Addendum 1 Specs - Patmac Contracting

advertisement
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
TOC - 1
TABLE OF CONTENTS
SPECIFICATIONS
Division 0 - Bidding and Contract Documents
*
*
*
*
*
*
*
*
*
*
00020
00101
00210
00310
00820
A101-2007
Advertisement Invitation For Bids ....................................................................Revised 3/16/11
Instruction to Bidders
Specific Date Construction Schedule ..............................................................Revised 3/16/11
Bid Proposal Form
Liquidated Damages
AIA Standard Form of Agreement
Between Owner and Contractor
--------AIA Closeout Documents
A201-2007 AIA General Conditions of the Contract for Construction (Modified)
--------Floor Phasing Plan of King Springs Elementary School .................................Revised 3/16/11
--------Report of Subsurface Exploration and
Geotechnical Engineering Evaluation ................................................... Issued 3/16/11
00901
Addendum No. 1 ................................................................................................ Issued 3/16/11
Division 1 - General Requirements
*
*
*
*
*
*
*
*
*
*
01010
01045
01101
01110
01200
01300
01310
01312
01400
01500
01630
01650
01700
Summary of Work ............................................................................................Revised 3/16/11
Cutting and Patching
Alternates .........................................................................................................Revised 3/16/11
Low-Emitting Materials
General Requirements
Submittals
Construction Schedules
Project Meetings
Testing Laboratory Services
Temporary Facilities
Substitutions
Project Record Documents
Contract Closeout
Division 2 - Sitework
*
*
*
*
*
*
*
*
*
*
*
*
*
02010
02220
02221
02222
02230
02240
02300
02360
02370
02510
02530
02630
02740
02750
02770
02900
General-Sitework
Site Demolition
Building Demolition
Selective Demolition
Clearing and Grubbing
Groundwater Control
Earthwork
Soil Treatment
Erosion Sedimentation and Pollution Control
Water Distribution
Sanitary Sewer System
Storm Drainage
Asphaltic Concrete Paving
Portland Cement Concrete Paving
Concrete Curbs, Gutters, and Walks
Landscaping
TOC - 2
TABLE OF CONTENTS
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Division 3 - Concrete
*
03300
03540
Cast-In-Place Concrete
Cementitious Underlayment
Division 4 - Masonry
04200
04210
04220
04720
Unit Masonry
Brick .................................................................................................................Revised 3/16/11
Concrete Unit Masonry
Architectural Cast Stone
Division 5 - Metals
*
*
*
05120
05210
05310
05400
05500
Structural Steel
Steel Joists
Steel Deck
Cold-Formed Metal Framing
Metal Fabrications
Division 6 - Wood and Plastics
06105
06400
Miscellaneous Carpentry
Architectural Woodwork ...................................................................................Revised 3/16/11
Division 7 - Thermal and Moisture Protection
07160
07210
07260
07415
07420
07527
07600
07710
07900
Bituminous Dampproofing
Building Insulation
Vapor Retarders
Metal Cladding Systems .................................................................................... Issued 3/16/11
Composite Panels .............................................................................................. Issued 3/16/11
SBS-Modified Bituminous Membrane Roofing
Flashing and Sheet Metal
Manufactured Roof Specialties
Joint Sealers
Division 8 - Doors and Windows
*
08100
08200
08336
08400
08710
08800
08900
Metal Doors and Frames
Wood Doors
Coiling Counter Shutters
Entrances and Storefronts
Door Hardware
Glazing
Exterior Wall Performance Requirements
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
TOC - 3
TABLE OF CONTENTS
Division 9 - Finishes
09100
09250
09300
09510
09622
09651
09653
09680
09900
Metal Support Systems
Gypsum Board
Tile
Acoustical Ceilings
Resilient Athletic Flooring
Resilient Wall Base and Accessories
Resilient Tile Flooring
Carpet
Painting
Division 10 - Specialties
10152
10155
10520
10531
10800
Hospital Cubical Curtains and Tracks ............................................................... Issued 3/16/11
Toilet Compartments
Fire Protection Specialties
Aluminum Canopy Structures ............................................................................ Issued 3/16/11
Toilet and Bath Accessories
Division 11 - Equipment
11132
Projection Screens
Division 12 - Furnishings
12491
Blinds
Division 13 - Special Construction
Division 14 - Conveying Systems
(Not Applicable)
(Not Applicable)
Division 15 - Mechanical
*
*
*
*
*
*
*
*
*
*
15010
15043
15400
15450
15525
15774
15800
15820
15840
15900
Mechanical General
HVAC Test & Balance
Plumbing Systems
Plumbing Fixtures and Trim
Fire Suppression Systems
Packaged Rooftop Units
Air Distribution Devices ..................................................................................Revised 3/16/11
Fans
Ductwork ........................................................................................................Revised 3/16/11
Controls
TOC - 4
TABLE OF CONTENTS
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Division 16 - Electrical
*
*
*
*
*
16010
16100
16300
16730
16920
Electrical General
Electrical Basic Materials & Methods
Lighting
Clock Systems
Motor Controls and Wiring
END OF TABLE OF CONTENTS
*
These specification sections not prepared by Cooper Carry.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
00020-1
INVITATION FOR BIDS
SECTION 00020
INVITATION FOR BIDS
BID 11-51
This project consists of Addition for Admin, Personnel, Modify/Renovate Restrooms, Flooring
Replacement, HVAC, Plumbing (Water Coolers), Add Sprinkler System, Electrical (Clock System,
Electrical (Fire Alarm System), Electrical (Lighting)
Sealed bids are requested by Cobb County School District from general contractors for construction of:
SCHOOL: King Springs Elementary School Additions and Modifications
PROJECT NO.: 224/8032
BID NO.: Bid No. 11-51
Bids will be received by the Cobb County School District, Procurement Services Department at 6975
Cobb International Blvd. Kennesaw, Georgia 30152 until:
11:30 AM, LOCAL TIME, March 30, 2011
At which time and place the bids will be publicly opened and read aloud. Bids will be time and date
stamped upon receipt at Cobb County School District Procurement Services Department. The exact time
of receipt is determined by the date/time stamp. Bids received late will not be considered.
A PRE-BID CONFERENCE will be held at King Springs Elementary School, 1041 Reed Rd.,
Smyrna, GA 30082 on March 10, 2011 at 3:00 PM.
Attendance at this Pre-bid Conference is mandatory in order to submit a bid.
All bids accepted must be in sealed envelopes marked with your company name and “Bid 11-51, King
Springs Elementary School Additions and Modifications”. For mailing purposes, please address
your bid to CCSD, Procurement Services Department, 6975 Cobb International Blvd., Kennesaw, Georgia
30152. Attn: Barbara Bates.
Bid Documents may be reviewed at the Office of the Architect, CCSD Procurement Services Dept., the
AGC Builders Exchange, the F.W. Dodge Plan Room, and Reed Construction Data.
Contractors shall submit to the Owner for consideration a properly executed AIA
Document A-305, Contractor’s Qualification Statement (that is less than one year old)
and a current Audited/Reviewed financial statement (that is less than eighteen months
old) no later than March 18, 2011). The Owner will consider the submittal and respond within five (5)
days if the submittal is not accepted.
Contractor’s Qualification statements should be addressed to: CCSD, Procurement Services Department,
6975 Cobb International Blvd., Kennesaw, Georgia 30152.
Attn: Barbara Bates, Emails to:
Barbara.Bates@cobbk12.org.
For Inquiries Regarding the Bid Documents:
All communications concerning these documents must be submitted in writing to the Cobb County School
District (CCSD) Procurement Services Department either by email, facsimile, or U.S. mail. Email is the
preferred method of communication. Email correspondence is to be directed to Barbara Bates at
Barbara.Bates@cobbk12.org. Fax correspondence is to be sent to 770 426 3371. Correspondence sent
by U.S. mail is to be sent to CCSD Procurement Services Department., 6975 Cobb International Blvd.,
Kennesaw, Georgia 30152, Attn: Barbara Bates.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
00020-2
INVITATION FOR BIDS
Only written inquiries received via email, fax, or U.S. mail by 5:00 P.M. March 25, 2011 will be
considered. Responses to all written inquiries will be posted to the Current Solicitations page on the Cobb
County School District website at
http://www.cobbk12.org/centraloffice/Purchasing/Current%20Bids%20and%20RFPs.htm
Bid Documents will be issued by:
The Architect:
William Collier
Cooper, Carry, Inc.
Suite 2400
191 Peachtree Street, NE
Atlanta, GA 30303
Phone:
Fax:
404-237-2000
404-237-0276
to all interested parties upon receipt of a request accompanied by a non-refundable check made payable
to the issuing party above in the amount of:
$75.00 per set.
Bid documents will be shipped post paid, as soon as possible.
Contract, if awarded, will be on the basis stated in the Instructions to Bidders. No bid may be withdrawn
for a period of 60 days after bid opening.
Bids must be accompanied by a bid bond made payable to the Cobb County School District, in the
amount equal to 5 percent of the bid price. (Certified Checks Not Acceptable.) The successful bidder will
be required to furnish a Performance Bond and a Payment Bond acceptable to the Cobb County School
District in an amount equal to 100 percent of the contract price and executed by a Surety Company
licensed to do business in the State of Georgia and listed in the Department of the Treasury Circular 570,
latest edition. The Surety Company shall have an A.M. Best Company minimum rating of "A-" with
a financial size of VI “6” or better. Bonds must be accompanied by letter stating bonding company's
current rating for verification prior to acceptance by the Owner and execution of the formal
Owner/Contractor agreement.
Bonding of Subcontractors: Include in the Base Bid, Performance and Labor and Materials Payment
Bonds, each in 100% of the subcontract sum, for each Subcontractor having a contract of $50,000.00 or
more for Roofing, HVAC, Plumbing, Sprinkler System and Electrical Work as required by the General
Conditions.
Contractor and Subcontractors shall require the Attorney-in-Fact who executes bonds on behalf of
sureties to attach a certified, current copy of his Power of Attorney.
Cobb County School District reserves the right to award the project on whatever basis is in the interest of
the Owner and to accept or reject any or all bids and to waive technicalities and informalities.
BY:
DATE:
Cobb County School District
Alisa Morningstar
Director, Procurement Services Dept.
March 1, 2011
END OF SECTION
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
00210-1
SPECIFIC DATE CONSTRUCTION SCHEDULE
SECTION 00210
SPECIFIC DATE CONSTRUCTION SCHEDULE
PART ONE - GENERAL
1.01
DESCRIPTION:
A.
Work Included: A Specific Date Construction Schedule for the project is stated here-in.
Dates for Items 1 through 4 may be considered preliminary until such time as Item No. 3
"Notice of Award" is made.
B.
If dates for Items 2 and 3 are maintained, then the dates for Items 4 through 9 become a
fixed Construction Schedule.
C.
If the Notice of Award date moves forward, then all subsequent dates for Items 4 through
9 shall move forward by the same number of days, unless otherwise stated in an
Addendum. If the Notice of Award date is moved back, then all subsequent dates for
items 5 through 9 shall remain the same, unless otherwise stated in an Addendum.
PART TWO - EXECUTION
2.01
GENERAL: The schedule dates for the project shall be adhered to and are the last acceptable
dates unless they are modified by change order. All dates indicate midnight unless otherwise
stipulated. All work affecting an existing facility shall be accomplished during non class time. The
Contractor shall be responsible for maintaining all emergency egress routes in accordance with
governing code criteria and security for the building.
2.02
PHASING: If the project has phases of work with different Substantial Completion dates, the
Contractor shall obtain a separate building permit for each Phase to allow separate inspections
and a Certificate of Occupancy to be issued for each Phase.
2.03
CONSTRUCTION SCHEDULE:
1. ADVERTISEMENT FOR BID:
2/28/2011
2. BID DATE & TIME:
3/30/2011 - 11:30 A.M.
3. NOTICE OF AWARD:
4/29/2011
4. CONTRACT AGREEMENT DATE:
4/28/2011
5. START OF CONTRACT TIME:
(10 DAYS AFTER NOTICE OF AWARD
OR ON NOTICE TO PROCEED DATE;
WHICHEVER OCCURS FIRST)
START OF CONSTRUCTION TIME:
5/9/2011
6/2/2011
6. COMPLETION DATES:
Phase 1 – Interior Building Renovation:
a. SUBSTANTIAL COMPLETION:
7/29/2011
b. ACTUAL DAMAGES OR LIQUIDATED
DAMAGES BECOME EFFECTIVE ON
ITEM 6a:
7/30/2011
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
c.
00210-2
SPECIFIC DATE CONSTRUCTION SCHEDULE
FINAL COMPLETION:
8/29/2011
d. ACTUAL DAMAGES OR LIQUIDATED
DAMAGES BECOME EFFECTIVE ON
ITEM # 6c
8/30/2011
Phase 2 – Administrative Addition:
e. SUBSTANTIAL COMPLETION:
f.
ACTUAL DAMAGES OR LIQUIDATED
DAMAGES BECOME EFFECTIVE ON
ITEM 6a:
10/3/2011
10/4/2011
g. FINAL COMPLETION:
11/3/2011
ACTUAL DAMAGES OR LIQUIDATED
h. DAMAGES BECOME EFFECTIVE ON
ITEM # 6c
11/4/2011
END OF SECTION
REPORT OF
SUBSURFACE EXPLORATION AND
GEOTECHNICAL ENGINEERING EVALUATION
KING SPRINGS ELEMENTARY SCHOOL
1041 Reed Road
Smyrna, Cobb County, Georgia
Prepared For:
COBB COUNTY SCHOOL DISTRICT
440 Glover Street
Marietta, Georgia 30060
NOVA Project Number 2011019
March 17, 2011
TABLE OF CONTENTS
1.0 1.1 1.2 1.3 1.4 2.0 2.1 2.2 3.0 3.1 3.2 4.0 4.1 4.2 5.0 5.1 5.2 6.0 6.1 6.2 6.3 6.4 6.5 6.6 SUMMARY ........................................................................................................................ 1 GENERAL .................................................................................................................................... 1 SITE PREPARATION .................................................................................................................. 1 FOUNDATIONS .......................................................................................................................... 1 SEISMIC ....................................................................................................................................... 1 INTRODUCTION.............................................................................................................. 2 PROJECT INFORMATION ......................................................................................................... 2 SCOPE OF WORK ....................................................................................................................... 2 SITE DESCRIPTION........................................................................................................ 4 GENERAL .................................................................................................................................... 4 GEOLOGY / HYDROLOGY ....................................................................................................... 4 FIELD AND LABORATORY PROCEDURES ............................................................. 6 FIELD EXPLORATION .............................................................................................................. 6 LABORATORY TESTING .......................................................................................................... 6 SUBSURFACE CONDITIONS ........................................................................................ 7 SOIL CONDITIONS .................................................................................................................... 7 GROUNDWATER CONDITIONS .............................................................................................. 8 CONCLUSIONS AND RECOMMENDATIONS ........................................................... 9 SITE GRADING ........................................................................................................................... 9 GROUNDWATER CONTROL .................................................................................................. 11 FOUNDATIONS ........................................................................................................................ 11 SLAB-ON-GRADE .................................................................................................................... 13 SEISMIC ..................................................................................................................................... 13 CONSTRUCTION OBSERVATIONS....................................................................................... 14 APPENDIX
Appendix A – Figures and Maps
Appendix B – Subsurface Data
Appendix C – Qualifications of Recommendations
King Springs Elementary School
Cobb County School District
March 17, 2011
NOVA Project Number 2011019
1.0 SUMMARY
A brief summary of pertinent findings, conclusions and recommendations are presented below.
This information should not be utilized in design or construction without reading the report in its
entirety and paying particular attention to the recommendations presented in the text and
Appendix.
1.1
GENERAL
•
Four soil test borings (B-1 through B-4) were drilled at the subject site during this exploration.
Generally, the borings encountered a surface veneer of asphalt underlain by gravel, previously
placed fill materials, residual soils and partially weathered rock.
•
Fill soils were encountered in borings B-2 and B-3 at depths of 11 and 6 feet beneath the
existing ground surface, respectively. The fill materials were generally described as sandy silt
with rock fragments and with a consistency of stiff to very stiff.
•
Partially weathered rock was encountered in borings B-1 and B-3 at depths ranging from 43 to
28 feet below the existing ground surface, respectively. Auger refusal materials were not
encountered in any of the borings above the boring termination depths of 20 to 50 feet below
the existing ground surface.
1.2
•
1.3
•
1.4
•
SITE PREPARATION
The majority of the encountered fill soils were fine grained soils. Although we do not
anticipate groundwater control problems, establishing subgrades in fine grained soils exposed
to inclement weather conditions can be challenging and may require drying and/or stabilizing
depending on the time of year and weather conditions.
FOUNDATIONS
We recommend that the proposed structure be supported on conventional shallow foundations
designed for a maximum allowable soil bearing pressure of 3,000 pounds per square foot (psf).
SEISMIC
In accordance with Section 1613.5.2 of the 2006 International Building Code, the seismic Site
Class was estimated using the standard penetration resistance values obtained from the soil test
borings performed during this study. Based upon this analysis, and our knowledge of general
subsurface conditions in the area, we believe the soil profiles associated with a Site Class “D”
are generally appropriate for this site.
Page 1
King Springs Elementary School
Cobb County School District
March 17, 2011
NOVA Project Number 2011019
2.0 INTRODUCTION
2.1
PROJECT INFORMATION
Our understanding of this project is based on discussions with Mr. Henry Gomez of Cobb County
School District, review of the provided site plans, a site reconnaissance during boring layout, and
our experience with similar projects.
The project site is located on the existing King Springs Elementary School campus located at 1041
Reed Road in Smyrna, Cobb County, Georgia.
We understand that the proposed construction will consist of a one-story addition. Final column
loads were not available at the time of issuance of this report. However, based upon previous
experience with similar structures, we estimate that compressive column loads will be on the
order of 80 to 100 kips, respectively. Wall loading is expected to be on the order of 2 to 3 kips
per linear foot. The planned first floor elevation of the building is currently proposed as 1015.5
feet-MSL. Minimal cuts and fills (on the order of 5 feet) are anticipated to achieve design grades.
2.2
SCOPE OF WORK
Cobb County School District engaged NOVA to provide geotechnical engineering consulting
services for the King Springs Elementary School project. This report briefly discusses our
understanding of the project, describes our exploratory procedures and presents our findings,
conclusions and recommendations.
The primary objective of this study was to perform a geotechnical exploration within the area of
the proposed construction and to assess these findings as they relate to geotechnical aspects of the
planned site development. The authorized geotechnical engineering services included a site
reconnaissance, a soil test boring and sampling program, engineering evaluation of the field data,
and the preparation of this report.
The services were performed substantially as outlined in the NOVA and Cobb County School
District RFP 34-10 Geotechnical Services contract dated August 3, 2010, and in general
accordance with industry standards.
As authorized per the above referenced contract, the completed geotechnical report was to include:
•
•
A description of the site, fieldwork, laboratory testing and general soil conditions
encountered, as well as a Boring Location Plan and individual Boring Records.
Discussion on potential design/construction issues indicated by the exploration, such as
materials that would require difficult excavation techniques, shallow groundwater table, etc.
Page 2
King Springs Elementary School
Cobb County School District
•
•
•
•
•
•
•
•
March 17, 2011
NOVA Project Number 2011019
Recommendations for controlling groundwater and/or run-off during construction and, the
need for permanent de-watering systems based on the anticipated post construction
groundwater levels.
Recommendations for foundation design and construction, including allowable bearing
capacities and bearing depths.
Estimate of total and differential settlements of foundation based on available structural
loading data.
Recommended quality control measures (i.e. sampling, testing, and inspection requirements)
for site grading and foundation construction. Soil compaction requirements for foundations,
structural fill and pavements were to be provided.
Slab-on-grade construction considerations based on the geotechnical findings, including the
need for a sub-slab vapor barrier or a capillary barrier.
Suitability of on-site soils for re-use as structural fill and backfill. Additionally, the criteria
for suitable fill materials were to be provided.
Seismic site classification using correlation with SPT N-values in accordance with the 2006
International Building Code.
Site preparation considerations that include geotechnical discussions regarding site stripping
and subgrade preparation, recommended cut or fill slopes, and engineered fill/backfill
placement.
The assessment of the presence of wetlands, floodplains or water classified as State Waters of
Georgia was beyond the scope of this study. Additionally, the assessment of site environmental
conditions, including the detection of pollutants in the soil, rock or groundwater, at the site was also
beyond the scope of this geotechnical study. If desired by the client, NOVA can provide these
services.
Page 3
King Springs Elementary School
Cobb County School District
March 17, 2011
NOVA Project Number 2011019
3.0 SITE DESCRIPTION
3.1
GENERAL
The site is the existing King Springs Elementary School campus located at 1041 Reed Road in
Smyrna, Cobb County, Georgia. The site is bounded by residential and educational development
to the north, residential development to the east, Reed Road then residential development to the
south, and Gann Road then residential development to the west.
Based on the provided site plan, current site grades in the area of the proposed addition range
from 1015.5 feet-MSL at the existing building to 1012 feet-MSL along the entrance drive just
south of the proposed addition.
Currently, the site is developed as an existing elementary school with several rectangular shaped
buildings, playground areas, and associated surface asphalt-paved parking and drive areas. The site
is also landscaped with trees, shrubs and grassed areas. Based on a limited visual assessment of the
existing structures, no distress or other evidence was noted that would indicate foundation related
support problems. We note however that the type, bearing design and design loading of
foundations for these structures are unknown.
3.2
GEOLOGY / HYDROLOGY
3.2.1 Site and Area Geology
The site is located in the Piedmont Geologic Region, a broad northeasterly trending province
underlain by crystalline rocks up to 600 million years old. The Piedmont is bounded on the
northwest by the Blue Ridge Range of the Appalachian Mountains, and on the southeast by the
leading edge of Coastal Plain sediments, commonly referred to as the “Fall Line”. Numerous
episodes of crystal deformation have produced varying degrees of metamorphism, folding and
shearing in the underlying rock. The resulting metamorphic rock types in this area of the Piedmont
are predominantly a series of Precambrian age schists and gneisses, with scattered granitic or
quartzite intrusions.
According to the "Geology of the Greater Atlanta Region" by McConnell and Abrams, 1984, the
site is generally underlain by the Sandy Springs Group. This geologic formation typically consists
of intercalated biotite gneiss, mica schist and amphibolite.
Residual soils in the region are primarily the product of in-situ chemical decomposition of the
parent rock. The extent of the weathering is influenced by the mineral composition of the rock and
defects such as fissures, faults and fractures. The residual profile can generally be divided into three
zones:
Page 4
King Springs Elementary School
Cobb County School District
March 17, 2011
NOVA Project Number 2011019
•
An upper zone near the ground surface consisting of red clays and clayey silts which have
undergone the most advanced weathering,
•
An intermediate zone of less weathered micaceous sandy silts and silty sands, frequently
described as “saprolite”, whose mineralogy, texture and banded appearance reflects the structure
of the original rock, and
•
A transitional zone between soil and rock termed partially weathered rock (PWR). Partially
weathered rock is defined locally by standard penetration resistances exceeding 100 blows per
foot.
The boundaries between zones of soil, partially weathered rock and bedrock are erratic and
poorly defined. Weathering is often more advanced next to fractures and joints that transmit
water, and in mineral bands that are more susceptible to decomposition. Boulders and rock lenses
are sometimes encountered within the overlying PWR or soil matrix. Consequently, significant
fluctuations in depths to materials requiring difficult excavation techniques may occur over short
horizontal distances.
3.2.2 Groundwater
Groundwater in the Piedmont typically occurs as an unconfined or semi-confined aquifer
condition. Recharge is provided by the infiltration of rainfall and surface water through the soil
overburden. More permeable zones in the soil matrix, as well as fractures, joints and
discontinuities in the underlying bedrock can affect groundwater conditions. The groundwater
table in the Piedmont is expected to be a subdued replica of the original surface topography.
