Uploaded by Sophia Hui Li

PMP

advertisement
DESC9074 – Project Management
Assignment Brief
Matthew Gralton
Managing Director, Cadence Australia
1 September 2020
INSTRUCTIONS
Assignments must be typed (Arial font at a size of 11) on A4 paper. The first page must
be the POSTGRADUATE assignment cover sheet found in the Project Information
section. The submission must be signed to indicate that the assignment is the student’s
own work. Please note that Turnitin Software will be used to check the originality of each
submission.
For this Assignment, you must submit an electronic copy by Tuesday 17 November
2020, 11:59pm. The Assignment must be submitted via the Turnitin link.
Late, illegible and/or incomplete assignments may prejudice the marks awarded. Please
refer to the Faculty Handbook Section 3.0. If you experience short-term circumstances
beyond your control, such as illness, injury or misadventure, which affect your
preparation or performance in an assessment, you may be eligible for special
consideration.
Please go to the website for more information http://sydney.edu.au/students/specialconsideration-and-arrangements.html
2
CONSTRUCTION PROJECT
You are to use 70 Esplanade, Strahan, Tasmania, Australia as the basis to prepare a
fictional Project Management Plan (PMP).
Note that, excluding the site and project information provided, your project and any related
information can be entirely fictional (e.g. fictional builder, fictional client, fictional consultants,
and fictional assumptions).
Your fictional client is your lecturer, Mr Matthew Gralton who you can ask as many
project related questions as required over the 5 days of lectures to complete your PMP
DELIVERABLES
You are to prepare a Project Management Plan (PMP) for the project.
You will need to research relevant information and make educated
assumptions.
3
CONTENT GUIDELINES - Refer to information package item 6 “Project Management
Plan - Table of Contents”
Students are to prepare a PMP establishing the role of the Project Manager throughout the
life of the project.
The Table of Contents for the PMP has been designed in conjugation with the Learning
Outcomes to ensure the students have an understanding of the Learning Outcomes being
assessed.
The PMP is broken down into the following Headings and assessed in relation to how these
Headings and Sub Headings are articulated by the students throughout the PMP. Each
Heading (with included Sub Headings) will be assessed as 10% of the total mark.
4
› Introduction
› Risk Management
-
Purpose of Project Management Plan (PMP)
-
Risk Review
-
Project Overview and Site Information
-
Risk Analysis
-
Key Documents and Project Brief
-
Risk Reporting & Monitoring
-
Project Control Group Members
-
Work, Health & Safety Risk Management
-
PMP Document Control
› Time Management
› Resources Management
-
Project Team Organisation Chart
-
Program Milestones
-
Meeting Schedule
-
Project Program
-
Stakeholder Management
-
Program Reporting
-
Communications Management for: Client, Designers,
Authorities, Contractors, Suppliers and Stakeholders
› Cost Management
-
Project Budget
-
Cost Planning and Reporting
› Quality Management
-
Quality Objectives
-
Quality Management during Design & Construction
› Sustainability and Environmental Management
-
Environmental Objectives & Outcomes
-
Sustainability incorporated into the Design
-
Material Selection, Electrical, Mechanical, Water & Waste
-
Environmental Management during Demolition & Construction
› Procurement, Contract Selection & Management
-
Consultants
-
Contractors
-
Equipment & Suppliers
› Authority & Design Management
-
Design Team Structure
-
Authority Team Structure
-
Safety in Design
-
Design Management Structure
› Construction Management
-
Work, Health & Safety Management
-
Demolitions & Site Clearance Management
-
Construction Management
-
Fixtures, Fittings & Equipment Management
-
Completion, Commissioning, Handover & Defects
Management
5
NOTES
As a minimum, your Assignment is to include details relating to each Heading and Sub
Heading included on the attached example “Table of Contents”. All items in the “Table of
Contents” must be included in your PMP. Additional sections may be included as necessary.
The maximum page limit for the Assignment is 50 pages combined including text, diagrams
and images.
You are to assume that you have been engaged by the Client to Project Manage the consultant
appointment, design process, authority approval, contractor tender and appointment, and
delivery and handover of the project.
You are to make assumptions regarding consultant appointment as relevant to the scale and
type of project. These assumptions are to be listed within your PMP.
You are to make assumptions regarding Contractor appointment and form of contract in
accordance with the scope of the project and corresponding risk profile.
