METHOD STATEMENT Sikafloor®-255 Screed 28.09.20 / V.3.1 / SIKA GCC / SIMON AMBAUEN THE ADDRESS HARBOUR POINT TABLE OF CONTENTS 1 Scope 3 2 2.1 2.2 2.3 Description and uses Description Products Characteristics/ advantages 3 3 3 3 3 System build-up 3 4 4.1 4.2 Substrate preparation Substrate pre-requisites Surface preparation 4 4 4 5 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 5.9 Application information Professional crew Temperatures Weather precautions Mixing Equipment Application of primer / bonding slurry Application of Sikafloor®-255 Screed mortar Treatment of joints Curing Wet on wet / thick bed tile applcation 6 6 6 7 7 8 8 11 11 12 6 Important Considerations 12 7 Health and safety recommendation 13 8 Legal Note 14 Method Statement Sikafloor®-255 Screed 29.9.20 2/14 Sika UAE 1 SCOPE This method statement describes application of internal bonded cementitious floor screed for residential use under floor covering (e.g. tiles, carpet, parquet, etc.) 2 DESCRIPTION AND USES 2.1 DESCRIPTION Sikafloor®-255 Screed is a one part cement based bonded screed. For levelling and smoothing uneven floors, and thick bed tile setting applications. Suitable for use in hot and tropical conditions. 2.2 PRODUCTS The system consisting of a bonding slurry and screed: PRODUCTS Sikafloor®-255 Screed One-part, economical, pre-mixed, cementitious screeds. Sikabond® DV or SikaLatex® Water-resistant bonding agent 2.3 CHARACTERISTICS/ ADVANTAGES Good workability Good compaction Ready to use Good finishing Application thickness from 20mm to 70mm Local application down to 10mm and up to 80mm possible, for areas <10m² 3 SYSTEM BUILD-UP CONSUMPTION RATE Coating System Product Consumption Primer / Bonding slurry Sikabond®DV / SikaLatex® mixed with cement As per site requirements Screed Sikafloor®-255 Screed ~2.25 kg/m2/mm Method Statement Sikafloor®-255 Screed 29.9.20 3/14 Sika UAE 4 SUBSTRATE PREPARATION 4.1 SUBSTRATE PRE-REQUISITES Concrete substrates must be of good condition, minimum 3 months old, with a pull off strength and compressive strength as mentioned below: Procedure Equipment Pull off Compressive Strength • The concrete substrate must be sound. • Compressive strength minimum 25 N/mm2. • Pull off strength > 1.5 N/mm2. Air Humidity • Relative air humidity max. 75%. • Beware of condensation. The substrate must be at least 3°C above dew point. Substrate & Ambient Temperature • Substrate temperature > 10ºC. • Ambient temperature below < 35°C. 4.2 SURFACE PREPARATION Concrete substrates must be mechanically prepared using abrasive blast cleaning to remove cement laitance, existing coatings and achieve a gripping profile that is clean, dry and free from laitance, dirt, grease, oil and any other form of surface contamination. Vacuum blasting or similar techniques are ideally suited. Procedure Equipment Vacuum shot blasting Concrete substrates must be prepared mechanically using abrasive blast cleaning or scarifying equipment to remove cement laitance and achieve a profiled open textured. Method Statement Sikafloor®-255 Screed 29.9.20 4/14 Sika UAE Cleaning of the surface All dust, loose and friable material must be completely removed from all surfaces before application of the product, preferably by brush and vacuum. Clean substrate The surface must be clean, dry and free of all contaminants, e.g. dirt, oils, grease, coatings and surface treatments, etc. Surface defects Repairs to the substrate, filling of blowholes/voids must be carried out using appropriate products from SikaTop®, Sika MonoTop®, Sikafloor®, Sikadur®, and Sikagard® range of materials. Surface roughness Pre-requisite for a good bond between the substrate and levelling screed is an appropriate roughness of the substrate. The mean surface roughness should be as large as possible, but at least 1 mm. The selected method of preparation will depend on the surface condition, environmental constraints and availability of services. The method may be selected on the basis of trial areas, approved by the Contract Administrator. For additional information, please refer to Sika's Method statement for "Evaluation and Preparation of Surfaces", available upon request. Method Statement Sikafloor®-255 Screed 29.9.20 5/14 Sika UAE 5 APPLICATION INFORMATION 5.1 PROFESSIONAL CREW The application of Sikafloor®-255 Screed may only be used by experienced professionals and therefor requires professional staff in sufficient quantity. The professional staff must be able to assess the substrate and take the necessary measures if necessary. Specifically, the smoothing and compacting work requires