UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PacifiCorp ) ) ) Docket No. EL08-___-000 PETITION FOR DECLARATORY ORDER OF PACIFICORP TO CONFIRM INCENTIVE RATE TREATMENT FOR THE ENERGY GATEWAY TRANSMISSION EXPANSION PROJECT July 3, 2008 Table of Contents Page I. Introduction .............................................................................................................. 1 II. Description Of PacifiCorp........................................................................................ 6 III. Description Of The Project....................................................................................... 6 A. Facilitation of the Delivery of Remote Renewable Resources ..................... 7 B. Project Configuration .................................................................................... 8 C. Priority One ................................................................................................. 10 D. E. F. 1. Walla Walla to McNary – Segment A ............................................. 10 2. Populus to Terminal – Segment B ................................................... 10 3. Mona to Oquirrh – Segment C ......................................................... 11 4. Sigurd to Red Butte to Crystal – Segment G ................................... 11 Priority Two ................................................................................................ 12 1. Windstar to Aeolus to Bridger – Segment D ................................... 12 2. Bridger to Populus – Segment E ...................................................... 13 Priority Three .............................................................................................. 14 1. Populus to Hemingway – Segment E............................................... 14 2. Hemingway to Captain Jack – Segment H....................................... 14 Priority Four ................................................................................................ 15 1. Aeolus to Mona – Segment F........................................................... 15 IV. Correspondence and Communications................................................................... 15 V. PacifiCorp’s Project qualifies for Incentive transmission Rates under order no. 67916 A. PacifiCorp is Entitled to a Rebuttable Presumption of Eligibility for the Requested Incentives................................................................................... 17 B. In the Alternative, Available Studies Demonstrate Requisite Project Benefits Sufficient to Satisfy the Order No. 679 Eligibility Criteria.......... 19 1. PacifiCorp’s IRP and Renewable Energy Procurement................... 20 2. Transmission Studies Have Identified Significant Transmission Bottlenecks, Many of Which the Project Will Help Alleviate......... 21 3. The Project Will Enable PacifiCorp to Access Location-Constrained Resources and Renewable Sources of Energy ................................. 24 i C. D. VI. 1. PacifiCorp Meets The Commission’s Nexus Test for a Non-Routine Project............................................................................................... 25 2. The Total Package of Requested Incentives Are Necessary to Compensate PacifiCorp for the Unique and Substantial Risks Posed by the Multi-State Project ................................................................ 35 The Commission Should Authorize The Requested Incentives.................. 41 Advanced technology statement............................................................................. 41 A. B. VII. The Requested Incentives Meet the Commission’s Nexus Test and Are Rationally Related To The Project’s Risks and the Investment Being Made25 Advanced Technologies to be Used By the Project .................................... 43 1. Trapezoidal Conductor..................................................................... 43 2. Static VAR Compensators ............................................................... 44 3. Fiber Optic Shield Wires.................................................................. 45 4. Phase Shifters ................................................................................... 46 5. Special Protection Schemes ............................................................. 46 6. Monitors for Transformers and Phase Shifters ................................ 47 PacifiCorp’s Decision to Forego the Use of Certain Advanced Technologies ............................................................................................... 47 Conclusion.............................................................................................................. 49 ii UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) ) PacifiCorp Docket No. EL08-___-000 PETITION FOR DECLARATORY ORDER OF PACIFICORP TO CONFIRM INCENTIVE RATE TREATMENT FOR THE ENERGY GATEWAY TRANSMISSION EXPANSION PROJECT Pursuant to Rule 207 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. § 385.207 (2007), Section 1241 of the Energy Policy Act of 2005 (“EPAct 2005”), adding new Section 219 of the Federal Power Act (“FPA”),1 and Order No. 679,2 PacifiCorp hereby submits this Petition for Declaratory Order (“Petition”) seeking incentive rate treatment in connection with PacifiCorp’s Energy Gateway Transmission Expansion Project (“Project”). I. INTRODUCTION The Project is one of the most ambitious electric infrastructure projects planned in the Western United States in the past two decades. By all reasonable measures, the size, scope, complexity and purpose of the Project is exceptional, far exceeding any of the proposed transmission projects that have been granted incentive rate treatment by the Commission to date 1 Energy Policy Act of 2005, Pub. L. No. 109-58, 119 Star. 594, 315 and 1283 (2005) (“EPAct 2005”). 2 See Promoting Transmission Investment Through Pricing Reform, Order No. 679, 116 FERC ¶ 61,057 at P 77 (2006) (“Order No. 679”), order on reh’g, Order No. 679-A, 117 FERC ¶ 61,345 (2006) (“Order No. 679-A”), order on reh’g, Order No. 679-B, 119 FERC ¶ 61,062 (2007) (“Order No. 679-B”). 1 under Order No. 679 and its progeny. At an estimated cost exceeding $6 billion,3 according to Mr. John Cupparo, PacifiCorp’s Vice President of Transmission, the Project will enlarge and expand PacifiCorp’s system-wide transmission network by adding approximately 2,000 miles of new extra-high voltage (“EHV”) transmission lines located in Idaho, Oregon, Utah, Washington, and Wyoming.4 The Project is intended to cost-effectively respond to regional needs and opportunities by providing: 1) improved reliability; 2) congestion reduction; 3) transmission access for renewable resources; 4) transmission for forecasted load growth; and 5) deployment of advanced transmission technologies. The Project also has the potential to provide other benefits consistent with the Commission’s policy objectives. Once completed, the Project will provide PacifiCorp’s customers across the West with substantial economic, reliability and environmental benefits. The Project has been scaled to improve the reliability of the bulk power system, and to reduce transmission congestion and the future cost of delivered power throughout PacifiCorp’s six-state service territory (California, Idaho, Oregon, Utah, Washington, and Wyoming). Were PacifiCorp only focused on small-scale, short-term solutions for serving its load, it would have proposed transmission projects that would have been far less comprehensive or as risky as the Project. However, PacifiCorp intends to do more than simply serve anticipated load growth through its development of the Project. For example, the Project is expected to deliver up to 3 As of the date of the filing of this Petition, this figure represents PacifiCorp’s best estimate of its forward-looking capital expenditures, as adjusted for inflation, and based on current estimates including Allowance for Funds Used During Construction (“AFUDC”). Given the long-lead times associated with regulatory and environmental approvals, securing qualified labor crews, and the costs of materials such as steel, this number will likely change over time. See Rebecca Smith, Costs to Build Power Plants Pressure Rates, WALL STREET JOURNAL, May 27, 2008 at B3 (noting the inflationary risks associated with energy project development). 4 The description of the Project, along with its associated risks and benefits, are set forth in Mr. Cupparo’s Affidavit, attached to this Petition as Appendix A (“Cupparo Affidavit”). 2 3,000 megawatts (“MW”) of capacity from location-constrained renewable resources in Wyoming to distant load centers. The Project will also provide a platform for integrating and coordinating future regional and sub-regional electric transmission projects being considered in the Pacific Northwest and the Intermountain West.5 This massive, multi-state, multi-jurisdictional Project is the very type of project that Congress envisioned when it added Section 219 to the FPA and that the Commission sought to encourage companies to explore when it issued Order No. 679.6 When the Project’s benefits are weighed against the substantial risks that PacifiCorp is taking on in developing it, the case for granting PacifiCorp’s requested incentives is a compelling one. The geographic and financial scale of the Project plainly places it in the category of “non-routine” projects to which the Commission has previously granted incentives. To offset the risks associated with the development of the Project, PacifiCorp, consistent with Section 219 of the FPA and Order No. 679, is requesting that the Commission issue a declaratory order granting the following incentive rate mechanisms for the Project: 5 The Project will establish the first-of-its-kind energy superhighway (500 kilovolt (“kV”)) connecting Wyoming, Idaho, Utah and Oregon. 6 See Order No. 679, 116 FERC ¶ 61,057 at P 24 (the Commission “must encourage investors to take risks associated with constructing large new transmission projects that can integrate new generation and otherwise reduce congestion and increase reliability. [The Commission’s] policies also must encourage all other needed transmission investments, whether they are regional or local, designed to improve reliability or to lower the delivered price of power”). 3 • A 250 basis point incentive rate adder to PacifiCorp’s base return on equity (“ROE”), not to exceed the upper end of the zone of reasonableness, as determined in a subsequent Section 205 proceeding; and • Authorization to recover all prudently incurred development and construction costs if the Project is cancelled or abandoned, in whole or in part, as a result of PacifiCorp’s inability to obtain necessary approvals, or as a result of any action or inaction by a governmental authority, or regulatory agency, for any reason outside PacifiCorp’s control. As described in greater detail below, these requested incentives have been narrowly tailored to address the considerable risks and challenges that PacifiCorp will face in constructing the Project. Rather than seeking a blanket request for all of the incentives identified in Order No. 679 (such as recovery of 100 percent of prudently incurred Construction Work In Progress (“CWIP”) and recovery of pre-commercial costs), PacifiCorp has instead limited its incentive requests to only those that are “rationally related to the investments being proposed.”7 Any Commission-granted incentives will compensate PacifiCorp’s retail electric customers for supporting the transmission investment through their retail electric rates, unlike many other projects considered to date by the Commission. PacifiCorp’s state regulators will be asked by – and are expected to allow – PacifiCorp to include the Project’s investment in retail electric rates. Of critical importance is the fact that such customers will be asked to support the portion of the investment needed for reliability and future growth – key elements that would be absent if this were a merchant project. To the extent that state regulators permit the recovery of all of the transmission investment in its retail rate base, PacifiCorp will compensate its retail customers by crediting the transmission-related revenues, inclusive of any incentives granted by the Commission, against its retail revenue requirement. PacifiCorp will also seek to optimize third-party usage of the transmission capacity created by the Project, and such revenues will also 7 Order No. 679, 116 FERC ¶ 61,057 at P 48. 4 be credited against PacifiCorp’s retail revenue requirement if all of the investment is included in retail rate base. Accordingly, PacifiCorp’s requested incentives will be an important consideration in obtaining state regulator support for including in retail rates the reliability and future growth elements of the Project. PacifiCorp is not at this time filing a request for a change in rates under Section 205 of the FPA. Consistent with Order No. 679,8 PacifiCorp intends to make a subsequent Section 205 rate filing at a future date to implement the applicable incentive rate treatment granted by the Commission in its order on this Petition. Due to the substantial risks associated with this Project, and the limited time available to coordinate with potential equity partners for commitments before a final decision can be made on whether PacifiCorp should commit to single or double circuit configuration on various segments of the Project,9 PacifiCorp respectfully requests that the Commission act upon this Petition within 60 days of this request, or in the alternative, by September 18, 2008.10 In support hereof, PacifiCorp respectfully states as follows: 8 See Order No. 679, 116 FERC ¶ 61,057 at P 79 (To implement authorized incentives, “applicant will have the option of filing a comprehensive section 205 rate case in which all of the utility’s rates would be reviewed in conjunction with the proposed recovery of the incentivebased rate treatments or filing a single-issue section 205 rate filing in which only the impact of the incentive-based rate treatment for the facility granted the incentive will be addressed”). 9 As discussed infra, the Project allows for the flexibility to be upsized from a singlecircuit to a double-circuit system, specifically for three discrete portions (Segments D, E and F). PacifiCorp is actively working with potential equity partners to determine the interest and commitment to such an upsize. PacifiCorp’s expectation is that any incentive rate treatment granted by the Commission in this proceeding would be applied to any variation in capital expenditure and Project scope. 10 Order No. 679, 116 FERC ¶ 61,057 at P 77 (“The Commission will seek to process petitions for declaratory orders quickly. While we cannot guarantee Commission action within 60 days of the request (as is statutorily required for section 205 filings), we will strive to meet that standard. . . . ”). 5 II. DESCRIPTION OF PACIFICORP PacifiCorp, an indirect, wholly-owned subsidiary of MidAmerican Energy Holdings Company (“MidAmerican”), is an investor-owned utility with its principal place of business in Portland, Oregon. PacifiCorp is primarily engaged in the business of providing electric service to approximately 1.7 million retail customers in six western states: California, Idaho, Oregon, Utah, Washington, and Wyoming. The company operates as Pacific Power in Oregon Washington and California, and as Rocky Mountain Power in Wyoming, Utah and Idaho. PacifiCorp’s retail rates and certain aspects of its operations are regulated by the following state public utility commissions: the California Public Utilities Commission, the Idaho Public Utilities Commission, the Oregon Public Utility Commission, the Public Service Commission of Utah, the Washington Utilities and Transportation Commission, and the Wyoming Public Service Commission.11 PacifiCorp provides electric transmission service in nine Western states, owning and operating approximately (1) 15,494 miles of transmission lines ranging from 46 kV to 500 kV and (2) 12,131 MW of generation capacity from coal, natural gas, hydroelectric, wind, and geothermal resources. PacifiCorp provides electric transmission service pursuant to a Commission-approved open access transmission tariff.12 III. DESCRIPTION OF THE PROJECT The Project, which was first announced by PacifiCorp in May 2007, is a system-wide transmission expansion program. Currently estimated to cost more than $6 billion, the Project is a substantial undertaking that is expected to add approximately 2,000 miles of new EHV 11 PacifiCorp is providing copies of this Petition to each of these state public utility commissions. 12 See PacifiCorp, 121 FERC ¶ 61,223 (2007). 6 transmission lines capable of delivering up to 3,000 MW of capacity from location-constrained renewable resources to distant load centers throughout the West. In terms of dollars of investment, miles of transmission lines and the number of states traversed, it is larger than any of the other transmission expansion projects that have been recently presented to the Commission. Appendix B to the Petition sets out the geographic and economic footprint of the Project, as measured against seven other regional transmission projects that have been found eligible for incentives by the Commission. Appendix B shows that the Project is the most ambitious transmission project to which the Commission has been asked to authorize rate incentives since the passage of EPAct 2005. The Project is a substantial financial undertaking by PacifiCorp, representing more than a 330% increase in PacifiCorp’s existing transmission rate base.13 A. Facilitation of the Delivery of Remote Renewable Resources The new EHV transmission lines proposed under the Project will move power from new renewable generation resources planned to be developed in Wyoming and Idaho to customer growth areas in Wyoming, Utah, and Oregon. Since its acquisition by MidAmerican, PacifiCorp has been actively adding renewable resources to its generation portfolio. Of the approximately 12,131 MW in PacifiCorp’s existing generation portfolio, approximately 1,556 MW comes from hydroelectric sources, and approximately 800 MW is produced by a combination of wind, geothermal, biomass and other renewable sources of energy. PacifiCorp’s 2007 Integrated Resource Plan (“IRP”) targets the system-wide procurement of an additional 2,000 MW of post2005 renewable resources (other than hydro) by 2013, assuming the procurement is costeffective.14 When completed, the Project will enhance the ability of PacifiCorp to gain access to 13 Cupparo Affidavit at ¶¶ 9, 63. 14 See 2007 IRP at http://www.pacificorp.com/Navigation/Navigation23807.html. 7 renewable energy sources, as well as will help PacifiCorp to continue to provide reliable and cost-effective electric service to its customers, while helping to relieve congestion in the transmission-constrained Western Interconnection. B. Project Configuration The Project is premised on a “hub and spoke” design that is characterized by major EHV transmission lines that connect areas with a strong potential for generation resource development (“hubs”) to an enhanced transmission system (“spokes”) for ultimate delivery to customers throughout the western United States. Under the Project, hubs are planned for western Wyoming, south central Wyoming, southeastern Idaho, southwestern Idaho, south central Utah, and southern Oregon. From these hubs, power will be collected and then moved in different directions, thereby allowing PacifiCorp to efficiently deliver power from a variety of generation sources to load. The significant improvement to critical transmission capacity and the Project’s “hub and spoke” design will provide flexibility, improve efficiency and enable development of (and access to markets for) clean and renewable energy resources.15 PacifiCorp’s approach to the design of the Project is a significant departure from past approaches to the development of major transmission projects. Historically, such projects were built when associated generation resources were sited. However, with the current uncertainty of the role of conventional generation technology, time duration to permit and construct major transmission, and the inability of many renewable resource developers to finance major 15 In addition to supporting PacifiCorp’s retail and network customers’ needs, the Project has adopted a flexible design approach to accommodate potential joint ownership participation in some segments of the Project, as well as potential upgrades driven by commitments from third parties with pending requests for points of new interconnection. The Project will strengthen the connections between PacifiCorp’s Rocky Mountain Power and Pacific Power service areas, and will help PacifiCorp ensure that its system is adequate and capable of meeting future regional needs. 8 transmission investments, transmission must be sited “ahead” of specific generation resources to best position utilities to meet future forecasted load growth. This approach presents greater additional risks for transmission investment than the historical norm: a risk that is only magnified by the scale and scope of the Project. As is common with any significant transmission project, PacifiCorp is developing the Project in separate stages. The Project will be comprised of eight interrelated and interdependent line segments. Each segment has been assigned one of four priority classifications, and are grouped as follows:16 • Priority One - Segments A, B, C and G • Priority Two - Segments D and E • Priority Three - Segments E and H • Priority Four - Segment F As most of these Segments are necessarily dependent on the development of the others, the different priority levels have been established to ensure the most prudent approach toward the overall in-service delivery of the Project, the most useful transfer capability as each segment is brought into service, and the ability to respond as flexibly as possible to the market demands. PacifiCorp is still moving forward to meet the announced 2014 in-service dates through its permitting, technical planning, and design workstreams. The later Priority segments will be shaped to best compliment the ability to deliver the first two Priority tiers. 16 A map of the Project, showing the individual Segments and their respective priorities, is located on PacifiCorp’s OASIS site at http://www.oasis.pacificorp.com/oasis/ppw/ EnergyGWMap_200806.pdf; see also Exhibit No. 1 to the Cupparo Affidavit. Some of the segments have also been grouped as follows: 1) Segments B and C – Gateway Central Transmission Project; 2) Segments D and E – Gateway West Transmission Project; and 3) Segments F and G – Gateway South Transmission Project. 9 Prioritizing the segments facilitates efficient and cost-effective development and construction of the Project by clustering segments that offer similar general benefits and asset inservice dates. Due to the scope and geographic characteristics of the Project, concurrent development of all the Project segments would not be not cost-effective. Development of all of the segments is progressing, and due to the inter-relationship of some of the segments, an order of priority is necessary to construct the segments in a prudent manner. C. Priority One The four segments that comprise Priority One of the Project are being built to enhance the base load service and reliability of PacifiCorp’s transmission system. Together, these segments are anticipated to be among the earliest portions of the Project to be placed into service, and PacifiCorp has already begun the preliminary permitting and contracting work necessary for getting these segments on line between 2010 and 2014. 1. Walla Walla to McNary – Segment A17 Segment A of the Project is an estimated $108 million project that will run approximately 56 miles between Walla Walla, Washington and Umatilla, Oregon, and will connect existing power substations at Walla Walla, Wallula and McNary. When completed in 2010, the 230 kV segment could be used to link existing and future sources of renewable resources to better benefit system power transfers. 2. Populus to Terminal – Segment B18 Segment B of the Project is an estimated $800 million project that will run from a new Populus substation, near Downey, Idaho, approximately 135 miles south to the existing Terminal 17 See Cupparo Affidavit at ¶ 14. 18 See Cupparo Affidavit at ¶¶ 15-17. 10 substation near the Salt Lake City Airport west of Salt Lake City, Utah. The double circuit 345 kV line will be constructed in two segments. The first segment will link the new Populus substation with the existing Ben Lomond substation north of Ogden, Utah. The second segment will link Ben Lomond with the Terminal substation. Both pieces of Segment B are anticipated to be placed in service in 2010, and are intended to deliver reliable power to the growing load demand along the Wasatch front in Utah. This segment is also critical to achieve the planned transfer capability rating on other Project segments. 3. Mona to Oquirrh – Segment C19 Segment C of the Project is an estimated $425 million project that will run north approximately 86 miles from the Mona substation near Mona, in Juab County, Utah, to two future substations. The line will then split and connect to the Oquirrh substation located in West Jordan, Utah and the Terminal substation located in Salt Lake City. The double circuit line will have one segment constructed at 500 kV and the other at 345 kV. Segment C is intended to serve one of the fastest growing areas in Utah, and in the region, by providing the additional capacity necessary to serve the growing customer demand, and to improve reliability and operational flexibility of the bulk transmission system. The line is also anticipated to assist in linking future generation resources with load centers in Utah. This Segment is also critical to achieve the planned transfer capability rating on other Project segments. 4. Sigurd to Red Butte to Crystal – Segment G20 Segment G is an estimated $754 million transmission project that will span approximately 280 miles, and will connect the existing Sigurd substation (about 50 miles south 19 See Cupparo Affidavit at ¶ 18. 20 See Cupparo Affidavit at ¶ 23. 11 of Mona), through the Red Butte substation in the southeast corner of Utah, to the Crystal substation north of Las Vegas, Nevada. The lines linking Sigurd to Red Butte will be a single circuit 345 kV line, and the one linking Red Butte to Crystal will be a single circuit 345 kV line, both lines will be dependent on the best determined voltage and scale needed to most efficiently interconnect with neighboring utilities and to meet customer needs. Segment G will provide additional capacity and access to resources from Wyoming necessary to serve growing customer demand, to meet point-to-point customer commitment requirements, and to improve the reliability and operational flexibility of the bulk transmission system. This project could be upsized to include a 500 kV line configuration, and additional line segments added between Mona and Crystal, if commitment is received from wholesale customers. The 345 kV lines would also provide the reliability base needed to support any of these scaled options, while also meeting the load service needs of PacifiCorp’s customers. PacifiCorp is actively working with interested parties to determine levels of interest and commitment in pursuing an upsize to this segment. D. Priority Two The two segments that have received the Priority Two classification (Segments D and part of Segment E) are designed to enhance the resource adequacy of the region by helping to connect transmission-constrained wind resources in Wyoming to westward load centers. 1. Windstar to Aeolus to Bridger – Segment D21 Segment D of the Project is an estimated $880 million line that will run approximately 298 miles from the Windstar substation in eastern Wyoming westward to the Bridger substation in western Wyoming. Segment D is part of the Gateway West Transmission Project, and is 21 See Cupparo Affidavit at ¶ 19. 12 currently jointly sponsored by PacifiCorp and Idaho Power. Segment D is expected to be in service by 2014, and will consist of two single circuit 230 kV lines connecting Windstar to Aeolus, and a double circuit 500 kV/230 kV line(s) connecting Aeolus to Bridger. The 230kV portion of the segment of the line from Aeolus to Bridger could be potentially upsized to 500 kV depending on the outcome of queue requests and equity partner interest. In addition to construction of a new Windstar substation, a new substation will also be built at Aeolus (to integrate new generation resources and to provide connection with the Gateway South Project). Segment D is intended to access and deliver energy from new and existing generating resources, which are currently anticipated to be primarily renewable energy resources such as wind. 2. Bridger to Populus – Segment E22 Segment E of the Project is also part of the jointly-sponsored Gateway West Project. This segment will be comprised of an estimated $1.02 billion line, which will run from a planned transmission hub near Rock Springs, Wyoming across Idaho to a point southwest of Boise. The line will be constructed in two sections. The first section, classified as Priority Two, will link the Bridger substation to the Populus substation via a single circuit 500 kV line. The second section has been categorized as Priority Three and is intended to connect the Populus substation to the Hemingway substation.23 A new substation will be built at Populus (to connect with Path C transmission into Utah as further described in the Cupparo Affidavit) for this portion of Segment E. Together with Segment D, Segment E will help access and deliver energy from new and existing generating resources, including renewable energy resources such as wind in Wyoming, 22 See Cupparo Affidavit at ¶ 20. 23 This portion of the segment will link the Idaho to Oregon segments. Exact location may change as a result of the Western Electricity Coordinating Council (“WECC”) regional planning process. 13 to load centers further west. The two single circuit Segments that comprise Gateway West have the potential to be upscaled if equity partners or wholesale customers commit to equitable cost sharing. E. Priority Three The remaining portion of Segment E, as well as Segment H, constitute the third level of priority for the Project. These segments are intended to help integrate PacifiCorp’s control area within the Project footprint, and to help provide a means for transmitting renewable energy supplies. 1. Populus to Hemingway – Segment E24 The second section of Segment E will connect the new substation at Populus to the new substation to be built at Hemingway as described above. Compared to the first section of Segment E, this portion will be placed into service at a later date as partner and construction conditions allow, as construction is planned to directly follow the Priority Two Segment E work. 2. Hemingway to Captain Jack – Segment H25 Segment H of the Project is an estimated $786 million line that will run approximately 375 miles from the Hemingway substation in western Idaho to the Bonneville Power Administration’s Captain Jack substation. The western terminus of this project, while currently planned for Captain Jack, has some ability to be moved within the same general area if equity partner and/or wholesale customer commitments are secured and efficiencies are identified. 24 See Cupparo Affidavit at ¶ 21. 25 See Cupparo Affidavit at ¶ 24. 14 F. Priority Four Segment F of the Project has been classified as Priority Four. This Priority status is intended to provide back up system reliability, as well as rating support for PacifiCorp’s newly enhanced system. 1. Aeolus to Mona – Segment F26 Segment F of the Project is an estimated $764 million line that will run approximately 395 miles from the Aeolus substation in eastern Wyoming southwest to the Mona substation in Juab County, Utah. This Segment is part of the Gateway South Transmission sub-area of the Project. This segment could be upsized to a double circuit 500 kV line depending on the outcome of queue requests and equity partner interest. IV. CORRESPONDENCE AND COMMUNICATIONS Correspondence or communications regarding this matter should be sent to the following individuals: Joseph H. Fagan Becky M. Bruner Sandy I. Grace Heller Ehrman LLP 1717 Rhode Island Ave., N.W. Washington, DC 20036-3001 Phone: (202) 912-2162 Fax: (202) 912-2020 joseph.fagan@hellerehrman.com becky.bruner@hellerehrman.com sandy.grace@hellerehrman.com Natalie L. Hocken Ryan Flynn PacifiCorp 825 NE Multnomah Avenue Suite 2000 Portland, OR 97232-2149 Phone: (503) 813-7205 Fax: (503) 813-7262 natalie.hocken@pacificorp.com ryan.flynn@pacificorp.com Jay Carriere Manager, Federal Regulatory Affairs MidAmerican Energy Holdings Co. 1800 M Street, NW, Ste. 330N Washington, DC 20036 (202) 828-4590 JGCarriere@midamerican.com 26 See Cupparo Affidavit at ¶ 22. 15 Copies of the filing are also available for inspection at PacifiCorp’s office and on PacifiCorp’s website at http://www.pacificorp.com/Article/Article43351.html. PacifiCorp has also served a copy of this filing on all of its customers by posting this filing electronically on its website, and requests waiver of the requirement to post by mailing paper copies to its customers. V. PACIFICORP’S PROJECT QUALIFIES FOR INCENTIVE TRANSMISSION RATES UNDER ORDER NO. 679 EPAct 2005 directed the Commission to “promote reliable and economically efficient transmission and generation of electricity by promoting capital investment in the enlargement, improvement, maintenance, and operation of all facilities for the transmission of electric energy in interstate commerce . . . .”27 In response to EPAct 2005, the Commission issued Order Nos. 679 and 679-A which provide incentive-based rate treatment for transmission infrastructure investment projects that will help ensure the reliability of the bulk power transmission system and/or reduce the cost of delivered power to customers by reducing transmission congestion. Order No. 679-A adopts a rebuttable presumption of eligibility for incentives with respect to transmission projects that either (1) result from a fair and open regional planning process that considers and evaluates projects for reliability and/or congestion and is found acceptable to the Commission, or (2) have received construction approval from an appropriate state commission or siting authority, provided that these approval processes require that a project ensures reliability or reduces the cost of delivered power by reducing congestion.28 Specifically, an applicant may rely on either of these rebuttable presumptions to support its request for a finding that the 27 16 U.S.C. § 824s(b)(1) (emphasis added). 28 Order No. 679-A, 117 FERC ¶ 61,345 at PP 48-49. 16 facilities qualify for incentive rate treatment.29 Under Order No. 679, the applicant requesting incentive rate treatment is required to provide a detailed explanation of how the proposed rate treatment complies with Section 219 of the FPA.30 In order to meet these standards, the applicant must demonstrate that: (1) the facilities for which it seeks incentives satisfy the requirements of FPA Section 219 (i.e., that they ensure reliability or reduce the cost of delivered power by relieving congestion); and (2) the total package of incentives is tailored to address the demonstrable risks or challenges faced by an applicant in undertaking the project.31 As described below, this Petition demonstrates that PacifiCorp’s request is entitled to a rebuttable presumption of eligibility for incentives. Alternatively, if the Commission does not determine that PacifiCorp is entitled to a rebuttable presumption, PacifiCorp submits that it has made the requisite showing, under Section 219 and Order No. 679, to justify the awarding of incentives for the Project. In either case, the Petition demonstrates the required nexus between the Project and PacifiCorp’s requested incentives. A. PacifiCorp is Entitled to a Rebuttable Presumption of Eligibility for the Requested Incentives PacifiCorp is entitled to a rebuttable presumption under Order No. 679 and its progeny on the basis that substantially all segments of the Project were approved by a fair and open subregional planning processes. Virtually all segments of the Project, were planned, coordinated 29 Id. at P 77. 30 18 C.F.R. § 35.35 (d). 31 Id. 17 and approved under the auspices of the Northern Tier Transmission Group (“NTTG”) planning process.32 PacifiCorp adopted NTTG as its sub-regional planning organization for the purposes of meeting the principles of Order No. 890, as described in its filed Attachment K which is currently pending at the Commission.33 NTTG is a coalition of investor-owned and public utilities, state agency officials, and customer groups committed to working with stakeholders to increase the efficient use of the grid and to develop the infrastructure needed to ensure reliability and to reduce congestion in the Pacific Northwest and Rocky Mountain states. NTTG performs both reliability and economic planning coordination for projects in the NTTG footprint,34 and coordinates with the WECC Regional Planning Process, which is responsible for coordinating and promoting electric system reliability across the Western Interconnection.35 NTTG’s 2007 Annual Report36 identified the need for additional transmission facilities to increase transmission capacity to reduce congestion and to improve reliability in the existing paths spanning the sub-region. In accordance with this need, NTTG members have developed a Fast Track Process, with the participation of stakeholders through a series of open meetings, in which projects required for reliability, and which are supported by transmission service requests 32 Segments A, B, and C originally represented transaction commitments agreed to as part of MidAmerican’s acquisition of PacifiCorp. As currently constituted, Segment A represents a variation, while Segments B and C represent significant expansions, of the original transaction commitments. 33 Compliance Filing Pursuant to Order No. 890, Docket No. OA08-40 (Dec. 7, 2007). 34 The NTTG footprint includes Oregon, Idaho, Utah, Montana and Wyoming. 35 WECC has developed policies and procedures for stakeholders to participate in the regional planning and project rating process and serves as the regional planning organization for evaluating the Project. 36 See discussion of NTTG in Cupparo Affidavit at ¶¶ 27-29, 32-35; the NTTG 2007 Annual Report is attached as Exhibit No. 2 to Cupparo Affidavit. 18 throughout the region are identified.37 Implicit in the NTTG planning process are the considerations of relieving congestion and enhancing reliability;38 therefore, in the course of developing the Fast Track Process, NTTG reviewed, among other things, the 2004 Rocky Mountain Area Transmission Study (“RMATS”) and the Seams Steering Group – Western Interconnection (“SSG-WI”) studies.39 As a participant in the NTTG Fast Track Process, PacifiCorp was required to develop a technical study plan that, among other things, identified interested and affected parties; coordinated with other regional and sub-regional planning groups, including the Northwest Transmission Assessment Committee, Columbia Grid and West Connect; and performed required WECC Regional Planning Review Studies. Among the Fast Track projects approved and identified in the 2007 Annual Report were Gateway South (Segments F and G), Gateway West (Segments D and E), Gateway Central (Segments B and C), and Segment H (Hemingway to Captain Jack). B. In the Alternative, Available Studies Demonstrate Requisite Project Benefits Sufficient to Satisfy the Order No. 679 Eligibility Criteria In the event the Commission determines that PacifiCorp is not yet entitled to a rebuttable presumption that it meets the criteria of FPA Section 219, PacifiCorp submits that it has nonetheless met the burden of demonstrating that the Project satisfies such criteria. There should be little doubt that the Project, once completed, will result in increased reliability and a reduction in congestion sufficient to fulfill the Order No. 679 eligibility criteria for the requested 37 NTTG 2007 Annual Report at 1. 38 Id. at 7 (identifying as the first step in the NTTG Fast Track Planning Process, the “[r]eview, with stakeholders, past transmission provider studies and additional data to identify congested transmission that impedes efficient and reliable operation of the grid”) (emphasis added). 39 The SSG-WI study summary is available, beginning on page 104, at: http://www.wecc.biz/documents/library/WCATF/Report_to_DOE_050806_Templates_Report_v er3.doc 19 incentives. Moreover, consistent with Commission policy, the Project will enable PacifiCorp to access location-constrained renewable sources, and thus provides an independent basis on which the Commission can grant the requested incentives. 1. PacifiCorp’s IRP and Renewable Energy Procurement As a threshold matter, the Project is consistent with the mandates set forth in PacifiCorp’s 2007 IRP.40 PacifiCorp’s IRP is the product of a collaborative public process, drawing considerable involvement from customer interest groups, regulatory staff and regulators, and other stakeholders. From late 2005 though April 2007, PacifiCorp held 13 public meetings to discuss important planning issues and to solicit comments on IRP analysis, methods and assumptions. The result of this public process was the 2007 IRP. The Project will assist PacifiCorp in meeting the mandate set forth in its 2007 IRP to cost-effectively enhance grid reliability, both on its network and region-wide. For example, the Project will 1) establish a 500 kV backbone;41 2) reduce curtailments resulting from overscheduled use; 3) provide additional accessibility to resources and reserves; 4) increase the 40 PacifiCorp prepares and submits an IRP for the states in which it provides retail service. 41 As there is currently no 500 kV infrastructure within the Project footprint in Idaho, Utah, and Wyoming, the first entity to construct a new 500 kV system will ultimately be responsible for mitigating the impacts caused on the underlying system by the introduction of a higher voltage than currently exists. This requirement is a result of North American Electric Reliability Corporation (“NERC”) reliability standards requiring that the system operate under conditions to withstand the next major facility electrical outage, or “n-1 outage”. If the existing system is equal to or higher in voltage to new additions, such additions do not typically cause as large of a concern with additional outages. With additions larger in voltage than the existing system, typically a fully redundant transmission system must be constructed. This is the case for Project Segments D, E and F. This effectively raises the costs and risks associated with incorporating a new higher voltage class of transmission facilities in any area. Once the initial construction is completed, future 500 kV additions in the same footprint, whether by PacifiCorp or others, could have much lower cost barriers to entry because of the network backbone created by the Project facilities. 20 diversity of the available resource mix; 5) connect PacifiCorp’s Rocky Mountain Power and Pacific Power control areas to better serve network load; and 6) assist in satisfying certain state renewable portfolio requirements or goals through its delivery of wind power. Further, as described in its 2007 IRP, PacifiCorp is also aggressively pursuing, on a longterm basis, renewable resources, if cost-effective. The Project will provide PacifiCorp and other interested parties with unprecedented access to high-value location-constrained renewable resources in Wyoming and other states. According to the American Wind Energy Association, Wyoming alone has the potential to accommodate approximately 85,200 MW of wind power capacity, with a substantial amount reflected in PacifiCorp’s interconnection queue.42 The Project’s location will help to efficiently and cost-effectively integrate some of these vast wind resources into the grid to the benefit of the entire region. 