REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 TOC - 1 TABLE OF CONTENTS SPECIFICATIONS Division 0 - Bidding and Contract Documents * * * * * * * * * * 00020 00101 00210 00310 00820 A101-2007 Advertisement Invitation For Bids ....................................................................Revised 3/16/11 Instruction to Bidders Specific Date Construction Schedule ..............................................................Revised 3/16/11 Bid Proposal Form Liquidated Damages AIA Standard Form of Agreement Between Owner and Contractor --------AIA Closeout Documents A201-2007 AIA General Conditions of the Contract for Construction (Modified) --------Floor Phasing Plan of King Springs Elementary School .................................Revised 3/16/11 --------Report of Subsurface Exploration and Geotechnical Engineering Evaluation ................................................... Issued 3/16/11 00901 Addendum No. 1 ................................................................................................ Issued 3/16/11 Division 1 - General Requirements * * * * * * * * * * 01010 01045 01101 01110 01200 01300 01310 01312 01400 01500 01630 01650 01700 Summary of Work ............................................................................................Revised 3/16/11 Cutting and Patching Alternates .........................................................................................................Revised 3/16/11 Low-Emitting Materials General Requirements Submittals Construction Schedules Project Meetings Testing Laboratory Services Temporary Facilities Substitutions Project Record Documents Contract Closeout Division 2 - Sitework * * * * * * * * * * * * * 02010 02220 02221 02222 02230 02240 02300 02360 02370 02510 02530 02630 02740 02750 02770 02900 General-Sitework Site Demolition Building Demolition Selective Demolition Clearing and Grubbing Groundwater Control Earthwork Soil Treatment Erosion Sedimentation and Pollution Control Water Distribution Sanitary Sewer System Storm Drainage Asphaltic Concrete Paving Portland Cement Concrete Paving Concrete Curbs, Gutters, and Walks Landscaping TOC - 2 TABLE OF CONTENTS REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Division 3 - Concrete * 03300 03540 Cast-In-Place Concrete Cementitious Underlayment Division 4 - Masonry 04200 04210 04220 04720 Unit Masonry Brick .................................................................................................................Revised 3/16/11 Concrete Unit Masonry Architectural Cast Stone Division 5 - Metals * * * 05120 05210 05310 05400 05500 Structural Steel Steel Joists Steel Deck Cold-Formed Metal Framing Metal Fabrications Division 6 - Wood and Plastics 06105 06400 Miscellaneous Carpentry Architectural Woodwork ...................................................................................Revised 3/16/11 Division 7 - Thermal and Moisture Protection 07160 07210 07260 07415 07420 07527 07600 07710 07900 Bituminous Dampproofing Building Insulation Vapor Retarders Metal Cladding Systems .................................................................................... Issued 3/16/11 Composite Panels .............................................................................................. Issued 3/16/11 SBS-Modified Bituminous Membrane Roofing Flashing and Sheet Metal Manufactured Roof Specialties Joint Sealers Division 8 - Doors and Windows * 08100 08200 08336 08400 08710 08800 08900 Metal Doors and Frames Wood Doors Coiling Counter Shutters Entrances and Storefronts Door Hardware Glazing Exterior Wall Performance Requirements REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 TOC - 3 TABLE OF CONTENTS Division 9 - Finishes 09100 09250 09300 09510 09622 09651 09653 09680 09900 Metal Support Systems Gypsum Board Tile Acoustical Ceilings Resilient Athletic Flooring Resilient Wall Base and Accessories Resilient Tile Flooring Carpet Painting Division 10 - Specialties 10152 10155 10520 10531 10800 Hospital Cubical Curtains and Tracks ............................................................... Issued 3/16/11 Toilet Compartments Fire Protection Specialties Aluminum Canopy Structures ............................................................................ Issued 3/16/11 Toilet and Bath Accessories Division 11 - Equipment 11132 Projection Screens Division 12 - Furnishings 12491 Blinds Division 13 - Special Construction Division 14 - Conveying Systems (Not Applicable) (Not Applicable) Division 15 - Mechanical * * * * * * * * * * 15010 15043 15400 15450 15525 15774 15800 15820 15840 15900 Mechanical General HVAC Test & Balance Plumbing Systems Plumbing Fixtures and Trim Fire Suppression Systems Packaged Rooftop Units Air Distribution Devices ..................................................................................Revised 3/16/11 Fans Ductwork ........................................................................................................Revised 3/16/11 Controls TOC - 4 TABLE OF CONTENTS REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Division 16 - Electrical * * * * * 16010 16100 16300 16730 16920 Electrical General Electrical Basic Materials & Methods Lighting Clock Systems Motor Controls and Wiring END OF TABLE OF CONTENTS * These specification sections not prepared by Cooper Carry. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 00020-1 INVITATION FOR BIDS SECTION 00020 INVITATION FOR BIDS BID 11-51 This project consists of Addition for Admin, Personnel, Modify/Renovate Restrooms, Flooring Replacement, HVAC, Plumbing (Water Coolers), Add Sprinkler System, Electrical (Clock System, Electrical (Fire Alarm System), Electrical (Lighting) Sealed bids are requested by Cobb County School District from general contractors for construction of: SCHOOL: King Springs Elementary School Additions and Modifications PROJECT NO.: 224/8032 BID NO.: Bid No. 11-51 Bids will be received by the Cobb County School District, Procurement Services Department at 6975 Cobb International Blvd. Kennesaw, Georgia 30152 until: 11:30 AM, LOCAL TIME, March 30, 2011 At which time and place the bids will be publicly opened and read aloud. Bids will be time and date stamped upon receipt at Cobb County School District Procurement Services Department. The exact time of receipt is determined by the date/time stamp. Bids received late will not be considered. A PRE-BID CONFERENCE will be held at King Springs Elementary School, 1041 Reed Rd., Smyrna, GA 30082 on March 10, 2011 at 3:00 PM. Attendance at this Pre-bid Conference is mandatory in order to submit a bid. All bids accepted must be in sealed envelopes marked with your company name and “Bid 11-51, King Springs Elementary School Additions and Modifications”. For mailing purposes, please address your bid to CCSD, Procurement Services Department, 6975 Cobb International Blvd., Kennesaw, Georgia 30152. Attn: Barbara Bates. Bid Documents may be reviewed at the Office of the Architect, CCSD Procurement Services Dept., the AGC Builders Exchange, the F.W. Dodge Plan Room, and Reed Construction Data. Contractors shall submit to the Owner for consideration a properly executed AIA Document A-305, Contractor’s Qualification Statement (that is less than one year old) and a current Audited/Reviewed financial statement (that is less than eighteen months old) no later than March 18, 2011). The Owner will consider the submittal and respond within five (5) days if the submittal is not accepted. Contractor’s Qualification statements should be addressed to: CCSD, Procurement Services Department, 6975 Cobb International Blvd., Kennesaw, Georgia 30152. Attn: Barbara Bates, Emails to: Barbara.Bates@cobbk12.org. For Inquiries Regarding the Bid Documents: All communications concerning these documents must be submitted in writing to the Cobb County School District (CCSD) Procurement Services Department either by email, facsimile, or U.S. mail. Email is the preferred method of communication. Email correspondence is to be directed to Barbara Bates at Barbara.Bates@cobbk12.org. Fax correspondence is to be sent to 770 426 3371. Correspondence sent by U.S. mail is to be sent to CCSD Procurement Services Department., 6975 Cobb International Blvd., Kennesaw, Georgia 30152, Attn: Barbara Bates. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 00020-2 INVITATION FOR BIDS Only written inquiries received via email, fax, or U.S. mail by 5:00 P.M. March 25, 2011 will be considered. Responses to all written inquiries will be posted to the Current Solicitations page on the Cobb County School District website at http://www.cobbk12.org/centraloffice/Purchasing/Current%20Bids%20and%20RFPs.htm Bid Documents will be issued by: The Architect: William Collier Cooper, Carry, Inc. Suite 2400 191 Peachtree Street, NE Atlanta, GA 30303 Phone: Fax: 404-237-2000 404-237-0276 to all interested parties upon receipt of a request accompanied by a non-refundable check made payable to the issuing party above in the amount of: $75.00 per set. Bid documents will be shipped post paid, as soon as possible. Contract, if awarded, will be on the basis stated in the Instructions to Bidders. No bid may be withdrawn for a period of 60 days after bid opening. Bids must be accompanied by a bid bond made payable to the Cobb County School District, in the amount equal to 5 percent of the bid price. (Certified Checks Not Acceptable.) The successful bidder will be required to furnish a Performance Bond and a Payment Bond acceptable to the Cobb County School District in an amount equal to 100 percent of the contract price and executed by a Surety Company licensed to do business in the State of Georgia and listed in the Department of the Treasury Circular 570, latest edition. The Surety Company shall have an A.M. Best Company minimum rating of "A-" with a financial size of VI “6” or better. Bonds must be accompanied by letter stating bonding company's current rating for verification prior to acceptance by the Owner and execution of the formal Owner/Contractor agreement. Bonding of Subcontractors: Include in the Base Bid, Performance and Labor and Materials Payment Bonds, each in 100% of the subcontract sum, for each Subcontractor having a contract of $50,000.00 or more for Roofing, HVAC, Plumbing, Sprinkler System and Electrical Work as required by the General Conditions. Contractor and Subcontractors shall require the Attorney-in-Fact who executes bonds on behalf of sureties to attach a certified, current copy of his Power of Attorney. Cobb County School District reserves the right to award the project on whatever basis is in the interest of the Owner and to accept or reject any or all bids and to waive technicalities and informalities. BY: DATE: Cobb County School District Alisa Morningstar Director, Procurement Services Dept. March 1, 2011 END OF SECTION REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 00210-1 SPECIFIC DATE CONSTRUCTION SCHEDULE SECTION 00210 SPECIFIC DATE CONSTRUCTION SCHEDULE PART ONE - GENERAL 1.01 DESCRIPTION: A. Work Included: A Specific Date Construction Schedule for the project is stated here-in. Dates for Items 1 through 4 may be considered preliminary until such time as Item No. 3 "Notice of Award" is made. B. If dates for Items 2 and 3 are maintained, then the dates for Items 4 through 9 become a fixed Construction Schedule. C. If the Notice of Award date moves forward, then all subsequent dates for Items 4 through 9 shall move forward by the same number of days, unless otherwise stated in an Addendum. If the Notice of Award date is moved back, then all subsequent dates for items 5 through 9 shall remain the same, unless otherwise stated in an Addendum. PART TWO - EXECUTION 2.01 GENERAL: The schedule dates for the project shall be adhered to and are the last acceptable dates unless they are modified by change order. All dates indicate midnight unless otherwise stipulated. All work affecting an existing facility shall be accomplished during non class time. The Contractor shall be responsible for maintaining all emergency egress routes in accordance with governing code criteria and security for the building. 2.02 PHASING: If the project has phases of work with different Substantial Completion dates, the Contractor shall obtain a separate building permit for each Phase to allow separate inspections and a Certificate of Occupancy to be issued for each Phase. 2.03 CONSTRUCTION SCHEDULE: 1. ADVERTISEMENT FOR BID: 2/28/2011 2. BID DATE & TIME: 3/30/2011 - 11:30 A.M. 3. NOTICE OF AWARD: 4/29/2011 4. CONTRACT AGREEMENT DATE: 4/28/2011 5. START OF CONTRACT TIME: (10 DAYS AFTER NOTICE OF AWARD OR ON NOTICE TO PROCEED DATE; WHICHEVER OCCURS FIRST) START OF CONSTRUCTION TIME: 5/9/2011 6/2/2011 6. COMPLETION DATES: Phase 1 – Interior Building Renovation: a. SUBSTANTIAL COMPLETION: 7/29/2011 b. ACTUAL DAMAGES OR LIQUIDATED DAMAGES BECOME EFFECTIVE ON ITEM 6a: 7/30/2011 REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 c. 00210-2 SPECIFIC DATE CONSTRUCTION SCHEDULE FINAL COMPLETION: 8/29/2011 d. ACTUAL DAMAGES OR LIQUIDATED DAMAGES BECOME EFFECTIVE ON ITEM # 6c 8/30/2011 Phase 2 – Administrative Addition: e. SUBSTANTIAL COMPLETION: f. ACTUAL DAMAGES OR LIQUIDATED DAMAGES BECOME EFFECTIVE ON ITEM 6a: 10/3/2011 10/4/2011 g. FINAL COMPLETION: 11/3/2011 ACTUAL DAMAGES OR LIQUIDATED h. DAMAGES BECOME EFFECTIVE ON ITEM # 6c 11/4/2011 END OF SECTION REPORT OF SUBSURFACE EXPLORATION AND GEOTECHNICAL ENGINEERING EVALUATION KING SPRINGS ELEMENTARY SCHOOL 1041 Reed Road Smyrna, Cobb County, Georgia Prepared For: COBB COUNTY SCHOOL DISTRICT 440 Glover Street Marietta, Georgia 30060 NOVA Project Number 2011019 March 17, 2011 TABLE OF CONTENTS 1.0 1.1 1.2 1.3 1.4 2.0 2.1 2.2 3.0 3.1 3.2 4.0 4.1 4.2 5.0 5.1 5.2 6.0 6.1 6.2 6.3 6.4 6.5 6.6 SUMMARY ........................................................................................................................ 1 GENERAL .................................................................................................................................... 1 SITE PREPARATION .................................................................................................................. 1 FOUNDATIONS .......................................................................................................................... 1 SEISMIC ....................................................................................................................................... 1 INTRODUCTION.............................................................................................................. 2 PROJECT INFORMATION ......................................................................................................... 2 SCOPE OF WORK ....................................................................................................................... 2 SITE DESCRIPTION........................................................................................................ 4 GENERAL .................................................................................................................................... 4 GEOLOGY / HYDROLOGY ....................................................................................................... 4 FIELD AND LABORATORY PROCEDURES ............................................................. 6 FIELD EXPLORATION .............................................................................................................. 6 LABORATORY TESTING .......................................................................................................... 6 SUBSURFACE CONDITIONS ........................................................................................ 7 SOIL CONDITIONS .................................................................................................................... 7 GROUNDWATER CONDITIONS .............................................................................................. 8 CONCLUSIONS AND RECOMMENDATIONS ........................................................... 9 SITE GRADING ........................................................................................................................... 9 GROUNDWATER CONTROL .................................................................................................. 11 FOUNDATIONS ........................................................................................................................ 11 SLAB-ON-GRADE .................................................................................................................... 13 SEISMIC ..................................................................................................................................... 13 CONSTRUCTION OBSERVATIONS....................................................................................... 14 APPENDIX Appendix A – Figures and Maps Appendix B – Subsurface Data Appendix C – Qualifications of Recommendations King Springs Elementary School Cobb County School District March 17, 2011 NOVA Project Number 2011019 1.0 SUMMARY A brief summary of pertinent findings, conclusions and recommendations are presented below. This information should not be utilized in design or construction without reading the report in its entirety and paying particular attention to the recommendations presented in the text and Appendix. 1.1 GENERAL • Four soil test borings (B-1 through B-4) were drilled at the subject site during this exploration. Generally, the borings encountered a surface veneer of asphalt underlain by gravel, previously placed fill materials, residual soils and partially weathered rock. • Fill soils were encountered in borings B-2 and B-3 at depths of 11 and 6 feet beneath the existing ground surface, respectively. The fill materials were generally described as sandy silt with rock fragments and with a consistency of stiff to very stiff. • Partially weathered rock was encountered in borings B-1 and B-3 at depths ranging from 43 to 28 feet below the existing ground surface, respectively. Auger refusal materials were not encountered in any of the borings above the boring termination depths of 20 to 50 feet below the existing ground surface. 1.2 • 1.3 • 1.4 • SITE PREPARATION The majority of the encountered fill soils were fine grained soils. Although we do not anticipate groundwater control problems, establishing subgrades in fine grained soils exposed to inclement weather conditions can be challenging and may require drying and/or stabilizing depending on the time of year and weather conditions. FOUNDATIONS We recommend that the proposed structure be supported on conventional shallow foundations designed for a maximum allowable soil bearing pressure of 3,000 pounds per square foot (psf). SEISMIC In accordance with Section 1613.5.2 of the 2006 International Building Code, the seismic Site Class was estimated using the standard penetration resistance values obtained from the soil test borings performed during this study. Based upon this analysis, and our knowledge of general subsurface conditions in the area, we believe the soil profiles associated with a Site Class “D” are generally appropriate for this site. Page 1 King Springs Elementary School Cobb County School District March 17, 2011 NOVA Project Number 2011019 2.0 INTRODUCTION 2.1 PROJECT INFORMATION Our understanding of this project is based on discussions with Mr. Henry Gomez of Cobb County School District, review of the provided site plans, a site reconnaissance during boring layout, and our experience with similar projects. The project site is located on the existing King Springs Elementary School campus located at 1041 Reed Road in Smyrna, Cobb County, Georgia. We understand that the proposed construction will consist of a one-story addition. Final column loads were not available at the time of issuance of this report. However, based upon previous experience with similar structures, we estimate that compressive column loads will be on the order of 80 to 100 kips, respectively. Wall loading is expected to be on the order of 2 to 3 kips per linear foot. The planned first floor elevation of the building is currently proposed as 1015.5 feet-MSL. Minimal cuts and fills (on the order of 5 feet) are anticipated to achieve design grades. 2.2 SCOPE OF WORK Cobb County School District engaged NOVA to provide geotechnical engineering consulting services for the King Springs Elementary School project. This report briefly discusses our understanding of the project, describes our exploratory procedures and presents our findings, conclusions and recommendations. The primary objective of this study was to perform a geotechnical exploration within the area of the proposed construction and to assess these findings as they relate to geotechnical aspects of the planned site development. The authorized geotechnical engineering services included a site reconnaissance, a soil test boring and sampling program, engineering evaluation of the field data, and the preparation of this report. The services were performed substantially as outlined in the NOVA and Cobb County School District RFP 34-10 Geotechnical Services contract dated August 3, 2010, and in general accordance with industry standards. As authorized per the above referenced contract, the completed geotechnical report was to include: • • A description of the site, fieldwork, laboratory testing and general soil conditions encountered, as well as a Boring Location Plan and individual Boring Records. Discussion on potential design/construction issues indicated by the exploration, such as materials that would require difficult excavation techniques, shallow groundwater table, etc. Page 2 King Springs Elementary School Cobb County School District • • • • • • • • March 17, 2011 NOVA Project Number 2011019 Recommendations for controlling groundwater and/or run-off during construction and, the need for permanent de-watering systems based on the anticipated post construction groundwater levels. Recommendations for foundation design and construction, including allowable bearing capacities and bearing depths. Estimate of total and differential settlements of foundation based on available structural loading data. Recommended quality control measures (i.e. sampling, testing, and inspection requirements) for site grading and foundation construction. Soil compaction requirements for foundations, structural fill and pavements were to be provided. Slab-on-grade construction considerations based on the geotechnical findings, including the need for a sub-slab vapor barrier or a capillary barrier. Suitability of on-site soils for re-use as structural fill and backfill. Additionally, the criteria for suitable fill materials were to be provided. Seismic site classification using correlation with SPT N-values in accordance with the 2006 International Building Code. Site preparation considerations that include geotechnical discussions regarding site stripping and subgrade preparation, recommended cut or fill slopes, and engineered fill/backfill placement. The assessment of the presence of wetlands, floodplains or water classified as State Waters of Georgia was beyond the scope of this study. Additionally, the assessment of site environmental conditions, including the detection of pollutants in the soil, rock or groundwater, at the site was also beyond the scope of this geotechnical study. If desired by the client, NOVA can provide these services. Page 3 King Springs Elementary School Cobb County School District March 17, 2011 NOVA Project Number 2011019 3.0 SITE DESCRIPTION 3.1 GENERAL The site is the existing King Springs Elementary School campus located at 1041 Reed Road in Smyrna, Cobb County, Georgia. The site is bounded by residential and educational development to the north, residential development to the east, Reed Road then residential development to the south, and Gann Road then residential development to the west. Based on the provided site plan, current site grades in the area of the proposed addition range from 1015.5 feet-MSL at the existing building to 1012 feet-MSL along the entrance drive just south of the proposed addition. Currently, the site is developed as an existing elementary school with several rectangular shaped buildings, playground areas, and associated surface asphalt-paved parking and drive areas. The site is also landscaped with trees, shrubs and grassed areas. Based on a limited visual assessment of the existing structures, no distress or other evidence was noted that would indicate foundation related support problems. We note however that the type, bearing design and design loading of foundations for these structures are unknown. 3.2 GEOLOGY / HYDROLOGY 3.2.1 Site and Area Geology The site is located in the Piedmont Geologic Region, a broad northeasterly trending province underlain by crystalline rocks up to 600 million years old. The Piedmont is bounded on the northwest by the Blue Ridge Range of the Appalachian Mountains, and on the southeast by the leading edge of Coastal Plain sediments, commonly referred to as the “Fall Line”. Numerous episodes of crystal deformation have produced varying degrees of metamorphism, folding and shearing in the underlying rock. The resulting metamorphic rock types in this area of the Piedmont are predominantly a series of Precambrian age schists and gneisses, with scattered granitic or quartzite intrusions. According to the "Geology of the Greater Atlanta Region" by McConnell and Abrams, 1984, the site is generally underlain by the Sandy Springs Group. This geologic formation typically consists of intercalated biotite gneiss, mica schist and amphibolite. Residual soils in the region are primarily the product of in-situ chemical decomposition of the parent rock. The extent of the weathering is influenced by the mineral composition of the rock and defects such as fissures, faults and fractures. The residual profile can generally be divided into three zones: Page 4 King Springs Elementary School Cobb County School District March 17, 2011 NOVA Project Number 2011019 • An upper zone near the ground surface consisting of red clays and clayey silts which have undergone the most advanced weathering, • An intermediate zone of less weathered micaceous sandy silts and silty sands, frequently described as “saprolite”, whose mineralogy, texture and banded appearance reflects the structure of the original rock, and • A transitional zone between soil and rock termed partially weathered rock (PWR). Partially weathered rock is defined locally by standard penetration resistances exceeding 100 blows per foot. The boundaries between zones of soil, partially weathered rock and bedrock are erratic and poorly defined. Weathering is often more advanced next to fractures and joints that transmit water, and in mineral bands that are more susceptible to decomposition. Boulders and rock lenses are sometimes encountered within the overlying PWR or soil matrix. Consequently, significant fluctuations in depths to materials requiring difficult excavation techniques may occur over short horizontal distances. 