Page 5
King Springs Elementary School
Cobb County School District
March 17, 2011
NOVA Project Number 2011019
4.0 FIELD AND LABORATORY PROCEDURES
4.1
FIELD EXPLORATION
Boring locations were specified on the Foundation and Framing Plans prepared by Willett
Engineering Company and were established in the field by NOVA personnel by taping and
estimating distances and angles from site landmarks. Underground and overhead utility related
adjustments of the boring locations were made at the time of the field exploration. Boring
elevations were then interpolated from the provided topographic survey. Consequently, referenced
boring locations and elevations are approximate. If increased accuracy is desired by the client,
NOVA recommends that the boring locations and elevations be surveyed.
Our field exploration was conducted on March 12, 2011 and included four soil test borings (B-1
through B-4) drilled to depths of 20 to 50 feet below the existing ground surface in the area of the
proposed addition. All drilling and sampling operations were performed in general accordance with
ASTM designations.
Test Boring Records in the Appendix show the standard penetration test (SPT) resistances, or “Nvalues”, and present the soil conditions encountered in the borings. These records represent our
interpretation of the subsurface conditions based on the field exploration data, visual examination
of the split-barrel samples, and generally accepted geotechnical engineering practices. The
stratification lines and depth designations represent approximate boundaries between various
subsurface strata. Actual transitions between materials may be gradual.
The groundwater levels reported on the Test Boring Records represent measurements made at the
completion of the soil test boring. The soil test borings were subsequently backfilled with the soil
cuttings.
4.2
LABORATORY TESTING
Split-barrel samples were returned to our testing laboratory, where they were classified using
visual/manual methods in accordance with the Unified Soil Classification System (USCS) and
ASTM designations. The descriptions presented in the boring logs should be considered
approximate. Further laboratory testing was beyond the scope of this exploration.
Page 6
King Springs Elementary School
Cobb County School District
March 17, 2011
NOVA Project Number 2011019
5.0 SUBSURFACE CONDITIONS
5.1
SOIL CONDITIONS
The following paragraphs provide generalized descriptions of the subsurface profiles and soil
conditions encountered by the borings conducted during this study. The Test Boring Records in the
Appendix should be reviewed to provide more detailed descriptions of the subsurface conditions
encountered at each boring location. Conditions may vary at other locations and times.
5.1.1 Surface Materials
The borings were performed within existing parking and drive areas and encountered up to 2
inches of asphalt underlain by up to 3 inches of gravel. Although not encountered in any of the
borings, concrete walkways were present in the area of the proposed addition.
5.1.2 Fill
Fill was encountered in borings B-2 and B-3 to depths of 11 and 6 feet below the existing ground
surface, respectively. The fill was generally described as sandy silt with rock fragments and a
consistency of stiff to very stiff. Standard penetration resistances in the fill varied from 9 to 21
blows per foot (bpf), but may have been amplified by the presence of rock fragments.
5.1.3 Residual Soils
Residual soils were encountered in all borings beneath the fill materials or ground surface. The
residuum was generally described as sandy silt. Standard penetration resistance values ranged from
14 to 63 bpf, but more typically varied from 18 to 28 bpf.
5.1.4 Partially Weathered Rock
Partially weathered rock (PWR) is a transitional material between soil and the underlying parent
rock that is defined locally as materials that exhibit a standard penetration resistance exceeding 100
bpf. PWR was encountered in borings B-1 and B-3 at depths of 43 and 28 feet below the ground
surface (approximate elevations of 970 and 986 feet-MSL), respectively.
5.1.5 Auger Refusal Materials
Auger refusal materials are any very hard or very dense material, frequently boulders or the upper
surface of bedrock, which cannot be penetrated by a power auger. Auger refusal was not
encountered in any of the borings above the boring termination depths of 20 to 50 feet below the
existing ground surface.
Page 7
King Springs Elementary School
Cobb County School District
5.2
March 17, 2011
NOVA Project Number 2011019
GROUNDWATER CONDITIONS
Groundwater was observed at the time of boring in borings B-1 and B-3 at depths of 46 and 38 feet
below the existing ground surface (approximate elevations of 967 and 976 ft-MSL). Groundwater
levels vary with changes in season and rainfall, construction activity, surface water runoff and
other site-specific factors. Groundwater levels in the Smyrna area are typically lowest in the late
summer-early fall and highest in the late winter-early spring; consequently, the water table may
vary at times.
Page 8
King Springs Elementary School
Cobb County School District
March 17, 2011
NOVA Project Number 2011019
6.0 CONCLUSIONS AND RECOMMENDATIONS
The following conclusions and recommendations are based on our understanding of the proposed
construction, site observations, our evaluation and interpretation of the field data obtained during
this exploration, our experience with similar subsurface conditions, and generally accepted
geotechnical engineering principles and practices.
Subsurface conditions in unexplored locations or at other times may vary from those encountered
at specific boring locations. If such variations are noted during construction, or if project
development plans are changed, we request the opportunity to review the changes and amend our
recommendations, if necessary.
As previously noted, boring locations were established by estimating distances and angles from site
landmarks. If increased accuracy is desired by the client, we recommend that the boring locations
and elevations be surveyed.
6.1
SITE GRADING
6.1.1 Site Preparation
General: An existing porte cochere that will require demolition currently occupies the site. Prior to
proceeding with construction, all slabs, foundations, pavements, vegetation, root systems, topsoil,
and other deleterious non-soil materials should be stripped from proposed construction areas.
Clean topsoil may be stockpiled and subsequently re-used in landscaped areas. Debris-laden
materials should be excavated, transported and disposed of off-site in accordance with
appropriate solid waste rules and regulations. All existing utility locations should be reviewed to
assess their impact on the proposed construction and relocated/grouted in-place as appropriate.
After clearing and stripping, areas which are at grade or will receive fill should be carefully
evaluated by a NOVA geotechnical engineer. The engineer will require proofrolling of the
subgrade with multiple passes of a 20 to 30 ton loaded truck or other pneumatic-tired vehicle of
similar size and weight. The purpose of the proofrolling is to locate soft, weak, or excessively wet
fill or residual soils present at the time of construction. Any unstable materials observed during the
evaluation and proofrolling operations should be undercut and replaced with structural fill or
stabilized in-place by scarifying and re-densifying.
Page 9
King Springs Elementary School
Cobb County School District
March 17, 2011
NOVA Project Number 2011019
Existing/Old Fill: Previously placed fill materials were encountered during this exploration.
Based on our experience, we anticipate fill materials likely exist at other locations between our
borings. Old fills are frequently erratic in composition and consistency. In the event that low
consistency and/or debris laden fill materials are encountered during construction, typical
recommendations would include undercutting and backfilling with structural fill and/or
stabilizing in-place with fabric, stone, and/or other remedial techniques. Actual remedial
recommendations can best be determined by the geotechnical engineer in the field at the time of
construction.
6.1.2 Difficult Excavation
None of the borings encountered dense soil, PWR or rock above planned finished grades.
Therefore, we do not anticipate that significant quantities of materials requiring difficult excavation
techniques will be encountered during mass grading and/or shallow foundation/utility excavation
operations.
6.1.3 Fill Placement
Fill materials should be low plasticity soil (Plasticity Index less than 30), free of non-soil materials
and rock fragments larger than 3 inches in any one dimension. Based on visual examination, the
existing residual soils and much of the existing fill, which does not contain appreciable amounts of
debris, rock, organics or other deleterious materials encountered during this exploration generally
appear suitable for re-use as structural fill. Prior to construction, bulk samples of the proposed fill
materials should be laboratory-tested to confirm their suitability.
Organic and/or debris laden material is not suitable for re-use as structural fill. Topsoil, mulch
and similar organic materials can be wasted in architectural areas. Debris-laden materials should
be excavated, transported and disposed of off-site in accordance with appropriate solid waste
rules and regulations.
Fill should be placed in thin, horizontal loose lifts (maximum 8-inch) and compacted to at least
95 percent of the standard Proctor maximum dry density (ASTM D 698). The upper 8 inches of
soil beneath pavements and slab-on-grade should be compacted to at least 98 percent. In
confined areas, such as utility trenches or behind retaining walls, portable compaction equipment
and thinner fill lifts (3 to 4 inches) may be necessary. Fill materials used in structural areas
should have a target maximum dry density of at least 95 pounds per cubic foot (pcf). If lighter
weight fill materials are used, the NOVA geotechnical engineer should be consulted to assess the
impact on design recommendations.
Page 10
King Springs Elementary School
Cobb County School District
March 17, 2011
NOVA Project Number 2011019
Soil moisture content should be maintained within 3 percent of the optimum moisture content. Fine
grained soils were encountered at the planned finished subgrade elevations at each of the boring
locations. Although we do not anticipate significant groundwater control problems based on the
stabilized groundwater levels, establishing subgrades in these fine grained soils may be challenging
and could require drying and/or stabilization depending on the time of year and weather conditions
when grading is performed. We recommend that the grading contractor have equipment on site
during earthwork for both drying and wetting fill soils. Moisture control may be difficult during
rainy weather.
All filling operations should be observed by a NOVA soils technician, who can confirm
suitability of material used and uniformity and appropriateness of compaction efforts. The
NOVA soils technician can also document compliance with the specifications by performing
field density tests using thin-walled tube, nuclear, or sand cone testing methods (ASTM D 2937,
D 6938, or D 1556, respectively). One test per 400 cubic yards and every 2 feet of placed fill is
recommended, with test locations well distributed throughout the fill mass. When filling in small
areas, at least one test per day per area should be performed.
6.2
GROUNDWATER CONTROL
During the current study, depths to groundwater ranged from 46 to 38 feet below the existing
ground surface (approximate elevations ranging from 967 to 976 feet-MSL). Based on the
planned cuts necessary to reach design subgrades, we do not anticipate significant groundwater
control problems during mass grading operations. The groundwater appears to be below planned
slab elevations.
As previously noted, groundwater levels are subject to seasonal, climatic and other variations and
may be different at other times and locations. The extent and nature of any dewatering required
during construction will be dependent on the actual groundwater conditions prevalent at the time of
construction and the effectiveness of construction drainage to prevent run-off into open
excavations.
6.3
FOUNDATIONS
After the recommended site and subgrade preparation and fill placement, we recommend that the
proposed structure be supported by conventional shallow foundations. Foundations bearing on
undisturbed residual soils and/or compacted structural fill may be designed for a maximum
allowable bearing pressure of 3,000 pounds per square foot (psf).
Previously placed fill materials were encountered on the site. In the event that low consistency or
debris-laden fill materials are present in foundation excavations, undercutting and backfilling with
crushed stone or structural fill or redesigning for a reduced bearing pressure, may be required.
Page 11
King Springs Elementary School
Cobb County School District
March 17, 2011
NOVA Project Number 2011019
We recommend minimum footing widths of 24 inches for ease of construction and to reduce the
possibility of localized shear failures. Exterior footing bottoms should be at least 18 inches below
exterior grades for protection against frost damage.
Settlements for spread foundations were assessed using SPT values to estimate elastic modulus,
based on published correlations and previous NOVA experience. We note that the settlements
presented are based on random field data and an assumed subsoil profile. Conditions may be better
or worse in other areas; however, we believe the estimated settlements are reasonable.
Based on column loadings, soil bearing capacities and the presumed foundation elevations as
discussed above, we expect primary total settlement beneath individual footings to be on the order
of ¾ to 1 inches.
The amount of differential settlement is difficult to predict because the subsurface and foundation
loading conditions can vary considerably across the site. However, we anticipate differential
settlement between adjacent footings could vary from ¼ to ½ inch. The final deflected shape of the
structure will be dependent on actual footing locations and loading.
Foundation support conditions are highly erratic and may vary dramatically in short horizontal
distances. It is anticipated that the geotechnical engineer may recommend a different bearing
capacity upon examination of the actual foundation subgrade at numerous locations.
To reduce the differential settlement if lower consistency materials are encountered, a lower
bearing capacity should be used or the foundations should be extended to more competent
materials. We anticipate that timely communication between the geotechnical engineer and the
structural engineer, as well as other design and construction team members, will be required.
All footing excavations should be evaluated by the NOVA geotechnical engineer prior to
reinforcing steel placement to observe foundation subgrade preparation and confirm bearing
pressure capacity.
Footing excavations should be level and free of debris, ponded water, mud, and loose, frozen or
water-softened soils. Concrete should be placed as soon as is practical after the footing is
excavated and the subgrade evaluated. Foundation concrete should not be placed on frozen or
saturated soil. If a footing excavation remains open overnight, or if rain or snow is imminent, a 3
to 4-inch thick "mud mat" of lean concrete should be placed in the bottom of the footing to
protect the bearing soils until reinforcing steel and concrete can be placed.
Page 12
King Springs Elementary School
Cobb County School District
6.4
March 17, 2011
NOVA Project Number 2011019
SLAB-ON-GRADE
The conditions exposed at subgrade levels will vary across the site and may include existing fill
materials, newly placed structural fill or residual soils. Provided the existing fill material does not
deflect or “pump” during the proofroll, slabs-on-grade may be adequately supported on these
subgrade conditions subject to the recommendations in this report. Slabs-on-grade should be
jointed around columns and along walls to reduce cracking due to differential movement. A 6-inch
layer of crushed stone may be placed beneath the building slabs to reduce non-uniform support
conditions. An underdrain system is not necessary beneath the slabs, but an impermeable vapor
barrier is recommended beneath finished spaces to reduce dampness.
Once grading within the building footprint is completed, the subgrade is usually exposed to
adverse construction activities and weather conditions during the period of sub-slab utility
installation. The subgrade should be well-drained to prevent the accumulation of water. If the
exposed subgrade becomes saturated or frozen, the geotechnical engineer should be consulted.
After utilities have been installed and backfilled, a final subgrade evaluation should be performed
by the geotechnical engineer immediately prior to slab-on-grade placement. If practical, proofrolling
may be used to redensify the surface and to detect any soil that has become excessively wet or
otherwise loosened.
6.5
SEISMIC
6.5.1 Soil Site Class
In accordance with Section 1613.5.2 of the 2006 IBC, the seismic Site Class was estimated using
the standard penetration resistance values obtained from the soil test borings performed during this
study. Based upon this analysis, and our knowledge of general subsurface conditions in the area, we
believe the soil profiles associated with a Site Class “D” are generally appropriate for this site.
We note that the IBC allows determination of Site Class using in-situ seismic shear wave survey
techniques. It should be noted that use of this supplemental method does not guarantee a lower site
class designation; however, it is a reasonable and prudent approach that can be performed in a
supplemental study, if requested.
Page 13
King Springs Elementary School
Cobb County School District
6.6
March 17, 2011
NOVA Project Number 2011019
CONSTRUCTION OBSERVATIONS
6.6.1 Shallow Foundations
Footing excavations should be level and free of debris, ponded water, mud, and loose, frozen or
water-softened soils. All footing excavations should be evaluated by the NOVA geotechnical
engineer prior to reinforcing steel placement to observe foundation subgrade preparation and
confirm bearing pressure capacity. Due to variable site subsurface and construction conditions,
some adjustments in isolated foundation bearing pressures, depth of footings or undercutting and
replacement with controlled structural fill may be necessary.
6.6.2 Subgrade
Once site grading is completed, the subgrade may be exposed to adverse construction activities and
weather conditions. The subgrade should be well-drained to prevent the accumulation of water. If
the exposed subgrade becomes saturated or frozen, the NOVA geotechnical engineer should be
consulted.
A final subgrade evaluation should be performed by the NOVA geotechnical engineer
immediately prior to pavements or slab-on-grade placement. If practical, proofrolling may be
used to re-densify the surface and to detect any soil, which has become excessively wet or
otherwise loosened.
Page 14
APPENDIX A
FIGURES AND MAPS
See map insert below
Subject Site
FIGURE 1
SITE LOCATION MAP
SOURCE: www.Mapquest.com
DATE: Unknown
SCALE: As Shown
COBB COUNTY SCHOOL
DISTRICT
King Springs Elementary School
Smyrna, Cobb County, Georgia
NOVA Project Number 2011019
Subject Site
FIGURE 2
TOPOGRAPHIC MAP
COBB COUNTY SCHOOL
DISTRICT
SOURCE: www.MSRMaps.com
USGS 7.5 Minute Series Topographic Quadrangle
July 1, 1991 Smyrna, Georgia
SCALE: As Shown
King Springs Elementary School
Smyrna, Cobb County, Georgia
NOVA Project Number 2011019
Subject Site
FIGURE 3
REGIONAL GEOLOGY
Geologic Map of Georgia
Georgia Department of Natural Resources, 1976
SCALE: As Shown
COBB COUNTY SCHOOL
DISTRICT
King Springs Elementary School
Smyrna, Cobb County, Georgia
NOVA Project Number 2011019
B-4
B-3
B-1
B-2
NOVA SOIL TEST BORINGS
FIGURE 4
BORING LOCATION PLAN
SCALE: Graphic
COBB COUNTY SCHOOL DISTRICT
King Springs Elementary School
Smyrna, Cobb County, Georgia
NOVA Project Number 2011019
APPENDIX B
SUBSURFACE DATA
KEY TO SYMBOLS AND CLASSIFICATIONS
DRILLING SYMBOLS
Split Spoon Sample
Undisturbed Sample (UD)
Standard Penetration Resistance (ASTM D1586‐67)
Water Table at least 24 Hours after Drilling
Water Table 1 Hour or less after Drilling
100/2”
Number of Blows (100) to Drive the Spoon a Number of Inches (2)
NX, NQ
Core Barrel Sizes: 2⅛‐ and 2‐Inch Diameter Rock Core, Respectively
REC
Percentage of Rock Core Recovered
RQD
Rock Quality Designation – Percentage of Recovered Core Segments 4 or more Inches Long
Loss of Drilling Water
MC
Moisture Content Test Performed
CORRELATION OF PENETRATION RESISTANCE WITH RELATIVE DENSITY AND CONSISTENCY
SANDS
SILTS
and
CLAYS
Number of Blows, “N”
0–4
5 – 10
11 – 30
31 – 50
Over 50
Approximate Relative Density
Very Loose
Loose
Medium Dense
Dense
Very Dense
Number of Blows, “N”
0–2
3–4
5–8
9 – 15
16 – 30
31 – 50
Over 50
Approximate Consistency
Very Soft
Soft
Firm
Stiff
Very Stiff
Hard
Very Hard
DRILLING PROCEDURES
Soil sampling and standard penetration testing performed in accordance with ASTM D1586‐67. The standard
penetration resistance is the number of blows of a 140 pound hammer falling 30 inches to drive a 2‐inch O.D., 1⅖‐
inch I.D. split spoon sampler one foot. Core drilling performed in accordance with ASTM D2113‐62T. The
undisturbed sampling procedure is described by ASTM D1587‐67. Soil and rock samples will be discarded 60 days
after the date of the final report unless otherwise directed.
SOIL CLASSIFICATION CHART
COARSE GRAINED
SOILS
GRAVELS
SANDS
FINE GRAINED
SOILS
SILTS AND CLAYS
Liquid Limit
less than 50
SILTS AND CLAYS
Liquid Limit
50 or more
HIGHLY ORGANIC
SOILS
Clean Gravel
less than 5% fines
Gravels with Fines
more than 12% fines
Clean Sand
less than 5% fines
Sands with Fines
more than 12% fines
Inorganic
Organic
Inorganic
Organic
Organic matter, dark
color, organic odor
GW
GP
GM
GC
SW
SP
SM
SC
CL
ML
OL
CH
MH
OH
Well graded gravel
Poorly graded gravel
Silty gravel
Clayey gravel
Well graded sand
Poorly graded sand
Silty sand
Clayey sand
Lean clay
Silt
Organic clay and silt
Fat clay
Elastic silt
Organic clay and silt
PT
Peat
PARTICLE SIZE IDENTIFICATION
GRAVELS
Coarse
Fine
¾ inch to 3 inches
No. 4 to ¾ inch
SANDS
Coarse
Medium
Fine
No. 10 to No. 4
No. 40 to No. 10
No. 200 to No. 40
SILTS AND CLAYS
Passing No. 200
AFTER 24 HOURS:
This information pertains only to this boring and should not be interpreted as being indicative of the site.
0
1010
ASPHALT: 2 inches
GRAVEL: 3 inches
RESIDUUM: Very stiff red purple brown fine sandy micaceous
SILT
N/O
2011019
1013 ft. -MSL
S. Miller
03-12-11
CAVING>
Graphic Depiction
N-Value
Description
ELEVATION:
LOGGED BY:
DATE:
Sample
Type
46
PROJECT NO.:
Groundwater
DEPTH TO - WATER> INITIAL:
Graphic
Elevation
(ft-MSL)
Depth
(feet)
TEST BORING
RECORD
B-1
PROJECT: King Springs Elementary School
CLIENT: Cobb County School District
PROJECT LOCATION: 1041 Reed Road
LOCATION: Smyrna, Cobb County, Georgia
DRILLER: Sunrise Drilling Company
DRILLING METHOD: Hollow Stem Auger
BLOW COUNT
NATURAL MOISTURE
PLASTIC LIMIT
LIQUID LIMIT
10
20 30 40 60 80
18
20
5
21
1005
18
10
1000
28
15
995
28
20
990
Very hard to hard gray tan brown fine sandy very micaceous SILT
63
25
985
40
30
980
35
36
Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate.
Page 1 of 2
This information pertains only to this boring and should not be interpreted as being indicative of the site.
AFTER 24 HOURS:
N/O
2011019
1013 ft. -MSL
S. Miller
03-12-11
CAVING>
Graphic Depiction
N-Value
Description
ELEVATION:
LOGGED BY:
DATE:
Sample
Type
46
PROJECT NO.:
Groundwater
DEPTH TO - WATER> INITIAL:
Graphic
Elevation
(ft-MSL)
Depth
(feet)
TEST BORING
RECORD
B-1
PROJECT: King Springs Elementary School
CLIENT: Cobb County School District
PROJECT LOCATION: 1041 Reed Road
LOCATION: Smyrna, Cobb County, Georgia
DRILLER: Sunrise Drilling Company
DRILLING METHOD: Hollow Stem Auger
975
BLOW COUNT
NATURAL MOISTURE
PLASTIC LIMIT
LIQUID LIMIT
10
20 30 40 60 80
63
40
970
45
PARTIALLY WEATHERED ROCK: Sampled as very hard gray
brown fine sandy very micaceous SILT
100/12"
965
100/10"
50
Boring Terminated at 50 ft.
960
55
955
60
950
65
945
70
940
75
Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate.
Page 2 of 2
AFTER 24 HOURS:
This information pertains only to this boring and should not be interpreted as being indicative of the site.
0
ASPHALT: 2 inches
GRAVEL: 3 inches
FILL: Stiff to very stiff red orange brown fine sandy SILT
N/O
2011019
1013 ft. -MSL
S. Miller
03-12-11
CAVING>
Graphic Depiction
N-Value
Description
ELEVATION:
LOGGED BY:
DATE:
Sample
Type
N/E
PROJECT NO.:
Groundwater
DEPTH TO - WATER> INITIAL:
Graphic
Elevation
(ft-MSL)
Depth
(feet)
TEST BORING
RECORD
B-2
PROJECT: King Springs Elementary School
CLIENT: Cobb County School District
PROJECT LOCATION: 1041 Reed Road
LOCATION: Smyrna, Cobb County, Georgia
DRILLER: Sunrise Drilling Company
DRILLING METHOD: Hollow Stem Auger
BLOW COUNT
NATURAL MOISTURE
PLASTIC LIMIT
LIQUID LIMIT
10
20 30 40 60 80
11
1010
21
5
16
1005
11
10
RESIDUUM: Very stiff red orange brown fine sandy SILT with
rock fragments
1000
21
15
995
19
20
Boring Terminated at 20 ft.
990
25
985
30
980
35
Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate.
Page 1 of 1
AFTER 24 HOURS:
This information pertains only to this boring and should not be interpreted as being indicative of the site.
0
ASPHALT: 2 inches
GRAVEL: 3 inches
FILL: Stiff red brown fine sandy SILT with rock fragments
N/O
2011019
1014 ft. -MSL
S. Miller
03-12-11
CAVING>
Graphic Depiction
N-Value
Description
ELEVATION:
LOGGED BY:
DATE:
Sample
Type
38
PROJECT NO.:
Groundwater
DEPTH TO - WATER> INITIAL:
Graphic
Elevation
(ft-MSL)
Depth
(feet)
TEST BORING
RECORD
B-3
PROJECT: King Springs Elementary School
CLIENT: Cobb County School District
PROJECT LOCATION: 1041 Reed Road
LOCATION: Smyrna, Cobb County, Georgia
DRILLER: Sunrise Drilling Company
DRILLING METHOD: Hollow Stem Auger
BLOW COUNT
NATURAL MOISTURE
PLASTIC LIMIT
LIQUID LIMIT
10
20 30 40 60 80
9
1010
11
5
RESIDUUM: Stiff to very stiff red orange brown fine sandy SILT
with rock fragments
14
1005
23
10
1000
13
15
995
17
20
990
25
25
985
30
PARTIALLY WEATHERED ROCK: Sampled as very hard
brown green fine sandy SILT with rock fragments
100/10"
980
35
100/8"
Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate.