2. Transmission Studies Have Identified Significant Transmission Bottlenecks, Many of Which the Project Will Help Alleviate As discussed in the Cupparo Affidavit, over the past decade, numerous studies have been issued that have documented the urgent need for new transmission in the Western United States. As early as 2002, the DOE National Transmission Grid Study identified the Wyoming-Idaho interface as a major constrained interface, and found, under optimal conditions, the WyomingNorthern Utah interface to be congested during 50 percent or more of the hours during the year.43 42 See American Wind Energy Association at http://www.awea.org/projects/projects.aspx?s=Wyoming. Information about PacifiCorp’s interconnection queue is located at http://www.oasis.pacificorp.com/oasis/ppw/lgia/pacificorplgiaq.htm. 43 Cupparo Affidavit at ¶ 47; this study listed the Wyoming-to-Idaho interface as major constraint and WY to Northern UT as congested 50% of hours or greater. See National Transmission Grid Study at pp 15, 18. An excerpt of this report is provided as Exhibit No. 8 to the Cupparo Affidavit. A full copy of this report is available at http://www.pi.energy.gov/documents/ TransmissionGrid.pdf. 21 The 2004 RMATS reached similar conclusions, the result of which was a recommended expansion of the 345 kV transmission lines connecting the Bridger substation (included in Segments D and E of the Project) to points south and west as critically needed improvements.44 In addition, the Department of Energy’s 2006 National Electric Transmission Congestion Study (“DOE Congestion Study”) identified several constrained transmission paths in the West, including lines used to deliver electricity from generation plants in Wyoming to loads in Utah and Oregon.45 Specifically, the DOE Congestion Study illustrated that the expansion of the Bridger West facility is critical for relieving congestion from Wyoming to Northern Utah, and Wyoming to Idaho.46 Similarly, the Western Interconnection 2006 Congestion Assessment Study, which was issued by the DOE Western Congestion Analysis Task Force, identified areas of congestion in the Rocky Mountain states, and projected that based on 2005 load and resource forecasts and a production model, many of the paths associated with the various segments of the Project were forecasted to be heavily congested.47 Lastly, reports initiated by the Western Governor’s Association (“WGA”) also show certain paths in PacifiCorp’s service territory (such 44 See Cupparo Affidavit at ¶ 43 (discussing the RMATS at Chapter 3-2, which shows the Bridger expansion as a critical expansion area from Wyoming to Northern Utah and Wyoming to Idaho). An excerpt of this report is provided as an attachment to the Cupparo Affidavit as Exhibit No. 4. The full report is available at:http://psc.state.wy.us/htdocs/ subregional/Reports.htm 45 See Cupparo Affidavit at ¶ 44 (discussing the National Electric Transmission Congestion Study (August 2006) at pp 31-35)). The transmission constraints identified in this study were identified by reviewing recent transmission studies such as those conducted by WECC and SSG-WI. An excerpt of the study is provided as an attachment to the Cupparo Affidavit, as Exhibit No. 5. The full report is available at http://nietc.anl.gov/documents/ docs/Congestion_Study_2006-9MB.pdf. 46 Such expansion is addressed by the Segment E portion of the Project. 47 Cupparo Affidavit at ¶ 45. See also Exhibit 6 to Cupparo Affidavit. A full copy of this study is available at http://www.oe.energy.gov/DocumentsandMedia/ DOE_Congestion_Study_2006_Western_Analysis.pdf. (Footnote continued) 22 as the Segment C Populus to Terminal portion of the Project) to be constrained.48 The Project is PacifiCorp’s affirmative response to these identified critical areas of congestion. In this respect, the Order No. 679 criteria dovetail with PacifiCorp’s long-term operational goals and its parallel obligation to provide its customers with cost-effective, safe and reliable electric service. To ensure long-term reliability, PacifiCorp must upgrade, reconfigure and supplement transmission facilities throughout its service area on an ongoing basis. The Project will be built to satisfy all of the WECC and NERC’s planning and reliability standards as they relate to system adequacy and security, system modeling data requirements, system protection and control, and system restoration.49 Without the new transmission capacity created by the Project, PacifiCorp would have to rely on existing transmission interconnections, or small-scale, low benefit projects, many of which are already fully utilized, or have already been undertaken. Such projects would not provide any long-term meaningful transmission capacity necessary for future projected load and ability to access generation. In the process of planning the Project, PacifiCorp considered many small-scale projects with limited risks and benefits, all of which were ultimately rejected because they did not yield the Project’s long-range benefits. PacifiCorp’s network load obligation is expected to grow during the next ten years at an average annual rate of approximately two to three percent.50 Accordingly, the amount of planning reserves, which are required to maintain reliability obligations, will increase. For example. the existing transmission capacity from 48 Cupparo Affidavit at ¶ 46; see also Exhibit No. 7 to the Cupparo Affidavit. The full report is available at http://www.westgov.org/wga/initiatives/cdeac/TransmissionReportfinal.pdf. 49 Cupparo Affidavit at ¶ 38. 50 Cupparo Affidavit at ¶ 42. 23 southeastern Idaho into Utah is fully utilized and no additional capacity can be made without the addition of new transmission lines. The proposed transmission segments under the Project’s umbrella are PacifiCorp’s long term response to the projected demands on PacifiCorp’s available capacity. These lines will also provide PacifiCorp with the ability to access power from numerous location-constrained renewable generation sources and to negotiate the most competitive pricing for those sources of power. 3. The Project Will Enable PacifiCorp to Access LocationConstrained Resources and Renewable Sources of Energy In addition to relieving already constrained paths, the Project will facilitate PacifiCorp’s access to location-constrained resources, especially renewable sources of energy. The WGA and its working groups have also identified the important need to develop transmission projects throughout the West to access location-constrained resources. The WGA’s Transmission Task Force Report, dated May 2006, considered the location and availability of location-constrained renewable resources and the effect that timely transmission projects could have on increasing the percentage of renewable resources serving load in the West. Specifically, the report commented with regard to location-constrained renewable resources that “[t]he key challenge for generation development in these areas is to build new transmission capacity in a synchronized manner.”51 As such, this Project represents the type of coordinated and comprehensive transmission development that meets the critical need (as well as the Commission policy) of linking remote renewable resources to load centers throughout the West.52 51 See Exhibit No. 7 to Cupparo Affidavit. 52 See Department of Energy Report - 20% Wind Energy by 2030, Increasing Wind Energy's Contribution to U.S. Electricity Supply, May 2008 at Chapter 4.2, 93 (concluding that if the United States is to reach the 20% wind scenario by 2030, that "a significant amount of new transmission will be required" as "[t]ransmission must be recognized as a critical infrastructure (Footnote continued) 24 C. The Requested Incentives Meet the Commission’s Nexus Test and Are Rationally Related To The Project’s Risks and the Investment Being Made Order No. 679 requires a utility to demonstrate a nexus between the requested incentives and the investment being made, i.e., that the incentives are “rationally related” to the investment based on the facts of the particular case.53 In evaluating whether a utility has satisfied the required nexus test, the Commission examines the total package of incentives being sought, the inter-relationship between any incentives, and how the requested incentives address the risks and challenges faced by the project.54 The Commission does not require a utility to demonstrate that the project would not be built “but for” the requested incentives,55 and the Commission has clarified that it retains the discretion to grant incentives that promote particular policy objectives, unrelated to whether a project presents specific economic risks or challenges.56 1. PacifiCorp Meets The Commission’s Nexus Test for a Non-Routine Project As part of its evaluation of whether the total package of requested incentives are tailored to address the demonstrable risks or challenges faced by the applicant, the Commission considers the question of whether a project is “routine” to be particularly probative.57 Among other things, the Commission evaluates whether the project’s stated risks involve common issues faced by element needed to enable regional delivery and trade of energy resources, much as the interstate highway system does for the nation's transportation needs"). This report is available at http://www1.eere.energy.gov/windandhydro/pdfs/41869.pdf. 53 Order No. 679, 116 FERC ¶ 61,057 at P 48. 54 Order No. 679-A, 117 FERC ¶ 61,345 at P 21. 55 Id at PP 21, 25; see also Bangor Hydro Elec. Co., 117 FERC ¶ 61,129 at P 105 (2006). 56 Order No. 679-A, 117 FERC ¶ 61,345 at P 21, n 37; see also Pacific Gas and Elec. Co., 123 FERC ¶ 61,067 at P 33 (2008) (“PG&E”). 57 Baltimore Gas and Elec. Co., 120 FERC ¶ 61,084 at P 48 (2007) (“BG&E”), order on reh’g, 123 FERC ¶ 61,262 (2008) (“BG&E Rehearing Order”). 25 other utilities in constructing transmission facilities in the normal course of business. Because the purpose of rate incentives under Order No. 679 is to encourage construction of non-routine regional transmission projects (routine projects are presumed to be undertaken as a matter of good utility practice or obligation), the less routine a project is determined to be, the more likely it is to merit rate incentives.58 To determine whether a project is not routine, the Commission will consider all relevant factors including: (i) the scope of the project (e.g., dollar investment, increase in transfer capability, involvement of multiple entities or jurisdictions, size, effect on region); (ii) the effect of the project (e.g., improving reliability or reducing congestion costs); and (iii) the challenges or risks faced by the project (e.g., siting, internal competition for financing with other projects, long lead times, regulatory and political risks, specific financing challenges, other impediments).59 PacifiCorp’s Petition seeks a package of incentives that are narrowly tailored to address the demonstrable risks and challenges that it faces in developing the Project. The incentives proposed by PacifiCorp satisfy the required nexus test, as they are necessary to promote further investment in the Project, to ameliorate the considerable financial and resource challenges that the Project would impose upon PacifiCorp and to offset the substantial additional risks identified 58 Id., at P 54 (“By definition, projects that are not routine under [the Commission’s] analysis … face inherent risks and challenges and/or provide benefits that are worthy of incentives.”); Southern California Edison, 123 FERC at P 38 (While “the Commission will consider applications for ROE incentives for all projects”. . . “the most compelling case for incentive ROEs are new projects that present special risks or challenges, not routine investments made in the ordinary course of business”) (internal citations omitted). 59 BG&E, 120 FERC ¶ 61,084 at P 52, n. 53 (The Commission has explained that “these are only examples of evidence that can help inform the Commission on the question of whether a project is routine” and that this is not a “new formulaic checklist that must be met by every applicant for every proposed incentive or project”). 26 below. By any reasonable measure, this Project is non-routine, and is deserving of the requested incentives.60 a. Scope As an initial matter, the immense size and financial scope of the Project supports a determination by the Commission that PacifiCorp is entitled to such an incentive. The Project is the very type of large scale interstate bulk transmission project that Congress intended to encourage in EPAct 2005. By all reasonable measures, the size, scope, complexity, and purpose of the Project is exceptional, far exceeding any of the proposed transmission projects that have been granted incentive rate treatment by the Commission to date under Order No. 679.61 The Project is intended to address regional needs and opportunities, including reliability, congestion reduction and the transmission of renewable resources, and it will support compliance with individual state renewable portfolio standards (“RPS”), to the extent that the acquisition of such resources is cost-effective, by providing the necessary transmission to location-constrained renewable resources. In fact, the Commission has granted ROE incentives for projects that are much smaller and provide fewer benefits than this Project.62 The Commission determined that smaller projects 60 See Order No. 679, 116 FERC ¶ 61,057 at P 24 (the Commission “must encourage investors to take risks associated with constructing large new transmission projects that can integrate new generation and otherwise reduce congestion and increase reliability. [The Commission’s] policies also must encourage all other needed transmission investments, whether they are regional or local, designed to improve reliability or to lower the delivered price of power”). 61 Cupparo Affidavit at ¶ 64. 62 See, e.g., BG&E, 120 FERC ¶ 61,084 at PP 8-9 (authorizing a 100 basis point ROE adder for two projects that involved replacing transformer banks and reconfiguring a switchyard at two substations at a total cost of less than $100 million); Duquesne Light Co., 118 FERC ¶ 61,087 (2007) (authorizing a 100 basis point adder for several upgrades to the transmission system in the Pittsburgh area, costing $184 million). 27 with generally localized benefits, like BG&E and Duquesne, faced sufficient risk, and were “non-routine” in nature such that they qualified for incentives. Accordingly, the case for granting incentives for the Project is compelling, since, among other things, it involves an undertaking of substantially greater geographic scale and financial commitment. Further, the Commission has provided incentives to projects crossing only one state boundary and costing no more than $1 billion on the basis that the attendant siting and regulatory risks justify the treatment.63 By comparison, this Project, a six-state, multi-segment EHV transmission expansion project necessitating construction of over 2,000 miles of new transmission lines, substations and related facilities, at an estimated cost of $6 billion, must also satisfy the Order No. 679 eligibility requirements. b. Effects Once completed, the Project has the potential for realizing a number of benefits that are consistent with significant policy objectives of the Commission. As discussed in the Cupparo Affidavit, the Project is an integral part of the major transmission upgrades that are either being planned or are underway in the NTTG footprint to address regional reliability issues, reduce congestion, and provide transmission access to serve load by securing new energy supplies, including renewable energy resources, in a manner that is expected to lower the delivered cost of power for customers and to support compliance with RPS obligations in the western states. 63 See, e.g., Southern California Edison Co., 121 FERC ¶ 61,168 (2007), reh’g denied, 123 FERC ¶ 61,293 (2008) (granting ROE incentives for a set of transmission projects expected to cost $2.3 billion involving 450 miles of construction and linking two states) (“SCE”); PPL Electric Utilities Corp., et al., 123 FERC ¶ 61,068 (2008) (granting ROE incentives for a proposed jointly-owned 130-mile transmission project spanning two states and estimated to cost $900 million to $1 billion) (“PPL”). 28 Indeed, as described above, the Project is intended to alleviate many of the region’s major constrained interfaces previously identified in government studies as needing improvements. One key benefit of the Project will be to strengthen PacifiCorp’s existing ability to withstand outages, thereby improving the overall reliability of PacifiCorp’s transmission system, as well as that of the neighboring utilities. As the backbone for a future 500 kV infrastructure in the Project footprint, the Project is anticipated to improve the ability of the existing Western grid to transmit bulk power and to improve reliability, while at the same time preserving the existing reliability of the underlying lower voltage systems. The Project has the potential to reduce the need to curtail transmission schedules and associated energy access. Post-Project completion, PacifiCorp will likely also have the ability to increase deliveries of energy from reserve sharing pools in contingencies. With respect to congestion reduction, the Project is anticipated to have the effect of reducing the loading of highly used lines. This will prevent increased energy costs associated with line loading, which prevents low cost energy from being delivered to demand areas. By creating greater access from resource-rich areas to market access points, the Project has the ability to facilitate a more efficient energy market and to reduce overall consumer costs. The Project will also potentially contribute to reductions in overall net power costs and differentials in pricing between multiple market points, as supported by numerous studies, and will reduce overall line losses associated with lost generation needed to transport energy. This may ultimately increase the benefits of economically-based energy transfers. The Project also supports an important policy objective recognized by the Commission of encouraging companies to explore new ways of finding and delivering renewable resources.64 64 See PG&E, 123 FERC ¶ 61,067 at P 33. 29 The significant infrastructure provided by the Project will facilitate the diversification of energy resources, including renewables and traditional baseload resources and further the policy of domestic energy independence. In this context, the Project specifically offers the opportunity to further diversify intermittent resources on the grid with existing areas under development, which may reduce the need to carry unnecessary reserves. Moreover, by providing the necessary transmission to access location-constrained renewable resources, the Project supports compliance with state RPS objectives, to the extent that the acquisition of such resources is cost-effective.65 c. Risks and Challenges Without question, PacifiCorp faces significant financial and regulatory risks in developing and constructing a project of this magnitude. The Project constitutes precisely the major, non-routine investment that the Commission had in mind when it observed that “the most compelling case for incentive ROEs are new projects that present special risks or challenges, not “’routine investments made in the ordinary course’” of business.”66 (1) Financial Risk Compared to PacifiCorp’s previous years’ transmission expansion expenditures, the Project’s currently estimated $6 billion cost is substantial.67 As Mr. Cupparo explains, during 2002-2007, PacifiCorp spent an average of $111 million in capital expenditures annually on 65 By supporting one of the Commission’s policy objectives, the Project presents another independent basis on which the Commission can grant the requested incentives. See SCE, 121 FERC ¶ 61,168 at P 45 (2007) (“[T]he Commission . . . retains the discretion to grant incentives that promote particular policy objectives, unrelated to whether or not a project presents specific economic risks or challenges”) (citing Order No. 679-A, 117 FERC ¶ 61,345 at n. 37) (footnote omitted), Commissioner Wellinghoff concurrence at 2 (“In light of the broad and substantial benefits associated with increasing the availability of renewable energy resources, I believe that it is appropriate for the Commission to provide investment incentives in this area”). 66 SCE, 123 FERC ¶ 61,168 at P 38 (quoting Order No. 679-A, 117 FERC ¶ 61,345 at P 67 Cupparo Affidavit at ¶ 63. 60). 30 transmission projects; the average annual capital expenditure for the Project alone will be nearly seven to eight times greater than PacifiCorp’s annual transmission expenditures during these years.68 Moreover, the estimated $6 billion cost of the Project is more than three times PacifiCorp’s current transmission rate base of $1.8 billion, and is nearly double the cost of the next highest cost projects that have been granted incentives in response to petitions filed with the Commission.69 Several other factors contribute to the enormity of PacifiCorp’s financial risk in undertaking the development of the Project. First, PacifiCorp faces added risk by virtue of its “first in time” status. As described above, the Project provides for the establishment of a 500 kV transmission backbone that will improve reliability, reduce congestion, and provide access to renewable resources across the Project footprint. However, in providing this 500 kV backbone, PacifiCorp will be responsible for ensuring that the underlying system, within the Project’s geographic footprint of Wyoming, Idaho and Utah, can withstand technical and regulatory scrutiny, including the protection of neighboring electrical systems. Transmission developers that come after PacifiCorp within this footprint will have the benefit of PacifiCorp’s experience and technical upgrades. In this regard, PacifiCorp respectfully requests that the Commission recognize PacifiCorp’s substantial risk in its pursuit of its groundbreaking Project. The “first-in-time” phenomenon has been felt more acutely in PacifiCorp’s continuing efforts to enlist business partners in the development of the Project. As currently contemplated, the Project is capable of being upsized from a single-circuit to a double-circuit transmission expansion for greater regional benefit. However, whether the Project is upsized depends on 68 Id. 69 See, e.g., Cupparo Affidavit and Appendix B. 31 whether regional participants are willing and capable of sharing in its costs and risks. PacifiCorp continues to actively pursue third party equity partners, including investor-owned utilities and public power entities, to join discrete portions of the Project, so as to facilitate broader regional benefits. To date, however, such potential partners have been unwilling to fully commit to the development of an upsized project of the scale that is described in this Petition.70 PacifiCorp’s financial risk is also impacted by the fact that its approach to the Project’s development (siting the transmission lines ahead of the specific generation resources) departs from past conventional approaches to developing transmission projects. Given the current uncertainty of the role of conventional generation technology, and the inability of many renewable developers to finance significant transmission investments, transmission cannot be sited before specific generation resources have been developed. This approach presents greater additional risks for transmission investment than the historical norm: a risk that is only magnified by the scale and scope of the Project. Yet another risk factor that PacifiCorp faces in the development of the Project is the virtual certainty that the overall development costs, as measured in estimated 2008 dollars, will likely change for reasons beyond PacifiCorp’s control. As the Commission itself has recognized, the costs of construction have increased substantially over the past several years, and there is no expectation that these increases will abate in the near future.71 It is no secret that the costs of raw 70 PacifiCorp anticipates making its final decision for moving forward with the Project on a double- or single-circuit configuration basis later in the year. If no additional partners sign up as co-sponsors for portions of the Project by that date, PacifiCorp will necessarily proceed on its own. 71 See “Increasing Costs in Electric Markets,” Presentation, Commission Public Meeting June 19, 2008 at 7-9 (powerpoint slides showing dramatic increases in capital and raw material costs since 2000 for energy construction); Statement of Chairman Joseph T. Kelliher on Cost of Electric Generation Staff Presentation, June 19, 2008 (noting the reality that “higher capital costs (Footnote continued) 32 materials for energy infrastructure projects, such as iron, steel and copper, have increased substantially, as the potential buyers for these materials are not just electric and natural gas project developers in the United States, but are also developers located overseas. PacifiCorp also anticipates increasing labor costs as Project construction progresses. The bulk of the Project’s segments will be located in remote regions where the available labor supply is limited, and the specialized personnel otherwise required for the construction of a project of this size may not be easy to locate and hire. Obtaining and retaining the skilled labor necessary for the construction of the Project presents a significant cost escalation risk.72 (2) Regulatory Risk PacifiCorp faces significant regulatory risks relating to local, state, and federal approval and permitting processes that make its Project unique among previous incentive rate applicants. The fact that no fewer than six states are involved in authorizing portions of the Project, and that federal land management and tribal issues are implicated in its construction and development further demonstrate the unprecedented scope of the Project. While PacifiCorp is taking all necessary action to work with affected jurisdictions and their constituents, these proceedings are expected to be prolonged and contested. As such, obtaining all of the necessary approvals, in a timely cost-effective fashion, is far from certain. Any delay in obtaining the necessary local, state and federal approvals will jeopardize the reliability, congestion and environmental benefits associated with the Project. Such a risk presents the exact type of regulatory and political risk for new power plants, higher construction costs, and higher fuel costs – will continue for some time”). See Rebecca Smith, Costs to Build Power Plants Pressure Rates, WALL STREET JOURNAL, May 27, 2008 at B3 (noting the inflationary risks associated with energy project development). 72 Cupparo Affidavit at ¶ 70. 33 that the Commission has determined to be “relevant to determining whether [a transmission project] is routine.”73 Further, with large portions of the Project expected to traverse federally-administered lands, including in Idaho, Nevada, Oregon, Utah, and Wyoming, as well as through routes that are not situated on existing right-of-ways (“ROWs”), PacifiCorp faces added authorization complexities on a scale unlike previous transmission projects for which the Commission has granted requested rate incentives. ROW applications have been filed, or will be filed with the Bureau of Land Management (“BLM”) and the United States Forest Service (“USFS”), and other federal agencies, as applicable. These agencies will consider various factors during the review process, including alternatives to the Project, route alternatives and potential environmental impacts and mitigation measures. As an illustration, the Gateway West portion of the Project is not anticipated to obtain the necessary ROW authorization until late 2010 at the earliest, according to the BLM Project Manager.74 This introduces additional risk to the Project in the 73 BG&E Rehearing Order, 23 FERC ¶ 61,262 at n. 42. In light of escalating capital expenditure costs, PacifiCorp also faces potential litigation risk related to formal challenges seeking to limit any incentives that it may otherwise receive from the Commission after-the-fact. See “Complaint of the New England Conference of Public Utilities Commissioners, Inc., Seeking Limitation on Amount of Transmission Costs to which Incentive ROE Adder Applies,” Docket No. EL08-69-000 (June 12, 2008) (complaint filed under Section 206 of the FPA seeking to limit application of ROE cost adder for certain qualified projects in ISO-New England two years after Commission order originally granting incentives due to the escalating costs of the transmission projects qualifying for the ROE adder). 74 See Dustin Bleizeffer, Officials Lay Out Power Line Project, CASPER STAR-TRIBUNE (June 10, 2008), available at http://trib.com/articles/2008/06/10/news/casper/c4ad3235b59ce7158725746400009725.txt (quoting Wyoming BLM Project Manager). 34 form of siting delays and potential re-routing of various portions of the Project that will inevitably add to the overall cost and time completion of the Project.75 Finally, as noted earlier, state regulators will be asked to include in PacifiCorp’s retail rate base all of this transmission investment, including that portion that represents investments for reliability and future growth. PacifiCorp faces a risk that state regulators will not include all of the investment in retail rates if the benefits to retail customers are not proven to be sufficient. (3) Technology Risk The Project also faces uncommon technology-related risks because of PacifiCorp’s contemplated investment in several advanced transmission technologies that have not been widely deployed. Reliance on novel technologies inherently poses increased risks in the form of added uncertainty as to how they will perform within the context of the larger Project. As described in the Cupparo Affidavit and as noted further below, PacifiCorp plans on utilizing Trapezoidal Conductors, a newer form of technology that allows transmission lines to conduct at more than twice the accepted temperature limit of more conventional lines, as well as Fiber Optic Shield Wires that assist in enhancing the functionality and reliability of the Project’s transmission lines. The use of these and the other innovative technologies described herein must be designed, constructed and tested to ensure they meet the requirements of the Project. 2. The Total Package of Requested Incentives Are Necessary to Compensate PacifiCorp for the Unique and Substantial Risks Posed by the Multi-State Project As demonstrated herein, the Project represents the type of large scale interstate transmission project that Congress intended to encourage in EPAct 2005. From a broader policy perspective, granting PacifiCorp a 250 basis point ROE adder and authorization to seek 75 See PPL, 123 FERC ¶ 61,068 at P 37 (acknowledging that siting issues associated with securing ROE approvals “can be both protracted and challenging”). 35 prudently-incurred abandonment costs in a future rate filing fulfills and reinforces the goals of Congress of encouraging and compensating those who undertake significant regional bulk power transmission projects that benefit customers by ensuring reliability or reducing congestion.76 In addition, a favorable ruling on this Petition may attract greater participation from potential equity partners. The Project merits an ROE enhancement above and beyond all other project-specific ROE basis point adders previously approved by the Commission.77 As noted by Mr. Cupparo, it represents the largest, most ambitious transmission project when compared to other projects for which incentive rate treatment has been sought under Order No. 679 and its progeny, and this Petition demonstrates that the Project offers broad customer benefits by addressing regional needs and opportunities, including improved reliability, congestion reduction, transmission access for renewable resources and deployment of advanced transmission technologies.78 Granting PacifiCorp an ROE adder of 250 basis points reasonably compensates PacifiCorp and its investors for the unique and substantial risks attributable to the Project, and facilitates the completion of the Project by, among other things, encouraging PacifiCorp to devote the necessary management, regulatory and political attention in order to see this Project to fruition. As described below in the Advanced Technology Statement, PacifiCorp intends to use a number of advanced technologies, as defined by Section 1223 of EPAct 2005 and Order No. 679, in the construction of portions of the Project. PacifiCorp is investing in these technologies based 76 Order No. 679, 116 FERC ¶ 61,057 at P 7. 77 See Appendix B. 78 Cupparo Affidavit at ¶ 64 (“The projected capital investment is nearly double the highest capital investment projected among projects previously granted incentive rate treatment”). 36 on its expectation that they will improve reliability and project efficiency, just as the Commission intended in Order No. 679-A. However, as explained in the Cupparo Affidavit, using and obtaining the benefits of these advanced technologies pose several unique risks and challenges.79 As such, a portion of PacifiCorp’s 250 basis point ROE adder request is intended to help compensate for the costs of the portion of the Project utilizing such advanced technologies. In its ongoing efforts to develop and construct the Project, PacifiCorp will incur significant costs to determine whether the Project is feasible from a financial, environmental, regulatory and a siting perspective. Indeed, PacifiCorp anticipates spending approximately $70 million alone on continued planning, studies, and permitting and design activities associated with the Project. Accordingly, PacifiCorp requests authorization to recover 100 percent of its prudently incurred transmission–related development and construction costs in the event the Project is cancelled or abandoned, in whole or in part, due to an action or inaction by a governmental authority, regulatory agency, or for other reasons beyond PacifiCorp’s control. In Order No. 679, the Commission held that the abandoned plant rate incentive is an effective means to encourage transmission development by reducing the risk of non-recovery of costs.80 The incentive is available to any applicant that can show that any such abandonment is a result of factors beyond its control; this demonstration could be made in any subsequent section 79 Id. at ¶ 69. 80 Order No. 679, 116 FERC ¶ 61,057 at P 163; see also Order No. 679-A, 117 FERC ¶ 61,345 at P 115 (explaining that an abandoned plant incentive “may be needed (and requested) in advance of a project being approved through a regional planning process or receiving any necessary siting approvals. To the extent an applicant demonstrates that the incentives sought . . . are tailored to address the demonstrable risks and challenges of the applicant, we will permit recovery of such prudently-incurred costs”). 37 205 filings for recovery of abandoned plant.81 The Commission has in recent cases granted similar requests for such recovery.82 In previously granting a requested abandonment incentive where only two states were involved, the Commission noted that “[d]ependence upon approval by multiple jurisdictions introduces a significant element of risk to the [transmission p]roject that is not faced by utilities building transmission facilities within a single jurisdiction.”83 Given the scope and complexity of the Project, the same conclusion holds true in this circumstance. PacifiCorp submits that this incentive will be an effective means to encourage the completion of its Project. The Project faces several risks that no other applicant for rate incentives has encountered before, including approvals from six different states, along with various federal approvals from BLM and USFS. Moreover, the capital commitment that will be required in a time project of this magnitude will be substantial. PacifiCorp plans to capitalize its construction financing costs through accrual of AFUDC. However, under this approach, PacifiCorp will not be able to recover its expenditures related to the construction of the Project or to earn its allowed rate of return until the segments of the Project are placed in service. Because PacifiCorp is not seeking an incentive to include CWIP in rate base or the recovery of precommercial costs, it faces additional exposure related to its significant capital investment absent the incentive for recovery of costs in the event some or all of the Project was abandoned before being placed in service. 81 Order No. 679, 116 FERC ¶ 61,057 at PP 165-66. 82 See Allegheny Energy Inc., 116 FERC ¶ 61,058 at P 122 (2006), Southern California Edison Co., 112 FERC ¶ 61,014 at PP 58-61 (2005), reh’g denied, 113 FERC ¶ 61,143 (2005); Duquesne, 118 FERC ¶ 61,087 at P 61. 83 SCE, 121 FERC ¶ 61,168 at P 72. 38 As conceived, PacifiCorp is under no federal or state obligation to construct this scale of a project, other than general service obligations. However, PacifiCorp has voluntarily decided to move forward with its development for the reasons stated throughout this Petition. The overall risks associated with building the Project are not fully mitigated by an abandonment incentive. In contrast to past petitioners that have sought incentives under Order No. 679, PacifiCorp receives over ninety percent of its recovery on transmission investment through its native load retail ratemaking processes. As such, Commission-authorized transmission incentives, such as abandonment and CWIP, do not provide significant protection against loss of recovery of investment dollars for factors outside of PacifiCorp's control Accordingly, such an incentive could never compensate PacifiCorp for the costs incurred as a result of choosing to spend billions of dollars and several years on a regulated electric transmission project. Reducing PacifiCorp's requested 250 basis point ROE adder on the basis that it has been granted the abandonment incentive would misalign the scope of PacifiCorp's risks with its narrowly tailored incentive package. In Order No. 679-A, the Commission clarified that its nexus test is met when an applicant demonstrates that the total package of incentives requested is tailored to address the demonstrable risks or challenges faced by the applicant. The Commission further held that this nexus test is fact-specific and requires the Commission to review each application on a case-bycase basis. Consistent with Order No. 679,84 the Commission has consistently approved multiple rate incentives for particular projects85 in accordance with its policy that each incentive must be 84 Order No. 679, 116 FERC ¶ 61,057 at P 55. 85 See, e.g., Allegheny Energy, Inc., 116 FERC ¶ 61,058, at P 60, 122 (2006) (approving ROE at the upper end of the zone of reasonableness and 100 percent abandoned plant recovery); (Footnote continued) 39 justified by a showing that it satisfies the requirements of Section 219 and that there is a nexus between the incentives being proposed and the investment being made. The same result is warranted here. This Petition does not seek pre-commercial operational costs, CWIP or any other incentive described by the Commission. As a six-state utility, PacifiCorp has narrowly tailored its request to those incentives that will most efficiently facilitate the continued development of the Project, while accounting for the critical regulatory differences between PacifiCorp and other utilities in the West. For purposes of establishing retail rates, PacifiCorp applies an allocation methodology to determine how costs and revenues associated with PacifiCorp’s generation, transmission and distribution system will be assigned or allocated among its six state jurisdictions. PacifiCorp’s unique multi-state operations necessitates that it place a premium on ensuring consistency between state and federal ratemaking procedures. Accordingly, PacifiCorp has elected to forego any incentives that may compromise efficiencies and ratemaking clarity among its state jurisdictions, either in the short-term or in the long-term. PacifiCorp has demonstrated, consistent with Order No. 679-A, that the total package of incentives is tailored to address the demonstrable risks or challenges faced by the Project.86 The specific incentives sought by PacifiCorp are not mutually exclusive, and are in fact compatible because they serve different purposes. Granting the ROE incentive, together with abandoned plant recovery, will help PacifiCorp justify the extraordinary financial investment that will be required to build the Project. Duquesne, 118 FERC ¶ 61,087 at P 55 (granting an enhanced ROE, 100 percent CWIP, and 100 percent abandoned plant recovery). 86 Order No. 679-A, 117 FERC ¶ 61,345 at P 21, 27. 40 D. The Commission Should Authorize The Requested Incentives The Commission does not require that a utility demonstrate that a particular project would only be built if the requested incentives are obtained. Such a test would impose an impossible hurdle for applicants and would be inconsistent with the fundamental objective of Section 219 of the FPA and the Commission’s current policy of encouraging new transmission construction that helps ensure reliability of the bulk power transmission system and/or reduce the cost of delivered power by reducing transmission congestion.87 Therefore, the nexus between PacifiCorp’s proposed Project and the requested incentives should be viewed within the context of PacifiCorp’s commitment to the Project, and its overall commitment to improving reliability, reducing congestion, promoting renewable energy resource development and advanced transmission technology utilization, and the positive correlation between that commitment and the requested incentive rate treatment. The requested rate treatment will foster PacifiCorp’s continued commitment to such goals, consistent with important state and federal policy objectives. Indeed, denial of the requested rate treatment would be at odds with the objectives of Section 219 of the FPA, and the Commission’s policy of “encourage[ing] investors to take risks associated with constructing large new transmission projects that can integrate new generation and otherwise reduce congestion and increase reliability.”88 VI. ADVANCED TECHNOLOGY STATEMENT Order No. 679 requires applicants for incentive rate treatment to include a technology statement with their requests describing any advanced technologies that have been considered 87 Id. at P 25; Bangor Hydro Elec. Co., 117 FERC ¶ 61,129 at PP 93 and 105. 88 Order No. 679, 116 FERC ¶ 61,057 at P 24. 41 and, if not employed, an explanation of the reasons why they were not.89 Section 1223(a) of EPAct 2005 defines “advanced transmission technology” to mean “a technology that increases the capacity, efficiency, or reliability of an existing or new transmission facility . . .” and provides a non-exclusive list of examples that satisfy this definition.90 To the extent that a transmission project intends to use advanced technologies that will increase efficiency, and will enhance grid operations and reliability, thus contributing to system-wide benefits, the Commission will view favorably in its determination of whether the project is worthy of an incentive ROE adder. As noted in the Cupparo Affidavit, PacifiCorp is committed to optimizing the technology that will be utilized by the Project. Subject to further study and final engineering, PacifiCorp intends to utilize several types of advanced technologies in connection with various segments of the Project. All of these technologies meet the standard set forth in Order No. 679, and in Section 1223 of EPAct, as they mitigate congestion and enhance grid reliability by increasing the capacity, efficiency and reliability of an existing or new transmission facility. Falling into the following statutory categories of advanced conductor technology, enhanced power device monitoring, fiber optic technologies, power electronics and other technologies, PacifiCorp intends to invest in the following advanced technologies for use in its Project. 89 Id. at P 302. 90 EPAct 2005, § 1223(a). The Commission regards this statutory list as being illustrative of the kinds of technologies encouraged by Congress, but not otherwise exclusive of the advanced technologies that can determine whether a project is deserving of incentive rate treatment. Section 1223 also provides that advanced transmission technologies include any other related technologies that the Commission considers appropriate. 