3.2.2 Groundwater Groundwater in the Piedmont typically occurs as an unconfined or semi-confined aquifer condition. Recharge is provided by the infiltration of rainfall and surface water through the soil overburden. More permeable zones in the soil matrix, as well as fractures, joints and discontinuities in the underlying bedrock can affect groundwater conditions. The groundwater table in the Piedmont is expected to be a subdued replica of the original surface topography. Page 5 King Springs Elementary School Cobb County School District March 17, 2011 NOVA Project Number 2011019 4.0 FIELD AND LABORATORY PROCEDURES 4.1 FIELD EXPLORATION Boring locations were specified on the Foundation and Framing Plans prepared by Willett Engineering Company and were established in the field by NOVA personnel by taping and estimating distances and angles from site landmarks. Underground and overhead utility related adjustments of the boring locations were made at the time of the field exploration. Boring elevations were then interpolated from the provided topographic survey. Consequently, referenced boring locations and elevations are approximate. If increased accuracy is desired by the client, NOVA recommends that the boring locations and elevations be surveyed. Our field exploration was conducted on March 12, 2011 and included four soil test borings (B-1 through B-4) drilled to depths of 20 to 50 feet below the existing ground surface in the area of the proposed addition. All drilling and sampling operations were performed in general accordance with ASTM designations. Test Boring Records in the Appendix show the standard penetration test (SPT) resistances, or “Nvalues”, and present the soil conditions encountered in the borings. These records represent our interpretation of the subsurface conditions based on the field exploration data, visual examination of the split-barrel samples, and generally accepted geotechnical engineering practices. The stratification lines and depth designations represent approximate boundaries between various subsurface strata. Actual transitions between materials may be gradual. The groundwater levels reported on the Test Boring Records represent measurements made at the completion of the soil test boring. The soil test borings were subsequently backfilled with the soil cuttings. 4.2 LABORATORY TESTING Split-barrel samples were returned to our testing laboratory, where they were classified using visual/manual methods in accordance with the Unified Soil Classification System (USCS) and ASTM designations. The descriptions presented in the boring logs should be considered approximate. Further laboratory testing was beyond the scope of this exploration. Page 6 King Springs Elementary School Cobb County School District March 17, 2011 NOVA Project Number 2011019 5.0 SUBSURFACE CONDITIONS 5.1 SOIL CONDITIONS The following paragraphs provide generalized descriptions of the subsurface profiles and soil conditions encountered by the borings conducted during this study. The Test Boring Records in the Appendix should be reviewed to provide more detailed descriptions of the subsurface conditions encountered at each boring location. Conditions may vary at other locations and times. 5.1.1 Surface Materials The borings were performed within existing parking and drive areas and encountered up to 2 inches of asphalt underlain by up to 3 inches of gravel. Although not encountered in any of the borings, concrete walkways were present in the area of the proposed addition. 5.1.2 Fill Fill was encountered in borings B-2 and B-3 to depths of 11 and 6 feet below the existing ground surface, respectively. The fill was generally described as sandy silt with rock fragments and a consistency of stiff to very stiff. Standard penetration resistances in the fill varied from 9 to 21 blows per foot (bpf), but may have been amplified by the presence of rock fragments. 5.1.3 Residual Soils Residual soils were encountered in all borings beneath the fill materials or ground surface. The residuum was generally described as sandy silt. Standard penetration resistance values ranged from 14 to 63 bpf, but more typically varied from 18 to 28 bpf. 5.1.4 Partially Weathered Rock Partially weathered rock (PWR) is a transitional material between soil and the underlying parent rock that is defined locally as materials that exhibit a standard penetration resistance exceeding 100 bpf. PWR was encountered in borings B-1 and B-3 at depths of 43 and 28 feet below the ground surface (approximate elevations of 970 and 986 feet-MSL), respectively. 5.1.5 Auger Refusal Materials Auger refusal materials are any very hard or very dense material, frequently boulders or the upper surface of bedrock, which cannot be penetrated by a power auger. Auger refusal was not encountered in any of the borings above the boring termination depths of 20 to 50 feet below the existing ground surface. Page 7 King Springs Elementary School Cobb County School District 5.2 March 17, 2011 NOVA Project Number 2011019 GROUNDWATER CONDITIONS Groundwater was observed at the time of boring in borings B-1 and B-3 at depths of 46 and 38 feet below the existing ground surface (approximate elevations of 967 and 976 ft-MSL). Groundwater levels vary with changes in season and rainfall, construction activity, surface water runoff and other site-specific factors. Groundwater levels in the Smyrna area are typically lowest in the late summer-early fall and highest in the late winter-early spring; consequently, the water table may vary at times. Page 8 King Springs Elementary School Cobb County School District March 17, 2011 NOVA Project Number 2011019 6.0 CONCLUSIONS AND RECOMMENDATIONS The following conclusions and recommendations are based on our understanding of the proposed construction, site observations, our evaluation and interpretation of the field data obtained during this exploration, our experience with similar subsurface conditions, and generally accepted geotechnical engineering principles and practices. Subsurface conditions in unexplored locations or at other times may vary from those encountered at specific boring locations. If such variations are noted during construction, or if project development plans are changed, we request the opportunity to review the changes and amend our recommendations, if necessary. As previously noted, boring locations were established by estimating distances and angles from site landmarks. If increased accuracy is desired by the client, we recommend that the boring locations and elevations be surveyed. 6.1 SITE GRADING 6.1.1 Site Preparation General: An existing porte cochere that will require demolition currently occupies the site. Prior to proceeding with construction, all slabs, foundations, pavements, vegetation, root systems, topsoil, and other deleterious non-soil materials should be stripped from proposed construction areas. Clean topsoil may be stockpiled and subsequently re-used in landscaped areas. Debris-laden materials should be excavated, transported and disposed of off-site in accordance with appropriate solid waste rules and regulations. All existing utility locations should be reviewed to assess their impact on the proposed construction and relocated/grouted in-place as appropriate. After clearing and stripping, areas which are at grade or will receive fill should be carefully evaluated by a NOVA geotechnical engineer. The engineer will require proofrolling of the subgrade with multiple passes of a 20 to 30 ton loaded truck or other pneumatic-tired vehicle of similar size and weight. The purpose of the proofrolling is to locate soft, weak, or excessively wet fill or residual soils present at the time of construction. Any unstable materials observed during the evaluation and proofrolling operations should be undercut and replaced with structural fill or stabilized in-place by scarifying and re-densifying. Page 9 King Springs Elementary School Cobb County School District March 17, 2011 NOVA Project Number 2011019 Existing/Old Fill: Previously placed fill materials were encountered during this exploration. Based on our experience, we anticipate fill materials likely exist at other locations between our borings. Old fills are frequently erratic in composition and consistency. In the event that low consistency and/or debris laden fill materials are encountered during construction, typical recommendations would include undercutting and backfilling with structural fill and/or stabilizing in-place with fabric, stone, and/or other remedial techniques. Actual remedial recommendations can best be determined by the geotechnical engineer in the field at the time of construction. 6.1.2 Difficult Excavation None of the borings encountered dense soil, PWR or rock above planned finished grades. Therefore, we do not anticipate that significant quantities of materials requiring difficult excavation techniques will be encountered during mass grading and/or shallow foundation/utility excavation operations. 6.1.3 Fill Placement Fill materials should be low plasticity soil (Plasticity Index less than 30), free of non-soil materials and rock fragments larger than 3 inches in any one dimension. Based on visual examination, the existing residual soils and much of the existing fill, which does not contain appreciable amounts of debris, rock, organics or other deleterious materials encountered during this exploration generally appear suitable for re-use as structural fill. Prior to construction, bulk samples of the proposed fill materials should be laboratory-tested to confirm their suitability. Organic and/or debris laden material is not suitable for re-use as structural fill. Topsoil, mulch and similar organic materials can be wasted in architectural areas. Debris-laden materials should be excavated, transported and disposed of off-site in accordance with appropriate solid waste rules and regulations. Fill should be placed in thin, horizontal loose lifts (maximum 8-inch) and compacted to at least 95 percent of the standard Proctor maximum dry density (ASTM D 698). The upper 8 inches of soil beneath pavements and slab-on-grade should be compacted to at least 98 percent. In confined areas, such as utility trenches or behind retaining walls, portable compaction equipment and thinner fill lifts (3 to 4 inches) may be necessary. Fill materials used in structural areas should have a target maximum dry density of at least 95 pounds per cubic foot (pcf). If lighter weight fill materials are used, the NOVA geotechnical engineer should be consulted to assess the impact on design recommendations. Page 10 King Springs Elementary School Cobb County School District March 17, 2011 NOVA Project Number 2011019 Soil moisture content should be maintained within 3 percent of the optimum moisture content. Fine grained soils were encountered at the planned finished subgrade elevations at each of the boring locations. Although we do not anticipate significant groundwater control problems based on the stabilized groundwater levels, establishing subgrades in these fine grained soils may be challenging and could require drying and/or stabilization depending on the time of year and weather conditions when grading is performed. We recommend that the grading contractor have equipment on site during earthwork for both drying and wetting fill soils. Moisture control may be difficult during rainy weather. All filling operations should be observed by a NOVA soils technician, who can confirm suitability of material used and uniformity and appropriateness of compaction efforts. The NOVA soils technician can also document compliance with the specifications by performing field density tests using thin-walled tube, nuclear, or sand cone testing methods (ASTM D 2937, D 6938, or D 1556, respectively). One test per 400 cubic yards and every 2 feet of placed fill is recommended, with test locations well distributed throughout the fill mass. When filling in small areas, at least one test per day per area should be performed. 6.2 GROUNDWATER CONTROL During the current study, depths to groundwater ranged from 46 to 38 feet below the existing ground surface (approximate elevations ranging from 967 to 976 feet-MSL). Based on the planned cuts necessary to reach design subgrades, we do not anticipate significant groundwater control problems during mass grading operations. The groundwater appears to be below planned slab elevations. As previously noted, groundwater levels are subject to seasonal, climatic and other variations and may be different at other times and locations. The extent and nature of any dewatering required during construction will be dependent on the actual groundwater conditions prevalent at the time of construction and the effectiveness of construction drainage to prevent run-off into open excavations. 6.3 FOUNDATIONS After the recommended site and subgrade preparation and fill placement, we recommend that the proposed structure be supported by conventional shallow foundations. Foundations bearing on undisturbed residual soils and/or compacted structural fill may be designed for a maximum allowable bearing pressure of 3,000 pounds per square foot (psf). Previously placed fill materials were encountered on the site. In the event that low consistency or debris-laden fill materials are present in foundation excavations, undercutting and backfilling with crushed stone or structural fill or redesigning for a reduced bearing pressure, may be required. Page 11 King Springs Elementary School Cobb County School District March 17, 2011 NOVA Project Number 2011019 We recommend minimum footing widths of 24 inches for ease of construction and to reduce the possibility of localized shear failures. Exterior footing bottoms should be at least 18 inches below exterior grades for protection against frost damage. Settlements for spread foundations were assessed using SPT values to estimate elastic modulus, based on published correlations and previous NOVA experience. We note that the settlements presented are based on random field data and an assumed subsoil profile. Conditions may be better or worse in other areas; however, we believe the estimated settlements are reasonable. Based on column loadings, soil bearing capacities and the presumed foundation elevations as discussed above, we expect primary total settlement beneath individual footings to be on the order of ¾ to 1 inches. The amount of differential settlement is difficult to predict because the subsurface and foundation loading conditions can vary considerably across the site. However, we anticipate differential settlement between adjacent footings could vary from ¼ to ½ inch. The final deflected shape of the structure will be dependent on actual footing locations and loading. Foundation support conditions are highly erratic and may vary dramatically in short horizontal distances. It is anticipated that the geotechnical engineer may recommend a different bearing capacity upon examination of the actual foundation subgrade at numerous locations. To reduce the differential settlement if lower consistency materials are encountered, a lower bearing capacity should be used or the foundations should be extended to more competent materials. We anticipate that timely communication between the geotechnical engineer and the structural engineer, as well as other design and construction team members, will be required. All footing excavations should be evaluated by the NOVA geotechnical engineer prior to reinforcing steel placement to observe foundation subgrade preparation and confirm bearing pressure capacity. Footing excavations should be level and free of debris, ponded water, mud, and loose, frozen or water-softened soils. Concrete should be placed as soon as is practical after the footing is excavated and the subgrade evaluated. Foundation concrete should not be placed on frozen or saturated soil. If a footing excavation remains open overnight, or if rain or snow is imminent, a 3 to 4-inch thick "mud mat" of lean concrete should be placed in the bottom of the footing to protect the bearing soils until reinforcing steel and concrete can be placed. Page 12 King Springs Elementary School Cobb County School District 6.4 March 17, 2011 NOVA Project Number 2011019 SLAB-ON-GRADE The conditions exposed at subgrade levels will vary across the site and may include existing fill materials, newly placed structural fill or residual soils. Provided the existing fill material does not deflect or “pump” during the proofroll, slabs-on-grade may be adequately supported on these subgrade conditions subject to the recommendations in this report. Slabs-on-grade should be jointed around columns and along walls to reduce cracking due to differential movement. A 6-inch layer of crushed stone may be placed beneath the building slabs to reduce non-uniform support conditions. An underdrain system is not necessary beneath the slabs, but an impermeable vapor barrier is recommended beneath finished spaces to reduce dampness. Once grading within the building footprint is completed, the subgrade is usually exposed to adverse construction activities and weather conditions during the period of sub-slab utility installation. The subgrade should be well-drained to prevent the accumulation of water. If the exposed subgrade becomes saturated or frozen, the geotechnical engineer should be consulted. After utilities have been installed and backfilled, a final subgrade evaluation should be performed by the geotechnical engineer immediately prior to slab-on-grade placement. If practical, proofrolling may be used to redensify the surface and to detect any soil that has become excessively wet or otherwise loosened. 6.5 SEISMIC 6.5.1 Soil Site Class In accordance with Section 1613.5.2 of the 2006 IBC, the seismic Site Class was estimated using the standard penetration resistance values obtained from the soil test borings performed during this study. Based upon this analysis, and our knowledge of general subsurface conditions in the area, we believe the soil profiles associated with a Site Class “D” are generally appropriate for this site. We note that the IBC allows determination of Site Class using in-situ seismic shear wave survey techniques. It should be noted that use of this supplemental method does not guarantee a lower site class designation; however, it is a reasonable and prudent approach that can be performed in a supplemental study, if requested. Page 13 King Springs Elementary School Cobb County School District 6.6 March 17, 2011 NOVA Project Number 2011019 CONSTRUCTION OBSERVATIONS 6.6.1 Shallow Foundations Footing excavations should be level and free of debris, ponded water, mud, and loose, frozen or water-softened soils. All footing excavations should be evaluated by the NOVA geotechnical engineer prior to reinforcing steel placement to observe foundation subgrade preparation and confirm bearing pressure capacity. Due to variable site subsurface and construction conditions, some adjustments in isolated foundation bearing pressures, depth of footings or undercutting and replacement with controlled structural fill may be necessary. 6.6.2 Subgrade Once site grading is completed, the subgrade may be exposed to adverse construction activities and weather conditions. The subgrade should be well-drained to prevent the accumulation of water. If the exposed subgrade becomes saturated or frozen, the NOVA geotechnical engineer should be consulted. A final subgrade evaluation should be performed by the NOVA geotechnical engineer immediately prior to pavements or slab-on-grade placement. If practical, proofrolling may be used to re-densify the surface and to detect any soil, which has become excessively wet or otherwise loosened. Page 14 APPENDIX A FIGURES AND MAPS See map insert below Subject Site FIGURE 1 SITE LOCATION MAP SOURCE: www.Mapquest.com DATE: Unknown SCALE: As Shown COBB COUNTY SCHOOL DISTRICT King Springs Elementary School Smyrna, Cobb County, Georgia NOVA Project Number 2011019 Subject Site FIGURE 2 TOPOGRAPHIC MAP COBB COUNTY SCHOOL DISTRICT SOURCE: www.MSRMaps.com USGS 7.5 Minute Series Topographic Quadrangle July 1, 1991 Smyrna, Georgia SCALE: As Shown King Springs Elementary School Smyrna, Cobb County, Georgia NOVA Project Number 2011019 Subject Site FIGURE 3 REGIONAL GEOLOGY Geologic Map of Georgia Georgia Department of Natural Resources, 1976 SCALE: As Shown COBB COUNTY SCHOOL DISTRICT King Springs Elementary School Smyrna, Cobb County, Georgia NOVA Project Number 2011019 B-4 B-3 B-1 B-2 NOVA SOIL TEST BORINGS FIGURE 4 BORING LOCATION PLAN SCALE: Graphic COBB COUNTY SCHOOL DISTRICT King Springs Elementary School Smyrna, Cobb County, Georgia NOVA Project Number 2011019 APPENDIX B SUBSURFACE DATA KEY TO SYMBOLS AND CLASSIFICATIONS DRILLING SYMBOLS Split Spoon Sample Undisturbed Sample (UD) Standard Penetration Resistance (ASTM D1586‐67) Water Table at least 24 Hours after Drilling Water Table 1 Hour or less after Drilling 100/2” Number of Blows (100) to Drive the Spoon a Number of Inches (2) NX, NQ Core Barrel Sizes: 2⅛‐ and 2‐Inch Diameter Rock Core, Respectively REC Percentage of Rock Core Recovered RQD Rock Quality Designation – Percentage of Recovered Core Segments 4 or more Inches Long Loss of Drilling Water MC Moisture Content Test Performed CORRELATION OF PENETRATION RESISTANCE WITH RELATIVE DENSITY AND CONSISTENCY SANDS SILTS and CLAYS Number of Blows, “N” 0–4 5 – 10 11 – 30 31 – 50 Over 50 Approximate Relative Density Very Loose Loose Medium Dense Dense Very Dense Number of Blows, “N” 0–2 3–4 5–8 9 – 15 16 – 30 31 – 50 Over 50 Approximate Consistency Very Soft Soft Firm Stiff Very Stiff Hard Very Hard DRILLING PROCEDURES Soil sampling and standard penetration testing performed in accordance with ASTM D1586‐67. The standard penetration resistance is the number of blows of a 140 pound hammer falling 30 inches to drive a 2‐inch O.D., 1⅖‐ inch I.D. split spoon sampler one foot. Core drilling performed in accordance with ASTM D2113‐62T. The undisturbed sampling procedure is described by ASTM D1587‐67. Soil and rock samples will be discarded 60 days after the date of the final report unless otherwise directed. SOIL CLASSIFICATION CHART COARSE GRAINED SOILS GRAVELS SANDS FINE GRAINED SOILS SILTS AND CLAYS Liquid Limit less than 50 SILTS AND CLAYS Liquid Limit 50 or more HIGHLY ORGANIC SOILS Clean Gravel less than 5% fines Gravels with Fines more than 12% fines Clean Sand less than 5% fines Sands with Fines more than 12% fines Inorganic Organic Inorganic Organic Organic matter, dark color, organic odor GW GP GM GC SW SP SM SC CL ML OL CH MH OH Well graded gravel Poorly graded gravel Silty gravel Clayey gravel Well graded sand Poorly graded sand Silty sand Clayey sand Lean clay Silt Organic clay and silt Fat clay Elastic silt Organic clay and silt PT Peat PARTICLE SIZE IDENTIFICATION GRAVELS Coarse Fine ¾ inch to 3 inches No. 4 to ¾ inch SANDS Coarse Medium Fine No. 10 to No. 4 No. 40 to No. 10 No. 200 to No. 40 SILTS AND CLAYS Passing No. 200 AFTER 24 HOURS: This information pertains only to this boring and should not be interpreted as being indicative of the site. 0 1010 ASPHALT: 2 inches GRAVEL: 3 inches RESIDUUM: Very stiff red purple brown fine sandy micaceous SILT N/O 2011019 1013 ft. -MSL S. Miller 03-12-11 CAVING> Graphic Depiction N-Value Description ELEVATION: LOGGED BY: DATE: Sample Type 46 PROJECT NO.: Groundwater DEPTH TO - WATER> INITIAL: Graphic Elevation (ft-MSL) Depth (feet) TEST BORING RECORD B-1 PROJECT: King Springs Elementary School CLIENT: Cobb County School District PROJECT LOCATION: 1041 Reed Road LOCATION: Smyrna, Cobb County, Georgia DRILLER: Sunrise Drilling Company DRILLING METHOD: Hollow Stem Auger BLOW COUNT NATURAL MOISTURE PLASTIC LIMIT LIQUID LIMIT 10 20 30 40 60 80 18 20 5 21 1005 18 10 1000 28 15 995 28 20 990 Very hard to hard gray tan brown fine sandy very micaceous SILT 63 25 985 40 30 980 35 36 Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate. Page 1 of 2 This information pertains only to this boring and should not be interpreted as being indicative of the site. AFTER 24 HOURS: N/O 2011019 1013 ft. -MSL S. Miller 03-12-11 CAVING> Graphic Depiction N-Value Description ELEVATION: LOGGED BY: DATE: Sample Type 46 PROJECT NO.: Groundwater DEPTH TO - WATER> INITIAL: Graphic Elevation (ft-MSL) Depth (feet) TEST BORING RECORD B-1 PROJECT: King Springs Elementary School CLIENT: Cobb County School District PROJECT LOCATION: 1041 Reed Road LOCATION: Smyrna, Cobb County, Georgia DRILLER: Sunrise Drilling Company DRILLING METHOD: Hollow Stem Auger 975 BLOW COUNT NATURAL MOISTURE PLASTIC LIMIT LIQUID LIMIT 10 20 30 40 60 80 63 40 970 45 PARTIALLY WEATHERED ROCK: Sampled as very hard gray brown fine sandy very micaceous SILT 100/12" 965 100/10" 50 Boring Terminated at 50 ft. 960 55 955 60 950 65 945 70 940 75 Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate. Page 2 of 2 AFTER 24 HOURS: This information pertains only to this boring and should not be interpreted as being indicative of the site. 0 ASPHALT: 2 inches GRAVEL: 3 inches FILL: Stiff to very stiff red orange brown fine sandy SILT N/O 2011019 1013 ft. -MSL S. Miller 03-12-11 CAVING> Graphic Depiction N-Value Description ELEVATION: LOGGED BY: DATE: Sample Type N/E PROJECT NO.: Groundwater DEPTH TO - WATER> INITIAL: Graphic Elevation (ft-MSL) Depth (feet) TEST BORING RECORD B-2 PROJECT: King Springs Elementary School CLIENT: Cobb County School District PROJECT LOCATION: 1041 Reed Road LOCATION: Smyrna, Cobb County, Georgia DRILLER: Sunrise Drilling Company DRILLING METHOD: Hollow Stem Auger BLOW COUNT NATURAL MOISTURE PLASTIC LIMIT LIQUID LIMIT 10 20 30 40 60 80 11 1010 21 5 16 1005 11 10 RESIDUUM: Very stiff red orange brown fine sandy SILT with rock fragments 