Interim Advice Note (This Document will become a new separate Section within the upcoming revision of the DMA Roadway Lighting Specification) Solar Street Lighting Specification Revision 0 18th July 2013 Contents Clause Section Page 1........... Executive Summary................................................................................... 2 2........... Solar Street Lighting System Types........................................................... 3 3........... General...................................................................................................... 5 4........... Project Economic Cost Analysis................................................................ 6 5........... Applicable Standards & Guidance Documents.......................................... 7 6........... System Components................................................................................. 11 6.1 LED Luminaires...................................................................................... 11 6.2 PV-Pole System..…..…………………………..............................……….. 12 6.3 Inverter/Controller.....…………………………..……………….………….... 15 6.4 Batteries…………………………...……….….........................…………... 16 6.5 Controls………………………………………..........………….…………….. 17 6.6 Cleaning System…………………………..........………….…....………….. 17 7........... Pole Assembly........................................................................................... 18 8........... Pole Design Submission and Production.................................................. 19 9........... Quality Assurance..................................................................................... 20 10......... Warranty and Maintenance Cover............................................................. 20 10.1 Warranty............................................................................................... 20 10.2 Maintenance/Defects Contract Period ……………..................……….. 21 11......... Measurement and Payment...................................................................... 21 12......... Operation and Maintenance...................................................................... 22 Revision 0 Page 1 18th July 2013 Solar Street Lighting Specification All use of “The Department” in the following clauses refers to The Municipality of Abu Dhabi City*. *Note: If this document is used as a brief for projects outside the ADM Municipal area, “The Department” would therefore refer to the relevant Municipality and/or Transport Authority for the project and area. The local authority applicable standards and/or guidance documents listed under clause 3.1 would therefore all need to be assessed under direction from the other authority and amended as necessary. 1. Executive Summary The technical brief criteria within this specification have been established after access to over four years of on-site test data from various different solar street lighting technologies within Abu Dhabi and the UAE. From these results, has come the evidence of which types of technologies are viable as long-term sustainable solutions for use on Abu Dhabi street lighting projects and which are not viable. Therefore there are some key factors for the specific criteria for solar street lighting, the main critical points of which, as set out within the clauses of this Specification, can be summarised as follows: 1.1 Required/Permitted under this Specification a) b) c) d) e) f) g) h) i) j) k) l) m) n) o) Revision 0 Vertically-mounted pole-integrated solar PV systems only Monocrystalline or Polycrystalline silicon wafer PV construction VRLA or Gel Lead Acid and Nickel Metal Hydride (NiMH) battery technologies Solar standalone solutions or grid-connected system options Wind-generation components only as an addition to solar PV and with full material, maintenance and efficiency data provided Batteries mounted above ground within the base of the pole system Batteries mounted below ground within the concrete foundation of the pole system Standalone systems with batteries to have minimum 2-days autonomy LED (or similar) lighting fixtures complying fully with the requirements of the DMA Roadway Lighting Specification Standalone or grid-connected project solar lighting control/operation fully interlinked via wireless PLMS (Project Lighting Management System) Minimum 5-year full on-site combined maintenance and defects cover in addition to the standard warranty requirements Full project cost analysis including payback Provision of Operation and Maintenance Manual Cleaning Proposal including the equipment as part of the project system provision Environmental Policy Proposal for battery and component recycling/disposal Page 2 18th July 2013 1.2 Not Permitted under this Specification a) b) c) d) e) f) g) h) i) j) k) l) m) Pole-top or side mounted flat PV-panel solar systems Open ‘wet-type’ Lead Acid, or other battery technologies to those listed in clause 1.1 Batteries mounted above ground at high-level on the pole system Batteries mounted below ground within separate battery enclosure/pits LED (or similar) lighting fixtures not complying fully with the requirements of the DMA Roadway Lighting Specification Any claim for “self cleaning” PV panels and/or unjustified maintenance factors provided to include for dust accumulation Any in-built mechanical/electrical automated cleaning mechanism or apparatus Any wind-generation devices without full test data to prove long-term viability and sustainability Standalone project solar lighting individual pole (non-interconnected PLMS) operation System approval unless full cost analysis provided and checked/approved by The Department Any non-site specific sun-availability criteria used in calculations/analysis Any deviation from the system technical criteria as set out within this Specification Any deviation from the minimum maintenance and warranty requirements as set out within this Specification 2. Solar Street Lighting System Options 2.1 There are three viable solar street lighting system options available for consideration for a project. A. Standalone – No grid-connection, standalone vertical PV-poles with integral batteries, controller/inverter and wireless PLMS. For solar street light projects: Without existing substation/cabling/infrastructure Or with existing cabling/infrastructure, but unsuitable for utilisation Or where new cabling may not be commercially feasible The battery is installed within