TMG G1492 FS2500 TRACK CIRCUIT TEST AND INVESTIGATION GUIDELINE Version 1.1 Issued December 2010 Owner: Chief Engineer Signals and Control Systems Approved by: Warwick Allison Chief Engineer Signals and Control Systems Authorised by: Paul Szacsvay Principal Engineer Signalling Technology Disclaimer This document was prepared for use on the RailCorp Network only. RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to ensure that the copy of the document it is viewing is the current version of the document as in use by RailCorp. RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes any liability which arises in any manner by the use of this document. Copyright The information in this document is protected by Copyright and no part of this document may be reproduced, altered, stored or transmitted by any person without the prior consent of RailCorp. UNCONTROLLED WHEN PRINTED Page 1 of 39 Engineering Procedure Engineering Procedure Signals RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Document control Version 1.0 1.1 Date January 2008 14 December 2010 Summary of change Original Issue Application of TMA 400 format Summary of changes from previous version Summary of change © RailCorp Issued December 2010 Section UNCONTROLLED WHEN PRINTED Page 2 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Contents 1 Introduction .............................................................................................................................4 2 Test & Failure Investigation Strategy....................................................................................4 3 3.1 3.2 3.3 Typical Problems ....................................................................................................................4 Faults with no significant change in recorded values ...............................................................4 Faults with a significant change in recorded values .................................................................5 Installation factors that can contribute to failures......................................................................5 3.3.1 General factors ..........................................................................................................5 3.3.2 FS2500 specific factors .............................................................................................6 4 Typical Symptoms ..................................................................................................................8 5 FS2500 Failure Investigation & Test Form 1 ........................................................................9 6 FS2500 Failure Investigation & Test Form 2 ......................................................................10 7 FS2500 Failure Investigation & Test Form 3 ......................................................................11 8 8.1 8.2 8.3 8.4 8.5 8.6 8.7 8.8 8.9 8.10 8.11 8.12 8.13 8.14 8.15 8.16 Tests .......................................................................................................................................12 Test Equipment Requirements ...............................................................................................12 Power Supply Investigation and Test......................................................................................13 Transmitter Investigation and Test..........................................................................................15 Matching Transformer Investigation and Test.........................................................................17 Tuning Unit Investigation and Test .........................................................................................18 Tuning Unit Impedance Tests .................................................................................................20 End Tuning Unit Impedance Test ...........................................................................................21 Track Investigation and Test...................................................................................................22 DPU Investigation and Test ....................................................................................................25 Compensating Capacitors Investigation and Test ..................................................................27 Spark Gap Investigation and Test...........................................................................................28 Electrolysis bond Investigation and test..................................................................................29 Impedance Bond Investigation and Test.................................................................................30 Receiver Unit Investigation and Test ......................................................................................33 Receiver Lockup Investigation and Test .................................................................................36 8.15.1 Initial Receiver check...............................................................................................36 8.15.2 Receiver with contacts in the receiver power circuit................................................36 8.15.3 Receiver with contacts in the track relay circuit.......................................................36 8.15.4 Receiver fed from a TU............................................................................................36 8.15.5 Receiver fed from a DPU.........................................................................................37 8.15.6 Electrical noise.........................................................................................................37 Surge Protection Investigation and Tests ...............................................................................38 9 mV AC measurements in electrically noisy environments...............................................39 U © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 3 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 1 TMG G1492 Introduction This document has been produced to improve performance in fault finding on the FS2500 Track Circuit. This document details recommended practice for the testing and investigation of No Cause Found (NCF) failures for FS2500 track circuits. 2 Test & Failure Investigation Strategy Once a cause has not been able to be found for a failure then: • All the investigations detailed on the I&T Form 1 must be completed. The tests associated with the form are listed as Level 1 in the section detailing the tests. • If the Rx Monitor voltage has changed by more than 80mV from last full test of the track circuit, I&T Form 2 must be completed in addition to I&T Form 1. The tests associated with the form are listed as Level 2 in the section detailing the tests. Investigations of repeat No Cause Found failures (within 3 months of previous NCF failure) and significant incidents must complete I&T Form 3. The tests associated with the form are listed as Level 3 in the section detailing the tests. Specific tests that are carried out during fault finding or when required by the Signal Engineer or tester are listed as “As Requested”. The information recorded on the forms is to be analysed by the Signal Electrician, and Signal Engineer to determine further action required identifying and correcting the fault. If no cause can be identified after 3 NCF failures with the same transmitter and receiver in place then the transmitter and receiver are to be replaced as a pair and returned to the repairer for a priority test to specifications. This is to determine that the modules are the cause of the repeated no cause found failures or not. 3 Typical Problems 3.1 Faults with no significant change in recorded values Cause Test Loose or poor connection Covered in Level 1, 2, and 3 tests. Tu - Loose back nuts for B/W Covered in Level 1 test. Rx - internal connections Covered in Level 1 test. Rx - Internal Drift Covered by elimination of other