Specification Land and Trackwork Surveys SECTION 22 Survey control generally LAND AND TRACKWORK SURVEYS 1 Survey control shall be established by the Contractor at a density sufficient to achieve the specified accuracy. All surveys shall be in SI metric units, and shall be co-ordinated by northings and eastings referenced to Ordnance Survey National Grid. (22.001) Permanent ground markers 2 Permanent ground markers (P.G.M.) intended for survey control shall be constructed at all control stations and primary and subsidiary traverse stations and shall be placed in stable and protected locations out of trafficked areas and suitable for frequent access and possible use for future setting out. Where practicable, P.G.M.s shall not be located within 3.0 metres of any rail. P.G.M.s may also be used as bench marks. Where a preferred marker location is away from the main survey area, or outside the Railtrack boundary in private lands, the Contractor shall agree the marker location with the land owner before such markers are installed. For string line survey pegs, the taping offset dimension shall not exceed 5.0 metres without triangulation to the pegs, and string line pegs shall be placed not more than 2.0 metres from the nearest rail. Unmarked pegs shall not be left so as to constitute a tripping hazard. Where possible ground markers shall be positioned at a density of at least two stations per hectare in open ground, and at approximately 100 metres intervals for longitudinal trackwork surveys. The distance between permanent ground markers may be increased in open locations, but the interval used shall allow for survey closure to the specified accuracy utilising the survey equipment proposed by the Contractor. New instrument stations shall be established either by conventional traversing or by GPS baselines between adjacent stations. Each instrument station shall be visible from and connected to at least two other survey stations. New instrument stations shall be established to better than ± (3 mm + one part in 30,000) horizontally and ± (3 mm + 3 mm /km) vertically relative to the nearest P.G.M. Domed brass rivets of suitable design shall be placed in permanent structures by drilling and fixing with an epoxy resin compound or internal clamping device. Earth anchors and ground markers shall be used in open ground. Other designs for survey stations may be used subject to prior agreement by the Employer’s Representative. Specification Land and Trackwork Surveys The grid to which the site survey shall be related shall be (INSERT). The accuracy to which the survey grid shall be fixed to the Ordnance Survey National Grid shall be /±20 mm. /±150 mm. / (22.002) Accuracy 3 A closed ground control network shall be established prior to linking individual survey detail elements. The survey method shall be appropriate to the required accuracy. Adequate checks such as equipment calibration, survey closure methods and calculations shall be carried out for all survey techniques used to maintain the specified accuracy. Unless specified otherwise in the relevant Clause, the maximum error between permanent survey control stations shall not exceed 1 in 20,000. For distances between adjacent survey control stations of less than 200 metres, the maximum error shall not be greater than ± 10 mm. Unless specified otherwise in the relevant Clause, the height difference between any two points used as permanent bench marks ½ shall not be in error by more than ± (12k ) mm, where k is the distance in kilometres between the two points being considered, or ± 5 mm, whichever is the greater, except for river to lake bed levels which shall be measured to ± 50 mm. The accuracy achieved in longitudinal distance, and height shall be quoted on all survey plans. (22.003) Schedule of survey control stations 4 A series of individual indexed diagrams shall be prepared by the Contractor detailing for each permanent survey control station: (i) general location, (ii) description of marker type, (iii) control station designations, (iv) survey grid co-ordinates, (v) reduced level to scheme datum, (vi) tie dimensions to at least three easily recognisable and durable features located within, if possible, 50 metres of the control station. A copy of the schedule of permanent ground markers shall be provided to the Employer's Representative. (22.004) Control diagrams for survey markers 5 A control network diagram defining the horizontal and vertical interrelationship between permanent survey control stations, including designation, distance, angles, reduced level, type etc shall be prepared by the Contractor. (22.005) Specification Land and Trackwork Surveys Level datum 6 All levels shall be related to Ordnance Datum Newlyn height datum except for isolated surveys where a level datum proposed by the Contractor may be used with the agreement of the Employer’s Representative. The value of the datum bench mark to which the survey is related shall be confirmed by check levelling out and back to at least one other existing permanent bench mark. The location, designation and value of the datum bench marks used shall be quoted on each survey plan. (22.006) Site bench marks 7 A minimum of three site bench marks shall be established on existing stable features at, where possible a minimum density of one per map sheet. A diagram shall be prepared for each site bench mark showing its location dimensioned to at least three easily recognisable and durable points located, if possible within 5.0 metres of the site bench mark. A simple plan shall be provided to the Employer’s Representative showing the vertical control network and the inter-relationships between