the solar PV-clad pole base or in a separate, concrete foundation-located formed battery enclosure. The standalone PV-pole’s controller/inverter controls the charge and discharge of the battery, the battery status and the status of the solar pole PVs. A wireless type PLMS provides and controls the power for the light fitting, including coordinated activation, dimming and status of the lights. Revision 0 Page 3 18th July 2013 B. Grid Connected – Electric grid-connection, vertical PV-poles without batteries, with controller/inverter and wireless PLMS. For solar street light projects: With existing substation/cabling/infrastructure Or where new cabling may be commercially feasible The grid-connected pole’s controller/inverter during the daytime converts the solar energy via the PVs from DC to AC and feeds it to the power grid. During the night, the pole and LED fixture work like any other conventional street light, with the required energy for lighting taken from the power grid. A wireless type PLMS provides and controls the power for the light fitting, including coordinated activation, dimming and status of the lights. Ideally, the design of the system would ensure more energy from the solar PVs is produced during the day than required for lighting the LED fixture during the night. Excess energy can be used for its own purposes or could be sold/credited in the future. C. Full Backup – Electric grid-connection, vertical PV-poles with integral batteries, controller/inverter and wireless PLMS For solar street light projects: With existing substation/cabling/infrastructure Or where new cabling may be commercially feasible Or for areas with infrastructure, but susceptible to power outages Or for a project where maximised efficiency of power generation is desirable Or for a project where 100% assurance of illumination is always essential Solar energy generated from the PVs during the day is stored in a battery. Once the battery is charged, excess solar generated energy is converted from DC to AC and fed into the power grid. The battery is installed within the solar PV-clad pole base or in a separate, foundation- located formed battery enclosure. During the night, the pole and LED fixture can be designed to work in one of two ways: Either like any other conventional street light, with the required energy for lighting taken from the power grid. Then in the case of power outage, the system switches immediately to the battery backup. Or, the required energy for lighting taken solely from the battery with the grid used as a back-up in the event of the battery failing or discharging fully before daytime. A wireless type PLMS provides and controls the power for the light fitting, including coordinated activation, dimming and status of the lights. Revision 0 Page 4 18th July 2013 With a system such as this the autonomy and thus size of the battery could be relaxed from the normal Specification’s requirements as part of the overall system design. Excess energy can be used for its own purposes or could be sold/credited in the future. 2.2 The decision about which system option is best considered for a project can be determined primarily by what level of existing street lighting electrical infrastructure is present for the project. The site-specific infrastructure as far as a local sub-station being either present or not present is another primary consideration; also if planned for a defined or undefined future date or present but lacking sufficient capacity. Even if local substation and capacity is available, but there is no existing street lighting electrical infrastructure currently in place (sub-mains distribution, lighting control cabinets, final circuit cabling etc.) this can have a further implication. A project area might indeed have both full infrastructure and capacity in place, but other factors such as a client’s paramount need to ensure illumination is maintained at all times or any area is subject to, or has a history of, power outages, may be an issue. The main factors for consideration have been suggested in this section; however there may be other factors to determine the best system for a specific project. All these factors all need to be weighed up when deciding on the most appropriate system option to consider and propose through the project cost analysis. 3. General 3.1 The design, specification, calculation, manufacturing, testing, shipment, installation and performance of Solar and LED (or similar) lighting systems shall be in accordance with the applicable requirements of all The Department’s civil, electrical, mechanical and lighting standards for electrical distribution works, except as specified herein. Copies should be requested from The Department if not already held. 3.2 The Project’s lighting design and luminance level requirements and the LED (or similar) street lighting luminaires shall be fully in accordance with the requirements of the DMA Roadway Lighting Specification. Submissions for the project made to the Department must include all the usual proof of compliance; lighting calculations, layouts, compliance checklist, luminaire/lampsource/gear data and all accredited test sheets to show the requirements of the DMA Lighting Roadway Lighting Specification have been met fully. Revision 0 Page 5 18th July 2013 3.3 The Consultant and manufacturers shall guarantee adherence to this Specification and the performance of the Solar Pole, system and LED (or similar) luminaire under all the required design conditions. 3.4 The Consultant shall be responsible to ensure that the project and product specifications are fully in compliance, without any deviation from this Specification prior to forwarding to The Department for approval. Any deviation should be brought to the notice of The Department. The Consultant shall ensure in his design the following: integration, coordination, functionality and accessibility of these services. It shall be the Consultant’s responsibility to bring the system to the design & operating and maintenance conditions. 