1000 21 15 995 19 20 Boring Terminated at 20 ft. 990 25 985 30 980 35 Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate. Page 1 of 1 AFTER 24 HOURS: This information pertains only to this boring and should not be interpreted as being indicative of the site. 0 ASPHALT: 2 inches GRAVEL: 3 inches FILL: Stiff red brown fine sandy SILT with rock fragments N/O 2011019 1014 ft. -MSL S. Miller 03-12-11 CAVING> Graphic Depiction N-Value Description ELEVATION: LOGGED BY: DATE: Sample Type 38 PROJECT NO.: Groundwater DEPTH TO - WATER> INITIAL: Graphic Elevation (ft-MSL) Depth (feet) TEST BORING RECORD B-3 PROJECT: King Springs Elementary School CLIENT: Cobb County School District PROJECT LOCATION: 1041 Reed Road LOCATION: Smyrna, Cobb County, Georgia DRILLER: Sunrise Drilling Company DRILLING METHOD: Hollow Stem Auger BLOW COUNT NATURAL MOISTURE PLASTIC LIMIT LIQUID LIMIT 10 20 30 40 60 80 9 1010 11 5 RESIDUUM: Stiff to very stiff red orange brown fine sandy SILT with rock fragments 14 1005 23 10 1000 13 15 995 17 20 990 25 25 985 30 PARTIALLY WEATHERED ROCK: Sampled as very hard brown green fine sandy SILT with rock fragments 100/10" 980 35 100/8" Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate. Page 1 of 2 This information pertains only to this boring and should not be interpreted as being indicative of the site. ELEVATION: LOGGED BY: DATE: AFTER 24 HOURS: N/O 2011019 1014 ft. -MSL S. Miller 03-12-11 CAVING> N-Value Graphic Depiction Sample Type Description 38 PROJECT NO.: Groundwater DEPTH TO - WATER> INITIAL: Graphic Elevation (ft-MSL) Depth (feet) TEST BORING RECORD B-3 PROJECT: King Springs Elementary School CLIENT: Cobb County School District PROJECT LOCATION: 1041 Reed Road LOCATION: Smyrna, Cobb County, Georgia DRILLER: Sunrise Drilling Company DRILLING METHOD: Hollow Stem Auger BLOW COUNT NATURAL MOISTURE PLASTIC LIMIT LIQUID LIMIT 10 20 30 40 60 80 975 100/6" 40 970 100/12" 45 965 100/0" 50 Boring Terminated at 50 ft. 960 55 955 60 950 65 945 70 940 75 Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate. Page 2 of 2 AFTER 24 HOURS: This information pertains only to this boring and should not be interpreted as being indicative of the site. 0 ASPHALT: 2 inches GRAVEL: 1 inch RESIDUUM: Very stiff to hard brown fine sandy micaceous SILT N/O 2011019 1014 ft. -MSL S. Miller 03-12-11 CAVING> Graphic Depiction N-Value Description ELEVATION: LOGGED BY: DATE: Sample Type N/E PROJECT NO.: Groundwater DEPTH TO - WATER> INITIAL: Graphic Elevation (ft-MSL) Depth (feet) TEST BORING RECORD B-4 PROJECT: King Springs Elementary School CLIENT: Cobb County School District PROJECT LOCATION: 1041 Reed Road LOCATION: Smyrna, Cobb County, Georgia DRILLER: Sunrise Drilling Company DRILLING METHOD: Hollow Stem Auger BLOW COUNT NATURAL MOISTURE PLASTIC LIMIT LIQUID LIMIT 10 20 30 40 60 80 21 1010 25 5 21 1005 29 10 1000 21 15 995 33 20 Boring Terminated at 20 ft. 990 25 985 30 980 35 Note: Elevations were interpolated from the provided topographic site plan and should therefore be considered approximate. Page 1 of 1 APPENDIX C QUALIFICATIONS OF RECOMMENDATIONS QUALIFICATIONS OF RECOMMENDATIONS The findings, conclusions and recommendations presented in this report represent our professional opinions concerning subsurface conditions at the site. The opinions presented are relative to the dates of our site work and should not be relied on to represent conditions at later dates or at locations not explored. The opinions included herein are based on information provided to us, the data obtained at specific locations during the study and our past experience. If additional information becomes available that might impact our geotechnical opinions, it will be necessary for NOVA to review the information, reassess the potential concerns, and re-evaluate our conclusions and recommendations. Regardless of the thoroughness of a geotechnical exploration, there is the possibility that conditions between borings will differ from those encountered at specific boring locations, that conditions are not as anticipated by the designers and/or the contractors, or that either natural events or the construction process have altered the subsurface conditions. These variations are an inherent risk associated with subsurface conditions in this region and the approximate methods used to obtain the data. These variations may not be apparent until construction. The professional opinions presented in this geotechnical report are not final. Field observations and foundation installation monitoring by the geotechnical engineer, as well as soil density testing and other quality assurance functions associated with site earthwork and foundation construction, are an extension of this report. Therefore, NOVA should be retained by the owner to observe all earthwork and foundation construction to document that the conditions anticipated in this study actually exist, and to finalize or amend our conclusions and recommendations. NOVA is not responsible or liable for the conclusions and recommendations presented in this report if NOVA does not perform these observation and testing services. This report is intended for the sole use of Cobb County School District only. The scope of work performed during this study was developed for purposes specifically intended by Cobb County School District and may not satisfy other users requirements. Use of this report or the findings, conclusions or recommendations by others will be at the sole risk of the user. NOVA is not responsible or liable for the interpretation by others of the data in this report, nor their conclusions, recommendations or opinions. Our professional services have been performed, our findings obtained, our conclusions derived and our recommendations prepared in accordance with generally accepted geotechnical engineering principles and practices in the State of Georgia. This warranty is in lieu of all other statements or warranties, either expressed or implied. MARCH 16, 2010 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 00901 - 1 ADDENDUM NO. 1 SECTION 00901 ADDENDUM NO. 1 PART 1 - GENERAL 1.1 GENERAL REQUIREMENTS A. General: For the purpose of proposal, the Bidding and Contract Documents for the above project are changed as described herein. The changes shall take precedence, and all other provisions of the Bidding and Contract Documents shall remain in force. B. Notation on Bid Form: Failure to note receipt of this Addendum on a submitted Bid Form in accordance with the Bidding Documents may be cause for rejection of any Bid so submitted. PART 2 - DRAWING CHANGES 2.1 A. REVISED DRAWINGS The following Drawings have been revised, bear revision date MARCH 16, 2011, are issued with this Addendum, and are deemed a part thereof. The changes to be made are identified on each Drawing. Number Title See attached list of drawings. PART 3 - SPECIFICATION CHANGES 3.1 A. NEW SPECIFICATIONS The following additional Specification sections dated MARCH 16, 2011 are issued with this Addendum, and are deemed a part thereof. In addition, these sections are added to the Table of Contents within the Project Manual. Section Number -------00901 07415 07420 10152 10531 Title Report of Subsurface Exploration and Geotechnical Engineering Evaluation Addendum No. 1 Metal Cladding Systems Composite Panels Hospital Cubical Curtains and Tracks Aluminum Canopy Structures SECTION 00901 - 2 ADDENDUM NO. 1 3.2 A. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 REVISED SPECIFICATIONS The following Specification sections have been revised, bear revision date MARCH 16, 2011, are issued with this Addendum, and are deemed a part thereof. The changes to be made are identified on the revised pages of each section, attached hereinafter, unless noted otherwise. Section Number/Page -------00020 00210 -------01010 01101 04210 06400 15800 15840 Title Table of Contents Advertisement Invitation For Bids Specific Date Construction Schedule Floor Phasing Plan of King Springs Elementary School Summary of Work Alternates Brick Architectural Woodwork Air Distribution Devices Ductwork END OF SECTION Drwg Revision LOG D.4 Addendum Drawing Revision Log: Changes included prior to signed Contract for Construction Draw Rev LOG Project Name: King Springs Elementary School Project Name: Project Number: Principal In Charge: Project Architect: Contract Administration Lead: Date of Permit / Bid Set: Date of Notice to Proceed: King Springs Elementary 20100358 Jerome M. Cooper William Collier 2/24/2011 XX/XX/XX Project Number: 20100358 Revised, Deleted or New Issued as COVER SHEET Revised Addendum 1 GENERAL INFORMATION & SHEET INDEX Revised Addendum 1 SITE DEMOLITION PLAN Revised Addendum 1 SITE LAYOUT & STAKEOUT PLAN Revised Addendum 1 SITE GRADING, DRAINAGE & UTILITY PLAN Revised Addendum 1 03/16/11 DEMOLITION PLANS Revised Addendum 1 03/16/11 ENLARGED FLOOR PLAN – ADMINISTRATION ADDITION Revised Addendum 1 A2.2 03/16/11 Addendum 1 03/16/11 ENLARGED FLOOR PLAN – RENOVATED ADMINISTRATION ENLARGED FLOOR PLAN – RESTROOMS Revised A2.6 Revised Addendum 1 A2.7 03/16/11 RESERVED Revised Addendum 1 A2.8 03/16/11 PARTIAL LOWER ROOF PLAN Revised Addendum 1 A2.9 03/16/11 PARTIAL UPPER ROOF PLAN Revised Addendum 1 Drawing # Date G0.0 03/16/11 G0.2 03/16/11 C2.0 03/16/11 C3.0 03/16/11 C4.0 03/16/11 A1.2 A2.1 Title A3.1 03/16/11 FINISH FLOOR PLAN – ADMINISTRATION ADDITION Revised Addendum 1 A3.2 03/16/11 FINISH FLOOR PLAN – RENOVATED ADMINISTRATION Revised Addendum 1 Addendum 1 A3.3 03/16/11 FINISH FLOOR PLAN – CLASSROOM WING SOUTH Revised A3.4 03/16/11 FINISH FLOOR PLAN – MEDIA CENTER AND CAFETERIA Revised Addendum 1 A3.5 03/16/11 FINISH FLOOR PLAN – CLASSROOM WING NORTH Revised Addendum 1 A4.1 03/16/11 EXTERIOR BUILDING ELEVATIONS Revised Addendum 1 A4.2 03/16/11 EXTERIOR BUILDING ELEVATIONS Revised Addendum 1 A4.3 03/16/11 BUILDING SECTIONS Revised Addendum 1 A5.1 03/16/11 BUILDING SECTIONS Revised Addendum 1 A5.3 03/16/11 INTERIOR ELEVATIONS Revised Addendum 1 A6.1 03/16/11 SECTION DETAILS Revised Addendum 1 A9.1 03/16/11 PARTITION SCHEDULE, NOTES, AND DETAILS Revised Addendum 1 A11.1 03/16/11 ENLARGED REFLECTED CEILING PLANS Revised Addendum 1 A11.2 03/16/11 ENLARGED REFLECTED CEILING PLANS Revised Addendum 1 S2.1 03/16/11 FOUNDATION AND FRAMING PLANS Revised Addendum 1 S3.1 03/16/11 SECTIONS Revised Addendum 1 S4.2 03/16/11 TYPICAL DETAILS Revised Addendum 1 M1.0 03/16/11 DEMOLITION PLAN-MECHANICAL Revised Addendum 1 M2.0 03/16/11 REFERENCE PLAN –MECHANICAL Revised Addendum 1 M2.1 03/16/11 ADMINISTRATION ADDITION FLOOR PLAN-MECHANICAL Revised Addendum 1 M2.2 M2.3 03/16/11 03/16/11 ADMINISTRATION RENOVATION FLOOR PLAN-MECHANICAL NORTH WING PARTIAL FLOOR PLAN-MECHANICAL Revised Revised Addendum 1 Addendum 1 M2.4 03/16/11 ROOF PLAN-MECHANICAL Revised Addendum 1 M7.1 03/16/11 LEGEND, NOTES, SCHEDULES & ABBREVIATIONSMECHANICAL Revised Addendum 1 P1.0 03/16/11 DEMOLITION PLAN-PLUMBING Revised Addendum 1 P2.0 03/16/11 REFERENCE PLAN-PLUMBING Revised Addendum 1 P2.2 03/16/11 ADMINISTRATION RENOVATION FLOOR PLAN-PLUMBING Revised Addendum 1 P2.5 03/16/11 ROOF PLAN-PLUMBING Revised Addendum 1 P4.1 03/16/11 RESTROOMS PARTIAL FLOOR PLANS-PLUMBING Revised Addendum 1 E0.1 03/16/11 ELECTRICAL LEGEND, NOTES & SCHEDULES Revised Addendum 1 E1.1 03/16/11 ADMINISTRATION ADDITION FLOOR PLAN-ELECTRICAL Revised Addendum 1 E1.2 03/16/11 ADMINISTRATION RENOVATION FLOOR PLAN-ELECTRICAL Revised Addendum 1 E1.5 03/16/11 NORTH WING PARTIAL FLOOR PLAN-ELECTRICAL Revised Addendum 1 E2.1 03/16/11 ADMINISTRATION ADDITION FLOOR PLAN-LIGHTING Revised Addendum 1 E2.2 03/16/11 ADMINISTRATION RENOVATION FLOOR PLAN-LIGHTING Revised Addendum 1 E/Administrative/Draft CA Forms/Final/revised-dwg_00901-a1-d-4_addendums_log.xls Date Printed: 3/21/2011 Page #1 REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 01010 - 1 SUMMARY OF WORK SECTION 01010 SUMMARY OF WORK PART 1 - GENERAL 1.1 A. 1.2 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General Conditions, other sections of Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project Manual apply to the work specified in this Section. WORK COVERED BY CONTRACT DOCUMENTS A. Scope: The Contractor shall supply materials, labor, tools, plant, supplies, equipment, transportation, superintendence, temporary construction of every nature, and other services and facilities necessary to complete the construction of the described facilities, including, but not limited to, incidental work described in the Contract Documents. B. Work Includes: Work covers demolition, renovation, construction and maintenance of King Springs Elementary School, located in Smyrna, Georgia. C. Hazardous Materials: Do not incorporate any products or materials into the work that contain asbestos or other hazardous substances, as such are defined under the federal Toxic Substance Control Act, 15 U.S.C. § 2601 et seq., and the rules and regulations promulgated pursuant thereto, and more specifically 40 C.F.R. § 763.103 (c) (1988). 1.3 CONTRACTS A. Construct work under a single contract. 1.4 WORK UNDER OTHER CONTRACTS A. 1.5 The following items of work will be furnished and installed by the Owner: 1. Asbestos abatement. 2. Audio/Visual 3. Furniture and furnishings. OWNER-FURNISHED PRODUCTS A. Products Furnished by the Owner: 1. Relocate existing vault from media center corridor to Records / Vault Room.. 2. Relocate existing PA (public address) main unit from current reception to new reception. 3. Relocate existing knox box to location shown on the Drawings. 4. Relocate existing mailboxes to Work Room No. 218 as shown on the Drawings. B. Owner's Duties: 1. Schedule delivery date with supplier in accordance with Construction Progress Schedule. 2. Make specified submittals to the Contractor. 3. Submit claims for transportation damages. 4. Arrange warranties. SECTION 01010 - 2 SUMMARY OF WORK C. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Contractor's Duties: 1. Designate required submittal date for each product in the Submittals Schedule. 2. Coordinate submittals with work of adjacent trades and submit them to the Architect. 3. Designate required delivery date for each product in the Construction Progress Schedule. 4. Promptly inspect delivered products, report damaged or defective items to the Owner. 5. Handle at site, including, but not limited to, unloading, uncrating, and storage. 6. Protect from exposure to elements and from damage. 7. Repair or replace damaged items. 8. Install, connect, and finish products. 1.6 SITE INVESTIGATION DATA A. Investigation Report: 1. General: Soil and subsurface investigations were conducted at the site, the results of which are to be found in a report dated MARCH 17, 2011 and issued by: Name: Address: City, State, Zip: Telephone: Fax: 2. 3. B. 1.7 A. NOVA Engineering and Environmental 3640 Kennesaw North Industrial Pkwy, Suite E Kennesaw, GA 30144 770-425-0777 770-425-1113 Copies: The report is included in the project manual. Status: The soil and subsurface investigation report is not a part of the Contract Documents. The bidder or Contractor who obtains a copy of the report releases the Owner and the Architect from any responsibility or obligation as to its accuracy or completeness or for any additional compensation for work performed under the Contract due to assumptions based on use of such furnished information. Interpretation: Data concerning subsurface materials or conditions which is based upon soundings, test pits, or test borings, has been obtained by the Owner for the Architect's use in designing the Project. Its accuracy or completeness is not guaranteed by the Owner or the Architect. The Contractor shall assume all responsibility in excavating for this Project and shall not rely on subsurface information obtained from the Architect, or indirectly from the Owner. Bidders or the Contractor shall make their own investigation of existing subsurface conditions; neither the Owner or the Architect will be responsible in any way for additional compensation for excavation work performed under the Contract due to the Contractor's assumptions based on soil investigation data prepared solely for the Architect's use. The Contractor shall notify the Owner and the Architect in writing immediately should any discrepancy be discovered between the conditions at the site and information contained in the report. CONTRACTOR'S USE OF PREMISES The Contractor shall confine operations at the site to areas permitted by law, ordinances, permits, and the Contract Documents and shall not unreasonably encumber the site with materials and equipment. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 1.8 A. 1.9 SECTION 01010 - 3 SUMMARY OF WORK OCCUPANCY REQUIREMENTS Partial Owner Occupancy: The Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with the Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the work so as not to interfere with Owner's operations. Maintain existing exits, unless otherwise indicated. Make available for the Owner's use such building services as heating, ventilating, cooling, water, lighting, and telephone; and complete as soon as practicable, equipment required to furnish such services which are not ready for operation and use. 1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Owner and authorities having jurisdiction. 2. Provide not less than 72 hours' notice to the Owner of activities that will affect the Owner's operations. WORK RESTRICTIONS A. On-Site Work Hours: Work shall be generally performed during normal business working hours, Monday through Friday, except as otherwise agreed to by the Owner. 1. Hours for Noisy Activity: Restricted per local ordinance. B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by the Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated: 1. Notify the Owner not less than two days in advance of proposed utility interruptions. 2. Do not proceed with utility interruptions without the Owner's written permission. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) END OF SECTION REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 01101-1 ALTERNATES SECTION 01101 ALTERNATES PART ONE-GENERAL 1.01 BIDDING REQUIRMENTS CCSD may use deductive alternates to reduce the base bid on state- funded projects using the design/bid/build construction delivery method; however, the deductive alternates shall be bid prioritized and exercised in numerical sequence as used in the bid documents. When the CCSD determines that deductive alternatives must be selected, all bids will be recalculated removing the deductive alternates to be taken. The low bid shall then be determined on the base bid less any deductive alternates. The plans and specifications shall indicate if the project will be awarded by base bid or base bid plus selected alternates. Additive alternates may be exercised in any order. If the plans and specifications state that the contract will be awarded on base bid, then additive alternates are considered only after the low base bidder has been declared. If the plans and specifications state that the project will be awarded by base bid plus additive alternates, all bids will be recalculated adding the additive alternates to be taken. The low bid shall then be determined on the base bid plus the selected additive alternates. 1.02 DESCRIPTION: A. An alternate is an amount proposed by bidders, and stated on the Bid Form, for certain work defined in the Bidding Requirements that may be added to or deducted from the Base Bid amount if the Owner decides to accept a corresponding change in either the amount of construction to be completed, or in the products, materials, equipment, systems, or installation methods described in the Contract Documents. B. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate the Alternate into the Work. No other adjustments are made to the Contract Sum. C. Related Work Described Elsewhere: 1. Materials and methods to be used in the Base Bid and in the Alternates have been described on the Drawings and in pertinent Sections of these Specifications. 2. Method for stating the proposed Contract Sum is described in the bid form. 1.03 All alternates described in this Section are required to be reflected on the Bid Form as submitted by Bidders. Do not submit Alternates other than as described in this Section. 1.04 If the Owner elects to proceed on the basis of one or more of the Alternates, the Contractor shall make all modifications to the work required in furnishing and installing the selected Alternates to the approval of the Architect and at no additional cost to the Owner other than as proposed on the Bid Form. 1.05 All Alternates must be executed with an appropriate response. A "blank space", or a "No Bid" statement is inappropriate. The space must include a "Specific Sum" or a "No Change in Price" statement. Failure to provide this information may be cause for rejection of the bid at the Owner's discretion. 1.06 Proposal amounts for Alternates shall remain open for acceptance by the Owner for (60) sixty days after the Notice of Award date. 1.07 If liquidated damages are deleted by Alternate, Addendum or Change Order, completion time remains unchanged and time is still the essence of the contract and in lieu of liquidated damages the Owner retains the right to pursue the collection of actual damages for delayed completion, pursuant to the provisions of the contract documents, under existing state statutes and/or law. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 01101-2 ALTERNATES PART TWO - SCHEDULE OF ALTERNATES: ALTERNATE NO. 1: The deletion of liquidated damages: (See Section 00820) ALTERMATE NO. 2: Provide METAL CLADDING SYSTEM as defined in Section 07415 in lieu of COMPOSITE PANELS as defined in Section 07420. ALTERMATE NO. 3: Delete the demolition and renovation of the existing Counselor's office to new Classroom 125, including new RTU & associated ductwork, electrical, lighting, flooring and ceiling. ALTERMATE NO. 4: Delete 2 foot wide cantilevered metal panel "eyebrow" at new administration wing and accent brick color below. Replace with standard running bond brick. END OF SECTION REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 04210 - 1 BRICK SECTION 04210 BRICK PART 1 - GENERAL 1.1 A. 1.2 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General Conditions, Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project Manual apply to the work specified in this Section. SUMMARY A. Scope: Provide labor, material, equipment, related services, and supervision required, including, but not limited to, manufacturing, fabrication, erection, and installation for brick as required for the complete performance of the work, and as shown on the Drawings and as herein specified. B. Section Includes: The work specified in this Section includes, but shall not be limited to, clay unit masonry in the form of brick. 1.3 REFERENCES A. The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by the basic designation only. B. The edition/revision of the referenced publications shall be the latest date as of the date of the Contract Documents, unless otherwise specified. C. ASTM (ASTM): 1. ASTM C 67, "Standard Test Methods of Sampling and Testing Brick and Structural Clay Tile." 2. ASTM C 216, "Standard Specification for Facing Brick (Solid Masonry Units Made from Clay or Shale)." 1.4 SUBMITTALS A. General: See Section 01300 - SUBMITTALS. 1. See Section 04200 - UNIT MASONRY. B. Product Data: Submit product data showing material proposed. Submit sufficient information to determine compliance with the Drawings and Specifications. Product data shall include, but shall not be limited to, manufacturer's recommended cleaning agent and application procedure. C. Shop Drawings: Submit shop drawings for each product and accessory required. Include information not fully detailed in manufacturer’s standard product data. D. Samples: 1. Submit samples for verification purposes. Submit two sets of samples of each type of exposed brick specified. Include in each set the full range of exposed color and texture to be expected in the completed work. SECTION 04210 - 2 BRICK E. 1.5 REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Qualification Data: Submit qualification data for firms and persons specified in Quality Assurance Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names of architects and owners, and other information specified. QUALITY ASSURANCE A. Qualifications: 1. Manufacturer Qualifications: Manufacturer shall be a firm engaged in the manufacture of brick of types and sizes required, and whose products have been in satisfactory use in similar service for a minimum of five years. 2. Installer Qualifications: Installer shall be a firm that shall have a minimum of five years of successful installation experience with projects utilizing brick similar in type and scope to that required for this Project. B. Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances, and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary approvals from such authorities. C. Mock-Ups: See Section 04200 - UNIT MASONRY. D. Pre-Installation Conference: See Section 04200 - UNIT MASONRY. E. Single Source Responsibility: Obtain exposed brick units of a uniform texture and color, or a uniform blend within the ranges accepted for these characteristics, from one source and by a single manufacturer for each different product required. 1.6 A. 1.7 A. DELIVERY, STORAGE, AND HANDLING Store brick on elevated platforms, under cover, and in a dry location to prevent their deterioration or damage due to moisture, temperature changes, contaminants, corrosion, or other causes. If units become wet, do not install until they are in an air-dried condition. PROJECT CONDITIONS See Section 04200 - UNIT MASONRY. PART 2 - PRODUCTS 2.1 A. MANUFACTURERS Manufacturer: Subject to compliance with requirements, provide products of one of the following: 1. Acme Brick Co. 2. Cherokee Sanford Group, Inc. 3. D'Hanis Brick and Tile Co. 4. Henderson Brick. 5. Henry Brick. 6. Interstate Brick Div., Pacific Coast Building Products. 7. Jenkins Brick Co. 8. Lee Brick Co. 9. Merry Brothers Brick & Tile Co. 10. Palmetto Brick. 11. Robinson Brick Co. 12. Summit Brick & Tile Co. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 04210 - 3 BRICK 13. Victor Cushwa & Sons, Inc. B. 2.2 Basis of Design: Items specified are to establish a standard of quality for design, function, materials, and appearance. Equivalent products by listed manufacturers are acceptable. The Architect will be the sole judge of the basis of what is equivalent. BRICK MATERIALS A. General: Provide shapes indicated and as follows for each form of brick required. Provide units without cores or frogs and with exposed surfaces finished for ends of sills and caps and for similar applications that would otherwise expose unfinished brick surfaces. B. Special Shapes: Provide special shapes for applications requiring brick of size, form, color, and texture on exposed surfaces that cannot be produced by sawing. 1. Provide special shapes for applications where stretcher units cannot accommodate special conditions, including, but not limited to, those at corners, movement joints, bond beams, sashes, and lintels. 2. Provide special shapes for applications where shapes produced by sawing would result in sawed surfaces being exposed to view. C. Face Brick: ASTM C 216 and as follows: 1. Grade: Grade SW. 2. Unit Compressive Strength: 3000 psi. 3. Initial Rate of Absorption: Between 5 grams per 30 square inches and 20 grams per 30 square inches per minute when tested per ASTM C 67. 4. Surface Coloring: Brick with surface coloring, other than flashed or sand-finished brick, shall withstand 50 cycles of freezing and thawing per ASTM C 67 with no observable difference in the applied finish when viewed from 10 feet. 5. Type: Type FBS. 6. Size: Bricks manufactured to the following actual dimensions within tolerances specified in ASTM C 216: a. Modular: 3-1/2 inches to 3-5/8 inches thick by 2-1/4 inches high by 7-1/2 inches to 7-5/8 inches long. 7. Application: Use where brick is exposed, unless otherwise indicated. 8. Match Existing: Where shown to match existing, provide face brick matching color, texture, and size of existing adjacent brickwork. (Auditorium wall - North wall of bus corridor.) 9. Color and Texture: Match the Architect's samples. 10. Color and Texture: Medium brown, wirecut. 11. Color and Texture: Full-range red, sand-molded. 12. Color and Texture: Gray, velour. 13. Basis of Design: a. Field Brick: 1) "No. 204F", Plant # 4, Lee Brick Co. 2) "Range Alahambra, Montgomery Plant", Jenkins Brick Co. 3) "FR Diplomat", Henry Brick. b. Accent Brick: Continuous soldier course below metal panel "eyebrow". 1) "Whitestone", Palmetto Brick 2.3 A. SOURCE QUALITY CONTROL General: The Owner will employ and pay a qualified independent inspecting and testing agency to perform the following testing for source quality control. Retesting of materials failing to meet specified requirements shall be done at the Contractor's expense. SECTION 04210 - 4 BRICK 1. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Brick Tests: For each type and grade of brick indicated, units will be tested per ASTM C 67 except five bricks will be selected at random for each 100,000 units or fraction thereof installed. PART 3 - EXECUTION 3.1 A. 3.2 A. 3.3 A. 3.4 A. 3.5 A. EXAMINATION Verification of Conditions: Examine areas and conditions under which the work is to be installed, and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected. 1. Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by the Installer. PREPARATION See Section 04200 - UNIT MASONRY. INSTALLATION See Section 04200 - UNIT MASONRY. ADJUSTING AND CLEANING See Section 04200 - UNIT MASONRY. PROTECTION Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall ensure that the brick shall be without damage at time of Substantial Completion. END OF SECTION REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 06400 - 1 ARCHITECTURAL WOODWORK SECTION 06400 ARCHITECTURAL WOODWORK PART 1 - GENERAL 1.1 A. 1.2 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General Conditions, Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project Manual apply to the work specified in this Section. SUMMARY A. Scope: Provide labor, material, equipment, related services, and supervision required, including, but not limited to, manufacturing, fabrication, erection, and installation for architectural woodwork as required for the complete performance of the work, and as shown on the Drawings and as herein specified. B. Section Includes: The work specified in this Section includes, but shall not be limited to, the following: 1. Laminate-clad cabinets. 2. Laminate-clad countertops. 1.3 REFERENCES A. The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by the basic designation only. B. The edition/revision of the referenced publications shall be the latest date as of the date of the Contract Documents, unless otherwise specified. C. American National Standards Institute (ANSI): 1. ANSI A208.2, "Medium Density Fiberboard for Interior Use.” D. American Society of Mechanical Engineers (ASME): 1. ANSI/ASME B18.6.1, "Wood Screws (Inch Series)” (copyrighted by ASME, ANSI approved). E. American Wood Preservers Association (AWPA): 1. AWPA C20, "Structural Lumber, Fire-Retardant Pressure Treatment." F. Architectural Woodwork Institute (AWI): 1. AWI AWQSI, "Architectural Woodwork Quality Standards Illustrated." G. ASTM (ASTM): 1. ASTM C 1048, "Standard Specification for Heat-Treated Flat Glass - Kind HS, Kind FT Coated and Uncoated Glass." 2. ASTM E 84, "Standard Test Method for Surface Burning Characteristics of Building Materials." 3. ASTM F 1667, "Standard Specification for Driven Fasteners: Nails, Spikes, and Staples.” SECTION 06400 - 2 ARCHITECTURAL WOODWORK REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 H. Builders Hardware Manufacturers Association, Inc. (BHMA): 1. ANSI/BHMA A156.9, "Cabinet Hardware" (copyrighted by BHMA, ANSI approved). 2. ANSI/BHMA A156.18, "Materials and Finishes" (copyrighted by BHMA, ANSI approved). I. Glass Association of North America (GANA): 1. GANA GM, "Glazing Manual.” J. Green Seal (GS): 1. GS-37, “Industrial & Institutional Cleaners.” K. Hardwood Plywood and Veneer Association (HPVA): 1. ANSI/HPVA HP-1, "American National Standard for Hardwood and Decorative Plywood" (copyrighted by HPVA, ANSI approved). L. National Electrical Manufacturers Association (NEMA): 1. NEMA LD 3, "High Pressure Decorative Laminate." M. National Particleboard Association (NPA): 1. NPA 9, "Voluntary Standard for Formaldehyde Emission From Medium Density Fiberboard (MDF)." N. South Coast Air Quality Management District (SCAQMD): 1. SCAQMD Rule #1168, “Adhesive and Sealant Applications,” including most recent amendments. O. U.S. Department of Commerce, National Institute of Standards and Technology (DOC PS): 1. DOC PS 1, "U.S. Product Standard for Construction and Industrial Plywood." 1.2 A. 1.3 DEFINITIONS Architectural woodwork includes, but shall not be limited to, wood furring, blocking, shims, hanging strips, etc., as required for installing architectural woodwork items unless concealed within other construction prior to architectural woodwork installation. SUBMITTALS A. General: See Section 01300 - SUBMITTALS. B. Product Data: Submit product data showing material proposed. Submit sufficient information to determine compliance with the Drawings and Specifications. Submit product data for each type of product and process specified and incorporated into items of architectural woodwork during fabrication, finishing, and installation. C. Shop Drawings: Submit shop drawings for each product and accessory required. Include information not fully detailed in manufacturer’s standard product data, including, but not limited to, location of each item in dimensioned plans and elevations, large scale details, attachment devices, and other components. D. Samples: 1. Submit samples for initial color selection. Submit samples of each specified finish. Submit samples in form of manufacturer’s color charts showing full range of colors and finishes available. Where finishes involve normal color variations, include samples showing the full, range of variations expected. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 2. SECTION 06400 - 3 ARCHITECTURAL WOODWORK Submit samples for verification purposes. Additional samples may be required to show fabrication techniques and workmanship. Submit samples as follows: a. Laminate-clad products, 8 inches by 10 inches, for each type, color, pattern, and surface finish. b. Exposed cabinet hardware, one unit of each type and finish. E. Quality Control Submittals: 1. Fire Retardant Treatment Data: Submit fire retardant treatment data for material treated to reduce combustibility. Include certification by treating plant that treated materials comply with requirements. 2. Qualification Data: Submit qualification data for firms and persons specified in Quality Assurance Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names of architects and owners, and other information specified. F. Low-Emitting Materials: Submit certification by the manufacturer confirming that products (i.e., adhesives, sealants, paints, coatings, etc.) meet or exceed the volatile organic compound (VOC) limits set by specific agencies or other requirements as outlined in Section 01110 - LOW-EMITTING MATERIALS. VOC limits shall be clearly stated in the submittal. G. Maintenance Data: Submit maintenance data for architectural woodwork to include in operation and maintenance manuals specified in Division 1 - GENERAL REQUIREMENTS. 1.4 QUALITY ASSURANCE A. Qualifications: 1. Fabricator Qualifications: Fabricator shall be a firm engaged in the fabrication of architectural woodwork of types and sizes required, whose products have been in satisfactory use in similar service for a minimum of five years, and with sufficient capacity to produce required units without delaying the work. a. Fabricator shall assume undivided responsibility for fabricating and installing architectural woodwork specified in this Section. B. Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances, and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary approvals from such authorities. C. Quality Standard: Comply with AWI AWQSI for grades of architectural woodwork, construction, finishes, and other requirements. Provide AWI Certification labels or Certificates of Compliance indicating that woodwork meets requirements of grades specified. D. Surface Burning Characteristics: Provide materials with the following characteristics as determined by testing identical products per ASTM test method indicated below, by Underwriters Laboratories, Inc. (UL), Intertek Testing Services (ITS), or another inspecting and testing agency acceptable to authorities having jurisdiction. 1. Surface burning characteristics shall not exceeding values indicated below, tested per ASTM E 84. a. Flame Spread: 75. b. Smoke Developed: 450. 2. Identify fire retardant-treated material with appropriate markings of inspecting and testing agency in the form of separable paper label or, where required by authorities having jurisdiction, imprinted on surfaces of materials that will be concealed from view after installation. SECTION 06400 - 4 ARCHITECTURAL WOODWORK REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 E. Mock-Ups: Prior to installation of the work, fabricate and erect mock-ups for each type of finish and application required to verify selections made under sample submittals and to demonstrate aesthetic effects as well as qualities of materials and execution. Build mock-ups to comply with the following requirements, using materials indicated for final unit of work. 1. Locate mock-ups on site in location and of size indicated or, if not indicated, as directed by the Architect. 2. Demonstrate the proposed range of aesthetic effects and workmanship to be expected in the completed work. 3. Obtain the Architect’s acceptance of mock-ups before start of final unit of work. 4. Retain and maintain mock-ups during construction in undisturbed condition as a standard for judging completed unit of work. a. Accepted mock-ups in undisturbed condition at time of Substantial Completion may become part of completed unit of work. F. Pre-Installation Conference: Conduct pre-installation conference in accordance with Section 01312 - PROJECT MEETINGS. Prior to commencing the installation, meet at the Project site to review the material selections, installation procedures, and coordination with other trades. Mock-ups shall be reviewed during the pre-installation conference. Pre-installation conference shall include, but shall not be limited to, the Contractor, the Installer, manufacturer’s representatives, and any trade that requires coordination with the work. Date and time of the pre-installation conference shall be acceptable to the Owner and the Architect. 1.5 DELIVERY, STORAGE, AND HANDLING A. Deliver materials to the Project site in supplier’s or manufacturer’s original wrappings and containers, labeled with supplier’s or manufacturer’s name, material or product brand name, and lot number, if any. B. Store materials in their original, undamaged packages and containers, inside a well-ventilated area protected from weather, moisture, soiling, extreme temperatures, and humidity. C. Protect architectural woodwork during transit, delivery, storage, and handling to prevent damage, soilage, and deterioration. D. Do not deliver architectural woodwork until painting, wet-work, grinding, and similar operations which could damage, soil, or deteriorate architectural woodwork have been completed in installation areas. If architectural woodwork must be stored in other than installation areas, store only in areas meeting requirements specified in Project Conditions Article. 1.6 PROJECT CONDITIONS A. Environmental Limitations: Do not deliver or install architectural woodwork until building is enclosed, wet-work is completed and nominally dry, and HVAC system is operating and will maintain temperature and relative humidity at occupancy levels during the remainder of the construction period. B. Field Measurements: Take field measurements prior to fabrication of the work and preparation of shop drawings, to ensure proper fitting of the work. Show recorded measurements on final shop drawings. Notify the Owner and the Architect, in writing, of any dimensions found which are not within specified dimensions and tolerances in the Contract Documents, prior to proceeding with the fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the work. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 06400 - 5 ARCHITECTURAL WOODWORK PART 2 - PRODUCTS 2.1 A. 2.2 MANUFACTURERS Fabricator: Subject to compliance with requirements, provide architectural woodwork fabricated by one of the following firms: 1. Cabinets by Design, Inc. 2. Mill-Rite Woodworking Co., Inc. 3. Mortensen Woodwork, Inc. 4. On Site Woodwork Corp. 5. Signature Interior Woodwork Corp. MATERIALS A. Low-Emitting Materials: 1. Use adhesives, sealants, paints, coatings, etc., that comply with the specified limits for VOC content when calculated according to SCAQMD Rule #1168. See Section 01110 - LOWEMITTING MATERIALS for VOC content limits. 2. Do not use composite wood and agrifiber products that contain urea-formaldehyde resin. B. Materials: Provide materials that comply with requirements of the AWI quality standard for each type of architectural woodwork and quality grade indicated and, where the following products are part of the work, with requirements of the referenced product standards that apply to product characteristics indicated. 1. Medium Density Fiberboard: ANSI A208.2, Product Class MD-Exterior Glue, urea-formaldehyde-free in accordance with NPA 9. 2. Plywood: DOC PS 1. a. Environmental Standards: Provide urea-formaldehyde-free plywood to comply with HUD 24 CFR Part 3280 and ANSI/HPVA HP-1. 3. Hardwood Plywood and Face Veneers: ANSI/HPVA HP-1. C. High Pressure Decorative Laminate: NEMA LD 3, grades as indicated or, if not indicated, as required by architectural woodwork quality standard. 1. Manufacturer: Subject to compliance with requirements, provide products of one of the following: a. Formica Corp. b. Laminart, Inc. c. Nevamar Corp. d. Pionite Decorative Laminates Div., Panolam Industries, Inc. e. Wilsonart International, Inc. 2.3 A. FIRE RETARDANT-TREATED MATERIALS General: Where indicated, use materials impregnated with fire retardant chemical formulations indicated, by a pressure process or by other means acceptable to authorities having jurisdiction, to produce products with surface burning characteristics specified. 1. Fire Retardant Chemicals: Use chemical formulations that do not bleed through or otherwise affect finishes. Do not use colorants in solution to distinguish treated material from untreated material. 2. Formulation: Use interior Type A per AWPA C20. 3. Milling: Mill lumber before treatment and implement special procedures during treatment and drying processes that shall prevent lumber from warping and developing discolorations from drying sticks or other causes, marring, and other defects affecting appearance of treated architectural woodwork. SECTION 06400 - 6 ARCHITECTURAL WOODWORK 4. 5. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Drying: Kiln-dry material before and after treatment to levels required for untreated material. Defective Material: Discard treated material that does not comply with requirements of referenced woodworking standard. Do not use twisted, warped, bowed, discolored, or otherwise damaged or defective material. B. Fire Retardant-Treated Fiberboard: Provide medium density fiberboard panels complying with ANSI A208.2, made from softwood fibers, synthetic resins, and fire retardant chemicals mixed together at time of panel manufacture to achieve products identical to those tested for flame spread and smoke developed per ASTM E 84 by UL, Intertek Testing Services (ITS), or another inspecting and testing agency acceptable to authorities having jurisdiction. Identify products with appropriate markings of applicable inspecting and testing agency. C. Items to be Fire Retardant-Treated: Treat indicated items and the following: 1. Laminate-clad cabinets. 2. Laminate-clad countertops. 2.4 CABINET HARDWARE AND ACCESSORIES A. Cabinet Hardware: Provide cabinet hardware and accessory material associated with architectural woodwork cabinets. 1. Standard: Comply with ANSI/BHMA A156.9. 2. Finish for Exposed Hardware: Provide finish that complies with ANSI/BHMA A156.18 and as follows: a. Satin Stainless Steel, on Stainless Steel Base: BHMA 630. 3. Finish for Concealed Hardware: Provide manufacturer’s standard finish that complies with product class requirements of ANSI/BHMA A156.9. 4. Hardware: Provide the following in accordance with ANSI/BHMA A156.9: a. Semiconcealed Hinges: For overlay doors. Back mounted. B01523 b. Frameless Concealed Hinges: B01602, with 165 degree of opening capability. c. Back-Mounted Pulls: B02011. d. Adjustable Shelf Standards and Brackets: B04102 with B04112. e. Shelf Rests: B04081. f. Side-Mounted, Full Extension, Drawer Slides: B05091. g. Door Locks: E07121. h. Drawer Locks: E07041. B. Glass for Doors: 1. Tempered: ASTM C 1048, Kind FT (fully tempered), Condition A (uncoated surfaces), Type I (transparent glass, flat), Class 1 (clear), Quality q3 (glazing select), manufactured by horizontal (roller hearth) process, with exposed edges seamed before tempering, 1/4 inch thick unless otherwise indicated. a. Thickness: 1/8 inch thick unless otherwise indicated. C. Grommets for Cable Passage through Countertops: 2 inch outside diameter, black, molded plastic grommets and matching plastic caps with slot for wire passage. 1. Basis of Design: Product specified is “OG Series” as manufactured by Doug Mockett & Co., Inc. Items specified are to establish a standard of quality for design, function, materials, and appearance. Equivalent products by other manufacturers are acceptable. The Architect will be the sole judge of the basis of what is equivalent. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 2.5 SECTION 06400 - 7 ARCHITECTURAL WOODWORK INSTALLATION MATERIALS A. Furring, Blocking, Shims, Hanging Strips, Etc.: Provide fire retardant-treated softwood lumber, kiln-dried to less than 15 percent moisture content. B. Screws: Select material, type, size, and finish required for each use. Comply with ANSI/ASME B18.6.1 for applicable requirements. 1. For metal framing supports, provide screws as recommended by metal framing manufacturer. C. Nails: Select material, type, size, and finish required for each use. Comply with ASTM F 1667 for applicable requirements. D. Anchors: Select material, type, size, and finish required for each substrate for secure anchorage. Provide non-ferrous metal or hot-dip galvanized anchors and inserts on inside face of exterior walls and elsewhere as required for corrosion resistance. 2.6 FABRICATION, GENERAL A. Comply with requirements of referenced quality standard for wood moisture content in relation to relative humidity conditions existing during time of fabrication and in installation area. B. Sand fire retardant-treated wood lightly to remove raised grain on exposed surfaces before fabrication. C. Fabricate architectural woodwork to dimensions, profiles, and details indicated. Complete fabrication, including, but not limited to, assembly, finishing, and hardware application, before shipment to the Project site to maximum extent possible. Disassemble components only as necessary for shipment and installation. Where necessary for fitting at site, provide ample allowance for scribing, trimming, and fitting. D. Shop cut openings, to maximum extent possible, to receive hardware, appliances, plumbing fixtures, electrical work, and similar items. Locate openings accurately and use templates or roughing-in diagrams to produce accurately sized and shaped openings. Smooth edges of cutouts and, where located in countertops and similar exposures, seal edges with a water-resistant coating. E. Install glass to comply with applicable requirements of Section 08800 - GLAZING and GANA GM. For glass in wood frames, secure glass with removable stops. 2.7 LAMINATE-CLAD CABINETS A. Quality Standard: Comply with AWI AWQSI, Section 400 requirements for laminate-clad cabinets. B. Grade: Provide custom grade. C. Type of Cabinet Construction: Provide flush overlay type. D. Laminate Cladding for Exposed Surfaces: 1. Horizontal Surface Other Than Tops: HGS, 0.048 inch nominal thickness. 2. Post-Formed Surfaces: HGP, 0.039 inch nominal thickness. 3. Vertical Surfaces: HGS, 0.048 inch nominal thickness. 4. Edges: VGS, 0.028 inch nominal thickness. SECTION 06400 - 8 ARCHITECTURAL WOODWORK REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 E. Semi-Exposed Surfaces: 1. Surfaces Other Than Drawer Bodies: High pressure decorative laminate, VGS, 0.028 inch nominal thickness. 2. Drawer Sides and Backs: Solid hardwood lumber, shop-finished. 3. Drawer Bottoms: Hardwood plywood. F. Dust Panels: Provide dust panels of 1/4 inch plywood or tempered hardboard above compartments and drawers except where located directly under countertops. G. Colors, Patterns, and Finishes: Provide materials and products that result in colors and textures of exposed laminate surfaces complying with the following requirements: 1. Provide the Architect’s selections from laminate manufacturer’s full range of colors and finishes. 2.8 COUNTERTOPS A. Quality Standard: Comply with AWI AWQSI, Section 400 requirements for countertops. B. Grade: Provide custom grade. C. Plastic Laminate Countertop: Provide high pressure plastic laminate. 1. Grade: HGS, 0.048 inch nominal thickness. 2. Colors, Patterns, and Finishes: Provide the Architect’s selections from laminate manufacturer’s full range of colors and finishes. 3. Edge Treatment: Same as laminate cladding on horizontal surfaces. 4. Core Material at dry locations: Medium density fiberboard. 5. Core Material at wet locations: Exterior grade plywood. PART 3 - EXECUTION 3.1 A. 3.2 EXAMINATION Verification of Conditions: Examine areas and conditions under which the work is to be installed, and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected. 1. Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by the Installer. PREPARATION A. Condition architectural woodwork to average prevailing humidity conditions in installation areas before installing. B. Before installing architectural woodwork, examine shop-fabricated work for completion and complete work as required, including, but not limited to, backpriming and removal of packing. 3.3 A. INSTALLATION Quality Standard: Install architectural woodwork to comply with AWI AWQSI, Section 1700 for the same grades specified in Part 2 - PRODUCTS of this Section for type of architectural woodwork involved. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 06400 - 9 ARCHITECTURAL WOODWORK B. Installation Tolerances: Install architectural woodwork plumb, level, true, and straight with no distortions. Shim as required with concealed shims. 1. Variation From Plumb and Level: ±1/8 inch in any 96 inch dimension. 2. Offset In Flush Adjoining Surfaces: ±1/16 inch maximum. 3. Offset In Revealed Adjoining Surfaces: ±1/8 inch maximum. C. Fitting: Scribe and cut architectural woodwork to fit adjoining work and refinish cut surfaces or repair damaged finish at cuts. D. Fire Retardant-Treated Wood: Handle, store, and install fire retardant-treated wood to comply with recommendations of chemical treatment manufacturer, including, but not limited to, those for adhesives used to install architectural woodwork. E. Fasteners: Anchor architectural woodwork to anchors or blocking built-in or directly attached to substrates. Secure to grounds, stripping, and blocking with countersunk, concealed fasteners and blind nailing as required for a complete installation. Use fine finishing nails for exposed nailing, countersunk and filled flush with architectural woodwork and matching final finish where transparent finish is indicated. F. Cabinets: Install without distortion so that doors and drawers fit openings properly and are accurately aligned. Adjust hardware to center doors and drawers in openings and to provide unencumbered operation. Complete the installation of hardware and accessory items as indicated. Install cabinets with no more than 1/8 inch in 96 inches for sag, bow, or other variation from a straight line. 1. Fasten wall cabinets through back, near top and bottom, at ends and not more than 16 inches on center. G. Countertops: Anchor securely to base units and other support systems as indicated. Caulk space between backsplash and wall with specified sealant. Install countertops with no more than 1/8 inch in 96 inches for sag, bow, or other variation from a straight line. H. Paneling: Anchor paneling to supporting substrate with concealed panel hanger clips and by blind nailing on back-up strips, splined connection strips, or similar associated trim and framing. Do not face nail unless otherwise indicated. Install paneling flush with no more than 1/16 inch in 96 inches vertical cup and bow and 1/8 inch in 96 inches horizontal variation from a true plane. I. Finishing: Complete the finishing work specified in this Section to the extent not completed at the shop or before installation of the architectural woodwork. Fill nail holes with matching filler where exposed. Apply specified finish coats, including, but not limited to, stains and paste fillers (if any), to exposed surfaces where only seal or prime coats were applied in the shop. 1. See Section 09900 - PAINTING for final finishing of installed architectural woodwork that is not the work of this Section. 