bench marks. (22.007) Site details to be surveyed generally 8 The planimetric features to be surveyed shall be: (i) control points, (ii) buildings and structures, (iii) boundary features, (iv) roads, tracks and footpaths, (v) street furniture and visible service features, (vi) water, drainage and coastal features, (vii) slopes and earthworks, (viii) woods, trees and recreational areas, (ix) industrial features, (x) trackwork, bridges, structures, train operating equipment. The absolute plan position of any well defined point of detail shall be correct to within ± 0.3 mm root mean squared equivalent at the plan scale checked from the nearest survey control station. Co-ordinates and levels shall be obtained by direct measurement of each point except as follows: (i) where the ground surface is obscured by thick vegetation, Specification Land and Trackwork Surveys (ii) where there are expanses of water, the water level at the time of the survey shall be used, unless soundings have been specified, When height points are to be interpolated from a surveyed framework of levels, details of the Contractor's proposed method shall be submitted with the Tender. The method used shall define the ground surface to the same accuracy as direct measurement. Mature trees shall be identified by species and girths and spreads plotted. Overall extent of the canopy shall be shown where it is not possible to identify individual trees. Features which cannot be surveyed to the specified accuracy without extensive site clearance shall either be surveyed approximately and annotated accordingly or where specified in the Contract, arrangements shall be made to clear the Site to enable the survey to the specified accuracy to be undertaken. (22.008) Height information 9 Sufficient spot levels shall be surveyed such that true ground configuration is accurately represented on the plans. The maximum distance between adjacent spot levels shall be (INSERT). Ground survey spot levels on hard surfaces shall be correct to ± 10 mm r.m.s.e. except on ploughed or otherwise broken surfaces. Where specified, contours shall be shown at vertical intervals of 1.0 metre. At least 90% of all contours shall be correct to within one half of the specified contour interval. Any contour which can be brought within this vertical tolerance by moving its plotted position in any direction by an amount equal to 0.1 of the horizontal distance between contours, or 0.5 mm at plan scale, whichever is the greater, shall be considered as correct. Contours which cannot be surveyed to the specified accuracy without extensive site clearance shall be surveyed approximately and annotated accordingly on the plan. In flat areas where the horizontal distance between contours exceeds 50 mm at plan scale, supplementary spot levels shall be surveyed at intervals not exceeding 50 mm at plan scale, parallel to the contours. (22.009) Specification Land and Trackwork Surveys Underground services generally 10 For the services specified in Clause 22.011, underground service information may be taken from statutory authorities' or other service owners' record drawings and plotted to agree as closely as possible with surveyed surface features. For the services specified in Clause 22.011, accessible manhole covers and inspection chambers shall be lifted where permissible and a direct visual survey carried out. The number of underground access points and where possible the type of services, with numbers of cables or drains shall be identified. Routes of buried services between access points may be taken from record drawings and plotted to agree as close as practical with surveyed surface features. Railtrack personnel and other on site personnel with local knowledge shall be consulted, where available, to assist in identifying routes of buried services and utilities. The ends of inaccessible service routes shall be investigated initially by visual survey and for the services specified in Clause 22.011, supplementary surveyed by electronic or other tracing methods. For the services specified in Clause 22.011, verification by excavation shall be carried out. Excavation and backfilling shall be in accordance with Sections 50 and 51: Excavations. (22.010) Services to be surveyed 11 The schedule of services in the form of a tick list to be surveyed are listed in Table 22/1. Table 22/1 Service Specify service if applicable and insert where applicable !C! Records Direct Visual Electronic Excavation tracing Surface water drainage Foul drainage Water Gas Electricity Telecommunication Other services Other underground utility features RT signalling cables RT power cables The following data shall be recorded for each underground chamber, catchpit, manhole and the like: (i) shape of unit with principal plan dimensions together with sidewall and centre depths, Specification Land and Trackwork Surveys (ii) width and levels of all channels and pipes. Levels shall be taken at regular intervals and in any event at not more than 5.0 metres centres, (iii) invert level, material, location and diameter of all pipes, bellmouths and valves together with direction of flow, (iv) top and bottom water levels of all underground structures. Where information is derived from statutory authorities' or other Service owners' record drawings, a schedule shall be provided giving full details such as record office location, drawing number, scale etc. (22.011) Measured structure and building survey 12 The absolute plan position of any well defined detail shall be accurate to ± 0.3 mm r.m.s.e. at the specified plan scale, when checked from the nearest survey control station. Directly measured dimensions