4. Project Economic Cost Analysis 4.1 The Consultant shall, as requested by The Department, provide full cost analysis including payback assessments as required for the project solar proposal(s) and in accordance with the instructions given by The Department. The full life cycle cost analysis asset comparison shall be undertaken to the BS ISO 15686-5 Supplement (Publicly Available Specification - published by the British Standards Institution) or similar and cover parameters which fully meets the requirements of this specification. All information provided and the cost analysis/payback calculations should be calculated with the exact required LED (or similar) lighting fixture, driver/load, solar equipment, battery, inverter, autonomy and site position (sun availability). The Economic Cost Analysis should include the following parameters and allowances: a) Compare the solar proposal(s) against the base standard of LED (or similar) as per the DMA Roadway Lighting Specification, with standard non-solar poles as per the project’s brief requirements and electrical infrastructure matching the site’s existing constraints b) Compare project specific Initial Capital Expenditure (CapEx) costs. c) Compare project specific Annual Operational Expenditure (OpEx) to include electricity usage and maintenance cost allowances. d) Compare long-term total costs over minimum of 10-years based on present value cost assessment including initial CapEx, annual OpEx and future CapEx for required component replacement. e) Compare Salvage Value of the system at the end of the study period. f) Revision 0 Include all justifications of given and calculated values and timescales with annotation and supporting data where applicable. Page 6 18th July 2013 g) Provide the calculated Payback Period (if applicable) for the solar proposal(s) against the base LED conventional approach h) Provide report and output graphs/tables as required to present project data clearly. i) Include also average ‘per-pole’ cost comparisons of all options within report findings. j) Allow for 0.35fils/kWhr. As per the Average Economic Cost of Electricity; taken from the DMA Sustainable Lighting Strategy. k) Allow for 11-hours per night, 365-days a year luminaire operation. l) Allow for load of actual luminaire, with actual driver/current including all losses as per the fixture’s LM-79 report or similar accredited laboratory test. m) Allow for stated average useful life of all components in the long-term analysis, and salvage analysis, including, but not limited to, the luminaire, driver, inverter, battery, control components, cables, PV-panels/modules, pole, base and associated synthetic and metal materials. n) For any solar grid-connected systems for which the poles have no batteries, but connect to a conventional grid, generate electricity in the daytime and run conventionally at night time, provide justified figures based on the local environment and actual site situation on assessed generation value used in the analysis. o) Use an annual discount rate of 7% for the long-term Present Value analysis unless confirmed otherwise by The Department p) Allow for dimming savings in the analysis only if included within the project proposal(s) and then only pro-rata as per the exact dimming settings proposed and justified. q) If local infrastructure is present or not present this should also be factored into the analysis for cost comparison purposes including, as applicable, local sub-station provision, sub-mains distribution, lighting control cabinets, final circuit cabling, protection, civil works and connections. 5. Applicable Standards & Guidance Documents The following documents (or equivalent International approved documents) shall be followed. Versions listed shall be superseded by updated versions as they become available. 5.1 Abu Dhabi Standards: .1 Revision 0 DMA Lighting Specification for Roadway/Parking, Tunnel/Underpasses, Lighting Poles & Public Lighting Management System - Rev.01 1st November 2011. (Referred to also as the DMA Roadway Lighting Specification). Page 7 18th July 2013 5.2 5.3 5.4 .2 The Department’s Sustainability Guideline Standards. For ADM, the IRI Sustainability Guideline Standard 2010 .3 ESTIDAMA - Community Pearl Rating System .4 UPC - Utilities Design Guidelines: Public Realm Design Manual (PRDM) & Urban Street Design Manual (USDM). .5 The Department’s Electrical Standards. For ADM, the Standard Specification Sections XVI-14 - Lighting and Electrical Distribution Works .6 The Department’s Civil, Mechanical and Material Standards. For ADM, the Standard Specification Sections I to XIII .7 The Department’s Standards for tree/lighting-pole safety clear-zone safety setting-off distances. For ADM, Interim Advice Note 01/308/06/2011 Maintenance: .1 IESNA DG-4-03 Design Guide for Roadway Lighting Maintenance. .2 CIE154:2003 The Maintenance of outdoor lighting systems Solar PV Systems and Components: .1 IEC 61215 Crystalline Silicon Terrestrial Photovoltaic (PV) Modules – Design Qualification and Type Approval .2 IEC 61646 Thin-Film Terrestrial Photovoltaic (PV) Modules - Design Qualification and Type Approval .3 IEC 61730 Photovoltaic (PV) Module Safety Qualification – Part 1: Requirements for Construction .4 IEC 62093 Balance-of-System Components for Photovoltaic Systems - Design Qualification Natural Environments .5 IEC 60050 International Electrotechnical Vocabulary (IEV) .6 ISO 9488 Solar Energy – Vocabulary .7 ASTM E772 Standard Terminology Relating to Solar Energy Conversion Batteries: .1 IEC 60050 (IEV) Chapter 486: Secondary Cells and Batteries .2 IEC 60086-1 BS 387, Primary Batteries – General .3 IEC 60086-2 BS, Batteries – General Revision 0 Page 8 18th July 2013 5.5 .4 IEC 60896-1, EN 60896-1 Stationary Lead Acid Batteries, Vented Types: General Requirements and Methods of Test .5 IEC 60896-2, EN 60896-2 Stationary Lead Acid Batteries, Valve-Regulated Types (VRLA): General Requirements and Methods of Test .6 IEC 60896-21, EN/IEC 60896-21 Stationary Lead Acid Batteries, ValveRegulated Types: Methods of Test .7 IEC 60896-22, EN/IEC 60896-22 Stationary Lead Acid Batteries, ValveRegulated Types: Requirements .8 IEC 61951-2 Ed. 3.0 b:2011, BS EN 61951-2:2011 Secondary cells and batteries containing alkaline or other non-acid electrolytes - Portable sealed rechargeable single cells - Part 2: Nickel-metal hydride Life-Cycle Cost Analysis: .1 5.6 5.7 Supplement to BS ISO 15686-5 - Standardized Method of Life Cycle Costing for Construction Procurement Mechanical: .1 Degrees of Protection Provided by Enclosures (IP Code for ingress protection and IK Code for Mechanical Strength): IEC 60529 (IP) and IEC 62262 (IK). .2 Testing of Materials: i. ASTM B 117-07a Standard Practice for Operating Salt Spray (Fog) Apparatus, 2007 and ASTM D1654 - 08 Standard Test Method for Evaluation of Painted