3.4 ADJUSTING AND CLEANING A. Repair damaged and defective architectural woodwork where possible to eliminate functional and visual defects. Where not possible to repair, replace architectural woodwork. Adjust joinery for visual appearance. B. Clean, lubricate, and adjust hardware. C. Clean architectural woodwork on exposed and semi-exposed surfaces. Touch-up shop-applied finishes to restore damaged or soiled areas. SECTION 06400 - 10 ARCHITECTURAL WOODWORK 3.5 A. REVISED MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 PROTECTION Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall ensure that the architectural woodwork shall be without damage at time of Substantial Completion. END OF SECTION MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 07415 - 1 METAL CLADDING SYSTEMS SECTION 07415 METAL CLADDING SYSTEMS PART 1 - GENERAL 1.1 A. 1.2 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General Conditions, Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project Manual apply to the work specified in this Section. SUMMARY A. Alternate Scope: In lieu of COMPOSITE PANELS as defined in Section 074320, provide design and engineering, labor, material, equipment, related services, and supervision required, including, but not limited to, manufacturing, fabrication, erection, and installation for metal cladding systems as required for the complete performance of the work, and as shown on the Drawings and as herein specified. Refer to Section 01101 ALTERNATES. B. Section Includes: The work specified in this Section includes, but shall not be limited to, metal cladding systems, including, but not limited to, trim, terminations, flashings, miscellaneous steel and sub-girts, clip angles, fasteners, and other devices for secure anchorage of panels to structural steel frame members or other substrate provided for this purpose. 1.3 REFERENCES A. The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by the basic designation only. B. The edition/revision of the referenced publications shall be the latest date as of the date of the Contract Documents, unless otherwise specified. C. American Architectural Manufacturers Association (AAMA): 1. AAMA 2605, "Voluntary Specification, Performance Requirements, and Test Procedures for Superior Performing Organic Coatings on Aluminum Extrusions and Panels." D. American Institute of Steel Construction, Inc. (AISC): 1. AISC 303, "Code of Standard Practice for Steel Buildings and Bridges." 2. AISC MSC, "Manual of Steel Construction ASD.” E. ASTM (ASTM): 1. ASTM B 209, "Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate.” 2. ASTM B 221, "Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Shapes, and Tubes.” 3. ASTM E 119, "Standard Test Methods for Fire Tests of Building Construction and Materials.” 4. ASTM E 329, "Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction." F. Green Seal (GS): 1. GS-37, “Industrial & Institutional Cleaners.” SECTION 07415 - 2 METAL CLADDING SYSTEMS MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 G. National Association of Architectural Metal Manufacturers (NAAMM): 1. NAAMM MFM, "Metal Finishes Manual.” H. Sheet Metal and Air Conditioning Contractors' National Association (SMACNA): 1. SMACNA ASMM, "Architectural Sheet Metal Manual." I. SSPC: The Society for Protective Coatings (SSPC): 1. SSPC Paint 12, "Paint Specification No. 12 Cold-Applied Asphalt Mastic (Extra Thick Film).” J. Underwriters Laboratories, Inc. (UL): 1. UL FRD, "Fire Resistance Directory.” 1.4 A. 1.5 A. DEFINITION Metal Cladding System Assembly: Metal plate wall panels, attachment system components, miscellaneous metal framing, and accessories necessary for a complete weathertight wall system. SYSTEM DESCRIPTION Design Requirements: 1. General: Provide the manufacturer's metal cladding system, adapted to the application indicated, and modified as required to comply with performance requirements and materials specified, as demonstrated by testing the manufacturer's corresponding systems according to test methods indicated. Where modifications to the manufacturer's tested metal cladding system are required for compliance with performance, or materials specified, and such modifications invalidate laboratory testing as determined by the Architect, test in accordance with Section 08900 - EXTERIOR WALL PERFORMANCE REQUIREMENTS, with no increase in the Contract Sum. In addition to the requirements specified herein comply with additional provisions specified in Section 08900 - EXTERIOR WALL PERFORMANCE REQUIREMENTS. a. The metal cladding system, including, but not limited to, stiffeners and sealants, shall meet the specified requirements for wind loading, air infiltration, and water penetration. b. The anchorage system shall be designed so that the panels are secure yet free-floating to accommodate expansion and contraction, and that individual panels may be installed or removed without disturbing adjacent panels. c. The panel system shall have an internal drainage system to catch condensation within the wall and direct it to designated weepage points. d. Panels shall be finished after fabrication to ensure integrity of applied finish. 2. Structural Design Limitations: a. Normal-to-wall deflection shall not exceed 1/240 of clear span or 1/4 inch, whichever is less at full design load for each panel. b. Metal copings shall be designed to resist a 250 pound live load per 5 foot section without permanent distortion, or disengagement of anchors or seals. c. Thermal movement within the system shall not result in oil canning or similar irregularities. 3. Structural Basis for Design: a. Base calculations for such deflections upon the combination of maximum direct loadings, building deflections, thermal stresses, and erection tolerances. Do not permit any permanent deflections of members in the metal cladding work in excess of 0.1 percent of their clear span. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 4. 5. 6. 7. B. 1.6 SECTION 07415 - 3 METAL CLADDING SYSTEMS b. Design, fabricate, and install structural components of the metal cladding system with a factor of safety not less than 1.5 (basis for design calculations shall be 1.5 times the maximum design wind pressure), such that failure of any structural component shall not occur at less than 1.5 times the maximum design wind pressures as indicated on the Drawings or, if not indicated, as required by local authorities having jurisdiction. Failure is defined as breakage, component disengagement, or permanent distortion. Sealant Joint Design: Joints within system shall be designed to incorporate sealant and bond breaker in such a way to reduce or eliminate shear forces on sealant. Seals or joint fillers shall not be interrupted by anchors, shims, or similar components. Coordinate with design of anchorage. Weeps: Protect weeps with reticulated foam baffles of appropriate PPI (pores per inch). Thermal Movements: Allow for thermal movement resulting from the following maximum change (range) in ambient and surface temperatures in engineering, fabricating, and installing metal cladding systems. Base engineering calculation on actual surface temperatures of materials due to both solar heat gain and nighttime sky heat loss. a. Temperature Change (Range): 120 °F ambient, 180 °F material surfaces. Copings: Metal copings shall be designed to resist a point load of 250 pounds without permanent deformation or disengagement of anchors or seals. Performance Requirements: See Section 08900 - EXTERIOR WALL PERFORMANCE REQUIREMENTS. SUBMITTALS A. General: See Section 01300 - SUBMITTALS. B. Product Data: Submit product data including, but not limited to, manufacturer's product specifications, installation instructions, recommendations for maintenance, and general recommendations, as applicable to materials and finishes for each component and for total cladding system. 1. Include complete test reports for consideration by the Architect where acceptance to waive testing as delineated in Section 08900 - EXTERIOR WALL PERFORMANCE REQUIREMENTS is to be proposed. 2. Include type of sealant to be used and application instructions. C. Shop Drawings: Submit shop drawings showing adaptation of manufacturer's metal cladding system, including, but not limited to, layouts of panels on roofs and walls, details of edge conditions, joints, corners, supports, anchors, trim, flashings, closures, and special details for all Project conditions. Shop drawings shall also include, but shall not be limited to, metal thickness, finish methods of installation, and joints necessary to accommodate thermal movement. Include plans and elevations at a scale of 1/2 inch equals 1 foot minimum and details at full-size. Incorporate material lists. 1. Materials List: Submit a list of selected manufacturers, product names, product model numbers, and other information furnished by the Contractor to document the sources and general properties of materials and equipment used in the work. Incorporate into shop drawing submittal. D. Samples: 1. Submit samples for initial color selection. Submit samples of each specified finish. Submit samples in form of manufacturer’s color charts showing full range of colors and finishes available. Where finishes involve normal color variations, include samples showing the full, range of variations expected. SECTION 07415 - 4 METAL CLADDING SYSTEMS 2. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Submit samples for verification purposes. Submit samples of metal cladding panels. Provide sample panels 24 inches square, in the color and finish indicated. Include clips, fasteners, closures, and other panel accessories. The Architect reserves the right to require fabrication samples showing the following: a. Prime members. b. Joinery. c. Anchorage. d. Expansion provisions. e. Profiles. f. Intersections. E. Quality Control Submittals: 1. Design Data: Submit structural design calculations for the metal cladding system and the connections for attaching it to the structure. Show that maximum stresses and deflections do not exceed specified performance requirements under full design loading. The design data shall be signed and sealed by the professional engineer. Only the loadings on the structure at the connections will be reviewed. 2. Qualification Data: Submit qualification data for firms and persons specified in Quality Assurance Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names of architects and owners, and other information specified. 3. Test Reports: Submit a report of inspections of connections and welds. 4. Certificates: a. Submit Installer certificates signed by the manufacturer certifying that the Installer of the metal cladding system complies with requirements indicated, including, but not limited to, structural performance, flame and smoke contribution, and air and water infiltration. b. Submit designer certificates, signed and sealed by the structural engineer licensed to practice in the State where the Project is located that he has visited the site and that to the best of his information, knowledge, and belief the metal cladding system has been installed in accordance with his design. F. Maintenance Data: Furnish complete maintenance manuals describing the materials, devices, and procedures to be followed in cleaning and maintaining the work. Include manufacturer's brochures and parts lists describing the actual materials used in the work, including, but not limited to, metal alloys, finishes, sealants, and other major components. Assemble manuals for component parts into single binders. 1.7 A. QUALITY ASSURANCE Qualifications: 1. Manufacturer Qualifications: Manufacturer shall be a firm engaged in the manufacture of metal cladding systems of types and sizes required, and whose products have been in satisfactory use in similar service for a minimum of five years. 2. Installer Qualifications: Installer shall be a firm that shall have a minimum of five years of successful installation experience with projects utilizing metal cladding systems similar in type and scope to that required for this Project, and shall be approved by the manufacturer. 3. Engineer Qualifications: The engineer shall be a professional engineer legally authorized to practice in the jurisdiction where the Project is located and experienced in providing engineering services of the kind indicated that have resulted in the installation of products similar to this Project in material, design, and extent, and that have a record of successful in-service performance. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 4. 5. SECTION 07415 - 5 METAL CLADDING SYSTEMS Inspecting and Testing Agency Qualifications: To qualify for acceptance, an independent inspecting and testing agency hired by the Contractor or manufacturer to test products shall demonstrate to the Architect’s satisfaction that they are qualified according to ASTM E 329 to conduct testing indicated. Welder's Qualifications: Qualify welding processes and welding operators in accordance with American Welding Society (AWS) standard qualification procedure. Operators shall carry proof of qualification on their persons. B. Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances, and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary approvals from such authorities. C. Mock-Ups: Prior to installation of the work, fabricate and erect mock-ups for each type of finish and application required to verify selections made under sample submittals and to demonstrate aesthetic effects as well as qualities of materials and execution. Build mock-ups to comply with the following requirements, using materials indicated for final unit of work. 1. Locate mock-ups on site in location and of size indicated or, if not indicated, as directed by the Architect. 2. Demonstrate the proposed range of aesthetic effects and workmanship to be expected in the completed work. 3. Obtain the Architect’s acceptance of mock-ups before start of final unit of work. 4. Retain and maintain mock-ups during construction in undisturbed condition as a standard for judging completed unit of work. a. Accepted mock-ups in undisturbed condition at time of Substantial Completion may become part of completed unit of work. D. Pre-Installation Conference: Conduct pre-installation conference in accordance with Section 01200 - PROJECT MEETINGS. Prior to commencing the installation, meet at the Project site to review the material selections, installation procedures, and coordination with other trades. Mock-ups shall be reviewed during the pre-installation conference. Pre-installation conference shall include, but shall not be limited to, the Contractor, the Installer, manufacturer’s representatives, and any trade that requires coordination with the work. Date and time of the pre-installation conference shall be acceptable to the Owner and the Architect. E. Single Source Responsibility: Obtain metal cladding systems from a single source with resources to produce products of consistent quality in appearance and physical properties without delaying the work. F. Coordination: Coordinate metal cladding systems with rain drainage work, flashing, trim, and construction of walls and other adjoining work to provide a leakproof, secure, and non-corrosive installation. 1.8 DELIVERY, STORAGE, AND HANDLING A. Deliver panels and other components so they shall not be damaged or deformed. Package panels for protection against transportation damage. B. Exercise care in unloading, storing, and erecting panels to prevent bending, warping, twisting, and surface damage. C. Stack materials off the ground with a suitable weathertight ventilated covering. Store panels so that they shall not accumulate water. Do not store panels in contact with other materials that might cause staining, denting, or other surface damage. SECTION 07415 - 6 METAL CLADDING SYSTEMS 1.9 MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 PROJECT CONDITIONS A. Weather Limitations: Proceed with installation only when existing and forecasted weather conditions permit metal cladding system work to be performed according to manufacturer's written instructions and warranty requirements. B. Field Measurements: Take field measurements before fabrication. Show recorded measurements on final shop drawings. Notify the Architect and the Contractor in writing of any dimensions found which are not within specified dimensions and tolerances in the Contract Documents prior to proceeding with fabrication. Coordinate fabrication schedule with construction progress to avoid delay. Field trimming of panel units shall not be permitted. 1.10 WARRANTY A. General: See Section 01770 - CLOSEOUT PROCEDURES. B. Special Warranty: 1. The Contractor shall warrant the work of this Section to be in accordance with the Contract Documents and free from faults and defects in materials and workmanship for a period of five years. This special warranty shall extend the one year period of limitations contained in the General Conditions. The special warranty shall be countersigned by the Installer and the manufacturer. Defective is defined to include, but shall not be limited to, the following: a. Early deterioration, aging, or discoloration of finishes, gaskets, or other components. b. Uncontrolled penetration of air or water. c. Failure of the system to meet performance requirements. 2. This warranty shall specifically include the work of the following additional sections of the Specifications. Upon notification of defects, within the warranty period, make necessary repairs or replacement at the convenience of the Owner. a. Section 07900 - JOINT SEALERS. C. Special PVDF Finish Warranty: Submit a written warranty, signed by manufacturer, covering failure of the factory-applied exterior finish within the specified warranty period and agreeing to repair finish or replace work that shows evidence of finish deterioration. Deterioration of finish includes, but shall not be limited to, color fade, chalking, cracking, peeling, and loss of film integrity. 1. Warranty Period: Warranty period shall be 20 years from date of Substantial Completion. D. Additional Owner Rights: The warranty shall not deprive the Owner of other rights the Owner may have under other provisions of the Contract Documents and shall be in addition to and run concurrent with other warranties made by the Contractor under requirements of the Contract Documents. PART 2 - PRODUCTS 2.1 A. MANUFACTURERS Manufacturer: Subject to compliance with requirements, provide products of one of the following: 1. Alply, Inc. 2. Architectural Specialty Products, Inc. 3. Firestone Metal Products. 4. Industrial Building Panels, Inc. 5. Protean Construction Products, Inc. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 B. 2.2 SECTION 07415 - 7 METAL CLADDING SYSTEMS Basis of Design: Product specified is "UNA-CLAD 3000" as manufactured by Firestone Metal Products. Items specified are to establish a standard of quality for design, function, materials, and appearance. Equivalent products by listed manufacturers are acceptable. The Architect will be the sole judge of the basis of what is equivalent. MATERIALS A. Sheet and Extruded Materials: 1. Aluminum Panels: Panels shall be custom-fabricated from minimum 0.120 inch thick aluminum solid plate of 3003-H134 or 5005-H32AQ alloy, in accordance with the Drawings and manufacturer's requirements, including, but not limited to, verified field dimensions, complying with ASTM B 209. 2. Extruded Aluminum Bars and Shapes: Extruded aluminum support members shall be a minimum 0.093 inch thick 6063-T52 alloy, complying with ASTM B 221; supplied pre-cut to size. B. Concealed Flashing: Provide dead-soft 26 gage stainless steel concealed flashing of type selected for compatibility by the manufacturer. C. Panel Accessories: Except as indicated as work of another Specification section, provide components required for a complete metal cladding system. Match materials and prefinish to match panels. D. Bituminous Coating: Provide cold-applied asphalt mastic, SSPC Paint 12, compounded for 15 mil dry film thickness per coat. E. Fasteners: Provide bolts, self-drilling screws, and other fastening devices, as recommended by the panel manufacturer for conditions of each application. Provide Type 305 stainless steel. Where exposed, finish to match adjacent surfaces. F. Sealants: See Section 07900 - JOINT SEALERS. 2.3 FABRICATION A. Fabricate and finish metal cladding systems and accessories at the factory to greatest extent possible, by manufacturer's standard procedures and processes, as necessary to fulfill indicated performance requirements demonstrated by laboratory testing. Comply with indicated profiles and with dimensional and structural requirements. B. Fabricate metal cladding systems in a manner that eliminates condensation on interior side of panel and with joints between panels designed to form weathertight seals. C. Fabricate panels with panel stiffeners as required to comply with deflection limits. Weld and grind panel corners smooth. Fabricate panels to the following dimensional tolerances: 1. Length and Width: ±0.032 inch up to 48 inches, ±0.064 inch from 48 inches to 144 inches. 2. Diagonal: ±0.1875 inch. 3. Panel Bow: Not more than 0.2 percent of panel length or width up to 0.1875 inch maximum. 4. Thickness: ±0.008 inch. 5. Squareness: 0.1875 inch difference between diagonal measurements. 6. Camber: 0.032 inch. D. Fabricate flashing and trim to comply with recommendations in SMACNA ASMM that apply to the design, dimensions, metal, and other characteristics of item indicated. SECTION 07415 - 8 METAL CLADDING SYSTEMS 1. 2. 3. 4. 5. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Form exposed sheet metal accessories that are without excessive oil-canning, buckling, and tool marks and that are true to line and levels indicated, with exposed edges folded back to form hems. Fabricate non-moving seams in accessories with flat-lock seams. Form seams and seal with epoxy seam sealer. Rivet joints for additional strength. Form non-expansion but movable joints in metal to accommodate elastomeric sealant to comply with SMACNA standards. Conceal fasteners and expansion provisions where possible. Exposed fasteners are not allowed on faces of accessories exposed to view. Fabricate cleats and attachment devices from same material as accessory being anchored or from compatible, non-corrosive metal recommended by metal panel manufacturer. Size shall be as recommended by SMACNA ASMM or metal panel manufacturer for application but not less than thickness of metal being secured. E. Panels shall be formed to specified dimensions with tolerances to accommodate expansion and contraction between panels and structural members. Curved panels shall be accurately formed to radii in plant of manufacturer. F. Panel corners shall be welded and ground smooth prior to finishing. G. Accessory and trim components shall be factory-fabricated and ready for installation. H. Fabricate and finish panels and accessories at the factory, by processes, as required to fulfill indicated performance requirements demonstrated by laboratory testing. Comply with dimensional requirements and with structural requirements. I. Apply bituminous coating or other permanent separation materials on concealed panel surfaces where panels would otherwise be in direct contact with substrate materials that are non-compatible or could result in corrosion or deterioration of either material or finishes. J. Use electrodes and methods recommended by manufacturer of material being welded, and in accordance with applicable AWS standards. Use only methods which prevent distortion and discoloration of exposed faces. Grind weld areas smooth, using only clean equipment and materials free of iron or iron compounds. Restore finish of component parts after welding and grinding. K. Provide temporary coating and coverings to protect the work during shipment and construction. Such protection shall avoid development of non-uniformity in finishes, shall not impart a residue which would adversely affect the adhesion of sealants, nor cause other deleterious effects in the work. Temporarily remove such protection when requested by the Architect for review of finishes, and completely remove protection when no longer required. 2.4 A. FINISHES General: Comply with NAAMM MFM for recommendations relative to application and designations of finishes. 1. Finish designations prefixed by "AA" conform to the system established by the Aluminum Association for designating aluminum finishes. 2. Remove die markings, scratches, abrasions, dents, and other blemishes before applying finish. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 B. SECTION 07415 - 9 METAL CLADDING SYSTEMS High Performance Organic Coating: AA-C12-C42-R1x (Chemical Finish: cleaned with inhibited chemicals; Chemical Finish: chemical conversion coating, acid chromate-fluoride-phosphate pretreatment; Organic Coating: as specified below). Prepare, pretreat, and apply coating to exposed metal surfaces to comply with coating and resin manufacturer's instructions. 