scheduling and production, and error in data
configuration.
 Delay in delivery, with excesses, shortages and omissions.
 Project suspension and material supply delay, so that the
installation personnel can do nothing but wait, and there is no
installation solution confirmed by both parties, possibly causing
changes of customer requirements, reworking, and refusal of
acceptance.
 Lack of original materials in the completion report.
 Lack of links in normalized project management.
Content
Overview
Project Survey Process
Project Environment Survey Guide
Node-B (NB09) Project Survey Guide
Quality Control of Project Survey
Project Survey Flowchart
Start
Preparing for
project survey
Making project survey
plan
Project Survey
Guide
Conducting field project survey and
first environmental acceptance
Producing survey
documents
No
Guide for Project
Survey Report Review
Reviewing
the survey
Qualified?
Yes
Handling
documents
End
Project Survey
Plan
Contract Problem
Feedback
Project Survey
Report
Environmental
Acceptance Report
Review Form of
Project Survey
Report
Description of Project Survey Process

Preparing for Project Survey



Purpose: To ensure smooth project survey
Person in Charge: Project survey engineer
Responsibilities:



1. Accepting tasks, receiving materials, and
understanding requirements
2. Taking charge of consultation, understanding, and
communication
3. Keeping in touch with the customer to know on-site
situations and identify conditions
–
–



Actions to take under poor survey conditions
Actions to take under good survey conditions
4. Drafting a Project Survey Plan
5. Making survey tools and meters ready
6. Carrying survey documents
Project Survey Process

Making Project Survey Plan




Purpose: To conduct planned project survey
Person in Charge: Project survey engineer
Output document: Project Survey Plan
Responsibilities:



Holding a project survey briefing
Making a Project Survey Plan
Being ready for carrying out the project survey
Project Survey Process

Conducting Field Project Survey and First
Environmental Acceptance




Purpose: To ensure that the field survey meet
specifications
Person in Charge: Project survey engineer
Input Document: Project Survey Guide
Responsibilities:




Conducting field survey, with the customer involved, to
record on-site information and data
Conducting first check of equipment operating
environment
Defining installation environment requirements
Knowing preparations of both parties for the project
Project Survey Process

Producing Survey Documents




Purpose: To ensure production debugging and accurate delivery, and to guide
project construction and commissioning, serving as the basis of producing
project design documents
Person in Charge: Project survey engineer
Output document: Project Survey Report (Scheduling & Delivery Data), Project
Survey Report (Project Design Information), Project Survey Report
(Commissioning Data), Environmental Acceptance Report, and Contract
Problem Feedback
Responsibilities:





Collating and filling in survey data according to the requirements specified in
Project Survey Guide; signing in the Project Survey Report and in the First
Environmental Acceptance column of the Project Survey Report after both the
customer and ZTE reach an agreement on the results of the survey and
environment acceptance
Communicating and negotiating with the customer, asking them for advice to
reach an agreement, and listing important things into the project survey
memorandum
Providing the customer with a copy of the documents
Filling in the Contract Problem Feedback to help the business manager and the
customer solve problems upon discussion if the result of the survey does not
conform to the contract
Submitting the Project Survey Report
Project Survey Process

Reviewing the Survey
 Purpose: To ensure the integrity, compliance, and
correctness of the project survey data
 Person in Charge: Project survey assessment engineer
 Input Document: Guide for Project Survey Report Review
 Output document: Review Form of Project Survey Report
 Responsibilities:





Assessing the integrity, compliance, and correctness of the
Project Survey Report
Filling in the Review Form of Project Survey Report
Revising the survey documents in any unqualified Project
Survey Report, and repeating field survey if necessary until it
meets the requirements
Submitting the qualified Project Survey Report to project
survey engineer for filing
Submitting the Review Form of Project Survey Report to
project survey engineer for filing
Project Survey Process