or Coated Specimens Subjected to Corrosive Environments, or ii. ISO International Organization for Standardization. ISO 9227 Corrosion tests in artificial atmospheres—Salt spray tests, 2006. iii. ISO8289A: Low voltage test for detecting and locating defects iv. ISO 4892-1: Plastics -- Methods of exposure to laboratory light sources Electrical: .1 Electrical Safety - General and for Road Lighting Luminaires: EN 60598-parts 1, 2-1 & 2-3 .2 Electromagnetic Compatibility: i. EN 61547, EN 61000-3-2, EN 61000-3-3 & EN 55015 (CISPR-15) – for (Immunity Requirements, Harmonics Requirements, Flicker Requirements & Radiated and Conducted Emissions, respectively). ii. ANSI C82.77-2002 - Harmonic Emission Limits & IEEE Std 519 1992 Harmonic Limits iii. FCC 47 CFR Part 15 Radio Frequency Devices Revision 0 Page 9 18th July 2013 .3 5.8 RoHS Directive 2002/95/EC, on the restriction of the use of certain hazardous substances in electrical and electronic equipment Lighting Design/Project Setting Out (In addition to the standards/guidance already listed within the DMA Roadway Lighting Specification): .1 Road: i. IESNA RP-8-00 (Roadway Lighting) ii. CIE 115 - 2010(Lighting of Roads for Motor and Pedestrian Traffic) iii. BS 5489-1(Code of Practice for Design of Road Lighting), BS EN 132012 (Road Lighting – Performance Requirements),13201 - Road Lighting ME/MEW Classes .2 Bridges: iv. IESNA RP-8-00 (Roadway Lighting) v. CIE 115 (Lighting of Roads for Motor and Pedestrian Traffic) vi. EN 13201 - Road Lighting ME/MEW Classes vii. BS 5489-1(Code of Practice for Design of Road Lighting), BS EN 132012 (Road Lighting – Performance Requirements) .3 Roundabouts: viii. IESNA RP-8-00 (Roadway Lighting, Conflict Area) and DG-19-08 (Design ix. Guide for Roundabout Lighting) x. CIE 115 (Lighting of Roads for Motor and Pedestrian Traffic) – Zones of Conflict xi. EN 13201 – Road Lighting CE Classes xii. BS 5489-1(Code of Practice for Design of Road Lighting), BS EN 132012 (Road Lighting – Performance Requirements) .4 Pedestrian Crossings: xiii. IESNA RP-08-00 (conflict Areas and Interaction) and DG-5-94 (Recommended Lighting for Walkways and Class I Bikeways xiv. CIE 115 (Lighting of Roads for Motor and Pedestrian Traffic) xv. EN 13201 – Road Lighting EV Classes xvi. BS 5489-1(Code of Practice for Design of Road Lighting), BS EN 132012 (Road Lighting – Performance Requirements) .5 Interchanges: xvii. IESNA RP-8-00 (Conflict areas) xviii. CIE 115 (Lighting of Roads for Motor and Pedestrian Traffic) – Zones of Conflict xix. EN 13201 - Road Lighting CE Classes xx. BS 5489-1(Code of Practice for Design of Road Lighting), BS EN 132012 (Road Lighting – Performance Requirements) .6 Revision 0 Parking: xxi. IESNA RP-20-98 (Parking Lot and Parking Garages) xxii. CIE 129(Guide for Lighting Exterior Work Areas) xxiii. CEN 13201 – Road Lighting S Classes Page 10 18th July 2013 xxiv. BS 5489-1(Code of Practice for Design of Road Lighting), BS EN 124642(Lighting of Work Places - Outdoor Work Places) 6. System Components 6.1 LED Luminaires .1 The design, specification, calculation, manufacturing, testing, shipment, installation and performance of LED lighting system (or other equally sustainable technology) shall be in accordance with the applicable requirements of all The Department’s electrical and lighting standards for electrical distribution works, except as specified herein. Copies should be requested from The Department if not already held. .2 Lighting fixtures must be LED (or similar), fully in accordance with the requirements of the DMA Lighting Specification for Roadway/Parking, Tunnel/Underpasses, Lighting Poles & Public Lighting Management System Rev.01 1st November 2011. (Referred to also as the DMA Roadway Lighting Specification). .3 The Consultant shall note that all lighting calculations for parking lots/areas adjacent to roads must take into account the road lighting contribution into the parking lighting design and vice-versa. All projects shall be undertaken, checked and approved as the responsibility of the Consultant to meet the required roadway and parking levels as set out in the DMA Roadway Lighting Specification. .4 The Consultant and Manufacturers shall ensure all luminaires are fully compatible with the Solar PV Pole system, the fixture driver, the solar pole inverter/controller, PLMS and components to meet all the overall design requirements. .5 All luminaire drivers must be specified correctly to have suitable inputs for the solar system’s (usually12 or 24v) DC output from the battery/inverter/controller. .6 Some systems may negate the need for a driver with the fixture entirely as the driver current function forms part of the inverter/controller equipment. Refer also to clause 6.3 to see details about the inverter/controller .7 All luminaire test data and supporting information must be provided with the specific driver specification used. Revision 0 Page 11 18th July 2013 6.2 PV-Pole System .1 General The pole for the solar street lighting system shall only be of the vertically integrated PVclad variety. Herein referred to as PV-Poles or PV-Poles Systems. Separate flat design PV panels mounted on the top of, or offset from, a standard pole are not permitted for use on The Department’s street lighting projects. Flat PV panels are not acceptable due their high maintenance requirements, inherent dust accumulation issues, high wind-loads, aesthetic concerns and cleaning issues regarding both dirty water falling onto parked vehicles and a potential for breach of privacy laws in residential areas. All PV-poles shall be of a type that can accommodate a variety of applications. The PVpole shall be either circular or square in cross-section, made up of an extruded aluminium or steel mast that enables proprietary accessories, as required by the project, to be mounted at set distances along its length at heights and positions coordinated within the PV sections. The finish colour and design of the PV-pole and accessories shall be as agreed with The Department for the project. Minimum Ingress Protection ratings for the PV-pole system: Mast component - IP40, IK-07 PVs and electrical components – protected to IP66 Glass components IK-08 Batteries – IP44 Battery housing above ground within pole-base – IP66, IK-07 Battery housing foundation-mounted – below-ground – IP68, Battery housing foundation-mounted cover plate – IP67, IK-10 Revision 0 Page 12 18th July 2013 .2 Materials