trained specialists who are familiar with the handling of the Sikafloor® products, effects of general environmental conditions and its changes, and which fully complies with the application limits of the products. As the installation speed or the daily area size increase, the demand for installation personnel increases. The quantitative demand for specialized, trained personnel increases with high installation performance. Sika® recommends to start with small sample surfaces and to create test surfaces. Application window changes with the thickness of the layer, the substrate, the temperature (substrate, mortar, air, water) of mortar consistency, as well as the sun. 5.2 TEMPERATURES The following minimum and maximum temperatures must be strictly adhered to start the application of the screeds until and when the final strength has been reached: Minimum temperatures +10° C for product, ambient air and substrate. Maximum temperatures +25° C for product. Maximum temperatures +35° C for ambient air and substrate. Be aware that: Fresh mortar temperatures ≤ 18 °C retard the strength development. Fresh mortar temperatures ≥ 22 °C accelerate the strength development. The fresh mortar temperature follows not linearly the temperatures of the substrate, air and water. Should these temperatures vary on the day of application, the mortar binding will vary with regard to stiffening and curing. Depending on the temperature, water content and layer thickness, the freshly applied mortar needs up to a few hours to react / stiffens. When the mortar starts stiffening, however, the mortar can harden very quickly (do not miss the smoothing / troweling window). Lower or higher fresh mortar temperatures, than the given temperatures, are outside the application limits and not guaranteed. Method Statement Sikafloor®-255 Screed 29.9.20 6/14 Sika UAE 5.3 WEATHER PRECAUTIONS In direct connection to the above-mentioned temperatures is the weather. Direct exposure of the sun on the freshly laid area has a considerable influence. In principle direct solar irradiation must be avoided. Shrinkage cracks can occur very quickly when a temperature rises above 25 °C . This has to be avoided in any case, for example, the sun's course can be checked in advance and the installation time / sequence of the application can take place accordingly in the shade. In particular, sun exposure midday / early afternoon during hardening of the mortar must be avoided. Combination of the daytime temperature with rising solar radiation and the warmth of the hardening screed will lead to quality losses and possible appearances of cracks. Be aware that: Shade can be ensured by for example setting up a tent. Alternatively, the installation stage can be laid on a night shift. It has been proven in practice that application during decreasing daily temperature improves the quality of the screed. The newly laid mortar must be protect against draft wind and/or draughts. Wind and draught quickly evaporates the water out of the surface of the mortar and forces a loss of volume, which in turn can lead to cracks and loss of surface quality. 5.4 MIXING EQUIPMENT For Small to Medium volumes the following equipment is of use: ▪ Mixing containers ▪ Weighing scales ▪ Water containers ▪ Water measuring container ▪ Double spiral mix paddle & drill (< 500 rpm) For Medium to Large volumes the following equipment should be used: ▪ Weighing scales ▪ Water containers ▪ Water measuring container ▪ Forced action mixer or rotating pan, paddle or trough type. (Compulsory mixer) ▪ Mixed material carriers/carts ( wheel barrows) Note : Free fall (tumble) mixers must not be used in any case. Method Statement Sikafloor®-255 Screed 29.9.20 7/14 Sika UAE 5.5 APPLICATION OF PRIMER / BONDING SLURRY Adequate evaluation of the substrate conditions and state will determine the type of bonding slurry required and allow taking preventive measures to reduce the risk of failures. Bonding slurry must be used as a wet-on-wet application with the Sikafloor®-255 Screed. The cement-bonded system slurry must always be mixed like a mortar. MIXING & APPLICATION Prior to the application of the system bonding slurry the absorbent mineral based substrate must be pre dampened with sufficient water (warning: no standing water/puddles) to a saturated, surface dry condition (SDD) substrate that helps to prevent the subsequent bond slurry for drying out. Our recommendation is to pre-wat substrate 3 days (vigouresly), 24 hours and 3 hours prior to screed application. The bonding slurry must always be mixed to a mortar before application in