TNB Engineering & Corporation Sdn.Bhd Proposed Development of 50 MW Large Scale Solar Photovoltaic Plant At Lot 3288, Mukim Tanjung Duabelas, Kuala Langat, Selangor -Solar Photovoltaic Plant Interconnection Facility Consisting Of The Design And Construction Of 132kv Substation At The SPP And The 132Kv Extension Bay At PMU Bukit Changgang Tender No. Contract No. TNB (N) 9/2017 Method Of Statement Installation works at PMU 132/33kV Bukit Changgang December 2017 KUB POWER SDN.BHD. Level 3, Unit 1, Capital 3, Oasis Square, Ara Damanasara, Jalan PJU 1A/7A, Ara Damansara, 47301 Petaling Jaya, Selangor, Malaysia METHOD STATEMENT BACKGROUND INFORMATION COMPANY DETAILS: KUB POWER SDN BHD LEVEL 3, UNIT 1, CAPITAL 3, OASIS SQUARE, ARA DAMANSARA, JALAN PJU 1A/7A, 47301, PETALING JAYA, SELANGOR Tel: 03-7610 0018 Fax: 03-7610 0017 SITE ADDRESS OVERVIEW OF PROJECT/ACTIVITY PMU BUKIT CHANGGANG PMU Bukit Changgang –Supply, Erect, Testing & Commissioning One (1) bay switchyard 1. To erect of Steel Structure and Outdoor HV Equipment. 2. To erect the conductor, clamps & connector for corresponding primary equipment. 3. Multicore Cable laying work. CONTACT PERSON Competent Engineer: Ir. Amri Bin Mamat (012-334 3407) TNEC- Project Manager: Azhar Bin Haji Idris TNEC- Engineer: Mohamad Syafiq Bin Yusoff KUBP Project Manager: Iznan Man (012-272 0586) KUBP Project Engineer: Mohd Izham (017-283 0441) Syed Mohd Shafik (013-633 5370) TABLE OF CONTENT 1. 1. METHOD STATEMENT FOR ERECTION STEEL STRUCTURE 132KV .................................................................................................................... 4 1.1.1 STEPS IN ERECTION WORKS OF 132kV EQUIPMENT.................................................................................................................................................... 4 1. 1. METHOD STATEMENT FOR ERECTION STEEL STRUCTURE 132KV Site preparations and ensure that: All equipment’s accessories and parts are in good conditions. Ensure position and conditions of. Mobile crane or skylift operation radius. (if any) Equipment and machinery location and position. Work area is defined and barricaded All personnel to work in high area or climbing to wear a safe body harness. Ensure that all workers wear minimum PPE 1.1.1 STEPS IN ERECTION WORKS OF 132kV EQUIPMENT Obtain PTW (permit to work) Toolbox talks to be conducted regarding scope of work. Bring the ladder horizontally to the working area and install the ladder at specified location of erection work. The safety clearance must be maintained and sufficient during works. Installation the steel structure follow the table below No Item unit 1 Cable Sealing (CSE) 3 nos 2 Surge Arrester (SA) 3 nos 3 Inductive Voltage Transformer (IVT) 3 nos 4 line Isolator (DS) 1 set 5 Shared Inductive Voltage Transformer(IVT) & Current Transformer(CT) 3 nos 6 Current Transformer(CT) 3 nos 7 Circuit Breaker (CB) 3 nos To erect the conductor,clamps & connector for all the outdoor HV equipment. To laying and termination of multicore cable from MK to Building and MK to Equipment. Associated civil work. Retrofitting of the existing 132Kv Control Panel. To erect 1 no of the 132kv Relay panel Extension of the 132kv RTU To carry out Test and Commissioning. Clearance Data: Description Normal System Voltage (Phase-to-Phase) Minimum Clearance between LIVE metal and EARTH Minimum Clearance between LIVE metal & different phase Minimum safety clearance between ground and the nearest point not at earth potential of an insulator (Ground Clearance) Data 132kV 1270mm 1473mm 2440mm