causes. Track stick Covered in Level 1, and 3 test. Track repeat relay, CBI, or telemetry fault. Tx - faulty output stage Not covered. External to track circuit. Tx - Frequency drift Covered in Level 1 test. Excessive Tx DC current draw. Covered in Level 3 test Tx - not recovering after passage of train. Tx - not recovering after power on. Covered in Tx as requested tests. Spark gap connection Covered in Level 1 test. © RailCorp Issued December 2010 Covered in Tx as requested tests. UNCONTROLLED WHEN PRINTED Page 4 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 3.2 TMG G1492 Cause Test Traction imbalance Covered in Level 1 test. Impedance bond or electrolysis bond PSU - AC ripple Covered in Level 1 test. Covered in Level 3 test. PSU output ripple. Track insulation defect Covered in Level 1, 2, and 3 tests. Rx - Lockup Covered in Level 1 test. Faults with a significant change in recorded values Cause Test TU - connection Covered in Level 1 tests. TU - impedance change Covered in Level 2 tests. PSU - low output Covered in Level 1 tests. Tx - low output Covered in Level 1 test. Tx - faulty output stage Covered in Level 1 test. Tx DC current draw. Ballast condition Covered in Level 1 tests. Broken rail Covered in Level 1 tests. 3.3 Installation factors that can contribute to failures 3.3.1 General factors General installation factors that can contribute to no cause found failures are: Factor Modules recently put into service. Modules that have been inservice for more than 12 years. Modules that are older than 20 years. Long term heat stress. Large day night temperature swings. Type of rail connections. Stability of the track at or near rail connections. Track leads. © RailCorp Issued December 2010 Concern Modules in service for less than 3 months may have a defect that was not found in production or repair. Modules continually in service for more than 12 years may start to have components that have drifted or start to have internal connection problems. Older modules are more likely to have components that are subject to temperature and vibration effects. Modules that have been operated for long periods (>5 years) at high average temperatures will have components that have deteriorated which can cause intermittent faults or higher failure rate. Modules that have been operated for long periods (>5 years) with large (>20ºC) day night temperature swings will have components that have internal connection problems that can cause intermittent faults. Web welded connections are more stable and are less likely to deteriorate or be the cause of intermittent faults. Vertical rail movement near track connections can cause bolted connections to 'work loose'. The leads from Tuning unit to rail should be held together from Tuning unit to near rail by non-metallic ties. A revised arrangement for securing track leads to reduce damage due to track work was issued during 2006. UNCONTROLLED WHEN PRINTED Page 5 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline Factor Spark Gap connections Power supply stability Surge protection Ballast condition and drainage Impedance bond mounted vertically 3.3.2 TMG G1492 Concern Requirements for spark gap connections changed in the late 1990's. Spark gap connections are only required as per Electrical Specification EP 12 20 00 01 SP Bonding of Overhead wiring structures to Rail. Some areas have their normal power supply fed via the railway 33kV network. The 33kV railway supply is not regulated and this can affect PSU output voltage. Intermittent load changes (like train stop or points operation) can cause output voltage of PSU to dip. No surge protection, or poorly installed surge protection will accelerate the deterioration of modules and increase all types of module faults. Installation of 120V bus MOV is particularly important. Tuning units also require protection in high lightning activity areas. Poor ballast condition, ballast height above foot of rail, and poor drainage can cause failures in wet conditions, as the ballast resistance change between wet and dry is too large for the normal track adjustment to handle. 2000R type mounted vertically should have a rain cover fitted. This is particularly important when two vertically mounted bonds are connected with a solid neutral bus bar. FS2500 specific factors Receiver version Check Receiver version is V34.1 or later. The current version is 36.2. Version 34.1 was introduced in June 2002. Versions prior to V34.1 had a number of problems particularly in regard to power disruption causing receiver lockups. Prior to version V34.1 the brown out relay was sensitive to vibration. This was corrected around year 2000. Earlier versions had an orange coloured brown out relay. A blue relay is now used. Since November 2003 (after V34.1) the brown out circuit has been adjusted and tested for each receiver to achieve more consistent values. Receivers originally used an electrolytic capacitor as C19, which was/is a significant cause of receiver failure. Capacitor C19 has been changed to a polyester type since November 2004. The polyester type capacitor has a longer life and better reliability. Degradation of C19 in older receivers can cause intermittent lockups before a complete failure. Voltages of 1.2V or more on monitor point indicates the possibility of clipping the input signal, which may produce frequency components that can lead to lock up of the receiver. Therefore the monitor voltage must be less than 1.20V. DPU Amp version The DPU AMP Version should be QAJTC1 Issue 4.0 as a minimum. The earlier versions did not have an isolated output. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 6 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 DPU The DPU should have a later serial number than IC394 and Issue 3.0 or Issue 5.0 with an R meaning it has been upgraded. This change was introduced in March 2004. Earlier versions had a significantly higher failure rate. TU version Westinghouse changed the design of the Tu in September 2002 to improve the effectiveness of the connections to eliminate Rx lockups or track failures due to Tu connections. A retrofit kit is available from Westinghouse to improve the connection method. Particular attention is required on the tightness of back nuts on Tx and Rx TUs for the original connections. Connection problems causing significant intermittent amplitude changes can cause the Rx to lockup. Tx No significant known issues. Relay Noise sensivity Q relay noise can be a cause of FS2500 Receiver lockups. This is a likely cause if: • The Receiver drives an un-snubbed track relay via a track stick circuit. • Q relays are installed with-in 300mm of the Receiver. • Input wiring from the track circuit cable terminals to the Receiver or DPU AMP is longer than 5m and mixed in with Q relay circuit wiring. Normal solutions are: • Fit diode or RC snub to track relays with track stick circuits. The diode or RC snub is to be mounted as close to the coil as practical and must be on the relay coil side of any contacts. and • Have a design done to snub other relays as necessary. The design must snub all relays (that need snubbing) mounted with-in 300mm of Receiver as a minimum. or • Fit a snap on ferrite choke around the input wires close to the Receiver terminals. Snap on ferrite chokes like RS 260-6486 or Farnell 9640444 are appropriate. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 7 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 4 TMG G1492 Typical Symptoms Symptom Likely Causes Slow to pick up after a train or picked after 2nd train. Tx - not recovering after passage of train, Tx - faulty output stage, Rx, rail connection, track stick, train stop, or PSU. Tu, Traction imbalance, Spark gap, connection or Rx. Tu, Ballast condition, Tx, Rx, Power supply AC, or DC, or un-intended rail connection (eg failed spark gap). People working in area, or Traction imbalance. Dropped on the approach of a train. Drop and pick intermittently without train present or nearby. Drop again after picking up after train had passed. Drop and pick within 30 seconds with no significant change in Monitor voltage. Drop and pick after 30 seconds. Pick up of failed track on the approach of a failed train. DPU track not shunting for 1st bogie Failure after heavy rain Rx lockup © RailCorp Issued December 2010 Tu, Traction imbalance, Spark gap, connection, Rx, or People working in area. Tx frequency at limits. Tu, connection (loose back nuts), Tx or Rx. Defective Tu. DPU Amp or Rx adjustment, and wheel rail contact are potential causes. Poor ballast Water ingress to vertically mounted 2000R impedance bond with internal fault. Impedance bond will recover when it dries out. Power supply disruption for Rx prior to V34.1. Un-snubbed track relay with track stick circuit on relay output. Relay noise affecting the Rx. Poor connections on Tu. Interfering Traction harmonics picked up via a DPU. The interfering traction harmonics are likely to have been produced by a Millennium train. UNCONTROLLED WHEN PRINTED Page 8 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 5 TMG G1492 FS2500 Failure Investigation & Test Form 1 FS2500 Failure Investigation & Test Form 1 Track Name: Inspection Date: Location: Failure Date(s): Inspection By: Time of Failure: Track Frequency: Hz Track Length: Metres TRANSMITTER END Failure Duration: (Approx.) Estimated temperature at time of failure: RECEIVER END PSU & Tx Connections Checked PSU & Rx Connections Checked PSU Input Voltage (Bx120/Nx120) Vac PSU Input Voltage (Bx120/Nx120) Vac PSU Output Voltage (B24/N24) Tx Input Voltage (B24/N24) Tx Input Current (B24 or N24) Tx Power percentage Tx Output Voltage (Loc. Track term.) Tx Power Setting (Low is 1/2 on TU) Vdc PSU Output Voltage (B24/N24) Has Track Stick Relay voltage (Relay R1/R2) Relay Output Voltage (R+/R-) Drop Shunt Rx Sensitivity Setting Vdc Last entry Monitor(Track History Card) mVac Receiver was locked up Receiver lockup test OK Rx Monitor(Track Unoccupied) Rx Input Voltage (Loc. Track term.) Rail to Rail Voltage (Rx end) Vd Up Rail Conn. (Rx end) Vd Dn Rail Conn. (Rx end) Vd Up Rail Conn. (Rx end adj TU) Vd Dn Rail Conn. (Rx end adj TU) Yes/No Vdc mAdc % Vac N or L Vac Rail to Rail Voltage (Tx end) Vd Up Rail Conn. (Tx end) Vd Dn Rail Conn. (Tx end) Vd Up Rail Conn. (Tx end adj TU) Vd Dn Rail Conn. (Tx end adj TU) mVac mVac mVac mVac TU Connections checked OK Record & Compare Track History Card FAILED WITH TRAIN Approaching Departing On Adjacent Line In Vicinity Not in Area Unknown Train Type was: ADDITIONAL CHECKS Repeat Relays Event Logs Reviewed Telemetry/ CBI Reviewed Work group(s) in area Yes/No Vdc Vdc ohm Yes/No mVac Vac Vac mVac mVac mVac mVac TU Connections checked OK DPU Checked OK Record & Compare Track History Card TRACK P F G Ballast Condition Track Inspected Spark Gaps Checked OK Impedance Bonds Checked Impedance Bonds resonated Traction Return Balanced on IB Electrolysis bond checked and balanced Equipment replaced in last 3 months: © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 9 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 6 TMG G1492 FS2500 Failure Investigation & Test Form 2 FS2500 Failure Inspection & Test Form 2 (Rx Monitor changed by more than 80mV from last full test.) FS2500 Failure Investigation & Test Form 1 must also be filled out with this form. Track Name: Location: Inspection By: Inspection Date: Failure Date(s): FS2500 Failure I. & T. Form 1 Dated TRANSMITTER END RECEIVER END TU Input Voltage (4/5 or 1/2) TU Type Vac Tu or ETu TU Output Voltage (1/2) TU Type Vac Tu or ETu TUNING UNIT (Track Under Test) TX END SHUNT TEST AT TRACK FREQUENCY Tx Rail volts Vac Tx Rail volts, 0R5 shunt Amps Shunt Vac Rail Vac Tx Voltage ratio TUNING UNIT (Track Under Test) TU IMPEDANCE TEST AT TRACK FREQUENCY TU Voltage T1/T2 mVac TU Current (T1 or T2) Amps mΩ TU Impedance (Z Calculated) TU IMPEDANCE AT ADJACENT TRACK FREQUENCY TU Voltage T1/T2 mVac TU Current (T1 or T2) Amps Z=TU(mV) I(A) mΩ TU Impedance (Z Calculated) TU IMPEDANCE TEST AT ADJACENT TRACK FREQ. TU Voltage T1/T2 mVac TU Current (T1 or T2) Amps Z=TU(mV) I(A) mΩ TU Impedance (Z Calculated) TUNING UNIT (Adjacent Track) TU IMPEDANCE AT TEST TRACK FREQUENCY (Zero) TU Voltage T1/T2 mVac TU Current (T1 or T2) Amps Z=TU(mV) I(A) mΩ TU Impedance (Z Calculated) TUNING UNIT (Adjacent Track) TU IMPEDANCE AT TEST TRACK FREQUENCY (Zero) TU Voltage T1/T2 mVac TU Current (T1 or T2) Amps Z=TU(mV) I(A) mΩ TU Impedance (Z Calculated) © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Z=TU(mV) Page 10 of 39 Version 1.1 I(A) RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 7 TMG G1492 FS2500 Failure Investigation & Test Form 3 Track Name: Location: Inspection By: FS2500 Failure Inspection & Test Form 3 (Repeat Failure follow up) Inspection Date: Failure Date(s): FS2500 Failure I. & T. Forms 1/ 2 TRANSMITTER END Vd Bx120v fuse RECEIVER END mVac Vd Bx120v fuse mVac Vd Nx120v Term. mVac Vd Nx120v Term. mVac Vd B24v fuse mVdc Vd B24v fuse mVdc Vd N24v Term. mVdc Vd N24v Term. mVdc PSU Output ripple Vac PSU Output ripple Vac Tx Frequency Hertz Vd Loc. Track Term mVac Zero feed test mVac mVac Track Stick resistance ohms Vd Loc. Track Term Shunt tested 0R15 Surge Protection Inspected Surge Protection Inspected 3Y20 Arresters Tested 3Y20 Arresters Tested Additional Tests © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 11 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 8 Tests 8.1 Test Equipment Requirements Test Equipment DMM (Digital Multi-Meter) General DMM with fast min/max or peak min/max. FSM (Frequency Selective Meter) DC Tong Meter for Traction current measurement DC Tong Meter for general use AC Tong Meter for general use AC Current clamp Rail current meter General Requirements Approved Test Equipment Must have true RMS to > 3kHz Frequency reading to 1 Hz. Min/Max is 100mS response time. As per the general Multimeter. Fast Min/Max is faster than 5mS response time. Centre frequencies of 1700hz, 2000Hz, 2300Hz, 2600Hz. Bandwidth < +/-0.5db at +/-30Hz, and > 60db rejection at +/-600Hz from centre frequency. Fluke 8060, 179, 87, 187, 189 Continued use of Fluke 27 averaging meter with no freq, or fast min/max facility is permitted. Comparison testing is to be carried out. Fluke 187, 189. Fast min/max Fluke 87V Peak min/max Selective Track Frequency Meter (STFM) or Track Circuit Filter Adaptor (TFA) and DMM. The TFA is not suitable for rejection ratio or TU impedance measurements. Accuracy of better than 1.5% of reading for traction return. 0 to 2000A DC. For conductor size 55mm diameter. Resolution of better than 0.1A. Resolution of better than 0.1A. 10Hz to 3kHz, 10mV/A, and 100mV/A. Indication of rail current. Resolution of 0.1A rail current at 1700Hz to 2600Hz. Kyoritsu 2003, 2003A, 2009 Kyoritsu AC/DC Digital Clamp meters. 