PJM Generator Interconnection Request Queue #B15 Morgantown / Oak Grove 230kV Impact Study Report March 2001 DMS#134867 General Project B15 Interconnection Customer, Orion, requested interconnection of a 550 MW (summer) gas-fired combined cycle generating facility to be located approximately 5 miles north of the Hawkins Gate substation which is located in Charles County, Maryland. The generating facility is scheduled to be commercial by June 2003. Pepco's four Morgantown-Talbert/Oak Grove 230 kV circuits are located next to the proposed generating site; two circuits were tapped for the interconnection of project B15. Direct Connection Requirements Shown below is a one-line diagram for the proposed interconnection of Project #B15 generation to the two Morgantown-Talbert/Oak Grove 230 kV circuits. 23087 23085 23085 23086 23086 B15 23084 230 157 23084 to Talbert - Oak Grove to Hawkins Gate Morgantown 23087 157 to Utility Distribution Circuit Project B15 Interconnection Customer will assume responsibility for design and construction of the new 230kV substation and connection to the two Morgantown - Oak Grove 230 kV circuits. PEPCO will review the design, and perform the necessary construction management and commissioning testing. In addition, PEPCO will also need to reroute the existing telecommunication optical fiber circuits, install EMS and relay equipment interfaces, and make all associated upgrades to existing equipment. The estimated cost of the work to be done by Confidential 1 PEPCO is $3.7 million. The PEPCO work can be done concurrent with the Interconnection Customer’s constructon of the 230kV substation. Network Impacts The system, as planned, was evaluated for compliance with reliability criteria. The Morgantown B15 project was studied as 550MW capacity. The results are summarized below. Normal System No identified problems. Single Contingency (MAAC Criteria IIA) No identified problems. Second Contingency (MAAC Criteria IIB) No identified problems. Multiple Facility Contingency (MAAC Criteria IIC) No identified problems. Generator Deliverability No identified problems. Stability (MAAC Criteria IV) No identified problems. See attachment #1 for the fault cases evaluated. The range of contingencies evaluated was limited to that necessary to demonstrate compliance with MAAC Reliability Criteria IV. Note: While the stability analysis has been performed at extreme system conditions, there is a potential that evaluation at higher levels of generator output over a range of load levels would disclose unforeseen stability problems. The MAAC yearly reliability analysis to be performed to test all system changes will include this evaluation. Any problems uncovered will need to be resolved. CETO/CETL (MAAC Criteria III / VIIB) No identified problems. Short Circuit Analysis No identified problems. System Reinforcements and Cost Allocation None. Confidential 2 ATTACHMENT #1 (Morgantown/Oak Grove Project B15) 2005 Light Load Stability Faults ALL FAULTS ARE STABLE b15-1a 3ph @ B15 230 kV on B15 - Morgantown 23084 b15-1b 3ph @ B15 230 kV on B15 - Morgantown 23086 b15-1c 3ph @ B15 230 kV on B15 – Oak Grove 23084 b15-1d 3ph @ B15 230 kV on B15 – Oak Grove 23086 b15-1e slg @ B15 230 kV on B15 - Morgantown 23084, stuck at B15 (L/O 23086) b15-1f slg @ B15 230 kV on B15 - Morgantown 23086, stuck at B15 (L/O 23084) b15-1g slg @ B15 230 kV on B15 – Oak Grove 23084, stuck at B15 (L/O 23086) b15-1h slg @ B15 230 