42 A. Advanced Technologies to be Used By the Project 1. Trapezoidal Conductor91 PacifiCorp intends on utilizing Trapezoidal Conductor technology in its Project. This technology involves the use of Aluminum Conductor Steel Supported/ Trapezoidal Wire (“ACSR/TW”), which can conduct at more than twice the accepted temperature limit of conventional Aluminum Conductor Steel Reinforced. The purpose of deploying such an advanced conductor design is to increase transmission capacity, and to reduce the sag of the transmission lines as well as reduced line energy losses. To this end, PacifiCorp commissioned an expert to compare and contrast several particular types of conductors under certain load factor assumptions to determine which offered the highest overall value for customers. The study revealed that the Lapwing TWD reduced line loss at a higher rate and with more overall benefit than the other conductors considered over the life of the Project’s facilities. The use of this technology provides long term benefits to customers and to connected generation. However, it also carries investment risk associated with any large capital expenditure depending on long term benefit streams. Nonetheless, PacifiCorp chose to undertake this risk in order to promote energy efficiency and to reduce the need for future resources which would have otherwise been needed to offset transmission line losses.92 PacifiCorp estimates that use of these advanced technologies on the Project’s proposed 500 kV lines will provide substantial incremental benefits over conventional alternatives. For example, as the Cupparo Affidavit explains, the ACSR-TW conductor will help avoid more than 120,000 MWhs of energy losses annually for the life of the Project over standard ACSR 91 Cupparo Affidavit at ¶¶ 51-52. 92 Cupparo Affidavit at ¶ 51. 43 conductor, and could approximately double those avoided losses for segments that are constructed to 500 kV double circuit configuration. As Mr. Cupparo further states, an estimated 60,000 to 120,000 metric tons of carbon dioxide (“CO2”) could be avoided annually for the base Project as a result of applying this technology.93 In this way, the Project’s use of advanced technology captures Commissioner Wellinghoff’s goal of “increase[ing] efficiency, enhanc[ing] grid operations and reliability, and result[ing] in greater grid flexibility, thus benefiting all users of the grid and ultimate consumers,”94 2. Static VAR Compensators95 PacifiCorp will use Static VAR Compensators (“SVCs”) in the Project. SVCs are electrical devices used to automatically match impedance to regulate voltage. SVCs also improve both dynamic and transient network stability, and are useful when placed near high and varying loads as they can smooth flicker voltage. The loadability of a transmission line is highly dependent on the line length. In order to increase line loadability and to balance phase voltages, PacifiCorp is evaluating the installation of SVCs on several Segments of the Project (including at several of the designated hubs). The intended use of SVC technology would not only support the required dynamic voltage regulation and the “firming up” of the system, it is also expected to improve reliability, power quality, contingency recovery, create operational benefits to support the deliverability of intermittent renewable energy sources as well as to help maximize the overall total transfer capability. The use of SVCs in the Project involves the use of relatively 93 Cupparo Affidavit at ¶ 52. 94 See, e.g., Potomac-Appalachian Transmission Highline, LLC., 122 FERC ¶ 61,188 (2008) (separate statement of Commissioner Wellinghoff at 2-4); PPL Electric Utilities Corp., 123 FERC ¶ 61,068 (2008) (separate statement of Commissioner Wellinghoff at 2). 95 Cupparo Affidavit at ¶ 53. 44 new solid state transient power and voltage control technology that helps avert the need for additional transmission infrastructure, including additional transmission line facilities, which would otherwise be needed solely to regulate voltage and to maintain system stability. 3. Fiber Optic Shield Wires96 PacifiCorp plans to use fiber optic technology in the Project. The use of this type of technology will provide several benefits that will enhance Project operations and efficiency. For example, PacifiCorp is planning to use fiber optic shield wires that will protect transmission lines by shielding phase conductors from direct lightning strikes. Fiber optic cable, in lieu of wave trap or microwave technology, allows a communications link to overhead transmission lines. In addition, shield wires with fiber optic cores enable the novel application of differential line protection, a superior technique borrowed from transformer protection that reliably detects short circuits. Fiber optic shield wires will also provide high-capacity, high-speed communication channels allowing system dispatchers to switch facilities remotely and reliably for voltage control, assist in the maintenance of grid reliability and security, and aid the engineering and maintenance staff in performing diagnostics of the remotely-located equipment. PacifiCorp is voluntarily incorporating the use of fiber optic technology to provide a more reliable communication path to operate the Project’s transmission facilities. The installation of fiber optic technology can also create additional latent capacity bandwidth, which while not currently anticipated to be used outside the operation of the transmission system, could also provide an alternate secure communication path that could be used for national security and regional development purposes. 96 Id. at ¶¶ 54-55. 45 4. Phase Shifters97 Phase shifters are intended to be utilized by PacifiCorp in the operation of the Project. Phase shifters improve and/or increase stability limits of transmission lines when the maximum power transfer is reached by changing the alternating current phase angle between the sending and receiving ends of the line. Specifically, the use of this technology maximizes the utilization of existing and newly installed transmission system assets by regulating alternating current (“AC”) power flows in both magnitude and direction. In this way, phase shifters help provide operational and seasonal flexibility, and allow the dispatch of flow patterns required to maximize the grid and to provide operational benefits during contingencies. PacifiCorp is pursuing targeted applications of this technology to reduce overall system losses by eliminating circulating currents, and helping to protect neighboring transmission systems. Phase shifters are a technology primarily used in the Western Interconnection due to the large number of highvoltage, long-distance transmission lines that are located in this region of the country. The use of phase shifters on the Project can reduce the detrimental impact of new transmission facilities on the existing underlying transmission system. Using this technology avoids the need for additional transmission infrastructure, including additional transmission line facilities, which would otherwise be needed solely to mitigate inadvertent transfer path flows on neighboring electric systems. 5. Special Protection Schemes98 PacifiCorp intends to employ Special Protection Schemes (“SPS”) to respond to system events and disturbance data that could potentially cause undue stress on its system. PacifiCorp 97 Id. at ¶¶ 56-57. 98 Id. at ¶ 58. 46 will employ advanced SPS technology as necessary to maximize grid total transfer capability, improve long-term reliability and reduce negative impacts to the interconnected systems, as well as to benefit the interim ratings of the lines. SPS technology will also be used to reduce the need for additional transmission infrastructure that would otherwise be needed only in extreme contingency situations. Despite having the benefit of avoiding redundant transmission construction, SPS technology places connected generation at risk for tripping to avoid creating an unstable system condition in the event of a transmission facilities outage. 6. Monitors for Transformers and Phase Shifters99 PacifiCorp is evaluating the use of advanced monitors in transformers at the new substations planned as part of the Project. PacifiCorp will employ the use of such technologies for real-time measurement and monitoring of dissolved combustible gases in oil filled equipment. This technology provides real-time monitoring of highly combustible gases (such as acetylene, hydrogen, methane and oxygen) that are dissolved in power equipment insulating oil, and will provide notification when the affected equipment is near failure. These monitors can improve the reliability of the Project, and can help insure that the transmission assets safely reach their useful expected life span. This technology, while not required by reliability standards, helps protect high-cost investments and improve reliability by providing for early detection of potential issues. B. PacifiCorp’s Decision to Forego the Use of Certain Advanced Technologies PacifiCorp considered, but does not currently plan to adopt, other types of advanced technologies. For example, PacifiCorp has evaluated the use of advanced composite core 99 Id. at ¶¶ 59-61. 47 conductors for the Project, and is using this technology on a limited basis on a small portion of Segment B by rebuilding an existing line with this technology to accommodate the new double-circuit 345 kV line. However, this technology is not economically justified on other portions of the Project, given the use of Trapezoidal conductor technology on the 500 kV facilities. In a similar vein, PacifiCorp decided to forgo the use of underground conductors on the Project, as the capital costs were multiples of overhead construction configurations, and would have rendered the Project economically unfeasible. Another type of technology that PacifiCorp has opted not to use in the Project is direct current (“DC”) technology. This technology will not be used so as to better optimize PacifiCorp’s ability to flexibly interconnect with the current and future additions to the existing alternating current system, and to best allow generation interconnection at intermediate points. The use of AC technology on the Project allows future projects to build off of the backbone that the Project will form in the Wyoming, Idaho, and Utah areas. DC technology can cause technology feasibility concerns when more terminals are used on a line. As such, a DC project can have a limited ability to interconnect with future projects and with generation additions at intermediate points. DC technology also may not have the direct benefit of strengthening the ability of the underlying network alternating current system to resist voltage stability disturbances. The AC configuration used on the Project will best meet these reliability and flexibility objectives. 48 Appendix A Affidavit of John Cupparo UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PacifiCorp ) ) Docket No. EL08-___-000 AFFIDAVIT OF JOHN CUPPARO ON BEHALF OF PACIFICORP 1 Appendix A Affidavit of John Cupparo Table of Contents Page I. INTRODUCTION AND EXPERIENCE.........................................................................3 II. PURPOSE...........................................................................................................................4 III. OVERVIEW OF PACIFICORP’S TRANSMISSION SYSTEM .................................4 IV. ENERGY GATEWAY TRANSMISSION EXPANSION PROJECT ..........................5 V. A. Overview .................................................................................................................5 B. Project Development..............................................................................................8 1. Walla Walla to McNary – Segment A ......................................................8 2. Populus to Terminal – Segment B ............................................................9 3. Mona to Limber to Oquirrh– Segment C ..............................................10 4. Windstar to Aeolus to Bridger – Segment D .........................................10 5. Bridger to Populus to Hemingway– Segment E ....................................11 6. Aeolus to Mona – Segment F...................................................................11 7. Sigurd to Red Butte to Crystal – Segment G.........................................11 8. Hemingway to Captain Jack– Segment H .............................................12 THE PROJECT IS THE RESULT OF A FAIR AND OPEN REGIONAL TRANSMISSION PLANNING PROCESS...................................................................12 A. Overview ...............................................................................................................12 B. The Project Has Been Designated By NTTG As A Critical Fast Track Project And Is Now Proceeding Through The WECC Process ....................................15 VI. THE PROJECT IS ELIGIBLE FOR INCENTIVES...................................................18 VII. ADVANCED TECHNOLOGIES ...................................................................................24 A. Trapezoidal Conductor .......................................................................................24 B. Static VAR Compensators (SVCs) .....................................................................25 C. Fiber Optic Shield Wires.....................................................................................26 D. Phase Shifters .......................................................................................................27 E. Special Protection Schemes.................................................................................27 F. Monitors for Transformers and Phase Shifters ................................................28 VIII. RISKS AND CHALLENGES FACED BY PACIFICORP..........................................29 Appendix A Affidavit of John Cupparo UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) PacifiCorp ) ) Docket No. EL08-___-000 AFFIDAVIT OF JOHN CUPPARO ON BEHALF OF PACIFICORP I. INTRODUCTION AND EXPERIENCE 1. My name is John Cupparo and I am Vice President of Transmission for PacifiCorp. My business address is 825 NE Multnomah Street, Portland, Oregon, 97232. 2. I have a Bachelor of Science degree in Computer Information Systems from Colorado State University. My experience spans 23 years in the energy industry, including oil, gas and electric utilities. The majority of my experience has been in information technology supporting natural gas pipelines, energy commodity trading and end-to-end electric utility operations. I have been employed at PacifiCorp since September, 2000. Prior to assuming my current position in August 2006, I was Chief Information Officer for PacifiCorp. My responsibilities have covered many aspects of utility operations – commercial and trading, outage management, customer service, transmission scheduling and regulatory issues. My experience within PacifiCorp includes management of multifunction organizations, large project delivery and resolving complex scheduling and contract scenarios. I am responsible for all aspects of PacifiCorp’s transmission investment strategy, customer service, main grid planning, contract administration and tariff management. I am the co-chair of the Northern Tier Transmission Group 3 Appendix A Affidavit of John Cupparo (“NTTG”) which coordinates transmission planning, and transmission expansion and project reviews with sub-regional and regional planning organizations within the Western Electricity Coordinating Council (“WECC”). II. PURPOSE 3. My Affidavit provides an overview of PacifiCorp’s transmission system and describes the new Energy Gateway Transmission Expansion Project (“Project”) for which PacifiCorp is seeking incentive rate treatment. Energy Gateway is a major, multi-state project designed to address regional reliability issues, reduce congestion, serve load, secure energy supply, and/or provide transmission access to new renewable energy resources in a manner that is expected to lower the delivered cost of power for customers and to meet RPS compliance obligations in the western states. My Affidavit describes the pressing need for investment in new transmission infrastructure in the West, as demonstrated by the Department of Energy’s (“DOE”) National Electric Transmission Congestion Study and other transmission studies. I will explain the process by which the company coordinates transmission planning and project review with stakeholders, including participation in the NTTG sub-regional and the WECC regional planning process. I also identify and explain the advanced technologies intended to be used by PacifiCorp as part of the Project. Finally, my Affidavit demonstrates the Project’s eligibility for incentives and describes the risks and challenges that the company faces in connection with the Project. III. OVERVIEW OF PACIFICORP’S TRANSMISSION SYSTEM 4. PacifiCorp is an indirect, wholly-owned subsidiary of MidAmerican Energy Holdings Company (“MidAmerican”). PacifiCorp provides delivery of electric power and energy 4 Appendix A Affidavit of John Cupparo to approximately 1.7 million electric customers in six western states. The company operates as Pacific Power in Oregon, Washington and California, and as Rocky Mountain Power in Wyoming, Utah and Idaho. PacifiCorp owns and operates approximately 15,494 miles of transmission lines ranging from 46 kV to 500 kV across ten states. As of December 31, 2007, PacifiCorp’s current net transmission plant in service is approximately $1.8 billion. PacifiCorp is interconnected with more than 80 generation plants and 15 adjacent control areas at approximately 124 points of interconnection. To provide electric service to its customers, PacifiCorp owns, or has interest in, generation resources directly interconnected to its transmission system with a system peak capacity of approximately 12,131 MW. This generation capacity includes a diverse mix of coal, hydro, wind power, natural gas-fired combined cycles and combustion turbines, and geothermal capacity. 5. Transmission capacity on PacifiCorp’s existing transmission system is at or near full utilization. The company’s most recent Integrated Resource Plan (“IRP”) identifies the need for investment in major new transmission facilities to meet forecasts of customers’ electricity usage, and to help satisfy renewable portfolio standards throughout its service territory. PacifiCorp’s existing transmission system, as well as the transmission grid across the western region, is severely constrained, and numerous regional study groups have identified the pressing need for investment in new transmission infrastructure. IV. ENERGY GATEWAY TRANSMISSION EXPANSION PROJECT A. Overview 6. The Project is a system-wide transmission expansion program, first announced by PacifiCorp in May, 2007. The Project will traverse six states, numerous communities and 5 Appendix A Affidavit of John Cupparo areas of federally-administered lands. Community outreach, siting, permitting and design work are underway for many segments of the multi-phased project that will add approximately 2,000 miles of new transmission lines and related improvements to the PacifiCorp transmission system. The Project will enhance reliability, reduce transmission congestion and improve the flow of electricity throughout the region. The Project’s 500 kV transmission lines will be the first such lines to be installed in the Project footprint (primarily Wyoming, Idaho and Utah), and the infrastructure will provide an essential reliability bedrock that will contribute to the addition of future 500 kV transmission lines in the region. 7. The Project will connect areas rich in energy resources to load centers, enabling access to markets for the development of new energy resources, including renewables. For example, Wyoming currently has more than 10,000 MW of wind resources associated with pending requests for interconnection to PacifiCorp’s transmission system. The Project will move power generated from these and other new renewable resources planned to be developed in Wyoming to customer growth areas in Wyoming, Utah and Oregon. 8. The Project is primarily driven by the long-term needs of PacifiCorp’s retail and network customers. Upgrades to core elements of the Project (e.g., installation of double-circuit, rather than single-circuit, 500 kV transmission lines) may be required if other participants express interest in portions of the Project (Idaho Power has agreed to participate in portions of Gateway West) or if the Company receives commitments from parties with pending requests for points of new interconnection. 6 Appendix A Affidavit of John Cupparo 9. The Project will provide the first direct interconnection between the Rocky Mountain Power and Pacific Power service areas, and it will help PacifiCorp ensure that its system is adequate and capable of meeting forecasted needs. PacifiCorp estimates that the entire project, or substantial elements of the project, will be completed in 2014, subject to schedule variations as necessary, at a cost of approximately $6 billion, as adjusted for inflation, and based on current estimates including Allowance for Funds Used During Construction (“AFUDC”)The Project is the first transmission investment of this scale in the western region in the last 15 years, and it represents a 330% increase to PacifiCorp’s current net transmission investment. 10. The Project is designed to provide an enhanced transmission delivery system utilizing major extra-high voltage (“EHV”) transmission lines. The Project will connect areas with abundant existing and potential generation resources, including renewables (“resource hubs”), with concentrated areas of customer load (“load centers”) throughout the PacifiCorp’s system, and it may enable future EHV projects within the region to rely upon and to expand this backbone infrastructure, if needed. The significant improvement to critical transmission capacity and the “hub and spoke” design will provide flexibility, improve efficiency and enable development of (and access to markets for) clean and renewal energy resources, such as wind. 11. The Project is a challenging undertaking. In terms of dollars of investment, miles of transmission lines and number of states traversed, the Project is larger than any of the recent transmission expansion projects presented to the Commission, and found eligible for incentives. 7 Appendix A Affidavit of John Cupparo B. Project Development 12. Development for a project of this magnitude must necessarily be undertaken in segments and the segments must be prioritized to maximize reliability and integration benefits, while incorporating the necessary flexibility in construction sequencing to prudently deliver all of the Project segments. The Project consists of eight segments located within four sub-regions, as shown on the Energy Gateway map provided in Exhibit No. 1. Project segments that offer similar general benefits and in-service dates have been grouped into levels of priority, with the goal of having the earliest prioritized groups in service and supporting the reliable construction of later groups. Project segments undertaken at the Priority One level are intended to reinforce reliable service to the company’s base load. Project segments undertaken at the Priority Two level are intended to support deliveries of wind energy and resource diversity. Project segments included in the Priority Three level are undertaken to enhance the integration of PacifiCorp’s east and west control areas, and to further support delivery of renewable energy. Project segments included in the Priority Four level are intended to provide reliability backup and ratings support for the grid. The priority levels allow PacifiCorp to exercise flexibility to adjust for cost and resource pressures and to accommodate potential third-party participation. 13. Priority level and transmission lines for each of the eight segments of the Project are summarized below. 1. Walla Walla to McNary – Segment A 14. A Priority One level project, Segment A is part of the Energy Gateway that will satisfy a transaction commitment made by MidAmerican in its acquisition of PacifiCorp, among other things. Estimated to cost $108 million, a 230 kV transmission line will run approximately 56 miles between Walla Walla, Washington and Umatilla, Oregon, and 8 Appendix A Affidavit of John Cupparo connect existing power substations at Walla Walla, Wallula and McNary. When completed in 2010, this segment will be the first leg of the Project to be placed in service, and it could be used to link existing and future sources of renewable resources. 2. Populus to Terminal – Segment B 15. Also a Priority One level project, Segment B is part of Gateway Central. Double circuit 345 kV transmission lines will run from a new Populus substation near Downey, Idaho, 135 miles south to the existing Terminal substation near the Salt Lake International Airport west of Salt Lake City, Utah. This segment is estimated to cost approximately $800 million and will be constructed in two sections. The first section will link the new Populus substation with the existing Ben Lomond substation north of Ogden, Utah. The second section will link Ben Lomond with the Terminal substation. Both sections of Segment B are anticipated to be placed in service in 2010, and are intended to deliver reliable power to the growing load demand along the Wasatch front in Utah. 16. PacifiCorp has submitted an application for certificate of public convenience and necessity for the Populus to Terminal transmission line and the new Populus substation to the Idaho Public Utilities Commission (“IPUC”), and a similar application for the transmission line to the Utah Public Service Commission (“UPSC”). PacifiCorp anticipates approval by October 2008 and September 2009, respectively. 17. Segment B will supplement a constrained path in Utah known as Path C. During its acquisition of PacifiCorp, MidAmerican agreed to increase transfer capacity on Path C by 300 MW. In fact, Segment B will increase transfer capacity by 1,400 MW when combined with other segments of the Project. As such, Segment B will significantly improve a point of constraint on the system that currently affects numerous transmission 9 Appendix A Affidavit of John Cupparo customers, strengthen reliability and enable the company to achieve the planned transfer capability rating of subsequent Project segments. 3. Mona to Limber to Oquirrh– Segment C 18. A Priority One level project, Segment C is part of Gateway Central. The new line, estimated to cost $425 million, will run approximately 86 miles north from the existing Mona substation in central Utah to two future substations (Limber and Oquirrh). Double circuit 500 kV/345 kV transmission lines are intended to improve reliability and operational flexibility of the electrical system, and to link distant generation resources to one of the fastest growing areas in Utah. Segment C fulfils and expands upon a prior transaction commitment. The Project is critical to achieving the planned transfer capability rating of subsequent Project segments. 4. Windstar to Aeolus to Bridger – Segment D 19. A Priority Two level project, Segment D is part of Gateway West. Segment D is expected to be jointly owned by PacifiCorp and Idaho Power. Segment D is estimated to cost $880 million. Two single circuit 230 kV transmission lines will run 156 miles from the new Windstar substation in eastern Wyoming southwest to a new Aeolus substation. From Aeolus, double circuit 500 kV/230 kV transmission lines will run 141 miles west to connect to the existing Bridger substation in western Wyoming. The 230 kV portion of the line from Aeolus to Bridger could be upsized to 500 kV if supported by queue customer commitments or new equity partner participation. Segment D, expected to be placed in service in 2014, is intended to access and deliver energy from new and existing generating resources, including renewable energy resources such as wind. 10 Appendix A Affidavit of John Cupparo 5. Bridger to Populus to Hemingway– Segment E 20. Segment E, part of Gateway West, is comprised of two sections with an estimated total cost of $1.02 billion. When both sections are completed, Segment E will run from a planned generation resource hub near Rock Springs, Wyoming, across Idaho to a point southwest of Boise, Idaho. The first section is a Priority Two level project that will link the new Bridger substation in Wyoming to the new Populus substation in Idaho via a single circuit 500 kV line. 21. The second section, a Priority Three project, will continue the single circuit 500 kV transmission line from Populus to a new Hemingway substation in western Idaho. The two segments of Gateway West (Segment D and E) will provide connections to Gateway South and Gateway Central, delivering energy from new and existing generating resources, including renewable energy resources such as wind in Wyoming, to load centers further west. PacifiCorp anticipates that portions of this section will be jointlyowned with Idaho Power and placed in service in 2014. 6. Aeolus to Mona – Segment F 22. A Priority Four level project, Segment F is part of Gateway South. The single circuit 500 kV transmission line, estimated to cost $764 million, will run approximately 395 miles from the new Aeolus substation in southeastern Wyoming southwest to the existing Mona substation in central Utah. The line could be upsized to a double circuit 500 kV line if warranted by queue customer commitments or new equity partner participation. 7. Sigurd to Red Butte to Crystal – Segment G 23. A Priority One level project, Segment G is part of Gateway South and is estimated to cost $754 million. The Segment G transmission line is approximately 280 miles and will connect the existing substation Sigurd (in central Utah) through the existing substation 11 Appendix A Affidavit of John Cupparo Red Butte (in southeast Utah) to the existing substation Crystal (north of Las Vegas, Nevada). The line linking these substations will be a single circuit 345 kV line, and is expected to be in service in 2013. Segment G will provide additional capacity and access to supplies from Wyoming to serve growing customer demand and it will improve the reliability and operational flexibility of the electrical system. If warranted by queue customer commitments or new equity partner participation, Segment G could be upsized to a 500 kV transmission line and/or an additional line segment connecting the Sigurd substation to the existing Mona substation, 50 miles north. PacifiCorp is actively working to determine the level of interest among potential third parties equity partners, including investor-owned utilities and public power entities, to help support upgrades that could facilitate broader regional benefits. PacifiCorp is also working with neighboring utilities to best interface at lowest cost through the WECC rating process. 8. Hemingway to Captain Jack– Segment H 24. A Priority Three level project, Segment H is part of the Westside portion of the Project and is expected to cost $786 million. The single circuit 500 kV transmission line will run approximately 375 miles from the existing Hemingway substation in western Idaho to the Bonneville Power Administration’s Captain Jack substation in Northern California. The line will provide access to the resource-rich areas of the Inland West with the growing population centers of the Pacific Coast. V. THE PROJECT IS THE RESULT OF A FAIR AND OPEN REGIONAL TRANSMISSION PLANNING PROCESS A. Overview 25. Due largely to failed or aborted efforts to develop regional transmission organizations in the West, the development and coordination of a definitive regional transmission 12 Appendix A Affidavit of John Cupparo planning process was slower to materialize than in some other areas of the country. The region, however, has developed a highly coordinated approach to regional planning and expansion that accommodates the existence of numerous sub-regional groups of utilities, and, in PacifiCorp’s view, satisfies the Commission’s requirements for a coordinated, open and transparent process that meets the planning principles stated in Order No. 890. Regional transmission planning and expansion within the West is coordinated under the auspices of the WECC. Three distinct, but coordinated, levels can be identified within the overall regional planning process: 1) the local planning processes of individual transmission providers, 2) the sub-regional planning processes of organized groups of utilities within the region, and 3) the regional planning processes of the WECC. 26. PacifiCorp’s local planning process is open and transparent. The company’s 2007 Integrated Resource Plan (“IRP”) is a long-term strategy to help ensure that PacifiCorp continues to provide reliable, least-cost service to its customers with consideration of risk and uncertainty. The IRP is informed by an analysis of the tradeoff between various resource options over a twenty-year period, as well as a collaborative public process with involvement from customer interest groups, regulators and other stakeholders. For example, from late 2005 though April 2007, the company held 13 public meetings with stakeholders to discuss important planning issues and to solicit comments on IRP analysis methods and assumptions. 27. PacifiCorp’s sub-regional planning process is also open and transparent. PacifiCorp is a member of the NTTG, a coalition of investor-owned and public utilities, state government agencies and customer groups that provides an open and transparent planning process for its transmission-owning members in the Pacific Northwest and 13 Appendix A Affidavit of John Cupparo Rocky Mountain states. NTTG coordinates transmission planning within its footprint with planning being undertaken by other sub-regional groups and with the Western Interconnection-wide planning efforts of the WECC. In addition to PacifiCorp, the NTTG sub-regional planning group includes Idaho Power, Deseret Power Electric Cooperative, NorthWestern Energy and Utah Associated Municipal Power Systems, and recently-joined Portland General Electric. The NTTG footprint includes approximately 2.7 million customers and more than 27,000 miles of transmission lines within Oregon, Washington, California, Idaho, Montana, Wyoming and Utah. 28. Exhibit No. 2 is a copy of the NTTG’s first annual report (“2007 Annual Report”). As explained in the 2007 Annual Report, stakeholder participation is important to the planning process. All interested parties are encouraged to attend and contribute to the many stakeholder meetings conducted by the NTTG transmission use, planning and cost allocation committees, and in preparing, developing and analyzing planning studies. The management arm of the NTTG – the Steering Committee -- is comprised of representatives of state regulatory commissioners, executive level utility representatives, and representatives of state consumer advocacy groups. 29. NTTG performs both reliability and economic planning coordination within its footprint, and works with the WECC Planning Coordination Committee for reliability planning and the WECC Transmission Expansion Planning Policy Committee for economic planning. In addition, NTTG coordinates and synchronizes its transmission expansion plan with neighboring sub-regional planning entities. 30. Transmission providers receive and act on requests for transmission service in accordance with their respective Open Access Transmission Tariffs. The 2007 Annual 14 Appendix A Affidavit of John Cupparo Report explains that transmission providers assess future load and resource developments to plan the evolution of an efficient transmission system, and to undertake reliability analysis and improvements. Where service requests and other identified needs call for the development of transmission that involves participation of multiple transmission providers within a sub-regional group’s footprint, the planning and analysis of improvements are coordinated at the sub-regional level. Projects that span greater distances are planned, analyzed and developed in coordination with other sub-regional groups or at the regional WECC level. 31. The WECC is responsible for coordinating and promoting electric system reliability for the vast region that spans the Western Interconnection, including the provinces of Alberta and British Columbia, the northern portion of Baja California, Mexico and all or portions of 14 western states. The regional planning process coordinated by WECC is designed to provide interested parties the opportunity to review and comment on proposed projects, and to solicit participation in the construction of the transmission lines. Several Project segments are completing the WECC planning process. B. The Project Has Been Designated By NTTG As A Critical Fast Track Project And Is Now Proceeding Through The WECC Process 32. All segments of the Project other than Segments A and C were planned, coordinated and approved by the NTTG Planning Committee. While the localized segments for Segments A and C were not explicitly incorporated into the NTTG Fast Track process, as described further, these segments will be incorporated into the NTTG biennial planning process. Due to the pressing need for critical transmission infrastructure, a Fast Track process was used by NTGG in advance of finalizing requirements for Attachment K of its Open Access Transmission Tariff. While the approval process was expedited to accommodate 15 Appendix A Affidavit of John Cupparo the critical need for timely transmission expansion, stakeholder participation was not comprised. Page 5 of the 2007 Annual Report, Exhibit No. 2 to my Affidavit, contains a summary of NTTG’s activities during 2007, including public stakeholder meetings and comment periods concerning the proposed Fast Track projects. 33. During 2007, NTTG undertook two parallel planning initiatives: 1) identification of Fast Track transmission expansion projects needed for reliability and to meet transmission service requests within the NTTG footprint, and 2) development of a prospective formal biennial planning process to be undertaken in conjunction with the Western Interconnection’s regional planning process. In order to quickly implement transmission expansion projects needed to meet immediate needs, the Fast Track process relied on studies previously done within the region to identify congested transmission that impedes efficient and reliable operation of the grid. The process provided a forum for stakeholder input and participation in the identification of Fast Track projects critical to relieving these areas of congestion and improving reliability. Organic agreements necessary for the going-forward biennial planning process were completed in 2007, and execution of the process began in January of 2008. The first NTTG biennial planning report is expected in the fourth quarter of 2009. 34. The 2007 Annual Report describes these parallel planning initiatives and identifies the Fast Track projects for the sub-region. As provided above, the projects identified under NTTG’s Fast Track process include all segments of the Project other than Segments A and C. Each sponsor of a Fast Track project is required to develop a technical study plan that, among other things, identifies interested and affected parties, provides a plan and schedule for coordinating with other regional and sub-regional planning groups, and 16 Appendix A Affidavit of John Cupparo performs required WECC regional planning review studies and ratings. The NTTG’s review of the Energy Gateway projects during the Fast Track process was coordinated with Northwest Transmission Assessment Committee, Columbia Grid, West Connect, and the WECC Transmission Expansion Planning Policy Committee. 35. Following the NTTG Planning Committee’s approval of the 2007 Annual Report and Fast Track recommendations, the Project (with the exception of Segments A and C) was submitted for WECC regional planning review. The regional planning review process is conducted by the WECC Planning Coordination Committee and is an open, transparent process that provides for stakeholder meetings and written comments in response to proposed projects. Following completion of the planning review, the three-phase facility rating process begins. During Phase I, studies are conducted to demonstrate the proposed non-simultaneous rating of the facilities. A comprehensive report is completed, and the proposed project’s facilities are granted a “planning rating.” During Phase II of the rating process, a “project review group” is established to evaluate the project’s plan of service. Other aspects of the project are also evaluated, including: i) further assessments of the planned rating, ii) effects on simultaneous transfer capability, and iii) impacts on neighboring systems. When this phase is completed, the project is given an “accepted rating.” Finally, during Phase III of the ratings process, WECC members and staff monitor the project as it is constructed. Phase III is completed when the facilities are placed in service. 36. As demonstrated in the letters from the WECC Planning Coordination Committee and Technical Studies Subcommittee included in Exhibit No. 3, the regional planning review process has been completed for Gateway West (Segments D and E) and Gateway South 17 Appendix A Affidavit of John Cupparo (Segments F and G). Segments A and H are currently in the regional planning review process. Some segments are not required to go through the regional rating process, however where segments may intersect, duplicate, or affect other proposed segments regional planning and rating is to occur. Segment C is not required to go through the WECC planning review process because this line is not likely to affect another system or line. Final facility ratings for Gateway West and Gateway South segments are expected in July of 2009. VI. THE PROJECT IS ELIGIBLE FOR INCENTIVES 37. The Commission deems a transmission project to be entitled to a rebuttable presumption of eligibility for transmission incentives if the project either (1) results from a fair and open regional planning process that considers and evaluates projects for reliability and/or congestion and is found acceptable to the Commission, or (2) has received construction approval from an appropriate state commission or siting authority. The Project, including any refinements or modifications resulting from completion of the WECC rating process or regulatory approvals, is the product of a coordinated local (PacifiCorp), sub-regional (NTTG) and regional (WECC) planning process that is fair and open and that considers a proposed project’s impact on reliability. PacifiCorp’s Petition requests that, subject to any modifications resulting from the coordinated regional planning and rating process, the Commission find that the Project is eligible for incentives. 38. By any measure, the Project’s eligibility for incentives is evident. The Project will be built to satisfy all WECC and North American Electric Reliability Council (“NERC”) planning and reliability standards for system adequacy and security, system modeling data requirements, system protection and control and system restoration. By adding 18 Appendix A Affidavit of John Cupparo critical EHV infrastructure to the bulk power transmission system, the Project will provide contingency capacity throughout the system, thereby enhancing reliability within the NTTG footprint and the broader region. NERC reliability standards require that the system operate under conditions that will withstand the next major facility electrical outage, or “n-1” outage. If the existing transmission system is equal to or higher in voltage to a new transmission addition, the new addition will not typically cause as drastic impacts to the system when an outage occurs. With the addition of major transmission facilities that are larger in voltage than the existing transmission system, a fully redundant transmission system must be constructed. This is the case for much of the Project (i.e., Segments D, E and F). 