1. Standard Two-Coat Polyvinylidene Fluoride (PVDF) Finish Coating: Manufacturer's standard thermocured system, complying with AAMA 2605, composed of specially formulated inhibitive primer and fluoropolymer color topcoat containing not less than 70 percent PVDF resin by weight, as produced by Arkema, Inc. ("Kynar 500") or by Solvay Solexis, Inc. ("Hylar 5000"). Provide minimum 1.2 mil total dry film thickness. a. Color and Gloss: Match the Architect's sample. (Intended to match Accent Brick color, Basis of Design "Whitestone" by Palmetto Brick.) b. PVDF Touch-Up Finish: PVDF finish coating, containing fluoropolymer resin and formulated for air-drying at ambient temperature. Provide for field touch-up and furnish in color to match shop-applied finishes. PART 3 - EXECUTION 3.1 A. 3.2 EXAMINATION Verification of Conditions: Examine areas and conditions under which the work is to be installed, and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected. 1. Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by the Installer. INSTALLATION A. Panel Supports and Anchors: Girts, purlin, and other secondary structural panel support members and anchorage shall be installed in accordance with AISC MSC and AISC 303, ASTM C 754, and metal panel manufacturer's written recommendations. B. Panel Installation: Comply with manufacturer's published instructions and recommendations for installation, as applicable to Project conditions and supporting substrates. Anchor panels and other components of the work securely in place, with provisions for thermal and structural movement. 1. Field cutting of panels is not permitted. 2. Install panels with concealed fasteners, unless shown otherwise. 3. Anchor components securely in place. Shim and allow for movement resulting from changes in thermal conditions. Provide separators and isolators to prevent corrosion, electrolytic deterioration, and freeze-up of moving joints. 4. Install the work level, plumb, and true-to-line, with uniform joints. 5. Cut and trim component parts during installation only with the approval of the manufacturer and in accordance with his recommendations. Restore finishes completely to protect the material and remove evidence of cutting or trimming. Remove and replace members where cutting and trimming has impaired strength or appearance. Do not cut through reinforcing members. 6. Use electrodes and methods recommended by manufacturer of material being welded, and in accordance with applicable AWS standards. Use only methods which prevent distortion and discoloration of exposed faces. Grind exposed welds smooth, using only clean equipment and materials free of iron or iron compounds. Restore finish of component parts after welding and grinding. SECTION 07415 - 10 METAL CLADDING SYSTEMS 7. 8. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Paint the contact surfaces of dissimilar materials, including, but not limited to, metal in contact with masonry or concrete work, with a heavy coating of epoxy paint, or provide other separation as recommended by the manufacturer. Paint steel clip angles, and other ferrous metal parts which shall be concealed, using epoxy paint. Do not erect members which are warped, bowed, deformed, or otherwise damaged or defaced to such extent as to impair strength or appearance. Remove and replace members which have been damaged. C. Accessories: Install components required for a complete watertight and airtight metal panel system. D. Joint Sealers: Install joint fillers and sealants where indicated and where required for weatherproof performance of panel systems. Provide types of sealants and fillers indicated or, if not otherwise indicated, types recommended by panel manufacturer. E. Installation Tolerances: Shim and align panel units within installed tolerance of 1/4 inch in 20 feet non-cumulative on level/plumb/slope and location/line as indicated, and within 1/16 inch offset of adjoining faces and of alignment of matching profiles. 3.3 FIELD QUALITY CONTROL A. General: See Section 01410 - INSPECTING AND TESTING SERVICES. B. Testing: Hose test in accordance with Section 08900 - EXTERIOR WALL PERFORMANCE REQUIREMENTS. C. Inspection: Inspecting and testing agency shall inspect and report on all connections and welds. 3.4 ADJUSTING AND CLEANING A. Damaged Units: Replace panels and other components of the work that have been damaged or have deteriorated beyond successful repair by means of finish touch-up or similar minor repair procedures. B. Cleaning: Remove temporary protective coverings and strippable films (if any) as soon as each panel is installed. Upon completion of panel installation, clean finished surfaces as recommended by panel manufacturer, and maintain in a clean condition during construction. 1. No cleaning products or processes shall exceed listed VOC limits or use ozone-depleting substances. Cleaning materials shall comply with GS-37. 3.5 A. 3.6 A. DEMONSTRATION Maintenance Instruction: Instruct the Owner's personnel who will be responsible for maintenance after the time of final acceptance. Demonstrate and train the Owner's personnel, for a period not less than two working days, in the proper methods of cleaning and maintaining the entire metal cladding system. PROTECTION Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall ensure that the metal cladding systems shall be without damage at time of Substantial Completion. END OF SECTION MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 07420 - 1 COMPOSITE PANELS SECTION 07420 COMPOSITE PANELS PART 1 - GENERAL 1.1 A. 1.2 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General Conditions, Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project Manual apply to the work specified in this Section. SUMMARY A. Base Design Scope: Provide labor, material, equipment, related services, and supervision required, including, but not limited to, manufacturing, fabrication, erection, and installation for composite panels as required for the complete performance of the work, and as shown on the Drawings and as herein specified. B. Alternate Scope: Provide METAL CLADDING SYSTEM as defined in Section 07515 in lieu of COMPOSITE PANELS. Refer to Section 01101 - ALTERNATES. C. Section Includes: The work specified in this Section includes, but shall not be limited to, composite panel system requirements, including, but not limited to, the following components: 1. Aluminum-faced composite metal panels with mounting system. 2. Panel mounting system, including, but not limited to, anchors, shims, furring, fasteners, gaskets and sealants, related flashing adapters, and masking (as required) for a complete watertight installation. 3. Parapet coping, column covers, soffits, sills, border, and filler items indicated as integral components of the composite panel system or as designed. 4. Interior composite panel system work that matches exterior system. 1.3 REFERENCES A. The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by the basic designation only. B. The edition/revision of the referenced publications shall be the latest date as of the date of the Contract Documents, unless otherwise specified. C. American Architectural Manufacturers Association (AAMA): 1. AAMA/WDMA 101/I.S. 2, "Voluntary Specifications for Aluminum, Vinyl (PVC), and Wood Windows and Glass Doors." 2. AAMA 611, "Voluntary Specifications for Anodized Architectural Aluminum (Revised).” 3. AAMA 2605, "Voluntary Specification, Performance Requirements, and Test Procedures for Superior Performing Organic Coatings on Aluminum Extrusions and Panels." 4. AAMA MCWM-1, "Metal Curtain Wall Manual." 5. AAMA SFM-1, "Aluminum Storefront and Entrance Manual." SECTION 07420 - 2 COMPOSITE PANELS MARCH 16, 2011 PROJECT NAME - XXXXX KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 D. ASTM (ASTM): 1. ASTM A 641, "Standard Specification for Zinc-Coated (Galvanized) Carbon Steel Wire." 2. ASTM A 653, "Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process.” 3. ASTM B 209, "Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate." 4. ASTM C 297, "Standard Test Method for Tensile Strength of Flat Sandwich Constructions in Flatwise Plane." 5. ASTM C 645, "Standard Specification for Non-Load (Axial) Bearing Steel Studs, Runners (Track), and Rigid Furring Channels for Screw Application of Gypsum Board." 6. ASTM C 754, "Standard Specification for Installation of Steel Framing Members to Receive Screw-Attached Gypsum." 7. ASTM D 1781, "Standard Test Method for Climbing Drum Peel for Adhesives.” 8. ASTM E 84, "Standard Test Method for Surface Burning Characteristics of Building Materials." 9. ASTM E 119, "Standard Test Methods for Fire Tests of Building Construction and Materials.” 10. ASTM E 162, "Standard Test Method for Surface Flammability of Materials Using a Radiant Heat Energy Source." 11. ASTM E 283, "Standard Test Method for Determining the Rate of Air Leakage Through Exterior Windows, Curtain Walls, and Doors Under Specified Pressure Difference Across the Specimen." 12. ASTM E 329, "Standard Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction." 13. ASTM E 330, "Standard Test Method for Structural Performance of Exterior Windows, Curtain Walls, and Doors by Uniform Static Air Pressure Difference." 14. ASTM E 331, "Standard Test Method for Water Penetration of Exterior Windows, Curtain Walls, and Doors by Uniform Static Air Pressure Difference." E. International Conference of Building Officials (ICBO): 1. ICBO UBC No. 17-5, “Room Fire Test Standard for Interior of Foam Plastic Systems.” F. National Association of Architectural Metal Manufacturers (NAAMM): 1. NAAMM MFM, "Metal Finishes Manual." G. Sheet Metal and Air Conditioning Contractors' National Association (SMACNA): 1. SMACNA ASMM, "Architectural Sheet Metal Manual." H. Underwriters Laboratories, Inc. (UL): 1. UL FRD, "Fire Resistance Directory.” 1.4 A. 1.5 A. DEFINITION Composite Panel System Assembly: Metal-faced composite wall panels, attachment system components, miscellaneous metal framing, and accessories necessary for a complete weathertight wall system. SYSTEM DESCRIPTION Design Requirements: 1. Deflection and Thermal Movement: Provide systems that have been tested and certified in accordance with ASTM E 330 to conform to the following criteria under wind loading as indicated on the drawings: a. Normal Deflection: 1) Normal to the plane of the wall between supports, deflection of the secured perimeter framing members shall not exceed L/175 or 3/4 inch, whichever is less. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 07420 - 3 COMPOSITE PANELS 2) Normal to the plane of the wall, the maximum panel deflection shall not exceed L/60 of the full span. 3) At 1-1/2 times design pressure, permanent deflections of framing members shall not exceed L/100 of span length and components shall not experience failure or gross permanent distortion. 4) At connection points of framing members to anchors, permanent set shall not exceed 1/16 inch. b. Anchor Deflection: At connection points of framing members to anchors, anchor deflection in any direction shall not exceed 1/16 inch. c. Thermal Movements: Allow for thermal movement resulting from the following maximum change (range) in ambient and surface temperatures in engineering, fabricating, and installing composite panel systems. Base engineering calculation on actual surface temperatures of materials due to both solar heat gain and nighttime sky heat loss. 1) Temperature Change (Range): 120 °F ambient, 180 °F material surfaces. B. Performance Requirements: See Section 08900 - EXTERIOR WALL PERFORMANCE REQUIREMENTS. C. Performance Requirements: 1. Air Infiltration: Provide composite panel assemblies with permanent resistance to air leakage through assembly of not more than 0.060 cfm per square foot of fixed wall area when tested according to ASTM E 283 at a static air pressure difference of 6.24 psf. 2. Water Penetration: Provide composite panel assemblies with no water penetration as defined in the test method when tested according to ASTM E 331 at a minimum differential pressure of 20 percent of inward acting, wind load design pressure of not less than 6.24 psf and not more than 12.0 psf. 1.6 SUBMITTALS A. General: See Section 01300 - SUBMITTALS. B. Product Data: Submit product data showing material proposed. Submit sufficient information to determine compliance with the Drawings and Specifications. Product data shall include, but shall not be limited to, manufacturer's product specifications, standard details, certified product test results, installation guidelines, and general recommendations applicable to specified materials and finishes. C. Shop Drawings: Submit shop drawings for each product and accessory required. Include information not fully detailed in manufacturer’s standard product data, including, but not limited to, layout and elevations, details showing thickness and dimensions of the various system parts, fastening and anchoring methods, trim, flashing; accessories, locations of joints and gaskets, and location and configuration of joints necessary to accommodate thermal movement. D. Samples: 1. Submit samples for initial color selection. Submit samples of each specified finish. Submit samples in form of manufacturer’s color charts showing full range of colors and finishes available. Where finishes involve normal color variations, include samples showing the full, range of variations expected. 2. Submit samples for verification purposes. Additional samples may be required to show fabrication techniques and workmanship. Submit the following: a. Include panel assembly samples not less than 12 inches by 12 inches, of each type of assembly in thickness specified, including, but not limited to, clips, anchors, supports, fasteners, closures, and other accessories. b. Include samples not less than 4 inches by 8 inches, of each color and finish selected. SECTION 07420 - 4 COMPOSITE PANELS E. 1.7 MARCH 16, 2011 PROJECT NAME - XXXXX KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Quality Control Submittals: 1. Qualification Data: Submit qualification data for firms and persons specified in Quality Assurance Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names of architects and owners, and other information specified. 2. Test Reports: Submit product test reports from a qualified independent inspecting and testing agency showing compliance of composite panels with requirements, based on comprehensive testing of current product formulations within the last two years. QUALITY ASSURANCE A. Qualifications: 1. Manufacturer Qualifications: Manufacturer shall be a firm engaged in the manufacture of composite panels of types and sizes required, and whose products have been in satisfactory use in similar service for a minimum of five years. 2. Installer Qualifications: Installer shall be a firm that shall have a minimum of five years of successful installation experience with projects utilizing composite panels similar in type and scope to that required for this Project, and shall be approved by the manufacturer. a. Installer shall assume undivided responsibility for all components of the composite panel system, including, but not limited to, attachment to sub-construction, panel-to-panel joinery, panel to dissimilar material joinery, and joint seal associated with the composite panel system. 3. Inspecting and Testing Agency Qualifications: To qualify for acceptance, an independent inspecting and testing agency hired by the Contractor or manufacturer to test products shall demonstrate to the Architect’s satisfaction that they are qualified according to ASTM E 329 to conduct testing indicated. B. Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances, and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary approvals from such authorities. C. Mock-Ups: Prior to installation of the work, fabricate and erect mock-ups for each type of finish and application required to verify selections made under sample submittals and to demonstrate aesthetic effects as well as qualities of materials and execution. Build mock-ups to comply with the following requirements, using materials indicated for final unit of work. 1. Locate mock-ups on site in location and of size indicated or, if not indicated, as directed by the Architect. 2. Demonstrate the proposed range of aesthetic effects and workmanship to be expected in the completed work. 3. Obtain the Architect’s acceptance of mock-ups before start of final unit of work. 4. Retain and maintain mock-ups during construction in undisturbed condition as a standard for judging completed unit of work. a. Accepted mock-ups in undisturbed condition at time of Substantial Completion may become part of completed unit of work. D. Pre-Installation Conference: Conduct pre-installation conference in accordance with Section 01200 - PROJECT MEETINGS. Prior to commencing the installation, meet at the Project site to review the material selections, installation procedures, and coordination with other trades. Mock-ups shall be reviewed during the pre-installation conference. Pre-installation conference shall include, but shall not be limited to, the Contractor, the Installer, manufacturer’s representatives, and any trade that requires coordination with the work. Date and time of the pre-installation conference shall be acceptable to the Owner and the Architect. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 07420 - 5 COMPOSITE PANELS E. Single Source Responsibility: Obtain composite panels from a single source with resources to produce products of consistent quality in appearance and physical properties without delaying the work. F. Coordination: Coordinate composite panel systems with rain drainage work, flashing, trim, and construction of walls and other adjoining work to provide a leakproof, secure, and non-corrosive installation. 1.8 DELIVERY, STORAGE, AND HANDLING A. Deliver materials to the Project site in supplier’s or manufacturer’s original wrappings and containers, labeled with supplier’s or manufacturer’s name, material or product brand name, and lot number, if any. Provide markings to identify components consistently with the Drawings. B. Store materials in their original, undamaged packages and containers, inside a well-ventilated area protected from weather, moisture, soiling, extreme temperatures, and humidity. Slope panels to ensure positive drainage of any accumulated water. Do not store panels in any enclosed space where ambient temperature can exceed 120 °F. Avoid contact with any other materials that might cause staining, denting, or other surface damage. C. Exercise care in unloading, storing, and installing composite panels to prevent bending, warping, twisting, and surface damage. D. Protect finish of panels by applying heavy duty removable plastic film during production in accordance with manufacturer’s recommendations. 1.9 PROJECT CONDITIONS A. Weather Limitations: Proceed with installation only when existing and forecasted weather conditions permit composite panel system work to be performed according to manufacturer's written instructions and warranty requirements. B. Field Measurements: Take field measurements prior to fabrication of the work and preparation of shop drawings, to ensure proper fitting of the work. Show recorded measurements on final shop drawings. Notify the Owner and the Architect, in writing, of any dimensions found which are not within specified dimensions and tolerances in the Contract Documents, prior to proceeding with the fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the work. 1.10 WARRANTY A. General: See Section 01770 - CLOSEOUT PROCEDURES. B. Special Warranty: The Contractor shall warrant the work of this Section to be in accordance with the Contract Documents and free from faults and defects in materials and workmanship within the specified warranty period. This special warranty shall extend the one year period of limitations contained in the General Conditions. The special warranty shall be countersigned by the Installer and the manufacturer. 1. Faults and Defects: Faults and defects include, but shall not be limited to, the following: a. Structural failures, including, but not limited to, rupturing, cracking, or puncturing. b. Deterioration of metals, metal finishes, and other materials beyond normal weathering. 2. Warranty Period: Warranty period shall be two years from date of Substantial Completion. SECTION 07420 - 6 COMPOSITE PANELS MARCH 16, 2011 PROJECT NAME - XXXXX KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 C. Special PVDF Finish Warranty: Submit a written warranty, signed by manufacturer, covering failure of the factory-applied exterior finish within the specified warranty period and agreeing to repair finish or replace work that shows evidence of finish deterioration. Deterioration of finish includes, but shall not be limited to, color fade, chalking, cracking, peeling, and loss of film integrity. 1. Warranty Period: Warranty period shall be 20 years from date of Substantial Completion. D. Additional Owner Rights: The warranty shall not deprive the Owner of other rights the Owner may have under other provisions of the Contract Documents and shall be in addition to and run concurrent with other warranties made by the Contractor under requirements of the Contract Documents. PART 2 - PRODUCTS 2.1 A. 2.2 MANUFACTURERS Product: Subject to compliance with requirements, provide one of the following products: 1. “Alucobond Aluminum Composite Material”, Alcan Composites USA, Inc. 2. “Reynobond”, Alcoa, Inc. 3. “Formabond Wall System”, CENTRIA. 4. “Envelope 2000”, Citadel Architectural Products, Inc. 5. “UNA-FAB”, Firestone Metal Products. 6. “Alpolic Composite Metal Panels”, Mitsubishi Chemical America, Inc. 7. “ACM 100”, Protean Construction Products, Inc. COMPOSITE METAL PANELS A. General: Provide two sheets of aluminum sandwiching a solid core of thermoplastic material formed in a continuous process with no glues or adhesives between dissimilar materials. The core material shall be free of voids and air spaces and shall not contain foamed insulation material. B. Core: Provide thermoplastic material that meets performance characteristics specified when fabricated into composite assembly. C. Face Sheets: Provide manufacturer’s standard aluminum alloy, 0.020 inch thick, and as follows: 1. Coil-coated with specified high performance finish or Spray coated with specified finish. D. Panel Characteristics: 1. Panel Thickness and Weight: 0.157 inch, 1.12 psf or less if performance criteria can be met. 2. Bond Integrity: Tested for resistance to delamination as follows: a. Bond strength shall be 1000 psi minimum, per ASTM C 297. b. Peel strength shall be 22.5 in.lb./inch minimum, per ASTM D 1781. There shall be no change in peel strength after eight hours of submersion in boiling water and after 21 days of immersion in water at 70 °F. 3. Surface Burning Characteristics: a. Flame Spread: 0, when tested per ASTM E 84. There shall be no flame spread along interior face or penetration through the wall assembly when tested in accordance with ICBO UBC No. 17-5. b. Smoke Developed: 10 maximum, when tested per ASTM E 84. c. Surface Flammability: There shall be no surface flaming when tested in accordance with ASTM E 162. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 E. 2.3 SECTION 07420 - 7 COMPOSITE PANELS Tolerances: 1. Width: ±0.08 inch. 2. Length: ±0.16 inch. 3. Panel Bow: Maximum 0.8 percent of any 72 inch panel dimension. 4. Squareness: Maximum 0.20 inch. 5. Flatness: Maximum deviation from panel flatness shall be 1/8 inch in 5 feet on panel in any direction for assembled units (non-accumulative, no oil-canning). ACCESSORIES A. Extrusions, formed members, sheet, and plate shall conform with ASTM B 209 and the recommendations of the manufacturer. B. Panel stiffeners, if required, shall be structurally fastened or restrained at the ends and shall be secured to the rear face of the composite panel with silicone of sufficient size and strength to maintain panel flatness. Stiffener material and finish shall be compatible with the silicone. C. Sealants and gaskets within the composite panel system shall be as per manufacturer's standards to meet performance requirements. D. Fabricate flashing materials from 0.030 inch minimum thickness aluminum sheet painted to match the adjacent composite panel system where exposed. E. Provide fasteners as recommended by composite panel manufacturer. Do not expose fasteners except where unavoidable and then match finish of adjoining metal. 2.4 FABRICATION A. General: Shop fabricate to sizes and joint configurations indicated on the Drawings. Field fabrication shall be allowed where necessary, but shall be kept to an absolute minimum. Fabrication shall be done under controlled shop conditions when possible. Form panel lines, breaks, and angles to be sharp and true, with surfaces that are free from warp or buckle. Fabricate with sharply cut edges, with no displacement of aluminum sheet or protrusion of core. B. System Type and Characteristics: 1. Wet System Type: System shall provide a wet seal (caulked) reveal joint as detailed on the Drawings. The sealant type shall be as specified in Section 07900 - JOINT SEALERS and with foamed type backer rod as indicated on the Drawings. 2. Characteristics: a. System shall not have any visible fasteners, telegraphing, or fastening on the panel faces or any other compromise of a neat and flat appearance. b. System shall comply with the applicable provisions of AAMA MCWM-1 and AAMA SFM-1, and with AAMA/WDMA 101/I.S. 2 requirements for aluminum windows. c. Fabricate composite panel system to dimension, size, and profile indicated on the Drawings based on a design temperature of 70 °F. d. Fabricate composite panel system so that no restraints can be placed on the panel which might result in compressive skin stresses. The installation detailing shall be such that the panels remain flat regardless of temperature change and at all times remain airtight and watertight. e. The finish side of the panel shall have a removable plastic film applied prior to fabrication which shall remain on the panel during fabrication, shipping, and erection to protect the surface from damage. SECTION 07420 - 8 COMPOSITE PANELS 3. C. 2.5 MARCH 16, 2011 PROJECT NAME - XXXXX KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Basis of Design: "UNA-CLAD Series 1000", Firestone Metal Products, modified to depth indicated on the drawings. Sheet Metal Accessories: Fabricate flashing and trim to comply with recommendations in SMACNA ASMM that apply to the design, dimensions, metal, and other characteristics of item indicated. 1. Form exposed sheet metal accessories that are without excessive oil-canning, buckling, and tool marks and that are true to line and levels indicated, with exposed edges folded back to form hems. 2. Fabricate non-moving seams in accessories with flat-lock seams. Form seams and seal with epoxy seam sealer. Rivet joints for additional strength. 