kV on B15 – Oak Grove 23086, stuck at B15 (L/O 23084) b15-2a 3ph @ Morgantown 230 kV on Morgantown – B15 23076 b15-2b 3ph @ Morgantown 230 kV on Morgantown – Oak Grove 23077 b15-2c 3ph @ Morgantown 230 kV on Morgantown – Oak Grove 23085 b15-2d 3ph @ Morgantown 230 kV on Morgantown – B15 23086 b15-2e 3ph @ Morgantown 230 kV on Morgantown – Chalk Point 23071 b15-2f slg @ Morgantown 230 kV on Morgantown – Oak Grove 23085, stuck at Morgntwn (L/O Morg north bus) b15-2g slg @ Morgantown 230 kV on Morgantown – Chalk Point 23071, stuck at Morgntwn (L/O Morg north bus) b15-3a 3ph @ Chalk Point 230 kV on Chalk Point – Morgantown 23072 b15-3b 3ph @ Chalk Point 230 kV on Chalk Point – Oak Grove 23062 b15-3c 3ph @ Chalk Point 230 kV on Chalk Point – Bowie 23063 b15-3d 3ph @ Chalk Point 230 kV on Chalk Point 500/230 #6 b15-3e slg @ Chalk Point 230 kV on Chalk Point – Morgantown 23074, stuck at Chalk Point (L/O 23065) b15-3f slg @ Chalk Point 230 kV on Chalk Point – Bowie 23065, stuck at Chalk Point (L/O 23074) b15-4a 3ph @ Oak Grove 230 kV on Oak Grove – B15 23066 b15-4b 3ph @ Oak Grove 230 kV on Oak Grove – B15 23068 b15-4c slg @ Oak Grove 230 kV on Oak Grove – Burtonsville 23042, stuck at Oak Grove (L/O 23064) b15-4d slg @ Oak Grove 230 kV on Oak Grove – Burtonsville 23045, stuck at Oak Grove (L/O 23068) b15-5a slg @ Burches Hill 230 kV on Burches Hill – Alabama 23093, stuck at Burches Hill (L/O 23081) Confidential 3 b15-5b slg @ Burches Hill 230 kV on Burches Hill – Palmers Corner 23091, stuck at Burches Hill (L/O 23082) b15-5c slg @ Burches Hill 230 kV on Burches Hill 500/230 kV, stuck at Burches Hill (L/O 23092) b15-6a slg @ Chalk Point 500 kV on Chalk Point – Burches Hill, stuck at Chalk Point (L/O 500/230 #6) Fault # b15-1a b15-1b b15-1c b15-1d b15-1e b15-1f b15-1g b15-1h b15-2a b15-2b b15-2c b15-2d b15-2e b15-2f b15-2g b15-3a b15-3b b15-3c b15-3d b15-3e b15-3f b15-4a b15-4b b15-4c b15-4d b15-5a b15-5b b15-5c Fault Description 3ph @ B15 230 kV on B15 - Morgantown 23084 3ph @ B15 230 kV on B15 - Morgantown 23086 3ph @ B15 230 kV on B15 - Oak Grove 23084 3ph @ B15 230 kV on B15 - Oak Grove 23086 slg @ B15 230 kV on B15 - Morgantown 23084, stuck at B15 (L/O 23086) slg @ B15 230 kV on B15 - Morgantown 23086, stuck at B15 (L/O 23084) slg @ B15 230 kV on B15 - Oak Grove 23084, stuck at B15 (L/O 23086) slg @ B15 230 kV on B15 - Oak Grove 23086, stuck at B15 (L/O 23084) 3ph @ Morgantown 230 kV on Morgantown - B15 23076 3ph @ Morgantown 230 kV on Morgantown - Oak Grove 23077 3ph @ Morgantown 230 kV on Morgantown - Oak Grove 23085 3ph @ Morgantown 230 kV on Morgantown - B15 23086 3ph @ Morgantown 230 kV on Morgantown - Chalk Point 23071 slg @ Morgantown 230 kV on Morgantown - Oak Grove 23085, stuck at Morgntwn (L/O Morg north bus) slg @ Morgantown 230 kV on Morgantown - Chalk Point 23071, stuck at Morgntwn (L/O Morg north bus) 3ph @ Chalk Point 230 kV on Chalk Point - Morgantown 23072 3ph @ Chalk Point 230 kV on Chalk Point - Oak Grove 23062 3ph @ Chalk Point 230 kV on Chalk Point - Bowie 23063 3ph @ Chalk Point 230 kV on Chalk Point 500/230 #6 slg @ Chalk Point 230 kV on Chalk Point - Morgantown 23074, stuck at Chalk Point (L/O 23065) slg @ Chalk Point 230 kV on Chalk Point - Bowie 23065, stuck at Chalk Point (L/O 23074) 3ph @ Oak Grove 230 kV on Oak Grove - B15 23066 3ph @ Oak Grove 230 kV on Oak Grove - B15 23068 slg @ Oak Grove 230 kV on Oak Grove - Burtonsville 23042, stuck at Oak Grove (L/O 23064) slg @ Oak Grove 230 kV on Oak Grove - Burtonsville 23045, stuck at Oak Grove (L/O 23068) slg @ Burches Hill 230 kV on Burches Hill - Alabama 23093, stuck at Burches Hill (L/O 23081) slg @ Burches Hill 230 kV on Burches Hill - Palmers Corner 23091, stuck at Burches Hill (L/O 23082) slg @ Burches Hill 230 kV on Burches Hill 500/230 kV, stuck at Burches Hill (L/O 23092) b15-6a slg @ Chalk Point 500 kV on Chalk Point - Burches Hill, stuck at Chalk Point (L/O 500/230 #6) Confidential 4 LOCAL Primary Stuck Breaker 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.2 4.4 4.2 4.2 4.2 4.2 4.2 4.2 4.7 4.2 4.4 3.2 11.6 11.6 11.6 11.6 11.6 11.6 12.3 12.3 12.3 12.3 15.9 15.4 15.6 12.6 REMOTE Primary 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 4.7 3.4 4.7 4.7 4.7 4.7 4.7 4.7 5.2 4.7 6.6 3.2 @ Possum 4.2 @ Burch ATTACHMENT #2 Unit Capability Data Gross MW Output GSU MW Losses Unit Auxiliary Load MW Station Service Load MW Net MW Capacity Net MW Capacity = (Gross MW Output - GSU MW Losses* – Unit Auxiliary Load MW - Station Service Load MW) Queue and Position/Project Name/Unit ID(s): ________ B15/Morgantown-Oak Grove/CT1, CT2 Estimated In-Service Date (mm/dd/yy)______________________________________ June 2003 Primary Fuel Type: ____________________________________________________ Natural Gas Maximum Summer (92º F ambient air temp.) Net MW Output**: ______________ 157 (Note 1) Maximum Summer (92º F ambient air temp.) Gross MW Output: ______________________161 Minimum Summer (92º F ambient air temp.) Gross MW Output: _______________________96 Maximum Winter (30º F ambient air temp.) Gross MW Output: _______________________211 Minimum Winter (30º F ambient air temp.) Gross MW Output: ________________________126 Reactive Power Capability at Maximum Summer Net MW Output: _________________+98, -52 Individual Unit Auxiliary Load at Maximum Summer MW Output (MW/MVAR): ________ 1.8 Individual Unit Auxiliary Load at Minimum Summer MW Output (MW/MVAR): _________ 1.8 Individual Unit Auxiliary Load at Maximum Winter MW Output (MW/MVAR): _________ 1.8 Individual Unit Auxiliary Load at Minimum Winter MW Output (MW/MVAR): _________ 1.8 Station Service Load (MW/MVAR): ______________________________________ 0.4 (Note 2) Please provide any comments on the expected capability of the unit: Note 1: Transformer Losses = 1.21 MW. Note 2: Represents ~ 1/3 of CC Unit. Gross Power of CC unit at 92 F =161 x 2 + 243 = 565 MW Gross. Net Power of CC Unit at 92 f = 157 x 2 + 230 = 544 MW Net. Confidential 5 Unit Generator Dynamics Data Queue and Position/Project Name/Unit ID(s): ________ B15/Morgantown-Oak Grove/CT1, CT2 MVA Base (upon which all reactances, resistance and inertia are calculated): _____________222 Nominal Power Factor: 0.85 Terminal Voltage (kV): ______________________________________________________ 16.5 Unsaturated Reactances (on MVA Base) Direct Axis Synchronous Reactance, Xd(i) :___________________________________________ 183.39 Direct Axis Transient Reactance, X’ d(i):________________________________________________ 23.43 irect Axis Sub-transient Reactance, X”d(i): _____________________________________________ 18.14 Quadrature Axis Synchronous Reactance, Xq(i) : _____________________________________ 178.63 Quadrature Axis Transient Reactance, X’ q(i): ___________________________________________ 41.3 Quadrature Axis Sub-transient Reactance, X”q(i) :______________________________________ 17.89 Stator Leakage Reactance, Xl :__________________________________________________________ 14.24 Negative Sequence Reactance, X2(i): ___________________________________________________ 18.01 Zero Sequence Reactance, X0 : _________________________________________________________ 19.08 Saturated Sub-transient Reactance, X”d(v) (on MVA Base): ___________________________________ 16.68 Armature Resistance, Ra (on MVA Base): ______________________________________________________ 0.07 Time Constants (seconds) Direct Axis Transient Open Circuit, T’do :______________________________________________ 9.921 Direct Axis Sub-transient Open Circuit, T”do : _________________________________________ 0.043 Quadrature Axis Transient Open Circuit, T’qo : __________________________________________ 1.1 Quadrature Axis Sub-transient Open Circuit, T”qo : ____________________________________ 0.077 Shaft Inertia (combined Generator/Prime Mover), H (kW-sec/kVA, on KVA Base):______ 6.543 Speed Damping, D (typically 0 to 2): ______________________________________ 0 (assumed) Saturation Values at Per-Unit Field Voltages [S(1.0), S(1.2)]:_________________0.0815, 0.3761 Units utilize an ESAC2A (1992 IEEE type AC2A) exciter model. Confidential 6 Unit GSU Data Queue and Position/Project Name/Unit ID(s): ________ B15/Morgantown-Oak Grove/CT1, CT2 Generator Step-up Transformer MVA Base: _______________________________________225 Generator Step-up Transformer Impedance (R+jX, or %, on transformer MVA Base): _____ 14% Generator Step-up Transformer Reactance-to-Resistance Ratio (X/R):____________________35 Generator Step-up Transformer Rating (MVA):______________ 135.54/180.27/225, OA/FA/FA Generator Step-up Transformer Low-side Voltage (kV):_____________________________ 16.5 Generator Step-up Transformer High-side Voltage (kV): _____________________________230 Generator Step-up Transformer Off-nominal Turns Ratio (per-unit, typically 1.0): _________ 1.0 Generator Step-up Transformer Number of Taps and Step Size (%): ____________ 5 of +/-2.5% GSUs are not shared. Confidential 7 Unit Capability Data Gross MW Output GSU MW Losses Unit Auxiliary Load MW Station Service Load MW Net MW Capacity Net MW Capacity = (Gross MW Output - GSU MW Losses* – Unit Auxiliary Load MW - Station Service Load MW) Queue and Position/Project Name/Unit ID(s): _____________ B15/Morgantown-Oak Grove/ST1 Estimated In-Service Date (mm/dd/yy): __________________________________B15 June 2003 Primary Fuel Type: ______________________________________________ Natural Gas/HRSG Maximum Summer (92º F ambient air temp.) Net MW Output**: ______________ 230 (Note 1) Maximum Summer (92º F ambient air temp.) Gross MW Output: ______________________243 Minimum Summer (92º F ambient air temp.) Gross MW Output: ______________________126 Maximum Winter (30º F ambient air temp.) Gross MW Output: _______________________293 Minimum Winter (30º F ambient air temp.) Gross MW Output: ________________________147 Reactive Power Capability at Maximum Summer Net MW Output: ________________+142, -75 Individual Unit Auxiliary Load at Maximum Summer MW Output (MW/MVAR): _______ 11.9 Individual Unit Auxiliary Load at Minimum Summer MW Output (MW/MVAR): ________ 10.0 Individual Unit Auxiliary Load at Maximum Winter MW Output (MW/MVAR): ________ 13.0 Individual Unit Auxiliary Load at Minimum Winter MW Output (MW/MVAR): _________ 6.5 Station Service Load (MW/MVAR): __________________________________ 0.4 MW (Note 2) Please