Handling Documents
Purpose: To file the survey results and provide them to the
departments that need them
 Person in Charge: Project survey engineer/document controller
 Responsibilities:
 SendingProject Survey Tasks,Project Survey Plan,Project Survey
Report (Scheduling & Delivery Data), Project Survey Report
(Project Design Information), Project Survey Report
(Commissioning Data), Environmental Acceptance Report, Survey
Problem Feedback,and Review Form of Project Survey Report to
document controller for filing
 Submitting Project Survey Report (Scheduling & Delivery Data) to
the involved Planning Department of the Product Division
 Submitting Project Survey Report (Project Design Information) to
project design manager
 Submitting Project Survey Report (Commissioning Data) to
commissioning engineer
 Submitting Environmental Acceptance Report to project
supervisor for a second environmental acceptance
Content
Overview
Project Survey Process
Project Environment Survey Guide
Node-B (NB09) Project Survey Guide
Quality Control of Project Survey
Requirements for Equipment Room Environment

Basic Environment of Equipment Room






High temperature, heavy dust, harmful gases, explosives, low air pressure,
strong vibration or noise, and high-voltage electrical equipment
The equipment room must be built at the location that meet the engineering
design requirements of the communication equipment. A long-term view should
be taken before construction. Do not relocate the equipment room unless
necessary. Durability should be considered to avoid frequent renovations. The
equipment room must be fireproof and shockproof.
Construction, structure, heating, ventilation, power supply, lighting and fire
protection are required.
MPT specifications must be followed.
The equipment room should be designed for the convenience of the cabling
and daily maintenance of the signal cable and power cable, to reduce cabling
cost and communcation failure and improve working efficiency.
General Information of Equipment Room




Location of equipment room
Type of equipment room
Route for equipment to enter the equipment room
Equipment unloading area
Working Environment Survey



Temperature, Humidity and Daylighting of Equipment Room
 Short-term working condition (temperature): -5C~+55C. A
temperature between +15℃~+30℃ is always
recommended.
 Short-term working condition (humidity): 20%~90%. A
humidity between 40~65 is always recommended.
 Direct sunlight should be avoided. There should be no glare.
Generally, the equipment room is lighted by fluorescence
lamps. For an equipment room where a power failure
frequently occurs, an emergency light should be installed at
a proper location.
Survey Description:
Generally, Node-B equipment rooms are unattended, so
fluorescence lamps are used for lighting.
Indoor Environment Survey

Equipment Room Floor and Fire Protection






Attention!
Antistatic raised floorboards or antistatic terrazzo should be laid in the
equipment room. Conductive floorboards should be used instead if raised
floorboards are unavailable. Static grounding must be performed for conductive
or raised floorboards, which should be connected to a grounding device
through a current-limiting resistor and a connecting wire.The resistance of the
current-limiting resistor should be 1MΩ.
Survey Description:
If antistatic floorboards are used in the equipment room, the floor height should
be checked.
Doors/Windows/Walls of Equipment Room





The bearing capacity of the equipment room floor should be higher than
450kg/m2.
The equipment room must be equipped with appropriate fire fighting devices,
such as several dry powder fire extinguishers.
The door should be over 2.0 m high and over 1 m wide.
The doors and windows must be sealed with anti-dust rubber strips. It is
recommended to use tightly sealed double-glass windows.
The walls and the ceiling should be free from pulverization, dust and peeling.
Decorative materials applied on the walls should be fire-retardant.
Survey Description:
There should be some space on the walls because wall-mounting DDFs or
ODFs are requied sometimes.
Indoor Environment Survey




Cabling Routes and Reserved Holes
The amount, location and size of hidden pipes, troughs and
holes reserved in the equipment room should fit various cables
and follow the engineering design. Damp-proof measures
should be taken for all troughs, with edges and corners well
trimmed. Lighting and power cables should be laid in a hidden
way.
Check to see if there is a hole for the antenna feeder system to
enter the equipment room. If no, check whether such a hole
can be made. The position and size of the hole must be
marked.
Construction Power Supply Requirements
 All equipment rooms should be equipped with 220V/2000W
power supply for construction. Multifunctional sockets with
both two-pin and three-pin jacks should be provided.
 Survey Description:
 An AC power supply is required during construction. Check
the voltage and frequency of the power supply, and note
the socket type (in the form of picture).
Indoor Environment Survey

Equipment Room Air Conditioning

An air conditioning system should be installed in the equipment room.

The heat radiation in the equipment room and the refrigerating output of the air
conditioning can be calculated as follows:

1. Heat radiation of the equipment: Q1=0.82VA (kcal/h)
– Where:
– Q1 is the head radiation of the equipment.
– V is the DC power supply voltage (V).
– A is the average power consumption current (A).
– The value 0.82 is the product of 0.86 (the scaling factor for converting every
watt of electrical energy into heat energy) and 0.95 (the scaling factor for
converting electrical energy to heat energy in the equipment room).