3. Form non-expansion but movable joints in metal to accommodate elastomeric sealant to comply with SMACNA standards. 4. Conceal fasteners and expansion provisions where possible. Exposed fasteners are not allowed on faces of accessories exposed to view. 5. Fabricate cleats and attachment devices from same material as accessory being anchored or from compatible, non-corrosive metal recommended by metal panel manufacturer. Size shall be as recommended by SMACNA ASMM or metal panel manufacturer for application but not less than thickness of metal being secured. FINISHES A. General: Comply with NAAMM MFM for recommendations relative to application and designation of finishes. 1. Finish designations prefixed by "AA" conform to the system established by the Aluminum Association for designating aluminum finishes. 2. Remove die markings, scratches, abrasions, dents, and other blemishes before applying finish. B. High Performance Organic Coating: AA-C12-C42-R1x (Chemical Finish: cleaned with inhibited chemicals; Chemical Finish: chemical conversion coating, acid chromate-fluoride-phosphate pretreatment; Organic Coating: as specified below). Prepare, pretreat, and apply coating to exposed metal surfaces to comply with coating and resin manufacturer's instructions. 1. Standard Two-Coat Polyvinylidene Fluoride (PVDF) Finish Coating: Manufacturer's standard thermocured system, complying with AAMA 2605, composed of specially formulated inhibitive primer and fluoropolymer color topcoat containing not less than 70 percent PVDF resin by weight, as produced by Arkema, Inc. ("Kynar 500") or by Solvay Solexis, Inc. ("Hylar 5000"). Provide minimum 1.2 mil total dry film thickness. a. Color and Gloss: Match the Architect's sample. (Intended to match Accent Brick color specified in Section 04210 - BRICK.) b. PVDF Touch-Up Finish: PVDF finish coating, containing fluoropolymer resin and formulated for air-drying at ambient temperature. Provide for field touch-up and furnish in color to match shop-applied finishes. PART 3 - EXECUTION 3.1 A. EXAMINATION Verification of Conditions: Examine areas and conditions under which the work is to be installed, and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 1. 3.2 SECTION 07420 - 9 COMPOSITE PANELS Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by the Installer. INSTALLATION A. Install girts, angles, and other secondary structural panel support members and anchorage according to ASTM C 754 and composite panel manufacturer's written recommendations. B. Install panels plumb, level, and true, in compliance with manufacturer's recommendations. C. Erect and anchor panels securely in place, in accordance with the final shop drawings. Attachment system shall allow for the free and noiseless vertical and horizontal thermal movement due to expansion and contraction for a material temperature range of -20 °F to 180 °F. Buckling of panels, opening of joints, undue stress on fasteners, failure of sealants or any other detrimental effects due to thermal movement will not be permitted. Fabrication, assembly, and erection procedure shall account for the ambient temperature at the time of the respective operation. D. Comply with manufacturer’s instructions for installation of concealed fasteners and with provisions of Section 07900 - JOINT SEALERS for installation of joint sealers. E. Comply with composite panel manufacturer's recommendations and guidelines for field forming of panels. F. Do not install component parts which are observed to be defective, including, but not limited to, warped, bowed, dented, abraised, and broken members. G. Do not cut, trim, weld, or braze component parts during erection in a manner which would damage the finish, decrease strength, or result in visual imperfection or a failure in performance. Return component parts which require alteration to shop for refabrication, if possible, or for replacement with new parts. H. Separate dissimilar metals and use gasketed fasteners where needed to eliminate the possibility of corrosive or electrolytic action between metals. I. Maximum deviation from vertical and horizontal alignment of erected panels shall be 1/4 inch in 20 feet, non-accumulative. 3.3 FIELD QUALITY CONTROL A. General: See Section 01410 - INSPECTING AND TESTING SERVICES. B. Testing: Hose test in accordance with Section 08900 - EXTERIOR WALL PERFORMANCE REQUIREMENTS. C. Inspection: Inspecting and testing agency shall inspect and report on all connections and welds. 3.4 ADJUSTING A. Remove and replace composite panels damaged beyond repair. Repair panels with minor damage so that repairs are not discernible at a distance of 10 feet. B. Remove protective film immediately after installation of joint sealers and immediately prior to completion of composite metal panel work. SECTION 07420 - 10 COMPOSITE PANELS MARCH 16, 2011 PROJECT NAME - XXXXX KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 C. Make sure weepholes and drainage channels are unobstructed and free of dirt and sealants. D. Remove from the job site damaged panels, protective film, and other debris attributable to work of this Section. 3.5 A. PROTECTION Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall ensure that the composite panels shall be without damage at time of Substantial Completion. END OF SECTION MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 10152 - 1 HOSPITAL CUBICLE CURTAINS AND TRACKS SECTION 10152 HOSPITAL CUBICLE CURTAINS AND TRACKS PART 1 - GENERAL 1.1 A. 1.2 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General Conditions, Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project Manual apply to the work specified in this Section. SUMMARY A. Scope: Provide labor, material, equipment, related services, and supervision required, including, but not limited to, manufacturing, fabrication, erection, and installation for hospital cubicle curtains and tracks as required for the complete performance of the work, and as shown on the Drawings and as herein specified. B. Section Includes: The work specified in this Section includes, but shall not be limited to, the following: 1. Hospital cubicle curtains. 2. Hospital cubicle curtain tracks. 1.3 REFERENCES A. The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by the basic designation only. B. The edition/revision of the referenced publications shall be the latest date as of the date of the Contract Documents, unless otherwise specified. C. American Architectural Manufacturers Association (AAMA): 1. AAMA 611, "Voluntary Specifications for Anodized Architectural Aluminum (Revised).” D. ASTM (ASTM): 1. ASTM B 221, "Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Shapes, and Tubes." 2. ASTM E 84, "Standard Test Method for Surface Burning Characteristics of Building Materials." E. National Association of Architectural Metal Manufacturers (NAAMM): 1. NAAMM MFM, "Metal Finishes Manual." 1.4 SUBMITTALS A. General: See Section 01300 - SUBMITTALS. B. Product Data: Submit product data showing material proposed. Submit sufficient information to determine compliance with the Drawings and Specifications. SECTION 10152 - 2 HOSPITAL CUBICLE CURTAINS AND TRACKS MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 C. Shop Drawings: Submit shop drawings for each product and accessory required. Include information not fully detailed in manufacturer’s standard product data, including, but not limited to, layout of tracks and method of anchorage. D. Samples: 1. Submit samples for initial color selection. Submit samples of each specified finish. Submit samples in form of manufacturer’s color charts showing full range of colors and finishes available. Where finishes involve normal color variations, include samples showing the full, range of variations expected. 2. Submit samples for verification purposes. Submit the following: a. One 12 inch long piece of cubicle curtain track with carrier access and end stop. b. One clip anchor for fastening track to grid system of acoustical ceilings. c. One curtain carrier. E. Qualification Data: Submit qualification data for firms and persons specified in Quality Assurance Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names of architects and owners, and other information specified. 1.5 QUALITY ASSURANCE A. Qualifications: 1. Manufacturer Qualifications: Manufacturer shall be a firm engaged in the manufacture of hospital cubicle curtains and tracks of types and sizes required, and whose products have been in satisfactory use in similar service for a minimum of five years. 2. Installer Qualifications: Installer shall be a firm that shall have a minimum of five years of successful installation experience with projects utilizing hospital cubicle curtains and tracks similar in type and scope to that required for this Project. B. Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances, and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary approvals from such authorities. C. Surface Burning Characteristics: Provide hospital cubicle curtains with the surface burning characteristics as indicated below, as determined by testing identical products per ASTM E 84, by Underwriters Laboratories, Inc. (UL), Intertek Testing Services (ITS), or other inspecting and testing agency acceptable to authorities having jurisdiction. Identify hospital cubicle curtains with appropriate markings of applicable inspecting and testing agency. 1. Flame Spread: 25 or less. 2. Smoke Developed: 450 or less. D. Single Source Responsibility: Obtain hospital cubicle curtains, tracks, and related accessories from a single source with resources to produce products of consistent quality in appearance and physical properties without delaying the work. 1.6 A. DELIVERY, STORAGE, AND HANDLING Deliver materials to the Project site in supplier’s or manufacturer’s original wrappings and containers, labeled with supplier’s or manufacturer’s name, material or product brand name, and lot number, if any. Do not open packages until contents are needed for installation, unless verification inspection is required. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 B. 1.7 A. SECTION 10152 - 3 HOSPITAL CUBICLE CURTAINS AND TRACKS Store materials in their original, undamaged packages and containers, inside a well-ventilated area protected from weather, moisture, soiling, extreme temperatures, and humidity. Store so as to not bend or warp the tracks. PROJECT CONDITIONS Field Measurements: Take field measurements prior to fabrication of the work and preparation of shop drawings, to ensure proper fitting of the work. Show recorded measurements on final shop drawings. Notify the Owner and the Architect, in writing, of any dimensions found which are not within specified dimensions and tolerances in the Contract Documents, prior to proceeding with the fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the work. PART 2 - PRODUCTS 2.1 A. 2.2 CUBICLE CURTAINS General: Cubicle curtains shall be minimum 10 percent wider than the track upon which they run. Cubicle curtains shall hang to within 15 inches above the finished floor. 1. Curtains Without Nylon Mesh Tops: Provide top hem of 1-1/2 inch width with three thicknesses of fabric. An integral webbing shall be provided in the top hem to ensure proper gripping of the grommets. The bottom hem shall be 1 inch wide, triple thickness, and the side hems shall be 1 inch wide with triple thickness of material. No crooked selvage edges shall be used in place of side hems. Vertical seams shall be overlapped and sewn with a double needle, interlocked stitch to ensure straightness and strength of seams. Bottom hem sewing shall be turned vertically at each corner to prevent unraveling of sewing thread. Sewing shall be performed with lock stitch machines. Grommets shall be nickel-plated brass and shall be machined into the top hem at 6 inch intervals. These grommets shall be firmly anchored into the triple thickness of the hem. 2. Color and Pattern: As selected by the Architect from the manufacturer’s standards. CUBICLE CURTAIN TRACKS A. Surface-Mounted Type Channel Tracks: Provide extruded aluminum, ASTM B 221, Alloy 6063, Temper T5 or Temper T6, channel-shaped, with smooth inside raceway for curtain carriers. B. Curtain Carriers: Provide nylon or delrin carriers, with either nylon or delrin wheels on metal, delrin, or nylon axles. Equip each carrier with either stainless steel, chromium-plated brass, or steel hooks with swivel, or nickel chromium-plated brass or stainless steel bead chain and hook assembly, or delrin carriers may have molded-on delrin hooks. Hook for bead chain may be the same material and finish as the bead chain or may be chromium-plated steel. Provide 2.2 carriers for every foot of each section of each track length, plus one additional carrier. C. End Stop Connectors, Ceiling Flanges, and Other Accessories: Fabricate from the same material with the same finish as the tracks or from nylon. 2.3 FASTENERS A. Exposed Fasteners, Screws, and Bolts: Provide stainless steel or chromium/nickel-plated brass. B. Concealed Fasteners, Screws, and Bolts: Provide hot-dip galvanized (except in high moisture areas use stainless steel). SECTION 10152 - 4 HOSPITAL CUBICLE CURTAINS AND TRACKS C. 2.4 A. 2.5 MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 Metal Clips: Anchor curtain tracks to exposed grid of lay-in acoustical panel ceilings, with concealed metal (butterfly) type or two-piece snap locking type of high strength spring steel. FABRICATION Weld and grind smooth joints of fabricated components. Form tracks and bends of lengths that will produce the minimum number of joints. Make track sections up to 16 feet without joints. Form corner bend on a 12 inch radius. Provide steel anchor plates, supports, and anchors for securing components to building construction. Form flat surface without distortion. Shop assemble components and package complete with anchors and fittings. FINISHES A. General: Comply with NAAMM MFM for recommendations relative to application and designation of finishes. 1. Finish designations prefixed by "AA" conform to the system established by the Aluminum Association for designating aluminum finishes. B. Aluminum Class II Clear Anodized Finish: AA-M12-C22-A31 (Mechanical Finish: as fabricated, non-specular; Chemical Finish: etched, medium matte; Anodic Coating: Class II Architectural, clear film thicker than 0.4 mil) complying with AAMA 611. PART 3 - EXECUTION 3.1 A. 3.2 EXAMINATION Verification of Conditions: Examine areas and conditions under which the work is to be installed, and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected. 1. Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by the Installer. INSTALLATION A. Install tracks after finish painting and ceiling finishing operations are complete. B. Anchor surface-mounted curtain tracks directly to exposed grid of lay-in acoustical panel ceilings with concealed metal clips, spaced approximately 24 inches on center. C. Securely fasten end stop caps to prevent their being forced out by the striking weight of carriers. D. Remove damaged or defective components and replace with new components or repair to the original condition. E. Track shall be installed neat, rigid, plumb, level and true, and securely anchored to the overhead construction. F. Carrier units shall operate smoothly and easily over the full range of travel. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 3.3 A. SECTION 10152 - 5 HOSPITAL CUBICLE CURTAINS AND TRACKS PROTECTION Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall ensure that the hospital cubicle curtains and tracks shall be without damage at time of Substantial Completion. END OF SECTION MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 SECTION 10531 - 1 ALUMINUM CANOPY STRUCTURES SECTION 10531 ALUMINUM CANOPY STRUCTURES PART 1 - GENERAL 1.1 A. 1.2 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General Conditions, Division 1 - GENERAL REQUIREMENTS, and other applicable specification sections in the Project Manual apply to the work specified in this Section. SUMMARY A. Scope: Provide design and engineering, labor, material, equipment, related services, and supervision required, including, but not limited to, manufacturing, fabrication, erection, and installation for aluminum canopy structures as required for the complete performance of the work, and as shown on the Drawings and as herein specified. B. Section Includes: The work specified in this Section includes, but shall not be limited to, prefabricated aluminum pedestrian canopy structure system designed and engineered by system manufacturer. 1.3 REFERENCES A. The publications listed below form a part of this Specification to the extent referenced. The publications are referred to in the text by the basic designation only. B. The edition/revision of the referenced publications shall be the latest date as of the date of the Contract Documents, unless otherwise specified. C. Aluminum Association, Inc. (AA): 1. AA SAS-30, "Specifications for Aluminum Structures." D. American Architectural Manufacturers Association (AAMA): 1. AAMA 2604, " Voluntary Specification, Performance Requirements and Test Procedures for High Performance Organic Coatings on Aluminum Extrusions and Panels." E. American Society of Civil Engineers (ASCE): 1. ASCE 7, "Minimum Design Loads for Buildings and Other Structures" (copyrighted by ASCE, ANSI approved). F. ASTM (ASTM): 1. ASTM B 209, "Standard Specification for Aluminum and Aluminum-Alloy Sheet and Plate." 2. ASTM B 221, "Standard Specification for Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Shapes, and Tubes." 3. ASTM C 1107, "Standard Specification for Packaged Dry, Hydraulic-Cement Grout (Non-Shrink).” G. Green Seal (GS): 1. GS-37, “Industrial & Institutional Cleaners.” SECTION 10531 - 2 ALUMINUM CANOPY STRUCTURES MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 H. National Association of Architectural Metal Manufacturers (NAAMM): 1. NAAMM MFM, "Metal Finishes Manual." I. Underwriters Laboratories, Inc. (UL): 1. UL 972, "Standard for Burglary Resisting Glazing Material" (copyrighted by UL, ANSI approved). 1.4 SYSTEM DESCRIPTION A. General: Metal canopy structure shall have internal drainage from deck to gutter and downspout through columns. Accessories shall be aluminum. B. Designer Requirements: Engage and pay for the services of an engineer to design the aluminum canopy structure system, including, but not limited to, foundations. C. Structural Requirements: Design aluminum canopy structure system and connections in accordance with the referenced standards and the applicable local code for wind load and live load criteria. 1.5 SUBMITTALS A. General: See Section 01300 - SUBMITTALS. B. Product Data: Submit product data showing material proposed. Submit sufficient information to determine compliance with the Drawings and Specifications. Product data shall include, but shall not be limited to, manufacturer's product information, specifications, and installation instructions for building components and accessories. C. Shop Drawings: Submit complete shop drawings, including, but not limited to, layout, necessary plan dimensions, elevations, and details. 1. Include location and details of anchorage devices that are to be embedded in other construction. Furnish templates if required for accurate placement. 2. Shop drawings shall be signed and sealed by the professional engineer. 3. Verify with the Contractor dimensions and elevations at each column and any related soffit before fabrication. D. Samples: 1. Submit samples for initial color selection. Submit samples of each specified finish. Submit samples in form of manufacturer’s color charts showing full range of colors and finishes available. Where finishes involve normal color variations, include samples showing the full, range of variations expected. 2. Submit samples for verification purposes. Submit samples of aluminum finishes for roof panel and extruded support structure. E. Quality Control Submittals: 1. Design Data: Submit design calculations for aluminum canopy structure system and connections attaching it to the main building structure. The design data shall be signed and sealed by the professional engineer. Only loading on the main building structure at any connections will be reviewed. 2. Qualification Data: Submit qualification data for firms and persons specified in Quality Assurance Article to demonstrate their capabilities and experience. Include lists of completed projects with project names and addresses, names of architects and owners, and other information specified. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 1.6 SECTION 10531 - 3 ALUMINUM CANOPY STRUCTURES QUALITY ASSURANCE A. Qualifications: 1. Manufacturer Qualifications: Manufacturer shall be a firm engaged in the manufacture of aluminum canopy structures of types and sizes required, and whose products have been in satisfactory use in similar service for a minimum of five years. 2. Installer Qualifications: Installer shall be a firm that shall have a minimum of five years of successful installation experience with projects utilizing aluminum canopy structures similar in type and scope to that required for this Project, and shall be approved by the manufacturer. 3. Engineer Qualifications: The engineer shall be a professional engineer legally authorized to practice in the jurisdiction where the Project is located and experienced in providing engineering services of the kind indicated that have resulted in the installation of products similar to this Project in material, design, and extent, and that have a record of successful in-service performance. B. Regulatory Requirements: Comply with applicable requirements of the laws, codes, ordinances, and regulations of Federal, State, and local authorities having jurisdiction. Obtain necessary approvals from such authorities. 1. The completed aluminum canopy structure system and its structural system shall meet applicable state and local building code requirements. C. Standards: Comply with applicable requirements of AA SAS-30 and ASCE 7. D. Single Source Responsibility: Obtain aluminum canopy structure, including, but not limited to, all necessary components and accessories, from a single source with resources to produce products of consistent quality in appearance and physical properties without delaying the work, or from a source approved by the aluminum canopy structure manufacturer. 1.7 DELIVERY, STORAGE, AND HANDLING A. Deliver materials to the Project site in supplier’s or manufacturer’s original wrappings and containers, labeled with supplier’s or manufacturer’s name, material or product brand name, and lot number, if any. B. Store materials in their original, undamaged packages and containers, inside a well-ventilated area protected from weather, moisture, soiling, extreme temperatures, and humidity. C. Deliver, store, and handle aluminum canopy structure system as recommended by manufacturer. 1.8 A. 1.9 A. PROJECT CONDITIONS Field Measurements: Take field measurements prior to fabrication of the work and preparation of shop drawings, to ensure proper fitting of the work. Show recorded measurements on final shop drawings. Notify the Owner and the Architect, in writing, of any dimensions found which are not within specified dimensions and tolerances in the Contract Documents, prior to proceeding with the fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the work. SEQUENCING AND SCHEDULING Concrete Footings: Layout and footings blockout shall be provided by aluminum canopy system manufacturer. Concrete, reinforcement, and formwork requirements are specified in Division 3 - CONCRETE. SECTION 10531 - 4 ALUMINUM CANOPY STRUCTURES 1.10 MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 WARRANTY A. General: See Section 01770 - CLOSEOUT PROCEDURES. B. Special PVDF Finish Warranty: Submit a written warranty, signed by manufacturer, covering failure of the factory-applied exterior finish within the specified warranty period and agreeing to repair finish or replace work that shows evidence of finish deterioration. Deterioration of finish includes, but shall not be limited to, color fade, chalking, cracking, peeling, and loss of film integrity. 1. Warranty Period: Warranty period shall be 5 years from date of Substantial Completion. C. Additional Owner Rights: The warranty shall not deprive the Owner of other rights the Owner may have under other provisions of the Contract Documents and shall be in addition to and run concurrent with other warranties made by the Contractor under requirements of the Contract Documents. PART 2 - PRODUCTS 2.1 A. 2.2 MANUFACTURERS Manufacturer: Subject to compliance with requirements, provide products of one of the following: 1. Dittmer Architectural Aluminum. 2. Peachtree Protective Covers. 3. Perfection Architectural Systems, Inc. 4. Royal Aluminum Inc. MATERIALS A. Aluminum: 1. Sheets: ASTM B 209 for Alloy 3105 H-28; minimum yield 30,000 ksi, or alloy and temper required to suit forming operations and finish requirements. 2. Extruded: ASTM B 221 Alloy 6061-T6, Alloy 6063-T5 and T6, or alloy and temper required to suit structural and finish requirements. B. Hardware: Provide plated non-corrosive hardware as recommended by manufacturer. C. Non-Metallic, Non-Shrink Grout: Provide premixed, non-metallic, non-corrosive, non-staining grout containing selected silica sands, portland cement, shrinkage-compensating agents, plasticizing and water-reducing agents, complying with ASTM C 1107, with fluid consistency and a 30 minute working time. Provide grout specifically recommended by manufacturer for applications. D. Gaskets: Provide manufacturer's standard design of neoprene or EPDM. E. Sealants: See Section 07900 - JOINT SEALERS. F. Flashing and Other Non-Structural Items: Provide as recommended by manufacturer. G. Accessories: Provide accessory items only as produced and recommended by manufacturer of primary product. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 2.3 SECTION 10531 - 5 ALUMINUM CANOPY STRUCTURES COMPONENTS A. Columns: Columns shall be extruded aluminum sections of sizes, shapes, and gage to meet required design loads, and as indicated on the Drawings. B. Beams: Beams shall be extruded aluminum sections of sizes, shapes, and gage to meet required design loads, and as indicated on the Drawings. Top edges shall be thickened for strength and designed to receive deck members in self-flashing manner. Structural ties shall be installed in tops of beams. C. Deck: Provide load-bearing aluminum roof deck properly supported by the primary framing members. Roof deck shall use interlocking joints designed and fabricated to provide structural continuity and self-flashing. Gage shall be sufficient to meet required design loads. Closures at deck ends shall be welded plates. D. Fascia: Fascia shall be manufacturer’s standard shape, size as indicated on the Drawings. E. Flashing: Flashing shall be 0.040 inch aluminum, minimum. Thru-wall flashing will be by others. F. Water Drainage System: Provide cutouts and internal deflectors in members as recommended by manufacturer to act as internal water drainage system. 2.4 FABRICATION A. Design: Aluminum canopy structure shall be all-welded extruded aluminum system complete with internal drainage. Non-welded systems are not acceptable. Roll-formed deck is not acceptable. Expansion joints shall be included to accommodate temperature changes of 120 °F. Expansion joints shall have no metal-to-metal contact. B. Bent Construction: Beams and columns shall be factory-welded with neatly mitered corners into one-piece rigid bents. Welds shall be smooth and uniform. Suitable edge preparation shall be performed to assure 100 percent penetration. Grind welds only where interfering with adjoining structure to allow for flush connection. Field welding is not permitted. Rigid mechanical joints shall be used when shipping limitations prohibit the shipment of fully welded bents. C. Deck Construction: Deck shall be manufactured of extruded modules that interlock in a self-flashing manner. Interlocking joints shall be positively fastened at 8 inch on center creating a monolithic structural unit capable of developing the full strength of the sections. The fastenings shall have minimum shear strength of 350 pounds each. Deck shall be assembled with sufficient camber to offset dead load deflection. 2.5 A. FINISHES General: Comply with NAAMM MFM for recommendations relative to application and designation of finishes. 1. Finish designations prefixed by "AA" conform to the system established by the Aluminum Association for designating aluminum finishes. 2. Remove die markings, scratches, abrasions, dents, and other blemishes before applying finish. 3. Finish for non-exposed aluminum extrusion or member shall be manufacturer's standard finish. SECTION 10531 - 6 ALUMINUM CANOPY STRUCTURES B. MARCH 16, 2011 KING SPRINGS ELEMENTARY SCHOOL ADDITIONS AND MODIFICATIONS - 20100358 CCSD PROJECT NO. 224/8032 High Performance Organic Coating: Prepare, pretreat, and apply coating to exposed metal surfaces to comply with coating and resin manufacturer's instructions. 1. Standard Two-Coat Polyvinylidene Fluoride (PVDF) Finish Coating: Manufacturer's standard thermocured system, complying with AAMA 2604, composed of specially formulated inhibitive primer and fluoropolymer color topcoat containing not less than 50 percent PVDF resin by weight, as produced by Arkema, Inc. ("Kynar 500") or by Solvay Solexis, Inc. ("Hylar 5000") and manufacturer's standard additive to produce a "metallic" color finish. Provide minimum 1.2 mil total dry film thickness. a. Color and Gloss: Match Architect's sample. b. PVDF Touch-Up Finish: PVDF finish coating, containing fluoropolymer resin and formulated for air-drying at ambient temperature. Provide for field touch-up and furnish in color to match shop-applied finishes. 2. Basis of Design: Permadized Hardcoat Finish, by Kawneer. PART 3 - EXECUTION 3.1 A. 3.2 A. 3.3 A. 3.4 A. B. 3.5 A. EXAMINATION Verification of Conditions: Examine areas and conditions under which the work is to be installed, and notify the Contractor in writing, with a copy to the Owner and the Architect, of any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected. 1. Beginning of the work shall indicate acceptance of the areas and conditions as satisfactory by the Installer. PREPARATION Installation shall not start until concrete, masonry, and roofing work in the vicinity is complete and cleaned. INSTALLATION Install aluminum canopy structure system with fasteners, connections, and sealants in strict accordance with manufacturer's written instructions, reviewed product data, and final shop drawings. 1. Aluminum canopy structures shall be erected true to line, level and plumb. Aluminum columns embedded in concrete shall be protected by manufacturer’s recommended coating. ADJUSTING AND CLEANING Touch-up minor scratches and abrasions. Aluminum canopy structures and components shall be cleaned promptly after installation in accordance with manufacturer’s recommendations. No cleaning products or processes shall exceed listed VOC limits or use ozone - depleting substances. Cleaning materials shall comply with GS-37. PROTECTION Provide final protection and maintain conditions in a manner acceptable to the Installer, that shall ensure that the aluminum canopy structures shall be without damage at time of Substantial Completion. END OF SECTION MARCH 16, 2011 - ADDENDUM #1 KING SPRINGS ELEMENTARY SCHOOL RENOVATION AND ADDITION – 20100358 CCSD PROJECT NO. 224/8032 BW&A 10958 SECTION 15800 - 1 AIR DISTRIBUTION DEVICES SECTION 15800 AIR DISTRIBUTION DEVICES PART 1 - GENERAL 1.1 1.2 DESCRIPTION A. All work specified in this section is governed by the Mechanical General Section 15010. B. This Section 15800 and the accompanying drawings cover the provisions of all labor, equipment, appliances and materials, and performing all operations in connection with the construction and installation of air distribution devices as specified herein and as shown. These units include, but are not limited to the following: Ceiling Diffusers (CD) 2. Return Air Grilles (RAG) 3. Exhaust Registers (ER) 4. Exhaust Grilles (EG) 5. Slot Diffusers (SD) 6. Return Air Slots (RS) 7. Supply Registers (SR) 8. Supply Grilles (SG) 9. Return Air Registers (RAR) 10. Linear Slot Diffusers (LSD) 11. Linear Return Slots (LRS) 12. Linear Exhaust Slots (LES) 13. Transfer Grilles (TG) 14. Architectural Linear Slot (ALS) INTENT A. 1.3 1. It is the intent of this Section of the specifications to provide complete, operable, adjusted air distribution devices as shown and specified which are free of excessive noise, vibration and airflow fluctuations. SELECTION CRITERIA A. All air distribution devices shall be selected in accordance with the following minimum SECTION 15800 - 2 AIR DISTRIBUTION DEVICES MARCH 16, 2011 - ADDENDUM #1 KING SPRINGS ELEMENTARY SCHOOL RENOVATION AND ADDITION – 20100358 CCSD PROJECT NO. 224/8032 BW&A 10958 criteria unless otherwise noted below or on the drawings: 1. Method of mounting shall be compatible with the ceiling, wall or duct surface which it mounts on or in; i.e. lay-in, surface mounting, plaster frame, duct collar, etc. The architectural drawings shall be referenced to determine the mounting method for each device. All flanges on surface mounted devices shall be provided with a gasket. 1.4 Finish of all ceiling mounted devices shall be selected to match the color of the adjacent ceiling. Finish of all wall mounted devices shall be primer which is compatible with the finish coating specified for the adjacent wall; finish coat will be applied under Division 9. 3. Noise Criteria for classrooms shall be 25-30 NC; the music room shall be 20 to 25 NC. All other spaces shall be as listed under PART 2 - PRODUCTS. BASIS OF DESIGN A. 1.5 2. The basis of design is Carnes. Any proposed substitutions shall be proven equal in all respects to the equipment specified as the basis of design. Any modifications to ductwork, controls, ceilings, building structure, etc., that result from any substitution shall be coordinated with all trades. This coordination shall occur before delivery of equipment and any modifications shall be performed without incurring additions to the Contract. ACCEPTABLE MANUFACTURERS A. Acceptable manufacturers are Price, Metal Aire, Nailor and Titus, provided that their units, performance, appearance and physical characteristics are equal in all respects for this specific project. PART 2 - PRODUCTS 2.1 DESCRIPTION A. Ceiling Diffuser (CD) 1. B. Return Air Grilles (RAG) 1. C. Ceiling diffusers shall be perforated face diffusers equipped with fully adjustable pattern controls, capable of providing one-way, two-way, two-way corner, threeway, and four-way air patterns; Carnes SPAB. Diffuser performance data shall be in accordance with ADC equipment test code 162R4. The perforated face shall be hinged for easy access to pattern controls and duct accessories. The maximum NC level at design airflow shall not exceed 35 when measured in a direct field 5'-0" from the face of the device. Return air grilles shall be hollow core, perforated face, lay-in type, selected to match the CDs; Carnes SPRB. Performance data shall be in accordance with ADC 1062R4. All other characteristics shall be equal to the ceiling diffusers. Exhaust Registers (ER) 1. Exhaust registers shall be surface mounted, fixed curved blade steel registers MARCH 16, 2011 - ADDENDUM #1 KING SPRINGS ELEMENTARY SCHOOL RENOVATION AND ADDITION – 20100358 CCSD PROJECT NO. 224/8032 BW&A 10958 SECTION 15800 - 3 AIR DISTRIBUTION DEVICES with blades at 0.666 to 0.750 inches on center. Provide opposed blade dampers with each ER for balancing purposes. ERs shall be Carnes RTLB, sized as indicated. D. Exhaust Grilles (EG) 1. E. Exhaust grilles shall be surface mounted, fixed curved blade steel grilles with blades at 0.666 to 0.750 inches on center. EGs shall be Carnes RSLA sized as indicated. Slot Diffuser 1. Supply (SD) a. 2. Return (RS) a. F. Supply registers shall be surface mounted, steel, adjustable double-deflection type complete with opposed blade dampers for balancing purposes. The outermost set of deflection blades shall be parallel to the long dimension of the SR and the innermost set of deflection blades shall be parallel to the short dimension of the SR. The registers shall be tested in accordance with ADC standards and shall be selected to provide design airflow at a maximum NC of 35. SRs shall be Carnes RTDB Series, sized as indicated. Supply Grilles (SG) 1. H. Return slots shall meet all above requirements for slot diffuser with the exception that the pattern controllers shall be removed to allow maximum free area for return air flow. Carnes DAHC. Supply Registers (SR) 1. G. Each slot diffuser shall be equipped with an individually adjustable pattern controller for each slot to insure full 180 degree air pattern; Carnes DASC. The diffuser shall be constructed of 24 gauge galvanized steel with inlet size and length as indicated. Each SD shall be provided with a lined steel plenum with tappings for round duct connections as indicated. Maximum NC level shall not exceed 35 at design airflow. Liner shall conform to NFPA 90A 25/50 requirements. Supply grilles shall be surface mounted, steel, adjustable double-deflection type. The outermost set of deflection blades shall be parallel to the long dimension of the SG and the innermost set of deflection blades shall be parallel to the short dimension of the SG. The grilles shall be tested in accordance with ADC standards and shall be selected to provide design airflow at a maximum NC of 35. SGs shall be Carnes RSDB Series, sized as indicated. Return Air Registers (RAR) 1. Return air registers shall be surface mounted, steel, registers with curved hemmed edge blades with an opposed blade damper. Damper blades shall be gang operated by means of a key which can be removed after balancing. RARs shall be Carnes RTLA, sized as indicated. SECTION 15800 - 4 AIR DISTRIBUTION DEVICES I. MARCH 16, 2011 - ADDENDUM #1 KING SPRINGS ELEMENTARY SCHOOL RENOVATION AND ADDITION – 20100358 CCSD PROJECT NO. 224/8032 BW&A 10958 Linear Slot Diffuser (LSD) 1. Supply (LSD) a. 2. Linear slot diffusers shall be Carnes Channelaire Model CH. Diffusers shall be of aluminum construction with one or more parallel slot(s). Each slot shall contain pattern controls, adjustable from the face of the diffuser. The same pattern controls shall function as volume controls without affecting the air discharge pattern. Each LSD shall be continuous length as indicated on the Drawings, complete with finished ends, mitered corners and splined joints. Plenums shall also be provided as indicated with all open inactive sections of the LSD covered with blank-off internal plates. Plenums shall have round collars for connection of flexible duct. Performance data shall be per ADC with a maximum NC of 35. Return (LRS) a. Linear return slots shall equal specified LSD with the following exceptions: 1) 2) 3. Exhaust (LES) a. Linear exhaust slots shall equal specified LSD's with the following exceptions: 1) 2) J. Plenums shall be lined in accordance with UL 181 and NFPA 90A. Pattern controls shall be used for dampering only. Transfer Grilles (TG) 1. K. Plenums shall be lined in accordance with ul 181 and NFPA 90A. Pattern controls are not required. Transfer grilles shall be similar to return air grilles (RAG) Architectural Linear Slot (ALS) 1. Supply (ALS) a. 2. Architectural linear slot shall be Carnes Channelaire wide body linear diffuser. Diffuser shall be aluminum construction with one (1) 2” wide slot. Diffuser shall be equipped with one (1) 2” wide slot. Diffuser shall be equipped with an individually adjustable pattern controller. Each ALS shall be provided with a lined stem plenum with tappings for round duct connections as indicated. Maximum NC shall not exceed 35 at design airflow. Linear shall conform to NFPA 90A 25/50 requirements. Border option to be selected by Architect. Return (ALR) MARCH 16, 2011 - ADDENDUM #1 KING SPRINGS ELEMENTARY SCHOOL RENOVATION AND ADDITION – 20100358 CCSD PROJECT NO. 224/8032 BW&A 10958 a. SECTION 15800 - 5 AIR DISTRIBUTION DEVICES Architectural return slot to be same as supply with the exception that the pattern controllers shall be removed to allow maximum free area. PART 3 - EXECUTION 3.1 INSTALLATION A. 3.2 Air distribution devices shall be installed as indicated and in conformance with the manufacturer's recommendations. The color, frame and border types shall be coordinated with Architectural requirements and shall be selected to install in the finished surface indicated. ADJUSTMENT A. Grilles, registers and diffusers shall be tested and adjusted to provide the scheduled air flow capacities. B. All adjustable air distribution devices located within three feet of any wall shall be set to blow directly away from, or parallel to, the wall. C. In all slot diffuser applications, the inactive sections of the slot shall be finished with perforated steel, painted flat black, selected to match the CDs. These sections shall be open to the plenum as a return air path. END OF SECTION MARCH 16, 2011 - ADDENDUM #1 KING SPRINGS ELEMENTARY SCHOOL RENOVATION AND ADDITION – 20100358 CCSD PROJECT NO. 224/8032 BW&A 10958 SECTION 15840 - 1 DUCTWORK SECTION 15840 DUCTWORK PART 1 - GENERAL 1.1 1.2 DESCRIPTION A. All work specified in this Section is governed by the Mechanical General Section 15010. B. This Section 15840 and the accompanying drawings cover the provisions of all labor, equipment, appliances, and materials and performing all operations in connection with the construction of the ductwork systems as specified herein and as shown. These systems include, but are not limited to, the following: Supply air ductwork 2. Return, transfer and relief air ductwork 3. Exhaust ductwork 4. Outside air ductwork INTENT A. 1.3 1. It is the intent of this Section of the specifications to provide a complete operable duct system as shown and specified which is reasonably airtight, free of noise, vibration and sweating, and fabricated so as to fit into the space allotted and to exhibit a minimum resistance to airflow. DESIGN AND CONSTRUCTION A. Ductwork shall be provided in strict accordance with the first edition - 1985 - of the SMACNA HVAC Duct Construction Standards - Metal and Flexible, NFPA No. 90A, 90B, 91 and 96, and UL 181. B. Ductwork dimensions shown are net, clear, inside dimensions with no allowance shown for duct liner. All ductwork specified to be lined shall be 2" larger than shown in each dimension to compensate for the liner. Ductwork shall be square, rectangular, round, spiral or flat oval as noted. Conversion of duct shapes and sizes shown shall be accomplished without increasing air velocities or friction losses and is subject to prior approval by the Architect. C. Elbows shall be either full radius type (inside radius equal to duct width), five-gore radiused flat-oval type or, in low pressure systems only, mitered with double-thickness turning vanes. D. Abrupt changes in duct sizes and shapes shall not be permitted. The total angle of diverging transitions shall be not more than 15 degrees; converging transitions shall be not more than 30 degrees unless otherwise noted or required due to structural SECTION 15840 - 2 DUCTWORK E. MARCH 16, 2011 - ADDENDUM #1 KING SPRINGS ELEMENTARY SCHOOL RENOVATION AND ADDITION – 20100358 CCSD PROJECT NO. 224/8032 BW&A 10958 constraints. Offsets, transitions, rises and drops are not individually called out on the design drawings. They shall be provided as required to fit the ductwork into the allocated spaces. F. Transition rectangular ductwork on bottom and sides. Maintain top of ductwork level and as high as possible. G. Provide the following types of ductwork material for the services indicated: TYPE OF MATERIAL SERVICE 1. Supply, return, exhaust and relief of comfort conditioned and outside air. Galvanized sheetmetal PART 2 - PRODUCTS 2.1 GALVANIZED SHEETMETAL A. 2.2 Galvanized sheetmetal shall be lock-forming grade G90-ASTM A 525 hot dip galvanized steel sheets. Sheetmetal shall be galvanized on each side with not less than 1.25 ounces of zinc per square foot. DAMPERS B. Manual Volume Dampers 1. Single blade butterfly dampers are acceptable up to 12" round or 12" x 12" square. Dampers larger than these dimensions shall be multi-blade type. Single blade dampers shall be constructed of 16 gauge or heavier galvanized sheetmetal. 2. No multi-blade damper blade shall exceed 8" in width. All multiple blade dampers shall be constructed of 16 gauge galvanized steel or heavier. The damper frame shall be 16 gauge or heavier. The damper action shall be opposed-blade type. 3. Each blade shall pivot on a 1/2" cadmium plated, cold-rolled steel axle which pivots within self-lubricating, oilite bronze bearings. 4. The top and bottom edges of each rectangular damper blade shall be crimped for stiffness. 5. The operating rod for all dampers shall be extended outside the damper frame for attachment of an operator. Each operator shall have a position indicator and locking quadrant. 6. All dampers utilized for introduction of outside air shall have flexible, gasketed edge and end seals. The leakage rate shall be less than 4 CFM per sq. ft. of face area against a 1" W.G. differential pressure, based on a nominal 48" x 48" MARCH 16, 2011 - ADDENDUM #1 KING SPRINGS ELEMENTARY SCHOOL RENOVATION AND ADDITION – 20100358 CCSD PROJECT NO. 224/8032 BW&A 10958 SECTION 15840 - 3 DUCTWORK damper size. 7. C. Control Dampers 1. D. Smoke dampers shall be UL-listed as Class 1 low-leakage smoke dampers and shall be products of Prefco or Nailor. LOW-PRESSURE DUCT BRANCHES A. 2.4 Fire dampers shall be UL-listed and labeled for 1 1/2 hours and shall be provided with 160 degrees F. links. Dampers installed within ducts shall be Type B or Type C with the blades out of the air stream. Areas indicated shall be net, clear, open areas. Smoke Dampers 1. 2.3 Control dampers shall be of the same construction as manual volume dampers, except that no manual operator and quadrant is required. The operating rod shall be suitable for operation by an automatic pneumatic or electric operator. Fire Dampers 1. E. Manual volume dampers shall be as manufactured by Louvers & Dampers, Inc., Nailor, or an approved equal. Splitter dampers shall be provided at all low-pressure ductwork branches. All lowpressure ductwork branches shall be radiused or 45 degree take-offs; straight taps are unacceptable. The length of the damper blade shall be the same as the width of the widest duct section at the split, but in no case shall blade length be less than 12". Each operator rod shall have a locking swivel joint. FLEXIBLE DUCT A. Flexible ductwork shall be Class 1, UL 181 air duct and meet NFPA 90A and 90B Standards. B. The internal duct surface shall be acoustically rated, black CPE bonded to a coated steel wire helix. The external jacket shall be a fiberglass, bi-directionally reinforced, metallized vapor barrier with a standing, triple ply seam. Fiberglass insulation shall be provided between the duct surface and the jacket to achieve a maximum thermal conductance of 0.23 BTU/Hr./sq. ft./degree F. at 75 degrees F. mean. C. Flexible ductwork shall be suitable for 10" W.G. positive pressure and 1" W.G. negative pressure. D. Flexible ductwork, insulation and insulation cover shall be suitable for ceiling return air plenum installation and shall comply with all applicable codes and standards regarding such ceiling plenum installations. E. Flexible duct shall be Thermaflex M-KE, Atco, or an approved equal. SECTION 15840 - 4 DUCTWORK F. G. 2.5 2. 4'-0" on medium and high-pressure supply air systems limited to the runouts from the sheetmetal ductwork to each terminal unit. 3. 2'-0" on connections from round neck grilles to sheetmetal ductwork on return, exhaust and transfer ductwork. Provide a spin-in fitting with integral scoop and volume damper at all flexible run-out connections in low-pressure supply air ductwork only. Provide flexible duct connections at the inlet and outlet of each belt-driven fan, indoor unit, fan coil unit, air handling unit, etc., and at all other locations indicated. Flexible connections shall be fabricated from a glass fabric coated on both sides with neoprene. Minimum weight shall be 30 oz. per sq. yard. Duct hardware shall be as manufactured by Young Regulator or an approved equal. A duct access door shall be provided at each fire damper. Access doors shall be designed for 1.5 times the pressure of the duct in which they are mounted. Access doors shall be of sufficient size to provide access to the dampers for resetting the blades and replacing the links. Access doors in medium and high-pressure ductwork shall be installed downstream of fire dampers and shall be implosion type. Where access is provided through gypsum board walls or ceilings, furnish access door for installation under Division 9. Each door shall match the fire-rating of the wall or ceiling indicated. DUCT LINER A. 2.9 5'-0" on low-pressure supply air systems limited to short runouts and end of runs connected to round neck supply diffusers and registers. ACCESS DOORS A. 2.8 1. DUCT HARDWARE A. 2.7 The maximum allowable installed length of flexible ductwork shall be as follows: FLEXIBLE CONNECTIONS A. 2.6 MARCH 16, 2011 - ADDENDUM #1 KING SPRINGS ELEMENTARY SCHOOL RENOVATION AND ADDITION – 20100358 CCSD PROJECT NO. 224/8032 BW&A 10958 Duct liner shall be one inch thick, 1 1/2 lb. density (3 lb. density on medium- and highpressure supply air systems) fibrous glass with one face coated with a black fire retardant compound. The permanent composite fire and smoke hazard rating of the liner shall be stenciled on the liner face and shall be: 1. Maximum flame spread 25 2. Maximum smoke developed 50 DUCT INSULATION A. Duct insulation shall be 2" thick, minimum 3/4 lb. density fiberglass with an FSKL MARCH 16, 2011 - ADDENDUM #1 KING SPRINGS ELEMENTARY SCHOOL RENOVATION AND ADDITION – 20100358 CCSD PROJECT NO. 224/8032 BW&A 10958 SECTION 15840 - 5 DUCTWORK 0.00035" thick aluminum foil jacket, reinforced with fiberglass scrim. Thermal conductivity shall be a maximum of K = 0.24 at 75 degrees F. mean temperature. B. Insulation adhesive shall be Benjamin Foster 85-20. Tape shall be aluminum foil and shall be SMACNA listed and labeled. C. The composite NFPA 90A and 90B, ASTM E84, UL rating of the installed insulation shall not exceed 25/50. PART 3 - EXECUTION 3.1 INSTALLATION A. Ductwork shall be installed in strict accordance with SMACNA, UL and NFPA standards. B. Duct liner shall be provided for the following minimum distances or through the first elbow(s) or as otherwise indicated on the drawings, whichever is greater, downstream of each unit indicated below: 1. Packaged rooftop unit 25 feet Duct liner shall also be provided throughout all return air, transfer and plenums. Note: All ductwork above music rooms shall be lined. C. Duct liner shall be cut to provide overlapped and compressed longitudinal corner joints. Liner shall be installed with the coated surface facing the air stream. Duct liner shall be adhered to the ductwork with a 100% coverage of the sheet metal surfaces using a fire retardant adhesive applied by spraying. Coat all exposed leading edges and all transverse joints with fire retardant adhesive. The liner shall be additionally secured using metal pins welded to the duct and speed washers. All leading edges shall be secured with sheet metal airfoils. D. All supply air ductwork which is not lined shall be insulated. All outside air ductwork shall be insulated. Insulation shall be cut slightly longer than circumference of duct to insure full thickness at corners. All insulation shall be applied with edges tightly banded. Insulation shall be adhered to duct with fire resistant adhesive. Adhesive shall be applied so that insulation conforms to duct surfaces uniformly and firmly. In addition to the adhesive, the insulation shall be additionally secured to the bottom of all ducts 18" or wider by means of welded pins and speed clips. The protruding end of the pins shall be cut off flush after the speed clips have been applied. The vapor-barrier facing shall be thoroughly sealed with tape where the pins have pierced through. All joints shall be sealed with 2" wide SMACNA tape. Any cuts or tears shall be sealed with SMACNA tape. E. Flexible ducts utilized in the low-pressure ductwork systems shall be installed without kinks or bends which are less than a centerline radius equal to or greater than twice the diameter of the flexible duct being installed. END OF SECTION