a) Foundations. Structural analysis shall be submitted to show that the foundation design meets the load of the given PV-pole type in its “Fully Loaded” state. Unless otherwise stated it is assumed the pole will sit above ground on a 100mm bed on non shrink grout. For all standard foundations and/or foundations designed to house a chamber for below ground mounting of a solar battery, full design details shall be submitted for The Department’s review and approval. Special design details shall also be submitted by the Contractor to install the poles above any tunnel structures. Where batteries are to be located below-ground, only a Battery Foundation: a battery pit constructed as part of the concrete foundation is permitted. This is to ensure the maximum physical protection of the pit and pit cover from damage. No remote battery pit enclosures are permitted on The Department’s projects The Two-Types of Permitted Solar PV-Pole Foundations Example of Typical Concrete Foundation Example of Typical Battery Foundation b) Service Hatch(es), Each pole shall have its necessary service hatch(es) positioned no lower than 400mm from finished ground level where all required electrical and solar components and connections are accessible. For a system where the connection of grid cables is required, a minimum of two hatches are required, a lower service hatch must meet The Department’s standards so electrical connections can be made between the outside network and the pole accessories as per normal pole design and work practices. The lower service hatch shall be used for street lighting and the remaining one(s) for the solar equipment. The service hatch(es) shall be accessible without removing the cover plates or cladding from the pole bases. Cover plates shall be fixed by two screws. The service hatches or hand hole covers shall be fixed with hinges made of corrosion resistant materials such as Revision 0 Page 13 18th July 2013 stainless steel grade 316(A4), brass, hot-dip galvanized steel, etc. as applicable based on the PV-pole and cover plate material and shall be lockable with padlocks complying with The Department’s standard specifications. As required by the project the hatch(es) shall house general purpose outlets (GPO) that can be accessed through an external lockable hatch. Hatch door keys shall be supplied as per The Department’s requirements. c) Foundation conduits. Electric conduits shall be installed through foundation and shall enter the PV-poles from the base plate. Regardless of which solar system type the project has, even if it is a standalone (battery) system, these conduits are required to be installed always for cabling entry purposes for both present and future needs to avoid any potential future remedial works to the foundations to be incurred. d) Steel work. PV-poles’ steel work shall be manufactured out of BS grade S355 steel for 10-14m poles or as appropriate to a pole of lower height. Hot dipped galvanizing (100 Microns minimum coating thickness) surface treatment shall be applied to both internal and external surfaces. The base plate shall be in accordance with The Department’s standard specifications. All additional fixtures (Fixture Type-1, Fixture Type-2, and Fixture Type-3) shall be on steel attachments of BS Grade S275 with hot dipped galvanizing (100 microns minimum). Base plate shall be manufactured as specified on the Drawings. Where steelwork is in contact with aluminium work, the manufacturer shall ensure that bi-metallic corrosion is prevented by means approved by The Department. e) Aluminium work. PV-poles’ aluminium shall be made up of extruded aluminium alloy (EN AW6005/6063/6082-T6) which shall have an anodized protective coating finish to 25 microns. The colour of the anodized finish shall be as approved by The Department. Any transition rim shall be of cast aluminium alloy of grade LM6 having coating of minimum 100 microns of polyester powder coating, type PE-SDF matching the approved colour of the anodized extruded aluminium. f) Photovoltaics (PVs). All photovoltaic components shall be either Monocrystalline or Polycrystalline silicon wafer types manufactured, tested and installed as per the respective International standards listed under Clause 5.3 of this Specification. The lowest level of the PVs on the PV-pole shall not be less than 3m from finished ground level for the 10 or 14m poles to ensure they are out of reach of the general public. g) Wind Generators. Wind-generation components are only permitted as a potential additional option to solar PV and must be proposed with full material, including maintenance requirements and justified lifetime efficiency data for The Department to consider their viability. For Warranty purposes they must be considered to meet the same requirements as the PV modules. Revision 0 Page 14 18th July 2013 h) Synthetic Materials. All synthetic materials including translucent (non-glass) PV covers shall be 100% UV Stable non-yellowing, environmentally resistant and scratch resistant. Laboratory test data shall be provided to The Department to prove the materials are resistant to deterioration. i) Bracketry and Base Plate Cover. Pole brackets and base plate cover shall be manufactured out of BS grade S275 Steel. This shall have high strength and finished to match the PV-pole. All steel components shall be hot-dip galvanized to a minimum thickness of 100microns and painted as per the applicable clauses of The Department’s standard specifications. The base plate cover shall be supplied along with the pole. j) Fasteners. All fasteners supplied shall be made of corrosion resistant materials such as stainless steel; - Grade 316, brass, hot-dip galvanized steel etc, based on the materials with which it will be in contact. Bi-metallic contact shall be properly designed to avoid any galvanic or bi-metallic corrosion. k) Electric Equipment. M8 x30 mm long threaded stud carrying two nuts and two washers shall be provided as an earth point. It shall be located within the lowest service hatch. The electrical termination cut-outs shall be supplied in accordance with the Supply Company’s (Street Lighting) requirements and as shown on the Drawings. Each pole as required shall be polyethylene rope (dia. 4mm) “draw wired” to assist in feeding electrical and service cables. l) Product Identification Tag. There should be a Name Plate affixed to the column in an appropriate location and manner to suit the column design and access which will give: a. Name of the Manufacturer or Distinctive Logo. b. Model Number c. Serial Numbers of all equipment d. Year of manufacture e. Separate battery details (where applicable for the system) m) Copper Content. All Aluminium Die-cast components shall have a very low copper content of less than 1%. 