Commissioning buildings, systems using ASHRAE Standard 202 ASHRAE Standard 202-2013 was recently released, which offers guidance on the building commissioning process. BY TERRENCE MALLOY PE, CxA, exp US Services Inc., Chicago Learning objectives Gain a basic understanding of the commissioning process. Learn about ASHRAE Standard 202. Examine some real-world examples of why commissioning is needed. W e hear a lot about commissioning (Cx) and retro-commissioning (RCx) these days, but what do we really know about it, and what standards do we use to ensure that it is done correctly? ASHRAE’s answer to that question is the 2013 edition of ASHRAE Standard 202: Commissioning Process for Buildings and Systems. Its purpose is to ensure the proper procedures, protocols, and documentation are used in the completion of all building Figure 1: The energy consumption of the large VAV air handler before implementation of any control changes is shown. All graphics courtesy: exp U.S. Services 26 Consulting-Specifying Engineer • DECEMBER 2013 and systems commissioning. It identifies the minimum acceptable commissioning process that must be used. The standard was developed by taking best practices from ASHRAE Guideline 0-2005, The Commissioning Process, which was first published in 1989 and then revised in 1996. The current Guideline 0-2005 was compiled by ASHRAE and the National Institute of Building Sciences to provide the guidelines for a universal commissioning process. Standard 202 is designed to benefit the building industry by ensuring that all participants follow the owner’s process for verifying and documenting that the performance of buildings and systems meets defined criteria. The standard was officially approved by ASHRAE at its June 2013 meeting. This article will discuss the basics of Standard 202-2013, but more importantly provide several examples from recent RCx projects that show that commissioning really is needed. In summary, the standard describes the commissioning process, the role of the commissioning authority (CxA), and a framework for developing the owner’s project requirements (OPR), basis of design (BOD), commissioning plan, speciwww.csemag.com Incomplete testing and evaluation of VAV system requires reset fications, procedures, documentation, and reports. This standard also describes the general requirements for a training program for continued successful system and equipment performance. It addresses the need for a document with more detail and content than was previously available. Whereas Guideline 0-2005 provided suggestions and guides through the Cx process, Standard 202 details the mandatory requirements of Cx that can be used and adopted by code officials. The new standard restates the same information contained in Guideline 0-2005 and also provides the minimum requirements for the owner and the Cx team. It details the mandatory role for the owner in defining requirements and developing the OPR. The main points are: 1. Purpose: The purpose is to identify the minimum acceptable commissioning process for buildings and systems. 2. Scope: This standard provides procedures, methods, and documentation requirements for each activity for project delivery from predesign through occupancy and operation, including: Overview of commissioning process activities Description of each process step’s minimum activities Minimum documentation requirements Acceptance requirements. 4. Initiation of the commissioning process: The standard delineates the owner’s responsibilities including CxA selection and development of the OPR, and also lists the overall Cx requirements. A n overhaul of the air handlers at a community college reaped energy savings and improved occupancy comfort. Through the local electric utility’s energy reduction program, exp US Services was hired to perform retro-commissioning of three of the buildings at a suburban community college. Although the buildings were less than 10 years old, they were not energy efficient and were a source of tenant complaints. The buildings used three large variable air volume (VAV) air handlers with a total fan motor horsepower of 770 hp. The investigation of the HVAC systems revealed that the VAV boxes were never properly commissioned, and the minimum settings were all above the 50% flow setting. Each classroom had a designated VAV box, but because the rooms were often sparsely occupied, these spaces were getting overcooled due to the high airflow. Additionally, the school was paying a double penalty in that the reheat coils in many of the boxes were coming on even in summer, to reheat the overcooled spaces. Through some minor changes in the building automation system (BAS), the commissioning team was able to reset the VAV flow minimums to much lower settings, and in some cases to zero when occupancy sensors signaled that the room was unoccupied, which was in keeping with the original design intent. The electric energy savings were substantial, and although the engineers did not verify the gas savings, it is estimated they were about 35,000 therms/year. The facility provided utility data for the before and after periods of September 2009 to August 2010 and March 2011 to February 2012 (see Table 1). This provided an excellent comparison of year-to-year electricity usage and savings. The Cx team installed amp loggers on an air handling unit (AHU-1), and the before and after data are shown in Figures 1 and 2. It is clear that the new VAV minimum settings allowed the AHU fans to drop to less than 30% of their peak loads, whereas previously the minimum load was never less than about 60% of the peak. 5. OPR: The standard states that the OPR should be developed by the owner and the CxA during the pre-design phase, and list all of the systems to be commissioned. At a minimum, the OPR should contain the following: Facility use and operating schedule Energy and efficiency goals Indoor space requirements such as temperature, ventilation, etc. List of all systems/ equipment to be commissioned Project schedule Testing and sampling procedures Training requirements Submittal requirements Cx report format. 