39. Another important feature of the Project is that it will directly link PacifiCorp’s east and west control areas, enabling the company to make efficient use of resources to meet its load and reserve obligations, as well as minimize congestion and relieve loading along paths between Wyoming and areas west and south. By adding interconnections and increasing transfer capacity throughout the system, the Project will reduce the need for curtailments resulting from overscheduled use, significantly improve access to generation resources to meet system demand and reserve obligations, facilitate a more diverse mix of available generation resources and assist in meeting renewable portfolio requirements. 40. The EHV transmission lines and use of advanced technology will allow long distance delivery of energy with reduced energy losses. The Project’s “resource hub-to-load center” design will enable better utilization of resources and create multiple options to serve customers. A significant benefit to the region as a whole is the establishment of the first 500 kV transmission “super-highway” within the Project footprint. With this 19 Appendix A Affidavit of John Cupparo backbone infrastructure in place in the footprint, future EHV transmission lines will likely face fewer engineering and system reliability obstacles. 41. PacifiCorp must provide network customers with adequate transmission capability that optimizes generation resources and provides reliable service. PacifiCorp’s decision to undertake the Project was driven by capacity shortages, network congestion, service obligations and the need to establish access to multiple resource types, including emerging renewable resources. Importantly, PacifiCorp considered many smaller scale projects with more limited risks and benefits, but these routine approaches were rejected because they would not have achieved the long-range system-wide benefits of the Project. 42. Ten-year forecasts from PacifiCorp’s recent annual IRPs have shown a steady and growing gap between existing resources and load/reserve obligations on the system. PacifiCorp’s network load obligation is expected to grow during the next ten years at an average annual rate of 2-3%. Renewable portfolio standards throughout PacifiCorp’s service territory have served to magnify the need for long-distance deliverability from resource hubs to load. Routine upgrades would not ensure long-term reliability and planning reserves. 43. The Western Governors and numerous regional study groups have been calling for new transmission construction for several years. In identifying the Fast Track projects recommended in the 2007 Annual Report, the NTTG Planning Committee reviewed many of these prior studies, including the 2004 Rocky Mountain Area Transmission Study (“RMATS”). The RMATS report was based on reviews by stakeholders, populated work groups of load forecasting, and resource/transmission additions 20 Appendix A Affidavit of John Cupparo developed under a production cost model operated by PacifiCorp to examine the value of potential transmission expansion under different generation scenarios. The RMATS report recommended that the most feasible transmission additions move forward, including a recommended expansion of PacifiCorp’s existing 345 kV transmission system from the Bridger substation in Wyoming to Utah and Idaho (identified as the “Bridger Expansion project”). While larger than the Bridger Expansion project recommended by the RMATS report, Energy Gateway West is similar in concept and will achieve the goals previously identified in the report. Relevant excerpts from the RMATS report are provided in Exhibit No. 4. 44. In August 2006, the DOE released the National Electric Transmission Congestion Study (“2006 DOE Study”), which examined transmission congestion and constraints nationwide. Within the Western Interconnection, DOE reviewed existing transmission studies, expansion plans and reliability assessments and examined historical data collected by the WECC, including hourly line flows. The 2006 DOE Study identified numerous paths and areas within PacifiCorp’s footprint where congestion currently exists or would result from future development of generation capacity in the Rocky Mountain area. The Bridger West line from Wyoming to Utah was specifically identified as currently one of the most heavily congested lines. Relying on projections from the Western Governors Association’s Clean and Diversified Energy Advisory Committee (“CDEAC”), the 2006 DOE Study finds that the Western Interconnection needs large additions to its transmission network to encourage development and export of electricity generated from the abundant coal and wind resources in the Montana-Wyoming area. The Project addresses the Bridger West constraints, as well as the need for major 21 Appendix A Affidavit of John Cupparo additions to the bulk power transmission system to support energy exports from Wyoming to loads located west and southwest. Relevant excerpts from the 2006 DOE Study are provided in Exhibit No. 5. 45. The Western Interconnection 2006 Congestion Assessment Study (“Congestion Assessment Study”), issued May 8, 2006 by the DOE Western Congestion Analysis Task Force, also identifies areas of congestion in the Rocky Mountain states. Based on 2005 load and resource forecasts and a production model, the Congestion Study Assessment forecasted that by 2008: • the Bridger West path (associated with Segment E of the Project) would be constrained at its limit 42% of the time in the most conservative gas price scenario; • Path C (associated with Segment B of the Project) would be constrained at its limit 7% of the time and heavily utilized in other hours; • the TOT 2C path (associated with Segment G of the Project) would be used at a level above 90% of its transfer capability 86% of the time; • TOT 4A path (associated with Segment D of the Project) would start showing signs of congestion in 2008 (hours at transfer limit), with the congestion significantly increasing as additional resources come on line in Wyoming; and • the Idaho-Northwest path (associated with Segment H of the Project) would start to show signs of congestion in 2008 (hours at transfer limit), with the congestion significantly increasing as additional resources come on line in Wyoming. Relevant excerpts from the Congestion Assessment Study are provided in Exhibit No. 6. 46. Reports initiated by the Western Governor’s Association (“WGA”) also show certain paths in PacifiCorp’s service territory (such as Segment C) to be constrained. The WGA and its working groups have also identified the important need to develop transmission projects throughout the West to access location-constrained resources. The WGA’s Transmission Task Force Report (“WGA Report”), dated May 2006, considered the location and availability of location-constrained renewable resources and the effect that 22 Appendix A Affidavit of John Cupparo timely transmission projects could have on increasing the percentage of renewable resources serving load in the West. The Project represents the type of coordinated and comprehensive transmission development that meets the critical need of linking remote renewable resources to load centers throughout the West. Relevant excerpts from the WGA Report are provided in Exhibit No. 7. 47. As early as 2002, congestion has been documented within PacifiCorp’s footprint. The 2002 DOE National Electric Transmission Congestion Study (“2002 DOE Study”) identified the Wyoming-Idaho interface as a major constrained interface and found that, under optimum use of system resources, the Wyoming-Northern Utah interface was congested during 50% or more of the hours during the year. Relevant excerpts from the 2002 DOE Study are provided in Exhibit No. 8. 48. Initiated by the Governors of Utah and Wyoming because of concerns that protracted regulatory uncertainties have left the industry reluctant to invest in new transmission infrastructure, the Seams Steering Group – Western Interconnection (“SSG-WI”) issued a study in 2005. The stakeholder-driven study found that investment in transmission infrastructure in the West is critical to efficient use of the region’s lower cost coal and wind generation. The SSG-WI study identified the Wyoming-Utah interface as a critical constraint. 49. The Project addresses these areas of congestion identified on the PacifiCorp transmission system in these studies. The Project brings two major export paths from resource rich Wyoming, each consisting of a targeted planned rating of 1,500 MW on each path for a total of 3,000 MW of total export capacity. The Project will facilitate the flow of electricity from resource hubs-to-load centers, and it will establish an EHV backbone 23 Appendix A Affidavit of John Cupparo transmission system to efficiently collect and connect existing and future resources and load centers. Having this critical EHV infrastructure in place also will greatly facilitate future EHV additions to the grid. VII. ADVANCED TECHNOLOGIES 50. PacifiCorp will be making use of technology as part of the Project to ensure that capacity, efficiency or reliability are maximized. Subject to further study and final engineering, the company intends to utilize several types of advanced technologies to mitigate congestion and enhance grid reliability. The advanced technologies fall under categories of: advanced conductor technology, enhanced power device monitoring, fiber optic technologies, power electronics and other technologies. A. Trapezoidal Conductor 51. Aluminum conductor steel supported trapezoidal wire conductors can conduct at more than twice the accepted temperature limit of conventional aluminum conductor steel reinforced conductors. Use of this advanced conductor design will increase transmission capacity and reduce the sag of the transmission lines, as well as reduce line energy losses. PacifiCorp commissioned an expert to compare and contrast five or more particular types of conductors under certain load factor assumptions to determine which offered the highest overall value for customers. The study showed that the Lapwing Trapezoidal Wire same Diameter (recently renamed as Trapezoidal Wire “Athabaska”) reduced line losses at a higher rate and with more overall benefit than the other conductors considered over the life of the facilities. Use of this technology provides long term benefits to customers and those with interconnected generation but at a higher upfront cost. Use of the technology, however, carries investment risk associated with the large capital 24 Appendix A Affidavit of John Cupparo expenditure required. PacifiCorp chose to undertake this risk to further energy efficiency and to reduce the need for future resources that otherwise would be needed to offset transmission line losses. 52. PacifiCorp estimates that use of the advanced technologies on the proposed 500 kV transmission lines will provide substantial incremental benefits over conventional alternatives. PacifiCorp estimates that use of these technologies will help avoid more than 120,000 MWhs of energy losses annually for the life of the Project over more standard technologies, and could approximately double those avoided losses for segments that are constructed to 500 kV double circuit configuration. An estimated 60,000 to 120,000 metric tons of carbon dioxide (“CO2”) emissions could be avoided annually for the base Project through the utilization of this technology over more conventional utility applications. B. Static VAR Compensators (SVCs) 53. SVCs are electrical devices used to automatically match impedance to regulate voltage. In addition, SVCs improve both dynamic and transient network stability, and are useful when placed near high and varying loads where they can smooth flicker voltage. The transfer capability of a high voltage transmission line is highly dependent on the line’s length. In order to increase line transfer capability and balance phase voltages, PacifiCorp is evaluating the installation of SVCs at several of the Project hubs, which would support the required dynamic voltage regulation and firm up the system. The intended use of SVC technology would not only support the required dynamic voltage regulation and the “firming up” of the system, it would also improve reliability, power quality, contingency recovery, create operational benefits to support the deliverability of intermittent renewable energy sources as well as would help maximize the overall total 25 Appendix A Affidavit of John Cupparo transfer capability. The use of SVCs as part of the Project relies on relatively new solid state transient power and voltage control technology to avoid the need for additional transmission infrastructure, including additional transmission line facilities, which would otherwise be needed solely to regulate voltage and maintain system stability. C. Fiber Optic Shield Wires 54. PacifiCorp is planning to use fiber optic shield wires to protect transmission lines by shielding phase conductors from direct lightning strikes. Fiber optic cable, in lieu of, or as complement to, wave trap or microwave technology, allows a communications link to overhead transmission lines. Furthermore, shield wires with fiber-optic cores enable the novel application of differential line protection, a superior technique borrowed from transformer protection that reliably detects short circuits. Fiber optic shield wires also provide high-capacity, high-speed communication channels allowing system dispatchers to switch facilities remotely and reliably for voltage control and to maintain reliable grid operation and security. In addition, these same channels will aid engineering and maintenance staff in performing diagnostics of the remotely-located equipment. 55. While not required by standard, PacifiCorp is incorporating the use of fiber optic technology to provide a more reliable communication path to operate the transmission facilities. The installation of fiber optic technology can also create additional latent capacity bandwidth, which while not currently anticipated to be used outside the operation of the transmission system, could also provides an alternate secure communication path that could be used in the interest of national security and regional development. 26 Appendix A Affidavit of John Cupparo D. Phase Shifters 56. Phase shifters improve and/or increase stability limits of transmission lines when the maximum power transfer is reached by changing the alternating current phase angle between the sending and receiving ends of the line. Specifically, the use of this technology maximizes the utilization of existing and newly installed transmission system assets by regulating alternating current (“AC”) power flows in both magnitude and direction. In this way, phase shifters help provide operational and seasonal flexibility, and allow the dispatch of flow patterns required to maximize the grid and to provide operational benefits during contingencies. PacifiCorp is pursuing targeted applications of this technology to reduce overall system losses through elimination of circulating currents and help protect neighboring transmission systems. Phase shifters are a technology primarily used in the Western Interconnection due to the high-voltage, longdistance lines in order to reduce phase shifting between the sending and receiving ends of the lines. 57. The use of phase shifters on the Project can reduce the detrimental impact of new transmission facilities on the existing underlying transmission system. Using this unique technology avoids the need for additional transmission infrastructure, including additional transmission line facilities, which would otherwise be needed solely to mitigate inadvertent flows on neighboring electric systems. PacifiCorp anticipates that this technology will help the Project to achieve an efficient integration with the Western Interconnection. E. Special Protection Schemes 58. PacifiCorp will employ Special Protection Schemes (“SPS”) to respond to system events and disturbance data that could potentially cause undue stress on its system. SPS 27 Appendix A Affidavit of John Cupparo technology will help PacifiCorp maximize grid total transfer capability, improve longterm reliability, and reduce negative impacts to the interconnected systems, as well as to benefit interim ratings as bulk transmission systems are ultimately built out over a period of time. F. Monitors for Transformers and Phase Shifters 59. PacifiCorp is evaluating the use of monitors in transformers at the new substations planned as part of the Project. PacifiCorp will employ the use of such technologies for real-time measurement and monitoring of dissolved combustible gases in oil filled equipment. Such technology provides real-time monitoring of highly combustible gases (such as acetylene, hydrogen, methane and oxygen) that are dissolved into power equipment insulating oil, and will provide notification when the affected equipment is near failure. These monitors can improve the reliability of the Project, and can help insure that the transmission assets reach their useful expected life spans. While not required by reliability standards, the use of monitors helps protect high-cost investments and improve reliability by providing for early detection of potential issues. 60. Other advanced technologies were considered by PacifiCorp, but not selected for this Project. For example, PacifiCorp evaluated the use of advanced composite core conductors, and we are using this technology on a limited basis on a small portion of Segment B by rebuilding an existing line with this technology to accommodate the new double-circuit 345 kV line. However, this technology is not economically justified on other portions of the Project, given the use of Trapezoidal conductor technology on the 500 kV transmission facilities and new line construction. Similarly, PacifiCorp decided to forgo the use of underground conductors, as the capital costs were multiples of 28 Appendix A Affidavit of John Cupparo overhead construction configurations and would have rendered the Project economically unfeasible. 61. Direct current (“DC”) technology was not used on the Project in order to optimize PacifiCorp’s ability to flexibly interconnect the current and future additions to the existing alternating current system and to best allow generation interconnection at intermediate points. The use of AC technology on the Project also allows future projects to build off of the backbone that the Project forms in the Wyoming, Idaho and Utah areas. DC technology can cause feasibility concerns the more terminals are used on a line, and as such can limit the ability of a direct current project to interconnect with future projects and generation additions at intermediate points on a direct current project. DC also may not have the direct benefit of strengthening the ability of the underlying network alternating current system to resist voltage stability disturbances. The alternating current configuration used on the Project will best meet these reliability and flexibility objectives. VIII. RISKS AND CHALLENGES FACED BY PACIFICORP 62. As noted previously, PacifiCorp is requesting the following incentives, each of which would be established in a future Section 205 rate case: 1) a 250 basis point adder to the PacifiCorp base ROE applicable to investment in the Project, and 2) authorization to recover prudently-incurred abandonment costs if the Project is abandoned for reasons beyond PacifiCorp’s control. 63. The requested incentives are rationally related to PacifiCorp’s investment in the Project, which is a major undertaking that inherently carries with it complexity and tremendous challenges and risks. PacifiCorp’s net transmission plant in service as of December 31, 29 Appendix A Affidavit of John Cupparo 2007 was approximately $1.8 billion. The company’s projected investment of $6 billion in the Project represents an increase in current net transmission plant of approximately 330%. When compared to PacifiCorp’s previous years’ transmission expansion budget, the estimated $6 billion cost of the Project is also substantial. In the five previous years (2002-2007), PacifiCorp expended an average of $111 million in capital expenditures per year on transmission projects. The average annual capital expenditure for the Project alone will be nearly seven to eight times greater than PacifiCorp’s historical annual capital expenditure budgets for all transmission. 64. In terms of investment, transmission miles and number of states traversed, the Project is larger than any other transmission project that has been proposed for incentive rate treatment to date. The projected capital investment for PacifiCorp is nearly double the highest capital investment projected among projects previously granted incentive rate treatment. The Project will result in construction of approximately 2,000 miles of EHV transmission lines traversing six states and federally-administered lands. The largest of the projects previously proposed for incentive rate treatment have proposed 550 miles of new transmission lines traversing, at most, four states. By all of these objective measures, the Project is larger, more complex and carries greater challenges and risks than any transmission expansion project previously approved for incentives by the Commission. 65. Given the scale and scope of the Project, it faces significant regulatory risks at local, state and federal levels. The Project requires siting/permitting approval of six state jurisdictions: Idaho, Nevada, Oregon, Utah, Washington, and Wyoming, as well as federal land management agencies for the various Project segments traversing federally- 30 Appendix A Affidavit of John Cupparo administered lands, and coordination with affected tribal interests. PacifiCorp will also face significant financial risks when it seeks rate recovery for its investment in the Project from its state regulators. PacifiCorp will ask all of the transmission investment for the Project to be included in PacifiCorp’s rate base for delivered retail electric service. However, PacifiCorp faces a risk that state regulators will not include all of the investment in retail rates if the benefits to retail customers are not proven to be sufficient. To the extent that state regulators permit the recovery of all of the transmission investment in retail rate base, PacifiCorp will credit FERC-jurisdictional transmission revenues, including any revenues associated with incentives granted by the Commission, against its retail revenue requirement. Thus, the incentives authorized by FERC could be an important consideration in the state regulators’ determination of whether to include PacifiCorp’s entire investment in the Project in retail rates. 66. The Project’s departure from conventional designs used in the past also represents a financial risk. The Project involves siting transmission lines to resource-rich areas, but prior to the actual siting of specific generation projects. This represents a departure from past conventional approaches to developing transmission. The novel approach and design of the Project presents investment risks greater than the historical norm, a risk that is magnified by the scale and scope of the Project. 67. PacifiCorp faces business, financial and technical risk by virtue of the “first in time” status for constructing a 500 kV transmission backbone within the Project footprint. In providing this 500 kV backbone, PacifiCorp will be responsible for ensuring that the underlying system can withstand technical and regulatory scrutiny, including the protection of neighboring electrical systems. 31 Appendix A Affidavit of John Cupparo 68. Large portions of the Project are expected to be routed through federally-administered lands, including in Idaho, Nevada, Oregon, Utah and Wyoming. Right-of-Way (“ROW”) applications have been filed with the Bureau of Land Management (“BLM”) and the United States Forest Service. These agencies will now consider various factors during the review process, including alternatives to the Project, route alternatives and potential environmental impacts and mitigation measures. These proceedings are expected to be prolonged, complex, controversial, and likely contested. As such, obtaining the necessary approvals is far from certain. Any delay in obtaining the necessary local, state and federal approvals will jeopardize the realization of reliability, congestion and environmental benefits associated with the Project. 69. The Project also faces risks in connection with the use of several advanced transmission technologies that have not been widely deployed. Reliance on novel technologies inherently poses increased risks in the form of added uncertainty as to how they will perform within the context of this large project. As described above, the Project will use Trapezoidal Conductors, a new form of technology that allows transmission lines to conduct at more than twice the accepted temperature limit of more conventional lines, as well as Fiber Optic Shield Wires that assist in enhancing the functionality and reliability of the Project’s transmission lines. The use of these and the other advanced technologies described in this Affidavit must be designed, constructed and tested to ensure they meet the requirements of the Project. 70. Escalation in land, material and labor costs presents increasing challenges and risks to PacifiCorp as it moves forward with the Project. Costs for land and materials have increased 20% in the last year alone. Steel costs have increased 40%. Across the globe, 32 Appendix A Affidavit of John Cupparo demand for labor and materials needed for major transmission expansion projects is outpacing supplies driving costs upward. The downturn in the domestic economy and the value of the US dollar exasperates the situation. 71. In conclusion, whether compared to PacifiCorp’s current net transmission rate base or historical annual transmission investment, or whether compared to the transmission expansion projects previously proposed by other companies, the Project is one of enormous size, scale and scope. As it moves forward with this major project, PacifiCorp faces significant business, financial, regulatory and technological challenges and risks. Moreover, the Project is a voluntary undertaking on the part of PacifiCorp and its parent MidAmerican, a company with many investment opportunities. 72. Further affiant sayeth not. 33 EXHIBIT 1 Energ y Gateway Status Update June 2008 PacifiCorp remains fully committed to the Energy Gateway transmission expansion project, which holds benefits for both its customers and the region. The company is moving on track to best meet the originally announced in-service dates, and is actively pursuing outreach, permitting, planning and design work to meet these goals. PacifiCorp also is incorporating flexibility into later priority segments that may be impacted by external factors. The priority levels below reflect current schedules based on what the company has learned in the first year of implementation, and retains the flexibility to adjust as needed to accommodate cost and resource pressures and the participation of third parties. For more information, please visit www.pacificorp.com/energygateway, or contact Darrell Gerrard, Pacific Power vice president of transmission system planning, at 503-813-6994. A G AT E WAY W EST H WYO M IN G E D G AT E WAY CENTRAL E B F C S PacifiCorp service area Planned transmission lines 500 kV minimum voltage A G G A T E O U T H Y W 345 kV minimum voltage 230 kV minimum voltage Transmission hub Substation Generation plant/station Priority One Base Load Service and Reliability Priority Two Wind Integration and Resource Adequacy Priority Three Integrated Control Area and Renewable Energy Delivery Priority Four Reliability Backup and Rating Support • Segment B (Populus to Terminal 345 kV), 700 MW – 2010 & 1,400 MW – 2014 • Segment A (Walla Walla to McNary 230 kV), 400 MW – 2010 • Segment C (Mona to Oquirrh 500 kV), 1,500 MW – 2012 • Segment G (Sigurd to Crystal 345 kV), 400-600 MW – 2013 • Segment D/E (Windstar to Populus 230/500 kV), 1,500 MW – 2012-14 • Segment E (Populus to Midpoint/Hemingway 500 kV), 1,500 MW • Segment H (Hemingway to Captain Jack 500 kV), 1,500 MW • Segment F (Mona to Aeolus), 1,500 MW EXHIBIT 2 NORTHERN TIER TRANSMISSION GROUP Annual Planning Report – 2007 April 2, 2008 Preface This report was prepared by Comprehensive Power Solutions, LLP, as part of its facilitation and coordination work for the Northern Tier Transmission Group. The members and other stakeholders participating in the effort to provide coordinated, efficient and effective planning for expansion of transmission within the Northern Tier footprint have been helpful in developing the content of this report. While the report is made available to the public, neither Northern Tier or CPS accepts any duty of care to third parties who may wish to make use of or rely upon information presented in this report. CPS has exercised due and customary care in developing this report, but has not independently verified information provided by others and makes no further express or implied warranty regarding the report’s preparation or content. Consequently, CPS and Northern Tier shall assume no liability for any loss due to errors, omissions or misrepresentations made by others. This report may not be modified to change its content, character or conclusions without the express written permission of CPS and Northern Tier. i Preface | 2007 Annual Planning Report To ensure efficient, effective, coordinated use and expansion of the members’ transmission systems in the Western Interconnection to best meet the needs of customers & stakeholders. Figure 1: Map of Northern Tier Member Transmission Lines 2007 Annual Planning Report | Preface ii Contents Preface........................................................................................................................................... i Contents....................................................................................................................................... iii Figures ......................................................................................................................................... iv Summary....................................................................................................................................... 1 Background ................................................................................................................................... 2 The Northern Tier Transmission Group ........................................................................................ 4 NTTG – Chronology of 2007 Activities .......................................................................................... 5 Transmission Queue – NTTG Companies .................................................................................... 6 The Northern Tier Fast-Track Planning Process .......................................................................... 7 The NTTG Fast-Track Projects ..................................................................................................... 8 NTTG Project Development Timelines ....................................................................................... 10 The Sub-Regional Planning Process .......................................................................................... 11 Relationships among Planning Entities in the West .................................................................... 12 Regional and Sub-Regional Planning Timelines ......................................................................... 14 Details of the Northern Tier Transmission Projects .................................................................... 15 Hemingway to Boardman Transmission Project ......................................................................... 16 Hemingway to Captain Jack Transmission Project ..................................................................... 17 Southwest Intertie Project (SWIP) North ..................................................................................... 18 Mountain States Transmission Intertie Project ........................................................................... 19 Gateway West Transmission Project .......................................................................................... 20 Gateway South and TransWest Express .................................................................................... 21 Gateway Central Transmission Project ....................................................................................... 22 NorthernLights Transmission Project – Inland Project ................................................................ 23 Internet Links and Other References .......................................................................................... 24 Regional Planning .................................................................................................................................... 24 Sub‐Regional Planning ............................................................................................................................ 24 Northern Tier Transmission Group Members ......................................................................................... 24 Integrated Resource Plans ...................................................................................................................... 25 Additional Information for Northern Tier Transmission Projects ........................................................... 25 iii Contents | 2007 Annual Planning Report Figures Figure 1: Map of Northern Tier Member Transmission Lines ....................................................... ii Figure 2: Structure of the Northern Tier Transmission Group ....................................................... 4 Figure 3: Northern Tier Transmission Request Queue ................................................................. 6 Figure 4: Northern Tier Fast-Track Project Map with Potential Resource Additions ..................... 8 Figure 5: Map of Fast-Track Transmission Showing Voltage & Points of Connection .................. 9 Figure 6: Development Timelines for Northern Tier Projects ...................................................... 10 Figure 7: Three-level Planning Process in the Western Interconnection .................................... 12 Figure 8: Timelines for Regional & Sub-Regional Planning ........................................................ 14 Figure 9: Proposed Transmission Projects as of December 2007 .............................................. 15 Figure 10: Map of Hemingway-to-Boardman Transmission Project ........................................... 16 Figure 11: Map of Hemingway to Captain Jack Transmission Project ........................................ 17 Figure 12: Map of Southwest Intertie Project (SWIP) ................................................................. 18 Figure 13: Potential Route of MSTI (Dashed Line) ..................................................................... 19 Figure 14: Map of the Gateway West Transmission Project ....................................................... 20 Figure 15: Map of Gateway South and TransWest Express Proposed Study Areas .................. 21 Figure 16: The Gateway Central Transmission Project .............................................................. 22 Tables Table 1: Existing and Prior Regional Transmission Studies ......................................................... 2 Table 2: Chronology of NTTG Activities in 2007 ........................................................................... 5 Table 3: Fast-Track Project Data .................................................................................................. 9 2007 Annual Planning Report | Figures iv Summary The Northern Tier Transmission Group was formed in the autumn of 2006 to establish a subregional planning process that would meet the needs of its members by coordinating the operation and expansion of transmission to serve customers and wholesale power markets. Northern Tier is also intended to meet the mandate set forth in the Federal Energy Regulatory Commission’s Order No. 890, to provide greater transparency to regional transmission planning. Northern Tier is a combined effort of transmission providers, state regulatory agencies, and other stakeholders. This document is a first annual report on the organization, structure, activities, accomplishments and future plans for coordination and planning of transmission within the geographic footprint defined by the members’ systems. Following an overview of Northern Tier, this report describes the development and execution of a Fast Track Project Process to expedite needed transmission additions without waiting for design and development of a more permanent Biennial Planning Process. A primary intent in forming the Northern Tier Transmission Group was to implement needed transmission projects and initiatives quickly, without being held back by the time-consuming and delaying processes that plagued development of RTO West and GridWest. The objective was to develop required organizational structures as needed, but in parallel with production of work products. The Fast Track Project Process was used in 2007 to identify projects needed for reliability and to meet Transmission Service Requests. The Fast Track Process, open to stakeholder input and participation, was pursued at the same time that a more formalized Northern Tier Transmission Group Sub-Regional Planning process was designed to dovetail with the Western Energy Coordinating Council’s Regional Planning Process. Other transmission providers, which would join the Northern Tier Transmission Group over time, were developing their own projects that, with their membership, would be included in the Northern Tier portfolio. Development of these synchronous planning processes, designed to meet requirements of the Federal Energy Regulatory Commission’s Order 890, are now complete but would have delayed needed transmission planning. 2007 saw the development of individual transmission providers’ Order 890, Attachment K, filings, which defined their individual processes, and the development of Northern Tier’s Biennial Planning Process. The Northern Tier Projects are comprised primarily of 500 kV lines designed to connect the energy resource-rich regions of the Inland Northwest with the customer loads of the Pacific Northwest and Southwest, and the growing demands of Intermountain population centers. 1 Summary | 2007 Annual Planning Report Background Between 2001 and 2006, a series of transmission planning processes took place in the Western Interconnection. Among these were the SSG-WI (Seams Steering Group – Western Interconnection) framework, and the RMATS (Rocky Mountain Area Transmission Study), which led to creation of the Rocky Mountain Sub-regional Planning Group. The Western Governors Association, in addition to the RMATS initiative, promoted the CDEAC (Clean and Diversified Energy Advisory Committee) and the WGA Study (Conceptual Plans for Electricity Transmission in the West). Table 1: Existing and Prior Regional Transmission Studies WGA: Conceptual Plans for Electricity Transmission in the West SSG-WI: Seams Steering Group – Western Interconnection NTAC: Canada-NW-California Transmission Study Colorado Long-Range Transmission Planning Study Nevada State Office of Energy – T4 Wind Project RMATS: Rocky Mountain Area Transmission Study Montana-Northwest Transmission Equal Angle Report West of Hatwai System Upgrade Projects Canada-to-Northwest Intertie Expansion WECC Coordinated Phase Shifter Operation Western Interconnection 2006 Path Utilization Study (Dept. of Energy) CDEAC: Clean and Diversified Energy Advisory Committee Initiative A Northern Tier Transmission initiative was announced on October 11, 2006, and its initial meeting was held November 8, 2006. Northern Tier was initiated by members of the Grid West regional transmission organization that remained following a number of departures in 2006, in order to carry on several beneficial initiatives that were underway, including coordinated subregional planning, common assured transfer capability methods and coordination, and a diversity interchange for area control errors. Its participants were involved in the RMATS project, which identified several needed expansion projects that now form the core of the Northern Tier Transmission Projects, as well as the ACE Diversity Interchange initiative. 2007 Annual Planning Report | Background 2 The Northern Tier initiative led to formal creation of the Northern Tier Transmission Group as a sub-regional planning group and a part of the Western Energy Coordinating Council’s Transmission Expansion Planning Policy Committee efforts. The Transmission Expansion Planning Policy Committee was, like the Northern Tier Transmission Group, formed in response to the direction the federal government was taking in the FERC’s Order 890 promulgating regional and sub-regional transmission planning. The objectives of Order 890 were to promote coordination, openness, transparency, information exchange, interconnection-wide participation, and dispute resolution. In early 2007, the Northern Tier transmission providers undertook two parallel planning initiatives: Task I, to identify Fast Track projects, and a concurrent Task 2, to develop a biennial planning process in conjunction with the regional planning process being established by the Transmission Expansion Planning Policy Committee and the planning processes being set up by the other sub-regional groups within the Western Interconnection. In 2007, Northern Tier completed the Task 1 Fast Track Project Identification and, for Task 2, completed the Biennial Planning Process Charter and Planning Agreement, and established the organizational structure to carry out the task. Execution of the Biennial Planning Process began in January of 2008 and is expected to produce the first Northern Tier Transmission Group Biennial Planning Report in the fall of 2009. This report describes the Task 1 Fast Track Project Process and its results, as well as the integration of transmission initiatives already in development by providers joining the Northern Tier Transmission Group. 3 Background | 2007 Annual Planning Report The Northern Tier Transmission Group NTTG focuses its efforts on the evaluation of transmission projects that move power across the sub-regional bulk transmission system servicing load in its footprint. The transmission providers belonging to Northern Tier serve nearly 2.7 million retail customers with over 27,500 miles of high voltage transmission lines. These members provide service across much of Utah, Wyoming, Montana, Idaho and Oregon, and parts of Washington and California. NTTG is committed to coordinating sub-regional planning efforts with adjacent sub-regional groups and other planning entities. It is expected that the Western Electricity Coordinating Council will continue to be responsible for coordinating and promoting electric system reliability across the Western Interconnection through its role in regional reliability planning and facility rating, and by providing economic Transmission State Regulatory State Consumer planning services to its members Providers Commissions Advocacy Groups through its Transmission Expansion Planning Policy Committee. Steering NTTG performs both reliability and Committee economic planning coordination, and has started by identifying projects that have been previously Transmission Use Planning Cost Allocation studied and which spurred interest Committee Committee Committee from members within the NTTG service area. NTTG works with the WECC Planning Coordination Biennial Integrated Regional Committee for reliability planning, Transmission Plan the WECC TEPPC for economic planning, and is working to Figure 2: Structure of the Northern Tier Transmission Group implement a framework for cooperation with neighboring subregional planning entities. Stakeholder participation is important to the processes of the Northern Tier Transmission Group and all interested parties are encouraged to attend and contribute to the many stakeholder meetings conducted by the transmission use, planning and cost allocation committees, and in preparing, developing and analyzing planning studies. A chronology of 2007 activities is provided in Table 2, below. 