Page 1 of 2
This information pertains only to this boring and should not be interpreted as being indicative of the site.
ELEVATION:
LOGGED BY:
DATE:
AFTER 24 HOURS:
N/O
2011019
1014 ft. -MSL
S. Miller
03-12-11
CAVING>
N-Value
Graphic Depiction
Sample
Type
Description
38
PROJECT NO.:
Groundwater
DEPTH TO - WATER> INITIAL:
Graphic
Elevation
(ft-MSL)
Depth
(feet)
TEST BORING
RECORD
B-3
PROJECT: King Springs Elementary School
CLIENT: Cobb County School District
PROJECT LOCATION: 1041 Reed Road
LOCATION: Smyrna, Cobb County, Georgia
DRILLER: Sunrise Drilling Company
DRILLING METHOD: Hollow Stem Auger
BLOW COUNT
NATURAL MOISTURE
PLASTIC LIMIT
LIQUID LIMIT
10
20 30 40 60 80
975
100/6"
40
970
100/12"
45
965
100/0"
50
Boring Terminated at 50 ft.
960
55
955
60
950
65
945
70
940
75
Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate.
Page 2 of 2
AFTER 24 HOURS:
This information pertains only to this boring and should not be interpreted as being indicative of the site.
0
ASPHALT: 2 inches
GRAVEL: 1 inch
RESIDUUM: Very stiff to hard brown fine sandy micaceous SILT
N/O
2011019
1014 ft. -MSL
S. Miller
03-12-11
CAVING>
Graphic Depiction
N-Value
Description
ELEVATION:
LOGGED BY:
DATE:
Sample
Type
N/E
PROJECT NO.:
Groundwater
DEPTH TO - WATER> INITIAL:
Graphic
Elevation
(ft-MSL)
Depth
(feet)
TEST BORING
RECORD
B-4
PROJECT: King Springs Elementary School
CLIENT: Cobb County School District
PROJECT LOCATION: 1041 Reed Road
LOCATION: Smyrna, Cobb County, Georgia
DRILLER: Sunrise Drilling Company
DRILLING METHOD: Hollow Stem Auger
BLOW COUNT
NATURAL MOISTURE
PLASTIC LIMIT
LIQUID LIMIT
10
20 30 40 60 80
21
1010
25
5
21
1005
29
10
1000
21
15
995
33
20
Boring Terminated at 20 ft.
990
25
985
30
980
35
Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate.
Page 1 of 1
APPENDIX C
QUALIFICATIONS OF
RECOMMENDATIONS
QUALIFICATIONS OF RECOMMENDATIONS
The findings, conclusions and recommendations presented in this report represent our
professional opinions concerning subsurface conditions at the site. The opinions presented are
relative to the dates of our site work and should not be relied on to represent conditions at later
dates or at locations not explored. The opinions included herein are based on information
provided to us, the data obtained at specific locations during the study and our past experience. If
additional information becomes available that might impact our geotechnical opinions, it will be
necessary for NOVA to review the information, reassess the potential concerns, and re-evaluate
our conclusions and recommendations.
Regardless of the thoroughness of a geotechnical exploration, there is the possibility that
conditions between borings will differ from those encountered at specific boring locations, that
conditions are not as anticipated by the designers and/or the contractors, or that either natural
events or the construction process have altered the subsurface conditions. These variations are an
inherent risk associated with subsurface conditions in this region and the approximate methods
used to obtain the data. These variations may not be apparent until construction.
The professional opinions presented in this geotechnical report are not final. Field observations and
foundation installation monitoring by the geotechnical engineer, as well as soil density testing and
other quality assurance functions associated with site earthwork and foundation construction, are
an extension of this report. Therefore, NOVA should be retained by the owner to observe all
earthwork and foundation construction to document that the conditions anticipated in this study
actually exist, and to finalize or amend our conclusions and recommendations. NOVA is not
responsible or liable for the conclusions and recommendations presented in this report if NOVA
does not perform these observation and testing services.
This report is intended for the sole use of Cobb County School District only. The scope of work
performed during this study was developed for purposes specifically intended by Cobb County
School District and may not satisfy other users requirements. Use of this report or the findings,
conclusions or recommendations by others will be at the sole risk of the user. NOVA is not
responsible or liable for the interpretation by others of the data in this report, nor their conclusions,
recommendations or opinions.
Our professional services have been performed, our findings obtained, our conclusions derived
and our recommendations prepared in accordance with generally accepted geotechnical
engineering principles and practices in the State of Georgia. This warranty is in lieu of all other
statements or warranties, either expressed or implied.
MARCH 16, 2010
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 00901 - 1
ADDENDUM NO. 1
SECTION 00901
ADDENDUM NO. 1
PART 1 - GENERAL
1.1
GENERAL REQUIREMENTS
A.
General: For the purpose of proposal, the Bidding and Contract Documents for the above project
are changed as described herein. The changes shall take precedence, and all other provisions of
the Bidding and Contract Documents shall remain in force.
B.
Notation on Bid Form: Failure to note receipt of this Addendum on a submitted Bid Form in
accordance with the Bidding Documents may be cause for rejection of any Bid so submitted.
PART 2 - DRAWING CHANGES
2.1
A.
REVISED DRAWINGS
The following Drawings have been revised, bear revision date MARCH 16, 2011, are issued with this
Addendum, and are deemed a part thereof. The changes to be made are identified on each
Drawing.
Number
Title
See attached list of drawings.
PART 3 - SPECIFICATION CHANGES
3.1
A.
NEW SPECIFICATIONS
The following additional Specification sections dated MARCH 16, 2011 are issued with this
Addendum, and are deemed a part thereof. In addition, these sections are added to the Table of
Contents within the Project Manual.
Section Number
-------00901
07415
07420
10152
10531
Title
Report of Subsurface Exploration and
Geotechnical Engineering Evaluation
Addendum No. 1
Metal Cladding Systems
Composite Panels
Hospital Cubical Curtains and Tracks
Aluminum Canopy Structures
SECTION 00901 - 2
ADDENDUM NO. 1
3.2
A.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
REVISED SPECIFICATIONS
The following Specification sections have been revised, bear revision date MARCH 16, 2011, are
issued with this Addendum, and are deemed a part thereof. The changes to be made are identified
on the revised pages of each section, attached hereinafter, unless noted otherwise.
Section Number/Page
-------00020
00210
-------01010
01101
04210
06400
15800
15840
Title
Table of Contents
Advertisement Invitation For Bids
Specific Date Construction Schedule
Floor Phasing Plan of King Springs Elementary School
Summary of Work
Alternates
Brick
Architectural Woodwork
Air Distribution Devices
Ductwork
END OF SECTION
Drwg Revision LOG D.4
Addendum Drawing Revision Log:
Changes included prior to signed Contract for Construction
Draw Rev LOG
Project Name: King Springs Elementary School
Project Name:
Project Number:
Principal In Charge:
Project Architect:
Contract Administration Lead:
Date of Permit / Bid Set:
Date of Notice to Proceed:
King Springs Elementary
20100358
Jerome M. Cooper
William Collier
2/24/2011
XX/XX/XX
Project Number: 20100358
Revised, Deleted or New
Issued as
COVER SHEET
Revised
Addendum 1
GENERAL INFORMATION & SHEET INDEX
Revised
Addendum 1
SITE DEMOLITION PLAN
Revised
Addendum 1
SITE LAYOUT & STAKEOUT PLAN
Revised
Addendum 1
SITE GRADING, DRAINAGE & UTILITY PLAN
Revised
Addendum 1
03/16/11
DEMOLITION PLANS
Revised
Addendum 1
03/16/11
ENLARGED FLOOR PLAN – ADMINISTRATION ADDITION
Revised
Addendum 1
A2.2
03/16/11
Addendum 1
03/16/11
ENLARGED FLOOR PLAN – RENOVATED ADMINISTRATION
ENLARGED FLOOR PLAN – RESTROOMS
Revised
A2.6
Revised
Addendum 1
A2.7
03/16/11
RESERVED
Revised
Addendum 1
A2.8
03/16/11
PARTIAL LOWER ROOF PLAN
Revised
Addendum 1
A2.9
03/16/11
PARTIAL UPPER ROOF PLAN
Revised
Addendum 1
Drawing #
Date
G0.0
03/16/11
G0.2
03/16/11
C2.0
03/16/11
C3.0
03/16/11
C4.0
03/16/11
A1.2
A2.1
Title
A3.1
03/16/11
FINISH FLOOR PLAN – ADMINISTRATION ADDITION
Revised
Addendum 1
A3.2
03/16/11
FINISH FLOOR PLAN – RENOVATED ADMINISTRATION
Revised
Addendum 1
Addendum 1
A3.3
03/16/11
FINISH FLOOR PLAN – CLASSROOM WING SOUTH
Revised
A3.4
03/16/11
FINISH FLOOR PLAN – MEDIA CENTER AND CAFETERIA
Revised
Addendum 1
A3.5
03/16/11
FINISH FLOOR PLAN – CLASSROOM WING NORTH
Revised
Addendum 1
A4.1
03/16/11
EXTERIOR BUILDING ELEVATIONS
Revised
Addendum 1
A4.2
03/16/11
EXTERIOR BUILDING ELEVATIONS
Revised
Addendum 1
A4.3
03/16/11
BUILDING SECTIONS
Revised
Addendum 1
A5.1
03/16/11
BUILDING SECTIONS
Revised
Addendum 1
A5.3
03/16/11
INTERIOR ELEVATIONS
Revised
Addendum 1
A6.1
03/16/11
SECTION DETAILS
Revised
Addendum 1
A9.1
03/16/11
PARTITION SCHEDULE, NOTES, AND DETAILS
Revised
Addendum 1
A11.1
03/16/11
ENLARGED REFLECTED CEILING PLANS
Revised
Addendum 1
A11.2
03/16/11
ENLARGED REFLECTED CEILING PLANS
Revised
Addendum 1
S2.1
03/16/11
FOUNDATION AND FRAMING PLANS
Revised
Addendum 1
S3.1
03/16/11
SECTIONS
Revised
Addendum 1
S4.2
03/16/11
TYPICAL DETAILS
Revised
Addendum 1
M1.0
03/16/11
DEMOLITION PLAN-MECHANICAL
Revised
Addendum 1
M2.0
03/16/11
REFERENCE PLAN –MECHANICAL
Revised
Addendum 1
M2.1
03/16/11
ADMINISTRATION ADDITION FLOOR PLAN-MECHANICAL
Revised
Addendum 1
M2.2
M2.3
03/16/11
03/16/11
ADMINISTRATION RENOVATION FLOOR PLAN-MECHANICAL
NORTH WING PARTIAL FLOOR PLAN-MECHANICAL
Revised
Revised
Addendum 1
Addendum 1
M2.4
03/16/11
ROOF PLAN-MECHANICAL
Revised
Addendum 1
M7.1
03/16/11
LEGEND, NOTES, SCHEDULES & ABBREVIATIONSMECHANICAL
Revised
Addendum 1
P1.0
03/16/11
DEMOLITION PLAN-PLUMBING
Revised
Addendum 1
P2.0
03/16/11
REFERENCE PLAN-PLUMBING
Revised
Addendum 1
P2.2
03/16/11
ADMINISTRATION RENOVATION FLOOR PLAN-PLUMBING
Revised
Addendum 1
P2.5
03/16/11
ROOF PLAN-PLUMBING
Revised
Addendum 1
P4.1
03/16/11
RESTROOMS PARTIAL FLOOR PLANS-PLUMBING
Revised
Addendum 1
E0.1
03/16/11
ELECTRICAL LEGEND, NOTES & SCHEDULES
Revised
Addendum 1
E1.1
03/16/11
ADMINISTRATION ADDITION FLOOR PLAN-ELECTRICAL
Revised
Addendum 1
E1.2
03/16/11
ADMINISTRATION RENOVATION FLOOR PLAN-ELECTRICAL
Revised
Addendum 1
E1.5
03/16/11
NORTH WING PARTIAL FLOOR PLAN-ELECTRICAL
Revised
Addendum 1
E2.1
03/16/11
ADMINISTRATION ADDITION FLOOR PLAN-LIGHTING
Revised
Addendum 1
E2.2
03/16/11
ADMINISTRATION RENOVATION FLOOR PLAN-LIGHTING
Revised
Addendum 1
E/Administrative/Draft CA Forms/Final/revised-dwg_00901-a1-d-4_addendums_log.xls
Date Printed: 3/21/2011
Page #1
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 01010 - 1
SUMMARY OF WORK
SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
1.1
A.
1.2
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General Conditions, other sections of
Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project
Manual apply to the work specified in this Section.
WORK COVERED BY CONTRACT DOCUMENTS
A.
Scope: The Contractor shall supply materials, labor, tools, plant, supplies, equipment,
transportation, superintendence, temporary construction of every nature, and other services and
facilities necessary to complete the construction of the described facilities, including, but not
limited to, incidental work described in the Contract Documents.
B.
Work Includes: Work covers demolition, renovation, construction and maintenance of King Springs
Elementary School, located in Smyrna, Georgia.
C.
Hazardous Materials: Do not incorporate any products or materials into the work that contain
asbestos or other hazardous substances, as such are defined under the federal Toxic Substance
Control Act, 15 U.S.C. § 2601 et seq., and the rules and regulations promulgated pursuant thereto,
and more specifically 40 C.F.R. § 763.103 (c) (1988).
1.3
CONTRACTS
A.
Construct work under a single contract.
1.4
WORK UNDER OTHER CONTRACTS
A.
1.5
The following items of work will be furnished and installed by the Owner:
1. Asbestos abatement.
2. Audio/Visual
3. Furniture and furnishings.
OWNER-FURNISHED PRODUCTS
A.
Products Furnished by the Owner:
1. Relocate existing vault from media center corridor to Records / Vault Room..
2. Relocate existing PA (public address) main unit from current reception to new reception.
3. Relocate existing knox box to location shown on the Drawings.
4. Relocate existing mailboxes to Work Room No. 218 as shown on the Drawings.
B.
Owner's Duties:
1. Schedule delivery date with supplier in accordance with Construction Progress Schedule.
2. Make specified submittals to the Contractor.
3. Submit claims for transportation damages.
4. Arrange warranties.
SECTION 01010 - 2
SUMMARY OF WORK
C.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Contractor's Duties:
1. Designate required submittal date for each product in the Submittals Schedule.
2. Coordinate submittals with work of adjacent trades and submit them to the Architect.
3. Designate required delivery date for each product in the Construction Progress Schedule.
4. Promptly inspect delivered products, report damaged or defective items to the Owner.
5. Handle at site, including, but not limited to, unloading, uncrating, and storage.
6. Protect from exposure to elements and from damage.
7. Repair or replace damaged items.
8. Install, connect, and finish products.
1.6 SITE INVESTIGATION DATA
A.
Investigation Report:
1. General: Soil and subsurface investigations were conducted at the site, the results of which
are to be found in a report dated MARCH 17, 2011 and issued by:
Name:
Address:
City, State, Zip:
Telephone:
Fax:
2.
3.
B.
1.7
A.
NOVA Engineering and Environmental
3640 Kennesaw North Industrial Pkwy, Suite E
Kennesaw, GA 30144
770-425-0777
770-425-1113
Copies: The report is included in the project manual.
Status: The soil and subsurface investigation report is not a part of the Contract Documents.
The bidder or Contractor who obtains a copy of the report releases the Owner and the Architect
from any responsibility or obligation as to its accuracy or completeness or for any additional
compensation for work performed under the Contract due to assumptions based on use of such
furnished information.
Interpretation: Data concerning subsurface materials or conditions which is based upon soundings,
test pits, or test borings, has been obtained by the Owner for the Architect's use in designing the
Project. Its accuracy or completeness is not guaranteed by the Owner or the Architect. The
Contractor shall assume all responsibility in excavating for this Project and shall not rely on
subsurface information obtained from the Architect, or indirectly from the Owner. Bidders or the
Contractor shall make their own investigation of existing subsurface conditions; neither the Owner or
the Architect will be responsible in any way for additional compensation for excavation work
performed under the Contract due to the Contractor's assumptions based on soil investigation data
prepared solely for the Architect's use. The Contractor shall notify the Owner and the Architect in
writing immediately should any discrepancy be discovered between the conditions at the site and
information contained in the report.
CONTRACTOR'S USE OF PREMISES
The Contractor shall confine operations at the site to areas permitted by law, ordinances, permits,
and the Contract Documents and shall not unreasonably encumber the site with materials and
equipment.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
1.8
A.
1.9
SECTION 01010 - 3
SUMMARY OF WORK
OCCUPANCY REQUIREMENTS
Partial Owner Occupancy: The Owner will occupy the premises during entire construction period,
with the exception of areas under construction. Cooperate with the Owner during construction
operations to minimize conflicts and facilitate Owner usage. Perform the work so as not to interfere
with Owner's operations. Maintain existing exits, unless otherwise indicated. Make available for the
Owner's use such building services as heating, ventilating, cooling, water, lighting, and telephone;
and complete as soon as practicable, equipment required to furnish such services which are not
ready for operation and use.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
Do not close or obstruct walkways, corridors, or other occupied or used facilities without written
permission from the Owner and authorities having jurisdiction.
2. Provide not less than 72 hours' notice to the Owner of activities that will affect the Owner's
operations.
WORK RESTRICTIONS
A.
On-Site Work Hours: Work shall be generally performed during normal business working hours,
Monday through Friday, except as otherwise agreed to by the Owner.
1. Hours for Noisy Activity: Restricted per local ordinance.
B.
Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by the Owner or
others unless permitted under the following conditions and then only after arranging to provide
temporary utility services according to requirements indicated:
1. Notify the Owner not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without the Owner's written permission.
PART 2 - PRODUCTS
(Not Applicable)
PART 3 - EXECUTION
(Not Applicable)
END OF SECTION
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
01101-1
ALTERNATES
SECTION 01101
ALTERNATES
PART ONE-GENERAL
1.01
BIDDING REQUIRMENTS
CCSD may use deductive alternates to reduce the base bid on state- funded projects using the
design/bid/build construction delivery method; however, the deductive alternates shall be bid
prioritized and exercised in numerical sequence as used in the bid documents. When the CCSD
determines that deductive alternatives must be selected, all bids will be recalculated removing the
deductive alternates to be taken. The low bid shall then be determined on the base bid less any
deductive alternates.
The plans and specifications shall indicate if the project will be awarded by base bid or base bid plus
selected alternates. Additive alternates may be exercised in any order. If the plans and specifications
state that the contract will be awarded on base bid, then additive alternates are considered only after
the low base bidder has been declared. If the plans and specifications state that the project will be
awarded by base bid plus additive alternates, all bids will be recalculated adding the additive
alternates to be taken. The low bid shall then be determined on the base bid plus the selected additive
alternates.
1.02
DESCRIPTION:
A.
An alternate is an amount proposed by bidders, and stated on the Bid Form, for certain
work defined in the Bidding Requirements that may be added to or deducted from the
Base Bid amount if the Owner decides to accept a corresponding change in either the
amount of construction to be completed, or in the products, materials, equipment,
systems, or installation methods described in the Contract Documents.
B.
The cost or credit for each alternate is the net addition to or deduction from the Contract
Sum to incorporate the Alternate into the Work. No other adjustments are made to the
Contract Sum.
C.
Related Work Described Elsewhere:
1.
Materials and methods to be used in the Base Bid and in the Alternates have
been described on the Drawings and in pertinent Sections of these Specifications.
2.
Method for stating the proposed Contract Sum is described in the bid form.
1.03
All alternates described in this Section are required to be reflected on the Bid Form as submitted
by Bidders. Do not submit Alternates other than as described in this Section.
1.04
If the Owner elects to proceed on the basis of one or more of the Alternates, the Contractor shall
make all modifications to the work required in furnishing and installing the selected Alternates to
the approval of the Architect and at no additional cost to the Owner other than as proposed on the
Bid Form.
1.05
All Alternates must be executed with an appropriate response. A "blank space", or a "No Bid"
statement is inappropriate. The space must include a "Specific Sum" or a "No Change in Price"
statement. Failure to provide this information may be cause for rejection of the bid at the Owner's
discretion.
1.06
Proposal amounts for Alternates shall remain open for acceptance by the Owner for (60) sixty
days after the Notice of Award date.
1.07
If liquidated damages are deleted by Alternate, Addendum or Change Order, completion time
remains unchanged and time is still the essence of the contract and in lieu of liquidated damages
the Owner retains the right to pursue the collection of actual damages for delayed completion,
pursuant to the provisions of the contract documents, under existing state statutes and/or law.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
01101-2
ALTERNATES
PART TWO - SCHEDULE OF ALTERNATES:
ALTERNATE NO. 1: The deletion of liquidated damages: (See Section 00820)
ALTERMATE NO. 2: Provide METAL CLADDING SYSTEM as defined in Section 07415 in lieu of
COMPOSITE PANELS as defined in Section 07420.
ALTERMATE NO. 3: Delete the demolition and renovation of the existing Counselor's office to
new Classroom 125, including new RTU & associated ductwork, electrical, lighting, flooring and
ceiling.
ALTERMATE NO. 4: Delete 2 foot wide cantilevered metal panel "eyebrow" at new administration
wing and accent brick color below. Replace with standard running bond brick.
END OF SECTION
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 04210 - 1
BRICK
SECTION 04210
BRICK
PART 1 - GENERAL
1.1
A.
1.2
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General Conditions,
Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project
Manual apply to the work specified in this Section.
SUMMARY
A.
Scope: Provide labor, material, equipment, related services, and supervision required, including, but
not limited to, manufacturing, fabrication, erection, and installation for brick as required for the
complete performance of the work, and as shown on the Drawings and as herein specified.
B.
Section Includes: The work specified in this Section includes, but shall not be limited to, clay unit
masonry in the form of brick.
1.3
REFERENCES
A.
The publications listed below form a part of this Specification to the extent referenced. The
publications are referred to in the text by the basic designation only.
B.
The edition/revision of the referenced publications shall be the latest date as of the date of the
Contract Documents, unless otherwise specified.
C.
ASTM (ASTM):
1. ASTM C 67, "Standard Test Methods of Sampling and Testing Brick and Structural Clay
Tile."
2. ASTM C 216, "Standard Specification for Facing Brick (Solid Masonry Units Made from Clay
or Shale)."
1.4
SUBMITTALS
A.
General: See Section 01300 - SUBMITTALS.
1. See Section 04200 - UNIT MASONRY.
B.
Product Data: Submit product data showing material proposed. Submit sufficient information to
determine compliance with the Drawings and Specifications. Product data shall include, but shall not
be limited to, manufacturer's recommended cleaning agent and application procedure.
C.
Shop Drawings: Submit shop drawings for each product and accessory required. Include
information not fully detailed in manufacturer’s standard product data.
D.
Samples:
1. Submit samples for verification purposes. Submit two sets of samples of each type of exposed
brick specified. Include in each set the full range of exposed color and texture to be expected in
the completed work.
SECTION 04210 - 2
BRICK
E.
1.5
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Qualification Data: Submit qualification data for firms and persons specified in Quality Assurance
Article to demonstrate their capabilities and experience. Include lists of completed projects with
project names and addresses, names of architects and owners, and other information specified.
QUALITY ASSURANCE
A.
Qualifications:
1. Manufacturer Qualifications: Manufacturer shall be a firm engaged in the manufacture of
brick of types and sizes required, and whose products have been in satisfactory use in similar
service for a minimum of five years.
2. Installer Qualifications: Installer shall be a firm that shall have a minimum of five years of
successful installation experience with projects utilizing brick similar in type and scope to that
required for this Project.
B.
Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances,
and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary
approvals from such authorities.
C.