2. The refrigerating output of the equipment room: Q2=S×150 (kcal/h)
– Q2: The refrigerating output of the switching room
– S: The area of the switching room (M2)
– 150: The parameter for converting room area to refrigerating output
(Kcal/h×M2)

3. The refrigerating output of the air conditioning (actual capacity): Q=Q1+Q2

Survey Description:

Different models of equipment has different requirements on ambient temperature and
humidity. For detailed information, refer to the corresponding equipment technical manuals.
Generally, it is required to install an air conditioning system in the equipment room. If an air
conditioning system exists, the power of the air conditioning and the heat radiation of the
existing equipment should be noted during survey. If the existing air conditioning system
cannot meet the requirements of the new equipment, additional air conditioners are
required. The air conditioners should run automatically once powered.
General Information of Antenna Feeder Plane

Antenna feeder plane: the surface on which the
outdoor antenna feeder system is installed
 Survey Items:
 Rooftop
 Bearing capacity of the antenna feeder plane
 Ways to reach the antenna feeder plane
 Pole-mounted mode
 Tower-mounted mode
 Maximum wind speed
 Weather conditions
 Height of the antenna feeder plane
 Electromagnetic Environment
Outdoor Auxiliary Facilities

Lightning-Protection Grounding
 Joint lightning-protection grounding is used, with a
grounding resistance of no higher than 5Ω.
 Outdoor cabling racks, poles, and towers


Grounding bar of lightning-Protection Ground



Lightning-Protection grounding principle, length of the
grounding cable, grounding mode, and rust prevention
Functions and installation position
Survey Description:
The principle for BS equipment grounding is to make indoor
grounding and outdoor grounding separately. If the customer
cannot provide outdoor grounding bars, a note should be
written during the survey to say that the grounding bars will be
provided by ZTE. Generally, one site provides one outdoor
grounding bar. Outdoor grounding bars are directly connected
to outdoor cabling racks or lightning-protection networks.
Outdoor Auxiliary Facilities

Tower
 Requirements:
 A tower is required if a tower-mounted
antenna is used.
 Tower provider
 The design and instillation should
meet the telecommunication system
specifications.
 160KM/H
 Professional tower provider
 The tower must be grounded and
lightning-protected according to
technical specifications.
 The grounding resistance of the tower
must meet the requirements.
 The installation height of the lightning
arrester must meet the requirements.



Survey items:
Tower space
Isolation from the existing
antennas
 Spatial separation used
 Feeder routing
 Weight bearing and height
The antenna must be within the 45-degree protection range of the lightning
arrester.
Attention!
Outdoor Auxiliary Facilities

Pole








A pole is used for rooftop antenna installation.
The pole height should meet wind and ightning
protection requirements.
Each pole should be connected to the lightning belt
separately, and should be rust-proof and corrosionproof.
Survey Description:
Pole diameter: 60 mm or above
Accessory: lightning arrester
Protective angle of the lightning arrester
The length and specification of the pole's grounding
cable should be checked during the survey.
Content
Overview
Project Survey Process
Project Environment Survey Guide
Node-B (NB09) Project Survey Guide
Quality Control of Project Survey
Survey of Equipment Installation Information


Node B (B8200, BS8800) supports back-to-wall
installation.
Cabinet Placement


Attention!
The commissioning side of the equipment should be
no less than 1.2 m away from other objects in front.
Survey Description:


Enough space in all directions should be considered
in cabinet positioning (depending on cabinet model). If
the cabinet supports back-to-wall installation, small
space or no space should be reserved in the back.
For cabinets that support back-to-wall installation: If
there is enough space in the equipment room, a
distance of 40-50 cm from the wall is recommended in
the back.
Survey of Equipment Installation Information
0.40.5m
1m
1m
1.2m
Survey of Equipment Installation Information

Area of Equipment Room


There should be enough space in the equipment
room for cabinet installation. The area of the
equipment room should be larger than the base area
of the cabinet, being equal to the sum of the base
area and the required space in the front/back of the
cabinet.
Enough space should be reserved for the main
equipment, auxiliary equipment, and capacity
exapnsion.
Survey of Equipment Installation Information

Equipment Room Size Measurement
 Measure the size and net height of the equipment room.
 Measure the positions and dimensions of the existing
equipment.