2003, 2003A, 2004, 2033 Kyoritsu 2033 Chauvin Arnoux 1000/1 A current clamp. AMEC AC current probe SD661 Clancy meter: Calibrated at 50Hz. The Clancy meter tends to read high at audio track circuit frequencies but does provide an indication of comparative rail current. RAS Coil: Output 1mV/A at 50Hz and about 1mV/A at 1700 2600Hz. Reads about 10-20% low at audio frequencies. The readings are lower as the frequency increases. Used in conjunction with a DMM. Must use a Fluke 189 or equivalent meter. Using Hz button on multimeter can check the frequency of the dominant rail current if the output of the RAS coil is high enough for the meter. Rail Current Meter: Output 1mV/A or 10mV/A. Used in conjunction with a DMM. CRO (Oscilloscope) Arrestor Tester © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 12 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.2 TMG G1492 Power Supply Investigation and Test Test Test Equipment Test Point Terminals Readings Checks Action If Not Compliant Condemning Visual and Physical Checks Hand tools Visual Inspect and check all terminations Terminations effective and secure PSU Unit secure Correct as required Loose or ineffective connections. PSU Input Voltage DMM on Vac BX120 bus AC voltage 110 – 132Vac PSU Output Voltage DMM on Vdc B24/N24 24Vdc – 27Vdc PSU Output ripple Voltage DMM on Vac B24/N24 < 0.1Vac Fuse terminal voltage drop. DMM on Vac, and Vdc Bx120v fuse and B24 fuse terminals. <30mVac or <30mVdc Disconnect terminal Voltage Drop DMM on Vac, and Vdc NX120 and N24 disconnect terminals. <5mVac or <5mVdc If voltage is <114V Check the PSU voltage tapping for the voltage lower than that read. Supply voltage for Tx and Rx. See Note 1. Power Supply Ripple Rxs are more sensitive to electrical noise when PSU ripple is high. Test Required Level 1, 2 and 3 Adjust input voltage taps on PSU. Supply voltage less than 108Vac. Adjust or replace power supply. <22.5Vdc >30.5Vdc Level 1, 2 and 3 Track Circuit History Card Replace power supply. >0.2Vac Level 3 – Detailed Investigation Connections. Clean and ReSecure or replace fuse. >60mVac or >60mVdc Connections. Clean and ReSecure >5mVac or >5mVdc Level 1, 2 and 3 Level 3 – Detailed Investigation Level 3 – Detailed Investigation Note 1: Most power supplies for this type of track circuit are not regulated. If the unregulated DC voltage is below 24 volts then check the 120 Vac voltage on the PSU. The PSU DC voltage should be approximately 26 Vdc for the average 120Vac voltage for the location. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 13 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Power Supply Investigation and Test (Continued) Test VA loss PSU output voltage earth balance © RailCorp Issued December 2010 Test Equipment Test Point Terminals Readings Checks Action If Not Compliant Condemning DMM and AC, DC current tong. Voltage at BX120, and B24, AC current input PSU, DC current out of PSU. AC current times voltage to give VAinput DC current times by voltage to give VAoutput. Va loss = VA input – VA output. Replace power supply. VA Loss more than 50VA. As Requested Earth fault inside modules or wiring insulation. Earth faults can be caused by internal faults in Rx, or Tx. Test surge protectors. Test insulation resistance of wiring. Replace modules. >2 Volts for either B24 or N24 to earth. As Requested DMM on Vdc with 20k shunt. B24, N24, and earth bar. < 0.5Volts from B24, or N24 to earth. UNCONTROLLED WHEN PRINTED Test Required Page 14 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.3 TMG G1492 Transmitter Investigation and Test Test Test Equipment Visual and Physical Checks Hand tools Visual Input Voltage DMM on Vdc Input Current Output voltage DC Tong meter DMM on Vac Test Point Terminals Readings Checks Action If Not Compliant Condemning Test Required Inspect and check all terminations. Terminations effective and secure Check Mounting and environment. Roof leaking, and vermin urine etc. Correct as required Visible defects Level 1, 2 and 3 B24/N24 24Vdc to 27Vdc Test Power Supply Unit <22.5V or >30.5V Level 1, 2 and 3 Wire to B24 or N24 < 2.2 Amps. Current decreases with power setting. See Note 1 Increasing current means an increased load on track or faulty transmitter. Replace transmitter or find cause of excessive load. Change Transmitter If above maximum reading. Level 1 Location Track Terminals 2.6 to 13.0Vac based on power setting of 20 to 100%. Dependant on power setting. Change Transmitter or find and correct any fault loading the track. <2.3Vac, >14.3Vac, or more than +/-10% based on power setting. TX Output cable terminals <5mVac Clean and ReSecure >5mVac Location Track Terminals Base Frequency ± 2Hz. Use Min/Max to get Average if unstable reading. Level 1, 2 and 3 Track Circuit History Card DMM on vac TX Output Terminal Voltage Drop See section 9 for meter usage details. DMM on Vac, Hz measuring output of TFA, or STFM. Transmitter Frequency Note 1: © RailCorp Issued December 2010 Drift in transmitter components or loss of modulation. Nominally: 1699, 2002, 2299, 2602Hz. Level 3 – Detailed Investigation Change Transmitter Change Transmitter >Base Frequency+6Hz <Base Frequency-6Hz Level 3 – Detailed Investigation The DC current can fluctuate between upper and lower frequencies by up to 0.4A on normal power. UNCONTROLLED WHEN PRINTED Page 15 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Transmitter Investigation and Test (Continued) Test Equipment Test Point Terminals Readings Checks TX Output voltage earth balance DMM on Vac Location Track Terminals and earth bar. About 50% of output voltage from each leg to earth. Earth fault inside modules or wiring insulation. Recovery after shunt. Shunt box on short circuit. Start-up at power on. - Apply shunt at Tx Tu for 10 seconds. Pull N24 pin for Tx, and restore after 10 seconds. Track relay drops and picks due to test. Track relay drops and picks due to test. Test © RailCorp Issued December 2010 Action If Not Compliant Test surge protectors and insulation resistance of wiring. Replace modules. Tx output voltage recovers after power limiting. Replace Tx. Tx starts working at power on. Replace Tx. UNCONTROLLED WHEN PRINTED Condemning Test Required One leg being more than 75% of output voltage to earth. As Requested Track does not pick within 3 seconds. Track does not pick within 3 seconds. As Requested As Requested Page 16 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.4 TMG G1492 Matching Transformer Investigation and Test Test Test Equipment Inspect for signs of damage or poor connections Visual Check voltage ratio DMM on Vac VA Loss FSM and AC current clamp Primary Current DMM on Iac or AC current Clamp Note 1: Test Point Terminals Checks Action If Not Compliant Condemning Connections secure. Repair/Replace Visible defects As Requested Input terminals and Output terminals Voltage ratio matches the transformer ratio within +/- 20% Operation of transformer. See Note 1. Replace or find and remove cause of excessive load current. Voltage ratio different from Transformer ratio by more than +/- 50%. As Requested Primary terminals and secondary terminals. Primary current times voltage to give VA input Secondary current times by voltage to give VA output. VA loss = VA input – VA output Replace transformer. VA Loss more than 5VA. As Requested Typically <5A Primary current less than 50VA transformer rating. Find and remove cause of excessive load current. >5A As Requested Primary Terminal Readings Test Required Matching transformers are used to compensate for longer distance cables from Tx to the Tu. They are not installed for the Rx end. Matching transformers used in pairs are set to the same transformer ratio (normally 1:5 or 1:9), and have the primary connected to the equipment. Matching transformers used singly are normally set to 1:5 and have the primary connected to the Tx. The Tu connections are non-standard when a single matching transformer is used. The Tu is connected to provide a similar transformer ratio as the matching transformer. This means the Tx Tu connection is to 1/2 instead of 4/5. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 17 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.5 TMG G1492 Tuning Unit Investigation and Test Readings Checks Action If Not Compliant Condemning Test Requirement Terminations effective and secure Current version or modified Tu. Correct as required Visible defect. Level 1, 2 and 3 FSM and 0.5ohm shunt Apply a 0.5ohm shunt at TX end TU rail connections. Rail to Rail voltage should be halved. If rail to rail voltage is halved then TX end equipment and connections are okay. Check TX end equipment and connections. Rail to Rail voltage less than 1/3 or greater than 2/3. Level 2 Short Circuit Test (Considered as a track shunt rather than Bridging or Releasing) A registered jumper wire. Apply jumper wire across T1/T2 of adjacent Tuning unit at either TX or RX end to confirm TU. Track voltages on track circuit should return to track history card values or better. Track relay picks up. Replace adjacent tuning unit Rx end Rx short circuit test A registered jumper wire. Apply jumper wire across 1/2 of Tu. The Rx B/W. T1/T2 voltage should increase by about 10%. H/R connections or open circuits in Rx wiring or Rx. Inspect receiver circuit wiring and connections. Replace Rx. Test Test Equipment Visual and Physical Checks Hand tools Visual TX end shunt test © RailCorp Issued December 2010 Test Point Terminals Inspect and check all terminations, including back nuts. UNCONTROLLED WHEN PRINTED Track picks up when adjacent tuning unit is short-circuited or track voltage increases by more than 25%. A low T1/T2 voltage returning to 10% more than the History card. As Requested As Requested Page 18 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Tuning Unit Investigation and Test (Continued) Test Attenuation Ratio Test Test Equipment FSM Test Point Terminals VR1=Rail to Rail Voltage of tuning unit at track frequency. VR2=Rail to Rail Voltage at adjacent tuning unit at track frequency. Readings Checks VR1/VR2>12 for 1Q, and 3Q. VR1/BR2>18 for 2Q, and 4Q. Both measurements are at frequency of track under test. Action If Not Compliant Perform Short circuit test and change adjacent TU is short circuit test picks track other wise change track TU. Condemning VR1/VR2<10 for 1Q, and 3Q. VR1/VR2<16 for 2Q, and 4Q. Test Requirement As Requested See also Section 8.6 Tuning Unit Impedance Test or Section 8.7 End Tuning Unit Impedance Test © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 19 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.6 TMG G1492 Tuning Unit Impedance Tests Test Test Equipment Test Point Terminals Readings Tuning Unit "Pole" Impedance Test AT TRACK FREQUENCY FSM AC Current Clamp 1. TU Voltage T1/T2 2. Current to T1 or T2 Use readings to calculate impedance and compare with Table Tuning Unit "Zero" Impedance Test AT ADJACENT FREQUENCY FSM AC Current Clamp 1. TU Voltage T1/T2 2. Current to T1 or T2 Use readings to calculate impedance and compare with Table TUNING UNIT IMPEDANCE RANGES Z at 1700Hz TU 1Q 1699 260<Z<320mΩ TU 4Q 2602 Notes: Condemning Test Requirement Z = TU(mV) I(A) Change out Tuning Unit See Table for same freq. as TU. Level 2 Z = TU(mV) I(A) Change out Tuning Unit See Table for different freq. to TU. Level 2 Z at 2000Hz Z at 2300Hz Z at 2600Hz Z<55mΩ 312<Z<382mΩ TU 2Q 2002 TU 3Q 2299 Action If Not Compliant Checks Z<55mΩ Z<65mΩ 344<Z<422mΩ Z<65mΩ 382<Z<470mΩ The impedance ranges are different to the CSEE UM71 values. The Tx end shunt test as per Section 8.5 Tuning Unit Investigation and Test is used to prove the "pole" impedance of the Tx tuning unit. The "zero" impedance of the Tx tuning unit can be measured in service, but the "pole" impedance of the Tx tuning unit can not be measured in service. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 20 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.7 TMG G1492 End Tuning Unit Impedance Test Test Test Equipment Test Point Terminals Readings Tuning Unit "Pole" Impedance Test AT TRACK FREQUENCY FSM AC Current Clamp 1. TU Voltage T1/T2 2. Current to T1 or T2 Use readings to calculate impedance and compare with Table Tuning Unit "Zero" Impedance Test AT ADJACENT FREQUENCY FSM AC Current Clamp 1. TU Voltage T1/T2 2. Current to T1 or T2 Use readings to calculate impedance and compare with Table END TUNING UNIT IMPEDANCE RANGES TU 1Q (1699Hz) TU 2Q (2002Hz) TU 3Q (2299Hz) TU 4Q (2602Hz) Notes: Z at 1700Hz Action If Not Compliant Condemning Test Requirement Z = TU(mV) I(A) Change out Tuning Unit See Table for same freq. as TU. Level 2 Z = TU(mV) I(A) Change out Tuning Unit See Table for different freq. to TU. Level 2 Checks Z at 2000Hz Z at 2300Hz 675<Z<1620mΩ Z at 2600Hz Z<80mΩ 1000<Z<2400mΩ Z<80mΩ Z<80mΩ 1000<Z<2400mΩ Z<80mΩ 1500<Z<3000mΩ Normally only the "pole" impedance of the Rx End Tuning Unit can be measured in service. The "zero" impedance of an End Tuning Unit can not normally be measured in service, as the adjacent frequency is not present. The "pole" impedance of the Tx End Tuning Unit can not be measured in service. The Tx end shunt test as per Section 8.5 Tuning Unit Investigation and Test is used to prove the "pole" impedance of the Tx End tuning unit. The Rx B/W is connected to 1, and 2 in the ETu. Long Rx cable runs will decrease the ETU "pole" impedance. The values for End Tuning Units and have not been verified by field testing. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 21 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.8 TMG G1492 Track Investigation and Test Test Test Equipment Test Point Terminals Track Voltage FSM Rail to Rail Readings Checks Action If Not Compliant Condemning As per Track Circuit History Card Voltage drops on all Track Connections. This includes both TU for TX and RX tuned loops. DMM on Vac See section 9 for meter usage details. Test point depends on the type of connection. See Note 1 <10mV drop for bolted connections. <40mV for welded connections. Fixed Shunt Test DMM 0.15Ω Fixed Shunt 3 metres either side of the TU at both Tx and Rx end of the track as well as mid point of the track length. Relay front contacts should be observed to open. Rail connections. Target for rail connections is less than 1 mOhm. Test Required Level 1, 2 and 3 Repair/replace connection and make good See Note 2. Advise Civil of any track movement. >20mV drop for bolted connections. >60mV for welded connections. One rail connection > twice the other connection and >10mV Level 1, 2 and 3 Report findings to DSE and Signal Engineering Unable to shunt track. Level 3 – Detailed Investigation Note 1: Test points for track connection. First meter lead is held on the palm of the crimp for tapered bolt and welded stud connections. First meter lead is held on the exposed copper part of the bi-metallic inline crimp for direct welded connections. The other meter lead should be held on the wheel/rail contact band on the head of the rail. Note 2: Direct welded connection tests include more than just the rail connection. Condemn at >3mOhms per complete connection. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 22 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Track Investigation and Test (Continued) Test General Inspection © RailCorp Issued December 2010 Test Equipment Test Point Terminals Visual Track Connections Trackside Equipment (Incl. Impedance bonds and spark gaps) Ballast Condition, Ballast height, Rails, Bonding, Bridge Structures etc. Insulation on spark gap connections that pass under the other rail. No long pieces of rail scale rail flow, or conductive material around IRJs. Readings Checks Action If Not Compliant Condemning Installed to standards, free of defects, damage, and contamination Track Insulation Plan Standards No cause of rail to rail short circuits or rail to earth short circuits. Report, record and if possible, rectify. Visible defects UNCONTROLLED WHEN PRINTED Test Required Level 1, 2 and 3 Page 23 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Track Investigation and Test (Continued) Test Equipment Test Rail voltage drop profile Rail current profile FSM Rail Current meter. Rail current balance Rail Current meter. Readings Checks Action If Not Compliant Condemning Rail to rail voltages at regular intervals. (~100m) From Tx to Rx. Voltage drop should range from 1.5 to 0.3V per 100m. The voltage drop per 100m should reduce along the track. The rate of reduction should decrease. The reduction can be constant for good ballast. Look for a rail to rail connection across the track. See Note 3. As Requested Up rail, or Down Rail currents at regular intervals. (~100m) from Tx to Rx. This test does not include measurements in the tuned loop. Initial rail currents of 1.5 to 0.4A are typical. Shorter track circuits tend to have higher rail currents. See Note 4. Look for a rail to rail connection across the track. See Note 5. As Requested Unbalanced leakage and external currents. Look for: external