2007 Annual Planning Report | The Northern Tier Transmission Group 4 NTTG – Chronology of 2007 Activities Table 2: Chronology of NTTG Activities in 2007 Jan 9 Transmission Use Committee meeting 30 Area Control Error Diversity Interchange presentation 31 Public stakeholder meeting Feb 16 FERC issues Order 890. Among other things, it requires a ‘straw man’ proposal outlining a process for complying with the planning principals adopted in the Final Rule. Mar 13 Transmission Use Committee meeting 14 Public stakeholder meeting to initiate development of the Straw Proposal. 15 Order 890 Final Rule posted in the Federal Registry. 23 Initial conference call to begin coordinating sub-regional planning with other groups in the Western Interconnection, discuss order 890 compliance. 4 Northern Tier co-chair discussed the group’s efforts to comply with Order 890 with the Committee on Regional Electric Power Cooperation (CREPC). 6 Public meeting with the Northwest Transmission Advisory Committee and Columbia Grid to discuss Order 890 compliance requirements and approaches to integration and cooperation. 10 Northern Tier participated with the Western Electricity Coordinating Council in a public meeting to discuss planning roles and relationships among regional, sub-regional and transmission provider planning groups. 14 Planning & Stakeholder meeting 16-May 7 Open comment period for the Northern Tier Straw Proposal 23-24 Northern Tier public stakeholder meeting for final walkthrough and review of the Northern Tier Straw Proposal. 29 Northern Tier Straw Proposal posted on the Northern Tier Web site and on the transmission providing members’ OASIS sites. Jun 13 Northern Tier presentation at FERC Technical Conference, Park City, Utah Jul 9 Public stakeholder meeting – Planning 10 Transmission Use Committee meeting Aug 20 Public stakeholder meeting – Planning Oct 22 Public stakeholder meeting – Planning Nov 7 Public stakeholder meeting 13 Public stakeholder meeting – Planning 16 Cost Allocation meeting 17 Joint Cost Allocation & Planning meeting Apr May Dec 5 NTTG – Chronology of 2007 Activities | 2007 Annual Planning Report Transmission Queue – NTTG Companies The Northern Tier Transmission Group’s member transmission providers elicit requests for transmission service from generation builders, electricity users and others in the first quarter of each year in accordance with their Open Access Transmission Tariffs. Figure 3, below, shows the amounts of capacity requested in the 2007 solicitation, along hypothetical paths between different regions within the Northern Tier footprint. Most of these requests are for service beyond current and forecasted Assured Transfer Capability, given the existing transmission system and planned loads and resources. To meet these needs in a timely fashion, a “Fast-Track” planning process was established and a set of transmission additions were identified. Figure 3: Northern Tier 2007 Transmission Request Queue 2007 Annual Planning Report | Transmission Queue – NTTG Companies 6 The Northern Tier Fast-Track Planning Process Here are the steps followed in the fast-track planning process: 1) Review, with stakeholders, past transmission provider studies and additional data to identify congested transmission that impedes efficient and reliable operation of the grid 2) Collect and review information available from the Western Electricity Coordinating Council and others regarding future projects that affect the Northern Tier footprint 3) Review the RMATS and SSG-WI congestion studies, and historical Available Transmission Capacity and utilization data from the Northern Tier Transmission Use Committee 4) Acquire, review and align loads and resources and Integrated Resource Plan data for member transmission providers, augmenting and revising to accommodate shareholder input a) Update and finalize 5-, 10- and 15-year load projections 5) Tabulate Available Transmission Capacity and Transmission Service Requests from member transmission providers 6) Aggregate load and resource needs, locating them geographically and compare to existing transmission path capabilities to determine if additional transmission construction is needed 7) Review expansion requirements with stakeholders 8) Identify hub and spoke candidates 9) Review RMATS and other studies’ recommended capacity expansions 10) Northern Tier transmission providers select transmission expansion candidates, identifying Fast Track Projects by June 30, 2007 11) Each project sponsor develops a technical study plan that: a) Identifies interested parties b) Identifies affected parties c) Invites participation in study efforts d) Coordinates with other regional and sub-regional planning groups e) Establish meeting times and locations, coordinated via Northern Tier with other sub-regional planning groups and the Western Electricity Coordinating Council f) Defines a technical studies process to be integrated with the WECC Regional Planning Review and Three-Phase Rating Process 12) Each project sponsor performs required WECC Regional Planning Review Process studies, Phase I, Phase II rating studies, and submit to Northern Tier Planning Committee to review and present to stakeholders 13) Northern Tier facilitates project implementation and coordination with the Western Electricity Coordinating Council and other sub-regional planning groups. 14) Cost Allocation Committee processes Fast-Track Projects in the 2008 Biennial Planning Process as a pilot project 7 The Northern Tier Fast-Track Planning Process | 2007 Annual Planning Report The NTTG Fast-Track Projects Figure 6, below, is a map of the Western Interconnection showing the set of transmission improvements designed by the Northern Tier transmission providers to accommodate projected needs for future capacity. The lines comprise the ‘Fast-Track Projects’ which provide for pressing development needs and constitute the first iteration of the Northern Tier planning process. The primary benefit of the Fast-Track expansion plan is the timely connection of substantial and diverse resource development in the sparsely populated Mountain States with population centers along the West Coast and in the Desert Southwest. In addition, the interties will allow significant diversity transactions among the distinctly different climate, weather and resource regimes of the Western Interconnection. Load Growth Figure 4: Northern Tier Fast-Track Project Map with Potential Resource Additions The table and map on the next page show the principal projects in the Fast-Track Program, their points of termination, voltages, potential routes, current status and anticipated completion dates. 2007 Annual Planning Report | The NTTG Fast-Track Projects 8 Table 3: Fast-Track Project Data Project Name Voltage (kV) States Length (Miles) Gateway South 500/345 WY, UT, NV 450± Gateway West 500/230 WY, ID,OR 650 Gateway Central 345 ID, UT 136 HemingwayBoardman 500 ID, OR 230 HemingwayCaptain Jack 500 ID, OR 320 Mountain States Transmission Intertie 500 MT, ID 460 SouthWest Intertie Project - North 500 ID, NV 230 WECC Rating Phase Permit Status InService Year In Phase 1 Applications Submitted 2014 In Phase 1 Applications Submitted 2012 In Phase 1 2010 In Phase 1 Applications Submitted 2012 In Phase 1 2014 Phase 1 Complete In Permitting Process 2013 In Phase 1 Active in Siting 2011 Figure 5: Map of Fast-Track Transmission Showing Voltage & Points of Connection Townsend WASHINGTON MONTANA Boardman HemingwayBoardman Mountain States Intertie Idaho Power NorthWestern Energy OREGON HemingwayCaptain Jack Gateway West IDAHO PacifiCorp Idaho Power Hemingway PacifiCorp Midpoint Captain Jack Legend LSPower Windstar Aeolus Populus Cedar Hill SWIP North WYOMING Bridger Gateway Central PacifiCorp Terminal Existing 230 kV Ely Energy Center 345 kV 345 kV Double Circuit 500 kV Mona UTAH NEVADA Gateway South PacifiCorp Sigurd 500 kV Double Circuit CALIFORNIA Crystal 9 ARIZONA NEW MEXICO NTTG Project Development Timelines | 2007 Annual Planning Report NTTG Project Development Timelines Figure 6: Development Timelines for Northern Tier Projects 2007 Annual Planning Report | NTTG Project Development Timelines 10 The Sub-Regional Planning Process In addition to and in parallel with their Fast-Track Project activities, the Northern Tier Transmission Group and its member transmission providers developed, in 2007, individual Attachment K planning processes and a two-phase sub-regional Northern Tier Biennial Planning Process. Initiated in January, 2008, the steps of the Biennial Planning Process include: Phase 1: Northern Tier Transmission Group Planning Process 1. Annual Planning Process – identify needs, least cost expansion project alternatives, technical benefits, and project costs. 2. Planning Committee – identify expansion beneficial projects with sponsorrecommended cost and benefit allocations. 3. Cost Allocation Committee – reviews identified projects, applies principles and recommends likely cost allocation. 4. Planning Committee – develops and circulates a Draft Annual Expansion Plan. 5. NTTG Steering Committee – approves the draft expansion plan. 6. Final Annual Expansion Plan – includes likely cost and benefit allocation estimates for the given planning assumptions. 7. Planning Estimates – for expansion projects, congestion and re-dispatch, and additional assured transfer capability, costs and cost allocations are prepared by the Economic Study Process with input from the Transmission Use Committee. 8. Customer Decision Process – customers, other stakeholders and interested parties are informed of and asked to comment on the plan and its estimated impacts, costs and benefits. 9. Formal Open Access Transmission Tariff Service Request Process – customers make network transmission and point-to-point transmission requests via the transmission providers’ Open Access Transmission Tariffs and planning for firm needs and reliability is undertaken by members. Phase 2: Transmission Provider Project Implementation Process 1. Transmission providers and project sponsors will finance projects, facilitate permitting, and implement their formal Open Access Transmission Tariff processes. 2. Service Request Aggregation Process – Northern Tier Transmission Group may facilitate open seasons or coordinate requests made of individual transmission providers as appropriate and requested. 3. Steering Committee – may initiate coordinated queues and consolidated transmission service request processes in the future. 11 The Sub-Regional Planning Process | 2007 Annual Planning Report 4. Transmission Providers’ Formal Open Access Transmission Tariff Process 5. Transmission Providers – undertake transmission construction, including detailed planning, permitting and building. 6. Transmission Providers – each undertakes its own regulatory approval and rate process. Relationships among Planning Entities in the West Transmission planning in the Western Interconnection has evolved to incorporate three distinct levels activity: Transmission providers, sub-regional transmission groups, and regional planning entities. The relationships among regional, sub-regional and individual transmission providers are shown in the following diagram: Deseret G&T Local Planning Processes Idaho Power Local Planning Processes Northern Tier Transmission Group Sub‐Regional Planning Processes: •Aggregated Planning Requests •Cost Allocation Estimates •Coordination with Other Regions Northwestern Energy Local Planning Processes Western Interconnection Regional Planning PacifiCorp Western Electricity Coord. Council Comm. on Regional Electric Power Coop. Western Governors Association Local Planning Processes Additional Members •Policies •Standards •Coordination •Reliability & Economic Data •Base Cases •Annual Study Plan •Economic Studies •Congestion Analysis Local Planning Processes Transmission Provider Local Planning Processes Transmission Provider Local Planning Processes Transmission Provider Local Planning Processes Other Sub‐Regional Transmission Groups Sub‐Regional Planning Processes Figure 7: Three-level Planning Process in the Western Interconnection Individual transmission providers were once (for the most part) fully-integrated generation, transmission and distribution utilities that, with deregulation, have now changed focus to provide equal access to all markets and customers. The transmission providers each develop and maintain an Open Access Transmission Tariff that receives and acts on requests for transmission service in accordance with a well-defined procedure. The transmission providers also assess future load and resource developments to 2007 Annual Planning Report | Relationships among Planning Entities in the West 12 plan the evolution of an efficient transmission system, and undertake reliability analysis and improvements. Where service requests and other identified needs call for the development of transmission that involves participation of multiple transmission providers within a sub-regional transmission group’s footprint, the planning and analysis of improvements are coordinated at the sub-regional level. Projects that span greater distances are planned, analyzed and developed in coordination with other sub-regional groups or at the regional WECC level. 13 Relationships among Planning Entities in the West | 2007 Annual Planning Report Regional and Sub-Regional Planning Timelines The Northern Tier Transmission Group’s planning timelines are designed to coordinate with those of the Western Electricity Coordinating Council, with a two-year cycle for transmission expansion and reliability and a one-year economic study cycle that examines preliminary plans for the first year of the biennial cycle, and draft plans for the second year of the preceding cycle. Sep 2007 Oct Nov Dec Jan Feb Mar 2008 Apr May Jun Jul Execute Studies Analyze Aug Sep Oct Nov Dec Jan 2009 Feb Mar Apr Western Electricity Coordinating Council Regional Planning Process Timeline Get Approvals Prepare Report 2007 Cycle Prepare Database Take Requests Analyze Develop Study Plans Prepare Report Execute Studies Historical Data Analysis Get Approvals 2008 Cycle Prepare Database Take Requests Northern Tier Transmission Group Sub-Regional Planning Process Timeline Develop Study Plan 2009 Cycle 2008 Bienniel Cycle - Year 1 Gather Data Do Study Plan Analyze Draft & Review Take Requests Econ Studies Report & Review Results Take Requests Econ Studi 2008 Annual Cycle Sep 2008 Oct Nov Dec Jan Feb Mar 2009 Apr May Jun Jul Aug Sep Oct Nov Dec Jan 2010 Feb Mar Apr 2008 Bienniel Cycle - Year 2 Analyze Draft & Review Cost Allocation Gather Data Do Study P Report & Review Results Take Requests Econ Studies Report & Review Results Take Requests Econ Studi Gather Data Do Study Plan Analyze Draft & Review Final Approval Report, Review Final Approval 2009 Biennial Cycle - Year 1 Figure 8: Timelines for Regional & Sub-Regional Planning 2007 Annual Planning Report | 14 Details of the Northern Tier Transmission Projects Mountain States Intertie NorthWestern Energy Black Hills Hem ingway-Boardman Idaho Power Hem ingway-Captain Jack Gateway West PacifiCorp PacifiCorp Idaho Power S WIP North Hyperlinks: LS Power Gateway C entral PacifiCorp NTTG.biz Gateway South PacifiCorp Northern Lights (D C Projects) TransCanada TransWest Express National Grid Arizona Public Service Wyoming Infrastructure Authority Figure 9: Proposed Transmission Projects as of December 2007 The following pages provide maps and descriptions of major components of the Northern Tier Transmission Group’s projects. Following these overviews, in the table of References, are links to Web pages containing additional information for the projects. Note: At the time of this report, the Sigurd-Crystal segment of the Gateway South was being evaluated in the WECC Phase 1 Rating Process as a 500-kV line. 15 Details of the Northern Tier Transmission Projects | 2007 Annual Planning Report Hemingway to Boardman Transmission Project The project consists of a single-circuit 500-kV transmission line with a proposed bi-directional rating of 1000 MW stretching about 230 miles from Hemingway substation (formerly Melba) southeast of Boise, Idaho, to a new substation being planned near Boardman, in north-central Oregon. This project, sponsored by Idaho Power, is designed to provide for anticipated service-area load growth and to meet transmission service requests. By 2017, Idaho Power forecasts an additional 800 MW of Idaho native load. Further, Idaho Power is obligated, pursuant to its Open Access Transmission Tariff, to plan and expand its transmission system based on needs of its network customers and eligible customers that agree to expand the Idaho Power transmission system. Boardman Constraints on the existing Idaho to Northwest transmission path (Path 14) prevent Idaho Power from meeting transmission requests currently in its queue. Path 14 is currently rated at 1,200 MW with a summer operating transfer capability of 1090 MW westto-east, and is fully subscribed. The Hemingway-toBoardman Transmission Hemingway Project was initiated in Figure 10: Map of Hemingway-to-Boardman Transmission Project response to a transmission request submitted by Idaho Power’s merchant group and was identified in Idaho Power’s 2006 Integrated Resource Plan to access Pacific Northwest energy resources to serve Idaho Power’s growing customer needs. The Rocky Mountain Area Transmission Study (RMATS) of 2004 evaluated many expansion scenarios, with the Phase 1 Report including a Midpoint-to-Oregon transmission path as a recommended transmission path to support the development of Wyoming resources beyond the RMATS study footprint, providing an estimated annual savings of $516 million. A Regional Planning Review Group was established and held its first meeting on September 7, 2007, with additional stakeholder meetings on October 17 and November 13. Meeting notices, presentations and minutes were posted on Idaho Power’s OASIS Web site (http://www.oatioasis.com/ipco/index.html). 2007 Annual Planning Report | Hemingway to Boardman Transmission Project 16 Hemingway to Captain Jack Transmission Project Northern Tier Transmission Group member PacifiCorp is sponsoring the development of a 500kV transmission line from the Hemingway substation at Melba, Idaho (southeast of Boise), to the Bonneville Power Administration’s Captain Jack substation near Bonanza in Northern California. The single-circuit line will span approximately 320 miles and is planned to be in service in 2014. The existing Midpoint-to-Summer Lake 500 kV line between South Central Idaho and Southern Oregon will add a terminus at the Hemingway substation. The lines will provide a robust pathway for energy between the Pacific Coast and the Inland West. WASHINGTON Boardman HemingwayBoardman Idaho Power OREGON HemingwayCaptain Jack Hemingway PacifiCorp Captain Jack Figure 11: Map of Hemingway to Captain Jack Transmission Project 17 Hemingway to Boardman Transmission Project | 2007 Annual Planning Report Southwest Intertie Project (SWIP) North The Southwest Intertie Project is being developed by LS Power, LLC, under the name Great Basin Transmission, LLC, in cooperation with Idaho Power, which holds the permits. Great Basin purchased an exclusive option to build the SWIP from Idaho Power, which has studied the project for a number of years. The project is being approached in two segments, with the SWIP North segment being part of the Northern Tier Transmission Group’s Fast-Track Project. SWIP North is a 500kV single-circuit line that will be built between the Midpoint substation in South Central Idaho and the White Pine Generating Station near Ely, Nevada. The initial proposed rating for the MidpointWhite Pine line is 2,000 MW in each direction, subject to results of the WECC Phase 1 Comprehensive Progress Report. The line is proposed to be Figure 12: Map of Southwest Intertie Project (SWIP) in service in 2011. 2007 Annual Planning Report | Southwest Intertie Project (SWIP) North 18 Mountain States Transmission Intertie Project The Mountain States Transmission Intertie (MSTI, pronounced ‘misty’) is sponsored by Northwestern Energy and will provide a 500-kV link of approximately 460 miles between a new Townsend substation in Southwestern Montana and the Midpoint substation in South Central Idaho. An intermediate connection will be made at the existing Mill Creek substation. The MSTI will be built to meet transmission service requests and to relieve constraints on the region’s existing transmission system. The project will also improve transmission system reliability, meet growing electricity demand in the region, provide regional energy diversification and make a positive economic impact on the area. The project is planned to be in service in 2013, and has a proposed north-south rating of 1,500 MW and a prospective southnorth rating of 950 MW. The Townsend substation will tie into two existing 500-kV east-west interties approximately mid-way between the existing Broadview and Garrison substations. The new line will have series compensation and a phase-shifting transformer to control power flow. Series capacitors will be located at the Midpoint substation, while a substation for the phaseshifting transformer and additional series capacitors will be built near the Mill Creek substation. Figure 13: Potential Route of MSTI (Dashed Line) Northwestern Energy initiated both the WECC Regional Planning Process and Path Rating Process in 2007. NWE submitted the Final Regional Planning Project Report to complete the Regional Planning Process in March 2008 after a 30-day comment period. In early April, NWE will finalize and submit its Comprehensive Progress Report to the Western Electricity Coordinating Council for the required 60-day comment period to complete the Phase 1 Path Rating Process. 19 Gateway West Transmission Project | 2007 Annual Planning Report Gateway West Transmission Project The Gateway West Transmission Project is sponsored by Idaho Power and PacifiCorp, and is planned to provide for growth in load within the service territory of the two companies. The project will also meet their obligation to plan for and expand their transmission systems based on the needs not only of native load customers but network customers and eligible customers that agree to expand the transmission system. The project was announced in May of 2007. It is a part of PacifiCorp’s broader Energy Gateway initiative, which also encompasses the Gateway South and Gateway Central Transmission Projects. The project is comprised of a number of new substations and a new, primarily 500-kV pair of lines from a new Windstar substation near the Dave Johnston power plant in Eastern Wyoming to the Hemingway substation near the western border of Idaho. The project has a proposed combined rating of 3,000 MW, and will parallel three existing WECC-defined bulk power transmission paths: TOT 4A (Path 37), Bridger West (Path 19), and Borah West (Path 17). Besides the terminating Windstar and Hemingway substations, new stations will be built at Aeolus (to integrate new generation resources and to provide connection with the Gateway South Project), Populus (to connect with Path C transmission into Utah), and at Cedar Hill (to tie the more southern of the two lines into the Midpoint substation for increased reliability). Figure 14: Map of the Gateway West Transmission Project 2007 Annual Planning Report | Gateway West Transmission Project 20 Gateway South and TransWest Express The Gateway South Transmission Project is part of PacifiCorp’s Energy Gateway initiative and proposes new high-voltage transmission between Wyoming and Southern Nevada. Arizona Public Service, the Wyoming Infrastructure Authority and National Grid are proposing a similar line from Wyoming through Southern Nevada and prospectively on to the Phoenix, Arizona area. Recognizing a number of common interests and similar planning and development requirements, the participants in the two projects an interim agreement in August of 2007 to pursue initial development while more complex technical and regulatory issues were considered. The joint effort undertook a common project team implementation strategy and resource deployment, led by National Grid, coordinating Regional Planning and Rating Review processes, coordinating environmental permitting, and engaging in a common stakeholder and public outreach. Each project would undertake its own right-of-way filings, WECC rating process and regulatory filings. Figure 15: Map of Gateway South and TransWest Express Proposed Study Areas The Gateway South project calls for a 500-kV line from the proposed new Aeolus substation in Southeast Wyoming to the Mona substation in Central Utah, to be completed by 2013. A 345-kV line will be built from the existing Sigurd substation (about 50 miles south of Mona), through the Red Butte substation in the southeast corner of Utah, to the Crystal substation north of Las Vegas, Nevada, with completion scheduled for 2012. 21 Gateway South and TransWest Express | 2007 Annual Planning Report Gateway Central Transmission Project PacifiCorp is sponsoring a double-circuit 345-kV transmission line from a new Populus substation near Downey, Idaho, 136 miles south to the existing Terminal substation near the Salt Lake International Airport west of Salt Lake City, Utah. The line is being developed in two segments that will link north of Ogden, Utah, at the Ben Lomond substation. The southern segment is planned to be in service in March of 2010, while the northern segment is targeted for June, 2010. The line is intended to increase the ability to deliver electricity to the fast-growing population along the Wasatch front of Utah in an efficient and cost-effective manner. The new transmission lines and expanded substations will also provide for improved reliability and operational flexibility with future generation resources, including renewable resources such as wind Figure 16: The Gateway Central Transmission Project 2007 Annual Planning Report | Gateway Central Transmission Project 22 NorthernLights Transmission– Inland Project NorthernLights is a TransCanada initiative that proposes three major high-voltage direct current (HVDC) transmission lines linking low cost, environmentally attractive fossil fuelled and renewable generation with growing loads in the Pacific Northwest, Nevada, Arizona and California. The NorthernLights initiative consists of two projects – the Celilo Project between Northern Alberta and the Bonneville Power Administration’s Big Eddy substation next to the high voltage direct current inverter station at Celilo near The Dalles, Oregon, and the Inland Project connecting Montana and Wyoming generation to Las Vegas and electricity users in Southern California and the Desert Southwest. The Celilo Project is being developed in coordination with the Western Electricity Coordinating Council and the ColumbiaGrid regional transmission group. The Inland Projects consist of two HVDC transmission lines to Las Vegas, with one line beginning in Wyoming and the other in Montana. Several major inter-regional high voltage transmission paths are already interconnected at substations in the Southern Nevada area. The lines will connect wind generation resources in Montana, Wyoming and other western states with growing loads in Southern Nevada, Arizona and California. Extension of the Inland Project lines to southern California and Arizona is contemplated as market conditions evolve. Current plans call for the two 500-kV direct current lines to be energized in 2014. It is anticipated that they will carry up to 3,000 megawatts each and cost between $1.5 and $2.0 billion to construct. 23 NorthernLights Transmission– Inland Project | 2007 Annual Planning Report Internet Links and Other References Regional Planning Western Electricity Coordinating Council (http://www.wecc.biz) o Transmission Expansion Planning Policy Committee Western Interconnection economic transmission expansion planning support o Planning Coordination Committee Evaluate transmission design and expansion, recommend criteria for reliable operation Committee on Regional Electric Power Cooperation (http://www.westgov.org/wieb/site/crepcpage/) A committee of the Western Governors Association’s Western Interstate Energy Board Sub-Regional Planning Northern Tier Transmission Group (http://www.nttg.biz) ColumbiaGrid (http://www.columbiagrid.org) WestConnect (and Sub-Groups) (http://www.westconnect.com/planning.php) o Colorado Coordinated Planning Group o National Renewable Energy Laboratory o Sierra Pacific Planning Group o Southwest Area Transmission Northern Tier Transmission Group Members Deseret Generation & Transmission (http://www.oasis.pacificorp.com/oasis/dgt/main.html) Idaho Power Company (http http://www.oatioasis.com/ipco/index.html) Northwestern Energy (http://www.oatioasis.com/NWMT/index.html) PacifiCorp (http://www.oasis.pacificorp.com/oasis/ppw/main.htmlx) Utah Associated Municipal Power Systems (http://www.uamps.com) 2007 Annual Planning Report | NorthernLights Transmission– Inland Project 24 Integrated Resource Plans Idaho Power Company (http://www.idahopower.com/energycenter/irp/2006/) Idaho Power is currently developing its 2008 Integrated Resource Plan, and preliminary information will be made available on its Web site as it is evolved. NorthWestern Energy (http://www.northwesternenergy.com/display.aspx?Page=Default_Supply_Electric&Item=16) NorthWestern does not produce an ‘Integrated Resource Plan’, per se, but they maintain and make available an “Electric Default Supply Resource Procurement Plan.’ PacifiCorp (http://www.pacificorp.com/Navigation/Navigation23807.html) PacifiCorp’s currently posted plan was completed in May of 2007, and development of the 2008 IRP is currently underway. Additional Information for Northern Tier Transmission Projects • Hemingway to Boardman • Hemingway to Captain Jack • Gateway Central (http://www.pacificorp.com/Article/Article79647.html) • Gateway South • Gateway West (http://www.idahopower.com/newsroom/projnews/Gateway/) • NorthernLights (http://www.transcanada.com/company/northernlights.html) • Mountain States Transmission Intertie (http://www.msti500kv.com/default.htm) • Southwest Intertie Project - North • Transwest Express (https://transwest.azpsoasis.com/) 25 NorthernLights Transmission– Inland Project | 2007 Annual Planning Report EXHIBIT 3 Brian Silverstein Chair, Planning Coordination Committee Bonneville Power Administration (360) 418-2122 blsilverstein@bpa.gov May 28, 2008 PLANNING COORDINATION COMMITTEE TECHNICAL STUDIES SUBCOMMITTEE Subject: Acceptance of Regional Planning Report for the Gateway South Project On June 25, 2007, PacifiCorp notified the Western Electricity Coordinating Council (WECC) that it was initiating the WECC Regional Planning Review Process for the Gateway South and Gateway West Projects. Since the initiation of the Gateway South project, four stakeholder meetings occurred to solicit interest in the project. The meetings were held on October 17, November 7 and December 5 of 2007, with a final stakeholder meeting January 23, 2008 for the Project Rating Review Process. The Gateway South Project as proposed by PacifiCorp is a 500 kV EHV AC transmission line that is approximately 770 miles long. This project will have two separate timeframes to serve load in growing markets. The first portion of the project is for a single-circuit 500 kV transmission line approximately 330 miles that starts at the Mona substation in Utah and terminates at the Crystal substation near Las Vegas, Nevada with a planned in-service date of 2012. The second portion of the project is a double-circuit 500 kV transmission line approximately 400 miles originating at a new substation, Aeolus, in southeastern Wyoming and continues to the Mona substation, with an in-service completion date of 2014. On March 28, 2008, the Regional Planning Project Report for the project was provided to PCC for a 30-day comment period. This comment period allowed PCC members the opportunity to review and comment on the project conformity with the Regional Planning Guidelines. No comments were received during the 30-day comment period. Accordingly, this letter serves as notification that the Regional Planning Project Review has been completed for the Gateway South Project. Sincerely, Brian Silverstein Brian Silverstein cc: Kent Bolton, WECC Tom Green, TSS Chair Darrell Gerrard, PacifiCorp W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L • W W W . W E C C . B I Z 615 ARAPEEN DRIVE • SUITE 210 • SALT LAKE CITY • UTAH • 84108-1262 • PH 801.582.0353 • FX 801.582.3918 Brian Silverstein Chair, Planning Coordination Committee Bonneville Power Administration (360) 418-2122 blsilverstein@bpa.gov May 30, 2008 PLANNING COORDINATION COMMITTEE TECHNICAL STUDIES SUBCOMMITTEE Subject: Acceptance of Regional Planning Report for the Gateway West Transmission Project On July 5, 2007, Idaho Power Company (IPC) notified the Western Electricity Coordinating Council (WECC) that it was initiating the WECC Regional Planning Review Process for a transmission project from Jim Bridger to Northeastern Oregon. During this process, two distinct projects, serving different purposes, emerged: the Gateway West Transmission Project, and the Hemingway to Boardman Transmission Project. Idaho Power and PacifiCorp are proposing the Gateway West Transmission Project because of service area load growth internal to both companies. Idaho Power forecasts the need for 800 MW of additional power to serve its southern Idaho load by 2017 and PacifiCorp forecasts that its load on the Wasatch Front of Utah will double in the next 20 years. Additionally, both companies have independent obligations, pursuant to their Open Access Transmission Tariffs, to plan for and expand their respective transmission systems based upon the needs of their native load and network customers along with eligible customers that agree to expand the transmission system. Regional Planning for this project was coordinated through the Northern Tier Transmission Group (NTTG) planning process. A Regional Planning Review Group (RPRG) was formed and consisted of representatives from PacifiCorp, Deseret Power Electric Cooperative, NorthWestern Energy and Utah Associated Municipal Power Systems, and utility commission representatives from the states of Idaho, Oregon, Utah, Wyoming and Montana. On February 27, 2008, the Regional Planning Project Report for the project was provided to PCC for a 30-day comment period (Report and request letter dated February 19, 2008). This comment period allowed PCC members the opportunity to review and comment on the project conformity with the Regional Planning Guidelines. One comment and a request for additional information were received during the 30-day comment period. The commenter agreed that the requested map correction would be done in the Comprehensive Report and that the Regional Planning Report is acceptable. Accordingly, this letter serves as notification that the Regional Planning Project Review has been completed for the Gateway West Transmission Project. Sincerely, Brian Silverstein Brian Silverstein W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L • W W W . W E C C . B I Z 615 ARAPEEN DRIVE • SUITE 210 • SALT LAKE CITY • UTAH • 84108-1262 • PH 801.582.0353 • FX 801.582.3918 cc: Kent Bolton, WECC David Angell, IPC W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L • W W W . W E C C . B I Z 615 ARAPEEN DRIVE • SUITE 210 • SALT LAKE CITY • UTAH • 84108-1262 • PH 801.582.0353 • FX 801.582.3918 EXHIBIT 4 Rocky Mountain Area Transmission Study Connecting the region today for the energy needs of the future September 2004 Table of Contents EXECUTIVE SUMMARY.......................................................................................................................................... I RECOMMENDED PROJECTS ........................................................................................................................................ II Recommendation 1: Expansion Projects within the Rocky Mountain Footprint ...................................................................II Montana System Upgrade Project ................................................................................................................................... III Bridger Expansion Project............................................................................................................................................. IV Wyoming to Colorado Transmission Project ................................................................................................................ IV Recommendation 2: Export Projects beyond the Rocky Mountain Footprint ...................................................................... IV Economic Analysis of Recommendations ........................................................................................................................VI NEXT STEPS........................................................................................................................................................... VIII Needed Institutional Improvements ...............................................................................................................................IX Further following specific actions are recommended............................................................................................................. X CHAPTER 1 - IDENTIFYING TRANSMISSION EXPANSION OPPORTUNITIES ............................. 1-1 A. THE COST OF DOING NOTHING ........................................................................................................................ 1-1 B. GENERIC BENEFITS AND COSTS OF TRANSMISSION EXPANSION ...................................................................... 1-1 Discussion of Types of Benefits and Beneficiaries............................................................................................................ 1-2 Lower Cost Generation:.....................................................................................................................................................1-2 Fuel Diversity ....................................................................................................................................................................1-2 Enhanced Competition in Energy Markets: ........................................................................................................................1-4 Local and State Economic Development:...........................................................................................................................1-4 Reliability:..........................................................................................................................................................................1-4 C. BACKGROUND AND HISTORY OF THE RMATS EFFORT ................................................................................... 1-5 RMATS Charter (excerpts) ..................................................................................................................................... 1-6 PART 1. PART 2. PART 3. Goals...........................................................................................................................................................1-6 Principles.....................................................................................................................................................1-6 Operating Procedures ..................................................................................................................................1-7 The RMATS Process.............................................................................................................................................. 1-9 CHAPTER 2 -TRANSMISSION STUDY APPROACH ................................................................................. 2-1 A. INTRODUCTION ................................................................................................................................................ 2-1 B. OVERALL APPROACH....................................................................................................................................... 2-2 Production Costs..................................................................................................................................................... 2-3 Capital and Other Fixed Costs ................................................................................................................................. 2-4 C. KEY DATA ASSUMPTIONS................................................................................................................................ 2-5 Transmission Topology............................................................................................................................................. 2-5 Transmission Path Ratings and Nomograms................................................................................................................ 2-7 Powerflow Case ...................................................................................................................................................... 2-7 Electricity Demand (i.e., “Loads”)............................................................................................................................. 2-7 Natural Gas Prices................................................................................................................................................. 2-8 Coal Prices ............................................................................................................................................................ 2-8 Existing Thermal Plants.......................................................................................................................................... 2-9 Hydroelectric Resources............................................................................................................................................. 2-9 Wind Resources...................................................................................................................................................... 2-9 Congestion and Congestion Costs................................................................................................................................ 2-9 D. RESOURCE AND TRANSMISSION EXPANSION ALTERNATIVES .........................................................................2-12 E. GENERATION ALTERNATIVES FOR 2013 .........................................................................................................2-14 Alternative 1: Existing IRPs................................................................................................................................. 2-14 Alternative 2: “Quasi” IRP for the RMATS Region................................................................................................. 2-14 Alternative 3: Double the Resource Additions in Alternative 2 for Export...................................................................... 2-16 Alternative 4: Triple the Resource Additions in Alternative 2 for Export to West Coast ................................................... 2-17 F. CONCLUSIONS ................................................................................................................................................2-18 i CHAPTER 3 - RECOMMENDATIONS FOR TRANSMISSION EXPANSION ....................................... 3-1 A. INTRODUCTION ................................................................................................................................................ 3-1 B. RECOMMENDATIONS FOR TRANSMISSION EXPANSION .................................................................................... 3-1 Recommendation 1: Projects within the Rocky Mountain Footprint .................................................................................. 3-1 Montana System Upgrade Project ......................................................................................................................................3-2 Bridger Expansion Project .................................................................................................................................................3-3 Wyoming to Colorado Transmission Project ......................................................................................................................3-4 Recommendation 2: Export Projects Beyond the RMATS Footprint................................................................................. 