Mock-Ups: See Section 04200 - UNIT MASONRY.
D.
Pre-Installation Conference: See Section 04200 - UNIT MASONRY.
E.
Single Source Responsibility: Obtain exposed brick units of a uniform texture and color, or a
uniform blend within the ranges accepted for these characteristics, from one source and by a
single manufacturer for each different product required.
1.6
A.
1.7
A.
DELIVERY, STORAGE, AND HANDLING
Store brick on elevated platforms, under cover, and in a dry location to prevent their deterioration or
damage due to moisture, temperature changes, contaminants, corrosion, or other causes. If units
become wet, do not install until they are in an air-dried condition.
PROJECT CONDITIONS
See Section 04200 - UNIT MASONRY.
PART 2 - PRODUCTS
2.1
A.
MANUFACTURERS
Manufacturer: Subject to compliance with requirements, provide products of one of the following:
1. Acme Brick Co.
2. Cherokee Sanford Group, Inc.
3. D'Hanis Brick and Tile Co.
4. Henderson Brick.
5. Henry Brick.
6. Interstate Brick Div., Pacific Coast Building Products.
7. Jenkins Brick Co.
8. Lee Brick Co.
9. Merry Brothers Brick & Tile Co.
10. Palmetto Brick.
11. Robinson Brick Co.
12. Summit Brick & Tile Co.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 04210 - 3
BRICK
13. Victor Cushwa & Sons, Inc.
B.
2.2
Basis of Design: Items specified are to establish a standard of quality for design, function,
materials, and appearance. Equivalent products by listed manufacturers are acceptable. The
Architect will be the sole judge of the basis of what is equivalent.
BRICK MATERIALS
A.
General: Provide shapes indicated and as follows for each form of brick required. Provide units
without cores or frogs and with exposed surfaces finished for ends of sills and caps and for similar
applications that would otherwise expose unfinished brick surfaces.
B.
Special Shapes: Provide special shapes for applications requiring brick of size, form, color, and
texture on exposed surfaces that cannot be produced by sawing.
1. Provide special shapes for applications where stretcher units cannot accommodate special
conditions, including, but not limited to, those at corners, movement joints, bond beams,
sashes, and lintels.
2. Provide special shapes for applications where shapes produced by sawing would result in
sawed surfaces being exposed to view.
C.
Face Brick: ASTM C 216 and as follows:
1. Grade: Grade SW.
2. Unit Compressive Strength: 3000 psi.
3. Initial Rate of Absorption: Between 5 grams per 30 square inches and 20 grams per 30
square inches per minute when tested per ASTM C 67.
4. Surface Coloring: Brick with surface coloring, other than flashed or sand-finished brick,
shall withstand 50 cycles of freezing and thawing per ASTM C 67 with no observable
difference in the applied finish when viewed from 10 feet.
5. Type: Type FBS.
6. Size: Bricks manufactured to the following actual dimensions within tolerances specified in
ASTM C 216:
a. Modular: 3-1/2 inches to 3-5/8 inches thick by 2-1/4 inches high by 7-1/2 inches to
7-5/8 inches long.
7. Application: Use where brick is exposed, unless otherwise indicated.
8. Match Existing: Where shown to match existing, provide face brick matching color, texture,
and size of existing adjacent brickwork. (Auditorium wall - North wall of bus corridor.)
9. Color and Texture: Match the Architect's samples.
10. Color and Texture: Medium brown, wirecut.
11. Color and Texture: Full-range red, sand-molded.
12. Color and Texture: Gray, velour.
13. Basis of Design:
a. Field Brick:
1) "No. 204F", Plant # 4, Lee Brick Co.
2) "Range Alahambra, Montgomery Plant", Jenkins Brick Co.
3) "FR Diplomat", Henry Brick.
b. Accent Brick: Continuous soldier course below metal panel "eyebrow".
1) "Whitestone", Palmetto Brick
2.3
A.
SOURCE QUALITY CONTROL
General: The Owner will employ and pay a qualified independent inspecting and testing agency
to perform the following testing for source quality control. Retesting of materials failing to meet
specified requirements shall be done at the Contractor's expense.
SECTION 04210 - 4
BRICK
1.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Brick Tests: For each type and grade of brick indicated, units will be tested per ASTM C 67
except five bricks will be selected at random for each 100,000 units or fraction thereof
installed.
PART 3 - EXECUTION
3.1
A.
3.2
A.
3.3
A.
3.4
A.
3.5
A.
EXAMINATION
Verification of Conditions: Examine areas and conditions under which the work is to be installed,
and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions
detrimental to the proper and timely completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected.
1. Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by
the Installer.
PREPARATION
See Section 04200 - UNIT MASONRY.
INSTALLATION
See Section 04200 - UNIT MASONRY.
ADJUSTING AND CLEANING
See Section 04200 - UNIT MASONRY.
PROTECTION
Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall
ensure that the brick shall be without damage at time of Substantial Completion.
END OF SECTION
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 06400 - 1
ARCHITECTURAL WOODWORK
SECTION 06400
ARCHITECTURAL WOODWORK
PART 1 - GENERAL
1.1
A.
1.2
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General Conditions,
Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project
Manual apply to the work specified in this Section.
SUMMARY
A.
Scope: Provide labor, material, equipment, related services, and supervision required, including, but
not limited to, manufacturing, fabrication, erection, and installation for architectural woodwork as
required for the complete performance of the work, and as shown on the Drawings and as herein
specified.
B.
Section Includes: The work specified in this Section includes, but shall not be limited to, the
following:
1. Laminate-clad cabinets.
2. Laminate-clad countertops.
1.3
REFERENCES
A.
The publications listed below form a part of this Specification to the extent referenced. The
publications are referred to in the text by the basic designation only.
B.
The edition/revision of the referenced publications shall be the latest date as of the date of the
Contract Documents, unless otherwise specified.
C.
American National Standards Institute (ANSI):
1. ANSI A208.2, "Medium Density Fiberboard for Interior Use.”
D.
American Society of Mechanical Engineers (ASME):
1. ANSI/ASME B18.6.1, "Wood Screws (Inch Series)” (copyrighted by ASME, ANSI approved).
E.
American Wood Preservers Association (AWPA):
1. AWPA C20, "Structural Lumber, Fire-Retardant Pressure Treatment."
F.
Architectural Woodwork Institute (AWI):
1. AWI AWQSI, "Architectural Woodwork Quality Standards Illustrated."
G.
ASTM (ASTM):
1. ASTM C 1048, "Standard Specification for Heat-Treated Flat Glass - Kind HS, Kind FT Coated
and Uncoated Glass."
2. ASTM E 84, "Standard Test Method for Surface Burning Characteristics of Building Materials."
3. ASTM F 1667, "Standard Specification for Driven Fasteners: Nails, Spikes, and Staples.”
SECTION 06400 - 2
ARCHITECTURAL WOODWORK
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
H.
Builders Hardware Manufacturers Association, Inc. (BHMA):
1. ANSI/BHMA A156.9, "Cabinet Hardware" (copyrighted by BHMA, ANSI approved).
2. ANSI/BHMA A156.18, "Materials and Finishes" (copyrighted by BHMA, ANSI approved).
I.
Glass Association of North America (GANA):
1. GANA GM, "Glazing Manual.”
J.
Green Seal (GS):
1. GS-37, “Industrial & Institutional Cleaners.”
K.
Hardwood Plywood and Veneer Association (HPVA):
1. ANSI/HPVA HP-1, "American National Standard for Hardwood and Decorative Plywood"
(copyrighted by HPVA, ANSI approved).
L.
National Electrical Manufacturers Association (NEMA):
1. NEMA LD 3, "High Pressure Decorative Laminate."
M.
National Particleboard Association (NPA):
1. NPA 9, "Voluntary Standard for Formaldehyde Emission From Medium Density Fiberboard
(MDF)."
N.
South Coast Air Quality Management District (SCAQMD):
1. SCAQMD Rule #1168, “Adhesive and Sealant Applications,” including most recent
amendments.
O.
U.S. Department of Commerce, National Institute of Standards and Technology (DOC PS):
1. DOC PS 1, "U.S. Product Standard for Construction and Industrial Plywood."
1.2
A.
1.3
DEFINITIONS
Architectural woodwork includes, but shall not be limited to, wood furring, blocking, shims, hanging
strips, etc., as required for installing architectural woodwork items unless concealed within other
construction prior to architectural woodwork installation.
SUBMITTALS
A.
General: See Section 01300 - SUBMITTALS.
B.
Product Data: Submit product data showing material proposed. Submit sufficient information to
determine compliance with the Drawings and Specifications. Submit product data for each type of
product and process specified and incorporated into items of architectural woodwork during
fabrication, finishing, and installation.
C.
Shop Drawings: Submit shop drawings for each product and accessory required. Include
information not fully detailed in manufacturer’s standard product data, including, but not limited to,
location of each item in dimensioned plans and elevations, large scale details, attachment devices,
and other components.
D.
Samples:
1. Submit samples for initial color selection. Submit samples of each specified finish. Submit
samples in form of manufacturer’s color charts showing full range of colors and finishes
available. Where finishes involve normal color variations, include samples showing the full,
range of variations expected.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
2.
SECTION 06400 - 3
ARCHITECTURAL WOODWORK
Submit samples for verification purposes. Additional samples may be required to show
fabrication techniques and workmanship. Submit samples as follows:
a. Laminate-clad products, 8 inches by 10 inches, for each type, color, pattern, and surface
finish.
b. Exposed cabinet hardware, one unit of each type and finish.
E.
Quality Control Submittals:
1. Fire Retardant Treatment Data: Submit fire retardant treatment data for material treated to
reduce combustibility. Include certification by treating plant that treated materials comply with
requirements.
2. Qualification Data: Submit qualification data for firms and persons specified in Quality
Assurance Article to demonstrate their capabilities and experience. Include lists of completed
projects with project names and addresses, names of architects and owners, and other
information specified.
F.
Low-Emitting Materials: Submit certification by the manufacturer confirming that products (i.e.,
adhesives, sealants, paints, coatings, etc.) meet or exceed the volatile organic compound (VOC)
limits set by specific agencies or other requirements as outlined in Section 01110 - LOW-EMITTING
MATERIALS. VOC limits shall be clearly stated in the submittal.
G.
Maintenance Data: Submit maintenance data for architectural woodwork to include in operation
and maintenance manuals specified in Division 1 - GENERAL REQUIREMENTS.
1.4
QUALITY ASSURANCE
A.
Qualifications:
1. Fabricator Qualifications: Fabricator shall be a firm engaged in the fabrication of architectural
woodwork of types and sizes required, whose products have been in satisfactory use in similar
service for a minimum of five years, and with sufficient capacity to produce required units
without delaying the work.
a. Fabricator shall assume undivided responsibility for fabricating and installing architectural
woodwork specified in this Section.
B.
Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances,
and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary
approvals from such authorities.
C.
Quality Standard: Comply with AWI AWQSI for grades of architectural woodwork, construction,
finishes, and other requirements. Provide AWI Certification labels or Certificates of Compliance
indicating that woodwork meets requirements of grades specified.
D.
Surface Burning Characteristics: Provide materials with the following characteristics as
determined by testing identical products per ASTM test method indicated below, by Underwriters
Laboratories, Inc. (UL), Intertek Testing Services (ITS), or another inspecting and testing agency
acceptable to authorities having jurisdiction.
1. Surface burning characteristics shall not exceeding values indicated below, tested per
ASTM E 84.
a. Flame Spread: 75.
b. Smoke Developed: 450.
2. Identify fire retardant-treated material with appropriate markings of inspecting and testing
agency in the form of separable paper label or, where required by authorities having jurisdiction,
imprinted on surfaces of materials that will be concealed from view after installation.
SECTION 06400 - 4
ARCHITECTURAL WOODWORK
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
E.
Mock-Ups: Prior to installation of the work, fabricate and erect mock-ups for each type of finish and
application required to verify selections made under sample submittals and to demonstrate aesthetic
effects as well as qualities of materials and execution. Build mock-ups to comply with the following
requirements, using materials indicated for final unit of work.
1. Locate mock-ups on site in location and of size indicated or, if not indicated, as directed by the
Architect.
2. Demonstrate the proposed range of aesthetic effects and workmanship to be expected in the
completed work.
3. Obtain the Architect’s acceptance of mock-ups before start of final unit of work.
4. Retain and maintain mock-ups during construction in undisturbed condition as a standard for
judging completed unit of work.
a. Accepted mock-ups in undisturbed condition at time of Substantial Completion may
become part of completed unit of work.
F.
Pre-Installation Conference: Conduct pre-installation conference in accordance with
Section 01312 - PROJECT MEETINGS. Prior to commencing the installation, meet at the Project
site to review the material selections, installation procedures, and coordination with other trades.
Mock-ups shall be reviewed during the pre-installation conference. Pre-installation conference shall
include, but shall not be limited to, the Contractor, the Installer, manufacturer’s representatives, and
any trade that requires coordination with the work. Date and time of the pre-installation conference
shall be acceptable to the Owner and the Architect.
1.5
DELIVERY, STORAGE, AND HANDLING
A.
Deliver materials to the Project site in supplier’s or manufacturer’s original wrappings and containers,
labeled with supplier’s or manufacturer’s name, material or product brand name, and lot number, if
any.
B.
Store materials in their original, undamaged packages and containers, inside a well-ventilated area
protected from weather, moisture, soiling, extreme temperatures, and humidity.
C.
Protect architectural woodwork during transit, delivery, storage, and handling to prevent damage,
soilage, and deterioration.
D.
Do not deliver architectural woodwork until painting, wet-work, grinding, and similar operations which
could damage, soil, or deteriorate architectural woodwork have been completed in installation areas.
If architectural woodwork must be stored in other than installation areas, store only in areas meeting
requirements specified in Project Conditions Article.
1.6
PROJECT CONDITIONS
A.
Environmental Limitations: Do not deliver or install architectural woodwork until building is
enclosed, wet-work is completed and nominally dry, and HVAC system is operating and will maintain
temperature and relative humidity at occupancy levels during the remainder of the construction
period.
B.
Field Measurements: Take field measurements prior to fabrication of the work and preparation of
shop drawings, to ensure proper fitting of the work. Show recorded measurements on final shop
drawings. Notify the Owner and the Architect, in writing, of any dimensions found which are not
within specified dimensions and tolerances in the Contract Documents, prior to proceeding with the
fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the work.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 06400 - 5
ARCHITECTURAL WOODWORK
PART 2 - PRODUCTS
2.1
A.
2.2
MANUFACTURERS
Fabricator: Subject to compliance with requirements, provide architectural woodwork fabricated by
one of the following firms:
1. Cabinets by Design, Inc.
2. Mill-Rite Woodworking Co., Inc.
3. Mortensen Woodwork, Inc.
4. On Site Woodwork Corp.
5. Signature Interior Woodwork Corp.
MATERIALS
A.
Low-Emitting Materials:
1. Use adhesives, sealants, paints, coatings, etc., that comply with the specified limits for VOC
content when calculated according to SCAQMD Rule #1168. See Section 01110 - LOWEMITTING MATERIALS for VOC content limits.
2. Do not use composite wood and agrifiber products that contain urea-formaldehyde resin.
B.
Materials: Provide materials that comply with requirements of the AWI quality standard for each
type of architectural woodwork and quality grade indicated and, where the following products are part
of the work, with requirements of the referenced product standards that apply to product
characteristics indicated.
1. Medium Density Fiberboard: ANSI A208.2, Product Class MD-Exterior Glue,
urea-formaldehyde-free in accordance with NPA 9.
2. Plywood: DOC PS 1.
a. Environmental Standards: Provide urea-formaldehyde-free plywood to comply with
HUD 24 CFR Part 3280 and ANSI/HPVA HP-1.
3. Hardwood Plywood and Face Veneers: ANSI/HPVA HP-1.
C.
High Pressure Decorative Laminate: NEMA LD 3, grades as indicated or, if not indicated, as
required by architectural woodwork quality standard.
1. Manufacturer: Subject to compliance with requirements, provide products of one of the
following:
a. Formica Corp.
b. Laminart, Inc.
c. Nevamar Corp.
d. Pionite Decorative Laminates Div., Panolam Industries, Inc.
e. Wilsonart International, Inc.
2.3
A.
FIRE RETARDANT-TREATED MATERIALS
General: Where indicated, use materials impregnated with fire retardant chemical formulations
indicated, by a pressure process or by other means acceptable to authorities having jurisdiction, to
produce products with surface burning characteristics specified.
1. Fire Retardant Chemicals: Use chemical formulations that do not bleed through or otherwise
affect finishes. Do not use colorants in solution to distinguish treated material from untreated
material.
2. Formulation: Use interior Type A per AWPA C20.
3. Milling: Mill lumber before treatment and implement special procedures during treatment and
drying processes that shall prevent lumber from warping and developing discolorations from
drying sticks or other causes, marring, and other defects affecting appearance of treated
architectural woodwork.
SECTION 06400 - 6
ARCHITECTURAL WOODWORK
4.
5.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Drying: Kiln-dry material before and after treatment to levels required for untreated material.
Defective Material: Discard treated material that does not comply with requirements of
referenced woodworking standard. Do not use twisted, warped, bowed, discolored, or
otherwise damaged or defective material.
B.
Fire Retardant-Treated Fiberboard: Provide medium density fiberboard panels complying with
ANSI A208.2, made from softwood fibers, synthetic resins, and fire retardant chemicals mixed
together at time of panel manufacture to achieve products identical to those tested for flame spread
and smoke developed per ASTM E 84 by UL, Intertek Testing Services (ITS), or another inspecting
and testing agency acceptable to authorities having jurisdiction. Identify products with appropriate
markings of applicable inspecting and testing agency.
C.
Items to be Fire Retardant-Treated: Treat indicated items and the following:
1. Laminate-clad cabinets.
2. Laminate-clad countertops.
2.4
CABINET HARDWARE AND ACCESSORIES
A.
Cabinet Hardware: Provide cabinet hardware and accessory material associated with architectural
woodwork cabinets.
1. Standard: Comply with ANSI/BHMA A156.9.
2. Finish for Exposed Hardware: Provide finish that complies with ANSI/BHMA A156.18 and as
follows:
a. Satin Stainless Steel, on Stainless Steel Base: BHMA 630.
3. Finish for Concealed Hardware: Provide manufacturer’s standard finish that complies with
product class requirements of ANSI/BHMA A156.9.
4. Hardware: Provide the following in accordance with ANSI/BHMA A156.9:
a. Semiconcealed Hinges: For overlay doors. Back mounted. B01523
b. Frameless Concealed Hinges: B01602, with 165 degree of opening capability.
c. Back-Mounted Pulls: B02011.
d. Adjustable Shelf Standards and Brackets: B04102 with B04112.
e. Shelf Rests: B04081.
f. Side-Mounted, Full Extension, Drawer Slides: B05091.
g. Door Locks: E07121.
h. Drawer Locks: E07041.
B.
Glass for Doors:
1. Tempered: ASTM C 1048, Kind FT (fully tempered), Condition A (uncoated surfaces), Type I
(transparent glass, flat), Class 1 (clear), Quality q3 (glazing select), manufactured by horizontal
(roller hearth) process, with exposed edges seamed before tempering, 1/4 inch thick unless
otherwise indicated.
a. Thickness: 1/8 inch thick unless otherwise indicated.
C.
Grommets for Cable Passage through Countertops: 2 inch outside diameter, black, molded
plastic grommets and matching plastic caps with slot for wire passage.
1. Basis of Design: Product specified is “OG Series” as manufactured by Doug Mockett & Co.,
Inc. Items specified are to establish a standard of quality for design, function, materials, and
appearance. Equivalent products by other manufacturers are acceptable. The Architect will be
the sole judge of the basis of what is equivalent.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
2.5
SECTION 06400 - 7
ARCHITECTURAL WOODWORK
INSTALLATION MATERIALS
A.
Furring, Blocking, Shims, Hanging Strips, Etc.: Provide fire retardant-treated softwood lumber,
kiln-dried to less than 15 percent moisture content.
B.
Screws: Select material, type, size, and finish required for each use. Comply with
ANSI/ASME B18.6.1 for applicable requirements.
1. For metal framing supports, provide screws as recommended by metal framing manufacturer.
C.
Nails: Select material, type, size, and finish required for each use. Comply with ASTM F 1667 for
applicable requirements.
D.
Anchors: Select material, type, size, and finish required for each substrate for secure anchorage.
Provide non-ferrous metal or hot-dip galvanized anchors and inserts on inside face of exterior walls
and elsewhere as required for corrosion resistance.
2.6
FABRICATION, GENERAL
A.
Comply with requirements of referenced quality standard for wood moisture content in relation to
relative humidity conditions existing during time of fabrication and in installation area.
B.
Sand fire retardant-treated wood lightly to remove raised grain on exposed surfaces before
fabrication.
C.
Fabricate architectural woodwork to dimensions, profiles, and details indicated. Complete
fabrication, including, but not limited to, assembly, finishing, and hardware application, before
shipment to the Project site to maximum extent possible. Disassemble components only as
necessary for shipment and installation. Where necessary for fitting at site, provide ample allowance
for scribing, trimming, and fitting.
D.
Shop cut openings, to maximum extent possible, to receive hardware, appliances, plumbing fixtures,
electrical work, and similar items. Locate openings accurately and use templates or roughing-in
diagrams to produce accurately sized and shaped openings. Smooth edges of cutouts and, where
located in countertops and similar exposures, seal edges with a water-resistant coating.
E.
Install glass to comply with applicable requirements of Section 08800 - GLAZING and GANA GM.
For glass in wood frames, secure glass with removable stops.
2.7
LAMINATE-CLAD CABINETS
A.
Quality Standard: Comply with AWI AWQSI, Section 400 requirements for laminate-clad cabinets.
B.
Grade: Provide custom grade.
C.
Type of Cabinet Construction: Provide flush overlay type.
D.
Laminate Cladding for Exposed Surfaces:
1. Horizontal Surface Other Than Tops: HGS, 0.048 inch nominal thickness.
2. Post-Formed Surfaces: HGP, 0.039 inch nominal thickness.
3. Vertical Surfaces: HGS, 0.048 inch nominal thickness.
4. Edges: VGS, 0.028 inch nominal thickness.
SECTION 06400 - 8
ARCHITECTURAL WOODWORK
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
E.
Semi-Exposed Surfaces:
1. Surfaces Other Than Drawer Bodies: High pressure decorative laminate, VGS, 0.028 inch
nominal thickness.
2. Drawer Sides and Backs: Solid hardwood lumber, shop-finished.
3. Drawer Bottoms: Hardwood plywood.
F.
Dust Panels: Provide dust panels of 1/4 inch plywood or tempered hardboard above compartments
and drawers except where located directly under countertops.
G.
Colors, Patterns, and Finishes: Provide materials and products that result in colors and textures
of exposed laminate surfaces complying with the following requirements:
1. Provide the Architect’s selections from laminate manufacturer’s full range of colors and finishes.
2.8
COUNTERTOPS
A.
Quality Standard: Comply with AWI AWQSI, Section 400 requirements for countertops.
B.
Grade: Provide custom grade.
C.
Plastic Laminate Countertop: Provide high pressure plastic laminate.
1. Grade: HGS, 0.048 inch nominal thickness.
2. Colors, Patterns, and Finishes: Provide the Architect’s selections from laminate
manufacturer’s full range of colors and finishes.
3. Edge Treatment: Same as laminate cladding on horizontal surfaces.
4. Core Material at dry locations: Medium density fiberboard.
5. Core Material at wet locations: Exterior grade plywood.
PART 3 - EXECUTION
3.1
A.
3.2
EXAMINATION
Verification of Conditions: Examine areas and conditions under which the work is to be installed,
and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions
detrimental to the proper and timely completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected.
1. Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by
the Installer.
PREPARATION
A.
Condition architectural woodwork to average prevailing humidity conditions in installation areas
before installing.
B.
Before installing architectural woodwork, examine shop-fabricated work for completion and complete
work as required, including, but not limited to, backpriming and removal of packing.
3.3
A.
INSTALLATION
Quality Standard: Install architectural woodwork to comply with AWI AWQSI, Section 1700 for the
same grades specified in Part 2 - PRODUCTS of this Section for type of architectural woodwork
involved.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 06400 - 9
ARCHITECTURAL WOODWORK
B.