The net height refers to the vertical distance from the beam
and air duct to the antistatic floor surface.
 The net height should be no less than 2.5 m for upward
cabling.
 The net height should be no less than 2.2 m for downward
cabling if antistatic floor is used.
The Node B equipment room has less demanding
requirements than the central equipment room in terms of net
height.
Attention!

Survey of Indoor Auxiliary Facilities

Cabling Rack




The equipment room should be equipped with upward
cabling racks if upward cabling is used. Generally, the
customer should provide cabling racks and finish
installing them before rack (cabinet) installation.
The cabling racks should be about 2 m high and 300
mm~600 mm wide. The capacity planned for terminal
offices should be considered when determining the
rack width.
Survey Description:
If the customer cannot provide indoor cabling racks,
the length and installation mode (ceiling-mounted or
bracket-mounted) of the required cabling racks, as
well as the length and specification of the grounding
cables, should be surveyed.
Survey of Indoor Auxiliary Facilities

DC Power Supply Equipment
 Generally, a -48V DC power supply system should be provided by
the customer. The power supply must meet the power requirement
of the equipment, and provide surplus power for capacity
expansion.
 Batteries should be provided in the places where a power failure
often occurs. The battery capacity should be selected according to
the duration of power supply. Generally, a battery should have a
capacity of four hours' power supply.
 Survey Description:
 The power consumption of ZXWR NB09 in full configuration is
2,700 W. If the DC power supply equipment is provided by ZTE, a
power supply survey is required.
 The survey report template is provided by the Mobile Business
Department. The survey should focus on the placement of the
power supply equipment and the batteries, and the specification
and length of the AC power cable from the AC power supply
system to the DC power supply system.
 ZXWR NB09 requires a DC voltage range of -57V~ -40V.
Survey of Indoor Auxiliary Facilities

AC Power Supply System












Single-phase 220V or 3-phase 380V AC power supply should be used.
Preferably, two separate mains should be used to ensure reliable power supply.
Generators should be provided in the places where a power failure often occurs.
An AC power distribution box or a switch box should be provided. The AC
power supply system should be safe and reliable.
Other Requirements of Power Supply System:
The primary power supply system should have an alarm device, which will
gives visible and audible alarm signals if the power supply system is in
abnormal condition.
Power cables should be kept intact, and any joint is unacceptable.
Check to see if protective tubes should be used, and if signal cables will be laid
nearby.
An appropriate surplus length should be reserved for the power cables between
the AC power distribution box and the equipment.
Survey Description:
Special attention should be paid to the voltage, frequency, and capacity of the
AC power supply during the survey to see if they can meet the requirements.
The length of the AC power cable should also be measured.
If the customer asks ZTE to provide the AC power distribution box or the AC air
switch, such a requirement should be noted in the survey report, with
specifications and models specified.
ZXWR requires an AC voltage range of: 380 V±10% (3-phase power supply),
or  220 V±10% (single-phase power supply).
Survey of Indoor Auxiliary Facilities

AC Power Supply System












Single-phase 220V or 3-phase 380V AC power supply should be used.
Preferably, two separate mains should be used to ensure reliable power supply.
Generators should be provided in the places where a power failure often occurs.
An AC power distribution box or a switch box should be provided. The AC
power supply system should be safe and reliable.
Other Requirements of Power Supply System:
The primary power supply system should have an alarm device, which will
gives visible and audible alarm signals if the power supply system is in
abnormal condition.
Power cables should be kept intact, and any joint is unacceptable.
Check to see if protective tubes should be used, and if signal cables will be laid
nearby.
An appropriate surplus length should be reserved for the power cables between
the AC power distribution box and the equipment.
Survey Description:
Special attention should be paid to the voltage, frequency, and capacity of the
AC power supply during the survey to see if they can meet the requirements.
The length of the AC power cable should also be measured.
If the customer asks ZTE to provide the AC power distribution box or the AC air
switch, such a requirement should be noted in the survey report, with
specifications and models specified.
ZXWR requires an AC voltage range of: 380 V±10% (3-phase power supply),
or  220 V±10% (single-phase power supply).
Survey of Indoor Auxiliary Facilities