3-5 C. TWO REFERENCE CASES .................................................................................................................................. 3-7 All-Gas Reference Case ........................................................................................................................................... 3-8 IRP-Based Reference Case ........................................................................................................................................ 3-8 D. ECONOMIC EVALUATION ................................................................................................................................. 3-9 Production Costs..................................................................................................................................................... 3-9 E. SENSITIVITIES .................................................................................................................................................3-10 F. CAPITAL REQUIREMENTS ...............................................................................................................................3-12 G. DISTRIBUTION OF ECONOMIC GAINS AND LOSSES ..........................................................................................3-15 H. CONCLUSIONS ................................................................................................................................................3-17 CHAPTER 4 - COST ALLOCATION AND COST RECOVERY ISSUES ................................................... 4-1 State Regulation ..................................................................................................................................................... 4-5 FERC Regulation .................................................................................................................................................. 4-5 Cost of Service Methodology....................................................................................................................................... 4-6 Transmission Recommendation 1 ............................................................................................................................... 4-8 Transmission Recommendation 2 ............................................................................................................................... 4-8 Phase II Initial Step............................................................................................................................................................4-9 Develop Multi-State Pricing Principles ............................................................................................................................. 4-10 Institutionalize RMATS Regional Planning ...................................................................................................................... 4-11 Coordinate Regional Transmission Planning with LSE Resource Plans............................................................................. 4-11 Engage the Wyoming Infrastructure Authority................................................................................................................. 4-11 Pursue More Efficient Ways to Use, Operate and Expand the Transmission System..................................................... 4-12 Strengthen Regional Coordination ................................................................................................................................... 4-13 Montana System Upgrade Project............................................................................................................................. 4-14 Bridger Expansion Project...................................................................................................................................... 4-15 Wyoming to Colorado Transmission Project................................................................................................................ 4-15 CHAPTER 5 - OTHER IMPORTANT ISSUES FOR TRANSMISSION EXPANSION ........................... 5-1 WECC Regional Planning Project Review Process ........................................................................................................ 5-1 Siting and Permitting............................................................................................................................................... 5-2 Rocky Mountain State Siting Requirements ................................................................................................................. 5-4 COLORADO ....................................................................................................................................................................5-4 IDAHO .............................................................................................................................................................................5-5 MONTANA .....................................................................................................................................................................5-6 UTAH...............................................................................................................................................................................5-7 WYOMING.......................................................................................................................................................................5-9 ROIWG Case Study Results.................................................................................................................................. 5-11 TOT3............................................................................................................................................................................... 5-11 West of Naughton ............................................................................................................................................................... 5-13 Montana-Northwest............................................................................................................................................................. 5-13 Case Study Conclusions ......................................................................................................................................... 5-13 ROIWG Tariff Development Results ....................................................................................................................... 5-14 CHAPTER 6 - SUMMARY OF RECOMMENDATIONS AND NEXT STEPS .......................................... 6-1 Recommendation 1: ................................................................................................................................................. 6-1 Recommendation 2: ................................................................................................................................................. 6-1 ii iii Table of Figures FIGURE E- 1: RECOMMENDATION 1 PROJECTS ............................................................................................... III FIGURE E- 2: TRANSMISSION EXPANSION EXTENDING BEYOND THE ROCKY MOUNTAIN REGION ............... V FIGURE E- 3: GENERATION ADDITIONS ASSUMED IN RECOMMENDATION 2................................................. VI FIGURE E- 4: ECONOMIC BENEFITS AND LOSSES ..........................................................................................VII FIGURE E- 5: ECONOMIC BENEFITS AND LOSSES ........................................................................................ VIII FIGURE 1- 1: NATURAL GAS AND COAL FUEL PRICES .................................................................................. 1-2 FIGURE 1- 2: 2008 FORECASTED GENERATING RESOURCE CAPACITY IN THE WESTERN INTERCONNECTION BY FUEL TYPE ..................................................................................................................................................... 1-3 FIGURE 1- 3: GAS-FIRED GENERATION ACCOUNTS FOR 92% OF NEWLY ADDED CAPACITY OVER THE LAST 10 YEARS ............................................................................................................................................................. 1-3 FIGURE 1- 4: PHASES OF RMATS WORK ...................................................................................................... 1-8 FIGURE 1- 5: CHRONOLOGY OF RMATS PHASE I ACTIVITIES ...................................................................... 1-9 FIGURE 2- 1: POTENTIAL BENEFITS OF NEW TRANSMISSION INVESTMENT .................................................. 2-1 FIGURE 2- 2: RMATS ANALYSIS PROCESS .................................................................................................... 2-3 FIGURE 2- 3: TRANSMISSION SYSTEM TOPOLOGY......................................................................................... 2-6 FIGURE 2- 4: RMATS REGIONAL AGGREGATION ........................................................................................ 2-6 FIGURE 2- 5: ANNUAL ENERGY (GWH) WITH COINCIDENTAL SUMMER AND WINTER PEAKS (GW) ............ 2-8 FIGURE 2- 6: EXAMPLE OF HOW CONGESTION ARISES AS LOADS GO UP DURING A TYPICAL SUMMER DAY2-11 FIGURE 2- 7: SAMPLE DURATION CURVE ................................................................................................... 2-12 FIGURE 2- 8: CONGESTION IF NO TRANSMISSION IS ADDED IN ALTERNATIVE 2 ....................................... 2-15 FIGURE 2- 9: TRANSMISSION ADDITIONS IN ALTERNATIVE 2 ..................................................................... 2-15 FIGURE 2- 10: TRANSMISSION ADDITIONS IN ALTERNATIVE 4 ................................................................... 2-17 FIGURE 3- 1: RECOMMENDATION 1: TRANSMISSION EXPANSION IN THE ROCKY MOUNTAIN AREA ............. 3-2 FIGURE 3- 2: TRANSMISSION EXPANSION EXTENDING BEYOND THE ROCKY MOUNTAIN REGION .............. 3-5 FIGURE 3- 3: GENERATION ADDITIONS ASSUMED IN RECOMMENDATION 2................................................. 3-6 FIGURE 3- 4: WESTERN INTERCONNECTION PRODUCTION COSTS .............................................................. 3-10 FIGURE 5- 1: FEDERAL LANDS AND WESTERN UTILITY GROUP CORRIDOR RECOMMENDATIONS ................ 5-3 FIGURE 5- 2: STATUS OF RECENT TRANSMISSION PROPOSAL 345 AND ABOVE ............................................. 5-4 iv Table of Tables TABLE E- 1: ANNUAL SAVINGS COMPARED TO REFERENCE CASES ................................................................ VI TABLE 2- 1: ANNUAL ENERGY (GWH) WITH COINCIDENTAL SUMMER AND WINTER PEAKS (GW)............... 2-8 TABLE 2- 2: TYPICAL PLANT OUTAGE RATES ................................................................................................ 2-9 TABLE 2- 3: 2013 RESOURCE ALTERNATIVES .............................................................................................. 2-13 TABLE 3- 1: RECOMMENDATION 1: TRANSMISSION EXPANSION IN THE ROCKY MOUNTAIN AREA ............. 3-3 TABLE 3- 2: BRIDGER EXPANSION INTERFACE (PATH) CAPACITY ADDITIONS ............................................. 3-4 TABLE 3- 3: WYOMING TO COLORADO INTERFACE (PATH) CAPACITY ADDITIONS ...................................... 3-4 TABLE 3- 4: CAPACITY INCREASES FROM CONSTRUCTION OF EXPORT TRANSMISSION ................................. 3-7 TABLE 3- 5: WESTERN INTERCONNECTION PRODUCTION COSTS (VOM) (MILLIONS OF DOLLARS) .............. 3-9 TABLE 3- 6: WESTERN INTERCONNECTION PRODUCTION COST SAVINGS FROM REFERENCE CASES .......... 3-11 TABLE 3- 7: ECONOMIC COMPARISONS ...................................................................................................... 3-13 TABLE 3- 8: ANNUAL SAVINGS COMPARED TO REFERENCE CASES............................................................. 3-14 TABLE 3- 9: ANNUAL SAVINGS COMPARED TO REFERENCE CASES- ........................................................... 3-14 TABLE 3- 10: ECONOMIC BENEFITS AND LOSSES (MILLIONS OF DOLLARS) ................................................ 3-16 TABLE 5- 1: AVERAGE CURTAILMENT BASED ON HOURLY ATC, IN PERCENT OF 100MW WIND FARM TOTAL OUTPUT ........................................................................................................................................................... 5-13 TABLE 5- 2: AVERAGE CURTAILMENT BASED ON HOURLY ATC, IN PERCENT OF 500 MW WIND FARM TOTAL OUTPUT .............................................................................................................................................. 5-14 v Executive Summary On August 22, 2003, Wyoming Governor Dave Freudenthal and Utah Governor Michael Leavitt announced the formation of the Rocky Mountain Area Transmission Study (RMATS). They did so because the electric power industry has been reluctant to invest in new transmission infrastructure due to protracted regulatory uncertainties. Without such investment, the region1 may not be able to tap lower cost coal and wind generation for Rocky Mountain load growth, or to export generation to other parts of the Western Interconnection. Making greater use of the region’s coal and wind resources can lower power costs to consumers and reduce the volatility of electricity prices. The Governors created a charter that established the guiding principles for the RMATS effort, which are: • Include all interested stakeholder individuals and groups; • Work together for effective solutions in a balanced, open and inclusive public process; • Conduct analysis of generation and transmission alternatives based on data, assumptions, and scenarios developed by participating stakeholders; • Consider every need, generation technology and location option that is appropriate for the region; • Evaluate all potential transmission alternatives within the region; • Identify the costs and benefits of generation and transmission options for serving the electricity needs of consumers that make operational, economic, and environmental sense for the region; and, • Cooperate and coordinate with the west-wide Seams Steering Group-Western Interconnection (SSG-WI) planning effort and other sub-regional planning efforts and with WECC in order to ensure maintaining or improving system reliability. The RMATS footprint covers the States of Colorado, Idaho, Montana, Utah and Wyoming. In the first phase of the RMATS process, stakeholders joined in work groups on load forecasting, resource additions, and transmission additions which developed assumptions that were input into a production cost model to examine the value of potential transmission expansion under different generation scenarios. The information used in the modeling effort is publicly available. A steering committee guided the integration of the activities of the work groups and the RMATS modeling team to: (1) evaluate the overall economics of transmission expansion under four generation scenarios; and, (2) identify transmission projects that may be economic and feasible because of the savings they provide Rocky Mountain region and elsewhere in the West. The analysis tested the sensitivity of the results under a variety of assumptions, such as high and low hydroelectric generation, high and low natural gas prices, significant improvements in energy efficiency, and potential imposition of constraints on carbon dioxide emissions. 1 In this Report the term “region will refer to the Rocky Mountain area of the states of Idaho, Montana, Wyoming, Utah and Colorado except where there are references to the Seams Steering Group-Western Interconnection (SSGWI) planning effort where the Rocky Mountain area will be referred to as a sub-region. Executive Summary I The most feasible transmission additions are recommended to proceed to Phase II. The purpose of Phase II is to conduct transmission technical studies, address siting and cost assignment and recovery issues, identify project sponsors, and arrange project financing. To jumpstart Phase II work, RMATS formed a cost allocation and cost recovery team to begin identifying promising approaches to financing the recommended transmission additions. The team also recommended process improvements that would (1) make it more likely that economic transmission expansion projects would be implemented; and, (2) set the stage for continuing improvements in transmission planning. Because of the potential for significant new wind generation in the Rocky Mountain region in the near term and the unique characteristics of wind development and operation, RMATS also formed a work group to explore ways in which the existing transmission system could be used more efficiently to enable the development of additional wind generation. The work group found, after comparing wind output and existing flow data on three specific transmission paths in the region, that there is substantial physical capacity available at most times of the year that current operational practices and tariff requirements do not make available to wind on a long-term basis. Additional study work will be required to take into account the scheduled use of the transmission system as well as the actual power flows. There is potential for wind to make better use of the existing system through innovative tariff products. A “conditional firm” product would offer firm service except for certain defined periods, and a long term “priority non-firm” product would offer a high priority non-firm service on a long-term contractual basis. Other resources may find this product attractive also. Contractual, tariff and operating practices limit the use of existing transmission assets. Such institutional impediments also limit transmission access and raise the cost of operating and expanding the grid. Removing or reducing these impediments would enable the existing system to be used more fully and optimally, and potentially allow some capital investment in grid expansion to be deferred. The RMATS simulation includes the benefits of a regionally operated system that avoids rate pancaking, consolidates control areas, and removes other institutional impediments to fuller use of the existing system. Recommended Projects The RMATS process identified two projects that are needed to serve load in the near-term, involve limited investment and provide significant benefits: • • A transformer replacement at Flaming Gorge to increase transfer capacity on existing lines in southwest Wyoming and northeast Utah; and A phase shifter on the line between Montana and Idaho to increase the control of actual flow and usability of the path from Montana. The Western Area Power Administration will replace the transformers at Flaming Gorge in 2006; and Northwestern Energy, Idaho Power Company and PacifiCorp are examining the addition of the phase shifter. Recommendation 1: Expansion Projects within the Rocky Mountain Footprint RMATS identified projects that would provide significant economic benefit over the longer term. There are three discreet transmission projects within the RMATS footprint included in Recommendation 1, and several options in Recommendation 2 for longer-term development. Figure E-1 shows the three discrete projects included in Recommendation 1: Montana Upgrades Executive Summary II (tan oval), Bridger Expansion (green oval), and Wyoming to Colorado Project (yellow oval). The capital cost for these three transmission expansion projects is estimated to be $970 million. An economic comparison of Recommendation 1 with the two Reference Cases indicates these three transmission expansion projects are cost justified and capable of producing annual net savings of $61 million to $531 million per year. While each project is discrete, the three projects together provide the greatest benefit to the region. Figure E- 1: Recommendation 1 Projects Montana to NW Taft Modified Interface 280 Wind West of Broadview Townsend West of Colstrip Broadview Garrison Added Resource 250 Coal Added 345 kV Line Montana Upgrades 50 Wind Colstrip 359 Coal Added Series Compensation Only Borah West Midpoint 250 Wind 125 Wind Path C Treasureton 700 Coal West of Bridger Black Hills to C. Wyoming Dave Johnston 575 Coal 100 Wind Antelope Mine Bridger E LRS Jim Bridger Ben Lomond West of Naughton Naughton Miners 1150 Wind 500 Wind Cheyenne Tap TOT 4A TOT 3 Ault 575 Coal Bridger Expansion C Wyoming to LRS New WY- CO lines TOT 7 Green Valley 140 Gas 210 Gas 500 Coal 500 Wind Recommendation 1 is predicated on the new wind capacity and coal-fired generation additions shown on the map. The new capacity will meet expected load growth in the Rocky Mountain region for the 2013 timeframe. Montana System Upgrade Project This project upgrades the existing Montana 500 kV transmission system to enable exports from the Rocky Mountain region to the Pacific Northwest and does not require new transmission lines. By installing series compensation in the 500 kV lines from Colstrip to Taft, adding a 500/230 kV autotransformer at Colstrip, and adding two new substations on the 500 kV transmission system near Ringling and Missoula, transfer capacity can be increased by an estimated 500 MW. The capital cost for the Montana System Upgrade project is estimated to be $72 million. The resource additions assumed include 330 MW of nameplate capacity wind generation and 609 MW of coal-fired generation in Montana. The Montana System Upgrade is expected to have limited siting requirements. All the impacts are local in nature and a new transmission corridor is not required. The additions at the Colstrip and Broadview buses constitute upgrades to existing substation sites and will have little if any Executive Summary III environmental impact. The new substation sites will have minimal siting requirements. Acquisition of sufficient land for the substations may be the most serious issue. Local opposition may be reduced if future ties to the lower voltage systems at these two locations reduce the requirements for new transmission in these areas as loads grow. Bridger Expansion Project Expansion of the Bridger 345 kV transmission system involves the addition of 345 kV transmission facilities from Miners to Bridger in Wyoming and from Bridger to Ben Lomond in Utah and to Midpoint in Idaho. These additions would increase transfer capacity by an estimated 1,350 MW. Resource additions are assumed to include 1,375 MW of wind and 575 MW of coal-fired generation in southwest Wyoming and southern Idaho. The capital cost of the Bridger Expansion project is estimated to be $580 million. A new transmission corridor may be required between Naughton and northern Utah, and a new transmission corridor will be required between Bridger and Midpoint (potentially traversing an environmentally sensitive area north of Bear Lake in southern Idaho). New substation sites could have siting requirements. Siting issues may be reduced through use of existing lower voltage transmission corridors. Wyoming to Colorado Transmission Project This project involves the addition of a 345 kV line from northeastern Wyoming across the constrained path between Wyoming and Colorado to Denver. The new line is estimated to increase capacity by 500 MW. The addition of series compensation to this new line (and potentially other lines) is estimated to increase capacity by an additional 250 MW. Assumed resource additions are 500 MW of wind capacity and 700 MW of coal-fired generation capacity. The capital requirements for the Wyoming to Colorado project are an estimated $318 million. The new 345 kV line would have substation interconnections in Wyoming potentially in the Dave Johnston, Laramie River Station and Cheyenne areas. It would also require an interconnection in northern Colorado, perhaps at the Ault substation, with a final destination near the Green Valley substation northeast of Denver. Congestion resulting from the generation additions would be reduced from an estimated high of 73 percent to below 30 percent with these line additions. Substantial siting work is expected. Siting issues may be reduced through use of existing lower voltage transmission corridors. Recommendation 2: Export Projects beyond the Rocky Mountain Footprint In addition to the projects in Recommendation 1, RMATS recommends transmission expansions that extend beyond the Rocky Mountain States to enable exports of generation. This is a longerterm export proposal that: (1) includes the generation assumed for the projects in Recommendation 1; (2) assumes construction of an additional 3,900 MW of coal generation and remote wind generation; and, (3) builds two export paths to the West Coast, Nevada and Arizona markets. The viability of Recommendation 2 depends on the fuel preferences of load-serving entities outside the Rocky Mountain region. Recommendation 2 includes two of five optional 500 kV paths shown in the colored ovals in Figure E-2. Additional transmission upgrades in the Rocky Mountain region are also part of Executive Summary IV Recommendation 2, including: • Upgrading the Bridger Expansion project from 345 kV to 500 kV west of Bridger. Specifically, new 500 kV lines would be added between Bridger and Ben Lomond, Ben Lomond and Midpoint, Ben Lomond and Kinport, Borah and Midpoint, Borah and Ringling (including a phase shifter), and Ringling and Broadview; • In lieu of a line from Broadview to Ringling to Borah, a 500 kV line from Broadview to Hot Springs may be considered; and, • Adding new 345 kV lines between Grand Junction and Emery, Antelope and Laramie River Station, and Dave Johnson to Bridger. In addition, the existing IPP-Adelanto DC line would be upgraded. The capital cost for the Recommendation 2 transmission expansion is estimated to be $4,265 million. Figure E- 2: Transmission Expansion Extending Beyond the Rocky Mountain Region Bell Noxon Taft Ashe Great Falls Hot Springs Missoula Grizzly Broadview Colstrip Midpoint 500 kV Kinport 345 kV Dave Johnson Borah Inc. DC Consistent with Rec 1 Ringling Option 1 Jim Bridger LRS Ben Lomond Naughton Table Mtn. IPP Ant Mine Miners Mona Cheyenne Tap Ault Emery Grand Junction Tesla Crystal Added Phase Shifter Red Butte This recommendation requires two 500 kV lines for export Option 2 Green Valley Option 3 Market Place Adelanto Options 2-4 Option 4 Option 1 Only The economic analysis for these transmission export options was based on the assumed generation additions shown in Figure E-3. Executive Summary V Figure E- 3: Generation Additions Assumed in Recommendation 2 500 Coal 950 Wind 260 Gas 500 Wind 609 Coal 100 Wind 250 Wind 1400 Coal 125 Wind 50 Gas 575 Coal 160 Wind 1000 Wind 500 Wind 200 Wind 950 Coal 250 575 Coal 140 Gas Wind 1540 Coal 210 Gas 800 Wind 120 Wind Economic Analysis of Recommendations To determine the benefits from transmission expansion, annual electricity production costs were simulated using the generation additions outlined above. The production costs were then added to the annualized capital and other fixed costs for the resource and transmission additions. These project cost totals were then compared with the project cost totals from two reference cases, an “all gas” case and an “IRP case”2. Table E-1 summarizes the annual savings from Recommendations 1 and 2 compared with the two reference cases. Table E- 1: Annual Savings Compared to Reference Cases (Savings West-wide for Representative Year, Millions of Dollars) Reference Case All-Gas Case IRP-Based Case Recommendation 1 (531) (61) Recommendation 2 (986) (516) These estimated economic benefits are based on critical assumptions, including the future price of natural gas and hydroelectric conditions. These benefits assumed a 2013 gas price of $6.50/MMBtu ($5.20 in 2004 dollars). If natural gas prices drop and remain at $4.50 ($3.60 in 2004 dollars) over the long term, then the economic benefits of the Recommendations would be largely eliminated. However, if one assumes $6.50 gas prices and low hydro conditions over time, then the annual 2 The All-Gas Reference Case assumes all load growth in the Western Interconnection is met by gas-fired generation. The IRP-based Reference (integrated resource plan) Case is grounded in the resource plans of PacifiCorp, Idaho Power and Xcel Energy and assumes all new generation outside the RMATS footprint is gasfired. Executive Summary VI production cost savings and the net benefit from constructing the projects in Recommendations 1 and 2 are significantly higher than shown in the table. Equally important, but not evaluated in the modeling, are the natural gas price hedging benefits of increasing access to coal and wind resources, through new transmissions. Strategies to hedge against volatile natural gas prices are important to provide greater stability in electricity prices. Analyses were also performed to test the sensitivity of the findings to increased energy efficiency and potential constraints on carbon emissions. Increased energy efficiency could reduce or eliminate the need for new generation and transmission to meet load growth within the Rocky Mountain region. However, in that event, the transmission expansions in the Recommendation 2 would enable exports that reduce costs outside the Rocky Mountain region. A carbon adder of $15 per ton would not affect the dispatch of power plants that have been constructed by the time the adder is imposed. However, such a carbon constraint would affect the choice of new generation, an issue addressed in utility resource plans and not in this report. Understanding where economic benefits will fall helps to identify likely project participants. The distribution of economic benefits from the projects in Recommendations 1 and 2 can be inferred from the modeling data, but not precisely calculated because the model diverges from current conditions by assuming perfect competition and locational marginal pricing. Figures E-4 and E-5 show the estimated distribution of annual economic gains based on fuel and other variables from Recommendations 1 and 2. Figure E- 4: Economic Benefits and Losses (Annual Benefits in Millions of Dollars) Recommendation 1 Compared to Reference Cases 1,800 1,600 1,400 Annual Benefits in $ millions 1,106 1,200 1,000 The Rocky Mountain region benefits, while other regions are largely unaffected. 800 600 290 400 200 0 (200) Rocky Mountain California Northwest Recommendation 1 Compared to IRP-Based Reference Case Executive Summary Desert SW Canada Mexico Recommendation 1 Compared to All Gas - Reference Case VII Figure E- 5: Economic Benefits and Losses (Annual Benefits in Millions of Dollars) Recommendation 2 Compared to Reference Cases 1,742 1800 1600 1400 Both the Rocky Mountain region and California enjoy significant benefits. Other regions are largely unaffected. Annual Benefits in $ millions 1200 926 1000 800 600 400 200 0 -200 Rocky Mountain California Northwest Recommendation 2 Compared to IRP - Reference Case Desert SW Canada Mexico Recommendation 2 Compared to All Gas - Reference Case The distribution of economic gains associated with the three projects in Recommendation 1 fall predominantly within the Rocky Mountain region. This makes a compelling case for project beneficiaries to undertake needed technical studies and for entities in the Rocky Mountain region to work together to develop a cost allocation and cost recovery solution to capture this benefit. Recommendation 2 entails exports from the Rocky Mountain region that would help the West diversify fuels and reduce opportunities to exercise market power by allowing new generators to develop projects that compete with incumbents. With Recommendation 2, the annual consumer and generator benefits for the Rocky Mountain region increases to between $926 million to $1.7 billion. California consumers also stand to benefit from Recommendation 2, by $325 million to nearly $400 million annually. These results suggest that RMATS Phase II should coordinate work on Recommendation 2 with California’s transmission planning institutions. Next Steps As an initial step under Phase II, RMATS recommends, for each of the recommended transmission expansion projects, that the Governors of the states where the line would be sited convene a meeting of their public utility commissioners and the CEOs of entities that would benefit for the purpose of: (1) presenting the RMATS findings; (2) urging the beneficiaries to sponsor the projects; Executive Summary VIII (3) setting in place a process to address siting and cost allocation and recovery issues, (4) assessing financing issues; and, (5) initiating technical studies. The Governors should also consider inviting Governors and public utility commissioners from states outside the geographic scope of the transmission projects that would also benefit. • For the Montana System Upgrade Project, RMATS recommends that the Governor of Montana convene a meeting of the CEOs of Northwestern Energy, the Bonneville Power Administration, the Montana Public Service Commission, coal and wind power plant developers in Montana, merchant transmission developers, and other potential project sponsors and participants. • For the Bridger Expansion Project, RMATS recommends that the Governors of Idaho, Utah and Wyoming convene a meeting of the CEOs of Idaho Power, PacifiCorp, the Utah Associated Municipal Power Systems, the Utah Municipal Power Authority, the Wyoming Infrastructure Authority, coal and wind power plant developers in Wyoming, the Idaho Public Utilities Commission, the Utah Public Service Commission, the Wyoming Public Service Commission, merchant transmission developers, and other potential project sponsors and participants. • For the Wyoming to Colorado Transmission Project, RMATS recommends that the Governors of Colorado and Wyoming convene a meeting of the CEOs of Xcel Energy, PacifiCorp, Black Hills Power, Basin Electric Power Cooperative, Tri-State G&T, the Western Area Power Administration, the City of Colorado Springs, the Platte River Power Authority, the Colorado Public Utilities Commission, the Wyoming Public Service Commission, the Wyoming Infrastructure Authority, coal and wind power plant developers in Wyoming and Colorado, merchant transmission developers, and other potential project sponsors and participants. • For the export project options included in Recommendation 2, RMATS recommends that, depending on the option under consideration, the Governors of the affected states convene a meeting of the interested utilities, regulatory agencies and others. For example, if an option enhancing exports to California were being considered, we recommend that the Governors of Utah, Idaho and California convene a meeting including PacifiCorp, the Utah Association of Municipal Power Systems, California investor-owned and municipal utilities, the California ISO, the Utah Public Service Commission and the California Public Utility Commission. The Wyoming Infrastructure Authority should also be involved in meetings associated with Recommendation 2 projects. Following such meetings, technical studies need to be conducted to examine the impact of the recommended projects on transmission system operations. Needed Institutional Improvements To improve the process of evaluating and financing transmission expansion and to operate the existing transmission system more efficiently, RMATS recommends that: • Multi-State transmission expansion pricing principles be developed; Executive Summary IX • The Wyoming Infrastructure Authority be engaged in transmission expansion financing discussions; • The evaluation of transmission expansion to facilitate power exports from the Rocky Mountain region be integrated with regional planning in other parts of the Western Interconnection; • Governors and regulators consider the formulation of a Regional Transmission Organization (RTO) with features appropriate to the region, including independence and costeffectiveness; and • The physical transfer capacity on existing lines be better utilized by requesting that transmission owners develop conditional firm or priority non-firm transmission products that quantify curtailment risks and place curtailment priority for conditional firm ahead of any non-firm transactions and curtailment priority for priority non-firm ahead of any nonfirm transactions except secondary network resource service. Further following specific actions are recommended: 1. To address cost allocation and recovery uncertainties, RMATS recommends that the state public utility commissions and energy agencies in the five states in the RMATS footprint deliver a report to their Governors in six months discussing multi-state transmission expansion cost recovery and pricing principles. 2. RMATS recommends that the regulatory commissions in Colorado, Idaho, Montana, Utah and Wyoming enter into a memorandum of agreement adopting pricing principles, and jointly file the MOA with FERC, requesting its endorsement. These principles would then apply to any applications for transmission cost recovery received by regulatory commissions within the Rocky Mountain region, providing a degree of certainty and consistency in regulatory treatment. 3. RMATS recommends that the RMATS Steering Committee, Load Forecasting Work Group, Resource Additions Work Group, Transmission Additions Work Group, and Cost Allocation/Cost Recovery Team be maintained and be available to conduct additional work as conditions warrant. An agreement among states and the electric power industry to maintain and finance a pro-active transmission planning process in the Rocky Mountain region is needed. 4. RMATS recommends that SSG-WI use RMATS export case analyses in the development of an interconnection-wide “realistic” generation scenario that would be studied in late 2004 and early 2005. Executive Summary X Chapter 3 - Recommendations for Transmission Expansion A. Introduction As noted in Chapter 2, the Work Groups developed and evaluated generation and transmission alternatives through a series of scenarios and simulation studies. From these economic screening analyses and with the professional judgment of Work Group members, two recommendations are made to expand the region’s transmission system. These recommendations are dependent upon further technical studies to address siting, financing, cost allocation and recovery, and other issues in RMATS Phase II. They are endorsed by the Steering Committee, and are respectfully offered to the sponsoring Governors, State and Federal regulators and potential project participants for their consideration. The two transmission expansion recommendations, along with two reference cases, are described in this chapter. Production cost results from system simulation studies are presented, as are cost/benefit analyses that take into account production costs, capital investment requirements, and annualized fixed costs. Economic benefits and losses are then estimated by region within the West. Chapters 4 and 5 address the challenging issues that lay ahead for further work on these recommendations in Phase II and beyond. B. Recommendations for Transmission Expansion The RMATS Steering Committee urges that the following transmission recommendations be pursued in Phase II: • Recommendation 1, consisting of three transmission expansion projects within the Rocky Mountain region. These include a Montana System Upgrade, a Bridger Expansion, and a Wyoming to Colorado Project. • Recommendation 2, consisting of a larger transmission build, extending outside the Rocky Mountain region to enable exports from the Rocky Mountain region. The RMATS Steering Committee also supports two projects that are currently being analyzed by local entities. These incremental projects are relatively low-cost enhancements that provide economic benefits and can be accomplished in the near term to resolve some immediate congestion problems. The projects involve adding a phase shifter on the Idaho to Montana Amps line and upgrading the capacity of two transformers on the Flaming Gorge line. The economic analysis of these investment priorities is included in Appendix B.3. Recommendation 1: Projects within the Rocky Mountain Footprint Figure 3-1 shows the three discrete projects included in Recommendation 1. These expansions include: • • Montana Upgrades (tan oval), Bridger Expansion (green oval), and Chapter 3 Rocky Mtn. Area Transmission Study 3-1 • Wyoming to Colorado Project (yellow oval). This recommendation is predicated on the new wind capacity and coal-fired generation additions as shown in Figure 3-1. The new capacity will meet expected load growth in the Rocky Mountain region. Figure 3- 1: Recommendation 1: Transmission Expansion in the Rocky Mountain Area Modified Interface Montana to NW Taft 280 Wind West of Broadview Townsend Montana Upgrades 50 Wind Colstrip 250 Coal Added 345 kV Line Added Series Compensation Only West of Colstrip Broadview Garrison Added Resource 359 Coal Borah West Midpoint 250 Wind 125 Wind Path C Treasureton 700 Coal West of Bridger Black Hills to C. Wyoming Dave Johnston 575 Coal 100 Wind Antelope Mine Bridger E LRS Jim Bridger Ben Lomond Naughton West of Naughton Miners 1150 Wind 500 Wind Cheyenne Tap TOT 4A TOT 3 Ault 575 Coal Bridger Expansion C Wyoming to LRS New WY- CO lines TOT 7 Green Valley 140 Gas 210 Gas 500 Coal 500 Wind The capital cost for Recommendation I is estimated to be $970 million for the three transmission expansion projects and $6.604 billion for generating resources. Using reasonable assumptions, an economic comparison of Recommendation 1 with the two reference cases indicates these three projects are economic, producing annual net savings of between $61 million and $531 million. While each project is discrete, the three projects together provide the greatest benefit to the region. Montana System Upgrade Project This project upgrades the existing Montana 500 kV transmission system to enable exports from the Rocky Mountain region to the Pacific Northwest. This project does not include new transmission lines. By installing series compensation in the 500 kV lines from Colstrip to Taft, adding a 500/230 kV autotransformer at Colstrip, and adding two new substations on the 500 kV transmission system near Ringling and Missoula, transfer capacity on this path will increase by 500 MW. The capital costs for the Montana System Upgrade project are estimated to be $72 million. These transmission additions efficiently reduced the congestion created by the assumed generating resource additions, which include 330 MW of nameplate capacity wind generation and 609 MW of coal-fired generation in Montana. Several transmission options were considered to expand capacity to move this additional generation, including transmission from Ringling, Montana, to Borah, Idaho, Chapter 3 Rocky Mtn. Area Transmission Study 3-2 transmission from Colstrip to Northern Wyoming, and upgrades to the existing Montana 500 kV system. The Ringling-Borah transmission option relieved the congestion but provided more capacity than would be needed for the assumed generation additions. A transmission line into Northern Wyoming did not relieve the congestion across cut planes in Montana. The Montana System Upgrade is expected to have limited siting requirements. All the impacts are local in nature and a new transmission corridor is not required. The additions at the Colstrip and Broadview buses constitute upgrades to existing substation sites and will have little if any environmental impact. The new substation sites will have minimal siting requirements. This project may be completed within a two-year period. Table 3-1 shows the transfer capacity associated with the Montana System Upgrade. Table 3- 1: Recommendation 1: Transmission Expansion in the Rocky Mountain Area Interface Transmission Addition West of Colstrip Added Series Capacitor Added Series Capacitor Added Series Capacitor West of Broadview Montana to Northwest Before (Reverse) – Forward N/A - 2,598 After Incremental (Reverse) – (Reverse) – Forward Forward N/A – 3,098 +500 N/A – 2,572 N/A – 3,072 +500 (1,350) - 2,200 (1,350) - 2,700 +500 Bridger Expansion Project Expansion of the Bridger 345 kV transmission system involves the addition of 345 kV transmission facilities from Miners to Bridger in Wyoming and from Bridger to Ben Lomond in Utah and to Midpoint in Idaho. These additions would increase transfer capacity by an estimated 1,350 MW and support the resource additions of 1,375 MW of wind generation and 575 MW of (Bridger) coal-fired generation in southwest