6
HISTORIC PROJECT INFORMATION
•
•
•
•
•
•
•
Site purchased December 2017
Architect, Civil and Hydraulic Engineer appointed May 2018 for the Development
Application submission
Planner appointed June 2018 for management of the Development Application
submission
July – November 2018: Development Application prepared
December 2018: Development Application submitted
May 2019: Project consented by West Coast Council
June 2020: Extension of time for DA consent granted until 3 May 2023
7
EXISTING CONSULTANTS
•
•
•
•
•
•
•
•
Site Surveyor
Planner
Architect
Civil and Structural Engineer
House Energy Rating Consultant
Geotechnical Consultant
Mechanical/Electrical/Hydraulic & Fire Consultant
Model Maker
CURRENT AUTHORITIES
•
•
•
•
•
Building Surveyor (Private Certifier)
West Coast Council, Tasmania
TAS Water
TAS Networks (Electrical)
National Broadband Network (NBN)
8
SITE INFORMATION
•
•
•
Existing shed to be demolished 500m2
and hardstand
Site area 1312m2
Site coverage 41%
BUILDING INFORMATION
•
•
•
•
•
•
•
Building length ~ 66 metres
Building height ~ 6.7 metres
Building depth ~ 8.2 metres
Floor to ceiling GF 2.7 metres
Floor to ceiling FF 2.85 metres
Southern unit GF 2.5 metres
Southern unit FF 2.8 metres
•
•
•
•
•
•
Glass façade 66 x 7 metres ~ 462 metres
Built form site footprint ~ 540m2
Total m2 usable space ~ 1000m2
4 x units ~ 128m2 each
1 x Southern unit ~ 360m2
Eastern hardstand area ~ 550m2
9
SERVICES & SUSTAINABILITY
•
PV cells on building roof, as per
Development Consent
•
Water tanks to harvest rain water
•
Electrical infrastructure for possible
future windmill
•
Possible Grey water re-use
•
Low maintenance building via material
selection
•
Off-site fabrication for key building
elements in factory environment
PROGRAM INFORMATION
August 2020
Project Manager appointment
September 2020
Consultant appointment and start up meeting
October – December 2020
Design development and procurement of Building Certificate
January – March 2021
Design document review and document coordination
April 2021
Finalise all documents “Approved for Construction”
May, June & July 2021
Tender, review and award main Contractor appointment
August 2021
Contractor mobilisation
September 2021 – Sept 2022
Construction and handover
10
INFORMATION PACKAGE
1. Google Maps site location
2. Site photographs
3. Site survey information
4. Project information
a) Consented Architectural Drawings
b) Consented Civil and Hydraulic Drawings
c) May 2019 West Coast Council Development Consent
d) Extension to Development Consent to 3 May 2023
5. Project Costs
6. Project Management Plan – “Table of Contents”
7. Postgraduate Assignment Cover Sheet to be included on front page of Assignment
11
1.
GOOGLE MAPS AND SITE LOCATION
12
13
2.
SITE PHOTOGRAPHS
14
15
16
3. SITE SURVEY INFORMATION
17
4. PROJECT INFORMATION
a) Consented Architectural Drawings
18
19
GROUND FLOOR PLAN 1:200
20
FIRST FLOOR PLAN 1:200
21
22
23
24
25
26
27
28
29
b) Consented Civil and Hydraulic Drawings
30
31
32
33
c) May 2019 West Coast Council Development Consent
34
35
36
d) Extension to Development Consent to 3 May 2023
37
5. PROJECT COSTS (Including GST at 10%)
LAND ACQUISITION & DEVELOPMENT CONSENT
AUTHORITY & BUILDING SURVEYOR FEES
Land acquisition and holding costs (spent)
$
400,000
Tasmania, West Coast Council
$
(TBA)
Development Application consent costs (spent)
$
119,913
TAS Water
$
(TBA)
Total
$
519,913
TAS Networks (Electrical)
$
(TBA)
National Broadband Network (NBN)
$
(TBA)
House Energy Rating ABSA / NatHERS Certification
$
2,239
Building Surveyor, Project Certifier (committed)
$
4,400
Total
$
(TBA)
Site Demolition (estimate)
$
50,000
Builder Procurement via Architect (actual)
$
19,800
Construction (estimate)
$
2,950,000
PROFESSIONAL FEES
1:200 Project Model Production (spent)
$
3,740
Architect (committed)
$
92,400
Structural / Civil Engineer (committed)
$
21,648
Geotechnical Engineer (committed)
$
3,300
Mechanical Engineer (committed)
$
10,890
Hydraulic Engineer (committed)
$
6,050
Electrical Engineer (committed)
$
10,450
Fire Engineer
$
(TBA)
Furniture, Fixtures and Equipment: FF&E (allowance)
$
300,000
Quantity Surveyor
$
(TBA)
Demolition & Construction Contingency @ 5%
$
150,000
Project Manager
$
(TBA)
Total
$
3,469,800
Other Consultants as required (estimate)
$
15,000
Consultant’s Construction Inspections (allowance)
$
150,000
GRAND PROJECT TOTAL
$
(TBA)
Professional Fees Contingency @ 5% (allowance
$
(TBA)
Total
$
(TBA)
DEMOLITION, PROCUREMENT, CONSTRUCTION & FITOUT
38
6. PROJECT MANAGEMENT PLAN – “TABLE OF CONTENTS”
›
›
›
›
›
›
Introduction
›
Risk Management
-
Purpose of Project Management Plan (PMP)
-
Risk Review
-
Project Overview and Site Information
-
Risk Analysis
-
Key Documents and Project Brief
-
Risk Reporting & Monitoring
-
Project Control Group Members
-
Work, Health & Safety Risk Management
-
PMP Document Control
›
Resources Management
Time Management
-
Project Team Organisation Chart
-
Program Milestones
-
Meeting Schedule
-
Project Program
-
Stakeholder Management
-
Program Reporting
-
Communications Management for:
Cost Management
-
Project Budget
-
Cost Planning and Reporting
›
Client, Designers, Authorities, Contractors, Suppliers
and Stakeholders
Authority & Design Management
Quality Management
-
Design Team Structure
-
Quality Objectives
-
Authority Team Structure
-
Quality Management during Design & Construction
-
Safety in Design
-
Design Management Structure
Sustainability and Environmental Management
›
Construction Management
-
Environmental Objectives & Outcomes
-
Sustainability incorporated into the Design
-
Work, Health & Safety Management
-
Material Selection, Electrical, Mechanical, Water & Waste
-
Demolitions & Site Clearance Management
-
Environmental Management during Demolition & Construction
-
Construction Management
Procurement, Contract Selection & Management
-
Fixtures, Fittings & Equipment Management
-
Consultants
-
Completion, Commissioning, Handover & Defects
Management
-
Contractors
-
Equipment & Suppliers
39
7. POSTGRADUATE ASSIGNMENT COVER SHEET (to be included on front page of Assignment)
40
Download