Digital Distribution Frame (DDF) and Optical Distribution Frame
(ODF)
 If the DDF is provided by ZTE according to the project
interface, ZTE should survey the DDF.
 Placement
 DDF specifications - ZTE specially provides a reference list
for model selection. Generally, rack-type or cabinet-type is
selected.
 The length of the grounding cable of the DDF
 75 ohms or 120 ohms.
 If the ODF is provided by ZTE according to the project
interface, ZTE should survey the ODF.
 Placement
 ODF specifications - ZTE specially provides a reference list
for model selection. Generally, rack-type or cabinet-type is
selected.
 The length of the grounding cable of the ODF
 Type of the Optical connector (optical ring flange)
Survey of Indoor Auxiliary Facilities

Transmission Equipment






ZXWR Node B supports multiple transmission modes:
Direct optical fiber connection
Direct 2M cable connection
SDH transmission-based connection
ZXWR Node B provides two transmission interfaces:
STM-1 and E1.
ZXWR Node B supports 75-ohm and 120-ohm
interfaces.
Survey of Indoor Cables and Materials
Attention!
注意!
– Make sure the installation positions and cabling routes of
the related equipment.
– General principles for cabling routes:
» It should facilitate the wiring of signal cables and
power cables and routine maintenance.
» It should make the lines as short as possible to avoid
detours.
» It should help reduce wiring costs and
communication failures.
– All cables must be kept intact, and any joint or transition
point is unacceptable.
– A 10% surplus length should be reserved for all cables.
Survey of Indoor Cables and Materials


Grounding Cables
Generally, the indoor grounding bar is installed on the lower part of the wall in the
equipment room.

The protective grounding cable of the rack: 35 mm2 multi-strand soft copper wire; the cable
length should be the focus during the survey.

The protective grounding cable of the indoor cabling rack: 35 mm2 multi-strand soft copper
wire; the cable length should be the focus during the survey.

The protective grounding cable of the DDF/ODF: 35 mm2 multi-strand soft copper wire; the
cable length should be the focus during the survey.

The protective grounding cable of the power supply equipment: 35 mm2 multi-strand soft
copper wire; the cable length should be the focus during the survey.

The protective grounding cable of the transmission equipment: 35 mm2 multi-strand soft
copper wire; the cable length should be the focus during the survey.

The grounding downlead from the indoor grounding bar to the grounding body in the
equipment room: 95 mm2 multi-strand soft copper wire, or 40 mm × 4 mm zinc-plated flat
steel; the cable length should be the focus during the survey.

Note: Whether the grounding cables described in points 2, 3, 4, 5, and 6 is provided by ZTE
or other companies should be made clear.
Survey of Indoor Cables and Materials

Transmission Cables



Different transmission modes require different transmission cables, which
should be selected during survey according to the applications.
The selection of transmission cables is specified in the Technical Proposal .
Optical fiber connection: Single-mode tail fibers



BII board: SC connector; opposite end: Being determined according to actual
applications, generally being FC connector
The number and length of tail fibers, as well as connector types, should be the
focus during the survey.
2M cables: Node B mostly uses 2M cables for transmission.






If Node B and RNC are in the same equipment room, direct connection is used
through 2M cables.
If Node B and RNC are not in the same equipment room, indirect connection is
used through 2M cables from Node B to transmission equipment, and then to
RNC.
Matching impedance: 75 ohms in China, 120 ohms abroad
Opposite connectors and connector types: Being provided by the DDF supplier
or transmission equipment supplier
Survey Focuses:
Matching impedance of 2M cables, number and length of 2M cables, and
opposite connector types
Survey of Indoor Cables and Materials

DC Power Cables

-48VDC racks

There are two types of DC power cables: -48V working grounding cable (GND) and -48V power
cable (-48V).

Focus during survey: diameter, specification, and length of power cables.