Wyoming and southern Idaho. The capital cost of the Bridger Expansion project is estimated to be $580 million. A new transmission corridor may be required between Naughton and northern Utah, and a new transmission corridor will be required between Bridger and Midpoint (potentially traversing an environmentally sensitive area north of Bear Lake in southern Idaho). New substation sites could have siting requirements. Siting issues may be reduced through use of existing lower voltage transmission corridors. This project may be completed within a five-year period. Table 3-2 shows the increases in transfer capacity with the recommended Bridger Expansion. Chapter 3 Rocky Mtn. Area Transmission Study 3-3 Table 3- 2: Bridger Expansion Interface (Path) Capacity Additions Interface Addition Bridger West- w/ series comp Before After Incremental (Reverse) – (Reverse) – (Reverse) – Forward Forward Forward N/A – 2,200 N/A – 3,550 +1,350 Bridger to Treasureton 345kV Bridger to Naughton 345kV Borah West - w/ Treasureton to Midpoint N/A – 2,307 N/A – 3,057 +750 series comp 345kV Loop in Ben Lomond to (750) – 750 (1,500) – +750 Path C- w/ series Borah at Treasureton With seasonal 1,500 (Nominal) variation West of Naughton- Naughton to Ben Lomond N/A – 920 N/A – 1,520 +600 w/ series comp 345kV Bridger East Miners to Jim Bridger (600) - 600 (1,100) – +500 345kV 1,100 Wyoming to Colorado Transmission Project This project involves the addition of a 345 kV line from northeastern Wyoming across the constrained path between Wyoming and Colorado to Denver. The new line is estimated to increase capacity by 500 MW. The addition of series compensation to this new line (and potentially other lines) is estimated to increase capacity by an additional 250 MW and support the assumed resource additions of 500 MW of wind (nameplate capacity) and 700 MW of coal-fired generation capacity. The capital requirements for the Wyoming to Colorado project are an estimated $318 million. The new 345 kV line would have substation interconnections in Wyoming, potentially in the Dave Johnston, Laramie River Station and Cheyenne areas. It would also require an interconnection in northern Colorado, perhaps at the Ault substation, with a final destination near the Green Valley substation northeast of Denver. Congestion resulting from the assumed generation additions would be reduced from an estimated high of 73 percent to below 30 percent with these line additions. Siting issues may be reduced through use of existing lower voltage transmission corridors. This project may be completed within a five-year period. Table 3-3 shows the increased transfer capacity associated with the Wyoming to Colorado Project. Table 3- 3: Wyoming to Colorado Interface (Path) Capacity Additions Antelope Mine to DJ 345kV Before (Reverse) – Forward (332) - 332 After (Reverse) – Forward (832) - 832 Incremental (Reverse) – Forward +500 LRS to C Wyoming TOT 3- w/ series comp DJ to LRS 345kV Cheyenne Tap to Ault 345kV (640) - 640 N/A – 1,424 (1,140) – 1,140 N/A – 2,174 +500 +750 TOT 7- w/ series comp TOT 4A Ault to Green Valley 345kV Miners to Cheyenne Tap 345kV N/A – 890 N/A – 810 N/A – 1,640 N/A – 1,560 +750 +750 Interface Addition Black Hills to C. Wyoming Chapter 3 Rocky Mtn. Area Transmission Study 3-4 Recommendation 2: Export Projects Beyond the RMATS Footprint RMATS also recommends transmission expansions that extend beyond the Rocky Mountain states to enable exports of generation. This is a longer-term export proposal that: (1) includes the generating resources assumed for the projects in Recommendation 1; (2) assumes construction of an additional 3,900 MW of coal generation and remote wind resources; and, (3) builds two export paths to the West Coast, Nevada and Arizona markets. The viability of Recommendation 2 depends on the fuel preferences of load-serving entities (LSEs) outside the Rocky Mountain region. Recommendation 2 includes two of five optional 500 kV paths shown in the colored ovals in Figure 3-2. Additional transmission upgrades in the Rocky Mountain region beyond those identified in Recommendation 1 are also part of Recommendation 2, including: • Upgrading the Bridger Expansion project from 345 kV to 500 kV west of Bridger. Specifically, new 500 kV lines would be added between Bridger and Ben Lomond, Ben Lomond and Mid Point, Ben Lomond and Kinport; Borah and Midpoint, Borah and Ringling (including a phase shifter), and Ringling and Broadview. • Adding new 345 kV lines between Grand Junction and Emery, Antelope and Laramie River Station, and Dave Johnston to Bridger. The capital cost for the Recommendation 2 transmission expansion is estimated to be $4.265 billion and $ 10.05 billion for generating resources. Figure 3- 2: Transmission Expansion Extending Beyond the Rocky Mountain Region Recommended for Further Development Bell Noxon Taft Ashe Great Falls Hot Springs Missoula Grizzly Broadview Colstrip Midpoint 500 kV Kinport 345 kV Dave Johnson Borah Inc. DC Consistent with Rec 1 Ringling Option 1 Jim Bridger LRS Ben Lomond Naughton Table Mtn. IPP Ant Mine Miners Mona Cheyenne Tap Ault Emery Grand Junction Tesla Crystal Added Phase Shifter Red Butte This recommendation requires two 500 kV lines for export Option 2 Green Valley Option 3 Market Place Adelanto Options 2-4 Option 4 Option 1 Only Chapter 3 Rocky Mtn. Area Transmission Study 3-5 The economic analysis for these export options is based on the generation additions shown in Figure 3-3. Figure 3- 3: Generation Additions Assumed in Recommendation 2 500 Coal 950 Wind 260 Gas 500 Wind 609 Coal 100 Wind 250 Wind 1400 Coal 125 Wind 50 Gas 575 Coal 160 Wind 1000 Wind 500 Wind 200 Wind 950 Coal 250 Wind 1540 Coal 575 Coal 210 Gas 140 Gas 800 Wind 120 Wind Total resource additions are assumed to include 660 MW of new gas-fired generation, 4,955 MW of remote wind resources (nameplate capacity) and 6,149 MW of coal-fired Powder River Basin generation. To export this remote generation, the existing IPP-Adelanto DC line would be upgraded and two 500 kV lines to export markets would be needed. Five potential paths were examined for these 500 kV lines. Study results show the economic benefits for different combinations of paths to be similar. Decisions on which two paths to pursue will need to be determined as technical studies, right-of-way issues, cost recovery issues, and financing options are addressed in Phase II. Chapter 3 Rocky Mtn. Area Transmission Study 3-6 Table 3-4 summarizes the estimated increases in transfer capacity from the transmission facilities added in Recommendation 2. Table 3- 4: Capacity Increases from Construction of Export Transmission Interface Option West of Colstrip West of Broadview 1-4 1-4 2-4 1 1-4 1 1 Added Series Capacitor Added Series Capacitor Broadview to Ringling 500kV Broadview to Hot Springs (via Great Falls) 500kV Added Series Capacitor Hot Springs to Noxon 500kV Noxon to Ashe (via Bell) 500kV 2-4 1-4 1 2-4 1-4 1-4 2-4 1 2-4 1 1-4 1-4 Ringling to Borah 500 kV [phase shifter] Bridger to Borah 500kV (series comp) Bridger to Ben Lomond 500kV (series comp) Bridger to Naughton 500kV (series comp) Kinport to Midpoint 500kV (convert 345kV) 2 Borah to Midpoint 500kV Naughton to Ben Lomond 500kV (series comp) Bridger to Ben Lomond 500 kV Ben Lomond to Borah 500kV Ben Lomond to Midpoint 500 kV Miners to Jim Bridger 345kV Ant Mine to DJ 345kV 1-4 1-4 1-4 Montana to Northwest West of Hatawai Idaho to Montana Bridger West Borah West West of Naughton Path C Bridger East Black Hills to C. Wyoming Black Hills to LRS LRS to C Wyoming TOT 1A Addition Before (Reverse) – Forward N/A - 2,598 N/A – 2,572 (1,350) - 2,200 N/A – 4000 (337) – 337 N/A – 2,200 Incremental (Reverse) – Forward +500 +500 +1000 +1000 +500 +1000 +1000 (750) -750 w/ seasonal variations (600) – 600 (332) – 332 +1000 +1000 +1000 +1000 +500 +2000 +1000 +1000 +1000 +1000 +500 +500 Ant Mine to LRS 345kV DJ to LRS 345kV Emery to Grand Junction 345kV (332) – 332 (640) – 640 N/A – 650 +500 +500 +500 N/A – 2,307 N/A – 920 TOT 3 1-4 Cheyenne Tap to Ault 345kV N/A - 1,424 +500 TOT 7 TOT 4A 1-4 1-4 N/A – 890 N/A – 810 TOT 2C 2-3 Ault to Green Valley 345kV Miners to Cheyenne Tap 345kV Dave Johnston to Jim Bridger Ben Lomond to Market Place (via Mona, Red Butte & Crystal) 500kV [phase shifter] (series comp) Midpoint to Market Place (via Crystal) 500kV (series comp) Midpoint to Tesla (via Table Mtn) 500kv (series comp) Midpoint to Grizzly (series comp) (300) – 300 +500 +500 +500 +1200 N/A +1200 N/A +1500 (400) – 1,500 +1000 (300) – 1,920 N/A +500 N/A Idaho to Las Vegas 4 Idaho to N. California Midpoint-Summer Lake IPP DC Others 1, 2, 4 2&3 1-4 1-4 1-4 Add Converter Stations LRS to Cheyenne Tap 345kV Borah to Kinport 345kV C. Two Reference Cases Recommendations 1 and 2 are predicated on the development of remote coal and wind resources to meet the region’s load growth and to serve export markets, and they entail substantial new investment in transmission. Two reference cases were created to compare economic benefits of the remote generation/transmission intensive recommendations and alternatives that do not rely on new transmission. These reference cases avoid or minimize new transmission investment primarily by locating new generation near loads. Chapter 3 Rocky Mtn. Area Transmission Study 3-7 The reference cases differ in the type and location of resource additions in the Rocky Mountain region. The All-Gas Reference Case assumes that load growth is met through new gas-fired generation. The IRP-Based Reference Case includes new gas-fired generation, but also new coal generation, primarily at existing sites, and new wind resources. The reference cases are similar in that both add the same overall resource capacity, and both use the same gas and coal fuel prices and hydro condition assumptions. Both cases assume that generation additions outside the Rocky Mountain states after 2008 will take the form of gas-fired generation located near loads. Both cases also include no significant transmission investment other than for resource integration. As a result, the reference cases bracket a range of potential outcomes that would occur if little new transmission were built. All-Gas Reference Case: This case assumes that load growth in the Rocky Mountain states for the 2008 to 2013 period will be met exclusively by adding gas-fired generation located close to load centers. Capital investment in this case is limited to gas-fired generation additions and associated interconnection costs. The All-Gas Reference Case is representative of the recent past. In the 1990’s, nearly all load growth in the West was met by building gas-fired plants. The All-Gas Reference Case assumes this trend will continue, and it is akin to a “do-nothing” case from a transmission expansion perspective. This case is useful for comparing the fuel and investment costs of alternative resources, and for measuring the value of diversifying fuels. Indeed, annual west-wide production costs in Recommendations 1 and 2 are $1.238 to $2.560 billion lower than the All-Gas Reference Case. IRP-Based Reference Case: This case is based on resource additions in the integrated resource plans of LSE’s in the Rocky Mountain states, where available. Where IRPs are not available, wind capacity is assumed to fill the gap. The IRP-Based Reference Case presumes significant wind and some coal resources are added. Because little transmission is added in the IRP-Based Reference Case, wind generation additions are limited by transmission capacity and the physical ability of coal plants to rapidly cycle to meet changes in the output of wind generators1. Consequently, production costs are substantially lower than in the All-Gas Reference Case because of lower fuel costs. Capital requirements are higher than in the All-Gas Reference case because of the higher up-front cost of remote coal and wind units. The IRP-based case is a compilation of existing IRPs, and as such, represents the current planning path for major LSEs in the RMATS footprint; but they may, however, not include the transmission investment that would be required to integrate the wind and other resources they propose. The annual reduction in the West’s production costs between the IRP-based and All-Gas Reference Cases ($972 million) indicates the value that may be created by capitalizing on the region’s lower cost fuels. To the extent that transmission bottlenecks preclude the wind and coal generation in IRPs from being developed, this reduction in production costs would not materialize as LSEs turn to gasfired plants to meet load growth. The reduction in annual production costs between the IRP-based reference case and Recommendation 1 ($266 million) reflects the value that could be created by moving from company-specific resource planning to regionally integrated resource and transmission planning. 1 There may be new coal generation technologies that could minimize the problem of cycling coal plants to accommodate more wind generation, such as Integrated Gasification/Combined Cycle (IGCC) coal plants coupled with temporary gas storage capability that would enable the gasification process to operate continuously, but the burning of the gas to generate electricity could better match periods of slack wind generation. Chapter 3 Rocky Mtn. Area Transmission Study 3-8 The two reference cases represent a range of costs for meeting load growth in the Rocky Mountain region if transmission expansions do not occur. The following is a comparison of costs and savings between Recommendations 1 and 2 and the two reference cases. D. Economic Evaluation The economic evaluation begins with a simulation of productions costs for 2013. Sensitivities on certain key assumptions are included. Capital requirements and annualized fixed costs are then calculated and combined with the production costs for an overall economic comparison. The distribution of economic gains and losses associated with changes in production costs are also determined. Production Costs The simulation logic seeks to minimize production costs for the Western Interconnection, including fuel and other variable operating and maintenance (O&M) costs. Production costs for Recommendations 1 and 2 and the two reference cases are illustrated in Figure 3-4. Production costs are lower in Recommendations 1 and 2 than in the two Reference Cases because the addition of transmission and large amounts of coal- and wind generation displace higher-cost natural gasfired generation. The production costs produced in the All-Gas and IRP-Based Reference Cases are estimated to be $21.018 billion and $20.046 billion, respectively. Production costs for Recommendation 1 are estimated to be $19.780 billion, a reduction of $1.238 billion and $266 million, respectively, when compared to the All-Gas and IRP-Based Reference Cases. Production costs for Recommendation 2 are estimated to be $18.458 billion, a substantially greater reduction from the All-Gas and IRP-Based reference cases of $2.56 billion and $1.588 billion, respectively. Table 3- 5: Western Interconnection Production Costs (VOM) (millions of dollars) Recommendation 2 Defference reflects benefit of moving from companyspecific IRPs to regionally integrated resource and transmission Wind and coal exports displace gas $18,458 generation because fuel costs are lower $19,780 Recommendation 1 $20,046 IRP-Bas ed Reference Cas e Higher, more uncertain fuel costs than coal $21,018and wind alternatives A ll Gas Reference Cas e $18,000 $18,500 $19,000 $19,500 $20,000 $20,500 $21,000 $ Millions Chapter 3 Rocky Mtn. Area Transmission Study 3-9 $21,500 E. Sensitivities The production costs in Figure 3-4 are calculated with natural gas prices of $6.50 in 2013 dollars ($5.20 gas in 2004 dollars) and medium hydro conditions. See the Key Assumptions discussion in Chapter 2. Production costs associated with Recommendations 1 and 2 are sensitive to natural gas prices, and, to a lesser extent, hydro conditions. Simulations were performed using a reasonable range of potential natural gas prices and hydro conditions. Other sensitivity analyses were performed as well. Results from all the sensitivity analyses can be seen in Appendix B.7. Under low natural gas prices, annual production costs are lower in all cases. Even in the low gas sensitivity, the fuel costs for coal-fired and wind resources are lower than the fuel costs for gas-fired resources. This causes already-constructed coal-fired and wind resources to continue to be dispatched before existing gas-fired resources. To further test this, a high gas price sensitivity of $8.50 was performed for the All Gas Reference Case. This sensitivity results in higher production costs ($3.5 billion increase over the $6.50 gas price case). This increase is essentially due to the higher gas price, not to a change in redispatch of resources. Under low hydro conditions, production costs increase in all four cases. On a comparative basis, the savings from Recommendations 1 and 2 increase during a low water year. Production costs are shown to be much less sensitive to hydro conditions than to gas prices. The comparative result of these sensitivities is summarized in Figure 3-5. Note that the production costs are lower under Recommendations 1 and 2 than the reference cases even with low gas prices. Figure 3- 4: Western Interconnection Production Costs (Variable Operating and Maintenance Cost in millions of dollars) ( ) $14,988 $18,458 Recommendation 2 $20,454 $15,923 $19,780 Recommendation 1 $21,862 $16,121 $20,046 IRP- Bas ed Reference Cas e $22,143 $16,783 $21,018 A ll-Gas Reference Case $23,118 $14,000 $16,000 $18,000 $20,000 $22,000 $24,000 $ Millions $6.50 gas- low hydro $6.50 gas- medium hydro Chapter 3 Rocky Mtn. Area Transmission Study $4.50 gas- medium hydro 3-10 Table 3- 6: Western Interconnection Production Cost Savings from Reference Cases ($ - Millions) All-Gas Case Recommendation 1 Base Case ($6.50 gas-median hydro) Low Natural Gas Price ($4.50 gas-median hydro) Low Hydro Condition ($6.50 gas-low hydro) Recommendation 2 Base Case ($6.50 gas-median hydro) Low Natural Gas Price ($4.50 gas-median hydro) Low Hydro Condition ($6.50 gas-low hydro) Reference Case IRP-Based Case (1,238) (266) (860) (197) (1,257) (281) (2,560) (1,588) (1,795) (1,132) (2,665) (1,689) The robustness of Recommendations 1 and 2 was tested by assuming a significant increase in demand-side management (DSM) activities. To reflect more aggressive DSM programs, the energy loads within the Rocky Mountain region are assumed to grow by 1.05% less per year than in the reference cases and that energy loads outside the Rocky Mountain region would grow by 0.51% less per year than in the reference cases. Peak load reductions are assumed to be 1.5 times the energy reduction. Within a couple of years of phase-in and including the five-year period between 2008 and 2013, peak loads in the Rocky Mountain region in 2013 are assumed to be reduced by 12% and energy by 8% while in the coastal states the reduction would be half that due to their already existing, more aggressive DSM programs. See Appendix G for discussion of these assumptions. Using these DSM assumptions, load growth in the Rocky Mountain region between 2008 and 2013 would be only 100 MW, thus negating the need for significant transmission additions to serve load in the region. In this case, both Recommendations 1 and 2 can be viewed as export projects. To reflect potential carbon dioxide constraints, a sensitivity analysis was conducted assuming $5/ton and $15/ton adders applied to CO2 emissions from new resource additions. This level of adder does not impact the dispatch of plants that the model assumes are built, and this sensitivity showed that the dispatch of these new resources was unaffected by these levels of adders.2 2 The impact of a CO2 adder on the decision of which existing plants to dispatch is much less than the impact of the adder on the choice of generation plant to build. Just as the economics of choosing between driving a car and riding a bus become dramatically different if you already own a car: All the fixed costs of owning the car are no longer relevant and you you would compare the incremental cost of running the car to the cost of a bus ticket. Thus, the greatest opportunity to reduce carbon emissions occurs in the choice of which resources to build. The ABB Market Simulator focuses on the use of the transmission system and has limited abilities to analyze generation resource choices. The models that utilities use in IRP efforts are better at evaluating resource addition options, but these models typically have very limited capabilities to model the transmission system. A back-of-the-envelope analysis using various assumptions (e.g., $6/MMBTU gas, 35% capacity availability for wind, 85% availability for Chapter 3 Rocky Mtn. Area Transmission Study 3-11 F. Capital Requirements The west-wide reductions in annual production costs from Recommendations 1 and 2 appear large. This conclusion is valid across a reasonable range of natural gas prices and hydro conditions, but this potential benefit is only part of the story. Alternatives 1 and 2 contemplate substantially higher levels of capital investment to build the needed transmission and to build coal and wind generation resources that have higher up-front costs than gas-fired generation. The economic comparisons are completed by combining fuel and other variable O&M costs with annualized capital and fixed O&M costs. The total costs of Recommendations 1 and 2 are then compared to the total costs of the reference cases for a more complete economic picture. Table 3-7 compares the total costs of Recommendation 1 and 2 and the two reference cases. Annualized costs associated with each scenario are shown in the column labeled “Representative Year.” This column represents a snapshot of real levelized annual capital costs for each case. Fuel and other variable O&M (production costs) are combined with annualized fixed costs to give a full cost picture of each scenario. The annual production costs from Figure 3-6 are shown in lines 1 through 3. Capital requirements for each case are shown in the column labeled “Initial Investment” and are grouped into generation resource investment and transmission investment. The generation resource investment numbers include wind, gas and coal capital investment as well as associated transmission integration investment (lines 5 to 11). In the case of Recommendation 2, generation investment outside the Rocky Mountain region is adjusted downward to the extent the Rocky Mountain region builds resources for export (line 12). Transmission costs include capital investment associated with transmission lines and any required customized equipment costs (lines 21 to 24). Capital requirements for the All-Gas and IRP-Based Reference Cases are $2.257 and $6.012 billion, respectively; and all of this investment is in generation with no transmission capital assumed.3 Generation capital for Recommendations 1 and 2 are $6.604 and $10.050 billion, respectively4. Transmission capital requirements assumed for Recommendations 1 and 2 are $970 million and $4.265 billion, respectively. coal and gas, and assumptions on capital costs and carrying charges) indicates that even with a $5/ton CO2 adder, coal is the lowest cost option. However, at $10/ton CO2 adder, wind becomes the lowest cost option. 3 Limited transmission investments to integrate local generation are included in the generation capital assumptions. 4 The capital requirements for Recommendation 2 include most of the capital requirements associated with Recommendation 1. Chapter 3 Rocky Mtn. Area Transmission Study 3-12 Wind Gas thermal Resource Costs: RM Resource Additions Capex Change from All Gas Case [Column A] Change from IRP- Based Case [Column B] Production Costs (Fuel & Other VOM) Chapter 3 Rocky Mtn. Area Transmission Study Annualized Costs 29 30 Total Initial Investment 33 Annual Net (Savings)/Cost from All Gas Case 34 Annual Net (Savings)/Cost from IRP- Based Case 31 32 Incremental Fixed O&M Incremental Capital Charge @ 10% RM Transmission Costs 26 27 28 25 Transmission Costs: 22 Incremental Line Capex 23 Customized Equipment Capex 24 RM Transmission Capex Sub Total 20 21 10 9 Coal thermal Incremental Transmission Integration Capex 11 RM Resource Capex Sub Total 12 Adj. Outside RM Resource Additions Capex 13 Other RM Costs Incremental Capital Charge @ 10% 14 Incremental Fixed O&M 15 Wind "wear and tear" 16 17 Subtotal Other RM Costs Adj. Other Costs Outside RM 18 19 Total Resource Costs 8 7 6 5 4 3 2 1 (2004 Dollars in Millions) 2,257 2,257 53 2,257 2,204 470 254 226 28 254 254 972 21,018 6,012 6,012 3,453 159 6,012 1,957 444 Initial Investment (470) - 756 756 601 116 39 756 (972) - 20,046 Representative Year Initial Investment Representative Year B IRP- Based Case IRP resources and no new transmission additions in Rocky Mountain States (Suppressed Wind) Reference Cases All Gas Case Gas resources and no new transmission additions in Rocky Mountain States A 7,574 970 777 193 970 6,604 3,985 175 6,604 2,246 198 (531) (61) 961 19 97 116 845 660 128 56 845 (1,238) (266) 19,780 Initial Investment Representative Year D 14,315 4,265 3,872 393 4,265 10,050 (2,257) 7,857 311 12,306 3,766 373 Initial Investment (986) (516) 1,828 85 427 512 1,231 245 94 1,570 (254) 1,316 (2,560) (1,588) 18,458 Representative Year Recommendation 2 Recommendations Recommendation 1 C Table 3- 7: Economic Comparisons “Initial investment” amounts are translated into annualized capital charges in the column labeled “Representative Year”. The annual capital charge reflects inflation adjusted (real) streams of depreciation, return on capital, property and income taxes, interest, replacements and administrative and general costs over the depreciable life of the asset. This charge is applied as a percentage of the initial investment, and is shown on lines 14 and 27. Fixed O&M costs are then added. The sum of the annualized capital charge and fixed O&M (line 30) is then compared to the annual production cost savings (lines 2-3) to determine annual net savings from the two reference cases (lines 33-34). See Appendix B.8 for a full explanation of the economic comparison table. 3-13 This analysis finds that Recommendation 1 would save $531 million annually on a west-wide basis compared to the All-Gas Reference Case and $61 million annually compared to the IRP-Based Reference Case.5 Recommendation 2 would save $986 million annually compared to the All-Gas Reference Case and $516 million compared to the IRP-Based Reference Case. See Table 3-8, which summarizes the data from lines 33-34 in Table 3-7. As noted in Chapter 2, capital investment amounts for new gas-fired resources do not include the investment that may be required for pipeline compression and expansion. If such investments were required, the savings for Recommendation 1 and 2 could be greater than shown. Table 3- 8: Annual Savings Compared to Reference Cases (Savings West-wide for a Representative Year, Millions of Dollars) Reference Case All-Gas Case IRP-Based Case Recommendation 1 (531) (61) Recommendation 2 (986) (516) An economic comparison of Recommendation 1 and 2 with the Reference Cases, using the low natural gas price sensitivity, produces the results shown in Table 3-8. A persistent, relatively low natural gas price assumption reduces the economic viability of Recommendations 1 and 2. Compared to the IRP-Based Reference Case, the benefits of Recommendation 1 do not appear to justify the required transmission investment. Compared to the All-Gas Case (which assumes heavy reliance on gas-fired plants) the benefits of both Recommendations 1 and 2 remain economic. Assuming high natural gas prices, the annual savings and net benefits of Recommendations 1 and 2 would be significantly higher than those shown in Table 3-8. Gas price hedging benefits provided by new transmission and low fuel cost resources should be considered, but are not reflected in this study. Strategies to hedge against uncertain – and potentially volatile – natural gas prices are important in providing greater stability in electricity prices. Table 3- 9: Annual Savings Compared to Reference CasesAssuming Low Natural Gas Prices (Savings West-wide for a Representative Year, Million of Dollars) All-Gas Case Reference Case IRP-Based Case Recommendation 1 (153) 7 Recommendation 2 (221) (61) 5 The savings from the IRP-Based Reference Case may be understated because the IRPs may not include the transmission investment needed to integrate the wind and coal resources they contemplate. Chapter 3 Rocky Mtn. Area Transmission Study 3-14 G. Distribution of Economic Gains and Losses To advance the development of transmission expansion projects that show economic benefits on an interconnection-wide basis, it is necessary to understand how the economic benefits and losses from the projects are distributed within the West. Table 3-10 shows the economic benefits (and losses) by region for Recommendations 1 and 2 in comparison with the two reference cases. The benefits (and losses) are categorized as load benefits and generation benefits. The numbers are derived from the production cost simulation and do not include capital and other fixed costs (See Chapter 2 for a discussion of locational marginal prices (LMPs) derived from the model.) In the simulation, the Load Benefit is defined as the reduction in cost to serve regional load, and is derived from the following: hourly demand (MWh) at each load node multiplied by the hourly LMP ($) and summed for the test year 2013. The simulation defines Generation Benefit as the gross generator margin, and is derived from the following: hourly generation (MWh) at each generation node multiplied by the hourly LMP ($) and summed for 2013 (i.e., generator revenue) less annual fuel and other production costs. The model-generated estimates of benefits and losses assume a real-time competitive market in which pricing is on an hourly, LMP basis. Although California is moving in this direction, such markets do not exist today in the West. For this reason, the actual distribution or sharing of the benefits (and losses) among consumers (i.e., load) and owners of generation in each region will vary from the distribution shown here. Benefits will flow to consumers when reductions in the cost of serving the load are passed through in retail rates. Benefits shown in the Generation Benefit column will mostly accrue to consumers in retail rates if the generation is owned by a vertically-integrated utility. On the other hand, Generator Benefits (and Losses) will accrue directly to independent power producers and merchant power plant owners to the degree the investment is not imbedded in regulated (or public utility) rate base pursuant to contracts between the generator and the load-serving entity. Depending on the terms of the power purchase contract, Generator Losses may not be in the rate base of LSEs and thus would not be borne by customers. In addition, as explained in Chapter 2, the system simulation includes none of the rate pancaking inefficiencies of the current system. Thus, the benefits and losses shown are in addition to benefits that would result from removing such inefficiencies. For example, northwestern generators would probably benefit on the whole from the removal of rate pancaking, but the losses shown in Table 3-9 do not take this benefit into account. Chapter 3 Rocky Mtn. Area Transmission Study 3-15 Table 3- 10: Economic Benefits and Losses (Millions of Dollars) Recommendation 1 Compared to IRP-Based Reference Case Region Load Benefit Generator Benefit Total Benefits Rocky Mountain Northwest Canada Mexico California Desert SW Total (5) 65 20 1 54 8 145 294 (78) (20) (1) (110) (9) 77 290 (13) 1 0 (56) 0 221 Recommendation 1 Compared to All-Gas Reference Case Region Load Benefit Generator Benefit Total Benefits Rocky Mountain Northwest Canada Mexico California Desert SW Total 123 128 37 (1) 91 0 377 983 (161) (35) 1 (76) 0 712 1,106 (32) 2 0 14 0 1,090 Recommendation 2 Compared to IRP-Based Reference Case Region Load Benefit Generator Benefit Total Benefits Rocky Mountain Northwest Canada Mexico California Desert SW Total 750 517 207 20 646 286 2,427 176 (550) (204) (23) (321) (395) (1,318) 926 (33) 3 (4) 326 (109) 1,109 Recommendation 2 Compared to All-Gas Reference Case Region Load Benefit Generator Benefit Total Benefits Rocky Mountain Northwest Canada Mexico California Desert SW Total 878 581 224 18 683 277 2,660 864 (633) (219) (22) (287) (386) (682) 1,742 (52) 4 (3) 396 (109) 1,978 Chapter 3 Rocky Mtn. Area Transmission Study 3-16 The distribution of gains and losses shows annual benefits to the Rocky Mountain region ranging from $290 million to over $1.106 billion, compared to the two reference cases. These benefits come with little net impact on western regions outside the Rocky Mountain States. This makes a compelling case for entities in the Rocky Mountain States to work together to build this transmission and capture the economic gain. Chapters 4 and 5 address some of the challenging issues that will need to be addressed in Phase II to accomplish this. The gains and losses comparisons for Recommendation 2 demonstrate that developing and exporting coal and wind generation from the Rocky Mountain region will benefit consumers in the Western Interconnection. Using the assumptions in this screening analysis, total west-wide consumer benefits range from $2.427 to $2.66 billion annually. In many parts of the West, load (i.e., consumer) benefits are roughly offset by generator losses. Such generator loses may or may not be passed on to consumers. The notable exception here is California. Even net of generation losses, California stands to gain between $326 and $396 million per year if Recommendation 2 is built. Benefits to the Rocky Mountain region also increase with Recommendation 2 by over $600 million per year, compared to Recommendation 1, and range from $926 million to $1.742 billion annually. The Rocky Mountain states should invite California to participate in future work pursuant to Recommendation 2. This and other Phase II efforts are discussed further in Chapters 4 and 5. H. Conclusions The economic screening study in RMATS Phase I finds that the transmission recommendations provide economic benefits over a reasonable range of future natural gas prices and hydro conditions. Significant benefits to the Rocky Mountain region appear attainable if the transmission projects in Recommendation 1 are constructed, enabling the region to increase its reliance on low fuel cost coal and wind resources rather than on new gas-fired generation. Recommendation 2 produces significant consumer benefits throughout the West, with strong beneficiaries in the Rocky Mountain region and in California. Future natural gas prices are the largest driver of the production costs. If a relatively low natural gas price future persists, Recommendation 1 does not appear to be economic. This conclusion ignores the benefits of hedging against uncertain future natural gas prices, which these transmission expansions would provide. Several conclusions can be drawn from the economic analysis of the Recommendations 1 and 2: • The Rocky Mountain region would benefit significantly if coal-fired and wind resource development is given priority over gas-fired resource development to meet its load growth. • Substantial increases in natural gas demand – driven in large part to gas-fired electric generators – has led to natural gas price escalation and volatility, making fuel diversification an increasingly important priority for LSEs throughout the West. • Given its abundant reserves of low-cost fuels, the Rocky Mountain region is well positioned to contribute to the West’s fuel diversification goals – if the West supports the necessary transmission expansion. • Diversification into new Rocky Mountain coal and wind generation reduces production costs throughout the West when compared to natural gas-fired generation. The Rocky Mountain states and West Coast markets (California markets in particular) stand to benefit. Chapter 3 Rocky Mtn. Area Transmission Study 3-17 EXHIBIT 5 NATIONAL ELECTRIC TRANSMISSION CONGESTION STUDY AUGUST 2006 U.S. Department of Energy NATIONAL ELECTRIC TRANSMISSION CONGESTION STUDY AUGUST 2006 U.S. Department of Energy Contents Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . vii Acronyms Used in This Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xi 1. Introduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.1. Organization of This Study . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.2. Definitions of Key Terms and Concepts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1.3. Consultation with States and Regional Entities. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 2 3 6 2. Study Approach and Methods . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.1. Review of Historical Transmission Studies. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.2. Simulations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.3. Scenario Analyses and Economic Assumptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.4. Estimating and Evaluating Congestion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.5. The Eastern Interconnection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2.6. The Western Interconnection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 9 9 10 13 14 17 3. Congestion and Constraints in the Eastern Interconnection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 3.1. Historical Transmission Constraints and Congestion Areas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 3.2. Results from Simulations of the Eastern Interconnection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 4. Congestion and Constraints in the Western Interconnection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31 4.1. Historical Transmission Constraints in the Western Interconnection . . . . . . . . . . . . . . . . . . . . . . 31 4.2. Congestion Findings From Modeling for the Western Interconnection . . . . . . . . . . . . . . . . . . . . 34 5. Critical Congestion Areas, Congestion Areas of Concern, and Conditional Congestion Areas . . . 5.1. Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.2. Congestion Areas in the Eastern Interconnection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.3. Congestion Areas in the Western Interconnection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5.4. Enabling New Resource Development: Conditional Constraint Areas. . . . . . . . . . . . . . . . . . . . . 5.5. Conclusion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 39 41 44 49 57 6. Request for Comments on Designation of National Corridors and on This Study . . . . . . . . . . . . . . 59 6.1. Request for Comments Concerning Designation of National Corridors. . . . . . . . . . . . . . . . . . . . 59 6.2. General Request for Comments on the Congestion Study . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62 7. Next Steps Regarding Congestion Areas and Considerations for Future Congestion Studies. . . . . 63 7.1. Next Steps Regarding Congestion Areas. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63 7.2. Considerations for Future Congestion Studies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64 U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 iii Contents (continued) Glossary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67 Appendixes A. Sections 368 and 1221(a) and (b) of the Energy Policy Act of 2005. . . . . . . . . . . . . . . . . . . . . . . . . . . B. Parties Responding to the Department of Energy’s February 2, 2006 Notice of Inquiry on “Considerations for Transmission Congestion Study and Designation of National Interest Electric Transmission Corridors” . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . C. Agenda for DOE’s March 29, 2006 Technical Conference on National Interest Electric Transmission Corridors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . D. On-Site Participants in DOE’s March 29, 2006 Technical Conference on National Interest Electric Transmission Corridors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . E. On-Line Participants in DOE’s March 29, 2006 Technical Conference on National Interest Electric Transmission Corridors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . F. Organizations Providing Formal Comments to DOE’s March 29, 2006 Technical Conference on National Interest Electric Transmission Corridors. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . G. Outreach Meetings Held Regarding the Congestion Study . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . H. General Documents or Data Reviewed for the Congestion Study . . . . . . . . . . . . . . . . . . . . . . . . . . . . I. Documents or Data Reviewed for the Eastern Interconnection Analysis . . . . . . . . . . . . . . . . . . . . . . . J. Documents or Data Reviewed for the Western Interconnection Analysis . . . . . . . . . . . . . . . . . . . . . . K. List of WECC Paths. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73 77 79 83 85 89 91 95 97 101 105 List of Tables 2-1. Crude Oil and Natural Gas Price Forecasts: Base Case, High Case, and Low Case . . . . . . . . . . . 10 2-2. Generation Assumptions for Western Interconnection Reference 2015 Cases . . . . . . . . . . . . . . . 12 List of Figures ES-1. Map of North American Electric Reliability Council (NERC) Interconnections. . . . . . . . . . . . . . ES-2. Critical Congestion Area and Congestion Area of Concern in the Eastern Interconnection . . . . . ES-3. One Critical Congestion Area and Three Congestion Areas of Concern in the Western Interconnection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ES-4. Conditional Constraint Areas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1-1. Map of North American Electric Reliability Council (NERC) Interconnections. . . . . . . . . . . . . . 2-1. Crude Oil Prices: History and Basis Forecast. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-2. Natural Gas Spot Prices at Henry Hub: History and Basis Forecast . . . . . . . . . . . . . . . . . . . . . . . 2-3. Nodes in Congestion Study Simulation of the Eastern Interconnection. . . . . . . . . . . . . . . . . . . . . 3-1. Constraints in the New England Region (ISO-New England) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-2. Constraints in the New York Region (New York ISO) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-3. Constraints in the PJM Region . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-4. Constraints in the Midwest ISO Region (MISO) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-5. Constraints in the Southwest Power Pool Region (SPP) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-6. Constraints in the SERC Reliability Corporation Region . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-7. Most Congested Paths in the Eastern Interconnection, 2008 Simulation . . . . . . . . . . . . . . . . . . . . 3-8. Time That Constraints Are Binding Relative to Level of Constrained Transmission Capacity. . . 3-9. Congestion Rent Versus Constrained Transmission Capacity . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3-10. Congestion Rent Versus Constrained Transmission Capacity . . . . . . . . . . . . . . . . . . . . . . . . . . . . iv U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 vii viii ix ix 2 10 10 18 22 22 23 23 24 24 27 28 28 28 List of Figures (continued) 4-1. Congestion on Western Transmission Paths. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-2. Actual Transmission Congestion, 1999-2005. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-3. Most Heavily Loaded Transmission Paths in 2004-2005 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-4. Projected Congestion on Western Transmission Paths, 2008. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-5. Projected Congestion on Western Transmission Paths, 2015. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4-6. Comparison of Historical and Modeled Congestion on Western Paths . . . . . . . . . . . . . . . . . . . . . 4-7. Existing and Projected Major Transmission Constraints in the Western Interconnection . . . . . . . 5-1. Critical Congestion Area and Congestion Area of Concern in the Eastern Interconnection . . . . . 