3. Utilization: The standard lists the required activities and related deliverables that are produced. The primary ones are: Activity Deliverable Initiate Cx process Roles and responsibilities Decide project requirements Owner’s project requirements Develop Cx plan Cx process plan Design approach to requirements Basis of design Set contractor Cx requirements Cx specifications Review design to requirements Design review report Review submittals Submittal review report Observe and test Construction checklists and reports Resolve issues Issues and resolution log Assemble systems manual Systems manual Conduct training Training plans and records Post-occupancy operation End-of-warranty Cx report Assemble Cx report Cx report www.csemag.com OPR should be included in contract documents for informational purposes, and be updated regularly throughout the Cx process to reflect any changes necessitated by the owner. 6. Commissioning plan: This provides the organizational plan and requisite documentation including: Overview of Cx process specific to the current project Roles of the Cx team Cx activities and schedules List and formats of all Cx evaluations and testing form List of systems to be commissioned and specific evaluation procedures for each. Consulting-Specifying Engineer • DECEMBER 2013 27 ASHRAE Standard 202 shall provide a design review report with comments, questions, and observations to the owner and design teams for compliance with the OPR. This design review is not design peer or code review. 10. Commissioning submittal review: The Cx team shall perform a review of the requisite submittal documents for all systems being commissioned, to ensure that they comply with the OPR. The CxA shall submit a written report to the owner and design authority. A copy of this review shall be included in the final commissioning report. Figure 2: This shows the energy consumption of the large VAV air handler after implementation of the recommended control changes. 7. BOD: The BOD lists the design team’s approach to meeting the OPR, and provides the owner with a better understanding of the design issues. The BOD is submitted by the design team to both the owner and the CxA and should contain: Design assumptions and attention to the OPR Consideration of design alternatives opportunities for improved performance Proper location of equipment Coordination of applicable technical and code requirements. 8. Contractor and supplier requirements: The applicable Cx process specifications and requirements shall be included in all contracts with contractors, subcontractors, suppliers, service providers, and manufacturers for the systems and equipment being commissioned. Contractors, suppliers, etc., shall provide the required documentation as defined in the contract documents. Examples of these documents include submittals, shop drawings, installation 28 manuals, operations and maintenance (O&M) manuals, and existing conditions documentation. 9. Design review: The CxA shall perform a review of the design documents to ensure that they comply with the OPR before construction documents are issued. A copy of this review shall be included in the final commissioning report. The CxA 11. Construction observation and testing: The proper installation, operation, and systems interaction shall be tested and verified for all equipment listed in the Cx plan. This step in the process shall consist of: Systems evaluation including detailed equipment information such as model, serial numbers, and name plate data, and condition of equipment upon delivery. Establishment of specific test procedures and sampling quantities for systems containing large numbers of components. Execution of test procedures repeated as often as needed until systems are in compliance with Fan controls don’t measure up T he fan controls at an airport terminal had never been reviewed, and needed to be updated with variable frequency drives. During a recent inspection of the HVAC systems for a 1-million-sq-ft airport terminal, the exp U.S. Services team noticed the installation of inlet vanes on about 35 of the variable air volume (VAV) air handlers. This seemed particularly odd because the fans were only about 10 years old. When the engineering team inquired about the installation, the client indicated it was a cost issue and that at the installation time the inlet vanes were a cheaper control method than variable frequency drives (VFDs). It seems that a proper design review by the CxA would have addressed this issue, and perhaps suggested a lifecycle cost analysis (LCCA) to show the actual operating costs of using the inlet vane controls versus VFD controls. The recommendation: replace the inlet vanes with VFDs. Although a moderately costly option, the annual savings are 2,360,000 kWh and $127,000. As a bonus, the state is offering incentives of about $160,000, so the effective payback is around 3.7 years. Consulting-Specifying Engineer • DECEMBER 2013 www.csemag.com Table 1: Electricity usage Pre-RCx electricity usage Months Usage (kWh) Post-RCx electricity usage Peak demand (kW) Months Usage (kWh) Peak demand (kW) Sept. 09 771,878 1,434 Mar. 11 529,538 1,059 Oct. 09 634,072 1,444 Apr. 11 520,226 1,076 Nov. 09 699,026 1,265 May 11 576,244 1,167 Dec .09 590,416 1,089 Jun. 11 626,308 1,162 Jan. 09 616,322 982 Jul. 11 767,057 1,730 Feb. 09 529,746 946 Aug. 11 755,127 1,673 Mar. 09 608,936 1,172 Sep. 11 741,862 1,794 Apr. 10 626,972 1,326 Oct. 11 639,417 1,260 May 10 629,940 