connection to rail, faulty spark gap, or a common mode external current. Clearly detectable difference of at least 0.2A. As Requested Test Point Terminals Up rail, and Down Rail currents at regular intervals. (~100m) Equal readings for Up and Down rails. Test Required Note 3: A higher rate of voltage drop occurs on the shorter higher frequency tracks. A higher rate of voltage drop occurs between a transmitter and a mid-track impedance bond. The voltage drop per 100m for each successive 100m should decrease when measured from transmitter to receiver end. The decrease should reduce for each 100m segment. An increase in the rate of reduction indicates an extra load across the track in the previous 100m. Note 4: The rail current should gradually decrease from transmitter to receiver. The rail current at the receiver end should be at least 0.1A. Note 5: Tracks without impedance bonds or electrolysis bonds should have a decreasing reduction in rail current for every 100m when the rail current is measured once every 100m from transmitter to receiver end. An increase in the current reduction indicates an extra load across the track in the previous 100m. Tracks with impedance bonds or electrolysis bonds should have a decreasing reduction in rail current for every 100m when the rail current is measured once every 100m from transmitter to receiver end except for the 100m segment with the impedance bond or electrolysis bond. An increase in the current reduction indicates an extra load across the track in the previous 100m. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 24 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.9 TMG G1492 DPU Investigation and Test Test Test Equipment Test Point Terminals Visual and Physical Checks Readings Checks Action If Not Compliant Condemning Version numbers. See Note 1. DPU is secure, parallel to the rail and correct spacing from the rail. Correct mounting Visible defects Level 1 Output Voltage less than 20mV. As Requested Unable to achieve DPU Amp output current. As Requested <28mA or >60mA As Requested <22.5V or >28.8V As Requested High gain output voltage < 1.8 times low gain voltage. As Requested DPU Output voltage FSM Output voltage of DPU. AC output voltage in the range of 20 to 60mV. Sufficient output voltage DPU Amp Input voltage FSM Voltage at A1/A2 AC voltage Sufficient input voltage Sufficient output current to drive Rx. DPU Amp output current DMM on Iac Rx input current DPU Amp DC voltage DMM on Vdc DPU Amp R1/R3 24 to 27Vdc Power supply to DPU Amp. DMM on Vac DPU Amp Output A5/A6 With D1/D2 bridge (High gain) and without. Output Voltage on high gain should be twice voltage on low gain. High gain strap effectiveness. DPU Amp High gain setting effectiveness. Note 1: Check connections or replace DPU. Insufficient rail current due to connection or RX Tuned loop. Check connections and adjustment or replace DPU. Readjust DPU Amp gain, Tx power or find and correct fault. Test Power supply unit, fuses and connections. Replace DPU Amp. Test Required DPU Version: Serial number IC394+ with Issue 3.0+ or Issue 5.0 with an R for revised. DPU Amp Issue 4.0 as minimum. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 25 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 DPU Investigation and Test (Continued) Test Point Terminals Test Test Equipment Over-energisation FSM and short circuit shunt 1m on Rx side of DPU. Rx input current DMM on Vac Each DPU cable wire to earth connection. Voltage balance to earth © RailCorp Issued December 2010 Readings Checks Rx input current should increase but not exceed the condemning limit given. About 50% of output voltage from each leg to earth. Over-energisation of receiver. Overenergisation can drop the Rx output. Earth fault on wiring insulation or in DPU Amp. UNCONTROLLED WHEN PRINTED Action If Not Compliant Re-adjust track circuit. The track may need to be set on Normal power. Test insulation resistance of wiring, and check DPU Amp. Condemning Test Required >120mA As Requested One leg being more than 75% of output voltage to earth. As Requested Page 26 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.10 TMG G1492 Compensating Capacitors Investigation and Test Test Impedance © RailCorp Issued December 2010 Test Equipment AC Current Clamp and FSM Test Point Terminals Voltage across the capacitor, and current through the capacitor at the track frequency. Readings Checks Impedance is Voltage divided by the current. (Z=V/I) The 33uF cap. for 1700Hz, and 2000Hz tracks impedance should be in the range of 1.9 to 3.4 ohms. The 22uF cap. for 2300Hz, and 2600Hz tracks impedance should be in the range of 2.2 to 3.8 ohms. UNCONTROLLED WHEN PRINTED Action If Not Compliant Condemning Check connections or replace capacitor. Impedance outside the range. Test Required As Requested Page 27 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.11 TMG G1492 Spark Gap Investigation and Test Test Test Equipment DC Volts Readings Checks Stanchion or Structure to Rail Connection Range: >3Vdc & <115Vdc Voltage should vary with electric train movements. Voltages < 3Vdc may occur if no electric trains are in the area. DC Tong Meter Connection from rail to structure or stanchion Not greater than minimum sensitivity of tong meter Should be zero current AC Current clamp Connection from rail to structure or stanchion Not greater than minimum sensitivity of tong meter Should be zero current DMM on Vdc DC Current AC Current Test Point Terminals Action If Not Compliant Report to Electrical Discipline any spark gap outside the condemning limits Report to Electrical Discipline any spark gap outside the condemning limits Report to Electrical Discipline any spark gap outside the condemning limits Condemning Test Required <3Vdc or >115Vdc Level 1, 2 and 3 See note. Measurable current Level 1, 2 and 3 See note. Measurable current Level 1, 2 and 3 See note. CAUTION Electrical safety issues exist relating to Over Head Wiring structures. Refer to Signalling Maintenance Procedure TMG J042 Safety Issues for Signalling Personnel for more details. Note: © RailCorp Issued December 2010 Only one of these three tests is required to test a spark gap. UNCONTROLLED WHEN PRINTED Page 28 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.12 TMG G1492 Electrolysis bond Investigation and test Test Test Equipment Test Point Terminals Readings Action If Not Compliant Inspect connections and Store 54. Visual and Physical Checks Store 54 Balance DMM on Vac Store 54 Impedance AC current clamp and FSM Leakage current AC current clamp and FSM Note: Checks Measure voltage from centre to each rail connection. Voltage across Store 54 and current. Measure track circuit current in electrolysis connection Voltages approximately same Each half of choke should be the same. Impedance of Store 54 not loading the track. No track circuit current should be leaving or entering the track via the electrolysis bond. Condemning Test Required Visible defects Level 1 Check connections and Store 54. > 10% difference. Level 1 Replace Store 54 <500 ohms at track frequency. See Note. As requested. Find and correct leakage path. > 0.1A As requested Impedance across Store 54 should be 30 ohms at 50Hz, 1020 ohms at 1700Hz, and 1560 ohms at 2600Hz. DC resistance of each leg of Store 54 to centre tap is 20 milliohms. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 29 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.13 TMG G1492 Impedance Bond Investigation and Test Test Test Equipment Test Point Terminals Readings Inspect bond for signs of damage Visual Rain cover when mounted vertically. 