Installation Tolerances: Install architectural woodwork plumb, level, true, and straight with no
distortions. Shim as required with concealed shims.
1. Variation From Plumb and Level: ±1/8 inch in any 96 inch dimension.
2. Offset In Flush Adjoining Surfaces: ±1/16 inch maximum.
3. Offset In Revealed Adjoining Surfaces: ±1/8 inch maximum.
C.
Fitting: Scribe and cut architectural woodwork to fit adjoining work and refinish cut surfaces or
repair damaged finish at cuts.
D.
Fire Retardant-Treated Wood: Handle, store, and install fire retardant-treated wood to comply with
recommendations of chemical treatment manufacturer, including, but not limited to, those for
adhesives used to install architectural woodwork.
E.
Fasteners: Anchor architectural woodwork to anchors or blocking built-in or directly attached to
substrates. Secure to grounds, stripping, and blocking with countersunk, concealed fasteners and
blind nailing as required for a complete installation. Use fine finishing nails for exposed nailing,
countersunk and filled flush with architectural woodwork and matching final finish where transparent
finish is indicated.
F.
Cabinets: Install without distortion so that doors and drawers fit openings properly and are
accurately aligned. Adjust hardware to center doors and drawers in openings and to provide
unencumbered operation. Complete the installation of hardware and accessory items as indicated.
Install cabinets with no more than 1/8 inch in 96 inches for sag, bow, or other variation from a
straight line.
1. Fasten wall cabinets through back, near top and bottom, at ends and not more than 16 inches
on center.
G.
Countertops: Anchor securely to base units and other support systems as indicated. Caulk space
between backsplash and wall with specified sealant. Install countertops with no more than 1/8 inch
in 96 inches for sag, bow, or other variation from a straight line.
H.
Paneling: Anchor paneling to supporting substrate with concealed panel hanger clips and by blind
nailing on back-up strips, splined connection strips, or similar associated trim and framing. Do not
face nail unless otherwise indicated. Install paneling flush with no more than 1/16 inch in 96 inches
vertical cup and bow and 1/8 inch in 96 inches horizontal variation from a true plane.
I.
Finishing: Complete the finishing work specified in this Section to the extent not completed at the
shop or before installation of the architectural woodwork. Fill nail holes with matching filler where
exposed. Apply specified finish coats, including, but not limited to, stains and paste fillers (if any), to
exposed surfaces where only seal or prime coats were applied in the shop.
1. See Section 09900 - PAINTING for final finishing of installed architectural woodwork that is not
the work of this Section.
3.4
ADJUSTING AND CLEANING
A.
Repair damaged and defective architectural woodwork where possible to eliminate functional and
visual defects. Where not possible to repair, replace architectural woodwork. Adjust joinery for
visual appearance.
B.
Clean, lubricate, and adjust hardware.
C.
Clean architectural woodwork on exposed and semi-exposed surfaces. Touch-up shop-applied
finishes to restore damaged or soiled areas.
SECTION 06400 - 10
ARCHITECTURAL WOODWORK
3.5
A.
REVISED MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
PROTECTION
Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall
ensure that the architectural woodwork shall be without damage at time of Substantial Completion.
END OF SECTION
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 07415 - 1
METAL CLADDING SYSTEMS
SECTION 07415
METAL CLADDING SYSTEMS
PART 1 - GENERAL
1.1
A.
1.2
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General Conditions,
Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project
Manual apply to the work specified in this Section.
SUMMARY
A.
Alternate Scope: In lieu of COMPOSITE PANELS as defined in Section 074320, provide design
and engineering, labor, material, equipment, related services, and supervision required, including,
but not limited to, manufacturing, fabrication, erection, and installation for metal cladding systems as
required for the complete performance of the work, and as shown on the Drawings and as herein
specified. Refer to Section 01101 ALTERNATES.
B.
Section Includes: The work specified in this Section includes, but shall not be limited to, metal
cladding systems, including, but not limited to, trim, terminations, flashings, miscellaneous steel
and sub-girts, clip angles, fasteners, and other devices for secure anchorage of panels to
structural steel frame members or other substrate provided for this purpose.
1.3
REFERENCES
A.
The publications listed below form a part of this Specification to the extent referenced. The
publications are referred to in the text by the basic designation only.
B.
The edition/revision of the referenced publications shall be the latest date as of the date of the
Contract Documents, unless otherwise specified.
C.
American Architectural Manufacturers Association (AAMA):
1. AAMA 2605, "Voluntary Specification, Performance Requirements, and Test Procedures for
Superior Performing Organic Coatings on Aluminum Extrusions and Panels."
D.
American Institute of Steel Construction, Inc. (AISC):
1. AISC 303, "Code of Standard Practice for Steel Buildings and Bridges."
2. AISC MSC, "Manual of Steel Construction ASD.”
E.
ASTM (ASTM):
1. ASTM B 209, "Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate.”
2. ASTM B 221, "Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods,
Wire, Shapes, and Tubes.”
3. ASTM E 119, "Standard Test Methods for Fire Tests of Building Construction and Materials.”
4. ASTM E 329, "Standard Specification for Agencies Engaged in the Testing and/or Inspection of
Materials Used in Construction."
F.
Green Seal (GS):
1. GS-37, “Industrial & Institutional Cleaners.”
SECTION 07415 - 2
METAL CLADDING SYSTEMS
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
G.
National Association of Architectural Metal Manufacturers (NAAMM):
1. NAAMM MFM, "Metal Finishes Manual.”
H.
Sheet Metal and Air Conditioning Contractors' National Association (SMACNA):
1. SMACNA ASMM, "Architectural Sheet Metal Manual."
I.
SSPC: The Society for Protective Coatings (SSPC):
1. SSPC Paint 12, "Paint Specification No. 12 Cold-Applied Asphalt Mastic (Extra Thick Film).”
J.
Underwriters Laboratories, Inc. (UL):
1. UL FRD, "Fire Resistance Directory.”
1.4
A.
1.5
A.
DEFINITION
Metal Cladding System Assembly: Metal plate wall panels, attachment system components,
miscellaneous metal framing, and accessories necessary for a complete weathertight wall system.
SYSTEM DESCRIPTION
Design Requirements:
1. General: Provide the manufacturer's metal cladding system, adapted to the application
indicated, and modified as required to comply with performance requirements and materials
specified, as demonstrated by testing the manufacturer's corresponding systems according
to test methods indicated. Where modifications to the manufacturer's tested metal cladding
system are required for compliance with performance, or materials specified, and such
modifications invalidate laboratory testing as determined by the Architect, test in accordance
with Section 08900 - EXTERIOR WALL PERFORMANCE REQUIREMENTS, with no
increase in the Contract Sum. In addition to the requirements specified herein comply with
additional provisions specified in Section 08900 - EXTERIOR WALL PERFORMANCE
REQUIREMENTS.
a. The metal cladding system, including, but not limited to, stiffeners and sealants, shall
meet the specified requirements for wind loading, air infiltration, and water penetration.
b. The anchorage system shall be designed so that the panels are secure yet free-floating
to accommodate expansion and contraction, and that individual panels may be installed
or removed without disturbing adjacent panels.
c. The panel system shall have an internal drainage system to catch condensation within
the wall and direct it to designated weepage points.
d. Panels shall be finished after fabrication to ensure integrity of applied finish.
2. Structural Design Limitations:
a. Normal-to-wall deflection shall not exceed 1/240 of clear span or 1/4 inch, whichever is
less at full design load for each panel.
b. Metal copings shall be designed to resist a 250 pound live load per 5 foot section without
permanent distortion, or disengagement of anchors or seals.
c. Thermal movement within the system shall not result in oil canning or similar
irregularities.
3. Structural Basis for Design:
a. Base calculations for such deflections upon the combination of maximum direct loadings,
building deflections, thermal stresses, and erection tolerances. Do not permit any
permanent deflections of members in the metal cladding work in excess of 0.1 percent of
their clear span.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
4.
5.
6.
7.
B.
1.6
SECTION 07415 - 3
METAL CLADDING SYSTEMS
b. Design, fabricate, and install structural components of the metal cladding system with a
factor of safety not less than 1.5 (basis for design calculations shall be 1.5 times the
maximum design wind pressure), such that failure of any structural component shall not
occur at less than 1.5 times the maximum design wind pressures as indicated on the
Drawings or, if not indicated, as required by local authorities having jurisdiction. Failure
is defined as breakage, component disengagement, or permanent distortion.
Sealant Joint Design: Joints within system shall be designed to incorporate sealant and
bond breaker in such a way to reduce or eliminate shear forces on sealant. Seals or joint
fillers shall not be interrupted by anchors, shims, or similar components. Coordinate with
design of anchorage.
Weeps: Protect weeps with reticulated foam baffles of appropriate PPI (pores per inch).
Thermal Movements: Allow for thermal movement resulting from the following maximum
change (range) in ambient and surface temperatures in engineering, fabricating, and installing
metal cladding systems. Base engineering calculation on actual surface temperatures of
materials due to both solar heat gain and nighttime sky heat loss.
a. Temperature Change (Range): 120 °F ambient, 180 °F material surfaces.
Copings: Metal copings shall be designed to resist a point load of 250 pounds without
permanent deformation or disengagement of anchors or seals.
Performance Requirements: See Section 08900 - EXTERIOR WALL PERFORMANCE
REQUIREMENTS.
SUBMITTALS
A.
General: See Section 01300 - SUBMITTALS.
B.
Product Data: Submit product data including, but not limited to, manufacturer's product
specifications, installation instructions, recommendations for maintenance, and general
recommendations, as applicable to materials and finishes for each component and for total
cladding system.
1. Include complete test reports for consideration by the Architect where acceptance to waive
testing as delineated in Section 08900 - EXTERIOR WALL PERFORMANCE
REQUIREMENTS is to be proposed.
2. Include type of sealant to be used and application instructions.
C.
Shop Drawings: Submit shop drawings showing adaptation of manufacturer's metal cladding
system, including, but not limited to, layouts of panels on roofs and walls, details of edge
conditions, joints, corners, supports, anchors, trim, flashings, closures, and special details for all
Project conditions. Shop drawings shall also include, but shall not be limited to, metal thickness,
finish methods of installation, and joints necessary to accommodate thermal movement. Include
plans and elevations at a scale of 1/2 inch equals 1 foot minimum and details at full-size.
Incorporate material lists.
1. Materials List: Submit a list of selected manufacturers, product names, product model
numbers, and other information furnished by the Contractor to document the sources and
general properties of materials and equipment used in the work. Incorporate into shop
drawing submittal.
D.
Samples:
1. Submit samples for initial color selection. Submit samples of each specified finish. Submit
samples in form of manufacturer’s color charts showing full range of colors and finishes
available. Where finishes involve normal color variations, include samples showing the full,
range of variations expected.
SECTION 07415 - 4
METAL CLADDING SYSTEMS
2.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Submit samples for verification purposes. Submit samples of metal cladding panels. Provide
sample panels 24 inches square, in the color and finish indicated. Include clips, fasteners,
closures, and other panel accessories. The Architect reserves the right to require fabrication
samples showing the following:
a. Prime members.
b. Joinery.
c. Anchorage.
d. Expansion provisions.
e. Profiles.
f. Intersections.
E.
Quality Control Submittals:
1. Design Data: Submit structural design calculations for the metal cladding system and the
connections for attaching it to the structure. Show that maximum stresses and deflections do
not exceed specified performance requirements under full design loading. The design data
shall be signed and sealed by the professional engineer. Only the loadings on the structure
at the connections will be reviewed.
2. Qualification Data: Submit qualification data for firms and persons specified in Quality
Assurance Article to demonstrate their capabilities and experience. Include lists of completed
projects with project names and addresses, names of architects and owners, and other
information specified.
3. Test Reports: Submit a report of inspections of connections and welds.
4. Certificates:
a. Submit Installer certificates signed by the manufacturer certifying that the Installer of the
metal cladding system complies with requirements indicated, including, but not limited to,
structural performance, flame and smoke contribution, and air and water infiltration.
b. Submit designer certificates, signed and sealed by the structural engineer licensed to
practice in the State where the Project is located that he has visited the site and that to
the best of his information, knowledge, and belief the metal cladding system has been
installed in accordance with his design.
F.
Maintenance Data: Furnish complete maintenance manuals describing the materials, devices,
and procedures to be followed in cleaning and maintaining the work. Include manufacturer's
brochures and parts lists describing the actual materials used in the work, including, but not
limited to, metal alloys, finishes, sealants, and other major components. Assemble manuals for
component parts into single binders.
1.7
A.
QUALITY ASSURANCE
Qualifications:
1. Manufacturer Qualifications: Manufacturer shall be a firm engaged in the manufacture of
metal cladding systems of types and sizes required, and whose products have been in
satisfactory use in similar service for a minimum of five years.
2. Installer Qualifications: Installer shall be a firm that shall have a minimum of five years of
successful installation experience with projects utilizing metal cladding systems similar in type
and scope to that required for this Project, and shall be approved by the manufacturer.
3. Engineer Qualifications: The engineer shall be a professional engineer legally authorized to
practice in the jurisdiction where the Project is located and experienced in providing engineering
services of the kind indicated that have resulted in the installation of products similar to this
Project in material, design, and extent, and that have a record of successful in-service
performance.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
4.
5.
SECTION 07415 - 5
METAL CLADDING SYSTEMS
Inspecting and Testing Agency Qualifications: To qualify for acceptance, an independent
inspecting and testing agency hired by the Contractor or manufacturer to test products shall
demonstrate to the Architect’s satisfaction that they are qualified according to ASTM E 329 to
conduct testing indicated.
Welder's Qualifications: Qualify welding processes and welding operators in accordance
with American Welding Society (AWS) standard qualification procedure. Operators shall
carry proof of qualification on their persons.
B.
Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances,
and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary
approvals from such authorities.
C.
Mock-Ups: Prior to installation of the work, fabricate and erect mock-ups for each type of finish and
application required to verify selections made under sample submittals and to demonstrate aesthetic
effects as well as qualities of materials and execution. Build mock-ups to comply with the following
requirements, using materials indicated for final unit of work.
1. Locate mock-ups on site in location and of size indicated or, if not indicated, as directed by the
Architect.
2. Demonstrate the proposed range of aesthetic effects and workmanship to be expected in the
completed work.
3. Obtain the Architect’s acceptance of mock-ups before start of final unit of work.
4. Retain and maintain mock-ups during construction in undisturbed condition as a standard for
judging completed unit of work.
a. Accepted mock-ups in undisturbed condition at time of Substantial Completion may
become part of completed unit of work.
D.
Pre-Installation Conference: Conduct pre-installation conference in accordance with
Section 01200 - PROJECT MEETINGS. Prior to commencing the installation, meet at the Project
site to review the material selections, installation procedures, and coordination with other trades.
Mock-ups shall be reviewed during the pre-installation conference. Pre-installation conference shall
include, but shall not be limited to, the Contractor, the Installer, manufacturer’s representatives, and
any trade that requires coordination with the work. Date and time of the pre-installation conference
shall be acceptable to the Owner and the Architect.
E.
Single Source Responsibility: Obtain metal cladding systems from a single source with resources
to produce products of consistent quality in appearance and physical properties without delaying the
work.
F.
Coordination: Coordinate metal cladding systems with rain drainage work, flashing, trim, and
construction of walls and other adjoining work to provide a leakproof, secure, and non-corrosive
installation.
1.8
DELIVERY, STORAGE, AND HANDLING
A.
Deliver panels and other components so they shall not be damaged or deformed. Package
panels for protection against transportation damage.
B.
Exercise care in unloading, storing, and erecting panels to prevent bending, warping, twisting, and
surface damage.
C.
Stack materials off the ground with a suitable weathertight ventilated covering. Store panels so
that they shall not accumulate water. Do not store panels in contact with other materials that
might cause staining, denting, or other surface damage.
SECTION 07415 - 6
METAL CLADDING SYSTEMS
1.9
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
PROJECT CONDITIONS
A.
Weather Limitations: Proceed with installation only when existing and forecasted weather
conditions permit metal cladding system work to be performed according to manufacturer's written
instructions and warranty requirements.
B.
Field Measurements: Take field measurements before fabrication. Show recorded
measurements on final shop drawings. Notify the Architect and the Contractor in writing of any
dimensions found which are not within specified dimensions and tolerances in the Contract
Documents prior to proceeding with fabrication. Coordinate fabrication schedule with construction
progress to avoid delay. Field trimming of panel units shall not be permitted.
1.10
WARRANTY
A.
General: See Section 01770 - CLOSEOUT PROCEDURES.
B.
Special Warranty:
1. The Contractor shall warrant the work of this Section to be in accordance with the Contract
Documents and free from faults and defects in materials and workmanship for a period of five
years. This special warranty shall extend the one year period of limitations contained in the
General Conditions. The special warranty shall be countersigned by the Installer and the
manufacturer. Defective is defined to include, but shall not be limited to, the following:
a. Early deterioration, aging, or discoloration of finishes, gaskets, or other components.
b. Uncontrolled penetration of air or water.
c. Failure of the system to meet performance requirements.
2. This warranty shall specifically include the work of the following additional sections of the
Specifications. Upon notification of defects, within the warranty period, make necessary
repairs or replacement at the convenience of the Owner.
a. Section 07900 - JOINT SEALERS.
C.
Special PVDF Finish Warranty: Submit a written warranty, signed by manufacturer, covering
failure of the factory-applied exterior finish within the specified warranty period and agreeing to repair
finish or replace work that shows evidence of finish deterioration. Deterioration of finish includes, but
shall not be limited to, color fade, chalking, cracking, peeling, and loss of film integrity.
1. Warranty Period: Warranty period shall be 20 years from date of Substantial Completion.
D.
Additional Owner Rights: The warranty shall not deprive the Owner of other rights the Owner may
have under other provisions of the Contract Documents and shall be in addition to and run
concurrent with other warranties made by the Contractor under requirements of the Contract
Documents.
PART 2 - PRODUCTS
2.1
A.
MANUFACTURERS
Manufacturer: Subject to compliance with requirements, provide products of one of the following:
1. Alply, Inc.
2. Architectural Specialty Products, Inc.
3. Firestone Metal Products.
4. Industrial Building Panels, Inc.
5. Protean Construction Products, Inc.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
B.
2.2
SECTION 07415 - 7
METAL CLADDING SYSTEMS
Basis of Design: Product specified is "UNA-CLAD 3000" as manufactured by Firestone Metal
Products. Items specified are to establish a standard of quality for design, function, materials, and
appearance. Equivalent products by listed manufacturers are acceptable. The Architect will be the
sole judge of the basis of what is equivalent.
MATERIALS
A.
Sheet and Extruded Materials:
1. Aluminum Panels: Panels shall be custom-fabricated from minimum 0.120 inch thick
aluminum solid plate of 3003-H134 or 5005-H32AQ alloy, in accordance with the Drawings
and manufacturer's requirements, including, but not limited to, verified field dimensions,
complying with ASTM B 209.
2. Extruded Aluminum Bars and Shapes: Extruded aluminum support members shall be a
minimum 0.093 inch thick 6063-T52 alloy, complying with ASTM B 221; supplied pre-cut to
size.
B.
Concealed Flashing: Provide dead-soft 26 gage stainless steel concealed flashing of type
selected for compatibility by the manufacturer.
C.
Panel Accessories: Except as indicated as work of another Specification section, provide
components required for a complete metal cladding system. Match materials and prefinish to
match panels.
D.
Bituminous Coating: Provide cold-applied asphalt mastic, SSPC Paint 12, compounded for
15 mil dry film thickness per coat.
E.
Fasteners: Provide bolts, self-drilling screws, and other fastening devices, as recommended by
the panel manufacturer for conditions of each application. Provide Type 305 stainless steel.
Where exposed, finish to match adjacent surfaces.
F.
Sealants: See Section 07900 - JOINT SEALERS.
2.3
FABRICATION
A.
Fabricate and finish metal cladding systems and accessories at the factory to greatest extent
possible, by manufacturer's standard procedures and processes, as necessary to fulfill indicated
performance requirements demonstrated by laboratory testing. Comply with indicated profiles and
with dimensional and structural requirements.
B.
Fabricate metal cladding systems in a manner that eliminates condensation on interior side of
panel and with joints between panels designed to form weathertight seals.
C.
Fabricate panels with panel stiffeners as required to comply with deflection limits. Weld and grind
panel corners smooth. Fabricate panels to the following dimensional tolerances:
1. Length and Width: ±0.032 inch up to 48 inches, ±0.064 inch from 48 inches to 144 inches.
2. Diagonal: ±0.1875 inch.
3. Panel Bow: Not more than 0.2 percent of panel length or width up to 0.1875 inch maximum.
4. Thickness: ±0.008 inch.
5. Squareness: 0.1875 inch difference between diagonal measurements.
6. Camber: 0.032 inch.
D.
Fabricate flashing and trim to comply with recommendations in SMACNA ASMM that apply to the
design, dimensions, metal, and other characteristics of item indicated.
SECTION 07415 - 8
METAL CLADDING SYSTEMS
1.
2.
3.
4.
5.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Form exposed sheet metal accessories that are without excessive oil-canning, buckling, and
tool marks and that are true to line and levels indicated, with exposed edges folded back to
form hems.
Fabricate non-moving seams in accessories with flat-lock seams. Form seams and seal with
epoxy seam sealer. Rivet joints for additional strength.
Form non-expansion but movable joints in metal to accommodate elastomeric sealant to
comply with SMACNA standards.
Conceal fasteners and expansion provisions where possible. Exposed fasteners are not
allowed on faces of accessories exposed to view.
Fabricate cleats and attachment devices from same material as accessory being anchored
or from compatible, non-corrosive metal recommended by metal panel manufacturer. Size
shall be as recommended by SMACNA ASMM or metal panel manufacturer for application
but not less than thickness of metal being secured.
E.
Panels shall be formed to specified dimensions with tolerances to accommodate expansion and
contraction between panels and structural members. Curved panels shall be accurately formed to
radii in plant of manufacturer.
F.
Panel corners shall be welded and ground smooth prior to finishing.
G.
Accessory and trim components shall be factory-fabricated and ready for installation.
H.
Fabricate and finish panels and accessories at the factory, by processes, as required to fulfill
indicated performance requirements demonstrated by laboratory testing. Comply with
dimensional requirements and with structural requirements.
I.
Apply bituminous coating or other permanent separation materials on concealed panel surfaces
where panels would otherwise be in direct contact with substrate materials that are
non-compatible or could result in corrosion or deterioration of either material or finishes.
J.
Use electrodes and methods recommended by manufacturer of material being welded, and in
accordance with applicable AWS standards. Use only methods which prevent distortion and
discoloration of exposed faces. Grind weld areas smooth, using only clean equipment and
materials free of iron or iron compounds. Restore finish of component parts after welding and
grinding.
K.
Provide temporary coating and coverings to protect the work during shipment and construction.
Such protection shall avoid development of non-uniformity in finishes, shall not impart a residue
which would adversely affect the adhesion of sealants, nor cause other deleterious effects in the
work. Temporarily remove such protection when requested by the Architect for review of finishes,
and completely remove protection when no longer required.
2.4
A.
FINISHES
General: Comply with NAAMM MFM for recommendations relative to application and
designations of finishes.
1. Finish designations prefixed by "AA" conform to the system established by the Aluminum
Association for designating aluminum finishes.
2. Remove die markings, scratches, abrasions, dents, and other blemishes before applying
finish.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
B.
SECTION 07415 - 9
METAL CLADDING SYSTEMS
High Performance Organic Coating: AA-C12-C42-R1x (Chemical Finish: cleaned with inhibited
chemicals; Chemical Finish: chemical conversion coating, acid chromate-fluoride-phosphate
pretreatment; Organic Coating: as specified below). Prepare, pretreat, and apply coating to
exposed metal surfaces to comply with coating and resin manufacturer's instructions.