5-2. One Critical Congestion Area and Three Congestion Areas of Concern in the Western Interconnection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-3. Southern California: Major Transmission into SP26 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-4. Congested Paths and Seasonal Power Flows in the Pacific Northwest . . . . . . . . . . . . . . . . . . . . . 5-5. Conditional Constraint Areas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-6. Potential Corridors on Federal Lands in the West . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-7. CDEAC 2015 High Coal Generation and Associated New Transmission Lines . . . . . . . . . . . . . . 5-8. CDEAC 2015 High Renewables Generation and Associated New Transmission Lines . . . . . . . . 5-9. Potential Wind Development and Associated Transmission Requirements in Northern Great Plains Area. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-10. Potential Wind Development and Associated Transmission Requirements in Central Great Plains Area . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-11. Locations of Proposed New Nuclear Generation Capacity in the Southeastern United States . . . U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 32 33 34 34 36 35 37 40 45 46 47 50 52 53 54 55 56 58 v 4. Congestion and Constraints in the Western Interconnection Chapter 4 has the same structure as Chapter 3—first it reviews the historical transmission constraints in the Western Interconnection, and then it presents the results of congestion simulation modeling. The logic and process of comparing the historical and modeled congestion results in the West was essentially parallel to that described in Chapter 3 for the Eastern Interconnection, so that process is not re-described here. 4.1. Historical Transmission Constraints in the Western Interconnection The transmission constraints described below were identified by reviewing recent transmission studies, expansion plans and reliability assessments conducted by subregional groups of western utilities, the Western Electricity Coordinating Council (WECC), the Seams Steering Group – Western Interconnection (SSG-WI), and the California Independent System Operator (CAISO). The studies covered in this review are listed in Appendix J. Figure 4-1 shows some of the Western Interconnection’s principal catalogued transmission paths and indicates those paths that were identified as congested in the historical studies.25 A transmission constraint (or constraints) inhibiting flows on a transmission path is represented by a red bar across the path. The bar also crosses or touches all lines comprising the path. The western analysis used significantly larger nodes (covering wider geographical spans with much larger generation and load weightings) than those used in the eastern modeling. The western path catalog includes 67 WECC paths, plus other monitored lines, as well as specific unscheduled flow paths, operating transfer capability group paths, and nomograms26 that reflect the effect of other lines (including smaller lines) upon the modeled paths. Some of these paths are internal to nodes, and so were not identified by the modeling described here, although they are well-known and studied in sub-regional analyses. In addition to reviewing existing studies by others, the western analysis team also examined data on actual transmission usage for the six-year period between 1999 and 2005. Below, Figure 4-2 shows the western transmission paths that were most heavily used. The usage metric shown is U75, the metric that reflects how many hours in a year the path was loaded at or above 75% of Operating Transfer Capability (OTC), the coordinated maximum flow limit set on actual path transfers reflecting system operating conditions at the time.27 Consistent with other congestion results, this shows that the most heavily loaded lines include the Bridger West line, the Southwest of Four Corners-to-Cholla-toPinnacle Peak lines (built to deliver power from baseload plants to loads), Western Colorado to Utah, the lines from Wyoming to Colorado, and the southern New Mexico path to El Paso. Figure 4-3 shows how heavily various paths within the West have been used over a recent 18-month period. Based on the U90 metric (which is the percentage of time a path is loaded at or above 90% of its limit), this figure shows that only five lines were at U90 or above for more than 10% of the hours in this time period. Of the most heavily loaded lines, note that the Bridger West line is dedicated to delivering electricity from the Bridger coal-fired power plants to loads in Utah and Oregon; this is one-way flow 25 Appendix K lists WECC’s 67 paths. A “nomogram” is a graphic representation that depicts operating relationships between generation, load, voltage, or system stability in a defined network. (See Glossary.) 27 WECC, Operating Transfer Capability Policy Committee Handbook, May 2006 (http://www.wecc.biz/documents/library/OTC/OTCPC_ HANDBOOK_05-19-06.pdf). 26 U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 31 Figure 4-1. Congestion on Western Transmission Paths Based on historical and existing modeling studies. Not all of WECC's 67 catalogued paths are shown. 32 U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 Figure 4-2. Actual Transmission Congestion, 1999-2005 Based on most heavily loaded season for each path during the 6-year period. U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 33 on a line designed specifically for delivery of the plants’ output to loads, so high loading for this line demonstrates desirable asset utilization, not undesirably high congestion. Many of the most heavily loaded lines in this period were other major tie-lines similarly designed to facilitate high-volume bulk power trades (Northwest to Canada northbound, Alberta west to British Columbia, the Pacific Direct Current Intertie, the California-Oregon AC Intertie, and the westbound line from Four Corners. 4.2. Congestion Findings From Modeling for the Western Interconnection Figure 4-4 shows how projected relative congestion patterns vary as a function of fuel prices. This graph orders the most heavily used transmission paths (as measured by U90, the number of hours when usage equals or exceeds 90% of the line’s limit), at the base case price for gas ($7/mmBtu). For each path, the graph also shows projected U90 hours for lowand high-case fuel prices as well. The shifts in usage between paths as fuel prices change reflects how electricity flows change with fuel prices—when gas prices are low, long-distance coal-by-wire imports are somewhat less competitive, but when gas prices rise, load-serving entities buy more coal, nuclear and hydropower (to the degree that they are available) and reduce purchases from gas-fired power plants. The shifts in relative congestion associated with fuel price changes would be even more pronounced in a low-hydro scenario. In its modeling, the western analysis sorted the congested paths by a number of methods to identify those that were most congested. Using an averaging method that combined both usage and economic impact, they found the following paths were the Figure 4-3. Most Heavily Loaded Transmission Paths in 2004-2005 Based on values for U90. Figure 4-4. Projected Congestion on Western Transmission Paths, 2008 U90 values at alternative natural gas prices. 34 U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 most likely to be the most heavily congested in 2008: • Arizona to Southern Nevada and Southern California • North and Eastern Arizona • In the Rocky Mountains, the Bridger West line from Wyoming to Utah • Montana to Washington and Oregon • Colorado to Utah • Colorado to New Mexico • Utah to Northern and Central Nevada • The Pacific Northwest south to California • Pacific Northwest flows northward to Canada • In Southern California, from the Imperial Irrigation District to Southern California Edison. deliver that production to load; without that transmission, the new generation would be trapped behind the constraints imposed by today’s transmission grid, and very likely the new generation itself would not be built.28 Beyond these specific transmission additions, however, the 2015 case deliberately does not add significant new transmission, so as to expose remaining transmission problems and identify where congestion will occur. As a result, the 2015 case finds that during many time periods, the full output of low-cost generators will not be deliverable to loads without further transmission expansion beyond that assumed in the scenario. It also shows transmission congestion as continuing in many of the same areas where it exists today. These findings match well with the results from other recent studies (compare to Figure 4-1). This case illustrates the importance of planning new generation and transmission jointly when seeking to develop new generation capacity distant from loads; without such joint planning and coordination between generation and transmission developers, needed new generation is not likely to be built when needed or in the most suitable locations. Figure 4-5 (next page) shows congestion on western transmission paths for the 2015 case. The resource assumptions in this case reflect utilities’ integrated resource plans and state renewable portfolio standards, as well as certain planned transmission lines that would support those developments. Thus the resource case for 2015 includes both new generation and the transmission that would be required to Figure 4-6 compares historical congestion patterns on western paths against modeled congestion for 2008 and 2015, using U75 (the percentage of time Figure 4-6. Comparison of Historical and Modeled Congestion on Western Paths 28 For details on the new transmission capacity assumed in the 2015 case, see WCATF’s report, posted on the WECC website, http://www. wecc.biz/index.php?module=pagesetter&func=viewpub&tid=5&pid=42. U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 35 Figure 4-5. Projected Congestion on Western Transmission Paths, 2015 Based on most heavily loaded season for each path during the 6-year period. 36 U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 Figure 4-7. Existing and Projected Major Transmission Constraints in the Western Interconnection Based on existing studies, usage data, and projections for 2008 and 2015. U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 37 when path loading is at or above 75% of the path’s reliability limit). For the paths that exist today (shown in Figure 4-6 with both blue and red bars, as distinguished from the lines that were created to connect new generation in 2015, with a blue bar only), there is a high correlation between current and projected transmission congestion. It is important to note, however, that more paths are heavily loaded in the 2015 case because the case assumes higher loads and higher generation outputs but did not increase transmission capacity correspondingly 38 across the interconnection. Thus, path usage levels increase broadly across the grid, not just on the new facilities built into the 2015 case specifically to serve associated new generating capacity. Figure 4-7 (previous page) displays the principal results of the western analysis in a single graphic. It shows the principal existing and projected constraints in the Western Interconnection, based on existing studies, usage data, and projections for 2008 and 2015. U.S. Department of Energy / National Electric Transmission Congestion Study / 2006 EXHIBIT 6 Western Interconnection 2006 Congestion Assessment Study Prepared by the Western Congestion Analysis Task Force May 08, 2006 1 2008 - Modeled Path Usage U75, U90 and U(Limit) - - $5, $7 and $9 HH Gas Price - Med Hydro, Average Losses Ordered by $7 U90 $5 Gas Page 1 of 2 Path Name Nav - Crystl Bonz - Mona ALB BC Cry - McC Pea - Mead HA RB PS TOT 2C PAC PG&E BR West IID - SCE MT NW INT GOND SW 4C COR SK KY EOR Ship San J PDCI INYO CONT Malin - RM IPP DC LINE COI LUGO - VIC ALTURAS TOT 2A W BROAD El Dor Lugo BONZ W CH PPK Hasy N Gila SDG&E to CFE PVINTR GOND Z2-WOR PATH C TOT 1A MARKETPLACE - ADELANTO U(Limit) Congestion Hours (Hrs) 7,428 7,198 7,650 7,180 7,006 7,460 6,653 3,633 2,620 3,761 4,821 1,194 1,383 1,395 2,945 3,585 2,645 2,164 841 92 509 1,190 702 609 707 80 U90 Hours (Hrs) 8,231 7,880 7,769 7,494 7,109 7,581 7,522 6,660 6,240 4,666 5,787 5,375 4,249 5,244 5,868 4,571 4,090 3,803 3,806 3,600 3,335 3,468 2,848 1,722 3,158 2,716 2,252 1,585 2,975 1,097 1,063 1,125 907 873 839 A dash in the table = 0 hours $7 gas U(Limit) U75 Hours Congestion (Hrs) Hours (Hrs) 8,760 6,997 8,513 7,045 7,938 7,493 7,916 7,366 7,338 7,072 7,728 6,912 7,678 6,704 6,605 7,884 3,763 6,905 3,725 7,718 3,624 6,255 4,348 7,541 1,860 7,030 1,234 8,192 949 6,804 3,018 4,612 3,592 4,717 5,258 2,389 5,486 2,365 4,945 6,104 3,822 3,330 1,925 7,710 7 6,048 479 7,982 6,917 6,547 588 1,895 794 5,157 5,091 1,515 652 4,234 709 4,154 82 U90 Hours (Hrs) 8,091 7,793 7,633 7,601 7,152 7,046 6,970 6,618 6,341 5,734 5,678 5,015 4,923 4,610 4,593 4,572 4,097 3,705 3,550 3,539 3,093 3,006 2,984 2,851 2,807 2,476 2,178 1,893 1,862 1,091 974 968 959 904 808 $9 Gas U(Limit) U75 Hours Congestion (Hrs) Hours (Hrs) 8,680 6,461 8,504 7,018 7,801 7,277 7,882 7,069 7,411 6936 7,216 6,546 7,159 6,684 6,418 7,905 3,967 7,390 4,861 7,688 4,029 6,073 4,315 7,555 2,308 7,009 1,130 8,058 356 6,652 2945 4,696 3,608 4,616 5,072 2203 5,285 2,519 4,773 5,509 4,009 4,144 2,530 7,486 86 5,794 317 7,904 6,830 5,195 177 1,641 1,005 4,778 4,725 1,587 639 4,296 700 3,964 44 U90 Hours U75 Hours (Hrs) (Hrs) 7,815 8,382 7,765 8,493 7,414 7,613 7,310 7,577 7054 7388 6,673 6,873 6,616 6,821 6,433 6,498 6,397 7,921 6,585 7,735 6,002 7,984 5,070 6,058 5,046 7,473 4,218 6,979 2,835 7,639 4510 6553 4,172 4,814 3,361 4,361 3275 4836 3,678 5,316 2,859 4,513 2,526 4,935 2,777 3,879 3,375 4,631 3,101 7,847 2,051 5,259 2,183 7,898 2,037 6,684 945 3838 1,270 1,842 815 4,848 587 4,093 972 1,566 877 4,251 664 3,516 17 $5 Gas page 2 of 2 Path Name IDAHO - SIERRA FOUR CORNERS 345_500 BILLINGS - YELLOWTAIL NORTH OF SAN ONOFRE MIDPOINT - SUMMER LAKE Moenkopi - El Dorado (EOR) TOT 4B WEST OF CROSSOVER N. Gila - Imperial Valley WOR) NORTHWEST - CANADA SOUTHERN NEW MEXICO (NM1) BORAH WEST PG&E - SPP PV to Devers (EOR) INTERMOUNTAIN - MONA 345 KV TOT 4A BROWNLEE EAST Mohave - Lugo (WOR) TOT 2B2 IDAHO - NORTHWEST TOT 3 WEST OF COLSTRIP SILVER PEAK - CONTROL 55 KV PERKINS - MEAD - MARKETPLACE 500 NORTHERN NEW MEXICO (NM2) TOT 7 ALBERTA - SASKATCHEWAN CENTENNIAL EAGLE MTN 230_161 KV - BLYTHE 16 ELDORADO - MCCULLOUGH 500 KV ELDORADO - MEAD 230 KV LINES IDAHO - MONTANA NORTH OF JOHN DAY SOUTH OF SAN ONOFRE SYLMAR - SCE TOT 2B1 TOT 5 WEST OF CASCADES - NORTH WEST OF CASCADES - SOUTH WEST OF HATWAI U(Limit) Congestion Hours (Hrs) 338 624 27 38 87 19 42 6 1 3 - U90 Hours (Hrs) 908 626 386 469 491 675 385 313 564 320 256 185 303 194 77 62 73 15 6 26 - $7 gas U75 Hours (Hrs) 2,046 2,710 1,558 2,255 1,863 7,855 1,517 7,498 4,110 689 1,670 3,655 4,365 2,419 426 258 467 4,106 359 520 318 6,600 4,081 1,495 71 9 - U(Limit) Congestion Hours (Hrs) 286 624 33 58 169 35 21 5 - U90 Hours (Hrs) 690 624 623 613 587 459 459 447 415 399 364 230 215 98 89 66 64 19 7 6 3 - $9 Gas U(Limit) U75 Hours Congestion (Hrs) Hours (Hrs) 1,679 342 3,175 624 1,868 2,973 40 2,181 7,674 1,817 40 7,483 2,915 775 221 2,184 44 3,813 4,160 26 2,034 510 258 8 416 3,833 752 596 219 6,600 4,249 1,108 85 6 - U90 Hours (Hrs) 802 624 468 499 573 216 429 289 165 461 608 246 187 31 111 97 63 4 5 7 - U75 Hours (Hrs) 1,804 3,224 1,633 3,089 2,128 7,248 1,530 7,477 1,872 906 3,046 3,760 4,294 1,567 518 285 408 3,187 1,030 586 200 6,600 4,326 537 99 2 - 18 2008 - Modeled Path Usage Metric Ranking U75, U90 and U(Limit) - - $5, $7 and $9 HH Gas Price - Med. Hydro, Average Losses Ordered by $7 U90 Page 1 of 2 Path Name Navajo - Crystal (EOR) Bonanza - Mona (Bonanza West) ALBERTA - BRITISH COLUMBIA Crystal - McCullough (EOR) Peacock - Mead (EOR) HA PS - Red Butte (TOT 2C) TOT 2C PACIFICORP_PG&E 115 KV INTERCON. BRIDGER WEST IID - SCE MONTANA - NORTHWEST INTERMOUNTAIN - GONDER 230 KV SOUTHWEST OF FOUR CORNERS CORONADO - SILVER KING - KYRENE EOR Shiprock - San Juan PACIFIC DC INTERTIE (PDCI) INYO - CONTROL 115 KV TIE Malin - RM 1 & 2 (COI) IPP DC LINE COI LUGO - VICTORVILLE 500 KV LINE ALTURAS PROJECT TOT 2A WEST OF BROADVIEW El Dor to Lugo (WOR) BONANZA WEST CHOLLA - PINNACLE PEAK Hassy - N. Gila (EOR) SDG&E to CFE PAVANT INTRMTN - GONDER 230 KV Z2-WOR PATH C TOT 1A MARKETPLACE - ADELANTO U(Limit) Congestion Hours Ranking 3 4 1 5 6 2 7 10 15 9 8 19 18 17 12 11 13 16 21 28 26 20 23 25 22 30 A dash in the table indicates the path was unranked since the Hours = 0 $5 Gas $7 gas U90 Hours Ranking 1 2 3 6 7 4 5 8 9 14 11 12 17 13 10 15 18 20 19 21 23 22 26 29 24 27 28 30 25 32 33 31 35 36 37 U75 Hours Ranking 1 2 5 6 15 9 12 20 7 18 10 24 13 16 3 19 33 32 28 27 31 25 40 42 11 26 4 17 23 47 29 30 52 35 36 U(Limit) Congestion Hours Ranking 5 4 1 2 3 6 7 9 10 11 8 18 19 20 13 12 14 15 17 34 26 25 21 23 22 29 U90 Hours Ranking 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 U(Limit) Congestion Hours U75 Hours Ranking Ranking 1 6 2 3 7 1 6 2 13 4 15 5 16 19 7 4 11 14 8 8 10 23 9 10 16 17 19 3 24 20 13 32 12 33 28 17 26 15 30 25 38 37 14 11 29 24 26 5 18 27 28 51 20 29 31 52 22 34 21 39 30 $9 Gas U90 Hours U75 Hours Ranking Ranking 1 2 2 1 3 9 4 10 5 13 6 16 7 17 9 21 10 4 8 7 11 3 12 22 13 12 15 15 24 8 14 20 16 29 19 32 20 28 17 24 23 31 26 26 25 37 18 30 22 6 28 25 27 5 29 18 32 38 30 47 34 27 39 36 31 51 33 35 36 40 19 $5 Gas Page 2 of 2 Path Name IDAHO - SIERRA FOUR CORNERS 345_500 BILLINGS - YELLOWTAIL NORTH OF SAN ONOFRE MIDPOINT - SUMMER LAKE TOT 4B Moenkopi - El Dorado (EOR) WEST OF CROSSOVER N. Gila - Imperial Valley WOR) NORTHWEST - CANADA SOUTHERN NEW MEXICO (NM1) BORAH WEST PG&E - SPP PV to Devers (EOR) INTERMOUNTAIN - MONA 345 KV TOT 4A BROWNLEE EAST Mohave - Lugo (WOR) TOT 2B2 IDAHO - NORTHWEST TOT 3 WEST OF COLSTRIP SILVER PEAK - CONTROL 55 KV PERKINS - MEAD - MARKETPLACE 500 NORTHERN NEW MEXICO (NM2) TOT 7 ALBERTA - SASKATCHEWAN CENTENNIAL EAGLE MTN 230_161 KV - BLYTHE 16 ELDORADO - MCCULLOUGH 500 KV ELDORADO - MEAD 230 KV LINES IDAHO - MONTANA NORTH OF JOHN DAY SOUTH OF SAN ONOFRE SYLMAR - SCE TOT 2B1 TOT 5 WEST OF CASCADES - NORTH WEST OF CASCADES - SOUTH WEST OF HATWAI U(Limit) Congestion Hours Ranking 27 24 33 32 29 34 31 35 37 36 - U90 Hours Ranking 34 39 43 42 41 44 38 46 40 45 48 50 47 49 51 53 52 55 56 54 - $7 gas U75 Hours Ranking 46 43 50 45 48 51 8 14 37 54 49 41 34 44 57 60 56 38 58 55 59 22 39 53 61 62 - U(Limit) Congestion Hours Ranking 27 24 32 30 28 31 33 35 - U90 Hours Ranking 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 58 58 58 58 - $9 Gas U75 Hours Ranking 50 42 48 43 46 49 9 12 44 54 45 41 36 47 58 60 59 40 56 57 61 21 35 53 62 63 - U(Limit) Congestion Hours Ranking 25 23 32 33 27 31 34 35 - U90 Hours Ranking 35 37 42 41 40 44 47 45 49 43 38 46 48 53 50 51 52 56 55 54 - U75 Hours Ranking 48 41 49 43 45 52 14 11 46 54 44 39 34 50 57 59 58 42 53 55 60 19 33 56 61 62 - 20 - Path Name TOT 1A PATH C Z2-WOR PVINTR GOND SDG&E to CFE Hasy N Gila CH PPK BONZ W El Dor Lugo W BROAD TOT 2A ALTURAS LUGO - VIC COI IPP DC LINE Malin - RM INYO CONT PDCI Ship San J EOR COR SK KY SW 4C INT GOND MT NW IID - SCE BR West PAC PG&E TOT 2C HA RB PS Pea - Mead Cry - McC ALB BC Bonz - Mona Nav - Crystl Hours 2008 Model Study U90, U75 and U(Limit) - $7 HH Gas, Medium Hydro, Ave. Losses Ordered by U90, $7 Gas 10,000 9,000 8,000 7,000 6,000 5,000 U90 U75 4,000 U(Lim) 3,000 2,000 1,000 21 - Path Name TOT 1A PATH C Z2-WOR PVINTR GOND SDG&E to CFE Hasy N Gila CH PPK BONZ W El Dor Lugo W BROAD TOT 2A ALTURAS LUGO - VIC COI IPP DC LINE Malin - RM INYO CONT PDCI Ship San J EOR COR SK KY SW 4C INT GOND MT NW IID - SCE BR West PAC PG&E TOT 2C HA RB PS Pea - Mead Cry - McC ALB BC Bonz - Mona Nav - Crystl Hours 2008 Modeling Study U90 at $5, $7 and $9 HH Gas, Medium Hydro, Average Losses Ordered by U90 $7 Gas 10,000 9,000 8,000 7,000 6,000 5,000 $7 Gas $5 Gas 4,000 $9 Gas 3,000 2,000 1,000 22 - Path Name TOT 1A PATH C Z2-WOR PVINTR GOND SDG&E to CFE Hasy N Gila CH PPK BONZ W El Dor Lugo W BROAD TOT 2A ALTURAS LUGO - VIC COI IPP DC LINE Malin - RM INYO CONT PDCI Ship San J EOR COR SK KY SW 4C INT GOND MT NW IID - SCE BR West PAC PG&E TOT 2C HA RB PS Pea - Mead Cry - McC ALB BC Bonz - Mona Nav - Crystl Hours 10,000 2008 Modeling Study U(Limit) - $5, $7 and $9 Gas, Medium Hydro, Ave. Losses Ordered by U90 $7 Gas 9,000 8,000 7,000 6,000 5,000 $7 Gas $5 Gas 4,000 $9 Gas 3,000 2,000 1,000 23 - Path Name TOT 1A PATH C Z2-WOR PVINTR GOND SDG&E to CFE Hasy N Gila CH PPK BONZ W El Dor Lugo W BROAD TOT 2A ALTURAS LUGO - VIC COI IPP DC LINE Malin - RM INYO CONT PDCI Ship San J EOR COR SK KY SW 4C INT GOND MT NW IID - SCE BR West PAC PG&E TOT 2C HA RB PS Pea - Mead Cry - McC ALB BC Bonz - Mona Nav - Crystl Hours 2008 Modeling Study U75 - $5, $7 and $9 Gas, Medium Hydro, Ave. Losses Ordered by U90, $7 Gas 10,000 9,000 8,000 7,000 6,000 5,000 $7 Gas $5 Gas 4,000 $9 Gas 3,000 2,000 1,000 24 TOT 2A PG&E - SPP SILPK - CON TOT 1A INYO CONT PDCI Z2-WOR COI PVINTR GOND Malin - RM Hasy N Gila IPP DC LINE LUGO - VIC El Dor Lugo INT GOND W OF COLS Ship San J PAC PG&E CH PPK COR SK KY TOT 2C HA RB PS IID - SCE Pea - Mead W OF CROSS W BROAD SW 4C Moen - El D MT NW ALB BC Cry - McC BONZ W BR West EOR Bonz - Mona Nav - Crystl Hours 2008 Model Study U75 - $5, $7 and $9 Gas - - Medium Hydro, Ave Losses Ordered by U75, $7 Gas 10,000 9,000 8,000 7,000 6,000 5,000 $7 Gas $5 Gas 4,000 $9 Gas 3,000 2,000 1,000 Path Name 25 2008 Path Shadow Prices Results 26 2008 - Modeled Path Shadow Prices Congestion Rent, Average Shadow Price and Binding Hours Average Shadow Price for $5, $7 and $9 HH gas - Med. Hydro, Ave Losses - - Ordered by $7 Gas Binding Average Shadow Price - - A dash in the table = 0 value $5 Gas Path Name Shiprock - San Juan Bonanze - Mona (Bonanza West) 4C Trans BRIDGER WEST Cor - Sking - Kyrene TOT 1A Navajo - Crystal (EOR) SW of 4C Malin - RM 1 & 2 (COI) PATH C TOT 4B Mont - NW W of Broad AL - BC TOT 2A Inter- Gonder IPP DC LINE PDCI TOT 4A Lugo - Victorville (WOR) NW - Canada Peacock - Mead (EOR) HA PS - Red Butte (TOT 2C) S NM Crystal - McCullough (EOR) SDG&E to CFE IDAHO - SIERRA PAC- PG&E 115 MKT - Adelanto El Dor to Lugo (WOR) EOR IID - SCE Hassy - N. Gila (EOR) N of San Ono PG&E - SPP ID - NW TOT 3 ALBERTA - SASKATCHEWAN ALTURAS PROJECT BILLINGS - YELLOWTAIL BONANZA WEST Congestion Rent (k$/yr) 76,189.97 107,145.85 9,064.17 96,626.08 13,949.27 5,530.90 140,908.70 22,402.87 35,022.26 3,324.91 155.17 53,230.99 1,095.70 34,070.17 2,065.56 4,083.24 14,878.02 29,356.02 11.18 12,364.42 419.66 8,397.42 3,332.36 26.99 24,786.21 1,109.89 252.04 760.87 110.59 1,325.02 15,432.41 1,297.60 2,232.26 23.46 2.52 3.73 2.03 - Binding Average Average Shadow Shadow Price ($/MW) Price ($/MW) 12.7 38.0 19.8 24.1 1.2 17.3 5.0 12.1 1.4 9.2 1.0 12.0 11.4 13.4 1.1 8.1 2.7 8.9 0.5 6.9 0.0 6.0 2.8 6.4 0.0 4.6 5.5 6.4 0.3 3.6 2.1 3.8 0.9 3.6 1.1 2.7 0.0 2.3 0.6 2.1 0.0 2.4 2.0 2.5 1.3 1.6 0.0 1.4 1.6 2.0 0.2 2.1 0.1 1.5 1.1 1.4 0.0 1.2 0.1 0.9 0.2 1.5 0.2 0.8 0.1 1.0 0.0 0.4 0.0 0.4 0.0 3.1 0.0 0.5 - $7 Gas Congestion Rent (k$/yr) 129,963.36 131,555.28 10,898.85 134,152.81 21,445.63 7,019.06 116,844.42 43,389.05 31,846.99 4,518.17 323.17 63,815.86 123.56 35,227.22 7,848.89 4,676.19 18,623.10 30,951.55 10.13 12,160.90 722.96 7,255.19 4,002.12 72.86 20,737.79 482.24 192.87 701.47 126.78 1,325.43 6,095.96 1,809.29 637.24 29.54 0.84 - Binding Average Average Shadow Shadow Price Price ($/MW) ($/MW) 21.7 63.2 24.3 30.2 1.5 20.8 6.9 16.2 2.2 15.8 1.2 15.2 9.4 11.8 2.1 10.0 2.4 9.0 0.6 8.8 0.1 8.2 3.3 8.0 0.0 6.9 5.7 6.7 1.3 5.9 2.4 4.9 1.1 4.1 1.2 2.9 0.0 2.5 0.6 2.3 0.0 2.1 1.7 2.1 1.6 2.0 0.0 2.0 1.4 1.6 0.1 1.4 0.0 1.3 1.0 1.3 0.0 1.3 0.1 1.0 0.1 0.9 0.3 0.8 0.6 0.0 0.4 0.0 0.2 - $9 Gas Congestion Rent (k$/yr) 175,350.41 159,709.73 11,105.78 156,967.43 31,425.74 8,444.83 89,182.88 70,111.43 29,295.25 5,074.11 233.55 89,353.26 2,030.99 36,591.23 17,524.90 5,369.55 21,670.00 33,589.62 28.32 10,465.25 1,239.27 5,782.45 4,554.29 122.17 15,974.52 2,411.61 215.12 664.51 56.71 672.14 1,123.50 2,812.40 141.51 56.24 1.03 - Average Binding Shadow Average Price Shadow Price ($/MW) ($/MW) 29.3 87.4 29.4 36.9 1.5 21.2 8.1 18.0 3.3 25.3 1.5 18.6 7.2 9.8 3.4 13.1 2.3 9.0 0.7 10.0 0.0 8.6 4.6 10.1 0.1 9.2 6.0 7.2 2.9 10.0 2.8 5.7 1.3 4.5 1.3 3.1 0.0 4.4 0.5 2.4 0.1 2.8 1.4 1.7 1.8 2.4 0.0 2.6 1.1 1.3 0.5 3.9 0.0 1.3 0.9 1.3 0.0 1.1 0.0 0.8 0.0 0.4 0.5 1.0 0.4 0.0 0.6 0.0 0.2 - 27 2008 - Modeled Shadow Price Metric Ranking Congestion Rent, Average Shadow Price and Binding Hours Average Shadow Price for $5, $7 and $9 HH gas - Med Hyrdo, Ave Losses - - Ordered by $7 Gas Binding Average Shadow Price $5 Gas Path Name Shiprock - San Juan Bonanza - Mona (Bonanza West) 4C Trans BRIDGER WEST Cor - SKing - Kyrene TOT 1A Navajo - Crystal (EOR) SW of 4C Malin - RM 1 & 2 (COI) PATH C TOT 4B Mont - NW W of Broad AL - BC TOT 2A Inter- Gonder IPP DC LINE PDCI TOT 4A Lugo - Victorville (WOR) NW - Canada Peacock - Mead (EOR) HA PS - Red Butte (TOT 2C) S NM Crystal - McCullough (EOR) SDG&E to CFE IDAHO - SIERRA PAC- PG&E 115 MKT - Adelanto El Dor to Lugo (WOR) EOR IID - SCE Hassy - N. Gila (EOR) N of San Ono PG&E - SPP ID - NW TOT 3 ALBERTA - SASKATCHEWAN ALTURAS PROJECT BILLINGS - YELLOWTAIL BONANZA WEST BORAH WEST Average Congestion Rent Shadow Price Ranking Ranking 4 2 2 1 15 13 3 5 13 11 17 17 1 3 10 15 6 7 20 20 30 29 5 6 26 28 7 4 22 21 18 8 12 18 8 14 34 33 14 19 28 30 16 9 19 12 32 32 9 10 25 24 29 26 27 16 31 31 23 27 11 23 24 22 21 25 33 33 36 33 35 33 37 33 $7 Gas $9 Gas Binding Binding Binding Average Average Average Average Average Shadow Price Congestion Shadow Price Shadow Price Congestion Rent Shadow Price Shadow Price Ranking Rent Ranking Ranking Ranking Ranking Ranking Ranking 1 3 2 1 1 2 1 2 2 1 2 2 1 2 3 14 13 3 14 13 4 5 1 4 4 3 3 6 7 10 9 5 9 8 3 6 17 16 6 16 14 5 4 4 3 7 5 4 11 9 6 10 8 6 7 7 8 8 8 9 10 11 13 10 20 20 10 19 20 10 13 28 26 11 28 26 14 11 5 6 12 4 6 8 14 31 31 13 23 24 12 12 7 5 14 7 5 15 17 15 15 15 12 9 9 15 19 7 16 18 10 16 16 12 18 17 11 16 17 19 9 17 18 8 17 20 22 34 31 19 34 26 18 24 13 21 20 15 22 24 21 24 28 21 24 25 21 20 16 11 22 17 15 25 26 21 12 23 20 12 23 30 32 30 24 31 26 22 25 11 14 25 13 18 26 23 27 23 26 22 23 19 27 29 27 27 29 26 28 29 25 19 28 27 19 27 31 30 29 29 32 26 29 33 23 25 30 26 26 31 28 18 24 31 25 26 33 34 22 22 32 21 21 30 32 26 31 33 30 26 34 37 33 31 34 33 26 32 36 35 31 35 35 26 35 18 36 31 36 36 26 36 35 36 31 36 36 26 36 28 NW - Canada Lugo Vict IID - SCE EOR El Dor to Lugo MKT - Adelanto PAC- PG&E ID Sierra SDG&E to CFE Cryst McC S NM HA RB PS Peacock Mead Path Name TOT 4A PDCI IPP DC LINE Inter- Gonder TOT 2A AL - BC W of Broad Mont - NW TOT 4B PATH C Malin RM SW of 4C Nav Cryst TOT 1A Cor SK Ky BRIDGER W 4C Trans Bonz Mona Ship San Juan Shadow Price - $/MW 2008 Model Study Binding Average Hours Shadow Price and Average Shadow Price $7 gas, Medium Hydro, Average Losses 40.0 35.0 $63 30.0 25.0 20.0 B SP Ave SP 15.0 10.0 5.0 29 Path Name IID - SCE EOR El Dor to Lugo MKT - Adelanto PAC- PG&E ID Sierra SDG&E to CFE Cryst McC S NM HA RB PS Peacock Mead NW - Canada Lugo Vict TOT 4A PDCI IPP DC LINE Inter- Gonder TOT 2A AL - BC W of Broad Mont - NW TOT 4B PATH C Malin RM SW of 4C Nav Cryst TOT 1A Cor SK Ky 30.0 BRIDGER W 4C Trans Bonz Mona Ship San Juan Shadow Price - $ / MW 2008 Modeling Study Binding Hours Shadow Price - $5, $7 and $9 Gas Medium Hydro and Average Losses 40.0 $88 35.0 $63 25.0 20.0 $7 Gas $5 Gas 15.0 $9 Gas 10.0 5.0 - 30 EXHIBIT 7 Western Governors’ Association Clean and Diversified Energy Initiative Transmission Task Force Members Chair – Jim Wilcox, Xcel Energy Grace Anderson, California Energy Commission Frank Barbera, Imperial Irrigation District Jim Caldwell, PPM Steve Dayney, Xcel Energy Mike DeWolf, PacifiCorp Allan Edwards, Basin Electric Steve Ellenbecker, Wyoming Governor’s Office Robert Gough, Intertribal Council on Utility Policy Roger Hamilton, Wind on the Wires (West) Bill Hose, TransCanada Robert Kondziolka, Salt River Project Hal LaFlash, Pacific Gas & Electric Marv Landauer, Bonneville Power Administration Ron Lehr, American Wind Energy Association Iain Kinnis and Stephen Burnage, National Grid Craig O’Hare, New Mexico Department of Energy Lee Otteni and Ray Brady, Bureau of Land Management Bill Pascoe, Great Northern Dean Perry, SSG-WI Holly Propst, Western Business Roundtable Chris Reese, Puget Sound Energy Robert Smith, Peter Krzykos, and Yvonne Hunter, Arizona Public Service Jerry Vaninetti, Trans-Elect John Woody and Judi Greenwald, Pew Center for Global Climate Change Support Staff: Doug Larson, Western Interstate Energy Board Thomas Carr, Western Interstate Energy Board Bill Moye, Star Consulting Group, LLC May 30, 2006 This document is intended as background information for the Clean and Diversified Energy Advisory Committee. It does not represent the adopted policies and views of the Western Governors’ Association. CDEAC Transmission Task Force Report (05-30-06) Table of Contents Executive Summary 1 I. Transmission Opportunities to Support CDEAC Generation A. Transmission in the Eastern Interconnection and ERCOT B. Transmission in the Western Interconnection C. Long-Term Outlook 1. Transmission Adequacy Beyond 2015 2. Non-Wires Alternatives 3. Technological Innovation for Transmission 5 6 7 10 10 10 11 II. Encouraging Efficient Use and Expansion of the Western Transmission Infrastructure: Policy Recommendations A. Background B. Challenges and Policy Options 1. Efficient Use of the Existing Transmission System Background a. FERC’s Open Access Transmission Policies b. Emerging Issues Under Order 888 i. Historical Flows ii. Conditional Firm, Priority Non-firm and Other Transmission Service iii. Evaluation of ATC iv. Rate Pancaking v. Control Area Consolidation vi. Economic Dispatch of Transmission vii. Common Oasis Recommendations 1-6 2. Transmission Expansion a. Transmission Planning Background i. Western Transmission Planning Efforts ii. FERC Generation Interconnection Policies (1) Order 2003 and the Interconnection Queue (2) Small Generator Interconnection (3) Codes of Conduct iii. Interaction of Transmission Planning and ii 15 15 20 20 20 20 21 21 23 23 24 24 25 27 27 30 30 30 30 32 32 34 34 May 30, 2006 This document is intended as background information for the Clean and Diversified Energy Advisory Committee. It does not represent the adopted policies and views of the Western Governors’ Association. Generation Interconnection Rules (1) Open Season (2) EPACT Congestion Study Recommendations 7-10 35 36 36 37 b. Cost Allocation and Cost Recovery Background i. FERC Policy ii. State Cost Allocation Policies iii. Transmission for Location-Constrained, Modular Development Generation iv. Infrastructure Authorities v. Western Area Power Administration vi. EPAct Incentives Recommendations 11-17 39 39 39 40 c. Transmission Siting and Permitting Background Recommendations 18-19 49 49 51 Appendices A. Results of Transmission Analysis in the Western Interconnection B. Results of Transmission Analysis in the Eastern Interconnection and ERCOT iii 41 43 44 44 45 53 67 May 30, 2006 This document is intended as background information for the Clean and Diversified Energy Advisory Committee. It does not represent the adopted policies and views of the Western Governors’ Association. identify current beneficiaries of transmission investments. Over time, the level and distribution of benefits from transmission becomes even more diffuse since incremental transmission investments improve overall reliability to the system, and interactions of additions of new generation and other transmission projects alter the flow of electricity over the grid in complex and unanticipated ways. Transmission for Location-Constrained, Modular Development Generation. Policy rules governing transmission expansion has developed over time in parallel with conventional generating fossil resources and hydro power. The prevailing transmission expansion rules are problematic for a class of emerging generation technologies with the following characteristics: 1) generation that is location-constrained given the nature of the resource; and 2) development that occurs in a disaggregated and modular fashion by multiple entities. Location-constrained-type resources such as wind, geothermal and centralized solar plants must be sited close to where the resource can be harnessed. Wind generators need to be placed where the wind blows and geothermal generators must be located at specific geological sites. The best sites for centralized solar power are located in the desert. In contrast, natural gas generation can be located very close to loads. Coal plants have geographic flexibility given the ability to transport coal by railroads. The second factor concerns the disaggregated and modular development of generation resources. Certain emerging resources like wind, geothermal and biomass are best suited for development in geographic concentrated areas. Development for these resources generally occurs not by a single centralized entity, but by many different small development projects in a disaggregated fashion. Over time, development can expand in a modular and sequential fashion with the addition of new projects in the region. The key challenge for generation development in these areas is to build new transmission capacity in a synchronized manner. Under current transmission policy, however, the burden of building new transmission falls on the first projects making generation interconnection requests. The initial project developers are not able to provide the financing and assume the risk to build transmission for the region. This approach does not encourage or facilitate a coordinated, planned, modular development of the resource. As a result, current policy for new transmission does not address a fundamental chicken and egg timing problem between potential generation projects and corresponding potential transmission projects. New approaches are needed to provide transmission for location-constrained, modular development resource areas. Several recent initiatives in Texas, Minnesota and California provide potential models to address this problem. Texas and Minnesota recently enacted legislation to provide legal and regulatory incentives to build transmission in support of and prior to building of renewable 41 May 30, 2006 This document is intended as background information for the Clean and Diversified Energy Advisory Committee. It does not represent the adopted policies and views of the Western Governors’ Association. generation. In Texas, SB 2075 authorized the public utility commission to require electric utilities to construct or enlarge transmission facilities to meet Texas RPS goals. The Texas public utility commission must designate renewable energy zones and develop a plan to construct transmission to those zones. SB 20 requires the public utility commission to issue a final order within 181 days of the filing of an application for certificate of public convenience and necessity to build transmission to meet RPS goals. Applications are automatically approved if the commission fails to act after 181 days. Additionally, SB 20 provides cost recovery incentives. Transmission projects supporting RPS goals shall be deemed used and useful, and prudent and includable in the rate base, regardless of the utility’s actual use of the facilities. In Minnesota, SF 136876 contains transmission provisions to support renewable energy development and to meet the Minnesota RPS goal. SF 1368 requires utilities to identify future transmission inadequacies in the transmission system, identify alternative means to address such inadequacies and submit transmission reports to the public utility commission. Utilities must determine necessary transmission upgrades to support development of renewable energy to meet the RPS conditions. Transmission projects determined to be necessary to support a utility’s plan to meet RPS requirements would be deemed a priority electric transmission project and serve to satisfy a certificate of need. SF 1368 grants public utility commission authority to approve transmission cost adjustments for new transmission facilities deemed a priority transmission project. Such transmission tariffs would allow utilities to recover costs on a timely basis, allow a return on investment at a level most recently approved or another rate consistent with the public interest, and for a current return on construction work in progress. In California, Southern California Edison (SCE) proposed the “renewable trunk line” concept for its Tehachapi/Antelope transmission project. This proposal envisioned transmission expansion in advance of generator requests based on predictable growth of many independent wind generation projects in a designated concentrated area. The proposal avoids the pitfall of inefficient piecemeal studies required under current interconnection rules. Specific elements of the SCE proposal are summarized below: • • Rolled-in rate treatment for high-voltage (220kV or higher) trunk-line transmission project costs necessary to integrate large concentrations of renewable generation resources located a reasonable distance from the existing grid. To be eligible for this treatment, large concentrations of renewable resources should be located in a limited geographic area. Permit rolled-in rate treatment and cost recovery for prudent costs for transmission facilities described above regardless of whether the full increment of forecast generation that would justify the upgrades commences commercial operations. 75 Texas Legislature SB 20, Legislative Session 79(1), signed by Governor Rick Perry on August 2, 2005, and effective on Sept. 1, 2005. Section 3 of SB 20 raised the Texas RPS goal to 5,880 MW of cumulative installed renewable capacity by 2015, and a target of 10,000 MW by 2025 (http://www.capitol.state.tx.us/ ). 76 Minnesota State Legislature, SF 1368, Legislative Session 84, signed by Governor Tim Pawlently on May 25, 2005 (http://www.leg.state.mn.us/leg/legis.asp). 42 May 30, 2006 This document is intended as background information for the Clean and Diversified Energy Advisory Committee. It does not represent the adopted policies and views of the Western Governors’ Association. • Grant 100% cost recovery for prudent costs even if the transmission project is cancelled or abandoned either because there is insufficient generation development in the region or necessary regulatory approvals for project construction are not granted. Under current policy, FERC limits recovery from ratepayers to only 50% of the utility’s prudently-incurred investment in abandoned or cancelled FERC-jurisdictional plant (facilities not completed and placed into operation).77 On July 1, 2005, FERC issued a split decision that rejected the renewable trunk-line features of the SCE proposal but accepted cost recovery features of 2 of the 3 proposed transmission system upgrades. The majority rejected the trunk-line feature on grounds that it was contrary to FERC policy on generation interconnection policies and that SCE did not establish system-wide benefits to all consumers of the transmission system. Infrastructure Authorities. The Wyoming Infrastructure Authority (WIA) was created June 10th, 2004, by the state legislature, tasked with diversifying and growing the state's economy through the development of Wyoming's electric transmission infrastructure. The WIA is also responsible for planning, financing, building, maintaining, and operating electric transmission and related facilities. Specific responsibilities of the WIA include the following: • • • • • Issuing up to $1 billion in bonds to finance new transmission lines to support new generation facilities in the state; Owning and operating lines in instances where private investment is not offered; Entering into partnerships with public or private entities to build and upgrade transmission lines; Investigating, planning, prioritizing, and establishing corridors for electric transmission; and Establishing and charging fees and rates for use of its facilities in consultation with the public service commission and other related government entities. The WIA is a new institution that will become involved in transmission planning and expansion. This creates opportunities to collaborate on transmission investments, to pursue partnerships with public and private entities, to begin to address siting and rightsof-way issues, and to explore creative financing and contracting.78 Following the Wind Task Force, p. 65-66. 78 Rocky Mountain Area Transmission Study (RMATS), September 2004, p. 4-11. There is no statutory limit on this bonding authority for projects the WIA might own. The WIA also has the capability, within an outstanding bond cap of $1 billion, to issue bonds to build transmission facilities owned by other entities. All WIA-issued bonds would be exempt from state taxation. Tax-exempt bond financing may reduce the cost of transmission projects compared to private-sector equity and debt financing. The WIA is constitutionally barred from issuing revenue bonds backed by the faith and credit of the State of Wyoming. This means for any WIA bond issuance to be successfully received by the financial community, the bonds will likely need to be secured by an expected revenue stream from the transmission investment. This security could take the form of subscription-type contracts with entities expected to use the transmission, a lease agreement with one or more utilities agreeing to take transmission capacity, or other means. 43 EXHIBIT 8 National Transmission Grid Study The Honorable Spencer Abraham Secretary of Energy U.S. Department of Energy May 2002 2 Major Western Transmission Bottlenecks Electricity trading patterns and transmission over long distances. Several large power plants congestion are somewhat different in the West in the West were intentionally built in remote than in the East for several reasons. First, the locations; along with these plants, owners con- transmission system in the West, unlike the one structed high-voltage transmission lines to ship in the East, was built primarily to carry power power to densely populated load centers.14 Size of Transmission Paths Fig. 2.2 Map of Congested Paths in the Western Interconnection 56 < 1 GW >=1 and <3 GW >=3 GW 51 53 52 48 Percentage of Hours Congested 55 50% and greater 40% to 49% 47 30% to 39% d 20% to 29% 54 10% to 19% 49 58 57 50 67 61 65 62 66 59 69 68 64 63 60 14 For example, the Palo Verde nuclear plant was built in southern Arizona in part to serve load in southern California. Similarly, the Intermountain Power Project, a 1,640-megawatt coal plant in Utah, was built to serve a number of municipalities in Utah and in California, including Los Angeles. A 490-mile transmission line connects the plant to southern California. 15 National Transmission Grid Study Transmission Constraints in Contiguous U.S. Pacific DC Intertie ISO-NE CA/OR Interface Southwest MI NWPA WY/ID Interface East NY MAPP NYISO PJM ECAR Central IA CA/MX MAIN East KS/MO Interface Central CA East Boston SW CT Interface Southeast PA Central MO RMPA West VA/PJM Interface SPP Southeast West VA Northeast AZ Southern CA SERC AZ/NM/SNV FRCC : Constraint and constrained flow direction FERC found that the costs of individual con- conditions in the eastern portion of New York straints for these months generally ranged during the summer of 2000, FERC estimated a from less than $5 million to more than $50 cost of more than $700 million. million. However, for one particular set of Source: FERC. 2001. Electric Transmission Constraint Study. Division of Market Development. Download from http://www.ferc.gov Finally, POEMS does not analyze relia- The POEMS analysis offers minimum bility benefits. Increased transmission estimates of the benefits of vibrant whole- capacity will generally improve the overall sale markets to the consumer. However, reliability of the grid and allows regions to the trend is clear: transmission bottle- share capacity reserves. Although the risk necks today compromise important nation- of blackouts is generally small, blackouts al interests in efficient regional wholesale usually entail very high economic costs. As electricity markets and reliable transmis- such, even a small reduction in the risk of sion systems. a blackout will have substantial benefits. The National Interest in Relieving Transmission Bottlenecks 18