1,201 Nov. 11 537,964 1,278 Jun. 10 779,401 1,488 Dec. 11 503,887 1,033 Jul. 10 956,229 1,566 Jan. 12 429,176 969 Aug. 10 833,145 1,521 Feb. 12 446,561 976 Total 8,276,083 15,434 Total 7,073,367 15,177 Table 1: The total annual electricity savings were 1,202,716 kWh and $91,960. requirements. The CxA witnesses and documents these tests. n Any equipment or system that fails to meet requirements in a timely manner is assigned an issue number and recorded in the issue and resolution log. 12. Issues and resolution documentation: The Cx team shall develop a formal issues and resolution log, and document any open or continuing item from the Cx progress reports. The log will list all continuing items along with the person/organization responsible for their resolution. The log will be maintained throughout the project until all issues are resolved, or accepted by the owner. 13. Systems manual: This shall provide the information needed to understand, operate, and maintain the building’s systems. It is provided to the owner for training purposes, and should contain the following: n Executive summary n Facility design and construction: copies of OPR and BOD n Building systems: equipment specifications, contractor www.csemag.com submittals, manufacturers’ O&M data n Facility operations: equipment operating schedules, control sequences and setpoints, operating plan n Training: training plan and materials, training records n Final commissioning report: Cx plan, testing and evaluation reports, design review report, and issues and resolution log. 14. Training plan: O&M personnel and occupants shall be trained in the operation and maintenance of the commissioned systems. The training plan should contain: n Outline of instructional topics addressing the design, operation, and maintenance of specific systems and equipment. n The location and minimum duration of training sessions, along with the instructors’ qualifications, and training records. n A copy of the plan shall be included in the systems manual. 15. Post-occupancy operation: The post-occupancy activities begin at substantial completion and include any delayed or seasonal testing not yet completed. Also, any warranty issues should be dealt with at this time. The owner or general contractor is responsible for contractor call-backs. At the conclusion of the post-occupancy operations, the systems manual, testing documentation, and final Cx report shall be submitted to the owner. 16. Commissioning report: The final Cx report shall summarize the Cx process and building operations, and be submitted to the owner. It shall contain the Cx plan and results of that plan. An executive summary will identify all systems commissioned and the location of the final OPR and BOD documents and project record drawings. It should also contain the following: n The final Cx process plans n Copies of design and submittals review reports n A completed copy of the CxA evaluations and start-up and test forms n Copies of all of the Cx progress reports n A copy of the issues and resolutions log and descriptions of measures taken for resolving all issues n A list and explanation of any Consulting-Specifying Engineer • DECEMBER 2013 29 ASHRAE Standard 202 systems that do not perform in accordance with the OPR. n A resolution plan approved by the owner for any incomplete issues or testing and the party responsible for their resolution. Cx in the real world As important as the Cx process is, in reality it is often not completed thoroughly, if at all. The examples in this article reveal projects in which one or more of the critical commis- Snowmelt system controls adjusted to save energy A t this large office campus, the sidewalk snowmelt system had never been reviewed or commissioned. During a recent retro-commissioning investigation for a large office complex, exp U.S. Services learned that the boiler-heated glycol system used for snow melting ran continually whenever the outdoor air temperature was below 38 F. NOAA weather records revealed that while the temperature is below 38 F for about 2250 hours/year, the actual amount of time of snowfall is only 580 hrs/yr. This difference of about 1,700 hrs represents the time the snowmelt system is on when it doesn’t need to be. Because large areas were covered by eight different snowmelt systems, the calculated annual savings was 43,000 therms of natural gas and $21,000. This system was installed many years before the popularity of commissioning, but this speaks to the need for retro-commissioning, and/or at least a periodic review of control sequences and operations. sioning process steps were not completed properly—or were omitted entirely. The consequences of these omissions became apparent in the forms of high energy use, poor system operations, and occupant comfort complaints. The four examples cited are indicative of what we find almost everywhere, and clearly indicate the need for more complete and rigorous commissioning. The new ASHRAE Standard 202 provides an excellent and straightforward manual from which to complete the commissioning process. Terrence Malloy is project manager for the energy solutions group at exp US Services Inc. He focuses on energy conservation, retrocommissioning, and renewable energy systems. HVAC and Building Controls Study sponsored by The study was conducted by Consulting-Specifying Engineer to evaluate engineers’ challenges/issues, product specification factors, and supplier preference for of various types of HVAC and building automation/control products. This study addresses: • HVAC/building controls equipment • Challenges, issues in the HVAC and controls market • Important factors for selecting products • Basic information about engineers’ choices, needs To view and download the study please visit: www.csemag.com/2013HVACBAS