1. Standard Two-Coat Polyvinylidene Fluoride (PVDF) Finish Coating: Manufacturer's
standard thermocured system, complying with AAMA 2605, composed of specially
formulated inhibitive primer and fluoropolymer color topcoat containing not less than
70 percent PVDF resin by weight, as produced by Arkema, Inc. ("Kynar 500") or by Solvay
Solexis, Inc. ("Hylar 5000"). Provide minimum 1.2 mil total dry film thickness.
a. Color and Gloss: Match the Architect's sample. (Intended to match Accent Brick color,
Basis of Design "Whitestone" by Palmetto Brick.)
b. PVDF Touch-Up Finish: PVDF finish coating, containing fluoropolymer resin and
formulated for air-drying at ambient temperature. Provide for field touch-up and furnish
in color to match shop-applied finishes.
PART 3 - EXECUTION
3.1
A.
3.2
EXAMINATION
Verification of Conditions: Examine areas and conditions under which the work is to be installed,
and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions
detrimental to the proper and timely completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected.
1. Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by
the Installer.
INSTALLATION
A.
Panel Supports and Anchors: Girts, purlin, and other secondary structural panel support
members and anchorage shall be installed in accordance with AISC MSC and AISC 303,
ASTM C 754, and metal panel manufacturer's written recommendations.
B.
Panel Installation: Comply with manufacturer's published instructions and recommendations for
installation, as applicable to Project conditions and supporting substrates. Anchor panels and
other components of the work securely in place, with provisions for thermal and structural
movement.
1. Field cutting of panels is not permitted.
2. Install panels with concealed fasteners, unless shown otherwise.
3. Anchor components securely in place. Shim and allow for movement resulting from changes
in thermal conditions. Provide separators and isolators to prevent corrosion, electrolytic
deterioration, and freeze-up of moving joints.
4. Install the work level, plumb, and true-to-line, with uniform joints.
5. Cut and trim component parts during installation only with the approval of the manufacturer
and in accordance with his recommendations. Restore finishes completely to protect the
material and remove evidence of cutting or trimming. Remove and replace members where
cutting and trimming has impaired strength or appearance. Do not cut through reinforcing
members.
6. Use electrodes and methods recommended by manufacturer of material being welded, and
in accordance with applicable AWS standards. Use only methods which prevent distortion
and discoloration of exposed faces. Grind exposed welds smooth, using only clean
equipment and materials free of iron or iron compounds. Restore finish of component parts
after welding and grinding.
SECTION 07415 - 10
METAL CLADDING SYSTEMS
7.
8.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Paint the contact surfaces of dissimilar materials, including, but not limited to, metal in
contact with masonry or concrete work, with a heavy coating of epoxy paint, or provide other
separation as recommended by the manufacturer. Paint steel clip angles, and other ferrous
metal parts which shall be concealed, using epoxy paint.
Do not erect members which are warped, bowed, deformed, or otherwise damaged or
defaced to such extent as to impair strength or appearance. Remove and replace members
which have been damaged.
C.
Accessories: Install components required for a complete watertight and airtight metal panel
system.
D.
Joint Sealers: Install joint fillers and sealants where indicated and where required for
weatherproof performance of panel systems. Provide types of sealants and fillers indicated or, if
not otherwise indicated, types recommended by panel manufacturer.
E.
Installation Tolerances: Shim and align panel units within installed tolerance of 1/4 inch in
20 feet non-cumulative on level/plumb/slope and location/line as indicated, and within 1/16 inch
offset of adjoining faces and of alignment of matching profiles.
3.3
FIELD QUALITY CONTROL
A.
General: See Section 01410 - INSPECTING AND TESTING SERVICES.
B.
Testing: Hose test in accordance with Section 08900 - EXTERIOR WALL PERFORMANCE
REQUIREMENTS.
C.
Inspection: Inspecting and testing agency shall inspect and report on all connections and welds.
3.4
ADJUSTING AND CLEANING
A.
Damaged Units: Replace panels and other components of the work that have been damaged or
have deteriorated beyond successful repair by means of finish touch-up or similar minor repair
procedures.
B.
Cleaning: Remove temporary protective coverings and strippable films (if any) as soon as each
panel is installed. Upon completion of panel installation, clean finished surfaces as recommended
by panel manufacturer, and maintain in a clean condition during construction.
1. No cleaning products or processes shall exceed listed VOC limits or use ozone-depleting
substances. Cleaning materials shall comply with GS-37.
3.5
A.
3.6
A.
DEMONSTRATION
Maintenance Instruction: Instruct the Owner's personnel who will be responsible for
maintenance after the time of final acceptance. Demonstrate and train the Owner's personnel, for
a period not less than two working days, in the proper methods of cleaning and maintaining the
entire metal cladding system.
PROTECTION
Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall
ensure that the metal cladding systems shall be without damage at time of Substantial Completion.
END OF SECTION
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 07420 - 1
COMPOSITE PANELS
SECTION 07420
COMPOSITE PANELS
PART 1 - GENERAL
1.1
A.
1.2
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General Conditions,
Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project
Manual apply to the work specified in this Section.
SUMMARY
A.
Base Design Scope: Provide labor, material, equipment, related services, and supervision
required, including, but not limited to, manufacturing, fabrication, erection, and installation for
composite panels as required for the complete performance of the work, and as shown on the
Drawings and as herein specified.
B.
Alternate Scope: Provide METAL CLADDING SYSTEM as defined in Section 07515 in lieu of
COMPOSITE PANELS. Refer to Section 01101 - ALTERNATES.
C.
Section Includes: The work specified in this Section includes, but shall not be limited to, composite
panel system requirements, including, but not limited to, the following components:
1. Aluminum-faced composite metal panels with mounting system.
2. Panel mounting system, including, but not limited to, anchors, shims, furring, fasteners,
gaskets and sealants, related flashing adapters, and masking (as required) for a complete
watertight installation.
3. Parapet coping, column covers, soffits, sills, border, and filler items indicated as integral
components of the composite panel system or as designed.
4. Interior composite panel system work that matches exterior system.
1.3
REFERENCES
A.
The publications listed below form a part of this Specification to the extent referenced. The
publications are referred to in the text by the basic designation only.
B.
The edition/revision of the referenced publications shall be the latest date as of the date of the
Contract Documents, unless otherwise specified.
C.
American Architectural Manufacturers Association (AAMA):
1. AAMA/WDMA 101/I.S. 2, "Voluntary Specifications for Aluminum, Vinyl (PVC), and Wood
Windows and Glass Doors."
2. AAMA 611, "Voluntary Specifications for Anodized Architectural Aluminum (Revised).”
3. AAMA 2605, "Voluntary Specification, Performance Requirements, and Test Procedures for
Superior Performing Organic Coatings on Aluminum Extrusions and Panels."
4. AAMA MCWM-1, "Metal Curtain Wall Manual."
5. AAMA SFM-1, "Aluminum Storefront and Entrance Manual."
SECTION 07420 - 2
COMPOSITE PANELS
MARCH 16, 2011
PROJECT NAME - XXXXX
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
D.
ASTM (ASTM):
1. ASTM A 641, "Standard Specification for Zinc-Coated (Galvanized) Carbon Steel Wire."
2. ASTM A 653, "Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron
Alloy-Coated (Galvannealed) by the Hot-Dip Process.”
3. ASTM B 209, "Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate."
4. ASTM C 297, "Standard Test Method for Tensile Strength of Flat Sandwich Constructions in
Flatwise Plane."
5. ASTM C 645, "Standard Specification for Non-Load (Axial) Bearing Steel Studs, Runners
(Track), and Rigid Furring Channels for Screw Application of Gypsum Board."
6. ASTM C 754, "Standard Specification for Installation of Steel Framing Members to Receive
Screw-Attached Gypsum."
7. ASTM D 1781, "Standard Test Method for Climbing Drum Peel for Adhesives.”
8. ASTM E 84, "Standard Test Method for Surface Burning Characteristics of Building Materials."
9. ASTM E 119, "Standard Test Methods for Fire Tests of Building Construction and Materials.”
10. ASTM E 162, "Standard Test Method for Surface Flammability of Materials Using a Radiant
Heat Energy Source."
11. ASTM E 283, "Standard Test Method for Determining the Rate of Air Leakage Through Exterior
Windows, Curtain Walls, and Doors Under Specified Pressure Difference Across the
Specimen."
12. ASTM E 329, "Standard Specification for Agencies Engaged in the Testing and/or Inspection of
Materials Used in Construction."
13. ASTM E 330, "Standard Test Method for Structural Performance of Exterior Windows, Curtain
Walls, and Doors by Uniform Static Air Pressure Difference."
14. ASTM E 331, "Standard Test Method for Water Penetration of Exterior Windows, Curtain
Walls, and Doors by Uniform Static Air Pressure Difference."
E.
International Conference of Building Officials (ICBO):
1. ICBO UBC No. 17-5, “Room Fire Test Standard for Interior of Foam Plastic Systems.”
F.
National Association of Architectural Metal Manufacturers (NAAMM):
1. NAAMM MFM, "Metal Finishes Manual."
G.
Sheet Metal and Air Conditioning Contractors' National Association (SMACNA):
1. SMACNA ASMM, "Architectural Sheet Metal Manual."
H.
Underwriters Laboratories, Inc. (UL):
1. UL FRD, "Fire Resistance Directory.”
1.4
A.
1.5
A.
DEFINITION
Composite Panel System Assembly: Metal-faced composite wall panels, attachment system
components, miscellaneous metal framing, and accessories necessary for a complete weathertight
wall system.
SYSTEM DESCRIPTION
Design Requirements:
1. Deflection and Thermal Movement: Provide systems that have been tested and certified in
accordance with ASTM E 330 to conform to the following criteria under wind loading as
indicated on the drawings:
a. Normal Deflection:
1) Normal to the plane of the wall between supports, deflection of the secured
perimeter framing members shall not exceed L/175 or 3/4 inch, whichever is less.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 07420 - 3
COMPOSITE PANELS
2) Normal to the plane of the wall, the maximum panel deflection shall not exceed L/60
of the full span.
3) At 1-1/2 times design pressure, permanent deflections of framing members shall not
exceed L/100 of span length and components shall not experience failure or gross
permanent distortion.
4) At connection points of framing members to anchors, permanent set shall not
exceed 1/16 inch.
b. Anchor Deflection: At connection points of framing members to anchors, anchor
deflection in any direction shall not exceed 1/16 inch.
c. Thermal Movements: Allow for thermal movement resulting from the following maximum
change (range) in ambient and surface temperatures in engineering, fabricating, and
installing composite panel systems. Base engineering calculation on actual surface
temperatures of materials due to both solar heat gain and nighttime sky heat loss.
1) Temperature Change (Range): 120 °F ambient, 180 °F material surfaces.
B.
Performance Requirements: See Section 08900 - EXTERIOR WALL PERFORMANCE
REQUIREMENTS.
C.
Performance Requirements:
1. Air Infiltration: Provide composite panel assemblies with permanent resistance to air
leakage through assembly of not more than 0.060 cfm per square foot of fixed wall area when
tested according to ASTM E 283 at a static air pressure difference of 6.24 psf.
2. Water Penetration: Provide composite panel assemblies with no water penetration as
defined in the test method when tested according to ASTM E 331 at a minimum differential
pressure of 20 percent of inward acting, wind load design pressure of not less than 6.24 psf
and not more than 12.0 psf.
1.6
SUBMITTALS
A.
General: See Section 01300 - SUBMITTALS.
B.
Product Data: Submit product data showing material proposed. Submit sufficient information to
determine compliance with the Drawings and Specifications. Product data shall include, but shall not
be limited to, manufacturer's product specifications, standard details, certified product test results,
installation guidelines, and general recommendations applicable to specified materials and
finishes.
C.
Shop Drawings: Submit shop drawings for each product and accessory required. Include
information not fully detailed in manufacturer’s standard product data, including, but not limited to,
layout and elevations, details showing thickness and dimensions of the various system parts,
fastening and anchoring methods, trim, flashing; accessories, locations of joints and gaskets, and
location and configuration of joints necessary to accommodate thermal movement.
D.
Samples:
1. Submit samples for initial color selection. Submit samples of each specified finish. Submit
samples in form of manufacturer’s color charts showing full range of colors and finishes
available. Where finishes involve normal color variations, include samples showing the full,
range of variations expected.
2. Submit samples for verification purposes. Additional samples may be required to show
fabrication techniques and workmanship. Submit the following:
a. Include panel assembly samples not less than 12 inches by 12 inches, of each type of
assembly in thickness specified, including, but not limited to, clips, anchors, supports,
fasteners, closures, and other accessories.
b. Include samples not less than 4 inches by 8 inches, of each color and finish selected.
SECTION 07420 - 4
COMPOSITE PANELS
E.
1.7
MARCH 16, 2011
PROJECT NAME - XXXXX
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Quality Control Submittals:
1. Qualification Data: Submit qualification data for firms and persons specified in Quality
Assurance Article to demonstrate their capabilities and experience. Include lists of completed
projects with project names and addresses, names of architects and owners, and other
information specified.
2. Test Reports: Submit product test reports from a qualified independent inspecting and testing
agency showing compliance of composite panels with requirements, based on comprehensive
testing of current product formulations within the last two years.
QUALITY ASSURANCE
A.
Qualifications:
1. Manufacturer Qualifications: Manufacturer shall be a firm engaged in the manufacture of
composite panels of types and sizes required, and whose products have been in satisfactory
use in similar service for a minimum of five years.
2. Installer Qualifications: Installer shall be a firm that shall have a minimum of five years of
successful installation experience with projects utilizing composite panels similar in type and
scope to that required for this Project, and shall be approved by the manufacturer.
a. Installer shall assume undivided responsibility for all components of the composite panel
system, including, but not limited to, attachment to sub-construction, panel-to-panel
joinery, panel to dissimilar material joinery, and joint seal associated with the composite
panel system.
3. Inspecting and Testing Agency Qualifications: To qualify for acceptance, an independent
inspecting and testing agency hired by the Contractor or manufacturer to test products shall
demonstrate to the Architect’s satisfaction that they are qualified according to ASTM E 329 to
conduct testing indicated.
B.
Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances,
and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary
approvals from such authorities.
C.
Mock-Ups: Prior to installation of the work, fabricate and erect mock-ups for each type of finish and
application required to verify selections made under sample submittals and to demonstrate aesthetic
effects as well as qualities of materials and execution. Build mock-ups to comply with the following
requirements, using materials indicated for final unit of work.
1. Locate mock-ups on site in location and of size indicated or, if not indicated, as directed by the
Architect.
2. Demonstrate the proposed range of aesthetic effects and workmanship to be expected in the
completed work.
3. Obtain the Architect’s acceptance of mock-ups before start of final unit of work.
4. Retain and maintain mock-ups during construction in undisturbed condition as a standard for
judging completed unit of work.
a. Accepted mock-ups in undisturbed condition at time of Substantial Completion may
become part of completed unit of work.
D.
Pre-Installation Conference: Conduct pre-installation conference in accordance with
Section 01200 - PROJECT MEETINGS. Prior to commencing the installation, meet at the Project
site to review the material selections, installation procedures, and coordination with other trades.
Mock-ups shall be reviewed during the pre-installation conference. Pre-installation conference shall
include, but shall not be limited to, the Contractor, the Installer, manufacturer’s representatives, and
any trade that requires coordination with the work. Date and time of the pre-installation conference
shall be acceptable to the Owner and the Architect.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 07420 - 5
COMPOSITE PANELS
E.
Single Source Responsibility: Obtain composite panels from a single source with resources to
produce products of consistent quality in appearance and physical properties without delaying the
work.
F.
Coordination: Coordinate composite panel systems with rain drainage work, flashing, trim, and
construction of walls and other adjoining work to provide a leakproof, secure, and non-corrosive
installation.
1.8
DELIVERY, STORAGE, AND HANDLING
A.
Deliver materials to the Project site in supplier’s or manufacturer’s original wrappings and containers,
labeled with supplier’s or manufacturer’s name, material or product brand name, and lot number, if
any. Provide markings to identify components consistently with the Drawings.
B.
Store materials in their original, undamaged packages and containers, inside a well-ventilated area
protected from weather, moisture, soiling, extreme temperatures, and humidity. Slope panels to
ensure positive drainage of any accumulated water. Do not store panels in any enclosed space
where ambient temperature can exceed 120 °F. Avoid contact with any other materials that might
cause staining, denting, or other surface damage.
C.
Exercise care in unloading, storing, and installing composite panels to prevent bending, warping,
twisting, and surface damage.
D.
Protect finish of panels by applying heavy duty removable plastic film during production in
accordance with manufacturer’s recommendations.
1.9
PROJECT CONDITIONS
A.
Weather Limitations: Proceed with installation only when existing and forecasted weather
conditions permit composite panel system work to be performed according to manufacturer's written
instructions and warranty requirements.
B.
Field Measurements: Take field measurements prior to fabrication of the work and preparation of
shop drawings, to ensure proper fitting of the work. Show recorded measurements on final shop
drawings. Notify the Owner and the Architect, in writing, of any dimensions found which are not
within specified dimensions and tolerances in the Contract Documents, prior to proceeding with the
fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the work.
1.10
WARRANTY
A.
General: See Section 01770 - CLOSEOUT PROCEDURES.
B.
Special Warranty: The Contractor shall warrant the work of this Section to be in accordance with
the Contract Documents and free from faults and defects in materials and workmanship within the
specified warranty period. This special warranty shall extend the one year period of limitations
contained in the General Conditions. The special warranty shall be countersigned by the Installer
and the manufacturer.
1. Faults and Defects: Faults and defects include, but shall not be limited to, the following:
a. Structural failures, including, but not limited to, rupturing, cracking, or puncturing.
b. Deterioration of metals, metal finishes, and other materials beyond normal weathering.
2. Warranty Period: Warranty period shall be two years from date of Substantial Completion.
SECTION 07420 - 6
COMPOSITE PANELS
MARCH 16, 2011
PROJECT NAME - XXXXX
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
C.
Special PVDF Finish Warranty: Submit a written warranty, signed by manufacturer, covering
failure of the factory-applied exterior finish within the specified warranty period and agreeing to repair
finish or replace work that shows evidence of finish deterioration. Deterioration of finish includes, but
shall not be limited to, color fade, chalking, cracking, peeling, and loss of film integrity.
1. Warranty Period: Warranty period shall be 20 years from date of Substantial Completion.
D.
Additional Owner Rights: The warranty shall not deprive the Owner of other rights the Owner may
have under other provisions of the Contract Documents and shall be in addition to and run
concurrent with other warranties made by the Contractor under requirements of the Contract
Documents.
PART 2 - PRODUCTS
2.1
A.
2.2
MANUFACTURERS
Product: Subject to compliance with requirements, provide one of the following products:
1. “Alucobond Aluminum Composite Material”, Alcan Composites USA, Inc.
2. “Reynobond”, Alcoa, Inc.
3. “Formabond Wall System”, CENTRIA.
4. “Envelope 2000”, Citadel Architectural Products, Inc.
5. “UNA-FAB”, Firestone Metal Products.
6. “Alpolic Composite Metal Panels”, Mitsubishi Chemical America, Inc.
7. “ACM 100”, Protean Construction Products, Inc.
COMPOSITE METAL PANELS
A.
General: Provide two sheets of aluminum sandwiching a solid core of thermoplastic material
formed in a continuous process with no glues or adhesives between dissimilar materials. The
core material shall be free of voids and air spaces and shall not contain foamed insulation
material.
B.
Core: Provide thermoplastic material that meets performance characteristics specified when
fabricated into composite assembly.
C.
Face Sheets: Provide manufacturer’s standard aluminum alloy, 0.020 inch thick, and as follows:
1. Coil-coated with specified high performance finish or Spray coated with specified finish.
D.
Panel Characteristics:
1. Panel Thickness and Weight: 0.157 inch, 1.12 psf or less if performance criteria can be
met.
2. Bond Integrity: Tested for resistance to delamination as follows:
a. Bond strength shall be 1000 psi minimum, per ASTM C 297.
b. Peel strength shall be 22.5 in.lb./inch minimum, per ASTM D 1781. There shall be no
change in peel strength after eight hours of submersion in boiling water and after 21 days
of immersion in water at 70 °F.
3. Surface Burning Characteristics:
a. Flame Spread: 0, when tested per ASTM E 84. There shall be no flame spread along
interior face or penetration through the wall assembly when tested in accordance with
ICBO UBC No. 17-5.
b. Smoke Developed: 10 maximum, when tested per ASTM E 84.
c. Surface Flammability: There shall be no surface flaming when tested in accordance
with ASTM E 162.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
E.
2.3
SECTION 07420 - 7
COMPOSITE PANELS
Tolerances:
1. Width: ±0.08 inch.
2. Length: ±0.16 inch.
3. Panel Bow: Maximum 0.8 percent of any 72 inch panel dimension.
4. Squareness: Maximum 0.20 inch.
5. Flatness: Maximum deviation from panel flatness shall be 1/8 inch in 5 feet on panel in any
direction for assembled units (non-accumulative, no oil-canning).
ACCESSORIES
A.
Extrusions, formed members, sheet, and plate shall conform with ASTM B 209 and the
recommendations of the manufacturer.
B.
Panel stiffeners, if required, shall be structurally fastened or restrained at the ends and shall be
secured to the rear face of the composite panel with silicone of sufficient size and strength to
maintain panel flatness. Stiffener material and finish shall be compatible with the silicone.
C.
Sealants and gaskets within the composite panel system shall be as per manufacturer's
standards to meet performance requirements.
D.
Fabricate flashing materials from 0.030 inch minimum thickness aluminum sheet painted to match
the adjacent composite panel system where exposed.
E.
Provide fasteners as recommended by composite panel manufacturer. Do not expose fasteners
except where unavoidable and then match finish of adjoining metal.
2.4
FABRICATION
A.
General: Shop fabricate to sizes and joint configurations indicated on the Drawings. Field
fabrication shall be allowed where necessary, but shall be kept to an absolute minimum.
Fabrication shall be done under controlled shop conditions when possible. Form panel lines,
breaks, and angles to be sharp and true, with surfaces that are free from warp or buckle.
Fabricate with sharply cut edges, with no displacement of aluminum sheet or protrusion of core.
B.
System Type and Characteristics:
1. Wet System Type: System shall provide a wet seal (caulked) reveal joint as detailed on the
Drawings. The sealant type shall be as specified in Section 07900 - JOINT SEALERS and
with foamed type backer rod as indicated on the Drawings.
2. Characteristics:
a. System shall not have any visible fasteners, telegraphing, or fastening on the panel faces
or any other compromise of a neat and flat appearance.
b. System shall comply with the applicable provisions of AAMA MCWM-1 and
AAMA SFM-1, and with AAMA/WDMA 101/I.S. 2 requirements for aluminum windows.
c. Fabricate composite panel system to dimension, size, and profile indicated on the
Drawings based on a design temperature of 70 °F.
d. Fabricate composite panel system so that no restraints can be placed on the panel which
might result in compressive skin stresses. The installation detailing shall be such that
the panels remain flat regardless of temperature change and at all times remain airtight
and watertight.
e. The finish side of the panel shall have a removable plastic film applied prior to fabrication
which shall remain on the panel during fabrication, shipping, and erection to protect the
surface from damage.
SECTION 07420 - 8
COMPOSITE PANELS
3.
C.
2.5
MARCH 16, 2011
PROJECT NAME - XXXXX
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Basis of Design: "UNA-CLAD Series 1000", Firestone Metal Products, modified to depth
indicated on the drawings.
Sheet Metal Accessories: Fabricate flashing and trim to comply with recommendations in
SMACNA ASMM that apply to the design, dimensions, metal, and other characteristics of item
indicated.
1. Form exposed sheet metal accessories that are without excessive oil-canning, buckling, and
tool marks and that are true to line and levels indicated, with exposed edges folded back to
form hems.
2. Fabricate non-moving seams in accessories with flat-lock seams. Form seams and seal with
epoxy seam sealer. Rivet joints for additional strength.
3. Form non-expansion but movable joints in metal to accommodate elastomeric sealant to
comply with SMACNA standards.
4. Conceal fasteners and expansion provisions where possible. Exposed fasteners are not
allowed on faces of accessories exposed to view.
5. Fabricate cleats and attachment devices from same material as accessory being anchored or
from compatible, non-corrosive metal recommended by metal panel manufacturer. Size shall
be as recommended by SMACNA ASMM or metal panel manufacturer for application but not
less than thickness of metal being secured.
FINISHES
A.
General: Comply with NAAMM MFM for recommendations relative to application and designation of
finishes.
1. Finish designations prefixed by "AA" conform to the system established by the Aluminum
Association for designating aluminum finishes.