The cable diameter can be calculated as follows: S=∑I×2L/(×△U)

S: Cross section of power cables (mm2)

∑I: Total current

L: Effective length of the feeder (M)

△U: Permissible voltage of the feeder (v)

: Conductivity of the feeder

For copper core cables, =54.4,

For aluminum core cables, =34

Value range of △U:

From battery to DC power supply: △U≤0.2V

DC power supply: △U≤0.2V

From DC power supply to DC power distribution cabinet: △U≤0.8V

From DC power distribution cabinet to switch rack: △U≤0.4V

Power cable specifications:

1, 1.5, 2.5, 4, 6, 10, 16, 25, 35, 50, 70, 95, 120, and 185 (unit: mm2)

Generally, 25 mm2 cables are used as DC power cables for the racks; 35mm2 cables are used as
protective grounding cables for the equipment. Fire-retardant cables should be used.

A back-up power supply should be provided if there are two ways of separate DC power inputs.

-48V power cable: 25 mm2 multi-strand soft copper core power cable; fire-retardant; blue

-48V working grounding cable: 25 mm2 multi-strand soft copper core power cable; fire-retardant;
black

The length of the power cables should be the focus during the survey.

If the length exceeds 100 m, 35 mm2 fire-retardant, multi-strand soft copper core power cables
should be used instead.
Survey of Indoor Cables and Materials

AC Power Cables
 If ZTE provides the primary power supply equipment, it
should also provide the AC power cable from the primary
power supply equipment to the AC power distribution box.
 The length of the AC power cable from the primary power
supply equipment to the AC power distribution box should
be measured during the survey. Generally, a 16 mm2 fourcore fire-retardant cable is used. For more details, refer to
the survey report sumbitted by the primary power supply
equipment supplier.
 It is required to lay the AC power cable and other cables
separately, with a distance of over 150 mm away from each
other. If separate cabling is impossible, a shielding tube
must be used. The length of the shielding tube should be
noted during the survey.
Outdoor Installation Survey

Installation Position of Antenna


Main Feeder Routing


Installation height, position, and orientation
Check to see if the feeder routing is reasonable, if any
hidden danger exists, and if the installation is difficult.
Outdoor Cabling Rack


Measure the length of the required cabling racks
according to the cabling rack routing.
Check the length and Specifications of the grounding
cable of the cabling racks.
Outdoor Material Survey



Outdoor Materials:
Antenna, tower amplifier, feeder, jumper, and
grounding clip
Feeder clip and outdoor grounding bar
Lightning
arrester
Antenna (6 pieces;
directional)
Jumper (1/2"; 6 pieces)
Lightningprotection
grounding clip
Main feeder (7/8''; 6 pieces)
Equipment
room
Lightningprotection
grounding clip
Lightningprotection
grounding clip
Tower
Lightning
arrester
Cabling
rack
Jumper
1/2"; 6 pieces
Node
BTS
B
Cabinet
Outdoor Material Survey









Tower Amplifier
A jumper from the antenna to the tower amplifier, as well as a
jumper from the tower amplifier to the main feeder, should be
provided when configuring the tower amplifier. Currently,
ZXWR NB09 (V3) has no tower amplifier.
If a tower amplifier is planned, it should be noted during the
survey.
Jumper
The 1/2”super-flexible jumper has fixed length. By default, the
rack-top jumper is 2 m long, and tower-top jumper is 3 m.
Distribute the jumpers according to the site configurations
during survey.
Feeder
Measure the feeder length along the designed feeder routing.
Generally, the main feeder is 7/8'' feeder cable, or 5/4'' feeder
cable if the length exceeds 60 m.
Outdoor Material Survey

Grounding Cables
 Outdoor grounding bar: Check the number of the outdoor
grounding bars.
– Generally, ZTE distributes one outdoor grounding bar to each
site.

Grounding downlead of the outdoor grounding bar: 95 mm2
multi-strand soft copper wire, or 40 mm × 4 mm zincplated flat steel
– The cable length should be the focus during the survey.

Outdoor equipment grounding cable: the grounding cable
from the lightning arrester busbar to the outdoor grounding
bar
– 25 mm2 multi-strand soft copper wire; the cable length should be
the focus during the survey.