suitable ratio which is defined through site trials for specific project, considering surface absorption, temperature, humidity, etc. The bonding slurry must be applied uniformly over the surface at a thickness of ~ 1 mm. Avoid excess thicknesses of the material (even in local areas), by suitably prefilling any surface voids with appropriate Sika® mortars as required. The Sikafloor®-255 Screed mortar has to follow wet-on-wet on the bonding slurry. Therefore apply an area of ~2 m² in front of the application of the Sikafloor®-255 Screed. Application of the bonding slurry on the prepared and pre-dampened (SSD) substrate by brushing vigorously into the substrate with stiff bristle brushes. Make sure that the freshly applied bonding slurry does not start to dry out. Do not mix more bonding slurry than can be used for each area within it’s potlife, always make it up fresh. The freshly applied bonding slurry must be covered with fresh Sikafloor®-255 Screed mortar within 10 minutes (at 25°C) of its application (wet-on-wet application). 5.6 APPLICATION OF SIKAFLOOR®-255 SCREED MORTAR In order to achieve the quality characteristics according to the product data sheet, it is essential that the application is according to the specifications as given in the product data sheets and this method statement. Specifications of main importance are: water content, machine technology, personnel resources and qualification as well as the treatment after troweling of the applied mortar. Method Statement Sikafloor®-255 Screed 29.9.20 8/14 Sika UAE MIXING WITH HAND MIXER When mixing manually add the right amount of clean cold water, as per recommendation in Product Data Sheet, into a suitable mixing vessel before slowly adding dry powder. Work accurate with the amount of water and always mix full bags. Do not split the bags. Do not mix with cement or other cementitious products. In case of high temperatures, water can be cooled by using clean ice. For measurement of the water use a balance or a measuring cup. Thoroughly mix the Sikafloor®-255 Screed in the specified ratio with an electric hand mixer (approx. 300-400 rpm.) until lamp free, smooth and homogeneous mixture. It is important to mix for min. 3 minutes. It is recommended that a double spiral mix paddle is used. MACHINE MIXING Use only mixing equipment as advised. Free fall (Tumble) type mixers must not be used. For measurement of the water use a balance or a measuring cup. Water ammount is depending of the size of the mixer. Always follow Sika’s recommendation in terms of water to powder ratio. Method Statement Sikafloor®-255 Screed 29.9.20 9/14 Sika UAE Transportation of Sikafloor®-255 Screed mortar. APPLICATION Immediately apply mixed mortar screed mix wet on wet onto the bonding slurry, ensuring sufficient compaction by pouring the mixed product to the surface and spread to the level, 10 mm above the pre installed batten (e.g. steel guides adjusted to the desired height), giving it a surcharge. Than tamp down the screed heavily to the level to give full compaction. Strike off excess screed material until the top level (above the batten) by running a straight edge ruler alongside it. The use of laser height leveling is recommended, or previously applied mortar dots combined with steel guides. Ruling off and final screed finishing must be accurate enough to meet the requirements of the specification. Wood or plastic float finishes maybe acceptable, but generally a closed, flat steel trowelled finish is preferred. Acheive the desired finishing by final troweling to make it rough or smooth, depending from specification of final covering. At the time when the mortars gets a bit stiff and has nice troweling properties (tested by hand troweling) the final surface finishing should take place. In case of conduits and pipes running through the screed, it must be mechanically fixed to the substrate and reinforced by using wire mesh wrapped over them. The recommendations set out in relevant standard (e.g. BS 8204-1, SIA 252, FeRFA, etc.) should be followed during the application. Method Statement Sikafloor®-255 Screed 29.9.20 10/14 Sika UAE 5.7 TREATMENT OF JOINTS Building separation joints, dilatations and connecting joints in the substrate and different components must in all cases be incorporated into the new screed covering and appropriately executed. Joints design is project specific and should be recommended by designer. Generally, following should be taken into consideration: Always transfer (mirror) the joints from concrete slab below screed (both expansion and construction joints) Include