6.3 Inverter/Controller The inverter/controller controls the charge and discharge of the battery, the battery status and the status of the solar PV modules. The inverter/controller provides and controls the power for the street lighting fixture(s), including dimming and status.. Technical Requirements Selected for minimum 2-days autonomy operation (2-nights bad weather capability) Revision 0 Page 15 18th July 2013 Photovoltaic charge control for 24V DC batteries as per the project system requirements 24V DC output for powering LED fixture drivers Intelligent charging of Ni-MH or Lead-Acid batteries, battery charging 24V DC 0-10V DC dimming (optional PWM dimming 0-100%) Solar PV module input 10-24V DC Nominal input 230V AC (optional 120-277V AC if required for project) Can be combined with DC/AC inverter for grid system connection as required for the project Specified for the project assessed solar energy yield in combination with wattage of LED luminaire used, battery size and usage of dimming 130W max typical normal load (Input Power), options up to max 200W loads if needed Automatic Light Switching Light On/Off controlled by sunset/sunrise Automatic Light Level Calculation / Automatic Dimming functionality for bad weather situations based on calculated night length & energy available in batteries. If not enough energy available for whole night, can be programmed to be dimmed accordingly Operating Conditions Operating temperature: - 20°C to +60 °C Storage (non-operating) - 40°C to +80 °C 6.4 Batteries The type, size and quality of batteries specified shall be selected for their optimum performance and integration for the project specific requirements. Technical Requirements VRLA (Valve Regulated Lead Acid), Gel Lead Acid or Nickel Metal Hydride (NiMH) battery technologies Selected for minimum 2-days autonomy system capacity (2-nights bad weather capacity) 24V DC, Min 100Ah rated. 24V DC output for powering LED fixture drivers Expected Lifetime for the project design - 5-6 Years Guaranteed Lifetime for the project design - 5 Years 75 % of the rated capacity of the battery should be between fully charged and load cut off conditions. Manufactured, tested and installed as per the respective International standards listed under Clause 5.4 of this Specification. Mounted either in the PV-Pole base or below ground within concrete combined battery/foundation type Operating Conditions Operating temperature: - 20°C to +60 °C Storage (non-operating) - 40°C to +80 °C Revision 0 Page 16 18th July 2013 6.5 Controls Whether the Standalone, Grid-Connected or Full Backup type systems, the project solar lighting control/operation shall be fully interlinked via a wireless PLMS system. Technical Requirements Wireless, Wi-Fi, Cloud or RFI system fully tested and compatible with the solar system proposed (GSM 900/1800, GPRS, SMS, ZigBee etc.) Wireless communication complying with IEEE 802.15.4a The proposed system shall be fully compatible with the specified LED luminaire and driver proposed for the project and the inverter/controller Any brand of manufacturer’s LED luminaires shall be able to be controlled from the system to ensure luminaire choice can be made openly for the best current marketplace products available for the project. System interface/software to be password encrypted, able to program the project system and cater for revised programming settings for future if required System interface able to be interconnected to outside central system and control room in the future as and when required. 0-10V DC dimming (optional PWM dimming 0-100%) Light levels configurable at 1-10% step increments as required Remote Light Switching, automatic-programmed and manual override Standard & customizable light profiles for peak/off-peak times Individual Dimming Profiles, changeable according to weekly plans Automatic luminous flux reduction in case of consecutive bad weather periods to avoid light switch off Error Reporting - Comprehensive & instant overview about infrastructure problems like lamp/driver errors, battery errors, inverter errors per pole Energy Reports - Detailed daily overview about solar energy produced, energy consumed, energy fed to the grid, energy charged to battery, etc. Optional iPhone/iPad/Android mobile application interface for maintenance work at site – Basic status info and instant setting configuration via mobile phone, while on site Data Export for further in depth analysis or integration into existing inventory management systems operated by The Department Operating Conditions Operating temperature: - 20°C to +60 °C Storage (non-operating) - 40°C to +80 °C 6.6 Cleaning System To ensure optimum performance at all times, the PV-pole must be cleaned on a regular basis. To avoid dirty water falling onto parked vehicles and a potential for breach of privacy laws in residential areas, The Department requires a proprietary ground-level cleaning system solution and equipment to form part of the project proposal. It shall be purchased as part of the project. At the end of the maintenance period, and as and when determined by The Department, the cleaning equipment shall be handed to the Department to be retained and re-distributed as per The Department’s requirements. Revision 0 Page 17 18th July 2013 High pressure hose cleaning is not acceptable, nor are any automated/motorised systems on the PV-poles themselves and any solution should be based on the following parameters: Technical Requirements Cleaning must be undertaken using pure filtered water and no chemical additives A telescopic low-pressure hose and brush system enabling the operator to reach all PV surfaces from ground level Water supply transportable via a truck/trailer with low-pressure electric pump Minimum 100m hose Minimum 10-14m telescopic pole (as per project PV-pole requirements) Soft brush designed specifically for PV applications to avoid damage and scratches to the PV module clear covers Cleaning Cycles Average time to fully clean a single PV-pole should be 4-5minutes It should be able to operated by a single person PV-Poles should cleaned initially once a month However, the specific long-term cleaning cycle is to be defined after the first 6months of operation, where energy yields can be analysed and compared by the PLMS against the degree of dust accumulation on the PV-panels for the site specific project location. If assessed as satisfactory the cleaning cycle beyond the initial 6-months can be reduced to 2 or 3 months as appropriate. 