2. Remove die markings, scratches, abrasions, dents, and other blemishes before applying
finish.
B.
High Performance Organic Coating: AA-C12-C42-R1x (Chemical Finish: cleaned with inhibited
chemicals; Chemical Finish: chemical conversion coating, acid chromate-fluoride-phosphate
pretreatment; Organic Coating: as specified below). Prepare, pretreat, and apply coating to
exposed metal surfaces to comply with coating and resin manufacturer's instructions.
1. Standard Two-Coat Polyvinylidene Fluoride (PVDF) Finish Coating: Manufacturer's
standard thermocured system, complying with AAMA 2605, composed of specially
formulated inhibitive primer and fluoropolymer color topcoat containing not less than
70 percent PVDF resin by weight, as produced by Arkema, Inc. ("Kynar 500") or by Solvay
Solexis, Inc. ("Hylar 5000"). Provide minimum 1.2 mil total dry film thickness.
a. Color and Gloss: Match the Architect's sample. (Intended to match Accent Brick color
specified in Section 04210 - BRICK.)
b. PVDF Touch-Up Finish: PVDF finish coating, containing fluoropolymer resin and
formulated for air-drying at ambient temperature. Provide for field touch-up and furnish
in color to match shop-applied finishes.
PART 3 - EXECUTION
3.1
A.
EXAMINATION
Verification of Conditions: Examine areas and conditions under which the work is to be installed,
and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions
detrimental to the proper and timely completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
1.
3.2
SECTION 07420 - 9
COMPOSITE PANELS
Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by
the Installer.
INSTALLATION
A.
Install girts, angles, and other secondary structural panel support members and anchorage
according to ASTM C 754 and composite panel manufacturer's written recommendations.
B.
Install panels plumb, level, and true, in compliance with manufacturer's recommendations.
C.
Erect and anchor panels securely in place, in accordance with the final shop drawings.
Attachment system shall allow for the free and noiseless vertical and horizontal thermal
movement due to expansion and contraction for a material temperature range of -20 °F to 180 °F.
Buckling of panels, opening of joints, undue stress on fasteners, failure of sealants or any other
detrimental effects due to thermal movement will not be permitted. Fabrication, assembly, and
erection procedure shall account for the ambient temperature at the time of the respective
operation.
D.
Comply with manufacturer’s instructions for installation of concealed fasteners and with provisions
of Section 07900 - JOINT SEALERS for installation of joint sealers.
E.
Comply with composite panel manufacturer's recommendations and guidelines for field forming of
panels.
F.
Do not install component parts which are observed to be defective, including, but not limited to,
warped, bowed, dented, abraised, and broken members.
G.
Do not cut, trim, weld, or braze component parts during erection in a manner which would damage
the finish, decrease strength, or result in visual imperfection or a failure in performance. Return
component parts which require alteration to shop for refabrication, if possible, or for replacement
with new parts.
H.
Separate dissimilar metals and use gasketed fasteners where needed to eliminate the possibility
of corrosive or electrolytic action between metals.
I.
Maximum deviation from vertical and horizontal alignment of erected panels shall be 1/4 inch in
20 feet, non-accumulative.
3.3
FIELD QUALITY CONTROL
A.
General: See Section 01410 - INSPECTING AND TESTING SERVICES.
B.
Testing: Hose test in accordance with Section 08900 - EXTERIOR WALL PERFORMANCE
REQUIREMENTS.
C.
Inspection: Inspecting and testing agency shall inspect and report on all connections and welds.
3.4
ADJUSTING
A.
Remove and replace composite panels damaged beyond repair. Repair panels with minor
damage so that repairs are not discernible at a distance of 10 feet.
B.
Remove protective film immediately after installation of joint sealers and immediately prior to
completion of composite metal panel work.
SECTION 07420 - 10
COMPOSITE PANELS
MARCH 16, 2011
PROJECT NAME - XXXXX
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
C.
Make sure weepholes and drainage channels are unobstructed and free of dirt and sealants.
D.
Remove from the job site damaged panels, protective film, and other debris attributable to work of
this Section.
3.5
A.
PROTECTION
Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall
ensure that the composite panels shall be without damage at time of Substantial Completion.
END OF SECTION
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 10152 - 1
HOSPITAL CUBICLE CURTAINS AND TRACKS
SECTION 10152
HOSPITAL CUBICLE CURTAINS AND TRACKS
PART 1 - GENERAL
1.1
A.
1.2
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General Conditions,
Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project
Manual apply to the work specified in this Section.
SUMMARY
A.
Scope: Provide labor, material, equipment, related services, and supervision required, including, but
not limited to, manufacturing, fabrication, erection, and installation for hospital cubicle curtains and
tracks as required for the complete performance of the work, and as shown on the Drawings and as
herein specified.
B.
Section Includes: The work specified in this Section includes, but shall not be limited to, the
following:
1. Hospital cubicle curtains.
2. Hospital cubicle curtain tracks.
1.3
REFERENCES
A.
The publications listed below form a part of this Specification to the extent referenced. The
publications are referred to in the text by the basic designation only.
B.
The edition/revision of the referenced publications shall be the latest date as of the date of the
Contract Documents, unless otherwise specified.
C.
American Architectural Manufacturers Association (AAMA):
1. AAMA 611, "Voluntary Specifications for Anodized Architectural Aluminum (Revised).”
D.
ASTM (ASTM):
1. ASTM B 221, "Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars,
Rods, Wire, Shapes, and Tubes."
2. ASTM E 84, "Standard Test Method for Surface Burning Characteristics of Building
Materials."
E.
National Association of Architectural Metal Manufacturers (NAAMM):
1. NAAMM MFM, "Metal Finishes Manual."
1.4
SUBMITTALS
A.
General: See Section 01300 - SUBMITTALS.
B.
Product Data: Submit product data showing material proposed. Submit sufficient information to
determine compliance with the Drawings and Specifications.
SECTION 10152 - 2
HOSPITAL CUBICLE CURTAINS AND TRACKS
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
C.
Shop Drawings: Submit shop drawings for each product and accessory required. Include
information not fully detailed in manufacturer’s standard product data, including, but not limited to,
layout of tracks and method of anchorage.
D.
Samples:
1. Submit samples for initial color selection. Submit samples of each specified finish. Submit
samples in form of manufacturer’s color charts showing full range of colors and finishes
available. Where finishes involve normal color variations, include samples showing the full,
range of variations expected.
2. Submit samples for verification purposes. Submit the following:
a. One 12 inch long piece of cubicle curtain track with carrier access and end stop.
b. One clip anchor for fastening track to grid system of acoustical ceilings.
c. One curtain carrier.
E.
Qualification Data: Submit qualification data for firms and persons specified in Quality Assurance
Article to demonstrate their capabilities and experience. Include lists of completed projects with
project names and addresses, names of architects and owners, and other information specified.
1.5
QUALITY ASSURANCE
A.
Qualifications:
1. Manufacturer Qualifications: Manufacturer shall be a firm engaged in the manufacture of
hospital cubicle curtains and tracks of types and sizes required, and whose products have been
in satisfactory use in similar service for a minimum of five years.
2. Installer Qualifications: Installer shall be a firm that shall have a minimum of five years of
successful installation experience with projects utilizing hospital cubicle curtains and tracks
similar in type and scope to that required for this Project.
B.
Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances,
and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary
approvals from such authorities.
C.
Surface Burning Characteristics: Provide hospital cubicle curtains with the surface burning
characteristics as indicated below, as determined by testing identical products per ASTM E 84, by
Underwriters Laboratories, Inc. (UL), Intertek Testing Services (ITS), or other inspecting and
testing agency acceptable to authorities having jurisdiction. Identify hospital cubicle curtains with
appropriate markings of applicable inspecting and testing agency.
1. Flame Spread: 25 or less.
2. Smoke Developed: 450 or less.
D.
Single Source Responsibility: Obtain hospital cubicle curtains, tracks, and related accessories
from a single source with resources to produce products of consistent quality in appearance and
physical properties without delaying the work.
1.6
A.
DELIVERY, STORAGE, AND HANDLING
Deliver materials to the Project site in supplier’s or manufacturer’s original wrappings and containers,
labeled with supplier’s or manufacturer’s name, material or product brand name, and lot number, if
any. Do not open packages until contents are needed for installation, unless verification
inspection is required.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
B.
1.7
A.
SECTION 10152 - 3
HOSPITAL CUBICLE CURTAINS AND TRACKS
Store materials in their original, undamaged packages and containers, inside a well-ventilated area
protected from weather, moisture, soiling, extreme temperatures, and humidity. Store so as to not
bend or warp the tracks.
PROJECT CONDITIONS
Field Measurements: Take field measurements prior to fabrication of the work and preparation of
shop drawings, to ensure proper fitting of the work. Show recorded measurements on final shop
drawings. Notify the Owner and the Architect, in writing, of any dimensions found which are not
within specified dimensions and tolerances in the Contract Documents, prior to proceeding with the
fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the work.
PART 2 - PRODUCTS
2.1
A.
2.2
CUBICLE CURTAINS
General: Cubicle curtains shall be minimum 10 percent wider than the track upon which they run.
Cubicle curtains shall hang to within 15 inches above the finished floor.
1. Curtains Without Nylon Mesh Tops: Provide top hem of 1-1/2 inch width with three
thicknesses of fabric. An integral webbing shall be provided in the top hem to ensure proper
gripping of the grommets. The bottom hem shall be 1 inch wide, triple thickness, and the
side hems shall be 1 inch wide with triple thickness of material. No crooked selvage edges
shall be used in place of side hems. Vertical seams shall be overlapped and sewn with a
double needle, interlocked stitch to ensure straightness and strength of seams. Bottom hem
sewing shall be turned vertically at each corner to prevent unraveling of sewing thread.
Sewing shall be performed with lock stitch machines. Grommets shall be nickel-plated brass
and shall be machined into the top hem at 6 inch intervals. These grommets shall be firmly
anchored into the triple thickness of the hem.
2. Color and Pattern: As selected by the Architect from the manufacturer’s standards.
CUBICLE CURTAIN TRACKS
A.
Surface-Mounted Type Channel Tracks: Provide extruded aluminum, ASTM B 221, Alloy 6063,
Temper T5 or Temper T6, channel-shaped, with smooth inside raceway for curtain carriers.
B.
Curtain Carriers: Provide nylon or delrin carriers, with either nylon or delrin wheels on metal,
delrin, or nylon axles. Equip each carrier with either stainless steel, chromium-plated brass, or
steel hooks with swivel, or nickel chromium-plated brass or stainless steel bead chain and hook
assembly, or delrin carriers may have molded-on delrin hooks. Hook for bead chain may be the
same material and finish as the bead chain or may be chromium-plated steel. Provide 2.2 carriers
for every foot of each section of each track length, plus one additional carrier.
C.
End Stop Connectors, Ceiling Flanges, and Other Accessories: Fabricate from the same
material with the same finish as the tracks or from nylon.
2.3
FASTENERS
A.
Exposed Fasteners, Screws, and Bolts: Provide stainless steel or chromium/nickel-plated
brass.
B.
Concealed Fasteners, Screws, and Bolts: Provide hot-dip galvanized (except in high moisture
areas use stainless steel).
SECTION 10152 - 4
HOSPITAL CUBICLE CURTAINS AND TRACKS
C.
2.4
A.
2.5
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
Metal Clips: Anchor curtain tracks to exposed grid of lay-in acoustical panel ceilings, with
concealed metal (butterfly) type or two-piece snap locking type of high strength spring steel.
FABRICATION
Weld and grind smooth joints of fabricated components. Form tracks and bends of lengths that
will produce the minimum number of joints. Make track sections up to 16 feet without joints.
Form corner bend on a 12 inch radius. Provide steel anchor plates, supports, and anchors for
securing components to building construction. Form flat surface without distortion. Shop
assemble components and package complete with anchors and fittings.
FINISHES
A.
General: Comply with NAAMM MFM for recommendations relative to application and designation of
finishes.
1. Finish designations prefixed by "AA" conform to the system established by the Aluminum
Association for designating aluminum finishes.
B.
Aluminum Class II Clear Anodized Finish: AA-M12-C22-A31 (Mechanical Finish: as fabricated,
non-specular; Chemical Finish: etched, medium matte; Anodic Coating: Class II Architectural,
clear film thicker than 0.4 mil) complying with AAMA 611.
PART 3 - EXECUTION
3.1
A.
3.2
EXAMINATION
Verification of Conditions: Examine areas and conditions under which the work is to be installed,
and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions
detrimental to the proper and timely completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected.
1. Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by
the Installer.
INSTALLATION
A.
Install tracks after finish painting and ceiling finishing operations are complete.
B.
Anchor surface-mounted curtain tracks directly to exposed grid of lay-in acoustical panel ceilings
with concealed metal clips, spaced approximately 24 inches on center.
C.
Securely fasten end stop caps to prevent their being forced out by the striking weight of carriers.
D.
Remove damaged or defective components and replace with new components or repair to the
original condition.
E.
Track shall be installed neat, rigid, plumb, level and true, and securely anchored to the overhead
construction.
F.
Carrier units shall operate smoothly and easily over the full range of travel.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
3.3
A.
SECTION 10152 - 5
HOSPITAL CUBICLE CURTAINS AND TRACKS
PROTECTION
Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall
ensure that the hospital cubicle curtains and tracks shall be without damage at time of Substantial
Completion.
END OF SECTION
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
SECTION 10531 - 1
ALUMINUM CANOPY STRUCTURES
SECTION 10531
ALUMINUM CANOPY STRUCTURES
PART 1 - GENERAL
1.1
A.
1.2
RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General Conditions,
Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project
Manual apply to the work specified in this Section.
SUMMARY
A.
Scope: Provide design and engineering, labor, material, equipment, related services, and
supervision required, including, but not limited to, manufacturing, fabrication, erection, and
installation for aluminum canopy structures as required for the complete performance of the work,
and as shown on the Drawings and as herein specified.
B.
Section Includes: The work specified in this Section includes, but shall not be limited to,
prefabricated aluminum pedestrian canopy structure system designed and engineered by system
manufacturer.
1.3
REFERENCES
A.
The publications listed below form a part of this Specification to the extent referenced. The
publications are referred to in the text by the basic designation only.
B.
The edition/revision of the referenced publications shall be the latest date as of the date of the
Contract Documents, unless otherwise specified.
C.
Aluminum Association, Inc. (AA):
1. AA SAS-30, "Specifications for Aluminum Structures."
D.
American Architectural Manufacturers Association (AAMA):
1. AAMA 2604, " Voluntary Specification, Performance Requirements and Test Procedures for
High Performance Organic Coatings on Aluminum Extrusions and Panels."
E.
American Society of Civil Engineers (ASCE):
1. ASCE 7, "Minimum Design Loads for Buildings and Other Structures" (copyrighted by ASCE,
ANSI approved).
F.
ASTM (ASTM):
1. ASTM B 209, "Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate."
2. ASTM B 221, "Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods,
Wire, Shapes, and Tubes."
3. ASTM C 1107, "Standard Specification for Packaged Dry, Hydraulic-Cement Grout
(Non-Shrink).”
G.
Green Seal (GS):
1. GS-37, “Industrial & Institutional Cleaners.”
SECTION 10531 - 2
ALUMINUM CANOPY STRUCTURES
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
H.
National Association of Architectural Metal Manufacturers (NAAMM):
1. NAAMM MFM, "Metal Finishes Manual."
I.
Underwriters Laboratories, Inc. (UL):
1. UL 972, "Standard for Burglary Resisting Glazing Material" (copyrighted by UL, ANSI approved).
1.4
SYSTEM DESCRIPTION
A.
General: Metal canopy structure shall have internal drainage from deck to gutter and downspout
through columns. Accessories shall be aluminum.
B.
Designer Requirements: Engage and pay for the services of an engineer to design the aluminum
canopy structure system, including, but not limited to, foundations.
C.
Structural Requirements: Design aluminum canopy structure system and connections in
accordance with the referenced standards and the applicable local code for wind load and live load
criteria.
1.5
SUBMITTALS
A.
General: See Section 01300 - SUBMITTALS.
B.
Product Data: Submit product data showing material proposed. Submit sufficient information to
determine compliance with the Drawings and Specifications. Product data shall include, but shall not
be limited to, manufacturer's product information, specifications, and installation instructions for
building components and accessories.
C.
Shop Drawings: Submit complete shop drawings, including, but not limited to, layout, necessary
plan dimensions, elevations, and details.
1. Include location and details of anchorage devices that are to be embedded in other
construction. Furnish templates if required for accurate placement.
2. Shop drawings shall be signed and sealed by the professional engineer.
3. Verify with the Contractor dimensions and elevations at each column and any related soffit
before fabrication.
D.
Samples:
1. Submit samples for initial color selection. Submit samples of each specified finish. Submit
samples in form of manufacturer’s color charts showing full range of colors and finishes
available. Where finishes involve normal color variations, include samples showing the full,
range of variations expected.
2. Submit samples for verification purposes. Submit samples of aluminum finishes for roof panel
and extruded support structure.
E.
Quality Control Submittals:
1. Design Data: Submit design calculations for aluminum canopy structure system and
connections attaching it to the main building structure. The design data shall be signed and
sealed by the professional engineer. Only loading on the main building structure at any
connections will be reviewed.
2. Qualification Data: Submit qualification data for firms and persons specified in Quality
Assurance Article to demonstrate their capabilities and experience. Include lists of completed
projects with project names and addresses, names of architects and owners, and other
information specified.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
1.6
SECTION 10531 - 3
ALUMINUM CANOPY STRUCTURES
QUALITY ASSURANCE
A.
Qualifications:
1. Manufacturer Qualifications: Manufacturer shall be a firm engaged in the manufacture of
aluminum canopy structures of types and sizes required, and whose products have been in
satisfactory use in similar service for a minimum of five years.
2. Installer Qualifications: Installer shall be a firm that shall have a minimum of five years of
successful installation experience with projects utilizing aluminum canopy structures similar in
type and scope to that required for this Project, and shall be approved by the manufacturer.
3. Engineer Qualifications: The engineer shall be a professional engineer legally authorized to
practice in the jurisdiction where the Project is located and experienced in providing engineering
services of the kind indicated that have resulted in the installation of products similar to this
Project in material, design, and extent, and that have a record of successful in-service
performance.
B.
Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances,
and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary
approvals from such authorities.
1. The completed aluminum canopy structure system and its structural system shall meet
applicable state and local building code requirements.
C.
Standards: Comply with applicable requirements of AA SAS-30 and ASCE 7.
D.
Single Source Responsibility: Obtain aluminum canopy structure, including, but not limited to, all
necessary components and accessories, from a single source with resources to produce products of
consistent quality in appearance and physical properties without delaying the work, or from a source
approved by the aluminum canopy structure manufacturer.
1.7
DELIVERY, STORAGE, AND HANDLING
A.
Deliver materials to the Project site in supplier’s or manufacturer’s original wrappings and containers,
labeled with supplier’s or manufacturer’s name, material or product brand name, and lot number, if
any.
B.
Store materials in their original, undamaged packages and containers, inside a well-ventilated area
protected from weather, moisture, soiling, extreme temperatures, and humidity.
C.
Deliver, store, and handle aluminum canopy structure system as recommended by manufacturer.
1.8
A.
1.9
A.
PROJECT CONDITIONS
Field Measurements: Take field measurements prior to fabrication of the work and preparation of
shop drawings, to ensure proper fitting of the work. Show recorded measurements on final shop
drawings. Notify the Owner and the Architect, in writing, of any dimensions found which are not
within specified dimensions and tolerances in the Contract Documents, prior to proceeding with the
fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the work.
SEQUENCING AND SCHEDULING
Concrete Footings: Layout and footings blockout shall be provided by aluminum canopy system
manufacturer. Concrete, reinforcement, and formwork requirements are specified in
Division 3 - CONCRETE.
SECTION 10531 - 4
ALUMINUM CANOPY STRUCTURES
1.10
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
WARRANTY
A.
General: See Section 01770 - CLOSEOUT PROCEDURES.
B.
Special PVDF Finish Warranty: Submit a written warranty, signed by manufacturer, covering
failure of the factory-applied exterior finish within the specified warranty period and agreeing to repair
finish or replace work that shows evidence of finish deterioration. Deterioration of finish includes, but
shall not be limited to, color fade, chalking, cracking, peeling, and loss of film integrity.
1. Warranty Period: Warranty period shall be 5 years from date of Substantial Completion.
C.
Additional Owner Rights: The warranty shall not deprive the Owner of other rights the Owner may
have under other provisions of the Contract Documents and shall be in addition to and run
concurrent with other warranties made by the Contractor under requirements of the Contract
Documents.
PART 2 - PRODUCTS
2.1
A.
2.2
MANUFACTURERS
Manufacturer: Subject to compliance with requirements, provide products of one of the following:
1. Dittmer Architectural Aluminum.
2. Peachtree Protective Covers.
3. Perfection Architectural Systems, Inc.
4. Royal Aluminum Inc.
MATERIALS
A.
Aluminum:
1. Sheets: ASTM B 209 for Alloy 3105 H-28; minimum yield 30,000 ksi, or alloy and temper
required to suit forming operations and finish requirements.
2. Extruded: ASTM B 221 Alloy 6061-T6, Alloy 6063-T5 and T6, or alloy and temper required to
suit structural and finish requirements.
B.
Hardware: Provide plated non-corrosive hardware as recommended by manufacturer.
C.
Non-Metallic, Non-Shrink Grout: Provide premixed, non-metallic, non-corrosive, non-staining
grout containing selected silica sands, portland cement, shrinkage-compensating agents,
plasticizing and water-reducing agents, complying with ASTM C 1107, with fluid consistency and a
30 minute working time. Provide grout specifically recommended by manufacturer for
applications.
D.
Gaskets: Provide manufacturer's standard design of neoprene or EPDM.
E.
Sealants: See Section 07900 - JOINT SEALERS.
F.
Flashing and Other Non-Structural Items: Provide as recommended by manufacturer.
G.
Accessories: Provide accessory items only as produced and recommended by manufacturer of
primary product.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
2.3
SECTION 10531 - 5
ALUMINUM CANOPY STRUCTURES
COMPONENTS
A.
Columns: Columns shall be extruded aluminum sections of sizes, shapes, and gage to meet
required design loads, and as indicated on the Drawings.
B.
Beams: Beams shall be extruded aluminum sections of sizes, shapes, and gage to meet required
design loads, and as indicated on the Drawings. Top edges shall be thickened for strength and
designed to receive deck members in self-flashing manner. Structural ties shall be installed in tops
of beams.
C.
Deck: Provide load-bearing aluminum roof deck properly supported by the primary framing
members. Roof deck shall use interlocking joints designed and fabricated to provide structural
continuity and self-flashing. Gage shall be sufficient to meet required design loads. Closures at
deck ends shall be welded plates.
D.
Fascia: Fascia shall be manufacturer’s standard shape, size as indicated on the Drawings.
E.
Flashing: Flashing shall be 0.040 inch aluminum, minimum. Thru-wall flashing will be by others.
F.
Water Drainage System: Provide cutouts and internal deflectors in members as recommended by
manufacturer to act as internal water drainage system.
2.4
FABRICATION
A.
Design: Aluminum canopy structure shall be all-welded extruded aluminum system complete with
internal drainage. Non-welded systems are not acceptable. Roll-formed deck is not acceptable.
Expansion joints shall be included to accommodate temperature changes of 120 °F. Expansion
joints shall have no metal-to-metal contact.
B.
Bent Construction: Beams and columns shall be factory-welded with neatly mitered corners into
one-piece rigid bents. Welds shall be smooth and uniform. Suitable edge preparation shall be
performed to assure 100 percent penetration. Grind welds only where interfering with adjoining
structure to allow for flush connection. Field welding is not permitted. Rigid mechanical joints shall
be used when shipping limitations prohibit the shipment of fully welded bents.
C.
Deck Construction: Deck shall be manufactured of extruded modules that interlock in a
self-flashing manner. Interlocking joints shall be positively fastened at 8 inch on center creating a
monolithic structural unit capable of developing the full strength of the sections. The fastenings shall
have minimum shear strength of 350 pounds each. Deck shall be assembled with sufficient camber
to offset dead load deflection.