joints in all areas where there is a major change in screed thickness Include joints in all areas where substantial change of shape occurs Include joints under doorways For slab on grade max. length between the joints should not exceed 5m. This is not required for suspended slabs, in this case only follow construction and expansion joints mirrored from the suspended slab Saw cuts can be used to create control joints in the applied screed with a recommended depth of min. 70% of the screed thickness (2/3) General application practice applies Always refer to relevant international standards for bonded screed installation and application (e.g. BS 8204 – Part 1, FeRFA) 5.8 CURING Curing must start immediately after application by covering finished areas with polyethylene sheet (with all leading edges lapped and secured), and left covered for a minimum 3 days. Covering by polyethylene sheet is essential to prevent premature drying. Failure to carry out adequate protection early enough can lead to edges curling and/or a dry friable surface through moisture loss. Alternateviely, depending from site conditions, wet hessian curing method can be combined with polyethylene sheeting. Protect against wind, sun and rain for minimum 10 days. Method Statement Sikafloor®-255 Screed 29.9.20 11/14 Sika UAE Next day the surface could show some discoloration [white blush] marks or may show trowel marks. This does not affect properties of the placed screed. 5.9 WET ON WET / THICK BED TILE APPLCATION Alternative to previous described curing method non-moisture sensitive tiles can be applied immediately into the wet screed by thick bed application method. For non-absorbent tiles like porcelain an additional suitable thin bed tile adhesive has to be applied as contact layer in a suitable manner. Refer to relevant standards, guidelines and good industry practice. 6 IMPORTANT CONSIDERATIONS During summer season or temperature higher than 35°C, working area should be covered to prevent the direct sun effects. Water can be cooled down by using clean ice. Protect the floor screed after levelling from direct sunlight, wind and rain. Do not use where negative hydrostatic pressure is evident (i.e. rising damp) Only for residential and internal use (no heavy traffic, etc.). Raw material-related variations in the color, texture, pores on the surface are in mineral systems (floor leveling compounds) normal and no reason for complaint. Under certain circumstances (drafts, sunlight, low humidity, etc.) fine "hairline cracks" can be expected. This is normal with cementitious screed system and it is no reason for complaint. Confirm required moisture content of substrate prior to application of overlayments which are not tollerant to moisture (e.g. vinyl, parquest, etc.) Prepare the screed as per requirements of overlaying material, rough or smooth. Do not mix Sikafloor®-255 Screed with cement or other cementitious products. Do not add extra water or other ingredients. Mix only full bags. Method Statement Sikafloor®-255 Screed 29.9.20 12/14 Sika UAE 7 HEALTH AND SAFETY RECOMMENDATION For information and advice on the safe handling, storage and disposal of chemical products, users shall refer to the most recent Safety Data Sheet (SDS) containing physical, ecological, toxicological and other safety-related data. Method Statement Sikafloor®-255 Screed 29.9.20 13/14 Sika UAE 8 LEGAL NOTE The information, and, in particular, the recommendations relating to the application and enduse of Sika products, are given in good faith based on Sika's current knowledge and experience of the products when properly stored, handled and applied under normal conditions in accordance with Sika’s recommendations. in practice, the differences in materials, substrates and actual site conditions are such that no warranty in respect of merchantability or of fitness for a particular purpose, nor any liability arising out of any legal relationship whatsoever, can be inferred either from this information, or from any written recommendations, or from any other advice offered. The user of the product must test the products suitability for the intended application and purpose. Sika reserves the right to change the properties of its products. The proprietary rights of third parties must be observed. All orders are accepted subject to our current terms of sale and delivery. Users must always refer to the most recent issue of the local Product Data Sheet for the product concerned, copies of which will be supplied on request. Sika UAE Version given by: Simon Ambauen Version reviewed by: Tarek Sallam