7 Pole Assembly a) Assembly of PV-pole. The pole shall be complete with all accessories and all necessary component assembly undertaken at the factory. The final assembly of pole and components shall be ready for installation at site without any works required other than using suitable fixing tools. b) Mast arm for the Luminaires. The mast arm for the luminaire shall manufactured by the PV-pole manufacturer for the required length and fitted to the pole at the factory for the correct orientation of the pole and PV panel sections for the project locations. The attachment of the mast arms shall be made of standard fasteners (DIN M60 or similar) through the structural casting without any detriment to the PV-pole’s IP rating. As per The Department’s lighting design requirements as set out within the DMA Roadway Lighting Specification, mast arm heights of approximately 10m should be provided for projects normally requiring conventional 10m poles and 14m should be provided for projects normally requiring conventional 14m poles. Solar system options for projects designed with lower luminaire mounting heights, thus resulting in closer pole spacings and an increase in pole numbers on projects is not acceptable under normal circumstances unless justification can be provided. The mast arm shall be self-supporting against all forces including uplift, without the use of any guy wires unless approved by The Department. The luminaire shall be fixed to the Revision 0 Page 18 18th July 2013 mast arm and electrically wired. Finally the cable end shall be connected to the solar system inverter/controller as required by the system type at the service hatch(es) located in the pole base. c) Additional Assembly. If required by the project brief, provisions shall be made on the PV-pole for enabling the fixing of other accessories such as fixed arms for fabric banners, or CCTV cameras. These provisions shall allow for the planned accessories to be added without having to remove the existing installed accessories, luminaire brackets or the like. The provisions shall be such as to ensure the clean, aesthetic look is maintained, the solar-collecting capability of the PVs to not be compromised. If required these provisions shall be designed to allow for complete dismantling, when not in use, without leaving behind any clamps, lugs, etc... d) Pole Base Cladding. Where a decorative element shall be used for the cladding at the base of the PV-pole it shall be made from laser-cut, anodized or PE-SDF powdercoated aluminium sheeting and UV-stabilized, scratch-resistant polycarbonate incorporating LED lighting as shown on the project drawings. LED strip shall be hidden behind the polycarbonate sheet. The number and type of fixtures shall be as advised and approved by The Department and all lighting equipment must meet LED standards as set out within the DMA Lighting Specifications. LED types and wattage shall be finalized on product testing and clear adhesive 3M VHB or equivalent, 1mm thick film shall be applied to aluminium prior to laser cutting. Pattern shall be laser cut through both. Otherwise, adhesive shall bond aluminium to 6mm satin ice 100% UV-stable, scratch-resistant polycarbonate after forming. If required to be supplied from a solar system with batteries, the additional load and operation of this lighting must be including within the overall system and battery capacity design together with the street lighting luminaire. 8 Pole Design Submission and Production a) Design for Strength. The PV-poles shall be capable of withstanding a basic wind speed of 45 m/s or 160 km/hr (3 second gust) when equipped with the equivalent of the actual type and number of LED lanterns for the project and the associated fittings or accessories as confirmed by The Department. All PV-poles shall be designed in accordance with the requirements of the latest edition of AASTHO or equivalent European or International standard. Design calculations shall be submitted, for The Department’s approval, showing the following:i. Wind load derivation (hand calculation) on luminaires and mounted accessories ii. Wind loading derivation (hand calculation) on the pole iii. Sectional area of the pole at regular intervals of height along the pole, especially at areas of cross-section change and hand hole opening iv. Stress at the intervals specified in (iii) above v. Strength of the pole at the intervals specified in (iii) above vi. Combined Stress Ratios at the intervals specified in (iii) above Revision 0 Page 19 18th July 2013 . b) Design for Deflection. Actual deflection against the deflection limit of the PV-poles shall be clearly stated in the design calculations and shall conform to AASTHO or equivalent European or International standard. The actual deflection calculated shall be based on the basic wind speed of 45m/s and shall be measured at the lantern position(s). The calculated deflection shall be the sum of deflection on the vertical PV-pole section as well as the outreach bracket arm section(s). Deflection of both the vertical pole and the arm(s) shall be shown in the design submission. Design calculations shall show the pole deflection and shall be checked against the allowable deflection and special deflection limits required for CCTV cameras, where applicable for the project. c) Notarized Statement. A notarized statement, attested by the UAE Embassy, certifying the PV-poles were built conforming to the manufacturer’s approved drawings and design calculations, shall be submitted after completion of manufacture, and prior to delivery of poles to site. PV-pole delivery to project site shall not be accepted without this. 9 Quality Assurance The Department may request standard production model samples, identical to the proposed products to be installed. The Department may request independent testing of the sample PV-pole masts and equipment to verify the performance and compliance with the specifications. The Department shall be the sole judge regarding the acceptability of the performance of the light poles. According to the requirements of the Project’s Contract documents, if required The Department reserves the right to attend, or appoint a third party to attend, a factory inspection. During a factory inspection, the manufacturer shall perform a full deflection test, as agreed jointly with an accredited independent test house and department, on a randomly selected pole from the manufactured lot, for each type of ordered pole, to establish the design compliance and structural integrity of the manufactured pole under simulated conditions of full loading, strictly in accordance with the approved design calculations and drawings. If requested by The Department, different options of the base or lower cladding unit are to be shown on the project drawings. The Department will choose one option during the material review process and the sample shall be submitted accordingly. 