Grounding cable of pole or tower lightning arrester: 40×4
mm zinc-plated flat steel
– Check the cable length, which should be the total length. The
nearest grounding should always be made.
Outdoor Material Survey




Number of Main Feeder Grounding Clips
The number of the grounding clips depends on the
feeder length and routing.
Feeder length: 5 m, 20 m, 60 m, and〈60 m
Installation modes: On-tower, rooftop, and horizontal
cabling
Outdoor Material Survey




Feeder Clips
Triple feeder clip
Double feeder clip
The number of the feeder clips depends on the
feeder length.
Filling in Survey Forms






Purposes
To identify the environmental conditions, equipment installation,
cabling, and project tasks & responsibilities; to know all related
details; to make preparations for scheduling, delivery and field
installation.
Tasks
Completing the survey on environmental conditions, floor plan
of the equipment room, cabling, original debugging data, and
hardware installation interface.
Requirements
The environment conditions should be fully described. The
installation position of each equipment should be identified.
The number, length, and cabling route of every kind of cable
should be checked. The installation interfaces for both parties
should be identified.
Filling in Survey Forms-First Environmental
Condition Survey

1.Conduct the first environmental acceptance according to the
items specified in the Environmental Acceptance Report

2.For compulsory items, specified conditions must be
provided by the customer. For the conditions that are currently
not provided, a deadline should be negotiated by both parties.

3. For general items, it is unnecessary to "force" the customer
to meet the environmental conditions, but it is necessary to
explain the advantages/disadvantages to the customer. A
deadline should be negotiated by both parties if the customer is
capable of meeting such requirements.
Filling in Survey Forms-General Project Information












The project survey personnel should collect the following basic
information and fill in the cover pages of all Project Survey
Reports:
Contract No.
Party A's name
Party A's contact person
Tel/fax
Survey personnel
Tel/fax
The project survey personnel should collect the following basic
information and fill in the Site Information Forms of all Project
Survey Reports:
Site name
Equipmeng configurations
Project types (including new construction, capacity expansion,
and reconstruction)
Survey results and notes
Filling in Survey Forms-Scheduling and Delivery
Data

Collect scheduling and delivery data; fill in the Project Survey Report
(Scheduling & Delivery Data)







Attention!
The report should include such information as site name, configuration, floor
height, number of racks, and length of digital trunk cable, fire-retardant power
cable, grounding cable, optical fiber, and cabling rack.
Where:
There are two types of optical fiber interfaces: LC/PC - LC/PC and LC/PC FC/PC. Fill the selected type(s) in the report according to the survey results.
A 10% surplus length should be reserved for all cables.
All power cables must be fire-retardant, with 25 mm2 (for power cables) and 35
mm2 (for protective grounding cables) in cross section. If the length of a power
cable exceeds 100 m, a 35 mm2 power cable should be used instead. The
length of the grounding cable should be the total length of all grounding cables.
The Project Survey Report (Scheduling & Delivery Data) must be sent back to
the Planning Department of the Mobile Division.
Helping the Planning Department complete material clarification.
Filling in Survey Forms-Commissioning Data
Collect information about equipment installation & commissioning;
fill in the Project Survey Report (Commissioning Data)
 Description of Networking Structure Diagram Drawing





Actual logic networking topology
The networking structure diagram should be drawn according to the
technical agreement. Network topology should be confirmed by
signature. Any possible changes must be noted in the diagram.
Drawing requirements: The networking modes among all NEs and
networks, number of trunks, trunk type, signaling type, and number of
links should be drawn in the diagram.
Visio or AUTOCAD should be used for drawing.

Sometimes the diagram can be obtained from the pre-sales
support personnel or the technical proposal.
 Filling in the information about software installation and debugging




Some data is only available from the customer through negotiation.
Some data is only available from RNC through negotiation.
Some data is only available from network planning.
Such information should be filled in according to the actual
situations.
Filling in Survey Forms-Project Design Information

Collect information about equipment installation &
commissioning; fill in the Project Survey Report
(Project Design Information)
Filling in Survey Forms-Project Design Information
–






Description of Equipment Layout Drawing
The layout describes the planimetric position of the equipment in all equipment
rooms.
The dimensions and positions of all equipment, the distances between them,
and the reserved positions should be measured, marked and recorded
carefully and accurately.
Unnecessary changes must not be made once the equipment positions are
confirmed by both parties!
The customer must send a prior written notice to ZTE for any necessary
changes.
Drawing Requirements:
The size of the equipment should be marked in the layout.