2000R/AF Inspect resonating capacitor box (when fitted). Visual See Note 1, and Note 2. Check for Traction Return balance 2 off DC Tong for traction Impedance bond side leads. DC Rail currents are similar with variance <10% FSM (V1) Rail to Rail Voltage (V2) Resonating winding Voltage The Resonating winding Voltage (V2) should be >60 times the rail to rail voltage (V1) FSM (V1).Up Rail to Imp. bond 4 way. (V2).Dn Rail to Imp. bond 4 way. V1 ≈ V2 2000R/AF Resonating winding Test Voltage Comparison Up and Down Rails to Neutral Lead Checks Connections secure. Side leads are equal lengths. Bond okay. Capacitor links securely open, or closed. Transzorb not fitted across capacitors. MOV (B32K385) fitted. Turns ratio of resonating winding. Action If Not Compliant Condemning Test Required Repair/Replace Visible defects Repair/Replace Visible defects Level 1, 2 and 3 Check connections, bond, side leads Variance >33% Level 1, 2 and 3 < 40 times As Requested > +/-20% difference. As Requested Level 1, 2 and 3 Try to re-resonate bond and if unable to achieve acceptable value then do impedance test. Check connections and possible rail faults to earth. Replace impedance bond if no other cause found. Note 1: If the 2000R/AF Impedance bond is resonated then typically the resonating capacitors should be about 9nF for 1700Hz, 5.7nF for 2000Hz, 4.7nF for 2300Hz, or 3.2nF for 2600Hz. Lower capacitor values should be used for tracks with a DPU. During the 1990's higher capacitor values were used, which are no longer recommended. Note 2: The 2000R/AF Impedance bond resonation is affected by capacitance of the MOV (~1.5nF) protecting the capacitors. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 30 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Impedance Bond Investigation and Test (Continued) Test Test Equipment Side Lead Current AC Current Clamp FSM Test Point Terminals Each individual side lead Readings Checks All individual measurements should be equal Can have errors due to large changes in DC currents. (V)=Rail to Rail (I)=Sum of a set of side lead currents Z=V/I 17 to 26 Ω AC Current Clamp FSM (V)=Rail to Rail (I)= Sum of a set of side lead currents Z=V/I Not Resonated: 2 to 3 Ω. Resonated. 10 to 30Ω. Impedance bond loading the track. See Note 3. CIT1400 Impedance bond impedance AC Current Clamp FSM (V)=Rail to Rail (I)=S Sum of a set of side lead currents Z=V/I Not Resonated: 9 to 15 Ω. Resonated. 1 to 4 Ω Impedance bond loading the track. See Note 3 and 4. 2000R/AF Secondary coil resistance. DMM ohms scale Across winding 1.5 to 2 ohms. MJS, MJX, Macolo Impedance Bond Impedance 2000R/AF Impedance bond impedance AC Current Clamp FSM Impedance bond loading the track. See Note 3. Action If Not Compliant Check connections and possible rail faults to earth. Replace impedance bond if no other cause found. Replace bond. Not Resonated: Replace bond. Resonated: Re-resonate bond. If unable to reresonate, check coil. Not Resonated: Replace bond. Resonated: Check capacitor, and coil. Replace bond. Condemning > +/-10% difference. <8 Ω Test Required As Requested As Requested Not Resonated: < 1.5 Ω Resonated: <8 or >40 Ω As Requested Not Resonated: <4Ω Resonated: >9Ω As Requested <1 ohm or >3 ohms As Requested. Note 3: This test is normally only used for mid-track impedance bonds as impedance measurements at Tx end have the track in parallel with the bond, and at Rx end have the ETU in parallel with the bond. This typically results in significantly lower impedances measured for impedance bonds at the Tx end, or Rx end of a track. Note 4: CIT1400 bonds should only be resonated for tracks longer than 600m or when two bonds are installed on the track. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 31 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Impedance Bond Investigation and Test (Continued) Test Test Equipment Vac Case to Resonating Coil Leads DMM on Vac 20K Shunt Vdc across impedance bond Note 5: © RailCorp Issued December 2010 Precision DMM on Vdc. Eg Fluke 187 or 189. Test Point Terminals (V1) Coil Lead (1) to Case. (V2) Coil Lead (2) to Case Rail connection bus bar to Rail connection bus bar. Can be from palm to palm of side lead connections. Readings Checks V1 <0.5Vac V2 < 0.5Vac < 10mV DC Value will vary with train movement. Ignore readings with train on track circuit. See Note 5. Traction current balance. Action If Not Compliant Condemning Verify by megger test and replace impedance bond. V1 >0.5Vac or V2 > 0.5Vac Further investigation as to reason for traction imbalance. > 200mV for 2000R > 300 mV for Macolo > 350mV for other bonds. Test Required As Requested As Requested If using Min/Max then a suitable scale (eg 500mV) must be manually set before Min/Max is selected. UNCONTROLLED WHEN PRINTED Page 32 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.14 TMG G1492 Receiver Unit Investigation and Test Test Equipment Test Visual and Physical Checks Hand tools Visual Test Point Terminals Inspect and check all terminations and Rx version. Readings Checks Action If Not Compliant Condemning Terminations effective and secure Check Mounting and environment Correct as required Visible defect or Rx version is less than V34.1. DMM R+/R- Acceptable Range 50Vdc to 65Vdc Track Receiver Input Voltage FSM Location Track Terminals Comparison to History card value. Receiver Monitor Voltage Track Unoccupied FSM Monitor voltage See Note 1. Drop Shunt Test Variable Shunt Box / DMM Relay Output Voltage Zero Feed Receiver Voltage Track Stick contacts resistance Note 1: © RailCorp Issued December 2010 DMM on Vac DMM on ohms Rail to Rail Between 0.8 and 1.2 Ω Monitor voltage Take readings with Tx feed disconnected Should be < 250mV. Track Relay A1/A2 (stick finger). Typically less than 2 ohms per contact. Change Receiver Investigate connections from Rx TU to Rx. Identify and correct cause or readjust track circuit. Readjust or Refer to DSE. DPU may be higher. <40Vdc or >65Vdc More than 25% change from History Card. <0.9 or >1.2Vac Test Required Level 1, 2 and 3 Level 1, 2 and 3 Level 1, 2 and 3 Track Circuit History Card Level 1, 2 and 3 Track Circuit History Card Normal power: <0.7 Ω or >1.3 Ω Low power: <1.0 Ω or >2.0 Ω Level 1, 2, and 3 Track Circuit History Card Interference from same freq. tracks. Investigate source of supply. >400mV Level 3 – Detailed Investigation Track Circuit History Card Measure resistance with receiver deenergised. Replace relays with HR contact/s. >10 ohms Level 3 Detailed investigation Drop away voltage is 0.8V, and the monitor voltage saturates at 1.2Vac. UNCONTROLLED WHEN PRINTED Page 33 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Receiver Unit Investigation and Test (Continued) Test Test Equipment Receiver Monitor Voltage, Track Shunted DMM on Vac Fixed Shunt Track Stick Voltage Drop during pickup. DMM Vdc set for Fast or peak min/max Track Relay A1/A2 (stick finger) (Meter set up with relay de-energised.) Adjacent Frequency FSM Monitor Voltage Adjacent frequency should be less than 100mV. FSM Monitor Voltage The measured value should not change by more than 50mV. Beating Note 2: © RailCorp Issued December 2010 Test Point Terminals Readings Checks Action If Not Compliant Condemning Use 0R15 shunt at Rx TU. Operation of Track. Zero feed test. Readjust track. >400mV Track Circuit History Card Maximum between 0V and 2Vdc (Once relay energised) Voltage drop on track stick contacts during pickup. Test pick-up and holding path for HR contact/s. >3V drop across contacts. As Requested Investigate RX tuned loop. Beating with other track circuits. Isolate and find source of interfering signal. See Note 2. > 1/3 of voltage from own frequency. Changes of more than 50mV when observed for 10 seconds. Test Required As Requested As Requested Fluctuating Rx voltage can occur due to differing series impedances of Tuning units at upper and lower frequencies. The Adjacent Frequency and Zero feed tests are the preferred method to find interfering signals for this type of track circuit. UNCONTROLLED WHEN PRINTED Page 34 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 Receiver Unit Investigation and Test (Continued) Test Test Equipment Receiver Input current from track. DMM on Iac Receiver current from power supply DC Tong Meter N24 Receiver Track Input impedance DMM Location term. Vac and Iac. RX Input voltage earth balance © RailCorp Issued December 2010 DMM on Vac Test Point Terminals In series with location terminals Location Track Terminals and earth bar. Readings Checks 15mA to 100mA 0.2Amps to 0.5Amps with relay up. Approx 0.05 Amps with relay down. Rx Input Z approx. 