within building surveys shall be quoted to the nearest 10 mm. The following data shall be recorded for each bridge, retaining wall and the like: (i) vertical and horizontal clearances from rails, (ii) heights of parapets, soffit levels etc, (iii) alignment of track, (iv) dimensions of main structural members, (v) materials of construction, (vi) elevations. The following information shall be recorded for each building. (i) building outline, (ii) floor plans, (iii) roof plans, (iv) sections, (v) elevations. Further to Clause 22.003, the level of accuracy required is (INSERT). (22.012) Specification Land and Trackwork Surveys Accuracy for trackwork survey 13 All points shall be recorded to an accuracy of ± (5 mm + one part in 30,000) horizontally and ± (5 mm + 3 mm /km) vertically relative to the nearest P.G.M. Adjacent features within 10 metres shall be recorded to a tolerance not more than 5 mm. Lateral and vertical clearances to the track or road at bridges, tunnels, canopies or platform faces etc, shall be recorded to an accuracy of ± 3 mm. Directly measured fixed infrastructure dimensions more than 10 metres from the track may be quoted to the nearest 100 mm. (22.013) Survey interval for trackwork 14 The survey interval for trackwork shall be as follows: (i) On straight track, the running edge of the rails shall be surveyed at 10 metres intervals, (ii) On curved track, both rails shall be surveyed at 10 metre intervals for a radius greater than 500 metres, and at 5 metre intervals for a radius less than 500 metres. Where a Hallade type curve survey is specified, the curve survey half chords shall be marked out and used as the survey reference points on the curve. Chord points shall be related to mile posts or chainage mark, with chord point numbering starting at the top of the ramp London end of any station, with decreasing numbers towards London. (22.014) Information to be shown on drawings of trackwork survey 15 The following information and details shall be surveyed and provided on the trackwork survey plans: (i) running edges of railway tracks and check rails to curves, (ii) wing and check rails to S&C, location of switch tips and crossing noses of points, knuckles of diamonds, switch types and angle of crossings (iii) positions of rail welds, insulated and non insulated rail joints, adjustment switches, and twist rails, (iv) position of electrified conductor rails including feeder cabling, hook switches with numbers and end ramps, (v) all cable ducting, cables and lineside equipment. (The ownership and/or type shall be noted) eg posts, poles, lightning columns, cable markers, (vi) signal gantries, posts and bases, and ground signals together with signal numbers, (vii) a.c. electrification overhead line equipment gantries, masts, stays and bases), together with structure numbers, (viii) track drains, manholes, culverts, ducts etc including invert levels, Specification Land and Trackwork Surveys (ix) buildings, cabins, concrete or brick bases etc together with an indication of any overhangs, canopies etc, (x) buffer stops, (xi) platform coper edge and any non moveable platform furniture, (xii) overbridges - abutments, pier positions and numbers, (xiii) underbridges - parapets, centre girders (including heights are to be clearly stated on the plot) wheel timbers, and numbers, (xiv) both top and bottom of retaining walls, (xv) spot levels on areas of hard open ground at intervals not more than 10 metres, (xvi) signalling equipment, point machines, pump disconnection boxes, equipment cupboards, manifolds, pressure vessels, valves, (xvii) switch heater units, including type, (gas, electric, strip, cartridge, or pad) as applicable and controls, (xviii) any two levelling schemes within switch and crossing to be noted. units, pipes, Where structures are numbered, the structure number shall be included on drawings of the trackwork survey. Where datum plates are attached to structures, the location of the datum plates, and the information shown on the datum plates shall be included on drawings of the trackwork survey. Further detail shall be surveyed to an accuracy of ± 75 mm horizontally relative to adjacent features and ± (30 mm + 5 mm /km) vertically relative to the nearest P.G.M. (i) level crossing surfacing system, cattle-cum trespass guards and cattle grids, (ii) level crossing barriers or gates and operating equipment, associated road traffic lights, signs and telephones, (iii) start and finish of transitions, (iv) mile, half mile, and quarter mile posts and gradient boards with value, (v) approximate position of overhead power lines, telephone cables etc and warning boards, (vi) top and bottom of earthwork slopes together with any obvious change of slope and ballast profiles, Specification Land and Trackwork Surveys (vii) mature trees and areas of substantial vegetation, (viii) spot levels in areas of soft open ground, at intervals of not more than 20 metres, (ix) Railtrack Zone boundary, fence lines, stiles, gates etc together annotation of type where this is within 5 metres from the nearest rail of any running line. Where the boundary fence is more than 5 metres, the survey width may be limited to that distance unless important or relevant features, including the bottom of any embankments, occur between the 5 metre distance and the boundary fence in which case the survey shall be extended to include such features, (x) footpaths. The existing track type, eg C.W.R, jointed, flat bottom, bull head, including type of fastening and sleepers shall be shown with the extent indicated by arrows. Names or roads, streets, railway buildings and structures, and stations shall be