The positions of ODF, DDF, transmission equipment, switching equipment and
access equipment should be provided in the layout.
Old and new equipment should be drawn differently (described by text, or
marked by bold or fine line).
The rack front, storey height, ceiling, and floor height should be marked.
The position and size of holes, doors and windows should be marked.
If the description is not clear by using a planar top view, a detail view can be
used instead.
Both sketch and formal VISIO diagram should be produced.
Copying this diagram is permitted.
Filling in Survey Forms-Project Design Information
– Description of Cable Route Drawing







It describes all cabling routes in the equipment room.
It shows all cabling routes and modes, as well as detailed
cabling facilities.
Unnecessary changes must not be made once the cabling
routes are confirmed by both parties!
If cabling facilities are not in position, their installation locations
should be identified, and then marked and noted in a sketch.
Drawing Requirements:
 The cabling route from the digital trunk cable to the DDF
should be marked.
 Different types of cables should be marked differently.
Both sketch and formal VISIO diagram should be produced.
Copying this diagram is permitted.
Filling in Survey Forms-Project Design Information




Installation and Cabling of Antenna Feeder System
It is the schematic diagram of antenna feeder installation.
Drawing Requirements:
 The tower position, antenna (including GPS antenna)
installation position, and parameters (such as tower height,
platform height, pole height, and lightning arrester height)
should be marked in the diagram.
 The installation mode of the omnidirectional antenna, as
well as the position and height of the lightning arrester,
must be indicated.
 The outdoor cabling rack routes should be drawn, with the
length of all feeder segments being marked.
 If the tower has not been installed yet, the customer should
provide the tower blueprint and the cabling design.
 All kinds of information can be marked in the diagram by
text.
Sketch, and formal AUTOCAD or VISIO diagram should be
produced.
Filling in Survey Forms-Project Design
Information


Construction Difficulty Description
It describes the construction for which ZTE is responsible. The purpose is to
provide a brief explanation for the convenience of the construction afterwards.





The outdoor cabling rack, feeder cabling, feeder window installation, and how
difficult it is to make a hole, should be described.
Equipment securing and indoor cabling rack positioning should be explained.
Equipment handling (including the route to reach the equipment room from the
ground, the highest floor that the cargo lift can reach, the distance for manual
handling, width limit of the handling route, and precautions) should be
described in detail.
Equipment Capacity Expansion Information
The capacity expansion information includes a basic information form and a
board slot layout. Fill in the form with the basic configurations of the
unexpanded equipment, making good preparations for the capacity expansion.



The cabinet type, height, color, shelf type, and wiring capacity of the equipment
specified in the current contract should be marked.
The existing board positions should be marked.
The required new cables and sub-shelves should be described in detail.
Filling in Survey Forms-Project Memorandum






Every report includes a memorandum.
Communication engineering is rather complicated,
with many issues being involved.
Extra, special, or unexpected problems or situations
will possibly happen.
All these issues should be recorded into the Project
Survey Memorandum.
Any special installation materials that are not
recorded in the Project Survey Report (Scheduling &
Delivery Data) should be included into the
memorandum.
The memorandum is very important. Forgetting to fill
in it will probably result in serious consequences.
Content
Overview
Project Survey Process
Project Environment Survey Guide
Node-B (NB09) Project Survey Guide
Quality Control of Project Survey
Quality Control of Project Survey





Quality is the center of any work.
The quality of the survey must be ensured.
The quality of the project survey should be ensured
in two ways:
Process quality
Document quality
Process Quality Control






Every step must be carried out according to the project survey
process.
Project-related information should be collected carefully.
Project requirements, including general and key tasks, should
be understood thoroughly.
The project survey process must be strictly followed. The
survey should be scheduled and planned reasonably to ensure
high efficiency.
The survey should be conducted together with the customer to
obtain accurate original information about the site and
understand special requirements and situations.
Countermeasures should be planned to avoid emergencies
during the survey.
Every possible resource should be fully used during the survey
based on a good cooperation with the local ZTE office.
Site-related data should be measured and reorded accurately.
All sites should be designed accurately to avoid delay or
waiting due to unconformity during construction.
Document Quality Control

Document reflects the quality of your work.
» Integrity: Ensure the integrity of the documents.
» Accuracy: Ensuer the accuracy of the documents.
» Timeliness: Ensure the timeliness of the documents.