10 Warranty and Maintenance Cover 10.1 Warranty The Consultant/Contractor shall provide a written undertaking of the Warranty from the Solar system supplier, accompanied with the written proof of the local representative’s UAE Operating License and established UAE background, to the satisfaction of The Department to warranty the materials and performance, as follows: Revision 0 Page 20 18th July 2013 a) Provide a written minimum-ten (minimum-10) year Warranty for on-site replacement: material, fixture finish, and workmanship. On-site replacement includes transportation, removal and installation of new products. Finish warranty shall include warranty against corrosion, failure or substantial deteriorations such as blistering, cracking, peeling, chalking or fading. The warranty shall include for maintained aesthetic integrity of the PVpole, photovoltaic panels, accessories, components and assemblies (not including the photovoltaic panels and batteries), without any partial or complete separation, corrosion, leaking, dislocation, disjointing, flaring, etc. of any elements of the PV-pole, system components and assembly with no cost to The Department. b) Provide a written minimum-ten (minimum-10) year replacement warranty for defective PV-poles, photovoltaics, accessories, components and assemblies (not including the photovoltaic panels and batteries), with no cost to The Department c) Provide a written minimum-five (minimum-5) year Warranty on the batteries for on-site replacement: material and workmanship. On-site replacement includes transportation, removal and installation of new products. Warranty shall include substantial deteriorations such as leaking, buckling, corrosion, inability to be charged or withhold a charge, impacted system autonomy and reduced DC output with no cost to The Department. d) Provide a written minimum-twenty five (minimum-25) year replacement warranty for the photovoltaic (PV) modules for their output peak watt capacity to not fall below 80% at the end of twenty five (25) years. With a minimum-ten (minimum-10) year replacement warranty for their output peak watt capacity to not fall below 90% at the end of ten (10) years. With no cost to The Department. 10.2 Maintenance/Defects Contract Period If requested within the Project documents, the Consultant/Contractor shall provide for the solar street lighting system manufacturer to include for a full maintenance and defects contract for a defined period for the project. This would be above and beyond the normal defects arrangements This contract shall include for all preventative and reactionary maintenance of the solar system and components, including all parts and materials throughout the duration of the contract. Refer also to clause 6.6 regarding cleaning. Full details of this maintenance contract including method statement for the maintenance to be included for approval of The Department. The maintenance contract should include for a renewal and/or extension of the contract if required in the future by The Department. 11 Measurement and Payment a) General. The measurement and payment for the PV-pole solar street lighting system shall include, but not by way of limitations, the complete PV-poles and components, batteries, invertors, controllers, PLMS, LED luminaires with all accessories, foundations, arthing and all related materials and works for the complete installation and energizing the system. Revision 0 Page 21 18th July 2013 Installation of cables in PV-poles shall be in accordance with The Department’s standard specifications. b) PV-Poles. Measurement and payment for the PV-poles, solar system and components, will be at the unit rates as included in the Bills of Quantities, which rates shall be considered as full compensation for all labour materials, finishes, tools, equipment and appurtenances as required, as specified, and as directed by The Department. 12 Operation and Maintenance Manual An Operation, Instruction and Maintenance Manual (O&M Manual), in both English and Arabic, should be provided for The Department for the project solar street lighting system. The following minimum details must be provided in the Manual: Revision 0 Basic principles of the photovoltaic system. A small write-up (with a block diagram) on the project solar street lighting system - its components, PV-poles and PV-modules, batteries, inverter/controller electronics and LED luminaires, driver, including expected performance. Type, Model number, Voltage & capacity of the batteries used in the system. Charging, discharging regime and significance of any indicators. Clear instructions about erection of the PV-poles and mounting of PV-modules, arms, fixtures and accessory housing assemblies on the PV-pole. Equipment manufacturer’s documentation (data sheets, handbooks, etc. A list of actions to be taken in the event of an earth fault alarm The shutdown and isolation procedure for emergency and maintenance A copy of the Shutdown procedure and any electrical safety warnings Clear instructions on regular maintenance, cleaning and troubleshooting of the solar street lighting system. The system performance estimate, including expected seasonal or operational variation Do's and Don’ts. Environmental Policy regarding the origin and manufacturer of all components, operation performance and safe transportation, disposal and/or recycling of components after removal/changing-over. All names and contact details of the relevant contact persons for repair, cleaning and maintenance, in case of non-functionality of the solar street lighting system. Page 22 18th July 2013