Project Charter
Part I – General Information
(1) Project Title
Aimmal Office Complex and Parking Lot in Abu Dhabi
(2) Project Scope
Aimmal Corporation has its headquarters in Ajman, Arab Emirates. The project aims at
realizing new Aimmal offices in Abu Dhabi.
The offices will be located in the city centre. An underground parking lot will be built as well
as restaurants and a pied-a-terre for the Top Management of Aimmal.
(3) Project Manager
(3) Level of Authority
(4) Project Sponsor(s)
(5) Type of Project Sponsor
Massimo Longo
Full Decision And Spending Federico Lazzarin
Aimmal CEO
Authority
(6) Product Description /
The full complex is made of a tower in the city centre of Abu Dhabi. Besides the new
Deliverables
offices of Aimmal, a two-floor underground parking lot will be built.
A restaurant will be built in the ground floor. A second restaurant will be located in the
first floor of the building. Both restaurants will function as a canteen for the employees
and as a restaurant for visitors.
Abstract
At the last floor of the tower small pied-a-terre apartments will be located to host Aimmal
Management in case they need to attend evening meetings.
The internal lighting of the tower and the climate control has been designed by the
Novara snc. The whole system has been designed to have the lowest environment impact
thanks to computer controlled panels.
(7) Project Objectives
(8) Work Site
(9) Pre-assigned
Resources
Project deliverables are:
1. 70-metre office complex tower.
2. Two-floor underground parking lot with 400 spaces.
3. 20 pied-a-terre apartments for Aimmal Top Management.
4. Two restaurants at the ground floor and first floor for 500 seats each.
5. Computerized lighting and climate control system.
6. Maintenance plan of the complex.
The project is part of our strategic expansion plan in the arab countries. With this project
we also establish a strategic partnership with Novara snc. This collaboration will enhance
the chance of success in future project biddings thanks to their innovative system.
The overall infrastructure of the lighting system and climate control will be developed by
the DeCarlo spa. The project aims at developing a strong relationship with the DeCarlo
spa as well.
The site is located in Abu Dhabi (Hamdan Street).
Particular attention will be given to the relationship management with the project
sponsor and local stakeholders. Project personnel will be trained in order to maintain
correct behaviours with all local project stakeholders.
Mario Bianchi. Skilled Team Leader with long experience in the arab countries.
Livio Rossi. Project Planner with a deep knowledge of Primavera P6.
Two Liebherr cranes (280 HC-L 16/28 and 357 HC-L 18/32)
1
© Massimo Longo
Rev 1.0 20/12/2014
Template Ver. 1.0
(10) Stakeholders List
Name
Title
John Moore
Project Sponsor
Frank Underwood
Sub-contractor
Marco Grillo
Chief Architect
Paolo Burchio
Solar Radiation System Proj. Manager
Mohammed Abakir
Local Authority
(11) Summary Milestone Schedule
Description
Project Kick Off
Fundation Completion
Computerized lighting and climate control system
Offices Tower Handover
Parking Lots Handover
Restaurants Opening
(12) Summary Budget
Parking Construction $ 10M USD
Tower Construction $ 200M USD
Solar Radiation System $ 10M USD
Organization
Aimmal Corp.
Piling Company
Studio Novara s.n.c.
De Carlo s.p.a
Construction Government Office
Due Date
1st Feb. 2015
30th March 2015
1st March 2016
30th April 2016
30th May 2016
15th June 2016
TOTAL $ 320M USD
Contingency Reserve (%15) $ 48M USD
Management Reserve (%3) $ 10M USD
(13) Assumptions
(13) Constraints
th
Authorizations will not delay more than 30 days from
Project has to terminate before 30 June 2016 date of
request presentations.
Expo 2020 world presentation.
Payments will not be delayed.
Budget cannot exceed total contingencies.
No more than 15 non-working days due to adverse
Formal written communication will be in Arab and
climate conditions are considered.
English language
(14) High Level
1. Because there may be changes due the Foundations,the project may requires extra
Project Risks
work due to unstable terrain.
2. Because the Computerized lighting and climate control systems approval may
requires changes due to its innovative nature, Local Authority may require extra
information about it.
3. Because the Computerized lighting and climate control systems is the innovation for
the Company, it may require extra time and budget for testing and bug-fixing.
2
© Massimo Longo
Rev 1.0 20/12/2014
Template Ver. 1.0
Part II – Business Information
(15) Main Contract
(19) Stakeholders
Payments to be done 30 days from date of invoice.
Warranty on Deliverable is provided for 12 months after hand-over.
Liability is set to the value of the project budget.
All claims are to be settled through arbitrate within 3 months from notice.
With this project the expected revenue is set to about 20% the value of the project. In case
all contingencies are used this will be 10%.
With the success of this project it is expected that the Company will acquire 15% of the
construction market within the next 5 years.
John Moore. Aimmal Construction want to be the first real estate company in Abu Dhabi.
Frank Uderwood and its Dandy Constructions with this project want to develop its business
in the Arab countries.
Marco Grillo. They want to maintain the well established reputation with this project.
Marco Grillo and Paolo Burchio. They want to deploy their innovative system and open the
market in the Arab country.
Mohammed Abakir. Improve the beauty and majesty of the city towards Expo 2020
Communication Plan is to be defined according to stakeholder requirements. Because of
language barrier, communication will mainly be written.
Monthly status updates will be provided to stakeholders.
All key stakeholders are leading the project.
Reference to be provided following stakeholder requirements analysis.
Requirements
(20) Success Criteria
Success is to be measured according the following criteria:
Terms & Conditions
(16) Business Case
(17) Stakeholders Main
Expectations
(18) Stakeholders
Engagement
1.
2.
3.
4.
Value (40% at deliverable acceptance ,-5% for every $100K USD spent for rework
due to no-requirements adherence)
Quality (30% at deliverable acceptance, -3% for every $100K USD spent for rework
due to bad performance)
Budget (20% if no contingencies are used, 15% in case contingencies are used)
Schedule (10% if project delivers on time, +10%for any month earlier)
Part III – Organizational Information
(21) High Level Process
Improvement Plan
(22) Organizational
Process Definition
(23) Main Lessons
Learned Applied
(24) Tools & Templates
Project Technical Review meetings will be held on a monthly bases for lessons learned
analysis.
Kanban Board will be used to enhance communication in project teams.
New excavator technologies will be applied to reduce time and reworks.
Computerized lighting and climate control systems will be developed within the agile/scrum
methodology.
The project will be implemented within company ISO quality standards.
All procurement will be done through informal RFI and formal RFQ according to company
quality standard.
Contract Manager will be on-site.
Lessons from following projects have been analysed.
1. City Tower construction in Hong Kong.
2. Lloyds Tower in London.
The Team Leader will receive Primavera P6 training in order to understand the work done
by the Planner.
3
© Massimo Longo
Rev 1.0 20/12/2014
Template Ver. 1.0
Signature(s)
Project Sponsor(s)
Project Manager
_______________________
_______________________
Date:
Date:
__/__/____
__/__/____