shown. (22.015) Extent of trackwork survey 16 All lines having independent alignments or which may be affected by the proposed design shall be surveyed. Surveys shall extend a minimum 50 metres and where practicable 100 metres longitudinally outside the proposed track work sites shown on the Contract Drawings. The survey shall extend out a minimum 3.0 metres parallel to the nearest track. Sufficient survey detail shall be taken to prove any reasonably practical design scheme. Track cant, track intervals and clearances, together with structure clearances shall be measured. The baseline for tape surveys shall be located so that its alignment can easily be replicated. Measured offsets exceeding 5.0 metres shall be triangulated from survey pegs. Surveys which would otherwise end within curving tracks shall be extended clear of any transition curves. Curve survey information shall be extended a minimum of the equivalent of two half chord lengths into the adjacent straight. Hallade schemes shall be tied into theodolite straights established as part of the survey. Where the limits of the proposed trackwork scheme is specified, the existing rail depth shall be taken at the proposed rail break points. (22.016) Specification Land and Trackwork Surveys Structures, including bridges, retaining walls etc 17 The survey shall note details of structure type, construction materials and general condition, of the structure, parapets, roads and footpaths and dimensions of main structural members. High level detail shall be separately identified from the lower detail and underground information. The survey interval for vertical and horizontal clearances from rail to adjacent structures up to 20 metres along the tracks in both directions from the structure shall be noted. Clearances of the bridge girders, abutments and associated retaining wing walls to bridges shall be physically checked by direct measurement. At high level the survey shall include road or track levels information (centre and kerbs) cess or footpath levels (kerb and parapet), kerb heights, details of utilities, parapets, pilasters, newels and string courses. At low levels the survey shall include abutments, wing walls, buttresses, springing and soffit levels, (profile for arches), offset distance of tracks and cable routes. Surveys of bridges shall include six taped check dimensions to abutment corners at road or rail level as applicable, and at springing level or underside of bed course to the bridge deck as applicable. The verticality of the abutment faces shall be recorded. (22.017) Trackwork and trackside train operating equipment 18 The inter-relationship, including alignment of all trackwork and adjacent infrastructure for a 50 metre distance from the structure shall be surveyed. Sufficient detail shall be measured to enable full cross sections at critical points to be drawn. The location of all signalling and power supply equipment, cable routes and ducting shall be surveyed and the position of a.c. electrification overhead equipment and associated supports defined. The survey shall be extended to the Railtrack boundary and include platform detail, platform and bridge clearances, track formation information and record the level of any adjacent water course. (22.018) Roads and associated information 19 The survey shall be sufficiently detailed to give accurate road profiles and cross-sections along the route approaching and crossing the railway and clearances to the fixed infrastructure. The distance to be surveyed along the road shall be 40 metres on each side approaching the Railway. The survey shall record the following information: (i) road layout including kerb alignment, junctions, footpaths, outline of buildings and fencing, and where applicable entrances to adjacent properties, (ii) location of street lights, traffic lights, signs and other street furniture, Specification Land and Trackwork Surveys (iii) manholes, gullies, stop cocks, vent pipes etc, (iv) utilities and overhead lines, (v) levels of roads at centre and kerbs, top of kerb, footpaths, and centre of road and edge of footpaths across level crossings, (vi) level crossing gates and operating equipment, (vii) earthworks, including embankment slopes, (viii) tree types and size within 3 metres of route, or as defined. (22.019) Trial holes for undertrack survey 20 Where specified, trial holes shall be dug in accordance with Section 215: Maintenance of Permanent Way to give under track survey information or clearance dimensions between trackwork and buried footings. The interval for the survey trial holes shall be at a nominal 10 metre intervals along each track. The size of trial holes shall be kept to a minimum to avoid any possibility of track alignment distortion following excavation work. (22.020) Platforms and underbridges to be gauged 21 All platforms and underbridges with parapets or centre girders above 100 mm from top of rail shall be physically gauged by direct measurement in accordance with Railway Group Standard GC/RC5504. A Hallade scheme shall be undertaken with half chord points at 5 metre half chord intervals marked out and used as the datum points during the survey. Gauging of the platforms and underbridges shall be undertaken at the half chord points and at bottom and top of platform ramps and ends of bridge girders. The location, extent and values of clearances of platforms and underbridges below Standard as defined in Railway Group Standard GC/RT5204 shall be recorded. The type of construction and the overhang of the platform edge to the platform wall shall be recorded. The data shall be recorded in accordance with Railway Group Standard GC/RT5204. (22.021)