2.5
A.
FINISHES
General: Comply with NAAMM MFM for recommendations relative to application and designation of
finishes.
1. Finish designations prefixed by "AA" conform to the system established by the Aluminum
Association for designating aluminum finishes.
2. Remove die markings, scratches, abrasions, dents, and other blemishes before applying
finish.
3. Finish for non-exposed aluminum extrusion or member shall be manufacturer's standard finish.
SECTION 10531 - 6
ALUMINUM CANOPY STRUCTURES
B.
MARCH 16, 2011
KING SPRINGS ELEMENTARY SCHOOL
ADDITIONS AND MODIFICATIONS - 20100358
CCSD PROJECT NO. 224/8032
High Performance Organic Coating: Prepare, pretreat, and apply coating to exposed metal
surfaces to comply with coating and resin manufacturer's instructions.
1. Standard Two-Coat Polyvinylidene Fluoride (PVDF) Finish Coating: Manufacturer's
standard thermocured system, complying with AAMA 2604, composed of specially
formulated inhibitive primer and fluoropolymer color topcoat containing not less than
50 percent PVDF resin by weight, as produced by Arkema, Inc. ("Kynar 500") or by Solvay
Solexis, Inc. ("Hylar 5000") and manufacturer's standard additive to produce a "metallic" color
finish. Provide minimum 1.2 mil total dry film thickness.
a. Color and Gloss: Match Architect's sample.
b. PVDF Touch-Up Finish: PVDF finish coating, containing fluoropolymer resin and
formulated for air-drying at ambient temperature. Provide for field touch-up and furnish
in color to match shop-applied finishes.
2. Basis of Design: Permadized Hardcoat Finish, by Kawneer.
PART 3 - EXECUTION
3.1
A.
3.2
A.
3.3
A.
3.4
A.
B.
3.5
A.
EXAMINATION
Verification of Conditions: Examine areas and conditions under which the work is to be installed,
and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions
detrimental to the proper and timely completion of the work. Do not proceed with the work until
unsatisfactory conditions have been corrected.
1. Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by
the Installer.
PREPARATION
Installation shall not start until concrete, masonry, and roofing work in the vicinity is complete and
cleaned.
INSTALLATION
Install aluminum canopy structure system with fasteners, connections, and sealants in strict
accordance with manufacturer's written instructions, reviewed product data, and final shop drawings.
1. Aluminum canopy structures shall be erected true to line, level and plumb. Aluminum columns
embedded in concrete shall be protected by manufacturer’s recommended coating.
ADJUSTING AND CLEANING
Touch-up minor scratches and abrasions. Aluminum canopy structures and components shall be
cleaned promptly after installation in accordance with manufacturer’s recommendations.
No cleaning products or processes shall exceed listed VOC limits or use ozone - depleting
substances. Cleaning materials shall comply with GS-37.
PROTECTION
Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall
ensure that the aluminum canopy structures shall be without damage at time of Substantial
Completion.
END OF SECTION
MARCH 16, 2011 - ADDENDUM #1
KING SPRINGS ELEMENTARY SCHOOL
RENOVATION AND ADDITION – 20100358
CCSD PROJECT NO. 224/8032
BW&A 10958
SECTION 15800 - 1
AIR DISTRIBUTION DEVICES
SECTION 15800
AIR DISTRIBUTION DEVICES
PART 1 - GENERAL
1.1
1.2
DESCRIPTION
A.
All work specified in this section is governed by the Mechanical General Section 15010.
B.
This Section 15800 and the accompanying drawings cover the provisions of all labor,
equipment, appliances and materials, and performing all operations in connection with
the construction and installation of air distribution devices as specified herein and as
shown. These units include, but are not limited to the following:
Ceiling Diffusers (CD)
2.
Return Air Grilles (RAG)
3.
Exhaust Registers (ER)
4.
Exhaust Grilles (EG)
5.
Slot Diffusers (SD)
6.
Return Air Slots (RS)
7.
Supply Registers (SR)
8.
Supply Grilles (SG)
9.
Return Air Registers (RAR)
10.
Linear Slot Diffusers (LSD)
11.
Linear Return Slots (LRS)
12.
Linear Exhaust Slots (LES)
13.
Transfer Grilles (TG)
14.
Architectural Linear Slot (ALS)
INTENT
A.
1.3
1.
It is the intent of this Section of the specifications to provide complete, operable, adjusted
air distribution devices as shown and specified which are free of excessive noise,
vibration and airflow fluctuations.
SELECTION CRITERIA
A.
All air distribution devices shall be selected in accordance with the following minimum
SECTION 15800 - 2
AIR DISTRIBUTION DEVICES
MARCH 16, 2011 - ADDENDUM #1
KING SPRINGS ELEMENTARY SCHOOL
RENOVATION AND ADDITION – 20100358
CCSD PROJECT NO. 224/8032
BW&A 10958
criteria unless otherwise noted below or on the drawings:
1.
Method of mounting shall be compatible with the ceiling, wall or duct surface
which it mounts on or in; i.e. lay-in, surface mounting, plaster frame, duct collar,
etc. The architectural drawings shall be referenced to determine the mounting
method for each device. All flanges on surface mounted devices shall be
provided with a gasket.
1.4
Finish of all ceiling mounted devices shall be selected to match the color of the
adjacent ceiling. Finish of all wall mounted devices shall be primer which is
compatible with the finish coating specified for the adjacent wall; finish coat will
be applied under Division 9.
3.
Noise Criteria for classrooms shall be 25-30 NC; the music room shall be 20 to
25 NC. All other spaces shall be as listed under PART 2 - PRODUCTS.
BASIS OF DESIGN
A.
1.5
2.
The basis of design is Carnes. Any proposed substitutions shall be proven equal in all
respects to the equipment specified as the basis of design. Any modifications to
ductwork, controls, ceilings, building structure, etc., that result from any substitution shall
be coordinated with all trades. This coordination shall occur before delivery of equipment
and any modifications shall be performed without incurring additions to the Contract.
ACCEPTABLE MANUFACTURERS
A.
Acceptable manufacturers are Price, Metal Aire, Nailor and Titus, provided that their
units, performance, appearance and physical characteristics are equal in all respects for
this specific project.
PART 2 - PRODUCTS
2.1
DESCRIPTION
A.
Ceiling Diffuser (CD)
1.
B.
Return Air Grilles (RAG)
1.
C.
Ceiling diffusers shall be perforated face diffusers equipped with fully adjustable
pattern controls, capable of providing one-way, two-way, two-way corner, threeway, and four-way air patterns; Carnes SPAB. Diffuser performance data shall
be in accordance with ADC equipment test code 162R4. The perforated face
shall be hinged for easy access to pattern controls and duct accessories. The
maximum NC level at design airflow shall not exceed 35 when measured in a
direct field 5'-0" from the face of the device.
Return air grilles shall be hollow core, perforated face, lay-in type, selected to
match the CDs; Carnes SPRB. Performance data shall be in accordance with
ADC 1062R4. All other characteristics shall be equal to the ceiling diffusers.
Exhaust Registers (ER)
1.
Exhaust registers shall be surface mounted, fixed curved blade steel registers
MARCH 16, 2011 - ADDENDUM #1
KING SPRINGS ELEMENTARY SCHOOL
RENOVATION AND ADDITION – 20100358
CCSD PROJECT NO. 224/8032
BW&A 10958
SECTION 15800 - 3
AIR DISTRIBUTION DEVICES
with blades at 0.666 to 0.750 inches on center. Provide opposed blade dampers
with each ER for balancing purposes. ERs shall be Carnes RTLB, sized as
indicated.
D.
Exhaust Grilles (EG)
1.
E.
Exhaust grilles shall be surface mounted, fixed curved blade steel grilles with
blades at 0.666 to 0.750 inches on center. EGs shall be Carnes RSLA sized as
indicated.
Slot Diffuser
1.
Supply (SD)
a.
2.
Return (RS)
a.
F.
Supply registers shall be surface mounted, steel, adjustable double-deflection
type complete with opposed blade dampers for balancing purposes. The
outermost set of deflection blades shall be parallel to the long dimension of the
SR and the innermost set of deflection blades shall be parallel to the short
dimension of the SR. The registers shall be tested in accordance with ADC
standards and shall be selected to provide design airflow at a maximum NC of
35. SRs shall be Carnes RTDB Series, sized as indicated.
Supply Grilles (SG)
1.
H.
Return slots shall meet all above requirements for slot diffuser with the
exception that the pattern controllers shall be removed to allow maximum
free area for return air flow. Carnes DAHC.
Supply Registers (SR)
1.
G.
Each slot diffuser shall be equipped with an individually adjustable
pattern controller for each slot to insure full 180 degree air pattern;
Carnes DASC. The diffuser shall be constructed of 24 gauge galvanized
steel with inlet size and length as indicated. Each SD shall be provided
with a lined steel plenum with tappings for round duct connections as
indicated. Maximum NC level shall not exceed 35 at design airflow.
Liner shall conform to NFPA 90A 25/50 requirements.
Supply grilles shall be surface mounted, steel, adjustable double-deflection type.
The outermost set of deflection blades shall be parallel to the long dimension of
the SG and the innermost set of deflection blades shall be parallel to the short
dimension of the SG. The grilles shall be tested in accordance with ADC
standards and shall be selected to provide design airflow at a maximum NC of
35. SGs shall be Carnes RSDB Series, sized as indicated.
Return Air Registers (RAR)
1.
Return air registers shall be surface mounted, steel, registers with curved
hemmed edge blades with an opposed blade damper. Damper blades shall be
gang operated by means of a key which can be removed after balancing. RARs
shall be Carnes RTLA, sized as indicated.
SECTION 15800 - 4
AIR DISTRIBUTION DEVICES
I.
MARCH 16, 2011 - ADDENDUM #1
KING SPRINGS ELEMENTARY SCHOOL
RENOVATION AND ADDITION – 20100358
CCSD PROJECT NO. 224/8032
BW&A 10958
Linear Slot Diffuser (LSD)
1.
Supply (LSD)
a.
2.
Linear slot diffusers shall be Carnes Channelaire Model CH. Diffusers
shall be of aluminum construction with one or more parallel slot(s). Each
slot shall contain pattern controls, adjustable from the face of the
diffuser. The same pattern controls shall function as volume controls
without affecting the air discharge pattern.
Each LSD shall be
continuous length as indicated on the Drawings, complete with finished
ends, mitered corners and splined joints. Plenums shall also be
provided as indicated with all open inactive sections of the LSD covered
with blank-off internal plates. Plenums shall have round collars for
connection of flexible duct. Performance data shall be per ADC with a
maximum NC of 35.
Return (LRS)
a.
Linear return slots shall equal specified LSD with the following
exceptions:
1)
2)
3.
Exhaust (LES)
a.
Linear exhaust slots shall equal specified LSD's with the following
exceptions:
1)
2)
J.
Plenums shall be lined in accordance with UL 181 and NFPA
90A.
Pattern controls shall be used for dampering only.
Transfer Grilles (TG)
1.
K.
Plenums shall be lined in accordance with ul 181 and NFPA
90A.
Pattern controls are not required.
Transfer grilles shall be similar to return air grilles (RAG)
Architectural Linear Slot (ALS)
1.
Supply (ALS)
a.
2.
Architectural linear slot shall be Carnes Channelaire wide body linear
diffuser. Diffuser shall be aluminum construction with one (1) 2” wide
slot. Diffuser shall be equipped with one (1) 2” wide slot. Diffuser shall
be equipped with an individually adjustable pattern controller. Each ALS
shall be provided with a lined stem plenum with tappings for round duct
connections as indicated. Maximum NC shall not exceed 35 at design
airflow. Linear shall conform to NFPA 90A 25/50 requirements. Border
option to be selected by Architect.
Return (ALR)
MARCH 16, 2011 - ADDENDUM #1
KING SPRINGS ELEMENTARY SCHOOL
RENOVATION AND ADDITION – 20100358
CCSD PROJECT NO. 224/8032
BW&A 10958
a.
SECTION 15800 - 5
AIR DISTRIBUTION DEVICES
Architectural return slot to be same as supply with the exception that the
pattern controllers shall be removed to allow maximum free area.
PART 3 - EXECUTION
3.1
INSTALLATION
A.
3.2
Air distribution devices shall be installed as indicated and in conformance with the
manufacturer's recommendations.
The color, frame and border types shall be
coordinated with Architectural requirements and shall be selected to install in the finished
surface indicated.
ADJUSTMENT
A.
Grilles, registers and diffusers shall be tested and adjusted to provide the scheduled air
flow capacities.
B.
All adjustable air distribution devices located within three feet of any wall shall be set to
blow directly away from, or parallel to, the wall.
C.
In all slot diffuser applications, the inactive sections of the slot shall be finished with
perforated steel, painted flat black, selected to match the CDs. These sections shall be
open to the plenum as a return air path.
END OF SECTION
MARCH 16, 2011 - ADDENDUM #1
KING SPRINGS ELEMENTARY SCHOOL
RENOVATION AND ADDITION – 20100358
CCSD PROJECT NO. 224/8032
BW&A 10958
SECTION 15840 - 1
DUCTWORK
SECTION 15840
DUCTWORK
PART 1 - GENERAL
1.1
1.2
DESCRIPTION
A.
All work specified in this Section is governed by the Mechanical General Section 15010.
B.
This Section 15840 and the accompanying drawings cover the provisions of all labor,
equipment, appliances, and materials and performing all operations in connection with
the construction of the ductwork systems as specified herein and as shown. These
systems include, but are not limited to, the following:
Supply air ductwork
2.
Return, transfer and relief air ductwork
3.
Exhaust ductwork
4.
Outside air ductwork
INTENT
A.
1.3
1.
It is the intent of this Section of the specifications to provide a complete operable duct
system as shown and specified which is reasonably airtight, free of noise, vibration and
sweating, and fabricated so as to fit into the space allotted and to exhibit a minimum
resistance to airflow.
DESIGN AND CONSTRUCTION
A.
Ductwork shall be provided in strict accordance with the first edition - 1985 - of the
SMACNA HVAC Duct Construction Standards - Metal and Flexible, NFPA No. 90A, 90B,
91 and 96, and UL 181.
B.
Ductwork dimensions shown are net, clear, inside dimensions with no allowance shown
for duct liner. All ductwork specified to be lined shall be 2" larger than shown in each
dimension to compensate for the liner. Ductwork shall be square, rectangular, round,
spiral or flat oval as noted. Conversion of duct shapes and sizes shown shall be
accomplished without increasing air velocities or friction losses and is subject to prior
approval by the Architect.
C.
Elbows shall be either full radius type (inside radius equal to duct width), five-gore
radiused flat-oval type or, in low pressure systems only, mitered with double-thickness
turning vanes.
D.
Abrupt changes in duct sizes and shapes shall not be permitted. The total angle of
diverging transitions shall be not more than 15 degrees; converging transitions shall be
not more than 30 degrees unless otherwise noted or required due to structural
SECTION 15840 - 2
DUCTWORK
E.
MARCH 16, 2011 - ADDENDUM #1
KING SPRINGS ELEMENTARY SCHOOL
RENOVATION AND ADDITION – 20100358
CCSD PROJECT NO. 224/8032
BW&A 10958
constraints.
Offsets, transitions, rises and drops are not individually called out on the design
drawings. They shall be provided as required to fit the ductwork into the allocated
spaces.
F.
Transition rectangular ductwork on bottom and sides. Maintain top of ductwork level and
as high as possible.
G.
Provide the following types of ductwork material for the services indicated:
TYPE OF MATERIAL
SERVICE
1.
Supply, return, exhaust and relief of
comfort conditioned and outside air.
Galvanized sheetmetal
PART 2 - PRODUCTS
2.1
GALVANIZED SHEETMETAL
A.
2.2
Galvanized sheetmetal shall be lock-forming grade G90-ASTM A 525 hot dip galvanized
steel sheets. Sheetmetal shall be galvanized on each side with not less than 1.25
ounces of zinc per square foot.
DAMPERS
B.
Manual Volume Dampers
1.
Single blade butterfly dampers are acceptable up to 12" round or 12" x 12"
square. Dampers larger than these dimensions shall be multi-blade type. Single
blade dampers shall be constructed of 16 gauge or heavier galvanized
sheetmetal.
2.
No multi-blade damper blade shall exceed 8" in width. All multiple blade
dampers shall be constructed of 16 gauge galvanized steel or heavier. The
damper frame shall be 16 gauge or heavier. The damper action shall be
opposed-blade type.
3.
Each blade shall pivot on a 1/2" cadmium plated, cold-rolled steel axle which
pivots within self-lubricating, oilite bronze bearings.
4.
The top and bottom edges of each rectangular damper blade shall be crimped for
stiffness.
5.
The operating rod for all dampers shall be extended outside the damper frame
for attachment of an operator. Each operator shall have a position indicator and
locking quadrant.
6.
All dampers utilized for introduction of outside air shall have flexible, gasketed
edge and end seals. The leakage rate shall be less than 4 CFM per sq. ft. of
face area against a 1" W.G. differential pressure, based on a nominal 48" x 48"
MARCH 16, 2011 - ADDENDUM #1
KING SPRINGS ELEMENTARY SCHOOL
RENOVATION AND ADDITION – 20100358
CCSD PROJECT NO. 224/8032
BW&A 10958
SECTION 15840 - 3
DUCTWORK
damper size.
7.
C.
Control Dampers
1.
D.
Smoke dampers shall be UL-listed as Class 1 low-leakage smoke dampers and
shall be products of Prefco or Nailor.
LOW-PRESSURE DUCT BRANCHES
A.
2.4
Fire dampers shall be UL-listed and labeled for 1 1/2 hours and shall be provided
with 160 degrees F. links. Dampers installed within ducts shall be Type B or
Type C with the blades out of the air stream. Areas indicated shall be net, clear,
open areas.
Smoke Dampers
1.
2.3
Control dampers shall be of the same construction as manual volume dampers,
except that no manual operator and quadrant is required. The operating rod
shall be suitable for operation by an automatic pneumatic or electric operator.
Fire Dampers
1.
E.
Manual volume dampers shall be as manufactured by Louvers & Dampers, Inc.,
Nailor, or an approved equal.
Splitter dampers shall be provided at all low-pressure ductwork branches. All lowpressure ductwork branches shall be radiused or 45 degree take-offs; straight taps are
unacceptable. The length of the damper blade shall be the same as the width of the
widest duct section at the split, but in no case shall blade length be less than 12". Each
operator rod shall have a locking swivel joint.
FLEXIBLE DUCT
A.
Flexible ductwork shall be Class 1, UL 181 air duct and meet NFPA 90A and 90B
Standards.
B.
The internal duct surface shall be acoustically rated, black CPE bonded to a coated steel
wire helix. The external jacket shall be a fiberglass, bi-directionally reinforced, metallized
vapor barrier with a standing, triple ply seam. Fiberglass insulation shall be provided
between the duct surface and the jacket to achieve a maximum thermal conductance of
0.23 BTU/Hr./sq. ft./degree F. at 75 degrees F. mean.
C.
Flexible ductwork shall be suitable for 10" W.G. positive pressure and 1" W.G. negative
pressure.
D.
Flexible ductwork, insulation and insulation cover shall be suitable for ceiling return air
plenum installation and shall comply with all applicable codes and standards regarding
such ceiling plenum installations.
E.
Flexible duct shall be Thermaflex M-KE, Atco, or an approved equal.
SECTION 15840 - 4
DUCTWORK
F.
G.
2.5
2.
4'-0" on medium and high-pressure supply air systems limited to the runouts from
the sheetmetal ductwork to each terminal unit.
3.
2'-0" on connections from round neck grilles to sheetmetal ductwork on return,
exhaust and transfer ductwork.
Provide a spin-in fitting with integral scoop and volume damper at all flexible run-out
connections in low-pressure supply air ductwork only.
Provide flexible duct connections at the inlet and outlet of each belt-driven fan, indoor
unit, fan coil unit, air handling unit, etc., and at all other locations indicated. Flexible
connections shall be fabricated from a glass fabric coated on both sides with neoprene.
Minimum weight shall be 30 oz. per sq. yard.
Duct hardware shall be as manufactured by Young Regulator or an approved equal.
A duct access door shall be provided at each fire damper. Access doors shall be
designed for 1.5 times the pressure of the duct in which they are mounted. Access doors
shall be of sufficient size to provide access to the dampers for resetting the blades and
replacing the links. Access doors in medium and high-pressure ductwork shall be
installed downstream of fire dampers and shall be implosion type. Where access is
provided through gypsum board walls or ceilings, furnish access door for installation
under Division 9. Each door shall match the fire-rating of the wall or ceiling indicated.
DUCT LINER
A.
2.9
5'-0" on low-pressure supply air systems limited to short runouts and end of runs
connected to round neck supply diffusers and registers.
ACCESS DOORS
A.
2.8
1.
DUCT HARDWARE
A.
2.7
The maximum allowable installed length of flexible ductwork shall be as follows:
FLEXIBLE CONNECTIONS
A.
2.6
MARCH 16, 2011 - ADDENDUM #1
KING SPRINGS ELEMENTARY SCHOOL
RENOVATION AND ADDITION – 20100358
CCSD PROJECT NO. 224/8032
BW&A 10958
Duct liner shall be one inch thick, 1 1/2 lb. density (3 lb. density on medium- and highpressure supply air systems) fibrous glass with one face coated with a black fire
retardant compound. The permanent composite fire and smoke hazard rating of the liner
shall be stenciled on the liner face and shall be:
1.
Maximum flame spread 25
2.
Maximum smoke developed 50
DUCT INSULATION
A.
Duct insulation shall be 2" thick, minimum 3/4 lb. density fiberglass with an FSKL
MARCH 16, 2011 - ADDENDUM #1
KING SPRINGS ELEMENTARY SCHOOL
RENOVATION AND ADDITION – 20100358
CCSD PROJECT NO. 224/8032
BW&A 10958
SECTION 15840 - 5
DUCTWORK
0.00035" thick aluminum foil jacket, reinforced with fiberglass scrim.
Thermal
conductivity shall be a maximum of K = 0.24 at 75 degrees F. mean temperature.
B.
Insulation adhesive shall be Benjamin Foster 85-20. Tape shall be aluminum foil and
shall be SMACNA listed and labeled.
C.
The composite NFPA 90A and 90B, ASTM E84, UL rating of the installed insulation shall
not exceed 25/50.
PART 3 - EXECUTION
3.1
INSTALLATION
A.
Ductwork shall be installed in strict accordance with SMACNA, UL and NFPA standards.
B.
Duct liner shall be provided for the following minimum distances or through the first
elbow(s) or as otherwise indicated on the drawings, whichever is greater, downstream of
each unit indicated below:
1.
Packaged rooftop unit
25 feet
Duct liner shall also be provided throughout all return air, transfer and plenums.
Note: All ductwork above music rooms shall be lined.
C.
Duct liner shall be cut to provide overlapped and compressed longitudinal corner joints.
Liner shall be installed with the coated surface facing the air stream. Duct liner shall be
adhered to the ductwork with a 100% coverage of the sheet metal surfaces using a fire
retardant adhesive applied by spraying. Coat all exposed leading edges and all
transverse joints with fire retardant adhesive. The liner shall be additionally secured
using metal pins welded to the duct and speed washers. All leading edges shall be
secured with sheet metal airfoils.
D.
All supply air ductwork which is not lined shall be insulated. All outside air ductwork shall
be insulated. Insulation shall be cut slightly longer than circumference of duct to insure
full thickness at corners. All insulation shall be applied with edges tightly banded.
Insulation shall be adhered to duct with fire resistant adhesive. Adhesive shall be applied
so that insulation conforms to duct surfaces uniformly and firmly. In addition to the
adhesive, the insulation shall be additionally secured to the bottom of all ducts 18" or
wider by means of welded pins and speed clips. The protruding end of the pins shall be
cut off flush after the speed clips have been applied. The vapor-barrier facing shall be
thoroughly sealed with tape where the pins have pierced through. All joints shall be
sealed with 2" wide SMACNA tape. Any cuts or tears shall be sealed with SMACNA
tape.
E.
Flexible ducts utilized in the low-pressure ductwork systems shall be installed without
kinks or bends which are less than a centerline radius equal to or greater than twice the
diameter of the flexible duct being installed.
END OF SECTION
Download