24Ω and varies with sensitivity setting. About 50% of input voltage from each leg to earth. Earth fault inside modules or wiring insulation. UNCONTROLLED WHEN PRINTED Action If Not Compliant Condemning Test Required Find and correct cause or readjust track. <15mA As Requested Change Receiver >0.7 Amps As Requested Analysis by Engineer. Determination by Engineer. As Requested Test surge protectors. Test insulation resistance of wiring. Replace modules. One leg being more than 90% of track voltage to earth and the other leg being less than 10% of track voltage to earth. As Requested Page 35 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 8.15 Receiver Lockup Investigation and Test 8.15.1 Initial Receiver check Measure B24/N24 on receiver. If below 20V then correct power supply voltage first. The 24V led turns off below 16 volts, and turns on above 19.5V. Power off and power on the receiver and check that it restarts. If the receiver re-starts then perform the following checks otherwise replace the receiver. Tap the receiver about 50mm back from the monitor terminals or the right hand side. Confirm that the receiver does not restart or lockup. This checks the stability of the brown out relay due to vibration. Check the manufacture and/or repair date of the receiver. Receivers manufactured or repaired prior to November 2004 use an electrolytic capacitor as C19. This capacitor has been changed to a polyester type since November 2004. Degradation of C19 in receivers dated prior to November 2004 can cause intermittent lockups before a complete failure. Receivers with a manufacture and/or repair date prior to November 2004 should be replaced after a lockup. 8.15.2 Receiver with contacts in the receiver power circuit. Power off receiver, and remove track relay. Then power on receiver and measure receiver B24/N24 voltage, which must be greater than 22 volts. Otherwise check the back proving track stick contacts. Power off receiver, and restore track relay. Then power on receiver and measure receiver B24/N24 voltage, which must be greater than 22 volts. Otherwise check track relay stick contact. 8.15.3 Receiver with contacts in the track relay circuit Check RC snubber or diode is fitted across track relay coil. If no RC snubber or diode fitted then arrange for Signal design to fit a snubber or diode to the track relay. 8.15.4 Receiver fed from a TU Check the tightness of back nuts on Tx and Rx TUs. Westinghouse changed the design of the Tu in September 2002 to improve the effectiveness of the connections to eliminate this type of problem. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 36 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline TMG G1492 The TUs made after September 2002 and the modified TUs were produced to design out the main causes of intermittent connections that cause significant amplitude changes, which can cause the Rx to lockup. Check millivolt drop on all associated TU connections from/to rail. This includes both TU in the TX tuned loop, and both TU in the RX tuned loop. <5mV per connection. TU connections on up and down rail should be the similar. Check rail connections in tuned loop. This includes for both TU in the TX tuned loop, and for both TU in the RX tuned loop. <20mV per connection. Rail connections on up and down rail should be the similar. Note: 8.15.5 Rail connection checks are not required for direct web welded connections. TU connections still need to be checked. Receiver fed from a DPU The drop shunt should be > 1 ohm so that the receiver is not over energised when a train shunt is approaching the DPU. Voltage drops across location disconnect terminals are less than 5mV. Traction return current harmonics from a millennium train could have been the cause. 8.15.6 Electrical noise Check for noise sources like un-snubbed QN or QB style relays installed with-in 300mm of the Receiver or input wiring from the track circuit cable terminals to the Receiver or DPU AMP longer than 5m and mixed in with Q relay circuit wiring. Suppress electrical noise by fitting a snap on ferrite choke around the input wires close to the Receiver terminals. Snap on ferrite chokes like RS 2606486 or Farnell 9640444 are appropriate. Alternatively organise for a signal design to snub relays as necessary. The design must snub all relays (that need snubbing) mounted with-in 300mm of Receiver as a minimum. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 37 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 8.16 TMG G1492 Surge Protection Investigation and Tests Test Test Equipment 3Y20 Gas Arrestor Visual Inspection Visual 3Y20 Gas Arrestor Test Arrestor Tester MOV on 24V bus Visual Inspection Visual Test Point Terminals Unplug unit and plug into arrestor tester. Readings Approximately 290Vdc for Line to earth. MOV on 24V bus DMM on Ohmmeter, and diode test. Disconnect one leg and measure across the MOV Ohmmeter should read >10 meg ohm. Diode test should read OL in both directions. MOV on 24V bus Arrestor Test Arrestor Tester Disconnect one leg and measure across the MOV Approximately 40Vdc. MOV on 120V bus Visual Inspection Visual MOV on 120V bus Arrestor Test Arrestor Tester © RailCorp Issued December 2010 Disconnect one leg and measure across the MOV Approximately 210Vdc. Checks Action If Not Compliant Condemning No visible cracking, splitting, burn marks or blackening of the case. Replace arrestor Visible defects Level 3 – Detailed Investigation Break down voltage Replace arrestor <220Vdc >360Vdc Level 3 – Detailed Investigation No visible cracking, splitting, or burn marks. Replace MOV Visible defects As Requested Replace MOV Ohmmeter reading of <10 meg ohm or Diode test of less than OL. As Requested Maximum operating voltage Replace MOV <36Vdc >45Vdc As Requested No visible cracking, splitting, or burn marks. Replace MOV Visible defects As Requested Maximum operating voltage Replace MOV <190Vdc >230Vdc As Requested UNCONTROLLED WHEN PRINTED Test Required Page 38 of 39 Version 1.1 RailCorp Engineering Procedure — Signals FS2500 Track Circuit Test and Investigation Guideline 9 TMG G1492 mV AC measurements in electrically noisy environments mV AC measurements made in electrically noisy environments can have significant errors due to induced currents, and meter input impedance. Measurements made for mV drop on rail connections for audio frequency track circuits can have errors due to the high currents (up to 20A) and higher frequencies (up to 2600Hz) from the track circuit as well as harmonics in the electric traction currents for trains. A test measurement can be made with both meter probes touching same connection point. Any reading on the DMM will be the residual reading that the meter is capable of in that environment. Move the meter leads and check if the readings vary significantly. If the readings vary significantly then twist the meter leads (about 10 times) and repeat the test. If the residual meter reading is not significantly less (< ½ ) than the value to be measured then the meter is not suitable for the measurement. A comparison of commonly used meters is: • Fluke 87 typically has a minimum valid reading of 2mV. It is the least sensitive to the electrical environment. • Fluke 87 III, or V typically has a minimum valid reading of 1mV. It is slow to show the reading, as it will gradually decrease to a stable reading when measuring low voltages. • Fluke 189 typically has a minimum valid reading of 0.1mV with leads twisted. It has the best resolution but is most sensitive to the electrical environment. © RailCorp Issued December 2010 UNCONTROLLED WHEN PRINTED Page 39 of 39 Version 1.1