provide any comments on the expected capability of the unit: Note 1: Transformer Loss =1.16 MW Note 2: brepresents 1/3 total CC Unit * GSU losses are expected to be minimal. Confidential 8 ** Your project’s declared MW, as first submitted in Attachment N, and later confirmed or modified by the Impact Study Agreement, should be based on either the 92 o F Ambient Air Temperature rating of the unit(s) or, if less, the declared Capacity rating of your project. Unit Generator Dynamics Data Queue and Position/Project Name/Unit ID(s): _____________ B15/Morgantown-Oak Grove/ST1 MVA Base (upon which all reactances, resistance and inertia are calculated): _____________276 Nominal Power Factor: 0.85 Terminal Voltage (kV): ________________________________________________________18 Unsaturated Reactances (on MVA Base) Direct Axis Synchronous Reactance, Xd(i) :___________________________________________ 210.69 Direct Axis Transient Reactance, X’ d(i):________________________________________________ 26.44 Direct Axis Sub-transient Reactance, X”d(i) : ____________________________________________ 20.4 Quadrature Axis Synchronous Reactance, Xq(i) : _____________________________________ 205.22 Quadrature Axis Transient Reactance, X’ q(i): __________________________________________ 45.22 Quadrature Axis Sub-transient Reactance, X”q(i) :______________________________________ 20.12 Stator Leakage Reactance, Xl :__________________________________________________________ 15.96 Negative Sequence Reactance, X2(i): ___________________________________________________ 20.26 Zero Sequence Reactance, X0 : _________________________________________________________ 10.37 Saturated Sub-transient Reactance, X”d(v) (on MVA Base): ___________________________________ 18.77 Armature Resistance, Ra (on MVA Base): ______________________________________________________ 0.08 Time Constants (seconds) Direct Axis Transient Open Circuit, T’do :____________________________________________ 10.127 Direct Axis Sub-transient Open Circuit, T”do : _________________________________________ 0.043 Quadrature Axis Transient Open Circuit, T’qo : _________________________________________ 1.13 Quadrature Axis Sub-transient Open Circuit, T”qo : ____________________________________ 0.075 Shaft Inertia (combined Generator/Prime Mover), H (kW-sec/kVA, on KVA Base):______ 7.514 Speed Damping, D (typically 0 to 2): ______________________________________ 0 (assumed) Saturation Values at Per-Unit Field Voltages [S(1.0), S(1.2)]:_______________0.07395, 0.35201 Unit utilizes an ESAC2A (1992 IEEE type AC2A) exciter model. Confidential 9 Unit GSU Data Queue and Position/Project Name/Unit ID(s): _____________ B15/Morgantown-Oak Grove/ST1 Generator Step-up Transformer MVA Base: _______________________________________280 Generator Step-up Transformer Impedance (R+jX, or %, on transformer MVA Base): _____ 14% Generator Step-up Transformer Reactance-to-Resistance Ratio (X/R):____________________35 Generator Step-up Transformer Rating (MVA):_______________ 168.67/224.34/280 OA/FA/FA Generator Step-up Transformer Low-side Voltage (kV):_______________________________18 Generator Step-up Transformer High-side Voltage (kV): _____________________________230 Generator Step-up Transformer Off-nominal Turns Ratio (per-unit, typically 1.0): _________ 1.0 Generator Step-up Transformer Number of Taps and Step Size (%): ____________ 5 of +/- 2.5% GSU is not shared. Confidential 10